A Review of the Uk Fast Reactor

Total Page:16

File Type:pdf, Size:1020Kb

A Review of the Uk Fast Reactor Pumps 1. Inducer test to start 1979. 2. CRBRP test to start 1980. A REVIEW 3. Large pump test to start 1983. OF THE U.K. FAST REACTOR PROGRAMME: MARCH 1978 Reference Fuel Verification to be completed in 1982. R.D. SMITH Advanced Fuel United Kingdom Atomic Energy Authority, Selection in 1985. Risley, United Kingdom Facilities 1. Fuel storage at FFTF. 2. 70 MWt steam generator to be completed at LMEC 1978. 1. BACKGROUND TO THE 1978 REVIEW 3. FMEF design work started. The main events during 1977 concerning the nuclear power programme were the public inquiry into the proposal to buiid a new Thermal Oxide Reprocessing Plant (THORP) at VVindscale and the 4. HPFL design work started. government decision on the choice of nuclear reactors for the next stage of the thermal reactor pro- gramme. Both these events, though not directly concerned with fast reactor development have significant 5. TTF at LMEC in operation. implications for the UK fast reactor programme. Indeed, during the course of the Windscale inquiry it was made clear that there was to be an inquiry on fast reactors that would consider all the issues con- 6. Upgrading of TREAT to be completed in next several years. sequent upon the introduction of fast reactors as major contributors to the UK power supplies. Fast reactor matters were therefore not discussed extensively at Windscale - nevertheless some of the con- The efforts described would serve as a focal point for the expanded base clusions concerning the various facets of the use of plutonium for power generation were considered and program, but more importantly, it would assure a viable breeder option the conclusions are of importance to fast reactor development. which could meet the requirement stated by President Carter: "I believe that a strong research and development program for the breeder reactor The decision to build two further AGR power stations and in addition to develop the option of is essential to maintaining diversity of energy supply options for this adopting the Pressurised Water Reactor (PWR) System in the early 198O's impacts on the fast reactor country ...." programme mainly as a result of competition for resources. The Secretary of State for Energy has stated that the next decision to be made is that on the fast breeder reactor. In the meantime the development To summarize, from the U.S. domestic viewpoint, there appears to be time programme :s continuing at a rate of over £60M per year on the fast breeder development programme to develop a better product and to examine proliferation considerations including the operation of the Prototype Fast Reactor (PFR) at Dounreay. more deliberately. The Nuclear Power Company (NPC) responsible for the design and construction of nuclear reactors in the UK has continued work on the engineering design of the 1300 MW(E) fast reactor now called the Commerciai Demonstration Fast Reactor (CDFR). A restrained core design has now been developed to replace the free-standing design of the type used for the PFR and the engineering design of the plant is continually being revised and improved. The Central Electricity Generating Board (CEGB) continue to play an active part in the develop- ment programme. They have made their own studies of uranium demand and the system penetration characteristics of the fast reactor under varying assumptions for future system growth. These underline the need for achieving short plutonium tumround time in the fuel cycle, particularly where fast reactors are supported solely by plutonium produced in an adjoint thermal reactor programme, if ore demand is to be minimised. CEGB continue to support the operation of the PFR at Dounreay by secondment of suitably experienced staff. In addition scientific staff have been seconded to assist in reprocessing activity in the UK O ! and in sodium boiling experiments at KfK Karlsruhe. Secondment to the SNR-300 project continues. O ro CD The Nuclear Installations Inspectorate (Nil) have continued their independent assessment of fast caution a detailed survey of all the welds in the tube plate was carried out. The reactor was restarted in 57 reactor safety, devoting much effort to Whole Core Accidents (WCA). The work has included studies of May on Circuits 1 and 2, and Circuit 3 was recommissioned in July. Subsequently the reactor has the explosion yield of postulated accidents and the consequences for the population of extreme examples operated very reliably. of such accidents. Operation at reduced power levels has been required while thermal hydraulics were studied in the The behaviour in normal operation of a prestressed containment is being investigated and the primary circuit using special thermocouple probes loaded during die shutdown. Reduced power operation Inspectorate has participated in the APRICOT international comparative exercise on the analysis of struc- in the last quarter of the year was due to minor mechanical problems with some conventional plant items. tural response to WCA pressure loads. A further leak in Evaporator No. 3 was detected, located and plugged in less than two weeks. The USA government policies with regard to the development of the fast reactor have had some Equipment to provide a larger steam dump capacity has been installed. This will increase opera- impact on the UK fast reactor programme. In particular the UK is participating in the International tional flexibility and should prevent tripping of the reactor as a consequence of turbine trips during start- Nuclear Fuel Cycle Evaluation (INFCE) programme, including possible alternative fuel cycles for fast up or shutdown sequences. Operation on all three circuits was resumed during December; then in reactors, and is devoting some effort to this work, even though it is thought unlikely that any practicable January 1978 there was a severe storm which disconnected Dounreay completely from the grid of the major changes in the fast reactor fuel cycle are likely to result. North of Scotland Hydro-electric Board (NSHEB). This is the first time since the stair of construction that this has occurred. The loss of grid connection tripped both reactor and turbine. The diese! alterna- tors and guaranteed power supply systems all operated correctly and the decay heat was rejected through 2. THE DOUNREAY FAST REACTOR (DFR) the thermal syphon loops. The station was restarted early in February 1978 and operated at high power until the planned refuelling and maintenance shutdown in March. The length of this shutdown will DFR was closed down as scheduled on 23 March I 977 after seventeen yeais of successful operation depend on the time taken to re-blade the end rows of the LP turbine. Erosion shields had been removed as a development and test facility. in 1973 and wear has been exacerbated by the prolonged operation under non-standard steam conditions. During the last run before closure a series of coolant boiling experiments was carried out in which During this year steam generator performance has been much improved, the only leaks occurring on specially contained experimental rigs containing fast reactor type ruel pins at various levels of burn-up Evaporator No. 3 which haH been severely contaminated with sodium during early operations. Measure- were operated with gradually reduced coolant flow with repeated periods of local coolant boiling. One ments of the temperatures in the hot sodium pool and above-core structures, with development work and rig was in tact subjected to 12 runs and a total of nearly 24 hours above boiling temperatures. Detailed rig tests, confirm that sustained full power operation will be possible with the core-loading arranged analysis of the results of the experiments is still being made but in general it appears that the following during the present shutdown. broad conclusions can be drawn: Good proeress has been made with commissioning of the irradiated-fuel caves, including the com- (1) Fast reactor fuel is extremely durable. plete sodium filling of the equipment tanks and the filter testing. Many of the moves of irradiated fuel and (2) Boiling behind a blockage develops axially rather than radially and therefore has little effect on components between the in-reactor store and caves have been completed for the next reioad. the bulk flow through the sub-assembly. (3) In cases where pin failure occurs it is innocuous and would be easily detected well within the 4. COMMERCIAL DEMONSTRATION FAST REACTOR (CDFR) time scale required by safety considerations. (4) In general, theoretical predictions of the outset of boiling are substantiated. 4.1 Core design and parameters Since the closure of DFR, work has continued on the decontamination of certain items of plant, the A review of the different designs of heterogeneous cores is being prepared. It is not certain that recovery of certain components for examination and the disposal of some NaK. a worthwhile improvement in safety will be achieved by the adoption of such a core but the UK designers are considering in some detail the engineering effects of the various alternatives. The main factors to be The reactor will be partially decommissioned, and the outer containment sphere retained, possibly as an industrial exhibition hall. influenced are the overall size of the core and the disposition of absorber rods and nucleonic inst-uments. As work continues on the restrained core, a definitive design has been produced and analysed. The 3. PROTOTYPE FAST REACTOR (PFR) conclusion is that this design of restrained core is satisfactory. Design of the diagrid and carriers has resulted in an alternative scheme featuring hydraulic hold-down for the carriers distinct from the earlier The last review was made just after the reactor had reached its full thermal power of 600 MW with mechanical hold-down system. Fabrication problems of both diagrid and carriers will be examined to an electrical output of 200 MW.
Recommended publications
  • Download a Copy
    Cover image: Courtesey of EDF Energy — www.edfenergy.com/energy CONTENTS... 1 AT A GLANCE... 2 A BRIEF HISTORY OF NUCLEAR ENERGY... 4 BENEFITS OF NUCLEAR ENERGY... 5 WHAT THE PUBLIC THINK... 6 HOW NUCLEAR CREATES ENERGY... 7 HOW A REACTOR WORKS... 8 THE NUCLEAR FUEL CYCLE... 9 MANAGING WASTE... 10 RADIATION EXPLAINED... 12 NUCLEAR AROUND THE WORLD... 14 UK NUCLEAR SITES... 16 NUCLEAR NEW BUILD... 17 NEW BUILD IN NUMBERS... 18 LOOKING TO THE FUTURE... 19 DECOMMISSIONING... 20 CAREERS IN NUCLEAR... 21 FUTHER INFORMATION... AT A GLANCE... Nuclear is a major part of our energy mix. Today it accounts for 21% of electricity generated in the UK and has been providing secure low carbon electricity for over 60 years. Low carbon energy, including There are 15 nuclear power and renewables, nuclear power account for almost 51% of the reactors operating UK’s generation electricity mix across eight sites in the UK In 2016 nuclear energy avoided 22.7 million metric tonnes of CO2 emissions in the UK BEIS,Digest of UK Energy Statistics 2018 That’s equivalent to taking around a third of all cars in the UK off the road Civil nuclear contributes over £6 billion to the jobs in the UK civil nuclear sector UK economy as much as aerospace manufacturing 12,159 Women in civil nuclear 1,981 People on apprenticeships Three quarters of the public 914 believe nuclear should be part People on graduate schemes of the clean energy mix Jobs Map figures generated from participating NIA members 1 This simple timeline charts some of the key people, events and legislation A BRIEF HISTORY OF NUCLEAR ENERGY..
    [Show full text]
  • Memorandum Forwarding Memorandum from the Director Of
    1 0-I AEc 755/36 Februar 27, 1661 COPY,-NO.A.L ATOMIC ENERGY COMMISSION REPORT BY DR. LOUIS B. WERNER, ABC SCIENTIFIC REP•ESENTATIV, LONDON Note by the Secretary The General Manager has requested that the attached memorandum and enclosures from the Director of International Affairs be circulated for the information of the Commission. W, B. McCool Secretary DISTRIBUTION COPY NO. DISTRIBUTION COPY NO. Secretary 1 International Affairs 29 - 39 Commissioners 2 - 6,81 Licensing & Regulation 40 - 41 General Manager 7 Operations Analysis 42 Deputy Gen. Mgr. 8 Production 43 - 44 Asst. Gen. Mgr. 9- 10 Raw Materials 45 - 46 Asst. Gen. Mgr. IA 11 Reactor Development 5 - 55 Asst. Gen. Mgr. Mfg. 12 Research Asst. Gen. Mgr. R&S 13 Security 56 Asst. Gen. Mgr. R&ID 14 Special Projects Asst. Gen. Mgr. Adm. 15 Albuquerque Oprns. 58 5-7 60 Asst, to the GM 16 Chicago Oprns. 61 - 62 General Counsel 17 - 20 Hanford Oprns. 63 Biology & Medicine 21 Idaho Oprns. 64 - 65 Classification 22 New York Oprns. 66 Congr. Relations 23 Oak Ridge Oprns. 67-69 Health & Safety 24 San Francisco Oprns. 70 Isotope Development 25 Savannah River Oprns. 71 - 72 Public Information 26 - 27 D. C. Office 73 - 75 Intelligence 28 Secretariat 76 - 80 When sen enclosures3 ha . LASSIFIED fit, CMEN qITH CONTAINS CLA FENSE INFORMATION RRNTOREBILII'TRAL FILES ROOM 016 UNITED STATES GOVERNMENT Memorandum TO : A. R. Luedecke, General Hianaj2pr DATE: FEB 13 16 THRU: John A. Hall, AGMIIA fl.' FROM. : A. A. Wells, i o Division of I~ e a SUBJECT: REPORT PREPARED BY DR.
    [Show full text]
  • 小型飛翔体/海外 [Format 2] Technical Catalog Category
    小型飛翔体/海外 [Format 2] Technical Catalog Category Airborne contamination sensor Title Depth Evaluation of Entrained Products (DEEP) Proposed by Create Technologies Ltd & Costain Group PLC 1.DEEP is a sensor analysis software for analysing contamination. DEEP can distinguish between surface contamination and internal / absorbed contamination. The software measures contamination depth by analysing distortions in the gamma spectrum. The method can be applied to data gathered using any spectrometer. Because DEEP provides a means of discriminating surface contamination from other radiation sources, DEEP can be used to provide an estimate of surface contamination without physical sampling. DEEP is a real-time method which enables the user to generate a large number of rapid contamination assessments- this data is complementary to physical samples, providing a sound basis for extrapolation from point samples. It also helps identify anomalies enabling targeted sampling startegies. DEEP is compatible with small airborne spectrometer/ processor combinations, such as that proposed by the ARM-U project – please refer to the ARM-U proposal for more details of the air vehicle. Figure 1: DEEP system core components are small, light, low power and can be integrated via USB, serial or Ethernet interfaces. 小型飛翔体/海外 Figure 2: DEEP prototype software 2.Past experience (plants in Japan, overseas plant, applications in other industries, etc) Create technologies is a specialist R&D firm with a focus on imaging and sensing in the nuclear industry. Createc has developed and delivered several novel nuclear technologies, including the N-Visage gamma camera system. Costainis a leading UK construction and civil engineering firm with almost 150 years of history.
    [Show full text]
  • Hot Particles at Dounreay
    SEPTEMBER 20, 2007 | No. 660 HOT PARTICLES AT DOUNREAY The Dounreay nuclear complex, situated on a remote part of the north coast of Scotland, was once home to a variety of experimental nuclear facilities including two prototype fast breeder reactors, a reprocessing plant and a materials test reactor. Nearly all of these are now closed, but the legacy of their waste, pollution and accidents HOT PARTICLES AT DOUNREAY 1 lives on. One of the main areas of concern is the radioactive particles ILLEGAL TRAFFICKING: INCREASE found near the complex. The latest radioactive fragment found on INCIDENTS INVOLVING THEFT OR LOSS 2 Sandside beach is one of the hottest yet detected. SLEBOS CASE REVEALS FAILURE OF DUTCH AND EU NUCLEAR NON- (660.5826) WISE Amsterdam - The They entered the drains, which should PROLIFERATION POLICIES 4 particle of cesium-137 picked up during have carried only low-active waste a sweep of the beach on September 7 waster, either from the reprocessing RECORD URANIUM PRICE - WHAT was the third recovered since monitoring plant or from a controversial waste shaft. IS BEHIND AND WHAT ARE THE resumed on August 5 after a lengthy The highly radioactive particles were CONSEQUENCES 5 gap. This brings the legacy of pollution known as 'swarf' -the outside cladding from the nearby Dounreay plant to 97 from spent fuel assemblies which are cut HEAVY SUBSIDIES IN HEAVY used reactor fuel particles and an off at the very start of the reprocessing WATER: ECONOMICS OF NUCLEAR unidentified radioactive object. procedure to expose the fuel rods. These POWER IN INDIA 6 are some of the most highly radioactive After being taken back to a lab at the wastes from spent fuel reprocessing.
    [Show full text]
  • Onr Corporate Plan 2017/18 En Route to 2020
    ONR CORPORATE PLAN 2017/18 EN ROUTE TO 2020 Office for Nuclear Regulation Corporate Plan 2017/18 Financial year 1 April 2017 to 31 March 2018 Presented to Parliament pursuant to Paragraphs 23 and 25(3) of Schedule 7 to the Energy Act 2013 July 2017 © ONR copyright 2017 The text of this document (this excludes, where present, the Royal Arms and all departmental or agency logos) may be reproduced free of charge in any format or medium provided that it is reproduced accurately and not in a misleading context. The material must be acknowledged as ONR copyright and the document title specified. Where third party material has been identified, permission from the respective copyright holder must be sought. Any enquiries related to this publication should be sent to us at [email protected] This publication is available at https://www.gov.uk/government/publications Print ISBN 9781474145695 Web ISBN 9781474145701 ID P002881793 06/17 Printed on paper containing 75% recycled fibre content minimum Printed in the UK for Williams Lea Group on behalf of the Controller of Her Majesty’s Stationery Office CONTENTS 1. Foreword .........................................................................................................1 2. About this plan ..............................................................................................3 3. Our Operating Environment .........................................................................9 4. Our Strategic Themes and Key Activities ....................................................15 Influencing improvements
    [Show full text]
  • Magnox Achievements 2017/18 Magnox Achievements 2017/18 3
    Achievements 2 017/18 2 Magnox Achievements 2017/18 Magnox Achievements 2017/18 3 Introduction We can all be extremely proud of the achievements that the Magnox and Cavendish Bradwell Site takes another critical step towards care and maintenance, as the end of Fluor Partnership team have made in the safe and secure decommissioning of intermediate level waste (ILW) operations is set to complete. Magnox sites. This includes the successful and safe management Of the packages placed for interim storage to date, more than During the past 12 months we have made further significant acknowledge and this booklet cannot do it justice but at of sludges, which accumulated during the 40 years 40 contain dried resin and more than 60 contain dried sludge. progress and there is much to celebrate, not least: forging least it will give you a flavour of the work that is being done of Bradwell’s operation. This achievement follows a significant 12 months for the ahead with the closure of Bradwell Site in 2018; continued across Magnox that might not be visible to all. In a programme spanning more than seven years, several site, which also saw the completion of fuel element debris defuelling at Wylfa; nuclear material transfers from Harwell separate projects covering waste retrieval, packaging dissolution in June 2017 and the reclassification of some Site to Sellafield and making significant advances in hazard We recognise and appreciate all the good work that and conditioning have contributed to the site’s ILW being of this ILW as low level waste, enabling it to be sent to reduction across all our sites as follows: is being done by our staff, suppliers and contractors; working together as one team to make things happen transferred into the interim storage facility.
    [Show full text]
  • United Kingdom
    UNITED KINGDOM (Updated 2013) 1. GENERAL INFORMATION 1.1 Country Overview 1.1.1 Governmental System Not provided. 1.1.2 Geography and Climate United Kingdom (UK) is an abbreviated form of United Kingdom of Great Britain and Northern Ireland. The UK consists of England, Northern Ireland, Scotland and Wales, and lies in north-western Europe, occupying the major portion of the British Isles. The country’s only land boundary is with the Republic of Ireland. The UK is separated from the coast of Western Europe by the English Channel to the south and by the North Sea to the east. The northern and western shores are washed by the Atlantic Ocean. Generally, the United Kingdom has cool to mild winters and warm summers, with moderate variation in temperature throughout the year. In England, the average annual temperature varies from 8.5 °C in the north to 11 °C in the south, but over the higher ground this can be several degrees lower. This small variation in temperature is to a large extent due to the moderating effect the Atlantic Ocean has—water has a much greater specific heat capacity than air, and tends to heat and cool slowly throughout the year. This has a warming influence on coastal areas in winter and a cooling influence in summer. On average, the warmest winter temperatures occur on the south and west coasts, although warm temperatures occasionally occur due to a foehn wind warming up the downwind after crossing the mountains. Temperatures in these areas can rise to 15 °C in winter, on rare occasions.
    [Show full text]
  • Beauly to Loch Buidhe 275Kv Overhead Line Reinforcement
    Beauly to Loch Buidhe 275kV Overhead Line Reinforcement About Scottish Hydro Electric (SHE) Transmission plc Scottish and Southern Energy Power Distribution is part of the SSE plc group pf companies. We own, maintain and invest in the electricity networks in the north of Scotland – the electricity transmission network (132kV and above) and the electricity distribution network (below 132 kV). In Scotland, Scottish and Southern Energy Power Distribution is made up of two businesses: Scottish Hydro electric Transmission (SHE Transmission) owns and maintains the electricity transmission network across the north and west of Scotland, in some of the UKs most challenging terrain; and Scottish Hydro Electric Power Distribution (SHEPD) operates the high and low voltage electricity network that distributes electricity to around 700,000 customers in north mainland Scotland and Scottish islands. SHE Transmission owns around 5,000km of electricity transmission infrastructure which spans about 70% of the land mass in Scotland. Electricity networks like this provide a physical link between electricity generators and electricity users. We have three main objectives over the next decade: To keep the lights on for our customers To invest for a greener future; and To minimise, as far as possible, our impact on the environment. Our network crosses some of the UK’s most challenging terrain – including some circuits which are over 750 metres above sea level and up to 250km long. The landscape and environment that contribute to the challenges we face also give the area a rich resource for renewable energy generation. There is enough demand to connect from new wind, hydro and marine generators which rely on us to provide a physical link between the new sources of power and electricity users.
    [Show full text]
  • Glossary of Nuclear Terms
    BURGES SALMON LLP Glossary of Nuclear Terms June 2015 Edited by Gareth Davies Editor: Gareth Davies, Davies Nuclear Associates Ltd Co-Editors: Thomas Carpenter, Burges Salmon LLP Sarah Raby, Burges Salmon LLP Sponsor: Ian Salter, Head of Nuclear Practice, Burges Salmon LLP Glossary of Nuclear Terms Peer Reviewers for 2015: Ian Bonnett, Davies Nuclear Associates Ltd Adrian Bull, National Nuclear Laboratory Samantha Dancy, Nuclear Decommissioning Authority Tristram Denton, Hitachi Europe Ltd Anna Ellis, Frazer-Nash Consultancy Neil Foreman, Centronic Ltd Dr Justin Goldberg, Jacobs Engineering (UK) Limited Colin Goodrum, LDA Design Peter Haslam, Nuclear Industry Association Allison Hunt, National Skills Academy for Nuclear Stuart Hunt, EDF Energy Terry Kelly, Cavendish Nuclear David Lawson, GD Energy Services Mark Liddiard, HR Wallingford Jean Llewellyn, National Skills Academy for Nuclear Amanda MacMillan, Horizon Nuclear Power John McNamara, NuGeneration Ltd Melanie Sachar, EDF Energy Terry Selby, NuGeneration Ltd Dr Tim Stone, former Expert Chair, Office for Nuclear Development Chris Williams, Nuvia Version Date: June 2015 © 2015 Burges Salmon LLP www.burges-salmon.com All rights reserved. Any use or reproduction of this Glossary, whether in whole or part, must clearly attribute authorship and acknowledge that © remains with Burges Salmon LLP. The moral rights of Burges Salmon LLP have been asserted in accordance with the Copyright, Designs and Patents Act 1988. Disclaimer: This Glossary is intended as a general guide only. The information and opinions which it contains are not intended to be a comprehensive study, nor to provide legal advice, and should not be treated as a substitute for legal advice containing particular situations.
    [Show full text]
  • Dounreay Mybster Transmission Project Exhibition Handout
    Project Background The Route Selection Process Tower Construction This proposal is part of the reinforcement of the electricity We have worked closely with a team of environmental The OHL will be constructed using self-supporting lattice transmission network, envisaged by the National Planning consultants and overhead line engineers to identify a steel towers. The towers used for the 275 kV OHL will vary Framework (NPF2) and the Energy Networks Strategy technically feasible (both in terms of constructability and long in height between 32m and 52m to accommodate changes Group. Analysis of the existing transmission network in the term maintenance), economically viable, new transmission in topography and where the line crosses roads and rivers, north of Scotland identified the need for increased network OHL which gives rise to: although the height will generally be in the region of 40m. capacity to facilitate the transmission of renewable The 132kV OHL towers will vary in height between 23m and generation projects north of Beauly including onshore / • The least disruption to the amenity of people living and 38m, although the height will generally be in the region of offshore wind and marine and tidal generation. This increase working in the area; 28m. in network capacity can only be achieved by undertaking • The least impact on the physical and natural environment, reinforcement of the transmission network in the north of and on nationally important species, habitats and cultural The spacing between towers will vary depending on Scotland. assets; topography, altitude and land usage. The height and • The least disruption to current land use and management distance between towers will be determined later in the Project Description practices; and design process; however the spacing will be generally in the • The least disruption to existing and proposed infrastructure range of 260-360 m for the 275 kV towers and 200-300 m and other economically beneficial uses of land.
    [Show full text]
  • IAEA Nuclear Energy Series Managing the Unexpected in Decommissioning No
    IAEA Nuclear Energy Series IAEA Nuclear No. NW-T-2.8 No. IAEA Nuclear Energy Series Managing the Unexpected in Decommissioning Managing the Unexpected No. NW-T-2.8 Basic Managing the Principles Unexpected in Decommissioning Objectives Guides Technical Reports INTERNATIONAL ATOMIC ENERGY AGENCY VIENNA ISBN 978–92–0–103615–5 ISSN 1995–7807 @ 15-40561_PUB1702_cover.indd 1,3 2016-03-30 10:56:45 IAEA Nuclear Energy Series IAEA Nuclear IAEA NUCLEAR ENERGY SERIES PUBLICATIONS STRUCTURE OF THE IAEA NUCLEAR ENERGY SERIES No. NW-T-2.8 No. Under the terms of Articles III.A and VIII.C of its Statute, the IAEA is authorized to foster the exchange of scientific and technical information on the peaceful uses of atomic energy. The publications in the IAEA Nuclear Energy Series provide information in the areas of nuclear power, nuclear fuel cycle, in Decommissioning Managing the Unexpected radioactive waste management and decommissioning, and on general issues that are relevant to all of the above mentioned areas. The structure of the IAEA Nuclear Energy Series comprises three levels: 1 — Basic Principles and Objectives; 2 — Guides; and 3 — Technical Reports. The Nuclear Energy Basic Principles publication describes the rationale and vision for the peaceful uses of nuclear energy. Nuclear Energy Series Objectives publications explain the expectations to be met in various areas at different stages of implementation. Nuclear Energy Series Guides provide high level guidance on how to achieve the objectives related to the various topics and areas involving the peaceful uses of nuclear energy. Nuclear Energy Series Technical Reports provide additional, more detailed information on activities related to the various areas dealt with in the IAEA Nuclear Energy Series.
    [Show full text]
  • Identification of Potential Opportunities for Development of UK R&D
    Identification of potential opportunities for development of UK R&D capability and strategic UK supply chain to the deployment of Advanced Modular Reactors NNL 14790 ISSUE 1 This document is prepared by National Nuclear Laboratory Limited ("NNL") for Department for Business, Energy and Industrial Strategy (BEIS) pursuant to a contract, dated 16 May 2018, reference TRN1431/01/2018 ("the Contract"). The ownership of this document, and the material contained within it, shall be treated in accordance with the provisions of the Contract Page 1 of 73 National Nuclear Laboratory Limited (Company number 3857752) Registered in England and Wales. Registered office: Chadwick House Warrington Road Birchwood Park Warrington WA3 6AE Page 2 of 73 NNL 14790 ISSUE 1 Identification of potential opportunities for development of UK R&D capability and strategic UK supply chain to the deployment of Advanced Modular Reactors NNL 14790 ISSUE 1 Nicholas Barron, 21 February 2020 . Name Signature • Date i Checked Kevin Hesketh I /(;, N\cJd... c. d1..0 By Approved Emma Vernon By Work Order 10725.300 Number Keywords ADVANCED MODULAR REACTOR; AMR; HTGR; VHTR; SFR; LFR; MSR; MSTHR; MSFR; FAST REACTOR; TRL; R&D; SCRL; GAS; SODIUM; LEAD; MOLTEN SALT National Nuclear Laboratory limited (Company number 3857752) Registered in England and Wales. Registered office: Chadwick House Warrington Road Birchwood Park Warrington WA3 6AE Page 3 of 73 NNL 14790 ISSUE 1 Executive Summary The Committee on Climate Change (CCC) has recommended that significant decarbonisation of the energy sector is required to meet the UK Governments’ ambitious and legally binding net zero emissions by 2050. The Department of Business, Energy and Industrial Strategy (BEIS) expects new nuclear power to play a role in supporting this deep decarbonisation and in maintaining energy supply and security.
    [Show full text]