<<

The World Bank Implementation Status & Results Report Cold Weather Smart Public Transportation System (P133114)

Heilongjiang Cold Weather Smart Public Transportation System (P133114)

EAST ASIA AND PACIFIC | | Transport Global Practice | IBRD/IDA | Investment Project Financing | FY 2014 | Seq No: 14 | ARCHIVED on 13-Jan-2021 | ISR45167 | Public Disclosure Authorized

Implementing Agencies: Heilongjiang Development and Reform Commission, Project Management Office, Project Management Office, People's Republic of China

Key Dates

Key Project Dates

Bank Approval Date: 28-Mar-2014 Effectiveness Date: 18-Aug-2014 Planned Mid Term Review Date: 04-Sep-2017 Actual Mid-Term Review Date: 18-Sep-2017 Original Closing Date: 30-Jun-2020 Revised Closing Date: 30-Jun-2021 pdoTable

Public Disclosure Authorized Project Development Objectives

Project Development Objective (from Project Appraisal Document) The Project Development Objective (PDO) is to upgrade the quality and efficiency of public transport services in selected public transport corridors of the project cities.

Has the Project Development Objective been changed since Board Approval of the Project Objective? No

Components Table

Name Component 1. Public Transport Corridor Improvement:(Cost $106.23 M) Component 2. Public Transport Infrastructure Improvement:(Cost $127.39 M) Public Disclosure Authorized Component 3. Traffic Management and Safety Improvement:(Cost $47.90 M) Component 4. Road Maintenance and Emergency Response Equipment:(Cost $10.21 M) Component 5. Capacity Building:(Cost $7.62 M)

Overall Ratings

Name Previous Rating Current Rating

Progress towards achievement of PDO Satisfactory Satisfactory Overall Implementation Progress (IP) Satisfactory Satisfactory Overall Risk Rating Moderate Moderate

Implementation Status and Key Decisions

The project made steady progress in the past two years. The purchase of new-energy buses in both cities have been completed, and the traffic

Public Disclosure Authorized management center in Mudanjiang and the public transport control center in Harbin have been completed. The public transport corridors are the essential component of the project for achieving PDO. By this ISR, Mudanjiang city has completed all 4 bus corridors and Harbin city has completed all 3 corridors.

1/13/2021 Page 1 of 8 The World Bank Implementation Status & Results Report Heilongjiang Cold Weather Smart Public Transportation System (P133114)

Risks

Systematic Operations Risk-rating Tool

Risk Category Rating at Approval Previous Rating Current Rating

Political and Governance -- Low Low Macroeconomic -- Moderate Moderate Sector Strategies and Policies -- Moderate Moderate Technical Design of Project or Program -- Substantial Substantial Institutional Capacity for Implementation and -- Moderate Moderate Sustainability Fiduciary -- Moderate Moderate Environment and Social -- Moderate Moderate Stakeholders -- Moderate Moderate Other ------Overall -- Moderate Moderate

Results

PDO Indicators by Objectives / Outcomes

To upgrade quality of public transport services in selected public transport corridors

IN00943026 ►Increase in public transport service satisfaction along the targeted corridors (Harbin City) (Percentage, Custom)

Baseline Actual (Previous) Actual (Current) End Target

Value 35.00 39.00 79.90 70.00

Date 30-Nov-2013 01-Jun-2020 31-Oct-2020 30-Jun-2021

This indicator is to be collected only at the mid-term and the end of the project. Comments:

IN00943028 ►Increase in public transport service satisfaction along the targeted corridors (Mudanjiang) (Percentage, Custom)

Baseline Actual (Previous) Actual (Current) End Target

Value 75.00 75.00 75.00 85.00

Date 30-Nov-2013 01-Jun-2020 31-Dec-2020 30-Jun-2021

This indicator is to be collected only at the mid-term and the end of the project. Comments:

1/13/2021 Page 2 of 8 The World Bank Implementation Status & Results Report Heilongjiang Cold Weather Smart Public Transportation System (P133114)

IN00943030 ►Increased share of buses arriving on schedule. (Harbin) (Percentage, Custom)

Baseline Actual (Previous) Actual (Current) End Target

Value 56.00 49.55 48.34 75.00

Date 30-Nov-2013 01-Jun-2020 31-Dec-2020 30-Jun-2021 The share of buses arriving on schedule is lower than the one in 2019 mainly because of the construction Comments: of the corridors this year

IN00943032 ►Increased share of buses arriving on schedule (Mudanjiang). (Percentage, Custom)

Baseline Actual (Previous) Actual (Current) End Target

Value 87.00 87.00 92.00 92.00

Date 30-Nov-2013 01-Jun-2020 31-Dec-2020 30-Jun-2021

To upgrade efficiency of public transport services in selected public transport corridors

IN00943027 ►Increase in bus speed (Harbin) Km/h (Kilometers, Custom)

Baseline Actual (Previous) Actual (Current) End Target

Value 29.00 21.27 28.60 33.00

Date 30-Nov-2013 01-Jun-2020 31-Dec-2020 30-Jun-2021

IN00943029 ►Increase in bus speed (Mudanjiang) Km/h (Kilometers, Custom)

Baseline Actual (Previous) Actual (Current) End Target

Value 19.00 17.00 19.00 24.00

Date 30-Nov-2013 01-Jun-2020 31-Dec-2020 30-Jun-2021

IN00943031 ►Reduced fatalities and major injuries along the targeted corridors (Harbin) (Number, Custom)

Baseline Actual (Previous) Actual (Current) End Target

Value 57.00 32.00 0.00 21.00

Date 30-Nov-2013 01-Jun-2020 31-Dec-2020 30-Jun-2021

The indicator could not be surveyed and updated due to COVID-19 Comments:

IN00943033 ►Reduced fatalities and major injuries along the targeted corridors (Mudanjiang) (Number, Custom)

Baseline Actual (Previous) Actual (Current) End Target

1/13/2021 Page 3 of 8 The World Bank Implementation Status & Results Report Heilongjiang Cold Weather Smart Public Transportation System (P133114)

Value 32.00 10.00 9.00 20.00

Date 30-Nov-2013 01-Jun-2020 31-Dec-2020 30-Jun-2021

IN00943034 ►Reduced energy consumption by buses along the targeted corridors (Harbin) (Text, Custom)

Baseline Actual (Previous) Actual (Current) End Target

Value 0.00 0.30 0.30 0.30

Date 30-Nov-2013 01-Jun-2020 31-Dec-2020 30-Jun-2021

IN00943035 ►Reduced energy consumption by buses along the targeted corridors (Mudanjiang) (Text, Custom)

Baseline Actual (Previous) Actual (Current) End Target

Value 0.00 0.30 0.20 0.20

Date 30-Nov-2013 01-Jun-2020 31-Dec-2020 30-Jun-2021

Intermediate Results Indicators by Components

Component 1. Public Transport Corridor Improvement

IN00943036 ►Total length of public transport corridors developed. (Harbin) (Kilometers, Custom)

Baseline Actual (Previous) Actual (Current) End Target

Value 0.00 6.06 17.72 17.70

Date 30-Nov-2013 01-Jun-2020 31-Dec-2020 30-Jun-2021

IN00943041 ►Total length of public transport corridors developed. (Mudanjiang) (Kilometers, Custom)

Baseline Actual (Previous) Actual (Current) End Target

Value 0.00 17.00 18.10 24.80

Date 30-Nov-2013 01-Jun-2020 31-Dec-2020 30-Jun-2021

IN00943044 ►Increased annual bus ridership volume along the targeted corridors. (Million/year) (Harbin) (Text, Custom)

Baseline Actual (Previous) Actual (Current) End Target

Value 0.00 0.00 -19.80 35.00

Date 30-Nov-2013 01-Jun-2020 31-Dec-2020 30-Jun-2021 Comments: This indicator is negative due to COVID-19.

1/13/2021 Page 4 of 8 The World Bank Implementation Status & Results Report Heilongjiang Cold Weather Smart Public Transportation System (P133114)

IN00943046 ►Increased annual bus ridership volume along the targeted corridors. (Million/year) (Mudanjiang) (Text, Custom)

Baseline Actual (Previous) Actual (Current) End Target

Value 0.00 0.80 -0.20 3.50

Date 30-Nov-2013 01-Jun-2020 31-Dec-2020 30-Jun-2021

Component 2. Public Transport Infrastructure Improvement

IN00943037 ►Number of passenger hubs and depots constructed. (Harbin) (Number, Custom)

Baseline Actual (Previous) Actual (Current) End Target

Value 0.00 1.00 2.00 3.00

Date 30-Nov-2013 01-Jun-2020 31-Dec-2020 30-Jun-2021

IN00943042 ►Number of passenger hubs and depots constructed. (Mudanjiang) (Number, Custom)

Baseline Actual (Previous) Actual (Current) End Target

Value 0.00 0.00 0.00 2.00

Date 30-Nov-2013 01-Jun-2020 31-Dec-2020 30-Jun-2021

IN00943045 ►Number of cleaner-fuel vehicles procured. (Harbin) (Number, Custom)

Baseline Actual (Previous) Actual (Current) End Target

Value 0.00 200.00 200.00 200.00

Date 30-Nov-2013 01-Jun-2020 31-Dec-2020 31-Dec-2017

IN00943047 ►Number of cleaner-fuel vehicles procured. (Mudanjiang) (Number, Custom)

Baseline Actual (Previous) Actual (Current) End Target

Value 0.00 129.00 129.00 120.00

Date 30-Nov-2013 01-Jun-2020 31-Dec-2020 31-Dec-2017

IN00943048 ►% completion of the agreed completed measures in the Performance and Lease Agreements (Harbin) (Percentage, Custom)

Baseline Actual (Previous) Actual (Current) End Target

Value 0.00 50.00 80.00 80.00

1/13/2021 Page 5 of 8 The World Bank Implementation Status & Results Report Heilongjiang Cold Weather Smart Public Transportation System (P133114)

Date 30-Nov-2013 01-Jun-2020 31-Dec-2020 30-Jun-2021

IN00943049 ►% completion of the agreed completed measures in the Performance and Lease Agreements (Mudanjiang) (Percentage, Custom)

Baseline Actual (Previous) Actual (Current) End Target

Value 0.00 100.00 100.00 80.00

Date 30-Nov-2013 01-Jun-2020 31-Dec-2020 31-Dec-2019

Component 3. Traffic Management and Safety Improvement

IN00943038 ►Number of intersections upgraded with traffic signals with bus priority function and pedestrian crossings installed. (Harbin) (Number, Custom)

Baseline Actual (Previous) Actual (Current) End Target

Value 0.00 9.00 16.00 45.00

Date 30-Nov-2013 01-Jun-2020 31-Dec-2020 30-Jun-2021

IN00943043 ►Number of intersections upgraded with traffic signals with bus priority function and pedestrian crossings installed. (Mudanjiang) (Number, Custom)

Baseline Actual (Previous) Actual (Current) End Target

Value 0.00 117.00 117.00 110.00

Date 30-Nov-2013 01-Jun-2020 31-Dec-2020 30-Jun-2021

Component 4. Road Maintenance and Emergency Response Equipment

IN00943039 ►Number of emergency rescue equipment and specialized road maintenance equipment procured. (Harbin) (Number, Custom)

Baseline Actual (Previous) Actual (Current) End Target

Value 0.00 104.00 104.00 104.00

Date 30-Nov-2013 01-Jun-2020 31-Dec-2020 31-Dec-2017

Component 5. Capacity Building

IN00943040 ►At least one urban transport related policy/plan/strategy issued by each city (Harbin and Mudanjiang) (Text, Custom)

Baseline Actual (Previous) Actual (Current) End Target

Value 0.00 0.00 0.00 1.00

Date 30-Nov-2013 01-Jun-2020 31-Dec-2020 30-Jun-2021

1/13/2021 Page 6 of 8 The World Bank Implementation Status & Results Report Heilongjiang Cold Weather Smart Public Transportation System (P133114)

Performance-Based Conditions

Data on Financial Performance

Disbursements (by loan)

Project Loan/Credit/TF Status Currency Original Revised Cancelled Disbursed Undisbursed % Disbursed

P133114 IBRD-83460 Effective USD 200.00 200.00 0.00 200.00 0.00 100%

Key Dates (by loan)

Project Loan/Credit/TF Status Approval Date Signing Date Effectiveness Date Orig. Closing Date Rev. Closing Date

P133114 IBRD-83460 Effective 28-Mar-2014 21-May-2014 18-Aug-2014 30-Jun-2020 30-Jun-2021

Cumulative Disbursements

PBC Disbursement

Achievement Disbursed amount in Disbursement % PBC ID PBC Type Description Coc PBC Amount Status Coc for PBC

1/13/2021 Page 7 of 8 The World Bank Implementation Status & Results Report Heilongjiang Cold Weather Smart Public Transportation System (P133114)

Restructuring History

Level 2 Approved on 30-Aug-2019 ,Level 2 Approved on 09-May-2020

Related Project(s)

There are no related projects.

1/13/2021 Page 8 of 8