State/UT wise details of Flood Management Project Proposals ( coordinated by CWC) during XII Plan inculding spillovers as on 21.03.2016

Sl Estt. Cost Date of Under Name of works/scheme Status of examination Cleared Returned Awaited No. (Rs. In Cr) Receipt examination 1 Assam 1 R/S to Puthimari Embankment on B/B 35.8377 11.12.2012 FMP Dte examined the DPR and Comments were 35.8377 from R. A. Railway line to Boromboi furnished to State Government of Assam vide letter dated 25.02.2013. Hyd (NE) also furnished comments vide letter dated 28.11.2013 and the same have been forwarded to State Governmment vide letter dated 03.12.2013.Reply awaited. Reminded on 25.02.2016

2 M/E along both bank of Pohumra from 34.2844 02.01.2013 The scheme was examined and comments of FMP Dte. 34.2844 Kathalmurighat to Railway Line (R/S and 18.02.2014 were sent to State Government vide letter dated A/E measures at different reaches of both 10.04.2013. State Government submitted Revised DPR bank embankment) vide letter dated 11.02.2014. The revised DPR was examined and further comments were sent to State Government on 17.06.2014. Reply awaited.

3 Raising and Strengthening old existing 28.5000 07.01.2013 The DPR was examined and comments were 28.5 embankment with anti-erosion measures on communicated vide letter dated 04.04.2014. Compliance left bank of river Saral Bhanga from from State Government received on 24.07.2014. Revised Patgaon to Khalashi DPR was examined, the cost finalised and TAC Note prepared and submitted to AC-MOWR on 03.02.2015. AC-MOWR considerd it during its 125th meeting held on 25.05.15. Advisory commitee requested State Govt. to submit unconditional SFC and deferred the proposal to next meeting. AC-MoWR,RD&GR in its 126thmeeting on 16th july,2015 decided that this project may be taken as'deemed returned' with the proviso that State Govt may resubmit the Project proposal afresh with updated cost of techno-economic appraisal.

4 Flood Management works to protect Silchar 53.2812 14.01.2013 The scheme was examined and comments of FMP Dte. 53.2812 Town from the erosion of river Barak at were sent to State Government of Assam vide letter dated Angerjur, Bethukandi and Manikpur area 15.04.2013.comments of Hyd (NE) received vide letter dated 08.01.14. Reply awaited. Reminded on 25.02.2016 5 Protection of Bahari, Phulbari, Bhogerpar, 80.0927 24.01.2013 FMP Dte examined the DPR and comments were 80.0297 Pazarbhanga and its adjoining area from the communicated to WRD Assam vide letter dated 26.03.2014. erosion of river Brahmaputra Reply awaited. Reminded on 25.02.2016

6 Integrated approach for flood and erosion 156.63 26.02.2013 Hydrology (NE) Dte finalised design discharge 2034 156.63 control of river Puthimari under BTC area cumec for 50 year return period vide letter dated 4/10/2013. The comments of FMP Dte. were sent to the State Government vide letter dated 05/12/2013.Revised DPR received vide letter dated 10/09/2015.

7 Raising and Strengthening of Brahmaputra 124.86 08.03.2013 The comments of Hyd (NE) and FMP Dte. were sent to 124.86 dyke from Bahari to Baghbar including State Government vide letter dated 20.11.2013. The State closing of breaches at Pazarbhanga and Governement submitted the revised DPR with cost of Manikpur area along with Channelization of 124.86 Crore vide letter dated 01.06.2015. Revised DPR river Brahmaputra and reclamation of was sent to Hydrology (NE) dte for examination on eroded land within the reach 06.07.2015. Reply from Hyd(NE) received vide letter dated 01/10/2015.The same was sent to State Govt. along with other observations vide letter dated 30.10.2015. Reply awaited.

8 Protection of Borbeel, Muwamari and Goroimari 59.5574 15.03.2013 Comments of Hyd (NE) and FMP were communicated to WRD 59.5574 from erosion of river Brahmaputra(construction Assam vide letter dated 24.03.2014.Reminded on 04.03.2016. of Land Spur and Tie Bund) Reply awaited.

9 Integrated flood and river bak erosion 76.12 17.07.2013 Scheme has been cleared by AC-MOWR in its meeting held 76.12 management works at Rohmoria on 16.10.2014. 10 Construction of Brahmaputra byke and Anti- 320.7 15.03.2013 The comments of FMP Dte. were sent to State Government 320.7 erosion measures along left bank of river vide letter dated 28.11.2013. WRD Assam submitted a revised Brahmaputra from Dhing to Hilloikhunda DPR of Rs 306.70 crore vide letter dated 27.01.2014. The (Extension 0f embankment from Pabhakati to revised DPR was examined and comments were sent to WRD Kasosila Hill) Assam vide letter dated 26.05.2014. WRD Assam submitted revised DPR on 17.06.2014. Revised report submitted to BCD (E&NE) on 05.08.2014. BCD furnished comments on19.08.2014. WRD Assam submitted revised report on 27.02.2015. The same has been forwarded to BCD dte on 22.04.2015. BCD comments has been forwarded to State Govt. on 23.07.2015. Response from Hydrology (NE) received vide letter dated 23/11/2015.forwarded to State Govt vide letter dated 01.12.2015. Reply awaited.

11 Protection of Kolbari and Lality area from the 56.4956 25.03.2013 The comments of FMP Dte. have been submitted to State 56.4956 erosion of river Brahmaputra (Construction of Government vide letter dated 01.11.2013.WRD Assam three nos of spurs and a check dam) submitted revised DPR 20.11.2014. The DPR has been examined and forwarded to CA (HWF) for cost examination 07.05.2015. CA(HWF) examined the DPR and furnished comments vide letter dated 08.05.2015, the same were forwarded to Assam on 14.05.2015. compliance on cost estimate receved on 03.08.15. Cost estimate from Cost Appraisal sent to state govt on 12.08.15. Reminder was sent to State Govt on 03.11.15.Reply awaited.

12 Protection of Brahmaputra dyke at Amguri 53.36 03.06.2013 State government requested to submit the concurrence of state 53.36 Pichala area from the erosion of river finance department . DPR examined and TAC Note prepared Brahmaputra and Submitted to AC-MOWR 04.02.2015.AC-MoWR considered it during 125th meeting requested State Govt. Representative to submit SFC in Proper format and deferred proposal for next meeting. AC-MoWR,RD&GR in its meeting on 16th july,2015 decided that this project may be taken as'deemed returned' with the proviso that State Govt may resubmit the Project proposal afresh with updated cost of techno-economic appraisal. State/UT wise details of Flood Management Project Proposals ( coordinated by CWC) during XII Plan inculding spillovers as on 21.03.2016

Sl Estt. Cost Date of Under Name of works/scheme Status of examination Cleared Returned Awaited No. (Rs. In Cr) Receipt examination 13 Protection of village Domgaon, Dababeel, 128.42 03..06.2013 The scheme was examined by the FMP Dte and 128.42 Chotonilibari, Debargaon, Dangaigaon, comments were sent to State Government of Assam vide Birengaon, Bherbheri, Rowmari, letter 31.01.2014. Compliance received from state vide Khagrabari, Sanyashibari, Uttar-Popragaon letter dated 01.08.14. Scheme was further examined and and Popragaon from the erosion of river Aie comments conveyed on 02.01.2015. Compliance from State Govt was received and DPR Sent to Cost Appraisal Dte on 07.09.15. Reply from Cost Appraisal Directorate received vide letter dated 14.09.2015 which was forwarded to State Govt. vide letter dated 17/09/2015. The response from State Govt received vide letter dated 06/10/2015 which was sent to CA(HWF) vide letter dated 09/10/2015.CA(HWF) has finalized the cost of the scheme.

14 Construction of Embankment at North bank 338.52 25.03.2013 DPR was sent to Hyd (NE) vide letter dated 338.52 including fortification existing embankment 07/08/2013.Reply from Hyd(NE) was received vide letter system to provide flood protection to Majuli dated 27/08/2013 which was forwarded to State Govt island vide letter dated 17.09.2013.FMP has sought Comments from Brahmaputra Board vide letter dated 21.11.2013 . BB replied vide letter dated 24.12.2013.Further letter was sent to BB on 29.01.2014. BB replied vie letter dated 16.07.2014.COmments were sent to Hyd(NE) and State Govt vide letter dated 06.08.2014. Further comments were sent to State Govt vide letter dated 20.10.2014.The revised proposal was received on 06.01.2015 and same was submitted to Hyd(NE).Hyd (NE) made comments vide letter dated 10.06.2015 which was forwarded to state govt on 17.06.2015.Compliance submitted onvide letter dated 16.07.2015 .Revised DPR received vide letter dated 24.09.2015 which was forwarded to Hyd(NE) on 24.09.2015.Comments from Hydrology (NE) received vide letter dated 23/11/2015. Forwarded to State Govt vide letter dated 01.12.2015. Reply awaited.

15 Protection and R/S to Desang Bund on both 376.46 02.01.2013 Hyd (NE) examined the DPR and commnets were 376.46 banks from Desangpani to Dhai Ali on R/Bank communicated vide letter dated 02.04.2014 and the same were and Challapathar to Desangmukh on L/B at communicated to WRD Assam vide letter dated 05.06.2014. different reaches The same was reminded vide letter dated 12.12.2014.Reply awaited. 16 Assam Integrated Flood and River Bank 125.33 27.03.2015 Only one set of DPR received vide letter dated 16.03.15 125.33 Erosion Risk Management Project” which has been sent to Hyd (NE) 31.03.15 .Requested (Kaziranga Sub Project) State Govt. to submit two more sets of DPR on 31.03.15 . Additional sets of DPR received vide letter dated 15.06.2015. One set sent to BCD(E&NE) on 02.07.2015.Comments of BCD sent to state govt on 12.08.15.Comments of Hydrology(E&NE) received on 05/10/2015. State Govt was requested to process DPR through MOWR vide letter dated 24/09/2015. Comments of Hydrology(NE) send vide letter dated 12/10/2015. Reply awaited.

17 Assam Integrated Flood and River Bank 89.87 09.04.2015 DPR sent to Hyd (NE) on 10.04.2015. Received 89.87 Erosion Risk Management Project” , Trench- observations from Hyd (NE) vide letter dated 04.08.15. II(Dibrugarh sub Project) State Govt was requested to process DPR through MOWR vide letter dated 24/09/2015. Comments of Hydrology(NE) send vide letter dated 12/10/2015. Reply awaited. Reply received on 14.03.2016 vide letter dated 02.03.2016. comments of CWC have been sent to State Govt of Assam on 21.03.2016

18 Assam Integrated Flood and River Bank 88.06 08.04.2015 DPR was sent to Hyd (NE) on 10.04.2015. Received 88.06 Erosion Risk Management Project” , observations from Hyd (NE) vide letter dated 03.08.15. II(Palasbari Reach Trench-II) State Govt was requested to process DPR through MOWR vide letter dated 24/09/2015. Comments of Hydrology(NE) send vide letter dated 12/10/2015. Reply awaited. 19 Assam Integrated Flood and River Bank 82.4 08.04.2015 DPR sent to Hyd (NE) on10.04.2015. Received from Hyd 82.4 Erosion Risk Management Project” , for (NE) vide letter dated 04.08.15. State Govt was requested Gumi and its Downstream area Trench-II) to process DPR through MOWR vide letter dated 24/09/2015. Comments of Hydrology(NE) send vide letter dated 12/10/2015. Reply awaited.

20 Anti-erosion measures to protect Bor-Dirak, Na- Cleared by CWC/PC 14.1510 Chumoni and its adjoining areas from the 14.1510 07.01.2013 erosion of river Noa-Dehing & Dirak 21 R/S o R/B embankment of river Aie from ch. 0 m 111.46 02.01.2013 Comments issued in April 2013. Reminded on 30.01.2015. 111.46 to ch 2200 m and from ch. 8000 m to 18000 m Reply awaited. including A/E measurement at different reaches

22 Improvement of Flood Protection System 4454.09 15.10.2014 A Copy of DPR without drawing volume was received vide 4454.09 along the both bank of river Brahmaputra letter dated 22/09/2014 and State Govt. was requested to submit at least one more set of DPR vide letter dated 21.10.2014. Reminded vide letter dated 12.11.2014 ,10.12.2014 and 16.04.2015. Reply received from State Govt vide letter dated 06/06/2015. A copy of DPR was sent to Hyd(NE) Dte for examination. Comments of FMP Dte were sent to State Govt on 11.08.15. Response from State Govt. received vide letter dated 31.08.2015. Observations from Hydrology(NE) received vide letter dated 22/09/2015.Comments from Hydrology (NE) and other observations sent to Govt. of Assam vide letter dated 17/12/2015. Reply awaited. State/UT wise details of Flood Management Project Proposals ( coordinated by CWC) during XII Plan inculding spillovers as on 21.03.2016

Sl Estt. Cost Date of Under Name of works/scheme Status of examination Cleared Returned Awaited No. (Rs. In Cr) Receipt examination 23 Protection of Jatiabori and Kuptimari area form 180.77 13.10.2014 Received on 13.10.2014 . Forwarded to Hydrology (NE) 180.77 the erosion of river Brahamaputra vide letter dated 15.10.2014. Comments from Hydrology (NE) received vide letter dated 22/12/2014 which was forwarded to Govt of Assam vide letter dated 23.12.2014. Revised DPR submitted vide Govt of Assam letter dated 27/04/2015. Under examination of CWC. forwarded to Embankment (E&NE) Dte on 12.10.15. Comments received from Embankment (E&NE) Dte on 20.10.15. comments of FMP and Embankment (E&NE) Dte sent to State Govt on 08.01.16. Reply awaited.

24 Raising and Strengthening (R/S) of Dikhow 213.8 22-01-2013 Comments sent to state government on 06.08.2013. Reminded 213.8 embankment both banks from Upper Nazira to on 30.01.2015.The state governement has not submitted the Dikhowmukh at different reaches along with complliance. protection measures 25 R/S to Puthimari Both Bank Embankment from 35.05 02.01.2013 One Set of DPR received at CWC(HQ) on 01.01.2015 and 35.05 Baramboi to its outfall forwarded to Hyd (NE) for examination. WRD Assam has been requested to submit the 4 more sets of DPR vide letter dated 02.01.2015. Reply from Assam is awaited

26 Anti erosion measures at different reaches of 32.61 01-09-2013 Observations communicated to State Govt. on 29-01-2013. 32.61 right bank of river Jiabharali including R/S of Reminded on 30.01.2015.The state governement has not embankment of Kurkani submitted the complliance. 27 R/S of Dhansiri bund from Panjan to Barpathar 61.96 01-11-2013 Comments issued on 31.05.2013.State Govt. replies received 61.96 and Dowel bund at Kamargaon including A/E on 16.09.2013, Replies are under examination in CWC. measures at different reaches Submission of modified DPR from state government is awaited.Reminded on 30.01.2015.Received in FMO vide letter dated 26.10.2015.Sent to Hydrology (NE) on 04.01.2016. Reply from Hyd (NE) received on 07.03.2016

28 Channelization and Stabilisation of Brahmajan 103.18 22-01-2013 Comments issued in March 2013. The state governement has 103.18 and Tupang river including R/S of existing and not submitted the complliance. Reminded on 30.01.2015. providing new marginal embankment

29 Flood mangaement of river Subansiri along with 1155.7064 22-01-2013 Comments made by BB on 15.01.2013. The state 1155.7064 river training works on both banks embankment governement has not submitted the complliance. Reminded in Assam on 30.01.2015. SE( C ) visited site on 02.03.15. Estt cost revised from Rs. 1564.22 crore to 1155.7064 crore Compliance received on 20.10.15. Under examination. Received in FMP on 21.12.2015 vide letter dated 17.11.15.Sent to Hydrology(NE) on 28.12.2015.

30 Flood and erosion Protection measures at 296.74 22-01-2013 Comments made by BB on 15.01.2013. Reminded on 296.74 Gainadi Basins 30.01.2015.The state governement has not submitted the complliance. 31 Anti Erosion measure at different reaches of 36.43 21-02-2013 DPR received on 12.02.2015. Send to Hyd (NE) on 12.02.2015. 36.43 Jhanji river on Left Bank Comments of Hydrolgy received on 10.07.2015 forwarded to State Govt. Reply awaited. 32 Integrated Flood and erosion mangement of 379.3 25-02-2013 Comments given on 05-08-2013.Reminded on 30.01.2015.The 379.3 Manas and Beki rivers in districts of Baksa and state governement has not submitted the complliance. Barpeta 33 Protection of Jatiabori, Nitmari&Kapurpura area 32.35 06-12-2013 Report returned back on 01.08.2013 for clarification. 32.35 including Bhuragaon town from the erosion of Reminded on 30.01.2015. river Brahmaputra 34 Protection of Neematighat from the erosion of 68.48 07-05-2013 Observations communicated to State Govt. on 05-09-2013.The 68.48 river Brahmaputra state governement has not submitted the complliance. Reminded on 30.01.2015 35 Anti-erosion measures to project different 154.382 07-11-2013 Observations communicated to State Govt. on 05-09- 154.382 reaches from the erosion of river Kopili on both 2013.Reminded on 30.01.2015. The state governement has banks not submitted the complliance. 36 Flood and erosion management of Jiadhal basin 75.0709 22.11.2013 Observation conveyed by BBBO on 09.01.2014 to CE, WRD 75.0709 from railway line to Gurathali Chapori and reminded on 12.03.2014. Reminded on 30.01.2015.The state governement has not submitted the complliance.

37 Protection of Different reaches from the erosion 13.06 22-01-2013 Compliance awaited to the observations made by B Board awaited 13.06 of river Jamuna on both banks from State Govt. Reminded on 30.01.2015. 38 Protection of Karimganj town and adjoining area 23.55 31-12-2012 from the erosion of river Kushiyara on its L/B at Returned back on 22-01-2013 for want of fresh State TAC as scope of 23.55 West Serulbagh, Jagamathi, Chandsrikona and the Scheme Changed Compliance awaited. Reminded on 30.01.2015. Jabainpur 39 Anti Erosion measures to protect Hirapara and 15.34 01-02-2013 its adjoining area from the erosion of river TEC accorded on 15.12.14. 15.34 Brahmaputra 40 Anti Eerosion measures to protect Dakurvita- 13.53 01-02-2013 Kusbari and Chatiarpar area (atU/S & D/S of Observations communicated to State Govt. on 08-08-2013. 13.53 RIDF-VII scheme) from the erosion of river Compliance awaited. Reminded on 30.01.2015. Brahmaputra 41 Anti Erosion Measures to T/Dyke along the Right 12.95 02-08-2013 Comments issued on 17.6.2013. Replies along with modified estimate of Rs Bank of river Buridehing from Bhekuljan to 12.87 Crore rcvd on 27.6.13. Further observations communicated on 12.95 Tipling 12.08.2013. Compliance awaited. Reminded on 30.01.2015. 42 Channelization of river Brahmaputra and 24.99 02-08-2013 reclamation of eroded land by choking of various Observations communicated on 08-08-2013. Compliance awaited. 24.99 oblique channel at different location from Beldubi Reminded on 30.01.2015. to Shishumara 43 Protection of Kapurpura area including 17.38 25-02-2013 Bhuragaon Town from the erosion of river Comments given on 11.7.2013 Compliance awaited. Reminded on 17.38 Brahmaputra (construction of Land Spur and Tie 30.01.2015. Bund) Ph-III 44 Anti-erosion measures to extension of 13.93 18-07-2013 Observations communicated on 12-08-2013. Compliance awaited. Tengakhat bund from Jokai RF to AT Road at 13.93 Reminded on 30.01.2015. 5th KM (KatchamariDeoriGaon) 45 Raising and strengthening of Kakoi R/B 24.85 09-10-2013 Examined. Observations conveyed by BBBO on 09.1.14 to CE, WRD embankment from Lilabari T.G. to Kadam 24.85 Compliance awaited. Reminded on 30.01.2015. including Anti Erosion works Phase-II 46 Protection of Dikhow bund R/bank from NH 22.75 22.11.2013 bridge to Dikhowmukh at different reaches along Examined. Observations conveyed by BBBO on 10.1.14 to CE, WRD 22.75 with antierosion measures at Kariagaon, Compliance awaited. Reminded on 30.01.2015. Bokabel and Santipur State/UT wise details of Flood Management Project Proposals ( coordinated by CWC) during XII Plan inculding spillovers as on 21.03.2016

Sl Estt. Cost Date of Under Name of works/scheme Status of examination Cleared Returned Awaited No. (Rs. In Cr) Receipt examination 47 Extension and strenghthening of existing 23.2796 22.11.2013 protection of B/dyke from ( Desangmukh) to Examined. Observations conveyed by BBBO on 10.1.14 to CE, WRD 23.2796 Dikhowmukh at Aphala missing Gaon (Proction Compliance awaited. Reminded on 30.01.2015. at Charaipara & Garbhanga) 48 Protection to Desang bund R/Bank at Khamon 16.6345 22.11.2013 Khanikar reach- I reach -II, Ikoratoli reach and Examined. Observations conveyed by BBBO on 9.1.14 to CE, WRD 16.6345 Bakulduba area under Thowra LAC, Compliance awaited. Reminded on 30.01.2015.

49 Protection of Sivasagar Town at different 24.8495 22.11.2013 reaches including A/E measures from the Examined. Observations conveyed by BBBO on 8.1.14 to CE, WRD 24.8495 erosion of river Dokhow from Manipuri Basti to Compliance awaited. Reminded on 30.01.2015. NH Bridge. 50 Protection of Flood embankment along Kollong 24.579 16.12.2013 Examined. Observations conveyed by BBBO on 09.1.14. Complied/TE river from Raha to Jagi (R/B) (in between Ch. 24.579 clearance to PC on 10.05.14 19th km.to 54th km) 51 Protection of Desang bund R/B from Desangpani 15.7762 16.12.2013 to Patsaku at Shyamgaon, Goriagaon -I & Examined. Observations conveyed by BBBO on 28.2.14 to CE, WRD 15.7762 Goriagaon -II under Mahmara LAC Compliance awaited. Reminded on 30.01.2015.

52 R/S to construction of M/E along both bank of 14.3468 19.12.2013 Mora Pagaladiya river from NH-31 bridge TEC accorded on 04.06.14 14.3468 crossing including A/E measure at different reaches 53 Anti Erosion messures to different reaches of 20.154 07.01.2014 Desang Bund L/B from Pathaligarh to Bahgarh to Examined. Observations conveyed by BBBO on 28.2.14 to CE, WRD . Baksu Kotoky Koch and Moutgaon sgainst the 20.154 Compliance awaited. Reminded on 30.01.2015. erosion of river Desang

54 13.391 20.02.2014 Preservation, protection & improvement & Examined. Observations conveyed on 13.5.14 to Chairman, SDA, 13.391 cleaning of historical Yamuna around Sivasagar Sivasagar Compliance awaited. Reminded on 30.01.2015. Tank and Siva Doul at Sivasagar Town 55 14.78 20.02.2014 Examined. Observations conveyed by BBBO on 04.4.14 to CE, WRD. Reply received on 17.09.2014. Further observations conveyed on Protection of L/B of river Borgang from erosion 14.78 at d/s of NH 52 to its outfall on Brahmaputra 10.10.14. Reply received on 25.03.2015. Further observations under NLCPR conveyed on 29.05.2015. 56 13.66 21.03.2014 Examined. Observations conveyed by BBBO on 04.06.14 to CE, WRD. Reply along with modified DPR received on 28.10.14. Further 13.66 Protection of Gangmouthan and its adjoining observations conveyed on 15.12.14. Reply awaited.. Reminded on areas from erosion of river Borgang on L/B 30.01.2015. 57 river erosion management project in Dissang 7.12 22-01-2013 Observation made by Brahmaputra Board. Reminded on 7.12 Basin at Chitum and Nissa river/ Tissang 30.01.15. Reply awaited. 58 Anti erosion measures to protect Gaur 4.04 22-01-2013 Observation made by Brahmaputra Board. Reminded on 4.04 jhapsabari village and Indo Bangladesh Border 30.01.15. Reply awaited. Fencing from flood damage of river Kaljani

59 Protection of Hasantuk and its adjoining areas of 7.04 22-01-2013 Observation made by Brahmaputra Board.Reminded on 7.04 Rangia Town from erosion of Baralia river 30.01.15. Reply awaited.

60 Anti erosion measures to extension of Tengakhat 6.18 22-01-2013 Observation made by Brahmaputra Board. Reminders 6.18 and from Jokai R.F to A.T Road at 5 km. alongwith broad comments issed on 17.06.2014. Reminded on (DatahamariDeriogaon) 30.01.15. Reply awaited. 61 Anti erosion measures of Desang Bund Left 4.06 01-02-2013 Observation communicated on 02.07.2014.Reminded on 4.06 Bank from Akhyphutia to Desang much 30.01.15. Reply awaited. (protection work at 44th and 48th km.) 62 Protection of Baghedhora, Sakupara and 12.27 01-11-2013 Project visited by SE(C), B&BBO on 05.03.2013. Comments 12.27 adjoining area of DakhinAhotguri from erosionof given on 14.05.2013. Replies of State Govt. received on river Brahmaputra 30.07.2013. Further observation communicated on 22.07.2014. reply received on 07.11.2014. Further observation Conveyed on 29.12.2014 reminded on 30.01.15. Reply received on 20.07.2015. Under Examination.

63 Extension of Anti erosion Measures to Dehing 8.56 02-08-2013 Comments issued on 17.06.2013. Replies along received on 8.56 Bund L/ Bank from Anghuribari to Sesughat 27.06.2013. After Examination further Observations were communicated to State Govt. on 12.08.2013. reminded on 30.01.15. Reply awaited.

64 Protection of Dharpur and Garal area D/S of 9.46 30-07-2013 Observations were communicated to State Govt. On 9.46 Dhoptala Bazaar from the erosion of river 16.09.2013. reminded on 30.01.15. The state governement Brahmaputra from Ch. 5500m to 6100m has not submitted the complliance

65 Protection of Sonapur and adjoining area from 5.5 Cleared by CWC 5.5 severe bank erosion of river Puthimari – NLCPR scheme of M/o DoNER 66 A/E measures at right bank of Charamari village 2.3368 19.12.2013 Observation were communicated to CE, WRD assam on 2.3368 and its adjoining areas from the erosion of 20.12.2013.reminded on 30.01.15. The state governement Dekadong river has not submitted the complliance 67 Anti erosion measures to protect Chapakhowa 10.8035 10.02.2014 Cleared by CWC on 03.06.2014 10.8035 town and its adjoining areas from the erosion of river Kundil ph-III 68 Closing avulsion of river Chamrang at Chamrang 4.6529 20.02.2014 Cleared by cWC on 20.08.2014 4.6529 Village 69 Anti erosion measures to protect Singirbond 10.998 20.02.2014 10.998 area from erosion of river Barak on its L/B Examined. Observations conveyed by BBBO on 13.5.14 to CE, WRD. Reply received on 08.09.2014. Further, observation conveyed on 12.11.2014. Reply awaited. Reminded on 30.01.2015. Reply received on 03.12.2015 and uner observation.

70 Anti erosion measures in extension of Sassoni 13.8907 12.06.2014 Cleared by CWC ON 15.09.2014 13.8907 Tingkhong Bund, Ph-1 on the left bank of river buridehing (Protection work at Bamunibeel and Uriamguri area ) 71 Pro si;tatopm measures to protect Sarulah 11.3523 03.11.2014 TEC accorded on 23.01.2015 11.3523 Barlah village and its adjoining area from the erosiin of river Brahamputra 72 Providing revetement and R/S to M/E along 10.71 21.02.2013 Earlier estimated cost of Rs 6.99 Crore modified to Rs 10.58 Crore 10.71 both banks of river Durpang from near rcvd as per observation of B Board. Scheme recommended to State Rajgarhaliu to its outfall at Pichala Government for sanction at cost of Rs 10.58 Crore in April 2013. Reminded on 30.01.2015. State/UT wise details of Flood Management Project Proposals ( coordinated by CWC) during XII Plan inculding spillovers as on 21.03.2016

Sl Estt. Cost Date of Under Name of works/scheme Status of examination Cleared Returned Awaited No. (Rs. In Cr) Receipt examination 73 Anti erosion measueres to protect Chapakhowa 24.992 12.06.2014 examined observati9on conyeed on 22.07.2014 . Compliance 24.992 town and its adjooining areas from the erosion 0f awated. .reminded on 30.01.15. river Kundli under sadia civila sub divison (Desoi river protection ) 74 anti erosin meausre to Roypur area against ythe 15.0995 08.09.2014 Observation Conveyed on 20.11.14. Reply Awaited. Remined 15.0995 erosin Borak on its left bank on 30.01.2015 75 Protection of Choudhary Bazar and its adjoining 14.59 09.01.2015 observation conveyed on 23.01.15. replies along with 14.59 areas from the erosion of river Beki modified DPR received on 03.08.15. Observations conveyed on 08.09.15. Reply awaited 76 Anti erosion measures to protect Panikhaiti and 24.69 22.06.2015 Observation conveyed on 13.07.2015. Reply awaited 24.69 sontoli area from erosion of river Brahmaputra

77 construction of T/Dyke along R/B of river 24.6548 10.11.2014 Observation Conveyed on 15.12.14 .reminded on 30.01.15. 24.6548 Kollong from Dhankhunda to Gobardhan hill and TE clearance conveyed on 23.03.2015 sluice gate at Dhepuijan Ghoramarajaan and Kajolijan 78 Protection of Makadhuj area from the erosion of Cleared by CWC and approved by IMC in its first meeting held river Brahmaputra (Construction of landspur at 14.2078 14.2078 on 19.12.2013. Investment Clearance on 27.09.2012 ch.9560m) 79 A/E measures for protection of KatlicerraBagan Cleared by CWC and approved by IMC in its first meeting held 14.279 14.279 Area on the left bank of river Katakhal adjacent on 19.12.2013. Investment Clearance on 07.01.2013 to NH-154 PH-II in a lenth of 600m 80 A/E measures to protect Berabhanga area of left Cleared by CWC and approved by IMC in its first meeting held bank of river Brahmaputra (chanalisation of river 14.9491 14.9491 on 19.12.2013. Investment Clearance on 07.01.2013 Brahmaputra from barobluecher to Kalair Alga with reclamation of eroded land within the reach) 81 Anti erosion measures for extention of Tangakhat Bund up to jokai Reserve Forest at Dehinghulla(chainage 4000 m ) Telpani reserve Cleared by CWC and approved by IMC in its first meeting held 16.7163 16.7163 Forest (chainage 8800 m) Bhurbhuri on 19.12.2013. Investment Clearance on 07.01.2013 (chainage15800 m) and Bhurbhuri(chainage18500m) 82 R/S to Dehing bund left bank from Joongaon to Cleared by CWC and approved by IMC in its first meeting held Laibeel including A/E measures at defferent 13.89 13.89 on 19.12.2013. Investment Clearance on 07.01.2013 reaches 83 A/E measures to pagladia left bank embankment from domukh to adabariincluding strengthening Cleared by CWC and approved by IMC in its first meeting held 14.4492 14.4492 and widening of the dyke at different reaches;at on 19.12.2013. Investment Clearance on 07.01.2013 1st km(kathaghopa) at 4th km (Hablakha and at 6th km(Bullutpar) 84 Strenghtening and extension of Dhubri TOWN Cleared by CWC and approved by IMC in its first meeting held 14.8998 14.8998 plrotection works from newghat to Aironjongla on 19.12.2013. Investment Clearance on 07.01.2013 from erosion of river Brahmaputra 85 Anti erosion measures at panchgram das colony Cleared by CWC and approved by IMC in its first meeting held area from erosion of river barak of its left bank (0 17.5747 17.5747 on 19.12.2013. Investment Clearance on 25.02.2013 to 800m) 86 Anti erosion measures to plrotect Sirigouri Bazar Cleared by CWC and approved by IMC in its first meeting 12.69 12.69 NH-44 and Badarpur to Bhanga PH-II dyke from held on 19.12.2013. Investment clearance on 21.02.2013 erosion of river Borak on its left bank 87 Flood Management works on to protect the Cleared by CWC and approved by IMC in its first meeting village channinghat and Laltugram from erosion 14.93 14.93 of river Rukini on its L/B ncluding R/S of held on 19.12.2013. Investment clearance on 21.02.2013 embankment from Bhangabazar to Sundari 88 Protection of Sonabarighat, Uttarkrishnapur and Weavers colony- Beranga Nath Para Cleared by CWC and approved by IMC in its first meeting 22.35 22.35 area from the erosion of river Barak on its left held on 19.12.2013. Investment clearance on 21.02.2013 Bank 89 Construction of retirement of B/Dyke from Kharmuza to Bailikuchi from Ch 11.55 Km to Cleared by CWC and approved by IMC in its first meeting 24.4161 24.4161 13.46 Km at solmari including anti- erosion held on 19.12.2013. Investment clearance on 17.05.2013 measures 90 Construction of Retirement of B/Dyke from Balikuchi to Beldubi from Ch 33.94 Km (at Cleared by CWC and approved by IMC in its first meeting 24.4893 24.4893 Jaleswar) connecting to DRDA bund at held on 19.12.2013. Investment clearance on 17.05.2014 Nichipur including A/E measures 91 Anti-erosion measures to protect Brahmaputra dyke on Right bank of river Cleared by CWC and approved by IMC in its first meeting Brahmaputra from Adabari to Kukrajan 13.6612 13.6612 held on 19.12.2013. Investment clearance on 17.05.2015 including strengthening of the dyke from Ch 26th Km to Ch 33rd Km 92 R/S of B/dyke on L/B from Gumi to Kalatoli from ch. 21.30 km to 27.80 km including Cleared by CWC and approved by IMC in its first meeting 14.49 14.49 recoupment of the dyke from ch. 27.80 km to held on 19.12.2013. Investment clearance on 01.11.2011 ch. 35.00 km.- 93 Anti-erosion measures to protect Moisa and Cleared by CWC and approved by IMC in its first meeting Belguri village from the erosion of river 14.97 14.97 held on 19.12.2013. Investment clearance on11.11.2011 Gangadhar. 94 Raising and Strangthening of flood embankment along right bank of river Barnadi Cleared by CWC and approved by IMC in its first meeting from Halda to its outfall at Lenga at different 15.7751 15.7751 held on 19.12.2013. Investment clearance on 20.06.2013 reaches including anti-erosion measures.

95 Anti-erosion measures to protrct Soalkuch Cleared by CWC and approved by IMC in its first meeting town from the erosion of river Brahmaputra 22.7124 22.7124 held on 19.12.2013. Investment clearance on 20.06.2013 PH-V. 96 Anti-erosion measures at different reaches of river Dhansiri on its banks. Cleared by CWC and approved by IMC in its first meeting 11.8193 11.8193 held on 19.12.2013. Sanctioned by State

97 Anti-erosion measures to protect Bhalukmari Cleared by CWC and approved by IMC in its first meeting and its adjoing areas from the erosion of river 11.7791 11.7791 held on 19.12.2013. Sanctioned by State Brahmaputra. State/UT wise details of Flood Management Project Proposals ( coordinated by CWC) during XII Plan inculding spillovers as on 21.03.2016

Sl Estt. Cost Date of Under Name of works/scheme Status of examination Cleared Returned Awaited No. (Rs. In Cr) Receipt examination 98 Channelisation of Gangadhar river in between Chilaraj bridge and Railway bridge Cleared by CWC and approved by IMC in its first meeting to protect Pub-Kanori Ratiadah and 12.4275 12.4275 held on 19.12.2013. Sanctioned by State Golakganj Town from the erosion of river Gangadhar. 99 Ant-erosion measures at different reaches of Cleared by CWC and approved by IMC in its first meeting dhansiri and its Sub-tributaries ( rewta & 12.461 12.461 held on 19.12.2013. Sanctioned by State Rowtamukh River). 100 Anti erosion measures to protect left bank Cleared by CWC and approved by IMC in its first meeting held embankment of River BurhiDehing at Namfakial 13.4527 13.4527 on 19.12.2013. Investment clearance on 13.09.2013 village 101 M.E alonag both bank of river Mora pagaldia Cleared by CWC and approved by IMC in its first meeting held from N.H.way TihuAdhra PWD road (raising and 18.0064 18.0064 on 19.12.2013. Investment clearance on 13.09.2013 strengthening of embankment including anti erosion works on both bnank at different reaches 102 Protection of Brahmaputra Dyke from Cleared by CWC (117th TAC held on 12.04.2013) and Sissikalghar to Tekelilphuta at different reaches 155.3667 approved by IMC in its first meeting held on 19.12.2013. 155.3667 from Lotasur to T ekeliphuta from the erodion of Investment clearance on 06.09.2013 river Brahmaputra (Review) 103 Cleared by CWC (118th TAC held on 12.08.2013) and Flood Management of river Dikrong along with 105.9628 approved by IMC in its first meeting held on 19.12.2013. 105.9628 river training works on both banks embankment Investment clearance on 20.11.2013 in the Lakhimlpur district, Assam 104 Cleared by CWC (118th TAC held on 12.08.2013) and Flood Management of river Ranganadi along 361.4292 approved by IMC in its first meeting held on 19.12.2013. 361.4292 with river training works on both bank Investment clearance on 20.11.2013 embankments in the Lakhimlpur district, Assam 105 Providing revetment and R/S to M/E along Cleared by CWC and approved by IMC in its second both banks of river Durpang from near 10.585 10.585 meeting held on 03.03.2014. Not required Rajgarhali to its outfall at Pichala 106 Anti-erosion measures in both banks of river Cleared by CWC and approved by IMC in its second Mangaldal to protect Mangaldal town and 10.9096 10.9096 meeting held on 03.03.2014. Not required adjoining villages 107 R/S to Bramahaputra Dyke from Palasbari to Cleared by CWC and approved by IMC in its second Gumi fron Ch. 0 Km to 21.2 Km including anti- 23.6972 meeting held on 03.03.2014. Investment clearance on 23.6972 erosion measures at different reaches. 17.05.2013 108 Anti-erosion measures to protect Dirakmukh Cleared by CWC and approved by IMC in its second area on the left banks of Non-Dehing river at 11.3362 meeting held on 03.03.2014. Investment clearance on 11.3362 Saikhowa protection bund ph-1 24.12.2013 109 Raising and strengthening to Dehing bund Cleared by CWC and approved by IMC in its second right bank from Kotoha to Sessamukh 12.6036 meeting held on 03.03.2014. Investment clearance on 12.6036 24.12.2013 110 Protection of T/Dyke from Chilanipam to Cleared by CWC and approved by IMC in its second Orangbasti from the erosion of river Jiabharat 13.646 meeting held on 03.03.2014. Investment clearance on 13.646 on its left bank 24.12.2013 111 Raising and strengthening to flood protection Cleared by CWC and approved by IMC in its second bund of TengakhatMouza including anti- 14.6192 meeting held on 03.03.2014. Investment clearance on 14.6192 erosion measures at 3 rd Km (Bantana) abd 24.12.2013 12 th km (Tikirabali) 112 Protection of Biswanatha -Panpur including Cleared by CWC (11th TAC held on 25.08.2011) and areas of upstream Silamari and far 167.09 approved by IMC in its second meeting held on 167.09 downsteamBhumuragauri to Borgaon against 03.03.2014. Investment clearance on 24.12.2013 erosion of river Bramhaputra 113 Protection of Tezpur university & its adjoing Cleared by CWC and approved by IMC in its second area from erosion of river Jiabharli 23.18 meeting held on 03.03.2014. Investment clearance on 23.18 26.11.2013 114 Anti-erosion measures at different eaches of Investment clearance on 24.01.2014Cleared by CWC and right bank of river Brahmaputra from 21.9218 approved by IMC in its second meeting held on 21.9218 Berachapori to Chengajanghat 03.03.2014. 115 Anti-erosion measures to protect both bank of Cleared by CWC and approved by IMC in its second river Simen in Jonai Civil sub-division. 24.1521 meeting held on 03.03.2014. Investment clearance on 24.1521 24.01.2014 116 Channelelization of river Brahmaputra from Cleared by CWC and approved by IMC in its second U/s of Neamatighat to Lality 14.5377 meeting held on 03.03.2014. Investment clearance on 14.5377 25.02.2013 117 R/S of Barnadi L/B embankment from Cleared by CWC and approved by IMC in its second Patgirlsuba to RK embankment 13.2687 meeting held on 03.03.2014. Investment clearance on 13.2687 24.12.2013 118 Protection of Bhurbanda and its adjoining Cleared by CWC and approved by IMC in its second areas against the erosion of river 21.27 meeting held on 03.03.2014. Investment clearance on 21.27 Brahmaputra ( construction of land spur) 10.01.2014 119 De-silttaion and re-sectioning of Jita Naadi 24.92 (Drainage Channel) under Hailakandi Civil 24.92 Observation conveyed on 04.08.2015. Reply awaited Sub-Division, Hailakandi 09.07.2015 120 Anti erosion measures of Matrijuri Bazar area 22.7663 from the erosion of river Katakhal on its left 22.7663 Observation conveyed on 26.08.15. Reply awaited bank, Hailakandi 20.07.2015 121 Raising and strengthning of Brahmaputra 10.8153 Dyke from Gohaingaon to Khutiaputa Tie 10.8153 Observations conveyed on 09.03.15. Reply awaited bund, Jorhat 30.01.2015 122 Anti erosion measures to protect Uttar 8.63 Ramfalbil, Roy Basti, Moinaguri villages and 8.63 Observation conveyed on 06.10.15. Reply awaited its adjoining areas from the erosion of river Longa 25.08.2015 123 Anti erosion measures to protect from D/S of 14.3177 Longa Irrigation Project to PWD road 14.3177 Observation conveyed on 06.10.15. Reply awaited Laudonga from the erosion of river Longa 25.08.2015 124 A/E measures to protect Shilbari, Borogaon, 12.0532 Kuyarpar, Jalabila and Maha Mayasnanghat 12.0532 Observation conveyed on 13.10.15. Reply awaited and its adjoining area from the erosion of river Tipkai 09.09.2015 125 A/E measures at different reaches of Pagla/Batiamari river on its both bank (Phase- 11.8382 Under examination 11.8382 II) 19.10.2015 State/UT wise details of Flood Management Project Proposals ( coordinated by CWC) during XII Plan inculding spillovers as on 21.03.2016

Sl Estt. Cost Date of Under Name of works/scheme Status of examination Cleared Returned Awaited No. (Rs. In Cr) Receipt examination 126 A/E measures to protect the Subansiri river bank alongwith R/S work from Bodali to Kharoi outfall (Review) 86.6980 16.11.2015 Under Observation 86.6980

127 Protection of Boradi, belartari, habi-goroimari and its adjoining areas from the erosion of river Brahmaputra (Review) 51.8000 27.01.2016 Under Observation 51.8000

128 Raising and strengthening of Brahmaputra dyke 14.3815 29.08.2015 Observation conveyed on 16.12.2015. Reply awaited 14.3815 from Neamati PWD Road to Gohaingaon (Borali)

129 Raising and strengthening of Brahmaputra dyke 10.6217 29.08.2015 Observation conveyed on 16.12.2015. Reply awaited 10.6217 from Gohaingaon to Khutiaputa Tie bund

130 A/E measures at different reaches of 15.6855 03.10.2015 Observation conveyed on 29.12.2015. Reply awaited 15.6855 Pagla/Batiamari river on its both banks (Phase I)

131 Extension of Brahmaputra dyke Ph- IV from 21.593 20.07.2015 Observation conveyed on 03.02.2016. Reply awaited 21.593 Chaulkhowa Medellagaon to Madhupur Deurigaon 132 A/E measures at different reaches of Golondi 23.0539 11.01.2016 Under observation 23.0539 river on its both banks 133 Anti erosion measures at different reaches of 22.9020 26.11.2015 Under observation 22.9020 Gangia river 12050.1385 1613.0728 137.76 8576.9662 1722.2765 2 Arunachal Pradesh 1 Flood & River Erosion Management Project 92.00 27.11.2013 DPR received in CWC (HQ) on 27.11.2013 and was 92 in Dikrong Basin, Papumpare (ARP-25) forwarded to the Hydrology Dte.(NE) vide letter dated10.12.2013. Hyd(NE) furnished comments vide letter dated 11.03.2014 and the same forwarded to the state government vide letter dated 11.03.2014. Further, Compliance from state government received vide letter dated 19.08.2014 and the same was forwarded to the Hydrology Dte.(NE) vide letter dated 01.09.2014. Hyd (NE) conveyed its clearance vide letter dated 01.10.2014. Comments on the Hydrological and design aspects were send to WRD , Ar. Pradesh vide letter dated 11.11.2014. WRD, AP submitted compliance vide letter dated 28.11.2014. DPR has been examined and comments sent on 23.04.2015. Reply from State Govt received on 03.11.15. DPR is forwarded to Embankment (E&NE) on 21.03.2016 for examination

2 Flood & River Erosion Management Project 65.00 27.11.2013 DPR received in CWC (HQ) on 27.11.2013 and same 65 under Siang Basin (ARP-35) forwarded to the Hydrology Dte.(NE) vide letter dated 10.12.2013. Hyd(NE) furnished its comments vide letter dated 14.02.2014 and the same forwarded to State govt. vide letter dated 18.02.2014.WRD Ar. Pradesh submitted compliance vide letter dated 02.12.2014. Hyd (NE) Dte examined the DPR and further comments communciated vide letter dated 24.04.2015 and same were forwarded to state Government vide letter dated 11.05.2015. Reply awaited. Reminded on 25.02.2016

3 Flood & River Erosion Management Project 37.00 27.11.2013 DPR received in CWC (HQ) on 27.11.2013 and same 37 in Lohit Basin(ARP-38) forwarded to the Hydrology Dte.(NE) vide letter dated10.12.2013. The Hyd (NE) Dte has examined the DPR and furnished its comments vide letter dated 05.03.2014 and the same forwarded to state government vide letter dated 11.03.2014. Further, Compliance from state government received vide letter dated 05.09.2014 and the same been forwarded to the Hydrology Dte.(NE) vide letter dated 09.09.2014.Hyd(NE) conveyed its clearance vide letter dated 19.11.2014. Comments on design aspects conveyed on 08.01.2015. Reply awaited.

4 Anti-Erosion & Flood Protection work in Noa- 83.00 27.11.2013 DPR received in CWC (HQ) on 27.11.2013 and same 83 Dehing Basin (ARP-39) forwarded to the Hydrology Dte.(NE) vide letter dated10.12.2013. The Hyd (NE) Dte examined the DPR and furnished its comments vide letter dated 28.02.2014 and the same forwarded to state government vide letter dated 11.03.2014. Further, Compliance from state government received vide letter dated 25.08.2014 and the same forwarded to the Hydrology Dte.(NE) vide letter dated 12.09.2014. Hydrology cleared vide letter dated 19.11.2014. Commnets on the design aspects submitted to state Govt vide letter dated 28.01.2015. Reply awaited.

5 Flood Mgmt. works in Bichom Basin (ARP 15.00 01.10.2013 Cleared by CWC 11.12.2013 15.00 22) 6 Anti Erosion works to protect Kameng Basin 20.00 01.10.2013 Cleared by CWC 11.12.2013 20.00 (ARP 23) 7 Flood & river Erosion management (FREM) 21.78 01.10.2013 Cleared by CWC 11.12.2013 21.78 project in Buroi Basin (ARP 26)

8 Anti Erosion works on Tirap Basin (ARP 40) 25.00 04.10.2013 25.00 Examined, Observation conveyed by Dir M&A on 18.12.2013 to CE,WRD (E/Z). Modified DPR received on 30.12.2013. M&A pointed out some discrepencies to SE(WRD).Modified DPR received on 05.01.2015. further observations conveyed on 05.02.2015.Reply awaited. State/UT wise details of Flood Management Project Proposals ( coordinated by CWC) during XII Plan inculding spillovers as on 21.03.2016

Sl Estt. Cost Date of Under Name of works/scheme Status of examination Cleared Returned Awaited No. (Rs. In Cr) Receipt examination 9 FREM project in Ranganadi Basin (ARP 27) 19.00 01.10.2013 19.00 Examined, Observation conveyed by Dir M&A on 18.12.2013 to CE,WRD (E/Z). Modified DPR received on 13.01.2014. M&A pointed out some discrepencies to SE(WRD). Reminded on 03.12.2014.Reply awaited. 10 FREM project in Subansiri Basin (daporijo, 20.66 01.10.2013 20.66 Dumporiju and Nacho) (ARP 28) Examined, Observation conveyed by Dir M&A on 18.12.2013 to CE,WRD (E/Z). Modified DPR received on 13.01.2014. M&A pointed out some discrepencies to SE(WRD). Revised DPR received on 22.08.2014. further observations conveyed on 20.01.2015. Reply received. Observation conveyed on 10.03.15. Reply awaited 11 FREM project in Siyum & Sipeng river at 15.56 01.10.2013 TEC accorded on 17.03.2015 15.56 Jomlo area (ARP 30)

12 FREM project at Hoo river at Nikte Village 16.51 01.10.2013 TEC Accorded on 07.01.15 (Estimated cost revised to 16.51 under aalo Circle (ARP 31) 16.51 Cr) 13 FREM project on Datung River under 14.83 01.10.2013 TEC Accorded on 07.01.15 (Estimated cost revised to 14.83 Dambuk sub division (ARP 36) 14.827 Cr) 14 FREM project in Deopani and Sine river in 14.69 01.10.2013 TEC Accorded on 07.01.15 (Estimated cost revised to 14.69 Dibang Basin (ARP 37) 14.6919 Cr). 15 Flood and River erosiin managemen (FREM) 13.05 12.11.2013 Observation conveyed. Modified DPR rceived on 13.05 project on Sirti & Jabung River under 11.08.2014. Observation sent on 04.09.2014. Reminded Rumgong circle (ARP-32) on 03.12.14. Reply awaited. 16 Flood and erosion management under 14.50 12.11.2013 Revised DPR recived on 22.08.2014 observation conveyed 14.50 Kamla sub basin work and Sirrey sub basin on21.01.2015. Reply awaited. (ARP-47) 17 River Erosion management project in 14.61 03.11.2014 TEC accorded on 07.01.15 14.61 Dissang basin at Chitum and Niausa in Tissa river / Tissing (ARP-44) 18 FREM project at Yamgo River at Bene village 10 (ARP-34) State Govt. was intimated on12.01.2015 that BC ratio of 10.00 12.11.2013 project is less than 1. Doesnot qualify under FMP scheme 19 FREM Project in Disang basin at Banfera & TEC accorded and communicated to the state Govt. on 11.23 Wanu village (ARP-42) 11.23 12.11.2013 02.12.2014 20 FREM project in Buri Dehing Basin (ARP- TEC accorded and communicated to the state Govt. on 10.58 43) 10.58 12.11.2013 02.12.2014 21 Anti Erosion and Flood Protection work on 20.00 Sipu River at Aalo Revised DPR received on 07.11.2014. Observation sent 20.00 07.11.14 to State vide letter dated 21.01.2015. Reply awited 22 FREM in Desang Basin at Mopakhat and TEC accorded and communicated on to the State Govt. 11.58 Longhua village (ARP-41) 11.58 12.11.2013 02.12.2014 23 TEC accorded and communicated to the State Govt. on 10.08 Anti erosion work at Pachuk river (ARP-24) 10.08 29.10.2014 FMP works from Govt. Secondary School, Observations conveyed on 28.05.15. Reply received on 15 Pachin Colony to wire rope suspension 03.08.15 & 06.08.15. Further observations conveyed on 24 bridge at D Sector 15.00 26.05.15 21.09.15 590.66 176.45 10.00 312.21 92.00 3 Manipur 1 Development of Water Body and 627.23 17.12.2013 DPR received on 17.12.2013 and forwarded to Hyd 627.23 Improvind Drainage System at (NE) Dte on 23.12.2013. Comments on design Lamphelpat in Manipur aspects sent on 27.12.2013 and on Hydrological aspects sent on 27.01.2014. Revised DPR received on 21.04.2014. Revised DPR discussed with official of WRD, Manipur. and comments send on 20.01.2015.Reminded on 30.01.2015.Reply awaited.

2 Anti-erosion & flood control schemes on 1122.35 15-03-2013 DPR examined. Comments sent to State Goiverment 1122.35 various major rivers of Manipur river on 02.05.2013. Correcteed DPR received on basin 21.10.2013 in single copy is under examination.CE IFCD has been requested to submit one more copy of the DPR.Returned to State Govt on 30.12.14 as compliace is pending for more than one year. Reminded on 30.01.2015

3 Anti-erosion & flood control works along 359.77 15-03-2013 DPR examined. Comments sent to State Goiverment 359.77 major rivers/sreams flowing into Loktak on 02.05.2013. Correcteed DPR received on lake 21.10.2013 in single copy is under examination.CE IFCD has been requested to submit one more copy of the DPR.Returned to State Govt on 30.12.14 as compliace is pending for more than one year.Reminded on 30.01.2015

4 Control of water logging causing flood 54.13 15-03-2013 DPR examined. Comments sent to State Goiverment 54.13 hazards in and around drainage basin of on 02.05.2013. Correcteed DPR received on imphal sub-urban areas. 21.10.2013 in single copy is under examination.CE IFCD has been requested to submit one more copy of the DPR.Returned to State Govt on 30.12.14 as compliace is pending for more than one year.Reminded on 30.01.2015

5 Anti-erosion & flood control schemes on 45.29 15-03-2013 DPR examined. Comments sent to State Goiverment 45.29 various major rivers of Barak river basin on 02.05.2013. Correcteed DPR received on in Manipur 21.10.2013 in single copy is under examination.CE IFCD has been requested to submit one more copy of the DPR.Returned to State Govt on 30.12.14 as compliace is pending for more than one year.Reminded on 30.01.2015 State/UT wise details of Flood Management Project Proposals ( coordinated by CWC) during XII Plan inculding spillovers as on 21.03.2016

Sl Estt. Cost Date of Under Name of works/scheme Status of examination Cleared Returned Awaited No. (Rs. In Cr) Receipt examination 6 Anti-erosion & flood control schemes on 17.63 15-03-2013 comments send on 21.08.2013. Modifeied DPR 17.63 various major rivers of Chindwin/Yu received on 21.10.2013. State Government asked to river submit one more copy of the DPR. CE IFCD has been requested to submit one more copy of the DPR.Returned to State Govt on 30.12.14 as compliace is pending for more than one year.Reminded on 30.01.2015 2226.4 0 0 0 1599.17 627.23 0

4 Meghalaya

1 Flood Control on Flash Flood along the 42.40 25.03.2013 DPR received on 25.03.2013.The comments of Hyd 42.4 rivers of Wahumkhrah and Umshyrpi, (NE) along with the comments of FMP has been Shillong forwarded to the State government of Meghalya vide letter dated 03.04.2014. The compliance from state government received vide letter dated 28.08.2014. scheme examined and comments were furnished on 12.11.2014. The state Government submitted the revised DPR vide letter dated 16.02.2015. the DPR has been examined and forwarded to CA (HWF) vide letter dated 16.04.2015. CA (HWF) finilized the cost of RS. 48.7035 cr vide letter dated 28.04.2015. TAC note was approved by Member(RM). comments were communicated to State Govt on 28.09.15. Reply awaited.

2 Construction of embankment along the 25.32 14-03-2013 Dir M&A submitted observation to PWD, Meghlaya 25.32 river bank of Jingiram for protection of on 01.10.2013 . Conveyed to submit the revised DPR Phersakandi&Solartek village from flood on 12.08.2014. Reminded on 30.01.2015.Revised and erosion of river Jinjiram & DPR awaited Brahmaputra 3 Survey & investigation including 63.36 14-03-2013 Dir M&A submitted observation to PWD, Meghlaya 63.36 feasibility report and prepartation of DPR on 01.10.2013 reply awaited.Modified DPR of RS for protefction of Williamnagar town from 67.6736 crore received at M&A on 21.01.2014 . erosion of river Simsang Further observation conveyed on 12.08.2014.Reminded on 30.01.2015. Reply awaited. 4 Construction of embankment along left 205.489 14-03-2013 Proposal preliminarily examined/scrutinized in 205.489 bank of river jinjiram from Phulbari to Director, M&A office and observations sent vide letter Nidanpur and protection of banks of dated 14.08.2013 for compliance.New proposal river Rongai by Providing backwater amounting to Rs. 205.46 Cr. Some minor embankment observations alon with request to submit copies of DPR conveyed on 14.08.2014. Modified DPR received on 19.06.2015. Forwarded to CWC HQ on 30.06.2015 . Received in CWC HQ in July 2015 forwarded to BCD (E&NE) Dte and Hydrology Dte for examination. Requested State govt for additional copies of DPR. comments of BCD Dte have been forwarded to State Govt on 02.09.15. comments of Hyd(NE) and FMP Dte have been sent to State Govt on 27.01.16. Compliance to letter dated 02.09.15 and 27.01.16 awaited

5 Raising of KolongkinBundh due to 88.48 14-03-2013 Dir M&A submitted observation to PWD, Meghlaya 88.48 change in HFL of river Jinjiram on 01.10.2013. the cost of the proposal has been reduced to RS. 38.03 . Observation conveyed on 12.08.2014. Reminded on 30.01.2015. Reply awaited. 6 Protection of Munai Village from erosion 12.78 14-03-2013 Proposal scrutinized in Director, M&A office and 12.78 of River Mula etc. observation sent vide letter dated 26-08-2013 fro compliance. Reminder issued on 20.08.2014. Reply awatied. Return to State Govt. on 31.12.2014 as the compliance from State Govt is pending for more than one Year. Reminded on 30.01.15

7 Khangmusna Minor Irrigation Project 0.98386 Under Observation 0.98386 8 RRR of Pynthor MIS water body 1.7856 Under Observation 1.7856 9 RRR of Goragre MIS water body 1.04321 Under Observation 1.0432 441.64 0.00 12.78 425.05 3.81 5 Mizoram 1 Pala river anti erosion scheme , Phura 24.39 09.09.2013 Observation conveyed on 18.12.2013. Revised DPR 24.39 received on 21.03.2014. further observation conveyed on 18.09.2014. Reply received on 09.12.2014, not fully complied, reminder issued on 16.12.2014.Partial reply submitted on 23.01.15. request for full compliance on 04.02.15 Replies received on 29.06.2015. Forwarded to FMO on 30.06.2015. Forwarded to Hydrology (NE) on 22.07.2015.Under examination.

2 Phaisen river anti ersoion schem, Champai 6.48 09.09.2013 6.48 As the scheme costing less than 10 corre are not eligible for funding under FMP. State Govt. has been requested on 18.12.2013 to intimate about interstate implication or proposal of state govt for central funding other than FMP. Reminded on 30.01.2015. Reply awaited State/UT wise details of Flood Management Project Proposals ( coordinated by CWC) during XII Plan inculding spillovers as on 21.03.2016

Sl Estt. Cost Date of Under Name of works/scheme Status of examination Cleared Returned Awaited No. (Rs. In Cr) Receipt examination 3 Tuiphai river anti erosion scheme, 5.27 06.09.2013 5.27 N.Vanlaiphai As the scheme costing less than 10 corre are not eligible for funding under FMP. State Govt. has been requested on 18.12.2013 to intimate about interstate implication or proposal of state govt for central funding other than FMP. Reminded on 30.01.2015. Reply awaited 4 Zuva river anti erosoin scheme, Leng 9.30 06.09.2013 9.30 As the scheme costing less than 10 corre are not eligible for funding under FMP. State Govt. has been requested on 18.12.2013 to intimate about interstate implication or proposal of state govt for central funding other than FMP. Reminded on 30.01.2015 .Reply awaited Sub Total 45.44 0.00 0.00 21.05 24.39 6 Nagaland 1 Flood management works on Both banks of 123 29.10.2013 DPR received vide CWC letter dated 26.09.2013 and the 123 Dhansiri and Diphu river, Dimapur, Nagaland comments has been furnished to State Government vide letter dated 14.11.2013. The state governement has not submitted the complliance. Reminder isseued on 24.06.2014 and 05.02.2015. Revised DPR received on 13.07.2015. forwarded to regional office on 13.07.15 for Preliminary examination. B&BBO forwarded the DPR to M&A, Guwahati on 04.08.15. obseravtion sent to State Govt. on 07.08.15. Reply awaited

2 Anti Erosion wrok for protection of Zutovi, 12.45 02-06-2013 Techno-economic clearance conveyed on 25.11.2013 12.45 Pimla&Kiyeto village areas 3 Anti Erosion work for protection of Rengmapani, 12.48 02-06-2013 Techno-economic clearance conveyed on 25.11.2013 12.48 K.Hetoi&Hozukhe village areas 4 Anti Erosion work for protection of Kayevi, 12.46 02-06-2013 Techno-economic clearance conveyed on 25.11.2013 12.46 Shokhuvi, Vidima, Khriezephe&Singrijan village areas 5 Memo of Work for protection of erosion from 3.09 02-06-2013 Techno-economic clearance conveyed on 25.11.2013 3.09 Maratchu river at Merapani, Wokha, Nagaland

6 Protection of erosion from stream at NST 1.43 02-06-2013 Techno-economic clearance conveyed on 25.11.2013 1.43 Colony,Wokha, Nagaland 7 Anti Erosion work for protection of Tizit Town 8.96 02-06-2013 Techno-economic clearance conveyed on 25.11.2013 8.96 from erosion of Tizit river 8 Memo of work forprotection of erosion from 1.31 02-06-2013 Techno-economic clearance conveyed on 25.11.2013 1.31 steam at Veterinary Colony, Wokha, Nagaland

9 Protection measaures in Tsutsung Valley 7.02 02-06-2013 After review, DPR returned to State Govt on 29-04-2013. 7.02 Compliance received on 13.11.2013.Scheme has been acknowledged of not having any interstate implication by state govt. on 04.12.14. Declared ineligible for funding Under FMP and same intimated to state govt on 17.12.14

10 Integrated catchement treatment of upper Sidzu 12.4246 26.02.2014 12.4246 river Kohima Cancelled vide letter SC/NWM (FMP-C80)-1/2003 dated 19.11.14

11 Integrated catchement treatment Menung river 12.3386 26..02.2014 12.3386 Mokokchung Cancelled vide letter SC/NWM (FMP-C80)-1/2003 dated 19.11.14

12 Integrated catchement treatment of Nanga 12.4718 26..02.2014 12.4718 Ghoki river , Zunheboto Cancelled vide letter SC/NWM (FMP-C80)-1/2003 dated 19.11.14

13 Protection of Tuli town from erosion of Milak 10.12195 14.10.2014 Revised DPR received on 20.11.14. observation of CWC sent 10.2195 river Phase -II Mokokchung on 16.01.2015. Partial Reply Received on 03.02.15. Requested for full reply on 04.02.15. Reply received on 03.03.15. further observation conveyed on 29.05.15. Replies received on 16.06.2015. Further observation conveyed on 22.06.15 and 24.06.2015. Reply received on 03.08.2015. TEC clearance accorded vide B&BBO letter dated 08.09.2015

14 Doyang Catchment area treatment at Chuben 12.3883 20.11.14 Observation Conveyed on 23.01.15. Reply received on 12.3883 Sub-Watershed 03.02.15. Further observation conveyed on 25.02.15. Reply received on 25.03.15. Further observations conveyed on 27.05.15. Reply received on 07.10.15. Further observations conveyed on 19.10.15 15 Integrated Tizu Catchment Area Treatment at 11.0223 20.11.14 Revised DPR received on 20.11.14. observation of CWC sent 11.0223 Thiza sub-watershed. on .09.01.2015. Reply received on 25.03.15. Further observations conveyed on 27.05.15. Reply received on 07.10.15. Further observations conveyed on 19.10.15 16 Integrated Dikhu Catchment area treatment at 12.12 20.11.14 After preliminary observation of CWC sent on 09.01.2015. Reply 12.12 Pachi sub-watershed. received on 25.03.15. Further observations conveyed on 27.05.15. Reply received on 07.10.15. Further observations conveyed on 19.10.15 17 Integrated Zungki catchment area treatment at 12.0373 20.11.14 After preliminary observation of CWC sent on 09.01.2015.Reply 12.0373 Yai sub-watershed. received on 25.03.15. Further observations conveyed on 27.05.15. Reply received on 07.10.15. Further observations conveyed on 19.10.15 18 Integrated Milak catchment area treatment at 12.3386 20.11.14 After preliminary observation of CWC sent on 09.01.2015. Reply 12.3039 Menung sub-watershed. received on 25.03.15. Further observations conveyed on 27.05.15. Reply received on 07.10.15. Further observations conveyed on 19.10.15 19 Integrated Dhansiri catchment area treatment at 12.2379 20.11.14 After preliminary observation of CWC sent on 09.01.2015.Reply 12.2379 Dzuma sub-watershed. received on 25.03.15. Further observations conveyed on 27.05.15. Reply received on 07.10.15. Further observations conveyed on 19.10.15 20 Integrated Zungki catchment area treatment at 12.0425 20.11.14 After preliminary observation of CWC sent on 09.01.2015.Reply 12.0425 Tepe sub-watershed. received on 25.03.15. Further observations conveyed on 27.05.15. Reply received on 07.10.15. Further observations conveyed on 19.10.15 21 Integrated Dhansiri catchment area treatment at 12.2615 20.11.14 After preliminary observation of CWC sent on 09.01.2015.Reply 12.2615 Nzu sub-watershed received on 25.03.15. Further observations conveyed on 27.05.15. Reply received on 07.10.15. Further observations conveyed on 19.10.15 22 Integrated Dikhu catchment area treatment at 12.109 20.11.14 After preliminary observation of CWC sent on 09.01.2015.Reply 12.109 Tipui/Tokok sub-watershed. received on 25.03.15. Further observations conveyed on 27.05.15. Reply received on 07.10.15. Further observations conveyed on 19.10.15 23 Integrated Dhansiri catchment area treatment at 12.4689 20.11.14 After preliminary observation of CWC sent on 09.01.2015. Reply 12.4689 Diphupani sub-watershed. received on 25.03.15. Further observations conveyed on 27.05.15. Reply received on 07.10.15. Further observations conveyed on 19.10.15 State/UT wise details of Flood Management Project Proposals ( coordinated by CWC) during XII Plan inculding spillovers as on 21.03.2016

Sl Estt. Cost Date of Under Name of works/scheme Status of examination Cleared Returned Awaited No. (Rs. In Cr) Receipt examination 24 Development of Dimapur Airport drainage , Ph- 10.06 14.10.2014 observations sent on 18.12.14,Partial reply received on 10.06 IV, Dimapur 03.02.15. Requested for full reply on 03.02.15 . Full reply received on 03.03.15.complete compliance received on 07.10.15. under examination 25 Observation conveyed on 23.01.15. Reply received on 03.02.15. Mitigation of Flood & River erosion management Observation conveyed on 25.2.15. Reply received on 25.3.15. Further in Nanga Ghoki River a tributary of river Dikhu 12.4718 20.11.14 observations conveyed on 27.5.15. Reply received on 07.10.15. 12.4718 through integrated catchment area treatment Further observations conveyed on 19.10.15

26 Observation conveyed on 23.01.15. Reply received on 03.02.15. Mitigation of Flood & River erosion management Observation conveyed on 25.2.15. Reply received on 25.3.15. Further in Upper Sidzu River a tributary of river Doyang 12.4246 26.02.14 observations conveyed on 27.5.15. Reply received on 07.10.15. 12.4246 through integrated catchment area treatment Further observations conveyed on 19.10.15

385.53965 62.3995 44.255 268.888 10.06 7 Sikkim 1 Storm Water Drainage System/Jhoras 95.38 05.08.2013 DPR received on 05.08.2013 and submitted to Hyd 95.38 HQ Training Work in and around Gangtok” (NE) on 07.08.2013. Hyd (NE) furnished comments at the Estimated Cost: Rs. 95.38 crore vide letter dated 28.11.2013 and the same was forwarded on 03.12.2013.Reply awaited. Reminded on 25.02.2016 2 River training work along Rani Khola 14.595 Cleared by CWC and approved by IMC in its second 14.595 below 32 numbers bazar and Sikkim meeting held on 03.03.2014. Investment clearance Supreme Factory and Golitar in East on 26.09.2013 Sikkim. 3 River training work along Lasher Chu at 13.9966 Cleared by CWC and approved by IMC in its second 13.9966 Thanggu/ Thangchund along Teesta meeting held on 03.03.2014. investment clearance on River at Yanthang, North Sikkim. 25.09.2013

4 River training work along River 14.7062 Cleared by CWC and approved by IMC in its second 14.7062 BakchaKhola under KabiLungchok meeting held on 03.03.2014. investment clearance on constituency North Sikkim. 25.09.2013 5 River Training work along River Teesta at 16.8373 Cleared by CWC and approved by IMC in its second 16.8373 Kerabari and below beer factory at meeting held on 03.03.2014. investment clearance on Mellin, South Sikkim 25.09.2013 6 River Training work/ Anti-Erosion works 14.6149 Cleared by CWC and approved by IMC in its second 14.6149 at BaniyaKhola under BerfungZaroong. meeting held on 03.03.2014. investment clearance on 25.09.2013 7 River Training work/ Anti_Erosion works 14.6136 Cleared by CWC and approved by IMC in its second 14.6136 along river Teesta and its tributaries meeting held on 03.03.2014. investment clearance on .Ramphokkhola, South Sikkim 25.09.2013

8 River training works at PolokHotspring 14.8201 Cleared by CWC and approved by IMC in its second 14.8201 along River Rangit, South Sikkim meeting held on 03.03.2014. investment clearance on 25.09.2013

9 Landslide below RabongSangmoo at 13.8914 Cleared by CWC and approved by IMC in its second 13.8914 RangmooKhola South Sikkim meeting held on 03.03.2014. investment clearance on 25.09.2013 10 River training Work/ Anti-Erosion works 14.8319 Cleared by CWC and approved by IMC in its second 14.8319 along River Rangit and its tributaries meeting held on 03.03.2014. investment clearance on LingdingRalang South Sikkim. 25.09.2013

11 River Training works/Anti-Erosion works 14.3996 Cleared by CWC and approved by IMC in its second 14.3996 along River Teesta and its tributaries meeting held on 03.03.2014. investment clearance on Kaw Khola, South Sikkim 25.09.2013

12 River Training works/Anti-Erosion works 14.3588 Cleared by CWC and approved by IMC in its second 14.3588 along River Rangit and its tributaries meeting held on 03.03.2014. investment clearance on DharGaonBorong South Sikkim. 25.09.2013

13 River Training works /Anti-Erosion 14.7728 Cleared by CWC and approved by IMC in its second 14.7728 works along river Teesta and its meeting held on 03.03.2014. investment clearance on tributaries KhundrukeyKhola, South 25.09.2013 Sikkim 14 River training works along ReliKhola, 15.4586 Cleared by CWC and approved by IMC in its second 15.4586 Nar Khola, Rathangchu and Rangit River meeting held on 03.03.2014. investment clearance on in West Sikkim 25.09.2013

15 River Training works along RangpoKhola 14.2732 Cleared by CWC and approved by IMC in its second 14.2732 at Rongli bazar in East Sikkim meeting held on 03.03.2014. investment clearance on 25.09.2013 16 River Training/Jhora Training /Anti- 14.3474 Cleared by CWC and approved by IMC in its second 14.3474 Erosion works along Lachung Chu meeting held on 03.03.2014. investment clearance on PhakunderLachungZumsa North Sikkim 25.09.2013

17 River Training works along River Teesta 23.88 Cleared by CWC and approved by IMC in its second 23.88 and its tributaries in North Sikkim meeting held on 03.03.2014. investment clearance on 25.09.2013 18 River Training Works along River Teesta 17 Cleared by CWC and approved by IMC in its second 17 below Sangkalang, Dzongu & RTW along meeting held on 03.03.2014. investment clearance on River Kanaka below Lingza and its 25.09.2013 joining villages Dzongu in North sikkim

Subtotal 356.7774 261.3974 0 95.38 0 8 Tripura 1 54.9958 Cleared by AC-MOWR in its meeting held on 13.09.20.IC 54.9958 Anti Erosion Work along the bank of river by PC accorded vide letter no. 12(1)/23/2006-WR Gumti for protection of vulnerable locations dated 14.02.2014 from Dalak Samatal Para to Durgapur under Amarpur, Udaipur and Sonamura Sub Division of South Tripura & West Tripura District (Tripura)”. State/UT wise details of Flood Management Project Proposals ( coordinated by CWC) during XII Plan inculding spillovers as on 21.03.2016

Sl Estt. Cost Date of Under Name of works/scheme Status of examination Cleared Returned Awaited No. (Rs. In Cr) Receipt examination 2 42.9565 Cleared by AC-MOWR in its meeting held on 13.09.20.IC 42.9565 by PC accorded vide letter no. 12(1)/23/2006-WR Anti Erosion Work along the bank of river dated 14.02.2014 Haora for protection of vulnerable locations from Champaknager to Baldakhal under Sadar Sub Division of West Tripura District 3 Anti erosion work along the bank of river 91.0261 Cleared by AC-MOWR in its meeting held on 13.09.20.IC 91.0261 Khowai for protection of vulnerable by PC accorded vide letter no. 12(1)/23/2006-WR locations from Netajinagar (Brahma cherra) dated 14.02.2014 to Banglahour under Teliamura Sub- Division and from South L.N.Pur to Paharmura Bridge under Khowai Sub- Division of West Tripura District

4 RRR of Rudrasagar lake in Tripura 84.92 15.02.2016 under observation 84.92 Sub Total 273.8984 188.9784 0 0 84.92 9 Brahmaputra Board 1 Restoration of Lohit and Dibang rivers to their 381.18 18.04.2013 The comments were sent to Br. Board vide letter dated 381.18 origional courses at Dholla Hathighully 28.11.2014 30.01.2014. Revised Report with an estimated cost of Rs. 363.18 crore received on 21.05.2014. The same was forwarded to Hyd (NE) vide letter dated 23.05.2014. Fresh comments on DPR were conveyed vide letter dated 23.06.2014. Br. Board has submitted modified report on 18.11.2014. Revised DPR forwarded to Emb(E&NE) and Hyd(NE) on 01.01.2015 for examination. Emb(E&NE) examined the DPR and furnished the comments on 16.02.2015 and the same were forwarded to the BB on 23.02.2015. The same was reminded vide letter dated 31.03.2015.Reply received from Br. Board and sent to Design unit (Embk, E&NE). Hyd (NE) Dte has made comments which have been forwarded to Br. Board on 16.06.15. Embk (E&NE) reviewed replies of Br. Board and further comments forwarded to Br. Board vide letter dated June 2015. Reply awaited. Reminded on 25.02.2016

2 Protection of Majuli Island from flood and erosion 272.17 22.07.2013 . The Hyd (NE) furnished its comments vide letter dated 272.17 of river Brahmaputra –Phase-IV 04.10.2013. The comments of Hyd (NE) and FMP Directotrae were forwarded to Br. Board vide letter dated 12.12.2013. Reply received from Brahamputra Board on 04.01.2014. Hyd (NE) conveyed clearance vide letter dated 10.02.2014. FMP Dte examiend the DPR and comments sent on 03.07.2014. Br. Board submitted compliance vide letter dated 10.10.2014. FMP examined the DPR and forwarded to CA (HWF) vide letter dated 23.12.2014. CA (HWF) examined the DPR and finilized the cost vide letter dated 12.03.2015. the FMP Dte again examined ther DPR and commments send on 30.03.2015.Br. Board responded vide letter dated 18.05.2015. DPR has been returned to Br. Board with comments to prepare it keeping in view recommendation made by Standing committee of experts during its 10th visit to Majuli Island on May 2015. based on recommendation of standing committee, DPR is broken into 2 parts and submitted on 25.02.2016. Immediate interim commnets on DPR sent to BB on 26.02.2016. part A accepted and part B returned. complaince received on 26.02.15. sent to Cost Appraisal (HWF) on 26.02.2015. comments from cost apprasial received on 29.02.16. a note has been sent to MoWR on 01.03.16 for consideration

3 Protection of Manakchar ,Klair & Alga 23.08 04.04.2012 Cleared by CWC 23.08 internation border area from erosion of river Brahamaputra , Dhubri 4 Protection of Nagarijuli, Rangia Town 36.77 04-04-2012 Returned to B/Board on 30.12.2014 as compliance is pending 36.77 &Mukalamua/Barbhag Area from flood and for more than one year. Reminded on 30.01.15. erosion of river Puthimari (Barnadi) Phase-II 5 Amjur Drainage Development scheme 56.37 01.11.2013 Observation sent to B Board on 16.12.2013 for 56.37 compliance. Modified received on 19.02.2014. furter observation conyed on 19.08.2014. compliance received on 10.12.14, forwarded to Hydrology (E&NE) on 26.05.2015 and BCD (E&NE) on 15.06.15.BCD (E&NE) has cleared the scheme.Forwarded to Embankment (E&NE).Response from Embankment(E&NE) received vide letter dated 08.09.2015.COmments sent to BB vide letter dated 06.10.2015.Reply awaited.

6 Bharbhag Drainage Development Scheme , 14.8 04.04.2012 Cleared by CWC 14.8 NalBari 7 Nelli Drainage Dev. Scheme-A 13.25 23-07-2013 comments sent to Brahmaputra Board on dated 29-04-2013. 13.25 Reply received on 09-09-2013 . Further observation communicated on 31.07.2014. Reply received on 06.05.15. further observation conveyed on 11.05.15.Reply awaited.

8 Nelli Drainage Dev. Scheme-B 14.5989 11.02.2016 Under observation 14.5989 9 Pola Drainage Dev. Scheme 21.05 13-02-2012 Proposal examined & after discussion, B/Board has been 21.05 requested to submit the revised DPR. Revised DPR amounting to Rs. 21.05 Cr. Received on 29/07/2013 Further observation conveyed on 07.08.2014. Reply received on 22.01.15. Requested BB to submit copies of updated DPR on 29.05.15.Updated DPR received on 24.09.15. Further observations conveyed on 26.10.15 10 Revised Estimate for Dharmangar Draingage 20.21 16-07-2013 Revised DPR amounting to Rs. 20.21 Cr. Rcvd on 28.11.2013 20.21 development Scheme in state of Tripura at M&A Dte. Observation conveyed on 18.07.2014. Reminded on 30.01.15. Reply awaited 11 Kalamonizan Drainage Dev. Scheme 3.07 13-02-2012 TEC accorded on 16.03.15 3.07 12 Jengrai Drainage Dev. Scheme 4.90 13-02-2012 Cleared by CWC on 25.11.13 4.90 13 Protection of Masalabari Intl. Border Area from 5.76 07-03-2012 Cleared by CWC on 25.11.13 5.76 erosion of river Brahmaputra State/UT wise details of Flood Management Project Proposals ( coordinated by CWC) during XII Plan inculding spillovers as on 21.03.2016

Sl Estt. Cost Date of Under Name of works/scheme Status of examination Cleared Returned Awaited No. (Rs. In Cr) Receipt examination 14 Protection of Balat Village from the erosion of 10.18 30-07-2012 Cleared by CWC on 11.01.13 10.18 river Umngi

15 Larsing Drainage Dev. Scheme 7.20 23-07-2012 Compliance received on 20.10.14. Further observations conveyed 7.2 on31.12.14. Reply received on 21.05.15. Cost has been revised to Rs. 9.8816 crore. Requested to submit 3 sets of fresh DPR on 29.05.15. Further observations sent on 17.09.15. Reply awaited. 16 Anti-erosion measures for bank protection of 4.43 23-03-2013 Cleared on 06.11.2013 4.43 Bhajaner Charra Nishiganj 17 Bank Protective work to Bhogdebri area on the 5.39 23-03-2013 Cleared by CWC on 06.11.2013 5.39 right bank of river Mansai in P.S. Sitalkuchi

18 Anti erosion measures for protection to 5.26 14.02.2014 Proposal received on 14.02.2013 in CWC from MoWR vide 5.26 Padumani and Na-chumanai area on account of letter dated 03.02.2014. The proposla has been submitted to flood s in Padumaninala -distributry branch of CE, B&BBO, Shillong. Under examination. Noa Dehing 19 Pota Kollong Drainage Development Scheeme , 3.95 1.11.2013 Obesevation conveyed on 19.08.2014. Reply received on 3.95 Naogaon 22.04.15. further observation conveyed on 11.05.15 Compliance awaited 20 DPR on Demow Drainage Development 22.2315 5.11.15 Dir, M&A received DPR on 5.11.2015 for Techno -economical appraisal 22.2315 Scheme 21 Conversion of the existing Tie Bund across the All the schemes costing less than 10 Crores and not eligible for spill channel of river Dibang from ch. 480m to ch. funding under FMP. Dir M&A requested the State Govt. to intimate 2550m into a full-fledged embankment at about inter-state implication or proposal of State Govt. for central funding other than FMP in r/o these schemes so that these schemes Bahbari- Phase-V. 9.22 9.22 may be appraised for according techno-economic clearance by regional office of CWC. Further observation of Dir M&A was communicated to the CE-I, B/Board vide letter dtd. 18/09/2014. Reply is awaited. Sub Total 935.07 71.61 36.77 512.43 314.26 10 West Bengal 1 Bank protection work along the both banks 41.44 07.05.2013 The comments on Hydrological aspects have been sent to 41.44 of river Jaldhaka, Mansai and Dharala State government of West Bengal vide letter dated (tributaries of river Jaldhaka) at South 29.01.2014. The same was reminded vide letter dated Baraibari and Sonatali at East Kursamari 17.06.2014. The comments on the design aspects were Hardevpur, Chhederjhar in P.S Kotawali, communicated vide letter dated 17.11.2014. Reminder Kamatapur and Uttar Singimari at sent on 04.08.15. Reply awaited. Reminded on Natunbosh & 538Singimari in P.S Sitai and 25.02.2016 Dinhata and Madnakura; Protection work of Baro Adabari area, protection work of Baro Bangla and Jatigara village and 8 other reaches in river Dudua, Mujnai and Gilandi and reaches in river Sutunga and Dharala in P.S Sitai, Dinhata, Mathabhanga, Sitalkuchi and Ghokshadanga district Cooch Behar (Zone-27 Nos) Zone-I to XXVII

2 Construction of 3 nos long Premeable 44.73 06.05.2013 The comments on Hydrological aspects sent on 44.73 Deflector, strengtheningand re-sectioning of 21.01.2014. The state government has not submitted embankment on the both banks of river the complliance. Further, comments on the design teesta at Rangdhamali, Chumukdanga, aspects were send vide letter dated 27.01.2014. The same Banabasti, Mandalghat-Bibiganj, Bibiganj- was reminded vide letter dated 17.06.2014 and Jharsingheswar, Burigram, Rangdhamali to 05.11.2014. Reminder sent on 04.08.15.Reply awaited. Burigram, Mekhliganj town protective Reminded on 25.02.2016 embankment, Baikanthapur forest area and in between 7th and 10th mile of NH31, in PS Jalpiguri, Rajganj, Haldibari and Matigara Bhaktinagar disctrict Jalpaiguri, Cooch Behar and Darjeeling (zone-4 nos) under Jalpaiguri and Siliguri Irrigation Divesion.

3 Strengthening of Kutchlibari embankment 28.23 12.05.2012 Observations communicated to the State Govt. on 28.23 on the left bank of River Teesta in West 11.01.2013 for compliance. Reply awaited. Bengal 4 Bank protection work at Changmari 6.2456 03.01.2014 6.2456 Jhaljhali area along the left bank of river M&A, Kolkata submitted the DPR to this office vide letter Kaljani in P.S.- Tufanganj, Dist. Cooch dated 18.12.2015 for perusal and further necessary Behar. (B.P. No.- 987/11R to 988) under approval. Comments were sent to M&A, Kolkata vide RMBA letter dated 07.03.2016 5 5.5775 03.01.2014 5.5775 Bank protection work at Talai area along the M&A, Kolkata submitted the DPR to this office vide letter left bank of river Kaljani in P.S.- Tufanganj, dated 18.12.2015 for perusal and further necessary Dist. Cooch Behar. (B.P. No.- 996/12-S approval. Comments were sent to M&A, Kolkata vide Talai) under RMBA letter dated 07.03.2016 6 11.5069 03.01.2014 11.5069 Bank protection work at Gitaldaha BOP M&A, Kolkata submitted the DPR to this office vide letter (Bharampaisti Ghosh Para) along the L/B of dated 18.12.2015 for perusal and further necessary river Dharala, Dist. Cooch Behar. (B.P. No.- approval. Comments were sent to M&A, Kolkata vide 926 to 928) under RMBA letter dated 07.03.2016 7 Bank protection work at Panchodhoji BOP 7.858 03.01.2014 M&A, Kolkata submitted the DPR to this office vide letter 7.858 along the L/B of river Dharala, in P.S. dated 18.12.2015 for perusal and further necessary Dinhata, Dist. Cooch Behar. (B.P. No.- 925 approval. Comments were sent to M&A, Kolkata vide to 926) under RMBA letter dated 07.03.2016 145.588 0 0 114.4 31.188 11 Karnatka

1 Flood Protection Works along the banks of Tunga DPR was received on 18.11.2009 and examined in CWC. The River in Shimoga District of Karnataka State (Kar- proposal has been accepted in the 107th meeting of TAC-MoWR 55.18 18.11.2009 55.18 2) held on 27.10.2010. Investment Clearance has been accorded by the Planning Commission vide letter dated 16.03.2011 and State/UT wise details of Flood Management Project Proposals ( coordinated by CWC) during XII Plan inculding spillovers as on 21.03.2016

Sl Estt. Cost Date of Under Name of works/scheme Status of examination Cleared Returned Awaited No. (Rs. In Cr) Receipt examination 2 Construction of retaining wall along the Banks of Hemavathi river in Holenarsipura taluk of Hassan District of Karnataka State (Kar-1) DPR was received on 18.11.2009 and examined in CWC. The proposal was accepted in the 107th meeting of TAC-MoWR held on 27.10.2010. Investment Clearance was accorded by the Planning Commission vide letter dated 16.03.2011 and was scheduled to be completed by 31 March 2013.Funds have been provided to the scheme in the 7th Empowered Committee meeting held on 18.08.2011. An amount of 600 lakhs was 25.48 18.11.2009 released vide Ministry of Finance letter dated 23/03/2012. 25.48 Monitoring report for the year 2012-13 for the period ending June 2012 was received in this office on 20/09/2012. However, the shortfall of expenditure as on 01/06/2012 was Rs. 2.47 crores. Hence the case was not processed for the release of next installment. Observations on FMP-2 and FMP-3 for the quarter ending December 2013 ,received in this office in February,2014 was sent to CE, Mon(S),CWC vide letter dated 20/05/2014. Further, CE, Mon(S), CWC was requested to send the proposal for CA amounting to Rs. 13.11 crores.Cleared 3 Flood Protection Works for Bhadra River at DPR was received in CWC on 2.08.2010 and examined in CWC. Bhadrabathi Town of Shimoga District in The proposal was accepted in 110th meeting of TAC-MoWR Karnataka State held on 20.07.2011. Investment clearance from Planning Commission, was received vide letter dated 8.09.2011 and was scheduled to be completed by 31 March 2013. FMP-I and other certificates after completing all formalities were sent to MoWR 86.16 2.08.2010 on 30.11.2011. However, the project was not included under 86.16 FMP by Empowered Committee. The proposal for inclusion of the scheme under IMC-FMP was received vide letter dated 24/02/2014.The comments on the same was sent vide this office letter dated 19/03/2014. Proposal received from CE (mon) south, submitted to MoWR on 13.05.2015 for approval of IMC-FMP.Cleared 4 Flood Protection Works for River Hemavathi at Banakal Town and six villages of Mudigere Taluk DPR was received in CWC on 2.08.2010. After examination in of Chikkamagalur District in Karnataka State CWC, the proposal has been accepted in the 112th meeting of TAC-MoWR held on 14.09.2011. Investment clearance was given by the Planning Commission vide its letter dated 28.11.2011 and was scheduled to be completed by 31 March 47.56 2.08.2010 2013 .FMP-I and other certificates after completing all 47.56 formalities were sent to MoWR on 14.12.2011. However, the project was not included under FMP by Empowered Committee. The proposal for inclusion of the scheme under IMC-FMP was received vide letter dated 24/02/2014.The comments on the same was sent vide this office letter dated 03/04/2014. Proposal received from CE (mon) south, submitted to MoWR on 27.05.2015 for approval of IMC-FMP.Cleared 5 Flood Protection Works for Kabini River near Suttur Town of Mysore District of Karnataka DPR was received on 2.08.2010 and examined in CWC. The State proposal has been accepted in the 111th meeting of TAC- MoWR held on 17.08.2011. Investment Clearance from Planning Commission was accorded vide letter dated 8.09.2011 and was scheduled to be completed by 31 March 2012. FMP-I and other certificates, after completing all formalities, were sent to MoWR 26.93 2.08.2010 on 30.11.2011. CE, Mon(S), CWC was requested to send FMP-1 26.93 vide letter dated 9-08-2012 for submitting the proposal to MoWR for EC clearance. However, the project was not included under FMP by Empowered Committee. The proposal for inclusion of the scheme under IMC-FMP was received vide letter dated 24/02/2014.The comments on the same was sent vide this office letter dated 14/03/2014. Proposal received from CE (mon) south, submitted to MoWR on 13.05.2015 for approval of IMC-FMP.c leared 6 Flood Protection Works for Ghataprabha River at DPR was received on 2.08.2010 and examined in CWC. The Right Bank at Gokak Town in Belgaum District of th Karnataka State proposal was accepted in the 112 meeting of TAC-MoWR held on 14.09.2011. Investment clearance from the Planning Commission was given vide letter dated 15/12/2011 and was scheduled to be completed by 31 March 2013. The project was 34.07 2.08.2010 not included under FMP by Empowered Committee. The 34.07 proposal for inclusion of the scheme under IMC-FMP was received vide letter dated 24/02/2014.The comments on the same was sent vide this office letter dated 11/03/2014. After receiving the response for the same, the proposal was sent to MoWR vide letter dated 11/08/2014 for consideration of the IMC-FMP. Cleared State/UT wise details of Flood Management Project Proposals ( coordinated by CWC) during XII Plan inculding spillovers as on 21.03.2016

Sl Estt. Cost Date of Under Name of works/scheme Status of examination Cleared Returned Awaited No. (Rs. In Cr) Receipt examination 7 Flood Protection Works to Varada River in 70.63 09.05.2011 DPR was received in CWC on 9.05.2011 and was examined in 70.63 Hangal Taluk of Haveri District of Karnataka the UT&SS Dte. Comments of the UT&SS Dte were sent to the State Government of Karnataka on 30.05.2011. The compliance of observations of UT&SS Dte were received on 28.06.2011 which were examined. The copies of DPRs were then sent to Chief Engineer (NBO), Hydrology (S) Dte and Cost Appraisal (HW&F) Dte on the same day. The letter of finalized hydrology of the scheme was received on 13.07.2011 from Hydrology (S) Dte. The comments from Director (SSPH) were received on 18.07.2011 and sent to the State Government for compliance. The compliance of the observations of Director (SSPH) from the State Government was received on 24.08.2011 and sent to Director (SSPH) for examination. Consequently, reply of Director (SSPH) was received on 10.10.2011, which was sent to Secretary, WRD on 10.10.2011. The response of Govt. of Karnataka was received on 14.10.2011, which was sent to Director (SSPH) on 14.10.2011. The drawings as discussed with the State Govt officials were sent to Director (SSPH) on 8.11.2011. Consequently, the approval from SSPH Dte was received on 9.11.2011 which was intimated to the Government of Karnataka on 11.11.2011 with the request to submit the copies of the revised DPR. Copies of the revised DPRs were received on dated 02/02/2012.Subsequently, observations on the revised DPRs were sent to the Govt of Karnataka on 13/02/2012 and 15/02/2012. The opinion of SSPH on Design aspect was obtained and communicated to State Government vide letter dated 5/9/2012. A reminder for sending the revised DPR was also sent on 19/12/2012 and 05/04/2013. Reply Awaited 8 Flood Protection Works for Ghataprabha River at DPR was received on 2.08.210 in CWC. The proposal was techno- Mudhol Town in Bagalkot District of Karnataka economically cleared by Chief Engineer, Monitoring (South), CWC. State, Investment Clearance has been accorded by the Planning Commission vide letter dated 17.08.2011 and was scheduled to be completed by 31 March 2013 .Funds amounting to Rs.2.99 Crore were provided to the scheme in the 7th Empowered Committee meeting held on 18.08.2011. An amount of Rs 100 lakhs was released vide Ministry of 14.98 Finance letter dated 23/03/2012. CE, Mon(S) was requested to send FMP-4 along with monitoring report vide letter dated 6-08-2012 for release of first installment during 2012-13. A letter was sent on 11/2/2013 for sending FMP-2 and FMP-3 to Govt of Karanataka. Director(Appraisal), Mon(S),CWC vide letter dated 20.03.2013 communicated about the project being dropped. This has been 17.08.2011 intimated to MoWR , reply is awaited. Cleared Subtotal 360.99 290.36 0 70.63 0 12 Kerala In April, 2012, the Regional Office, CWC Coimbatore received 25 Nos. of proposals in the form of brief notes only from Govt. of Kerala for construction of 303 nos. of groynes at an estimated cost of Rs. 760.40 crore in five districts namely Ernakulam, Malappuram, Alappuzha, Kannur and Kasargod. These were examined and Proposal for construction of 114 nos of observations were communicated to Govt. of Kerala in groyne between Ch.53.635 km and 123.319 May, 2012. Subsequently, in Sep, 2012, the State Govt. 1 Km in between Vattachal and Chappakadavu 435.00 April, 2012 435.00 submitted the DPR for construction of 114 nos. of Groynes in Alappuzha District under Flood at an estimated cost of Rs. 435 crore in Alappuzha district Management Programme. only to Regional Office, CWC. It was observed that the earlier comments/observations sent in May, 2012 have not been fully complied with in the DPR. Therefore, in Sep, 2012, the State Govt. was requested to revise the DPR. The State Govt. did not submit the compliance since then along with the revised DPR. Project Proposal for construction of series of The observations /comments on the proposal were sent to 2 Groynes to combat sea erosion in Kerala 750.00 April, 2012 Govt. of Kerala in May, 2012. The state government has 750.00 coast not submitted the complliance The scheme has been accepted by Advisory Committee of Ministry in it its 124th meeting dated 16.10.2014. CWC- 3 Modernisation of Thanneermukkom Barrage 255.34 13.05.2013 255.34 HQ has forwarded the propsoal for consideration of IMC- FMP in March,2015. Renovation and River Training works of The comments on proposal were sent in March, 2014. The 4 33.75 10.12.2013 33.75 Kannampuzha in Kannur District in Kerala State Govt. did not submit the compliance since then.

DPR for FMP works in 397 Padasekharams for Rs. 758.98 Crore was examined and observations/comments issued on 03.04.2014. By adding 14 more padasekharams of Veeyapuram Mitigation of Flood in 397 Padasekharams of Panchayath of Kuttanad constituency, the DPR was Kuttanad Taluk in Alappuzha Dist. of Kerla resubmitted on 19.12.2014 for Rs. 1097.24 5 and Mitigation of flood in 14 padasekharams 1097.24 19.12.2014 Crore.Preliminary examination was made and observations 1097.24 of Veeyapuram Panchayath of Kuttanad issued on 22.01.2015. Pre TAC visit was carried out by constituency in Alappuzha Dist. of Kerala CSRO, CWC during Feb, 2015. Compliance recieved from State Govt. on 12.03.2015. Further comments/observations were issed vide letter dated 23.03.2015. State TAC was held on 22.04.2015 to consider the DPR. The State Govt. has not submitted the revised DPR since then.

Earlier Modernisation of Thottappally Spillway proposal was combined with Modernisation of Thannermukkom Renovation of leading channel for efficient Barrage. Later it was separated and submitted for Rs. flood water disposal from the confluence of 13.49 Crore. Further by changing the scope of works, the 6 Pamba and Achancovil rivers to sea at 47.00 19.12.2014 DPR was modified and submitted on 19.12.2014 for Rs. 47.00 Thottappally 47.00 Crore. Preliminary examination was made and observations issued on 22.01.2015. State TAC was held on 22.04.2015 to consider the DPR The State Govt. has not submitted the revised DPR since then. State/UT wise details of Flood Management Project Proposals ( coordinated by CWC) during XII Plan inculding spillovers as on 21.03.2016

Sl Estt. Cost Date of Under Name of works/scheme Status of examination Cleared Returned Awaited No. (Rs. In Cr) Receipt examination Beach Erosion Directorate received the DPR in March 2015. In The DPR reformation of Sea Wall for a length of Anti Sea Erosion works between CP-1745 11779m and construction of new sea wall for a length of 7 and CP-1882 in Kozhikode taluk of 45.49 31.03.2015 45.49 1485m has been proposed. DPR has been examined and Kozhikode district observations were communicated to Govt. of Kerala in June 2015. Compliance awaited from State government.

Beach Erosion Directorate received the DPR in April 2015. In the DPR reformation of sea wall for a length of 6549m Anti Sea Erosion works between CP-1883 and construction of new sea wall for a length of 4708m has 8 and CP-2034 of Koyilandy Taluk in 49.00 17.04.2015 49.00 been proposed. DPR has been examined and observations Kozhikode district. were communicated to Govt. of Kerala in June, 2015. Compliance awaited from State government.

Beach Erosion Directorate received the modified DPR in May 2015. In the DPR apart from construction of 8 nos of Proposal for construction of 8 nos of Groynes groynes, reformation of 2 nos of groynes already and allied works between CP-5919 and CP- constructed in 2009 and reformation of existing damaged 9 67.00 08.05.2015 67.00 5941 at Panathurakkara in sea wall for a length of 1750m has been proposed. DPR Thiruvananthapuram district (Modified DPR) has been examined and observations were communicated to Govt. of Kerala in June 2015. Compliance awaited from State government.

Beach Erosion Directorate received the DPR in June 2015. DPR of anti sea erosin works between CP- In the DPR reformation of sea wall for a length of 10762m 2033 and CP-2121 in Vatakara Taluk and construction of new sea wall for a length of 853m has 10 49.72 08.06.2015 49.72 and Kottakal Kadappuram of Kozhikode been proposed. DPR has been examined and observations district were communicated to Govt. of Kerala in August, 2015. Compliance awaited from state government. DPR was received in BED, Kochi on 03.08.2015. In the DPR long term flood mitigation measures in Long Term flood mitigation measures in Thiruvananathapuram for Karamana and Killy River has 11 Thiruvananathapuram for Karamana and Killy 500.00 03.08.2015 been proposed. The proposal has been examined in BED, 500.00 River Kochi and the Observations were communicated to State Govt. of Kerala in November, 2015. Compliance awaited from the State government. 3329.54 0.00 255.34 0.00 3074.20 0.00 13 Tamil Nadu The scheme was examined in CWC and comments were sent to State Govt. in May, 2012. In compliance , the State Govt. submitted the revised scheme namely " Excavation of Flood carries canal from Cauvery (Kattalai barrage) to Manimuthur, Vaigai and Gundur River (Phase-I &II). The comments on revised scheme was sent to State Govt. on Aug,2012. The State Govt. did not submit the Linking of Cauvery with Agniyar, South compliance since then. 1 Vellar, Pambar, Manimuthar, Vaigai and 5166.00 01-03-2012 5166.00 Gundar Rivers Further the State Govt. has reported in Apr, 2015 that This scheme is now being considered to pose under AIBP and accordingly the DPR is being prepared in phases incorporating the guidelines of new land acquisition act and adopting current schedule of rates. ( In view of this status the scheme is brought under Returned category from Awaited category)

The scheme was examined in CWC and comments were sent to State Govt. in May, 2013.The State Govt. did not reply since then. Further to above, in Nov,2013, CWC has suggested that this project can be considered as Irrigation project by taking account of water availability. The State Athikadavu-Avinashi Flood Flow Canal Govt. did not submit the compliance since then. 2 1862.00 Apr,2013 1862.00 Scheme Further the State Govt. has reported in Apr, 2015 that project report is under revision as per AIBP guidelines and Informed that the project is still under investigation with various alternatives under consideration. ( In view of this status the scheme is brought under 'Returned' category from Awaited category)

7028.00 0.00 7028.00 0.00 0.00 14 Lakshadweep The comments on proposal were sent in Oct, 2012. The UT 1 Closure of breach at Minicoy Island 9.36 Aug,2012 9.36 did not submit the compliance since then. 15 Chhatisgarh 1 Bhinjara Flood Protection scheme on Kauwa 5.3976 22-Dec-11 Appraisal was not required as the scheme was less than 5.3976 Nalla Rs.7.50 crore. Comments w.r.t. funding under FMP was sent to the State Govt. on 19.01.2012. Pending reply more than one year, the scheme has been deleted from list. 2 Jatangpur Flood Protection Scheme on Ahirab 6.7407 22-Dec-12 Appraisal was not required as the scheme was less than 6.7407 river Rs.7.50 crore. Comments w.r.t. funding under FMP was sent to the State Govt. on 19.01.2012. Pending reply more than one year, the scheme has been deleted from list. 3 Bango Flood Protection Scheme at Tan river 8.8978 22-Dec-12 The scheme was examined and comments were sent to the 8.8978 State Govt. on 19.01.2012. Pending reply more than one year, the scheme has been deleted from list. 4 Protection of Mahanadi riverbank in Pussore 5.5227 22-Dec-12 Appraisal was not required as the scheme was less than 5.5227 Blcok of district Raigarh Rs.7.50 crore. Comments w.r.t. funding under FMP was sent to the State Govt. on 19.01.2012. Pending reply more than one year, the scheme has been deleted from list. 5 Takhatpur Flood Management Scheme on 1.8241 19-Mar-12 Appraisal was not required as the scheme was less than 1.8241 Maniyari river Rs.7.50 crore. Comments w.r.t. funding under FMP was sent to the State Govt. on 07.09.2012. Pending reply more than one year, the scheme has been deleted from list. 6 Aamdi Flood Protection Scheme on Kharun 8.3017 13-Aug-12 Appraisal was not required as the scheme was less than 8.3017 River near Village Aamdi Rs.12.50 crore. Regarding funding under FMP, the scheme was returned to the State Govt. on 02.08.2013 because the cost was less than Rs. 40 crore State/UT wise details of Flood Management Project Proposals ( coordinated by CWC) during XII Plan inculding spillovers as on 21.03.2016

Sl Estt. Cost Date of Under Name of works/scheme Status of examination Cleared Returned Awaited No. (Rs. In Cr) Receipt examination 7 Mahadeo Ghat Flood Protection Scheme on 9.4945 13-Aug-12 The scheme was examined and comments were sent to the 9.4945 Kharun river near village Raipura State Govt. The compliance received was not as per guidelines and hence the scheme was returned with observation on 02.08.2013. Regarding funding under FMP, the scheme was returned to the State Govt. on 02.08.2013 because the cost was less than Rs. 40 crore 8 Amethi flood Protection Scheme on Mahnadi 8.2652 24-Aug-12 The scheme was examined and comments were sent to the 8.2652 River near Village Amethi State Govt. on 07.09.2012. Pending reply more than one year, the scheme has been deleted from list. 9 Rajim Nawapara Flood Protection Scheme on 14.77 24-Aug-12 The scheme was examined and comments were sent to the 14.77 Mahanadi River State Govt. on 07.09.2012. Pending reply more than one year, the scheme has been deleted from list. 10 Megha, Girod, Charbata, Botha and Gudguda 24.85 25-Oct-12 The scheme was examined and comments were sent to the 24.85 Flood Protection Scheme at edge of Mahanadi State Govt. on 26.11.2012. Pending reply more than one year, the scheme has been deleted from list. 11 Chipli(Dhabha), Jawergaon, Hardi and Kareli 23.72 25-Oct-12 The scheme was examined and comments were sent to the 23.72 badi Flood Protection Scheme at edge of State Govt. on 26.11.2012. Pending reply more than one year, Mahanadi River the scheme has been deleted from list. 12 Liagar Flood Protection Scheme on Lilagar River 13 29-Oct-12 The scheme was examined and comments were sent to the 13 State Govt. on 26.11.2012.Pending reply more than one year, the scheme has been deleted from list. 13 Madaku and Jondhara Flood Protection scheme 24.96 29-Oct-12 The scheme was examined and comments were sent to the 24.96 on Shivnath River State Govt. on 26.11.2012. Pending reply more than one year, the scheme has been deleted from list. 14 Kharung Flood Protection Scheme on river 14.89 29-Oct-12 The scheme was examined and comments were sent to the 14.89 Kharung River State Govt. on 26.11.2012. Pending reply more than one year, the scheme has been deleted from list. 15 Sarwani and Domuhani Flood Protection scheme 23.48 29-Oct-12 The scheme was examined and comments were sent to the 23.48 on Ghongha & Jewas River State Govt. on 26.11.2012. Pending reply more than one year, the scheme has been deleted from list. 16 Ghonhga and Jewas Flood Protection Scheme 19.95 30-Oct-12 The scheme was examined and comments were sent to the 19.95 on Ghongha &Jewas River State Govt. on 26.11.2012. Pending reply more than one year, the scheme has been deleted from list. 17 Talagaon and Takhatpur Flood Protection 15.81 30-Oct-12 The scheme was examined and comments were sent to the 15.81 Scheme on Maniyari River State Govt. on 26.11.2012. Pending reply more than one year, the scheme has been deleted from list. 18 Son and Chumara Flood Protection Scheme on 15.43 30-Oct-12 The scheme was examined and comments were sent to the 15.43 son and Banki River State Govt. on 26.11.2012. Pending reply more than one year, the scheme has been deleted from list. 19 Kiritpur-Chetua Flood Protection Scheme on 4.0454 26-Jun-13 Appraisal was not required as the scheme was less than 4.0454 Shinath River, District Bemetara (Chhatisgarh) Rs.12.50 crore. Regarding funding under FMP, the scheme was returned to the State Govt. on 19.08.2013 because the cost was less than Rs. 40 crore. 20 Malda Flood Management Scheme on Hamp 2.32 19-Jul-13 Appraisal was not required as the scheme was less than 2.32 River, District Bemetara, Chhatisgarh Rs.12.50 crore. Regarding funding under FMP, the scheme was returned to the State Govt. on 19.08.2013 because the cost was less than Rs. 40 crore 21 Tumdipar Flood Protection Scheme on Surhi 2.53 16-Aug-13 Appraisal was not required as the scheme was less than 2.53 River, District Bemetara (Chhatisgarh) Rs.12.50 crore. Regarding funding under FMP, the scheme was returned to the State Govt. on 03.10.2013.2013 because the cost was less than Rs. 40 crore

254.1997 865560 0 0 254.1997 0 0 16 Rajasthan 1 Flood protection works of Jawal to Satpura in 9.0991 18-Jul-11 The scheme was examined and the comments were sent to the 9.0991 Tehsil and District Sirohi State Government on 27.07.2011. The state government has not submitted the complliance 17 Himachal Pradesh 1 Swan river flood management and integrated 235.52 13.07.2004 The scheme was accorded clearance by TAC in its 84th meeting 235.52 land development project Phase –II in district held on 12.05.2005. The investment clearance has been Una of Himachal Pradesh District: Una. (HP-2) accorded by the Planning Commission vide letter No. 12(1)/8/2005-WR dated 22.10.2008. The schemes has been included under FMP in the 4th meeting of Empowered Committee held on 10.07.2009 and full amount of Central Assitance has been released and scheme has been physically compeleted in year 2013 with C.A. 165.84 Cr (total expenditure- 211.02 cr). This information of completion received via letter M&A Dte., Shimla dt. 17.11.2014.The completion report with completion cost 211.02 Cr (CA-Rs 165.84 Cr,SS- 45.18 Cr) submitted by IBO Chandigarh dated via letter dt 12.12.2014. 2 Detailed Project Report for Swan River Flood The scheme has been examined and found to be techo- 46.8 Management project Down Stream of economically viable. The scheme has been accepted by the AC- 46.80 22.02.2011 Santokhgarh bridge up to Himachal Pradesh MOWR in its 125th meeting held on 25.05.2015. Boundary in district Una (H.P) 3 Flood Protection/Channelization of Seer Khad 62.4641 The scheme was received on 12.02.2014 at M&A Dte, CWC, from Barchhwar to Jahu bridge in Tehsil Shimla. The scheme was examined and additional information Sarkaghat, Distt - Mandi (HP) was asked by M&A Dte., vide their letter dated 10.10.2012. The proposal was examined in FM-I Dte, CWC and comments/ observations was sent to the State Government vide letter dt. 22.09.2012/ 04.04.2014. A copy of the DPR was sent to Hyd(N) Dte. on 62.4641 12.02.2014 08.05.2014. Comments of Hyd(N) Dte, CWC was (Hq) communicated to the State Govt. on 05.06.2014. The complaince to comments of CWC was received by the State Govt. on 01.08.2014 but the complaince of the comments of Hyd(N) Dte (last issued on 08.05.2015) is still awaited for further appraisal of the scheme. 4 Providing Flood Protection Works to Lunkari 2.8505 22.04.2014 The minor flood scheme has been examined at M&A Dte CWC, 2.8505 Khad in Tehsil Bangana District Una, H.P Shimla and found in order. 5 Providing Flood Protection works on river Beas 1155.15 01.08.2014 The scheme was examined and comments of FM-I Dte & Hyd 1155.15 from Palchan to Aut in discrict Kullu, H.P 10.03.2015 (N) Dte, CWC were sent on 05.06.2015 and 19.06.2015 (Hq) respectively to State Govt. for compliance. Compliace of the observation has been received on 8.01.2016 by the State Govt. through CE (IBO) and sent to Hyd Dte on 4.3.2016 for examination in CWC. State/UT wise details of Flood Management Project Proposals ( coordinated by CWC) during XII Plan inculding spillovers as on 21.03.2016

Sl Estt. Cost Date of Under Name of works/scheme Status of examination Cleared Returned Awaited No. (Rs. In Cr) Receipt examination 6 Detailed Project proposal for Stabilization of 23.17 March, 2008 The Scheme has been examined and found to be techno- 23.17 Seer Khad and Flood Protection Works from economically viable. The project was cleared by Indus Wing, Jahuoo to Bum in tehsil Ghumarwin District , MoWR from Indus Waters Treaty angle on 14.03.2008. The Bilaspur (HP) (HP-6) scheme has been accepted by the AC-MOWR in its 112th meeting held on 14-09-2011. The investment clearance has also been accorded by the Planning Commission vide 12(1)/8/2011-WR dt. 2-11-2011. The scheme has been included under FMP in the 2nd meeting of IMC-FMP held on 03.03.2014 as HP-6. 1st instalment amounting to Rs. 4.9875 crore has been released to State Govt.

7 Detailed Project Report for Providing Flood 6.38 07.03.2011 The scheme was examined and found to be in order. This 6.38 Protection Work on the bank of Soan Khad from schemes has been cleared by CWC vide letter Sayathi Awal to Kalswai, Dharmpur in Tehsil No.11/11/HP/2011/FM-I/ 354-357 dated 01.08.2011. The Sarkaghat, Distt Mandi (HP). (HP-3) Scheme has been included under FMP in 7th meeting of EC- FMP held on 18.08.2011. 8 Swan River Flood Management project from 922.485 25.01.2012 The Scheme has been examined and found to be techno- 922.49 Daulatpur bridge to Gagret bridge in main Swan economically viable. The scheme was cleared by Indus Wing, river & all tributaries joining main Swan river MoWR from Indus Water Treaty angle on 22.05.2013. The from Daulatpur bridge upto Himachal Pradesh scheme has been accepted by the AC-MOWR in its 118th boundary in District Una (HP). (HP-4) meeting held on 30.07.2013.The investment clearance has also been accorded by the Planning Commission vide 12(1)/8/2011- WR dt. 20.09.2013.The scheme has been included under FMP in the 1st meeting of IMC-FMP held on 19.12.2013 as HP-4. Proposal for rereimbursement of 2nd instalment of Rs. 107.80 cr during 2014-15 and release of 1st instalment of Rs. 116.55 cr during 2015-16 has been sent to MoWR, RD & GR on 23.10.2015

9 Channelisation of Chhounchh Khad in Tehsil 179.59 31.08.2012 The Scheme has been examined and found to be techno- 179.59 Indora, District- Kangra (HP). (HP-5) economically viable. The scheme has been accepted by the AC- MOWR in its 118th meeting held on 30.07.2013.The investment clearance has also been accorded by the Planning Commission vide 12(1)/8/2011-WR dt. 14.10.2013.The scheme has been included under FMP in the 1st meeting of IMC-FMP held on 19.12.2013 as HP-5. Proposal of reimbursement of C.A. amounting to Rs. 11.10 crore has been sent to Ministry on 08.06.2015. 2398.89 1181.28 0.00 1217.61 0.00 18 Haryana 1 Revised Flood protection works along river The scheme was returned back to State Government as the 181.42 Yamuna in the State of Haryana.(HR-1) works have already been completed without the approval of 181.42 13.03.2013 CWC. Later on State Govt. has submitted Physical and Financial achievement of the project upto March, 2015. The proposal of re-appraisal of the project has been sent to Cost 19 Jammu & Apprisal (HWF) Dte, CWC on 21.01.2016. 1 Master Plan for Flood Protection Works on River 22.8200 24.11.2003 The Planning Commission has accorded its investment 22.82 Tawi District. (JK-01) clearance vide letter No 12(1)/9/2006-WR dated 21.11.2006. Total amount of C.A released so far is Rs. 17.5382 Cr. Proposal for release of next installment is not received from the State Govt. 2 Master Plan for Flood Protection Works on River 19.4500 24.11.2003 The Planning Commission has accorded its investment 19.45 Chenab. (JK-02) clearance vide letter No 12(1)/9/2006-WR dated 21.11.2006. Total amount of C.A released so far is Rs. 14.9835 Cr. Proposal for release of next installment is not received from the State Govt. 3 Improvement of flood spill channel in Jhelum by 14.9282 24.11.2003 The investment clearance of the scheme has been accorded by 14.93 way of construction of central cunnette in J&K. the Planning Commission vide letter No. 12(1)/9/2005-WR District-Jammu. (JK-03) dated 5.9.2005. Total amount of C.A released so far is Rs. 12.8983 Cr. The scheme has been completed as per State Govt. statement. 4 Construction of Flood Protection Works at 14.6300 29.08.2007 The scheme has been cleared by the CWC and forwarded to 14.63 vulnerable spots u/s & d/s of National Highway the Planning Commissiion got its investment clearance.Total along Ujh river from village Jakhole to Pandorian amount of C.A released so far is Rs. 12.9755 Cr . Proposal for District Kathua. (JK-04) release of next installment is not received from the State Govt.

5 Project report for critical anti erosion works on 14.9300 20.11.2007 The scheme has been cleared by CWC & the investment 14.93 river Chenab (Dera Baba Banda) tributary clearance from the Planning Commission has been received Halian (Doda) of Tawi- bridge (J&K) District vide letter No. 12(1)/9/2006-WR dated 17.03.2008. Total Doda. (JK-05) amount of C.A released so far is Rs. 13.1777 Cr.

6 Erosion control / Flood Control Works on Lidder 5.4700 26.09.2008 The scheme was found techno- economically viable and 5.47 Nallah Phase-II , Distt- Anantnag. (JK-06) cleared by CWC.Total amount of C.A released so far is Rs. 4.8144 Cr.The scheme has been completed as per State Govt. statement. 7 Flood control/Anti erosion works for Veshow 7.1500 2008-09 The scheme was found techno- economically viable and 7.15 Nalla Ph.II Distt Anantnag/ Kulgam. (JK-07) cleared by CWC.Total amount of C.A released so far is Rs. 6.3015 Cr. The scheme has been completed as per State Govt. statement. 8 Anti Erosion works of various Nallas i.e. Kanday 3.3300 16.09.2008 The Scheme was found techno- economically viable and 3.33 & Vethvathroo Nallahs, Districts Anantnag / cleared by CWC.Total amount of C.A released so far is Rs. Kulgam. (JK-08) 2.9281 Cr. The scheme has been completed as per State Govt. statement. 9 Erosion Conrol/Flood Control Works on 6.7250 16.09.2008 The Scheme was found techno- economically viable and 6.73 Sandran, Wankran and Sasara Nallah District- cleared by CWC..Total amount of C.A released so far is Rs. Anantnag. (JK-09) 5.9014 Cr. The scheme has been completed as per State Govt. statement. 10 Erosion Control/Flood Control Works on Vij 7.4660 17.09.2008 The Scheme was found techno- economically viable and 7.47 Nallah, Dist- Baramullah. (JK-10) cleared by CWC.Total amount of C.A released so far is Rs. 2.3062 Cr. The scheme has been completed as per State Govt. statement. 11 Project report for Erosion Control/Flood Control 7.4353 17.07.2008 The scheme was found techno- economically viable and 7.44 Works on various Nallahs i.e Dakil, Hamal, cleared by CWC on 10.02.2009. Total amount of C.A released Hapatnar & Binner Nallahs in Distt. Baramullah. so far is Rs. 6.3709 Cr. The scheme has been completed as (JK-11) per State Govt. statement. 12 Erosion Control/Flood Control Works on various 6.5500 2008-09 The Scheme was found techno- economically viable and 6.55 tributaries of Jhelum in Shangus, Bijbehara and cleared by CWC on 06.03.2009. Total amount of C.A released Dooru constituencies. Dist- Anantnag. (JK-12) so far is Rs. 5.7746 Cr.The scheme has been completed as per State Govt. statement. State/UT wise details of Flood Management Project Proposals ( coordinated by CWC) during XII Plan inculding spillovers as on 21.03.2016

Sl Estt. Cost Date of Under Name of works/scheme Status of examination Cleared Returned Awaited No. (Rs. In Cr) Receipt examination 13 Erosion Control/Flood Control Works on various 6.9900 2008-09 The scheme was found techno- economically viable and 6.99 Nallahs of Pahalgam constuency Distt. cleared by CWC vide letter dt. 02.01.2009. Total amount of C.A Anantnag. (JK-13) released so far is Rs. 6.1640 Cr. The scheme has been completed as per State Govt. statement. 14 Erosion Control/Flood Control Works on 6.4100 2008-09 The scheme was found techno- economically viable and 6.41 Watalara, Aripal, Lam, Satura, Mandoora, Kehlil cleared by CWC vide letter dt. 05.01.2009. Total amount of Distt Pulwama (JK-14) C.A released so far is Rs. 5.6301 Cr. The scheme has been completed as per State Govt. statement. 15 Project report for F.P.Works on river & Major/ 13.9100 02.11.2007 The scheme has been cleared by CWC & forwarded to 13.91 Minor nallahs in district (J&K) District planning commission for investment clearance. Vide letter no Rajouri. (JK-15) 7/37/J &K/2008/Fm-I/661-64 Dt 23.10.08. Total amount of C.A released so far is Rs. 9.9846 Cr.Proposal for release of next installment is not received from the State Govt.

16 Project report for construction of anti-erosion 11.3900 05.03.2008 The scheme has been Cleared by CWC & forwarded to 11.39 flood protection works for Ban Ganga at foothills Planning Commission for investment clearance vide letter no. of Shri Mata Vaishno Devi Ji Shrine, Katra,Distt 7/44/JK/2007/FM-I/256-259 dt.8-4-08. Investment clearance Reasi (J&K). (JK-16) has been received from Planning Commission vide letter No. 12(1)/9/2006-WR dated 18.12.08. An extension clearance has been provided by the planning commission vide letter dated 03.03.2014. Total amount of C.A released so far is Rs. 9.1294 Cr. Proposal for release of next installment is not received from the State Govt. 17 Project report for critical anti-erosion works on 14.9500 05.03.2008 The scheme has been cleared by CWC and forwarded to 14.95 river Tawi from Chenani to village Dibber and its Planning Commission for investment clearance vide letter no tributaries in Distt. Udhampur. (JK-17) 7/45/JK/2008/FM-I/522-525 dt.5/8/08. Investment clearance has been received from Planning Commission vide letter No. 12(1)/9/2006-WR dated 22.01.09. A request has been sent to C.E. (IBO) for the confirmation of the amount of 1st installment released vide letter dt. 26.03.2015. Total amount of C.A released so far is Rs. 11.2163 Cr. Proposal for release of next installment is not received from the State Govt.

18 Drainage development/ enhancing flood channel 9.8100 ----- The scheme has been cleared by CWC and forwarded to 9.81 capacity at critical reaches of river Jhelum Planning Commission for investment clearance vide letter no bundhs Ph.II from Sonwar Ghat to Dubji Ghat 7/35/JK/2006/FM-I/327-31 dt.12.05.2009 Investment clearance (Gowkadal) District Srinagar. (JK-18) has been received from Planning Commission vide letter No. 12(1)/9/2006-WR dated 29.05.2009.Total amount of C.A released so far is Rs. 8.6066 Cr.The scheme has been completed as per State Govt. statement.

19 Construction of protection works d/s Sidhra 14.6700 17.08.2007 The scheme has been cleared by CWC & forwarded to 14.67 Bridge on left bank of river Tawi for planning commission for investment clearance. Vide letter no training/reclamation of land. District Jammu. (JK- 7/38/J&K/2007/Fm-I/220-23 Dt 19/03/09. Investment 19) clearance has been accorded by the Planning Commission vide letter no 2(420)/2010-WR dated 30-04-2010.Total amount of C.A released so far is Rs. 10.7063 Cr. The state govt. has requested a time extension for the project from the planning commission vide letter dated 03.03.2014. Proposal for release of next installment is not received from the State Govt.

20 Detailed Project report for urgent works to 97.4600 05.11.2009 The scheme was examined in various directorates of CWC 97.46 mitigate the flood threat of river Jhelum, Distt- and found to be techno-economically viable . The scheme has Jammu. (JK-20) been accepted by AC-MOWR in 104th meeting held on 12-05- 2010. The investment Clearance has also been accorded by the Planning Commission vide letter No.12(1)/9/2010-WR dated 12-7-2010. Total amount of C.A released so far is Rs. 87.3562 crores. The scheme has been completed as per State Govt. statement. 21 Construction of Flood protection works on The scheme has been cleared by CWC ( M&A dte Jammu) and 14.99 Nallah in Block Boniyar (JK-21) Investment clearance has been received from Planning Commission vide letter No. 12(1)/9/2010-WR dated 30.05.2011. The scheme has been included under FMP in 7th 14.9900 27.09.2011 meeting of Empowered Committee.Total amount of C.A released so far is Rs. 3.3700 Cr. Proposal for release of next installment has been received from the State Govt. and sent to MoWR on 14.01.2016 (Rs. 1.955 cr.)

22 Construction of Flood protection works on The scheme has been cleared by CWC( M&A dte Jammu) and 14.96 Nallah in Block Uri (JK-22) Investment clearance has been received from Planning Commission vide letter No. 12(1)/9/2010-WR dated 30.05.2011. The scheme has been included under FMP in 7th 14.9600 27.09.2011 meeting of Empowered Committee. Total amount of C.A released so far is Rs. 3.3650 Cr. Proposal for release of next installment has been received from the State Govt. and sent to MoWR on 14.01.2016 (Rs. 1.951 cr.)

23 Construction of Flood protection works on The scheme has been cleared by CWC( M&A dte Jammu) and 14.95 Hapath Khai Trikanjan Nallah, Nowshera Nallah Investment clearance has been received from Planning , Pahlipora Yaran nallah, Naganri Zehanpora Commission vide letter No. 12(1)/9/2010-WR dated nallha of block Boniyar District Baramullah. (JK- 30.05.2011. The scheme has been included under FMP in 7th 23) 14.9500 27.09.2011 meeting of Empowered Committee. Total amount of C.A released so far is Rs. 3.3600 Cr. Proposal for release of next installment has been received from the State Govt. on 8.1.2016 and sent to MoWR on 14.01.2016 (Rs. 1.947 cr.) 24 Flood Protection and Training Works of Ney This scheme has been accepted by the Advisory Committee on 59.41 Basago Nallah (JK24) Irrigation, Flood Control and Multi Purposes for consideration in its 111th meeting held on 17.08.2011. Investment clearance has also been accorded by PC vide 12(1)/9/2011-WR dt. 24-10- 59.4100 08.06.2011 2011. Total amount of C.A released so far is Rs. 11.00 Cr. Proposal for release of next installment has been received from the State Govt. on 8.1.2016 and sent to MoWR on 08.02.2016 .

25 Flood Protection and Training Works of Phyang This scheme has been accepted by the Advisory Committee on 58.57 Nallah (JK-25) Irrigation, Flood Control and Multi Purposes for consideration in its 111th meeting held on 17.08.2011. Investment clearance has also been accorded by PC vide 12(1)/9/2011-WR dt. 24-10- 58.5700 08.06.2011 2011. Total amount of C.A released so far is Rs. 11.50 Cr.Proposal for release of next installment has been received from the State Govt. and sent to MoWR on 08.02.2016 . State/UT wise details of Flood Management Project Proposals ( coordinated by CWC) during XII Plan inculding spillovers as on 21.03.2016

Sl Estt. Cost Date of Under Name of works/scheme Status of examination Cleared Returned Awaited No. (Rs. In Cr) Receipt examination 26 Flood Protection and Training Works of Saboo This scheme has been accepted by the AC-MOWR for 47.04 Nallah (JK-26) consideration in its 111th meeting held on 17.08.2011. Investment clearance has also been accorded by PC vide 47.0400 08.06.2011 12(1)/9/2011-WR dt. 24-10-2011. Total amount of C.A released so far is Rs. 11.6150 Cr. Proposal for release of next installment has been received from the State Govt. and sent to MoWR on 08.02.2016 . 27 Flood Protection and Training Works of Igoo This scheme has been accepted by the Advisory Committee on 35.83 Nallah.(JK-27) Irrigation, Flood Control and Multi Purposes for consideration in its 111th meeting held on 17.08.2011. Investment clearance has also been accorded by PC vide 12(1)/9/2011-WR dt. 24-10- 35.8300 08.06.2011 2011. Total amount of C.A released so far is Rs. 6.750 Cr. Proposal for release of next installment has been received from the State Govt. and sent to MoWR on 08.02.2016 .

28 Flood Protection and Training Works of Nimoo This scheme has been accepted by the Advisory Committee on 26.25 Nallah. (JK-28) Irrigation, Flood Control and Multi Purposes for consideration in its 111th meeting held on 17.08.2011. Investment clearance has also been accorded by PC vide 12(1)/9/2011-WR dt. 24-10- 26.2500 08.06.2011 2011. Total amount of C.A released so far is Rs. 6.620 Cr. Proposal for release of next installment has been received from the State Govt. and sent to MoWR on 08.02.2016 .

29 Construction of flood protection works on river 14.9300 27.09.2011 The scheme was approved by IMC-FMP in its 2nd meeting held 14.93 Suru at , Parkachik, Tai Suruthang, on 03.03.2014. Total amount of C.A released so far is Rs. Parantee nallah, Chatkhar khows and Damsna in 1.6727Cr. Proposal for release of next installment Proposal for District, Jammu & Kashmir. (JK-29) release of next installment has been received from the State Govt. and sent to MoWR on 26.02.2016 . 30 Construction of flood protection works on river 12.3100 2010-11 The scheme was approved by IMC-FMP in its 2nd meeting held 12.31 Suru from Chechesna to Sheer Bagh on 03.03.2014. Total amount of C.A released so far is Rs. 1.00 Andoo, J& K. Distt- kargil. (JK-30) Cr. Proposal for release of next installment Proposal for release of next installment has been received from the State Govt. and sent to MoWR on 26.02.2016 . 31 Construction of Flood Protection Works at 11.1400 03.03.2014 The scheme was approved by IMC-FMP in its 2nd meeting held 11.14 Helipad and Sub-District Hospital at Gandoh on on 03.03.2014. Total amount of C.A released so far is Rs. 1.00 L&R side of Kalgoni Nallah at Gandoh Cr. Proposal for release of next installment is not received from (Bhalessa) Doda.J&K. (JK-31) the State Govt. 32 Construction of Flood Protection Works in 10.0600 03.03.2014 The scheme was approved by IMC-FMP in its 2nd meeting held 10.06 Kathar Tawi/ Queer Nallahs in . District: on 03.03.2014. Total amount of C.A released so far is Rs. 1.00 Jammu. (JK-32) Cr. Proposal for release of next installment is not received from the State Govt. 33 Construction of Flood Protection Works in Mawa 10.6500 03.03.2014 The scheme was approved by IMC-FMP in its 2nd meeting held 10.65 Brahmana Nallah in Akhnoor District: Jammu. on 03.03.2014. Total amount of C.A released so far is Rs. 1.00 (JK-33) Cr. Proposal for release of next installment is not received from the State Govt. 34 Construction of Flood Protection Works in 10.5100 03.03.2014 The scheme was approved by IMC-FMP in its 2nd meeting held 10.51 Sumah Nallah in Akhnoor. District: Jammu. (JK- on 03.03.2014. Total amount of C.A released so far is Rs. 1.00 34) Cr. Proposal for release of next installment is not received from the State Govt. 35 Construction of Flood Protection Works in Tanda 10.5100 03.03.2014 The scheme was approved by IMC-FMP in its 2nd meeting held 10.51 Nallah in Akhnoor. District: Jammu. (JK-35) on 03.03.2014. Total amount of C.A released so far is Rs. 1.00 Cr. Proposal for release of next installment is not received from the State Govt. 36 Construction of Protection Works in Tehsil 12.4885 03.03.2014 The scheme was approved by IMC-FMP in its 2nd meeting held 12.49 Chenani, Block Panchari, Tikri Dist:- Udhampur. on 03.03.2014. Total amount of C.A released so far is Rs. 1.00 (JK-36) Cr. Proposal for release of next installment is not received from the State Govt. 37 Construction of Flood Protection Work at 11.5900 03.03.2014 The scheme was approved by IMC-FMP in its 2nd meeting held 11.59 Changa Stadium ,PHC Changa, Diggi, Dudwar on 03.03.2014. Total amount of C.A released so far is Rs. 0.77 on Kahalijugsar Kalgoni Nallah with its tributaries Cr. Proposal for release of next installment is not received from Chanti, Ichier, Soti & Dhossa Nallah on L/S & the State Govt. R/S. Distt- Doda. (JK-37) 38 Construction of Flood Protection Work at 11.8400 03.03.2014 The scheme was approved by IMC-FMP in its 2nd meeting held 11.84 Gandoh, Shoran, Bhatyas, Bamboo, Bathri on on 03.03.2014. Total amount of C.A released so far is Rs. 0.52 Kalgoni Nallah with its tributaries, Jitota & Chilly Cr. Proposal for release of next installment is not received from Nallah on L/S & R/S. Distt- Doda, J&K. (JK-38) the State Govt.

39 Construction of F.P.Work /Anti erosion in various 10.0700 03.03.2014 The scheme was approved by IMC-FMP in its 2nd meeting held 10.07 Nallahs of Block Reasi, Pouni, Mahore and on 03.03.2014. Total amount of C.A released so far is Rs.1.0 Arnas in Tehsil and District Reasi. (JK-39) Cr. Proposal for release of next installment is not received from the State Govt. 40 Erosion Control /F .P. works on Kehmil Nallah 12.1800 03.03.2014 The scheme was approved by IMC-FMP in its 2nd meeting held 12.18 from Marsari to Mugal pora . District Kupwara ( on 03.03.2014. Total amount of C.A released so far is Rs.1.0 at Vulnerable spots). (JK-40) Cr. Proposal for release of next installment is not received from the State Govt. 41 FPW/Anti -Erosion Works on Doodhganga 12.4200 03.03.2014 The scheme was approved by IMC-FMP in its 2nd meeting held 12.42 Nallah. Dist- Budgam.(JK-41) on 03.03.2014. Total amount of C.A released so far is Rs.1.0 Cr. Proposal for release of next installment is not received from the State Govt. 42 FP/ Anti-Erosion works on critical reaches of 12.4800 03.03.2014 The scheme was approved by IMC-FMP in its 2nd meeting held 12.48 Vethwathroo/Sonman branch of Sandran Nallah. on 03.03.2014. Total amount of C.A released so far is Rs.1.0 Distt-Anantnag. (JK-42) Cr. Proposal for release of next installment is not received from the State Govt. 43 Priority Works-Comprehensive Plan for Flood 399.29 19.01.2015 Techno-economic appraisal of the Project has been complted 399.29 Management Works on Jhelum-Phase-I in and approved by 125th Advisory Committee of MoWR., RD & Kashmir. GR on Irrigation, Flood Control and Multi Purpose Projects on 25.05.2015. Proposal for investment clearance received from Sttae Govt. through CE (IBO), Chandigarh In Jan., 2016 has been send to CE (PAO), CWC on 28.01.2016.

44 Flood Protection works on River Indus from 14.18 2010-11 The scheme has been cleared by CWC( M&A Dte Jammu) and 14.18 Stakna to Phey, Disst- forwarded to Planning Commission for investment clearance vide letter dated 29.03.2011. Investment Clearnce and SFC awaited from State Govt. 45 Construction of Earthen Embankment with toe 13.00 29.03.2011 Appraisal note was sent to CE(IBO) for approval on 13.00 crate /strengthening of existing earthen 04.07.2011. The Chief Engineer advised to design the embankment from RD(0-4000) m on Left side of embankment of project as per the relevant IS codes and to Waddi Tawi from Karnala Chak to Nandpur, determine the feasibility of project in Planned way. The same Jammu was communicated to State Government vide letters dated 05.10.2011. Response from the State Government is awaited.Reminder sent on 12.03.2013. Replies awaited. State/UT wise details of Flood Management Project Proposals ( coordinated by CWC) during XII Plan inculding spillovers as on 21.03.2016

Sl Estt. Cost Date of Under Name of works/scheme Status of examination Cleared Returned Awaited No. (Rs. In Cr) Receipt examination 46 Construction of Flood Protection works on River 14.39 2010-11 Appraisal note was sent to CE(IBO) for approval on 26.07.2011 14.39 Drass at Matayen, Rambipora and Dongchik . SFC issued by Sate Government on 25.08.2011. The project under Flood Management Programme,Disst- authority was asked to design the project as per relevant BIS Kargil codes vide letters dated 19.09.2011 asper the instruction of CE , IBO conveyed by him vide letter dated 13.09.2011. Response from the state government is awaited. A reminder were issued on 21.11.2011 and on 22.02.2012. No response from State Govt. has been received.

47 Construction of Flood protection works/Anti 36.98 08.09.2011 Comments regarding the supply of hydrological data, design of 36.98 erosion works on Madhumati nallah Bandipore, structures and others were issued on 30.08.2011. Reminders Srinagar was also sent to the State Govt on 26.11.2012 for compliance of the observation but no response has been received from State Govt. 48 Construction of Earthen Embankment with toe 12.45 29.03.2011 Appraisal note was sent to CE(IBO) for approval on 12.45 crate /strengthening of existing earthen 04.07.2011. The Chief Engineer advised to design the embankment from RD (977-5250) m on Right embankment of project as per the relevant IS codes and to side of Waddi Tawi from Bhagwati Nagar to determine the feasibility of project in Planned way. The same Nadini Seyora. was communicated to State Government vide letters dated 05.10.2011. Response from the State Govt is awaited.

49 Construction of Flood Protection works on River Appraisal note was sent to CE(IBO) for approval on 12.11 Drass at Bearas, , Bimat , Vatakhul , 26.07.2011. SFC issued by State Government on 25.08.2011. Hardass and Karkitchoo The project authority was asked to design the project as per relevant BIS codes vide letters dated 19.09.2011as per the 12.11 01.07.2011 instruction of CE , IBO conveyed by him vide letter dated 13.09.2011. Reminders to the observations were conveyed to State Govt. on 21.11.2011 and 22.02.2012 but no response from State Govt. has been received.

50 Erosion Control/Flood Protection works on SFC issued by State Government on 25.08.2011. The project 14.14 Wakha Nallah from Gyail to Poyen at spots, authority was asked to design the project as per relevant BIS Kargil. codes vide letters dated 21.09.2011. A reminder regarding the 14.14 26.08.2011 observation was sent on 21.11.2011 and on 22.02.2012 but no response has been received from State Govt.

51 Flood Protection Works at Kishen Ganga Nallah Earlier DPR of cost Rs. 18.30 Cr. Has been revised to Rs. 12.43 and its tributaries in Gurez and Tulai Area , 12.43 14.01.2016 12.43 Cr. Revised DPR received on 14.01.2016 is under Bandipora under FMP. scrutiny in field office. 52 Construction of earthen Embankment and allied The complaince was received and revised DPR was sent to 75.35 protection works on L/S of Ujh River from village CE(IBO) on 10.02.2014. A copy of the comments of Hyd (N) Mai Chak to Village Nangal District Kahtua. 75.35 25.02.2014 were sent to the State Govt. on 13.05.2014 and comments of FM-I Dte. was sent on 13.08.2014. Reply from State Govt. is awaited. 53 Construction flood protection works on right bank The Prelimanry comments have been sent to the State 34.72 of river Chenab from Talwara to Jeeri vai Kansi Gvernemnt after scrutiny in M&A Dte, Jammu office on Pata Kansh Brahmana, Kansh Kasha, Panthaal 34.72 14.01.2016 15.01.2016. Revised DPR received on 14.01.2016 is under and Jambri inTehsil and District Reasai scrutiny.

54 Construction of flood protection works/anti- The Prelimanry comments have been sent to the State 22.62 erosion works on both side of river Ans and its Gvernemnt after scrutiny in M&A Dte. CWC, Jammu on 22.62 01.08.2013 tributaries from Saral to Ganjote Tehsil Mahore. 15.10.2013.The replies from State Governemnt is still awaited Distt. Reasi. 55 Construction of flood protection work by way to The Prelimanry comments have been sent to the State 21.32 Crate Revetment , earthen Embankment, studs Gvernemnt after scrutiny in M&A Dte. CWC, Jammu on and diversion Channel from Thandi Choi to Ditch 21.32 22.08.2013 15.10.2013.The replies from State Governemnt is still awaited cum bund near Indo Pak Border Lohaki Nallah and its triburataries. 56 Construction of flood protection work from d/s 26.91 22.08.2013 The DPR submitted to field office earlier was of cost Rs 14.73 26.91 Confluence point to Balole Nallah to village cr. The preliminary comments were sent to State Govt after Rakh Vikrama on left side of river Nikki Tawi, Scruitny in field office on 15.10.2013. Disst- Jammu A revised DPR has been submitted to field office by State Govt on 13.02.2015 with an updated cost of Rs 26.91 Cr. The DPR was scruitnised at field office and the preliminary observations were issued on 24.02.2015. No compliance till date from State Govt. 57 Construction of flood protection work/ Anti Comments were issued by M&A Dte, CWC, Jammu on 12.38 Erosion Works on both sides of River and its 13.09.2013.Compliance from State Governemnt is awaited. 12.38 22.08.2013 tributaries from Plassu to Arnas Tehsil Mahore District Reasi. 58 Construction of protection work in Devak at Comments were issued by M&A Dte, CWC, Jammuon 12.26 Udhampur Phase-II. 12.26 22.08.2013 07.10.2013. Compliance from State Governemnt is awaited.

59 Construction of critical Anti Erosion Works on Comments were issued by M&A Dte, CWC, Jammuon 12.49 Gambhir Nallah and its tributaries and other 20.09.2013. Compliance from State Governemnt is awaited. 12.49 22.08.2013 Nallah of Tehsil Majalta in District Udhampur.

60 Construction of Flood Protection Works on both Originally schme was submitted with cost Rs. 12.0 cr on 16.01 side of Tridwan Nallah and its tributaries in 22.08.2013. DPR was examined and prelimanry observations Tehsil and District Kathua. was conveyed to the State Govt. on 20.09.2013. by M&A Dte, CWC, Jammu. Revised DPR was submitted by the State Govt. 16.01 29.07.2015 on 29.07.2015 costing Rs. 16.012 cr.. Preliminary comments have been issued on 07.08.2015 by the field office and compliance of the comments is awaited.

61 Erosion Control/Flood Control Works on various The comments regarding the observations in design of Hydrolic 14.65 Nallahs on river Kokernag constituency District Structures sent to the State Government by M&A Dte, CWC, Anantnag Jammu vide letters dated 21.11.2011. Reminders in this 14.65 28.07.2011 regards were sent on 22.02.2012 and 07.09.2012,. No response from the State Government has been recived so far.

62 Construction of Flood Protection Works on Comments were issued on 20.09.2013. The DPR was again 11.60 Nowshera Tawi, Niayi Tawi and Thanda pani submitted on 24.02.2014 and as the DPR was not found in 11.60 10.09.2013 Tawi and Local Nallha Nowshera order. The revised comments were again issued on 22.04.2014. Complaince from State Govt. is awaited. 63 Construction of critical Anti erosion works on Scheme costing 11.6715 was submitted with revised 12.43 Ujh(U/S) and its tributaries and local nallah in 12.43 10.09.2013 cost.Comments were issued on 20.09.2013.Compliance from tehsil Ramnagar, Jammu. State Governemnt is awaited. 64 Construction of FPW of crate revetment, Originally schme was submitted with cost Rs. 10.37 Cr. on 11.19 Earthen Embankment & diversion channel in 22.08.2013. Revised DPR was examined and prelimanry 11.19 10.09.2013 Jourian Nallah. observations sent on 12.09.2013. Compliance from State Govt is awaited. State/UT wise details of Flood Management Project Proposals ( coordinated by CWC) during XII Plan inculding spillovers as on 21.03.2016

Sl Estt. Cost Date of Under Name of works/scheme Status of examination Cleared Returned Awaited No. (Rs. In Cr) Receipt examination 65 Construction of FPW on R/S of River Korepunnu Comments were issued on 07.10.2013. Revised DPR submitted 12.43 Area on 18.07.2014 and comments issued on 12.08.2014. 12.43 18.07.2014 Compliance from State Governemnt has been received in the field office on 27.11.2015 and has been examined and observations issued on 25.02.2016. 66 Construction of FMP by way of earthern Comments were issued on 12.09.2013. Compliance from State 11.94 embankment, spurs and crate revetment on R/S 11.94 13.09.2013 Government awaited. & L/S of River Basanter, Jammu. 67 Const of FPW in Banihal Area under Save Comments were issued on 11.10.2013. Compliance from State 10.57 10.57 17.09.2013 Banihal. Government awaited. 68 Const of FPW (Save Ramban), Jammu. Comments were issued on 11.10.2013. Compliance from State 11.08 11.08 17.09.2013 Government awaited. 69 Const of FPW in Ramsoo Area under Save Comments were issued on 11.10.2013. Compliance from State 10.57 10.57 17.09.2013 Ramsoo, Jammu. Government awaited. 70 Const of FPW on d/s of National Highway on Comments were issued on 28.10.2013. Compliance received 12.47 river Tarnah near Villages Chadwal, Chhapaki, on 18.12.2014. Revised DPR received on 15.06.2015 and Pathwal & Karwal in Teh: Hiranagar, Distt: 12.47 20.09.2013 detailed observation were issued by the field office on Kathua. 29.07.2015 along with arrangment of field visit. Complinace is awaited. 71 Const of FPW on d/s of National Highway on Comments were issued on 28.10.2013. Compliance received 12.37 river Tarnah near Villages Mathura Chak, Chhan on 18.12.2014. Revised DPR received on 15.06.2015 and Chankharian, Rakh Sarkar, Gujjar Basti & 12.37 20.09.2013 detailed observation were issued by the field office on Rattanu Chak Belian in Teh: Hiranagar, Distt: 29.07.2015 along with arrangment of field visit. Complinace is Kathua. awaited. 72 Const of FPW on u/s of National Highway on Comments were issued on 28.10.2013. Compliance received 12.46 both banks of river Tarnah near Villages Kot on 18.12.2014. Revised DPR received on 15.06.2015 and Quasba, Pacca Kotha & Salan in Teh: 12.46 20.09.2013 detailed observation were issued by the field office on Hiranagar, Distt: Kathua. 29.07.2015 along with arrangment of field visit. Complinace is awaited. 73 Const of FPW on d/s of National Highway on Comments were issued on 28.10.2013. Compliance received 12.48 both banks of river Tarnah near Villages Kunthal on 18.12.2014. Revised DPR received on 15.06.2015 and & Jangi Chak in Teh: Hiranagar, Distt: Kathua. 12.48 20.09.2013 detailed observation were issued by the field office on 29.07.2015 along with arrangment of field visit. Complinace is awaited. 74 Const of FPW on d/s of National Highway on Comments were issued by M&A Dte, CWC, Jammu on 12.49 both banks of Bein Nallah near Villages Panj 28.10.2013. Compliance received on 18.12.2014. Revised Grain, Muthi Charu, Kattal Brahmana, Chann 12.49 20.09.2013 DPR received on 15.06.2015 and detailed observation were Khatrian & Londi in Teh: Hiranagar, Distt: issued by the field office on 29.07.2015 along with arrangment Kathua. of field visit. Complinace is awaited. 75 Const of FPW/ anti erosion works on Left Bank Revised DPR with cost Rs. 14.79 Crore has been received on 14.79 of River Chenab Village Baradhari, Reasi to to 14.79 08.10.2013 14.01.2016 and is under scrutiny of field office. Bhabber 76 Const of FPW on various nallahs i.e Tipri, Kutan Comments were issued by M&A Dte, CWC, Jammu on 12.40 & Left Bank of River Chenab in Thathri, District 12.40 08.10.2013 29.10.2013. Compliance from State Government awaited. Doda 77 Construction of FPW works on various Nallahs Comments were issued by M&A Dte, CWC, Jammu on 12.46 i.e. Jangalwar, Nodi, Misri, Bhella/ Chilgad & 29.10.2013. Compliance from State Government awaited. 12.46 08.10.2013 Bhallara Nallah in the Thathri Distt: Doda.

78 Construction of FPW works on Gunda & Ghat Comments were issued by M&A Dte, CWC, Jammu on 11.85 11.85 20.11.2013 Area in Teh & Distt: Doda. 27.11.2013. Compliance from State Government awaited. 79 Flood Manegement on D/s of 2313.85 12.02.2014 DPR was examined and comments was communicated to the 2313.85 Akhnoor bridge, Jammu. State Govt. on 12.06.2014 and 12.08.2014. State Govt. was also requested to send five copies of modified DPR having compliance of commnets issued so that these can be forwarded to Indus Wing, MOWR as well as CA(HW&F) Dte, Hyd(N) Dte. and Embankment Dte for detailed examination. Reply to CWC's comments was received on 7/01/2015 with schedule of rates-2012. Five copies of revised DPR is still awaited. 80 Erosion control and FP works on various Nallahs the DPR was submitted to M&A Dte. Jammu and after detailed 12.42 of Chatroo, Keshwan in Inderwal Constituency, examination the DPR was not found in order and hence 12.42 24.02.2014 Distt- Kishtwar comments issued on 22.04.2014. No compliance has been received from state Govt. 81 FPW on Betar Nallah () The DPR was submitted to M&A Dte. Jammu and after detailed 12.40 examination the DPR was not found in order and comments 12.40 05.03.2014 was issued on 16.04.2014. No compliance has been received from state Govt. so far. 82 FPW on Khanetar, Bainch, Managahr Dhara & The DPR was submitted to M&A Dte. Jammu and after detailed 12.32 Salotri Nallah (Poonch) examination the DPR was not found in order and comments 12.32 05.03.2014 was issued on 16.04.2014. No compliance has been received from state Govt. 83 FPW on Rangar, Pulas, and Ajote. (Poonch) The DPR was submitted to M&A Dte. Jammu and after detailed 12.33 examination the DPR was not found in order and comments 12.33 05.03.2014 was issued on 16.04.2014. No compliance has been received from state Govt. 84 FPW on Bandi Chachian, Shahpur and Nangali The DPR was submitted to M&A Dte. Jammu and after detailed 12.40 Nallah (Poonch) examination the DPR was not found in order and hence 12.40 05.03.2014 comments issued on 16.04.2014. No compliance has been received from state Govt. 85 FPW on Kalai Bridge to confluence point of The DPR was submitted to M&A Dte. Jammu and after detailed 12.40 Drungali Nallah in (Poonch) examination the DPR was not found in order and hence 12.40 05.03.2014 comments issued on 16.04.2014. No compliance has been received from state Govt. 86 FPW on Seikloo, Chaktroo, Kulani, Chakara, The DPR was submitted to M&A Dte. Jammu and after detailed 12.45 Sathra, Trichal and Bholla Nallah (Poonch) examination the DPR was not found in order and hence 12.45 05.03.2014 comments issued on 16.04.2014. No compliance has been received from state Govt. 87 FPW on Poonch River from confluence point of the DPR was submitted to M&A Dte. Jammu and after detailed 12.40 Drungli Nallah to Sher-e-Kashmir Bridge. examination the DPR was not found in order and hence (Poonch) 05.03.2014 comments issued on 16.04.2014. State Govt. submitted revised 12.40 11.09.2014 DPR on 11.09.2014 and after scruitny the comments were reissued on 29.09.2014. complaince awaited.

88 FPW on Poonch River from Sher-e-Kashmir The DPR was submitted to field office, CWC, Jammu and after 12.40 Bridge to Salotri (Poonch) detailed examination, the DPR was not found in order and comments was issued on 16.04.2014. State Govt. had 05.03.2014 12.40 submitted revised DPR on 11.09.2014 and after scruitny the 11.09.2014 comments were again issued on 29.09.2014. No compliance of the comments has ben received from state Govt. State/UT wise details of Flood Management Project Proposals ( coordinated by CWC) during XII Plan inculding spillovers as on 21.03.2016

Sl Estt. Cost Date of Under Name of works/scheme Status of examination Cleared Returned Awaited No. (Rs. In Cr) Receipt examination 89 FPW on Chang, Sangla, Padhali and other The DPR was submitted to field office, CWC, Jammu and after 12.40 Nallahs feeding Suran River (Poonch) detailed examination, the DPR was not found in order and 12.40 05.03.2014 comments was issued on 16.04.2014. No compliance of the comments has ben received from state Govt.

90 FPW in Mendhar and its adjoining Nallahs. The DPR was submitted to field office, CWC, Jammu and after 12.45 (Poonch) detailed examination, the DPR was not found in order and 12.45 05.03.2014 comments was issued on 16.04.2014. No compliance of the comments has ben received from state Govt.

91 Construction of protection works by way of The DPR was submitted to field office, CWC, Jammu after 49.82 construction and revetment to protect defence scruitny the preliminary observation were issued on posts and village on R/S of river Basanter 29.10.2014.The revised DPR was recd in field office on 04.02.2015 and the same was sent to CE (IBO) on 06.02.2015 for further submission to CWC(HQ), New Delhi for detailed examination. The Said DPR has been returned to field office by CE(IBO) and a field visit was done by a team of CWC on 12.05.2015 and the DPR has been sent alongwith the field visit 49.82 09.10.2014 report to CE(IBO) for examintaion. DPR received in FM-I Dte on 24.08.2015 and sent to Hydrology (North) Dte, CWC on 28.08.2015 for examination of hydrological aspects. Comments of Hyd (N) Dte, CWC was forwarded to the State Govt. on 30.11.2015 and after discussion with project authority observation of FM-I Dte was forwarded to State authority on 9.03.2016 for compliance.

92 construction of Embankment of left & Rigtht The DPR was submitted to field office, CWC, Jammu and the 36.77 bank of river Tawi d/s of 3rd city bridge and U/s same has been sent to CE IBO on 13.11.2014 for clarification of the 4th city bridge regarding the project to be considered under FMP as the report shows that main purpose of the project arises due to construction of artiificial lake and the benefits in CBR comprises mailnly of land reclaimation benefits.DPR has been examined in field office and it has been observed that as per 36.77 15.10.2014 latest FMP guidelines, the aspect of reclamation is not covered under FMP.Therefore the proposal can not be considered under FMP scheme.As per the reply received to M&A Dte from CE (IBO) this project can not be considered under FMP and the same has been intimated to State Govt by M&A on 15/01/2015.

93 Construction of flood protection works on Sahar The Prelimanary comments have been sent to Sate Govt. after 76.79 Khad and its tributaries from Village Bhora to scruitny in M&A Dte, Jammu on 30.10.2013 asking State Govt. Village Saidpur district Kathua. to provide details for the comments sent to them. The revised DPR is submitted in field office on 18.07.2014 and comments 76.79 22.08.2013 issued on 12.08.2014. DPR received in FM-I Dte on 24.08.2015 and sent to Hydrology (North) Dte. on 28.08.2015 for examination of hydrological aspects. Comments of Hyd (N) Dte, CWC was forwarded to the State Govt. on 30.11.2015 for compliance. 94 Flood Protection Works from Kalai Bridge to 64.22 12.05.2015 A copy of the project report has been forwarded to Hydrology 64.22 Sher-e-Kashmir Bridge (N) Dte, CWc for detail examination of hydrological aspects on 14.05.2015. The preliminary comments have been sent to State Govt. after examination in FM-I Dte, CWC on 30.06.2015 for compliance. The comments of Hydrology (N) Dte, CWC was forwarded to State Govt. on 04.08.2015. Compliance of the State Govt, has been received on 17.11.2015 and after examination it is it is proposed to carry out mathematical model studies. 95 Flood Protection Works from Shahi Khul 51.00 12.05.2015 A copy of the project report has been forwarded to Hydrology 51.00 Surankot to Kalai Bridge (N) Dte, CWc for detail examination of hydrological aspects on 14.05.2015. The preliminary comments have been sent to State Govt. after examination in FM-I Dte, CWC on 30.06.2015 for compliance. The comments of Hydrology (N) Dte, CWC was forwarded to State Govt. on 04.08.2015. Compliance of the State Govt, has been received on 17.11.2015 and after examination it is it is proposed to carry out mathematical model studies. 96 Construction of FPW in Nowshera Tawi The Prelimanary comments have been sent to Sate Govt. after 31.84 (Manawar Tawi) from Sangpur Village to examination in field office, CWC, Jammu on 13.11.2013 for 31.84 04.10.2013 Lambari (Dhandani) Village, Disst- Rajouri compliance. Revised DPR submitted on 14.01.2016 is under scrutiny in field office 97 Construction of flood protection works on river The scheme has been cleared by CWC( M&A Dte Jammu) and 14.93 Kanji and its tributaries from Bodh Kharboo to also cleared by Planning Commission on 20.09.2011.The Sanjak, Kargil. scheme was not cleared by EC-FMP in 8th meeting of EC-FMP. The State Govt submitted new Budget certificate , FMP-I and other certificate for 2012-13 along with revised MOU for time extension which was forwarded to CE -IBO on 17.01.2013 but it 14.93 27.09.2011 was returned back by CE(IBO) citing that it was to be directly sumbitted to Advisor (WR) by State Government. All the original certificates were returned to State Government on 06.03.2013 advising them to submit it directly to Advisor(WR), New Delhi.

98 Construction of FPW at singpora, kalamsoi and Comments were issued on 12.09.2013.Compliance from State 2.13 passerkot habitation in The Chatroo, Inderwal 2.13 22.08.2013 Governemnt awated. constituency. 99 Construction of FPW on various nallahs in Comments were issued on 20.09.2013.Compliance from State 2.10 Bunda nallah and Urighad Nallah in Inderwal 2.10 22.08.2013 Governemnt is awaited. Constituency, District Kishtwar 100 Construction of FPW in Magger Khad and its Originally schme was submitted with cost Rs. 8.55 cr on 17.39 tributaries in Teh and Distt Kathua 22.08.2013. Revised DPR was examined in M&A Dte, CWC, Jammu and prelimanry observations was sent on 20.09.2013. 17.39 29.07.2015 A revised DPR was submitted by the State Govt. on 29.07.2015 to field office with revised cost of Rs. 17.3915 cr. The preliminary comments were issued on 07.08.2015 and compliance is awaited. 101 Draft comprehensive project report of flood 2083.90 05.11.2009 The project report was examined and comments of FM-I along 2083.90 management programme of river Jhelum and its with BCD(NW&NWS) Dte.of CWC were forwarded to CE(I&FC) tributaries. District Srinagar, Baramula etc. B.C J&K vide this office letter No. 7/73/J&K/2009/FM – I /27 Dt. Ratio 1.60:1 15.01.2010 for compliance. No response from State Govt has been received . State/UT wise details of Flood Management Project Proposals ( coordinated by CWC) during XII Plan inculding spillovers as on 21.03.2016

Sl Estt. Cost Date of Under Name of works/scheme Status of examination Cleared Returned Awaited No. (Rs. In Cr) Receipt examination 102 Construction of Flood protection works from 45.75 18.08.2015 The preliminary comments were issued to State Govt. by Daragaloon to Balnoi on Mendhar Nallah, Distt. (Field) Director (M&A), Jammu on 21.08.2015 and compliance is 45.75 Poonch awaited. 103 Training of river Tawi from Manwal to exit of Indo- 290 23.12.2015 DPR is under scruitiny in field office. Preliminary observation was 290.00 Pak border at spots and Balole Nallah Distt- issued on 1201.2016. Compliance received on 15.01.2016 is Jammu under process. Observations on earlier compliance and during field visit have been issued on 08.02.2016 and 25.02.2016 respectively. Field visit carried out on 10.02.2016 & 11.02.2016.

104 Const. of FWP at various spots between village 24.95 22.01.2016 DPR of cost Rs 24.63 Crore has been received and observations 24.95 Kheri to Sai on left & right side of Aik nallah in issued on 14.01.2016. Revised DPR has been examined and tehsil Bishnah and Suchetgarh. D/S NH-1A observations isued on 25.02.2016 by field office.

6966.73 1140.94 51.70 5649.88 124.21 20 Punjab 1 Consolidated Project proposal for work to be 161.0464 21.01.2013 The Scheme has been examined and found to be techno- 161.05 executed along Indo-Pak border on River Ravi economically viable; accepted by the AC-MOWR in its 119th and its tribuataries Ujh to check land erosion for meeting held on 29.08.2013; investtment clearance accorded safety of village Abadies Border fencing & other by the Planning Commission vide 12(1)/19/2011-WR dt. defense installation. 07.10.2013 for completion by 2014-15. DPR cleared from IWT angle vide 3/3/2008-IT/10086 dt. 26-7-2013. Case of release of Rs. 20.00 cr as CA (2014-15) sent to MOWR on 16-10-2014.

2 Construction of flood protection works along 11.02 It has been included under FMP in 7th meeting of EC-FMP held 11.02 River Ujh in district Gurudaspur, Punjab (Pb-5) on 18-08-2011. Rs. 5.51 crore as C.A was released to State Govt. as 1st installment on 23.03.2012. Proposal for release of balance C.A amounting to 2.755 crore was received on 20.06.2012 and examined in M&A Dte and observed that request for C.A. was not sent as per the FMP guidelines and relevent proforma and certificates. M&A Dte requested to provide physical and financial progress of originally approved works. Proposal for release of 275.5 lacs has been examined and returned to State authority on 08.07.2014 for the complaince of observations.

3 Project Proposal for strengthing (BDS) of 2-R 47.26 19.11.2012 The scheme has been examined and comment/ observation 47.26 and 3-R bandh and construction pucca road (Field Office) was sent to State Government vide letter dated 03.04.2013. along river between RD 76-18253 m of 2R 20.03.2013 The DPR for this project has also been forwarded to Director, bandh and between RD 1220-55373 m of 3-R (CWC Hq) Hydrology(N), Dte , CWC for detailed examination of bandh in district Jalandhar (Punjab) Hydrology vide letter dated 07.05.2013. Comment of the Hydrology(N) Dte,CWC were sent to State Government vide letter dated 04.06.2013, 07.10.2014, and 30.06.2015 for compliance. 4 Constructing/Repairing and Strengthening of 85.06 23.01.2013 The DPR for this project was forwarded to Hydrology(N), Dte , 85.06 Flood Protection Works on River Sutlej in border (Field Office) CWC for detailed examination of Hydrology vide letter dated area of Border Districts Ferozpur, Fazilka & Tarn 04.06.2013 04.06.2013. The comments of the Director, Hydrology(N), CWC Taran” under BADP (Punjab) (CWC,Hq) was forwarded to the State Goverment vide letter dated 14.06.2013 for compliance.Reply from State Govt. is still Awaited 5 Project proposal for Swan River Management 284.98 15.04.2015 The project proposal has been examined and observation was 284.98 and Integrated Land Development project sent to State Govt. on 07.07.2015 for complaince. The DPR for starting from Punjab boundary (d/s of this project has also been forwarded to Director, Hydrology(N), Santokhgarh Bridge) to its confluence point with Dte , CWC for detailed examination of Hydrology vide letter river Sutlej at u/s Thana Bridge near Sri dated 21.04.2015. Comments of FM-I was forwarded to State Anandpur Sahib including u/s & d/s flood Govt. on 07.07.2015. Observation of Hydrology Dte was protection works. communicated to State Govt. on 20.07.2015. Compliance of the comments by State Govt. was received on 11.09.2015 and 23.11.2015. A copy of the DPR was forwarded to Cost Appraisal (HWF) Dte, CWC by FM-I Dte on 23.10.2015 and the reply of Cost Apprisal Dte was further sent to State Govt. on 4.11.2015. Compliance of the comments of Cost Appraisal Dte has been received on 2.11.2015 and sent to State Govt. for compliance. Vetting of T&P items of the project has been recd from CMC Dte, CWC. After discussion with Project authority observations was sent to Govt. of Punjab on 24.02.2016 for compliance. 6 Construction of Flood Protection Works along 46.12 22.09.2014 The Scheme was accorded clearance by AC-MOWR in its 46.12 left and right side of River Beas in Districts 113th meeting held on 12.01.2012. Investment clerance was Gurudaspur, Hoshiarpur and Kapurthala. accorded by Planning Commission on 22.05.2012 with time of completion upto 31.03.2013. Further, time extension up to 31.03.2015 was granted by Planning Commission on 22.08.2014. FMP-I, I.C and other certificates was sent to MoWR on 25.11.2014 for inclusion under FMP by IMC-FMP.

7 Canalizing Sakki Kiran Nallah from RD 18000 to 118.05 05.04.2004 The Scheme was accorded clearance by TAC of MOWR in its 118.05 510000 in District Amritsar and Gurudaspur 85th meeting held on 22.02.2006 for an estimated cost of Rs. Punjab. District: Amritsar and Gurudaspur (Pb- 118.05 cr. Inv. Clearance was accorded by the Planning 1) Commission vide No.12(1)/19/06-WR dt. 10.06.2008. The scheme was included under FMP in its 2nd meeting of EC-FMP held on 6.08.2008 with FMP cost of Rs. 111.39 crore (C.A 83.5425 cr.) against the submitted project cost of Rs 118.05 crores. 1st installment of CA of Rs. 21.51 Cr. was released in Nov. 2008. Work on this project was started in 2009-10.An Exp. of Rs. 28.58 on construction of V.R. Bridges was incurred till Sept, 2013. Monitoring visit was done in Dec., 2010. Meanwhile due to defence considerations, the cost was revised to Rs. 350.0 cr which was returned to State Govt. on 15-01- 2013 stating that no cost escalation shall be allowed once it is approved under FMP. State Govt. submitted revised Project estimate of Rs. 400.26 Cr. in Sept, 2014 to Field Office. The proposal was examined by field office and returned to State Govt. for complaince of the observation on 15.10.2014. State/UT wise details of Flood Management Project Proposals ( coordinated by CWC) during XII Plan inculding spillovers as on 21.03.2016

Sl Estt. Cost Date of Under Name of works/scheme Status of examination Cleared Returned Awaited No. (Rs. In Cr) Receipt examination 8 Construction of FPW along I – R Bandh on river 11.67 12.02.2009 The scheme has been cleared vide CWC letter dated 1.05.2009. 11.67 Sutlej and local protection works along Choes in The investment Clearance has also been accorded by the district Nawanshehar District: Nawanshehar (Pb- Planning Commission vide letter No.2(408)/2008-WR dated 2) 18.05.2009. Further the revised proposal costing Rs 11.67 cr was cleared by CWC vide letter dated 03-05-2011. Investment Clearance has been given by Planning Commission vide letter dated 03.05.11. Request for release of Rs 258.70 lakh under FMP during 2014-15 was received in filed office of CWC at Chandigarh which was returned to State Govt on 4.3.2015 as the same was not as per FMP guidelines.The proposal has been again received in field office which has been returned to State Govt.

9 Plugging and Stg. breaches and bringing to 8.05 12.02.2009 The scheme has been cleared vide CWC letter dated 8.05 design section of FPE along Mehangerwal choe, 02.06.2009.The investment Clearance has also been accorded Arniala choe and Gambowal choe in distt- by the Planning Commission vide letterNo.12(1)/19/2009-WR Hoshiarpur (Part – I) (Pb-3) dated 09.07.2009 with the completion time of 31.03.2011. GoP requested P.C for time extenstion upto 31.03.2015 vide their letter dated 2.11.2014.

10 Plugging and Stg. Breaches and bringing to 11.27 12.02.2009 The scheme has been cleared vide CWC letter dated 11.27 design section of FPE along Choes in district 08.06.2009.The investment Clearance has also been accorded Hoshiarpur (Part I) District: Hoshiarpur (Pb-4) by the Planning Commission vide letter No.12(1)/19/2009-WR dated 09.07.2009 with the completion time of 31.03.2011. GoP requested P.C for time extenstion upto 31.03.2015 vide their letter dated 2.11.2014.

727.3864 310.0864 0.0000 417.3000 0.0000 21 Andhra Pradesh 1 Standardization of Flood banks of river 26.12.2006 DPR was received on 26.12.2006 and sent to the 815.00 Godavari in Andhra Pradesh specialized Directorates of CWC on 11.01.2007. Observations of CWC were sent to the State Govt. on 14.04.2007, 17.05.2007, 9.10.2007 and 20.01.2009. As no 815.00 reply was received from the State Government since long, a reminder was issued on 19.01.2011 to pursue the reply. As no response is received since long, the DPR has been deleted from the list of pending schemes.

2 Standardization of flood banks of river 22.12.2006 DPR was received on 22.12.2006 and sent to the Vamsadhara and Nagavali in Andhra specialized Directorates of CWC on 11.01.2007. 310.7 Pradesh Observations of CWC were sent to the State Govt. on 13.07.2007, and 18.03.2009. As no reply was received 310.7 from the State Government since long, a reminder was issued on 19.01.2011 to pursue the reply. As no response has been received since long, the DPR has been deleted from the list of pending schemes.

1125.7000 0.0000 1125.7000 0.000 0.0000 22 Goa 1 Flood Control and Improvement of Waterway 10.07.2008 The DPR was received in CWC on 10.07.2008. Investment Clearance 8.84 to Bicholim River in Bicholim Taluka of Goa from the Planning Commission was given vide letter dated 19.12.2008 State 8.84 and was scheduled to be completed by 31 March 2011. Funds have been provided for the scheme. The works of the scheme has been completed during 2010-11. Cleared

2 Flood control Measures for Improvement of 22.12.2006 The DPR was received in CWC on 8.10.2009. Scheme Waterway of Valvanta River at Bicholim was examined in CWC and found techno-economically Taluka of Goa State viable. Investment Clearance from the Planning Commission has been received and was scheduled to be completed by 31 March 2012.. The scheme was incuded under FMP by EC in its 6th meeting held on 12.07.2010. 13.89 Funds amounting to Rs.3.35 Crore were provided to the 13.89 scheme during 2010-11. The Proposal for releasing the Second installment /reimbursement of 5.95 Crore during 2012-13 to the State Govt.of. Goa received from CE, Mon (S) was examined and submitted to Commissioner (Ganga) MoWR vide letter dated 27/9/12. Cleared

22.7300 22.7300 0.0000 0.000 0.0000 23 Puducherry 1 Project Report on Flood Protection Works in Proposal was received on 25.07.2008. After examination by CWC, the 139.67 Yanam Region of Puducherry, proposal was cleared in 101st TAC of MOWR, held on 30.11.2009. Investment Clearance has been accorded by the Planning Commission and funds amounting to Rs.7.5 Crore were released during 2010-11 and was scheduled to be completed by 31 March 2012.. Monitoring team of CWC at Bangalore visited the project in July, 2011 and inspected the on- going works. It was found by the monitoring team that the progress was unsatisfactory. Monitoring team has not recommended for release of 2nd installment as the Government of Puducherry has not submitted the required certificates viz. State Budget allocation for 2011-12, concurrent evaluation report and construction programme till completion of the project. Government of Puducherry has been requested for sending the required documents vide letters dated 16.08.2011, 3.11.2011, 14.12.2011 and 20.01.2012. Government of Puducherry, vide letter dated 14.10.2011, submitted 139.67 25.07.2008 the revised quantities of project for which Government of Puducherry has been requested to submit the revised DPR vide letter dated 3.11.2011. The response from CE, PWD, Govt of Puducherry was received on 13/4/2012 which was replied on dated 25/4/2012 for sending the required documents. Concurrent Evaluation Report along with physical and financial progress report was received from CE, PWD, Govt of Puducherry on 01/05/2012. However, the observations to the same was sent vide letter dated 14/05/2012. It was known through Govt of Puducherry letter dated 13/09/2012 that a CBI enquiry was being conducted for the allegedly forged damage assessment report and the scheme was temporarily kept on hold. In this regard, a letters dated 26/03/2013 and 26/04/2013 have been received from MOWR that if the findings of CBI do not affect the viability and justification of the project then the required documents many be sent to CWC for further processing and the work may be resumed. The comments on the hydrology aspect of the project was sent to CE,PWD, Puducherry 139.6700 139.6700 0.0000 0.000 0.0000 State/UT wise details of Flood Management Project Proposals ( coordinated by CWC) during XII Plan inculding spillovers as on 21.03.2016

Sl Estt. Cost Date of Under Name of works/scheme Status of examination Cleared Returned Awaited No. (Rs. In Cr) Receipt examination 24 Maharashtra 1 Flood Protection works for Lendi Nalla at 29.11.2010 DPR was received in CWC on 29.11.2010 and examined in CWC. The 24.37 Katol Town in Nagpur District of Maharashtra proposal was found techno-economically viable and accepted in 112th State, meeting of TAC-MoWR held on 14.09.2011. Investment Clearance from the Planning Commission was given vide letter dated 24.10.2011 24.37 and was scheduled to be completed by 31 March 2014. Letters were sent to the CE, Mon(C), CWC for sending revised FMP-1 and seeking time extension from Planning Commission for the above project. However, the response from the State Govt. is still awaited. 2 Construction of structures for protection from 22.12.2006 DPR was received in CWC on 15.12.2008. The comments flood near Samadhi of late Dy. Prime Minister of CWC were sent to the State Govt on 21.07.2008. of , Shri Yashvantrao Chavan on the 14.65 Observations of UT&SS Dte. were sent to the Project 14.65 bank of river Krishna in Satara Dist. of Authority on 18.09.2008. As no response has been Maharashtra. received since long, the DPR has been deleted from the list of pending projects. 39.0200 24.3700 14.6500 0.000 0.0000