Initial Environment Examination

Project Number: 44427-013 May 2018 (Addendum)

IND: State Road Sector Project Subproject : Nandghat - Gidhoury (SH– 10) - Upgradation of 2 Lane to 4 Lane at Five Stretches under “Nandghat to Balodabazar” and “Balodabazar to Gidhoury”

Submitted by

Public Works Department, Government of Chattisgarh,

This report has been submitted to ADB by the Public Works Department, Government of Chattisgarh, Raipur and is made publicly available in accordance with ADB’s Public Communications Policy (2011). It does not necessarily reflect the views of ADB. This report is an addendum to the IEE report posted in July 2012 available on https://www.adb.org/projects/documents/chhattisgarh-state-road-sector-project-nandghat- gidhoury-sh-10-subproject-iee This addendum to initial environment examination report is a document of the borrower. The views expressed herein do not necessarily represent those of ADB's Board of Directors, Management, or staff, and may be preliminary in nature. In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.

Addendum Initial Environmental Examination

Nandghat - Gidhoury (SH– 10) Subproject (Upgradation of 2 Lane to 4 Lane at Five Stretches under “Nandghat to Balodabazar” and “Balodabazar to Gidhoury”)

Loan Number: 2981-IND March 2018

IND: Chhattisgarh State Road Sector Project

Prepared by: Public Works Department, Government of Chhattisgarh for the Asian Development Bank.

The addendum initial environmental examination is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board of Directors, Management, or staff, and may be preliminary in nature.

i

Contents

A. INTRODUCTION ...... 1 B. APPLICABLE ENVIRONMENTAL POLICIES AND OTHER LEGISLATIONS ...... 5 C. SUB-PROJECT DESCRIPTION ...... 5 D. APPROACH FOR ADDENDUM PREPRATION ...... 9 E. DESCRIPTION OF ENVIRONMENT ...... 9 F. POTENTIAL ENVIRONMENTAL IMPACTS AND MITIGATION MEASURES ...... 10 G. ENVIRONMENTAL MANAGEMENT ...... 11 H. INSTITUTIONAL REQUIREMENTS AND ENVIRONMENTAL MONITORING PLAN ...... 11 I. GRIEVANCE REDRESS MECHANISM ...... 12 J. PUBLIC CONSULTATION AND INFORMATION DISCLOSURE ...... 12 K. FIELD-BASED ENVIRONMENTAL DUE DILIGENCE ...... 13 L. CONCLUSION ...... 14

ii

List of Tables Table 1 - Details of Packages Under Group A, Group B and Group C ...... 1 Table 2 - Package Wise Details of ADB Approved IEE Reports ...... 3 Table 3 -Details of Packages under Nandghat-Gidhoury road (SH-10) ...... 4 Table 4 - Change of Scope from Two to Four Lane in Package-III and Package IV ...... 5 Table 5 - Environmental Features Along the Sections ...... 9 Table 6 - Details of Tree Cutting ...... 11 Table 7 - Details of Payment to Forest Department ...... 11

List of Figures Figure 1 - Project Location Map ...... 4 Figure 2 – Location Map on Toposheet from Km 14.200 to Km 19.500 (excluding ROB) ...... 6 Figure 3 - Location Map on Toposheet from Km 39.100 to Km 43.840 ...... 6 Figure 4 - Location Map on Toposheet from Km 43.840 to Km 45.200 ...... 7 Figure 5 - Location Map on Toposheet from Km 60+100 to Km 61.910 ...... 7 Figure 6 - Location Map on Toposheet from Km 68.600 to Km 71.774 ...... 8 Figure 7 - Approved Typical Cross section for 4 Lane (Package III) ...... 8 Figure 8 - Approved Typical Cross section for 4 Lane (Package IV) ...... 9 Figure 9 - Public Consultation at Package III ...... 13 Figure 10 - Public Consultation at Package IV ...... 13

List of Annexures Annexure I Rapid Environmental Assessment (REA) Checklist Annexure II Attendance Sheet of Public Consultation Annexure III Environmental Management Plan Annexure IV Environmental Monitoring Plan Annexure V Grevienece Readdressal Mechanishm Annexure VI Tree Cutting Permission (Package 3) Annexure VII Tree Cutting Permission (Package 4) Annexure VII Photographs of Field Visit

iii

List of Acronyms

ADB Asian Development Bank CGPWD Chhattisgarh Public Works Department Ch. Chainage CSC Construction Supervision Consultant CSRSDP Chhattisgarh State Roads Sector Development Project CSRSP Chhattisgarh State Road Sector Project CTE Consent to Establish Cum Cubic meter DFO Divisional Forest Officer DPR Detailed Project Report EA Executing Agency EARF Environmental Assessment and Review Framework EHS Environment Health Safety EMP Environmental Management Plan GoCG Government of Chhattisgarh GPS Global Positioning System GRC Grievance Redressal Cell GRM Grievance Redress Mechanism HIV/AIDS Human Immunodeficiency Virus/ Acquired Immune Deficiency Syndrome HMP Hot Mix Plant IEE Initial Environmental Examination IRC Indian Road Congress JV Joint Venture Km Kilometre LHS Left Hand Side M.T. Metric Tonne MDR Major District Road MoEF&CC Ministry of Environment Forest & Climate Change MoRTH Ministry of Road Transport Highways PIU Project Implementation Unit PM10 Particulate Matter < 10 micron PM2.5 Particulate Matter < 2.5 micron PUC Pollution Under Control PWD Public Works Department RF Resettlement Framework RHS Right Hand Side ROW Right of Way RMC Ready Mix Concrete SH State Highway SPCB State Pollution Control Board SPS ADB Safeguard Policy Statement, 2009

iv

A. INTRODUCTION

1. Roads are the main mode of transportation in Chhattisgarh. National highways (NH6, NH16 and NH78) provide good east-west connections with neighboring states, and NH43 and NH200 provide the main north-south connection between Raipur, Bilaspur and Jagdalpur. However, the remaining roads in Chhattisgarh are mostly in poor conditions, and not passable in the monsoon season. This is especially true for roads in southern and northern Chhattisgarh, where most of the tribal people live. The total road length in Chhattisgarh is about 36,000 km with the road density less than 30 km per 100 km2 against the national average of 100 km per 100 km2. To improve state roads, Chhattisgarh Public Works Department (CGPWD) in 2002–2003, prepared a 10-Year Master Plan for Road Sector Development (MPRSD) for the years 2003 to 2012. MPRSD aims to (i) promote development of six main road corridors, (ii) remove capacity bottlenecks from the network to better connect rural areas, and (iii) support socioeconomic development by improving road access and connectivity among growth centers. Based on MPRSD, Government of Chhattisgarh prepared and approved a priority investment program for improvement (rehabilitation, strengthening and widening) of about 5,000 km of state roads at an estimated cost of about Rs 105 billion ($2 billion). CGPWD has improved many roads through Government funds and support from funding agencies including 1249 Km roads with the help of ADB. 2. The Government of Chhattisgarh (GoCG) plans to improve the state road network under Chhattisgarh State Roads Sector Development Project (CSRSDP) with the assistance of Asian Development Bank and for that has applied a loan through Government of from the Asian Development Bank (ADB) for the improvement of about 916 kms state roads in Chhattisgarh. This road up-gradation and rehabilitation project will improve transport efficiency of the State road network which will contribute to expansion of economic opportunities and poverty reduction. 3. The Chhattisgarh Public Works Department (CGPWD), Government of Chhattisgarh is the Executing Agency (EA) for the project. The nineteen project roads have been divided into three Groups (Group A, B &C). The Consultancy services have been engaged for advisory and construction supervision, institutional strengthening, social rehabilitation and resettlement, environmental mitigation and road safety measures. The construction supervision consultancy works have been awarded to following agencies 4. This project comprises of widening and strengthening of state highways and major district roads. Under Group A roads, there are 6 packages (Package-1 to 6) of about 273.30 km, under Group B roads, there are 8 packages (Package-7 & 8, Package-10 to 15) about 390.36 km and under Group-C roads, there are 4 packages (Packages -16 to 19) comprising of 191.944 km road network. The details of road package, name of the road and length under each package are given in table 1. Table 1 - Details of Packages Under Group A, Group B and Group C S.No. Package Name of the Road Length (km) District Group –A 1. Package 1 Raipur – Bhaisa (SH-9) 36.50 Raipur Raipur & Baloda 2. Package 2 Bhaisa – Baloda Bazar (SH-9) 35.58 Bazar 3. Package 3 Nandghat – Baloda Bazar (SH-10) 42.19 Baloda Bazar 4. Package 4 Baloda Bazar - Gidhori (SH- 9) 49.04 Baloda Bazar 5. Package 5 Simga – (Gullu) (SH- 20) 57.15 Raipur

1

S.No. Package Name of the Road Length (km) District Raipur & 6. Package 6 Arang (Gullu) – Kurud (SH-20 / MDR) 52.84 Dhamtari Total Length of Project Road in Group –A (in KM) 273.30 Group –B Raipur-Urla-Patharidih-Berla-Kodwa Raipur and Durg 7. Package 7 48.03 (MDR) Package 8 Balod and 8. Rajnandgaon- Kachche (SH-5) 77.13 Rajnandgaon 9. Package 10 Chandukuri Maro Umariya (MDR) 68.27 Bemetra Package 11 Rohanda-Foratari-Atariya-Khairagarh 10. 39.25 Rajandgaon (MDR) Package 12 Khairagarh - Donagargarh - Tumadlbod Kabirdham 11. 53.31 (MDR) 12. Package 13 Balod -Dhamtari (MDR) 30.67 Kabirdham 13. Package 14 Anda-Funda (MDR) 32.73 Durg and Balod 14. Package 15 Bodla-Traegaon-Daldali (MDR) 40.97 Balod

Total Length of Project Road in Group –B (in KM) 390.36 Group –C 15. Package 16 Sheorinarayan – Birra – Champa (SH- 51.798 Janjgir-Champa Package 17 9) Bilaspur & 16. Ratanpur - Kota-Lormi (SH-10) 50.200 Mungeli Package 18 Lormi – Pandariya & Mungeli– Lormi Mungeli & 17. 37.007 with Mungeli bypass (SH-10/MDR) Kabirdham Package 19 Jairamnagar – Masturi – Malhar – Bilaspur & 18. 52.939 Jondhara - Lawan (MDR) Baloda Bazar Total Length of Project Road in Group –C (in KM) 191.944 Project Road Under Implementation in Group-A, B &C (in 855.604 KM)

5. As required by ADB’s Safeguard Policy Statement 2009 (SPS 2009), an environmental assessment and review framework (EARF) was prepared and approved in 2012 to provide guidance on environmental screening, assessment, institutional arrangements, and procedures to be followed, where components were not yet been fully defined and locations not identified. The EARF ensures that succeeding tranches comply with SPS 2009 and the applicable national laws and regulations. 6. The initial environmental examination was carried out for all the subprojects falling under group A, group B and group C and the details of ADB approved IEE reports against each package are provided in table 2 below:

2

Table 2 - Package Wise Details of ADB Approved IEE Reports (Chhattisgarh State Road Sector Project) ADB Approved IEE S.No. Package Name of the Road Report

1. Package 1 Raipur – Bhaisa (SH-9) Raipur to Balodabazar (SH-9); January 2013 2. Package 2 Bhaisa – Baloda Bazar (SH-9)

3. Package 3 Nandghat – Baloda Bazar (SH-10) Nandghat-Gidhoury (SH- 4. Package 4 Baloda Bazar - Gidhori (SH- 9) 10) July 2012 5. Package 5 Simga – Arang(Gullu) (SH- 20) Simga-Kurud (SH-20); 6. Package 6 Arang (Gullu) – Kurud (SH-20 / MDR) July 2012

Raipur-Urla-Patharidih Berla- Raipur-Urla-Belra-Kodwa 7. Package 7 Kodwa (MDR) Road; January 2013 Rajnandgaon 8. Package 8 Rajnandgaon- Kachche (SH-5) Kachche(Antagarh) Road; January 2013 Chandkhuri-Maro- 9. Package 10 Chandukuri Maro Umariya (MDR) Umariya Road; January 2013 Rohanda-Foratari-Atariya- Dhamda-Khairagarh 10. Package 11 Khairagarh (MDR) Road; January 2013 Khairagarh -Donagargarh Khairagarh-Tumdibod 11. Package 12 - Tumadlbod (MDR) Road; January 2013 Balod – Dhamtari Road; 12. Package 13 Balod -Dhamtari (MDR) January 2013 Anda-Funda Road; 13. Package 14 Anda-Funda (MDR) January 2013 Badola-Daldali Road; 14. Package 15 Bodla-Traegaon-Daldali (MDR) January 2013 Shivrinarayan-Birra- 15. Package 16 Sheorinarayan – Birra – Champa (SH-9) Champa Road; January 2013 16. Package 17 Ratanpur - Kota-Lormi (SH-10) Ratanpur-Kota-Lormi- Pandaria-Mungeli Road; Lormi – Pandariya & Mungeli– Lormi 17. Package 18 January 2013 with Mungeli bypass (SH-10/MDR)

– Jairamnagar – Masturi – Malhar Jairamnagar Masturi- 18. Package 19 Lawan Road; January – Jondhara - Lawan (MDR) 2013

7. The ADB approved IEE report “Nandghat - Gidhoury (SH-10)” approved in July 2012 covers two packages i.e. package 3 and package 4. During implementation stage change in scope of work was undertaken in package 3 and package 4 from the original provided scope of work as per ADB approved IEE report. The details of both the packages falling under

3

“Nandghat - Gidhoury road (SH-10)” are provided in table 3 while project location Map is given in figure 1. Table 3 -Details of Packages under Nandghat-Gidhoury road (SH-10) Sl.No. Package Name of Package Length Location 1. Package 3 Nandghat – Baloda Bazar 42.19 Baloda Bazar 2. Package 4 Baloda Bazar - Gidhori 49.04 Baloda Bazar

Figure 1 - Project Location Map 8. During the project implementation stage “Nandghat to Gidhoury” (SH–10)” has been bifurcated into two packages such as (i) Nandghat to Balodabazar (SH-10) under package-3 (length-42.19 km); and (ii) Baloda Bazar to Gidhoury (SH-9) under package-4 (length- 49.04 km). This report is proposed as addendum to the ADB approved IEE report prepared for Nandghat to Gidhoury (SH–10). The addendum to IEE report has been prepared due to change of scope of work from two lanes to four lanes at five different sections. Out of these five, two sections come under package 3 {Batapara [km 14.200 to km 19.500 (excluding RoB)] and Balodabazar (km 39.100 to km 43.840)} and three sections come under package 4 {Balodabazar(km 43.840 to km 45.200), Lawan (km 60.100 to km 61.910) and Kasdol (km 68.600 to km 71.774)}. 9. This addendum to IEE report would capture information on the environmental consequences associated with change of scope. This report will also cover the field based environmental due diligence studies to ascertain presence of any residual environmental impacts since the sub-projects were implemented without undertaking environmental assessments and suggest specific remedial measures, if any to address such residual impacts.

4

B. APPLICABLE ENVIRONMENTAL POLICIES AND OTHER LEGISLATIONS

10. As per the Ministry of Environment, Forest and Climate Change, GoI, vide its Notification No. S.O. 1533 dated 14-09- 2006 and its subsequent amendment, the environmental clearance is not applicable under the sub-project. Aside from SPS 2009, the project needs to comply with the requirements provided by the GoI acts, rules, notifications, standards, and policies and other state level guidelines that apply to the project. The relevant regulations and other legislations are given in chapter 2 of ADB approved IEE report, July 2012 are applicable for this subproject.

C. SUB-PROJECT DESCRIPTION

11. As per ADB approved IEE prepared in July 2012, the project involves widening of existing roads within available ROW to 2-lane carriageway (7.0 m wide with 3.5 m width of each lane and 2.5m earthen shoulder either side). The total length of the project road is 91.23 km. The road provides safe and rapid transport link between NH-6 at Nandghat and Balodabazar upto Gidhoury and further to Shivri Narayan, which is famous religious and tourist place. During the implementation stage this Nandghat to Gidhoury Road (91.23 km) is splited in two packages namely Package 3: Nandghat to Balodabazar (SH-10) Compraising of 42.19 km and Package 4: Baloda Bazar to Gidhaoury (SH – 9) comprising 49.04 km. 12. During the implementation stage the widening of road was undertaken for 4 lane carriageways instead of 2-lane at five chainages. The 4-lane carriageway included 14.0 m wide road with 3.5 m width of each lane, 1.2 median and 1.3 m of drainage on both sides. The hard shoulder will varies from 1.6m to 2.5m depending on the available RoW; as the work will be carried out within the existing RoW. 13. This addendum to ADB approved IEE report is being prepared due to upgradation of two lanes to four lanes at two stretches of package 3 and at three stretches of package 4 sub- projects. The details are given in table 4: Table 4 - Change of Scope from Two to Four Lane in Package-III and Package IV Package Location name Chainage (Km) Length (Km)

Km 14.200 to Km 19.500 Batapara 4.258 (excluding ROB) Package - 3 Baloda Bazar Km 39.100 to Km 43.840 4.74 Total 8.998

Baloda Bazar Km 43.840 to Km 45.200 1.36

Lawan Km 60+100 to Km 61.910 1.8 Package - 4 Kasdol Km 68.600 to Km 71.774. 3.174 Total 6.334 14. The location map on toposheet for sections from Km 14.200 to Km 19.500 (excluding ROB), Km 39.100 to Km 43.840, Km 43.840 to Km 45.200, Km 60+100 to Km 61.910 and Km 68.600 to Km 71.774. are given in figure 2, figure 3, figure 4, figure 5 and figure 6 respectively. The typical cross-section for four lane for package 3 and package 4 is given in figure 7 and figure 8 respectively. 15. The work is in progress by 99% at chainage, Km 14.200 to Km 19.500 (excluding ROB), Km 39.100 to Km 43.840, Km 43.840 to Km 45.200, Km 60+100 to Km 61.910 and Km 68.600 to Km 71.774, where the scope of work is changed from original provided scope in ADB approved IEE report.

5

Figure 2 – Location Map on Toposheet from Km 14.200 to Km 19.500 (excluding ROB)

Figure 3 - Location Map on Toposheet from Km 39.100 to Km 43.840

6

Figure 4 - Location Map on Toposheet from Km 43.840 to Km 45.200

Figure 5 - Location Map on Toposheet from Km 60+100 to Km 61.910

7

Figure 6 - Location Map on Toposheet from Km 68.600 to Km 71.774

Figure 7 - Approved Typical Cross section for 4 Lane (Package III)

8

Figure 8 - Approved Typical Cross section for 4 Lane (Package IV)

D. APPROACH FOR ADDENDUM PREPRATION

16. The Addendum to ADB-approved IEE report (July 2012) has been prepared based on field visits, carrying out discussion with field staffs and the officials of executing agency (EA) conducted during project implementation stage. The information gathered during site visit has been used to update the Rapid Environmental Assessment (REA) Checklist (Annexure I), which assisted in screening, categorization of sub-project and anticipating potential impacts on environment due to construction of sub-project.

E. DESCRIPTION OF ENVIRONMENT

17. The sub-project is located in district Raipur. The descriptions of environment for this district have been captured in Chapter 3.0 (Description of Environment) of ADB-approved IEE report prepared in July 2012, which adequately capture the environmental setting in the district and may be referred. The testing of environmental parameters such as ambient air quality, ambient noise levels and water quality have been conducted package wise under the project covered in different environmental monitoring reports. The environmental features along the sections from Km 14.200 to Km 19.500 (excluding ROB), Km 39.100 to Km 43.840, Km 43.840 to Km 45.200, Km 60+100 to Km 61.910 and Km 68.600 to Km 71.774.has been collected from site and given in the table 5. Table 5 - Environmental Features Along the Sections Sr. No. Environmental Features Status Remarks, if any No impact 1 Forest section Not involved anticipated The work is being carried out under existing Row. No 2 Number of trees available additional tree cutting is involved due to change of scope of work.

9

Sr. No. Environmental Features Status Remarks, if any Tree to be cut due to No additional tree cutting is No impact 3 change of scope involved anticipated No water bodies other than small village ponds are No impact is present along the sections anticipated on water Water bodies such as where the scope of work is bodies due to 4 pond, river changed. These ponds are construction of road/ majorly being used for change in scope of washing and bathing subproject. purpose by villagers. Educational institutions and hospitals are present alongside road in package 3 No major impact is and package 4. Proper road anticipated on any access facilities and traffic Environmental sensitive hospitals and management system was 5 features such as school, educational provided during college, hospitals institutions due to construction work. Proper change in scope of safety measures were work. undertaken to prevent any hindrance to educational institutions and hospitals. Archaeological site, No impact 6 monument, cultural Not involved anticipated heritage and temple

F. POTENTIAL ENVIRONMENTAL IMPACTS AND MITIGATION MEASURES

18. The preparation of this addendum is accordance to specified criteria provided in the Environmental Assessment Review Framework (EARF). These criteria were used for identifying the potential environmental impacts due to the sub-project in ADB-approved IEE report under the Chapter 5. The REA checklist prepared for the sub-project forms the basis for assessment of potential environmental impacts and suggesting mitigation measures. 19. No additional environmental impacts are anticipated due to widening of road from 2 lane (as per scope provided in ADB approved IEE report) to 4 lane (Changed scope of work). The change in scope of work does not involve any additional tree cutting, structure damage, impact on water bodies and environmental sensitive area. The upgradation of road is being undertaken within the existing RoW thus no land acquisition is required. Thus, the no additional mitigation measures are suggested. 20. The roads under package 3 and package 4 [Nandghat to Gidhoury (SH-10) Subproject] do not pass through any forest land. However, to up-grades the roads tree cutting is inevitable. During implementation stage, a total of trees (2549 trees in Package III and 3434 trees in Package IV), of which only 1949 and 3131 trees may need to be cut in actual within ROW in Package III and Package IV respectively. The number of trees impacted for upgradation to 4 lane remains same as for 2 lane, as there are no additional tree cutting involved due to change in scope of work. The details of trees required to be cut under package III and package IV is provided in table 6 and permission obtained from competent

10 authority for package III and package IV are provided below in Annexure VI and Annexure VII respectively. 21. The tree cutting required for widening of road to 2 lane road and 4 lane road remained same as no additional tree cutting was required for widening of road to 4 lane. This to clarify that the widening of road to 4 lane is done under the existing RoW and no land acquisition is involved. Table 6 - Details of Tree Cutting Package Permission Obtained Actual No. of No. of Trees Cut As on Saving of No. from Collector for Trees to be Cut 31st December 2017 Trees cutting of Trees III 2549 1949 1949 600 IV 3434 3131 3131 303 22. For each tree to be cut for the road widening, the concerned authority in their permission letters have imposed condition that 10 times the trees should be planted preferable near to the existing roads as compensatory plantation. The details of payment made to State Forest Department under each package for tree cutting and compensatory plantations are provided in table 7. Table 7 - Details of Payment to Forest Department Package Payments Done to Forest Department Forest Division No. As on 30thJune, 2017(Rs. in Lacs) For Cutting of Trees Compensatory Plantation III 26.80 57.29 DFO Balodabazar Sub Total 26.80 57.29 IV 37.60 101.02 DFO Balodabazar Sub Total 37.60 101.02 23. The change in scope of work will not change the environmental category of the project i.e. Category-B as no additional environmental impact is anticipated. Moreover, the widening of road from 2 to 4 lane is within the RoW of existing road. The potential environmental impacts anticipated remains same and are specifically capture in Section 4.0 of ADB- approved IEE report, which is also valid during widening of road to 4 lane.

G. ENVIRONMENTAL MANAGEMENT

24. The ADB-approved IEE report has suggested appropriate measures to mitigate impacts associated with construction activities. An Environmental Management Plan (Annexure III) has been prepared for the project that discusses the anticipated impacts, monitoring requirements, and development of mitigation measures with respect to the following stages: (i) Pre-Construction, (ii) Construction, and (iii) Operation and Maintenance. The environmental management plan was made part of contract agreement for contractor’s mandatory compliance to EMP. 25. The impacts associated with the sub-project are mainly due to activities during construction stage. As no additional environmental impacts are anticipated due to the change in scope of work. Thus, the Environmental Management Plan prepared for the project is adequate to mitigate the impacts due to sub-project.

H. INSTITUTIONAL REQUIREMENTS AND ENVIRONMENTAL MONITORING PLAN

26. Chhattisgarh State Roads Sector Development Project (CSRSDP) has taken up civil works for road up-gradation and rehabilitation, Consultancy services have been engaged for advisory and construction supervision, institutional strengthening, social rehabilitation and resettlement, environmental mitigation and road safety measures.

11

27. The Government of Chhattisgarh (GoCG) plans to improve the state road network under Chhattisgarh State Roads Sector Development Project (CSRSDP) with the assistance of Asian Development Bank. The Chhattisgarh Public Works Department (CGPWD), Government of Chhattisgarh is the Executing Agency (EA) for the project. 28. The Consultancy services for Construction Supervision for the project roads to be developed are divided into three Groups (Group A, Group B and Group C). The Chhattisgarh Public Works Department has employed SMEC International Pty. Ltd. In JV with SMEC India Pvt. Ltd. to undertake Consultancy services for Construction Supervision of Rehabilitation and Upgrading of Group “A” Road (Contract Package 1 to 6) Contract Agreement No.11 of 2014-2015 Raipur Dated 03.03.2015. The objectives of the Consultancy services are to ensure that high quality construction is achieved and to ensure that all work is carried out in full compliance with the Environmental Safeguard, Social Safeguard, Engineering design, technical specifications and other documents as well as promoting technology transfer by employment of local/PWD staff and on the job training. 29. The Road Specific Environment Management Plan has been formulated which consists of a set of mitigation measures; monitoring and institutional measures applicable to design, construction and operation stages of the project and roles and responsibilities of various parties. The upgradation of environmental management plan is not required due to change of scope and no additional environmental implications are anticipated. Thus, the EMP present in the ADB-approved IEE report has been implemented by the civil contractors. 30. In order to comply to requirements of Environmental Monitoring Plan (EMoP) as provided in Contract Agreement an external environmental monitoring agency M/s Enviro Analysts & Engineers Pvt. Ltd. (NABET Accredited & MoEF&CC approved Laboratory) has been hired by the Civil Contractors for their respective packages to carry out the environmental monitoring with regards to ambient air quality, water quality, soil quality and noise levels during the construction period. 31. The environmental monitoring for ambient air quality, water quality, soil quality and noise levels have been conducted during construction phase and test results along with analysis are covered in subsequent semi-annual environmental monitoring report.

I. GRIEVANCE REDRESS MECHANISM

32. Nandghat to Gidhoury Road (package III and package IV) falls under Baloda Bazar District. Grievance Redressal Committee (GRC) has been formed Baloda Bazar district. The details are provided in Annexure V. 33. Grievance Redress Committee (GRC) set up at district level monitors grievances arising during implementation for each package under area of its jurisdictions. The GRC determines the merit of each grievance, and resolve grievances within an outer time limit of three months of receiving the complaint. The Affected Persons has the right to refer the grievances to appropriate courts of law if not satisfied with the redress at any stage of the process. The set up GRC has the system of records keeping, contact details of complainant, date of the complaint received, nature of grievance etc. if any for the ongoing project and taking the necessary action against the complaint. 34. Till date no grievance has been reported with respect to environmental issues in package III (Nandghat – Baloda Bazar) and package IV (Baloda Bazar - Gidhouri). Any grievance from any person will be addressed in set time frame and will be properly documented.

J. PUBLIC CONSULTATION AND INFORMATION DISCLOSURE

35. Public Consultation meetings with local people residing along the road has conducted in Package III and IV. Particularly for the locations where widening of road is undertaken for 4-

12

lane instead of 2-lane. 36. The consultations with local people were carried out as part of continuous public participation. The consultation meeting was conducted at package III (Figure 9) and package IV (Figure 10). The meeting aims to address associated environmental implications due to proposed project. The attendance sheet of public consultation is provided in Annexure II. The discussions during the consultation are as follows: -

Figure 9 - Public Consultation at Package III Figure 10 - Public Consultation at Package IV • Local people showed the concern about drain construction. • In general people were informed about the arrangements with regards to access to shops and schools being planned, safety measures which shall be adopted during implementation after the up-gradation, provision of water sparkling to suppress dust and provision of environmental monitoring to be conducted during implementation. • General issues related to safety, accident and traffic control and dust emission has raised by the local community which contractor has proposed in their action plan to follow during construction. 37. The addendum to IEE shall be disclosed and made available to the public.

K. FIELD-BASED ENVIRONMENTAL DUE DILIGENCE

38. This chapter ascertains presence of any residual environmental impacts due to implementation of works at five chainages i.e. Km 14.200 to Km 19.500 (excluding ROB) at Batapara, Km 39.100 to Km 43.840 at Baloda bazar, Km 43.840 to Km 45.200 at Baloda bazar, Km 60+100 to Km 61.910 at Lawan and Km 68.600 to Km 71. 774.at Kasdol where scope of work is changed from the original provided scope and suggests appropriate, time- bound corrective measures to address those residual environmental impacts. The photographs of field visit are provided in Annexure VIII. 39. The various aspects considered for field-based environmental due diligence are elaborated below: (a) Confirmation of EMP in contractor’s contract agreement: EMP is made part of contractor’s contractor agreement and the contractor’s compliance to EMP is being monitored by carrying out field visits from time to time during the project implementation. The change of scope in package-III and package-IV have not resulted in any addition environmental implication. No impact is anticipated on environmental sensitive area, structures and water bodies in the area where the road is being upgraded from 2 lane to 4 lane. Moreover, the upgradation of road is being undertaken in the existing RoW. Thus, the upgradation of EMP is not required due to change of scope.

13

(b) Compliance status during pre-construction and construction stage of the sub- project(s): Environmental Management Plan is made part of contractor’s contract agreement and contractor is mandate to comply with the environmental implications provided in the EMP.

(c) Status of statutory permission applicable for the sub-project(s), if any: No additional statutory permission is required due to change of scope in package-III and package IV. The applicable statutory permissions such as (i) consent to establish and operate of construction plants; (ii) , permission to withdrawal of construction water from surface and ground water sources; (iii) quarry lease deed and quarry license from state department of mines and geology; (iv) labor licenses and associated insurance policy/workmen compensation; and (v) permission of storage handling and transport of hazardous material have been obtained by the respective civil contractors. , The civil contractors have also renewed the required statutory permissions for the sub-project.

(d) Status on implementation of environmental mitigation measures, if any and testing of environmental parameters of ambient air quality and ambient noise levels along the sub-projects as per agreed monitoring plan, if any: environmental monitoring for ambient air quality, water quality and ambient noise level have been carried out as per given ADB- approved environmental monitoring plan (Refer Annexure IV). All the test results are within permissible limits and no impacts on air quality, water quality and ambient noise levels are anticipated due to change of scope under package-III and package IV.

(e) Residual environmental impacts, if any with appropriate, time-bound corrective measures: The civil contactors is reminded from time to time, to follow the environmental management plan and the mitigation measures as per EMP. No environmental impact has been noticed. Thus, no added corrective measure is required/suggested.

(f) Public consultations during project implementation stages: Public consultation is being carried out as a part of continuous participation of public in the proposed project during the implementation stage. The details of public consultations carried out for the changed scope of subproject are provided in Chapter J of this addendum to IEE report. The public consultations being carried out during project implementation stage are also being updated in the subsequent semi-annual environmental monitoring reports.

(g) Status of grievances, if any, received due to implementation of the sub-projects: The grievance redressal committee are setup in all the concern districts (Annexure V). The details of GRC are provided in Chapter I of this addendum to IEE report. No grievance related to environmental issue for any subproject is recorded.

(h) Conclusions: No major environmental impact is predicted due to the change in scope of subproject.

L. CONCLUSION

40. This addendum to IEE report is based upon the environmental assessment and review framework (EARF) which is consistent with the ADB’s Safeguard Policy Statement (SPS) 2009. The subproject is classified as category “B” for environmental and does not require further environmental impact assessment. The ADB-approved EMP prepared for the project is valid and the same is recommended for adoption during implementation stage.

14

Annexure - I Rapid Environmental Assessment Checklist ROADS AND HIGHWAYS Instructions

(i) The project team completes this checklist to support the environmental classification of a project. It is to be attached to the environmental categorization form and submitted to the Environment and Safeguards Division (RSES), for endorsement by Director, RSES and for approval by the Chief Compliance Officer.

(ii) This checklist focuses on environmental issues and concerns. To ensure that social dimensions are adequately considered, refer also to ADB's (a) checklists on involuntary resettlement and Indigenous Peoples; (b) poverty reduction handbook; (c) staff guide to consultation and participation; and (d) gender checklists.

(iii) Answer the questions assuming the “without mitigation” case. The purpose is to identify potential impacts. Use the “remarks” section to discuss any anticipated mitigation measures. Country / Project Title: India: Chhattisgarh State Road Sector Project: Subproject – Nandghat to Gidhoury Road (Chhattisgarh) Sector Division: Transport Sector

Screening questions Yes No Remarks

A. Project Siting Is the project area adjacent to or within any of the following environmentally sensitive areas?

Cultural heritage site X No archaeologically protected monument or cultural heritage site in located within the road ROW or even within 2-3 Km distance from the road. Though, few religious structures like temple are located close to the roads. No archaeological site, monument, cultural heritage and temple is present at the location where scope of subproject is changed.

Protected Area X No protected area is located close to roads and nearby (assessment made upto 10 Km) area.

Wetland X No protected or classified wet land is located close to the roads. Few village ponds though are located close to the project road.

Mangrove X Project road is not located in coastal areas.

Estuarine X No Estuarine is located in the project area.

15

Screening questions Yes No Remarks

Buffer zone of protected area X No such area is located in the project vicinity.

Special area for protecting biodiversity X No such area is located in the project vicinity.

B. Potential Environmental Impacts

Encroachment on historical/cultural X The topography of project road is mainly areas; disfiguration of landscape by road plain. There is no encroachment of embankments, cuts, fills, and quarries? historical places. However, some small temples exist along the project road which may get impacted. Since road widening will be confined to available ROW, no change in landscape is expected. Opening of New Quarries is not envisaged. Only operational and licensed quarry will be used for road construction. Earth material will be sourced from pre- identified areas (located within 25 to 30 Km from the road) and with the consent of landowner. All borrow areas will be suitably rehabilitated. No such impact is envisaged because of changed scope of subproject.

Encroachment on precious ecology (e.g. X There is no National Parks, Wild Life Sensitive or protected areas)? Sanctuaries or any other similar eco- sensitive areas in and around the project area.

Alteration of surface water hydrology of X The proposed alignment is crossing waterways crossed by roads, resulting in through several small drains. There is no increased sediment in streams affected perennial river crossed by the project by increased soil erosion at construction road. All drainage courses will be site? maintained to avoid alteration in surface water hydrology so that watercourses

are not affected. The temporary soil stockpiles will be designed so that runoff will not induce sedimentation of waterways. Silt fencing during construction will be provided. No addition impact is anticipated due to changed scope of subproject.

Deterioration of surface water quality due X Adequate sanitary facilities including to silt runoff and sanitary wastes from sewage treatment facilities will be worker-based camps and chemicals provided at construction camps, which used in construction? will be set-up away from habitat and water bodies. No harmful ingredients are likely to be used in the construction activities. As

16

Screening questions Yes No Remarks such, no impact on surface water quality is anticipated due to construction. Measures like embankment slop stabilisation, RCC retaining walls are proposed to prevent siltation of ponds located next to the road due to surface runoff. No such additional impact is envisaged because of changed scope of subproject.

Increased local air pollution due to rock X Localised air pollution level is likely to crushing, cutting and filling works, and increase for short duration during chemicals from asphalt processing? construction period due to construction vehicle movement and asphalt processing. The asphalt mixing plant (hot mix plant) will be located away from habitat areas with adequately high stack for effective dispersion of likely emissions. Dust separation measures like spraying of water on unpaved vehicle movement areas are proposed to minimise the dust generation The changed scope of subproject does not result in any additional impact.

Risks and vulnerabilities related to X Workers may get exposed to dust and occupational health and safety due to noise during construction activities. physical, chemical, biological, and However, the exposure levels are likely radiological hazards during project to be short and insignificant. Workers will construction and operation? be provided requisite PPEs to minimise such exposure and associated harmful

occupational health effects. Traffic on the road is expected to be low and as such, no occupational health hazard is anticipated during operation phase. The impact due to changed scope of work will remain same as earlier.

Noise and vibration due to blasting and X No Blasting is involved. No significant other civil works? noise generation is expected during

construction activities except normal construction equipment operational noise. These noise levels will be impulsive in nature and its impact will be confined within few meters of either side of the road. All stationary noise making sources equipment like DG set, compressors will be installed with acoustic enclosures. There are few noise sensitive locations especially schools close to the alignment where noise level may increase due to

17

Screening questions Yes No Remarks increased traffic during operation stage. Provision of noise berries will be made wherever noise level is likely to increase beyond the prescribed ambient noise levels No such additional impact is envisaged because of changed scope of subproject.

Dislocation or involuntary resettlement of X The changed subproject location donot people involve any involuntary resettlement as the work is being undertaken under existing RoW. No involuntary resettlement is involved in the chainage where scope of subproject is changed.

Dislocation and compulsory resettlement X No displacement of people is involved. of people living in right-of-way?

Disproportionate impacts on the poor, X No such impact is anticipated. women and children, Indigenous Peoples or other vulnerable groups?

Other social concerns relating to X No such social concern is expected. inconveniences in living conditions in the Concern may arise during construction project areas that may trigger cases of stage due to increase in ambient air upper respiratory problems and stress? pollution level, which is expected to be localised and temporary in nature. This aspect will be effectively controlled with the proposed dust suppression and other mitigation measures. As such people at large are supportive of project and are least bothered about above air pollution concern as well. No such additional impact is envisaged because of changed scope of subproject.

Hazardous driving conditions where X Hazardous driving condition may arise construction interferes with existing around bridge construction areas and at roads? locations of road interface with non- project roads. To minimize the impact suitable traffic management plan will be designed and implement by the contractor to prevent any hazardous driving condition in above situations. No such additional impact is envisaged because of changed scope of subproject.

Poor sanitation and solid waste disposal X Proper provisions for sanitation (sewage in construction camps and work sites, treatment), health care (drinking water and possible transmission of supply and periodic health check-ups) communicable diseases from workers to and solid waste disposal (through local populations? composting) facilities will be made at

18

Screening questions Yes No Remarks each construction camp. Awareness will be created amongst the workers about hygiene and health protection.

Creation of temporary breeding habitats X No such condition is anticipated. Each for mosquito vectors of disease? borrow area will be rehabilitated as per

pre- agreed used and rehabilitation plan. No such additional impact is envisaged because of changed scope of subproject.

Accident risks associated with increased X Adequate safety measures will be vehicular traffic, leading to accidental adopted to avoid accidents during spills of toxic materials and loss of life? construction and operation stages. Measures, like signage, speed control, crash barriers will be taken close to sensitive locations such as schools, temple or hospitals.

Increased noise and air pollution X Increase in noise and air pollution is resulting from traffic volume? expected during construction phase but is likely to be confined within few meters of either side of the road. Adequate mitigation measures will be adopted to minimize the same. During operation phase, vehicular traffic will be the main source of air and noise pollution. Improved road conditions, extensive plantation including multi- layered plantation along the road will reduce the noise and air pollution impact. Moreover, most of the road stretch passes through open agricultural land, which will provide adequate dispersion to vehicular emission. No such additional impact is envisaged because of changed scope of subproject.

Increased risk of water pollution from oil, X This possibility is minimal but cannot be grease and fuel spills, and other ruled out. Controlled construction materials from vehicles using the road? activities and proper drainage system will reduce this possibility. Provision is made for adequate signage and crash barriers near water bodies, which will minimise the possibilities of accidental water pollution. No such additional impact is envisaged because of changed scope of subproject.

19

Screening questions Yes No Remarks

Social conflicts if workers from other X Most of the workers will be hired locally. regions or countries are hired?

Large population influx during project X Most of the workers will be hired locally. construction and operation that causes One construction camp is proposed per increased burden on social infrastructure package with expected workers and services (such as water supply and population of only 50-60. This is unlikely sanitation systems)? to cause any significant burden on social infrastructure and services.

Risks to community health and safety X The construction material (aggregate due to the transport, storage, and use from approved quarries, borrow earth, and/or disposal of materials such as bitumen) will be sourced from nearby explosives, fuel and other chemicals and approved sources. No explosive or during construction and operation? chemicals are likely to be used. Bitumen waste if any generated during construction will either recycled or disposed off in controlled manner.

Community safety risks due to both X No such impacts are anticipated. accidental and natural causes, especially Adequate awareness will be created where the structural elements or amongst people and workers through components of the project are accessible information disclosure, safety signage to members of the affected community or and public consultation about safety where their failure could result in injury to aspects. the community throughout project construction, operation and decommissioning.

Based on above assessment no additional environmental impact is anticipated and the project is categorized as ‘B’

20

Annexure II Attendance Sheet of Public Consultation

21

22

23

Annexure III Environmental Management Plan Nandghat - Bhatapara - Gidhoury Road (The requirement related to ‘Precautions for Safeguarding Environment” detailed at section 111of Technical Specifications and Sub clause of PCCB (pre-conditions for contract bidding) shall be read in conjunction with the measures given below. All the requirement detailed at section 111 and sub clause 4.18 and as given below are to be implemented.) Environmental Issue/ Reference to Laws Approximate Mitigation Institutional Responsibility Remedial Measure Component /Guidelines Location Cost Implementation Supervision A. Design and Pre - Construction Stage 1. Design Considerations Considering the proposed project activities, the following legislative approvals shall be required in advance: 1. Obtain permission from forest or district authorities as applicable for cutting of trees 2. Obtain concurrence from Gram Panchayats for shifting or As identified in Activity 1 to 3 demolition of community structure DPR for the Part of concerned Nodal Legislative ADB PIU Legislative approvals 3. Obtain permission from concerned authorities for shifting location of construction officer of PWD and requirements PWD of utilities (like electric pole, telephone lines, hand pumps) respective costs activity 4 & 5 4. Obtain connect to establish Hot Mix plant, batching plant, activity. contractor quarry operation if new quarry to be opened, and setting up construction 5. Obtain permission for withdrawal of ground water as applicable Utilities relocation will be reasonably completed before Included in As per ADB PIU Utility Relocation construction starts and without affecting any essential supplies Design requirement construction Design Consultant widening plan PWD to habitat like water supply. cost Included in Shifting of Community Community structures, like, religious structures will be shifted As per ADB PIU Design requirement construction Design Consultant Structure appropriately, if required. widening plan PWD cost No climate Change induced vulnerability anticipated.

Out of 2549 trees in Package III and 3434 trees in Package IV as per approval received from forest dept., only 1949 and 3131 Climate Change and Within RoW or Covered in Through Forest ADB PIU trees may need to be cut within ROW for up- gradation of the Local Forest Rule Removal of trees on Govt. Land EMP Department PWD project road before the commencement of construction with prior Clarence from the Forest Department/District Authorities as applicable.

24

Environmental Issue/ Reference to Laws Approximate Mitigation Institutional Responsibility Remedial Measure Component /Guidelines Location Cost Implementation Supervision Compensatory afforestation: Ten trees will be planted for each tree felled as per regulatory compliance.

Geometric adjustment to reduce tree cutting. Removal of structure and land acquisition if involved will be as Included in Removal of Structures Construction ADB PIU per as per SPS 2009 and Rehabilitation and Resettlement plan Design requirement Within RoW construction and acquisition of land Agencies, PIU/ PWD PWD prepared separately cost Widening Option and Selection of widening option (left aligned, right aligned or Pavement design and centric widening) to be decided based on the least cutting of inadequate drainage tree, minimum loss of structure. Embankment design considerations.

Selection of suitable pavement design in habitat areas considering alignment level and drainage requirements. All habitat Included in areas ADB PIU Design requirement construction Design Consultant Raise road level as feasible, above the nearby areas with throughout the PWD cost Provisions in habitat provision of adequate side drains to evacuate the rain water alignment areas and domestic discharges (drained by habitats occasionally) to prevent damage to road and rain water entry to habitats‟ houses.

Provision of adequate no of cross drainage structures based on drainage pattern shall be made to maintain natural flow of rain water across the road. Crash barriers are proposed at sensitive locations like school, medical Adequate safety provisions like crash barriers at accident centers, along prone areas, rumble strips in habitat areas to regulate speed, Included in Safety along the the project ADB PIU retro- reflective warning sign boards near school, hospital, Design requirement construction Design Consultant proposed alignment corridor PWD religious places (Preferably PCC boards with retro- reflective cost

paints to avoid its theft) shall be made. Rumble strips are proposed at the all the settlements and crossing points

25

Environmental Issue/ Reference to Laws Approximate Mitigation Institutional Responsibility Remedial Measure Component /Guidelines Location Cost Implementation Supervision 2. Natural Hazards IRC:34 Recommendations for road construction Throughout the Project Adoption of relevant IS codes for design in waterlogged area stretch preparation Protection from damage embankment/structures suitable to withstand earthquake ADB, PIU and IRC: 75 and especially and Design Consultant from Earthquake of highest magnitude in moderate earthquake intensity Zone PWD MoRSTH bridge construction (Seismic Zone II level as per Indian classification). guidelines for structures costs Cost Design of High Embankments B. Construction Stage 3. Climate and Air Quality Road Side Plantations in Additional Plantation on river banks, borrow areas and the ratio of Design Consultant CSC / ADB Local Weather conditions sensitive locations to increase the green cover and improve the 1:10 (costs and Contractor PIU PWD aesthetics highlight in the following Kyoto Protocol, table) Environmental Road design and Pavement roughness as per IRC Throughout Protection Act, 1986; specifications. project The Air (Prevention corridor, Poor air quality due to and Control of CSC / ADB congestion free movement of traffic with provision of junction’s mainly at compromise in design Pollution) Act, PIU PWD improvement at major intersections haulage roads, 1981+IRC and earthwork, MORSTH Plantation of pollutant absorbing trees. construction Specifications for Transport, of loose and fine materials through covered vehicles sites, loading and paved roads to the extent feasible. Road and Bridge Included in areas, storage Design Consultant Works Air (P and construction areas, and Contractor Loading and unloading of construction materials shall be made CP) Act 1974 and costs Dust Generation due to transport route. at designated locations in project area with provisions of water Central Motor and construction activities and fogging around these locations Vehicle Act 1988 CSC / ADB transport, storage and PIU PWD handling of construction Storage areas to be located downwind of the habitation area. materials Water spraying on earthworks, unpaved haulage roads and other dust prone areas.

Provision of PPEs to workers Emission from vehicle, Regular maintenance of machinery and equipment. Asphalt mixing Included in CSC/ CSC / Contractor equipment and machinery plants, construction ADB PIU

26

Environmental Issue/ Reference to Laws Approximate Mitigation Institutional Responsibility Remedial Measure Component /Guidelines Location Cost Implementation Supervision Hot Mix Plant shall be located at least 1 KM downwind of the crushers, DG costs PWD human settlement. sets locations

Batching, plants and crushers at downwind (0.5km) direction from the nearest settlement. Hot mix plant to be fitted with adequate stack height. Obtain consent to establish ( NOC ) from PCB before setting up these plants. Included in monitoring Only crushers licensed by the PCB shall be used DG sets with cost stacks of adequate height and use of low sulphur diesel as fuel.

Use LPG as fuel at construction camps

Undertake periodic ambient air quality monitoring as per EMOP 4 . Noise Provision is made for installing need base noise barrier near sensitive locations like hospitals, schools. Cost for All equipment shall be fitted with silencers and will be properly Plantation maintained to minimize its operational noise. already The school, Stationary noise making equipment shall be placed along indicated Legal requirement hospitals are uninhabited stretches. above. Noise Pollution away from the The timing for construction activities shall be regulated such Rest part of (Regulation and road, that all noise generating construction activities happen after construction Control) Rules, 2000 therefore, at school hours. costs Noise from construction and the time of The provision of temporary noise barrier (Barricading) shall be CSC / ADB vehicle, equipment and amendments thereof construction of Contractor made near identified sensitive locations or near the noise PIU PWD machinery. Clause No 501.8.6. road source during construction. MoRSTH supervision Plantation along the boundary wall shall be made at start of Specifications for consultant will construction itself. Road and Bridge evaluate the Protection devices (ear plugs or ear muffs) shall be provided to works need to noise the workers operating near high noise generating machines Monitoring barriers. Noise measurements as per EMoP should be carried out to Cost as ensure the effectiveness of mitigation measures and develop a indicated In mechanism to record and respond to complaints on noise EMoP. Noise monitoring as per EMoP. 5. Land and Soil The top soil from the productive land shall be preserved and Throughout the Included in Land use Change and reused for plantation purposes as top cover of embankment project section CSC / ADB Project requirement construction Contractor Loss of productive/top soil slope for growing vegetation to protect soil erosion. and borrow PIU PWD cost areas

27

Environmental Issue/ Reference to Laws Approximate Mitigation Institutional Responsibility Remedial Measure Component /Guidelines Location Cost Implementation Supervision The land taken on lease for access road and construction camp shall be is restored back to its original land use before handing it over back to land owner Bank protection measures shall be taken at erosion prone areas. The protection measures may include use of geo- textiles matting, bio (vegetative) – turfing

Side slopes of the embankment shall not be steeper than 2H:1V. Provision of side drain to guide the water to natural outfalls. In rural stretches, longitudinal side drains shall be intercepted by drains serving as outlet channels to reduce the IRC: 56 -1974 erosion. recommended practice for Soil spread on slopes for permanent disposal shall be treatment of Slope protection and Soil buttressed at the toe by retaining walls. embankment slopes At high erosion due to for erosion control Construction Design consultant CSC / ADB embankment construction activities, Turfing of embankment slopes shall be done along the stretch. Clause No. 306 cost and Contractor, PIU PWD area earthwork, and cut and fill Stone pitching wherever necessary. and 305.2.2 MoRSTH Shrubs shall be planted in loose soil area. Specifications for Road and Bridge Soil erosion shall be visually checked on slopes and high works embankment areas. In case soil erosion is found, suitable Guidelines IX for measures shall be taken to control the soil erosion further Soil erosion including bio-turfing

While planning or executing excavations the Contractor will take all adequate precautions against soil erosion as per MoRSTH 306. Soil erosion at earth The earth stockpiles to be provided with gentle slopes to At earth Construction CSC / ADB Contractor stockpiles prevent soil erosion and stock piles to be located downwind. stockpiles cost PIU PWD

28

Environmental Issue/ Reference to Laws Approximate Mitigation Institutional Responsibility Remedial Measure Component /Guidelines Location Cost Implementation Supervision IRC Guidelines (No. Non-productive, barren lands, wasteland shall be used for IRC:10-1961) borrowing earth with the necessary permissions/ consents. on borrow areas Borrow areas should not be located on cultivable lands except selection and in the situations where land owner’s desires to level the land. amount to be The top soil shall be preserved and depth shall be restricted to extracted the desired level and the slop shall not be steeper than 25%. For quarries

(Environmental Borrow areas shall be sited away from inhabited areas. To the Protection Act and Borrow sites Construction CSC / ADB Borrow areas extent possible, Contractor Rules, 1986; Water location. cost PIU PWD

Act, Air Act) To the extent borrow areas shall be sited away from inhabited + Clause No. areas. Borrow areas shall be leveled with salvaged material or 305.2.2 MoRSTH other filling materials which do not pose contamination of soil. Specifications for Else, it shall be converted into fishpond in consultation with Road and Bridge fishery department and land owner/community. Rehabilitation works Guidelines V of the borrow areas as per Guidelines for redevelopment of for Borrow Areas Borrow Areas. Management Clause No. 111.3 Aggregates will be sourced from existing licensed quarries. MoRSTH Copies of consent/ approval / rehabilitation plan for a new Specifications for quarry or use of existing source will be submitted to EO, PIU. Quarry Operations Road and Bridge The contractor will develop a Quarry Redevelopment plan, as Works Guidelines VI per the Mining Rules of the state and submit a copy of the for Quarry Areas approval to EA if new quarries are to be opened. . Management Construction vehicles, machinery, and equipment to be stationed in the designated ROW to avoid compaction. Approach roads/haulage roads Compaction of soil and shall be designed along the barren and hard soil area to Parking areas, impact on quarry haul reduce the compaction. Haulage roads Included in CSC / ADB roads due to movement Transportation of quarry material to the dumping site through Design requirement and construction Contractor PIU PWD of vehicles and heavy vehicles shall be done through existing major roads to construction cost equipment the extent possible to restrict wear and tear to the village/minor yards. roads. Land taken for construction camp and other temporary facility shall be restored to its original conditions.

29

Environmental Issue/ Reference to Laws Approximate Mitigation Institutional Responsibility Remedial Measure Component /Guidelines Location Cost Implementation Supervision

Fuel and lubricants shall be stored at the predefined storage location away from drainage channels. The storage area shall be paved with gentle slope to a corner and connected with a chamber to collect any spills of the oils Construction vehicles and equipment will be maintained and refueled in such a fashion that oil/diesel spillage does not contaminate the soil. All efforts shall be made to minimize the waste generation. Unavoidable waste shall be stored at the designated place prior to disposal. To avoid soil contamination at the wash-down and re-fuelling areas, “oil interceptors” shall be provided. Oil and grease spill and oil soaked materials are to be collected and stored in labeled containers (Labelled: WASTE OIL; and hazardous sign be displayed) and sold off to SPCB/ MoEF authorized Waste Oil Recycler Septic tank or mobile toilets fitted with anaerobic treatment facility shall be provided at construction camp. Fuelling Domestic solid waste at construction camp shall be segregated station, into biodegradable and non-biodegradable waste. The non- construction Contamination of soil and biodegradable and recyclable waste shall be sold off. Monitoring sites, and CSC / ADB construction waste Efforts shall be made that biodegradable waste shall be Design requirement Cost Included Contractor construction PIU PWD management composted in the mechanized and movable composter by the in EMoP camps and contractor. Non- bio-degradable and non-saleable waste shall disposal be disposed off to authorized land fill site. location. All excavated materials from roadway, shoulders, drains, cross drainage should be used for backfilling embankments, filling pits, and landscaping. Unusable debris material should be suitably disposed off at pre- designated disposal locations, with approval of the concerned authority.Unproductive/wastelands shall be selected for dumping sites. Away from residential areas and located at least 1KM downwind side of these locations, Dumping sites shall not be close to water body and contaminate any water sources, rivers. Dumping sites should have adequate capacity equal to the amount of debris generated. Public perception and consent from the village Panchayats about the location of debris disposal site shall be obtained before finalizing the location. The bituminous wastes shall be disposed in secure landfill sites only in environmentally accepted manner. For removal of debris, wastes and its disposal MoRSTH guidelines should be followed. Soil quality monitoring shall be carried out as per EMoP.

30

Environmental Issue/ Reference to Laws Approximate Mitigation Institutional Responsibility Remedial Measure Component /Guidelines Location Cost Implementation Supervision 6. Water Resources

Requisite permission as applicable shall be obtained for abstraction of groundwater. The contractor shall make arrangements for water required for Clause No. 1010 EP construction without affecting the water availability and supply Act 1986 MoRSTH Included in Throughout the CSC / ADB Construction water to nearby communities. Specifications for construction Contractor Project section PIU PWD Water intensive activities shall not be undertaken during Road and Bridge cost summer season. works Provisions shall be made to connect road side drains with exiting nearby ponds.

Existing drainage system to be maintained and further enhanced. Adequate cross drainage structures shall be provided. Additional balancing culverts shall be provided in flood prone areas. The embankment height shall be designed consistent with the Design requirement, existing topography of the region and shall be higher than the Clause No 501.8.6. HFL. MoRSTH Near all Alteration in surface water Included in Elaborate drainage system shall be provided to drain the storm Specifications for drainage CSC / ADB hydrology due to construction Contractor water from the roadway and embankment and to ensure Road and Bridge. channels, river PIU PWD embankment cost minimum disturbance to natural drainage of surface and IRC SP 42 and 50 crossings etc. subsurface water of the area. for design of surface Surface runoff from the main road and embankment slopes and subsurface shall be discharged through longitudinal drains, designed for adequate cross section, and the outfalls. No construction material will be stored or disposed near any water body except for reusing it for enhancement measures such as embankment raising. Embankment slopes to be modified suitably to restrict the soil debris entering water bodies. Provision of Silt fencing Design requirement, shall be made at water bodies. Clause No 501.8.6. Near Silt/sediment should be collected and stockpiled for possible MoRSTH Siltation in water bodies Mahanadi and reuse as surfacing of slopes where they have to be re-Specifications for Included in due to Joke River CSC / ADB vegetated. Road and Bridge construction Contractor construction activities/ bodies, PIU PWD Earthworks and stone works to be prevented from impeding works cost earthwork embankment natural flow of rivers, streams and existing drainage system. (CP and CP) slopes. Provision of retaining wall is made along the road for the ponds and worldwide best located next to the road to prevent soil erosion and siltation of practices pond

31

Environmental Issue/ Reference to Laws Approximate Mitigation Institutional Responsibility Remedial Measure Component /Guidelines Location Cost Implementation Supervision No vehicles or equipment should be parked or refueled near water-bodies, so as to avoid contamination from fuel and lubricants. Oil and grease traps and fuelling platforms to be provided at re- fuelling locations. All chemicals and oil shall be stored away from water and on concreted platform with catchment pit for spills collection. The Water Construction Water bodies, Deterioration in Surface All equipment operators, drivers, and warehouse personnel will (Prevention and cost refueling water quality due to be trained in immediate response for spill containment and Control of Pollution) Monitoring CSC / ADB stations, Contractor leakage from vehicles eventual cleanup. Readily available, simple to understand Act, 1974 and cost as PIU PWD construction and equipment. and preferably written in the local language emergency amendments indicated in camps. response procedure, including reporting, will be provided by the thereof. EMoP contractors Construction camp to be sited away from water bodies. Wastes must be collected, stored and taken to approve disposal site only. Water quality shall be monitored periodically. 7. Flora and Fauna

Suitable modifications in design to minimize tree cutting. Roadside trees to be removed with prior approval of competent authority. Compensatory plantation at 1:10 basis with local forest department. Provision of LPG in construction camp as fuel source to avoid Forest Department Vegetation loss Due to tree cutting, if possible. Forest Conservation for tree cutting and site Preparation and Additional plantation near river banks to check erosion (not Throughout Indicated CSC / ADB Act 1980 + IRC SP: compensatory tree construction activities and possible during construction stage). project corridor above PIU PWD 21 and IRC SP:66 plantation. Rest Plantation Strategy In the event of design changes during the construction stages contractor additional assessments including the possibility to save trees shall be made by the EA Road side Plantation Strategy as per IRC specifications including manuring. Control use of pesticides/manure

8. Construction Camps

32

Environmental Issue/ Reference to Laws Approximate Mitigation Institutional Responsibility Remedial Measure Component /Guidelines Location Cost Implementation Supervision All camps should maintain minimum distance from following: Both Included in Impact associated with CSC / ADB # 1000 m from habitation Design Requirement construction construction Contractor location PIU PWD # 500 m from water bodies camps cost The location, layout and basic facility provision of each labor camp will be submitted to CSC prior to their construction. The construction shall commence only after approval of CSC concurrence The contractor will maintain necessary living accommodation The Building and and ancillary facilities in functional and hygienic manner as Other Construction approved by the EA. workers (Regulation Preventive medical care to be provided to workers. of Employment and Disposal of solid waste on regular basis at identified locations. Conditions of worker’s Health in The Contractor will take all precautions to protect the workers Service) Act 1996 All construction Part of the CSC / ADB Contractor construction camp from insect and pest to reduce the risk to health. This includes and camps Contract PIU PWD the use of insecticides which should comply with local The Water regulations. (Prevention and No alcoholic liquor or prohibited drugs will be imported to, sell, Control of Pollution) give, barter to the workers of host community. Act, 1974 and Provision of day crèche for children amendments thereof Limited recreation and sporting facilities for the staff and workers. Immunization to immigrant workers/local community against communicable and sexually transmitted diseases. 9. Management of Construction Waste/Dismantled Debris Unproductive/wastelands shall be selected for dumping sites. Away from residential areas and water bodies Design Requirement Selection of Dumping Dumping sites have adequate capacity equal to the amount of At all Dumping Part of the CSC / ADB and MoRSTH Contractor. Sites debris generated. Sites contract PIU PWD guidelines Public perception and consent from the village Panchayats has to be obtained before finalizing the location. The existing bitumen surface shall be utilized for paving of cross roads, access roads, and paving works in construction sites and camps, temporary traffic diversions, and haulage routes. Reuse and Disposal of All excavated materials from roadway, shoulders, verges, construction and drains, cross drainage will be used for backfilling dismantled waste embankments, filling pits, and landscaping. Unusable debris material should be suitably disposed off at pre- designated disposal locations, with approval of the concerned authority. The bituminous wastes shall be disposed

33

Environmental Issue/ Reference to Laws Approximate Mitigation Institutional Responsibility Remedial Measure Component /Guidelines Location Cost Implementation Supervision in secure landfill sites only in environmentally accepted manner. For removal of debris, wastes and its disposal MORSTH guidelines should be followed. Unusable and surplus materials, as determined by the Project Engineer, will be removed and disposed off-site. 10. Accessibility, Traffic Management, Accident and Safety Risks

Temporary traffic diversion shall be planned by the contractor and approved by the. CSC. The traffic control plans shall contain details of diversions; traffic safety arrangements during construction; safety measures for nighttime traffic and precautions for transportation of hazardous materials. Traffic control plans shall be prepared in line with requirements of Project IRC‟s SP 55 document‟. Throughout the Design requirement and preparation The Contractor will ensure that the diversion/detour is always Design requirement project corridor CSC / ADB Traffic Planning During and Contractor maintained in running condition, particularly during the and IRC SP:55 especially at PIU PWD Construction Stage construction monsoon to avoid disruption to traffic flow. On stretches where intersections. cost it is not possible to pass the traffic on the part width of existing carriageway, temporary paved diversions will be constructed. The contractor shall inform local community of changes to traffic routes, and pedestrian access arrangements with assistance from CSC and Nodal officer concerned Use of adequate signage to ensure traffic management and safety. Conduct of regular safety audit on safety measures.

Design requirement Near habitation All measures for the safety of traffic during construction viz. and IRC: SP: 27 - on both sides signs, markings, flags, lights and flagmen as proposed in the Contractor in 1984 Report of schools, Included in Pedestrians, animal and Traffic Control Plan/Drawings shall be taken. consultation with CSC / ADB Containing temples, construction Vehicular movement, Temporary access and diversion, with proper drainage Forest department PIU PWD Recommendation ns hospitals, cost. facilities. and PIU of IRC Regional construction Access facility to the schools located adjacent to the highway. Workshops on sites, haulage Contractors to adopt and maintain safe working practices. Highway Safety IRC: roads, Usage of fluorescent and retro- reflective signage, in local SP: 32 -1988 Road diversion sites. language at the construction sites Safety for Children Included in Accident risk from Training to workers on safety procedures and precautions. (5-12 Years Old) Construction Obligation of CSC / ADB construction construction activities Provision of PPEs to workers. IRC: SP: 44 -1994 sites Contractor PIU PWD cost Provision of a readily available first aid unit including an Highway Safety adequate supply of dressing materials. Ensure ready access to Code IRC: SP: 55 - ambulance, nursing staff, and doctor when needed. 2001 Guidelines

34

Environmental Issue/ Reference to Laws Approximate Mitigation Institutional Responsibility Remedial Measure Component /Guidelines Location Cost Implementation Supervision The contractor will not employ any person below the age of 14 for Safety in years for any work and no woman will be employed on the Construction Zones work of painting with products containing lead in any form. the Building and Clear demarcation of areas for restricted accesses to avoid other Construction accidents. workers Act 1996 and Cess Act of 1996 Factories Act 1948 11. Common Property Resources and other Utilities Damage to Common Ensure that no construction material dumped close to the such Environment Throughout the Construction CSC / ADB Property Resources and facilities and all precautions are taken such that no damage Protection Contractor corridor cost PIU PWD Utilities happen to any of common property resources and utilities. Requirement The area shall be barricaded for safety prospective. It shall be Environment Access to common Throughout the Construction CSC / ADB ensured that access to these areas ensure for people to visit Protection Contractor property resources corridor cost PIU PWD such places. Requirement 12. Enhancement Measures Environmental Environmental Enhancement of tree plantations near likely to be relocated Enhancement as Throughout the Construction CSC / ADB enhancement along the community structures/ landscaping etc. Contractor part of project corridor cost PIU PWD corridor Enhancement/rehabilitation of borrow areas etc. requirement 13. Contractor Demobilization Contractor will prepare site restoration plans, which will be approved by the CSC. The cleanup and restoration operations are to be implemented by the contractor prior to demobilization. Clean-up Operations, All construction zones including river-beds, culverts, road-side Throughout the CSC / ADB Restoration and areas, camps, hot mix plant sites, crushers, batching plant sites Project requirement Corridor and ---- Contractor PIU PWD Rehabilitation and any other area used/affected by the project will be left borrow areas clean and tidy, at the contractor's expense, to the satisfaction of the Environmental officer. All the opened borrow areas will be rehabilitated .and CSC will certify in this regard. B. Operation Stage 1. Climate and Air quality

35

Environmental Issue/ Reference to Laws Approximate Mitigation Institutional Responsibility Remedial Measure Component /Guidelines Location Cost Implementation Supervision Roadside tree plantations shall be maintained. Regular maintenance of the road will be done to ensure good surface condition Environmental Ambient air quality monitoring shall be carried out as per Protection Act, 1986; Air pollution due to due to Throughout the Indicated in EMoP. If monitored parameters are above the prescribed limit, The Air (Prevention CSC / ADB PIU PWD vehicular movement Corridor EMoP suitable control measures must be taken. and Control of Road signs shall be provided reminding the motorist to properly Pollution) Act, 1981 maintain their vehicles to economize on fuel consumption and protect the environment. 2 Noise Environment Effective traffic management and good riding conditions shall Noise Pollution be maintained to reduce the noise level throughout the stretch Included in (Regulation and In all Noise due to movement and speed limitation and honking restrictions may be enforced additional Control) Rules, 2000 settlement CSC / ADB PIU PWD of traffic near sensitive locations. plantation and amendments areas The effectiveness of the multilayered plantation should be cost. thereof monitored. 3. Land and Soil Soil erosion at Periodic checking to be carried to assess the effectiveness of At bridge Included in embankment during the stabilization measures viz. turfing, stone pitching, river Project requirement locations and Operation/ CSC / ADB PIU PWD heavy rain fall. training structures etc. embankment Maintenance slopes and cost At bridge other probable Visual monitoring and inspection of soil erosion at borrow locations and Included in soil erosion Soil erosion at borrow areas, quarries (if closed and rehabilitated), embankments and embankment Operation/ Project requirement areas. CSC / ADB PIU PWD areas other places expected to be affected, will be carried out once in slopes and Maintenance every six months as suggested in monitoring plan. other probable cost 4. Water Resources soil erosion areas. Monitoring of surface water bodies Regular visual checks shall Contamination of surface be made to observe any incidence of blockade of Near Indicated in water quality due to drains/culverts. Regular checks shall be made for soil erosion Mahanadi and CSC / ADB PIU PWD EMoP leakage of oil Siltation and turfing conditions of river training structures for its effective Joke River maintenance. 5. Flora and Fauna

Planted trees, shrubs, and grasses to be properly maintained. Indicated in Forest Conservation Throughout the Vegetation The tree survivalist audit to be conducted at least once in a Monitoring CSC / ADB PIU PWD Act 1980 corridor year to assess the effectiveness cost in EMoP

6. Flooding/ inundation Road inundation due to Field Unit will ensure that all drains (side drains and all cross Project operation In settlement Overall CSC/PIU CSC / ADB PIU PWD

36

Environmental Issue/ Reference to Laws Approximate Mitigation Institutional Responsibility Remedial Measure Component /Guidelines Location Cost Implementation Supervision choking of drainage drainages) are periodically cleared especially before monsoon requirement area Operation channels season to facilitate the quick passage of rainwater and avoid cost flooding. 7. Right-of-Way Maintenance The construction site shall be kept completely clear of vegetation. Included in Accident Risk due to Regular maintenance of plantation Throughout the operation/ uncontrolled Growth of Invasive plant not to be planted near the road. Project requirement CSC / ADB PIU PWD Project route Maintenance vegetation Controlled use of herbicide/pesticide cost The designated ROW shall be maintained free of any encroachment. 8. Accidents and Safety Traffic control measures, including speed limits, will be enforced strictly. Included in Accident risks associated Further encroachment and squatting within the ROW will be Throughout the operation/ IRC: SP:55 CSC / ADB PIU PWD with traffic movement. prevented. Project route Maintenance Monitor/ensure that all safety provisions included in design and cost construction phase are properly maintained Included in Preparation of spill prevention and control and emergency Transport of Dangerous Throughout the operation/ preparedness and responsive plans based on an analysis of CSC / ADB PIU PWD Goods project stretch Maintenance hazards, implementation of presentation and control measures. cost. 9. Monitoring Operation Performance Monitor the operational performance of the mitigation/ enhancement measures carried out as a part of the project The indicators selected for monitoring include the survival rate Monitoring Operation Throughout the Included in of trees; utility of enhancement provision, status of CSC / ADB PIU PWD Performance corridor EMoP rehabilitation of borrow areas, Air quality, water quality, noise levels, soil quality, drainage pattern. The monitoring and reporting to be carried out as per EMoP EA: Executing Agency, PIU: Project Implementation Unit, PWD,CSC: Construction Supervision Consultant, EO : Environmental Officer, IRC: Indian Road Congress Source: ADB approved IEE report, Nandghat- Gidhoury (SH – 10) subproject Note: The changed scope of project has not resulted in any additional environmental implications thus the earlier proposed environmental management plan can be utilized and upgradation of EMP is not required.

37

Annexure IV Environmental Monitoring Plan (Package 3) Environmental Project stage Parameter Standards Locations Duration / Implementation Supervision Component Frequency

Air Construction PM2.5, PM10, Minimal National Wherever the Stack emission Construction PIU, PWD Phase SO2, NOx, CO, Standards contractor decides to monitoring Supervision HC locate the Hot Mix Consultant, Plant

PM2.5, PM10, National Ambient Stretch of the road Continuous 24- Construction PIU, PWD

SO2, NOx and Quality where construction hourly, twice a Supervision CO Standards in progress site week once during Consultant, Construction Phase

Operation PM2.5, PM10, National Ambient Villages along road Continuous 24- PIU, PWD PWD

Phase SO2, NOx and Quality stretch hourly, twice a CO Standards week once in year for 2 years Water Quality Construction pH, TDS, As Water quality Villages along road Once during the Construction PIU, PWD Stage TSS, Oil & standards stretch Construction Phase Supervision Grease (IS 10500) Consultant, Operation pH, TDS, As Water quality Villages along road End of summer PIU, PWD PWD

Phase TSS, Oil & standards stretch before the onset on Grease (IS 10500) monsoon every year for 2 years

Noise and Construction Noise Level in As per National Villages along road One-day hourly Construction PIU, PWD Vibration Phase dB (A) Noise standards stretch measurement, Supervision once in six Months Consultant, once during the construction Phase

Operation Noise Level in As per National Villages along road One day hourly PIU, PWD PIU, PWD Phase dB (A) Noise standards. stretch measurement,

38

Environmental Project stage Parameter Standards Locations Duration / Implementation Supervision Component Frequency Soil Erosion Construction Soil erosion -- On slops and After precipitation PIU, PWD PIU, PWD Phase embankment Operation Soil erosion -- On slops and After precipitation PIU, PWD PIU, PWD Phase embankment Road Side Construction Monitoring of As laid out in the Entire stretch of During felling of Forest Dept. PIU, PWD Plantation Phase trees felling detailed design for project road trees project Operation Survival rate of The survival rate Entire stretch of Every year for 3 PWD, Forest Dept. PIU, PWD Phase trees success of should be at least project road years re-plantation 70% below which re- plantation shall be done.

Source: ADB approved IEE report, Nandghat to Gidhoury (SH – 10) subproject

39

Environmental Monitoring Plan (Package 4) Environmental Project stage Parameter Standards Locations Duration / Implementation Supervision Component Frequency

Air Construction PM10 and Minimal National Wherever the Stack Emission Construction PIU, PWD Phase PM2.5, SO2, Standards contractor decides Monitoring Supervision NOx, CO, HC to locate the Hot Consultant, Mix Plant

PM2.5, PM10, National Ambient Stretch of the road Continuous 24- Construction PIU, PWD SO2, NOx and Quality where construction hourly, twice a Supervision CO Standards in Progress site. week once during Consultant, Construction Phase

Operation PM2.5, PM10, National Ambient Villages along road Continuous 24- PIU, PWD PIU, PWD Phase SO2, NOx and Quality stretch hourly, twice a CO Standards week once in year for 2 years Water Quality Construction pH, TDS, As Water quality Villages along road Construction PIU, PWD Stage TSS, Oil & standards (IS stretch Once during the Supervision Grease 10500) Construction Phase Consultant, Operation pH, TDS, As Water quality Villages along road PIU, PWD PIU, PWD Phase TSS, Oil & standards (IS stretch End of summer before Grease 10500) the onset on monsoon every year for 2 years

Noise and Construction Noise Level in As per National Villages along road Construction PIU, PWD Vibration Phase dB (A) Noise standards stretch One-day hourly Supervision measurement, once in Consultant, six months once during the Construction Phase

40

Environmental Project stage Parameter Standards Locations Duration / Implementation Supervision Component Frequency

Operation Noise Level in As per National Villages along road One - day hourly PIU, PWD PIU, PWD Phase dB (A) Noise standards. stretch measurement,

Soil Erosion Construction Soil erosion -- On slops and After precipitation PIU, PWD PIU, PWD Phase embankment Operation Soil erosion -- On slops and After precipitation PIU, PWD PIU, PWD Phase embankment Road Side Construction Monitoring of As laid out in the Entire stretch of During felling of Forest Dept. PIU, PWD Plantation Phase trees felling detailed design project road trees for project Operation Survival rate of The survival rate Entire stretch of Every year for 3 PWD, Forest Dept. PIU, PWD Phase trees success should be at least project road years of re- 70% below which plantation re- plantation shall be done.

Source: ADB approved IEE report, Nandghat to Gidhoury (SH – 10) subproject

41

Annexure – V Grievance Redress Committee – District Baloda bazar

Annexure VI Permission for Tree Cutting (Package III)

Annexure VII Tree cutting Permission (Package IV)

Annexure VIII

Photographs of Field Visit

Package 3 (Baloda bazar) Package 3 [Bhatapara (excluding RoB)]

Package 3 (end point 4 lane) Package 4 (Baloda bazar)

Package 4 (nearby pond Baloda bazar) Package 4 (Construction of drain)

Package 4 (Lawan) package 4 (No additional trees present alongside 2 lane road)

Package 4 (Kasdol) Baloda bazar Junction