Initial Environmental Examination

April 2009

IND: North Urban Sector Investment Program Tranche 4 – Sub-projects in Raichur

Prepared by Karnataka Urban Infrastructure Development and Finance Corporation, Government of Karnataka for the Asian Development Bank.

NKUSIP (Package IV – Bellary) Tranche I Sub Projects in Raichur Town IEE Report

Currency Equivalent

Currency Unit - Indian Rupee/s (Re/Rs)

Re. 1.00 = US$ 0.022 US$ 1.00 = Rs. 45

Abbreviations

ADB : Asian Development Bank

ASP : Activated Sludge Process BM : Bituminous Macadam DoEEF : Department of Ecology, Environment and Forests EIA : Environmental Impact Assessment EMP : Environmental Management Plan EP Act : Environment (Protection) Act, 1986 GoI : Government of GoK : Government of Karnataka GSB : Granular Sub-base IEE : Initial Environmental Examination KSPCB : Karnataka State Pollution Control Board MLD : Million Litre per Day MoEF : Ministry of Environment and Forests MSL : Mean Sea Level MSS : Mix Seal Surface NKUSIP : Urban Sector Investment Program NOC : No Objection Certificate NOx : Oxides of Nitrogen OM : Operations Manual PCC : Profile Concrete Course PWD : Public Works Department SOx : Oxides of Sulphur STP : Sewage Treatment Plant RSPM : Respirable Suspended Particulate Matter TSPM : Total Suspended Particulate Matter WMM : Wet Mix Macadam WRDO : Water Resource Development Organization

KUIDFC 1 Span & Voyants

NKUSIP (Package IV – Bellary) Tranche I Sub Projects in Raichur Town IEE Report

Contents

CHAPTER – I : INTRODUCTION......

1.1. Overview ...... 6 1.2. Environmental Regulatory Compliance ...... 6 1.3. Purpose of Initial Environmental Examination ...... 7 1.4. Scope of IEE ...... 7

CHAPTER – II: DESCRIPTION OF THE INVESTMENT PROGRAM COMPONENTS .....

2.1. NKUSIP Goal ...... 8 2.2 Need for Infrastructure Improvement in Raichur ...... 9 2.2.1. Karnataka – Health Status ...... 10 2.2.2. Sewerage System ...... 11 2.2.3. Water Supply Rehabilitation ...... 12 2.2.4. Drainage Up gradation...... 14 2.3 Sub-project Component Description...... 14 2.3.1. Sewerage System ...... 14 2.3.2. Water Supply ...... 18 2.3.3 Urban Drainage ...... 23 2.3.4. Urban Road Up gradation ...... 26 2.4. Investment Program Implementation Schedule ...... 26 2.5. Investment Program Benefits ...... 2 6 2.5.1 . Water Supply System Improvements ...... 26 2.5.2 Sewerage System Improvements ...... 29 2.5.3 Drainage System Improvements...... 3 0 2.5.4 Urban Roads Improvement ...... 3 0 2.6 Investment Program Alternatives...... 30

CHAPTER - III. DESCRIPTION OF THE ENVIRONMENT ......

3.1. Environmental Profile of Raichur ...... 32 3.1.1 Introduction...... 32 3.1.2 Physiographic ...... 32 3.1.3 Seismology ...... 32 3.1.4 Climatic Conditions ...... 3 2 3.1.5 Surface Water...... 35 3.1.6 Groundwater ...... 36 3.1.7 Air Quality ...... 37 3.1.8 Flora and Fauna ...... 38 3.1.9 Socio Economic Characteristics ...... 38 3.1.10 Historic and Cultural Places ...... 38

CHAPTER - IV. SCREENING OF POTENTIAL ENVIRONMENTAL IMPACTS AND MITIGATION MEASURES ...... 40

KUIDFC 2 Span & Voyants

NKUSIP (Package IV – Bellary) Tranche I Sub Projects in Raichur Town IEE Report

CHAPTER - V. INSTITUTIONAL REQUIREMENTS AND ENVIRONMENTAL MONITORING PLAN 45

5.1. Institutional Requirements ...... 58 5.2 Training Needs ...... 60 5.3 Environmental Monitoring Plans ...... 62

CHAPTER - VI. PUBLIC CONSULTATION AND INFORMATION DISCLOSURE

6.1. Overview ...... 70

CHAPTER - VII. FINDING AND RECOMMENDATION

7.1 . Findings ...... 73 7.2. Recommendations ...... 7 4

CHAPTER - VIII. CONCLUSIONS ……………………………………………………. 75

KUIDFC 3 Span & Voyants

NKUSIP (Package IV – Bellary) Tranche I Sub Projects in Raichur Town IEE Report

Tables

Table 1: Environmental Regulatory Compliance of NKUSIP components

Table 2: Water borne/related Diseases in Karnataka.

Table 3: Existing Sewerage System salient Feature.

Table 4: Access to Basic Services-Sewerage and Sanitation

Table : 5 Drainage system in Raichur

Table 6: Design Parameters of STP

Table 7: Existing Water Supply salient features

Table 8: Proposed Sewerage system

Table 9: Sewerage Component Investment Program Beneficiaries

Table 10 Existing Urban Drainage

Table 11 : Drainage Component Investment Program Beneficiaries (2011)

Table 12: Investment Program Alternatives

o Table 13: Mean Maximum and Mean Minimum Temperature (in C)

Table 14: Climatologically Characteristics of Raichur

Table 15: Groundwater Levels in Raichur

Table 16: Groundwater Characteristics in Raichur

Table 17: Ambient Air Quality of Raichur

Table 18: Screening of Impacts

Table 19: Environmental Impacts and Mitigation Measures for Sewerage System

Table 20: Environmental Impacts and Mitigation Measures for Water Supply Rehabilitation

Table21: Environmental Impacts and Mitigation Measures for Roads Up-gradation

Table 22: Institutional Role & Responsibilities

KUIDFC 4 Span & Voyants

NKUSIP (Package IV – Bellary) Tranche I Sub Projects in Raichur Town IEE Report

Table 23: Training Needs (2009 – 2015)

Table 24: Environmental Monitoring Plan for Sewerage Up-gradation

Table 25: Environmental Monitoring Plan for Water Supply Rehabilitation

Table26: Environmental Monitoring Plan for Roads Up-gradation

Table 27: Environmental Issues of Infrastructure c omponents

Figures

Fig: 1 : Wind rose Diagram of Raichur ( 0830 Hrs and 1730 Hrs)

Maps

Map: 1 Location Map of Raichur Town

Map 2 Lay out of proposed sewerage network with treatment facility.

Map 3 Existing and proposed water supply coverage in Raichur

Map 4 Layout of proposed storm water drain in the Raichur town .

KUIDFC 5 Span & Voyants

NKUSIP (Package IV – Bellary) Tranche I Sub Projects in Raichur Town IEE Report

CHAPTER - I INTRODUCTION

1.1 Overview

The North Karnataka Urban Sector Investment Program (NKUSIP) proposes to improve the environmental quality of the urban areas through better urban infrastructure facilities and thus improve living conditions of the urban people. In the wake of poor infrastructure facilities and services such as water supply, sewerage and sanitation, the risk of infectious diseases through exposure to unhealthy environment runs high, particularly in the case of urban poor. Hence, the proposed Investment Program aims at minimizing or mitigating the risk and ensures the well- being of people.

Though the Investment Program aims to improve the environmental condition of urban areas, the proposed improvements of infrastructure facilities may exert certain adverse impacts on the natural environment. While developing urban infrastructure facilities, impacts during the construction stage are expected to be more severe than the operation phase, though for a short duration. Exceptions being some facilities such as sewage treatment plant, which may also exert adverse impacts during the operation phase also, if due care is not taken. Again, most of the impacts are activity- specific. However, if due care is taken during the construction phase, investment Program negative impacts will be far outweighed by positive impacts.

1.2 Environmental Regulatory Compliance

The components of NKUSIP include environmental sanitation infrastructure, water supply infrastructure, urban roads improvement, slum infrastructure, and non-municipal infrastructure projects. Sub-components, which fall under the ambit of environmental regulations and mandatory requirement, are indicated in the Table -1.

Table – 1 Environmental Regulatory Compliance of NKUSIP Components

Sub- Component Applicability of Compliance Criteria Acts/Guidelines Sewage Environmental (Protection) Act, • Consent for Establishment and Treatment Plant 1986 Consent for Operation from Water (Prevention and Control of KSPCB as per Water Act. Pollution) Act, 1974 All sub- The Environment Policy and • Categorization of sub-project components Operations Manual (OM) 20: components into A, B or C and Environmental Considerations in developing required level of ADB Operation environmental assessment for each c ompone nt

KUIDFC 6 Span & Voyants

NKUSIP (Package IV – Bellary) Tranche I Sub Projects in Raichur Town IEE Report

The above table indicates that as far as GoI and GoK Acts/Guidelines are concerned, the proposed Investment Programs may not need to go through environmental assessment process; however, as specified, few sub-pro90ject components may require consent from Competent Authorities. The ADB guidelines, on the other hand, stipulate addressing environmental concerns, if any, of a proposed activity in the initial stages of Investment Program preparation. For this, the ADB Guidelines categorizes the proposed components into varies categories (A, B or C) to determine the level of environmental assessment required to address the potential impacts. Level of Environmental A ssessment required for each category of Investment Program, as per ADB’s Environmental Assessment Guidelines 2003 is presented below.

(i) Category A. Sub-project components with potential for significant adverse environmental impacts. An environmental impact assessment (EIA) is required to address significant impacts.

(ii) Category B. Sub-project components judged to have some adverse environmental impacts, but of lesser degree and/or significance than those for Category A projects. An initial environmental examination (IEE) is required to determine whether significant environmental impacts warranting an EIA are likely. If an EIA is not needed, the IEE is regarded as the final environmental assessment report.

(iii) Category C. Sub-components unlikely to have adverse environmental impacts. No EIA or IEE is required, although environmental implications are still reviewed.

1.3 Purpose of Initial Environmental Examination

The NKUSIP Package IV – Bellary covers Seven sub- project towns. To fulfil the ADB’s Environmental Assessment requirement for sector loans, the Initial Environmental Examination of sub-project were carried out. Owing to the scale and nature of the proposed infrastructure components and environmental profile of the NKUSIP sub – project towns, prima facie almost all Investment Program components are unlikely to have adverse environmental impacts.

Therefore, as per the ADB’s Environmental Assessment Guidelines, the sub-project components proposed in Raichur under NKUSIP are categorized as ‘B’ and it is proposed to carryout Initial Environmental Examination (IEE) for the proposed activities/Project.

1.4 Scope of IEE The IEE was based mainly on secondary sources of information and field reconnaissance surveys; no field monitoring (Environmental) survey was conducted. Stakeholder consultation was an integral part of the IEE.

KUIDFC 7 Span & Voyants

NKUSIP (Package IV – Bellary) Tranche I Sub Projects in Raichur Town IEE Report

CHAPTER – II

DESCRIPTION OF THE INVESTMENT PROGRAM COMPONENTS

2.1 NKUSIP Goal

The North Karnataka Urban Sector Investment Program (NKUSIP) will finance investment for (i) Environmental Sanitation Infrastructure; (ii) Water supply Infrastructure; (iii) Urban Roads Improvement; (iv) Poverty Alleviation; (v) Non- Municipal Infrastructure; (vi) Institutional Development; and (vii) Investment Program Assistance. The overall development goal of the NKUSIP is to facilitate economic growth in the towns of North Karnataka and bring about urban development through equitable distribution of urban basic services to the citizens that are environmentally sound and operationally sustainable. The development purpose is designed to assist Urban Local Bodies (ULBs) to “promote good urban management, and develop and expand urban infrastructure to increase economic opportunities and to reduce vulnerability to environmental degradation and urban poverty”.

The following are the urban infrastructure components proposed under the NKUSIP.

1. Water Supply; 2. Sewerage; 3. Urban Drainage; 4. Urban Roads; and, 5. Poverty alleviation and 6. Slum improvement

The location Map of Raichur is presented in MAP 1

KUIDFC 8 Span & Voyants

NKUSIP (Package IV – Bellary) Tranche I Sub Projects in Raichur Town IEE Report

Map: 1 Location Map of Raichur Town

2.2 Need Infrastructure Improvement

Raichur is an important destination for industrial and commercial growth due to availability of water. Providing basic amenities to ensure high level of performance in Environmental safe guard is quite necessary to ensure long term urban sustainability. A study conducted by Department of Forest , Ecology & Environment, Government of Karnataka, 2003 has shown that the cities in the state of Karnataka has poor Environmental performance due to lagging in ensuring basic infrastructure facilities to the urban population.

KUIDFC 9 Span & Voyants

NKUSIP (Package IV – Bellary) Tranche I Sub Projects in Raichur Town IEE Report

2.2.1 Karnataka - Health Status

In addition to the associated Environmental pollution, importantly, due to lack of safe and adequate water supply and sanitation facilities, the risk of infectious diseases through exposure to unhealthy environment runs high, particularly in the case of urban poor The State of Environment Report (SOER), 2003, Karnataka, brings out the fact that the lack of safe water supply and sanitation facilities is essentially leading to the health related consequences.

The yearly occurrence of water borne diseases like Cholera and Gastroenteritis makes it very clear that Environmental Impacts of water on health is very profound and significant.”

Table 2: Water borne/related Diseases in Karnataka

Year Gastroenter iti Cholera Lept ospir osi Viral Hepatitis Typhoid 1991 17455s 691 747 16 - s - 659 17 - - 1992 15262 608 402 14 - - 282 17 - - 1993 16206 855 424 13 - - 678 7 26047 1 1994 15932 325 304 10 - - 382 0 20349 0 1995 18645 396 532 38 - - 7146 1 10250 0 1996 22983 377 657 6 - - 1332 6 22221 12 1997 23665 361 714 10 67 2 1714 4 3880 5 1998 23881 501 434 2 1 0 3824 2 2435 0 1999 17743 126 134 3 54 2 4792 2 24356 1 2000 31132 265 354 3 3 1 3011 10 27210 0 2001 23893 198 342 1 68 7 5438 28 33346 6 2002 25218 146 384 0 27 0 4578 15 42936 2 Source: SOER 2003

Hence, it is evident that the lack of safe water supply and sanitation facilities in the State adversely affects health conditions of the population. The following section details the status of water supply, sanitation and other basic infrastructure facilities in Raichur i) Sewerage ii) Water supply iii) Urban Drainage iv) Urban road v) Poverty alleviation and vi) Slum improvement

KUIDFC 10 Span & Voyants

NKUSIP (Package IV – Bellary) Tranche I Sub Projects in Raichur Town IEE Report

Existing Infrastructure Facilities in Raichur town

2.2.2 Sewerage System

First sewerage system in Raichur was commissioned during the year 1971 with sewer lines of 55 km length. Subsequently another 30 km sewer were laid during 1991. The total network of sewers length of 85 km thus covers only about 40% of the town area. In the remaining area, only septic tanks and dry latrines exist to dispose the human waste / waste water. Also in certain areas, sludge and night soil is directly disposed into the roadside/storm water drains causing unhygienic conditions. Even in the areas covered by UGD are also most of the wastewater joins the open drains as the sewerage system is damaged.

- Total area of Raichur town – 50.70 Sq.kms - Total coverage Raichur area about 40 %. - Coverage of Individual House Hold Connection 19.77%w - Total length of roads of various categories – 476 km. - Tentative length of sewers laid –85 km.

Table 3: Existing Sewerage System salient Feature

1 Existing sewerage system Ist Stage Scheme commissioned in 1971 2nd Stage commissioned in 1991 Area covered 40% of the town Length of Network 85 Km No. of Manholes 3500 no. 2 Condition of the Existing Poor Sewerage system Type of Sewerage Treatment Oxidation Pond Plant 3 Condition of STP Not working 4 Land Availability 2 acres 5 Disposal of Treated Sewage Sewage not Treated and dispose to Nalla

Table - 4 indicates the access to the sewerage and sanitation facilities for various households in Raichur. Only 6 percent of the surveyed non-slum households are connected to the UDG system, while none of the slum households are connected. Majority (49 percent) of the non- slum households depend on septic tanks and 16 percent use low- cost sanitation (LCS). Around 45 percent of the slum households and 21 percent of the non-slum households do not have any facilities and resort to open defecation.

KUIDFC 11 Span & Voyants

NKUSIP (Package IV – Bellary) Tranche I Sub Projects in Raichur Town IEE Report

Table 4: Access to Basic Services-Sewerage and Sanitation S. No. Description Access to Non -slum Access to Slum House holds (%) House holds (%) 1 UGD 6 - 2. Septic Tank 49 - 3 Dry Latrines 8 - 4 Individual LCS 16 10 5 Public convenience - 45 6 None 21 45

Source: Socio-economic sample survey, 2004

At present there are two sewage treatment plants based on waste stabilization ponds with total capacity of 20.50 MLD, located near Hosur village and Ekalaspur village. Sewage does not reach Hosur STP, as the outfall sewer is damaged and Ekalaspur STP receives only 10 percent of the sewage flow of the three zones. The farmers tap the sewage from the outfall sewer for irrigation use. Thus, both the STPs are not working up to their efficiency. The wastewater from the ponds is pumped into the fields and is being used for agricultural purpose with out any treatment.

The anticipated demand for sewerage facility in Raichur in 2026 will increase to 36 MLD. The existing sewer network falls short even the present demand. Thus an Up gradation of the system is proposed under this investment Program

2.2.3 Water Supply Rehabilitation

Presently Raichur has three water supply schemes which were subsequently implemented during the year of 1936 and 1976 on a bank of Krishna River and Tungabhadra canal (Rampur water source) with capacity of 2.27 MLD and 18.16 MLD respectively with a distance 4 km from town near Rampur village. . In addition to this in 2003, augmentation of water supply with Krishna River as source was implemented designed to supply 40 MLD water (New Krishna WSS). Out of this, 10 MLD is provided for supply to the Industrial Growth Centre. The WTP is located in the Industrial Growth Centre. The source works are located upstream of raw water intake of Raichur Thermal Power Station. Thus the present available supply of water is 42.27 MLD against the requirement at consumer end of 25.21 MLD at 100 lpcd.

KUIDFC 12 Span & Voyants

NKUSIP (Package IV – Bellary) Tranche I Sub Projects in Raichur Town IEE Report

Intake of Left Bank canal ( Tungabhatra river) Impound Reservoir for Rampur

Krishna river – New Krishna scheme Krishna river

KUIDFC 13 Span & Voyants

NKUSIP (Package IV – Bellary) Tranche I Sub Projects in Raichur Town IEE Report

2.2.4. Drainage Up gradation

The drainage system in Raichur town mainly consists of five primary drains, which run through the town in East-West or South North direction and tertiary drains which are built around these primary drains.

Table : 5 Drainage system in Raichur . Drains. Length in Km Distribution Open drains (Pucca) 44.00 Kms. 67.50%

Open drains (Kutcha) 3.20 Kms. 4.90%

Closed drains (Pucca) 7.50 Kms. 11.50% Primary drain channels 10.50 Kms. 16.10% Total 65.20 Kms.

Source : DPR ( Detail Project Report ) Raichur.

The existing Drainage System carries Storm in rainy season and waste water in other season. The field inspection reveals that the most of the drains are choked up due to dumping of garbage and debris in secondary and tertiary drains. Practically the above drains are used by households as a dumping yard. In addition due to long neglect of O&M operation of the system most of the drains are in choked condition. Considering and taking in account above problems it is prime importance to up grade existing drainage system.

Proposed Improvement in Basic Infrastructures Of Raichur Town

2.3 Sub-project Component Description 2.3.1 Sewerage System

Around 85 km of the existing sewers lines is in bad condition and cannot be rehabilitated due to non-conformity with the proposed sewer network, being at greater depths. So new sewer network of 299.3km will be provided to replace the existing and expand the system into uncovered areas and also to cater for the future growth. This additional network will serve populations upto the year 2026

KUIDFC 14 Span & Voyants

NKUSIP (Package IV – Bellary) Tranche I Sub Projects in Raichur Town IEE Report

Figure 1: Sewage connecting to the nearby nallah behind IOC colony

It is proposed to construct two new STP’s as per t he zones at existing sites of ST P’s o n e at Ekalaspur and Hosur Villages of total capacity 36.00MLD. Hence the total capacities of the proposed facultative aerated lagoons based STPs at Ekalaspur and Hosur will be 24.00 MLD and 12.00 MLD respectively.

STPs based on facultative aerated lagoons are designed to treat the sewage to the standards for stream disposal even though the treated sewage is expected to be utilized for agricultural purposes. Above 75% reduction in the BOD and COD values shall be expected in the facultative ponds attributing to the design requirement. T able-6 shows the design parameters of STPs.

Table 6: Design Parameters of STP Parameter Unit Domestic Design Design CPCB Sewage Influent Effluent norms** Design Flow MLD -- 36.00 36.00 Biochemical Oxygen Demand Mg/l 250 300 20 30 Chemical Oxygen Demand Mg/l 600 700 250 250 Total Dissolved Solids Mg/l 650 800 500 2100 pH 6.5-8.2 6.5 – 8.2 6.5 – 7.5 5.5 – 9.0 Source: * KUWSDB, Raichur and Design Standards.

KUIDFC 15 Span & Voyants

NKUSIP (Package IV – Bellary) Tranche I Sub Projects in Raichur Town IEE Report

** CPCB standard to discharge effluent into Inland surface water & IS 2490 (1974). . Map 2 shows the lay out of proposed sewerage network with treatment facility.

KUIDFC 16 Span & Voyants

NKUSIP (Package IV – Bellary) Tranche I Sub Projects in Raichur Town IEE Report

FACULATIVE AERATED LAGOON (FAL) OF 24MLD FOR EKLASPUR ZONE

AERATORS 13HP FACULTATIVE AERATED LAGOON POLISHING POND 120.00 X 40.00 Mts. 100.00 X 40.00 Mts.

FACULTATIVE POLISHING POND AERATED LAGOON 100.00 X 40.00 Mts. 120.00 X 40.00 Mts.

OUTLET CHAMBER 5.15 X 5.15 Mts.

TREATED WASTE WATER TO BE DISPOSED FACULTATIVE AERATED LAGOON POLISHING POND 120.00 X 40.00 Mts. 100.00 X 40.00 Mts.

Ele. Control Room From OUT FALL SEWER DG. Room

FACULTATIVE AERATED LAGOON POLISHING POND 100.00 X 40.00 Mts. 120.00 X 40.00 Mts.

Project: URBAN INFRASTRUCTURE DEVELOPMENT SCHEME FOR SMALL AND MEDIUM TOWN (UIDSSMT) CROSS SECTION OF 24MLD SEWERAGE TREATMENT PLANT Client: DIRECTORATE OF MUNICIPAL ADMINISTRATION (DMA) FROM WET WELL 900mm DIA PIPE AERATORS 13HP AERATORS 13HP AERATORS 13HP Title: 386.80 386.70 FACULATIVE AERATED LAGOON (FAL) OF 386.20 386.12 386.55 386.03 385.80 CAPACITY 24MLD FOR RAICHUR 900mm RCC NP3 PIPE 150 THK PCC BAFFEL WALL 385.32 385.29 385.30 385.10 385.13 Consultant: 384.78 384.84 384.84 SPAN CONSULTANTS Pvt. Ltd. 900mm DIA 384.60 384.48 384.63 PIPE 384.30 384.34 384.49 384.18 384.03 (Member of SNC-Lavali Group) in association with SCREEN RAMK INLET 383.70 GRO UPY CHAMBER CHAMBER 384.00 150 THK PCC 2.2m x 2.9m 5.0m x 1.0m GRIT PARSHALL DISTRIBUTION PE 383.20 RAMKY INFRA CONSULTING Pvt. Ltd. LO CHAMBER FLUME CHAMBER INFLUENT S 3.2mx3.2m 1.5 1 383.20 SPAN HOUSE, 92-C, GURUDWAR ROAD, 7.0m x 7.0m 3.3M Length CHAMBER 1: :2 E E SL OP P 1.7mx1.7m O SL LO 1: P :2 MANDANGIR, NEW DELHI-110062 S 2 S E 1 1 .5 LO :1 :1 PE E .5 1 WELL COMPACTED EARTHEN EMBANKMENT EARTHEN BUND USING OP SL 2 SL O FOR GETTING SUITABLE ELEVATIONS FOR GRAVITY FLOW SELECTED EARTH 1 : PE OUTLET GL 380.90 CHAMBER 5.15X5.15M FGL 380.60 TREATED WASTE 0.3m EARTH CLEARANCE 0.3m EARTH CLEARANCE 0.30m BC BRANKET FOR SITTING OF BUND WATER TO BE DISPOSED FOR SITTING OF BUND 379.34

0.30m BC BRANKET

PLAN OF FACULTATIVE AERATED LAGOON (FAL) OF 2NOS. OF CAPACITY 12MLD

AERATORS 18HP

POLISHING POND 60.00 X 67.00 Mts.

FACULTATIVE AERATED LAGOON 72.00 X 67.00 Mts.

OUTLET CHAMBER 3.00 X 3.00 Mts. TREATED WASTE

F L O WATER TO BE W CHANNEL TO PARSHALL FLUME 0.8X.39M DISPOSED TURFING SLOPE 1:1.5 SLOPE INFLUENT SLOPE 1:1.5 CHAMBER 1.7.0X1.7.0M MEDIUM DISTRIBUTION GRIT SCREEN INLET AERATORS CHAMBER CHAMBER CHAMBER CHAMBER 5.0 x 5.0mts. P CC 0.15m DEPTH AND 0.75m 3.0X3.0M 5.0m x 1.3m 2.75m x 2.85m WIDTH BELOW PIPE 0.60m DIA (RM FROM WETWELL) 18HP

PARSHALL FLUME 1.52X0.15M E1:1.5 SLOP SLOPE 1:1.5

OW TURFING FL

BAFFELE WALL

POLISHING POND 60.00 X 67.00 Mts. Ele. Control Wet well Room From OF 600mm Dia. FACULTATIVE AERATED LAGOON DG. Room 72.00 X 67.00 Mts.

Project: URBAN INFRASTRUCTURE DEVELOPMENT SCHEME FOR SMALL AND MEDIUM TOWN (UIDSSMT) Client: DIRECTORATE OF MUNICIPAL ADMINISTRATION SECTION OF FACULATIVE AERATED LAGOON (FAL) OF 2NOS. OF CAPACITY 12MLD (DMA) Title: FACULATIVE AERATED LAGOON (FAL) OF FROM WET WELL PIPE AERATORS AERATORS 396.30 396.40 CAPACITY 24MLD FOR RAICHUR 395.90 395.63 395.72 395.80 396.15 395.42 395.42 395.04 395.09 395.00 150 THK PCC 600mm DIA 394.85 Consultant: 394.63 394.68 PIPE SPAN CONSULTANTS Pvt. Ltd. 394.36 394.36 394.13 394.08 394.10 SCREEN INLET 393.46 1 393.86 393.92 CHAMBER CHAMBER :1 PE 150 THK PCC .5 (Member of SNC-Lavali Group) in association with O 393.53 5.0m x 1.3m 2.7m x 1.5m S RAMK L L GROUP Y S EARTHEN BUND USING 1 O .5 :1 393.62 600mm DIA P :1 SELECTED EARTH .5 S DISTRIBUTION PARSHALL E 1 392.96 LO CHAMBER WELL COMPACTED EARTHEN EMBANKMENT PE FLUME GRIT 392.48 3.0mx3.0m CHAMBER FOR GETTING SUITABLE ELEVATIONS FOR GRAVITY FLOW RAMKY INFRA CONSULTING Pvt. Ltd. INFLUENT 1.52M Length 5.0m x 5.0m GL 392..30 2:1 PE CHAMBER

S 1.50 LO SLO 1.7mx1.7m SPAN HOUSE, 92-C, GURUDWAR ROAD, PE 2:1 FGL 392.00 2 PE 0.3m EARTH CLEARANCE :1 S SLO 0.3m EARTH CLEARANCE

L 5.00 :1 FOR SITTING OF BUND OPE 2 FOR SITTING OF BUND MANDANGIR, NEW DELHI-110062

0.30m BC BRANKET

388.86 0.30m BC BRANKET

KUIDFC 17 Span & Voyants

NKUSIP (Package IV – Bellary) Tranche I Sub Projects in Raichur Town IEE Report

The proposed treatment plant consists of preliminary, secondary and tertiary treatment units. The Primary Treatment Units comprises of Inlet Chamber, bar screen chamber, Grit Removal Unit with Grit Hopper, Par shall flume or Flow measuring unit with devices, Distribution Box, connecting channels and Inlet weirs. The secondary treatments units are the aerated lagoons/ with a liquid depth of 5.0mts and1.5mts for second and third stages. Impervious lining to the bed of the pond and sidewalls with retaining is proposed.

The tertiary treatment is proposed with chlorine disinfection and mixing baffles to mix the chlorine solution. The disinfected treated sewage flows to outlet channel and proposed to be used for irrigation purpose. The Buffer Zone is also proposed for green plantations around the site. There are provisions for access roads, lighting, and etc. with the total area completely fenced and entry into the STP premises is restricted to the authorized ones

2.3.2 Water Supply

As per the population forecast for 2011, 2026 and 2041 and considering at 100 lpcd at consumer end the requirements are 27.13 Mld, 38.40 Mld and 52.63mld against the present scheme which meet total requirement up to 2026 including the system losses. Hence it is necessary to augment some components of the scheme to meet the proposed demands for the projected population for the year 2026 and 2041 and accordingly the project is formulated.Raichur is more or less situated mid way between Tunga Bhadra River 30 Kms on the south and Krishna River 22 Kms on the north. These sources are studied and investigated in order to meet demand of projected population with demand of water of 38.40 Mld and 52.30 Mld in 2041. The proposed water supply system rehabilitation in Raichur aims at providing safe, adequate and reliable water supply to the inhabitants. The objectives of system improvement are:

(i) Improving the longevity of the individual components and the system; (ii) Improving the operational performance of the components and the system; and (iii) Reducing the loss of the water and increasing the utilizable output of the system.

KUIDFC 18 Span & Voyants

NKUSIP (Package IV – Bellary) Tranche I Sub Projects in Raichur Town IEE Report

OHT for Rampur OHT near Rampur

PCB colony OHT (10 LL) OHT at Nijalingappa nagar

KUIDFC 19 Span & Voyants

NKUSIP (Package IV – Bellary) Tranche I Sub Projects in Raichur Town IEE Report

Map 3 Indicates proposed water supply works in Raichur

M

u

m

b

a

i Y a r a m a r a s D a n d V i l l a g e

P r i v a t e L a y o u t

P r i v a t e L a y o u t

C ap:0.05 ML GL:375.000m

Y a r a m a r a s

P r i v a t e L a y o u t

C

M y r a C d n u B o o B u n C d a M r y C

B RB - 385.971

P r i v a t e L a y o u t

P r i v a t e L a y o u t

P r i v a t e L a y o u t

B h e e m a r a y a C o l o n y Y a r a m a r a s C a m p

Y a r a m a r a s C a m p

Cotton Market M a r v a d i C o l o n y C ap:0.50 ML G L:385.000m

A r j u n a C o l o n y

Capacity 1.00 ML

L .B .S . Nag ar oun dary C MC B C iv il H ospi tal

C handrab anda Lay out

T RB - 393.696

C B RB - 389.872 M C

B

o G L - 382.960 u n

d E klaspura a r C ap - 0.05ML V illage y

N G O C o l o n y

M ayalarahatti Nagar G L- 410.00 Mts. C ap- 0 .91 ML

5 00 MM K al ida s N ag ar D I P-R M K a l i d a s C o l o n y M ay a la rit Na gar

K a l i d a s C o l o n y O l d A s r a y a C o l o n y

H i O l d A s r a y a C o l o n y g h Te n s ion L i n e A P M C

Si y a t h l b a A mbedkar Colonl

Kak atiya Colo ny S i y a t h l b a N ee ra bhav i Na gar R a j i v N a g a r N e e r a b h a v i K u n t a R a g a p p a B a v i 5 00 M M K a l at a la b D I P -RM K a l a t a l a b Medh ar wadi TRB -419.447 J a l a l N a g a r Jal al N ag a r H a j i N a g a r T RB - 403.466 M RB -413.650 B RB -410.447 My ad arwadi T RB - 409.317 MRB - 3 99.591 G L - 399.337 B RB - 398.748 Karn ataka Housing MRB - 404.945Parv ath i NagarT i p p u N a g a r B oa rd H ig h Te nsion Line C apacity-0 .91 ML GL - 386.951 BRB - 396.445 H a j i N a g a r 3 50 M M DI C ap- 0 .05 ML GL -390.428 ( P -R e pl ace ment) Capacity-1.00 ML

H aje C o lo ny Su k a ni C o l o n y Venk ateshw ara Colony T o C T ipu Su ltan S u k a n i C o l o n y ity C olony M a n a s g a l TRB - 419.990 V e e r a n a g o u d a Basaveshwara Nagar C o l o n y M RB -414.775 B RB - 412.273 M addipetM a d i P e t M a n a s g a l V e e r a n a g o u d a PTip ark u Su ltan G L - 397.262 C o l o n y C apacity-0.91 ML

K E B C ol ony N e a r Ve era b had res hw ar N ij aligappa Colony T em p le Maddipet AV si kl li a h g a e l L oharwadi M a d d i P e t e M a k t h a l p e t

T RB - 399.613 F ort K o t t h a l a r M a d i P eA t m b e d k a r N a g a r B RB - 395.800 Am b ed kar Na ga r G L - 389.208 M a d i P e t Cap- 0 .05 ML V enkateshwara Colony G h a l i b N a g a r D e v i N a g a r S tadium H a r i j a n a w a d a P a rk B e r o o n Q u i l l a P a rk J ain Colony H a r i j a n a w a d a R O C K O U T N G O N a g a r C ity Municipal Th a i Na ga r K S R T C O ffice B us Dipo De v i Na ga r Co lo ny T RB -434.780 N e e l a k a n a t e s h w a r a N a g a Nr G O N a g a r D e v i N a g a r GL - 429.744 Capacity-0.45 ML Iq bal N agar A shmiya Compound K S R T C G ajgarpet F a r u k N a g a r B u s S tand I qbalN a g ar M aru thi Nagar Kullsmbi C ol ony Kullsmbi C ol ony G ajag aripe t F o rt

Mangalw ar Pe t P a n c h a m u r i N a g a r Sri Ram Nagar Ra m a n a Doddi J a y a N a g a r

J a y a N a g a r K r i s h n a S u d a m P o l i c e Q u t e r s P a r k

T him m apu r Pet J a w a h a r a N a g a r V i d y a P HE C o lo ny M utton Marke t P HEC ol ony N a g a r Pa n ch b ibiOah ad H o s p e t(Kw athpete) V a s a v i N a g a r P a r k P -S U M P A zad N agar N e w L a y o u t V i d y a N a g a r L a x s h m i p u r a m L a y o u t J a w a h a r a N a g a r T RB - 413.73 M o h a m a d N a g a r H o s p e t(Kw athpete) Ran a prathap Co lo ny A s h o k a D e p o MRB - 409.598 V a s a v i N a g a r PROPOSED ZONE BRB - 406.396 U r u k u n d i E r a n n a U r ukundi N Er annanagara g a r S h i v a s h a n k a r S h i n gK h r Ci so hl o n n a y D e v a r a y a N a g a r (KRISHNADEVARA COLONY) N e w L a y o u t GL - 395.796 r K r i s h n a D e v a r a y a N a g a r K h a d a r G u n d a S a v i t r i N a g a Capacity-0 .50 ML D evar Colony A round BR B College Sai Nagar Z a h i r a b a d N a g a r K h a d a r G u n d a Z a h i r a b a d N a g a r G ol M ark et Za h ee ra bad S a v i t r i G o l M a r k e t N a g a r T RB -442.170 P a r k B RB - 437.497 J a y a N a g a r E x t e n s i o n TRB - 404.869R am pu ra J a n a t h a C o l o n y GL -437.497 P a r k B V il la ge B r a m m a n V a d i S t r e a t N e w L a y o u t al BRB - 402.259 Capacity-1.36 ML am M a n i k a N a g a r an D GL - 394.307 od di M anik a NaM ga r a n i k a N a g a r Cap- 0.05 ML M a n i k a P r a b h u N a g a r S u c h i t r a N a g a r K S R T C S t a f f Q u t r e r s N e w L a y o u t S i d d a r t h a C o l o n y S i d d a rt h a Nag ar A s h o k N a g a r Y a r e g e r a L a y o u t A s h o k N a g a r M a l l i k a r j u n C o l o n y G L -425.000 M eth d is t Ch ur ch In d i ra Naga r M a n i k a P r a b h u N a g a r Capacity-0.30 ML T RB -427.836 I n d h i r a N a g a r BRB - 425.085 A s h o k N a g a r GL -425.085 S u c h i t r a N a g a r Capacity-1.36 ML P a rk S a t y a n a t h C o l o n y Sri Sai Ram Co lony I D S M T C o l o n y

N a d h i s h w a r a N a g a r V i j a y a L a k s h m i L a y o u t RAM PU R IR I .B C ol ony

E s h w a r a N a g a r RI .Ba C olom ny a N a g a r I D S M T C o l o n y V i j a y a L a k s h m i G a n g a M a t a s t a r a C o l o n y L a y o u t P ark R AW WATER PUM P HOUSE J a n a t h a C o l o n y W TP 18 Mld C LAR IFER J y o t h i C o l o n y N e w L a y o u t CLEAR W ATER PUM P HOUSE B S UM P ij a T RB - 403.554 nn C AN AL INTAKE a g BRB - 400.019 era

G L - 390.666 I B C o l o n y

N ea r R a ma lin g es hw ara C ap- 0 .05 ML Te mp le D a t a r C o l o n y S i d d a n a t h C o l o n y

R a g am a nG adda D/ S a n g a m e Jyos thh i Co lonyw a r a S a r d a r N a g a r A m b e d k a r N a g a r

A m a r e s h w a r a N a g a r

H o s u r A m a r e s h w a r a N a g a r y V i l l a g e r a

d

n

u

o

B K M C o l o n y

C

M

C ry B o unda C MC R a d h a k r i s h n a L a y o u t

M at am ari Ro ad

L a y o u t

G a n d h i N a g a r

L a y o u t A n u s h a N a g a r

S id CM C B ou ndary ra m d a a p o u R r a

m R a o y a R a j a m a t h a C o l o n y d al a r t a

M

O f f i c e r s C o l o n y

P a v a n C o l o n y

P a v a n C o l o n y

l P a d m a v a t h i C o l o n y a k a th n u G L a y o u t

P a d m a v a t h i C o l o n y

d

a

o

R

s l

l i S r i S a i E s t a t e H M a

l e y a

b

a

d

h

R

o

a S r i S a i E s t a t e d

d a o R

a r u p a h s A S r i L a k s h m i N a r a s h i m h a S w a m i C o l o n y

KUIDFC 20 Span & Voyants

NKUSIP (Package IV – Bellary) Tranche I Sub Projects in Raichur Town IEE Report

The following are the proposed improvements in water Supply System in Raichur under the NKUSIP. A. PROVIDING & FIXING OF BULK WATER METERS i) Providing & Fixing Bulk flow meters for existing & proposed water supply system

B. HEAD WORKS, WTP & TRANSMISSION MAIN, REHABILITATION & STRENGTHENING (ii) Electrical / mechanical works for raw water pump house at Rampur water works (2x80 hp & 2x 30 hp pumps) (iii) Electrical / mechanical works for WTP plant-2 , Rampur water works (2x150 hp & 150x1,and 350x1 hp pumps) (iv) R ehabilitation works for Rampur-WTP (v) Construction of pure water pump house of size 12.00m x 10.00m at IPS for Rampur zone (vi) Pure water pumping machinery & electrical works at pure water pump house at IPS (vii) Providing 500mm dia DI rising main of length 3720mtr from IPS to west police station (viii) Providing 350mm dia rising main of length 1750mtrs from IPS to Sath kacheri (replacement of existing HDPE pipe 355mm to DI 350mm ) (ix) P roviding 150mm dia DI rising main of length 1670mtrs from Panchamukhi sump to OHT 3.0lakhs litre at Krishna colony (x) Construction of circular pure water sump of size 5m. dia & 3.30m. Height at Krishna devaraya colony near Panchamukhi oht. (xi) Construction of Hume pipe pump house at Panchamukhi sump for Krishnadevaraya colony OHT (xii) Electrical / mechanical works for pure water pump @ Krishnadevaraya colony sump, 10 hpx 2motors (xiii) Construction Over Head tank of capacity: 3.0 lakhs litres staging height : 9 mtr @ Krishna devaraya colony (xiv) Providing 200mm dia DI rising main of length 1600mtrs from SBH junction sump at Satyanatha colony (Xv) Construction of circular pure water sump of size 6m. Dia & 3.30m. Height at Satyanatha colony (Xvi) Construction of Hume pipe pump house at Satyanatha colony sump (xvii) Electrical / mechanical works for pure water pump @ Sathynatha colony sump (20 hp x 2 motors) (xiii) Providing 200mm dia DI Rising main of length 320mtr from sump to GLSR at Satyanatha colony (xix) Construction of ground level service reservoir at Satyanatha colony capacity:5.00 lakhs litres (xx) Construction of 5.00 lakhs litres of 12mts. staging at Nijalingappa colony

C. CITY WATER SUPPLY SYSTEM DISTRIBUTION NETWORK OPTIMIZATION (xxi) Proposed distribution network priority 1&2 (100km length of 90mm dia to 300mm dia of HDPE & DI pipe)

KUIDFC 21 Span & Voyants

NKUSIP (Package IV – Bellary) Tranche I Sub Projects in Raichur Town IEE Report

Table 7: Existing Water Supply salient features A Water Supply System Quantity of Water Supply Designed Present Water Supply a)1st Stage Scheme Old Krishna 4.54 MLD 2.27 MLD river(Deosugur Head Work) b) 2nd Stage in MLD( Tungabhadra Left Bank 18.16 MLD 10.00 MLD canal) c) 3rd Stage New Krishna River 40.00 MLD 30 MLD Available Total Quantity of Water 62.70 MLD 42.27 MLD Per Capita Supply a) present water supply rate(2008) 167.00 LPCD b) In rainy season at consumer end 176.25 LPCD Duration of Supply Once every day for 1 hour Total No. of Public Fountains 2805 Nos. Reservoir / OHT (Liters) 25 No with 18.75 ML Capacity Total No. of House hold connection Domestic – 17000 Nos. Commercial – 335 Nos. % of House hold connection 40.% Monthly Water Tariff For house Connection / Household Rs. 55/- Household For Commercial connection Rs. 100/- connection B Water supply System in slum area a) Slum population ( As per CDP) 49,271 Declared Slum 29 Undeclared Slum - Details of water supply Through Public Fountains Partially provided to declared slums. Through Household Connections Partially provided to declared slums.

KUIDFC 22 Span & Voyants

NKUSIP (Package IV – Bellary) Tranche I Sub Projects in Raichur Town IEE Report

2.3.3 Urban Drainage

The proposal conceived in this report is to improve the existing storm water drains by transforming the discontinuous stretches into a continuous one so that the storm water is properly and adequately drained without overflows and does not lead to flooding in low lying areas. The proposal for Rs 345.00 lakhs provides for constructing 2.226 Kms of drains of sizes 1.50 m to 4.00 m wide and reconstruction of 6 existing road culverts to provide better system of Improvement as prier the study. The provision as per the NKUSIP for storm water drainage for Raichur is Rs 345.00 lakhs. Following are the works proposed under this scheme.

2..3.4 WORKS PROPOSED UNDER THIS PROJECT

1) Nalla no 4. The existing drain from the overflow point of Aam Talab (00.00Ch) to Basaveshwara circle (Ch 1277m) is lined and needs no repairs. From Chn 1277 to Ch 1577 up to the railway culvert there is no lining and is of varying width and hence has to be provided with side walls and bed. From Chn 1577m it is proposed to divert the existing alignment to avoid passing through private land. It is proposed to construct a new drain from this point parallel to the railway track for a length of 876 m so as to connect to primary drain no 3, near the main railway culvert which finally leads to Manchalapura Tank. The total length of the proposed construction of this drain is about 1176.50 Kms.

2) Nala no 3. This is a built up drain, starting from Bombay Company and Farooque Oil mill and flowing through Harijanwada, Maddipet, Basavannabavi, Goushala road, Siya talab and terminating into Manchalapura tank. The width is 4 to 5 m and length is about 3 km. The direction of flow is from east to west. The lining from Chn 0 to Chn 1002 is found to be good. From Chn 1002 to Chn 1232m, from Chn 1232 to Chn 1445 and 1601 Chn 1888 m it is proposed to undertake lining and reconstruction works of 1.75m X 1.50m (230m long), 4.0X1.80m (500m) sections and thereby improve the entire length of this Nalla within the Town. Since Nallah no 7 flows into Nallah 3 in Neerbhavi Kunta it is proposed to have a section of 4.0x1.8 for Nallah 3 to accommodate the flow from Nalla 7.

KUIDFC 23 Span & Voyants

NKUSIP (Package IV – Bellary) Tranche I Sub Projects in Raichur Town IEE Report

3) Nalla No.5: This nallah starts from Amit Ali Rice Mill, flows through Bruhasthwarpet pet on Gunj road to Sukhani colony and joins Nallah No.3 in Siya Talaab (Mukthal pet). The direction of flow is from southeast to northwest. The total length of this nallah is 1037 m, out of which 737 m from Chmn0 to Chn 737 is lined and found good. From Chn 737 to 1037 it is proposed to undertake lining and bed construction and link the Nala with Nala no 3. Hence the length of construction [proposed is 276 m with a box culvert at Chn 868m. 4) Nalla No-7: This nallah starts from Devinagar road and flows through Neerbhavi Kunta and joins the main primary drain no 3 in Neerbhavi Kunta. The length of this drain is about 1710 mts. The direction is from East to West. The entire drain is unlined. It is only proposed to take up lining for a length of 44 m, from Chn 1666 to end point at 1710m, near the junction with Nala 3 in Neerbhavi Kunta, for improving the flow at the joining point. The above works also includes the construction of required cross drainage works.

KUIDFC 24 Span & Voyants

NKUSIP (Package IV – Bellary) Tranche I Sub Projects in Raichur Town IEE Report

Map 4 shows the layout of proposed storm water drain in the Raichur town.

TOPOGRAPHICAL SURVEY MAP OF RAICHUR CITY FOR STORM WATER DRAIN

L E G E ND LOW LYING AREA /

FLOODING AREA M

u

m

b

a i Y a r a m a r a s D a n d EXISTING PRIMARY DRAINS V i l l a g e PROPOSED PRIMARY DRAINS P r i v a t e L a y o u t

W ATER BODIES

RAILWAY LINE

P r i v a t e L a y o u t R O A DS

MAJOR CONTOURS PROPOSED BOX CULVERTS

DRAIN CATCHMENT AREA CDP BOUNDARY CATCHMENT AREA

Y a r a m a r a s

P r i v a t e L a y o u t

P r i v a t e L a y o u t

P r i v a t e L a y o u t M ANCHALAPURA V IL LA GE

P r i v a t e L a y o u t

B h e e m a r a y a C o l o n y Y a r a m a r a s C a m p

Y a r a m a r a s C a m p

MANCHALAPURA TANK

M a r v a d i C o l o n y

A r j u n a C o l o n y

31MLD PROPOSED STP

Civil Hospital

Primary D rain-3

e n E klasp ura i L V illag e n o i s n N G O C o l o n y e T

h g i M ayalarahatti Nagar H

K a l i d a s C o l o n y

H

i g

h O l d A s r a y a C o l o n y T K a l i d a s C o l o n y

e n

s i o

n

e

L

n i i

n L

H e n O l d A s r a y a C o l o n y igh o T i ens s io n n L e in T e

h Primary D rain-3 g i A P M C H P rop osed A8=50.53 H A B ox Culvert at E k la spur R oad

Ambedkar Colonl

Kakatiya Colony S i y a t h l b a R a j i v N a g a r N e e r a b h a v i K u n t a Primary Drain-6 R a g a p p a B a v i K a l a t a l a b M edhar wadi J a l a l N Pro a g a posed r H a j i N a g a r Box Culvert Primary Drain-3 P roposed Box Primary D rain-3 at Neerbavi Proposed Primary C ulvert M edarvadiMyadarw adi K unta S iy a Th al ab P ro posed Box Culvert B asan K arn ataka Housing Parvathi Nagar D rain -4 o n L in e T i p p u N a g a r Bavi Circle B o ard H igh Te n si H a j i N a g a r J2 J1 Primary Drain-7

H aje C olony Pro posed P rop osed Venkateshwara Colony Box C ulvert B ox CulvertT o C T ip u Sultan S u k a n i C o l o n y ity Colony S iya Thalab at Gadwal M a n a s g a l Basaveshwara Nagar R oad V e e r a n a g o u d a A6=18.08 HA A 1= 224.56 HA C o l o n y M addipetM a d i P e t M a n a s g a l V e e r a n a g o u d a PTip ark u Sultan C o l o n y

K E B Colony Nijaligappa Colony M addipet AV si lk l ia h g ae l Loharwadi M a d d i P e tPrimary e Drain-2 M a k t h a l p e t

F o rt A5=32.58 HA K o t t h a l a r M a d i P Ae t m b e d k a r N a g a r M a d i P e t

Venkateshw ara Colony G h a l i b N a g a r D e v i N a g a r P rimary H a rPrim i j a n a w a ary d a Pa rk B e r o o n Q u i l l a P ark Jain C olony H a r i j a n a w a d a Primary Drain -4 D rain-5 R O C K O U T D rain-3 N G O N a g a r

N e e l a k a n a t e s h w a r a N a g N a Gr O N a g a r D e v i N a g a r

A7=99.03 HA Iqbal Nagar Ashmiya Compound A 3= 69.12 HA G ajgarpet F a r u k N a g a r M aruthi Nagar Kullsmbi Colony Kullsmbi Colony A2= 113.29 HA Fo rt

P a n c h a m u r i N a g a r Sri Ram Nagar J a y a N a g a r

J a y a N a g a r K r i s h n a S u d a m P o l i c e Q u t e r s P a r k PHE Colony J a w a h a r a N a g a r V i d y a N a g a r P rimary V a s a v i N a g a r P a r k Azad Nagar H o s p e t(K wathpete) N e w L a y o u t D rain-5 V i d y a N a g a r L a x s h m i p u r a m L a y o u t J a w a h a r a N a g a r M o h a m a d N a g a r H o s p e t(Kwathpete) R ana prathap Colony A s h o k a D e p o V a s a v i N a g a r

U r u k u n d i E r a n n a N a g a r S h i v a s h a n k a r S h i n Kg hr i Cs ho nl oa n D y e v a r a y a N a g a r N e w L a y o u t K r i s h n a D e v a r a y a N a g a r K h a d a r G u n d a S a v i t r i N a g a r Devar C olony Sai Nagar Z a h i r a b a d N a g a r K h a d a r G u n d a Z a h i r a b a d N a g a r S a v i t r i G o l M a r k e t N a g a r P a r k J a y a N a g a r E x t e n s i o n J a n a t h a C o l o n y Ram p ura P a r k Ba V illage B r a m m a n V a d i S t r e a t N e w L a y o u t la AAM THALAB - 164 ACRES M a n i k a N a g a r m a n D M a n i k a N a g a r o S u c h i t r a N a g a r d M a n i k a P r a b h u N a g a r di K S R T C S t a f f Q u t r e r s N e w L a y o u t S i d d a r t h a C o l o n y A s h o k N a g a r Y a r e g e r a L a y o u t A s h o k N a g a r M a l l i k a r j u n C o l o n y M a n i k a P r a b h u N a g a r

I n d h i r a N a g a r A s h o k N a g a r

S u c h i t r a N a g a r P ark S a t y a n a t h C o l o n y Sri Sai R am Colony I D S M T C o l o n y

N a d h i s h w a r a N a g a r V i j a y a L a k s h m i L a y o u t I.B Colony E s h w a r a N a g a r R a m a N a g a r I D S M T C o l o n y V i j a y a L a k s h m i G a n g a M a t a s t a r a C o l o n y L a y o u t P ark J a n a t h a C o l o n y A4=527.66 HA J y o t h i C o l o n y N e w L a y o u t B ija nn ag era I B C o l o n y D a t a r C o l o n y Prim ary S i d d a n a t h C o l o n y D / S a n g a m e s h w a r a S a r d a r D N arain-6 g a r TUNGABHADRA LEFT BANK CANAL A m b e d k a r N a g a r A m a r e s h w a r a N a g a r VH i ol ls a u g r e A m a r e s h w a r a N a g a r

K M C o l o n y

R a d h a k r i s h n a L a y o u t

L a y o u t

G a n d h i N a g a r

L a y o u t A n u s h a N a g a r

d S a id o r R a m m a a p y u la ra R a j a m a t h a C o l o n y a r R t o a a d M

O f f i c e r s C o l o n y

P a v a n C o l o n y

P a v a n C o l o n y

l a k a th n u G P a d m a v a t h i C o l o n y

L a y o u t

d P a d m a v a t h i C o l o n y a

o

R

s

l

l

i

S r i S a i E s t a t e H M

a

l e y

a

b

a

d

h

S r i S a i E s t a t e R

o

a d

KUIDFC 25 Span & Voyants

NKUSIP (Package IV – Bellary) Tranche I Sub Projects in Raichur Town IEE Report

2.4 Investment Program Implementation Schedule

The Investment Program is to be implemented over an six-year period, commencing in FY 2009-10 and civil works construction starting in FY 2009-10. Completion is scheduled by end FY 2015-16

2.5 Investment Program Benefits

In view of the lack of basic infrastructure facilities and its adverse impacts on the environment and also on socio-economic characteristics, the proposed Investment Program aims at providing infrastructure facilities such as adequate and safe water supply and sanitation facilities, to overcome negative environmental impacts. Investment Program benefits and beneficiaries in the Raichur are provided below.

2.5.1 Water Supply System Improvements

Benefits arising from improved water supply comprise of

(i) Reduced risk of water-borne diseases due to access to potable and adequate water supply; (ii) Reduced ground water exploitation; and (iii) Reduced time and costs in accessing alternative sources of water.

Investment Program beneficiaries will comprise households with existing connections and households with new connections who previously obtained municipal water from stand posts. Design year for the proposed water supply distribution network.

. 5 . 2 2 Sewerage System Improvements

Benefits arising from the provision of a well reticulated sewerage network and safe treatment and disposal of sewage comprise of

(i) reduced incidence of water-borne diseases; (ii) Improvement in public health conditions; (iii) Reduction in risks of ground water contamination; (iv) Stoppage of sewage flow in open storm water drains and consequent health hazards resulting from stagnating sewage pools; (v) Reduced risk of treated water supply contamination; (vi) Reduced health risk of agricultural labourers due to usage of raw sewage for irrigation; (vii) Reduced risk of contamination of agricultural fields; and (viii) Availability of treated effluent for agricultural purposes.

KUIDFC 26 Span & Voyants

NKUSIP (Package IV – Bellary) Tranche I Sub Projects in Raichur Town IEE Report

Investment Program beneficiaries will be households getting new connections through proposed sewer lines under this Investment Program. Households who are getting new connections will gain from improved environmental sanitation conditions through properly functioning sewerage system. About 50 percent of the projected populations in 2011 in the sample towns are projected to be the beneficiaries of the proposed sewerage improvement Investment Programs, as indicated in the following table.

Table 8: Existing and Proposed Sewerage system a)Salient Features: RAICHUR S. No. Item Description 1 Location Lat: 15 0 12 ¹¹ N Long: 77 0 21 ¹ E 2 Area 50.70 Sq Km 3 Population 2001 2,05,634 4 Population 2008 2,52,000 5 Number of Households 2008 37,918 6 Projected Population for the year 2011 2,71,400 (Design year) 7 Projected Population for the year 2026 3,84,029 (Intermittent) 8 Projected Population for the year 2041 ( 5,26,300 Ultimate) 9 Total Road Network 476 Kms Existing Sewerage System 10 Existing sewerage system Scheme commissioned in 1971 11 Area covered 40% of the town 12 Length of Network 85 Km 13 No. of Manholes 3500 no. 14 Type of Sewerage Treatment Plant Oxidation Ponds 15 Condition of STP Not working 16 Condition of the Existing Sewerage System BAD Operation and Management 17 Cost of O& M for sewerage system (Rs.) Rs 363 Lakhs per year 18 Cost of House connection Sewerage System Not Collecting (Rs.) 19 Total Cost 5259.73 Lakhs D. Proposed Sewerage System under this project HOSUR ZONE: I Providing &Laying of sewerage network for Hosur zone for a length of 98kms ii Electrical works of 11KV express feeder main of 33 KV from sub-station near K.E.B. colony (Nijalingappa colony) to wet well near sewerage treatment plant at Hosur village (12 MLD)

KUIDFC 27 Span & Voyants

NKUSIP (Package IV – Bellary) Tranche I Sub Projects in Raichur Town IEE Report

iii Providing and laying 300 mm ductile iron rising main from wet well-1 to inlet chamber of FAL 12MLD (Hosur) iv Providing pumping machinery & D.G set for wet well (12 MLD) V Construction of wet well (12 m dia) -12 MLD Vi Approach road to wet well (12 MLD) vii Construction of STP of 12.00 MLD capacity (FAL) EKALASPUR ZONE: I Providing Sewerage network of length 200.5 km Ii Electrical works of 11KV express feeder main of 33 KV from sub-station near K.E.B. colony (Nijalingappa colony) to wet well near sewerage treatment plant at Ekalaspur village (24- MLD) Iii Providing and laying 900 mm M.S. rising main from wet well to inlet chamber of FAL Ekalaspur (24 MLD) Iv Providing pumping machinery & D.G. set for wet well (24 MLD) V Construction of wet well (12 m dia)- 24 MLD Vi Approach road to wet well (24 MLD) vii Construction of STP of 24 MLD capacity (FAL)

Table 9: Sewerage Component Investment Program Beneficiaries

Details Value

HHs with existing connections (2004) No of households 7,500 Ave rage HH size 5.00

Total connected population 40,500

% of population covered 18% HHs with new connections (2011) No of additional households 11,333

Total beneficiary HHs 18,833 Total beneficiary population 101,698

Projected population 271,390 % of Population covered 37%

KUIDFC 28 Span & Voyants

NKUSIP (Package IV – Bellary) Tranche I Sub Projects in Raichur Town IEE Report

2 . 5 . 3

r a i n a g e S y s t e m I m p r o v e m e n t D

Benefits arising from improvement in the drainage system comprise

(i) Reduction in blocked drains and canals and overflowing of culverts, thereby reducing adverse health impacts on residents in low-lying areas; and (ii) Improvement in health and environmental conditions due to non-incidence of water stagnation and mosquito breeding; (iii) Reduction in pollution risk of downstream water bodies; and (iv) Direct benefits to households from avoided flood damage costs and work time lost.

Investment Program beneficiaries will comprise the households located within the drainage catchments areas with the improved environment and amenity provided by a proper functioning drainage system. The Socio-Economic Household Survey indicates that only core poor households are likely to benefit through this proposed improvement system

Table 10 Existing Urban Drainage 1 Open drains (Pucca) 44.00 Kms. 2 Closed drains (Pucca) 7.50 Kms. 3 Open drains (Kutcha) 3.20 Kms. 4 Primary drain channels 10.50 Kms. Proposed Urban Drainage 5 Construction of Urban drainage of length in 345.00 Lakhs 2.226km. Operation and Management 6 Existing Urban drainage 1300.00 Lakhs 7 Proposed Urban Drainage 345.00 Lakhs 8 Total 1645.00 Lakhs 9 Cost of O& M for Urban Drainage @ 1 %( 16.45 Lakhs per Annum. Rs.)

KUIDFC 29 Span & Voyants

NKUSIP (Package IV – Bellary) Tranche I Sub Projects in Raichur Town IEE Report

Table 11: Drainage Component Investment Program Beneficiaries (2011)

Details Value No. of HHs in catchment area (2011)

Numbers 18,833

% of HHs affected by flooding 0.72% Total beneficiary HHs 136 Av erage HH size 5.00

Total beneficiary population 584 Projected population 271,390 % of population covered 0.22%

2.5.4 Urban Roads Improvement

The improvements would increase the effectiveness of the road space by providing improved riding surfaces and removing impedances to the flow of traffic. This improvement reduces the effort or inconvenience of travel between the origin of the traveller and the destination offering these activities. Benefits of road improvements comprise (i) reduced dust generation due to improved road surface; and (ii) optimum fuel consumption due to improved vehicle speeds.

. 6 2 Investment Program Alternatives

The environmental suitability of the proposed components are judged through the selected location and proposed process/technology during both the construction and operation phases. The interaction and the level of interference with the surrounding land use determine the environmental sustainability of the Investment Program components. The following table shows environmental suitability of the selected alternatives.

KUIDFC 30 Span & Voyants

NKUSIP (Package IV – Bellary) Tranche I Sub Projects in Raichur Town IEE Report

Table 12 Investment Program Alternatives

Sub- Suitability of Selected Alternative Component Sewerage The best alternative for the sewerage system is to design the system based System on gravity flow. The proposed gravity system will be simple in operation and require less man power and importantly does not require energy. The natural gravity is utilized to run the system.

In terms of location of the treatment plants, as it is proposed to reconstruct and upgrade the existing plants, no alternative sites were identified. However, these sites are ideally located away from habitation and were selected based on the topography.

There are number of options to treat the wastewater to the standards of either for river discharges or for land disposal after treatment. The options like attached growth aerobic or anaerobic systems or suspended growth systems can be adopted. However, as the existing STPs are stabilization pond based plants and hence it is proposed to upgrade these STPs with FAL technology.

Storm water Only rehabilitation of existing drains is proposed and therefore no alternatives drainage were considered. However, the best alternative of gravity flow system is retained.

Water Supply The best alternative for water supply is to design the system based on gravity flow. However, due to topography and required pressure at the consumer end, the system is designed as partly gravity and partly pumping.

As the existing system losses are at higher side, reducing the losses and improving the efficiency of the system is identified as one of the important component under NKUSIP. Developing of a pumping station at the existing intake is proposed. This is necessitated as the existing pumping capacity is not sufficient. It is proposed to use high efficiency pumps to reduce the energy loads. Roads up Roads considered for improvement are selected based on the traffic and its gradation importance in connectivity and environmental and social issues involved.

No acquisition of land/structure is involved in the road improvement. It involves no tree cutting.

KUIDFC 31 Span & Voyants

NKUSIP (Package IV – Bellary) Tranche I Sub Projects in Raichur Town IEE Report

CHAPTER - III

DESCRIPTION OF THE ENVIRONMENT

3.1 Environmental Profile of Raichur

3.1.1 Introduction 0 0 Geographically, Raichur is situated at 15 12’ North latitude and 77 21’ east longitudes. The two important Rivers, the Tungabhadra and the Krishna form the two boundaries of the district; these rivers flow at around 20 and 30 km respectively from the district head quarter town of Raichur. The town is an important regional centre in the state of Karnataka and is one of the important centres for production of cotton in . Raichur is surrounded by vast agricultural lands and is major trading centre for groundnut, paddy, rice and the other agricultural produces.

3.1.2 Physiographic

The town’s general topography is plain with Rocky hills. The soil of the town is characterised by block cotton soil in the west of the railway line and the remaining area consists of red rocky soil.

3.1.3 Seismology

As per the Seismic Zoning map of India, the Raichur town falls under the Zone II, which is the lowest earth quake risk zone in India. This zone is termed as “low damage risk zone”.

3.1.4 Climatic Conditions

Raichur falls under arid region of the state of Karnataka. The climate of the town is characterised by dry weather in the major parts of the year with very hot summer. The temperature level goes as high as 430C during May and the minimum temperature will be around 15 0C during the months of December and January. The mean maximum temperature during the months of April and May is around 39 0 C. The following table shows the mean temperature values of Raichur.

KUIDFC 32 Span & Voyants

NKUSIP (Package IV – Bellary) Tranche I Sub Projects in Raichur Town IEE Report

Table 13: Mean Maximum and Mean Minimum Temperature (in o C)

Month Long term normal (30 Years) – Mean 2004 (Actual) – Mean

Daily Max Daily Min Hig hest in a Lowest in a Max daily Min month month Daily

Jan 29.9 18.1 32.5 14.8 31.5 15.3 Feb 33.2 20.3 36.3 17.2 34.3 17.4 Mar 36.7 23.4 39.4 19.5 39.7 21.1 April 38.9 25.9 41.3 21.3 40.9 23.0 May 39.3 25.9 42.2 21.9 37.5 22.5 June 34.9 23.7 93.6 21.4 35.8 24.0 July 31.8 22.6 35.5 21.0 32.7 23.2 Aug 31.5 22.2 34.7 20.8 32.8 22.6 Sep 31.7 22.3 34.6 20.5 32.1 22.6 Oct 31.4 22.1 34.1 19.4 32.4 21.8 Nov 29.9 19.7 32.0 16.0 31.8 19.5 Dec 28.8 17.8 31.2 14.8 31.2 16.8 Source: Meteorological Centre,

The town receives Southwest monsoon during the period of June to September and the period between the months of October and November can be termed as post monsoon months. The town experiences scanty rainfall and the long term annual average rainfall is 755 mm. The rainfall is confined and about 70 percent of the annual rainfall is received during the months of June to September. The region is continuously experiencing below normal rainfall during the last four years. The actual rainfall received in the year 2004 is 679 mm with a departure of -10 percent from the normal. However, the year 2004 can be termed as better of considering far below normal rainfall years of 2002 and 2003.

The relative humidity varies from 25 to 80 percent, and is generally higher during the southwest monsoon season ranging from 52 to 80 percent. The following table shows the climatologically details. the wind blows predominantly from west and southwest during monsoon period of June to September while from November to March the predominant wind direction east. The winds are light in this region. Most of the winds occur in the range of 1-5 kmph; and during the monsoon, winds are in the range of 6-11 kmph also occur.

KUIDFC 33 Span & Voyants

NKUSIP (Package IV – Bellary) Tranche I Sub Projects in Raichur Town IEE Report

Table 14: Climatologically Characteristics of Raichur

Month Long term normal (30 Years) – Mean 2004 – Actual RH Max RH Min Wind Total Mean RH Mean RH Total Speed Rainfall 0830 Hrs 1730 Hrs Rainfall

% % Kmph mm % % mm

Jan 62 33 9.2 0.5 50 36 4.5 Feb 52 27 9.6 1.7 38 29 0.0 Mar 47 25 10.1 4.6 34 23 0.0 April 52 27 10.4 25.8 41 27 36.1 May 59 31 13.7 41.3 57 43 127.0 June 72 49 18 86.9 59 47 37.4 July 79 59 18.4 145.6 68 59 115.1 Aug 78 57 16.5 140.8 65 49 15.3 Sep 77 55 11.9 170.7 71 63 284.4 Oct 71 50 8.7 115.7 69 59 58.8 Nov 63 41 9.2 13.6 53 41 0.0 Dec 64 37 8.8 7.4 47 34 0.0

Fig 2: Wind Rose Diagram of Raichur ( 0830 Hrs and 1730 Hrs)

KUIDFC 34 Span & Voyants

NKUSIP (Package IV – Bellary) Tranche I Sub Projects in Raichur Town IEE Report

3.1.5 Water Bodies

Tungabhadra flows at a distance of about 20 km from the town. Two water bodies, the Manchalapur tank and Aam talab, are located in the town. Almost 80 percent of the area drains into Manchalapur Tank and the remaining in to the Aam Talab. Due to low rainfall in the area, the tanks are almost dry. As the rainfall is confined to short period of the year, these streams carry wastewater for most parts of the year and eventually pollute the Manchalapur Lake and Aam Talab. At present, these lakes are polluted and filled with wastewater. Due to lack of adequate sewerage system, the wastewater enters these streams.

KUIDFC 35 Span & Voyants

NKUSIP (Package IV – Bellary) Tranche I Sub Projects in Raichur Town IEE Report

3.1.6 Groundwater

In addition to the municipal water supply in the town, sizable population also depends on groundwater resources; in the extension areas and uncovered areas the groundwater is only source of water. The depth of water table is medium and is in the range of 8 m to 14 m; however, due to low yield of top aquifer, the depth of wells are generally deep i.e. more than 50 m. Table -15 shows the fluctuation in the depth of water table at Raichur. There are no major fluctuations recorded during last three years.

Table 15:Groundwater Levels in Raichur

Month Groundwater Depth (m) 2002 2003 2004 January -- 11.05 11.86 February -- 12.50 12.01 March -- 12.80 12.70 April -- 12.95 12.85 May -- 13.50 12.21 June -- 13.70 11.85 July 8.15 12.90 11.14 August 7.75 12.00 12.12 September 7.31 12.63 8.85 October 5.21 11.10 7.80 November 9.70 11.14 8.27 December 11.05 11.79 9.16 Source: Department of Mines & Geology

Table -16 shows the groundwater characteristics in the area. Most of the monitored parameters are exceeding the desirable limit specified under IS 10500, however, are under permissible limits. The Nitrate concentration is much higher than the permissible value of 100 mg/l.

KUIDFC 36 Span & Voyants

NKUSIP (Package IV – Bellary) Tranche I Sub Projects in Raichur Town IEE Report

Table 16: Groundwater Characteristics in Raichur

Parameter July 2003 June 2004 pH 7.5 8.11 Total Hardness 565 316 TDS 1098 1110 CO3 0 0 HCO3 48 371 Cl 258 267 SO4 112 130 NO3 120 147 Ca 889 59 Mg 85 41 Na 169. 269.5 K 10.5 0.5 F 0.5 0.5 Fe 0.2 0.6 Source: Department of Geology and Mines 1 • All units are mg/l except pH

3.1.7 Ambient Air Quality

The ambient air quality status of Raichur shows that all the pollutants in ambient air are well with in the limits. Table - 17 shows the ambient air quality parameters of Raichur.

Table 17: Ambient Air Quality of Raichur

Parameter At KSCPB Office Ambient Air quality standard Average value of air pollutant

µg/m3 µg/m3 TSPM 127.42 360 RSPM -- 120 Sox -- 80 NOx -- 80 Source : KSPCB Annual Report 2002 – 03

KUIDFC 37 Span & Voyants

NKUSIP (Package IV – Bellary) Tranche I Sub Projects in Raichur Town IEE Report

3.1.8 Flora and Fauna

There are no forest areas in and around the town and there are no sensitive environmental features such as National Parks, Wetlands, and Biosphere Reserves in the . No endangered/protected species of either flora or fauna are found in the town and their surroundings.

3.1.9 Socio Economic Characteristics

Demography: Raichur has witnessed a remarkable increase in the population. It has grown from 169,488 in 1991 to 205,634 in 2001, registering a decadal growth rate of 36 percent. Extending to a total area of 41.23 sq. Km inhabiting little more than 0.2 million population, the gross density of the town is 4,987 persons per sq. km. Mukthalpet,

Maddipet, Arab Mohall, Androon Quill, Baron Quill, Mangalwarpet, Gajgaripeth and Somwarpet are thickly populated areas of the town. Due to lack infrastructure facilities such as water supply and sewerage in the fringe areas, the people prefer to remain in the central served areas rather than move to the town periphery.

The sex ratio (2001) in Raichur was 945, which is slightly lower than the district urban average of 949 and slightly more than the State urban average of 941. The town has higher and literacy rate in comparison with the district. The respective figure in 2001, for Raichur was 71.5 percent and that of district and State urban literacy was 67.6 percent and 71.4 percent.

Economic Base . Raichur is a focal point for trade and commercial activities in the region. There are eight large and medium scale industries in the taluka. The town has a sound industrial and as well agricultural based development. Cotton and rice are the main exports of the town. Raichur town has the most prestigious and profit making power generation unit, Raichur Thermal Power Station with 6 units each of 210 MW capacity which is running almost 100 percent capacity. As the power plant is located away from the town, interference with the town air quality is not observed, which is evident from the air quality data of the town.

Poverty . Urban slum dwellers in Raichur constitute 38 percent of the town’s population.

3.1.10 Cultural and Historic Places

Though the Raichur region has great mythological importance and rich history, there are no protected monuments in the town. Weapons and implements made of stone are found in villages called , Karadkal and Kallur. During the 3rd century, the district was ruled by

KUIDFC 38 Span & Voyants

NKUSIP (Package IV – Bellary) Tranche I Sub Projects in Raichur Town IEE Report

Maura Dynasty. It is said that the great emperors, namely, ‘Samarat Ashok’, Chalukyas, Rashtrakutas and Hoys alas have also ruled the district.

During the time of Independence Raichur was ruled by Nizams of Hyderabad. A fort was constructed during this period.

KUIDFC 39 Span & Voyants

NKUSIP (Package IV – Bellary) Tranche I Sub Projects in Raichur Town IEE Report

Chapter - IV

SCREENING OF POTENTIAL ENVIRONMENTAL IMPACTS AND MITIGATION MEASURES

Potential Environmental impacts of the proposed infrastructure components are presented in this section. Mitigation measures, to minimize/mitigate negative impacts, if any, are recommended along with the agency responsible for implementation. Monitoring actions to be conducted during the implementation phase is also recommended to reduce the impact.

Screening of potential environmental impacts is categorized into four categories considering Investment Program phases: location impacts and design impacts (pre construction phase), construction phase impacts and operations and maintenance phase impacts.

(i) Location impacts include impacts associated with site selection, and include loss of on- site biophysical array and encroachment either directly or indirectly on adjacent environments. It also includes impacts on people who will lose their livelihood or any other structures by the development of that site.

(ii) Design impacts include impacts arising from project design, including technology used, scale of operation/throughput, waste production, discharge specifications, pollution sources and ancillary services.

(iii) Construction impacts include impacts caused by site clearing, earthworks, machinery, vehicles and workers. Construction site impacts include erosion, dust, noise, traffic congestion and waste production.

(iv) O & M impacts include impacts arising from the operation and maintenance activities of the infrastructure facility. These include routine management of operational waste streams, and occupational health and safety issues.

Screening of environmental impacts has been based on the impact magnitude (negligible/moderate/severe – in the order of increasing degree) and impact duration (temporary/permanent). The following table shows the screening of impacts; N/T represents the lowest impact while S/P represents the highest impact. Numerator represents the Degree of Impact and denominator represents the Duration of impact.

KUIDFC 40 Span & Voyants

NKUSIP (Package IV – Bellary) Tranche I Sub Projects in Raichur Town IEE Report

Table 18 : Screening of Impacts

Magnitude (Degree of Impact)

Duration of Impact Negligible(N) Moderate(M) Severe(S) Temporary(T) N/T M/T S/T Permanent (P) N/P M/P S/P

The following tables show the potential Environmental Impacts and mitigation measures of all the sub-project components proposed for Raichur under NKUSIP.

KUIDFC 41 Span & Voyants

NKUSIP (Package IV – Bellary) Tranche I Sub Projects in Raichur Town IEE Report

Table 19: Environmental Impacts and Mitigation Measures for Sewerage System

Impact Description Significance of the Impact Mitigation Measures Implementation Preliminary Responsibility Costing Location impacts Change in land use; M/P Addressed in RP ULB will prepare and implement the Part of RP cost loss of land/lively RP; ULB may use the services of the hood due to The site selected for construction of Investment Program Consultant and construction of STPs STP at Hosur zone is agricultural NGO. at Ekalaspur and land. Hosur Only 10 acres of land to be acquired for Hosur Zone STP. No land acquisition required for Ekalaspur Zone STP. Land owners are predominantly small and marginal here are no structures situated in this land. The details of project affected people will take care in social impact assessment And R & R report separately.

KUIDFC 42 Span & Voyants

NKUSIP (Package IV – Bellary) Tranche I Sub Projects in Raichur Town IEE Report

Contamination of M/P A protective CMC Raichur The cost of soil groundwater It has been seen that groundwater impervious layer shall testing will be resources due to depth in Raichur is in the range of 10- be provided for the part of leaching from 15 mtr. As proposed activity is based bottom and walls of th e design facultative aerated on expansion of existing STP which ponds to avoid lagoons will receive very low flow there will be seepage. This minimum impact on ground water impervious layer is a because of proposed activity. Further, part of the design for Groundwater there is no groundwater data available not only to arrest the sampling and near the site to substantiate weather seepage but also to laboratory or not the oxidation ponds are leading provide smooth costs will be to groundwater pollution. This is working surface for de- part of applicable for both the STPs. sludging. design.

A groundwater test shall be conducted to . know the base water quality. Open well located in the northern side of the Ekalaspur site may be taken as monitoring well.

KUIDFC 43 Span & Voyants

NKUSIP (Package IV – Bellary) Tranche I Sub Projects in Raichur Town IEE Report

Imp act Desc ription Signifi cance of the Im pact Miti gation Meas ures Imple men tation Preliminary Responsibility Costing

Loss of amenity and N/P Development of CMC Raichur Part of design odour physical separation costs Nuisance to Due to Facultative aerated lagoons and visual screen neighbours. based STP; the odour problem around the facility will may be significant. Both the sites address this impact. A buffer zone in the form are located away from habitation. of landscaping and At Hosur site, a Railway Station is earthwork shall be located at 1 km. created around the STP. The reduction in land values is not Air dispersion envisaged; instead, value may modelling at detailed design stage. increase due to availability of treated water for irrigation.

KUIDFC 44 Span & Voyants

NKUSIP (Package IV – Bellary) Tranche I Sub Projects in Raichur Town IEE Report

Des ign Im pacts Discharge of partially M/P The sew age retention CMC Raichur N/a. treated sewage will period shall be fixed have potential to The treated sewage is proposed Considering pollute the to be used for irrigation. seasonal climatic Agricultural fields. variations. The The treatment process chosen effluent from the STP (FAL) is simple and does not shall be confirmed to involve any complexities in design, the following standards of construction or operation, thus discharge: ensures the treatment efficiency with least supervision. • BOD < 30 mg/l • pH – 5.5 – 9.0 • Suspended solids < 100 mg/l Nuisance due to N/P RegularThe tr e maintenanceat ed sew age is CMC Raichur N/a. leakage/ will nullify the impact. Overflowing of Usage of appropriate sewers. maintenance equipment would substantially reduce the maintenance time.

KUIDFC 45 Span & Voyants

NKUSIP (Package IV – Bellary) Tranche I Sub Projects in Raichur Town IEE Report

Poll utio n due to M/P Safe sludge handli ng CMC Raichur Part of O & M improper methods shall be costs Sludge disposal Sludge removal from the ponds may employed. methods. be done once for every 2 or 3 years, Personal protection Preparation of sludge depending on the sludge generation equipment such as management plan Quantity of sludge generation will be gloves, boots, shall be (consultant time: one considerable. Contaminated work provided to the person week) area may cause health hazards. workers. Sludge shall be dried in drying beds before its disposal in low-lying areas.

A sludge management plan shall be prepared.

Construction Impacts

Impacts to livelihood M/T Maintain assess to Head Contractor/CMC Preparation business (shops) people by Raichur and implementation of The laying of sewerage line will disturb the pro viding planks/ makeshift site management plan. day to day activities of public such as shops, pathways, etc. residence and also leads to un safety condition to them. While laying sewers through narrow streets and thick commercial establishments, the work will be planned to complete in short duration and care will be taken to avoid excavation of the entire road stretch in these areas.

KUIDFC 46 Span & Voyants

NKUSIP (Package IV – Bellary) Tranche I Sub Projects in Raichur Town IEE Report

Nuis ance due to du st M/T Con stru ct ion mate rial Head Pr epar ati on and and shall be stockpiled. Contractor/CMC Raichur implementation of noise; road Dust generation may be Adequate site blocking due to significant as the dry weather arrangements for traffic management plan laying of sewer condition prevails in the town. diversions including (preparation : network; and, erection of proper sign consultant time: increased traffic The proposed rehabilitation and boards. Dust one person week; flow due to vehicle laying of new sewers cover almost all generation must be implementation:1 day movement for the areas of the town. The impact of arrested by water per fortnight Construction spraying. Ensure of construction activities. construction activities on the densely usage of standard management population areas of Mukthalpet, equipment to reduce time) Maddipet, Arab Mohall, Androon the noise nuisance. Quill, Baron Quill a, Mangalwarpet, Construction Gajgaripeth and Somwarpet area equipment shall be may be considerable and in the other standard reputed make areas it may be insignificant. which itself take care of noise and will comply with standard stipulated by pollution control board. Noise level shall be reduced with increase in distance and construction activity will be restricted in day time only. In extreme case due care will be taken to minimize the noise during night time.

KUIDFC 47 Span & Voyants

NKUSIP (Package IV – Bellary) Tranche I Sub Projects in Raichur Town IEE Report

Impact Significance of the Impact Mitigation Measures Implementation Preliminary Description Responsibility Costing A construction site management plan shall be prepared. Poor performance of the contractor may potentially exacerbate these impacts and therefore qualified contractors to be appointed. The contracted work includes the implementation of construction site management plan, which will Address these issues.

O & M Impacts Odour nuisance M/P Buffer zone in the form of landscaping and Earthwork shall be created and well maintained around the site.

KUIDFC 48 Span & Voyants

NKUSIP (Package IV – Bellary) Tranche I Sub Projects in Raichur Town IEE Report

Potential pollution of N/P Implement the CMC Raichur Part of O & M agricultural fields mitigation measures costs As the STP is designed for stream suggested in the discharge standards, the impact design stage. may be minimal. However, the overloading of STP may When pond gets exaggerate these problems. over-loaded, adding oxidation agents and plant foods such as sodium nitrate must simulate the algae growth. The effluent discharge shall confirm to the following standards: • BOD < 30 mg/l • pH – 5.5 – 9.0 • Suspended solids < 100 mg/l Developing landscaping around the STP site to ensure aesthetic health environment and minimising odour problem if any.

KUIDFC 49 Span & Voyants

NKUSIP (Package IV – Bellary) Tranche I Sub Projects in Raichur Town IEE Report

Pollution and M/P Safe sludge handling CMC Raichur Part of O & M health methods shall be costs hazards due to Quantity of sludge generation will be employed. improper sludge considerable. Contaminated work Personal protection disposal methods area may cause health hazards. equipment such as gloves, boots, shall be provided. Sludge shall be dried in drying beds before its disposal. This sludge may be used as manure for non- food crops or land filled.

Sludge management plan shall be implemented. Impacts due to M/P Illegal tapping of CMC Raichur Part of O & M illegal sewage from the costs tapping of Trunk sewers traverse agricultural sewer lines shall not sewage for fields. Illegal tapping was observed. be allowed. Regular irrigation purpose This is more significant in the case maintenance and constant check would from trunk of Ekalaspur STP. reduce the problem. sewers:

KUIDFC 50 Span & Voyants

NKUSIP (Package IV – Bellary) Tranche I Sub Projects in Raichur Town IEE Report

Impact Description Significance of the Impact Mitigation Measures Implementation Preliminary Responsibility Costing Ground water; potential hazards due to entering of contaminants into food chain. Impact on the working condition of the STP due to reduced inflow.

Nuisance and M/P Regular maintenance CMC Raichur Part of O & M pollution of will nullify the impact costs Ground/surface Irrigation canals traverse the town water due to and the groundwater depth is overflowing/choking shallow in the northern part of the of sewers. town

KUIDFC 51 Span & Voyants

NKUSIP (Package IV – Bellary) Tranche I Sub Projects in Raichur Town IEE Report

Table 20: Environmental Impacts and Mitigation Measures for Water Supply Rehabilitation

Impact Description Significance of the Impact Mitigation Measures Implementation Preliminary Responsibility Costing Location impacts Since the location of N/a. N/a. N/a. N/a. rehabilitation Work will be at existing facilities, and the existing environment is not a sensitive environment, no location- specific impacts are envisaged. Design Impacts Since the location of N/a. N/a. N/a. N/a. rehabilitation work will be at existing facilities, and the existing environment is a built environment, no design- specific impacts are envisaged. High noise from the N/P Workers who are working on CMC Raichur Part of Design proposed 300 HP pumping pumping station shall be provided and station for Raichur. No sensitive area has with all personal protective Operation However, as the site is been envisaged around equipment. Like ear muffler etc. cost located far away from the site and impacts only sensitive locations, no major anticipated on worker. impact is envisaged.

KUIDFC 52 Span & Voyants

NKUSIP (Package IV – Bellary) Tranche I Sub Projects in Raichur Town IEE Report

Pollution and health risks M/P Safe sludge handling methods shall be CMC Raichur Part of O & M due to improper handling employed - Personal protection costs and disposal of sludge from The sludge may contain equipment such as gloves, boots, shall Preparation of water treatment plants harmful substances including be provided. Sludge shall be dried in sludge the alum sludge. drying beds before its disposal. This management sludge may be land filled. plan (time: 1 Sludge management plan shall be person week) prepared.

Construction Impacts

Impacts to livelihood M/T Maintain assess to busi ness (shops) Head Contractor/CMC Preparation people by providing planks/ makeshift Raichur and The laying of water line will pathways, etc. implementation of disturb the day to day activities of site management public such as shops, residence While laying water line through narrow plan. and also leads to un safety streets and thick commercial condition to them. establishments, the work will be planned to complete in short duration

and care will be taken to avoid Road blocking due to laying of N/T excavation of the entire road stretch in water supply network and these areas increased traffic flow due to The impact due to construction Head vehicle movement for activity may not be significant Construction material shall be Contractor/CMC Part of construction activities; as proposed network will be laid stockpiled to minimize traffic construction costs inconvenience to the local in a area which are not densely blockages. community. populated in the presently fringe and extension areas. Poor performance of the contractor may potentially exacerbate these impacts and therefore qualified contractors to be appointed. The contracted work includes the Implementation of construction site management plan, which will address these issues.

KUIDFC 53 Span & Voyants

NKUSIP (Package IV – Bellary) Tranche I Sub Projects in Raichur Town IEE Report

Impact Description Significance of the Impact Mitigation Measures Implementation Preliminary Responsibility Costing

Dust and noise from Frequent water Head Part of construction M/T spraying program will Contractor/CMC construction Activities. be employed to costs Due to dry climatic condition the ensure dust dust generation may be suppression in considerable. maximum extend. No major noise generating activities such as rock blasting and use of heavy noise generating equipment is not envisaged.

Operation Impacts Recurrence of The leak detection CMC Raichur Included in the blockage and and water auditing project cost leakage Problems. M/T surveys shall be conducted. The The existing system losses are leak restoration very high. time shall be minimized.

KUIDFC 54 Span & Voyants

NKUSIP (Package IV – Bellary) Tranche I Sub Projects in Raichur Town IEE Report

Pollution and M/T Implement the CMC Raichur Part of O & M health risks due mitigation measures as costs to improper in the Sludge handling and Management Plan. disposal of sludge from water treatment plant

Table 21: Environmental Impacts and Mitigation Measures for Roads Up-gradation

Impact Description Significance of the Mitigation Measures Implementation Preliminary Impact Responsibility Costing Location Impacts No location impacts are N/a. N/a. N/a. N/a. envisaged as the proposed activities do not encroach into any sensitive land uses nor it involves any land acquisition.

Design Impacts Acquisition of land/structure is N/a. N/a. N/a. N/a. not envisaged. No trees will be cut as part of the project.

Construction Impacts

KUIDFC 55 Span & Voyants

NKUSIP (Package IV – Bellary) Tranche I Sub Projects in Raichur Town IEE Report

Disturbance to informal N/T Temporary relocation CMC Raichur As part of RP commercial activities during of hawkers and costs construction. No Hawkers and vendors vendors; followed by were observed. A detailed reinstatement of survey will be conducted original premises at the design stage to when the work is identify hawkers and completed. vendors

Disturbance due to construction N/T N/a N/a N/a activities Road block and increase Low levels of traffic was in traffic on the observed on the alternative routes and proposed roads traffic congestion Nuisance due to noise. M/T Noise limits for Head Contractor N/a. construction Proposed roads pass equipments such as through residential areas. compactors, rollers shall not exceed 75 dB(A), as specified by CPCB. High noise generating activities, if any, shall be restricted in day time only. Dust nuisance. M/T Dust suppression Head Contractor Part of activities such as construction Proposed roads pass water sprinkling shall costs through residential be employed. areas. Due to dry weather condition dust nuis ance may be

KUIDFC 56 Span & Voyants

NKUSIP (Package IV – Bellary) Tranche I Sub Projects in Raichur Town IEE Report

Pollution and silt loading of N/a. N/a. N/a. N/a. water bodies Public and worker safety N/T Provide caution and Head Part of signboards. Contractor/CMC construction costs

KUIDFC 57 Span & Voyants

NKUSIP (Package IV – Bellary) Tranche I Sub Projects in Raichur Town IEE Report

Chapter – V

INSTITUTIONAL REQUIREMENTS AND ENVIRONMENTAL MONITORING PLAN

5.1 Institutional Requirements

Karnataka Urban Infrastructure Development & Finance Corporation (KUIDFC) is the nodal executing agency (EA) responsible for implementing NKUSIP. Investment Program implementation activities will be monitored by KUIDFC through a separate Investment Program Management Unit (IIPMU), which will be set-up within KUIDFC.

Implementing Agency (IA). Implementation Agencies (IA) will oversee sub-project component implementation at the sub-project towns, where the Investment Program ULB will implement sub- project components. The responsibilities of the IA shall include (i) carrying out detailed surveys, investigations and engineering designs of individual infrastructure components; (ii) tendering, evaluating bids and awarding works, contract administration, supervision and quality control; (iii) measuring works carried out by the contractors and certifying payments; (iv) conducting public awareness campaigns and participation programs, (v) carrying out environmental assessments; and (vi) preparing monthly reports. The Investment Program Consultants (PC) will assist the Investment Program ULB in all the aforesaid activities; in the case of other IAs, the PC shall proof check designs and quality check construction quality.

` Thus, the responsibility fulfilling environmental requirements of GoI/GoK (for the project- components of STP,) and conducting required level of environmental assessment as per ADB guidelines lies with the borrowing ULB. The Investment Program Consultants will assist the ULB in this regard. The IEE reports prepared by ULB will be reviewed by the IPMU as per the ADB’s Environmental Guidelines and forwarded to ADB for review and approval. In case of IEE reports, the ADB could delegate approval of IEE reports fully to the IPMU after reviewing the first two reports. However, all the IEE reports shall be sent to ADB for approval.

The mitigation measures identified through IEE are incorporated into the project cycle. Mitigation measures, which are implemented by the Contractor, shall form part of the Contract Documents. The other mitigation measures are undertaken by the ULB (itself or in assistance with Investment Program Consultants) as specified in the IEE.

KUIDFC 58 Span & Voyants

NKUSIP (Package IV – Bellary) Tranche I Sub Projects in Raichur Town IEE Report

Table 22: Institutional Roles and Responsibilities Inv estm Activity Details Responsible ent Agency Progra

Pre Investment Program Reviewing the REA and assigning project IPMU construct Categorization category (Ea/Eb/Ec) based on ion NKUSIP Environmental Assessment phase Guidelines and ADB Guidelines Conducting EA Conducting IEE/EIA based on the project Investment categorization Program Consultants Conducting Public Consultation and information disclosure

Investment Fulfilling GoK/GoI requirement such as ULB Program clearances from other Government Review of EIA/IEE Reviewing the EIA/IEE and SEIA/SIEE IPMU Reports to ensure compliance of the report Disclosure of SEIA/SIEE Information disclosure -SIEE/SEIA reports ULB should be made available to the public, Incorporation of Incorporation of necessary mitigation Investment mitigation measures measures identified in IEE/EIA in Program into Investment project design and in contract Consultants Review of Review of design and contractual IPMU design documents for compliance of mitigation Construct i Implementation Implementation of necessary mitigation Contractor on of mitigation measures Phas e Monitoring Environmental monitoring as specified in Investment monitoring plan during construction stage; Program monitoring of implementation of mitigation Consultants Preparation of Preparation of monthly progress reports to ULB in progress reports be submitted to IPMU including a section on assistance of

Review of progress IPMU to review the progress reports, IPMU Operation Environmentalreports Conductingcon solidate a environmentalnd send to ADB monitoring,revi ew ULB Stage Monitoring as specified in the environmental monitoring plan. Compliance Monitoring Compliance monitoring to review the KSPCB environmental performance of sub-

KUIDFC 59 Span & Voyants

NKUSIP (Package IV – Bellary) Tranche I Sub Projects in Raichur Town IEE Report

5.2 Training Needs

As described in the above table the IPMU will involve in monitoring the project implementation while the ULB will implement the Investment Program. It is therefore important that these agencies and particularly the officials involved in the Investment Program to have understanding of the ADBs environmental assessment procedures and also of environmental issues of various urban infrastructure components. As far as implementation of mitigation measures on site is concerned the Contractor will be involved. Hence, it is important to orient the contractors and supervisory staff towards the implementation of mitigation measures and their consequences. Hence, considering the existing capabilities of the agencies involved in NKUSIP, the following training program is suggested. The following table presents the suggested training program.

KUIDFC 60 Span & Voyants

NKUSIP (Package IV – Bellary) Tranche I Sub Projects in Raichur Town IEE Report

Table 23: Training Needs (2009 – 2015)

Description Contents Schedule Participants

Program 1 Module 1 – Orientation 2 days IPMU officials Orientation • Investment Program Cycle of involved in Program NKUSIP the Investment / Workshop for • ADBs Environmental Program and Assessment Guidelines ULB officials Implementing • EA requirements of NKUSIP involved in Ag ency and Indian Environmental Laws & Investment Program Executing Regulations relating to urban implementation n. Agency infrastructure project Environmental impacts of urban infrastructure projects

Module 2 Environmental Assessment Process Investment Program categorization as per ADB • IEE/EIA process, Formats and Reports • Identification of Environmental Impacts • Identification Mitigation Measures • Formulation of Environmental Management Plan • Implementation and Monitoring • Summary EIA/IEEs Review of EIA/IEE reports to comply with ADB requirements Incorporation of mitigating measures in the project design and contracts

KUIDFC 61 Span & Voyants

NKUSIP (Package IV – Bellary) Tranche I Sub Projects in Raichur Town IEE Report

Program - 2 Module 1 Implementation of 1 day Contractors involved Orientation Mitigation Measures in NKUSIP Program Environmental issues related urban • Supervisory staff of / Workshop forinfrastructure projects during ULB Contractors andconstruction Supervisory staff Implementation of mitigation measures • Monitoring of implementation Program - 3 Module – Experiences and Best 1 day (every • IPMU Experience Practices alternative officials Sharing Experiences on implementation in year from the • ULB officials terms of environmental concerns of start • Local NGOs implemented projects of project, • Best Practices followed i.e. 2009)

5.3 Environmental Monitoring Plans

The following tables indicate the recommended environmental monitoring programs for sub- project components in Raichur. The monitoring program has been developed based on Suggested mitigation measures presented in the earlier subsection.

KUIDFC 62 Span & Voyants

NKUSIP (Package IV – Bellary) Tranche I Sub Projects in Raichur Town IEE Report

Table 24: Environmental Monitoring Plan for Sewerage Up-gradation

Mitigation Measures Parameters to Location Measurement Frequency Responsibili Preliminary be ty Costing Monitored

Preconstru ct ion Preparation of the RP N/a. Verification of RP One-off IPMU IPMU staff Resettlement Plan documentation documentation verification time (RP) in accordance and progress of consistent with of designs as required with all applicable implementation the Resettlement Apex NGO Acts/Guidelines Framework, GoI, Once during will assist the including ADB’s IR GoK and the implementati IPMU in Policy. ADB Guidelines. on and once monitoring ju st after Monitoring based implementati on RP/RF on All location and design Incorporation of N/a. Verification of One-off IPMU N/a. Design related mitigation mitigation project design inspection checking measures. The measures in the documentation of designs measures are to design mitigate the following including air through appropriate dispersion design of process and modeling for layout. STP site. (i) Groundwater contamination (ii) sludge disposal and (iii) air dispersion modelling. Cons tructi on St ag e All construction related Incorporation of N/a. Inspection of One-off IPMU N/a. Design mitigation measures mitigation contract inspection checking such as construction measures in the documents before site management plan contract signing of to control the dust and documents the contract noise nuisance, and road blocks implementation of

KUIDFC 63 Span & Voyants

NKUSIP (Package IV – Bellary) Tranche I Sub Projects in Raichur Town IEE Report

construction site Dust and noise at the Uses of standard Weekly CMC Raichur management plan: nuisance, sewer reputed make with providing access to disturbance to laying equipment the businesses during traffic flow sites and comply with PCB assistance of pipe lying etc. (i) noise urroundin stipulated Investment and dust nuisance at gs standard . Program site (ii) traffic undertaking Consultants maintenance etc. water sprinkling to suppress dust

Mitigation Measures Parameters Location Measurement Frequency Responsibili Preliminary to be ty Costing Monitored

inspection and inter vie ws Oper ati on St age Check for Groundwater Open well Changes in water Prior to STP CMC Raichur Part of O & contamination of quality located in quality operation; M cost groundwater/ the northern thereafter, agricultural fields due side of the Quarterly to discharge of site (four untreated/partially seasons) treated STP effluent.

KUIDFC 64 Span & Voyants

NKUSIP (Package IV – Bellary) Tranche I Sub Projects in Raichur Town IEE Report

Influent Inlet of STP Analyze the Monthly as CMC Raichur Part of O & wa stewater wastewater part of M cost quality characteristics plant including heavy operation metals such as Mercury (As Hg), Lead (as Pb) Cadmium (as Cd), Total chromium (as Cr), Copper (as Cu), Zinc (as Zn) and Nickel (as Ni) Treated Outlet of Analyze the Monthly as CMC Raichur Part of O & wast ewater STP characteristics to part of M cost quality at comply with the plant outlet PCB disposal operation KSPCB discharge standards. These point of include: Seasonal STP • BOD < 30 (four mg/l seasons) as • pH – 5.5 – third party 9.0 monitoring. • SS < 100 mg/l

Implementation of the Health status N/a Health check up Yearly once CMC Raichur Part of O & Sludge Management of STP for STP staff M cost Plan - Check for health staff hazards due sludge handling.

KUIDFC 65 Span & Voyants

NKUSIP (Package IV – Bellary) Tranche I Sub Projects in Raichur Town IEE Report

Table 25: Environmental Monitoring Plan for Water Supply Rehabilitation

Mitigation Measures Pa rame ters Location Measurement Frequency Responsibili Preliminary to be ty Costing Monit ored Preconstru ct ion Stage All related design and Incorporation N/a. Verification of One-off IPMU IPMU staff Preconstruction stage of contract verification time mitigation measures. mitigation documents before as required The measures are to measures in signing the mitigate the the contract contract IPMU staff following (i) sludge documents N/a. IPMU time as related impacts (ii) Verification of One-off required construction Sludge plan inspection related impacts such management as dust plan nuisance

KUIDFC 66 Span & Voyants

NKUSIP (Package IV – Bellary) Tranche I Sub Projects in Raichur Town IEE Report

Dust At the Monitoring of air Weekly CMC Raichur Part of nuisance distribution quality is with construction network and not required. the costs transmission Ensure the assistance of main implementation of Investment replacement mitigation Program sites measures such Consultants as spraying of water; assess the situation through visual inspection and interviews with local people Construction Stage All construction related Incorporation Verification of mitigation measures of N/a Contract One-off IPMU N/a such as construction mitigation Documents inspection CMC Raichur Part of site management plan measures in at the water before signing of Contract with consultancy the contract to control the dust and laying sites the contract Document the assistance cost documents Monitoring of air noise nuisance, and and weekly of Investment Nuisance due surroundings quality and noise Program road block to generation is not required. Consultants implementation of of dust and Ensure the construction site noise and also implementation of management plan disturbance to mitigation measures (usage providing access traffic business during pipe of standard equipment lying, etc. (i) noise and dust nuisance at site (ii) complying with CPCB traffic maintenance, etc.

Operation stage

Check for blockage Effectiveness N/a Percentage of Yearly twice CMC Raichur Part of O & and of leak wa ter losses (once M leakage problems; detection and during costs reducing the water water normal losses auditing in season and reducing the once during losses lean season)

KUIDFC 67 Span & Voyants

NKUSIP (Package IV – Bellary) Tranche I Sub Projects in Raichur Town IEE Report

Implementation of the Health status N/a Health check for Yearly once CMC Raichur Part of O & Sludge of WTP WTP staff M cost Management Plan - staff involved Check for health in sludge hazards due to handling sludge handling.

Table 26: Environmental Monitoring Plan for Roads Up-gradation

Mitigation Measures Parameters Location Measurement Frequency Responsibili Preliminary to be ty Costing Monitored

Preconstru ct ion Stage. No significant impacts N/a. N/a. N/a. N/a. N/a. N/a. Envisaged. Construction Stage

Check for dust Incorporation N/a. Inspection of One-off IPMU IPMU staff nuisance of contract inspection time mitigation documents of before as required measures in signing the the contract contract do cuments

KUIDFC 68 Span & Voyants

NKUSIP (Package IV – Bellary) Tranche I Sub Projects in Raichur Town IEE Report

Dust and Work sites Monitoring of air Weekly CMC Raichur Part of noise of road quality wi th construction nuisance improvemen and noise is not the costs ts with in the required. Ensure assistance of town the Investment implementation of Program mitigation Consultants measures (usage of standard equipment complying to Noise levels of CPCB, spraying of water to arrest dust); assess the situation through visual inspection and interviews with local people

KUIDFC 69 Span & Voyants

NKUSIP (Package IV – Bellary) Tranche I Sub Projects in Raichur Town IEE Report

Chapter - VI

PUBLIC CONSULTATION AND INFORMATION DISCLOSURE

6.1 Overview

Project preparation exercise was carried out with couple of consultation meeting at every stage of project. Out comes of meeting in form of suggestion were considered and took in account in project preparation. Member presented in consultation meeting are the Commissioner, AEE, AE CMC, Raichur town. Prime importance were given to the project affected people meeting were conducted with Councillors, NGOs, local public, project affected persons at various stages of project such as project level, sub project level and component level .

During public participation, the consultant were briefed about the advantages of executing infrastructure facilities such as water system, sewerage system, storm water drainage system, slum improvement scheme, etc. and also touched the issues in the existing infrastructure facilities and need of the proposed projects. It is observed that in group discussion which involved in public consultation that people are in favour of project and willing to extend there support and co operation. People were seen in confident with project and aware about positive impacts in term of enhancing living standard and creation of aesthetic and safe environment condition.

Public had raised following points related to impacts which will be anticipated during construction and operation. The proposed mitigation measures have also been discussed in Table – 33.

Public consultation at Eklaspur STP site Public Consultation near Rampur Intake, Raichur.

KUIDFC 70 Span & Voyants

NKUSIP (Package IV – Bellary) Tranche I Sub Projects in Raichur Town IEE Report

Table 27 Public Comments & Mitigation measures SI No. Comments from local public Proposed mitigation (A) Pipe line works  Deep excavation leads to the collapsing of telecommunication services, water lines etc.

 Suggested appropriate safety aspect in a proper place during construction activity.  Highly Qualified contractor will be engaged to execute the work in proper way and specific conditions shall be imposed in the contract to take  Suggested deploying team as a part of safety safety measures. measure to take care of an emergency situation.

 Dust generation shall be arrested by water  Ensure minimum impact on environment spraying wherever required. during construction and operation activities .  Ensure usage of standard equipment to reduce the noise nuisance. Equipment shall comply with the noise levels of construction equipment laid out by the CPCB. High noise generating activities including material unloading shall be avoided during nights. The surrounding people shall be informed, especially in densely populated area, of nature and schedule of the high noise generating activities, if any.

 Adequate arrangements for traffic diversions including erection of proper sign boards.

 Barricading with red mark shall be fixed wherever deep excavation so that the public will not fall during day time as well as in night time. (B) Sewage Treatment Plant (STP) & Pumping Station (PS)  Bad smell due to sludge handling & spillage of  A buffer zone in the form of landscaping sewage. shall be created around the STP/PS to avoid odour nuisance.

 Ground water contamination & nearby surface  Since, the sewage Treatment plant (STP) / water contamination. Pumping station (PS) are constructed with water tight Reinforced cement concrete structure including epoxy painting inside the water tank, the seepage / leakage of sewage or treated water will not be there.

 Noise nuisance due to operation of STP/PS.  Ensure usage of standard equipment to

KUIDFC 71 Span & Voyants

NKUSIP (Package IV – Bellary) Tranche I Sub Projects in Raichur Town IEE Report

reduce the noise nuisance. Equipment shall comply with the noise levels of construction equipment laid out by the CPCB. High nois e generating activities including material unloading shall be avoided during nights. The surrounding people shall be informed, especially in densely populated area, of nature and schedule of the high noise generating activities, if any.

 Apart from this, it will be ensured to minimize the environmental impacts due to construction of STP/PS by following proper methods/ mitigation measures.

KUIDFC 72 Span & Voyants

NKUSIP (Package IV – Bellary) Tranche I Sub Projects in Raichur Town IEE Report

Chapter - VII FINDING AND RECOMMENDATION

7.1 Findings

Based on the screening of environmental impacts, all the proposed sub-project components in Raichur are found to be environmentally acceptable and therefore able to proceed to the implementation phase. In most cases, particular environmental issues identified are those that are typical for the type of component, and a range of proven mitigation strategies exist to address them. Table 27 indicates the environmental consideration of the proposed infrastructure components.

Table 27: Environmental Issues of Infrastructure Components Inf rast ructure Environmental Impact Issue Envir onment al Compon ent Mit igat ions Sewage treatment Appropriate mitigatio n measures plant and sewera g• Air dispersion modelling for odour as suggested up gradation • Construction and operation impacts Solid waste • No significant issues N/a. mana gement Water Supply • Sludge handling and disposal Appropriate mitigatio n measures Rehabilitat ion • Construction and operation imp acts as suggested Upgradation of r o• Disturbance to hawkers and vendors Appropriate mitigatio n measures and traffic system • Construction and operation impacts as suggested

As described above, most impacts are relevant to typical construction and operation. The important sets of mitigation measures, which are relevant to most of the components, include preparation of activity plans using appropriate mitigation measures identified in the earlier sections. These activity plans include:

• Sludge Management and Disposal Plan (to address sludge handling and disposal impacts at the STP) • Health Risk Plan (to address the health related impacts of the STP workers and sanitary workers)

These activity plans should be prepared by the Investment Program Consultants as a compendium of the relevant mitigation measures identified in earlier section. They should form part of the contractual arrangements with construction contractors, or directly implemented by the CMC as facility operator, as required ‘Work Practices’.

KUIDFC 73 Span & Voyants

NKUSIP (Package IV – Bellary) Tranche I Sub Projects in Raichur Town IEE Report

7.2 Recommendations

It is recommended that the IPMU should be involved in monitoring the implementation of those components that are critical to acceptable environmental performance of the component. Owing to the location of proposed facilities and geographical setting of the town/region as a whole, no major impacts envisaged from any of the proposed sub- components projects in Raichur. Most of the impacts could be mitigated with sound design and therefore the design stage becomes crucial. In view of this importance, the PMU is delegated with the monitoring responsibility of the design stage to ensure the environmental sustainability of the NKUSIP.

KUIDFC 74 Span & Voyants

NKUSIP (Package IV – Bellary) Tranche I Sub Projects in Raichur Town IEE Report

Chapter VIII

CONCLUSIONS

The proposed components should proceed through to design and implementation, subject to mitigation measures and monitoring programs identified in the IEE which will be updated detailed during detailed design stage. Owning to the nature and scale of the proposed components in Raichur it may be emphasized that the present IEE, which identifies potential impacts and suggests appropriate mitigation measures, is sufficient enough to safeguard the environment. There are no significant adverse impacts, which are irreversible or may lead to considerable loss/destruction of environment, envisaged. All the impacts are simple and moreover proven mitigation measures exists to minimize/mitigate the same. Hence, no further study such as an EIA is required.

KUIDFC 75 Span & Voyants

NKUSIP (Package IV – Bellary) Tranche I Sub Projects in Raichur Town IEE Report

APENDIX 1: Rapid Environmental Assessment (REA) Checklist SEWAGE TREATMENT Country / project Title : India / North Karnataka Urban Sector Investment Program Sector Division Urban Development ……………………………………………………………………………………………… Screening Questions Yes No Remarks B. Project Siting

Is the project area Densely populated √ Heavy with development √ activities Adjacent to or within any e nvironmentally sensitive area Cultural heritage site √ Protected area √ Wetland √ Mangrove √ Estuarine √ Buffer zone of protected area √ Special area for protecting √ biodiversity Bay √ Potential Environmental ` ImpactWill the project cause….. Impairment of historical / cultural monuments / √ areas and loss/ damage to the sites? During construction stage traffic and human Interference with other utilities activities may affected temporarily due to and blockage of access to generation of dust and noise from mechanical buildings nuisance to equipments. Adequate measure will be taken by √ neighboring areas due to skirling of water to minimize dust and traffic noise, smell and influx of management plan with sign board. Machinery insects rodents etc? with standard reputed make adopted that will itself taker care of noise. Dislocation or involuntary No any dislocation or involuntary √ resettlement of people? resettlement envisaged in a project.

KUIDFC 76 Span & Voyants

NKUSIP (Package IV – Bellary) Tranche I Sub Projects in Raichur Town IEE Report

The proposed activated sludge process system

is designed to meet the discharge norms of Impairment of downstream inland surface water as suggested by Central water quality due to in a √ Pollution Control Board. It is suggested that dequate sewage treatment proposed system will be properly maintained or release of untreated sewage? to ensure efficiency of treatment. Overflows and flooding Periodic maintenance of sewer lines has of neighboring properties √ been suggested in the EMP to avoid overflowing with raw sewage. ? and flooding of neighbouring properties. Environmental pollution due Sludge disposal will be carried out in frequently to inadequate sludge disposal say once in a 2 to 3 years. Sludge disposal √ or industrial waste discharge will be restricted in a confined space to avoid illegally disposed in sewer.? surface and soil pollution. Construction machineries used in a Noise and vibration due to construction will be standard reputed √ blasting and other civil works? made comply with noise level standard prescribed by pollution control board. Discharge of hazardous material It is suggested in EMP that Raichur CMC into sewers, resulting in damage √ has to ensure that no hazardous waste will be to sewer system and danger to illegally discharged in to sewer lines. workers ? Inadequate buffer zone around Buffer zone with screen and landscaping pumping and treatment plats to is suggested to provide proper shielding alleviate noise and other √ such that operation of STP will not have possible nuisances, and nuisance to surrounding. protect facilities? The local labour force will be utilized by Social conflicts between the contractor for construction activities construction workers from √ and hence there are no possibilities for other areas and community social conflict regarding employment workers? opportunities during construction phase. Road blocking and traffic re routing has been envisaged during construction stage of Road blocking and temporary sewer lines. Temporary flooding is not flooding due to land excavation √ anticipated as there is no deep excavation during the rainy season? or filling of low laying area envisaged in the project. Construction machineries will be reputed make Noise and dust construction √ which will itself take care of noise moreover activities? these machineries will be comply with standards

KUIDFC 77 Span & Voyants

NKUSIP (Package IV – Bellary) Tranche I Sub Projects in Raichur Town IEE Report

stipulated by Central pollution Control board. Water sprinkling program will be suggested to ensure minimize of dust generated. Traffic management with re routine of Traffic disturbances due to traffic during construction period is construction material √ required to avoid conflict of public transport and waste? transport with construction material. The construction waste water will be Temporary silt runoff due to channelled such that it will have sufficient √ construction? time to settle the solid and do not deteriorate water quality of discharging courses. Hazards to public health due to √ Regular maintenance of sewer line has been overflow flooding and ground suggested to avoid overflow of sewer line water pollution due to failure and related impact on public health due of sewage system? to pollution. Chances of failure sewage system will be less and in extreme case care will be taken by diverting sewage in nearby nalas and rectified defects quickly to take system in working. Deterioration of water quality √ Sludge from sludge drying bed will be removed due to inadequate sludge at regular interval to avoid re – suspension in t disposal or direct discharge he treated water and there by deteriorating treated of untreated sewage water? water quality. Direct discharge of untreated sewage water is not anticipated. Contamination of surface √ Sludge will be disposed of in a confined area and ground water due t the sludge disposal area will should be properly o sludge disposal on land? lined with geosynthetic lining such that it will no t leach to the nearby water courses / and and pollute environment. Health and safety hazards to √ Mixing of hazardous / industrial effluent with workers from toxic gases a sewage may result in sewer and STP which nd hazardous material which should may be contained in sewage be avoided through proper law and enforcement. flow and exposures to The sewer cleaning and STP workers should be pathogens in sewage and provided protective measures such as boots sludge? masks etc. to avoid exposure to pathogens in sewage and sludge.

KUIDFC 78 Span & Voyants

NKUSIP (Package IV – Bellary) Tranche I Sub Projects in Raichur Town IEE Report

Country / project Title : India / North Karnataka Urban Sector Investment Program. Sector Division Urban Development ……………………………………………………………………………………………… Screening Questions Yes No Remarks B. Project Siting Is the project area Densely populated √ Heavy with development √ activities Adjacent to or within any environmentally sensitive area Cultural heritage site √ Protected area √ Wetland √ Mangrove √ Estuarine √ Buffer zone of protected area √ Special area for protecting √ biodiversity Bay √ Potential Environmental Impact ` Will the project cause….. Pollution of raw water supply √ No such communities, industries from discharge envisage near the upstream waste water intake point. discharge from communities, industries, agriculture and soil erosion runoff. Impairment of historical / √ cultural monuments / areas and loss / damage to the site Hazard of land subsidence √ There is no ground water caused exploitation for proposed water by excessive ground water supply improvements for pumping Raichur CMC Social conflict arising from √ displacement of communities

KUIDFC 79 Span & Voyants

NKUSIP (Package IV – Bellary) Tranche I Sub Projects in Raichur Town IEE Report

Conflicts in abstraction of raw √ Since the water is drawing water for water supply with from tungabathra sub canals, other beneficial water uses for there will not be any water scarcity surface and ground waters? at any point of time. Unsatisfactory raw water √ The existing raw water supply sup[ply ( is supposed to continue. e.g. excessive pathogens or mineral constituents ? Delivery of unsafe water to √ distribution system Inadequate protection of intake √ The exiting intake well along works or wells leading to the down stream canal of pollution of water supply? tungabadra is in good condition, so there is no possibility of pollution due to inadequate protection of intake works or wells. Over pumping of ground water, √ There is no ground water l exploitation required for the eading to Stalinization and proposed improvements in ground subsidence? water supply. Excessive algal growth in √ Raichur CMC has to ensure storage reservoir? that the storage reservoir will be cleaned regularly to avoid excessive algal growth. Increase in production of √ The proposal involves ensuring sewage beyond capabilities of regular supply of 100 lpcd for community facilities? the public which neither will nor result in excess sewage production. The proposed STP for the city is designed to meet the sewage generated with 100 lpcd. Inadequate disposal of sludge √ There is no such proposal of from water treatment plants? altering design and facilities in water treatment plant. It is prime duty of Raichur CMC to ensure that the sludge is removed from water treatment plants regularly to meet standard of treated water. Inadequate buffer zone around √ Sufficient buffer zone / noise pumping barrier is to be developed around

KUIDFC 80 Span & Voyants

NKUSIP (Package IV – Bellary) Tranche I Sub Projects in Raichur Town IEE Report

and treatment plants to alleviate pumping station to alleviate noise. noise and other possible nuisance and protect facilities Impairments associated with √ Temporary impairments are transmission lines and access anticipated along the new roads? transmission lines routes during construction stage . no new access are proposed. Health Hazard arising from √ Proposed project seen to be inadequate design of facilitate not have any proposal for for receiving , storing, and altering design / facilities handling of chlorine and in water treatment plant. other hazardous chemicals Health and safety hazards √ Raichur CMC has to ensure t to workers from the hat proper safety practices management are ensured for workers in of chlorine used for disinfection water treatment plant. and other contaminants? Dislocation or involuntary √ There is no resettlement resettlement of people of people for project implementation. Social conflict between √ Local labour will be utilized construction in maximum number by contractor workers from other areas so possibility of social conflict and community workers? regarding employment opportunities will be less during construction stage Noise and dust from √ Measures will be taken in initial construction activities stage of project by deploying standard reputed make machinery with comply of stipulated noise standard to ensure noise with in limit and practice of frequent water spraying will be adopted to minimize dust. Increased road traffic due to √ The construction material transport interference of construction will increase traffic within city. activities? Proper traffic management will have to be implemented to avoid

KUIDFC 81 Span & Voyants

NKUSIP (Package IV – Bellary) Tranche I Sub Projects in Raichur Town IEE Report

conflict between public transport and construction material transport. Continuing soil erosion / silt √ Construction debris and excess runoff soil generated at construction from construction operation site should be properly disposed to avoid erosion. Delivery of unsafe water due to √ Hospet CMC has to ensure efficiency poor o & m treatment process of operation of water treatment plant. ( especially mud accumulation in filter ) and inadequate chlorination due to lack of adequate monitoring of chlorine residual in distribution system Accidental leakage of chlorine √ gas? Excess abstraction of water √ affecting downstream water users Competing uses of water √ Increased sewage flow due to √ The proposal is for ensuring increased water supply regular water supply of 100 lpcd for the public which will result in increased sewage generation. The propose STP for the city is designed too meet the sewage generated with 100 lpcd. Increased volume of sullage √ The proposed STP for the city is ( wastewater from cooking and designed to meet the sullage washing ) and sludge from generated due to project. Raichur waste CMC has to ensure that the sludge water treatment plant generated in STP is disposed off with safe disposal practices.

KUIDFC 82 Span & Voyants