<<

I) Basic information S. No. Item Details

1 Name of the project/s M/s. Laxmi Infobahn Software Technology park LLP - commercial complex 2 S. No. in the schedule Project Activity – 8a

Category B(B2) 3 Proposed capacity /area/ length/ S. No Floors Built up tonnage to be Area in handled/command area/lease Sq.mts area/ No of the well to be drilled 1 1st Floor 3,420.85 2 2nd Floor 4,566.67 3 3rd Floor 4,566.67 th 4 4 Floor 4,566.67 5 5th Floor 4,566.67 6 6th Floor 4,566.67 7 7th Floor 4,566.67 8 8th Floor 4,566.67 9 9th Floor 4,566.67

10 10th Floor 4,566.67 11 11th Floor 4,566.67 12 12th Floor 4,566.67 13 13th Floor 4,566.67 14 14th Floor 4,566.67

15 15th Floor 4,566.67 16 16th Floor 4,566.67 17 17th Floor 4,566.67 18 18th Floor 4,566.67 19 19th Floor 4,566.67 20 20th Floor 4,566.67 21 21st Floor 4,566.67 22 22nd Floor 4,566.67 23 23rd Floor 4,566.67 24 24th Floor 4,566.67 25 25th Floor 4,566.67 Total 1,13,020.93 Parking: S. No Phases Area in Sq Mtrs 1 Stilt 3804.91 2 Basement- 1 8271.60 3 Basement- 2 8271.60 4 Basement- 3 8271.60 5 Basement- 4 8271.60 TOTAL 36,891.31

M/s. Laxmi Infobahn Software Technology park LLP Sy.No: 107(P) & 108(P), (V), Rajendranagar Mandal,

( In Square Meters) commercial : 1,13,020.93 Total Parking Area : 36,891.31 Total Built-up area : 1,49,912.24

4 New/Expansion /Modernization Amendment

5 Existing capacity/Area etc… NA

6 Category of project A or B Category B ( ‘B2’) As Area is less than 1,50,000 Square Meters, the proposed project comes

under category B1

7 Does it attract the general No condition? If yes please specify

8 Does it attract the specific No condition? If yes please specify

9 Location Plot/ survey /Khasra no Sy No. 107(P) & 108(P) Village Kokapet (V), Tehsil/Mandal Rajendranagar Mandal, District RangaReddy District State 10 Nearest Railway station/Air port Rajiv Gandhi International Air port – 21.3 KM along with the distance in kms

11 Nearest Town, , District Kokapet Village – 0.72 Km Headquarters along with distances in kms.

12 Village Panchayats Zilla Parishad HMDA Municipal Corporation, Local body (complete postal Address with telephone no. to be given

13 Name of the applicant M/s. Laxmi Infobahn Software Technology park LLP - commercial complex 14 Registered address 8-2-682, Laxmi Cyber Centre, Road No.12, , - 500034

PRIDHVI ENVIROTECH (P) LIMITED Page 1

M/s. Laxmi Infobahn Software Technology park LLP Sy.No: 107(P) & 108(P), Kokapet (V), Rajendranagar Mandal, Ranga Reddy District

15 Address of the correspondence Name P. Obul Reddy Designation /owner/partner/CEO General Manager 8-2-682, Laxmi Cyber Centre, Road No.12, Address Banjara hills, Hyderabad- Pin code 500034 E-mail [email protected] Telephone no 040-23303449 Fax no 16 Details of Alternative Sites No examined if any.

Location of these sites Should be shown on a Topo sheet.

17 Interlinked Projects No

18 Whether separate application of Not Applicable interlinked projects has been submitted

19 If yes, date of submission Not Applicable

20 If no reason Not Applicable

21 Whether the proposal involves approval / clearances under: if yes, details of the same and their status to be given.

(a) The Forest (conservation) Act, 1980? No (b) The Wild life (protection)Act, 1972? No (c) The C.R.Z notification, 1991? No

22 Whether there is any Government No order/policy relevant/relating to the site?

23 Forest land involved (Hectares) No

PRIDHVI ENVIROTECH (P) LIMITED Page 2

M/s. Laxmi Infobahn Software Technology park LLP Sy.No: 107(P) & 108(P), Kokapet (V), Rajendranagar Mandal, Ranga Reddy District

24 Whether there is any litigation No pending against the project and/or land in which the project is propose to be set up?

(a)Name of the court (b)Case no. (c) Orders/directions of the court, if any and its relevance with the proposed project. (II) Activity

1.0 Construction, operation or decommissioning of the Project involving actions, which will cause Physical Changes in the locality (topography, land use, changes in water bodies, etc.).

S.No. Information /Checklist Yes Details thereof (with approximate confirmation quantities /rates, wherever possible ) /No with sources of information data

1.1 Permanent or temporary change Yes The proposed project activity is in land use, land cover or construction of Commercial Complex. topography including increase in This area is earmarked as commercial intensity of land use (with respect zone as per the Master plan of to local land use plan) Hyderabad Urban Development Authority. 1.2 Clearance of existing land, No There is no vegetation in the project site vegetation and buildings? requiring clearance.

1.3 Creation of new land uses? Yes The purpose of proposed project is construction of Commercial Complex hence there will not be any change in land use 1.4 Pre-construction investigations Yes Soil bearing tests were conducted e.g. bore holes, soil testing? before construction

1.5 Construction works? Yes The project is Commercial Complex.

1.6 Demolition Works? Yes There are no existing structures in the proposed area, which will be demolished.

PRIDHVI ENVIROTECH (P) LIMITED Page 3

M/s. Laxmi Infobahn Software Technology park LLP Sy.No: 107(P) & 108(P), Kokapet (V), Rajendranagar Mandal, Ranga Reddy District

1.7 Temporary sites used for No Temporary shelters for construction construction works or housing of workers are not required as labor will be construction works? hired from the surrounding locations

1.8 Above ground buildings, No The proposed development is structures or earthworks including Construction of Commercial Complex. linear structures, cut and fill or Cut and fill activity will be there for excavations basement and foundations

1.9 Underground works including No Not Applicable as this is a Construction mining or tunneling? of Commercial Complex.

1.10 Reclamation Works? No Not Applicable

1.11 Dredging? No Not Applicable as this is a Construction of Commercial Complex.

1.12 Offshore structures? No Not Applicable as this is a Construction of Commercial Complex.

1.13 Production and manufacturing No No manufacturing activity. processes? Activity is Construction of commercial Complex. 1.14 Facilities for storage of goods or Yes Storage space of building materials will materials? be earmarked onsite.

1.15 Facilities for treatment or disposal Yes Solid waste generated from the of solid waste or liquid effluents? construction includes rubble, used up cement, broken bricks etc, which will be

used for filling up low lying areas during developmental stage. Treated liquid effluents from domestic waste water will be used for flushing and gardening and rest would be sent to municipal drains. STP Sludge will be used as manure in green belt development 1.16 Facilities for long term housing of No Manpower requirement of operational operational workers? workers is nominal and will be recruited from surroundings therefore no long

PRIDHVI ENVIROTECH (P) LIMITED Page 4

M/s. Laxmi Infobahn Software Technology park LLP Sy.No: 107(P) & 108(P), Kokapet (V), Rajendranagar Mandal, Ranga Reddy District

term housing facilities are envisaged.

1.17 New road, rail or sea traffic during No Existing facilities will be used for the construction or operation? proposed project.

1.18 New road, rail, air waterborne or No Not envisaged other transport infrastructure including new or altered routes and stations, ports, airports etc?

1.19 Closure or diversion of existing No Not envisaged transport routes or infrastructure leading to changes in traffic movements?

1.20 New or diverted transmission lines No No diversions or pipelines?

1.21 Impoundment, damming, No The proposed development will not culverting, realignment or other disturb the natural terrain of the area changes to the hydrology of and will not disturb the water courses in watercourses or aquifers? any ways i.e. no drain flows through the site. Rain Water Harvesting system is proposed to recharge the GWL 1.22 Stream crossings? No There are no stream crossings the proposed site. 1.23 Abstraction or transfers of water Yes Water requirement of the project will be from ground or surface waters? met from Municipal supply and Ground water. 1.24 Changes in water bodies or the No The development will be carried out land surface affecting drainage with no disturbance to major water or or run-off? the land surface, affecting drainage or runoff. 1.25 Transport of personnel or Yes Transportation of personnel or material materials for construction, will be by trucks on road operation or decommissioning?

1.26 Long-term dismantling or No Not envisaged decommissioning which could have an impact on the

PRIDHVI ENVIROTECH (P) LIMITED Page 5

M/s. Laxmi Infobahn Software Technology park LLP Sy.No: 107(P) & 108(P), Kokapet (V), Rajendranagar Mandal, Ranga Reddy District

environment?

1.27 Ongoing activity during No Not envisaged decommissioning which could have an impact on the environment?

1.28 Influx of people to an area in Yes Commercial block is proposed. The either temporarily or local area is developing at a faster permanently? pace due to development in the surrounding areas. 1.29 Introduction of alien species? No Not envisaged

1.30 Loss of native species or genetic No Not envisaged diversity?

1.31 Any other actions? No Nil

2.0 USE OF NATURAL RESOURCES for construction or operation of the Project (Such as land, water, materials or energy, especially any resources which are non- renewable or in short supply):

S.No. Information /Checklist Yes Details thereof (with approximate confirmation quantities /rates, wherever possible) /No with sources of information data

2.1 Land especially undeveloped or No Total land available for the project is agricultural land (ha) 10,828.40 Sq.mts

2.2 Water (expected source & Yes Water Requirement : 600 KLD competing users) Unit : KLD Fresh water requirement – 274 KLD Source: Municipal Supply Recycled water –326.0 KLD Source : S.T.P 2.3 Minerals (MT) No Not Applicable as this is a construction project. 2.4 Construction material – stone, Yes Construction materials like coarse aggregates, and / soil (expected aggregate, fine aggregate, granite. source- MT) Kota stone, Dolhpur stone, Marble, bricks, sand, cement, steel will be used. The raw materials will be sourced from

PRIDHVI ENVIROTECH (P) LIMITED Page 6

M/s. Laxmi Infobahn Software Technology park LLP Sy.No: 107(P) & 108(P), Kokapet (V), Rajendranagar Mandal, Ranga Reddy District

local dealers & traders.

2.5 Forests and timber (source – MT) Yes Wood will be used only for preparing window and door frames. The required timber will be procured from local authorized timer dipos

2.6 Energy including electricity and Yes Power Required : 10.0 MV fuels (source, competing users) Source: Central Power Distribution Unit: fuel (MT), energy (MW) Company Limited (TSCPDCL). Back-up power: 7 X 2000 KVA DG sets

for emergency during power failures. Fuel: HSD will be sourced from local traders 2.7 Any other natural resources (use No Not Applicable appropriate standard units)

3.0 Use, storage, transport, handling or production of substances or materials which could be harmful to human health or THE ENVIRONMENT or raise concerns about actual or perceived RISKS TO HUMAN HEALTH.

S. No. Information /Checklist Yes/ Details thereof (with approximate confirmation quantities /rates, wherever possible ) No with sources of information data 3.1 Use of substance or materials, No Only HSD in small quantities will be used which are hazardous (as per for backup power DG sets. Paints are MSIHC rules) to human health or used during construction the environment (flora, fauna, and water supplies)

3.2 Changes in occurrence of No Not envisaged disease or affect disease vectors (e.g. insect or water borne diseases)

3.3 Affect the welfare or people e.g. Yes Good quality housing is proposed with by changing living conditions? good living environment for commercial complex

PRIDHVI ENVIROTECH (P) LIMITED Page 7

M/s. Laxmi Infobahn Software Technology park LLP Sy.No: 107(P) & 108(P), Kokapet (V), Rajendranagar Mandal, Ranga Reddy District

3.4 Vulnerable groups of people No -- who could be affected by the project e.g. hospital patient’s children, the elderly etc.,

3.5 Any other causes No --

4.0 Production of SOLID WASTES during construction or operation or decommissioning (MT/ month) S. No. Information /Checklist Yes/ Details thereof (with approximate confirmation quantities /rates, wherever possible ) No with sources of information data 4.1 Soil, overburden or mine wastes No There are no overburden or mine waste

4.2 Municipal waste (domestic and Yes Garbage – 1755.0 kgs/day disposed to or commercial wastes) GHMC

4.3 Hazardous wastes (as per No Used Oils Hazardous Waste Management Used Batteries Rules) Transformer Oil

4.4 Other industrial process wastes No Not Applicable

4.5 Surplus product No Not Applicable

4.6 Sewage sludge or other sludge Yes Sewage Sludge will be used as manure from effluent treatment for green belt development.

4.7 Construction or demolition Yes The demolition waste and during wastes construction some amount of construction debris may be generated which will be segregated and whatever re-saleable will be sold to supplier and rest waste will be used for filling up of low lying areas and development of internal roads and boundary walls etc 4.8 Redundant machinery or No Most of the equipment used for the equipment construction will be hired.

4.9 Contaminated soils or other No No soil contamination is anticipated as the proposed project is a construction

PRIDHVI ENVIROTECH (P) LIMITED Page 8

M/s. Laxmi Infobahn Software Technology park LLP Sy.No: 107(P) & 108(P), Kokapet (V), Rajendranagar Mandal, Ranga Reddy District

materials project all the waste generated will be in the form of solid waste of reusable nature. 4.10 Agricultural wastes No Not Applicable

4.11 Other solid wastes No --

5.0 Release of pollutants or any hazardous, toxic or noxious substances to AIR (Kg/hr)

S. No. Information /Checklist Yes/ Details thereof (with approximate confirmation quantities /rates, wherever possible ) No with sources of information data 5.1 Emissions from combustion of Yes Emissions will be mainly from vehicles fossil fuels from stationary or moving at the project site during mobile sources construction and operation period and secondly from the 7 X 2000 KVA DG sets used for backup power source operated only during power failures only for a short duration. As HSD will be used for the DG sets, the main emissions will be SO2 and NOx. For Proper dispersion of pollutants, the stack height meeting CPCB Norms will be maintained. 5.2 Emissions from production NO This is not an industry to have emissions processes from production process

5.3 Emissions from materials handling Yes Vehicular emissions are anticipated including storage or transport both during construction and during operation.

5.4 Emissions from construction Yes Fugitive emissions are likely during activities including plant and construction activities from the equipment materials. These are temporary in nature. The main emissions during the construction will be PM from the loading and unloading of materials on the site. SO2 and NOx from the combustion of fossil fuels and from vehicles.

PRIDHVI ENVIROTECH (P) LIMITED Page 9

M/s. Laxmi Infobahn Software Technology park LLP Sy.No: 107(P) & 108(P), Kokapet (V), Rajendranagar Mandal, Ranga Reddy District

5.5 Dust or odors from handling of Yes The particulate matter will be mainly materials including construction generated from loading and unloading materials, sewage and waste. of the material at the site. Other municipal solid waste will be disposed off to the Municipal solid waste dump yard. The construction material will be handled carefully to prevent any spill over or wastage. Construction labor will be provided with proper sanitation to avoid any unhygienic conditions. Therefore no odor generation is expected 5.6 Emissions from incineration of No Not envisaged waste

5.7 Emissions from burning of waste No Not envisaged in open air (e.g. slash materials, construction debris)

5.8 Emissions from any other sources No Not envisaged

6.0 Generation of Noise and Vibration, and Emissions of Light and Heat: S. No. Information /Checklist Yes/ Details thereof (with approximate confirmation No quantities /rates, wherever possible ) with sources of information data 6.1 From operation of equipment Yes Noise is anticipated during construction e.g. engines, ventilation plant, activities, movement of construction crushers material and use of machinery. These are temporary in nature and will

be minimized by adopting proper maintenance such as greasing, oiling and insulations (acoustic enclosures) for DG Set. 6.2 From industrials or similar No Not applicable processes

6.3 From construction or demolition No The noise and vibrations are only during the construction phase and proper

PRIDHVI ENVIROTECH (P) LIMITED Page 10

M/s. Laxmi Infobahn Software Technology park LLP Sy.No: 107(P) & 108(P), Kokapet (V), Rajendranagar Mandal, Ranga Reddy District

precautions are taken to ensure that the decibel levels are below the standards and the equipment utilized for constructions are properly serviced and maintained for reducing vibration and noise levels 6.4 From blasting or piling No Not envisaged

6.5 From construction or operational Yes Noise levels of 55dB (A) are anticipated traffic. during daytime due to the vehicular movement and construction activities, but it will be of temporary nature

6.6 From lighting or cooling systems No The lighting systems have a major component of LED to save an energy for the whole project 6.7 From any other sources No --

7.0 Risks of CONTAMINATION OF LAND OR WATER from releases of pollutants into the ground or into sewers, surface waters, groundwater, coastal waters or the sea :

S. No. Information /Checklist Yes/ Details thereof (with approximate confirmation No quantities /rates, wherever possible ) with sources of information data 7.1 From handling, storage, use or No Used batteries and waste oil shall be spillage of hazardous materials stored separately and shall not lead to contamination of land during normal operation.

7.2 From discharge of sewage or No The sewage shall be treated to achieve other effluents to water or the the standards prescribed by MoE&F land (expected mode and during operation phase. While the place of discharge ) discharges from temporary toilets during construction shall be sent to septic tank followed by municipal sewer lines. 7.3 By deposition of pollutants No No pollutants are emitted in to air. emitted to air into the land or Hence no deposition of pollutants into into water land or water.

7.4 From any other sources No --

PRIDHVI ENVIROTECH (P) LIMITED Page 11

M/s. Laxmi Infobahn Software Technology park LLP Sy.No: 107(P) & 108(P), Kokapet (V), Rajendranagar Mandal, Ranga Reddy District

7.5 Is there a risk of long term build No Proper Environmental management up of pollutants in the plan will be followed for air, water, noise environment from these sources? and solid waste. Hence no long term impacts are envisaged. 8.0 Risk of accidents during construction or operation of the Project, which could affect human or the environment S. No. Information /Checklist Yes/ Details thereof (with approximate confirmation No quantities /rates, wherever possible ) with sources of information data 8.1 From explosions, spillages, fires No Fire hydrant and Fire fighting systems will etc from storage, handling, use be installed and safety precautions will or production of hazardous be followed as per the safety rules. substances Only Diesel in small quantity and paints during construction phase will be flammable material used and stored. 8.2 From any other causes No Not Applicable

8.3 Could the project be affected No The project site is located at a higher by natural disasters causing elevation and the seismic zone for the environmental damage (e.g. project area is Zone-II, which is floods, earthquakes, landslides, considered safe. cloudburst etc)?

9.0 Factors which should be considered (such as consequential DEVELOPMENT) which could lead to ENVIRONMENTAL EFFECTS or the potential for cumulative impacts with other existing or planned activates in the locality

S. No. Information /Checklist Yes/No Details thereof (with approximate confirmation quantities /rates, wherever possible ) with sources of information data 9.1 Lead to development of Yes The proposed project is a supporting. utilities, ancillary construction of Commercial development or development Complex. So it leads to development stimulated by the project which of supporting facilities and ancillary & could have impact on the related activities. environment e.g.:

 Supporting infrastructure Yes (roads, power supply,

waste or waste water

PRIDHVI ENVIROTECH (P) LIMITED Page 12

M/s. Laxmi Infobahn Software Technology park LLP Sy.No: 107(P) & 108(P), Kokapet (V), Rajendranagar Mandal, Ranga Reddy District

treatment, etc.) Yes  Housing development  Extractive industries No

 Supply industries No No  Other

9.2 Lead to after use of the site, No -- which could have impact on the environment

9.3 Set a precedent for later Yes The area is developed commercial developments area.

9.4 Have cumulative effects due to No -- proximity to other existing or planned project as with similar effects )

(III) Environment Sensitivity

S. No. Areas Name/ Aerial distances (within 15 km.) Identity Proposed project location boundary

1. Areas protected under No - international conventions, national or local legislation for their ecological, landscape, cultural or other related values

PRIDHVI ENVIROTECH (P) LIMITED Page 13

M/s. Laxmi Infobahn Software Technology park LLP Sy.No: 107(P) & 108(P), Kokapet (V), Rajendranagar Mandal, Ranga Reddy District

2. Areas which are important or Yes MuskinCheruvu – 2.84 Km(E), sensitive for ecological reasons – Nallagandla Cheruvu – 7.35 km (NW), Wetlands, water courses or other Gopi Cheruvu – 8.15 km (N), water bodies, coastal zone, Pedda Cheruvu – 4.82 km (EN), biospheres. Mountains, forests Pedda Cheruvu – 6.66km (W), Osman Sagar– 2.57 km (SW), Vattinagulapalli Cheruvu – 4.62 km (WN), Battemma Cheruvu – 3.24 km (EN), Durgam Cheruvu – 6.36 km (EN), Chinta Kunta – 3.20 km (NE),

Himayat Sagar– 6.62 km (SE)

3. Areas and by protected, Yes important or sensitive species of - flora or fauna for breeding, nesting, foraging, resting, over wintering, migration 4. Inland, coastal, marine or No underground waters

5. State, National boundaries No -

6. Routes or facilities used by the No public for access to recreation or other tourist, pilgrim areas 7. Defense installations No None

8. Densely populated or built-up Yes The area is developing into a densely area populated area.

9. Areas occupied by sensitive Yes man-made land uses (hospitals, schools, places of worship, community facilities )

PRIDHVI ENVIROTECH (P) LIMITED Page 14

M/s. Laxmi Infobahn Software Technology park LLP Sy.No: 107(P) & 108(P), Kokapet (V), Rajendranagar Mandal, Ranga Reddy District

10. Areas containing important, high No - quality or scarce resources (ground water resources, surface resources, forestry, agriculture, fisheries, tourism, minerals) 11. Areas susceptible to natural No -- hazard which could cause the project to present environmental problems (earthquakes, subsidence, landslides, erosion, flooding or extreme or adverse climatic conditions) IV. Proposed Terms of Reference for B-2 Category Project EIA Studies

PRIDHVI ENVIROTECH (P) LIMITED Page 15

M/s. Laxmi Infobahn Software Technology park LLP Sy.No: 107(P) & 108(P), Kokapet (V), Rajendranagar Mandal, Ranga Reddy District

FORM-1 A (Only for construction projects listed items 8 of the Schedule) CHECK LIST OF ENVIRONMETNAL IMPACTS (Projects proponents are required to provide full information and wherever necessary attach explanatory notes with the Form and submit along with proposed environmental management plan & monitoring programme)

1. LAND ENVIRONMENT

S.N ITEM DETAILS o. 1.1 Will the existing land use get The proposed project is Construction of significantly altered from the Commercial complex. project that is not consistent with the surroundings? (Proposed The existing land is designated as commercial landuse must conform to the as per the master plan of HMDA

approved Master Plan / Development Plan of the area. Change of landuse if any and the statutory approval from the competent authority be submitted). Attach Maps of (i) site location, (ii) surrounding features of the proposed site (within 500 meters) and (iii)the site (indicating levels & contours) to appropriate scales. If not available attach only conceptual plans. 1.2 List out all the major project The major requirements of the project is requirements in terms of the land summarized as below: area, built up area, water 1. Plot area 11,736.56 Sq.mts consumption, power requirement, 2. Net plot 10,828.40 Sq.mts connectivity, community facilities, area parking needs etc. 3. Built-up area 1,13,020.93 Sq.mts Commercial 4. No. and type Not applicable it is a of flats commercial complex 5. Water Daily water demand will

PRIDHVI ENVIROTECH (P) LIMITED Page 1

M/s. Laxmi Infobahn Software Technology park LLP Sy.No: 107(P) & 108(P), Kokapet (V), Rajendranagar Mandal, Ranga Reddy District

consumption be 600 KLD (274 KLD fresh water demand + 326 KLD recycled STP treated water). The fresh water Demand will be met from Municipal Supply 6. Power 10 MV requirement 7. Connectivity The project is well facilities connected with the following: Rajiv Gandhi International Airport – 21.3 KM

8. Parking The total area allocated needs for stilt and basement parking is 36,891.31 sq.m Two stack parking is proposed to accommodate 1566 4 wheelers and adequate two wheeler parking 9. Total Cost of Rs. 170.0 Crores the project

1.3 What are the likely impacts of the There will be minor impacts during construction proposed activity on the existing activity from the proposed project due to dust facilities adjacent to the proposed generation and operating of machines which site? (Such as open spaces, will be temporary in nature. Sparingly community facilities, details of the vegetated land will be changed into a net real existing landuse, disturbance to the value land having good aesthetic value. As the local ecology). project does not require clearance of any big structures or deforestation minimum effect on the surroundings or on the environment will be noticed. The added plantation will increase the greenery and scenic view of the area. 1.4 Will there be any significant land The area is not prone to any land disturbance disturbance resulting in erosion, and no evident history of the same is available. subsidence & instability? (Details of Soil Type – Hard morum soil with outcrops

PRIDHVI ENVIROTECH (P) LIMITED Page 2

M/s. Laxmi Infobahn Software Technology park LLP Sy.No: 107(P) & 108(P), Kokapet (V), Rajendranagar Mandal, Ranga Reddy District

soil type, slope analysis, vulnerability Slope Analysis: to subsidence, seismicity etc may The topography of the site is almost flat. There be given). will not be any change in topography of the area. The drainage pattern will remain as per the existing pattern. Vulnerability to Subsidence: There is no subsidence reported in the area. Seismicity – Zone – II as per the IMD 1.5 Will the proposal involve alteration No, there is no change in the overall natural of natural drainage systems? (Give drainage system. However, the internal run off details on a contour map showing drainage is channelized to the rain water the natural drainage near the harvesting pits for re-charging the ground proposed project site) water 1.6 What are the quantities of There will be scrapping off soil which will be earthwork involved in the used within the site for filling purposes. No fill construction activity-cutting, filling, material is required from outside as excavated reclamation etc. (Give details of soil, construction and demolition waste (existing the quantities of earthwork structures) will be reused within the site. involved, transport of fill materials from outside the site etc.) 1.7 Give details regarding water Water supply: supply, waste handling etc during The domestic water demand during the construction period. construction phase will be about 50 KLD. The water will be met from bore well & water tanker. Solid waste: The solid waste will be generated during construction phase and will be sent to GHMC. 1.8 Will the low lying areas & wetlands There are no wetlands and low lying areas get altered? (Provide details of how around the site. low lying and wetlands are getting modified from the proposed activity) 1.9 Whether construction debris & The construction debris consists of variety of waste during construction cause materials. Iron, glass, plastics, cartons of paper, health hazard? (Give quantities of wood waste etc would be sold to re-users. Demolished bricks, Cement Concrete etc various types of wastes generated would be used in internal road formation and during construction including the as filling materials of basements.

PRIDHVI ENVIROTECH (P) LIMITED Page 3

M/s. Laxmi Infobahn Software Technology park LLP Sy.No: 107(P) & 108(P), Kokapet (V), Rajendranagar Mandal, Ranga Reddy District

construction labor and the means Paint cans, adhesives, thinner cans etc would of disposal) be sold to authorized re-cyclers

2.0 WATER ENVIRONMENT:

S.No. ITEM DETAILS 2.1 Give the total quantity of water The daily water requirement for the requirement for the proposed proposed project will be 600.0 KLD. The daily project with the breakup of fresh water requirement will be 274.0 KLD, requirements for various uses. How sourced from Bore well and Municipal supply will the water requirement met? and the recycled water requirement will be State the sources & quantities and 326.0 KLD, which will be used for flushing and furnish a water balance statement. gardening.

2.2 What is the capacity (dependable (Source: Municipal Supply & Borewell) flow or yield) of the proposed source of water? 2.3 What is the quality of water required, in case, the supply is not Water will be sourced from municipal supply from a municipal source? (Provide and Bore well. In case of any emergency physical, chemical, biological water will be purchased from private sources characteristics with class of water through tankers quality) 2.4 How much of the water Out of 600 KLD requirement, approximately requirement can be met from the 326.0 KLD of the water required will be met recycling of treated wastewater? through reuse of treated water from sewage (Give the details of quantities, treatment plant. sources and usage) 2.5 Will there be diversion of water from No other users? (Please assess the Water will be sourced from municipal supply impacts of the project on other and Bore well existing uses and quantities of consumption) 2.6 What is the incremental pollution The waste water generated will be to the load from wastewater generated tune of 440 KLD. The waste water generated from the proposed activity? (Give will be treated in sewage treatment plant details of the quantities and based on FAB technology of capacity 550.0

PRIDHVI ENVIROTECH (P) LIMITED Page 4

M/s. Laxmi Infobahn Software Technology park LLP Sy.No: 107(P) & 108(P), Kokapet (V), Rajendranagar Mandal, Ranga Reddy District

composition of wastewater KLD. generated from the proposed effluent characteristic is given as: activity) Parameter Unit Concentration Quantity KLD 440.0 pH -- 6.5-8.5 Oil & Mg/l 20 Grease TSS Mg/l 200 BOD Mg/l 350 mg/lit COD Mg/l 500 mg/lit

2.7 Give details of the water Elaborate plans have been made for requirements met from water channelizing the storm water by constructing harvesting? Furnish details of the water drains leading to the reservoirs. In facilities created. order to minimize the surface runoff loss, groundwater recharging through groundwater recharge pits at the project site has been planned. Appropriate design considerations have been taken while designing the recharge pits.

The rainwater is proposed to be channelized for storage in reservoirs to be used for project needs after due treatment and also for groundwater recharging through the recharge pits. 2.8 What would be the impact of the The project will involve construction of land use changes occurring due to rooftop & paved areas and hence, quantity the proposed project on the runoff of runoff will increase due to reduced characteristics (quantitative as well infiltration & increase in surface run off as qualitative) of the area in the coefficient in post construction phase as post construction phase on a long compared to the pre-construction phase. term basis? Would it aggravate the The overflow during abnormally heavy rains problems of flooding or water will follow the run off pattern. The proposed logging in any way? rainwater structures have been designed for accommodating peak rainfall intensity, which will not aggravate the problem of flooding in the project area. The run-off from roof top, paved and landscaped areas will be used for ground water recharge.

PRIDHVI ENVIROTECH (P) LIMITED Page 5

M/s. Laxmi Infobahn Software Technology park LLP Sy.No: 107(P) & 108(P), Kokapet (V), Rajendranagar Mandal, Ranga Reddy District

Provisions of capturing the surface runoff to the extent of 100% will be done. 2.9 What are the impacts of the No Impacts will be on the ground water the proposal on the ground water? (Will required water will be supplied by municipal there be tapping of ground water; supply, borewell and part of the treated give the details of ground water water is recycled and used for gardening & table, recharging capacity, and flushing. Rain water harvesting structures will approvals obtained from be provided in the site to tap the rain water competent authority, if any) which in turn recharges the ground water table. 2.10 What precautions/measures are There are effective measures adapted to taken to prevent the run-off from reduce the storm water run-off from the construction activities polluting land construction site- & aquifers? (Give details of  Ensuring vehicles stick to the access track. quantities and the measures taken  Cleaning all mud and dirt deposited on to avoid the adverse impacts) roads from construction-related activities.  Stabilizing a single entry/exit point to ensure sediment is not tracked off site-this also increase site durability during wet weather.  Excavation work will not be carried out during monsoon season.  Constructing a fence around the site to trap sediment whilst allowing water to flow through.  Diverting up-slope water with turf and not mixing mortar in locations that will drain into storm water system.  Preventing wastewater from brick cutting activities and stockpiles entering the storm water system.  Construction material will be stored at the earmarked places and will be covered with a temporary shed ensuring that no leachate or spoilage of land occurs.  Curing water will be sprayed and, after liberal curing, all concrete structures will be painted & covered with gunny bags, then the water will be sprayed. This will help to save water.

PRIDHVI ENVIROTECH (P) LIMITED Page 6

M/s. Laxmi Infobahn Software Technology park LLP Sy.No: 107(P) & 108(P), Kokapet (V), Rajendranagar Mandal, Ranga Reddy District

2.11 How is the storm water from within Infrastructural facilities like provision of the site managed?(State the adequate storm water drains, wastewater provisions made to avoid flooding collection and conveyance including of the area, details of the drainage treatment and disposal have been planned facilities provided along with a site in the project. layout indication contour levels) 2.12 Will the deployment of construction The local people will be deployed during labourers particularly in the peak construction. There will be no stagnant water period lead to unsanitary conditions at site, as the run off from the relevant areas around the project site (Justify with will be systematically drained. proper explanation) The civil contractor will be held responsible for site sanitation and will be bound by the management to adhere to healthy level of sanitation. 2.13 What on-site facilities are provided Construction phase: for the collection, treatment & safe The waste water to the tune of 5 KLD from disposal of sewage? (Give details of toilets will be diverted to sewer system in the the quantities of wastewater area after getting necessary permissions generation, treatment capacities with technology & facilities for Post construction phase: recycling and disposal) Sewage water will be collected and treated in FAB based 550.0 KLD STP. Treatment efficiency: >85% Reuse and disposal: STP treated water: 326.0 KLD for flushing and gardening and rest would be disposed the drain 2.14 Give details of dual plumbing There will be separate pipelines for the supply system if treated waste used is used of the fresh water and treated water from STP. for flushing of toilets or any other Treated water will be used for the flushing use. purposes & Gardening purposes, domestic consumption.

3. VEGETATION

S.No. ITEM DETAILS 3.1 Is there any threat of the project to There will be no threat on the biodiversity the biodiversity? (Give a description due to the proposed project. Project site is

PRIDHVI ENVIROTECH (P) LIMITED Page 7

M/s. Laxmi Infobahn Software Technology park LLP Sy.No: 107(P) & 108(P), Kokapet (V), Rajendranagar Mandal, Ranga Reddy District

of the local ecosystem with it’s almost flat terrain mostly unique features, if any) dominated/covered with common grass and shrub species. Moreover, site doesn’t support any critical or special habitat; which can support threatened, endangered species. 3.2 Will the construction involve The construction will not involve extensive clearing or modification clearing and modification. of vegetation? (Provide a detailed account of the trees & vegetation affected by the project) 3.3 What are the measures proposed Due care will be taken to protect the to be taken to minimize the likely important site features: impacts on important site features  Tree plantation will be done to protect the (Give details of proposal for tree site features such as topsoil erosion, plantation, landscaping, creation ground water attenuation and avoiding of water bodies etc along with a contamination by leachate. layout plan to an appropriate  The excavated soil will be stored at scale) earmarked places protected from contamination and from polluting the existing features and will be used for surface leveling and for creation of landscaped areas.  Piling will be done so as to minimize the impacts on the existing structures in the nearby areas.  Green belt will be developed in an area of 1154.20 Sq.mts

4. FAUNA

S.No. ITEM DETAILS 4.1 Is there likely to be any The proposed site does not have any displacement of fauna- both terrestrial and aquatic fauna, so no terrestrial and aquatic or creation displacement will take place. of barriers for their movement? Provide the details. 4.2 Any direct or indirect impacts on No endangered or endemic species of the avifauna of the area? Provide birds are found in the study area,

PRIDHVI ENVIROTECH (P) LIMITED Page 8

M/s. Laxmi Infobahn Software Technology park LLP Sy.No: 107(P) & 108(P), Kokapet (V), Rajendranagar Mandal, Ranga Reddy District

details 4.3 Prescribe measures such as Not applicable corridors, fish ladders etc to mitigate adverse impacts on fauna

5. AIR ENVIRONMENT:

S.No. ITEM DETAILS 5.1 Will the project increase There will be increase in intensity of land use atmospheric concentration of in the existing area, which may result in the gases & result in heat islands? (Give creation of heat islands. DG sets are details of background air quality deployed for the project, which will result in levels with predicted values based the increase in atmospheric concentration on dispersion models taking into of gases. account the increased traffic Impact: generation as a result of the  Urban Heat island effect due to increase in proposed constructions) the paved areas (Roof +& Non Roof).  Emissions due to traffic load  An emission due to DG sets Mitigation measures: Heat Island Effect: Roof  The roofs will be covered with solar panels which will reduce the exposed roof area.  The other exposed roof will be covered with white china mosaic tiles/green roof to reduce the heat gains inside the building. Heat Island Effect: Non-roof:  Hard paving onsite has been reduced to the best possible extent.  About 10% of the area will be under greenbelt, which will mitigate heat island effect. Fugitive dust emissions: Sources:  Construction activities.  Vehicular movement.  Road construction.  Paved and unpaved area emissions. Mitigation:

PRIDHVI ENVIROTECH (P) LIMITED Page 9

M/s. Laxmi Infobahn Software Technology park LLP Sy.No: 107(P) & 108(P), Kokapet (V), Rajendranagar Mandal, Ranga Reddy District

 Screening the construction site with the help of tarpaulin to contain the emissions within the site.  Water spraying on the haul roads.  Storage of construction material and waste at earmarked places and well covered. Impact due to traffic emissions: The impact of vehicular emissions varies with rate of movement of vehicles, atmospheric conditions and stability classes. Mitigation:  Area will be under landscape.  The vehicles will be PUC certified.  Reduced vehicular speed will also avoid the air borne fugitive emission on the unpaved areas. 5.2 What are the impacts on The impacts of dust and gaseous pollutants generation of dust, smoke, odorous due to different construction activities will be fumes or other hazardous gases? localized and will not affect the surrounding Give details in relation to all the environment. All necessary measures will be meteorological parameters taken.  Water spraying at dust generation sources  All transportation vehicles will be suitably covered to prevent dust dispersion from the trucks, and overloading of the vehicles will be avoided and must be PUC certified vehicle.  Plantation is proposed to be taken up along the boundary of the project site to the extent possible.  Eco-friendly D.G. Sets will be installed to maintain the emission within the norms etc.  The D.G. sets will be provided with adequate safe stack height to regulate the emission within the permissible norms.  Low sulphur content fuel (HSD: sulphur content: 0.25%) will be used which will help to contain the emissions within the

PRIDHVI ENVIROTECH (P) LIMITED Page 10

M/s. Laxmi Infobahn Software Technology park LLP Sy.No: 107(P) & 108(P), Kokapet (V), Rajendranagar Mandal, Ranga Reddy District

permissible range. 5.3 Will the proposal create shortage of Adequate provision will be kept for parking parking space for vehicles? Furnish at the proposed project. Sufficient planning details of the present level of is being done so that transport system is transport infrastructure and organized by following the good traffic measures proposed for management techniques. improvement including the traffic Proposed stilt and Basement parking area – management at the entry & exit to is 37,056.76 Sq.Mts the project site. No. of Vehicles – 2966 four wheelers & and adequate parking for Two wheelers. Following measures will be adopted for smooth traffic movements:  Provisions of fully internalized parking including the parking facilities for the visitors.  Guided traffic ways within the project site.  Speed humps will be installed for speed restrictions inside the project area. 5.4 Provide details of the movement The movement pattern inside the project patterns with internal roads, bicycle area will be guided traffic ways. There will tracks, pedestrian pathways, not be any separate bicycle tracks or footpaths etc., with areas under pedestrian pathways on the periphery each category. (driveway). 5.5 Will there be significant increase in There is no significant increase in noise and traffic noise & vibrations? Give vibration. The noise and vibrations level will details of the sources and the be well within the norms. Speed of the measures proposed for mitigation vehicles will be limited to 15-20 Km/hr to of the above. minimize noise and vibration. The following measures will be adopted to reduce the noise:  Trees with heavy foliage will be planted at the periphery so as to restrict the noise levels within the permissible norms.  Both entry and exit are manned with trained and efficient security.  Road markings, Stop lines, parking lanes are painted to guide the internal road user.  Separate entry/exit is provided such that it

PRIDHVI ENVIROTECH (P) LIMITED Page 11

M/s. Laxmi Infobahn Software Technology park LLP Sy.No: 107(P) & 108(P), Kokapet (V), Rajendranagar Mandal, Ranga Reddy District

enables the smooth movement of the vehicles. 5.6 What will be the impact of DG sets Construction Phase: & other equipment on noise levels The noise level due to construction activity & vibration in & ambient air quality and in operational phase will be localized to around the project site? Provide the source. During the construction phase, details. noise will be generated from the construction equipment’s and the operation of DG sets. Fugitive emissions generated from various construction activities will be contained by screening the site by tarpaulin. The noise level due to construction activity and in operational phase will be localized. Post Construction phase: The important source of pollution during post construction phase will be emissions from D.G. sets used in case of power cuts or failure (for complete power back up). The DG sets will be housed in an inbuilt acoustic enclosure for maximum noise attenuation. The DG sets deployed will be EPA/ CPCB certified for the permissible standards of noise & vibrations.

6. AESTHETICS S.No. ITEM DETAILS 6.1 Will the proposed constructions in The proposed project will not in any way any way result in the obstruction of obstruct any view, scenic amenity or a view, scenic amenity or landscapes. In fact it increases aesthetics of landscapes? Are these the area due to large scale green belt considerations taken into account development by the proponents? 6.2 Will there be any adverse impacts No, there will be no impact on existing from new constructions on the infrastructure due to the construction existing structures? What are the activities. considerations taken into account? 6.3 Whether there are any local The layout plan is on the basis of

PRIDHVI ENVIROTECH (P) LIMITED Page 12

M/s. Laxmi Infobahn Software Technology park LLP Sy.No: 107(P) & 108(P), Kokapet (V), Rajendranagar Mandal, Ranga Reddy District

considerations of urban form & development rules prescribed by GHMC. urban design influencing the design criteria? They may be explicitly spelt out. 6.4 Are there any anthropological or No, there are no anthropological or archaeological sites or artefacts archaeological sites or artefacts nearby. nearby? State if any other significant features in the vicinity of the proposed site have been considered.

7. SOCIO-ECONOMIC ASPECTS

S.No. ITEM DETAILS 7.1 Will the proposal result in any No such changes envisaged changes to the demographic structure of local population? Provide the details. 7.2 Give details of the existing social The proposed project is conveniently infrastructure around the proposed located close to Rajiv Gandhi International project. Airport – 21.3 km distance. As the unit is located in city area hence required infrastructures is located nearby the project site. Other basic infrastructural amenities like safe drinking water, electricity, market, and medical services are available around the proposed project. 7.3 Will the project cause adverse No, Project is not likely to have any adverse effects on local communities, effect on local population; rather the local disturbance to sacred sites or other population will get benefit arising due the cultural values? What are the proposed project. safeguards proposed? 8. BUILDING MATERIALS

S.No. ITEM DETAILS 8.1 May involve the use of building The basic materials used will be cement, materials with high-embodied steel, bricks, stones, ready mix concrete, energy. Are the construction sand, gypsum, plywood, hard wood,

PRIDHVI ENVIROTECH (P) LIMITED Page 13

M/s. Laxmi Infobahn Software Technology park LLP Sy.No: 107(P) & 108(P), Kokapet (V), Rajendranagar Mandal, Ranga Reddy District

materials produced with energy aluminum, glass, etc. efficient processes? (Give details of  Low energy embodied materials will be energy conservation measures in given preference. the selection of building materials  Energy efficient construction materials and their energy efficiency) such as Gypsum Plaster Concrete, Sand Aggregate, Fly Ash Cement, will be used to achieve the desired primary energy efficiency.  Ready Mix concrete will be used for construction of RCC structures. M-sand will be used as an alternative to river sand and the building blocks will be solid cement blocks that are energy efficient and work efficient compared to baked bricks.  Ensuring that the building materials and products have low energy embodied energy.  Minimizing the transport of temporary structures, scaffolding, formwork, consumables and building product to the construction site.  Minimizing overall waste and the transport of waste from site.  Use of energy efficient lighting.  Ensuring idle construction equipment is throttled down or switched off All the items to be used in the project are as per the National Building Code-2005 and ECBC. 8.2 Transport and handling of materials During the construction phase, the following during construction may result in measures will be taken to prevent pollution. pollution, noise & public nuisance.  Top soil excavated during construction What measures are taken to activities will be stored for use in minimize the impacts? horticulture/landscape development within the project site to the possible extent  Covering of the construction site from all four sides to a substantial height to

PRIDHVI ENVIROTECH (P) LIMITED Page 14

M/s. Laxmi Infobahn Software Technology park LLP Sy.No: 107(P) & 108(P), Kokapet (V), Rajendranagar Mandal, Ranga Reddy District

prevent dust emissions and other pollutants into surrounding area.  Covering loads to limit materials or litter blowing off and reducing smells.  Ready mix concrete will be used for concreting. This avoids cement and aggregate handling fugitive emissions and noises.  Noise machines will be preferred after 10.00 am. Loading and unloading will be done with low height.  Unloading of construction material will not be done during night  Water spraying to prevent dust pollution from different sources of construction.  Speed restriction of all the vehicles approaching the site and within the site.  All transportation vehicles will be suitably covered with tarpaulin & overloading of the vehicles will be avoided and must be pollution checked vehicle.  Heavy earth working will be avoided during night. 8.3 Are recycled materials used in The excavated soil will be used for backfilling roads and structures? State the as well as for creating landscaped areas. extent of savings achieved? 8.4 Give details of the methods of The estimated quantity of garbage will be collection, segregation & disposal around 1392 kg/day of. It is proposed to of the garbage generated during segregate the wastes and will be given to the operation phases of the GHMC waste collection center for disposal project. to municipal solid waste management facilities

9. ENERGY CONSERVATION S.No. ITEM DETAILS 9.1 Give details of the power The source of the Power is from TSCPDCL. requirements, source of supply, Power requirement: 10 MV backup source etc. What is the Backup power: 7 X 2000 KVA DG sets for energy consumption assumed per emergency during power failure.

PRIDHVI ENVIROTECH (P) LIMITED Page 15

M/s. Laxmi Infobahn Software Technology park LLP Sy.No: 107(P) & 108(P), Kokapet (V), Rajendranagar Mandal, Ranga Reddy District

square foot of built-up area? How Energy saving measures proposed to have you tried to minimize energy minimize energy consumption is as follows. consumption? 1) Use of energy saving methods in AC cooling and lift (V3F) in place of conventional methods 2) Corridors, walkways and staircases have been provided with natural lighting to the maximum extent possible 3) Use of Compact fluorescent lamps (CFL) & low voltage lighting. 9.2 What type of, and capacity of, 7 X 2000 KVA DG sets will be used as backup power back-up to you plan to power for emergency during power failure. provide? APFC panel will switch the above loads onto DG supply within 10 – 12 seconds. In case of repair/ maintenance or operational difficulty with any DG set, DG sets will be manually interchangeable to cater only to the critical loads. HSD requirement will be 300 Litres. 9.3 What are the characteristics of the The type of glass proposed to be used will be glass you plan to use? Provide plain glass with have low conductance and specifications of its characteristics high insulation properties so that heat ingress related to both short wave and into the inside of the building will be long wave radiation? minimized. This will help to reduce the heat gain in the building. 9.4 What passive solar architectural Passive solar cooling is incorporated in the features are being used in the building design. Buildings are suitably building? Illustrate the applications oriented for ensuring natural ventilation and made in the proposed project. day lighting. Building design and envelope may be optimized through selection of appropriate wall and roof construction and through adoption of solar passive measures after studying the sun path analysis to provide shading devices for windows and roof which would reduce energy demand. 9.5 Does the layout of streets & Solar power facilities shall be used for buildings maximise the potential for external lightning. solar energy devices? Have you Paving onsite (open area surrounding considered the use of street building premises) is reduced to the extent

PRIDHVI ENVIROTECH (P) LIMITED Page 16

M/s. Laxmi Infobahn Software Technology park LLP Sy.No: 107(P) & 108(P), Kokapet (V), Rajendranagar Mandal, Ranga Reddy District

lighting, emergency lighting and possible to minimize the imperviousness of solar hot water systems for use in the site and shade will be provided on hard the building complex? Substantiate paved surfaces to minimize heat island with details. effect. Passive solar cooling will be incorporated in the building design. Building will suitably orient for ensuring natural ventilation and day lighting. Solar panels will be used for the common area lighting load. 9.6 Is shading effectively used to Walls. reduce cooling/heating loads? East and West Elevations. What principles have been used to Walls that face the east and west will be well maximize the shading of Walls on insulated as possible, to prevent summer the East and the West and the heat gain from the low morning and evening Roof? How much energy saving sun. has been effected? Roof: Brickbats will be placed on the flat roof to give a slope and then grouting the same with cement mortar admixed with some water proofing compounds. 9.7 Do the structures use energy-  Automatic power factor compensating efficient space conditioning, multiple capacitor units are provided for lighting and mechanical systems? maintaining of average power factor of Provide technical details. Provide 0.99 to have effective savings in energy details of the transformers and cost. All capacitors are provided with motor efficiencies, lighting intensity Harmonic Filters to avoid distortion in and air-conditioning load Voltage i.e. Clean Power is available to assumptions? Are you using CFC building. and HCFC free chillers? Provide  An APFC relay based on thyristerised specifications. switching is proposed to effect the power factor correction /improvement within a few cycles of deviation from the setting & also to reduce inrush currents.  All cables shall be derated to avoid heating during use. This also indirectly reduces losses and improves reliability. Lighting System:  The recommended illumination levels (in

PRIDHVI ENVIROTECH (P) LIMITED Page 17

M/s. Laxmi Infobahn Software Technology park LLP Sy.No: 107(P) & 108(P), Kokapet (V), Rajendranagar Mandal, Ranga Reddy District

Lux) as per the National Building Code of (2005) will be applied 9.8 What are the likely effects of the Heat emission from the project can be from building activity in altering the the following sources: micro-climates? Provide a self-  Heat absorbed and radiated from the assessment on the likely impacts of paved and concrete structures. the proposed construction on  Increased population for a particular creation of heat island & inversion stretch of land. effects? Any building activity would alter the microclimate of a site and it is inevitable that wind patterns and thermal gain patterns on a site would be changed. But the proposed building has been carefully designed to modify the microclimate so as to improve overall thermal comfort and reduce energy consumption. Shade giving trees are planted near the east and west side which affect the microclimate and provide cooling effect in summers. 9.9 What are the thermal The building materials will be selected with characteristics of the building characteristics that limit heat ingress into the envelope? (a) roof; (b) external inside of the building will be minimized. walls; and (c) fenestration? Give U value R value details of the material used and the (W/m2-°C) (m2-°C/W) U-values or the R values of the Roof 0.261 3.5 individual components. Wall 0.352 2.35 Source: ECBC CODE 2005 9.10 What precautions & safety Essential fire safety measures will be installed measures are proposed against fire into the building to ensure the safety of the hazards? Furnish details of occupants within the building in the event of emergency plans. fire or other emergency. The entire building will be designed as per NBC-2005 of India pertaining to fire hazards. Safety measures:-  Proper fire exits and exit signs in case of any emergency will be made available.  Fire extinguishers of appropriate type will be placed on a readily accessible place and will be maintained accordingly.

PRIDHVI ENVIROTECH (P) LIMITED Page 18

M/s. Laxmi Infobahn Software Technology park LLP Sy.No: 107(P) & 108(P), Kokapet (V), Rajendranagar Mandal, Ranga Reddy District

9.11 If you are using glass as wall The type of glass proposed used have low material provides details and conductance and high insulation properties specifications including emissivity so that heat ingress into the inside of the and thermal characteristics. building will be minimized. This will reduce the air conditioning load. 9.12 What is the rate of air infiltration into The design is based on maintaining positive the building? Provide details of how pressure in the conditioned areas. As such you are mitigating the effects of there shall be no outdoor air filtration into the infiltration. conditioned areas. However measured amount of outdoor air will be introduced in the HVAC system to maintain “INDOOR AIR QUALITY” as per international standards. 9.13 To what extent the non- The solar energy will be utilized efficiently for conventional energy technologies Solar light for external lighting. are utilized in the overall energy consumption? Provide details of the renewable energy technologies used.

10. Environment Management Plan

The Environment Management Plan would consist of all mitigation measures for each item wise activity to be undertaken during the construction, operation and the entire life cycle to minimize adverse environmental impacts as a result of the activities of the project. It would also delineate the environmental monitoring plan for compliance of various environmental regulations. It will state the steps to be taken in case of emergency such as accidents at the site including fire. A total of Rs. 1.70 Crores is allocated for implementation of EMP

PRIDHVI ENVIROTECH (P) LIMITED Page 19

M/s. Laxmi Infobahn Software Technology park LLP Sy.No: 107(P) & 108(P), Kokapet (V), Rajendranagar Mandal, Ranga Reddy District

Brief Note for the amendments in the Existing Environmental Clearance.

M/s. Laxmi Infobahn Software Technology Park LLP proposed to develop a commercial project at Sy No. 107(P) & 108(P) of Kokapet (V), Rajendranagar Mandal, RangaReddy District and obtained EC for their proposed project for a total built up area of 1, 23,956.38 Sq.mts in April 2018 from the state level Environmental Impact Assessment Authority, vide Order No. SEIAA/TS/OL/RRD- 255/2018 dated 26.04.2018.

As there are few minor changes in number of Floors from the original plan this application is made for amendment of previous EC

Following changes are proposed from the previously approved EC S.NO DISCRIPTION PREVIOUS PROPOSED 1 Total plot area of the 11,736.56 Sq.mts 10,828.40 Sq.mts ( decreased plot because 908.16 Sq.mts is effected under road widening)( as per the site plan given) 2 Total Built up area 1,23,956.38 Square 1,49,912.24 Square meters ( including parking meters increase in built up area) 3 Commercial Area 90802.74 Sq.mts 1,13,020.93 Sq.mts ( increased) a) Parking 33,153.64 Sq.mts 36,891.31 Sq.mts ( increased) Two stack parking is proposed to accommodate 1566 (4 wheelers.) b) Green Belt area 1,537 Sq.mts 1154.20 Sq.mts (it is about 10.66% of the total area)

4 Number of Floors 4B+G+20 Floors S + 4B+25 Floors 5 No. of employees to be 5500 People 8700 People accommodated 6 Cost of the project 150 Crores 170 Crores 7 Total water consumption 480.0 KLD 600.0 KLD * Fresh Water – 274.0 KLD Recycling water- 326.0 KLD 8 Waste water generation 390.0 KLD 440.0 KLD * 9 STP Capacity 500.0 KLD 550.0 KLD 8 Solid waste from the 1452.0 Kgs/Day 1755.0 Kgs/Day complex 9 DG sets 7X 2000 KVA 7 X 2000 KVA Pridhvi Envirotech (P) Ltd,Hyderabad. Page 1

M/s. Laxmi Infobahn Software Technology park LLP Sy.No: 107(P) & 108(P), Kokapet (V), Rajendranagar Mandal, Ranga Reddy District

* In the earlier report no. of work force was mentioned as 5500. But it is 8700. Hence the Water quantity re-estimated based on revised employee count.

As the total area proposed to be developed <1,50,000 Square Meters, as per the EIA Notification dated 14th September 2006, the proposed project activity falls under Building & Construction projects 8(a) Category B (B2), which necessities to obtain Environmental Clearance from State Level Environmental Authority, .

BUILT UP AREA AS PER THE MODIFIED SITE PLAN:

Following is built up area of the proposed floors. Details are provided in Table 1

TABLE - 1 Area statement of the Phases

S. No Floors Built up Area in Sq.mts

1 1st Floor 3,420.85 2 2nd Floor 4,566.67 3 3rd Floor 4,566.67 4 4th Floor 4,566.67 5 5th Floor 4,566.67 6 6th Floor 4,566.67 7 7th Floor 4,566.67 8 8th Floor 4,566.67 9 9th Floor 4,566.67 10 10th Floor 4,566.67 11 11th Floor 4,566.67 12 12th Floor 4,566.67 13 13th Floor 4,566.67 14 14th Floor 4,566.67 15 15th Floor 4,566.67 16 16th Floor 4,566.67 17 17th Floor 4,566.67 18 18th Floor 4,566.67 19 19th Floor 4,566.67 20 20th Floor 4,566.67 21 21st Floor 4,566.67 22 22nd Floor 4,566.67

Pridhvi Envirotech (P) Ltd,Hyderabad. Page 2

M/s. Laxmi Infobahn Software Technology park LLP Sy.No: 107(P) & 108(P), Kokapet (V), Rajendranagar Mandal, Ranga Reddy District

23 23rd Floor 4,566.67 24 24th Floor 4,566.67 25 25th Floor 4,566.67 Total 1,13,020.93

PARKING AREA:

The total area allocated for stilt and basement parking as per the modified site plan is 36,891.31 Sq.Mts two stack parking is proposed which can accommodate 1566 four wheelers and adequate two wheelers parking is provided. The total parking area is being proposed in the proposed project is given below.

TABLE - 2: PARKING SPACE PROVISION

S. No Phases Area in Sq Mtrs 1 Stilt 3804.91 2 Basement- 1 8271.60 3 Basement- 2 8271.60 4 Basement- 3 8271.60 5 Basement- 4 8271.60 TOTAL 36,891.31 sq.m

The conceptual Plan of the project is given at Annexure II

WATER REQUIREMENT:

As per National Building Code, 2016 (NBC), water requirement for occupants is 45 litres/day/ person and for visitors the requirement is 15 litres/day/person. The total population likely to be accommodated would be around 8700 people. Another 25 people would be there like security and other support staff. Thus total water requirement for inmates is estimated at 393.0 KLD. Quantity estimated for guests and visitors is estimated at another 1.0 KLD.. Also it is estimated that about 6.0 KLD of water is required for landscaping and plantation purposes and for HVAC is 200 KLD. Thus total water

Pridhvi Envirotech (P) Ltd,Hyderabad. Page 3

M/s. Laxmi Infobahn Software Technology park LLP Sy.No: 107(P) & 108(P), Kokapet (V), Rajendranagar Mandal, Ranga Reddy District requirement would be 600 KLD. It is proposed to source water from municipal supply and ground water.

The treated waste water would be recycled for toilet flashings and green belt. Any additional treated waste is there, same will be connected to municipal sewer

The total sewage water generated is 440.0 KLD. It is proposed to treat the sewage in STP of capacity of 550 KLD. The treated waste water is used for Flushing & gardening and the rest of the treated water would be send to municipal sewer.

TABLE - 3: WATER REQUIREMENT

Quantity Fresh/ Wastewater Method of S.No. Stream in KLD Recycled generated Treatment 1 Domestic Water 274.0 Fresh 220.0 STP 2 Toilet flushing’s 120.0 Recycled 120.0 3 HVAC 200.0 Recycled 100.0 4 Gardening 6.0 Recycled - - 5 Evaporation loss - 160.0 Total 600.0 600.0

BACK-UP POWER DETAILS:

It is proposed to provide power back up for entire office complex including amenities with 7 X 2000 KVA capacities with double back system c) Solid & Hazardous Waste Details:

Domestic garbage is anticipated from the office space complex. Total solid waste estimated @ 0.20 Kg/day per person and 0.15 Kg/day per visitor. Thus total garbage anticipated from the complex will be 1755.0 Kgs/Day which is proposed to be disposed to municipal solid waste disposal facility of MCH through local municipal authorities. About 30 Kgs/day of solid waste anticipated from sewage treatment plant and same will be used as manure.

Pridhvi Envirotech (P) Ltd,Hyderabad. Page 4

M/s. Laxmi Infobahn Software Technology park LLP Sy.No: 107(P) & 108(P), Kokapet (V), Rajendranagar Mandal, Ranga Reddy District

The hazardous waste generated will primarily be waste lube oil from maintenance of DG set of about 200 liters per annum and 100 liters per annum of transformer oil from transformers. This waste oils will be collected in barrels and disposed off through parties authorized by TSPCB / CPCB.

7 no’s of per annum of used batteries will be disposed of by a buy-back arrangement with the battery supplier.

TABLE - 4: ESTIMATED WASTE GENERATION FROM DIFFERENT ACTIVITIES

Particulars No of Quantity Remarks persons Kg/ day Commercial 8700 1740.0 0.20 kg/person/day Visitors 100 15.0 0.15 kg/person/day Total 8800 1755 Kgs/ Day

% After segregation at site Recyclable 30 526.5 Sold to authorized recyclers Biodegradable 60 1053.0 To compost yard/ organic converter Inert material 10 175.5 Sent to municipal solid waste disposal site 1584.0 Disposed to authorized E-Waste - (0.18kg/person/year) recyclers 4.5 (15 kg/Acre/day or Horticulture Used as manure for green 0.0037kg/sq m/day waste belt Greenbelt area- 1154.20 Sq.mts e-waste source: International Resoure Group Systems South Asia Pvt. Ltd (IRGSSA), (m/s IRG Systems South Asia Pvt. Ltd),

Pridhvi Envirotech (P) Ltd,Hyderabad. Page 5

M/s. Laxmi Infobahn Software Technology park LLP Sy.No: 107(P) & 108(P), Kokapet (V), Rajendranagar Mandal, Ranga Reddy District

6.4.4 BUDGET FOR EMP:

The details of activities and expenses to be incurred on EMP are presented below.

TABLE - 6.7: BUDGET FOR EMP

S. No Component Amount Rs Lakhs 1 Dust Suppression 5.0 2 STP & storm water management 90.0 3 Acoustic enclosures to DG sets 45.0 4 Green Belt Development 15.0 5 Rainwater Harvesting 15.0 Total 170 Lakhs( 1% of the total project cost) Recurring Expenditure 20 Lakhs per annum

Pridhvi Envirotech (P) Ltd,Hyderabad. Page 6