Planning and Advanced Reservation of Capacity Agreement (PARCA)
NOTICE: PARCA APPLICATION - RESERVATION OF NTS EXIT CAPACITY
UPDATE – 25 March 2020
Dear Industry Colleague,
In accordance with Uniform Network Code, Section B, National Grid hereby publishes this notice to all interested parties.
On 26th May 2017, we issued a notice with respect to the receipt of a competent Planning & Advanced Reservation of Capacity Agreement (“PARCA”) application. The PARCA application was for a National Transmission System (“NTS”) exit capacity central requirement of 32,000,000kWh/d rising to 102,300,000kWh/d in North East Yorkshire and Lincolnshire (Region 3 as defined in Gas Ten Year Statement1). The indicative capacity Registration Date specified at the time was between 1st October 2020 and 1st October 2022.
On 30th November 2017we issued an informal notice (‘Eggborough Power Station ExCS Informal Notice (including Exit Substitution & Baseline Revision’) which outlined our proposals to meet the upper tolerance of the capacity requirement, 33,600,000kWh/d rising to 106,494,000kWh/d, with an indicative capacity Registration Date between 1st October, 2020 and 1st October, 2022.
On, 4th January, 2018, we issued a notice to confirm the PARCA application had progressed to Phase 2, and NTS exit capacity had been reserved.
We are issuing this notice to advise that the Reservation Dates have been revised following a request from the Reservation Party, and are now as follows
From 1st October 2024
Capacity Capacity Recipient NTS Point Donor NTS Points Donated Received (kWh/d) (kWh/d)
Pannal 28,230,041 28,330,000 Eggborough Power Station Burley Bank 5,296,185 5,270,000
1 https://www.nationalgrid.com/uk/publications/gas-ten-year-statement-gtys
Page 1 of 3 From 1st January 2025 Capacity Capacity Recipient NTS Point Donor NTS Points Donated Received (kWh/d) (kWh/d)
Pannal 28,230,041 28,330,000
Burley Bank 6,441,849 6,410,000
Asselby 1,000,269 1,010,000
Baldersby 213,358 210,000
Eggborough Power Station Towton 21,165,329 21,080,000
Ganstead 6,539,670 6,000,000
Goole Glass 1,620,000 1,900,000
Pickering 1,047,290 950,000
Blyborough (Brigg) Power Station 2,007,004 1,310,000
From 1st April 2025
Capacity Capacity Recipient NTS Point Donor NTS Points Donated Received (kWh/d) (kWh/d)
Pannal 28,230,041 28,330,000
Burley Bank 6,441,849 6,410,000
Asselby 1,000,269 1,010,000
Baldersby 213,358 210,000
Towton 21,165,329 21,080,000 Eggborough Power Station Ganstead 6,539,670 6,000,000
Goole Glass 1,620,000 1,900,000
Pickering 1,047,290 950,000
Blyborough (Brigg) Power Station 15,290,000 9,980,000
Eastoft Keadby Power Station 30,947,111 24,090,000
Page 2 of 3 From 1st October 2026
Capacity Capacity Recipient NTS Point Donor NTS Points Donated Received (kWh/d) (kWh/d)
Pannal 28,230,041 28,330,000
Burley Bank 6,441,849 6,410,000
Asselby 1,000,269 1,010,000
Baldersby 213,358 210,000
Towton 21,165,329 21,080,000
Eggborough Power Station Ganstead 6,539,670 6,000,000
Goole Glass 1,620,000 1,900,000
Pickering 1,047,290 950,000
Blyborough (Brigg) Power Station 15,290,000 9,980,000
Eastoft Keadby Power Station 36,060,000 28,070,000
West Burton Power Station 3,804,474 2,554,300
PARCA related notices and the PARCA Customer Guidance document can be found at:
https://www.nationalgridgas.com/connections/reserving-capacity-parca-and-cam
Should you wish to discuss the contents of this notice further please contact me as per below.
Kind regards,
Richard Hounslea, Gas Connections Contracts Manager, National Grid Gas Transmission