OFFICE OF INSPECTION INFORMATION REQUIRED TO BUILD A DECK 1. A recent survey showing the exact location of the proposed deck. 2. A set of plans showing how the deck will be constructed. You may be able to get a set of plans from your provider. (SEE SPAN TABLE) 3. A completed Village of Richfield building permit application. 4. Washington County Land Use office approval required! (SEE ATTACHED) 5. See Fee Schedule for current fee plus plan review fee.

VILLAGE REQUIREMENTS: • Decks must comply with building setback requirements. • Any deck attached to the must be provided with 48" of frost protection. • All wood used in deck construction must be pressure treated against decay or species that is naturally decay resistant. • Decks shall be designed for 50 P.S.F. (40# Live Load + 10# Dead Load). • Decks 6' or more above grade must use 6"x6" support posts. • All joists must have 1-1/2" bearing or be attached to beams with approved mechanical fasteners. • All hangers and hardware must be compatible for use with pressure treated wood and installed per manufacturer's specifications. • No deck may cantilever over a beam more than 24". • The maximum step to or from a deck is 8". • The maximum rise for deck is 8" and minimum tread is 9". Steps may not vary more than 3/16". • Handrails must be provided 30"-38" above the tread nosing on all open sides for all stairs more than 3 risers. • Guardrails are required around any deck more than 24" above grade level. Minimum height of guardrail is 36" and must have intermediate rails or (horizontal or vertical) not capable of passing a 4" object. The opening between the intermediate rails or balusters should be less than 4". • If the deck serves as an exit, the area shall be lighted. • Deck stairs to a pool must be equipped with a lockable, self-closing, self latching .

There shall be a distance of at least 5' from the well head and 5' from septic tanks.

Over => Revised 5/2016 Joel Jaster, Inspector [email protected]

Greg Darga, Inspector [email protected]

Richfield Village 4128 Hubertus Road Hubertus, Wisconsin 53033 www.richfieldwi.gov

Phone (262) 628-2260 Ext. 117 Fax (262) 628-2984 Table 2 (Treated Lumber)

JOIST LENGTH

S' 7' e' 9' 10" 11' 12' 73• lie 15' 16' .101eit ZS 16'0C 26 W OC 28 16-0C 23:8 IF OC 238 16' CO 24 ITOC 22418 10-00 2110 12' CC C Fee 20 24'OC 2$ 24" OC 248 24'OC 2x10 24" OC 210 24'00 210 24'OC 2:00 16'0C 2x12 24'OC 2x10 sr OC 2x12 16" OC 2412 16'00 Beam 1-24 1-26 1-243 1-23 1-218 1-2x8 1-2x10 1 - aio Size 1-26 1-24 1-248 1-210 1 -ZOO 1-210 1 -2x10 I-212 1-2x10 1-212 1-,2x12 Ixst 2 616'00 24 18.00. 24 16-0C 2x8 to-CO 2$ 16' CC 2x8 1,22 0C 210 16"00 2(10 IZOC ' 5 Size . 26 240C 24 24-00 2x8 24" OC 210 24- 0C NW 24° CC 2x10 240O alii 18'0C 242 DVOC 2x10 16'0C 2412 IF cc an 1e 0C Bean 2-25 2-24 1-24 1-28 1-24 1-248 1-2330 1-2;410 See 1-26 1-24 1-2x8 1-ar0 1 - an 1-2410 1--2x70 1-212 1-21D 1-212 1-212 Jaist 26 16. CC 24 16' 00 24 16' OC 2$ se cc as sew as 12.0C 210 16'0C 212 1Z 0G 6' Sae as aroc • 23 24-0C 28 240C 210 24-0C 210 24'0C 210 240C 2410 16'0C 212 24' CC WO 16'0C 212 WOC 2412 le oc Beam 2-24 2-24 2-2x8 2-24 2-246 2-26 2-210 2-x410 2-2d 0 2-2410 1 Sire 2-26 1-23 2-24 1 -210 1-210 1-210 1-2310 1-2x12 1-2412 1-2x12 1-2x72 Met 26 1610C 24 16" OC 24 16.02 27.13 16' Cc 2:r8 16.00 as IZOC zeta 10-01 We 12'0C T Ste 24 24'OC 22 24" OC 248 24'OC 2310 24' CC 2430 24-00 2310 24'0C 2x10 150C 212 2400 210 16'02 2xI2 IFCC 212 16"00 Beam 3-24 3-24 2-26 2-24e 2-24 3-248 2-210 2-2x10 2-2410 2-2310 Tr: 2-26 2-248 2-2x8 2-2x-D0 2-20 2-210 2-210 1-2212 2-2x12 2-212 2-212 kist - 24 W OC 226 16' oc as 16`oc as 16' CC 24 16'OC 28 12" OC 210 16.00, am 12-06 r Sze 24 24 Oc 24 24- CO 24824'0C 210 24r OC 210 24'0C am 24'0C 2x1016-00 212 24* CC 210 W OC 212 1F OC 2x12 16'0C Beam 3-2a 3 - 2,S 3-24 3-24 3-24 3-24 3-28 2-210 3-2x10 3-2x10 3 - a10 Sae 2-22e 2-24 2-28 2-210 2-2x10 2-210 2-210 2-212 2-212 2-2312 2-212 ..14.g. 24 IF CC 24 WOO 24 15- CC 2x818-0C 2c8 ?FOC 28 12'0C ale IF OC 2101700 9' Sze 26 240C as 24' CC 243 24'0C alo 24'0C 210 24'00 WO 24"00 ass 15 00 212 2V0C 2/0 16' OC 2312 16" CC 212 16'OC Beam 3-238 4-2x5 4-26 3-7xs 3-24 3-248 4-24 3-210 3- 7x10 3-2,10 3- 2X10 Sze 2-2(11 3-24 3-2%8 2-2x10 2-2110 2-2x10 3-210 2-2412 2-212 2-2412 2-212 Jzisi 2:6 16'0 246 16.00 24 IT OC 24 15" CC 2810'0C 2x8 1700 2x101502 aso 12' oc 10' Sae . 246 24-0C 245 24' OC 28 24'0C ale 24" OC 210 24-0C 210 24'0C 210 16'0C an 24'0C 210 16' OC 242 w CC 212 10-02 Beam 4-24 3-23 3-as 3-2xS 4-26 4-26 4-24 3-2e10 3 - 2x10 4-a10 4 - zdo Sze 3-228 2-2210 2-210 2-2.10 3-2x10 3-210 3-240 2-212 3-242 3-2x12 3-2x12 .tom 24 1r OC 2416- 00 28 IFOC 25 IF OC 26 1F OC 24 12'0C 2410 IFOC 201012'0C 11' size 24 24'0C 24 24' CC 28 24'0C 2410 24.0C 210 24.00 210 244 0C 210 10OC 212 24'0C 210 16-00 2312 16'00 an 10-CC Beam 3-28 3-23 4-2x8 4-228 3-2x10 3-1E10 3 - al0 4-210 4-210 4-2410 4-210 Size 2-210 2-213 3-210 3-216 2-202 3-212 3-2412 3-2(12 3 - 2e12 3-2002 3-2412 ..t.)./ as 16" 02 2:46 ir cc as 16' OC as 16' OC 24 16- cc 24 12'0C ale .16'OC 2x101200 12' Size 26 24'0C 24 24'0C 26 24- 0C WO 24'00 210 24-00 240 24.02 210 WOC 212 240C 2410- WOO 2312 15'00 2(12 WOO Beam 3-2.0 4-24 4-24 3-210 3 -2x10 4-210 4-210 4-210 Sim 2-210 3-210 3-2410 2-212 3-212 3-212 3-212 3-2x12 3-212 3-212 3-212 .6±0 as se oc 2x6 16' Cc 2,1 16' CC 2x8 WOC 2c8 16-0C al3 12 00 am 16-0C NW 12'0C 13' Size 24 24" cc 2x8 24'00 24 24`00 2r18 24-02 210 24'0C 210 240C 210 15. OC 212 24'0C 210 WOO 2x1216'06 212 WOC Beam 3-x48 4-24 3- Z40 4-210 4-2o0 4-2d0 Sae 3-210 3-22 3-212 3-212 3 -2x12 3-212 3-210 3-212 4-212 4-212 4-212 Joist 2x6 WOG 2x6 18' CC 2x8 16' OC 248 16-0C 248 16'02 at 1210C 210 16"00 2410 12'0C 14' Size 2V3 24' OC 7x8 24" OC al 24- pc " ass 24- 0C WO 24 oc alp 24-0C 210 IFOC an zroc aro sroc 2412 16' OC 212 16"OC Beam 4-248 3-2410 4-210 4-210 4-2x10 ENG. BF_Ati 1310.6151,M Size 3-2410 3-212 3-2412 3-242 3-212 3-3412 _ 4-212 4-2(12 4- zo 2 FrrcesRED 69:11.11REO

Washington County Planning and Parks Department

WASHINGTON COUNTY WISCONSTN

REMINDER TO PROPERTY OWNERS IN ALL UNINCORPORATED TOWNS Please note that the Washington County Planning and Parks Department Land Use Division administers and enforces the following ordinances within your municipality: CONTACT FOR THE FOLLOWING TOWNSHIPS: ■ Subdivision Ordinance ■ Sanitary Ordinance Phillip Gantlet-Land Resources Manager/Manager of Land Use Division ■ Shoreland/Wetland/Floodplain Wayne, Kewaskum, Addison, Hartford, Barton Zoning Ordinance Dave Sells-Inspector in Charge Polk, Erin, Richfield, Germantown

Dave Lindner-Land Use Inspector Farmington, West Bend, Trenton, Jackson Best time to call is from 8:00 to 9:00 A.M.

Before beginning any construction (including remodeling, reconstruction or any structural alterations), and landscaping, please contact us and request information on what permits and inspections may be necessary. The best time to call is from 8:00 to 9:00 A.M. Please contact us before doing any work on your Private Onsite Wastewater Treatment System (POWTS) other than the routine pumping of your septic tank every 2 or 3 years as required under County Ordinance; this includes the placement of covers, risers, pipes, vents, etc. County and State laws require that some repairs, alterations, extensions or additions require permits at the County level, and the State requires that the person performing the work be properly licensed.

Enforcement of the County Shoreland/Wetland/Floodplain Zoning Ordinance pertains especially to properties within 300' of a river or navigable stream, within 1,000' of a lake/pond as well as all floodplain and the majority of wetland areas. Please note that many very small ponds, streams and ditches are regulated as required by the State. Permits may require approval by the Washington County Planning, Conservation & Parks Committee and the full County Board prior to your starting work on the following projects within the shoreland/wetland/floodplain zoning district:

■ Landscaping, filling, grading, ponding, lagooning, dredging, excavating and any soil disturbance work. ■ Seawall or riprap. ■ Additions/alterations to existing structures or reconstruction of structures. ■ New construction of any type. ■ Retaining , sidewalks, driveways or other landscaping.

When working near lakes and streams, you are advised to contact the Wisconsin Department of Natural Resources in Milwaukee at (414) 263-8500, because in some cases permits will also be needed from them. Construction in any wetland or shoreline may require approval of the U.S. Army Corps of Engineers, phone number (262) 547-4171.

County approval will be needed for all subdivisions. Certified Survey Maps located in Shoreland/Wetland/Floodplain Zoning Districts frequently require County approval.

To help minimize complications, please do not hesitate to contact our office for information about the procedure for obtaining any of the permits mentioned above. This should be done several weeks prior to the proposed start of your project. When work takes place without permits, County and State laws usually hold the property owner responsible even if the work was done by a contractor. In some cases, the contractor may also be responsible. You should also contact the town regarding their permit requirements.

Form 1385 (Rev. 03115)

Public Agency Center - Suite 2300, 333 East Washington Street, P. 0. Box 2003, West Bend, WI 53095-2003 Phone: (262) 335-4445, Toll Free: 800-616-0446, FAX: (262) 335-6868