Inspectors Report

Total Page:16

File Type:pdf, Size:1020Kb

Inspectors Report Inspector’s Report ABP-300840-18. Development Baldoyle to Portmarnock Pedestrian and Cyclist Scheme. Location Between Baldoyle and Portmarnock, Co. Dublin. Local Authority Fingal County Council. Type of Application Application for approval made under Section 177(AE) of the Planning and Development Act, 2000 Prescribed Bodies • Department of Culture, Heritage and the Gaeltacht • National Transport Authority. Observer(s) • John Fay • Cllr. David Healy • Brendan Ryan TD and Cllr. Brian McDonagh • Portmarnock Community Association • Marie Cummins. Date of Site Inspection 29th May 2018 Inspector Deirdre MacGabhann. ABP-300840-18 Inspector’s Report Page 1 of 57 Contents 1.0 Introduction .......................................................................................................... 3 2.0 Proposed Development ....................................................................................... 3 3.0 Site and Location ................................................................................................. 6 4.0 Planning History ................................................................................................... 7 5.0 Legislative and Policy Context ............................................................................. 8 5.7. Regional Policy ........................................................................................... 10 5.8. Local Policy ................................................................................................. 10 6.0 The Natura Impact Statement. ........................................................................... 14 7.0 Consultations ..................................................................................................... 14 7.4. Further Submissions ................................................................................... 17 8.0 Assessment ....................................................................................................... 17 8.1. The likely consequences for the proper planning and sustainable development of the area ....................................................................................... 17 8.2. The likely effects on the environment .......................................................... 19 8.3. The likely significant effects on a European site.......................................... 28 9.0 Recommendation ............................................................................................... 52 10.0 Reasons and Considerations ...................................................................... 52 ABP-300840-18 Inspector’s Report Page 2 of 57 1.0 Introduction 1.1. Fingal County Council is seeking approval from An Bord Pleanála to undertake the construction of c.1.8km of pedestrian and cycleway adjacent to the Coast Road (R106) from Baldoyle (Red Arches Road) to Portmarnock (just south of the Coast Road/Station Road roundabout). 1.2. The development lies adjacent to Baldoyle Bay, a designated European site (SAC and SPA) and in proximity to other European sites. A Natura Impact Statement (NIS) and application under Section 177AE was lodged by the local authority on the basis of the proposed development’s likely significant effect on a European site. 1.3. Section 177AE of the Planning and Development act 2000 (as amended) requires that where an appropriate assessment is required in respect of development by a local authority, the authority shall prepare an NIS and the development shall not be carried out unless the Board has approved the development with or without modifications. Furthermore, Section 177V of the Planning and Development Act 2000 (as amended) requires that the appropriate assessment shall include a determination by the Board as to whether or not the proposed development would adversely affect the integrity of a European site and the appropriate assessment shall be carried out by the Board before consent is given for the proposed development. 2.0 Proposed Development 2.1. The proposed development comprises a new 1.8km pedestrian and cyclist scheme between Baldoyle and Portmarnock, Co. Dublin. The pedestrian/cyclist scheme will run approximately parallel to, and on the inland (west) side of, Coast Road (R106). It will lie almost wholly within Racecourse Park a new regional park, and consists of: • A 3m wide cycletrack and a 2m wide footpath separated by a 2.4m wide grass verge, • A new 30m long, 4m wide bridge over the Mayne River, ABP-300840-18 Inspector’s Report Page 3 of 57 • Upgrading of the existing priority junction between the Coast Road (R106) and Moyne Road to a signal controlled junction with pedestrian facilities, • Provision of toucan crossing facilities on Coast Road at either end of the proposed scheme, • Provision of a controllable, intelligent public lighting scheme, and • Provision of landscaping, signage and other works ancillary to the construction and operation of the proposed development. 2.2. The detailed design of Regional Park has been informed by recommendations set out in the Baldoyle-Stapolin Local Area Plan, 2013 and the Portmarnock South Local Area Plan, 2013 which seek protect the integrity of the neighbouring nationally and internationally designated sites e.g. by providing suitable habitat for key species and the new walking and cycling route located away from the shoreline to attract users away from the sensitive habitat areas (Figures 2.3 and 2.4, NIS). 2.3. The proposed pedestrian/cyclist route will merge as a shared path at the start and finish of the route and as it approaches and crosses the Mayne River. The 4m wide bridge over the River will be a concrete deck bridge supported by steel piles on each side of the River (depth of pile will depend on encountered ground conditions but are expected to be greater than 3m). The route will be finished in black asphalt. Lighting is proposed along the length of the scheme and will consist of 6m columns at 25m intervals. Poles will be located at the back of the footpath (landward side of the path), with the lights dimming by 50% between 11pm and 6am. No boundary fencing is proposed alongside the track and the development will form part of the new public park to be developed on adjoining lands. (The route is, and will remain, fenced off from proposed conservation areas within Racecourse Park to the west). 2.4. During construction a site compound will be located at the north-eastern portion of the Red Arches/Coast Road junction, within the lands of the proposed route. Access to the site will be from this end with haul routes running along the line of the proposed path (see Figure 2.2, NIS). 2.5. The application to the Board is accompanied by the following: • Planning Report – This principally sets out the strategic and local planning context for the development. In Section 3.3.2 it sets out the rational for the ABP-300840-18 Inspector’s Report Page 4 of 57 width of the pedestrian/cycle scheme, which differs from the 3m width referred to in the Baldoyle-Stapolin LAP and the Portmarnock LAP. Essentially the wider route, and separation of pedestrians from cyclists, better provides for the anticipated volume of users in the longer term (the development will become part of, and link to a wider cycle network connecting the urban and rural areas in the Dublin area). The report also states that it is important that the development be delivered as soon as possible to ensure that new residents of the c.2000 new homes provided under the two LAPs (c.800 already built) have no impact on the European site Baldoyle Bay, • Options Assessment Report – This report sets out the policy context for the development, key constrains along the route and four options for the pedestrian/cyclist scheme, namely (1) Upgrade Coast Road, (2) Off Road Shared Facility, (3) Off Road Segregated Facility and (4) Shared Boardwalk. Options are compared on economy, safety and environmental grounds and a preferred option, no. 3, Off Road Segregated Facility, is identified (the proposed scheme). • Preliminary Design Report – This report considers the context of the scheme, in terms of Local, Regional and National Planning policy and outlines the preliminary design of the preferred option. The report includes details on the junction design, crossing facilities, bus stops, drainage, public lighting, pavements, structures and services. In Section 8 it sets out a preliminary construction methodology. If approved, detailed design of the project will be developed. The methodology includes that construction be completed by the 1st November, to ensure no impacts on wintering wildfowl in Baldoyle SPA, and specific measures to manage construction of the bridge over the River Mayne, to prevent pollution of waters. • Drawing booklet. • Natura Impact Statement – This report includes (a) a screening exercise which screens out likely significant effects of the development on 16 European sites lying within 15km of the proposed development (it also rules out the likelihood of significant effects on European sites over 15km from the ABP-300840-18 Inspector’s Report Page 5 of 57 site), and (b) an appropriate assessment of the likelihood of significant effects on the Baldoyle Bay SAC, which the proposed development runs through, and Baldoyle Bay SPA. The report concludes that the development will not have any significant negative effect on either site. • EIA Screening Statement – The purpose of this report is to determine if the project requires Environmental Impact Assessment. It considers that EIA is not mandatory, as the development does not
Recommended publications
  • Appropriate Assessment Report Site Investigations Off Dublin and Wicklow Coast in the Vicinity of the Kish and Bray Banks (FS007029)
    Appropriate Assessment Report Site Investigations off Dublin and Wicklow coast in the vicinity of the Kish and Bray Banks (FS007029). Project Description: Innogy Renewables Ireland Ltd has submitted an application for a Foreshore Licence to carry out site investigations in the western Irish Sea off the coast of Dublin and Wicklow in the vicinity of the Kish and Bray Banks. The location of the proposed site investigations area is shown in the following drawing submitted by the applicant: Drawing No 1330-B-01 application , “Foreshore Licence Map 1 Foreshore Licence, Geophysical Survey Area and Metocean Monitoring” , Ver 3 dated 30/08/2019 The overall aim of the site investigations is to collect the necessary data and information required to inform the Environmental Impact Assessment Report (EIAR), Natura Impact Statement (NIS) and preliminary design for a proposed wind farm array and ancillary infrastructure in the vicinity of the Kish and Bray Banks. The possible installation of a windfarm and associated infrastructure in the area in the future would be the subject of a separate Foreshore Lease / Licence application and is not the subject of this current application. It is proposed that the site investigations will include: Geophysical Survey - involving the use of multibeam echo sounder, magnetometer, sub- bottom profiler and side scan sonar Geotechnical survey – involving cone penetration testing as well as vibrocoring and drilling of boreholes. The exact location, quantity and type of geotechnical samples collected would be subject to the results of the geophysical survey. The following indicative numbers, may be collected: 48 vibrocores – approximately 150mm diameter and penetration depth of up to 6m 15 cone penetration tests – in intertidal areas, approximately 4cm diameter and depth of up to 15m 3 boreholes – approximately 10cm diameter and depth of up to 20m Ecological Survey – It is anticipated that benthic grab samples will be collected at up to 30 sampling sites in the survey area.
    [Show full text]
  • Natura Impact Report BALDOYLE - STAPOLIN Local Area Plan
    Natura Impact Report Local Area Plan BALDOYLE - STAPOLIN Appropriate Assessment June 2013 Comhairle Contae Fhine Gall Fingal County Council NATURA IMPACT REPORT BALDOYLE-STAPOLIN LOCAL AREA PLAN 2013-2019 FINGAL COUNTY COUNCIL Rev. Status Author Reviewed By Approved By Issue Date D17 Final JAH/PS PS PS 10/06/13 Scott Cawley, 127 Lower Baggot Street, Suite 401 -404, Dublin 2, Ireland Tel+353(1)676-9815 Fax +353(1) 676-9816 TABLE OF CONTENTS 1 Introduction ..................................................................................................................................................3 1.1 Requirement for Appropriate Assessment ...........................................................................................3 1.2 Appropriate Assessment Process: Purpose and Process ......................................................................3 1.3 Formal Guidance...................................................................................................................................6 1.4 Data Sources .........................................................................................................................................7 1.5 Consultation..........................................................................................................................................7 2 Stage 1 Screening..........................................................................................................................................8 2.1 Methodology.........................................................................................................................................8
    [Show full text]
  • 2007 Portrane Beach Management Plan
    Development of a Beach Management Plan for the Burrow, Portrane, Co. Dublin An Action of the Fingal Heritage Plan, 2005-2010 January 2007 Fingal County Council County Hall Swords Co. Dublin FC0106/FINAL Fingal County Beach Management Plan for the Burrow, Portrane, Co. Dublin Council Table of Contents Chapters EXECUTIVE SUMMARY 1.0 Introduction........................................................................1 2.0 The Burrow Beach ...............................................................5 3.0 The Consultation Process .................................................... 14 4.0 Overview of Issues Raised in the Consultation Process ............ 20 5.0 Beach Management Plan - Options ....................................... 34 6.0 Project Conclusions............................................................ 50 Appendix 1: Legislative and Policy Context Appendix 2: Opinion Survey – Results Appendix 3: Public Meeting – Discussions Summary Appendix 4: Minutes of Meeting with Burrow Residents’ Association Appendix 5: Fingal County Council Beach and Foreshore Bye-Laws, 2006 Fingal County Beach Management Plan for the Burrow, Portrane, Co. Dublin Executive Council Summary EXECUTIVE SUMMARY 1. The Burrow is an area of the Portrane peninsula comprised mainly of open farm land, scattered housing, dunes and estuary foreshore defined to the north and west by the Rogerstown estuary, to the east by the Burrow beach and to the south by the urban area of Portrane village. 2. The Burrow beach is an extremely valuable resource to both residents and visitors for a number of reasons, including its aesthetic, environmental, recreational and community characteristics. In addition, the coastal waters of the Burrow Beach have achieved “Blue Flag” status in 2006. 3. Fingal County Council, with support from the Heritage Council, commissioned a consultative process with the objective of producing a beach management plan for The Burrow, in summer/autumn 2006.
    [Show full text]
  • Greater Dublin Drainage Project Irish Water
    Greater Dublin Drainage Project Irish Water Environmental Impact Assessment Report: Volume 3 Part A of 6 Chapter 17 Hydrology and Hydrogeology June 2018 Envir onmental Impact Assessment Report: Vol ume 3 Part A of 6 Irish Water Environmental Impact Assessment Report: Volume 3 Part A of 6 Contents 17. Hydrology and Hydrogeology .................................................................................................................. 1 17.1 Introduction .................................................................................................................................................. 2 17.2 Methodology ................................................................................................................................................ 4 17.2.1 Desktop Study ............................................................................................................................................. 5 17.2.2 Legislation ................................................................................................................................................... 6 17.2.3 Stakeholder Consultation ............................................................................................................................ 6 17.2.4 Groundwater Supplies – Surveys and Questionnaires ............................................................................... 6 17.3 Attributes ....................................................................................................................................................
    [Show full text]
  • Si No. 279 of 2016
    NATURA IMPACT REPORT IN SUPPORT OF THE APPROPRIATE ASSESSMENT FOR POOLBEG WEST SDZ PLANNING SCHEME (SI NO. 279 OF 2016) IN ACCORDANCE WITH THE REQUIREMENTS OF ARTICLE 6(3) OF THE EU HABITATS DIRECTIVE for: Dublin County Council Civic Offices Wood Quay Dublin 8 by: CAAS Ltd. 1st Floor, 24-26 Ormond Quay, Dublin 7 OCTOBER 2017 Includes Ordnance Survey Ireland data reproduced under OSi Licence Number 2016/22/CCMA/Dublin City Council. Unauthorised Reproduction infringes Ordnance Survey Ireland and Government of Ireland Copyright. © Ordnance Survey Ireland Table of Contents 1 Introduction ................................................................................................................... 1 1.1 Background.................................................................................................................... 1 1.2 Legislative Context ......................................................................................................... 1 1.3 Guidance ....................................................................................................................... 2 1.4 Stages of Screening Assessment ..................................................................................... 3 1.5 Relationship between the Appropriate Assessment process and the Plan............................ 4 1.6 Consultation Process ...................................................................................................... 5 2 Description of the Planning Scheme and Receiving Environment ................................
    [Show full text]
  • MDB0254RP0023 ASA2 Consultation
    Greater Dublin Drainage Public Consultation Report on ‘Alternative Sites Assessment and Routes Selection (Phase Two): Emerging Preferred Sites and Routes, May 2012’ TABLE OF CONTENTS 1 INTRODUCTION .......................................................................................................................... 1 1.1 PROJECT BACKGROUND ...................................................................................................... 1 1.1.1 Public Consultation 1: Constraints Consultation, May – June 2011 .................... 4 2 ASA PHASE 2 CONSULTATION (MAY – JULY 2012) .................................................................... 7 2.1 INTRODUCTION .................................................................................................................. 7 2.2 CONSULTATION PERIOD ....................................................................................................... 7 2.3 TERMS OF REFERENCE ....................................................................................................... 8 2.4 CONSULTATION GUIDELINES ................................................................................................ 8 2.5 PUBLICISING THE CONSULTATION ......................................................................................... 9 2.5.1 Media ................................................................................................................ 9 2.5.2 Information Service ........................................................................................ 14 2.5.3 Website
    [Show full text]
  • Download PDF (4.9MB)
    Natura Impact Report For the Clongriffin - Belmayne Local Area Plan Prepared by Planning and Economic Development Dublin City Council December 2012 TABLE OF CONTENTS 1.0 Introduction 1 1.1 Legislative Background 1 1.2 Methodology 2 1.3 Natura 2000 Sites 3 2.0 Stage One Screening 4 2.1 Description of the Plan 4 2.2 Integrating AA into the Plan-Making Process 4 2.3 Brief Description of the Natura 2000 Sites 5 3.0 Stage Two Appropriate Assessment 10 3.1 Introduction 10 3.2 Impact Prediction 13 3.3 Conservation Objectives 13 3.4 Mitigation Measures 14 3.5 Mitigatory Policies for Clongriifin-Belmayne Local Plan Area 16 3.6 Outcomes 31 3.7 Conclusion 31 LIST OF TABLES Table 1: Natura 2000 Sites within 15km of the Local Area Plan Administrative Boundary 5 Table 2: Schedule of Impacts for Natura 2000 sites 9 Table 3: List of Parameters 11 Table 4: Governing Legislative limits 12 Table 5: Policies and Objectives Screened in under stage 1 and possible Mitigatory measures, policies and actions 17 Table 6a: Mitigatory Policies – Part A 21 Table 6b: Mitigatory Policies – Part B 27 APPENDICES Appendix I: Screening Report 32 Appendix II: Result of analysis of samples 54 INTRODUCTION The Appropriate Assessment (AA) has been undertaken for the Clongriffin-Belmayne Local Area Plan 2012-2018 in accordance with the European Commission Methodological Guidance on the provision of Article 6(3) and 6(4) of the ‘Habitats’ Directive 92/43/EEC (EC 2001) and the Appropriate Assessment of Plans and Projects in Ireland (Guidance for Planning Authorities).
    [Show full text]
  • Volume I Non-Technical Summary
    GLL PRS Holdco Limited Proposed Strategic Housing Development “Kenelm” Deer Park Howth Co. Dublin VOLUME I NON-TECHNICAL SUMMARY MAY 2021 Client GLL PRS Holdco Limited Project Title Kenelm, Howth Document Title EIAR Volume I Non Technical Summary Document No. 3865 Document DCS TOC Text Appendices Comprises 1 1 114 0 Prepared by PG Checked by JK Revision Status Issue date A ISSUED 04.06.2021 Table of Contents Figure 1 Howth Castle Architectural Conservation Area ................................................................................. 15 Figure 2 Howth Special Area Amenity Order .................................................................................................. 16 Figure 3 Proposed Development Site & Site Context ...................................................................................... 17 Figure 4 Proposed Site Layout ......................................................................................................................... 21 Figure 5 Proposed Courtyards ......................................................................................................................... 23 Figure 6 Roof Garden (Extract from Landscape Design Statement)................................................................ 24 Figure 7 Proposed Public Open Space (Extract from Landscape Design Statement) ...................................... 25 Figure 8 Proposed Woodland Belt (Extract from BSLA Landscape Drawings) ................................................ 27 Figure 9 Proposed Movement Strategy .........................................................................................................
    [Show full text]
  • Acrobat Distiller, Job 6
    COASTAL ZONE MANAGEMENT A DRAFT POLICY FOR IRELAND MAIN REPORT BRADY SHIPMAN MARTIN in association with HR Wallingford Natural Environmental Consultants Ltd. COASTAL ZONE MANAGEMENT A DRAFT POLICY FOR IRELAND MAIN REPORT Prepared for Department of Arts, Heritage, Gaeltacht and the Islands Department of the Environment and Local Government Department of the Marine and Natural Resources by BRADY SHIPMAN MARTIN in association with HR Wallingford and Natural Environment Consultants Ltd. STUDY TEAM The study was carried out by a team of consultants from BRADY SHIPMAN MARTIN in association with HR Wallingford and Natural Environment Consultants Ltd. The team also included Dr. Susan Gubbay, an acknowledged international expert in the field of Coastal Zone Management. BRADY SHIPMAN MARTIN 26 Temple Road Dartry DUBLIN 6 © Government of Ireland 1997 Price: £10.00 COASTAL ZONE MANAGEMENT A DRAFT POLICY FOR IRELAND TABLE OF CONTENTS 1. INTRODUCTION 1 BACKGROUND AND CURRENT SITUATION 2. THE CONCEPT OF COASTAL ZONE MANAGEMENT 5 3. THE INTERNATIONAL CONTEXT 15 4. LEGISLATION AND ADMINISTRATION 33 5. CONSERVATION AND ENVIRONMENTAL PROTECTION 43 6. LAND-USE PLANNING AND CONTROL 63 7. COASTAL RESOURCE DEVELOPMENT 71 8. MARINE RESOURCE DEVELOPMENT 89 9. COASTAL PROTECTION 113 ISSUES AND RECOMMENDATIONS 10. KEY ISSUES 121 11. THE NEED FOR ICZM 129 12. THE SCOPE FOR ACTION 133 13. THE RECOMMENDED FRAMEWORK 141 14. OTHER RECOMMENDATIONS 155 APPENDICES 1. DESCRIPTION OF THE COASTLINE Appendices 1 2. DRAFT ICZM PLAN WORK PROGRAMME Appendices 17 3. BIBLIOGRAPHY
    [Show full text]
  • Screening Report for Appropriate Assessment of Mixed-Use Development, Clongriffin, Dublin 13
    1 Screening Report for Appropriate Assessment of mixed-use development, Clongriffin, Dublin 13 prepared by OPENFIELD Ecological Services for Gerard Gannon Properties Pádraic Fogarty MSc, MIEMA August 2019 www.openfield.ie 2 1.0 INTRODUCTION 1.1 About OPENFIELD Ecological Services OPENFIELD Ecological Services is headed by Pádraic Fogarty who has worked for over 20 years in the environmental field and in 2007 was awarded an MSc from Sligo Institute of Technology for research into Ecological Impact Assessment (EcIA) in Ireland. Pádraic has a primary degree in Analytical Science from DCU, and diplomas in Field Ecology (UCC), Environment and Geography (Open University) and Environmental Protection (IT Sligo). Since its inception in 2007 OPENFIELD has carried out numerous EcIAs for Environmental Impact Assessment (EIA), Appropriate Assessment under the EU Habitats Directive, as well as individual planning applications. Pádraic is a full member of the Institute of Environmental Management. 1.2 Protection of biodiversity Biodiversity is a contraction of the words ‘biological diversity’ and describes the enormous variability in species, habitats and genes that exist on Earth. It is an integral component of our heritage while also providing food, building materials, fuel and clothing, maintaining clean air, water, soil fertility and pollinating crops. A study by the Department of Environment, Heritage and Local Government placed the economic value of biodiversity to Ireland at €2.6 billion annually (Bullock et al., 2008) for these ‘ecosystem services’. All life depends on biodiversity and its current global decline is a major challenge facing humanity. In 1992, at the Rio Earth Summit, this challenge was recognised by the United Nations through the Convention on Biological Diversity which has since been ratified by 193 countries, including Ireland.
    [Show full text]
  • Baldoyle Bay SPA 004016 Conservation Objectives Supporting
    Baldoyle Bay Special Protection Area (Site Code 4016) ≡ Conservation Objectives Supporting Document VERSION 1 National Parks & Wildlife Service December 2012 T A B L E O F C O N T E N T S SUMMARY PART ONE - INTRODUCTION ........................................................................ 1 1.1 Introduction to the designation of Special Protection Areas ............................................. 1 1.2 Introduction to Baldoyle Bay Special Protection Area ...................................................... 2 1.3 Introduction to Conservation Objectives ........................................................................... 2 PART TWO – SITE DESIGNATION INFORMATION ....................................................................... 4 2.1 Special Conservation Interests of Baldoyle Bay Special Protection Area ........................ 4 PART THREE – CONSERVATION OBJECTIVES FOR BALDOYLE BAY SPA ............................... 6 3.1 Conservation Objectives for the non-breeding Special Conservation Interests of Baldoyle Bay SPA ................................................................................................................... 6 PART FOUR – REVIEW OF THE CONSERVATION CONDITION OF WATERBIRD SPECIAL CONSERVATION INTERESTS ........................................................................ 9 4.1 Population data for waterbird SCI species of Baldoyle Bay SPA ..................................... 9 4.2 Waterbird population trends for Baldoyle Bay SPA ........................................................ 10 4.3
    [Show full text]
  • Ecological Impact Assessment for a Proposed Development On
    1 Screening Report for Appropriate Assessment of a Strategic Housing Development at Auburn, Malahide, County Dublin prepared by OPENFIELD Ecological Services for Kinwest Limited Pádraic Fogarty MSc, MIEMA April 2021 www.openfield.ie 2 1.0 INTRODUCTION 1.1 About OPENFIELD Ecological Services OPENFIELD Ecological Services is headed by Pádraic Fogarty who has worked for 25 years in the environmental field and in 2007 was awarded an MSc from Sligo Institute of Technology for research into Ecological Impact Assessment (EcIA) in Ireland. Pádraic has a primary degree in Analytical Science from DCU, and diplomas in Field Ecology (UCC), Environment and Geography (Open University) and Environmental Protection (IT Sligo). Since its inception in 2007 OPENFIELD has carried out numerous EcIAs for Environmental Impact Assessment (EIA), Appropriate Assessment under the EU Habitats Directive, as well as individual planning applications. Pádraic is a full member of the Institute of Environmental Management and Assessment (IEMA). 1.2 Protection of biodiversity This report has been prepared by Padraic Fogarty of OPENFIELD Ecological Services. Pádraic Fogarty has worked for 25 years in the environmental field and in 2007 was awarded an MSc from Sligo Institute of Technology for research into Ecological Impact Assessment (EcIA) in Ireland. OPENFIELD is a full member of the Institute of Environmental Management and Assessment (IEMA). This report finds that significant effects to Natura 2000 sites will not arise as a result of this project, either alone or in combination with other plans and projects, and that this conclusion is beyond a reasonable scientific doubt on the basis of the best scientific knowledge available.
    [Show full text]