Investment Opportunities in the Philippine Energy Sector

Total Page:16

File Type:pdf, Size:1020Kb

Investment Opportunities in the Philippine Energy Sector IEEJ : November 2013 All Right Reserved Investment Opportunities in the Philippine Energy Sector SecretaryyJ Carlo Jericho L. Petilla Department of Energy IEEJ : November 2013 All Right Reserved Investment Opportunities • Power • Oil & Gas • Coal • Alterna tive Fue ls (for Transport) • RRblenewable Energy Investor’s Support IEEJ : November 2013 All Right Reserved Power IEEJ : November 2013 All Right Reserved Power Sector Situationer 2013 Capacity in MW LUZON VISAYAS MINDANAO PHILIPPINES FUEL TYPE MW % Share MW % Share MW % Share MW % Share Coal 4,531 36.16 806 32.91 232 11.32 5,568 32.71 Oil Based 1,778 14.19 670 27.39 625 30.50 3,074 18.05 Natural Gas 2,861 22.84 1 0.04 2,862 16.81 Geothermal 824 6.58 915 37.39 108 5.29 1,848 10.85 Hydro 2,462 19.66 11 0.47 1,047 51.09 3,521 20.68 Wind 33 0.26 33 0.19 Biomass 38 0.31 44 1.81 36 1.75 119 0.70 Solar 1 0.05 1 0.01 TOTAL 12,528 2,448 2,049 17,025 Source: DOE List of Existing Power Plants as of May 2013 • Includes embedded generators • Excludes off-grid generators Interconnection Line Capacity • Leyte‐Luzon (440 MW) • Leyte‐Cebu (400 MW) • Leyte‐Bohol (100 MW) • Cebu‐Negros (200 MW) • Negros – Panay ( 100 MW) IEEJ : November 2013 All Right Reserved LUZON SUPPLY‐DEMAND OUTLOOK 2013‐2020 Puting Bato Phase 1 (135 MW) Aug 2014 Pililia Wind (67 MW) Sep 2014 SJCI Biomass ()(9.9 MW) Nov 2014 Maibarara Southwest Luzon 1 (150 MW) Dec 2014 Geo (20 MW) Oct 2013 Southwest Luzon 2 (150 MW) Mar 2015 Isabela Biomass (18 MW) Mar 2015 Puting Bato Phase 2 (135 MW) Nov 2015 APC CFBC (82 MW) Mar 2016 Critical Periods On Available Capacity: On Available Capacity + Committed: • 2015 Peak: Projected Deficit of 184 MW • 2017 Peak: Projected Deficit of 339 MW • 2016 Peak: Projected Deficit of 635 MW • 2018 Peak: Projected Deficit of 833 MW NtNotes a. Demand curve as plotted includes total of peak demand and required Reserve Margin (RM) i.e. 4% regulating reserve and contingency and dispatchable reserve requirement b. 4.2 % peak demand growth rate resulted from observed 0.6 elasticity ratio of demand for electric power with nationa l economic growth applie d to 7 percent GDP growth rate (GR) tttarget for 2013‐2015. c. 4.8 % peak demand growth rate resulted from observed 0.6 elasticity ratio of demand for electric power with national economic growth applied to 8 percent GDP growth rate (GR) target for 2016‐2020. d. Assumed 6.6 percent average forced outage of the total dependable capacity IEEJ : November 2013 All Right Reserved COMMITTED POWER PROJECTS Luzon Grid Committed Power Projj,ects, 767.4 MW Project Rated Capacity Name of the Project Project Proponent Location Cost (Php Target Commissioning (MW) Billion) Brgy. Puting Bato 135 MW Puting Bato Coal South Luzon Thermal West, Calaca, 135.0 12.9 August 2014 Fired Power Plant Phase I Energy Corp. (SLTEC) Batangas Brgy. Puting Bato 135 MW Puting Bato Coal South Luzon Thermal West, Calaca, 135.0 9.6 November 2015 Fired Power Plant Phase II Energy Corp. (SLTEC) Batangas 2 X 150 MW SLPGC Coal-Southwest Luzon Power Brgy. San Rafael, Unit I - Dec 2014 300.0 45.4 Fired Power Plant Phase I Generation Corporation Calaca, Batangas Unit II - March 2015 82 MW APC Circulating Brgy. Bundagul, AdAnda Power Fluidized Bed Coal Fired Mabalacat, 82 8.6 March 2016 Corporation Power Plant Pampanga Sitio Capuz, Brgy. Maibarara Geothermal Maibarara Geothermal, San Rafael , Sto. 20. 0 343.4 October 2013 Power Project Inc. Tomas, Batangas Alternergy Wind One September 2014 Pililla Wind Power Project Pililla, Rizal 67.5 7.7 Corporation (Subject to FIT) 9.9 MWe (net) SJCiPower San Jose City I Power Brgy. Tulat, San Rice Husk-Fired Biomass 9.9 1.2 December 2014 Corporation Jose, Nueva Ecija power Plant Project 20 MW IBEC Biomass Isabela Biomass Energy March 2015 Isabela 18 1.9 Power Plant Corporation (Subject to FIT) TOTAL 767.4 90.7 IEEJ : November 2013 All Right Reserved INDICATIVE POWER PROJECTS Luzon Grid Indicative Power Projects, 10,152 .5 MW Rated Capacity Name of the Project Projjpect Proponent Location Targgget Commissioning (MW) 2 X 20 MW FDC Camarines CFB FDC Utilities, Inc. Camarines Sur 40.0 March 2016 Coal Power Plant Phase I - October 2016 2 X 300 MW Coal-Fired Power Redondo Peninsula Sitio Naglatore, Cawag, 600.0 Phase II - December Plant Energy, Inc. Subic Bay Freeport Zone 2016 2 X 600 MW Mariveles Expansion GNPower Mariveles Coal Mariveles, Bataan 1,200.0 2018 Project Plant Ltd . Co. 2 X 150 MW SLPGC Coal-Fired Southwest Luzon Power Brgy. San Rafael, Calaca, Unit I - 2017 300.0 Power Plant Phase II Generation Corporation Batangas Unit II - 2017 Unit 3 (300 MW) - AES Masinloc Power September 2016 2 X 300 MW Masinloc Expansion Zambales 600.0 Partners Co., Inc. Unit 4 (300 MW) - September 2016 300 MW Limay Power Plant Project SMC Consolidated Brgy. Lamao, Limay, 150 MW - Dec. 2015 300.0 Phase I Power Corporation Bataan 150 MW - May 2016 Quezon Power Expansion Project Quezon Power Phils. Mauban, Quezon 500.0 'March 2018 300 MW Limay Power Plant Project SMC Consolidated Brgy. Lamao, Limay, 300.0 2018 Phase II Power Corporation Bataan 300 MW Limay Power Plant Project SMC Consolidated Brgy. Lamao, Limay, 300. 0 2020 Phase III Power Corporation Bataan TOTAL COAL 4,140.0 List of Committed Power Projects as of 28 August 2013 IEEJ : November 2013 All Right Reserved INDICATIVE POWER PROJECTS Luzon Grid Indicative Power Projects, 10,152 .5 MW Rated Capacity Name of the Project Project Proponent Location Target Commissioning (MW) Aero Derivative Combined Cycle Calamba Aero Power Calamba, Laguna 150.0 TBA Power Plant Corporation TOTAL DIESEL 150.0 Brgy. Ibabang Polo , Pagbil ao 300 MW Com bine d Cyc le EWldEnergy World Grande Island, Pagbilao, 300.0 June 2014 Gas Fired Power Plant Corporation Quezon 300 MW Batangas Mid-Merit Plant First Gen Corporation Batangas 300.0 September 2014 Project San Gabriel Power Plant First Gas Power Corp . San Gabriel , Batangas 550. 0 September 2015 LNG-Fired Combined Cycle Power Meralco PowerGen Atimonan, Quezon 1,750.0 2018 Plant Corporation Combined Cycle Gas Turbine Atlantic, Gulf and Pacific Unit 1 – March 2017; Limay, Bataan 2,400.0 Power Plant Project Company of Manila, Inc Unit 2 – March 2018 TOGOTAL NATURAL GAS 5,300.0 Energy Development Tanawon Geothermal Project Guinlajon, Sorsogon 40.0 2018 Corporation Energy Development Rangas Geothermal Project Bacon District, Sorsogon 40.0 2019 Corporation Energy Development Kayabon Geothermal Project Manito, Albay 40.0 2019 Corporation TOTAL GEOTHERMAL 120.0 Dupinga Hydroelectric Power Constellation Energy Gabaldon, Nueva Ecija 3.0 October 2015 Project Corporation Ibulao Hydroelectric Power Project Hydrocore, Inc. Lagawe, Ifugao 4.5 May 2015 TOTAL HYDRO 7.5 List of Committed Power Projects as of 28 August 2013 IEEJ : November 2013 All Right Reserved INDICATIVE POWER PROJECTS Luzon Grid Indicative Power Projects, 10,152.5 MW Rated Capacity Name of the Project Project Proponent Location Target Commissioning (MW) Phase 2: Alternergy Sembrano Wind Mt. Sembrano, Mabitac, Laguna 56.0 January 2017 Mabitac Wind Power Project Corporation Phase 1: January 2017 Energy Logics Philippines, Inc. Pasuquin, Ilocos Norte 48.0 Pasuquin East Wind Power Project (Subject to FIT) EDC Burgos Wind Power Nagsurot-Saoit, Burgos, Ilocos October 2014 Burgos Wind Power Project 87.0 Corporation Norte (Subject to FIT) Alternergy Wind Cavinti Cavinti Wind Farm Project Corporation (Project Cavinti, Laguna 50.0 January 2017 Company) BCiidBliBrgys. Caparispisan and Balaoi, 80 MW Caparispisan and Balaoi Wind Northern Luzon UPC Asia Municipality of Pagudpud, 81.0 September 2014 Energy Project Corporation Province of Ilocos Norte Northern Luzon UPC Asia Brgy. Balaoi, Pagudpud, Ilocos Balaoi Wind Power Project 45.0 August 2015 Corporation Norte TOTAL WIND 367. 0 August 2014 Currimao Solar Photovoltaic Power Project Mirae Asia Energy Corporation Currimao, Ilocos Norte 20.0 Subject to FIT ATN Philippines Solar Energy Brgy. Macabud, Rodriguez, February 2016 Macabud Solar Photovoltaic Power Project 30.0 Group, Inc. Rizal Subject to FIT TOTAL SOLAR 50.0 20 MW Was te-to-EPjtiEnergy Project using CJ Glo ba l Green Energy Camarines Sur 18.0 June 2015 Thermal Gasifier Conversion Philippine Corp. TOTAL BIOMASS 18.0 List of Committed Power Projects as of 28 August 2013 IEEJ : November 2013 All Right Reserved VISAYAS SUPPLY‐DEMAND OUTLOOK 2013‐2020 Villasiga HEP(8 MW) Mar 2014 NasuloGeo ()(50 MW) Jun 2014 Toledo Expansion (82 MW) Sep 2014 San Carlos Biomass (16 MW) Concepcion Coal 1(135 MW) Jul 2016 Mar 2015 Concepcion Coal 2(135 MW) Sep 2016 ASIAN Biomass (3.6 MW) Jun 2015 Critical Periods On Available Capacity: On Available Capacity + Committed: • 2014 Peak: Projected Deficit of 92 MW • 2015 Peak: Projected Deficit of 62 MW • 2015 Peak: Projected Deficit of 221 MW • 2016 Peak: Projected Deficit of 100 MW • 2017 Peak: Projected Deficit of 121 MW NtNotes a.Demand curve as plotted includes total of peak demand and required Reserve Margin (RM) i.e. 4% regulating reserve and contingency and dispatchable reserve requirement b.7 % peak demand growth rate resulted from observed 1 elasticity ratio of demand for electric power with nationa l economic growth applie d to 7 percen t GDP growth rate (GR) tttarget for 2013‐2015. c.8 % peak demand growth rate resulted from observed 1 elasticity ratio of demand for electric power with national economic growth applied to 8 percent GDP growth rate (GR) target for 2016‐2020.
Recommended publications
  • COAL MINING EQUIPMENT Capacity
    COMPANY PROFILE VISION, MISSION AND VALUES Our Vision: COAL Towards An Energy-Sufficient Philippines Our Mission: To fulfill its commitment to provide affordable power to the Filipino people through the responsible use of coal as energy source, Semirara Mining and Power Corporation will continue to remain as: •The undisputed leader in the coal mining industry and vertically integrated coal-based power producer in the Philippines •Playing a vital role in the energy sector & working in harmony with the government to promote the use of coal as a reliable and economical power source. •Supplying its customer s with quality coal that meets their stringent specifications •Providing reasonable economic returns to its investors & business partners •Empowering its employees to prosper in a climate of integrity & excellence •Working in partners with its host communities to improve their sustainability while engaging in the judicious use and rational conservation of the country’s natural resources. Our Values: In fulfilling our vision, we are guided by : Teamwork that enables us to work toward common goals; Excellence that drives us to deliver outstanding results; Loyalty that keeps us steadfast over challenges and time; Integrity that upholds the cornerstone of our business ethics; Commitment that fuels realization of our mission; and Professionalism that embodies our work quality. ORGANIZATIONAL STRUCTURE A member of the DMCI Holdings, Inc. group of companies 100% 100% 100% 100% 100% 100% 100% *Sem-Cal *Sem- Southwest *St. Raphael Industrial *Semirara *Semirara Balayan Sem-Calaca Luzon Power Power Park Claystone, Energy Power Power Power Corp. Generation Generation Developers, Inc. Utilities, Inc. Generation Corp. Corp. Inc.
    [Show full text]
  • 2020 Private Sector Initiated Power Projects in Luzon (Committed)
    PRIVATE SECTOR INITIATED POWER PROJECTS (LUZON) COMMITTED As of 31 March 2020 Committed/ Rated Capacity Target Testing & Name of the Project Project Proponent Location Project Status Target Commercial Operation Indicative (MW) Commissioning COAL 3436 FEASIBILITY STUDY: • Completed February 2011 ARRANGEMENT FOR SECURING THE REQUIRED LAND: • No additional land will be aquired as the expansion will be inside the existing Masinloc Power Plant Complex. • NPC/PSALM, however, is still continuing the titling process and land registration for some parcels of land PERMITS AND OTHER REGULATORY REQUIREMENTS: • Grid Impact Studies obtained on 7 January 2011 • ECC Amendment was released by DENR on April 23, 2012 • The amended DOE Certificate of Endorsement for BOI was released on May 7, 2012 Q1 2020 AES Masinloc Power • Secured CoE for ERC on September 2011 Unit 3 -September 2019 Committed Masinloc Expansion Project Zambales 300 (Target Testing and Partners Co., Inc. • On-going processing of Certificate of Precondition from NCIP (commissioning test) Commissioning) • SAPA amendment is still pending with DENR FINANCING ARRANGEMENTS: • Provided bank certification for financial closing status to DOE dated 24 August 2016; • Project cost is Php49.45B CONSTRUCTION CONTRACTS FOR PLANTS AND EQUIPMENT: • POSCO Engineering and Construction Co. Ltd, Korea (Offshore - Engineering Procurement); Ventanas Philippines Construction Inc. (Onshore Construction Main Contractor) COMMENCEMENT OF CONSTRUCTION: • 2nd Qtr 2014 FEASIBILITY STUDY: Completed ARRANGEMENT FOR SECURING THE REQUIRED LAND: • Project Site secured and under possession of RPE MARKETING OF GENERATING CAPACITIES: • Started discussions with the Manila Electric Company for sale of power • 52% owned by Meralco PowerGen Corp. (MPGC) • 225 MW PSA with MERALCO & 75 MW with Aboitiz Energy Services Inc.
    [Show full text]
  • Chapter 26: Philippines
    26 Philippines 26.1 Summary of Coal Industry 26.1.1 ROLE OF COAL IN THE REPUBLIC OF THE PHILIPPINES Currently, coal-fired thermal power plants remain the number one producer of electricity and accounted for a total of 5,568 megawatts (MW), or 33 percent, of the Republic of the Philippines’ total installed power generating capacity in 2012 (PDOE, 2014a). The Philippines consumed 16.3 million tonnes (Mmt) of coal in 2012, around 75 percent of which was for power generation (EIA, 2014; Ocampo, 2012). The Philippines relies on imports to meet coal demand, importing 10.6 Mmt from Indonesia and 277 thousand tonnes from Vietnam in 2011 (Ocampo, 2012). The Philippine Energy Plan 2012-2030 (PEP) projects coal demand to increase by more than 70 percent between 2012 and 2030 (PDOE, 2014b). The country’s recoverable coal reserves, as shown in Table 26-1, are estimated at 315 Mmt, with most reserves as lignite. Total coal resources compiled by the Geothermal and Coal Resources Development Division (GCRDD) of the Department of Energy of the Philippines, are estimated at a minimum of 2,268.4 Mmt (USGS, 2006). The Philippines produced 8.0 Mmt of coal in 2012, the highest annual production to date. Coal production is increasing rapidly, more than doubling between 2008 and 2012 (EIA, 2014). The PEP projects domestic coal production to continue to increase, reaching more than 11 Mmt in 2015 and more than 12.5 Mmt in 2020 (PDOE, 2014b). Table 26-1. Philippines’ Coal Reserves and Production Sub- Anthracite & bituminous Total Global Rank Indicator Bituminous & Lignite (million tonnes) (# and %) (million tonnes) (million tonnes) Estimated Proved Coal Reserves 41 275 315 41 (0.04%) (2011) Annual Coal Production (2012) 8.0 0.0 8.0 29 (0.10%) Source: EIA (2014) The combined lignite and sub-bituminous coal reserves of the Philippines, including indicated and inferred reserves, are about 1,899.2 Mmt, which make up about 84 percent of the total coal reserves of the Philippines.
    [Show full text]
  • Department of the Interior Us Geological Survey
    DEPARTMENT OF THE INTERIOR U.S. GEOLOGICAL SURVEY Introducing coal-water-mix fuels to the Philippines Assessment of project feasibility Volume 1 - The Philippine coal resource by !/ 2!/ 2/ E. R. Landis, M. D. Carter, and J. H. MedlTn Open-File Report Report prepared for National Economic and Development Authority, Republic of the Philippines on behalf of the National Power Corporation, Development Bank of the Philippines under the auspices of the Office of Energy, U.S. Agency for International Development. This report is preliminary and has not been reviewed for conformity with U.S. Geological Survey editorial standards and stratigraphic nomenclature, I/ U.S. Geological Survey, Denver, CO Jj U.S. Geological Survey, Reston, VA 1985 FRONTISPIECE _____ ito f 12 0 Treaty limits of the Philippines PHILIPPINES PHILIPPIC CATANDUANES ISLAND MIMDANAO MALAYSIA CELEBES SEA Treaty limits of the Philippines L»'.' 'ssi'S.c-.s A (lnden«*io 1 / Index map of the Philippine Islands CONTENTS PREFACE.................................................. iii ACKNOWLEDGEMENTS......................................... iv 1.0 SUMMARY AND CONCLUSIONS............................. 1 2.0 COAL RESOURCES OF THE PHILIPPINES................... 4 2.1 Introduction.............'...................... 4 2.2 Geologic Setting............................... 6 2.3 Quanti ty....................................... 7 2.4 Quality........................................ 13 2.4.1 Philippine coals........................ 13 2.4.2 Coal from Seinrirara..................... 15 2.4.3 Coals
    [Show full text]
  • PRIVATE SECTOR INITIATED POWER PROJECTS (LUZON) COMMITTED As of 31 July 2020
    PRIVATE SECTOR INITIATED POWER PROJECTS (LUZON) COMMITTED As of 31 July 2020 Committed/ Rated Capacity Target Testing & Target Commercial Name of the Project Project Proponent Location Project Status Indicative (MW) Commissioning Operation COAL 3436 FEASIBILITY STUDY: • Completed February 2011 ARRANGEMENT FOR SECURING THE REQUIRED LAND: • No additional land will be aquired as the expansion will be inside the existing Masinloc Power Plant Complex. • NPC/PSALM, however, is still continuing the titling process and land registration for some parcels of land PERMITS AND OTHER REGULATORY REQUIREMENTS: • Grid Impact Studies obtained on 7 January 2011 • ECC Amendment was released by DENR on April 23, 2012 • The amended DOE Certificate of Endorsement for BOI was released on May 7, 2012 Masinloc Expansion AES Masinloc Power • Secured CoE for ERC on September 2011 Unit 3 -Sep 2019 Committed Zambales 300 Dec 2020 Project Partners Co., Inc. • On-going processing of Certificate of Precondition from NCIP (commissioning test) • SAPA amendment is still pending with DENR FINANCING ARRANGEMENTS: • Provided bank certification for financial closing status to DOE dated 24 August 2016; • Project cost is Php49.45B CONSTRUCTION CONTRACTS FOR PLANTS AND EQUIPMENT: • POSCO Engineering and Construction Co. Ltd, Korea (Offshore - Engineering Procurement); Ventanas Philippines Construction Inc. (Onshore Construction Main Contractor) COMMENCEMENT OF CONSTRUCTION: • 2nd Qtr 2014 FEASIBILITY STUDY: •Completed ARRANGEMENT FOR SECURING THE REQUIRED LAND: •GNPD has secured the rights over the project site. MARKETING OF GENERATING CAPACITIES: Signed contracts with a group of electric cooepratives and retail electricity supplier (RESs); On going sales and marketing to electric cooperatives, private distribution utilities, RESs and large end-users in the Luzon and Visayas grids.
    [Show full text]
  • Department of Labor and Employment List of Contractors/Subcontractors with Valid Registration (As of June 2018)
    Department of Labor and Employment List of Contractors/Subcontractors with valid Registration (as of June 2018) Date of D.O. Region Name of Establishments Address Registration Number Nature of Business Registration DO 174 III 1 AIM HIGH SECURITY AGENCY INC. #09 KENTUCKY LANE, UPPER KALAKLAN, OLONGAPO CITY 05-Mar-18 lll-093-0318-1243 OTHER SERVICE ACTIVITIES DO 18-A III 2ND KING ENTERPRISES 311 CAYBUTOK, BAKASING, STA. MARIA, BULACAN 15-Dec-15 LLL-093-1215-866 CONST. SERV. DO 18-A III 3 ACES TRUCKING AND ALLIED SERVICES 0386 NAT.L. ROAD, BRGY. TOWNSITE, LIMAY, BATAAN 06-Aug-15 111-093-0851-774 TRUCKING GLOBAL WIDE REALTY BLDG., BLK. 4 LOT 2, 6TH ST., DO 174 III 3C'S INDUSTRIAL STAFFING SOLUTIONS INC. 23-Feb-18 lll-093-0218-1241 OTHER SERVICE ACTIVITIES BALIBAGO, ANGELES CITY UNIT 25,THE PABILLION MALL PHILEXCEL BUS PARK M.A. DO 18-A III 3C'S INDUSTRIAL STAFFING SOLUTIONS INC. 29-Jul-15 LLL-093-0715-762 MANPOWER ROXAS, HIGHWAY, CFZ LIMESTONE ST/. ROMAN HIGHWAY, BRGY. TENEJERO, DO 174 III 3K. P. MANPOWER AGENCY 16-Mar-18 lll-093-0316-1247 OTHER SERVICE ACTIVITIES BALANGA CITY 2ND FLOOR, P2-3T'S BLDG. # O89 PERPETUAL HELP ST., DO 174 III 4 RUNNER SERVICES, INC. 27-Mar-18 lll-093-0318-1253 OTHER SERVICE ACTIVITIES DOLORES HOMESITE, EXTN. LL, CSFP 4+5=9 ELECTRICAL/ELECTRONICS AIRCON AND GEN. DO 18-A III B. MENDOZA, STO. ROSARIO, CSFP 20-Aug-15 111-093-0815-782 SERVICES SERV. CO. DO 18-A III 557 CORPORATION GLORIA 1, SINDALAN, CITY OF SAN FDO.
    [Show full text]
  • Carving out Coal in the Philippines: Stranded Coal Plant Assets and the Energy Transition
    Carving out Coal in the Philippines: Stranded Coal Plant Assets and the Energy Transition October 2017 Sara Jane Ahmed, IEEFA Energy Finance Analyst Jose Logarta Jr., ICSC Energy Policy Advisor Table of Contents Executive Summary ………………………………………………………………………………………2 Introduction……………………………………………………………..………………………………….5 The Economy-Electricity Nexus…………………………………………………………………………11 The Rise and Risks of Coal ………………………………………………………………………………18 Reforming the Automatic Fuel Pass-Through Model …………….…………………………......... 21 Inherent Risks for Ratepayers, Equity Investors and Lenders ……………………………..….….. 24 The Challenge from Natural Gas and Renewables …………………………………..………….. 36 Case Study: Meralco and the Atimonan Power Project…………………………………………. 42 Conclusion ………………………………………………………………………………………………... 51 Appendices ………………………………………………………………………………………………. 52 Carving out Coal in the Philippines: Stranded Coal Plant Assets and the Energy Transition 1 Executive Summary The Philippines has 10,423 megawatts (MW) (US$20.8 billion) of largely imported coal expansion in its current pipeline. This runs on top of a total of 7,419 MW of existing coal-fired capacity. Projections borne of such a pipeline raise vital questions about national energy policy and practices in an era of evolving electricity-generation trends. Stranded coal plant assets—those that are not delivering an economic return in line with the expectations from the project outset—is a growing material and inevitable risk in the Philippines. In Mindanao, even without retail competition enabled by the presence of a Wholesale Electricity Spot Market, stranding is already taking place due to an oversupply of approximately 700 MW of coal and hydro in an island grid lacking national connectivity. The surplus of coal fired power has led to a downtrend in utiliZation rates as compared to original expectations. Conservatively, the underutilization cost in Mindanao alone from 2014 to 2016 is Php 3 billion (US$60 million).
    [Show full text]
  • The Philippines Illustrated
    The Philippines Illustrated A Visitors Guide & Fact Book By Graham Winter of www.philippineholiday.com Fig.1 & Fig 2. Apulit Island Beach, Palawan All photographs were taken by & are the property of the Author Images of Flower Island, Kubo Sa Dagat, Pandan Island & Fantasy Place supplied courtesy of the owners. CHAPTERS 1) History of The Philippines 2) Fast Facts: Politics & Political Parties Economy Trade & Business General Facts Tourist Information Social Statistics Population & People 3) Guide to the Regions 4) Cities Guide 5) Destinations Guide 6) Guide to The Best Tours 7) Hotels, accommodation & where to stay 8) Philippines Scuba Diving & Snorkelling. PADI Diving Courses 9) Art & Artists, Cultural Life & Museums 10) What to See, What to Do, Festival Calendar Shopping 11) Bars & Restaurants Guide. Filipino Cuisine Guide 12) Getting there & getting around 13) Guide to Girls 14) Scams, Cons & Rip-Offs 15) How to avoid petty crime 16) How to stay healthy. How to stay sane 17) Do’s & Don’ts 18) How to Get a Free Holiday 19) Essential items to bring with you. Advice to British Passport Holders 20) Volcanoes, Earthquakes, Disasters & The Dona Paz Incident 21) Residency, Retirement, Working & Doing Business, Property 22) Terrorism & Crime 23) Links 24) English-Tagalog, Language Guide. Native Languages & #s of speakers 25) Final Thoughts Appendices Listings: a) Govt.Departments. Who runs the country? b) 1630 hotels in the Philippines c) Universities d) Radio Stations e) Bus Companies f) Information on the Philippines Travel Tax g) Ferries information and schedules. Chapter 1) History of The Philippines The inhabitants are thought to have migrated to the Philippines from Borneo, Sumatra & Malaya 30,000 years ago.
    [Show full text]
  • Subic Bay Freeport Chamber of Commerce Emerald Tier, Silver
    Subic Bay Freeport Chamber of Commerce Emerald Tier, Silver Circle and Corporate Members 2019 Company A Dream Life Branch - AXA Philippines Address 100 Magsaysay Drive, East Tapinac, Olongapo City Representative Mr. Danny A. Alimorong Secondary Representative N/A 1 E-mail Address [email protected] Phone/ Mobile Number 0917-877-5888 Website N/A Membership Category CORPORATE Company Aboitiz Power Corporation Address 16th Floor, NAC Tower, Bonifacio Global City, Taguig Representative Mr. Carlo Jose Morales Secondary Representative Ms. Gina Camacho 2 E-mail Address [email protected] Phone/ Mobile Number 09178750500(CM); 09173055645(GC) Website https://aboitizpower.com/ Membership Category SILVER CIRCLE Company Absolute Service, Inc. Address Bldg 1149, George Dewey Complex, Subic Bay Freeport Zone Representative Mr. Danny J. Piano Secondary Representative Ms. Lalaine Gamboa 3 E-mail Address [email protected] Phone/ Mobile Number (047) 252-3934; (047) 252-5235; (047) 252-3935 Website www.absoluteserv.com Membership Category EMERALD TIER Company Ace Motorcycles Address 640 Sampson Rd., Subic Bay Freeport Zone Representative Mr. Angus Robert Charlton Secondary Representative Ms. Jacquelyn Lagazon 4 E-mail Address [email protected] Phone/ Mobile Number 251-3924 Website www.acemotorcycle.ph Membership Category CORPORATE Company Acea Subic Bay Address San Bernardo Road, Subic Bay Freeport Zone Representative MS. Pamela Robinson Secondary Representative Ms. Jackie Lou Dilag 5 E-mail Address [email protected] Phone/ Mobile Number 252-2232 Website www.aceasubicbay.com Membership Category CORPORATE Company Airfreight 2100, Inc. (Air21, Inc.) Address Lot 27 No.13, Innovative St. Cor Commitment Ave., Subic Bay Freeport Zone Representative Ms. Leony A.
    [Show full text]
  • CHR 2015 Annual Accomplishment Report
    2015 Accomplishment Report COMMISSION ON 3333 HUMAN RIGHTS 2015 ACCOMPLISHMENT REPORT 2015 Accomplishment Report TABLE OF CONTENTS EXECUTIVE SUMMARY HUMAN RIGHTS PROTECTION SERVICES 1 DOCUMENTATION OF COMPLAINTS 1 Complaints Evaluated for Investigation 2 Gender-Based Violations 11 Violations of Children’s Rights 12 Business and Human Rights 15 Violations of Indigenous Peoples’ Rights 18 Internal Displacement of Peoples and Communities 20 Disposition of Cases 21 Persons Assisted 22 Monitoring of Jails/ Detention Centers 22 Financial Assistance 23 Forensic Services 24 Issuance of Human Rights Clearance/ Certification 24 HUMAN RIGHTS PROMOTION SERVICES 26 EDUCATION AND TRAINING ACTIVITIES 26 Human Rights IEC Materials 28 Training Modules Developed 31 Training Kits 32 HR Milestone Events and Celebratory Events 32 HUMAN RIGHTS POLICY SERVICES 35 Human Rights Advisories 35 Human Rights Position Papers 38 Human Rights Mechanisms/ Measures 39 Human Rights Treaty/ Situation Report 40 On-going Policy Development Initiatives 41 INTERNATIONAL COOPERATION PROJECTS 45 United Nations Development Programme (UNDP) 45 AECID Fortaleza 46 The Asia Pacific Forum (APF) 51 INSTITUTIONAL BUILDING 54 Internal Policies 55 International Engagements 55 Internal Capacity Building Programs 58 Manpower Complement 59 General Appropriations 59 2015 Accomplishment Report EXECUTIVE SUMMARY In monitoring the human rights situation in 2015, the Commission received a total of 6,448 requests for protection services of different types of human rights violations. Based on the preliminary evaluation of 6,448 complaints, only 1,413 required full blown investigation, while majority or 4,971 needed legal aide and counseling services. Some 29 complaints were found to be outside of the CHR jurisdiction, which were immediately referred to other agencies.
    [Show full text]
  • OSH PRACTITIONER PROFILE ACCREDITATION INFORMATION Name Company Name/Address Accreditation No
    LIST OF ACCREDITED SAFETY PRACTITIONERS WITH VALID ACCREDITATION as of September 2017 Region III OSH PRACTITIONER PROFILE ACCREDITATION INFORMATION Name Company Name/Address Accreditation No. Validity of Accreditation Field of Expertise NIDEC SUBIC PHILS. CORP / BLK 13, SUBIC 1 ABAD, MARY ANN G. 1033-150413C-120 13-Apr-2018 MANUFACTURING TECHNOPARK, BOTON AREA, SBFZ SANYO DENKI PHILS., INC / BLK F1, SUBIC 2 ADRANEDA, ELOISA DR. TECHNOPARK, ARGONAUT HIGHWAY, 1033-150327C-297 27-Mar-2018 MANUFACTURING BOTON AREA, SBFZ DONG IN GROUP OF COMPANIES, 3 ALILAO, RICARDO JR. E. MINDANAO AVENUE, PHASE 2 FAB 1033-170509C-402 9-May-2020 MANUFACTURING MARIVELES BATAAN TOLLWAYS MANAGEMENT CORP / STA. 4 ANDAN, GLENN ARCHIE M. 1033-141118-C-274 18-Nov-2017 TOLLWAYS RITA, BULACAN 5 ARRIETA, LIZA S. YOKOHAMA TIRE PHILS., INC. 1033-140905-C-266 5-Sep-2017 MANUFACTURING PHILIPPINE RESINS INDUSTRIES INC. / PPDC 6 ASUNCION, ORLANDO II ANDIA PETROCHEMICAL IND'L PARK, BATANGAS II, 1033-150928C-328 28-Sep-2018 MANUFACTURING MARIVELES, BATAAN PEREGRINE DEVELOPMENT INTERNATIONAL, 7 BABARAN, RENATO C. INC / SPUR ROAD 2, INDUSTRIAL ESTATE 5, 1033-150206C-99 6-Feb-2018 CONSTRUCTION CLARK FPZ, PAMPANGA METRO STONERICH CORP. BRGY ILANG 8 BALDECAÑAS, MELCHOR ESPEJO 1033-160907C-365 7-Sep-2019 CONSTRUCTION ILANG, GUIGUINTO, BULACAN TEXAS INSTRUMENTS (PHILS), INC / CLARK 9 BALTORES, RESZAN JOHN M. 1033-150206C-291 6-Feb-2018 MANUFACTURING FREEPORT ZONE, ANGELES CITY D & Y ALLIED PHIL. INC / SITIO PEAS, BRGY CONSTRUCTION / GAS 10 BANZON, JR., VIRGILIO S. 1033-141110-C-79 10-Nov-2017 DUALE, LIMAY, BATAAN MONITORING SUBICMAU CORP./ GREENBEACH 1 11 BEQUILLO, JEFFREY REDONDO PENINSULA, SUBIC BAY FREEPORT 1099-170118C-388 18-Jan-2020 SHIPBUILDING ZONE, ZAMBALES NPC ALLIANCE CORPORATION / PNOC BERNABE, RAPHAEL VICTOR 12 ALTERNATIVE FUEL CORPORATION, 1033-150803C-321 3-Aug-2018 PETROCHEMICAL SAFETY CORNEJO BATANGAS II, MARIVELES, BATAAN EAGLE CEMENT CORPORATION / #15 L.
    [Show full text]
  • Oriental Mindoro Facts and Figures 2013 Table of Contents
    ORIENTAL MINDORO FACTS AND FIGURES 2013 TABLE OF CONTENTS Page General Information 1 Administrative Map 2 Land and Other Natural Resources 3 a. Land Area by Municipality 3 b. Land Classification Statistics 3 c. Geographical Zone Surfaces 3 d. Mineral Resources 4 e. Forest Cover 4 f. Coastal Resources 5 Demography 8 a. Population Size by Municipality by Census 8 Years b. Actual and Projected Population and Number 9 of Households, Growth Rate by Municipality c. Life Expectancy 9 d. Projected Population by Province, MIMAROPA 10 e. Urban-Rural Population 10 f. Population Density 11 g. Mangyan Tribes by Municipality 11 h. Mangyan Households by Sex 12 Economic Profile 13 a. Agriculture 13 b. Tourism 18 c. Commerce and Industry 22 Infrastructure and Utilities 24 a. Transportation 24 b. Communication 25 c. Water 27 d. Power 28 Social Development Profile 30 a. Labor and Employment 30 b. Poverty and Income 30 c. Health 33 d. Education 36 e. Social Welfare Services 37 f. Protective Services 37 Financial Profile 39 a. Income Classification of City/Municipality 39 b. Annual Income and Budget Per 39 City/Municipality c. Income and Expenditure, Provincial 40 Government f Oriental Mindoro Institutional Profile 41 a. Organizational Chart of the Provincial 41 Government of Oriental Mindoro b. Provincial Government Personnel by Office 42 ORIENTAL MINDORO FACTS AND FIGURES 2013 General Information A. LOCATION Oriental Mindoro is located in Region IV-B, otherwise known as the MIMAROPA Region. It lies 45 kilometers south of Batangas and 130 kilometers south of Manila. B. BOUNDARY It is bounded on the North by Verde Island Passage; Maestro del Campo Island and Tablas Strait on the East; Semirara Island on the South; and Occidental Mindoro on the West.
    [Show full text]