OPERATIONAL UPDATES A. Fire Prevention B. Number of Establishment Inspected and Compliance Status C. Fire Suppression D. Fire Investigation E. Emergency Medical/Dental and Rescue Services BUDGETARY UPDATES A. Status of Utilization of Funds for CY 2018 PLANS AND PROGRAMS “We Save Lives and A. Action Plan 2018 VII . ISSUES AND CONCERN Properties” •Provincial Profile Area Profile NO OF NO. OF NO. OF NO. OF LAND AREA NO. OF ESTABLISMENTS PROVINCE POPULATION CITIES MUNICIPALITIES BARANGAYS (km2) HOUSEHOLDS (as per BPLO 2019)

QUIRINO 0 6 132 188,991 2,323.47 30,581 3,934

List of Municipalities with Firefighting Capability QUIRINO Aglipay •Jurisdictional Map Quirino (Ilokano: Probinsia ti Quirino) is a landlocked province in the located in the Valley region in Luzon and named after Elpidio Quirino, the sixth President of the Philippines. Its capital is Cabarroguis. The province borders to the southeast, to the west, and to the north. Quirino used to be part of the province of Nueva Vizcaya, until it was separated in 1966. Long before its formal creation as an independent province, Quirino was the forest region of the province of Nueva Vizcaya, inhabited by tribal groups known as the Negritos. They roamed the hinterlands and built their huts at the heart of the jungle. On June 18, 1966, Republic Act 4734 was enacted, constituting the municipalities of Diffun, Saguday, Aglipay, and Maddela (all of Nueva Vizcaya province) into a new sub-province to be known as "Quirino", named after the late Philippine president Elpidio Quirino. On June 21, 1969, Republic Act 5554 was enacted, amending RA 4734 and creating the municipality of Cabarroguis (now the provincial capital town), which was taken from portions of Diffun, Saguday, and Aglipay. Republic Act 6394, authored by then Congressman Leonardo B. Perez, was passed on September 10, 1971 further amending RA 5554 and separating the sub-province of Quirino from its mother province, Nueva Vizcaya, constituting it into a regular province. The province of Quirino was formally established on February 10, 1972 upon the assumption to office of the first elected provincial and municipal officials headed by Dionisio A. Sarandi as Provincial An old map showing the current Governor. territories of Quirino as part of Nueva On February 25, 1983, Batas Pambansa Blg. 345 was enacted, Vizcaya creating within Quirino the municipality of Nagtipunan, a division of the municipality of Maddela •ADMINISTRATIVE UPDATE

•Personnel Administration

TABLE A- 1A Personnel Strength

CITY/MUNICIPALIT OFFICER NON-OFFICER NUP TOTAL

Y SUPT CINSP SINSP INSP SFO4 SFO3 SFO2 SFO1 FO3 FO2 FO1

OPFM 1 1 6 4 2 3 12 29

AGLIPAY FS 1 2 3 4 4 14

CABARROGUIS FS 1 1 2 2 1 3 10 20

DIFFUN FS 1 4 3 5 4 17

MADDELA FS 1 1 1 5 8 16

NAGTIPUNAN FS 1 1 2 4 8

SAGUDAY FS 1 1 2 1 2 7 14

TOTAL 1 0 2 0 3 4 11 12 12 24 49 0 118 •ADMINISTRATIVE UPDATE

TABLE A- 1b Personnel Rank Profile CITY/MUNICIPA OFFICER NON-OFFICER NU TOTA LITY SUPT CINSP SINSP INSP SFO4 SFO3 SFO2 SFO1 FO3 FO2 FO1 P L

OPFM 1 1 6 4 2 3 12 29

AGLIPAY FS 1 2 3 4 4 14

CABARROGUIS FS 1 1 2 2 1 3 10 20

DIFFUN FS 1 4 3 5 4 17

MADDELA FS 1 1 1 5 8 16

NAGTIPUNAN FS 1 1 2 4 8

SAGUDAY FS 1 1 2 1 2 7 14

TOTAL 1 0 2 3 4 11 12 12 24 49 118 LOGISTICAL UPDATE

OPERATIONAL CAPABILITIES FIRETRUCK AMBULANCE CHAINSAW GENERATOR SET SCBA 1 (unserviceable subject OPFM 1 1 for major repair) 1 1 (unserviceable subject AGLIPAY 1 for major repair) 1 1 1 (unserviceable subject CABARROGUIS 3 for major repair) 1 4 1 (unserviceable subject DIFFUN 2 for major repair) 1 3 1 (unserviceable subject MADDELA 2 for major repair) 1 3 1(unserviceable subject 1 (unserviceable subject NAGTIPUNAN for major repair for major repair) 1 2 1 (unserviceable subject SAGUDAY 1 for major repair) 1 2 BFP Provincial Office

PROGRESS OF AMOUNT OF DATE OF REGION II DATE AWARDED BUDGET CONSTRUCTION (% of REMARKS CONTRACT COMPLETION Accomplishment)

November 21, Under OPFM QUIRINO 7,320,968.20 7,300,012.58 60% May 19, 2020 BUILDING 2019 construction OPERATIONAL UPDATE

FIRE PREVENTION

FIRE SAFETY INSPECTION CONDUCTED PER TYPE OF ESTABLISHMENT as of June 2020 Mixed TOTAL Storage Day Care Business Industrial Assembly Mercantile Residential Health Care Health Educational Municipality Special Structures Special Residential Board Board & Residential Care Detention and Correctional

AGLIPAY 7 2 0 1 0 0 1 523 45 68 14 0 2 663

CABARROGUIS 3 10 0 0 0 0 11 420 185 63 0 0 0 692 DIFFUN 0 2 0 1 0 0 18 719 179 30 40 0 0 989 MADDELA 6 4 0 4 0 0 1 685 122 92 3 0 8 925 NAGTIPUNAN 0 0 0 0 0 0 20 134 21 54 0 0 0 229 SAGUDAY 2 2 0 0 0 0 0 164 29 15 5 0 0 217 TOTAL 18 20 0 6 0 0 51 2645 581 322 62 0 10 3715 OPERATIONAL UPDATE

FIRE PREVENTION

FIRE PREVENTION ACTIVITIES As of June 2020 issued Issued Closure FSIC for stoppage of of stoppage Municipality Permit IssuedPermit Building Plans FSIC issued for Operate Issued Operate Operations and Operations and issued FSEC and issued Notice Correctto Violations Issued Notice Complyto Abatement Order Abatement AMOUNTFIRE OF Recommended for FSIC for Occupancy Occupancy for FSIC Business/Permit to FSIC issued for PEZA Reviewed, Processed Reviewed, CODE FEES ASSESSED FEES CODE Government Buildings Total No. of FSIC Issued FSIC of No. Total Aglipay 8 0 80 0 0 88 0 0 0 0 492,630.75 Cabarroguis 10 6 143 0 0 159 0 0 0 0 570,769.00 Diffun 24 0 157 0 0 181 0 0 0 0 718,447.00 Maddela 5 1 209 0 0 215 0 0 0 0 652,651.00 Nagtipunan 1 0 55 0 0 56 0 0 0 0 129,276.00 Saguday 17 0 15 0 0 32 0 0 0 0 163,833.00 TOTAL 65 7 659 0 0 731 0 0 0 0 2727606.75 OPERATIONAL UPDATE

FIRE PREVENTION

NUMBER OF ESTABLISHMENT INSPECTED PER MUNICIPALITY

as of Jan-Mar 2020 as of Apr-Jun 2020 Quarter MUNICIPALITY Variance Quarter (previous) (current)

Aglipay 642 21 -97%

Cabarroguis 640 52 -92% Diffun 948 41 -96% Maddela 888 37 -96%

Nagtipunan 222 7 -97% Saguday 205 12 -94% Total 3545 170 -571% OPERATIONAL UPDATE

FIRE PREVENTION

NUMBER OF ESTABLISHMENT INSPECTED PER MUNICIPALITY

as of Jul - Dec as of Jan-June 2020 MUNICIPALITY 2019 Semester Variance Semester (current) (previous)

Aglipay 91 663 629%

Cabarroguis 98 692 606% Diffun 101 989 879%

Maddela 97 925 854%

Nagtipunan 61 229 275%

Saguday 19 217 1042% Total 467 3715 4285% OPERATIONAL UPDATE

FIRE PREVENTION

NUMBER OF ESTABLISHMENT INSPECTED PER MUNICIPALITY

as of Jan - Jun as of Jan-June 2020 MUNICIPALITY 2019 (previous Variance (current year) year)

Aglipay 618 663 7% Cabarroguis 664 692 4% Diffun 941 989 5% Maddela 915 925 1% Nagtipunan 326 229 -30% Saguday 227 217 -4% Total 3691 3715 -16% OPERATIONAL UPDATE

FIRE PREVENTION

FIRE CODE FEES COLLECTED PER MUNICIPALITY as of 2nd Quarter

as of Jan-Mar 2020 1st as of Apr-Jun 2020 2nd MUNICIPALITY Variance Quarter (previous) Quarter (current)

Aglipay 470,936.75 21,694.00 -95% Cabarroguis 519,391.00 51,378.00 -90% Diffun 671,505.00 46,942.00 -93% Maddela 565,316.00 87,335.00 -85% Nagtipunan 121,702.00 7,574.00 -94% Saguday 138,397.00 25,436.00 -82% Total 2,487,247.75 240,359.00 -538% OPERATIONAL UPDATE

FIRE PREVENTION

FIRE CODE FEES COLLECTED PER MUNICIPALITY as of 1st Semester 2020

as of Jul - Dec 2019 as of Jan-June 2020 1st MUNICIPALITY 2nd Semester Variance Semester (current) (previous)

Aglipay 39,714.00 492,630.75 1140% Cabarroguis 112,933.00 570,769.00 405% Diffun 121,991.00 718,447.00 489% Maddela 87,342.00 652,651.00 647% Nagtipunan 10,292.00 129,276.00 1156% Saguday 23,247.00 163,833.00 605% Total 395,519.00 2,727,606.75 4443% OPERATIONAL UPDATE

FIRE PREVENTION

FIRE CODE FEES COLLECTED PER MUNICIPALITY as of June 2020

as of Jan - Jun 2019 as of Jan-June 2020 MUNICIPALITY Variance (previous year) (current year)

Aglipay 118,401.00 492,630.75 316%

Cabarroguis 282,621.00 570,769.00 102%

Diffun 406,546.00 718,447.00 77%

Maddela 322,317.00 652,651.00 102%

Nagtipunan 35,412.00 129,276.00 265%

Saguday 101,311.00 163,833.00 62%

Total 1,266,608.00 2,727,606.75 924% OPERATIONAL UPDATE FIRE SUPPRESSION Covering Covering KINDS OCCUPANCY period (Jan- period (Jan- VARIANCE Jun 2019) Jun 2020) Residential 5 5 0% Industrial/Factory 1 100% Commercial/Mercantile 1 1 0% Storage Mixed

Business/Gov't Offices

Educational 1 100% Institutional STRUCTURAL FIRE Place of Assembly 1 100% Miscellaneous TOTAL 6 9 50%

Grass, Rubbish and Forest Fire 1 1 0%

Motor Vehicle Ship/Water Vessel FIRE Aircraft Locomotive NON STRUCTURAL TOTAL 1 1 0%

AMOUNT OF DAMAGE BASED ON SUBMITTED AFFIDAVIT OF LOSS 3,274,500 3,517,561 7% OPERATIONAL UPDATE FIRE INVESTIGATION FIRE INVESTIGATION COMPARATIVE REPORT Covering Covering DESCRIPTION period (Jan- period (Jan- VARIANCE Jun 2019) Jun 2020) Electrical connection 1 2 100% Electrical appliances 1 -100% Electrical machinery 1 100% Spontaneous combustion 1 100% Unattended cooking/stove 1 4 300% Open flame due to 1 -100% torch/gasera LPG Explosion Lighted cigarette butt Chemicals

CAUSES OF FIRE Pyrotechniques Lighted match stick/lighter Incendiary devices/flammable liquid Lightning Bomb explosion Undetermined 2 1 -100% Others 1 1 0% TOTAL 7 10 300% Intentional 1 100% Accidental fire 6 9 300% Undetermined Fire cases under investigation 1 -100% ON OF FIRE

CLASSIFICATI TOTAL 7 10 300% Fatalities in fire fighter Fatalities in fire civilian Injuries in fire fighter Injuries in fire civilian

CASUALTIES TOTAL OPERATIONAL UPDATE EMERGENCY MEDICAL SERVICES AND RESCUE SERVICES EMS/RESCUE COMPARATIVE REPORT Covering Covering period (Jan- period (Jan- VARIANC ACTIVITIES Jun 2019) Jun 2020) E

FIRE INCIDENTS 7 10 300%

EMERGENCY RESPONSE RESCUE OPERATIONAL/DESASTERS VEHICULAR ACCIDENTS

MEDICAL CASES

TOTAL 7 10 300%

FREE MEDICAL AND DENTAL SERVICES

TT VACCINATION

BLOOD LETTING

CONSULATION NON EMERGENCY RESPONSE BP MONITORING

DRILL CONDUCTED 89 51 -43%

OTHERS

TOTAL 89 51 -43% BUDGETARY UPDATES

STATUS OF UTILIZATION OF FUND (CY 2020) Table VA-1 Status of Utilization of Fund

ACCOUNT EXPENDITURES ALLOTMENT UTILIZATION BALANCE CODE

Travel Expenses 751 50201010 00 70,000.00 70,000.00 0

Office Supplies Expenses 755 50203010 02 135,000.00 135,000.00 0

Gasoline, Oil & Lubricants Expenses 761 50203090 00 352,645.41 352,645.41 0

TOTAL 557,645.41 557,645.41 0 BFP QUIRINO PROVINCE OTHER ACTIVITIES BFP QUIRINO PROVINCE BAYANIHAN We Heal as One Relief Distribution (First Wave) headed by SUPT ROYGBIV L RUGAYAN, BFP Provincial Fire Marshal @ Purok 7 Brgy. San Marcos, Cabarroguis, Quirino May 12, 2020 and Four personnel of PNREO Quirino in-charge in the collection of segregated waste @BFP Provincial Office San Marcos Cabarroguis, Quirino May 20, 2020

BFP QUIRINO PROVINCE BAYANIHAN We Heal as One Relief Distribution (Second Wave) Brgy, Dissimungal, Nagtipunan, Quirino June 15, 2020

BFP-Quirino headed by SUPT ROYGBIV L RUGAYAN, aims to at least be a part of the edifice in extending hand to our less fortunate constituents during this COVID-19 Pandemic. Personnel of this province agreed to share a portion of their hearts, thus the 2nd wave of this project was made possible. Together with all MFM's and selected personnel of this province, said personnel proceeded at the barangays inhabited by Agtas located at the municipality of Nagtipunan. This outreach program aims to at least alleviate our fellow Indigenous People constituents in their plight amidst this crisis and in support with the "Adopt a family" program of the Bureau of Fire Protection.

BFP QUIRINO PROVINCE BAYANIHAN We Heal as One Relief Distribution (Third Wave) Relief Goods Distribution Brgy, Aurora West and Brgy. Rizal, Diffun, Quirino July 8, 2020 Brgy. Aurora West, Diffun, Quirino Brgy. Rizal, Diffun, Quirino BUREAU OF FIRE PROTECTION QUIRINO PROVINCE

Program Review and Analysis January – June 2020

“We Save Lives and ROYGBIV L RUGAYAN SUPT BFP Properties” Provincial Fire Marshal