PRE 1. EXECUTIVE SUMMARY Particulars Details Project name Proposed Masonry Stone Mining Lease Plot No. 12, Area: 1.00 Hect. (Non Forest) by M/s. P. C. Ferro Melters Pvt. Ltd. Location Near village – Khamor, Tehsil – Shahpura, District – () Coordinate of the lease Details of Coordinates are enclosed as Annexure –I. area Toposheet No. 45 K/14 Mine area 1.00 Hect. Proved Reserves Mineral Masonry Stone (MT) 504151 Probable Reserves Mineral Masonry Stone (MT) 186722.50 Possible Reserves Mineral Masonry Stone (MT) 93361 Rec. Mineral Masonry 784234.50 stone (tonnes) Life of Mine ~10.50 years Estimated project cost 30.0 Lacs/- EMP Cost 0.50 Lac/- Mining operation will be carried out in day time only. Therefore no Power Requirement electricity is required. Fuel Requirement About 100 litr. /day Highest and Lowest S. No. Particulars Elevation (mRL) Elevation 1. Highest 413 2. Lowest 412

Land use District Tehsil Village Plot Area Occupancy No. (ha.) Bhilwara Shahpura Bhilwara 12 1.0 Govt. Land

Nearest habitation/ town Khamor at a distance of ~1.2 km towards SW direction from lease boundary. Nearest Airport Jaipur International Airport at ~150.0 km towards NE direction from lease boundary.

Nearest Highway S. Highway Distance Direction No.

1. SH-39 ~10.1 NNE

Nearest Railway Station Non within 15.0 km radius from mining lease boundary.

Power supply Shahpura is electrified. The electric power supply facility is not available up to the mine site presently. Mining operations will be done in day time only. Nearest Telephone Khamor at a distance of ~1.2 km towards SW direction from lease boundary. Nearest Dispensary and Khamor at a distance of ~1.2 km towards SW direction from lease Govt. Hospital boundary. Educational facility Khamor at a distance of ~1.2 km towards SW direction from lease boundary.. Water demand and supply 3.0 KLD, Source-Nearby village through water tankers. Nearest tourist places None within the study area. Defense installations None within the study area. Archeological Features None within the study area. Ecological sensitive zones None within the study area. Forest Area (Reserve . Protected forest at a distance of ~4.60 km in SE direction from Forest/Protected mining lease boundary. Forest/Wildlife . Protected Forest at a distance of ~13.50 km in SSE direction Sanctuary/National Parks from mining lease boundary. etc.) Nearest streams/ rivers/ . Mansi River at a distance of ~6.0 km in NNW direction from water bodies (from mine mining lease boundary. boundary) . Samelia Nadi at a distance of ~10.4 km in SE direction from mining lease boundary. . Khari River at a distance of ~13.80 km in NNE direction from mining lease boundary. Seismic zone Seismic zone – II.

2.0 INTRODUCTION OF PROJECT / BACKGROUND INFORMATION Proposed Masonry Stone Mining Lease Plot No. 12, Area: 1.00 Hect. (Non Forest) Near village – Khamor, Tehsil – Shahpura, District – Bhilwara (Rajasthan). 2.1 Identification of the project and project proponent

7

Name of the Project Proposed Masonry Stone Mining Lease Plot No. 12, Area: 1.00 Hect. (Non Forest) Near village – Khamor, Tehsil – Shahpura, District – Bhilwara (Rajasthan). Name of the Applicant M/s. P. C. Ferro Melters Pvt. Ltd. Location of the project Near village – Khamor, Tehsil – Shahpura, District – Bhilwara (Rajasthan) Proposed Production Mineral ROM(MT) Masonry Stone 81,495 Lease Area 1.00 hect. Status of the firm Pvt. Ltd. Company M/s. P. C. Ferro Melters Pvt. Ltd.

2.2 Brief Description of nature of the project.  LOI for Masonry Stone mine for an area 1.00 hect. was granted in favor of M/s. P. C. Ferro Melters Pvt. Ltd., R/o G. T. Road, Bhirangi, Durgapur, Distt. Bardhwan (W.B.) vide order No. SME/Bhil-Cir/CC-2/Bhil/Plot No. 12/2018/732 dated 24/05/2018.  The Mining Plan with progressive mine closure plan was approved vide order no. SME/Bhil-Circle/CC-II/Bhil./Plot No. 12/2018/816 dated 14/08/2018 for the production capacity of 81,495 TPA. Copy of the same are enclosed as Annexure-II. Nature of the Project Mining of Masonry Stone is in the lease area of 1.00 ha, near Village Khamor, Tehsil- Shahpura, Dist.- Bhilwara (Rajasthan). Mining will be carried out by Semi-mechanized Opencast method. Proposed production is as below:

The production & waste generation can be summarized as: Masonry Stone

Year ROM excavated in Saleable Masonry stone Waste of Volume MT tonnage in tonnes (all Grades & in MT size) First year 57120 54264 2856 Second year 64084 60880 3204 Third year 79620 75639 3981 Fourth year 81495 77420 4075 Fifth year 62370 59252 3118 Total 344689 327455 17234

2.3 Need for the project and its importance to the Country:

8

The Mining project falls in the area of the district Bhilwara, Rajasthan devoid of sufficient agriculture activities and other industrial growth. The earning sources of the region are limited. The region has scarcity of water. Mineral wealth of the state Rajasthan provides the employment opportunity to the people of the state. Mining is one of the major core sector industries which play a crucial role in the process of country economic development. 2.4 Demands-Supply

Demand of Masonry Stone will be fulfilled by this project. 2.5 Imports vs. Indigenous Production There will be no import for the project. There will be indigenous inputs in the entire mining activity. 2.6 Export Possibility The mining activity is not prospecting exports. 2.7 Domestic/Export Markets Applicant would like to sale out the mineral in domestic market as per requirement. No export is proposed. 2.8 Employment Generation (Direct or Indirect) The mining project will generate direct & indirect employment. About 18-20 people will get direct employment, and some persons will also be affected indirectly and employed with allied and related industries, such as transportation, maintenance, etc. 3.0 PROJECT DESCRIPTION 3.1 Type of Project including interlinked and interdependent projects: Production Capacity: Mineral ROM(MT) Masonry Stone 81,495 Lease area is situated at N/v – Village Khamor, Tehsil- Shahpura, Dist.- Bhilwara (Rajasthan). No Interlinked or Interdependent project.

3.2 Location Village : Khamor Tehsil : Shahpura District : Bhilwara State : Rajasthan

The entire lease area is 1.00 Ha. The lease area is Govt. waste land.

9

Key Plan

3.3 Details of Alternate Site Considered and the Basis of Selecting the Proposed Site, Particularly the Environmental Considerations Gone Into Should Be Highlighted: Mining is site specific project and limited to mineralized area. 3.4 Size/Magnitude of Operation: Production Capacity from the lease area is follows by semi-mechanized open cast method of mining. Mineral ROM(MT) Masonry Stone 81,495 .3.5 Project Description with process details

Method of mining for mineral Masonry Stone: The applied mining lease area shall be developed by opencast Mining. The mining shall be started from the surface. The Masonry stone is laying on the sub surface therefore open cast mining has been the obvious choice. Bench Parameters shall be – 1. Height –6m 2. Width - More than Height (Three time of widest m/c used) No of old mining pits, their dimension and location, plan and section of the pits, brief geology of the area:- No of existing Average Pits dimension in (m) pits Length Width Depth 1 31 11 2 2 18 8 2 3 10 8 2 4 17 11 1 Applicant has not mined that’s pits. The production & waste generation can be summarized as: Masonry Stone

Year ROM excavated in Saleable Masonry stone Waste of Volume MT tonnage in tonnes (all Grades & in MT size) First year 57120 54264 2856 Second year 64084 60880 3204 Third year 79620 75639 3981 Fourth year 81495 77420 4075 Fifth year 62370 59252 3118 Total 344689 327455 17234 Source-Approved Mining Plan with progressive min closure plan Ground Water Table Working will not intersect ground water. Extent of Mechanization:

Initially Dumper will also arrange on hire basis. Later the Applicant will go for own mechanization.

The mining method shall be open cast mechanized mining.

(i) Details of Proposed Mining Machinery-

Machine Nos. Make HP/Capacity *Jack Hammers 1 Atlas Copco 32mm *Compressor 1 Local 62.5 HP D. G. Set 1 Local 15 KVA Excavator 1 Hitachi 148 HP Dumper 4 Ashok Leyland 75 HP Water Tanker 1 Ford 5000 Liter Wagon drill m/c 1 Atlas copco 30m

(ii) Excavation & loading of mineral from face As indicated earlier, it is proposed to use hydraulic excavation (Hitachi-210) of 1.2cum, bucket capacity for exaction & loading of material from the mine face. The production from the mine can be maintained during the next five years by working 1 shift per day. (iii) Excavation & Loading Capacity of Loader a. Haulage within the Mining Lease hold The loading capacity of Excavator & Loader are given by the following equation: L = B x r x n x t x E/K Where L = Excavator & Loading capacity per shift in cum. B = Bucket capacity in cum. (1.2cum.) r = Co- efficient of filling of filling (assumed 0.8) n = Avg. number of exaction working hours in a shift (taken as 50 on the basis if cycle time of 2.0 min.) t = No. of effective working hours in a shift (taken as 6.0) E = Efficiency of utilization (assumed as 0.80) K = Swell factor (taken as 1.25 i.e. 25%) L = 1.2 x 0.8 x 50 x 6 x 0.80/1.25 = 184.32 cum/shift (stay 184 cum.) Number of Excavator Required: Therefore number of excavators required for mineral production comes to 1 NO. A 5-10 H.P. diesel engine operated pump has deployed in the mine for pumping out accumulated rain water from pit bottom. Where the Dumpers are fitted with exhaust conditioner should be indicated Source-Approved Mining Plan with Progressive Mine Closure Plan

12

3.6 Availability of water its source, energy/power requirement and source

Total water requirement in the mine will be about 3.0 KLD for drinking, spraying and sanitation. Water will be available through water tankers from nearby village. Detail of water requirement in KLD is given below: 1. Dust Suppression – 1.5 2. Drinking – 0.5 3. Green belt – 1.0 Total – 3.0 KLD Diesel for Mining machinery – about 100 Lt. per day is assumed to be consumed. It will be made available by contractors. 3.8 Resource Optimization/Recycling and Reuse Envisaged In the Project, If any, Should Be Briefly Outlet: N.A 3.9 Raw Material Required Along With Estimated Quantity, Likely Source, Marketing Area of Final Products, Mode of Transport of Raw Material and Finished Product. No raw material is required. 3.10 Schematic Representations of The Feasibility Drawing Which Give Information of EC Purpose:

13

4.0 SITE ANALYSIS The lease area is for mineral which is suitable for use in roads, Monuments and other construction works. The selected site has the following advantages. 1. The area chosen is not having habitation. 2. The site is well connected by road. 3. There are no industries near the site and there is no pollution. 4. No endangered species around the mine site. 5. Availability of labors from nearby villages. 6. Proximity to the market.

14

4.1 Connectivity: Connectivity details from Project Site are given Form-IM. 4.2. Land form, land use and land ownership The lease area is Govt. waste land. The lease area falls in Toposheet No. 45 K/14. Lease Area : 1.00 hect. Village : Khamor Tehsil : Shahpura District : Bhilwara State : Rajasthan

4.3 Topography: The topography of this area is undulating. 4.4 Existing Land use Pattern There is no village or hutments within the lease area. 4.5 Existing Infrastructure Commensurate with the scale of mining operations, the requisite support facilities are proposed to be provided, which are adequate to meet the functional requirement of the mine. Site services such as mine office cum rest shelter, first aid station, toilet etc are already available. Water will be available through water tankers from nearby village Khamor. 4.6 Soil / rock classification The area comprises Calc-silicate rocks of Kekri formation of Mangalwar complex of Bhilwara Super Group. As per surface observation Calc-silicate rocks is light to dark greenish grey in colour, medium to coarse grained, hard & compact in nature. The general trend of litho units is from NW-SE to SW-NE with dipping 30o-35o due NE to NW. it is found grade in to mica places. Soil Cover/ Alluvium- The soil/alluvium covers almost a small part of the lease area (except the isolated hillock of Masonry stone deposit). It is derived locally and occupies the low-lying areas and can be used for cultivation purposes. The thickness of soil cover varies from 0.5m to 3.0m. Regional Geology: - The Precambrian rocks of the district have been classified into the Bhilwara Supergroup (more than 2500 m.y.), the Aravalli Supergroup (2500 to 2000 m.y.), the Delhi Supergroup (2000-850 m.y.) and the Vindhyan Supergroup (900-570 m.y.). The Bhilwara Supergroup includes Banded Gnessic Complex

15

represented by Sndmata complex comprising migmatite, gneiss, sillmanite- biotite schist, calc silicate rock etc are exposed in the central part. The Hindoli Group consisting of metagreywacke, tuf, phyllite, quartzite, marble/dolomite are exposed in justaposition with the Mangalwar complex in eastern part. Rocks of the Bhilwara Supergroup are intruded by the Gyangarh- acidic rocks, amphibolites, norite, dolerite, Berach and the Jahazpur Granites. The Lower Proterozoic calcareous rocks chiefly consisting calc-schist, calc-gneiss, dolomite and also mica schist, chert etc are grouped within the Pur-Banera, Jahazpur and Rajpura-Dariba Groups which occur as isolated cover sequences overlying the Mangalwars. These are exposed west of Bhilwara, between Kachola and Jahazpur and east of Gangapur respectively. A small patch of Aravalli rocks represented by Dovda Group occur in southwestern part. Rocks of Delhi Supergroup , in the extreme northwestern part of the district are represented by the Gogunda and Kumbhalgarh Groups. The Gogunda Group consists of mainly calc-gneiss, marble with minor schist and quartzite. The southeastern part of the district is occupied by a sequence of shale, sandstone, limestone belonging to the Khorip, the Kaimur, the Rewa and the Bhander Group of the Vindhyan Supergroup. These rocks are juxtaposed with the Hiindoli metasediments along the Great Boundary fault.

The geological sequence worked out by G.S.I. is given as under:

Era/ Peiod Gelogical Group Lithology Cycle

Quarternery - - Alluvium, blown sand

Upper Vindhyan Bhander Shale, snadstone and limestone Proterozie Supergroup Group

Delhi Kumbhalgarh Calc-Schist, gneisses, marble, garnet- Super Group boitite schust, migmatites Group Gogunda Quartzite, biotite schist, Calcschist, Group hornblende schist

Aravalli Dovda Group Quartzite, dolomite marble, dolomite, Super amphibolites, cals-sillicates rocks, ARCHEAN ARCHEAN Group biotite schist, quartz-biotite gneiss and PROTHROZOIC PROTHROZOIC migmatites

Igneous activity/Intrusives Dolerite dykes and sills

16

Ranthambor quartzite, shales and slates Group

Igneous Berach granite and gneisses Jahajpur activity/ granite Intrusives

Pur-Banera Calc-schist, gneisses, banded Group magnetite-quaratzite, dolomitic marble, quartzite, garnet-mica schist and amphibolites

Jahajpur Dolomite, Phyllite, Quartzite Group

Hindoli Shales, slates, phyllites, Group metagrawacke, limestone, dolomite, quartzite, mica shist, meta basics, volcanics.

Bhilwara Supergroup Supergroup Bhilwara Mangalwar Migmatites, gneisses, mica schist, Complex garnetiferous mica schist, para- amphibolites silicified mica schist.

Sandmata Para-gneisses, migmatites, pyroxene- Complex granulites, amphibolites, biotite- ultranatic rocks.

Igneous Acidic and mafic bodies activity/ Intrusive

Stratigraphy of the mineral deposit in the area

Super Group Group Formation Lithology

Bhilwara Super Group Mangalwar Complex Kekri Formation Calc-silicate rocks

4.7 CLIMATIC DATA FROM SECONDARY SOURCES The climate of the area is dry with extreme temperature variation i. e. in summer as high as 440 C, whereas in winter it lowers to 60C or even less. Most of the rain falls during the period of July to September. Maximum and minimum rain fall varies (500mm- 200mm).

17

4.8 SOCIAL INFRASTRUCTURE  The infrastructure like, toilets, first aid stations etc will be made available at mine site.  The nearest village is Khamor, health & educational facilities (in the form of primary and secondary schools) are available there.  Medical facilities, Primary Health Centre are there in the area, imparting services, for advance medical facilities. In each village one health worker has been appointed by the Govt. to provide primary health facilities.  Village people are availing drinking water facilities generally from the hand pump, open well and tube well & PHED supply. The water supply is also supplied through tanker in few villages. During summer scarcity of water has been noticed.  Communication services like post office and telephones are available in the nearby village. Some of the villagers are having mobile phones.  An occupational health unit will be organized and the proposed measures will be adopted:  Pre & Periodical Medical Checkup program for all the workers.  Compulsory medical checkup program and first-aid box with necessary equipment will be provided.  Training for workers regarding occupational hazards.  Safety equipment i.e. dusts mask, safety shoes, gloves etc. 5.0 PLANNING BRIEF 5.1 Planning Concept: It is a mining project of Masonry Stone. The mining operation is being/will be done by Semi-Mechanized Opencast method of mining will be adopted and transportation of mineral shall be done through road by trucks. 5.2 Population Projection Man power requirement for mining is estimated to be 18-20 Nos. Most of the employees will be recruited from neighboring village. The laborers are provided along with tractor trolley by contractor or from nearby villages. So there will no permanently migration of people, hence there will be no population projection. 5.3 Land use Planning:  At the end of mine life 0.7862 ha. Area will be excavated which will be converted in to water reservoir & 0.2138 ha. Area will remain non utilized.  Green Belt/Plantation will be done outside (near school, near temple) the lease area; because this lease area is surrounded by other leases by all four

18

sides.

Part-(B) POST MINING LAND USE OF CORE ZONE WITH ENVIRONMENT MANAGEMENT Sr. *All the areas are given Forest Pvt. Govt. waste Pvt. Total No. in Hectares Land Ag. Land Land Land 1 Water Reservoir ------0.7862 --- 0.7862 2 Top soil Dump ------3 Backfilled area ------4 Stack Yard ------5 Sub Grade stack Yard ------6 Infrastructure ( Work shop, administrative ------Building) 7 Roads ------8 Railway ------9 * Green Belt ------(other than Backfilled) 10 Tailing Pond ------11 Effluent Treatment Plant ------12 Mineral Separation Plant ------13 Township ------14 Non Utilized ------0.2138 ---- 0.2138 Total ------1.00 ---- 1.00 Source-Approved Mining Plan with Progressive Mine closure plan

Part-(C) REQUIREMENTS FOR PLANTS FOR AFFORESTATION AND RECLAMATION

Year Un-worked Waste Dump Inside Dump Top Soil Total Area (Outside) (Reclaimed Dumps Area)

Area No. of Area No. Area No. Area No. Area No. (Ha.) (Ha.) of (Ha.) of (Ha.) of (Ha.) of Trees Trees Trees Trees Trees

Existing ------

1st 0.0225 10 ------0.0225 10

2nd 0.0225 10 ------0.0225 10

3rd 0.0225 10 ------0.0225 10

4th 0.0225 10 ------0.0225 10

5th 0.0225 10 ------0.0225 10

6th Year 0.6521 260 ------0.6521 260 Onwards

Total 0.7646 310 ------0.7646 310

Source-Approved Mining Plan with Progressive Mine closure plan

5.4 Assessment of Infrastructure Demand

19

All basic infrastructures is available at mine site and as per requirement more facilities are proposed in the lease area. Water will be available through water tankers from nearby village Khamor. Most workers will be from nearby villages so no accommodation at mine site will be required. Medical facilities will be provided to the employees. 5.5 Facilities Provided: 5.5.1 Infrastructure The basic infrastructures will be made available in the lease area like office, store, workshop and shelter for the workers. Water will be available through water tanker from village Khamor. Most of the workers will be from nearby villages so no accommodation is proposed at mine site will be required. 5.5.2 Landscaping and Green Belt Development No trees are there in the area which will be uprooted during mining. It is proposed to plant a total no. 310 saplings per year on the non-mineralized area. The total proposed area is 0.7646 Ha. And survival rate 80% is expected; therefore 20% more saplings will be planted next year. A number of species will be planted suitable to this area of climate conditions like Neem, Babool, Khejari, Amal Taas, Vilayati Babool etc. Note: Total 310 trees will be planted (nearby area of school, along road side, at waste dump) outside of mine lease which will 33 % of the total lease area for plantation. Certain Species like Neem, Babool, Khejari, Amal Taas, Vilayati Babool which are more suitable to local soil are proposed to be planted. 5.5.3 Health and safety System During the opencast working, and allied activities, all the precautionary measures shall be taken into account as per MMR 1961 and MCDR 2017 for safety and security. Following Safety & security measures will be enforced;  Moving front of the quarry shall have temporary fencing.  Permanent fencing will be provided where quarry has reached the ultimate pit limit.  Mine entrance will have a permanent check post and record shall be maintained of all persons / vehicles entering the mine area.  Round the clock security arrangement shall be provided to prevent inadvertent entry of persons. 5.5.4 Disaster Management and Risk Assessment

20

Inspite of following all the precautionary measures and following all safety rules, regulations and procedures, in mining accidents cannot be ruled out completely. The Project Proponent will formulate a Disaster Management Plan with the approval of DGMS. Following are the accidents which can take place in mechanised opencast mining and measures proposed to be taken.  Fall of human beings or fall of machines from benches/ dumps/haul roads.  Due to drilling / blasting and handling of explosives.  Fire & Explosion in machinery  Emergency situation due to social reason such as public unrest, terrorism etc. Preventive Measures:  Creating berm on the side of benches/ haul roads of height greater than or equal to ½ tyre radius. Minimum height of berm shall be 1.2 m and slope 450. Minimum clearance of 1.5 m will be maintained between outer tyre and berm.  All provisions of MMR 1961, conditions imposed in permission for Deep hole drilling and blasting and use of HEMM, and conditions of explosive license will be followed.  Fire fighting equipment in the machinery/ workshop/ office will be maintained. Persons will be trained in the use of fire fighting equipment and mock rehearsal will be conducted.  Training of security personnel.  Procedures as laid down in Disaster Management Plan to be followed. Training; Persons will be trained in the following:  Knowledge of Chemicals and use of protective equipment  Procedures for reporting emergencies.  Location and use of fire fighting equipment  Knowledge of alarm system and siren  Evacuation procedures.  Training in first aid as per Mines Rules 1955 Emergency Equipment & Facilities:  Mobiles.  Fire fighting equipment’s  Emergency medical supplies

21

Other protective equipment’s i.e. goggles, helmet, face shield, hand gloves, safety belts, barricade tape. First Aid box as per the provisions of Mines Rules 1955.

6.0 PROPOSED INFRASTRUCTURE S.NO Details 1 Mining Area 1.00 hectares. 2 Residential Area Not Applicable 4 Green Belt Total 310 trees will be planted (nearby area of school, along road side, at waste dump) outside of mine lease which will 33 % of the total lease area for plantation. Certain Species like Neem, Babool, Khejari, Amal Taas, Vilayati Babool. Which are more suitable to local soil are proposed to be planted. 5 Water Management 3.0 KLD, Source: nearby village through water tanker. 6 Power Management N.A. 7 Waste Water Domestic and office effluent treated in individual septic tanks. 8 Solid Waste Waste dump generated will be stacked within Management the lease area as per approved Mining Plan with Progressive Mine Closure plan. 9 Hazardous waste N.A. Management 10 Social All necessary social Infrastructures will be Infrastructure provided by mine’s proponent.

7. REHABILITATION & RESETTLEMENTPLAN Since the project site is Govt. waste land and there is no village or hutments within the lease area. R&R is not applicable to this project. 8. PROJECT SCHEDULE 8.1 Likely date of start of construction and likely date of completion (time schedule for the project to be given) This is the exiting mine lease area and application is being filed within the stipulated time to the concerned department. 8.2 Project Cost Estimation Estimated Project Cost with the proposed production is Rs. 30.0 Lacs/- 9. ANALYSIS OF PROPOSAL  Project creates direct & indirect employment opportunities within the surrounding region. Unit uses good faith efforts to employ local people

22

from the nearby villages depending upon the availability of skilled & un- skilled man-power surrounding the project site.  In operation phase, the project would require significant workforce of non- technical and technical persons. Migration of highly education and skilled experience result in increase of literacy in the surrounding villages.  In addition, the proposed expansion of project shall enhance the prospects of employment.  Assessment of the potential socioeconomic benefits during mining focused primarily on work force requirements, acquisition of supplies, and the temporary increased demand for services related to the mining project like food, housing, communications, law enforcement, medical care, local transportation etc. Due to these, additional revenue to local suppliers for required products and services related to the construction and operation phases of the project will generate.  Thus, mining activities provide numerous new, although temporary, work opportunities for both skilled and unskilled labor, as well as contribute significantly to the local economy.  Additional government revenue expected from royalty, taxes, duties and other fees.  An added benefit to the project will result in considerable growth of stimulating the industrial and commercial activities in the state. Small and medium scale industries may be further developed as a consequence.

------********------

23

ENVIRONMENTAL MANAGEMENT PLAN

WATER QUALITY MANAGEMENT The Ground water table is 40m from the surface (in rainy season) to 45m (in Dry Season). In the mining lease area the flow of water is very low. The water from pit will be pumped by diesel pump of 5 HP capacities. The working at the end of third year will not intercept the water table. The natural gradient will drain out water from mine area in rainy season. Required rain water in the pit shall not discharge and shall be utilized for Water spraying, plantation, and other mining work. At the end of life of the mine the pit shall be used as water reservoir.

AIR QUALITY MANAGEMENT : Water sprinklers are proposed on haul road and at work place for dust suppression. Dust mask will be provided to the operator & mine workers. The source of air pollution is vehicular movement but the transportation will be towards the lower side hence the impact is not very much significant. Vehicular emission will be controlled and regularly monitored. Loading is also creating air pollution. Water spraying is proposed over the material before loading and transportation. Covered trucks will be used in transportation. Green belt will be developed to arrest dust pollution. Proposed mining is Semi-Mechanized and no processing/ grinding unit is proposed in the applied area, hence the air pollution will remain in permissible limit. For drilling wet drilling method will be used to control fugitive dust at source. Blasting will be done by covering blast holes with cement bags filled with sand so that chances of fly rocks will be minimized. Green belt development will be done to arrest dust pollution.

24

NOISE MANAGEMENT: The mining will be done by opencast method but some amount of noise will be generated due to operation of Dumper, and driller which will be deployed on hire basis for removal of overburden and due to vehicular movement. Transportation vehicles will be properly maintained and provided with good silencers. Precaution and regular maintenance of Dumper, tipper & Dumper replacement of damaged/ worn out parts when ever required will be taken. Ear plugs are being/will be provided to operator and mine workers. Trees will be planted which will attenuate the noise levels. Blasting will be done during day time. Blasting will be avoided in the morning and evening hours, on foggy days, at night time and at times of high wind velocity. All workers and other persons will be sent away in a safe zone prior to the blasting. Drilling will be done with the help of sharp drill bits. Trees will be planted along the barrier of 7.5 m along the boundary of mine lease area which will act as a buffer for noise. The greenbelt with species of rich canopy will further attenuate the noise levels. The main source of noise generation in drilling machine is compressor. Compressor will be fitted with an acoustic enclosure.

SOLID WASTE MANAGEMENT: Waste dump: The waste overburden in the area is only intermixed soil. The total waste rock to be handled in five years is as follows. Volume of waste Taking Swell Factor Total m3 swell Year in M3 30% in M3 Vol. First year 1142 343 1485 Second year 1282 384 1666 Third year 1592 478 2070 Fourth year 1630 489 2119 Fifth year 1247 374 1621 Total 6893 2068 8961

The waste rock produced shall be loaded by Excavator & dumped by dumpers for its transportation to the reject dump yard & when required for making road, the waste material shall be used. Generation & Stacking of top soil: No Top soil proposed during five year. Generation & Stacking of Sub Grade Mineral:- It is also proposed to stack the Sub grade. The sub grade generated shall be collected in sub grade stack

25

yard and shall be then mixed with high-grade mineral for use in various industries. The Sub grade mineral shall be used in mixing in high grade to make marketable/Avg. grade. The retaining walls of rubble stone are proposed towards lower altitude side of the dump for stabilization. Green Belt Development: No trees are there in the area which will be uprooted during mining. It is proposed to plant a total no. 310 saplings per year on the non-mineralized area. The total proposed area is 0.7646 Ha. And survival rate 80% is expected; therefore 20% more saplings will be planted next year. A number of species will be planted suitable to this area of climate conditions like Neem, Babool, Khejari, Amal Taas, Vilayati Babool etc. Reclamation Plan: At the end of mine life 0.7862 ha. Area will be excavated which will be converted in to water reservoir & 0.2138 ha. Area will remain non utilized. Green Belt/Plantation will be done outside (near school, near temple) the lease area; because this lease area is surrounded by other leases by all four sides. SOCIO-ECONOMIC IMPACT: The mining activity will have positive impact due to direct and indirect employment and development of ancillary industries. No displacement due to the proposed mine extension/ expansion project. Approx. 18-20 local workers will have employment opportunities along with periodical training to generate local skills. The Budgetary Breakup And Details Of Facility Provided For The Entrepreneur Social responsibility (ESR)

ENTREPRENEUR SOCIAL RESPONSIBILITY ACTIVITIES AND BUDGETARY ALOCATION

TOTAL Activities to be done by Project EXPENDITURE PER S. NO Particulars Proponent YEAR (Amount in Rs.) 1. EDUCATION Distribution of school bags & 13,000 stationery item to school children Distribution of books in school Distribution of sports good among school children. 2. COMMUNITY General health camps for nearby 14,000 HEALTH villagers Eye check up camp

26

Organization of dental check up camp

Distribution of medicines free of cost

3. INFRASTRUCTURE Renovation of nearby community hall 10,000 DEVELOPMENT Renovation of nearby school building

Repair/renovation of Anganbari centre

Repair of school terrace

4. SOCIAL WELFARE Support for supply of drinking water 13,000

Financial assistance to rural cultural programmes Social forestry Awareness programmes for villagers (Rainwater Harvesting, Adult Education / Health) Total 50,000

OCCUPATIONAL SAFETY AND HEALTH: All safety measures prescribed under mining laws will be followed strictly. All workers will be medically examined in pre- placement phase and also periodically. First Aid Personnel with First aid kit will be available at the mine site to provide first aid to injured person. Arrangement for transportation of persons to nearby medical facilities will be made. Potable water facility will be provided to mine workers. Personal protective equipments (earmuffs/ earplugs, helmets, face masks, gloves, goggles) will be provided to mine workers as safeguards. Regular medical check-up camps shall also be arranged for detection of occupational diseases and minor disease in the nearby villages. Free check-up and medicine for treatment for their acute and chronic illness shall be provided. Awareness program will be organized for workers. The medical examination schedule & cost is provided in Table below: Budget For Occupational Health & Safety S. No. Facilities provided for labourers Cost (Rs) 1. Shelter 9,000 2. Health Facility, Sanitation Facility 7,000 3. Drinking water, Fuel for cooking 8,000 4. Education for Children & others 11,000 Total 35,000

BUDGETARY PROVISION FOR EMP IMPLEMENTATION & MONITORING In order to implement the environmental protection measures, timely funds will be released as per requirement. In addition to above, it is proposed to invest total cost of Rs 0.50 Lac per year on pollution control, green belt and

27 environmental monitoring systems. The break-up of the investment is given in the following table.

Annual Capital & Recurring Cost For Environmental Protection Measures Sr. Particulars Cost (in Rs.) per annum No.

1. Pollution monitoring – Air, Rs .9,000 Water, Noise and Soil 2. Dust Suppression Rs 9,000 3. Wire fencing at plantation sites Rs.10,000 4. Plantation including Rs. 8,000 maintenance 5. Rainwater harvesting Rs. 7,000 6. Haul road and other roads Rs. 7,000 repair and maintenance Total Rs. 50,000/-

****

28