625 Liberty Avenue, Suite 1700 | , PA 15222 833-MV-SOUTH | [email protected]

www.mpvsouthgate.com

June 15, 2018

Ms. Kimberly D. Bose, Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, D.C. 20426

Re: Mountain Valley Pipeline, LLC Docket No. PF18-4-000 MVP Southgate Project Monthly Status Report No. 1

Dear Ms. Bose:

In compliance with Section 157.21(f)(6) of the Commission’s regulations, Mountain Valley Pipeline, LLC submits in this docket its Monthly Status Report for the MVP Southgate Project covering the period through May 31, 2018.

If you have any questions, please do not hesitate to contact me (412-553-5786; [email protected]) or William Lavarco (202-347-7127; [email protected]). Thank you.

Respectfully submitted,

MOUNTAIN VALLEY PIPELINE, LLC by and through its operator, EQM Gathering Opco, LLC

By: Matthew Eggerding Senior Counsel, Midstream Attachments

cc: Amanda Mardiney, OEP John Peconom, OEP Allen Jacks, Cardno

MOUNTAIN VALLEY PIPELINE, LLC MVP SOUTHGATE PROJECT FERC Docket No. PF18‐4‐000 FERC Pre-Filing Monthly Status Report

Period Ending: May 31, 2018 Status Report No.: 1

On May 3, 2018, Mountain Valley Pipeline, LLC submitted a request to use the Federal Energy Regulatory Commission’s Pre-Filing review process for the MVP Southgate Project (“Project”). In a letter dated May 15, 2018, the Commission subsequently approved Mountain Valley’s request and assigned the Project to FERC Docket No. PF18-4-000.

This Monthly Status Report provides a brief summary of recent Project activities, including surveys, stakeholder communications, and agency consultations, that have occurred during the reporting period.

Project Scope, Filings and Schedule

Mountain Valley is seeking a Certificate of Public Convenience and Necessity from the FERC pursuant to Section 7(c) of the Natural Gas Act to construct and operate the MVP Southgate Project located in Pittsylvania County, and Rockingham and Alamance Counties, North Carolina. Mountain Valley proposes to construct approximately 72-miles of 24-inch-diameter natural gas pipeline, two proposed compressor stations, and four meter (interconnect) stations and other ancillary facilities required for the safe and reliable operation of the pipeline.

Summary of Mountain Valley FERC Filings Date Submitted by Content 5/3/2018 Mountain Valley Request to Initiate NEPA Pre-Filing Process 6/14/2018 Mountain Valley Draft Resource Report 1, Resource Report 10-Summary of Alternatives

Schedule There are no updates to the proposed Project schedule.

Pipeline

Land Status • 71% survey permissions obtained for proposed route. • 0% right-of-way acquired by length. • 283 parcels containing access roads identified to date, 0% acquired. • 8 ancillary sites identified to date, 0% acquired.

Page 2 of 20 MOUNTAIN VALLEY PIPELINE, LLC MVP SOUTHGATE PROJECT FERC Docket No. PF18‐4‐000 FERC Pre-Filing Monthly Status Report

Period Ending: May 31, 2018 Status Report No.: 1

Environmental Surveys (through 5/29/2018) • Biological o 14% of the proposed route has been surveyed for wetlands and waterbodies. • Cultural o 11% of the proposed route has been surveyed for cultural resources. • Threatened and Endangered (T&E Species) o 14% of the proposed route has been surveyed for T&E species. • Aquatics o 0% of the proposed route has been surveyed for aquatic resources.

Engineering • Civil Survey Progress - (15.5 miles / 21.5% complete) • Preliminary mainline valve site selection is on‐going . • Preliminary pig launcher/receiver site selection and design is on‐going .

Compressor Stations

Lambert Station (Pittsylvania County, Virginia) at milepost 0.0 and Russell Station (Rockingham County, North Carolina) at milepost 26.

• Land o Proposed sites have been identified and survey permission granted for both station sites. • Environmental o Stream and wetland, rare, threatened and endangered species, and cultural surveys are ongoing. • Engineering o Preliminary compressor station designs are underway for both stations.

Interconnect Facilities

Lambert Interconnect, LN 3600 Interconnect, T-15 Dan River Interconnect, and T-21 Haw River Interconnect.

• Land o Locations have been identified and survey permission has been requested. • Environmental o Stream and wetland, rare, threatened and endangered species, and cultural surveys are ongoing. • Engineering ‐going. o Preliminary Interconnect station size and material sizing is on

Page 3 of 20 MOUNTAIN VALLEY PIPELINE, LLC MVP SOUTHGATE PROJECT FERC Docket No. PF18‐4‐000 FERC Pre-Filing Monthly Status Report

Period Ending: May 31, 2018 Status Report No.: 1

Resource Reports

Initial Draft Resource Report 1 and the Resource Report 10-Summary of Alternatives were filed with the Commission on June 14, 2018.

Stakeholder Communications

Mountain Valley is committed to actively engage stakeholders throughout the life cycle of the Project and has identified steps to ensure successful ongoing communication with stakeholders, including establishing a Project website (www.mvpsouthgate.com), a toll-free phone line (833- MV-SOUTH), and e-mail ([email protected]). This process was described in the project- specific Public, Stakeholder, and Agency Participation Plan (as filed with the Commission on May 3, 2018). Mountain Valley will continue to meet with stakeholders to discuss the ongoing efforts associated with the Project. Communications to date include:

• Government and Non-Government Communications o See attached Table 1.

In addition, Mountain Valley is proposing three (3) open houses (one in in each affected county) on June 25, 26, and 28, 2018 to provide information about the Project to all interested federal and state agencies, stakeholders, as well as the public. The dates and locations of the open houses are listed below: • June 25, 2018 o 5:30pm-7:30pm-The Palladium, 1272 Plaza Drive Burlington, NC 27215 • June 26, 2018 o 5:30pm-7:30pm-The Reidsville Event Center, 223 S. Scales Street Reidsville, NC 27230 • June 28, 2018 o 5:30pm-7:30pm-Olde Dominion Agricultural Complex, 19783 U.S. Hwy 29 South Chatham, VA 24531

Agency Communications

Mountain Valley continues to consult with federal, state and local government representatives to seek input, provide updates as the Project progresses, and extend an open invitation to all public meetings. Communications to date include:

o Agency Communications – See attached Table 2. o Bi-weekly phone calls with FERC started on May 31, 2018 and will continue though the Pre-filing Process.

Permitting Table

o A list of relevant Permits and Approvals are included in Table 3.

Page 4 of 20 MOUNTAIN VALLEY PIPELINE, LLC MVP SOUTHGATE PROJECT FERC Docket No. PF18‐4‐000 FERC Pre-Filing Monthly Status Report

Period Ending: May 31, 2018 Status Report No.: 1

TABLE 1

GOVERNMENT AND NON-GOVERNMENT COMMUNICATIONS

Stakeholder Affiliation Name Title/Position Method of Contact Federal Senator Meeting and Letter Office of US Senator Mark Warner, Virginia Kenneth S. Johnson, Senior Policy Advisor Meeting and Letter Jr. United States Senate Senator Meeting and Letter Office of US Senator Tim Kaine, Virginia Nick Barbash Legislative Assistant Meeting and Letter United States Senate Thom Tillis Senator Meeting and Letter Office of US Senator Thom Tillis, North Torie Ness Legislative Assistant Meeting and Letter Carolina United States Senate Richard Burr Senator Meeting and Letter Office of US Senator Richard Burr, North Ben Khouri Press Secretary Meeting and Letter Carolina United States House of Representatives Thomas Garrett Representative Meeting and Letter Office of US Representative Thomas Garrett, Tripp Grant Legislative Assistant Meeting and Letter North Carolina United States House of Representatives Mark Walker Representative Meeting and Letter Office of US Representative Mark Walker, Ryan Walker Legislative Assistant Meeting and Letter North Carolina Virginia (State) Commonwealth of Virginia Ralph Northram Governor Letter Office of The Governor, Commonwealth of Clark Mercer Chief of Staff Meeting and letter Virginia Lt. Governor, Commonwealth of Virginia Justin Fairfax Lt. Governor Meeting and letter Secretary of Commerce, Commonwealth Brian Ball Secretary of Commerce Meeting and letter of Virginia Virginia Senate - District 20 William Stanley, Jr Senator Meeting and letter

Page 5 of 20 MOUNTAIN VALLEY PIPELINE, LLC MVP SOUTHGATE PROJECT FERC Docket No. PF18‐4‐000 FERC Pre-Filing Monthly Status Report

Period Ending: May 31, 2018 Status Report No.: 1

TABLE 1

GOVERNMENT AND NON-GOVERNMENT COMMUNICATIONS

Stakeholder Affiliation Name Title/Position Method of Contact Virginia House of Delegates - District 16 Leslie Adams Delegate Meeting and letter Virginia House of Delegates - District 14 Daniel Marshall III Delegate Meeting and letter Virginia House of Delegates - District 9 Charles Poindexter Delegate Meeting Virginia Senate - District 15 Senator Phone call House of Delegates Kirk Cox Speaker of the House Meeting Virginia (Local) Pittsylvania County Robert "Bob" Warren Chair, Board of Letter Supervisors Pittsylvania County Joe Davis Supervisor Letter Pittsylvania County Charles Miller Supervisor Letter Pittsylvania County Tim Barber Supervisor Letter Pittsylvania County Elton W. Blackstock Supervisor Letter Pittsylvania County Ben Farmer Supervisor Letter Pittsylvania County Ronald Scearce Vice Chair, Board of Letter Supervisors Pittsylvania County David M. County Administrator Meeting and letter Smitherman Pittsylvania County Matt Rowe Economic Development Meeting and letter Director Danville Utilities Jason Grey Director Meeting and letter City of Danville Joni House Preservation Coordinator Letter City of Danville Telly Tucker Director of Economic Meeting Development North Carolina (State) State of North Carolina Roy Cooper Governor Letter

Page 6 of 20 MOUNTAIN VALLEY PIPELINE, LLC MVP SOUTHGATE PROJECT FERC Docket No. PF18‐4‐000 FERC Pre-Filing Monthly Status Report

Period Ending: May 31, 2018 Status Report No.: 1

TABLE 1

GOVERNMENT AND NON-GOVERNMENT COMMUNICATIONS

Stakeholder Affiliation Name Title/Position Method of Contact Office of Governor Roy Cooper, North Carolina Kristi Jones Chief of Staff Meeting and letter Office of Governor Roy Cooper, North Carolina Stephen Bryant Deputy Chief of Staff Meeting and letter State of North Carolina Dan Forest Lt. Governor Meeting and letter Office of Lt. Governor Dan Forrest, North Hal Weatherman Chief of Staff Meeting and letter Carolina - District 26 Phil Berger Senator Meeting and letter North Carolina Senate - District 24 Rick Gunn Senator Meeting and letter North Carolina Senate - District 8 Bill Rabon Senator Meeting and letter North Carolina Senate - District 6 Harry Brown Senate Majority Leader Meeting and letter North Carolina Senate - District 14 Dan Blue Senate Minority Leader Meeting and letter North Carolina House of Representatives - Bert Jones Representative Meeting and letter District 65 North Carolina House of Representatives - Kyle Hall Representative Meeting and letter District 91 North Carolina House of Representatives - Dennis Riddell Representative Meeting and letter District 64 North Carolina House of Representatives - Stephen Ross Representative Meeting and letter District 63 North Carolina House of Representatives - Darren Jackson House Minority Leader Meeting and letter District 39 North Carolina House of Representatives - David Lewis Representative Meeting and letter District 53 North Carolina House of Representatives - John R. Bell, IV House Majority Leader Meeting and letter District 10 North Carolina House of Representatives Tim Moore Speaker of the House Meeting and letter State of North Carolina Department of Anthony M. Secretary of Commerce Meeting and letter Commerce Copeland North Carolina Department of Administration Machelle Sanders Secretary Meeting and letter

Page 7 of 20 MOUNTAIN VALLEY PIPELINE, LLC MVP SOUTHGATE PROJECT FERC Docket No. PF18‐4‐000 FERC Pre-Filing Monthly Status Report

Period Ending: May 31, 2018 Status Report No.: 1

TABLE 1

GOVERNMENT AND NON-GOVERNMENT COMMUNICATIONS

Stakeholder Affiliation Name Title/Position Method of Contact North Carolina (Local) Rockingham County Lance L. Metzler County Manager Meeting and letter

Rockingham County Jan Critz-Yokeley Director of Economic Meeting and letter Development and Tourism Rockingham County Board of Commissioners Kevin Berger Chairman Meeting and letter Rockingham County Board of Commissioners A. Reece Pyrtle, Jr. Vice-Chairman Meeting and letter Rockingham County Board of Commissioners T. Craig Travis County Commissioner Letter Rockingham County Board of Commissioners Mark F. Richardson County Commissioner Letter Rockingham County Board of Commissioners W. Keith Mabe County Commissioner Letter City of Eden Michael Dougherty Director of Economic Meeting and letter Development City of Eden Debra Galloway Planner Letter City of Graham Nathan Page Planning Director Letter City of Graham Jerry Peterman Mayor Letter City of Graham Lee Kimrey Mayor Pro Tem Letter City of Graham Chip Turner Council Member Letter City of Graham Griffin McClure Council Member Letter City of Graham Melody Wiggins Council Member Letter

City of Burlington Todd Lambert, P.E. City Engineer Meeting and letter City of Burlington Bob Patterson Water Resources Director Meeting and letter Alamance County Brian Baker Director of Parks and Meeting and letter Recreation Alamance County Bryan Hagood County Manager Letter

Page 8 of 20 MOUNTAIN VALLEY PIPELINE, LLC MVP SOUTHGATE PROJECT FERC Docket No. PF18‐4‐000 FERC Pre-Filing Monthly Status Report

Period Ending: May 31, 2018 Status Report No.: 1

TABLE 1

GOVERNMENT AND NON-GOVERNMENT COMMUNICATIONS

Stakeholder Affiliation Name Title/Position Method of Contact Alamance County Historic Properties Jessica Dockery Planner Letter Commission Alamance County Board of Commissioners Amy Scott Galey Board Chair Meeting and letter Alamance County Board of Commissioners Bill Lashley Vice Chair, County Letter Commission Alamance County Board of Commissioners Bob Byrd Commissioner Letter Alamance County Board of Commissioners Tim Sutton Commissioner Letter Alamance County Board of Commissioners Eddie Boswell Commissioner Letter City of Reidsville Jeff Garstka Economic Development Meeting and letter Director City of Reidsville Jay Donecker Council Member Letter City of Reidsville Terresia Scoble Council Member Letter City of Reidsville Donald L. Gorham Council Member Letter City of Reidsville Harry L. Brown Council Member Letter City of Reidsville William Hairston Council Member Letter City of Reidsville James K. Festerman Council Member Letter City of Reidsville Sherri G. Walker Council Member Letter Town of Haw River Mr. Buddy E Boggs Mayor Meeting and letter Town of Haw River H. Lee Lovette Mayor Pro Tem Letter Town of Haw River Kelly Allen Council Member Letter Town of Haw River Jeff Fogleman Council Member Letter Town of Haw River Steve Lineberry Council Member Letter Town of Haw River Sean Tencer Assistant Town Manager Meeting and letter Town of Haw River Melanie Eveker Asst Finance Letter Officer/Town Clerk

Page 9 of 20 MOUNTAIN VALLEY PIPELINE, LLC MVP SOUTHGATE PROJECT FERC Docket No. PF18‐4‐000 FERC Pre-Filing Monthly Status Report

Period Ending: May 31, 2018 Status Report No.: 1

TABLE 1

GOVERNMENT AND NON-GOVERNMENT COMMUNICATIONS

Stakeholder Affiliation Name Title/Position Method of Contact Non-Government Organizations Piedmont Triad Partnership Stan Kelly President & CEO Letter Piedmont Triad Partnership Penny Whiteheart Executive Vice President Letter Piedmont Triad Partnership Jed McMillan Vice President, Letter Government Affairs Alamance Chamber of Commerce Mac Williams President Letter Alamance Chamber of Commerce Reagan Chandler Vice President Letter Gural Danville-Pittsylvania Chamber of Commerce Alexis Ehrhardt President & CEO Letter Virginia Economic Development Partnership Stephen Moret President & CEO Letter Virginia Economic Development Partnership Jason El Koubi Executive Vice President Letter Virginia Economic Development Partnership Vince Barnett Vice President, Business Letter Investment Virginia Economic Development Partnership Christy Morton Vice President, External Letter Affairs Virginia Chamber of Commerce Barry DuVal President & CEO Letter Virginia Chamber of Commerce Ryan Dunn Executive Vice Meeting and letter President of Government and Corporate Affairs North Carolina Chamber of Commerce S. Lewis Ebert President & CEO Meeting and letter North Carolina Chamber of Commerce Gary Salamido, MS Vice President, Letter Governmental Affairs North Carolina Chamber of Commerce Kate Catlin Payne Vice President, Letter Communications North Carolina Economic Development Steve Yost President Meeting and letter Association North Carolina Economic Development Lawrence Bivins Managing Director Meeting and letter Association

Page 10 of 20 MOUNTAIN VALLEY PIPELINE, LLC MVP SOUTHGATE PROJECT FERC Docket No. PF18‐4‐000 FERC Pre-Filing Monthly Status Report

Period Ending: May 31, 2018 Status Report No.: 1

TABLE 1

GOVERNMENT AND NON-GOVERNMENT COMMUNICATIONS

Stakeholder Affiliation Name Title/Position Method of Contact Economic Development Partnership of North Chris Chung CEO Meeting and letter Carolina Moving North Carolina Forward Tom Hendrickson President Meeting and letter Copland Fabrics Jason Copland President and CEO Meeting and letter Alamance County Area Chamber of Commerce Mac Williams President Meeting and letter Alamance Community College Algie Gatewood President Meeting and letter Alamance Community College Tom Hartman Director of Administrative Meeting and letter Services Alamance Community College Cindy Day Collie Vice President of Meeting and letter Administrative and Fiscal Services Pittsylvania Historical Society Larry Aaron President Letter Rockingham County Historical Society Jordan Rossi Executive Director Letter Dan River Basin Association Tiffany Haworth Executive Director Meeting Dan River Basin Association Jenny Edwards Program manager Meeting Dan River Basin Association Robin Light Office manager Meeting Dan River Basin Association Mark Bishopric Board member Meeting Haw River Assembly Elaine Chiosso Executive Director Meeting Haw River Assembly Emily Sutton Haw Riverkeeper Meeting Southern Environmental Law Center Geoff Gisler Staff attorney Meeting

Page 11 of 20 MOUNTAIN VALLEY PIPELINE, LLC MVP SOUTHGATE PROJECT FERC Docket No. PF18‐4‐000 FERC Pre-Filing Monthly Status Report

Period Ending: May 31, 2018 Status Report No.: 1

TABLE 2

AGENCY COMMUNICATIONS

Correspondence Agency Agency Contact Date a Correspondence Received Type Federal U.S. Army Corps of David Bailey, Project Telephone 4/16/2018 Called to discuss Project and to arrange in-person Engineers (USACE) Manager meeting. USACE in acknowledgment of meeting. – Wilmington District Email 4/17/2018 Requested pre-app meeting. Email 4/18/2018 Confirming meeting details and sent agenda. Email 4/27/2018 Met on 5/4/2018 to introduce the Project and discussed In-person meeting 5/4/2018 permitting and lessons learned from Mountain Valley Pipeline. USACE provided a form to fill out. Email 5/7/2018 Provided and update on the surveys and provided Email 6/4/2018 centerline shapefiles. Telephone 6/13/2018 Discussion on current centerline USACE – Norfolk Tom Walker, Regulatory Skype meeting 4/24/2018 Introduction to the Project. District Chief

Jennifer Fry, Western Section Chief

Todd Miller, Southern Section Chief U.S. Fish & Wildlife Bryan Tompkins, Telephone 4/16/2018 Introduction to the Project. Service (FWS) – North Conservation Biologist In-person meeting 5/4/18 Carolina 5/10/18 FWS – North Carolina John Ellis, Conservation Telephone 4/24/2018 Called to discuss Project and scheduled introduction Biologist In-person meeting 5/4/2018 meeting for 5/4/2018. Met on 5/4/2018 and 5/10/2018 In person meeting 5/10/2018 and introduced the Project and discussed permitting. John will be the contact person. FWS – Virginia Troy Anderson, Telephone 4/24/2018 Called to discuss Project and scheduled introduction Conservation Biologist In-person meeting 5/30/2018 meeting. Met on 5/30/2018 and introduced the Project. Troy requested online project review, official species list and spp conclusion table. Troy will be the contact person.

Page 12 of 20 MOUNTAIN VALLEY PIPELINE, LLC MVP SOUTHGATE PROJECT FERC Docket No. PF18‐4‐000 FERC Pre-Filing Monthly Status Report

Period Ending: May 31, 2018 Status Report No.: 1

TABLE 2

AGENCY COMMUNICATIONS

Correspondence Agency Agency Contact Date a Correspondence Received Type Virginia Virginia Department of Tyler Meader, Project Telephone 5/18/2018 Tyler called to discuss database, requested KMZ but can Conservation and Review Assistant pull data based on May 2018 PDF of route. Recreation (VDCR) Virginia Department of Roger Kirchen, Director, Letter 4/27/2018 Request for VDHR’s initial review of Project. Historic Resources Review and Compliance Email 4/27/2018 Received VDHR’s email receipt of request for Project (VDHR) Project Review review. Telephone 5/17/2018 Introduction to the Project and discussed methods and Marc Holma, Architectural Email 6/4/2018 agency review. Historian Provided an update on surveys, submitted detailed work plans, and provided centerline shapefiles. Libby Cook, Project Review Analyst Virginia Department of Amy Ewing, Project Telephone 4/25/2018 Left a voicemail to introduce the Project. Game and Inland Manager Telephone 5/30/2018 Participated by telephone a Project meeting. Fisheries (VDGIF) Virginia Department of Melanie Davenport & Telephone 4/26/2018 Introduction to the Project; discussed the permitting Environmental Quality James Holden, Director, approach, and lessons learned. VADEQ to discuss (VDEQ) Permitting Branch internally and respond to team within 2-3 weeks on strategy. Virginia Marine Randy Owen. Project Telephone 4/25/2018 Introduction to the Project and discussed the five VMRC Resources Commission Manager regulated streams. (VMRC) VDCR Jason Bulluck, Telephone 4/16/2018 Left a voicemail. Environmental Manager II - Telephone 6/6/2018 Spoke with Joe Weber. Division Director, Natural Heritage VDCR Rene Hypes, Program Telephone 4/17/2018 Introduction to the Project Coordinator Email 6/8/2018 DCR-DNH provided comments, invoice and maps.

Page 13 of 20 MOUNTAIN VALLEY PIPELINE, LLC MVP SOUTHGATE PROJECT FERC Docket No. PF18‐4‐000 FERC Pre-Filing Monthly Status Report

Period Ending: May 31, 2018 Status Report No.: 1

TABLE 2

AGENCY COMMUNICATIONS

Correspondence Agency Agency Contact Date a Correspondence Received Type North Carolina North Carolina Sue Homewood, Sr. Telephone 4/16/2018 Introduction to the Project. Department of Environmental Scientist Email 4/17/2018 NCDEQ in receipt and acknowledgement of meeting. Environmental Quality Telephone 4/18/2018 Follow-up with meeting and logistics. (NCDEQ) Email 4/18/2018 Scheduled introduction meeting for 5/4/2018. Email 4/18/2018 NCDEQ in receipt of email meeting request and have Email 4/19/2018 accepted. NCDEQ responding to email regarding meeting logistics. Email 6/4/2018 Provided and update on the surveys and provided centerline shapefiles. North Carolina State Renee Gledhill-Earley, Letter 4/27/2018 Request for HPO’s initial review of Project. Historic Preservation Environmental Review Email 4/27/2018 Received email receipt from DCR Reviewer of initial Office (NC HPO) Coordinator review request. Telephone 5/10/2018 Introduction of Project and discussion of methods and agency review. Email 5/22/2018 NH HPO request and no need for another meeting. Email 5/29/2018 Follow-up on use of route shapefiles. Email 6/4/2018 Provided an update on surveys, submitted detailed work plans, and provided centerline shapefiles.

NC HPO Ramona M. Bartos Letter 5/21/2018 Received recommendations and requests from the NC HPO. NC HPO Susan Myers, Assistant Email 5/22/2018 Sent information the NCECHO directory (county State Archaeologist and resources). Site Registrar North Carolina Wildlife Olivia Munzer / Vann Email 4/27/2018 NCWRC in receipt for meeting. Resources Commission Stancil Meeting 5/4/2018 Project introduction (NCWRC) Meeting 5/10/2018 Species discussion with USFWS

Page 14 of 20 MOUNTAIN VALLEY PIPELINE, LLC MVP SOUTHGATE PROJECT FERC Docket No. PF18‐4‐000 FERC Pre-Filing Monthly Status Report

Period Ending: May 31, 2018 Status Report No.: 1

TABLE 2

AGENCY COMMUNICATIONS

Correspondence Agency Agency Contact Date a Correspondence Received Type Native American Tribes Catawba Indian Nation Wenonah G. Haire, Tribal Letter 5/25/18 Project Introduction Letter Historic Preservation Email 6/1/18 Email with additional introductory information Officer Eastern Band of Russell Townsend, Tribal Letter 5/25/18 Project Introduction Letter Cherokee Indian Historic Preservation Phone call 5/31/18 Call on Project Introduction Officer Email 6/1/18 Email with additional introductory information Muscogee (Creek) Raelynn Butler, Manager, Letter 5/25/18 Project Introduction Letter Nation Historic and Cultural Email 6/1/18 Email with introductory information Preservation Email 6/8/18 Email – outside of area of interest, contact if change Tuscarora Nation Bryan Printup, Letter 5/25/18 Project Introduction Letter Representative Email 6/6/18 Email with introductory information Pawmunkey Indian Robert Gray, Letter 5/25/18 Project Introduction Letter Tribe Representative Call 5/31/18 Call of Project information, Chief Gray stated that no interest in further communication, outside area of interest Delaware Nation, Kim Penrod, Director of Letter 5/25/18 Project Introduction Letter Oklahoma Cultural Resources Email 6/6/18 Email with introductory information Delaware Tribe of Brice Obermeyer, Historic Letter 5/25/18 Project Introduction Letter Indians Preservation Director Email 6/6/18 Email with introductory information Email 6/7/18 Email – outside of area of interest Eastern Shawnee Tribe Brett Barnes, Tribal Historic Letter 5/25/18 Project Introduction Letter of Oklahoma Preservation Officer Email 6/6/18 Email with introductory information Chickahominy Tribe Stephen Adkins, Chief Letter 5/25/18 Project Introduction Letter Call 5/31/18 Call of introduction Email 6/1/18 Email with additional introductory information Chickahominy Tribe Gene Pathfollower Adkins, Letter 5/25/18 Project Introduction Letter Eastern Division Chief Email 6/6/18 Email with introductory information Upper Mattaponi Tribe Kenneth Adams, Chief Letter 5/25/18 Project Introduction Letter Call 5/30/18 Call of introduction Email 6/1/18 Email with additional introductory information

Page 15 of 20 MOUNTAIN VALLEY PIPELINE, LLC MVP SOUTHGATE PROJECT FERC Docket No. PF18‐4‐000 FERC Pre-Filing Monthly Status Report

Period Ending: May 31, 2018 Status Report No.: 1

TABLE 2

AGENCY COMMUNICATIONS

Correspondence Agency Agency Contact Date a Correspondence Received Type Rappahannock Tribe Anne Richardson, Chief Letter 5/25/18 Project Introduction Letter Call 5/30/18 Call of introduction Email 6/1/18 Email with additional introductory information Monacan Nation Dean Branham, Chief Letter 5/25/18 Project Introduction Letter Call 5/30/18 Call of introduction Email 6/1/18 Email with additional introductory information Nansemond Tribe Barry Bass, Chief Letter 5/25/18 Project Introduction Letter Call 5/30/18 Call of introduction Email 6/1/18 Email with additional introductory information Email 6/11/18 Resent introductory information Cheyenne River Sioux Steve Vance, Tribal Historic Letter 5/25/18 Project Introduction Letter Tribe Preservation Officer Email 6/6/18 Email with introductory information Call 6/7/18 Call of introduction Rosebud Sioux Tribe of Russell Eagle Bear, Tribal Letter 5/25/18 Project Introduction Letter Indians Historic Preservation Email 6/6/18 Email with introductory information Officer 6/7/18 Call of introduction

a agency communications are included through 6/14/2018

Page 16 of 20 MOUNTAIN VALLEY PIPELINE, LLC MVP SOUTHGATE PROJECT FERC Docket No. PF18‐4‐000 FERC Pre-Filing Monthly Status Report

Period Ending: May 31, 2018 Status Report No.: 1

TABLE 3

PERMITS AND APPROVALS

Permits/ Approvals/ Administering Agency Agency Address Status/ Comments Consultations Federal Required Permit: Federal Energy Regulatory Commission 888 First Street, NE. Initiate Pre-Filing – May 15, 2018 (FERC) Washington, DC o Certificate of Public Convenience and o Office of Energy Projects (OEP) 20426. File Formal FERC Application – November 2018 Necessity o National Environmental Policy Act (NEPA) – Environmental Impact Statement Review o Pipeline abandonment under Section 7(b) of the Natural Gas Act Required Permit: U.S. Army Corps of Engineers 9100 Arboretum Pre-application meeting Norfolk District Parkway, Ste. 235, o Section 10 Rivers and o Harbors Act o Wilmington District Richmond, VA 23236

o Section 404 Clean Water Act (CWA) 3331 Heritage Trade Drive, Suite 105, Wake Forest, NC 27587 Consultations: U.S. Fish & Wildlife Service 6669 Short Lane Consultations Gloucester, Virginia o Section 7 Endangered o Virginia Field Office Species Act North Carolina Field Office 23061 o o Migratory Bird Treaty Act and Bald and Golden 51F Pylon Drive Eagle Protection Act Raleigh, NC 27606 o Fish and Wildlife Coordination Act Consultations: Federally and State Recognized Tribes of Various Consultations Virginia and North Carolina

Page 17 of 20 MOUNTAIN VALLEY PIPELINE, LLC MVP SOUTHGATE PROJECT FERC Docket No. PF18‐4‐000 FERC Pre-Filing Monthly Status Report

Period Ending: May 31, 2018 Status Report No.: 1

TABLE 3

PERMITS AND APPROVALS

Permits/ Approvals/ Administering Agency Agency Address Status/ Comments Consultations o Section 106, National Historic Preservation Act (16 USC § 470f Virginia Consultations: Virginia Department of Historic Resources 2801 Kensington Consultations Section 106, National Historic (VDHR) Avenue Richmond, VA Preservation Act Division of Review and Compliance 23221 Required Permit: Virginia Marine Resources Commission 2600 Washington Pre-application meeting Permit to Encroach on State- Avenue, 3rd Floor Owned Sub-aqueous Lands Newport News, VA 23607 Required Permit: Virginia Department of Environmental Quality P.O. Box 1105 Pre-application meeting Water Protection Permit & (VDEQ), Water Division Richmond, VA 23218 Individual 401 Water Quality Certification Required Permit: VDEQ, Water Division P.O. Box 1105 Pre-application meeting Virginia Pollution Discharge Richmond, VA 23218 Elimination System Permit for construction stormwater discharge Required Permit: VDEQ, Water Division P.O. Box 1105 Hydrostatic Test Permit Richmond, VA 23218 Required Permit: VDEQ, Air Division 3019 Peters Creek Road Minor New Source Air Quality Roanoke, VA 24019 Permit Consultations: Virginia Department of Game and Inland P.O. Box 90778 Consultations Potential impacts to state- listed Fisheries (VDGIF) Henrico, VA 23228 wildlife species

Page 18 of 20 MOUNTAIN VALLEY PIPELINE, LLC MVP SOUTHGATE PROJECT FERC Docket No. PF18‐4‐000 FERC Pre-Filing Monthly Status Report

Period Ending: May 31, 2018 Status Report No.: 1

TABLE 3

PERMITS AND APPROVALS

Permits/ Approvals/ Administering Agency Agency Address Status/ Comments Consultations Consultations: Virginia Department of Conservation and 600 E Main Street FL Consultations Potential impacts to state-listed Recreation (VDCR) 24, Richmond, VA species and habitat 23219 Required Permit: Virginia Department of Transportation 1401 E. Broad St. Road bonds and crossing (VDOT) Richmond, VA 23219 permits North Carolina Consultations: North Carolina State Historic Preservation 4617 Mail Service Consultations Section 106, National Historic Office Center, Raleigh NC Preservation Act Department of Natural and Cultural 27699-4617 Resources Required Permit: North Carolina Department of Environmental 1611 Mail Service Pre-application meeting Permit for Isolated/non-404 Quality (NCDEQ) Center Wetlands and Waters, 401 o Division of Water Resources (DWR) Raleigh, NC 27699- Water Quality 1611 Certification/Riparian Buffer Required Permit: NCDEQ, 1641 Mail Service Minor New Source Air Permit o Division of Air Quality Center Raleigh, NC 27699- 1641 Required Permit: NCDEQ 1612 Mail Service Pre-application meeting NPDES Construction o Division of Energy, Mineral and Land Center Stormwater Discharge (including Resources Raleigh, NC 27699- Erosion Control Plan) 1612 Consultations: NCDEQ, Natural Heritage Program Consultations State listed species Consultations: North Carolina Wildlife Resources 1701 Mail Service Consultations State listed wildlife species Commission (NCWRC) Center, Raleigh, NC 27699-1700

Page 19 of 20 MOUNTAIN VALLEY PIPELINE, LLC MVP SOUTHGATE PROJECT FERC Docket No. PF18‐4‐000 FERC Pre-Filing Monthly Status Report

Period Ending: May 31, 2018 Status Report No.: 1

TABLE 3

PERMITS AND APPROVALS

Permits/ Approvals/ Administering Agency Agency Address Status/ Comments Consultations Required Permit: North Carolina Department of Transportation 1501 Mail Service Road bonds and crossing (NCDOT) Center permits Raleigh, NC 27699- 1501

Page 20 of 20