I N D E X

AGENDA FOR THE 14th S.L.C. MEETING TO BE HELD ON 21.03.2017 at 11.30 A.M. IN THE CONFERENCE HALL, COMMISSIONERATE OF INDUSTRIES, 1st FLOOR, GOVERNMENT PRINTING PRESS BUILDINGS, MUTYALAMPADU, VIJAYAWADA

ITEM ITEM PAGE NO. NO.

1 CONFIRMATION OF THE MINUTES OF THE PREVIOUS MEETING HELD ON 21/11/2016. 2 – 101

2 FOLLOW UP ACTION ON THE MINUTES OF THE PREVIOUS MEETING HELD ON 21/11/2016. 102 – 110

3 SANCTION OF INCENTIVES / CONCESSIONS TO THE UNITS UNDER VARIOUS SCHEMES. 111 – 142

STATUS REPORT ON RELEASE OF SANCTIONED INCENTIVES / CONCESSIONS TO THE UNITS 4 143 – 144 FOR THE YEAR 2015-16 & 2016-17.

STATUS REPORT ON THE PROPOSALS SENT TO THE GOVERNMENT PERTAINING TO THE 5 145 – 148 DECISIONS TAKEN BY THE S.L.C.

IIDF - PROPOSALS FOR ASSISTANCE UNDER INDUSTRIAL INFRASTRUCTURE DEVELOPMENT 6 149 – 154 FUND (IIDF) UNDER IIPP 2010-15 & 2015-20 – REGARDING

:: 2 ::

ITEM NO: 1

MINUTES OF THE 13th S.L.C. MEETING HELD ON 21/11/2016 AT 11.30 A.M. IN THE CONFERENCE ROOM OF COLLECTOR’S CAMP OFFICE , VIJAYAWADA

The list of the Members who attended the meeting is appended. Agenda Brief Description of the Issue Decision of the Committee Item 1 Confirmation of the Minutes of the previous Meeting held on 22/09/2016 with the following SLC confirmed the minutes of the amendments: previous meeting held on 22/09/2016. Noted. However, SLC has desired that the action on Table Agenda pertaining to SC/ST incentives to be initiated immediately and completed by 05/12/2016.

Further, SLC decided to write to 2 Follow up action on the minutes of the previous Meeting held on 22/09/2016. Government to constitute a consultative Committee with all Stake holders, Associations, Officials of Industries Department and AP Food Processing Society to do detailed study on processing of ineligible list related to Food Processing under Annexure-I of IDP – 2015-20. 3 IIPP 2005-10, IIPP 2010-15 & IDP – 2015-20 schemes – Sanction of reimbursement of stamp duty, SLC has examined the reimbursement of land cost purchased in IEs/IDAs, reimbursement of power cost and sanction of recommendations of the Verification / reimbursement of sales tax - Regarding. Scrutiny Committee and decided to ***** sanction eligible incentives / concessions to the industrial units The Verification / Scrutiny Committee meeting held on 09/09/2016 has verified / Scrutinized (29) where there are no short falls, under claim applications of reimbursement of power cost (03) claim application of reimbursement of Sales Tax and as per the Guidelines under respective schemes and recommended for sanction/rejection of various schemes as detailed below. eligible Incentives / Concessions to the units. The Minutes of Verification / Scrutiny Committee of Sales Tax and Power cost are appended as Annexure - XX. Further, SLC discussed the recommendation of SVC for sanction of incentive subject to submition of shortfall documents and a view was :: 3 ::

ABSTRACT taken to put an end of sanctioning subject shortfalls and kept in abeyance. No of Further, a Special SVC is to be claims as conducted within a week in repect of Sl. No of General Incentives per Amount these cases where shortfall submitted No units (in Rupees ) and recommend to the ensuing SLC seriatim Meeting. Chaiman SLC has essured ( website) that a Spcial SLC will be conducted for 1 Power Cost 29 25 222230619 all these cases.

2 Sales Tax 3 2 177691509 ABSTRACT OF SANCTION OF INCENTIVES No of Sl. Deferred by SVC & General claims as Amount No. per Incentives (in Rupees ) 3 Repeated. 22 16 0 seriatim (website) GRAND TOTAL 54 43 399922128 1 Power Cost 26 198972290

33.99 Crores 2 Sales Tax 4 30397314 Deferred by The Verification / Scrutiny Committee of Investment Subsidy and Sales Tax have 3 SLC 122 0 recommended for sanction / rejection of eligible Incentives/concessions to the units as 229369604 mentioned below: GRAND TOTAL 152

1.SANCTION OF REIMBURSEMENT OF POWER COST: DETAILS Date of Sl. No. & Date of Name & Commence Sl. date of Line of Nature of 1. Reimbursement of Power cost receipt of Address of the ment of Policy Decision No. SVC activity incentives Sanctioned: Reimbursement of claim unit commercial Meeting production power cost to (26) units under IIPP SVC has examined the case & IDP 2015-20 and the list is in light of precedent case of M/s Mohan appended as Annexure – I M/s. Srikalahasthi Pipes Spintex Limited (SPL) (Formerly: Ltd (Unit-II) Cotton Lanco Industries Limited) 2. Reimbursement of Sales tax: RS. No. Spinning Reimburse- Spill over IIPP where SLC has taken a view 1 289/2B3, Mills ment of Sanctioned to Reimbursement of case 2005-10 to refer to Government on Remalle (V), including power cost achievement of investment Sales Tax (4) units under IIPP & Bapulapadu Ginning promised in the special G.O. IDP 2015-20 and the list is (M), Krishna In this case, the company Dist appended as Annexure – II promised an investment of Rs.128.10 crores in three :: 4 ::

phases as cited in the G.O.Ms. 10 Industries & Commerce (IP) Department, Dated:31/01/2011, however, as per Statement of Accounts, the investment is Rs. 151.42 crores. Hence, the unit has fulfilled their investment as per G.O.

In this background, SVC examined the claim and recommended for sanction of Rs.3,64,58,239/- (Rupees three crores sixty four lakhs fifty eight thousand two hundred and thirty nine only) for 4th quarter of 2015-16, subject to submission of the following shortfall information: 1. Shortfalls confirmation from the GM, DIC since, shortfalls submitted by the unit holder directly. M/s.PVR SVC discussed the issue in Spinning and detail and recommended for Weaving Mills sanction of Rs.49,74,694/- (Expansion),RS (Rupees forty nine lakhs No.110/2, Cotton Reimburse- seventy four thousand six Spill over IIPP 2 108/2,3,4,, Spinning 26/05/2007 ment of hundred and ninety four only) case 2005-10 Kondaipalem Mills power cost i.e. deference amount duly road, Tetali taking upto base power village, Tanuku consumption as 697768 units (M), West per month which was revised Godavari for expansion project. M/s. Sri SVC verified the claim and Venkata Siva recommended for sanction of Parvathi Rs.25,80,122/- (Rupees Spinning twenty five lakhs eighty Reimburse- Spill over Mills(P) Ltd. Spinning IIPP thousand one hundred and 3 07/07/2008 ment of case (Expansion-II), Yarn 2005-10 twenty two only) pertaining power cost Chebrolu to deference amount for 3rd (V&M), Gutur quarter of 2015-16 including District march, 2016 reading of (EXPANSION) power bill. M/s Kallam Spinning, Reimburse SVC verified the claim and Spill over IIPP 4 Spinning Mills Weaving ment of recommended for sanction of case 2010-15 Ltd, and Power cost Rs.66,41,611/- (Rupees Sixty :: 5 ::

Kunukupadu processin six lakhs forty one thousand (V), Addanki g Six hundred and eleven only) (M), Prakasam pertaining to deference District. amount for 2nd half year of 2015-16 including march, 2016 reading of power bill. M/s Sri Anantha SVC verified the claim and Lakshmi recommended for sanction of Spinning Mills Rs.28,85,653/- (Rupees Reimburse- Spill over (P) Ltd, (Exp-1) Cotton IIPP twenty eight lakhs eighty five 5 26/06/2010 ment of case 59/1, Yarn 2005-10 thousand six hundred and power cost Boyapalem (V), fifty three only) for 4th Edlapadu (M), quarter of 2015-16 (March, Guntur District 2016 2nd reading) SVC verified the claim and recommended for sanction of Rs.68,53,690/- (Rupees sixty eight lakhs fifty three thousand six hundred and M/s. Jyotirmaye ninety only) for the 2nd half Textiles (P) year of 2015-16, subject to Ltd., Gorijavolu Reimburse submission of the following Cotton IDP 6 201 04/06/16 (V), Nadendla 18/06/2015 ment of shortfall documents / Yarn 2015-20 (M), Guntur Power cost information: District 1. Company Incorporation (EXPANSION) 2.Board resolution 3.Gram Panchayath, T&CP, and Factories Dept approved plans for expansion project. , 4.CA certificate for share holding. SVC verified the claim and recommended for sanction of Rs.42,93,794/-(Rupees forty two lakhs ninety three thousand seven hundred and ninety four only) for 2nd half M/s. Jyotirmaye year of 2015-16 including Textiles (P) Open Access units pertaining Reimburse Ltd., Gorijavolu Cotton IIPP to 1st half year of 2015-16 7 202 04/06/16 04/02/2011 ment of (V), Nadendla Yarn 2010-15 amount of Rs.30,540/-, Power cost (M), Guntur subject to submission of the District following shortfall documents / information: 1. Gram Panchayath, T&CP, and Factories Dept approved plans. 2. Land conversion certificate. 3. Civil Engineer Certificate 4. CA Certificate :: 6 ::

5. Reasons for increase for power load.

Further, SVC decided to all the power utilised in open access cases place before SLC as Agenda Item for taking a view. SVC verified the claim and recommended for sanction of Rs.1,61,71,470/- (Rupees one crore sixty one lakhs seventy thousand four hundred and sevety one only) for 2nd half year of 2015-16 including M/s. Sakku Open Access units pertaining Spinning Mills to 1st half year of 2015-16 Ltd., Reimburse amount of Rs.37,68,143, Chinakondrupa Cotton IIPP 8 203, 221 04/06/16 16/10/2011 ment of subject to submission of the du (V), Yarn 2010-15 Power cost following shortfall Prathipadu(M), documents / information: Guntur District 1. Board resolution not (EXPANSION) enclosed. 2. Grampanchayth , Factories and T&CO Dept approval 3. Land conversion certificate 4, Valed CFO from APPCB, 5. Approved project report 6. Reasons for increase power load. SVC verified the claim and recommended for sanction of Rs.62,03,000/- (Rupees sixty two lakhs three thousand M/s. Venkata only) for 2nd half year of Uma Sankar 2015-16, subject to Spintex (P) submission of the following Ltd., Reimburse Cotton IIPP shortfall documents / 9 204 04/06/16 S.No:33,35/1, 29/06/2013 ment of Yarn 2010-15 information: Vemavaram(V), Power cost 1. T&CP Factories Dept Phirangipuram( approved plan 2.Land M), Guntur conversion certificate District 3.Valied CFO from APPCB 4.Statement of Account 5. Original Bank Sanctioned Letter. M/s. Guntur SVC verified the claim and Reimburse Spinning Mills Cotton IDP recommended for sanction of 10 205 04/06/16 06/07/2015 ment of (P) Ltd., Yarn 2015-20 Rs.55,21,667/- ( Rupees fifty Power cost D.No:491, five lakhs twenty one :: 7 ::

492/2, NH-5, thousand six hundred and Obul Naidu sixty seven only) for 2nd half Palem (V), year of 2015-16 subject to Guntur District submission of the following (EXPANSION) shortfall documents / information and clarification from the Government on base power units. 1. Board resolution 2. Grampanchayath approved plan 3.Land conversion certificate 4.CE certificate 5.CA certificate for shareholding. M/s. Bhavanam Spinning Mills SVC verified the claim and Pvt. Ltd., recommended for sanction of Siripuram Road, Reimburse Rs.34,30,294/- (Rupees thirty Bhimanenivarip Cotton IIPP 11 206 04/06/16 25/03/2008 ment of four lakhs thirty thousand alem(V), Yarn 2005-10 Power cost two hundred and ninety four Medikonduru only) for 4th quarter of 2015- (M), Guntur 16. District (EXPANSION-1) SVC verified the claim and recommended for sanction of Rs.67,55,844/- (Rupees sixty seven lakhs fifty five thousand eight hundred and forty four only) for 2nd half M/s. Supriya year of 2015-16 including Spinning Mills Open Access units pertaining Pvt. Ltd., Reimburse to 1st half year of 2015-16 Cotton IIPP 12 207 04/06/16 Boyapalem(V), 22/02/2012 ment of amount of Rs.21,205, subject Spinning 2010-15 Edlapadu(M), Power cost to submission of the Guntur District following shortfall (EXPANSION) documents / information: 1. Grampanchayath , Factories and T&CP Dept approval .2 Land conversion certificate 3.Valied CFO from APPCB 4.CA certificate for share holding. M/s. Mittapalli SVC verified the claim and Spinners Ltd., recommended for sanction of Reimburse Chinaturakapale Cotton IIPP Rs.88,45,650/- (Rupees 13 208 04/06/16 29/12/2011 ment of m (V), Yarn 2010-15 eighty eight lakhs forty five Power cost Narasaraopet thousand six hundred and (M), Guntur fifty only) for 2nd half year :: 8 ::

District of 2015-16 subject to submission of the following shortfall documents / information: 1.Factories and T&CP Dept approval .2 Land conversion certificate 3.Valied CFO from APPCB 4.List of M/c as per the guidelines. SVC verified the claim and recommended for sanction of Rs.70,78,250/- (Rupees seventy lakhs seventy eight M/s.Thatavarthi thousand two hundred and Apparels Ltd fifty only) for 2nd half year (Spinning of 2015-16, subject to Reimburse Division), Cotton IIPP submission of the following 14 209 04/06/16 20/05/2011 ment of Kavuru(V), Yarn 2010-15 shortfall documents / Power cost Chilakaluripet information: (M), Guntur 1. Grampanchayath, Factories District and T&CO Dept approval . 2 Land conversion certificate 3.CE certificate 4.Approved project report 5. Original list of Plant & Machinery. SVC verified the claim and recommended for sanction of Rs.24,83,800/- ( Rupees twenty four lakhs eighty three M/s. Sri Mouli thousand and eight hundred Textiles Pvt only) for 2nd half year of Ltd., S.No: Cotton Reimburse IDP 2015-16, subject to 15 212 04/06/16 22/A, 22/B&25, Yarn 10/05/2015 ment of 2015-20 submission of the following Prathipadu open end Power cost shortfall documents / (V&M), Guntur information: District 1. Valied CFO from APPCB 2.Statement of A/c copy not attested 3.CA certification for share holding and Investment M/s. Sri SVC verified the claim and Venkateswara recommended for sanction of Spintex (P) Rs.52,58,245/- (Rupees fifty Ltd., two lakhs fifty eight thousand Reimburse D.No:20&21, Cotton IIPP two hundred and forty five 16 213 04/06/16 04/12/2011 ment of Narasaraopet Yarn 2010-15 only) for 2nd half year of Power cost Road, 2015-16, subject to Kavuru(V), submission of the following Chilakaluripet shortfall documents / (M), Guntur information: :: 9 ::

District 1.Grampanchayath plan approval 2.CFO from APPCB, 2.land conversion certificate, 4.CACertificate for share holding 5. Reason for power increate from DCP to present claim SVC verified the claim and recommended for sanction of M/s. Rs.73,99,945/- (Rupees Idupulapadu seventy three lakhs ninety Cotton Mills nine thousand nine hundred Pvt. Ltd., and forty five only) for 4th Cinima Theatre quarter of 2015-16, subject to Reimburse Road, Cotton IIPP submission of the following 17 214 04/06/16 04/12/2009 ment of Ganapavaram Yarn 2010-15 shortfall documents / Power cost (V), Nadendla information: (M), Guntur 1. Land documents 2.Board District resolution 3.Land conversion (EXPANSION- certificate 4.Grampanchayat 5) Factories, and T&CP Dept approval plan 5.C A certificate for share holding. SVC verified the claim and recommended for sanction of Rs.91,01,020/- (Rupees M/s. Sri Nukala ninety one lakhs one Rama thousand and twenty only) Koteswara Rao for 3rd quarter of 2015-16, Textiles Pvt Reimburse subject to submission of the Ltd., D.No: 1- Cotton IIPP 18 215 04/06/16 26/03/2010 ment of following shortfall 233, GBC Yarn 2005-10 Power cost documents / information: Road,Chebrolu 1. Land documents, 2, Board (V&M), resolution 3. Grampanchayat Guntur District Factories, and T&CP Dept (EXPANSION) approved plans 4.CFO from APPCB, 5. Approved project report. SVC verified the claim and recommended for sanction of M/s. Sri Rs.83,14,200/- (Rupees Venkata Siva eighty three lakhs fourteen Parvathi Reimburse thousand two hundred only) Spinning Mills Cotton IIPP 19 216 04/06/16 10/05/2012 ment of for 2nd half year of 2015-16, (P) Ltd., (Unit- Yarn 2010-15 Power cost subject to submission of the II), Cebrolu following shortfall (V&M), Guntur documents / information: District 1. Grampanchayat Factories, and T&CP Dept approved :: 10 ::

plans 2.Valied CFO from APPCB, 3.land conversion certificate 4.Statement of Account. M/s. Sri SVC verified the claim and Lakshmi recommended for sanction of Godavari Reimburse Rs.1,28,90,667/- (Rupees one Spinning Mills Cotton IIPP 20 217 04/06/16 22/03/2013 ment of crore twenty eighty lakhs Ltd., S.No:113, Yarn 2010-15 Power cost ninety thousand six hundred Chebrolu and sixty seven only) for 2nd (V&M), Guntur half year of 2015-16. District M/s. Sri Lakshmi SVC verified the claim and Godavari recommended for sanction of Spinning Mills Reimburse Rs.57,66,249/- (Rupees fifty Cotton IIPP 21 218 04/06/16 Ltd., S.No:113, 26/06/2010 ment of seven lakhs sixty six Yarn 2005-10 Chebrolu Power cost thousand two hundred and (V&M), Guntur forty nine only) for 4th District quarter of 2015-16. (EXPANSION) SVC verified the claim and M/s.Sriven recommended for sanction of Spincot (P) Reimburse Rs.4,22,450/- (Rupees four Cotton IIPP 22 219 04/06/16 Ltd., Edlapadu 09/06/2014 ment of lakhs twenty two thousand Yarn 2010-15 (V&M), Guntur Power cost four hundred and fifty only) District for 2nd half year of 2015-16 in 2nd bill in the March. M/s. Bhavanam Spinning Mills SVC verified the claim and Pvt. Ltd., recommended for sanction of Siripuram Road, Reimburse Rs.99,85,672/- (Rupees Bhimanenivarip Cotton IIPP 23 222 04/06/16 26/06/2010 ment of ninety nine lakhs eighty five alem(V), Yarn 2005-10 Power cost thousand six hundred and Medikonduru seventy two only) for 4th (M), Guntur quarter of 2015-16. District (EXPANSION-II) M/s. Balabalajee SVC verified the claim and Textiles recommended for sanction of Limited (Expn – Cotton Rs.74,77,739/- (Rupees Reimburse I), RS No. Yarn / IIPP seventy four lakhs seventy 24 229 06/06/16 27/03/2008 ment of 492/493, Synthetic 2005-10 seven thousand seven Power cost Tanuku (V), & Yarn hundred and thirty nine only) M, West for 4th quarter of 2015-16. Godavari District 25 232 06/06/16 M/s. Sri Cotton 08/08/2008 Reimburse IIPP SVC verified the claim and :: 11 ::

Srinivasa Spinning ment of 2005-10 recommended for sanction of Spintex Pvt. Power cost Rs.81,30,014/- (Rupees Ltd., KN Road, eighty one lakhs thirty Tadepalli, thousand and fourteen only) Tadepalligudem for 3rd quarter of 2015-16 (M), West including deferential amount Godavari of Rs.19,91,888/- duly District revising the base rate as Rs.2.60 instead of Rs.2.65 per month, Subject to submission of the following shortfall documents / information: 1.Grampanchayth approval 2. Land conversion certificate 3.Bank term loan sanctioned letter 4. Project report 5. CA certificate for share holding 6.T&CP approval 7. Factories Dept approved plan 8. Justification for increase of power load. SVC verified the claim and recommended for sanction of Rs.62,39,432/- (Rupees sixty M/s. two lakhs thirty nine Kalpataruvu thousand four hundred and Spinning Mills thirty two only) for 2nd half Ltd., S.No: Reimburse year of 2015-16, subject to Cotton IIPP 26 233 06/06/16 210,211/A, 01/06/2012 ment of submission of the following Yarn 2010-15 Thimmapuram Power cost shortfall documents / (V), information:: Edlapadu(M), 1.IEM part-B (Conformation Guntur District DCP) 2. T&CP , Factories Dept plan approval 3. Valid CFO from APPCB not enclosed. SVC verified the claim and recommended for sanction of M/s. Silica Rs.82,46,850/- (Rupees Ceramica Pvt Vertified eighty two lakhs forty six Ltd., D.No. 97- Ceramics IIPP thousand eight hundred and Reimburse 107, Tiles and 2005-10 fifty only) for the period of 27 240 07/06/16 11/05/2011 ment of Narayanapuram Ceramic Pipe 4th quarter of 2015-16, Power cost , Unguturu (M), Glazed Line subject to submission of the West Godavari Tiles following shortfall District information: 1. Achievement of investment criteria as per the :: 12 ::

G.O.Ms.No. 48 Industries & Commerce (IP) Department, Dated:18/06/2011. 2.Land sale deed or lease deed 3.Company incorporation 4.Project report 5. Valid CFO from APPCB 6. CA certificate for Shareholding 7.Machinery statement signed enclosing separate list 8. Factories department approved plans 9. Land conversion certificate 10. Board resolution authorizing the person to sign the claim 11. Bank sanction letter 12. Statement of Accounts with attestation. SVC verified the claim and M/s. recommended for sanction of Swarnalatha Rs.82,57,884/- (Rupees Spintex Pvt. eighty two lakhs fifty seven Ltd., Rs.No. thousand eight hundred and Reimburse 1/4, Cotton IIPP eighty four only) for 2nd half 28 246 09/06/16 12/02/2012 ment of Serinarasannapa Spinning 2010-15 year of 2015-16 including Power cost lem (V), missed claim for placing Bapulapadu before SLC in earlier meeting (M), Krishna an amount of Rs.3,93,554/- Dist pertaining to 2nd half year of 2011-12. SVC verified the claim and recommended for sanction of Rs.35,62,474/- (Rupees thirty five lakhs sixty two thousand four hundred and seventy four only) for 2nd half year of 2014-15 & 1st half year of M/s. Vasudha Allopathi 2015-16, subject to Pharma Chem c Reimburse submission of the following Ltd., Unit- III, Pharmace IIPP 29 247 09/06/16 23/03/2011 ment of shortfall Plot No. 23&24, utical 2010-15 Power cost information/documents: JNPC, Preparatio 1. Board resolution Parawada, VSP ns authorizing the person to sign the claim application. 2. IEM Part B 3. Line of activity in IEM Part B is different from GM,DIC report in his covering letter 4. CFO with attestation. 5. Valid boiler :: 13 ::

certificate 6. Statement of Accounts 7. List of Plant & Machinery as per operational guidelines.

2.SANCTION OF REIMBURSEMENT OF SALES TAX: Date of Sl. No. & Date of Name & Commence Sl. date of Line of Nature of receipt of Address of the ment of Policy Decision No. SVC activity incentives claim unit commercial Meeting production M/s. Godrej Agrovet Ltd., Crude SVC verified the claim and Unit – 2 Palm Oil, recommended for sanction of (Existing), RS. Crude Rs.85,53,175/- (Rupees No. 57, IIPP 1 225 06/06/16 Palm 09/07/2012 Sales Tax eighty five lakhs fifty three Chintampallem, 2010-15 kernel thousand one hundred and Chintalapudi Oil, Palm seventy five only) for the (M), West Nuts year 2015-16. Godavari District M/s. Godrej Agrovet Ltd., Crude SVC verified the claim and Unit - 2, (Expn- Palm Oil, recommended for sanction of 1) RS. No. 57, Crude IIPP Rs.89,35,020/- (Rupees 2 228 06/06/16 Chintampallem, Palm 15/06/2013 Sales Tax 2010-15 eighty nine lakhs thirty five Chintalapudi kernel thousand and twenty only) (M), West Oil, Palm for the year 2015-16 Godavari Nuts District SVC has examined the case in light of precedent case of M/s. Srikalahasthi Pipes Limited (SPL) (Formerly: Lanco Industries Limited) M/s. Silica where SLC has taken a view Ceramica Pvt Vertified to refer to Government on Ltd., D.No. 97- Ceramics IIPP achievement of investment 107, Tiles and 2005-10 promised in the special G.O. 3 239 07/06/16 11/05/2011 Sales Tax Narayanapuram Ceramic Pipe In this case, the company , Unguturu (M), Glazed Line promised an investment of West Godavari Tiles Rs.172.88 crores in three District phases as cited in the G.O.Ms. 48 Industries & Commerce (IP) Department, Dated:18/06/2011. As per para No.5 (a) of G.O. is as follows: :: 14 ::

50% VAT & CST/SGST reimbursement and Power Cost Reimbursement of @ Rs. 0.75 (maximum) for 5 years from the date of commissioning of II phase of the Project subject to condition that the unit should invest Rs. 100 Crores and above. Accordingly, the investment details of the unit in II Phase is as follows: (Rupees in Crores) Assets As per As per Statemen machi t of nery Accounts list & C. E. Certifi cate Building 13.06 13.06 Plant & 103.48 89.26 Machinery Total 116.54 102.32

The unit is actually invested Rs.102.32 Crores in IInd Phase i.e. the unit has fulfilled the condition stipulated in G.O. Further, the unit has totally invested an amount of Rs.190.39 Crores in three phases. The details are given below: (Rupees in crores) Ist Phase 48.74 IInd Phase 102.32 IIIrd Phase 39.33 Total 190.39

Hence, the unit is eligible for sanction of reimbursement of sales tax @50% for five years from the date of commencement of commercial production in IInd Phase i.e. from 11/05/2011. :: 15 ::

In this background, SVC examined the claim and recommended for sanction of Rs16,02,03,314/- (Rupees sixteen crores two lakhs three thousand three hundred and fourteen only) for the year 2015-16, subject to submission of the following shortfall information: 1. Land sale deed or lease deed 2.Company incorporation 3.Project report 4. Valid CFO from APPCB 5. CA certificate for Shareholding 6. Factories department approved plans 7. Land conversion certificate 8. Board resolution authorizing the person to sign the claim 9. Bank Term Loan sanction letter.

SLC may take a view. 4 STATUS NOTE ON RELEASE OF SANCTIONED INCENTIVE / CONCESSIONS OF Noted. TO THE INDUSTRIEAL UNITS UNDER IIPP 2005-10, IIPP 2010-15 & IDP 2015-20 AS ON 08/11/2016. Further, SLC has resolved that the Assiciation Members representing SLC General Budget: will submit separate representation to the Government and persue for Budget

release. Government have allocated budget of Rs.272.91 Crores for the year 2016-17 towards incentives for industrial promotion under single head of account, instead of three head of accounts issued separately for General incentives (excluding power and Pavala vaddi), Reimbursement of power cost, Reimbursement of Interest subsidy under pavalavaddi scheme.

The details of the sanctioned cases pending for releases are as detailed below:

Sanctioned as on Releases made Pending for releases 08/11/2016 Nature of Incentive No. of Amount No. of Amount No. of Amount cases Rs. in Cr cases Rs. in Cr cases Rs.in Cr General Incentives :: 16 ::

Investment subsidy 100% Reimbursement of Stamp Duty 100% Reimbursement of Mortgage Duty 25% Reimbursement of Land Cost Reimbursement of 2416 838.30 1206 272.91 1210 565.39 Power cost Reimbursement of Pavala Vaddi Quality certification Land Conversion charges Reimbursement of Sales tax

TOTAL CASES: Sanctioned as on Releases made Pending for releases 08/11/2016 Nature of Incentive No. of Amount No. of Amount No. of Amount cases Rs. in Cr cases Rs. in Cr cases Rs.in Cr State Level sanctions 2416 838.30 1206 272.91 1210 565.39 by SLC District level sanctioned 5193 217.66 0 0 5193 217.66 by DLC TOTAL 7609 1055.96 1206 272.91 6403 783.05

Net demand to clear all pending sanctioned cases = Rs. 783.05 Crores.

Double releases and triple releases are reconcilated and pending releases are under process for release the same.

:: 17 ::

5 STATUS REPORT ON THE PROPOSALS SENT TO THE GOVERNMENT AS ON:08/11/2016 SLC has discussed the issues regarding proposals pending with Date of Sl. Statues of the Government and decided to request SLC SLC Decision No issue the Government for quick disposal. Meeting 1 01/03/13 IIPP 2005-10 – M/s. Visaka Industries Limited – RS No. Government 385,386, jujjuru, Veerullapadu (M), Krishna District – Orders are Sanction of reimbursement of power cost – regarding. awaited. Further, issue The SLC has examined the issue on the following points: of reminder is G.O. Ms. No.108, Industries & Commerce (IP) under process. Department, dt.20/05/1996 pertains to Target – 2000 Scheme – New Industrial Policy 1995 and policy period is from 15.11.1995 to 31.03.2000, in which line of activity “Mangalore Tiles / Asbestos Products” is listed at Sl. No.49 in the ineligible industrial activities.

In this regard vide G.O. Ms. No.196, Industries & Commerce (IP) Department, dt.11.06.1998 an amendment was issued that words “Asbestos Products” occurring against item 49 in the list of ineligible industries annexed to G.O. Ms. No.108, Industries & Commerce (IP) Department, dt.20/05/1996 shall be deleted”. While issuing the G.O. Ms. No.178, Industries & Commerce (IP) Department, dt. 21-06-2005, the Government has not taken the order issued for amendment to the G.O. Ms. No.108, Industries & Commerce (IP) Department, dt.20/05/1996. They have taken only ineligible list annexure with the G.O.Ms.9 Industries & Commerce (IP) Department, dt. 05-01-2001. M/s. Visaka Industries Limited – RS No. 385,386, jujjuru, Veerullapadu (M), Krishna District were also processed for sanction of incentives under IIPP 2005-2010 and sanctioned in various SLCs an amount of Rs.30,18,270/- and also an amount of Rs.13,05,190/- were released pertaining to reimbursement of power cost. In view of the above circumstances, the SLC has decided :: 18 ::

to recommend the issue to the Government for making eligible for the line of activity of “Asbestos Products” and issue amendment accordingly to the G.O. Ms. No.178, Industries & Commerce (IP) Department, dt. 21/06/2005, since the same line of activity are eligible under IIPP 2010-15 schemes.

Accordingly, the proposals were recommended to the Government vide letter No. 10/3/2007/0568, dt.21/03/2013. 2. 20/05/15 IIPP 2010-15 – Sanction of Investment Subsidy – M/s. Government MNR Complex Sy.No.189/2 , Nandyal Road, Orders are Banaganapalli post and mandal, Kurnool District – awaited. sanctioned by DIPC – release of incentives – regarding Further, issue The SLC discussed the issue in detail and decided to of reminder is send the proposal of extending incentives to differently under process. able persons, to Government for the issue of appropriate orders on the operational guidelines in respect of G.O.Ms.No.188 Industries and Commerce (IP) Department dated 20.12.2013. Accordingly, the proposals were recommended to the Government vide letter No. Lr. No. 30/1/15/0288, dated 18/06/2015. 3. 20/05/15 IIPP 2005-2010 and 2010-15- claim applications revised Government for reimbursement of sales tax – clarification – regarding. Orders are The SLC discussed the issue in detail and decided to awaited. seek clarification from the Government regarding the Further, issue reimbursement of sales tax paid by the unit in the united of reminder is state of when the physical location of the under process. unit is in residual Andhra Pradesh. In view of the above Sales Tax reimbursement is sanctioned to all such units subject to outcome of Government orders. Accordingly, the proposals were recommended to the Government vide letter No. Lr. No. 30/1/14/0288/0288/ID, dated 23/05/2015 4 17/03/16 IIPP 2010-15 – Claim application for sanction of Government :: 19 :: reimbursement of power cost – M/s My Home Industries has been Ltd., unit II Mulakalapalli Village, Yelamanchi Mandal, requested to Visakhapatnam District - proposals for ascertaining the furnish “the status of Unit II as new Unit or expansion project - details of Regarding. month wise power SLC discussed the following issues in detail: consumption 1. Common Power for which Members from FAPSIA and AP Chamber of subsidy was Commerce and Industry expressed to seek a claimed and clarification from APEPDCL as why a separate meter paid to M/s was not installed instead of erecting the submeter and My Home sealing it, due to sealing of the submeter, the total Industries Ltd., units consumed by Unit-I and Unit-II are recorded in unit I the main meter. Mulakalapalli Village, 2. Common Railway Track: Yelamanchi Standing Scrutiny Committee has pointed that the raw Mandal, material unloading system through rail is common for Visakhapatna both Unit-I and Unit-II. Further, Unit-I and Unit-II m District” were using common rail loading system for Cement vide memo transportation. After detailed discussions, State Level No.1227/P&I/ Committee has taken a view that the unit should A1/2016, ensure that the premises of common railway transport Dated:08/08/2 or loading system should be notified as the public 016. property in accordance with relevant Railway Acts. for considering the proposal as separate identifiable The reply is investment. being submitted to 3. Stock transfer from sister concerned unit Government. Standing Scrutiny Committee has pointed that the main Raw material i.e., Clinker to Unit-II is through a stock transfer from its parent unit i.e., M/s My Home Industries Ltd., located in Nalgonda district, Telangana State and whereas the company was paying the Central Excise on the Clinker by the Parent unit at Nalgonda. During the discussions in the SLC meeting, :: 20 :: three views are emerged: View – I. The representatives from the Commercial Taxes Department have stated that the Stock transfer is permissible and it is common for the industries/dealers for effecting Sales Transaction across various places. Representative of FAPSIA has confirmed that it is common procedure being allowed by Sales Tax Department for effecting Sale Transaction beyond the production point across other places/States.Hence, sales tax reimbursement may be allowed on 100% sale value of cement manufactured through clinker grinding at unit – II. View – II. By considering the Transfer of clinker, a major Raw Material, from parent unit of My Home Industries Ltd., Nalgonda District, Telangana State to unit – II through sale transaction, the eligibility of Sales Tax reimbursement will net sale value of diference between cement and clinker. In the manufacturing process of cement major process is upto clinker and cement is simply the result of grinding of clinker with gypsum and other aditives as the case may be. View – III. The Sales Tax reimbursement on the cement sales at unit-II will be on 100% sale value of the cement if the clinker from parent unit of Nalgonda District, Telangana State is considered as clinker supplied on free of cost by stock transfer. Since, the proposal of the unit-II of My Home Industries Ltd is to consider it as a separate identifiable investment and in view of the financial implications, clarification from Government on stock :: 21 ::

transfer of clinker from parent unit in view of the above. 4. Machinery Bills Standing Scrutiny Committee has pointed that machinery invoices are not in the name of Unit-II and they are in the name of M/s My Home Industries Ltd., but they were showing the expenditure in the books of accounts of Unit-II as Machinery purchased. During the discussions in the SLC, the representatives from APSFC and FAPCCI have given their views that the expenditure for the machinery should be booked under new identity, Unit-II separately by having invoices of such plant and machinery only in the name of unit-II. That is, the procedure of invoices for plant & machinery in the name of main company My Home Industries Ltd and booking expenditure to unit – II will not come under the category of “Separate Books of Accounts”. 5. Statutory Approvals Standing Scrutiny Committee (SSC) has pointed that the originally approved the plan by VUDA, Factories, CFO and found that they are initially taken approvals under expansion and later modified as Unit-II. Representative of APPCB stated that the unit – I & II of My Home Industries Ltd. is running with single CFO. The SLC decided to verify the CFE and CFO obtained for both the units. 6. Remaining Items under common usage The SLC examined the remaining items of common usage pointed out by the Standing Scrutiny Committee and taken a view that they are not of major nature in view of investment made in unit – II vis-à-vis the :: 22 ::

investment in the remaining items of common usage and independent production line. Hence, the remaining items of common utilities may be exempted from the ambit of common utilities as per operational guidelines under IIPP 2010-15. Accordingly, the above issue has been place before SLC meeting held on 17/03/2016 and decision of the SLC, the issue referred to the Government with the observations of the State Level Committee vide Lr. No. 30/1/14/2105, dated 26/03/2016. 5 17/06/16 IIPP 2010 – 15 Scheme – M/s. Vasundhara Cotton Mills Government Private Limited (Expansion), S. No. 24A, Boyapalem (V), Orders are Edlapadu (M), Guntur district – Sanction of awaited. reimbursement of Power cost for their expansion Further, issue programme – Eligibility – Regarding. of reminder is under process. SLC has examined the recommendation of the verification /scrutiny committee and observed, there is a deviation in considering the expansion as per the operational guidelines i.e the increasing fixed capital investment is only 19.99% instead of at least 25%. The SLC discussed the issue in detail and decided to recommend the issue to the Government to consider the unit for sanction of incentives on the circumstances and the recommendation of the GM, DIC for considering the claim.

Accordingly, the proposals were recommended to the Government vide letter No. Lr. No.30/1/12/1146, dated:09/08/2016.

:: 23 ::

Supply. IIPP 2005-10, IIPP 2010-15 & IDP – 2015-20 schemes – Sanction of reimbursement of stamp Decission taken in Item No. 3. Item duty, reimbursement of land cost purchased in IEs/IDAs, reimbursement of power cost and No. 1 sanction of reimbursement of sales tax - Regarding. *****

The Verification / Scrutiny Committee meeting held on 15/11/2016 & 18/11/2016 has verified / Scrutinized (64) claim applications of reimbursement of power cost (11) claim application of reimbursement of Sales Tax and as per the Guidelines under respective schemes and recommended for sanction/rejection of eligible Incentives / Concessions to the units. The Minutes of Verification / Scrutiny Committee of Sales Tax and Power cost are appended as Annexure.

ABSTRACT

No of claims as Sl. No of General Incentives per Amount No units (in Rupees ) seriatim ( website) 1 Power Cost 64 54 960503760

2 Sales Tax 11 10 157297251

3 Stamp Duty 1 1 2574640

Deferred by SVC & 4 Repeated. 44 35 0

GRAND TOTAL 120 100 1120375651

112.04 Crores

The Verification / Scrutiny Committee of Investment Subsidy and Sales Tax have recommended for sanction / rejection of eligible Incentives/concessions to the units as :: 24 :: mentioned below:

1.SANCTION OF REIMBURSEMENT OF POWER COST: Date of Sl. No. of Date of Name & Commence Sl. Line of Nature of SVC receipt of Address of the ment of Policy Decision No. activity incentives Meeting claim unit commercial production SVC verified the claim and recommended for sanction of Rs.1,00,532/- (Rupees one lakh five hundred and thirty two only) for 3rd quarter of 2008-09, M/s RBA subject to submission of Textiles Pvt. the following shortfall Ltd., information: Krishnagiri Trading 1. Bank Term Loan Spill Road, Food of 06/11/200 IIPP Sanctioned letter 2) 1 1 Power over case Processing Cotton 8 2005-10 Company incorporation 3) Industrial Yarn List of Plant & Machinery Park, Kuppam as per operational (M), Chittoor guidelines 4) Dist Grampanchayath, T&CP dept approval 5) CA Certificate for share holding 6) valid CFO issued APPCB 8) Project report 9) Reasons for increasing the power SVC verified the claim and recommended for sanction of Rs.3,12,16,050/- (Rupees M/s. Smilax three crores twelve lakhs Laboratories sixteen thousand and fifty Ltd., Plot only) for the year of 2014- Spill Bulk 12/06/200 IIPP 5 4 No.70, JNPC, Power 15, subject to submission over case Drugs 9 2005-10 Parawada, of the following shortfall Visakhapatna information: m District 1. Valid CFO from APPCB.

04/06/1 M/s. Sree Cotton 10/04/200 IIPP SVC verified the claim and 3 6 Power 6 Veerabrahmen Yarn 8 2005-10 recommended for sanction :: 25 ::

ra Swamy of Rs.44,64,300/- (Rupees Spinning Mills forty four lakhs sixty four Pvt Ltd., thousand and three Lingamguntla( hundred only) for 3rd V), quarter of 2015-16, subject Chilakaluripet to submission of the (M), Guntur following shortfall District information: 1. Land conversion certificate. SVC verified the claim and recommended for sanction of Rs.21,90,638/- (Rupees twenty one lakhs ninety thousand six hundred and thirty eight only) for 1st & M/s.Y.S.R.Spi 2nd half year of 2015-16, nning subject to submission of &Weaving the following shortfall Mills Pvt. Ltd., information: D.No:5-265, 1 Land conversion Cinema hall 06/06/1 Cotton 03/10/201 IDP certificate, 2 4 7 Road,Ganapav Power 6 Yarn 1 2015-20 Grampanchayath T&CP, aram (V), Factories Dept plan Nadendla(M), approval 3. Land Guntur conversion certificate District 4.VAlied CFO from (EXPANSION APPCB 5.Statement of -III) Account not attested by GM, DIC 6. CE Certificate not furnished 7.CA certificate not furnished for investment and production particulars. M/s. Sai SVC verified the claim and Global recommended for sanction Yarntex of Rs.25,31,550/- (Rupees (India) Pvt twenty five lakhs thirty Ltd. one thousand five 06/06/1 (Expansion), Cotton 01/04/201 IIPP hundred and fifty only) 5 8 Power 6 Sy No:143/P, Yarn 1 2010-15 for 2nd half year of 2015-16, 133,103/P, subject to submission of NH-5, the following shortfall Vellampalli(V) information: , 1. IEM certificate 2. Land Maddipadu(M documents 3. :: 26 ::

), Prakasam Grampanchayath , T&CP , District Factories Dept plan approval 4. Land conversion certificate 5. Bank sanctioned letter 7. CE certificate 8. Power release certificate 9. Approved project report 10. CA certificate for investment and Last three years power particulars in original SVC verified the claim and recommended for sanction of Rs.47,28,460/- (Rupees forty seven lakhs twenty eight thousand four hundred and sixty only) for 4th quarter of 2015-16, subject to submission of the following shortfall information: 1) Meeseva receipt conformation form the GM, DIC 2) Valid CFO from APPCB, 3) Project M/s Ravali report 4) Chartered Spinners Pvt Accountant certification on Ltd. (Expn-I), 13/06/1 Cotton 01/01/200 IIPP shareholding 5) 6 14 13-194,, Power 6 Yarn 9 2005-10 Certificate of Khandavalli Incorporation 6) Board (V), Peravali resolution on (M), WG Dist authorization to sign the claim application 7) Statements of Accounts 8) IEM Part-B 9) Land Sale Deed / Lease Deed 10) Land Conversion Certificate 11) Plant & Machinery statement of the Financial Institution as per operational guidelines 12) Civil Engineer Certificate 13) Chartered Accountant Certificate for fixing the base units 14) :: 27 ::

Difference in power load w.r.t. DCP 15) Approved Plans from Gram Panchayat 16) Approved Plans from DT&CP with attestation 17)Approved Plans from Factories Department with attestation. SVC verified the claim and recommended for sanction of Rs.30,55,400/- (Rupees Thirty Lakhs fifty five thousand and four hundred only) for 2nd half year of 2015-16, subject to M/s SVR submission of the Spinning Mills following shortfall 13/06/1 Pvt Ltd., Cotton 01/01/200 IIPP 7 16 Power information: 6 Malleswaram, Yarn 9 2010-15 1. Board resolution 2. Peravali (M), Valid CFO from APPCB, WG 3.Civil Engineer certificate 4. Project report 5.CA certificate for share holding 6. Reason for increase in power load from 750KVA to 1501 KVA. SVC verified the claim and recommended for sanction of Rs.41,18,950/- (Rupees forty one lakhs eighteen M/s Ravali thousand nine hundred Spinners Ltd. and fifty only) for 2nd half (2nd expn.) year of 2015-16, subject to 13/06/1 Cotton 20/11/201 DIP 8 17 Khjandavalli , Power submission of the 6 Yarn 0 2015-20 Peravali following shortfall Mandal, WG information: District 1.DT&CP approval 2. Land conversion certificate 3. Valid CFO from APPCB 4. List of Plant & Machinery as per guidelines. M/s.Praveen SVC verified the claim and 14/06/1 Cotton 13/02/201 DIP 9 19 Spinners(India Power recommended for sanction 6 Yarn 3 2015-20 ) Pvt Ltd., Rs of Rs.52,94,590/- (Rupees :: 28 ::

No.142,147, Fifty two lakhs ninety Ravicherla, four thousand five Nuzivid hundred and ninety only) Mandal, for 2nd half year of 2015-16, Krishna subject to submission of District the following shortfall information: 1) Company incorporation 2) Land conversion 3) Valid CFO from APPCB

SVC verified the claim and recommended for sanction M/s.Tirumala of Rs.63,24,644/- (Rupees Cotton &Agro sixty three lakhs twenty Products(P) four thousand six Ltd., hundred and forty four (Spinning only) for 2nd half year of Division), 14/06/1 Cotton 05/10/201 DIP 2015-16, subject to 10 20 Thimmapura Power 6 Yarn 2 2015-20 submission of the m (V), following shortfall Edlapadu(M), information: Guntur 1.IEM Part -B 2.Town and District Country planning (EXPANSION Department approved ) plan 3.Land conversion certificate. M/s. Sree SVC verified the claim and Veerabrahmen recommended for sanction ra Swamy of Rs.49,20,040/- (Rupees Spinning Mills forty nine lakhs twenty 14/06/1 Pvt Ltd., Cotton 10/04/200 IIPP 11 22 Power thousand and forty only) 6 Lingamguntla( Yarn 8 2005-10 for 4th quarter of 2015-16, V), subject to submission of Chilakaluripet the following shortfall (M), Guntur information: District M/s. Rayani SVC verified the claim and Spintex Pvt recommended for sanction Ltd., S.No:82- of Rs.49,00,330/- (Rupees 14/06/1 1B, Cotton 16/11/201 DIP forty nine lakhs three 12 23 Power 6 Dhullipalla(V) Yarn 1 2015-20 hundred and thirty only) , for 2nd half year of 2015-16, Sattenapalli(M subject to submission of ),Guntur the following shortfall :: 29 ::

District information: 1. Grampanchayat approved plan 2. T&CP Department approved plan 3.Board resolution authorizing the person to sign 4.Reimbursement of power cost release certificate 5. CA certificate for Investment 6.CA certificate for shareholding 7.Justification for increase of Reimbursement of power cost load 8.Valid CFO from APPCB. SVC verified the claim and recommended for sanction of Rs.35,05,536/- (Rupees thirty five lakhs five thousand five hundred and thirty six only) for 2nd half year of 2015-16 after adjustment of Rs.36,87,850/- which was excess amount sanctioned M/s. Kallam earlier, subject to Brothers submission of the Cottons(P) following shortfall Ltd.,Dhulipall information: 14/06/1 a(V), Cotton 29/09/201 DIP 13 24 Power 1. Land sale deed or lease 6 Sattenapalli(M Yarn 3 2015-20 deed 2. Board resolution ), Guntur authorizing the person to District sign 3. T&CP Dept., (EXPANSION Factories Dept., ) Grampanchayat approved plans 4. Land conversion certificate 5. Reimbursement of power cost release certificate 6. Statement of Accounts 7. Reasons for increase in Reimbursement of power cost load from DCP to present claim. :: 30 ::

SVC verified the claim and recommended for sanction of Rs.38,63,321/- (Rupees thirty eight lakhs sixty M/s. Sri three thousand three Manjunatha hundred and twenty one Spinning Mills only) for 2nd half year of Ltd., 14/06/1 Cotton 14/02/201 DIP 2015-16, subject to 14 25 Thimmapura Power 6 Yarn 1 2015-20 submission of the m(V), following shortfall Edlapadu(M), information: Guntur 1.CE certificate 2.Land District conversion certificate.

SVC verified the claim and recommended for sanction of Rs.86,81,102/- (Rupees eighty six lakhs eighty one thousand one hundred and two only) for 4th quarter of 2015-16, subject to submission of M/s.Sree the following shortfall Lalitha information: Parameswari 1.Land sale deed or lease Spinning Mills deed 2.Board resolution 14/06/1 (Pvt) Ltd., Cotton 26/03/201 IIPP 15 26 Power authorizing the person to 6 Chebrolu(V Yarn 0 2005-10 sign 3.Town and &M), Guntur Country planning District approval 4. (EXPANSION Grampanchayat approved ) plan 5.Factories Department approved plan 6. Valid CFO from APPCB 7.Land conversion certificate 8. Reasons for increase of Reimbursement of power cost load M/s.Sri Naga SVC verified the claim and Malleswara recommended for sanction 14/06/1 Cotton 03/04/201 DIP 16 27 Spintex(India) Power of Rs.44,14,220/- (Rupees 6 Yarn 2 2015-20 Pvt Ltd., forty four lakhs fourteen Rajupalem(V thousand two hundred :: 31 ::

&M), Guntur and twenty only) for 2nd District half year of 2015-16, subject to submission of the following shortfall information: 1.Company incorporation certificate 2.Grampanchyat, Town& Country planning, Factories Department approved plans 3.Land conversion certificate 4.CA Certificate for shareholding of project 5.Valid CFO. SVC verified the claim and recommended for sanction of Rs.25,32,824/- (Rupees twenty five lakhs thirty two thousand eight hundred and twenty four only) for 4th quarter of 2015-16, subject to M/s. Pavan submission of the Cotton following shortfall Products Pvt information: Ltd., 1. Land sale deed or lease Pulladigunta( deed 2.Grampanchayat, 14/06/1 Cotton 23/03/200 IIPP 17 28 V), Power T&CP and Factories 6 Yarn 8 2005-10 Vatticherukur Department plan u(M), Guntur approvals 3.Land District conversion certificate 4. (EXPANSION Valid CFO from APPCB -1) 5.Copy of Approved project report 6.Plant and Machinery statement as per operational guidelines 7.Reasons for increse of Reimbursement of power cost load 8. All the documents duly attested by GM,DIC. M/s. Sree Caustic IIPP SVC verified the claim and 16/06/1 Rayalaseema Soda Lye 01/01/201 2005-10 recommended for sanction 18 30 Power 6 Alkalies and Flakes, 2 Pipelin of Rs.17,31,29,220/- allied Chlorine, e (Rupees seventeen crores :: 32 ::

Chemicals Hydron thirty one lakhs twenty Ltd., Gas HCL nine thousand two Gondiparla(V) hundred and twenty only) , Kurnool Post, for 4th quarter of 2015-16, Kurnool subject to submission of District the following shortfall information: 1. Land conversion approval 2. Project report 3. GM,DIC has not mentioned DCP and the products which are manufactured M/s. Shri Givindaraja Textiles Pvt SVC verified the claim and Ltd., 708, recommended for sanction ETC., of Rs.1,65,63,750/- (Rupees Cotton 17/06/1 Peddarangapu 01/04/200 IIPP one crore sixty five lakhs 19 32 Yarn Power 6 ram (V), 8 2005-10 sixty three thousand Spinning Pulivendula( seven hundred and fifty M), YSR only) for 4th quarter of Kadapa 2015-16. District

SVC verified the claim and recommended for sanction of Rs.2,59,36,580/- (Rupees M/s.Shri two crores fifty nine lakhs Govindaraja thirty six thousand five Textiles Pvt. hundred and eighty only) Ltd. for 2nd half year of 2015-16, (Expansion), Cotton 17/06/1 08/01/201 IIPP subject to submission of 20 33 Peddarangapu Yarn Power 6 4 2005-10 the following shortfall ram, Spinning information: Pulivendula 1. Gram panchayat Mandal, approval , 2. Land Kadapa conversion.3. Valid CFO District from APPCB, 4. Approved Project report 5. Form B not properly filed. M/s.Sudarsha SVC verified the claim and nam Spinning recommended for sanction 23/06/1 Cotton 20/08/200 IIPP 21 34 Mills, Power of Rs.45,42,640/- (Rupees 6 Yarn 8 2005-10 Tirumalagiri, forty five lakhs forty two Jaggaihpet thousand six hundred and :: 33 ::

Mandal, forty only) for 4th quarter Krishna of 2015-16. District M/s.Rajapalay SVC verified the claim and am Mills Ltd., recommended for sanction Gopinenipale of Rs.56,02,140/- (Rupees 23/06/1 Cotton 07/01/201 IIPP 22 35 m, Vatsavai Power fifty six lakhs two 6 Yarn 2 2005-10 Mandal, thousand one hundred Krishna and forty only) for 4th District quarter of 2015-16. M/s.Sri Vishnu SVC verified the claim and Shankar Mills Cotton recommended for sanction Ltd., 23/06/1 Yarn & 12/03/200 IIPP of Rs.51,05,030/- (Rupees 23 36 Gopinenipale Power 6 Synthetic 9 2005-10 fifty one lakhs five m, Vatsavai Yarn thousand and thirty only) Mandal, for 4th quarter of 2015-16. Krishna District SVC verified the claim and M/s.Sri Harini recommended for sanction Textiles Ltd., of Rs.43,19,030/- (Rupees Tirumalagiri, 23/06/1 Cotton 12/06/200 IIPP forty three lakhs nineteen 24 37 Jaggaiahpet Power 6 Yarn 8 2005-10 thousand and thirty only) Mandal, for 4th quarter of 2015-16. Krishna

District

M/s.Sandhya SVC verified the claim and Spinning Mill recommended for sanction Ltd.,, Cotton of Rs.49,26,480/- (Rupees 23/06/1 Gopinenipale Yarn & 01/05/200 IIPP 25 38 Power forty nine lakhs twenty 6 m, Vatsavai Synthetic 9 2005-10 six thousand four Mandal, Yarn hundred and eighty only) Krishna for 4th quarter of 2015-16. District SVC examined the M/s. proposal in reference to Rockworth the G.O.Ms.No.146 Systems(I) Pvt Office Industries & Commerce Ltd., 800 West 23/06/1 Modular 19/09/201 IIPP (IP & INF) Department, 26 41 Road, RI Power 6 Furnitur 1 2010-15 dated:18/11/2014 on the South Sricity, e amendment to the SEZ,Satyaved ineligible list as “All type u, Chittoor of Saw Mills, all types of District woden furniture and :: 34 ::

wood based products manufacturing units except Medium Density Fible Board (MDF) and Particle Board (PB) manufacturing units and articles made up of MDF & PB” and taken a view that the amendment to the ineligible list is applicable from the effective of the policy IIPP 2010-15.

Further, SVC has taken a view to process the eligible claims filed within the stipulated period as per operational guidelines and place before SLC as Agenda Item for sanction of reimbursement of Sales Tax & power cost. Accordingly SVC recommended for an amount of Rs 8,24,620/- for the period of 1st and 2nd half year of 2014-15 and 1st half year of 2015-16.

SVC verified the claim and M/s.Pinnae Other recommended for sanction Feeds Ltd., Animal of Rs.9,18,900/- (Rupees 24/06/1 Bogole (V & and Bird 02/07/201 IIPP 27 42 Power nine lakhs eighteen 6 M), SPSR Feed, 4 2010-15 thousand and nine Nellore Shrimp hundred only) for 2nd half District Feed year of 2015-16. SVC verified the claim and M/s. recommended for sanction Hindustan of Rs.3,69,40,000/- (Rupees National IIPP three crores sixty nine 25/06/1 Glass& Containe 28/09/201 2005-10 28 43 Power lakhs and forty thousand 6 Industries r Glass 2 Pipelin only) for 4th quarter of Ltd., APIIC e 2015-16, subject to Multiproduct submission of the Industrial following shortfall :: 35 ::

area, information: Menakur(V), 1.Company incorporation Naidupet(M), certificate SPSR Nellore 2.Grampanchyat District approvals 3. Town& Country planning/UDA approval 4. Factories Department approvals 5. Valid Boiler certificate 6.Land conversion approval 7.CA Certificate for shareholding 8.Valid CFO issued from APPCB 9.Resons for increase of power load. SVC verified the claim and recommended for sanction of Rs.6,03,95,340/- (Rupees six crores three lakhs ninety five thousand three hundred and forty only only) for 3rd quarter of 2015-16, subject to submission of the following shortfall information: 1. Certification of M/s. JSW incorporation of the Cements Ltd., company 2. Board Bilakalgudur Clinker Resolution authorising the 27/06/1 25/06/201 IIPP 29 44 (V), & Power person to sign the claim 6 2 2010-15 Gadivemula( Cement application is 3. M), Kurnool Approved plans for District expansion issued by T & C P Department .4. Land conversion approval 5. Civil Engineer Certificate for all civil works 6. Valid CFO / Acknowledgement from APPCB 7. Statement of Machinery duly certified by the Financial Institution and General Manager, DIC as per guidelines 8. Land Sale Deed / Lease Deed :: 36 ::

9. Statement of Accounts in original or attested copy .10. Approval and approved plans from the Factories Department. SVC verified the claim and recommended for sanction of Rs.45,31,980/- (Rupees forty five lakhs thirty one thousand nine hundred and eighty only) for 1st Fruit half year of 2014-15 and Juices M/s. Srini 2nd half year of 2015-16, (Packing Food park Pvt subject to submission of & Tetra Ltd., Mogili the following shortfall 29/06/1 Pack, 09/07/201 IIPP 30 45 (V),Bangarupa Power information: 6 Cold 2 2010-15 lem (M), 1. Submit the claim Storage Chittoor proposals along with bills and District and payment proof for 2nd Warehou half year of 2014-15 and 1st sing half year of 2015-16. If not submitted the claims by the unit, submit a detailed report on reasons not filing and any break-in- production in that period. SVC verified the claim and recommended for sanction of Rs.16,69,950/- (Rupees sixteen lakhs sixty nine thousand nine hundred M/s RBA and fifvy only) for 2nd half Textiles Pvt year of 2015-16, subject to Ltd submission of the (Expansion), Trading following shortfall Krishnagiri 02/07/1 of 25/12/201 IIPP information: 31 48 Road, Food Power 6 Cotton 0 2010-15 1. Land sale deed 2) Processing Yarn Company incorporation 3) Industrial Board resolution Park, Kuppam authorizing sing 4) (M), Chittoor Grampanchayath, T&CP Dist dept approval 5) Land converion approval 6) valied CFO issued APPCB 8) Project report 9) CA certificate 10) reasons for :: 37 ::

increasing the power M/s Sri Ravichandra SVC verified the claim and Textiles Pvt recommended for sanction Ltd., Cotton of Rs.34,08,620/- (Rupees 13/07/1 05/11/201 IIPP 32 53 Ponnnekallu Yarn Power thirty four lakhs eight 6 2 2010-15 (V), open end thousand six hundred and Tadikonda twenty only) for 2nd half Mandal, year of 2015-16. guntur Dist SVC verified the claim and recommended for sanction of Rs.99,33,500/- (Rupees M/s Sri Sai ninety nine lakhs thirty Balajee three thousand and five Spintex (India hundred only) for 2nd half 13/07/1 Cotton 14/04/201 IIPP 33 54 ) Pvt Ltd., Power year of 2015-16, subject to 6 Yarn 1 2010-15 Unnava (V), submission of the Edlapadu (M), following shortfall Guntur Dist information: 1. T&CP, Factories Dept approval 2. Valid CFO from APPCB. SVC verified the claim and recommended for sanction M/s Kallam of Rs.1,23,14,924/- (Rupees Spinning Mills Cotton one crore twenty three Limited, Spinning lakhs fourteen thousand Weaving Unit, , 13/07/1 01/09/201 IDP nine hundred and twenty 34 56 Sy.No. 197, Weaving Power 6 4 2015-20 four only) for 2nd half year Kunukupadu and of 2014-15 including (V), Addanki Processi deference amount of Mandal, ng Rs.47,92,330/- pertaining Prakasam Dist to 1st half year of 2015-16.

SVC verified the claim and M/s Sri recommended for sanction Lakshmi of Rs.62,32,040/- (Rupees Narasimha sixty two lakhs thirty two Spinning Mills thousand and forty only) 15/07/1 (India) Pvt Cotton 05/07/200 IIPP 35 58 Power for 4th quarter of 2015-16, 6 Ltd., Yarn 8 2005-10 subject to submission of Uppalavaripal the following shortfall em, Addanki information: Mandal, 1. T&CP Department Prakasam Dist approved plans 2. :: 38 ::

Grampanchayat approved plan 3. Land conversion certificate 4. Valid CFO from APPCB 5.Justification for Additional power required 6. Meeseva receipt confirmation from GM, DIC. SVC verified the claim and recommended for sanction of Rs.32,99,250/- (Rupees thirty two lakhs ninety nine thousand two Portland hundred and fifty only) Cement, for 4th quarter of 2015-16, M/s The KCP Alumino subject to submission of Limited (KCP us the following shortfall Cements) Cement, IIPP information: Unit-II, 18/07/1 Slag 29/10/201 2005-10 1.Company incorporation 36 59 Mukthyala Power 6 Cement 1 Pipelin certificate 2. Board (V), and e resolution authorizing the Jaggaiahpet Similar person to sign the claim (M), Krishna Hydrauli application 3. Dist c DT&CP/VUDA approval Cements 4. Valid CFO from APPCB 5.Project report 6. CA certificate for Shareholding 7.Valid Boiler certificate 8. Land conversion certificate. SVC verified the claim and recommended for sanction of Rs.64,94,470/- (Rupees M/s Sri sixty four lakhs ninety Vaishnavi four thousand four Spintex hundred and seventy (India) Pvt only) for 2nd half year of 18/07/1 Cotton 18/03/201 IDP 37 61 Ltd., Power 2015-16 including 6 Yarn 2 2015-20 Kolanapalli , deference amount of Kalla (M), Rs.11,69,170/- pertaining West to 1st half year of 2015-16, Godavari Dist subject to submission of the following shortfall information: 1.Company incorporation :: 39 ::

certificate 2. DT&CP approval 3. Land conversion 4. Valid CFO from APPCB 5. Machinery statement as per operational guidelines. M/s Idupulapadu SVC verified the claim and Cotton Mills recommended for sanction Pvt Ltd., of Rs.37,61,328/- (Rupees Expansion-5, thirty seven lakhs sixty 21/07/1 Cotton 09/08/201 IIPP 38 62 Cinema Power one thousand three 6 Yarn 1 2005-10 Theatre Road, hundred and twenty eight Ganapavaram, only) for 1st quarter of Nadendla 2015-16. Mandal, Guntur Dist SVC verified the claim and recommended for sanction M/s Avanthi of Rs.35,92,000/- (Rupees Feeds Ltd., thirty five lakhs and (Expansion) ninety two thousand 22/07/1 Sy.No. 746/3A Shrimp 07/04/201 IIPP 39 64 Power only) for 2nd half year of 6 & 544, Feed 4 2010-15 2015-16, subject to Kovvuru submission of the (V&M), WG following shortfall Dist information: 1. Valid CFO from APPCB. SVC verified the claim and recommended for sanction of Rs.32,92,530/- (Rupees M/s Vasanth thirty two lakhs ninety Chemicals Pvt two thousand five Ltd., Plot No. hundred and thirty only) Specialit 10 & 10A, for 2nd half year of 2013-14 y Western to 1st half year of 2015-16, 29/07/1 Chemica 27/12/201 IIPP 40 67 Sector, Power subject to submission of 6 ls and 2 2010-15 APSEZ, the following shortfall Pharmac Achyuthapura information: euticals m Mandal, 1) Approval from Factories Visakhapatna Department, 2) Approval m from Boiler Department, 3) Statement of Accounts, 4) C.A. Certificate of shareholding. :: 40 ::

SVC discussed and recommended for sanction of Rs.3,80,430/- (Rupees three lakhs eighty thousand four hundred M/s SNF and thirty only) for 2nd India Pvt Ltd., half year of 2015-16, Liquids, Plot No. 19, subject to submission of 06/08/1 Emulsio 09/11/201 IIPP 41 69 JNPC, Power the following shortfall 6 ns & 0 2010-15 Parawada, information: Powers Visakhapatna 1. List of Plant and m Machinery duly certified by as per guidelines 2.Project report 3. Power release certificate 4. Valid CFO 5. Term Loan sanction letter. SVC verified the claim and recommended for sanction of Rs.11,96,950/- (Rupees eleven lakhs ninety six M/s Rocks thousand nine hundred Forever Inc., Granite and fifty only) for 3rd Plot No. 1&2, Marbles 08/08/1 22/07/201 IIPP quarter of 2015-16, subject 42 70 Annangi (V), & Power 6 2 2010-15 to submission of the Maddipadu Natural following shortfall (M), Prakasam Stones information: Dist 1.Factories Department approval 2.Valid CFO certificate 3.Approved project report. SVC verified the claim and recommended for sanction of Rs.82,02,198/- (Rupees M/s Kolar eighty two lakhs two Paper Mills thousand one hundred Ltd., Sy.No. and ninety eight only) for 104, 105 and 28/08/1 Packagin 21/05/201 IDP 1st & 2nd half year of 2015- 43 74 106, Power 6 g Paper 5 2015-20 16, subject to submission Parameswara of the following shortfall mangalam (V), information: Puthur (M), 1. DT & CT Approved Chittoor Dist plans.

44 77 01/09/1 M/s Internal 03/08/201 Power IIPP SVC verified the claim and :: 41 ::

6 Makrocast Pvt Combsti 0 2010-15 recommended for sanction Ltd on Piston of Rs.37,75,914/- (Rupees (Expansion) , Engines thirty seven lakhs seventy RS No. and five thousand nine 612/2AB, ZP other hundred and fourteen Road, parts only) for 1st & 2nd half year Kolavennu and of 2013-14. (V), Accessor Kankipadu ies (M), Krishna N.E.C. Dist for Motor Vehicles SVC verified the claim and recommended for sanction of Rs.49,13,890/- (Rupees forty nine lakhs thirteen thousand eight hundred and ninety only) for 1st quarter of 2016-17, subject to submission of the following shortfall information: 1) Meeseva Receipt conformation form the GM, DIC 2) Valid CFO M/s Ravali from APPCB, 3) Project Spinners Pvt report 4) Chartered Ltd., ( Accountant certification on 06/09/1 Expansion -I), Cotton 01/01/200 IIPP 45 79 Power shareholding 5) 6 RS No. 13-194, Yarn 9 2005-10 Certificate of Khandavalli Incorporation 6) Board (V), Peravali resolution on (M), WG Dist authorization to sign the claim application 7) Statements of Accounts 8) IEM Part-B 9) Land Sale Deed / Lease Deed 10) Land Conversion Certificate 11) Plant & Machinery statement of the Financial Institution as per operational guidelines 12) Civil Engineer Certificate 13) Chartered Accountant Certificate for :: 42 ::

fixing the base units 14) Difference in power load w.r.t. DCP 15) Approved Plans from Gram Panchayat 16) Approved Plans from DT&CP with attestation 17)Approved Plans from Factories Department with attestation. M/s Vantage SVC verified the claim and Spinners Pvt Spinnin recommended for sanction Ltd., g of Rs.2,29,62,310/- (Rupees (Original), (Cotton 07/09/1 12/02/201 IIPP two crores twenty nine 46 80 Gollapalli (V), Yarn / Power 6 0 2005-10 lakhs sixty two thousand Nuzivud all other three hundred and ten Mandal, Fibre only) for 3rd & 4th Krishna Yarns) quarters of 2015-16. District SVC verified the claim and M/s Vantage recommended for sanction Spinners Pvt Spinnin of Rs.40,58,424/- (Rupees Ltd., g forty lakhs fifty eight (Expansion), (Cotton thousand four hundred 07/09/1 22/10/201 IDP 47 81 Gollapalli (V), Yarn / Power and twenty four only) for 6 5 2015-20 Nuzivud all other 2nd half year of 2015-16, Mandal, Fibre subject to submission of Krishna Yarns) the following shortfall District information: 1. Valid CFO from APPCB. SVC verified the claim and recommended for sanction of Rs.49,86,710/- (Rupees forty nine lakhs eighty six M/s Gajavalli thousand seven hundred Spinning Mills and ten only) for 2nd Cotton (P) Ltd., quarter of 2014-15, subject Yarn & 20/09/1 Narakoduru- 21/04/200 IIPP to submission of the 48 87 other Power 6 Tenali road, 8 2005-10 following shortfall Synthetic Chebrole (V) information: Yarns & (M), guntur 1)Valid CFO from APPCB Dist 2)Land Conversion certificate 3)Grampanchayat, factories and T&CP Department approved :: 43 ::

Plans 4)CA Certificate for Shareholdings.

SVC verified the claim and recommended for sanction of Rs.53,74,570/- (Rupees fifty three lakhs seventy four thousand five hundred and seventy only) for 1st quarter of 2015-16, subject to submission of the M/s Emami following shortfall Biotech information: Limited, Sy. 1.Physical submission of No. 501 to 510, claim at DIC is not Krishnapatna available for the claims m Port, Zero Vegetabl IIPP 2.IEM Part-B unattested 23/09/1 Point, e Oils & 19/02/201 2005-10 49 89 Power 3.Land sale deed or lease 6 Pantapalem Fats 2 Pipelin deed 4.Grampanchayat (V), Muthukur Refining e approval 5.Factories M), SPSR department approval Nellore 6.Valid Boiler certificate District (1st 7.Machinery list as per quarter of operational guidelines 2015-16) 8.Project report 9.Town andcountry planning Department approval. 10. Board resolution 11. Certificate of incorporation 12. Land convertion certificate 13.C.A. Certificate for shareholding. SVC verified the claim and M/s. recommended for sanction Mandava of Rs.35,53,030/- (Rupees Cotton Mills thirty five lakhs fifty Pvt Ltd., 27/09/1 Cotton 01/03/200 IIPP three thousand and thirty 50 93 Ampapuram Power 6 Spinning 8 2005-10 only) for 4th quarter of (V), 2015-16, subject to Bapulapadu submission of the (M), Krishna following shortfall District information: :: 44 ::

1. Valid CFO from APPCB 2.Bank sanction letter 3.Project report 4. Reasons for increase of KVA from 200 to 1650 KVA and clarify on connected load, 5. CA certificate for share holding. SVC verified the claim and recommended for sanction of Rs.3,26,311/- (Rupees three lakhs twenty six thousand three hundred and eleven only) for M/s.Patchala balance 10 days in 4th Spintex Pvt quarter of 2015-16, subject Ltd., to submission of the Rajupalem following shortfall 28/09/1 (V&M), Cotton 13/04/201 IIPP 51 94 Power information: 6 Sattenapalli to Yarn 2 2005-10 1)Board resolution Piduguralla authorizing the person to High-Way, sign 2)Town & Country Guntur Planning approved Plan District 3) Grampanchayat, Factories Department approved Plans 4)Land Conversion Certificate 5) Statement of Accounts 6) Approved Project report. SVC verified the claim and recommended for sanction of Rs.5,25,059/- (Rupees five lakhs twenty five M/s.Patchala thousand and fifty nine Spintex(P)Ltd. only) for balance 10 days , in 4th quarter of 2015-16, 28/09/1 (EXPANSION Cotton 01/05/201 IDP subject to submission of 52 95 Power 6 ), Yarn 5 2015-20 the following shortfall Rajupalem(V& information: M), Guntur 1.Board resolution District authorizing the person to sign 2.Grampanchyat approval 3.Grampanchyat, Town& Country planning, :: 45 ::

Factories Department approved plans 4.Land conversion certificate 5.Plant and Machinery list as per operational guidelines.

SVC verified the claim and recommended for sanction of Rs.33,92,700/- (Rupees M/s.Sudha thirty three lakhs ninety Agro Oils & two thousand and seven Chemical hundred only only) for 2nd Industries half year of 2015-16, Ltd., subject to submission of Cotton IIPP 01/10/1 (Spinning 29/09/201 the following shortfall 53 98 spinning Power 2010/1 6 Division), 1 information: in Mill 5 Valuthimmap 1. Land documents 2. uram(V), Board resolution Peddapuram( 3.Machinery statement as M), East per guideline 4. T&CP Goadavari approved plan 5. Valid CFO from APPCB 6.CE certificate 7.Power release certificate. SVC verified the claim and recommended for sanction of Rs.1,56,61,140/- (Rupees one crore fifty six lakhs sixty one thousand one hundred and forty only) M/s. NSL for 4th quarter of 2015-16, Textiles Ltd., subject to submission of Plot No:4, the following shortfall 05/10/1 Cotton 31/03/201 IIPP 54 100 APIIC Park, Power information: 6 Spinning 0 2005-10 Pulivendula(V 1.Reasons for increase in &M), YSR Reimbursement of power Kadapa cost load with respect initial filing of claim application 2. Reimbursement of power cost 2000 KVA released on 11.03.2010 and 1000 KVA released on 07/07/2010 :: 46 ::

and the same is not reflected in Part-B self declaration 3. Approval of Change of Name of the unit 4. Bank term loan sanctioned letter 5. Board resolution to authorizing the person to sign 6. DTCP approval 6. Valid CFO from APPCB. ** The above short fall information has been submitted by the unit holder without attestation of Concerned DIC. SVC verified the claim and recommended for sanction of Rs.1,52,30,370/- (Rupees M/s.Teamec one crore fifty two lakhs Chlorates Ltd., thirty thousand three Plot No:558 hundred and seventy &559, Sodium only) for 2nd half year of Industrial Chloride 2015-16, subject to 06/10/1 Growth 21/02/201 IIPP 55 101 & Power submission of the 6 Centre, 2 2010-15 Hydroge following shortfall Gundlapalli n information: (V), 1. Valid CFO from APPCB, Maddipadu(M 2. Justification whether ), Prakasam new unit or expansion as District per IEM, 3. Certification on Plant and Mahcinery as per Operation Guidelines. SVC verified the claim and recommended for sanction of Rs.6,40,483/- (Rupees M/s. rupees six lakhs forty Ranganayaka thousand four hundred Spinning Mills and eighty three only) for 07/10/1 (P) Ltd., Cotton 10/04/200 IIPP 10days in 4th quarter of 56 103 Power 6 Boyapalem(V), Yarn 8 2005-10 2015-16, subject to Edlapadu(M), submission of the Guntur following shortfall District information: 1. Boad resolution authorizing the person to sign, 2. Grampachayat :: 47 ::

approval, 3. Land conversion, 4. Valid CFO, 5. Term Loan sanction letter, 6. Approved project report, 7. CA certificate for shareholding. SVC verified the claim and recommended for sanction of Rs.5,72,229/- (Rupees five lakhs seventy two thousand two hundred M/s. and twenty nine only) for Ranganayaka 10days in 4th quarter of Spinning 2015-16, subject to Mills(P) Ltd., submission of the 07/10/1 Cotton 09/04/201 IIPP 57 104 (EXPANSION Power following shortfall 6 Yarn 0 2005-10 )Boyapalem(V information: ),Edlapadu(M) 1. Grampanchayat, T&CP , Guntur and Factories plan District approval, 2. Land conversion, 3. Valid CFO., 4. CE certificate, 5. Approved project report, 6. CA certificate for shareholding. SVC verified the claim and recommended for sanction of Rs.41,68,766/- (Rupees forty one lakhs sixty eight thousand seven hundred and sixty six only) for M/s 10days in 4th quarter of Idupulapadu 2015-16, subject to Cotton Mils submission of the 07/10/1 Cotton 09/08/201 IIPP 58 105 Pvt Ltd , Power following shortfall 6 Yarn 1 2005-10 Jonnatali (V), information: Martur (M), 1. Grampanchayat, T&CP Prakasam Dist and Factories plan approval, 2. Land conversion, 3. Valid CFO., 4. CE certificate, 5. Approved project report, 6. CA certificate for shareholding. 15/10/1 M/s Sree Caustic 01/01/201 IIPP SVC verified the claim and 59 107 Power 6 Rayalaseema Soda Lye 2 2005-10 recommended for sanction :: 48 ::

Alkalies and Flakes, Pipelin of Rs.16,08,17,521/- Allied Chlorine, e (Rupees sixteen crores Chemicals Hydron eight lakhs seventeen Ltd., Gas HCL thousand five hundred Gondiparla and twenty one only) for (V), Kurnool 1st quarter of 2016-17, District subject to submission of the following shortfall information: 1. Land conversion approval 2. Project report 3. GM,DIC has not mentioned DCP and the products which are manufactured

SVC verified the claim and recommended for sanction of Rs.42,03,940/- (Rupees M/s Samyu forty two lakhs three Glass Pvt Ltd., thousand nine hundred Plot No. 11, and forty only) for 3rd 2nd IDP, Glass & half year of 2015-16, 31/10/1 28/02/201 IIPP 60 110 Gundlamadug Glass Power subject to submission of 6 1 2010-15 u (V), Products the following shortfall Thonduru information: (M), YSR 1.Board resolution to Kadapa Dist authorizing the person to sign 2. Company incorporation 3. Valid CFO from APPCB SVC verified the claim and recommended for sanction Polished of Rs.16,38,660/- (Rupees Granites sixteen lakhs thirty eight M/s Krishna / thousand six hundred and Sai Exports, Marbles sixty only) for 1st & 2nd 03/11/1 16/03/201 IIPP 61 117 Maddepadu, Slabs Power half year of 2015-16, 6 1 2010-15 Prakasam Tiles, subject to submission of District Mounme the following shortfall nt & information: Articles 1. Valid CFO, 2. Approved Project Report, 3. CA Certificate for share :: 49 ::

holding, 4. Reasons for increase of power load. SVC verified the claim and recommended for sanction of Rs.86,05,462/- (Rupees eighty six lakshs five thousand four hundred and sixty two only) for 2nd half year of 2012-13 to 2nd M/s Tulip Granite half year of of 2015-16, Granites, Cutting 03/11/1 13/08/201 IIPP subject to submission of 62 118 BPSEZ, IBP, & Power 6 0 2010-15 the following shortfall Prakasam Polishin information: District g 1. Boar resolution, 2. Approved Project Report, 3. CA Certificate on project investment, 4. List of Plant & Machinery as per operational guidelines, 5. Power release certificate. SVC verified the claim and recommended for sanction of Rs.10,47,840/- (Rupees ten lakhs forty seven thousand eight hundred Granite M/s Hues and forty only) for 2nd half Cutting 03/11/1 Granites, 27/10/201 IIPP year of 2014-15 & 1st half 63 119 & Power 6 BPSEZ, IBP, 4 2010-15 year of 2015-16, subject to Polishin Prakasam, submission of the g following shortfall information: 1. Approved plans from Factories Department & DT&CP. Activate d M/s.Kanoria Natural SVC verified the claim and Chemicals & Mineral recommended for sanction Industries Ltd, Products of Rs.68,96,530/- (Rupees Plot No:32, 03/11/1 , Animal 06/01/201 IIPP sixty eight lakhs ninety 64 121 JNPC, Power 6 Black, 1 2010-15 six thousand five hundred Parawada Animal and thirty only) for 1st half Mandal, or year of 2014-15 to 1st half Visakhapatna Vegetabl year of 2015-16. m e Fats and Oils :: 50 ::

2.SANCTION OF REIMBURSEMENT OF SALES TAX: Date of Sl. No. & Date of Name & Commence Sl. date of Line of Nature of receipt of Address of the ment of Policy Decision No. SVC activity incentives claim unit commercial Meeting production SVC verified the claim and recommended for sanction of Rs.37,11,298/- (Rupees thirty seven lakhs eleven M/s Girnar thousand two hundred Packaging, and ninety eight only) for Plot No.11,12 the year of 2014-15, subject and 13, Indl. Spill Corrugat 16/05/201 IIPP to submission of the 1 3 Park, Sales Tax over case ed Boxes 3 2010-15 following shortfall Menakur(V), information: Naidupet(M), 1.Board resolution SPSR Nellore authorizing the person to District sign 2. Company incorporation 3. Valid Boiler certificate 4.Valid CFO from APPCB. SVC verified the claim and recommended for sanction of Rs.58,82,541/- (Rupees fifty eight lakhs eighty two thousand five hundred and forty one only) for the year 2012-13 M/s.NSL & 2013-14 including Textiles Ltd., deference amount of Rs. Veeravalli, 5,15,246/- which was Spill Cotton 01/01/200 IIPP 2 5 Bapulapadu Sales Tax earlier not sanctioned over case Yarn 9 2005-10 Mandal, additional 25% VAT in Krishna 2009-10, subject to District submission of the following shortfall information / documents: 1.Land sale deed or lease deed 2.DTCP Approved plans 3.Land conversion approval 4.Valid CFO from APPCB 5.Plant and :: 51 ::

Machinery statement duly certified by the Banker 6.Project report 7.CA certificate for shareholding 8.As per power bills, power was increased from October, 2009. Submit a report whether additional machinery acquired by the unit or reasons for increasing the power 9.Attested copy of Statement of Accounts. SVC discussed the proposal and taken a view to consider the sales tax incentives as per special G.O.Rt.684 Industries & Commerce (IP) Department, dated:27/06/2006 for a period of 5 years from DCP & remaining 3 years as per policy i.e @ 25%.

M/s.NSL Further, SVC decided to Textiles Ltd., seek the clarification on RS No.237, implementation of the 15/06/1 Veeravalli, Cotton 01/01/200 IIPP above special G.O., since 3 29 Sales Tax 6 Bapulapadu Yarn 9 2005-10 the policy period extended Mandal, another three years as per Krishna G.O.Ms.No.42 Industries District & Commerce (IP) Department, dated: 05/05/2011.

In view of the above, after examining the proposal, SVC has recommended Rs.50,62,613/- (Rupees fifty lakhs sixty two thousand six hundred and thirteen only) for the year 2014-15, subject to submission of the :: 52 ::

following shortfall information / documents: 1.Land sale deed or lease deed 2.DTCP Approved plans 3.Land conversion approval 4.Valid CFO from APPCB 5.Plant and Machinery statement duly certified by the Banker 6.Project report 7.CA certificate for shareholding 8.As per power bills, power was increased from October, 2009. Submit a report whether additional machinery acquired by the unit or reasons for increasing the power 9.Attested copy of Statement of Accounts.

SVC verified the claim and recommended for sanction of Rs.16,08,850/- (Rupees sixteen lakhs eight thousand eight hundred M/s. JC and fifty only) for the year Biotech Pvt 2015-16, subject to Ltd., IGC submission of the Bio 23/06/1 Gundlapalli 25/05/201 IIPP following shortfall 4 39 Pharmac Sales tax 6 (V), 1 2010-15 information: euites Maddipadu 1) Land Conversion (M), Prakasam Certificate 2) Valid CFO District from APPCB 3) Approved Plans from Factories Department 4) Plant & Machinery Statement from Financial Institution as per guidelines M/s. SVC examined the Office Rockworth proposal in reference to 23/06/1 Modular 19/09/201 IIPP 5 40 Systems(I) Pvt Sales tax the G.O.Ms.No.146 6 Furnitur 1 2010-15 Ltd., 800 West Industries & Commerce e Road, RI (IP & INF) Department, :: 53 ::

South Sricity, dated:18/11/2014 on the SEZ, amendment to the Satyavedu, ineligible list as “All type Chittoor of Saw Mills, all types of District woden furniture and wood based products manufacturing units except Medium Density Fible Board (MDF) and Particle Board (PB) manufacturing units and articles made up of MDF & PB” and taken a view that the amendment to the ineligible list is applicable from the effective of the policy IIPP 2010-15.

Further, SVC has taken a view to process the eligible claims filed within the stipulated period as per operational guidelines and place before SLC as Agenda Item for sanction of reimbursement of Sales Tax & power cost.

Accordingly SVC recommended for an amount of Rs 41,44,027/- for the period 2014-15 SVC verified the claim and Portland recommended for sanction Cement, of Rs.10,59,98,090/- M/s The KCP Alumino (Rupees ten crores fifty Limited (KCP us nine lakhs ninety eight Cements) Cement, IIPP thousand and ninety Unit-II, 18/07/1 Slag 29/10/201 2005-10 only) for the year 2015-16, 6 60 Mukthyala Sales Tax 6 Cement 1 Pipelin subject to submission of (V), and e the following shortfall Jaggaiahpet Similar information: (M), Krishna Hydrauli 1.Company incorporation Dist c certificate 2. Board Cements resolution authorizing the person to sign the claim :: 54 ::

application 3. DT&CP/VUDA approval 4. Valid CFO from APPCB 5.Project report 6. CA certificate for Shareholding 7.Valid Boiler certificate 8. Land conversion certificate. SVC verified the claim and recommended for sanction of Rs.49,93,870/- (Rupees forty nine lakhs ninety M/s Vennar three thousand eight Chemicals hundred and seventy Ltd., Ceramic only) for the year 2015-16, 26/07/1 Parikigudem 01/07/201 IIPP 7 65 Glazed Sales Tax subject to submission of 6 (V), 2 2010-15 Tiles the following shortfall Mandavalli information: (M), Krishna 1.Board resolution Dist authorizing the person to sign 2. Project report 3. CA certificate for Shareholding. SVC verified the claim and recommended for sanction of Rs.96,89,678/- (Rupees ninety six lakhs eighty nine thousand six hundred and seventy M/s SNF eight only) for the year India Pvt Ltd., Liquids, 2015-16, subject to Plot No. 19, 06/08/1 Emulsio 09/11/201 IIPP submission of the 8 68 JNPC, Sales Tax 6 ns & 0 2010-15 following shortfall Parawada, Powers information: Visakhapatna 1. List of Plant and m Machinery duly certified by as per guidelines 2.Project report 3. Power release certificate 4. Valid CFO 5. Term Loan sanction letter. M/s Paramesu SVC verified the claim and Biotech Pvt recommended for sanction 30/08/1 Maize 05/01/201 IIPP 9 75 Ltd., 972, Sales Tax of Rs.32,97,165/- (Rupees 6 Starch 5 2010-15 Devarapalli thirty two lakhs ninety (V&M), WG seven thousand one :: 55 ::

Dist hundred and sixty five only) for the year 2015-16, subject to submission of the following shortfall information: 1 Project re-port 2 IEM part-B 3. Gramapanchayath, Factories Dept and T&CP approved plans 4.Power release certificate. M/s. Shri Govindaraja Textiles Pvt SVC verified the claim and Ltd., Opp recommended for sanction JNTU Engg. of Rs.3,40,930/- (Rupees Cotton 24/09/1 College, 01/04/200 IIPP three lakhs forty 10 90 Yarn Sales Tax 6 Peddarangapu 8 2005-10 thousand nine hundred Spinning ram (V), and thirty only) for the Pulivendula year 2015-16. (M), YSR Kadapa District Activate d M/s.Kanoria Natural SVC verified the claim and Chemicals & Mineral recommended for sanction Industries Ltd, Products of Rs.1,25,68,189/- (Rupees Plot No:32, 19/10/1 , Animal 06/01/201 IIPP one crore twenty five 11 108 JNPC , Sales Tax 6 Black, 1 2010-15 lakhs sixty eight thousand Parawada Animal one hundred and eighty Mandal, or nine only) for the year Visakhapatna Vegetabl 2013-14 & 2014-15. m e Fats and Oils

1.SANCTION OF REIMBURSEMENT OF STAMP DUTY:

Date of Sl. No. Sl. Date of Name & Commence & date Line of Nature of N receipt of Address of the ment of Policy Decision of SVC activity incentives o. claim unit commercial Meeting production 03/11/1 M/s Sai Cotton Stamp IIPP SVC discussed and noted 1 114 14/01/2011 6 Manasa Yarn Duty 2010- that the the GM, DIC :: 56 ::

Spintex, 15 certified the plinth area / Martur (M) built up area as 6782 M2 Prakasam and the same was District reflected in DIPC Minutes which was approved. Hence, SVC recommended for sanction of Rs.25,74,640/- (Rupees twenty five lakhs seventy four thousand six hundred and forty only), subject to submission of DT & CP approved plans.

Supply. IIPP 2010 – 2015 Scheme – M/s. Rayani Spintex (P) Limited, Dhuulipalla (V), Sattenapalli SLC discussed the issue in detail and Item (M), Guntur district – Permission for change of Financial Institution of the unit – Regarding. decided to accord permission for No. 2 change of Financial Institutaion from M/s. Rayani Spintex (P) Limited, Dhuulipalla (V), Sattenapalli (M), Guntur district UCO Bank Limited, Arundalpet, has obtained IEM bearing No. 3983/IIM/Prod/2012, dated 17/04/2012 with line of activity Guntur to City Union Bank Ltd., “Cotton Yarn” and commencement of commercial production on 16/11/2011. The Financial Main Branch, Guntur. Institution i.e., UCO Bank Limited, Arundalpet, Guntur has financed the unit.

Further, the General Manager, District Industries Centre, Guntur has informed that M/s. Rayani Spintex (P) Limited, Dhuulipalla (V), Sattenapalli (M), Guntur district has submitted proposal for approval of change of Bank from UCO Bank Limited, Arundalpet, Guntur to City Union Bank Ltd., Main Branch, Guntur and submitted the following documents:

1. NOC from BM, UCO Bank Ltd., Arundalpet, Guntur. 2. Letter from BM, City Union Bank Ltd., Main Branch, Guntur.

In this regard, the General Manager, District Industries Centre, Guntur has requested to consideration of the proposal for change of Financial Institution i.e., , UCO Bank Ltd., Arundalpet, Guntur to City Union Bank Ltd., Main Branch, Guntur of M/s. Rayani Spintex (P) Limited, Dhuulipalla (V), Sattenapalli (M), Guntur district.

:: 57 ::

As per Para 11.0 of guidelines of IIPP 2005 – 10 “The Industrial units that availed incentives/concessions should obtain the No Objection Certificate from the concerned financing institutions in respect of aided units before seeking the approval of Commissioner of Industries for any change of the constitution/Management/name & style of the unit within the first six (6) years from the date of commencement of Commercial production”.

The SLC may take a view.

Supply. Incentives / Concessions Under IIPP 2005-10 & 2010-15 Schemes – reimbursement of power SLC examined the issue. The Item cost to M/s Spin Cot Textiles Pvt Ltd., - revival of the unit – issue of Government orders vide Chairman of SLC requested the No. 3 G.O.Ms.No.388 Industries & Commerce (P&I) Department dated 28.08.2015 - Release of members to give their views on this sanctioned amount to the industrial unit from the amount available in PD Account of issue. The representative of FAPSIA Commissioner of Industries.– Regarding. opined that the unit has to be inspected along with other member of the M/s Spin Cot Textiles Pvt Ltd.,19th Kilometer NH 5 , Marripalem Village, Edlapadu Mandal, Association. The representatives of the Guntur District is a Private Limited Company established with an investment of Rs. 59 Cr for Spinning Mills Association and AP the manufacture of Cotton Yarn and commenced commercial production with effect from Chamber of Commerce & Industry 05.04.2007. The unit is a large scale Industry having IEM Part B bearing No. Federation also supported the openion 1763/IIM/PROD/2008 Dated 26.09.2008. The incentives of Rs.1,65,90,184/- was released of FAPSIA Member. towards power cost reimbursement under Industrial Investment Promotion Policy (IIPP) 2005-2010 policy from the date of commencement of commercial production ie from Accordingly, SLC decided to 05.04.2007 upto 4th quarter of 2010-11. constitute a SLC-Sub Committee with the following members to inspect the Further release proceedings are issued as detailed below towards power cost reimbursement unit and submit report on working status and justification for transfer of S Consolidated Proceedings No & Period Amount funds to jointly operated account: . Date sanctioned in Rs N 1. Sri B. Suresh Babu, Additional o Director of Industries. . 2. Representative of SLBC :: 58 ::

1No.10/01/2014/8551/power cost 1st quarter of 2011-12 to 2,67,89,467/- 3. Representative of APSFC /FD Dated 18.12.2014. 1st quarter of 2013-14 4. Representative of AP Spinning 2No.10/01/2014/8551/power cost 2nd quarter of 2013-14 to 2,03,79,940/- Mills Association. /FD Dated 13.01.2015. 3rd & 4th quarter of 2013- 5. Representative of FAPSIA 14 6. Representative of FTAPCCI Total 4,71,69,347/- The above conistitued Committee The General Manager, DIC, Guntur in his letter dated 28-12-2014 informed that the unit is inspect the unit immedatly and submit sick / closed and he has not recommended for release of the above sanctioned amount. it’s report to Director of Industries.

As per operational guidelines issued vide G.O.Ms.No. 328 Industries and Further, SLC has resolved to authorise Commerce (IP) Department dated 13.12.2005, the Director of Industries to take decision based on the report of the Para No. 4.11. Continuous Production: Committee, subject to ratification from Continuous production means continuous working of SLC. an industrial unit in the manufacture of approved lines for a minimum period of six (6) years, without any break-in-Production.

Para No. 21.10. In respect of APSFC financed industrial units, subsidy amounts sanctioned and released shall not be credited to the A/c. of respective industrial units if they are sick, closed or changes of management taken place or sold away, etc.

Also wherever the General Manager, DICs finds an industrial unit sick, closed, change of management taken place etc. or for any other reason not worthy or receiving subsidy fill further examination, the Managing Director, APSFC / Branch Manager, APSFC shall not disburse the subsidy to such units on written intimation given to them by the General Managers DICs, or by Commissioner of Industries. In case of above two situations, the subsidy shall be disbursed only after further clearance given by the Additional Director of Industries and Member-Secretary, SLC. :: 59 ::

Further the unit holder vide his letter dated 06.02.2015 informed that due legal issue in NSEL Mumbai, the financial institution have not disbursed the working capital to the unit and unit was stopped due to financial crisis and represented to Government to release the sanctioned power cost reimbursement for revival of the unit.

The request of M/s Spin Cot Textiles Pvt Ltd was submitted to the Government vide letter no. 30/1/2009/0266 dated 7-2-2015. Government of Andhra Pradesh issued orders vide G.O.Rt.No.388 Industries and Commerce (P & I) Department Dated 28.08.2005 according permission for the release of an amount of Rs.2,50,00,000 to M/s Spin cot Textiles Pvt Ltd., Guntur District out of the total eligible subsidy of Rs.4.70 Crore from out of the already released funds towards incentives for Industrial promotion during the current financial year 2015-16 and available with the Department, so as to revive the unit by the promoter in relaxation of existing rules and subject to ratification by the State Level Committee.

In pursuance of the orders in the G.O.Rt.No.388 Inds & Comm (P & I) Department dated 28.08.2015 and as per the recommendation of General Manager, District Industries Centre, Guntur District an amount of Rs.2,49,96,220/- was released to the captioned unit 16.09.2015 and credited into the Joint Account No.3488716164 of Central Bank of India, Gottipadu operated by General Manager, District Industries Centre, Guntur and Managing Director of M/s Spin Cot Textiles Pvt Ltd towards the following.

S. No Released amount to be spent on Amount in Rs 1 For agreement with court receiver 1,00,00,000 2 Part payment of arrears to APSPDCL 40,00,000 3 For supply of Raw Material (cotton) to 68,00,000 Cotton Corporation of India, Guntur 4 For repairs and maintenance of M/c 41,97,000 Total 2,49,96,200

While releasing the amount of Rs.2,49,96,220/- to GM, DIC, Guntur, the General Manager, DIC, Guntur was directed to ensure that the funds released are not misutilised and that the funds are to be used only for revival / reopening of the unit. He should open a separate bank account with joint signatory of the Managing Director of M/s. Spincot Textiles Pvt Ltd for release of funds so that the General Manager, DIC, Guntur to oversee that the released funds can be utilized only for revival / reopening of the unit. Further M/s. Spincot Textiles Pvt Ltd :: 60 :: should submit the utilization certificate with relevant proof that the amount of Rs 2.50 crs released is spent for the revival of the unit within 15 days from the date of release or else proceedings under AP RR Act 1864 will be initiated by the General Manager, DIC, Guntur for the recovery of the above amount along with interest as per the lending rate of State Bank of India. The General Manager, DIC should have constant supervision and extreme vigil over the utilization of funds released to M/s. Spincot Textiles Pvt Ltd, Guntur and report compliance to the Director of Industries.

Subsequently, the General Manager, DIC, Guntur in his letter dated 27-10-2015 informed that the trial production of the unit started and the preparatory section machinery were found working except one carding machine and that he has given a cheque for Rs 1.00 crs in favour of court receiver, Mumbai High Court. He also informed that he released Rs 1,00,15,747/- and has balance Rs 50 lakhs available. He has requested another Rs 1.00 crs for procurement of raw material (cotton yarn) in addition to Rs 2.50 crores already released to him. Accordingly an amount of Rs.1.00 Cr out of pending power cost reimbursement Rs. 2.20 Cr payable to the captioned unit was released on 05.11.2015 duly imposing the same conditions for the revival of the unit.

Subsequently, the General Manager, DIC, Guntur in his letter dated 22-1-2016, & 1-2-2016 informed that the power bill of Rs 38,96,000 is to be paid by 5-2-2016 otherwise the power supply would be disconnected again. He has requested whether to recommend for release of balance Rs 1.20 crs or to utilize the amount of Rs 1.00 cr kept aside for payment towards court receiver in the joint account.

The General Manager, DIC, Guntur in his letter dated 2-2-2016 informed the details of the utilization of the Rs 3.50 crs released to him for revival of the unit. S. No Released amount to be spent on Amount in Rs 1 Amount set aside for court payment 1,00,00,000 2 Power charges paid 58,44,300 3 Paid to Cotton Corporation of India, 1,49,70,000 Guntur for cotton 4 Repairs and maintenance of M/c 41,86,698 Total 3,50,00,998

In this connection it is submitted that the total amount due for release to the units towards :: 61 :: reimbursement of the power charges is Rs 4,71,69,347/-. Till now, the amount released for the purpose of the revival of the unit is Rs 3,49,96,220. The balance amount is Rs. 1,21,73,127/-

The request of the General Manager, DIC, Guntur for release the balance amount of Rs 1,21,73,127/- was examined by the Director’s Office and noticed that the possibility of revival of the unit with the balance amount appears to be bleak. Hence, the matter is being examined on the working capital requirement of the unit and for further course of action in the matter.

In view of the above, the above issue has been placed before SLC meeting held on 17/03/2016 and decision of SLC discussed the issue in detail and ratified the release of power cost reimbursement amount of Rs. 3,49,96,200/- out of which an amount of Rs 1,00,00,000/- is with the joint account of General Manager, DIC and the Managing Director, M/s Spin Cot Textiles Pvt. Ltd., and the same is kept reserved for payment to Court Receiver.

Further, SLC also suggested for writing to banks to support the industry and also to propose the case of the unit to the State Level Inter Institutional Committee (SLIIC) for revival of the unit.

Further, it is to submit that an amount of Rs 61,35,420/- sanctioned towards 1st quarter of 2014-15 and release proceedings were issued vide Proc No. 10/1/2014/8551/Power cost/FD, Dated: 27.03.2015, which is not included in the G.O.Rt.No.388 dated 28.08.2015. This amount pertains to the Budget of 2014-15.

Now the GM, DIC submitted the documents and recommended to release the amount to same account maintained jointly by the Company and the GM, DIC.

As per Para 21.7 of GO Ms No. 65, Dated: 10.05.2016 (amendment issued to the operational Guidelines of IIPP 2005-10) it is mentioned as “the disbursements will be made to Term Loan account of the Financial Institution which sanctioned the loan for adjusting the outstanding dues”.

The unit holder has also requested to release the amount of Rs 61,35,420/- immediately or to utilize an amount of Rs 48,65.682/- temporarily from the available amount in Joint account/FD, for payment of power bills to APSPDCL for the month of October 2016 to avoid disconnection of Power.

In view of the above background :: 62 ::

1. a. A view may be taken to release the amount of Rs 61, 35,420/- immediately from the BE of 2014-15 to the joint account/FD maintained by the Company and GM, DIC in relaxation of Para 21.7 of GO Ms No. 65, Dated: 10.05.20168 (amendment issued to the Operational Guidelines of IIPP 2005-10) subject to ratification from the SLC. b. To place the issue before SLC to take a decision for releasing the amount of Rs 61,35,420/- in relaxation of para 21.7 GO Ms No. 65, Dated:10.05.2016 (amendment issued to the Operational Guidelines of IIPP 2005-10).

2. To accord permission to utilize the amount of Rs 48, 65,682/- for payment of power bills from the joint account/FD, subject to adjustment from the amount of Rs 61, 35,420/- as and when it is released, if 1 (a) is agreed.

The SLC may take a view Supply. IIPP 2005-10 - M/s Jaypee Balaji Cement Plant, Rs No: 99, Budawada (V), Jaggaiahpet (M), SLC discussed the issue in detail and Item Krishna Dist –Release the subsidy to South Indian Bank, Corporate Br, Hyderabad instead of decided to release the subsidy amount No. 4 Axis Bank, Chillakallu Br, Krishna Dist - Requested - Regarding. to the unit’s Term Loan account in Axis Bank, which is lead bank as per operational guidelines under IIPP The General Manager District Industries Centre, Krishna District has recommended the 2005-10. release of reimbursement of sales tax proposal of M/s Jaypee Balaji Cement Plant, Rs No: 99, Budawada (V), Jaggaiahpet (M), Krishna Dist to to South Indian Bank, Corporate Br, Hyderabad instead of Axis Bank, Chillakallu Br, Krishna Dist.

2. The unit is a Large & Medium Scale industry and obtained IEM bearing No. 2471/SIA/IMO/2009 Dt: 01/10/2009 from Government of India, for the line of activity of “ Portland Cement, Aluminous Cement, Slag Cement and similar Hydraulic cement”. The unit has Commenced Commercial Production w.e.f.16/11/2011.

3, In the present case, reimbursement of power cost was sanctioned in 7th SLC meeting dt: 22/11/2014 with an amount of Rs.7,53,76,030/- (Rupees seven crores fifty three lakhs seventy six thousand and thirty only) but the same was not disbursement to bank account.

4, In this case, the unit holder informed that the project funded by 8 banks is as follows a. The South India Bank Ltd :: 63 ::

b. Axis Bank Ltd c. Punjab National Bank d. Corporation Bank e. Allahabad bank f. State Bank of Bikanear & Jaipur g. Dhan bank h. State of Mysore.

As per para No: 21.4 in Operational guidelines under IIPP 2005-10 “ The General Manager shale ensure that in case no bridge loan is availed by the beneficiary unit, the assignment of investment subsidy must be in favour of the term lending institution and in the case of join financing it must be in favour of the lead institution.”

As per para no: 24.7 of G.OMs No: 67 Industires & Commerce (Policy & investment) Dept dt: 10/05/2016.

“The disbursements will be made to Term Loan account of the Financial Institution which sanctioned the loan for adjusting the outstanding dues. Where ever there is no outstanding in the loan account, the Financial Institution is permitted to transfer the balance subsidy amount to working capital loan account of unit holder after due adjusting the outstanding loan amount to facilitate for smooth running the Enterprise/Industry as per procedure of the concerned Bank from time to time. Where ever this facility is not available to certain Banks, the incentives/subsidy amount will be released to a non-operative savings account where the Banker / Financial Institution is advised to adjust the released amount to settle the outstanding dues of the loan account and the balance can be transfer to working capital loan :: 64 ::

account of the unit.”

5. In view of the above that the project cost certified by the Axis Bank, Delhi BR, and the Lead Bank is Axis Bank. But the unit holder requested to transfer the funds to the The South Indian Bank Ltd, Corporate Br, Hyderabad and it is one of the consortium bank for Term Loan Landing

6, SLC may take a view Supply. IIPP 2010 – 15 – M/s. Shri Govindaraja Textiles Limited, Opp. JNTU Engg. College, SLC discussed the issue in detail and Item Peddarangagapuram (V), Pulivendula (M), YSR District – Sanction of reimbursement decided to seek the clarification from No. 5 of Sales Tax – Regarding. the Government on the implementation of Special G.O. Ms. No. 26 Ind. & Com. (Tex) Dept., dated M/s. Shri Govindaraja Textiles Limited, Opp. JNTU Engg. College, 12/01/2012 on sanction and release of Peddarangagapuram (V), Pulivendula (M), YSR District has Large Industry and incentives to the unit in reference to obtained IEN vide 2146/SIA/SMD, dated 31/07/2007 for line of activity is Cotton Yarn the commitment made by the unit in Spinning. The unit was commenced Commercial production w.e.f. 01/04/2008. their representation and the effective Further, the unit has taken up to expansion programme w.e.f. 11/05/2014. The unit has date of implementation of G.O in enhanced the Investment and Capacities more than 25% and fulfilled condition at para order to have clarity. 4.4 guidelines.

Further, the unit has represented to Government and stating that the Company proposes to setup a new project in pulivendula with an investment of Rs.696.22 Crores with 1,72,080 spindles and 36,000 rotor (OE) which provide employment to 2000 people and requested for the following benefits:

a) Power cost reimbursement of @Rs.1.00 per unit for 8 years. b) 50% reimbursement of VAT/CST/SGST for 8 years. c) Assistance for Training to local employees as per Textiles Promotion Policy. d) Infrastructure facilities such as Roads, Water Electricity at door setp e) Other benefits as per policy.

The Government after careful examination of the proposal and in view of the recommendations of the SIPB, hereby extend the following incentives to M/s. Shri Govindaraja Textiles Limited, Opp. JNTU Engg. College, Peddarangagapuram (V), :: 65 ::

Pulivendula (M), YSR District vide G.O. Ms. No. 26 Ind. & Com. (Tex) Dept., dated 12/01/2012.

a) Reimbursement of 50% Net VAT & CST for a period of 5 year from date of commencement of Commercial Production (DCP). b) Fixed Power cost reimbursement of Rs.1.00 per unit for a period of 5 years from DCP. c) Reimbursement of cost incurred for skill up-gradation @ Rs.10,000 per person with a tie-up with Rajiv Yuva Kiranalu (RYK) and meeting expenditure from the resources of RYK scheme. d) All other incentives as per IIPP 2010 – 15 Policy, which include I. 100% Reimbursement of Stamp duty and transfer duty paid by the industry on purchase of Land meant for Industrial use. II. 100% Reimbursement of Stamp duty on Mortgages and hypothecations. III. 25% subsidy on specific cleaner production measures limited to Rs.5 lakhs. IV. Infrastucture assistance as per policy i.e., @50% of the cost up to Rs.1.00 Crore on roads, power and water will be provided at door step of the industry for standalone units.

Accordingly, the investment details of the unit is as follows: Assets As per Statement of As per machinery list & Accounts CA Certificate Rs. in Crores Buildings 24.67 24.67

Plant & Machinery 264.33 295.33

Total 289.00 320.00

The SLC (8th) held on 04.07.2015 has sanctioned 25% reimbursement of Sales Tax Rs.63,42,000/- as per IIPP 2005-10 policy for its 1st Expansion for the year 2014- 15. Further, unit claim applications of captioned unit processed and placed before SVC :: 66 ::

meeting held on In this regard, the Governments orders are not clear that the incentives are sanctioned reimbursement of sales tax to the unit “whether G.O. Ms. No. 26 Ind. & Com. (Tex) Dept., dated 12/01/2012 is applicable for extension of the incentives for the expansion unit and also existing unit, as DCP of Expansion I is 08/01/2014 and Existing DCP is 01/04/2008 and G.O. was issued on 01/04/2012”.

In this regard, the similar issue i.e., M/s. Srikalahasthi Pipes Limited (SPL) (Formerly Lanco Industries Limited)where SLC has taken a decision to seek clarification on sanction and release of incentives to the unit in reference tot the commitment made by the unit in their representation and the effective date of implementation of G.O in order to have clarity.

The issue was placed in SVC held on 18/11/2016. The SVC decided to tatke uniform procedure in such cases and write to Government for clarification.

The SLC may take a view.

Supply. IIPP 2005-10 - M/s South India Krishna Oil And Facts Pvt Ltd, Sy No: 272, 279, 280 SLC discussed the issue in detail and Item & 281, Epudu Bit 1-B Pntapalam (V), Muthukur (M), SPSR Nellore Dist –Release the decided to release the subsidy amount No. 6 subsidy to HSBC, Chennai Br instead of HSBC, New Delhi Br - Requested - Regarding. to the unit’s Term Loan Account of The General Manager District Industries Centre, SPSR Nellor District has HSBC, Chennai Branch as the same Branch certified the Plant & recommended the release of reimbursement of sales tax proposal of M/s South India Krishna Machinery as per operational Oil And Facts Pvt Ltd, Sy No: 272, 279, 280 & 281, Epudu Bit 1-B Pntapalam (V), Muthukur guidelines of IIPP 2005-10. (M), SPSR Nellore Dist to HSBC, Chennai Br instead of HSBC, New Delhi Br 2. The unit is a Large & Medium Scale industry and obtained IEM bearing No. 3771/IIM/PROD/ Dt: 21/10/2012 from Government of India, for the line of activity of “refine Vegetable Oils ”. The unit has Commenced Commercial Production /w.e.f.27/09/2011. 3, In the present case, reimbursement of sales tax was sanctioned in 4th SLC :: 67 ::

meeting dt: 22/11/2014 with an amount of Rs.14,04,82,850/- (Rupees fourteen crores four lakhs eigyty two thousand eight hundred and fifty only) but the same was not disbursement to his bank account. 4, Further the GM, DIC, SPSR Nellore Dist has informed the discussed with Bank officials of the HSBC, Chennai and it has informed that term the term loan was sanctioned by HSBC, New Delhi. But disbursement by Same bank but in Chennai branch and the Assignment letter was furnished in the name of HSBC Ltd, Delhi branch under Core Bank System it can be released to the any of the branch of the same bank. 5, SLC may take a view to release the incentives HSBC Br, Chennai or HSBC Br, Delhi. Supply. IIPP 2010-15 Scheme – M/s. Rockworth Systems Furniture (India) Pvt. Limited, 800 West SLC discussed the issue and decided Item Road, R1 South Sricity Sez., Satyavedu, Chittoor district – Sanction of Reimbursement of to defer the issue. No. 7 Power cost and Sales Tax – Regarding.

M/s. Rockworth Systems Furniture (India) Pvt. Limited, 800 West Road, R1 South Sricity Sez., Satyavedu, Chittoor district has large industry and obtained IEM vide 22/Sricity/9/SSEZ/2010, dated 27/06/2012 for line of activity is “Manufacturing of Office modular furniture using MDF/PB. The unit has commenced Commercial Production on 19/09/2011.

Further, the Government have issued G.O.Ms.No.61 Industries & Commerce (IP) Dept. dated 29.06.2010 and stating that the activity “CABINETS,CUPBOARDS, ALMAIRAHS, DESKS WITH SEATS FURNITURE AND FIXTURES MADE OF MDF & PARTICLE BOARDS” is eligible under IIPP 2010-15.

As per above Government orders, the General Manager, District Industries Centre, Chittoor has recommended the claim application of the above unit for sanction of reimbursement of Power cost and reimbursement of Sales tax under IIPP 2010 – 15.

The issue was placed in SVC held on 18.11.2016. The SVC considered the eligibility from DCP of the unit and the claims filed within prescribed time as per the Government orders by interpreting the applicability of the G.O from the effective date of policy period. . The SVC has verified the claim applications of the unit and recommended to SLC for sanction of reimbursement of Power Cost for the application filed by the unit within time for Rs :: 68 ::

8,24,620/- for the period 1st and 2nd half year of 2014-15 and 1st half year of 2015-16 and reimbursement of Sales Tax for an amount Rs.41,44,027- for the period of 2014-15.

The SLC may take a view.

Supply. IIPP 1015 – 20 – M/s. Kallam Brothers Cottons (P) Limited, (Expansion), D. No. 160 B, Dhulapalla SLC discussed the issue and decided Item (V), Sattenapalli (M), Guntur district – Revised the base – As per CA certificate – Regarding. to sanction after submission of the No. 8 following shortfall information: M/s. Kallam Brothers Cottons (P) Limited, (Expansion), D. No. 160 B, Dhulapalla (V), Sattenapalli (M), Guntur district has obtained I.E.M. Ack. Vide No. 1304/SIA/IMO/2012, dated 04/06/2012 for the line of activity “Cotton Yarn” and commenced commercial production w.e.f. 1. Land sale deed or lease deed 2. 29/09/2013. The Original unit has commenced commercial production on 27/04/2007. Board resolution authorizing the person to sign 3. T&CP Dept., The General Manager, District Industries Centre, Guntur has recommended the claim Factories Dept., Grampanchayat st application for sanction of reimbursement of power cost 1 half year 2015-16 to the unit. After approved plans 4. Land verification of the claim application, the base was fixed wrongly as 945000 due to some errors. Now conversion certificate 5. the base is revised as per CA certificate and fixed as 658529. The details are as follows: Reimbursement of power cost release certificate 6. Statement of Accounts 7. Reasons for increase in Reimbursement of power cost load from DCP to present claim. Supply. Incentives under IIPP 2010-15 – Condonation of break in production to M/s SBQ Steels Ltd., SLC discussed the issue in detail and Item Ankalapaturu (V), Chilakuru Mandal, SPSR Nellore District decided to ratify the action in No. 9 constitution of SLC Sub-Committee Consolidated proceedings were issued in December 2014 to release the sanctioned with the following member: reimbursement of Sales Tax subsidy of Rs. 3,63,55,300/- to M/s SBQ Steels Ltd., Ankalapaturu 1. Additional Director of Industries (V), Chilakuru Mandal, SPSR Nellore District. - Chairman 2. Executive Director of APSFC The Executive Director, M/s SBQ Steels Ltd represented to the Commissioner of - Member Industries that within a short span of time from the commencement commercial operations, 3. Representative of Commissioner, Steel Melting Shop plant operations were shut down due to sudden ban on mining of iron ores Commercial Tax Dept - imposed by the Hon’ble Supreme Court of India. Imposition of Power restrictions by Andhra Member :: 69 ::

Pradesh State Power Distribution Company Limited have resulted in huge cash losses. 4. Representative of AP Trans Co / DISCOM - Due to sluggish phase of steel industry, increase of raw material costs and diminishing Member of Rupee value constrained the company to shutdown the Steel manufacturing operations. 5. Representative of Director of Mines and Geology - As per the operational guidelines under Industrial Investment Promotion Policy 2010- Member 15 policy issued vide G.O.Ms.No.42 Industries & Commerce (I) Department dt. 05.05.2011at para No.4.13 the captioned unit should be in continuous production to avail the incentives is as Further, SLC has taken a decision to follows: include the representative of “4.13 Continuous Production: Continuous Production means continuous working of FTAPCCI & CII which are the an industrial Enterprise engaged in the activity of manufacture of approved lines for a representative obody of Large & Mega minimum period of six (6) years, without any break in production. If any break in production is industries. there, such period will be extended. If any industrial enterprise is not in operation / working for more than 90 days continuously, then the industrial enterprise will be treated as not in continuous working. This condition is not applicable for seasonal industrial enterprises which must be working during the season”

The unit is representing to release the sanctioned sales tax reimbursement to enable them to resume their steel plant operations. As per the IIPP 2010-15 policy at para No.16.0

“The Industrial Enterprises obtaining incentives should be in continuous production for a period of six (6) years from the date of commencement of commercial production failing which all incentives / concessions sanctioned are liable to be cancelled and the incentives / concessions sanctioned are liable to be cancelled and the incentives / concessions already availed re liable for recovery. In this regard, the General Manager, District Industries Centre concerned should monitor the progress of these Enterprises and submit report to the Commissioner of Industries on half-yearly basis. Break-in production upto a period of three (3) years due to the reasons beyond its control such as shortage of raw-materials, power and change of management, etc. may be condoned by State Level Committee (SLC) on merits. Any break-in-production beyond three (3) years will result in extending the six (6) years continuous production condition by the period of such break”

The General Manager, DIC, SPSR Nellore District informed that the unit was inspected by the Deputy Director (EII&I) and noticed that it is an integrated steel plant. Out of all divisions of Steel Plant only the DRI plant which produces sponge iron was found working and other divisions namely MBF, Coke oven plant, Sinter plant, Steel melting shop, Roller Mills are found to be closed. It was also informed that DRI plant was recommenced :: 70 :: production of Sponge Iron on 15.03.2015. The General Manager, DIC, SPSR Nellore District sent the proposal for condonation of break in production and extending the continuous production for 15 months. The issue was placed in 8th SLC and the decision of the SLC is as follows The State Level Committee discussed the issue and decided to obtain the documentary evidence from M/s SBQ Steels Limited, after the deliberations of the members on the following points.

Representative of APTRANSCO has informed that there are no restrictions imposed for the supply of power to M/s SBQ Steels Limited during the period of stoppage of production as claimed by the unit.

SLC opined that he contention of theM/s SBQ Steels Limited that the steel melting shop plant is shut down due to sudden ban on mining ores is to be examined as the unit does not have the facility o f captive mining.

SLC noticed that since other steel plants in the State are working the increase of raw material cost could not have been the reason to shut down the productions.

The unit holder has furnished information as Annexure as follows Annexure –I : APERC revised order in restriction and control measures on consumption of Power. Annexure-II : Correspondences received tot eh concerned unit regarding the restrictions and control measures of APERC on usage of power from the year 2011 onwards. Annexure-III: Press releases on power restrictions and control measure of APRC and the severely affected manufacturing sector and other allied industries. Annexure-IV: Press releases on imposing ban on iron ore mining operations at State of Karnataka and Andhra Pradesh by Hon’ble Supreme court of India. Annexure –V:Press releases on the financial status of other steel industries in the state due to sudden increase of raw material. In view of the complexity and financial involvement it is felt that constitution of an SLC Sub- :: 71 ::

Committee with the following members is more appropriate for deciding the issue 1. Additional Director of Industries - Chairman 2. Executive Director of APSFC - Member 3. Representative of Commissioner, Commercial Tax Dept - Member 4. Representative of AP Trans Co / DISCOM - Member 5. Representative of Director of Mines and Geology - Member

SLC may ratify the action in constitution of the committee.

Supply. IIPP 2005 – 10 – M/s. NSL Textiles Limited, Sy. No. 371 – 382, Kuchalavaripalem (V), SLC discussed the issue. The Item Cherukapali (M), Guntur district – Release of the sanctioned reimbursement of power cost Chairman has requested the members No. 10 amount to the unit – Regarding. to give their openion on this issue. The representative of AP Spinning Mills Association has informed that as Trust M/s. NSL Textiles Limited, Sy. No. 371 – 382, Kuchalavaripalem (V), Cherukapali and Retention account (TRA) is (M), Guntur district has Large industry and obtained IEM vide No. 3247/SIA/IMO/2007, maintained by the Term Loan dated 12/11/2007 for line of activity “Cotton Weaving and Processing” and Commercial Institution-Canara Bank for all units, Production as 31/03/2010. The unit was financed by Canara Bank, Prime Corporate Branch, SLC has ratified the action of Bangalore Branch. releasing incentives to the Company’s Trust and Retention account (TRA) In this connection, the General Manager, District Industries Centre, Guntur has maintained with Canara Bank, Prime submitted the required documents for release of reimbursement of Power cost an amount of Corporate Branch, Banglore on behalf Rs.3,21,06,110/- to the unit. After verification of documents the unit holder submitted the of all the 11 consortium as the same Assignment letter and informed that payment of sanctioned reimbursement of Power Bank is Term Loan lending institution incentives through Canara Bank, Prime Corporate Branch, Banglore for being credited to for all the 11 units. Current Account No. 2636201000173, IFSC Code CNRB0002636. Further, the term loan sanctioned by Financial Institution Canara Bank has given NOC and stating that the power Power Subsidy released to M/s. NSL Textiles Limited and M/s. NSL Textiles (Edlapadu) Ltd., may be tredited / transferred to Company’s Trust and Retention account (TRA) maintained with Bank on behalf of all the 11 consortium lenders for crediting the sales receipts/incentives/other claims. In view of the above, the both accounts numbers i.e., M/s. NSL Textiles Limited and M/s. NSL Textiles (Edlapadu) Ltd., indicated are same. The SLC may take a view.

:: 72 ::

Supply. IIPP-2010-15 – Application of M/s. Chandu Harvestor, D. No. 4-63, Malakapalli Village, SLC discussed the issue and decided Item Tallapudi Mandal, West Godavari District for permission for Change of Management from to accord permission for change of No. 11 Partnership firm to Proprietrix– Regarding. constitution of the unit from Partnership to Propietory. The General Manager, District Industries Centre, Eluru, West Godavari District has informed that the unit represented by its Proprietrix, Guntu Rameswari completed the documentation as required under the scheme (Originally, M/s. Chandu Harvestor is a partnership firm, Smt. Guntu Rameswari W/o. G. Yedukondalu is Managing Partner and Sri G. Yedukondalu is partner of the firm. In mean time one of the partners Sri Guntu Yedukondalu has expired on 26/11/2015. The other partner Smt. Guntu Rameswari has taken overall assets and liabilities of the firm.

The General Manager, District Industries Centre, Eluru, West Godavari District District has informed that the unit has obtained EM part-II acknowledgement bearing No. 28/015/22/00459/Part-II, dated: 10-3-2015 for the line of activity “Harvestor Hiring Services” and the unit has commenced its commercial production on 18/12/2014 and sanctioned Investment Subsidy of Rs. 7,91,000/- under IIPP-2010-15 scheme.

The Harvestor is working in good condition. And obtained all necessary documents and recommended for change of constitution from Partnership to Proprietary in the name of Smt. Guntu Rameswari, after the death of the partner. As per the Deed of dissolution dated 08/01/2016, Smt. Guntu Rameswari taken over all assets and liabilities of the firm and continued the business as Proprietrix of the firm. Now, the release documents are submitted in the name of Proprietrix Smt. Guntu Rameswari. The GM has submitted the following documents for release and also recommended for release. 1. Original Agreement bond with proper attestation :: 73 ::

2. Original Advance Stamped Receipt with proper attestation 3. Original Assignment letter with proper attestation 4. Confirmation of bank account details by the financial institution. 5. Copy of Deed of dissolution submitted by Guntu Rameswari W/o. late Yedukondalu. 6. Death certificate of Guntu Yedukondalu, S/o. Samuel issued by Registrar Births and Deaths and Panchayat Secretary, Grampanchayati, Malakapalli. 7. The original partnership deed was between the wife and husband, wherein the partnership deed got dissolved due to death of husband and thus wife becomes sole proprietor. 8. NOC from the Financial Institution, APSFC in the letter dated:30-03-2016, accepted the change of constitution form partnership firm to sole proprietary concerned . 9. Copy of affidavit submitted by Smt. Guntu Bullema, W/o. Samyulu @ Swamy and mother of late Guntu Yedukondalu, stating that his son Guntu Yedukondalu is passed away on 26/11/2015. Mother of the deceased person submitted affidavit that she did not have any claim over the assets. 10. Family Members certificate issued by Tahasildar, Thallapudi, as per Family Members Certificate, apart from the wife of deceased person, the other members are minor sons (two) 11. The DIPC Meeting dt:14-09-2016, the decision was that this issue does not come under the purview of the DIPC. The request of the unit holder for Change of Management from Partnership firm to sole proprietory concern in the name of Smt. Guntu Rameswari Rameswari W/o. late Yedukondalu may be considered. Accordingly, the unit may be released an amount of Rs.7,91,000/- as investment subsidy to the unit. The SLC may take a view on the proposal. Table Target 2000 Scheme - M/s. Coastal Agro Industries Ltd.Unit-II, K.Savaram, Tanuku (M), SLC discussed the issue in detail and Item West Godavari District - Inclusion of the Additional Line of activity in the Final Eligibility decided to constitute SLC Sub- No. 12 Certificate - Regarding. Committee with the following member: M/s. Coastal Agro Industries Ltd., Unit-II, K.Savaram, Tanuku (M), West Godavari 1. Additional Director of Industries District is a Medium Scale Enterprise engaged in the manufacture of “Straw Boards” w.e.f. - Chairman 2. Representative from APSFC :: 74 ::

20/09/1998. The unit has been sanctioned Sales Tax incentives under Target 2000 Scheme - Member and issued Final Eligibility Certificate for availing Sales Tax Deferment to a tune of 3. Representative from Commercial Rs.4,96,56,280/- for a period of 14 years from 20/09/1998 to 19/09/2012 for the line of Tax Dept - Member activity of “Straw Boards” vide Final Eligibility Certificate No. 10/1/9/0006/0006/ID, dated 4. Representative from AP Paper 20/02/1999. Mills Association.

The Management of M/s. Coastal Agro Industries Ltd., Unit-II, K.Savaram, Tanuku 5. Representative from FAPSIA (M), West Godavari District has informed that they have been manufacturing “Straw Boards, Multi Ply Straw Boards, Kraft Paper” under the category of Paper & Paper Boards with the In view of the urgency due to same machinery, usage of Raw Material of Paddy Straw & Waste Paper depend up on market recommendation of recovery of Sales demand and raw material availability and requested for inclusion of additional products in the Tax Deferment (availed by the unit) Final Eligibility Certificate for availing the Sales Tax incentives. availed, by the AG of Commercial Taxes Department, SLC desired that They have also informed that the Sales Tax Department received an audit objection the Committee shall inspect the unit from AG audit to issue a show cause notice to them to recover Sales Tax Deferment amount and submit its report before for the years 2008-09, 2009-10 and 2010-11 according to principle product Straw Board 10/12/2016. without mentioning the other products. They have obtained IEM Part-B vide Ack. No.42/IIM/Prod/2016, Dated:09/02/2016 from the Government of India for the manufacture of “Straw Boards and Kraft Boards.

The General Manager, District Industries Centre, West Godavari District has informed that the unit was inspected by the Deputy Director (EII&I) along with IPO on 18/03/2016 and reported that the unit is found working & engaging in activity of “Kraft Board, Multiple Ply Straw Board, Kraft Board with the usage of raw material Paddy straw and waste paper.

Further, the General Manager has informed that the inspecting officers verified the month wise production and sales records of the unit submitted to Central Excise Department (RT-12 returns), it is observed that the unit is manufacturing the “Straw Board and Kraft Board” from the commencement of commercial production as per the market demand and availability of raw material up to 2007-08. But due to shortage of raw material for straw board and slump in the market demand, the unit has stopped the production of straw board and continued with Kraft Board. At present also the unit is engaging the manufacturing of “Kraft Board’ only.

The General Manager, District Industries Centre, West Godavari District has recommended the proposal and requested the Director of Industries to include the line of activity of “Kraft Board” in the Final Eligibility Certificate of the unit. :: 75 ::

As per the para 4.8 of guideline under Target 2000 scheme

“Exemption of Sales Tax / Sales Tax Deferment: The sales tax payable by the new Industrial Units on the sales of finished goods ( approved products Manufactured in the unit) both under APGST Act and CST Act from the date of commencement of commercial production for a period of 5 years in case of exemption / upto 10 years in case of deferment subject to limits prescribed under the scheme.”

As per G.O.Ms.No.108 Industries and Commerce (IP) Department dated 20.05.1996 at para 6.03 (a), “Sales tax refers to Sales tax on products manufactured in the New Industrial Units ”SLC decision as per 91st S.L.C. meeting held on 24/02/2012 in respect of M/s. S.P.S. Textiles & Industries Limited, No.9-93, Ravikampadu(V), Thondangi Mandal, East Godavari District – is as follows.

“SLC examined the issue and decide to issue the revised Final Eligibility Certificate of Sales Tax Deferment duty including, the line of activity “ Polyster Viscose Yarn, Polyster Yarn and Viscose Yarn” instead of Synthetic Yarn for their original and expansion projects sine the line of activities are coming under the category of “Synthetic Yarn” subject to condition that the line of activities are within the approved project cost with respect to machinery at the time of sanction of sales tax deferment under Target- 2000 scheme and also the unit should not add any new machinery for manufacture of the said products.

General Manager, District Industries Centre, West Godavari district also informed that the unit is manufacturing the “Straw Board and Kraft Board” from the commencement of commercial production as per the market demand and availability of raw material up to 2007- 08.

In view of the above, the proposal of the unit may be considered for the issue of revised final eligibility certificate for sales tax deferment as the products Straw Board and Kraft Board” are within the approved project cost with respect to machinery at the time of sanction of sales tax deferment under Target-2000 scheme subject to condition that the line of activities are within the approved project cost with respect to machinery at the time of sanction of sales tax deferment under Target-2000 scheme and also the unit should not add any new machinery for manufacture of the said products.

:: 76 ::

The SLC may take a view. General General observations While concluding the SLC Meeting, the Chairman SLC informed all the Members that this may be last SLC Meeting for claims file manually. Online filing of incentives is very active and the next SVC/SLC will be conducted to the screens derived from online system.

Further, Chairman SLC has requested all the SLC Members to give the details of persons nominated on permanent bais so as to give digital signature/one time password (OTP) so as to process and scrutiny the incentives claims through online.

Chairman of SLC assured that all the pending release proposals will be cleared within 7 days.

Chairman of SLC further assured that the action for getting installments to the Sick unit M/s. Seapearl Industries as represented by ALEAP will be immediately taken by writing to CMD of APSPDCL.

:: 77 ::

LIST OF MEMBERS ATTENDED THE 13th STATE LEVEL COMMITTEE MEETING HELD ON 21/11/2016 AT 11.30AM. IN THE CONFERENCE ROOM OF COLLECTOR’S CAMP OFFICE , VIJAYAWADA

SL.NO. MEMBERS NAME & DESIGNATION OF MEMBER / REPRESENTATIVE ______Sri / Smt:

1. Chairman, Kartikeya Misra, IAS., State Level Committee. Chairman, SLC / Director of Industries.

2. The President GRK Reddy FAPSIA Working President

3. The Managing Director, I. Ramachandra Rao, APSFC . Dy. General Manager.

4. The Chairman, P. Koti Rao, AP Spinning Mill Assosiation Director

5. The Managing Director Subrahmanyeswara Rao, APIIC. Dy. Director, APIIC

6. The Commissioner, K. Chandrasekhara Rao, Commercial Taxes, AP. Assistant Commissioner

7. The Cheif Engineer (Commercial), Ch.V Ramana, APTRANSCO . ADE (Comml.)

8. The Commissioner & Inspector General, P. Ramalakshmi Patnaik, Registration Stamps Department. Asst. Inspector General.

9. The Member Secretary, R Sreeramulu APPCB SEE

10. The Deputy General Manager S. Venkata Ramana, SME, Head Office, SBH Asst. General Manager.

11. The President K.V.C.S.Prasad, DICCI, (AP) General Secretary

12. The President APK Reddy, FSME President

:: 78 ::

13. The President P.Bhaskara Rao AP Chambers of Commerce & Industry Member. Fadaration

14. Member-Convenor, B.Suresh Babu Additional Director of Industries. Additional Director

:: 79 ::

I. REIMBURSEMENT OF POWER COST Annexure -1 Date of Sl. No. Date of Commence Sl. & date Name & Address of Line of Nature of Amount sanctioned by SLC / Decision of receipt of ment of Policy No. of SVC the unit activity incentives SLC claim commercial Meeting production M/s Mohan Spintex Cotton Rs.3,64,58,239/- (Rupees three crores India Ltd (Unit-II) RS. Spinning Reimburse- Spill over IIPP sixty four lakhs fifty eight thousand two 1 No. 289/2B3, Remalle Mills ment of case 2005-10 hundred and thirty nine only) for 4th (V), Bapulapadu (M), including power cost quarter of 2015-16. Krishna Dist Ginning M/s.PVR Spinning Rs.49,74,694/- (Rupees forty nine lakhs and Weaving Mills seventy four thousand six hundred and (Expansion),RSNo.11 Cotton Reimburse- Spill over IIPP ninety four only) i.e. deference amount 2 0/2, 108/2,3,4,, Spinning 26/05/2007 ment of case 2005-10 duly taking upto base power consumption Kondaipalem road, Mills power cost as 697768 units per month which was Tetali village, Tanuku revised for expansion project. (M), West Godavari M/s. Sri Venkata Siva Rs.25,80,122/- (Rupees twenty five lakhs Parvathi Spinning eighty thousand one hundred and twenty Mills(P) Ltd. Reimburse- Spill over Spinning IIPP two only) pertaining to deference amount 3 (Expansion-II), 07/07/2008 ment of case Yarn 2005-10 for 3rd quarter of 2015-16 including march, Chebrolu(V&M), power cost 2016 reading of power bill. Gutur District

(EXPANSION) Rs.66,41,611/- (Rupees Sixty six lakhs M/s Kallam Spinning Spinning, forty one thousand Six hundred and Mills Ltd, Weaving Reimburse Spill over IIPP eleven only) pertaining to deference 4 Kunukupadu(V), and ment of case 2010-15 amount for 2nd half year of 2015-16 Addanki (M), processin Power cost including march, 2016 reading of power Prakasam District. g bill. M/s Sri Anantha Rs.28,85,653/- (Rupees twenty eight Lakshmi Spinning Reimburse- Spill over Cotton IIPP lakhs eighty five thousand six hundred 5 Mills (P) Ltd, (Exp-1) 26/06/2010 ment of case Yarn 2005-10 and fifty three only) for 4th quarter of 59/1, Boyapalem (V), power cost 2015-16 (March, 2016 2nd reading) Edlapadu (M), Guntur :: 80 ::

District M/s. Jyotirmaye Textiles (P) Ltd., Reimburse Gorijavolu (V), Cotton IDP Deferred for want of shortfalls as detailed 6 201 04/06/16 18/06/2015 ment of Nadendla (M), Guntur Yarn 2015-20 in SVC Minutes. Power cost District (EXPANSION) M/s. Jyotirmaye Textiles (P) Ltd., Reimburse Cotton IIPP Deferred for want of shortfalls as detailed 7 202 04/06/16 Gorijavolu (V), 04/02/2011 ment of Yarn 2010-15 in SVC Minutes. Nadendla (M), Guntur Power cost District M/s. Sakku Spinning Mills Ltd., Reimburse Chinakondrupadu (V), Cotton IIPP Deferred for want of shortfalls as detailed 8 203, 221 04/06/16 16/10/2011 ment of Prathipadu(M), Yarn 2010-15 in SVC Minutes. Power cost Guntur District (EXPANSION) M/s. Venkata Uma Sankar Spintex (P) Reimburse Ltd., S.No:33,35/1, Cotton IIPP Deferred for want of shortfalls as detailed 9 204 04/06/16 29/06/2013 ment of Vemavaram(V), Yarn 2010-15 in SVC Minutes. Power cost Phirangipuram(M), Guntur District M/s. Guntur Spinning Mills (P) Ltd., D.No:491, 492/2, Reimburse Cotton IDP Deferred for want of shortfalls as detailed 10 205 04/06/16 NH-5, Obul Naidu 06/07/2015 ment of Yarn 2015-20 in SVC Minutes. Palem (V), Guntur Power cost District (EXPANSION) M/s. Bhavanam Spinning Mills Pvt. Reimburse Rs.34,30,294/- (Rupees thirty four lakhs Ltd., Siripuram Road, Cotton IIPP 11 206 04/06/16 25/03/2008 ment of thirty thousand two hundred and ninety Bhimanenivaripalem( Yarn 2005-10 Power cost four only) for 4th quarter of 2015-16. V), Medikonduru (M), Guntur District :: 81 ::

(EXPANSION-1) M/s. Supriya Spinning Mills Pvt. Ltd., Reimburse Boyapalem(V), Cotton IIPP Deferred for want of shortfalls as detailed 12 207 04/06/16 22/02/2012 ment of Edlapadu(M), Guntur Spinning 2010-15 in SVC Minutes. Power cost District (EXPANSION) M/s. Mittapalli Deferred for want of shortfalls as detailed Spinners Ltd., Reimburse Cotton IIPP in SVC Minutes. 13 208 04/06/16 Chinaturakapalem 29/12/2011 ment of Yarn 2010-15 (V), Narasaraopet Power cost (M), Guntur District M/s.Thatavarthi Deferred for want of shortfalls as detailed Apparels Ltd Reimburse in SVC Minutes. (Spinning Division), Cotton IIPP 14 209 04/06/16 20/05/2011 ment of Kavuru(V), Yarn 2010-15 Power cost Chilakaluripet (M), Guntur District M/s. Sri Mouli Textiles Pvt Ltd., Cotton Reimburse IDP Deferred for want of shortfalls as detailed 15 212 04/06/16 S.No: 22/A, 22/B&25, Yarn open 10/05/2015 ment of 2015-20 in SVC Minutes. Prathipadu (V&M), end Power cost Guntur District M/s. Sri Venkateswara Spintex (P) Ltd., D.No:20&21, Reimburse Cotton IIPP Deferred for want of shortfalls as detailed 16 213 04/06/16 Narasaraopet Road, 04/12/2011 ment of Yarn 2010-15 in SVC Minutes. Kavuru(V), Power cost Chilakaluripet (M), Guntur District M/s. Idupulapadu Cotton Mills Pvt. Ltd., Cinima Theatre Road, Reimburse Cotton IIPP Deferred for want of shortfalls as detailed 17 214 04/06/16 Ganapavaram (V), 04/12/2009 ment of Yarn 2010-15 in SVC Minutes. Nadendla (M), Guntur Power cost District (EXPANSION-5) :: 82 ::

M/s. Sri Nukala Rama Koteswara Rao Textiles Pvt Ltd., Reimburse D.No: 1-233, GBC Cotton IIPP Deferred for want of shortfalls as detailed 18 215 04/06/16 26/03/2010 ment of Road,Chebrolu Yarn 2005-10 in SVC Minutes. Power cost (V&M), Guntur District (EXPANSION) M/s. Sri Venkata Siva Parvathi Spinning Reimburse Cotton IIPP Deferred for want of shortfalls as detailed 19 216 04/06/16 Mills (P) Ltd., (Unit- 10/05/2012 ment of Yarn 2010-15 in SVC Minutes. II), Cebrolu (V&M), Power cost Guntur District M/s. Sri Lakshmi Rs.1,28,90,667/- (Rupees one crore Godavari Spinning Reimburse Cotton IIPP twenty eighty lakhs ninety thousand six 20 217 04/06/16 Mills Ltd., S.No:113, 22/03/2013 ment of Yarn 2010-15 hundred and sixty seven only) for 2nd Chebrolu (V&M), Power cost half year of 2015-16. Guntur District M/s. Sri Lakshmi Godavari Spinning Rs.57,66,249/- (Rupees fifty seven lakhs Reimburse Mills Ltd., S.No:113, Cotton IIPP sixty six thousand two hundred and 21 218 04/06/16 26/06/2010 ment of Chebrolu (V&M), Yarn 2005-10 forty nine only) for 4th quarter of 2015- Power cost Guntur District 16. (EXPANSION) M/s.Sriven Spincot Rs.4,22,450/- (Rupees four lakhs twenty Reimburse (P) Ltd., Edlapadu Cotton IIPP two thousand four hundred and fifty 22 219 04/06/16 09/06/2014 ment of (V&M), Guntur Yarn 2010-15 only) for 2nd half year of 2015-16 in 2nd Power cost District bill in the March. M/s. Bhavanam Spinning Mills Pvt. Rs.99,85,672/- (Rupees ninety nine lakhs Ltd., Siripuram Road, Reimburse Cotton IIPP eighty five thousand six hundred and 23 222 04/06/16 Bhimanenivaripalem( 26/06/2010 ment of Yarn 2005-10 seventy two only) for 4th quarter of 2015- V), Medikonduru (M), Power cost 16. Guntur District (EXPANSION-II) M/s. Balabalajee Cotton Reimburse IIPP Rs.74,77,739/- (Rupees seventy four 24 229 06/06/16 27/03/2008 Textiles Limited Yarn / ment of 2005-10 lakhs seventy seven thousand seven :: 83 ::

(Expn – I), RS No. Synthetic Power cost hundred and thirty nine only) for 4th 492/493, Tanuku (V), Yarn quarter of 2015-16. & M, West Godavari District M/s. Sri Srinivasa Spintex Pvt. Ltd., KN Road, Tadepalli, Reimburse Cotton IIPP Deferred for want of shortfalls as detailed 25 232 06/06/16 Tadepalligudem (M), 08/08/2008 ment of Spinning 2005-10 in SVC Minutes. West Godavari Power cost District

M/s. Kalpataruvu Spinning Mills Ltd., Reimburse S.No: 210,211/A, Cotton IIPP Deferred for want of shortfalls as detailed 26 233 06/06/16 01/06/2012 ment of Thimmapuram (V), Yarn 2010-15 in SVC Minutes. Power cost Edlapadu(M), Guntur District Vertified M/s. Silica Ceramica Ceramics IIPP Pvt Ltd., D.No. 97- Reimburse Tiles and 2005-10 Deferred for want of shortfalls as detailed 27 240 07/06/16 107, Narayanapuram, 11/05/2011 ment of Ceramic Pipe in SVC Minutes. Unguturu (M), West Power cost Glazed Line Godavari District Tiles Rs.82,57,884/- (Rupees eighty two lakhs M/s. Swarnalatha fifty seven thousand eight hundred and Spintex Pvt. Ltd., Reimburse eighty four only) for 2nd half year of Rs.No. 1/4, Cotton IIPP 28 246 09/06/16 12/02/2012 ment of 2015-16 including missed claim for placing Serinarasannapalem Spinning 2010-15 Power cost before SLC in earlier meeting an amount of (V), Bapulapadu (M), Rs.3,93,554/- pertaining to 2nd half year of Krishna Dist 2011-12. Allopathic M/s. Vasudha Pharma Pharmace Reimburse Chem Ltd., Unit- III, IIPP Deferred for want of shortfalls as detailed 29 247 09/06/16 utical 23/03/2011 ment of Plot No. 23&24, 2010-15 in SVC Minutes. Preparatio Power cost JNPC, Parawada, VSP ns Deferred for want of shortfalls as detailed 30 1 Spill over M/s RBA Textiles Trading of 06/11/2008 Power IIPP in SVC Minutes. :: 84 ::

case Pvt. Ltd., Cotton 2005-10 Krishnagiri Road, Yarn Food Processing Industrial Park, Kuppam (M), Chittoor Dist M/s. Smilax Laboratories Ltd., Deferred for want of shortfalls as detailed Spill over Plot No.70, JNPC, Bulk IIPP 31 4 12/06/2009 Power in SVC Minutes. case Parawada, Drugs 2005-10

Visakhapatnam District M/s. Sree Veerabrahmenra Swamy Spinning Cotton IIPP Deferred for want of shortfalls as detailed 32 6 04/06/16 Mills Pvt Ltd., 10/04/2008 Power Yarn 2005-10 in SVC Minutes. Lingamguntla(V), Chilakaluripet(M), Guntur District M/s.Y.S.R.Spinning &Weaving Mills Pvt. Ltd., D.No:5- 265, Cinema hall Cotton IDP Deferred for want of shortfalls as detailed 33 7 06/06/16 03/10/2011 Power Road,Ganapavaram Yarn 2015-20 in SVC Minutes. (V), Nadendla(M), Guntur District (EXPANSION-III) M/s. Sai Global Yarntex (India) Pvt Ltd. (Expansion), Sy Cotton IIPP Deferred for want of shortfalls as detailed 34 8 06/06/16 No:143/P, 01/04/2011 Power Yarn 2010-15 in SVC Minutes. 133,103/P, NH-5, Vellampalli(V), Maddipadu(M), :: 85 ::

Prakasam District M/s Ravali Spinners Pvt Ltd. (Expn-I), 13-194,, Cotton IIPP Deferred for want of shortfalls as detailed 35 14 13/06/16 01/01/2009 Power Khandavalli (V), Yarn 2005-10 in SVC Minutes. Peravali (M), WG Dist M/s SVR Spinning Mills Pvt Ltd., Cotton IIPP Deferred for want of shortfalls as detailed 36 16 13/06/16 01/01/2009 Power Malleswaram, Yarn 2010-15 in SVC Minutes. Peravali (M), WG M/s Ravali Spinners Ltd. (2nd Cotton DIP Deferred for want of shortfalls as detailed 37 17 13/06/16 expn.) Khjandavalli 20/11/2010 Power Yarn 2015-20 in SVC Minutes. , Peravali Mandal, WG District M/s.Praveen Spinners(India) Pvt Deferred for want of shortfalls as detailed Ltd., Rs No.142,147, Cotton DIP in SVC Minutes. 38 19 14/06/16 13/02/2013 Power Ravicherla, Nuzivid Yarn 2015-20 Mandal, Krishna District M/s.Tirumala Cotton &Agro Products(P) Ltd., (Spinning Division), Cotton DIP Deferred for want of shortfalls as detailed 39 20 14/06/16 Thimmapuram (V), 05/10/2012 Power Yarn 2015-20 in SVC Minutes. Edlapadu(M), Guntur District (EXPANSION)

M/s. Sree Rs.49,20,040/- (Rupees forty nine Cotton IIPP 40 22 14/06/16 Veerabrahmenra 10/04/2008 Power lakhs twenty thousand and forty Yarn 2005-10 Swamy Spinning only) for 4th quarter of 2015-16, :: 86 ::

Mills Pvt Ltd., Lingamguntla(V), Chilakaluripet(M), Guntur District M/s. Rayani Spintex Pvt Ltd., S.No:82-1B, Cotton DIP Deferred for want of shortfalls as detailed 41 23 14/06/16 16/11/2011 Power Dhullipalla(V), Yarn 2015-20 in SVC Minutes. Sattenapalli(M),Gun tur District M/s. Kallam Brothers Cottons(P) Ltd.,Dhulipalla(V), Cotton DIP Deferred for want of shortfalls as detailed 42 24 14/06/16 29/09/2013 Power Sattenapalli(M), Yarn 2015-20 in SVC Minutes. Guntur District (EXPANSION) M/s. Sri Manjunatha Spinning Mills Ltd., Cotton DIP Deferred for want of shortfalls as detailed 43 25 14/06/16 14/02/2011 Power Thimmapuram(V), Yarn 2015-20 in SVC Minutes. Edlapadu(M), Guntur District M/s.Sree Lalitha Parameswari Spinning Mills (Pvt) Ltd., Chebrolu(V Cotton IIPP Deferred for want of shortfalls as detailed 44 26 14/06/16 &M), Guntur 26/03/2010 Power Yarn 2005-10 in SVC Minutes. District (EXPANSION)

M/s.Sri Naga Deferred for want of shortfalls as detailed Cotton DIP 45 27 14/06/16 Malleswara 03/04/2012 Power in SVC Minutes. Yarn 2015-20 Spintex(India) Pvt :: 87 ::

Ltd., Rajupalem(V &M), Guntur District M/s. Pavan Cotton Deferred for want of shortfalls as detailed Products Pvt Ltd., in SVC Minutes. Pulladigunta(V), Cotton IIPP 46 28 14/06/16 23/03/2008 Power Vatticherukuru(M), Yarn 2005-10 Guntur District (EXPANSION-1) M/s. Sree Caustic Rayalaseema Soda Lye IIPP Alkalies and allied Flakes, 2005-10 Deferred for want of shortfalls as detailed 47 30 16/06/16 Chemicals Ltd., 01/01/2012 Power Chlorine, Pipelin in SVC Minutes. Gondiparla(V), Hydron e Kurnool Post, Gas HCL Kurnool District M/s. Shri Givindaraja Textiles Rs.1,65,63,750/- (Rupees one crore Pvt Ltd., 708, ETC., Cotton IIPP sixty five lakhs sixty three thousand 48 32 17/06/16 Peddarangapuram Yarn 01/04/2008 Power 2005-10 seven hundred and fifty only) for 4th (V), Spinning quarter of 2015-16. Pulivendula(M), YSR Kadapa District M/s.Shri Govindaraja Textiles Pvt. Ltd. Cotton (Expansion), IIPP Deferred for want of shortfalls as detailed 49 33 17/06/16 Yarn 08/01/2014 Power Peddarangapuram, 2005-10 in SVC Minutes. Spinning Pulivendula Mandal, Kadapa District M/s.Sudarshanam Rs.45,42,640/- (Rupees forty five lakhs Cotton IIPP 50 34 23/06/16 Spinning Mills, 20/08/2008 Power forty two thousand six hundred and Yarn 2005-10 Tirumalagiri, forty only) for 4th quarter of 2015-16. :: 88 ::

Jaggaihpet Mandal, Krishna District M/s.Rajapalayam Mills Ltd., Rs.56,02,140/- (Rupees fifty six lakhs Cotton IIPP 51 35 23/06/16 Gopinenipalem, 07/01/2012 Power two thousand one hundred and forty Yarn 2005-10 Vatsavai Mandal, only) for 4th quarter of 2015-16. Krishna District M/s.Sri Vishnu Cotton Shankar Mills Ltd., Rs.51,05,030/- (Rupees fifty one lakhs Yarn & IIPP 52 36 23/06/16 Gopinenipalem, 12/03/2009 Power five thousand and thirty only) for 4th Synthetic 2005-10 Vatsavai Mandal, quarter of 2015-16. Yarn Krishna District M/s.Sri Harini Rs.43,19,030/- (Rupees forty three Textiles Ltd., lakhs nineteen thousand and thirty Tirumalagiri, Cotton IIPP 53 37 23/06/16 12/06/2008 Power only) for 4th quarter of 2015-16. Jaggaiahpet Yarn 2005-10

Mandal, Krishna

District M/s.Sandhya Cotton Rs.49,26,480/- (Rupees forty nine Spinning Mill Ltd.,, Yarn & IIPP lakhs twenty six thousand four 54 38 23/06/16 Gopinenipalem, 01/05/2009 Power Synthetic 2005-10 hundred and eighty only) for 4th Vatsavai Mandal, Yarn quarter of 2015-16. Krishna District M/s. Rockworth Systems(I) Pvt Ltd., 800 West Road, RI Office South Sricity, IIPP 55 41 23/06/16 Modular 19/09/2011 Power Deferred. SEZ,Satyavedu, 2010-15 Furniture Chittoor District

M/s.Pinnae Feeds Other Rs.9,18,900/- (Rupees nine lakhs IIPP 56 42 24/06/16 Ltd., Bogole (V & Animal 02/07/2014 Power eighteen thousand and nine hundred 2010-15 M), SPSR Nellore and Bird only) for 2nd half year of 2015-16. :: 89 ::

District Feed, Shrimp Feed M/s. Hindustan National Glass& Industries Ltd., IIPP APIIC Multiproduct Containe 2005-10 Deferred for want of shortfalls as detailed 57 43 25/06/16 28/09/2012 Power Industrial area, r Glass Pipelin in SVC Minutes. Menakur(V), e Naidupet(M), SPSR Nellore District M/s. JSW Cements Ltd., Bilakalgudur Clinker & IIPP Deferred for want of shortfalls as detailed 58 44 27/06/16 (V), 25/06/2012 Power Cement 2010-15 in SVC Minutes. Gadivemula(M), Kurnool District Fruit Juices M/s. Srini Food (Packing park Pvt Ltd., & Tetra Mogili Pack, IIPP Deferred for want of shortfalls as detailed 59 45 29/06/16 09/07/2012 Power (V),Bangarupalem Cold 2010-15 in SVC Minutes. (M), Chittoor Storage District and Warehous ing M/s RBA Textiles Pvt Ltd (Expansion), Krishnagiri Road, Trading of IIPP Deferred for want of shortfalls as detailed 60 48 02/07/16 Food Processing Cotton 25/12/2010 Power 2010-15 in SVC Minutes. Industrial Park, Yarn Kuppam (M), Chittoor Dist 61 53 13/07/16 M/s Sri Cotton 05/11/2012 Power IIPP Rs.34,08,620/- (Rupees thirty four :: 90 ::

Ravichandra Yarn open 2010-15 lakhs eight thousand six hundred and Textiles Pvt Ltd., end twenty only) for 2nd half year of 2015- Ponnnekallu (V), 16. Tadikonda Mandal, guntur Dist M/s Sri Sai Balajee Spintex (India ) Pvt Cotton IIPP Deferred for want of shortfalls as detailed 62 54 13/07/16 Ltd., Unnava (V), 14/04/2011 Power Yarn 2010-15 in SVC Minutes. Edlapadu (M), Guntur Dist Rs.1,23,14,924/- (Rupees one crore M/s Kallam Cotton twenty three lakhs fourteen thousand Spinning Mills Spinning, nine hundred and twenty four only) Limited, Weaving Weaving IDP for 2nd half year of 2014-15 including 63 56 13/07/16 Unit, Sy.No. 197, 01/09/2014 Power and 2015-20 deference amount of Rs.47,92,330/- Kunukupadu (V), Processin pertaining to 1st half year of 2015-16. Addanki Mandal, g Prakasam Dist

M/s Sri Lakshmi Narasimha Spinning Mills Cotton IIPP Deferred for want of shortfalls as detailed 64 58 15/07/16 (India) Pvt Ltd., 05/07/2008 Power Yarn 2005-10 in SVC Minutes. Uppalavaripalem, Addanki Mandal, Prakasam Dist Portland Cement, M/s The KCP Alumino Limited (KCP IIPP us Cements) Unit-II, 2005-10 Deferred for want of shortfalls as detailed 65 59 18/07/16 Cement, 29/10/2011 Power Mukthyala (V), Pipelin in SVC Minutes. Slag Jaggaiahpet (M), e Cement Krishna Dist and Similar :: 91 ::

Hydrauli Cements M/s Sri Vaishnavi Spintex (India) Pvt Ltd., Kolanapalli , Cotton IDP Deferred for want of shortfalls as detailed 66 61 18/07/16 18/03/2012 Power Kalla (M), West Yarn 2015-20 in SVC Minutes. Godavari Dist

M/s Idupulapadu Cotton Mills Pvt Rs.37,61,328/- (Rupees thirty seven Ltd., Expansion-5, lakhs sixty one thousand three Cinema Theatre Cotton IIPP 67 62 21/07/16 09/08/2011 Power hundred and twenty eight only) for 1st Road, Yarn 2005-10 quarter of 2015-16. Ganapavaram,

Nadendla Mandal, Guntur Dist M/s Avanthi Feeds Ltd., (Expansion) Shrimp IIPP Deferred for want of shortfalls as detailed 68 64 22/07/16 Sy.No. 746/3A & 07/04/2014 Power Feed 2010-15 in SVC Minutes. 544, Kovvuru (V&M), WG Dist M/s Vasanth Chemicals Pvt Ltd., Plot No. 10 & 10A, Speciality Western Sector, Chemicals APSEZ, IIPP Deferred for want of shortfalls as detailed 69 67 29/07/16 and 27/12/2012 Power Achyuthapuram 2010-15 in SVC Minutes. Pharmace Mandal, uticals Visakhapatnam

M/s SNF India Pvt Liquids, IIPP Deferred for want of shortfalls as detailed 70 69 06/08/16 Ltd., Plot No. 19, Emulsio 09/11/2010 Power 2010-15 in SVC Minutes. JNPC, Parawada, ns & :: 92 ::

Visakhapatnam Powers M/s Rocks Forever Granite Inc., Plot No. 1&2, Marbles IIPP Deferred for want of shortfalls as detailed 71 70 08/08/16 Annangi (V), & 22/07/2012 Power 2010-15 in SVC Minutes. Maddipadu (M), Natural Prakasam Dist Stones M/s Kolar Paper Mills Ltd., Sy.No. 104, 105 and 106, Packaging IDP Deferred for want of shortfalls as detailed 72 74 28/08/16 21/05/2015 Power Parameswaramanga Paper 2015-20 in SVC Minutes. lam (V), Puthur (M), Chittoor Dist Internal Combstio M/s Makrocast Pvt n Piston Rs.37,75,914/- (Rupees thirty seven Ltd (Expansion) , RS Engines lakhs seventy five thousand nine No. 612/2AB, ZP and other IIPP 73 77 01/09/16 03/08/2010 Power hundred and fourteen only) for 1st & Road, Kolavennu parts and 2010-15 2nd half year of 2013-14. (V), Kankipadu (M), Accessorie

Krishna Dist s N.E.C. for Motor Vehicles M/s Ravali Spinners Pvt Ltd., ( Expansion -I), RS No. 13-194, Cotton IIPP Deferred for want of shortfalls as detailed 74 79 06/09/16 Khandavalli (V), 01/01/2009 Power Yarn 2005-10 in SVC Minutes. Peravali (M), WG Dist

M/s Vantage Spinning Rs.2,29,62,310/- (Rupees two crores IIPP 75 80 07/09/16 Spinners Pvt Ltd., (Cotton 12/02/2010 Power twenty nine lakhs sixty two thousand 2005-10 (Original), Yarn / all three hundred and ten only) for 3rd & :: 93 ::

Gollapalli (V), other 4th quarters of 2015-16. Nuzivud Mandal, Fibre Krishna District Yarns) M/s Vantage Spinning Spinners Pvt Ltd., (Cotton (Expansion), Yarn / all IDP Deferred for want of shortfalls as detailed 76 81 07/09/16 22/10/2015 Power Gollapalli (V), other 2015-20 in SVC Minutes. Nuzivud Mandal, Fibre Krishna District Yarns) M/s Gajavalli Cotton Spinning Mills (P) Yarn & Ltd., Narakoduru- IIPP Deferred for want of shortfalls as detailed 77 87 20/09/16 other 21/04/2008 Power Tenali road, 2005-10 in SVC Minutes. Synthetic Chebrole (V) & (M), Yarns guntur Dist M/s Emami Biotech Limited, Sy. No. 501 to 510, Vegetable IIPP Krishnapatnam Oils & 2005-10 Deferred for want of shortfalls as detailed 78 89 23/09/16 Port, Zero Point, 19/02/2012 Power Fats Pipelin in SVC Minutes. Pantapalem (V), Refining e Muthukur M), SPSR Nellore District (1st quarter of 2015-16) M/s. Mandava Cotton Mills Pvt Ltd., Ampapuram Cotton IIPP Deferred for want of shortfalls as detailed 79 93 27/09/16 (V), Bapulapadu 01/03/2008 Power Spinning 2005-10 in SVC Minutes. (M), Krishna District

M/s.Patchala Cotton IIPP Deferred for want of shortfalls as detailed 80 94 28/09/16 Spintex Pvt Ltd., 13/04/2012 Power Yarn 2005-10 in SVC Minutes. Rajupalem (V&M), :: 94 ::

Sattenapalli to Piduguralla High- Way, Guntur District M/s.Patchala Spintex(P)Ltd., Cotton IDP Deferred for want of shortfalls as detailed 81 95 28/09/16 (EXPANSION), 01/05/2015 Power Yarn 2015-20 in SVC Minutes. Rajupalem(V&M), Guntur District M/s.Sudha Agro Oils & Chemical Industries Ltd., Cotton IIPP (Spinning Division), Deferred for want of shortfalls as detailed 82 98 01/10/16 spinning 29/09/2011 Power 2010/1 Valuthimmapuram( in SVC Minutes. in Mill 5 V), Peddapuram(M), East Goadavari M/s. NSL Textiles Ltd., Plot No:4, Cotton IIPP Deferred for want of shortfalls as detailed 83 100 05/10/16 APIIC Park, 31/03/2010 Power Spinning 2005-10 in SVC Minutes. Pulivendula(V&M), YSR Kadapa M/s.Teamec Chlorates Ltd., Plot No:558 &559, Sodium Industrial Growth Chloride IIPP Deferred for want of shortfalls as detailed 84 101 06/10/16 Centre, Gundlapalli 21/02/2012 Power & 2010-15 in SVC Minutes. (V), Maddipadu(M), Hydrogen Prakasam District

M/s. Ranganayaka Cotton IIPP Deferred for want of shortfalls as detailed 85 103 07/10/16 Spinning Mills (P) 10/04/2008 Power Yarn 2005-10 in SVC Minutes. Ltd., Boyapalem(V), :: 95 ::

Edlapadu(M), Guntur District M/s. Ranganayaka Spinning Mills(P) Ltd., Cotton IIPP 86 104 07/10/16 09/04/2010 Power Deferred for want of shortfalls (EXPANSION)Boya Yarn 2005-10 palem(V),Edlapadu( M), Guntur District M/s Idupulapadu Cotton Mils Pvt Ltd Cotton IIPP Deferred for want of shortfalls as detailed 87 105 07/10/16 , Jonnatali (V), 09/08/2011 Power Yarn 2005-10 in SVC Minutes. Martur (M), Prakasam Dist M/s Sree Caustic Rayalaseema Soda Lye IIPP Alkalies and Allied Flakes, 2005-10 Deferred for want of shortfalls as detailed 88 107 15/10/16 Chemicals Ltd., 01/01/2012 Power Chlorine, Pipelin in SVC Minutes. Gondiparla (V), Hydron e Kurnool District Gas HCL

M/s Samyu Glass Pvt Ltd., Plot No. Glass & 11, IDP, IIPP Deferred for want of shortfalls as detailed 89 110 31/10/16 Glass 28/02/2011 Power Gundlamadugu (V), 2010-15 in SVC Minutes. Products Thonduru (M), YSR Kadapa Dist Polished Granites / M/s Krishna Sai Marbles Exports, Slabs IIPP Deferred for want of shortfalls as detailed 90 117 03/11/16 16/03/2011 Power Maddepadu, Tiles, 2010-15 in SVC Minutes. Prakasam District Mounmen t & Articles :: 96 ::

M/s Tulip Granites, Granite IIPP Deferred for want of shortfalls as detailed 91 118 03/11/16 BPSEZ, IBP, Cutting & 13/08/2010 Power 2010-15 in SVC Minutes. Prakasam District Polishing M/s Hues Granites, Granite IIPP Deferred for want of shortfalls as detailed 92 119 03/11/16 BPSEZ, IBP, Cutting & 27/10/2014 Power 2010-15 in SVC Minutes. Prakasam, Polishing Activated Natural M/s.Kanoria Mineral Rs.68,96,530/- (Rupees sixty eight Chemicals & Products, lakhs ninety six thousand five Industries Ltd, Plot Animal IIPP 93 121 03/11/16 06/01/2011 Power hundred and thirty only) for 1st half No:32, JNPC, Black, 2010-15 year of 2014-15 to 1st half year of 2015- Parawada Mandal, Animal or 16. Visakhapatnam Vegetable Fats and Oils

:: 97 ::

II. REIMBURSEMENT OF SALES TAX Annexure –II

Date of Sl. No. Date of Commence Sl. & date Name & Address of Line of Nature of receipt of ment of Policy Decision No. of SVC the unit activity incentives claim commercial Meeting production M/s. Godrej Agrovet Crude Ltd., Unit – 2 Palm Oil, (Existing), RS. No. Crude Rs.85,53,175/- (Rupees eighty five lakhs IIPP 1 225 06/06/16 57, Chintampallem, Palm 09/07/2012 Sales Tax fifty three thousand one hundred and 2010-15 Chintalapudi (M), kernel seventy five only) for the year 2015-16. West Godavari Oil, Palm District Nuts M/s. Godrej Agrovet Crude Ltd., Unit - 2, (Expn- Palm Oil, 1) RS. No. 57, Crude Rs.89,35,020/- (Rupees eighty nine lakhs IIPP 2 228 06/06/16 Chintampallem, Palm 15/06/2013 Sales Tax thirty five thousand and twenty only) for 2010-15 Chintalapudi (M), kernel the year 2015-16 West Godavari Oil, Palm District Nuts Vertified M/s. Silica Ceramica Ceramics IIPP Pvt Ltd., D.No. 97- Tiles and 2005-10 Deferred for want of shortfalls as detailed 3 239 07/06/16 107, Narayanapuram, 11/05/2011 Sales Tax Ceramic Pipe in SVC Minutes. Unguturu (M), West Glazed Line Godavari District Tiles M/s Girnar Packaging, Plot No.11,12 and 13, Spill over Corrugat IIPP Deferred for want of shortfalls as detailed 4 3 Indl. Park, 16/05/2013 Sales Tax case ed Boxes 2010-15 in SVC Minutes. Menakur(V), Naidupet(M), SPSR Nellore District :: 98 ::

M/s.NSL Textiles Ltd., Veeravalli, Spill over Cotton IIPP Deferred for want of shortfalls as detailed 5 5 Bapulapadu 01/01/2009 Sales Tax case Yarn 2005-10 in SVC Minutes. Mandal, Krishna District M/s.NSL Textiles Ltd., RS No.237, Veeravalli, Cotton IIPP Deferred for want of shortfalls as detailed 6 29 15/06/16 01/01/2009 Sales Tax Bapulapadu Yarn 2005-10 in SVC Minutes. Mandal, Krishna District M/s. JC Biotech Pvt Ltd., IGC Bio IIPP Deferred for want of shortfalls as detailed 7 39 23/06/16 Gundlapalli (V), Pharmace 25/05/2011 Sales tax 2010-15 in SVC Minutes. Maddipadu (M), uites Prakasam District M/s. Rockworth Systems(I) Pvt Ltd., Office 800 West Road, RI IIPP 8 40 23/06/16 Modular 19/09/2011 Sales tax Deferred. South Sricity, SEZ, 2010-15 Furniture Satyavedu, Chittoor District Portland Cement, Alumino M/s The KCP us Limited (KCP Cement, IIPP Cements) Unit-II, Slag 2005-10 Deferred for want of shortfalls as detailed 9 60 18/07/16 29/10/2011 Sales Tax Mukthyala (V), Cement Pipelin in SVC Minutes. Jaggaiahpet (M), and e Krishna Dist Similar Hydrauli c Cements :: 99 ::

M/s Vennar Chemicals Ltd., Ceramic IIPP Deferred for want of shortfalls as detailed 10 65 26/07/16 Parikigudem (V), Glazed 01/07/2012 Sales Tax 2010-15 in SVC Minutes. Mandavalli (M), Tiles Krishna Dist M/s SNF India Pvt Liquids, Ltd., Plot No. 19, Emulsio IIPP Deferred for want of shortfalls as detailed 11 68 06/08/16 09/11/2010 Sales Tax JNPC, Parawada, ns & 2010-15 in SVC Minutes. Visakhapatnam Powers M/s Paramesu Biotech Pvt Ltd., Maize IIPP Deferred for want of shortfalls as detailed 12 75 30/08/16 05/01/2015 Sales Tax 972, Devarapalli Starch 2010-15 in SVC Minutes. (V&M), WG Dist M/s. Shri Govindaraja Textiles Pvt Ltd., Rs.3,40,930/- (Rupees three lakhs forty Opp JNTU Engg. Cotton IIPP thousand nine hundred and thirty 13 90 24/09/16 College, Yarn 01/04/2008 Sales Tax 2005-10 only) for the year 2015-16. Peddarangapuram Spinning

(V), Pulivendula (M), YSR Kadapa District Activated Natural M/s.Kanoria Mineral Chemicals & Products, Rs.1,25,68,189/- (Rupees one crore Industries Ltd, Plot Animal IIPP twenty five lakhs sixty eight thousand 14 108 19/10/16 06/01/2011 Sales Tax No:32, JNPC , Black, 2010-15 one hundred and eighty nine only) for Parawada Mandal, Animal or the year 2013-14 & 2014-15. Visakhapatnam Vegetable Fats and Oils

:: 100 :: :: 101 ::

REIMBURSEMENT OF STAMP DUTY: Annexure – III

Date of Sl. No. Date of Commence Sl. & date Name & Address of Line of Nature of receipt of ment of Policy Decision No. of SVC the unit activity incentives claim commercial Meeting production M/s Sai Manasa IIPP Cotton Stamp Deferred for want of shortfalls as detailed 1 114 03/11/16 Spintex, Martur (M) 14/01/2011 2010- Yarn Duty in SVC Minutes. Prakasam District 15

:: 102 ::

ITEM NO: 2 ACTION TAKEN REPORT ON MINUTES OF THE 13th S.L.C. MEETING HELD ON 21/11/2016

Agenda Brief Description of the Issue Decision of the Committee Action Taken Item 1 Confirmation of the Minutes of the previous SLC confirmed the minutes of the Noted. Meeting held on 22/09/2016 with the following previous meeting held on 22/09/2016. amendments: Noted. However, SLC has desired that Meeting has been conducted on the action on Table Agenda pertaining 30/11/2016. to SC/ST incentives to be initiated immediately and completed by 05/12/2016.

Further, SLC decided to write to Letter is being addressed to the Follow up action on the minutes of the previous 2 Government to constitute a Government. Meeting held on 22/09/2016 consultative Committee with all Stake holders, Associations, Officials of Industries Department and AP Food Processing Society to do detailed study on processing of ineligible list related to Food Processing under Annexure-I of IDP – 2015-20. 3 IIPP 2005-10, IIPP 2010-15 & IDP – 2015-20 SLC has examined the Intimation letters have been sent to the schemes – Sanction of reimbursement of stamp duty, recommendations of the Verification / Industries units. reimbursement of land cost purchased in IEs/IDAs, Scrutiny Committee and decided to reimbursement of power cost and sanction of sanction eligible incentives / reimbursement of sales tax - Regarding. concessions to the industrial units ***** where there are no short falls, under

various schemes as detailed below.

Further, SLC discussed the recommendation of SVC for sanction of incentive subject to submition of shortfall documents anda view was taken to put an end of sanctioning subject shortfalls and kept in abeyance. :: 103 ::

Further, a Special SVC is to be conducted within a week in repect of these cases where shortfall submitted and recommend to the ensuing SLC Meeting. Chaiman SLC has essured that a Spcial SLC will be conducted for all these cases.

ABSTRACT OF SANCTION OF INCENTIVES No of Sl. General claims as Amount No. per Incentives (in Rupees ) seriatim (website)

1 Power Cost 26 198972290

2 Sales Tax 4 30397314 Deferred by 3 SLC 122 0

229369604 GRAND TOTAL 152

DETAILS 3. Reimbursement of Power cost Sanctioned: Reimbursement of power cost to (26) units under IIPP & IDP 2015-20 and the list is appended as Annexure – I

4. Reimbursement of Sales tax: Sanctioned to Reimbursement of Sales Tax (4) units under IIPP & IDP 2015-20 and the list is appended as Annexure – II

:: 104 ::

4 STATUS NOTE ON RELEASE OF Noted. Noted. SANCTIONED INCENTIVE / CONCESSIONS OF TO THE INDUSTRIEAL Further, SLC has resolved that the UNITS UNDER IIPP 2005-10, IIPP 2010-15 & Assiciation Members representing SLC IDP 2015-20 AS ON 08/11/2016. will submit separate representation to the Government and persue for Budget

release.

5 STATUS REPORT ON THE PROPOSALS SENT SLC has discussed the issues Noted. TO THE GOVERNMENT AS ON:08/11/2016 regarding proposals pending with Government and decided to request the Government for quick disposal.

Supply. IIPP 2005-10, IIPP 2010-15 & IDP – 2015-20 Decission taken in Item No. 3. Noted. Item schemes – Sanction of reimbursement of stamp No. 1 duty, reimbursement of land cost purchased in IEs/IDAs, reimbursement of power cost and sanction of reimbursement of sales tax - Regarding. ***** Supply. IIPP 2010 – 2015 Scheme – M/s. Rayani Spintex SLC discussed the issue in detail and Sanctioned power cost reimbursement Item (P) Limited, Dhuulipalla (V), Sattenapalli (M), decided to accord permission for was released to the unit through No. 2 Guntur district – Permission for change of change of Financial Institutaion from RTGS/NEFT to City Union Bank Financial Institution of the unit – Regarding. UCO Bank Limited, Arundalpet, Ltd., Main Branch, Guntur. Guntur to City Union Bank Ltd., Main Branch, Guntur. Supply. Incentives / Concessions Under IIPP 2005-10 & SLC examined the issue. The Unit inspected by the Committee on Item 2010-15 Schemes – reimbursement of power cost Chairman of SLC requested the 09/12/2016 and submitted its report. No. 3 to M/s Spin Cot Textiles Pvt Ltd., - revival of the members to give their views on this The Committee is of opinion that SLC unit – issue of Government orders vide issue. The representative of FAPSIA may take a view to release the amount G.O.Ms.No.388 Industries & Commerce (P&I) opined that the unit has to be inspected directly to DISCOM by obtaining Department dated 28.08.2015 - Release of along with other member of the concurence from the court receiver by sanctioned amount to the industrial unit from the Association. The representatives of the GM, DIC by deputing the Officer to amount available in PD Account of Spinning Mills Association and AP Mumbai to meet court receiver in Commissioner of Industries.– Regarding. Chamber of Commerce & Industry person. Federation also supported the openion The GM,DIC, Guntur District has of FAPSIA Member. reported that he has contacted the Court receivers, Mumbai over phone and they :: 105 ::

Accordingly, SLC decided to have confirmed the receipt of mail. He constitute a SLC-Sub Committee with also stated that the Court receiver will the following members to inspect the communicate the next course of action unit and submit report on working on the matter. status and justification for transfer of Further the GM,DIC, Guntur has informed funds to jointly operated account: that the Tax Recovery Officer, Guntur has

7. Sri B. Suresh Babu, Additional issued a Notice to the Branch Manager, Director of Industries. Central Bank of India, Gottipadu stating 8. Representative of SLBC that M/s.Spin Cot Textiles is due of 9. Representative of APSFC Rs.3.54 Crores to them and directed to 10. Representative of AP Spinning hold and pay the amount, if any held by Mills Association. the unit in the Bank or due to the unit by 11. Representative of FAPSIA the Bank. 12. Representative of FTAPCCI He also informed that an amount The above conistitued Committee of Rs.1.00 Crs is available in the Bank as a inspect the unit immedatly and submit fixed deposit in the joint account it’s report to Director of Industries. operated by the MD of the unit and the

Further, SLC has resolved to authorise GM, DIC, Guntur, towards the payment to the Director of Industries to take the Court receiver. decision based on the report of the In view of the above a letter was Committee, subject to ratification from addressed to the concerned SLC. Commissioner Income Tax with a request, for not to attach the said account as the money was released by Government, for revival of the unit as special Case.

Supply. IIPP 2005-10 - M/s Jaypee Balaji Cement Plant, SLC discussed the issue in detail and Sanctioned incentive amount is yet to Item Rs No: 99, Budawada (V), Jaggaiahpet (M), decided to release the subsidy amount be released, since there is a No. 4 Krishna Dist –Release the subsidy to South Indian to the unit’s Term Loan account in discripency on the Ternm loan bank in Bank, Corporate Br, Hyderabad instead of Axis Axis Bank, which is lead bank as per the Assignment letter and lead bank. Bank, Chillakallu Br, Krishna Dist - Requested - operational guidelines under IIPP Regarding. 2005-10.

:: 106 ::

Supply. IIPP 2010 – 15 – M/s. Shri Govindaraja Textiles SLC discussed the issue in detail and Proposals submitted to the Item Limited, Opp. JNTU Engg. College, decided to seek the clarification from Government for clarification. No. 5 Peddarangagapuram (V), Pulivendula (M), YSR the Government on the implementation of Special G.O. Ms. District – Sanction of reimbursement of Sales Tax No. 26 Ind. & Com. (Tex) Dept., dated – Regarding. 12/01/2012 on sanction and release of incentives to the unit in reference to the commitment made by the unit in their representation and the effective date of implementation of G.O in order to have clarity. Supply. IIPP 2005-10 - M/s South India Krishna Oil And SLC discussed the issue in detail and Addressed a letter to the SLBC for Item Facts Pvt Ltd, Sy No: 272, 279, 280 & 281, decided to release the subsidy amount clarification whether the Term loan / No. 6 Epudu Bit 1-B Pntapalam (V), Muthukur (M), to the unit’s Term Loan Account of Current loan can be operated from the SPSR Nellore Dist –Release the subsidy to HSBC, Chennai Branch as the same same Account, as per the Banking HSBC, Chennai Br instead of HSBC, New Delhi Branch certified the Plant & regulations, which is required to Br - Requested - Regarding. Machinery as per operational release the sanctioned incentives to the guidelines of IIPP 2005-10. unit account maintained in HSBC.

However, this issue was placed in the SVC Meeting held on 10/03/2017 and discussed in detail. SLBC represenetative has informed that the Term Loan and Current Account cannot be operated with a single Account number and there should be a separate account numbers for Term Loan and Current Account. The Term Loan can be linked to the Current Account for recovery of the loan amount.

In view of the above, it is decided to refer the matter to a Commettee with the following members:

1. Representative of SLBC. :: 107 ::

2. Representatives of HDFC/ICICI/Axis Bank. 3. Representative of APSFC. 4. Additional Director, Industries Department

Supply. IIPP 2010-15 Scheme – M/s. Rockworth Systems SLC discussed the issue and decided The issue is placed before SLC for Item Furniture (India) Pvt. Limited, 800 West Road, to defer the issue. taking a view. No. 7 R1 South Sricity Sez., Satyavedu, Chittoor district – Sanction of Reimbursement of Power cost and Sales Tax – Regarding.

Supply. IIPP 1015 – 20 – M/s. Kallam Brothers Cottons (P) SLC discussed the issue and decided Shortfall documents received the GM, Item Limited, (Expansion), D. No. 160 B, Dhulapalla (V), to sanction after submission of the DIC. The same was processed duly No. 8 Sattenapalli (M), Guntur district – Revised the base – following shortfall information: fixing the base power consumption as As per CA certificate – Regarding. 658529 units per month and its will be placed before next SVC Meeting. 1. Land sale deed or lease deed 2. Board resolution authorizing the person to sign 3. T&CP Dept., Factories Dept., Grampanchayat approved plans 4. Land conversion certificate 5. Reimbursement of power cost release certificate 6. Statement of Accounts 7. Reasons for increase in Reimbursement of power cost load from DCP to present claim.

Supply. Incentives under IIPP 2010-15 – Condonation of SLC discussed the issue in detail and The Committee was discussed the Item break in production to M/s SBQ Steels Ltd., decided to ratify the action in issue on 17/01/2017 and submitted its No. 9 Ankalapaturu (V), Chilakuru Mandal, SPSR constitution of SLC Sub-Committee report. Committee opined that with the following member: physical inspection of the unit is Nellore District 6. Additional Director of Industries essential by the Committee members - Chairman to arrive the genuinity of the reasons

7. Executive Director of APSFC for the break in production from - Member 01.01.2014 to 31.03.2015, especially :: 108 ::

8. Representative of Commissioner, to examine the load restrictions Vs Commercial Tax Dept - load utilized during break in period Member and the sourcing of Iron ore. 9. Representative of AP Trans Co / DISCOM - Member 10. Representative of Director of Mines and Geology - Member

Further, SLC has taken a decision to include the representative of FTAPCCI & CII which are the representative obody of Large & Mega industries. Supply. IIPP 2005 – 10 – M/s. NSL Textiles Limited, Sy. SLC discussed the issue. The Noted and released the sanctioned Item No. 371 – 382, Kuchalavaripalem (V), Chairman has requested the members incentives amount accordingly. No. 10 Cherukapali (M), Guntur district – Release of the to give their openion on this issue. The representative of AP Spinning Mills sanctioned reimbursement of power cost amount Association has informed that as Trust to the unit – Regarding. and Retention account (TRA) is maintained by the Term Loan Institution-Canara Bank for all units, SLC has ratified the action of releasing incentives to the Company’s Trust and Retention account (TRA)

maintained with Canara Bank, Prime Corporate Branch, Banglore on behalf of all the 11 consortium as the same Bank is Term Loan lending institution for all the 11 units. Supply. IIPP-2010-15 – Application of M/s. Chandu SLC discussed the issue and decided Permission has been accorded to the Item Harvestor, D. No. 4-63, Malakapalli Village, to accord permission for change of unit. No. 11 Tallapudi Mandal, West Godavari District for constitution of the unit from permission for Change of Management from Partnership to Propietory. Partnership firm to Proprietrix– Regarding.

:: 109 ::

Table Target 2000 Scheme - M/s. Coastal Agro SLC discussed the issue in detail and Committee, yet to inspect the unit. Item Industries Ltd.Unit-II, K.Savaram, Tanuku (M), decided to constitute SLC Sub- No. 12 West Godavari District - Inclusion of the Committee with the following Additional Line of activity in the Final Eligibility member: Certificate - Regarding. 6. Additional Director of Industries - Chairman 7. Representative from APSFC - Member 8. Representative from Commercial Tax Dept - Member 9. Representative from AP Paper Mills Association.

10. Representative from FAPSIA

In view of the urgency due to recommendation of recovery of Sales Tax Deferment (availed by the unit) availed, by the AG of Commercial Taxes Department, SLC desired that the Committee shall inspect the unit and submit its report before 10/12/2016.

General General observations While concluding the SLC Meeting, Noted. the Chairman SLC informed all the Members that this may be last SLC Meeting for claims file manually. Online filing of incentives is very active and the next SVC/SLC will be conducted to the screens derived from online system.

Further, Chairman SLC has requested Members yet to submit the details. all the SLC Members to give the details of persons nominated on permanent basis so as to give digital :: 110 :: signature/one time password (OTP) so as to process and scrutiny the incentives claims through online.

Chairman of SLC assured that all the It is under process. pending release proposals will be cleared within 7 days.

Chairman of SLC further assured that Addressed a letter to CMD of the action for getting installments to APSPDCL (copy of letter is the Sick unit M/s. Seapearl Industries appended). as represented by ALEAP will be immediately taken by writing to CMD of APSPDCL.

:: 111 ::

ITEM NO: 3

IIPP 2005-10, IIPP 2010-15 & IDP – 2015-20 schemes – Sanction of reimbursement of stamp duty, reimbursement of land cost purchased in IEs/IDAs, reimbursement of power cost and sanction of reimbursement of sales tax - Regarding. *****

The Verification / Scrutiny Committee meeting held on 17/01/2017 & 10/03/2017 has verified / Scrutinized (58) claim applications of reimbursement of power cost, (4) claim application of reimbursement of sales tax, (1) claim application of reimbursement of interest subsidy & (3) claim application of reimbursement of stamp duty as per the Guidelines under respective schemes and recommended for sanction/rejection of eligible Incentives / Concessions to the units. The Minutes of Verification / Scrutiny Committee of Power cost are appended as Annexure – I & II.

ABSTRACT

No. of claims as Sl. No of General Incentives per Amount No units (in Rupees ) seriatim (website) 1 Power Cost 18 16 432980902

2 Sales Tax 3 3 173145428

3 Interest Subsidy 1 1 86541396

Stamp Duty 2 2 2130164

Deferred by SVC & 2 Repeated cases 42 37 0

GRAND TOTAL 66 59 694797890

69.48 Crores The Verification / Scrutiny Committee of Investment Subsidy and Sales Tax have recommended for sanction / rejection of eligible Incentives/concessions to the units as mentioned below:

:: 112 ::

1. SANCTION OF REIMBURSEMENT OF POWER COST: Date of Commence Sl. No. & Date of Sl. Date of Name & Address Line of ment of Nature of receipt of Policy Decision No. SVC of the unit activity commercial incentives claim Meeting production

SVC verified the shortfall documents submitted by the General Manager, District Industries Centre and M/s Sri Vaishnavi recommended for sanction of Spintex (India) Pvt 31, Cotton IDP Rs.64,94,470/- (Rupees sixty four 1 04/01/2016 Ltd., Kolanapalli , 18/03/2012 Power 17/01/17 Kalla (M), West Yarn 2015-20 lakhs ninety four thousand four Godavari Dist hundred and seventy only) for 2nd half year of 2015-16 including deference amount of Rs.11,69,170/- pertaining to 1st half year of 2015-16. SVC examined the issue pertaining to Land Conversion and decided to place before SLC all similar cases as special Agenda in light of Minutes of its Meeting held on 03/03/2017. M/s.Ravali Spinners

Pvt Ltd., (Expan-1), Cotton IIPP SVC verified the claim and 2 1, 10/03/17 18/04/2016 Khandavalli (V), 01/01/2009 Power recommended for sanction of Peravali (M), West Yarn 2005-10 Rs.96,42,350/- (Rupees ninety six Godavari District lakhs forty two thousand three hundred and fifty only) for 4th quarter of 2015-16 and 1st quarter of 2016-17, subject to confirmation of SLC. SVC verified the shortfall documents M/s. Guntur submitted by the General Manager, Spinning Mills (P) Cotton IIPP District Industries Centre and noticed 3 1, 17/01/17 03/06/2016 Ltd, Obulanaidu 12/04/2007 Power that the following shortfalls are palem (V), Guntur Yarn 2005-10 required for processing the claim and (M) & District advised to obtain the same from :: 113 ::

General Manager, District Industries Centre with proper attestation: 1. Confirmation on installation of additional machinery in view of increase in power load.2. Land sale deed.3. Valid CFO from APPCB 4. Approved project report.6. Signature of authorized person not attested in board resolution / authorization and not indicated the name of person in the claim application.7. DT&CP Dept and Factories Dept Plans.8. Bank Sanctioned letter 9. Banker has not attested as machinery as per guidelines.10. Valid CFO from APPCB.11. There is increase in power load from 600KVA to 2240KVA.12. CA certificate for share holding. SVC verified the shortfall documents submitted by the General Manager, District Industries Centre and noticed M/s. Sri Venkata that the following shortfalls are not Siva Parvathi Cotton submitted and advised to obtain the Spinning Mills (P) Yarn & IIPP same from General Manager, District 4 2, 17/01/17 07/06/2016 Ltd., (1st 10/01/2007 Power Industries Centre: 1) Reasons for Expansion), GBC Synthetic 2005-10 increase of Power Load. 2)Land Road, Chebrolu Yarn Conversion certificate 3) Approved (V&M), Guntur Dist Project report 4) Grampanchayath approved plans 5) Factories Dept approved plans 6) DT&CP approved plans Vertified M/s. Silica Ceramica SVC examined the claim and Ceramics recommended for sanction of Pvt Ltd., D.No. 97- Tiles and IIPP 5 2, 10/03/17 07/06/2016 107, Narayanapuram, 11/05/2011 Sales Tax Rs16,02,03,314/- (Rupees sixteen Unguturu (M), West Ceramic 2005-10 crores two lakhs three thousand Godavari District Glazed three hundred and fourteen only) Tiles for the year 2015-16 M/s. Tirumala Wind IDP SVC examined the claim and 6 3, 10/03/17 18/07/2016 Cotton & Agro Stamp Duty recommended for rejection, the line of Products Pvt Ltd, Power 2015-20 activity of Wind Power is not eligible :: 114 ::

Ananthapur District for sanction of reimbursement of Stamp Duty under IDP 2015-20. SVC verified the shortfall documents submitted by the General Manager, District Industries Centre and noticed that the following shortfalls are M/s. Amoda Spintex required for processing the claim and Ltd, Ravikampadu Cotton IIPP advised to obtain the same from 7 3, 17/01/17 09/08/2016 08/08/2007 Power (V), Jaggaiahpet (M), Yarn 2005-10 General Manager, District Industries Krishna District Centre: 1) Detailed report on the unit added any additional machinery and whether the unit utilized any additional power consumption include in the recommended claim or not SVC verified the shortfall documents submitted by the General Manager, District Industries Centre and noticed that the following shortfalls are M/s. Gemini Edibles Refining required for processing the claim and and Fats India (P) Cin advised to obtain the same from Ltd., S.No.1607/2, Fractctionn IIPP General Manager, District Industries 8 4, 17/01/17 22/08/2016 Industrial Park, 23/09/2010 Power Centre: 1. Boiler certificate 2. Pantapalem (V), ation of 2005-10 List of Plant & Machinery duly SPSR Nellore Vegetable certified by GM, DIC and Financial District Oils Institution as per operational guidelines. 3. CA certificate indicating the share holding of directors (all the copies should attested) SVC verified the claim and M/s Paramesu recommended for sanction of 11, Biotech Pvt Ltd., Maize IIPP Rs.32,97,165/- (Rupees thirty two 9 30/08/2016 05/01/2015 Sales Tax 10/03/17 972, Devarapalli Starch 2010-15 lakhs ninety seven thousand one (V&M), WG Dist hundred and sixty five only) for the year 2015-16 SVC verified the shortfall documents M/s. NSL Textiles submitted by the General Manager, Ltd, Inkollu (V & Cotton IIPP 10 5, 17/01/17 06/09/2016 01/01/2008 Power District Industries Centre and noticed M), Prakasam Spinning 2005-10 that the following shortfalls are Dstrict. required for processing the claim and :: 115 ::

advised to obtain the same from General Manager, District Industries Centre: 1) IEM Part-B ,2) Factories Dept approved Plan 3) land conversion 4) Approved Project report 5) Valid CFO 6) Factories Dept approved plan 7) DT&CP dept approved plan 8) M/c statement as per guideline 9) Statement of accounts 10) Base power loan as per report duly attested by GM, DIC SVC verified the shortfall documents M/s. Sai Global submitted by the General Manager, Yarntex India (India) District Industries Centre and noticed Pvt Ltd, Sy No: Cotton that the following shortfalls are 103/1A, 107, 133, Yarn & IIPP 11 6, 17/01/17 07/09/2016 01/04/2007 Power required for processing the claim and 143/1, 143/2 & Synthetic 2005-10 advised to obtain the same from 143/3, Vellampalli Yarn General Manager, District Industries (V), Maddipadu (M), Centre: 1) DT&CP Dept approved Prakasam Dstrict. Plans 2) Land conversion certificate SVC verified the shortfall documents submitted by the General Manager, District Industries Centre and M/s Sree Costic soda recommended for sanction of Rayalaseema Lye Flakes Rs.17,31,29,220/- (Rupees seventeen Alkalies and Allied , Chlorine , IIPP crores thirty one lakhs twenty nine 12 7, 17/01/17 07/09/2016 01/01/2012 Power Chemicals Ltd., Hydrogen 2005-10 thousand two hundred and twenty Gondiparla (V), gas M3 only) for 4th quarter 2015-16 and Kurnool District HCl Rs.16,08,17,468/- (Rupees sixteen crores eight lakhs seventeen thousand four hundred and sixty eight only) for 1st quarter of 2016-17. SVC verified the shortfall documents M/s. Thatavarthi submitted by the unit holder and Aapparels Ltd., noticed that the following shortfalls Appapuram Road, Cotton IIPP are required for processing the claim 13 8, 17/01/17 08/09/2016 20/05/2011 Power Kavuru (V), Yarn 2010-15 and advised to obtain the same from Chilakaluripet (M), General Manager, District Industries Guntur District Centre with proper attestation:1. Grampanchayath, Factories and :: 116 ::

DT&CP Dept approval . 2 Land conversion certificate 3.CE certificate 4.Approved project report 5. Original list of Plant & Machinery as per operational guidelines 6. Valid CFO from APPCB. SVC verified the shortfall documents submitted by the General Manager, District Industries Centre and noticed that the following shortfalls are M/s. Mittapalli required for processing the claim and Spinners Limited, Cotton IIPP advised to obtain the same from 14 9, 17/01/17 12/09/2016 Chinaturakapalem 29/12/2011 Power General Manager, District Industries (V), Narasaraopet Yarn 2010-15 Centre:1) DT& CP department (M). Guntur Dist approved plans. 2) Valid CFO from APPCB, 3) List of Plant machinery as per operational guidelines under IIPP 2010-15 SVC verified the shortfall documents M/s. Smilax submitted by the General Manager, Laboratories Ltd., District Industries Centre and 10, Cotton IIPP 15 14/09/2016 Plot No.70, JNPC, 12/06/2009 Power recommended for sanction of 17/01/17 Yarn 2005-10 Parawada, Rs.3,12,16,050/- for the period from Visakhapatnam 2nd quarter of 2009 -10 to 4th quarter of 2013-14. SVC verified the shortfall documents submitted by the General Manager, District Industries Centre and noticed that the following shortfalls are M/s. Gowthami required for processing the claim and Spintex (India) Ld., 12, Cotton IIPP advised to obtain the same from 16 21/09/2016 Duvva, Tanuku (M), 08/09/2011 Power 17/01/17 General Manager, District Industries West Godavari Yarn 2005-10 Centre:1. Registered Land Sale Deed District 2) Grampanchayath approved plans 3) DT&CP approved plans 4) List of Meachinery not as per guidelines 5) Approved project report M/s The Gowthami Cotton 14, IIPP SVC verified the shortfall documents 17 21/09/2016 Solvent Oilss Ltd, Yarn / 04/07/2017 Power 17/01/17 2010-15 submitted by the General Manager, Satyawada Road, Synthetic District Industries Centre and noticed :: 117 ::

Tetali (V), Tanuku Yarn that the following shortfalls are (M), W.G Dist required for processing the claim and advised to obtain the same from General Manager, District Industries Centre:1) IEM Part-B , 2) Grampanchyath approval Plan 3) DT&CP approval plan 4) Land Conversion certificate 5) Statement of Accounts as per guidelines along with Andhra Bank Certificate 6) List of Plant & Machinery as per guidelines 7) Project report SVC verified the shortfall documents submitted by the General Manager, District Industries Centre and noticed M/s. Sri Nukala that the following shortfalls are Rama Koteswara required for processing the claim and Rao Textiles Pvt advised to obtain the same from 16, Ltd., D.No: 1-233, Cotton IIPP 18 04/11/2016 26/03/2010 Power General Manager, District Industries 17/01/17 GBC Road,Chebrolu Yarn 2005-10 Centre:1. Land documents, 2, Board (V&M), Guntur resolution 3. Grampanchayat District Factories, and DT&CP Dept approved (EXPANSION) plans 4.CFO from APPCB, 5. Approved project report 6. Land conversion certificate. SVC verified the shortfall documents submitted by the General Manager, M/s Kalpataru District Industries Centre and noticed Spinning Mills (P) that the following shortfalls are 17, Ltd (Exp) S No: 210, Cotton IIPP required for processing the claim and 19 15/11/2016 01/06/2012 Power 17/01/17 211/A, thimmapuram Yarn 2010-15 advised to obtain the same from (V), Edlapadu (M), General Manager, District Industries Guntur Dis t Centre:1) IEM Part -B for Expansion project 2) DT&CP approved Plan. 3) Factories Dept approved Plan M/s. Sudha Agro & SVC verified the shortfall documents Chemicals Ins. Ltd., submitted by the General Manager, 18, Cotton IIPP 20 25/11/2016 (Spinning Dvision), 29/09/2011 Power District Industries Centre and noticed 17/01/17 Valuthimmapuram Yarn 2010-15 that the following shortfalls are (V), Peddapuram required for processing the claim and :: 118 ::

(M), E.G.Dist. advised to obtain the same from General Manager, District Industries Centre:1) List of Plant & machinery as per guidelines 2) DT &CP Approved plans. SVC verified the shortfall documents submitted by the General Manager, M/s Tirumala Cotton District Industries Centre and noticed Agro Products (P) that the following shortfalls are 19, Ltd, Thimmapuram Cotton IIPP required for processing the claim and 21 25/11/2016 05/10/2012 Power 17/01/17 (V), Yarn 2010-15 advised to obtain the same from Chilakaluripet(M), General Manager, District Industries Guntur District Centre:1. DT&CP approval along with plans.

SVC verified the shortfall documents submitted by the General Manager, M/s. SVR Spinning District Industries Centre and Mills (P) Ltd., 20, Cotton IIPP recommended for sanction of 22 26/11/2016 Malleswaram, 23/12/2011 Power 17/01/17 Rs.30,55,400/- (Rupees thirty lakhs Peravali (M), West Yarn 2010-15 fifty five thousand and four hundred Godavari District only) for the period 2nd half year of 2015-16. M/s Girnar SVC examined the claim and decided Packaging, Plot to defer for want of following shortfall No.11,12 and 13, Corrugated IIPP documents:1.Board resolution 23 5, 10/03/17 28/11/2016 Indl. Park, 16/05/2013 Sales Tax authorizing the person to sign 2. Menakur(V), Boxes 2010-15 Company incorporation 3. Valid Naidupet(M), SPSR Boiler certificate 4.Valid CFO from Nellore District APPCB. M/s A.S. Jute Products Pvt Ltd., Jute, Yarn, (Existing), Sy.No. Twine, IIPP SVC examined the claim and 24 6, 10/03/17 28/11/2016 20/2 & 21, 28/03/2012 Power recommended for sanction of Rs. Narlavalasa (V), Gunny 2010-15 6,86,160/- (Rupees six lakhs eighty Padmanabham (M), Bags six thousand one hundred and sixty Visakhapatnam only) for 1st half year of 2015-16. M/s. Hindustan SVC verified the shortfall documents 21, Container IIPP 25 02/12/2016 National Glass & 28/09/2012 Power submitted by the General Manager, 17/01/17 Industries Ltd, Glass 2005-10 District Industries Centre and noticed :: 119 ::

Meenakur (V), that the following shortfalls are Naidupeta (M), required for processing the claim and SPSR Nellore advised to obtain the same from District General Manager, District Industries Centre with proper attestation:1 Company incorporation 2) Factories Dept approved plans 3) Valied CFO 4) CA Certificate 5) Reason for increase power load, 6) Land conversion. SVC verified the shortfall documents submitted by the General Manager, M/s. Jyothirmaye District Industries Centre and Textiles (P) Ltd., 22, Cotton IIPP recommended for sanction of 26 05/12/2016 Gorijavolu (V), 04/02/2011 Power 17/01/17 Rs.42,93,794/- (Rupees forty lakhs Nadendla (M), Yarn 2010-15 ninety three thousand seven Guntur District hundred and ninety four only) for 2nd Half Year of 2015-16 M/s. Sri Teja Bio SVC examined the claim and Fuels Pvt Ltd, ENT IDP recommended for sanction of 27 8, 10/03/17 07/12/2016 Annadevarapeta (V), 27/05/2015 Stamp Duty Rs.3,82,224/- (Rupees three lakhs Tadepalli (M), West Granis 2015-20 eighty two thousand two hundred Godavari District and twenty four only). SVC verified the shortfall documents submitted by the General Manager, M/s. Patchala District Industries Centre and noticed Spintex (P) Ltd., that the following shortfalls are 23, Cotton IIPP 28 08/12/2016 (Existing), 13/04/2012 Power required for processing the claim and 17/01/17 Rajupalem (V & M), Yarn 2010-15 advised to obtain the same from Guntur Dist General Manager, District Industries Centre:1) List of Plant & Machinery as per guidelines SVC verified the shortfall documents submitted by the General Manager, M/s. Patchala Cotton District Industries Centre and noticed Spintex (P) Ltd., that the following shortfalls are 24, Yarn & IIPP 29 08/12/2016 (Expansion), 01/05/2015 Power required for processing the claim and 17/01/17 Rajupalem (V & M), Synthetic 2010-15 advised to obtain the same from Guntur District Yarn General Manager, District Industries Centre:1) List of Plant & Machinery as per guidelines :: 120 ::

SVC verified the shortfall documents submitted by the General Manager, District Industries Centre and noticed that the following shortfalls are M/s. Rayani Spintex required for processing the claim and 25, (P) Ltd., Dhulipalla Cotton IIPP 30 08/12/2016 16/11/2011 Power advised to obtain the same from 17/01/17 (V) Sattenapalli (M), Yarn 2010-15 General Manager, District Industries Guntur District Centre:1) Detailed report on reasons for increasing the power load from DCP to present claim 2) DT & CP Approved plans SVC verified the shortfall documents submitted by the unit holder and noticed that the following shortfalls are required for processing the claim M/s RBA Textiles and advised to obtain the same from Pvt. Ltd. (Existing), General Manager, District Industries Krishnagiri Road, Trading of Centre with proper attestation:1. Bank 26, IIPP 31 13/12/2016 Food Processing Cotton 06/11/2008 Power Term Loan Sanctioned letter 2) 17/01/17 2005-10 Industrial Park, Yarn Company incorporation 3) List of Kuppam (M), Plant & Machinery as per operational Chittoor Dist guidelines 4) Grampanchayath, DT&CP dept approval 5) CA Certificate for share holding 6) valid CFO issued APPCB 8) Project report 9) Reasons for increasing the power SVC verified the shortfall documents submitted by the unit holder and noticed that the following shortfalls M/s. RBA Textiles are required for processing the claim Pvt. Ltd., and advised to obtain the same from (Expansion), Trading of General Manager, District Industries 27, Krishnagii Road, IIPP Centre with proper attestation:1. Land 32 13/12/2016 Cotton 25/12/2010 Power 17/01/17 Food processing 2010-15 sale deed 2) Company incorporation Park, Kuppam Yarn 3) Board resolution authorizing sing 4) (V&M), Chittoor Grampanchayath, DT&CP dept Dist approval 5) Land conversion approval 6) valid CFO issued APPCB 8) Project report 9) CA certificate 10) reasons for increasing the power :: 121 ::

M/s. BMM Cements SVC examined the claim and decided Ltd., Gudipadu (V), IIPP to defer for want of following shortfall 33 9, 10/03/17 13/12/2016 Power Yadiki (M), 2010-15 documents: 1.DT & CP approved Anantapur District plans. SVC verified the shortfall documents M/s. PVR Spinning submitted by the General Manager, and Weaving Ltd. District Industries Centre and noticed (Expansion), that the following shortfalls are R.S.No.110/2, Trading of required for processing the claim and 28, IIPP 34 19/12/2016 108/2,3,4, Cotton 27/08/2010 Power advised to obtain the same from 17/01/17 2005-10 Kondayapalem Road, Yarn General Manager, District Industries Tetali (V), Tanukum Centre:1) DT&CP approved plans. (M), West Godavari District

SVC examined the claim and decided to defer for want of following shortfall documents: 1.As per the IEM Part – B, M/s. Chowdary the DCP of the unit is 22/03/2008. But Spinners Ltd. the GM, DIC has recommended the (Expansion), 1-168, Cotton 10, IIPP claim as DCP on 31/07/2007. Hence, 35 19/12/2016 Chivatam (V), yarn 31/07/2007 Power 10/03/17 the GM, DIC to submit a detailed Undrajavaram (M), 2005-10 spinning report on ambiguity on the DCP. 1. West Godavari IEM par – B acknowledgement issued District by GoI. 3. DT & CP approval along with plans. 4. Registered land sale deed. SVC examined the claims in detailed along with members from SLBC & APSFC and recommended for M/s Kallam Spinning Spinning, sanction of Rs.8,65,41,396/- (Rupees Mills Ltd, 12, Weaving Interest IDP eight crores sixty five lakhs forty 36 21/12/2016 Kunukupadu(V), 01/09/2014 10/03/17 one thousand three hundred and Addanki (M), and Subsidy 2015-20 ninety six ony) for 1st & 2nd half year Prakasam District. processing of 2015-16. Further, SVC advised to process all the similar claim in the same formate. M/s. Avanthi Feeds, SVC verified the shortfall documents 29, Cotton IIPP 37 28/12/2016 Unit -3, R.S. No. 07/04/2014 Power submitted by the General Manager, 17/01/17 544/2, 544/1B, Yarn 2010-15 District Industries Centre and :: 122 ::

545/3B, 545/5, recommended for sanction of 746/3A, Kovur V & Rs.35,92,000/- (Rupees thirty five M, West Godavari lakhs and ninety two thousand only) District for 2nd half year of 2015-16. SVC verified the shortfall documents M/s. Sri Mouli submitted by the General Manager, Textiles pvt. Ld., Sy. 30, Cotton IIPP District Industries Centre and 38 29/12/2016 No. 22/A, 22/B & 10/05/2017 Power 17/01/17 recommended for sanction of 25, Prathipadu Yarn 2010-15 Rs.24,83,800/- for the period of 2nd (V&M), Guntur Half Year of 2015-16 SVC verified the shortfall documents submitted by the M/s. Kolar Paper General Manager, District Mills Ltd., Industries Centre and Sy.No.104, 105 & 32, Packaging IIPP recommended for sanction of 39 05/01/2017 106, 21/05/2015 Power 17/01/17 Parameswaramangal Paper 2010-15 Rs.82,02,198/- (Rupees eighty two am (V), Puttur (M), lakhs two thousand one hundred Chittoor District and ninety eight only) for the period 1st & 2nd half year of 2015-16 SVC verified the shortfall documents submitted by the General Manager, M/s Supriya District Industries Centre and noticed Spinning Mills (P) that the following shortfalls are 33, Ltd, (Exp) Cotton IIPP 40 05/01/2017 22/02/2012 Power required for processing the claim and 17/01/17 Boyapalem (V), Spinning 2005-10 advised to obtain the same from Edlapadu (M)Guntur General Manager, District Industries Dist Centre:1 DT&CP approval along with plans SVC verified the shortfall documents submitted by the General Manager, District Industries Centre and noticed M/s Nandhivadhana that the following shortfalls are Textiles Mlls (P) Ltd, 34, Cotton IIPP required for processing the claim and 41 05/01/2017 NH-5, thimmapuram 25/09/2010 Power 17/01/17 advised to obtain the same from (V), Edlapadu (M) Yarn 2005-10 General Manager, District Industries Gnntur Centre:1 DT&CP approval along with plans 2) Land conversion certificate

:: 123 ::

SVC verified the shortfall documents submitted by the General Manager, M/s Ranganayaka District Industries Centre and noticed Spinning Mills (P) that the following shortfalls are 35, Ltd, (Exp) Cotton IIPP required for processing the claim and 42 05/01/2017 09/04/2010 Power 17/01/17 Boyapalem (V), Yarn 2005-10 advised to obtain the same from Edlapadu (M), General Manager, District Industries Guntur Dist Centre:1 DT&CP approved plans 2) C.E. Certificate.

SVC verified the shortfall documents submitted by the M/s Ranganayaka General Manager, District Spinning Mills (P) Industries Centre and 36, Ltd, (Existing) Cotton IIPP 43 05/01/2017 10/04/2008 Power recommended for sanction of 17/01/17 Boyapalem (V), Yarn 2005-10 Edlapadu (M), Rs.6,40,483/- (Rupees six lakhs Guntur Dist forty thousand four hundred and eightythree only) for 10 days of 4the quarter of 2015-16. M/s. Sri Venkateswara Spintex (P) Ltd., SVC verified the claim and 13, D.No:20&21, Cotton IIPP recommended for sanction of 44 05/01/2017 04/12/2011 Power 10/03/17 Narasaraopet Road, Yarn 2010-15 Rs.52,58,245/- (Rupees fifty two Kavuru(V), lakhs fifty eight thousand two Chilakaluripet (M), hundred and forty five only) for 2nd Guntur District half year of 2015-16. SVC examined the issue pertaining to Land Conversion and decided to place before SLC all similar cases as special Agenda in light of Minutes of its M/s.Ravali Spinners Meeting held on 03/03/2017. Pvt Ltd., (Expan-2), Reimburse- 14, Cotton IIPP 45 07/01/2017 Khandavalli (V), 20/11/2010 ment of 10/03/17 SVC verified the claim and Peravali (M) W G Yarn 2010-15 power cost recommended for sanction of District Rs.62,49,710/- (Rupees sixty two lakhs forty nine thousand seven hundred and ten only) for 2nd half year of 2015-16 :: 124 ::

Vertified SVC verified the claim and M/s. Silica Ceramica Ceramics Pvt Ltd., D.No. 97- Reimburse IIPP recommended for sanction of 16, Tiles and 46 14/02/2017 107, Narayanapuram, 11/05/2011 ment of 2005-10 Rs.82,42,540/- (Rupees eighty two 10/03/17 Ceramic Unguturu (M), West Power cost Pipe Line lakhs forty two thousand five Godavari District Glazed hundred and forty only) for the Tiles period of 4th quarter of 2015-16, SVC examined the claim and decided to defer for want of following shortfall documents: 1.Certification of incorporation of the company 2. Board Resolution authorising the person to sign the claim application is 3. Approved plans for expansion issued by T & C P Department .4. Land conversion approval 5. Civil M/s. JSW Cements Engineer Certificate for all civil works 17, Ltd., Bilakalgudur Clinker & IIPP 47 14/02/2017 25/06/2012 Power 6. Valid CFO / Acknowledgement 10/03/17 (V), Gadivemula(M), Cement 2010-15 from APPCB 7. Statement of Kurnool District Machinery duly certified by the Financial Institution and General Manager, DIC as per guidelines 8. Land Sale Deed / Lease Deed 9. Statement of Accounts in original or attested copy .10. Approval and approved plans from the Factories Department 11. Power release certificate. M/s Ruchi Soya SVC verified the claim, discussed in Industries Ltd, NH-5, Crude detailed and recommended for 18, Main Road, Plam IIPP sanction of Rs.96,44,949/- (Rupees 48 14/02/2017 11/12/2009 Sales Tax 10/03/17 Ampapura (V), Oilpalm 2005-10 ninety six lakhs forty four thousand Bapulapadu (M), Kernel Oil nine hundred and forty nine only) Krishna Dist for the year 14-15. SVC verified the claim and M/s. Sri Manjunatha recommended for sanction of Spinning Mills Ltd., 19, Cotton DIP Rs.38,63,320/- (Rupees thirty eight 49 14/02/2017 Thimmapuram(V), 14/02/2011 Power 10/03/17 lakhs sixty three thousand three Edlapadu(M), Guntur Yarn 2015-20 hundred and twenty only) for 2nd District half year of 2015-16. :: 125 ::

SVC examined the claim and decided to defer for want of following shortfall M/s. NSL Textiles Cotton 20, IIPP documents: 1)IEM Part-B for 50 14/02/2017 Ltd., Inkollu(V&M), Spinning 01/02/2008 Power 10/03/17 declaration of DCP 2) Base power Prakasam District 2005-10 Mills load as per CA report duly attested by GM, DIC M/s .Anjani Tiles SVC verified the claim and Limited, Eguva recommended for sanction of 21, Vitrified IDP 51 14/02/2017 Rajupalem (V), 01/04/2016 Stamp Duty Rs.17,47,940/- (Rupees seventeen 10/03/17 Tiles 2015-20 Chilalur (M), SPSR lakhs forty seven thousand nine Nellore Dist hundred and forty only) SVC verified the claim and M/s Vantage Spinning recommended for sanction of Spinners Pvt Ltd., (Cotton Rs.40,58,424/- (Rupees forty lakhs 23, (Expansion), IDP 52 14/02/2017 Yarn / all 22/10/2015 Power fifty eight thousand four hundred 10/03/17 Gollapalli (V), 2015-20 and twenty four only) for 2nd half Nuzivud Mandal, other Fibre year of 2015-16. Krishna District Yarns)

M/s NG Fertilizers and Chemicals Pvt SVC examined the claim and decided 25, Ltd, Rs.No: 224/2,3, IIPP to defer for want of following shortfall 53 15/02/2017 Fertilizers 25/05/2014 Power 10/03/17 Kondruupadu (V), 2010-15 documents: 1.Land conversion 2. C.E. Bapulapadu (M), Certificate 3. Approved Project report Krishna District 4. C.A. Certificate for Investment. M/s NG Fertilizers and Chemicals Pvt SVC examined the claim and decided 26, Ltd, Rs.No: 224/2,3, IIPP to defer for want of following shortfall 54 15/02/2017 Fertilizers 25/05/2014 Sales Tax 10/03/17 Kondruupadu (V0, 2010-15 documents: 1.Land conversion 2. C.E. Bapulapadu (M), Certificate 3. Approved Project report Krishna District 4. C.A. Certificate for Investment. SVC verified the claim and recommended for sanction of M/s.Aequites Rs.10,55,270/- (Rupees ten lakhs Exports (P) Ltd., Plot fifty five thousand two hundred and 29, No.7, BPSEZ, Granite IDP seventy only) for 1st & 2nd half year 55 22/02/2017 28/05/2015 Power 10/03/17 Annangi (V), slabs 2015-20 of 2015-16. Maddipadu (M), Prakasam District

:: 126 ::

M/s. Idupulapadu Cotton Mills & Pvt. SVC examined the issue in detailed Ltd., Sy. No. 1260 & Wind Investment IDP along with the member of NREDCAP 56 7, 10/03/17 1265, and decided to place all the similar Bhogasamudram (V), Power Subsidy 2015-20 cases in ensuing SLC Meeting for Tadiptri (M), taking a view. Anantapur.

SLC may take a view. :: 127 ::

Annexure – I. Minutes of the special Meeting of Scrutiny/Verification Committee for various incentives/concessions of Large and Mega Industries held on 17/01/2017 in the Conference Hall of the Directorate of Industries, A.P., Hyderabad. The Special Meeting of the Scrutiny cum Verification Committee for scrutinizing the shortfall documents for sanction of various incentives was convened on 17/01/2017. The following members have attended the meeting:

1 Sri B. Suresh Babu Chairman Additional Director of Industries 2 Sri K. Chandrasekhara Rao, Member Asst. Commissioner of Commercial Taxes 3 Sri J. Krishnaiah, Member Senior Manager, APSFC, Hyderabad 4 Sri G. Krishna Prasad, Member Manager (PR)/PAGED-I, APIIC 5 Sri M. Upender, Member SM-LB, Andhra Bank, Head Office 6 Sri G.R.K.Reddy, Member Working President, FAPSIA 7 Sri L. Girijapathi, Asst. Director, Member FTAPCCI, Hyderabad 8 Sri Ch.V. Ramana, Member ADE, AP Transco, Hyderabad 9 Sri K. Vijayarathnam, Member - Convenor Deputy Director of Industries (II)

The shortfall documents for sanction of Investment Subsidy, Interest Subsidy, Reimbursement of Power Cost, Reimbursement of sales tax, Reimbursement of Stamp Duty & Reimbursement of Land Cost under IIPP – 2005-10, IIPP 2010-15 & IDP 2015-20 submitted by the respective General Manager, District Industries Centres, along with Appraisal Notes were placed before the above constituted Committee for scrutiny cum verification and the details are as follows: Date of Date of Commence Sl. Name & Address of the Line of Nature of receipt of ment of Policy Decision No. unit activity incentives claim commercial production 1 03/06/2016 M/s. Guntur Spinning Cotton 12/04/2007 Power IIPP SVC verified the shortfall documents :: 128 ::

Mills (P) Ltd, Obulanaidu Yarn 2005-10 submitted by the General Manager, District palem (V), Guntur (M) & Industries Centre and noticed that the District following shortfalls are required for processing the claim and advised to obtain the same from General Manager, District Industries Centre with proper attestation 1. Confirmation on installation of additional machinery in view of increase in power load.2. Land sale deed.3. Valid CFO from APPCB 4. Approved project report.6. Signature of authorized person not attested in board resolution / authorization and not indicated the name of person in the claim application.7. DT&CP Dept and Factories Dept Plans.8. Bank Sanctioned letter 9. Banker has not attested as machinery as per guidelines.10. Valid CFO from APPCB.11. There is increase in power load from 600KVA to 2240KVA.12. CA certificate for share holding. SVC verified the shortfall documents submitted by the General Manager, District Industries Centre and noticed that the M/s. Sri Venkata Siva Cotton following shortfalls are not submitted and Parvathi Spinning Mills Yarn & IIPP advised to obtain the same from General 2 07/06/2016 (P) Ltd., (1st Expansion), 10/01/2007 Power Manager, District Industries Centre GBC Road, Chebrolu Synthetic 2005-10 1) Reasons for increase of Power Load. 2)Land (V&M), Guntur Dist Yarn Conversion certificate 3) Approved Project report 4) Grampanchayath approved plans 5) Factories Dept approved plans 6) DT&CP approved plans SVC verified the shortfall documents submitted by the General Manager, District Industries Centre and noticed that the M/s. Amoda Spintex Ltd, following shortfalls are required for processing Ravikampadu (V), Cotton IIPP the claim and advised to obtain the same from 3 09/08/2016 08/08/2007 Power Jaggaiahpet (M), Krishna Yarn 2005-10 General Manager, District Industries Centre District 1) Detailed report on the unit added any additional machinery and whether the unit utilized any additional power consumption include in the recommended claim or not :: 129 ::

SVC verified the shortfall documents submitted by the General Manager, District Industries Centre and noticed that the Refining following shortfalls are required for processing M/s. Gemini Edibles and Cin the claim and advised to obtain the same from Fats India (P) Ltd., Fractctionn IIPP General Manager, District Industries Centre 4 22/08/2016 S.No.1607/2, Industrial 23/09/2010 Power 1. Boiler certificate 2. List of Plant & Park, Pantapalem (V), ation of 2005-10 Machinery duly certified by GM, DIC and SPSR Nellore District Vegetable Oils Financial Institution as per operational guidelines. 3. CA certificate indicating the share holding of directors (all the copies should attested) SVC verified the shortfall documents submitted by the General Manager, District Industries Centre and noticed that the following shortfalls are required for processing the claim and advised to obtain the same from M/s. NSL Textiles Ltd, Cotton IIPP General Manager, District Industries Centre 5 06/09/2016 Inkollu (V & M), 01/01/2008 Power 1) IEM Part-B ,2) Factories Dept approved Prakasam Dstrict. Spinning 2005-10 Plan 3) land conversion 4) Approved Project report 5) Valid CFO 6) Factories Dept approved plan 7) DT&CP dept approved plan 8) M/c statement as per guideline 9) Statement of accounts 10) Base power loan as per report duly attested by GM, DIC SVC verified the shortfall documents M/s. Sai Global Yarntex submitted by the General Manager, District India (India) Pvt Ltd, Sy Cotton Industries Centre and noticed that the No: 103/1A, 107, 133, Yarn & IIPP following shortfalls are required for processing 6 07/09/2016 143/1, 143/2 & 143/3, 01/04/2007 Power the claim and advised to obtain the same from Vellampalli (V), Synthetic 2005-10 General Manager, District Industries Centre Maddipadu (M), Yarn 1) DT&CP Dept approved Plans 2) Land Prakasam Dstrict. conversion certificate Costic soda SVC verified the shortfall documents M/s Sree Rayalaseema Lye Flakes submitted by the General Manager, District Alkalies and Allied , Chlorine , IIPP Industries Centre and recommended for 7 07/09/2016 Chemicals Ltd., 01/01/2012 Power sanction of Rs.17,31,29,220/- (Rupees Hydrogen 2005-10 Gondiparla (V), seventeen crores thirty one lakhs twenty nine gas M3 Kurnool District thousand two hundred and twenty only) for 4th HCl quarter 2015-16 and Rs.16,08,17,468/- :: 130 ::

(Rupees sixteen crores eight lakhs seventeen thousand four hundred and sixty eight only) for 1st quarter of 2016-17. SVC verified the shortfall documents submitted by the unit holder and noticed that the following shortfalls are required for M/s. Thatavarthi processing the claim and advised to obtain the Aapparels Ltd., same from General Manager, District Appapuram Road, Cotton IIPP Industries Centre with proper attestation 8 08/09/2016 20/05/2011 Power Kavuru (V), Yarn 2010-15 1. Grampanchayath, Factories and DT&CP Chilakaluripet (M), Dept approval . 2 Land conversion certificate Guntur District 3.CE certificate 4.Approved project report 5. Original list of Plant & Machinery as per operational guidelines 6. Valid CFO from APPCB. SVC verified the shortfall documents submitted by the General Manager, District Industries Centre and noticed that the M/s. Mittapalli Spinners following shortfalls are required for processing Limited, Cotton IIPP the claim and advised to obtain the same from 9 12/09/2016 Chinaturakapalem (V), 29/12/2011 Power General Manager, District Industries Centre Narasaraopet (M). Guntur Yarn 2010-15 1) DT& CP department approved plans. 2) Dist Valid CFO from APPCB, 3) List of Plant machinery as per operational guidelines under IIPP 2010-15 SVC verified the shortfall documents M/s. Smilax Laboratories submitted by the General Manager, District Ltd., Plot No.70, JNPC, Cotton IIPP Industries Centre and recommended for 10 14/09/2016 12/06/2009 Power Parawada, Yarn 2005-10 sanction of Rs.3,12,16,050/- for the period Visakhapatnam from 2nd quarter of 2009 -10 to 4th quarter of 2013-14. SVC verified the shortfall documents submitted by the General Manager, District M/s. Ajantha Spintex Industries Centre and advised to issue Ltd., Kakani (V), Cotton IIPP revised sanctioned intimation letters for an 11 16/09/2016 20/02/2013 Power Narsaraopet (M), Guntur Yarn 2010-15 amount of Rs.38,52,320/- & District Rs.12,08,089/- for the period 1st half year of 2015-16. which were sanctioned in 11th SLC & 12th SLC respectively. :: 131 ::

SVC verified the shortfall documents submitted by the General Manager, District Industries Centre and noticed that the M/s. Gowthami Spintex following shortfalls are required for processing (India) Ld., Duvva, Cotton IIPP the claim and advised to obtain the same from 12 21/09/2016 08/09/2011 Power Tanuku (M), West Yarn 2005-10 General Manager, District Industries Centre Godavari District 1. Registered Land Sale Deed 2) Grampanchayath approved plans 3) DT&CP approved plans 4) List of Meachinery not as per guidelines 5) Approved project report SVC verified the shortfall documents submitted by the General Manager, District Industries Centre and advised to issue M/s. Gowthami Solvent Cotton revised sanctioned intimation letters for an Oils Ltd, RS No 323, Yarn & IIPP 13 21/09/2016 Velagaduru Rd, Morta 18/10/2011 Power amount Rs.42,03,780/- for 1st half year of Synthetic 2010-15 (V), Undrajavaram (M), 2015-16 and Rs.55,74,830/- for the Yarn West Godavari District period 2nd half year of 2015-16. which were sanctioned in 11th SLC & 12th SLC respectively. SVC verified the shortfall documents submitted by the General Manager, District Industries Centre and noticed that the M/s The Gowthami following shortfalls are required for processing Cotton Solvent Oilss Ltd, the claim and advised to obtain the same from Yarn / IIPP General Manager, District Industries Centre 14 21/09/2016 Satyawada Road, Tetali 04/07/2017 Power Synthetic 2010-15 1) IEM Part-B , 2) Grampanchyath approval (V), Tanuku (M), W.G Yarn Plan 3) DT&CP approval plan 4) Land Dist Conversion certificate 5) Statement of Accounts as per guidelines along with Andhra Bank Certificate 6) List of Plant & Machinery as per guidelines 7) Project report SVC verified the shortfall documents submitted by the General Manager, District M/s. Net Matrix Ltd., Plot Agro Industries Centre and advised to issue No.15&15A, APSEZ, IIPP 15 15/10/2016 Chemical 12/03/2014 Power revised sanctioned intimation letter with an Atchuthapuram, 2010-15 Visakhapatnam District Mfg amount Rs.16,89,180/- for the period 1st & 2nd half year of 2014-15. which was sanctioned in 11th SLC. 16 04/11/2016 M/s. Sri Nukala Rama Cotton 26/03/2010 Power IIPP SVC verified the shortfall documents :: 132 ::

Koteswara Rao Textiles Yarn 2005-10 submitted by the General Manager, District Pvt Ltd., D.No: 1-233, Industries Centre and noticed that the GBC Road,Chebrolu following shortfalls are required for processing (V&M), Guntur District the claim and advised to obtain the same from (EXPANSION) General Manager, District Industries Centre 1. Land documents, 2, Board resolution 3. Grampanchayat Factories, and DT&CP Dept approved plans 4.CFO from APPCB, 5. Approved project report 6. Land conversion certificate. SVC verified the shortfall documents submitted by the General Manager, District M/s Kalpataru Spinning Industries Centre and noticed that the Mills (P) Ltd (Exp) S No: following shortfalls are required for processing 210, 211/A, Cotton IIPP 17 15/11/2016 01/06/2012 Power the claim and advised to obtain the same from thimmapuram (V), Yarn 2010-15 General Manager, District Industries Centre Edlapadu (M), Guntur 1) IEM Part -B for Expansion project 2) Dis t DT&CP approved Plan. 3) Factories Dept approved Plan SVC verified the shortfall documents M/s. Sudha Agro & submitted by the General Manager, District Chemicals Ins. Ltd., Industries Centre and noticed that the (Spinning Dvision), Cotton IIPP following shortfalls are required for processing 18 25/11/2016 29/09/2011 Power Valuthimmapuram (V), Yarn 2010-15 the claim and advised to obtain the same from Peddapuram (M), General Manager, District Industries Centre E.G.Dist. 1) List of Plant & machinery as per guidelines 2) DT &CP Approved plans. SVC verified the shortfall documents M/s Tirumala Cotton submitted by the General Manager, District Agro Products (P) Ltd, Cotton IIPP Industries Centre and noticed that the 19 25/11/2016 Thimmapuram (V), 05/10/2012 Power following shortfalls are required for processing Chilakaluripet(M), Yarn 2010-15 the claim and advised to obtain the same from Guntur District General Manager, District Industries Centre 1. DT&CP approval along with plans. SVC verified the shortfall documents M/s. SVR Spinning Mills submitted by the General Manager, District (P) Ltd., Malleswaram, Cotton IIPP Industries Centre and recommended for 20 26/11/2016 23/12/2011 Power Peravali (M), West Yarn 2010-15 sanction of Rs.30,55,400/- (Rupees thirty Godavari District lakhs fifty five thousand and four hundred only) for the period 2nd half year of 2015- :: 133 ::

16. SVC verified the shortfall documents submitted by the General Manager, District Industries Centre and noticed that the M/s. Hindustan National following shortfalls are required for processing Glass & Industries Ltd, Container IIPP the claim and advised to obtain the same from 21 02/12/2016 Meenakur (V), Naidupeta 28/09/2012 Power General Manager, District Industries Centre (M), SPSR Nellore Glass 2005-10 with proper attestation District 1 Company incorporation 2) Factories Dept approved plans 3) Valied CFO 4) CA Certificate 5) Reason for increase power load, 6) Land conversion. SVC verified the shortfall documents submitted by the General Manager, District M/s. Jyothirmaye Textiles Industries Centre and recommended for (P) Ltd., Gorijavolu (V), Cotton IIPP 22 05/12/2016 04/02/2011 Power sanction of Rs.42,93,794/- (Rupees forty Nadendla (M), Guntur Yarn 2010-15 lakhs ninety three thousand seven hundred District and ninety four only) for 2nd Half Year of 2015-16 SVC verified the shortfall documents submitted by the General Manager, District M/s. Patchala Spintex (P) Industries Centre and noticed that the Ltd., (Existing), Cotton IIPP 23 08/12/2016 13/04/2012 Power following shortfalls are required for processing Rajupalem (V & M), Yarn 2010-15 the claim and advised to obtain the same from Guntur Dist General Manager, District Industries Centre 1) List of Plant & Machinery as per guidelines SVC verified the shortfall documents submitted by the General Manager, District M/s. Patchala Spintex (P) Cotton Industries Centre and noticed that the Ltd., (Expansion), Yarn & IIPP 24 08/12/2016 01/05/2015 Power following shortfalls are required for processing Rajupalem (V & M), Synthetic 2010-15 the claim and advised to obtain the same from Guntur District Yarn General Manager, District Industries Centre 1) List of Plant & Machinery as per guidelines SVC verified the shortfall documents submitted by the General Manager, District M/s. Rayani Spintex (P) Industries Centre and noticed that the Ltd., Dhulipalla (V) Cotton IIPP 25 08/12/2016 16/11/2011 Power following shortfalls are required for processing Sattenapalli (M), Guntur Yarn 2010-15 the claim and advised to obtain the same from District General Manager, District Industries Centre 1) Detailed report on reasons for increasing the :: 134 ::

power load from DCP to present claim 2) DT & CP Approved plans SVC verified the shortfall documents submitted by the unit holder and noticed that the following shortfalls are required for processing the claim and advised to obtain the M/s RBA Textiles Pvt. same from General Manager, District Ltd. (Existing), Trading of Industries Centre with proper attestation Krishnagiri Road, Food IIPP 26 13/12/2016 Cotton 06/11/2008 Power 1. Bank Term Loan Sanctioned letter 2) Processing Industrial 2005-10 Company incorporation 3) List of Plant & Park, Kuppam (M), Yarn Machinery as per operational guidelines 4) Chittoor Dist Grampanchayath, DT&CP dept approval 5) CA Certificate for share holding 6) valid CFO issued APPCB 8) Project report 9) Reasons for increasing the power SVC verified the shortfall documents submitted by the unit holder and noticed that the following shortfalls are required for processing the claim and advised to obtain the M/s. RBA Textiles Pvt. same from General Manager, District Ltd., (Expansion), Trading of IIPP Industries Centre with proper attestation 27 13/12/2016 Krishnagii Road, Food Cotton 25/12/2010 Power 1. Land sale deed 2) Company incorporation processing Park, Kuppam 2010-15 Yarn 3) Board resolution authorizing sing 4) (V&M), Chittoor Dist Grampanchayath, DT&CP dept approval 5) Land conversion approval 6) valid CFO issued APPCB 8) Project report 9) CA certificate 10) reasons for increasing the power M/s. PVR Spinning and SVC verified the shortfall documents Weaving Ltd. submitted by the General Manager, District Trading of (Expansion), IIPP Industries Centre and noticed that the 28 19/12/2016 R.S.No.110/2, 108/2,3,4, Cotton 27/08/2010 Power following shortfalls are required for processing 2005-10 Kondayapalem Road, Yarn the claim and advised to obtain the same from Tetali (V), Tanukum (M), General Manager, District Industries Centre West Godavari District 1) DT&CP approved plans SVC verified the shortfall documents M/s. Avanthi Feeds, Unit submitted by the General Manager, District -3, R.S. No. 544/2, Cotton IIPP Industries Centre and recommended for 29 28/12/2016 544/1B, 545/3B, 545/5, 07/04/2014 Power sanction of Rs.35,92,000/- (Rupees thirty five 746/3A, Kovur V & M, Yarn 2010-15 lakhs and ninety two thousand only) for 2nd West Godavari District half year of 2015-16. :: 135 ::

SVC verified the shortfall documents M/s. Sri Mouli Textiles submitted by the General Manager, District pvt. Ld., Sy. No. 22/A, Cotton IIPP 30 29/12/2016 10/05/2017 Power Industries Centre and recommended for 22/B & 25, Prathipadu Yarn 2010-15 sanction of Rs.24,83,800/- for the period of (V&M), Guntur 2nd Half Year of 2015-16 SVC verified the shortfall documents submitted by the General Manager, District Industries Centre and recommended for M/s Sri Vaishnavi sanction of Rs.64,94,470/- (Rupees sixty Spintex (India) Pvt Ltd., Cotton IDP 31 04/01/2016 18/03/2012 Power four lakhs ninety four thousand four Kolanapalli , Kalla (M), Yarn 2015-20 West Godavari Dist hundred and seventy only) for 2nd half year of 2015-16 including deference amount of Rs.11,69,170/- pertaining to 1st half year of 2015-16. SVC verified the shortfall documents M/s. Kolar Paper Mills submitted by the General Manager, District Ltd., Sy.No.104, 105 & Industries Centre and recommended for 106, Packaging IIPP 32 05/01/2017 21/05/2015 Power sanction of Rs.82,02,198/- (Rupees eighty Parameswaramangalam Paper 2010-15 (V), Puttur (M), Chittoor two lakhs two thousand one hundred District and ninety eight only) for the period 1st & 2nd half year of 2015-16 SVC verified the shortfall documents submitted by the General Manager, District M/s Supriya Spinning Industries Centre and noticed that the Mills (P) Ltd, (Exp) Cotton IIPP 33 05/01/2017 22/02/2012 Power following shortfalls are required for processing Boyapalem (V), Edlapadu Spinning 2005-10 the claim and advised to obtain the same from (M)Guntur Dist General Manager, District Industries Centre 1 DT&CP approval along with plans SVC verified the shortfall documents submitted by the General Manager, District M/s Nandhivadhana Industries Centre and noticed that the Textiles Mlls (P) Ltd, Cotton IIPP following shortfalls are required for processing 34 05/01/2017 25/09/2010 Power NH-5, thimmapuram (V), Yarn 2005-10 the claim and advised to obtain the same from Edlapadu (M) Gnntur General Manager, District Industries Centre 1 DT&CP approval along with plans 2) Land conversion certificate M/s Ranganayaka Cotton IIPP SVC verified the shortfall documents 35 05/01/2017 Spinning Mills (P) Ltd, 09/04/2010 Power submitted by the General Manager, District (Exp) Boyapalem (V), Yarn 2005-10 Industries Centre and noticed that the :: 136 ::

Edlapadu (M), Guntur following shortfalls are required for processing Dist the claim and advised to obtain the same from General Manager, District Industries Centre 1 DT&CP approved plans 2) C.E. Certificate SVC verified the shortfall documents submitted by the General Manager, District Industries Centre and recommended for M/s Ranganayaka sanction of Rs.6,40,483/- (Rupees six Spinning Mills (P) Ltd, Cotton IIPP lakhs forty thousand four hundred and 36 05/01/2017 (Existing) Boyapalem 10/04/2008 Power (V), Edlapadu (M), Yarn 2005-10 eightythree only) for 10 days of 4the Guntur Dist quarter of 2015-16.

SVC verified the shortfall documents submitted by the General Manager, District M/s Sree lalitha Industries Centre and noticed that the Parameswari (P) Ltd Cotton IIPP following shortfalls are required for processing 37 05/01/2017 26/03/2010 Power (Exp) Chebrolu (V&M), Yarn 2005-10 the claim and advised to obtain the same from Guntur Dist General Manager, District Industries Centre 1 DT&CP approval along with plans 2) Reasons for increase power load. Sd/- Sd/-

(J. Krishnaiah) ( K. Chandrasekara Rao ) Senior Manager, APSFC, Hyderabad Asst. Commissioner, Commercial Taxes Department Sd/- Sd/- (G. Krishna Prasad) (M. Upender) Manager (PR)/PAGED-I, APIIC SM-LB, Andhra Bank, Head Office

Sd/- Sd/- Sd/- ( Ch.V. Ramana) (G.R.K.Reddy) ( L. Girijapathi ) ADE, AP.TRANSCO, Hyderabad Working President, FAPSIA Asst. Director, FTAPCCI, Hyderabad

:: 137 ::

Sd/- Sd/- ( K. Vijayaratanam) ( B.Suresh Babu ) Deputy Director (II), Directorate of Industries Additional Director, Directorate of Industries.

:: 138 ::

Annexure – II. Minutes of the Meeting of Scrutiny/Verification Committee for various incentives/concessions of Large and Mega Industries held on 10/03/2017 in the Conference Hall of the Commissionerate of Industries, A.P., Vijayawada. The Meeting of the Scrutiny cum Verification Committee for scrutinizing the claim applications for sanction of various incentives was convened on 10/03/2017. The following members have attended the meeting:

1 Sri B. Suresh Babu Chairman Additional Director of Industries 2 Sri K. Chandrasekhara Rao, Member Asst. Commissioner of Commercial Taxes 3 Smt. S.V.S.S. Laxmi, Member Deputy Collector, CCLA Department 4 Smt. P. Ramalaxmi Patnaik, Asst. Inspector General, Member Stamps & Registration Department 5 Sri S. Sreenivasa Mani, Member Senior Branch Manager, APSFC, Hyderabad 6 Sri GVS Sunderam, Member Chief Manager, Andhra Bank 7 Sri V. Murali Krishna, Member General Secretary, FAPSIA 8 Smt. A. Rajyalaxmi, Asst. Director, Member FTAPCCI 9 Sri K.S. Rao, Special Invitee District Manager, NREDCAP. 10 Sri K. Vijayarathnam, Member - Convenor Deputy Director of Industries (II)

The claim applications for sanction of Investment Subsidy, Interest Subsidy, Reimbursement of Power Cost, Reimbursement of sales tax, Reimbursement of Stamp Duty & Reimbursement of Land Cost under IIPP – 2005-10, IIPP 2010-15 & IDP 2015-20 submitted by the respective General Manager, District Industries Centres, along with Appraisal Notes were placed before the above constituted Committee for scrutiny cum verification and the details are as follows: Date of Date of Name & Address of the Line of Commence Nature of Sl. No. receipt of Policy Decision unit activity ment of incentives claim commercial :: 139 ::

production SVC examined the issue pertaining to Land Conversion and decided to place before SLC all similar cases as special Agenda in light of M/s.Ravali Spinners Pvt Minutes of its Meeting held on 03/03/2017. Ltd., (Expan-1), Reimburse- IIPP 2005- 1 18/04/2016 Khandavalli (V), Peravali Cotton Yarn 01/01/2009 ment of SVC verified the claim and recommended for 10 (M), West Godavari power cost sanction of Rs.96,42,350/- (Rupees ninety six District lakhs forty two thousand three hundred and fifty only) for 4th quarter of 2015-16 and 1st quarter of 2016-17, subject to confirmation of SLC. M/s. Silica Ceramica Pvt Vertified SVC examined the claim and recommended for Ltd., D.No. 97-107, Ceramics sanction of Rs16,02,03,314/- (Rupees sixteen IIPP 2005- 2 07/06/16 Narayanapuram, Tiles and 11/05/2011 Sales Tax crores two lakhs three thousand three 10 Unguturu (M), West Ceramic hundred and fourteen only) for the year Godavari District Glazed Tiles 2015-16 SVC examined the claim and recommended for M/s. Tirumala Cotton & IDP 2015- rejection, the line of activity of Wind Power is 3 18/07/2016 Agro Products Pvt Ltd, Wind Power Stamp Duty 20 not eligible for sanction of reimbursement of Ananthapur District Stamp Duty under IDP 2015-20. M/s Laurus labs Pvt Ltd (Exp) Plot No: 21, JNPC, IIPP 2010- 4 18/11/2016 Bulk Drugs 01/01/2013 Power Deferred for detailed examination. Parawada (M), 15 Visakhapatnam SVC examined the claim and decided to defer M/s Girnar Packaging, for want of following shortfall Plot No.11,12 and 13, Corrugated IIPP 2010- documents:1.Board resolution authorizing the 5 28/11/2016 Indl. Park, Menakur(V), 16/05/2013 Sales Tax Boxes 15 person to sign 2. Company incorporation 3. Naidupet(M), SPSR Valid Boiler certificate 4.Valid CFO from Nellore District APPCB. M/s A.S. Jute Products Pvt Ltd., (Existing), SVC examined the claim and recommended for Jute, Yarn, Sy.No. 20/2 & 21, IIPP 2010- sanction of Rs. 6,86,160/- (Rupees six lakhs 6 28/11/2016 Twine, 28/03/2012 Power Narlavalasa (V), 15 eighty six thousand one hundred and sixty Gunny Bags Padmanabham (M), only) for 1st half year of 2015-16. Visakhapatnam M/s. Idupulapadu Cotton SVC examined the issue in detailed along with Investment IDP 2015- 7 Mills & Pvt. Ltd., Sy. No. Wind Power the member of NREDCAP and decided to Subsidy 20 1260 & 1265, place all the similar cases in ensuing SLC :: 140 ::

Bhogasamudram (V), Meeting for taking a view. Tadiptri (M), Anantapur. M/s. Sri Teja Bio Fuels SVC examined the claim and recommended for Pvt Ltd, Annadevarapeta IDP 2015- sanction of Rs.3,82,224/- (Rupees three lakhs 8 07/12/2016 ENT Granis 27/05/2015 Stamp Duty (V), Tadepalli (M), West 20 eighty two thousand two hundred and Godavari District twenty four only). M/s. BMM Cements Ltd., SVC examined the claim and decided to defer IIPP 2010- 9 13/12/2016 Gudipadu (V), Yadiki Power for want of following shortfall documents: 15 (M), Anantapur District 1.DT & CP approved plans. SVC examined the claim and decided to defer for want of following shortfall documents: 1.As per the IEM Part – B, the DCP of the unit M/s. Chowdary Spinners is 22/03/2008. But the GM, DIC has Ltd. (Expansion), 1-168, Cotton yarn IIPP 2005- recommended the claim as DCP on 10 19/12/2016 Chivatam (V), 31/07/2007 Power spinning 10 31/07/2007. Hence, the GM, DIC to submit a Undrajavaram (M), West detailed report on ambiguity on the DCP. 1. Godavari District IEM par – B acknowledgement issued by GoI. 3. DT & CP approval along with plans. 4. Registered land sale deed. M/s Paramesu SVC verified the claim and recommended for Biotech Pvt Ltd., 972, Maize IIPP sanction of Rs.32,97,165/- (Rupees thirty two 11 19/12/2016 05/01/2015 Sales Tax Devarapalli (V&M), Starch 2010-15 lakhs ninety seven thousand one hundred WG Dist and sixty five only) for the year 2015-16 SVC examined the claims in detailed along with members from SLBC & APSFC and M/s Kallam Spinning Spinning, recommended for sanction of Rs.8,65,41,396/- Mills Ltd, Weaving Interest IDP 2015- (Rupees eight crores sixty five lakhs forty 12 21/12/2016 Kunukupadu(V), 01/09/2014 and Subsidy 20 one thousand three hundred and ninety six Addanki (M), Prakasam processing ony) for 1st & 2nd half year of 2015-16. District. Further, SVC advised to process all the similar claim in the same formate. M/s. Sri Venkateswara Spintex (P) Ltd., SVC verified the claim and recommended for D.No:20&21, Reimburseme IIPP 2010- sanction of Rs.52,58,245/- (Rupees fifty two 13 05/01/2017 Narasaraopet Road, Cotton Yarn 04/12/2011 nt of Power 15 lakhs fifty eight thousand two hundred and Kavuru(V), cost forty five only) for 2nd half year of 2015-16. Chilakaluripet (M), Guntur District 14 07/01/2017 M/s.Ravali Spinners Pvt Cotton Yarn 20/11/2010 Reimburse- IIPP 2010- SVC examined the issue pertaining to Land :: 141 ::

Ltd., (Expan-1I), ment of 15 Conversion and decided to place before SLC Khandavalli (V), Peravali power cost all similar cases as special Agenda in light of (M) W G District Minutes of its Meeting held on 03/03/2017.

SVC verified the claim and recommended for sanction of Rs.62,49,710/- (Rupees sixty two lakhs forty nine thousand seven hundred and ten only) for 2nd half year of 2015-16 SVC examined the claim and decided to defer for want of following shortfall M/s.Gowtami Spintex documents:1.IEM Part B 2. Land documents (India) Limited., RS Reimburse- IIPP 2010- 3.Memorandum of article 4.GP, T&CP and 15 12/01/2017 No.398/399, Duvva, Cotton Yarn 08/09/2011 ment of 15 Factories Department approved plans 5.Valid Tanuku Mandal, West power cost CFO from APPCB 6.Statement of Accounts Godavari District 7.List of plant and machinery statement as per guidelines 8.CE certificate 9.Project report. M/s. Silica Ceramica Pvt Vertified SVC verified the claim and recommended for Ltd., D.No. 97-107, Ceramics Reimburseme IIPP 2005- sanction of Rs.82,42,540/- (Rupees eighty two 16 14/02/2017 Narayanapuram, Tiles and 11/05/2011 nt of Power 10 Pipe lakhs forty two thousand five hundred and Unguturu (M), West Ceramic cost Line forty only) for the period of 4th quarter of Godavari District Glazed Tiles 2015-16, SVC examined the claim and decided to defer for want of following shortfall documents: 1.Certification of incorporation of the company 2. Board Resolution authorising the person to sign the claim application is 3. Approved plans for expansion issued by T & C P Department .4. Land conversion approval M/s. JSW Cements Ltd., 5. Civil Engineer Certificate for all civil Bilakalgudur (V), Clinker & IIPP 2010- 17 14/02/2017 25/06/2012 Power works 6. Valid CFO / Acknowledgement Gadivemula(M), Kurnool Cement 15 from APPCB 7. Statement of Machinery duly District certified by the Financial Institution and General Manager, DIC as per guidelines 8. Land Sale Deed / Lease Deed 9. Statement of Accounts in original or attested copy .10. Approval and approved plans from the Factories Department 11. Power release certificate. M/s Ruchi Soya Crude Plam IIPP 2005- SVC verified the claim, discussed in detailed 18 14/02/2017 11/12/2009 Sales Tax Industries Ltd, NH-5, Oilpalm 10 and recommended for sanction of :: 142 ::

Main Road, Ampapura Kernel Oil Rs.96,44,949/- (Rupees ninety six lakhs forty (V), Bapulapadu (M), four thousand nine hundred and forty nine Krishna Dist only) for the year 14-15. M/s. Sri Manjunatha SVC verified the claim and recommended for Spinning Mills Ltd., sanction of Rs.38,63,320/- (Rupees thirty DIP 2015- 19 14/02/2017 Thimmapuram(V), Cotton Yarn 14/02/2011 Power eight lakhs sixty three thousand three 20 Edlapadu(M), Guntur hundred and twenty only) for 2nd half year District of 2015-16. SVC examined the claim and decided to defer M/s. NSL Textiles Ltd., Cotton Reimburse- for want of following shortfall documents: IIPP 2005- 20 14/02/2017 Inkollu(V&M), Prakasam Spinning 01/02/2008 ment of 1)IEM Part-B for declaration of DCP 2) Base 10 District Mills Power cost power load as per CA report duly attested by GM, DIC M/s .Anjani Tiles SVC verified the claim and recommended for Limited, Eguva Vitrified IDP 2015- sanction of Rs.17,47,940/- (Rupees seventeen 21 14/02/2017 01/04/2016 Stamp Duty Rajupalem (V), Chilalur Tiles 20 lakhs forty seven thousand nine hundred (M), SPSR Nellore Dist and forty only) M/s.Sriven Spincot (P) Reimburseme IIPP 2010- 22 14/02/2017 Ltd., Edlapadu (V&M), Cotton Yarn 09/06/2014 nt of Power Repeated. Already sanction in 13th SLC. 15 Guntur District cost SVC verified the claim and recommended for M/s Vantage Spinners Spinning sanction of Rs.40,58,424/- (Rupees forty Pvt Ltd., (Expansion), (Cotton Yarn IDP 2015- 23 14/02/2017 22/10/2015 Power lakhs fifty eight thousand four hundred and Gollapalli (V), Nuzivud / all other 20 twenty four only) for 2nd half year of 2015- Mandal, Krishna District Fibre Yarns) 16. M/s Laurus labs Pvt Ltd (Exp) Plot No: 21, JNPC, IIPP 2010- 24 14/02/2017 Bulk Drugs 01/01/2013 Sales Tax Deferred for detailed examination. Parawada (M), 15 Visakhapatnam District M/s NG Fertilizers and SVC examined the claim and decided to defer Chemicals Pvt Ltd, for want of following shortfall documents: Rs.No: 224/2,3, IIPP 2010- 25 15/02/2017 Fertilizers 25/05/2014 Power 1.Land conversion 2. C.E. Certificate 3. Kondruupadu (V), 15 Approved Project report 4. C.A. Certificate for Bapulapadu (M), Krishna Investment. District M/s NG Fertilizers and SVC examined the claim and decided to defer Chemicals Pvt Ltd, for want of following shortfall documents: IIPP 2010- 26 15/02/2017 Rs.No: 224/2,3, Fertilizers 25/05/2014 Sales Tax 1.Land conversion 2. C.E. Certificate 3. 15 Kondruupadu (V0, Approved Project report 4. C.A. Certificate for Bapulapadu (M), Krishna Investment. :: 143 ::

District SVC examined the claim and decided to defer M/s Mohan Spintex India for want of following shortfall documents: Ltd, Unit -III, Remalle Spinning IDP 2015- 27 16/02/2017 Power 1.C.A. Certificate for investment as well as (V), Bapulapadu (M), yarn 20 capacity before expansion and under Krishna District expansion. Internal Combstion M/s Makrocast Pvt Ltd Piston (Expansion) , RS No. Engines and 612/2AB, ZP Road, other parts IIPP 2010- 28 20/02/2017 03/08/2010 Sales Tax Deferred for detailed examination. Kolavennu (V), and 15 Kankipadu (M), Krishna Accessories District N.E.C. for Motor Vehicles M/s.Aequites Exports (P) SVC verified the claim and recommended for Ltd., Plot No.7, BPSEZ, Granite IDP 2015- sanction of Rs.10,55,270/- (Rupees ten lakhs 29 22/02/2017 28/05/2015 Power Annangi (V), Maddipadu slabs 20 fifty five thousand two hundred and seventy (M), Prakasam District only) for 1st & 2nd half year of 2015-16.

Sd/- Sd/-

(Sri S. Sreenivasa Mani) ( K. Chandrasekara Rao ) Senior Manager, APSFC Asst. Commissioner, Commercial Taxes Department Sd/- Sd/- Sd/ - (P. Ramalaxmi Patnaik) (K.S. Rao) (S.V.S.S. Laxmi) Asst. Inspector General, District Manager, NREDCAP. Deputy Collector, CCLA Department Stamps & Registration Department

Sd/- Sd/- Sd/- (GVS Sunderam) (V. Murali Krishna) (A. Rajyalaxmi) Chief Manager, Andhra Bank General Secretary, FAPSIA Asst. Director, FTAPCCI

:: 144 ::

Sd/- ( K. Vijayaratanam) ( B.Suresh Babu ) Deputy Director (II), Directorate of Industries Additional Director, Directorate of Industries.

:: 145 ::

ITEM NO: 4.

STATUS NOTE ON RELEASE OF SANCTIONED INCENTIVE / CONCESSIONS OF TO THE INDUSTRIEAL UNITS UNDER IIPP 2005-10, IIPP 2010-15 & IDP 2015-20 AS ON 15/03/2017.

General Budget:

Government have allocated budget of Rs.272.91 Crores for the year 2016-17 towards incentives for industrial promotion under single head of account, instead of three head of accounts issued separately for General incentives (excluding power and Pavala vaddi), Reimbursement of power cost, Reimbursement of Interest subsidy under pavalavaddi scheme.

The details of the sanctioned claims from 6th SLC to 13th SLC and pending for release are as detailed below:

Sanctioned as on Releases made Pending for releases 15/03/2017 Nature of Incentive

No. of Amount No. of Amount No. of Amount cases Rs. in Cr cases Rs. in Cr cases Rs.in Cr General Incentives Investment subsidy 100% Reimbursement of Stamp Duty 100% Reimbursement of Mortgage Duty 25% Reimbursement of Land Cost Reimbursement of 3652 1134.15 1206 272.91 2446 861.24 Power cost Reimbursement of Pavala Vaddi Quality certification Land Conversion charges Reimbursement of

Sales tax

:: 146 ::

Total cases sanctioned by SLC and DLC and Pending for release Releases by Sanctioned as on Government to PD Pending for releases 15/03/2017 Nature of Incentive Account No. of Amount No. of Amount No. of Amount cases Rs. in Cr cases Rs. in Cr cases Rs.in Cr State Level sanctions 3652 1134.15 1206 272.91 2446 861.24 by SLC

District level sanctioned 5193 217.66 0 0 5193 217.66 by DLC TOTAL 8845 1351.81 1206 272.91* 7639 1078.90

* Out of Rs 272.91 Cr an amount of Rs 226.20 Cr for 601 units, is disbursed. Release of the remaining is under process.

Net demand to clear all pending sanctioned cases = Rs. 1078.90 Crores (7639 cases).

To be sanctioned before 31.03.2017:

Physical claims (L&M) : Rs 155.89 Cr (122 claims)

Online claims (L&M) : Rs 132.60 Cr (134 claims)

Online claims (MSME) : Rs 237.00Cr (3741claims)

Total to be sanctioned : Rs 525.49 (3997 claims)

Total Budget required: (Sanctioned + Pending for sanction) = Rs 1624.39 Cr

A single file was sent to Government with a request to release additional budget of Rs 1624.39 under 2016-17 to clear 11636 claims as on 31.03.2017.

:: 147 ::

ITEM NO. 5.

STATUS REPORT ON THE PROPOSALS SENT TO THE GOVERNMENT AS ON:08/03/2017

Date of Sl. SLC SLC Decision Statues of the issue No Meeting 1 01/03/13 IIPP 2005-10 – M/s. Visakha Industries Limited – RS No. 385,386, jujjuru, Veerullapadu (M), Government Orders are Krishna District – Sanction of reimbursement of power cost – regarding. awaited. Further, issue of reminder is under The SLC has examined the issue on the following points: process. G.O. Ms. No.108, Industries & Commerce (IP) Department, dt.20/05/1996 pertains to Target – 2000 Scheme – New Industrial Policy 1995 and policy period is from 15.11.1995 to 31.03.2000, in which line of activity “Mangalore Tiles / Asbestos Products” is listed at Sl. No.49 in the ineligible industrial activities.

In this regard vide G.O. Ms. No.196, Industries & Commerce (IP) Department, dt.11.06.1998 an amendment was issued that words “Asbestos Products” occurring against item 49 in the list of ineligible industries annexed to G.O. Ms. No.108, Industries & Commerce (IP) Department, dt.20/05/1996 shall be deleted”. While issuing the G.O. Ms. No.178, Industries & Commerce (IP) Department, dt. 21-06-2005, the Government has not taken the order issued for amendment to the G.O. Ms. No.108, Industries & Commerce (IP) Department, dt.20/05/1996. They have taken only ineligible list annexure with the G.O.Ms.9 Industries & Commerce (IP) Department, dt. 05-01-2001. M/s. Visaka Industries Limited – RS No. 385,386, jujjuru, Veerullapadu (M), Krishna District were also processed for sanction of incentives under IIPP 2005-2010 and sanctioned in various SLCs an amount of Rs.30,18,270/- and also an amount of Rs.13,05,190/- were released pertaining to reimbursement of power cost. In view of the above circumstances, the SLC has decided to recommend the issue to the Government for making eligible for the line of activity of “Asbestos Products” and issue amendment accordingly to the G.O. Ms. No.178, Industries & Commerce (IP) Department, dt. 21/06/2005, since the same line of activity are eligible under IIPP 2010-15 schemes.

Accordingly, the proposals were recommended to the Government vide letter No. 10/3/2007/0568, dt.21/03/2013.

:: 148 ::

2. 20/05/15 IIPP 2010-15 – Sanction of Investment Subsidy – M/s. MNR Complex Sy.No.189/2 , Nandyal Road, Government Orders are Banaganapalli post and mandal, Kurnool District – sanctioned by DIPC – release of incentives – awaited. Further, issue regarding of reminder is under The SLC discussed the issue in detail and decided to send the proposal of extending incentives to process. differently able persons, to Government for the issue of appropriate orders on the operational guidelines in respect of G.O.Ms.No.188 Industries and Commerce (IP) Department dated 20.12.2013. Accordingly, the proposals were recommended to the Government vide letter No. Lr. No. 30/1/15/0288, dated 18/06/2015. 3. 20/05/15 IIPP 2005-2010 and 2010-15- claim applications revised for reimbursement of sales tax – clarification Government Orders are – regarding. awaited. Further, issue The SLC discussed the issue in detail and decided to seek clarification from the Government of reminder is under regarding the reimbursement of sales tax paid by the unit in the united state of Andhra Pradesh when process. the physical location of the unit is in residual Andhra Pradesh. In view of the above Sales Tax reimbursement is sanctioned to all such units subject to outcome of Government orders. Accordingly, the proposals were recommended to the Government vide letter No. Lr. No. 30/1/14/0288/0288/ID, dated 23/05/2015 4 17/03/16 IIPP 2010-15 – Claim application for sanction of reimbursement of power cost – M/s My Home Government has been Industries Ltd., unit II Mulakalapalli Village, Yelamanchi Mandal, Visakhapatnam District - requested to furnish proposals for ascertaining the status of Unit II as new Unit or expansion project - Regarding. “the details of month wise power SLC discussed the following issues in detail: consumption for which 7. Common Power subsidy was claimed Members from FAPSIA and AP Chamber of Commerce and Industry expressed to seek a and paid to M/s My clarification from APEPDCL as why a separate meter was not installed instead of erecting the Home Industries Ltd., submeter and sealing it, due to sealing of the submeter, the total units consumed by Unit-I and unit I Mulakalapalli Unit-II are recorded in the main meter. Village, Yelamanchi Mandal, 8. Common Railway Track: Visakhapatnam Standing Scrutiny Committee has pointed that the raw material unloading system through rail is District” vide memo common for both Unit-I and Unit-II. Further, Unit-I and Unit-II were using common rail loading No.1227/P&I/A1/2016, system for Cement transportation. After detailed discussions, State Level Committee has taken a Dated:08/08/2016. view that the unit should ensure that the premises of common railway transport or loading system should be notified as the public property in accordance with relevant Railway Acts. for The reply is being considering the proposal as separate identifiable investment. submitted to Government. 9. Stock transfer from sister concerned unit :: 149 ::

Standing Scrutiny Committee has pointed that the main Raw material i.e., Clinker to Unit-II is through a stock transfer from its parent unit i.e., M/s My Home Industries Ltd., located in Nalgonda district, Telangana State and whereas the company was paying the Central Excise on the Clinker by the Parent unit at Nalgonda. During the discussions in the SLC meeting, three views are emerged: View – I. The representatives from the Commercial Taxes Department have stated that the Stock transfer is permissible and it is common for the industries/dealers for effecting Sales Transaction across various places. Representative of FAPSIA has confirmed that it is common procedure being allowed by Sales Tax Department for effecting Sale Transaction beyond the production point across other places/States.Hence, sales tax reimbursement may be allowed on 100% sale value of cement manufactured through clinker grinding at unit – II. View – II. By considering the Transfer of clinker, a major Raw Material, from parent unit of My Home Industries Ltd., Nalgonda District, Telangana State to unit – II through sale transaction, the eligibility of Sales Tax reimbursement will net sale value of diference between cement and clinker. In the manufacturing process of cement major process is upto clinker and cement is simply the result of grinding of clinker with gypsum and other aditives as the case may be. View – III. The Sales Tax reimbursement on the cement sales at unit-II will be on 100% sale value of the cement if the clinker from parent unit of Nalgonda District, Telangana State is considered as clinker supplied on free of cost by stock transfer. Since, the proposal of the unit-II of My Home Industries Ltd is to consider it as a separate identifiable investment and in view of the financial implications, clarification from Government on stock transfer of clinker from parent unit in view of the above. 10. Machinery Bills Standing Scrutiny Committee has pointed that machinery invoices are not in the name of Unit-II and they are in the name of M/s My Home Industries Ltd., but they were showing the expenditure in the books of accounts of Unit-II as Machinery purchased.

During the discussions in the SLC, the representatives from APSFC and FAPCCI have :: 150 ::

given their views that the expenditure for the machinery should be booked under new identity, Unit-II separately by having invoices of such plant and machinery only in the name of unit-II. That is, the procedure of invoices for plant & machinery in the name of main company My Home Industries Ltd and booking expenditure to unit – II will not come under the category of “Separate Books of Accounts”. 11. Statutory Approvals Standing Scrutiny Committee (SSC) has pointed that the originally approved the plan by VUDA, Factories, CFO and found that they are initially taken approvals under expansion and later modified as Unit-II. Representative of APPCB stated that the unit – I & II of My Home Industries Ltd. is running with single CFO. The SLC decided to verify the CFE and CFO obtained for both the units. 12. Remaining Items under common usage The SLC examined the remaining items of common usage pointed out by the Standing Scrutiny Committee and taken a view that they are not of major nature in view of investment made in unit – II vis-à-vis the investment in the remaining items of common usage and independent production line. Hence, the remaining items of common utilities may be exempted from the ambit of common utilities as per operational guidelines under IIPP 2010-15. Accordingly, the above issue has been place before SLC meeting held on 17/03/2016 and decision of the SLC, the issue referred to the Government with the observations of the State Level Committee vide Lr. No. 30/1/14/22105, dated 26/03/2016. 5 17/06/16 IIPP 2010 – 15 Scheme – M/s. Vasundhara Cotton Mills Private Limited (Expansion), S. No. 24A, Government Orders are Boyapalem (V), Edlapadu (M), Guntur district – Sanction of reimbursement of Power cost for their awaited. Further, issue expansion programme – Eligibility – Regarding. of reminder is under process. SLC has examined the recommendation of the verification /scrutiny committee and observed, there is a deviation in considering the expansion as per the operational guidelines i.e the increasing fixed capital investment is only 19.99% instead of at least 25%. The SLC discussed the issue in detail and decided to recommend the issue to the Government to consider the unit for sanction of incentives on the circumstances and the recommendation of the GM, DIC for considering the claim. Accordingly, the proposals were recommended to the Government vide letter No. Lr. No.30/1/12/1146, dated:09/08/2016. :: 151 ::

ITEM NO. 6.

IIDF - Proposals for assistance under Industrial Infrastructure Development Fund (IIDF) under IIPP 2010-15 & 2015-20 – Regarding.

The Scrutiny / Verification Committee meeting held on 16-11-2016 to verify the proposals for assistance under Industrial Infrastructure Development Fund (IIDF) under IIPP 2010-15 & 2015-20 as per guidelines issued vide G.O. Ms. No. 42, Industries & Commerce (IP) Department dated 05.05.2011, G.O. Ms. No. 108, Industries & Commerce (P&I) Department dated 14.11.2015.

The Minutes of the Scrutiny / Verification Committee are appended at Annexure-III.

The Scrutiny / Verification Committee has verified and scrutinized the proposals and recommend for sanction of eligible amounts for the development of infrastructure facilities to the unit as mentioned below:

Total Amount of Expenditure on Infrastructure considered by the Sl. committee after deducting in-eligible Observation of the Scrutiny / Verification Name and address of the Unit No amounts Committee Amount Infrastructure facility (in Rs.) 1 M/s. Pinnae feeds. Ltd., Sy No. 555/2, etc., Power connection 90,72,014/- Scrutiny and verification committee approved Bogole(V&M), SPSR Nellore District for and formation of and recommended to place in SLC for sanction sanction of financial assistance for the approach BT Road of incentives under IID Scheme. expenditure incurred under IIDF Scheme. 2 M/s. BMM Cements Limited, Gudipadu(V), Providing power 1,00,00,000/- Scrutiny and verification committee approved Yadiki(M), Ananthapur District -- Large Scale supply to the door and recommended to place in SLC for sanction Industry Sanction of financial assistance under step of the Industry of incentives under IID Scheme. IIDF for providing power supply to the door step of the Industry under IIDF Scheme. 3 IIPP 2010-15 Scheme – Claim application of Erection of 4.1 Kms 48,69,377/- Scrutiny and verification committee approved M/s. Srini Food Park Private Limited, Sy. of 33 KV line and and recommended to place in SLC for sanction No.11-24/2, Mogili (V), Bangarupalem (M), 33/11 KV Sub- of incentives under IID Scheme Chittoor District – Submission of claim station proposal - for sanction of Industrial Infrastructure Development Fund (IIDF) under IIPP 2010 – 15.

:: 152 ::

As per the guidelines issued vide G.O. Ms. No. 42, Industries & Commerce (IP) Department dated 05.05.2011, G.O. Ms. No. 108, Industries & Commerce (P&I) Department dated 14.11.2015 the proposal for financial assistance for creation of infrastructure facilities under Industrial Infrastructure Development Fund (IIDF), shall be placed before the State Level Committee and the decision of the SLC shall be sent to Government along with the proposal.

The State Level Committee may take a view. :: 153 ::

Annexure – III

MINUTES OF THE 4th SCRUTINY / VERIFICATION COMMITTEE OF CLAIMS FOR IIDF MEETING HELD ON 16.11.2016 AT 2.00 PM IN THE CHAMBER OF ADDITIONAL DIRECTOR OF INDUSTRIES, O/o. DOI, GOVT. OF A.P., CHIRAG ALI LANE, ABIDS, HYDERABAD

List of members attended:

Sarva Sri

1. B. Suresh Babu, Additional Director (Chairman) 2. Dr.J.Krishnaiah Senior Manager, APSFC (Member) 3. B Subbarao ED,APIIC (Member) 4. L. Girijapathi, AD, FTAPCCI (Member) 5. A. Sreeramprasad, SE/Constn, APTANSCO (Member) 6. G. Sarathkumar, GM-Comml, DISCOM (Member) 7. B. Arunadevi,EE (R&B) (Member) 8. B. SrinivasaRao, Joint Director (INF) I/c, O/o.D.O.I. (Member - Convener)

The claim applications of Industrial Infrastructure Development Fund (IIDF) under IIPP 2010-15 and 2015-20 along with the appraisal notes were placed before the Pre-Scrutiny / Verification Committee has reviewed the item wise agenda and examined the proposals for IIDF and the decisions taken after deliberations are as follows:

Sl. Name and address of the Unit Infrastructure Eligible Observation of the Scrutiny / Verification No facility amount in Rs. Committee . Recommende d by the GM, DIC/DIPC

1 M/s. Pinnae feeds. Ltd., Sy No. 555/2, etc., Power 90,72,014/- Scrutiny and verification committee Bogole(V&M), SPSR Nellore District for sanction of connection approved and recommended to place in

financial assistance for the expenditure incurred under and formation SLC for sanction of incentives under IID IIDF Scheme. of approach Scheme BT Road

2 M/s. BMM Cements Limited, Gudipadu(V), Yadiki(M), Providing 1,00,00,000/- Scrutiny and verification committee Ananthapur District -- Large Scale Industry Sanction of power supply approved and recommended to place in :: 154 ::

financial assistance under IIDF for providing power to the door SLC for sanction of incentives under IID supply to the door step of the Industry under IIDF step of the Scheme. Scheme. Industry 3 M/s. Nexus Feeds Limited, Seesali (V), Kalla (M), West 33 KV -- Scrutiny and verification committee Godavari district for sanction of financial assistance for Potential line reviewed and taken a decision not to the expenditure incurred for obtaining 33 KV Potential for a CMD of consider as the representation of the unit 1600 KVA and line for a CMD of 1600 KVA and L of 2386.2 + 20 KW to holder did not have any reasons to re- L of 2386.2 + the door step of their unit under IIDF Scheme. 20 KW to get examine. However, the unit holder is un-interrupted advised to approach DIPC for power supply. reconsideration of his proposal.

4 M/s. SVR Spinnig Mills pvt ltd, Malleswaram (v). Power -- Scrutiny and verification committee Peravali (M), West Godavari District for sanction of connection HT reviewed and taken a decision not to financial assistance for the expenditure incurred for power line. consider as the representation of the unit obtaining HT power line to the door step of their unit holder did not have any reason to re- under IIDF Scheme – DIPC recommended for rejection examine. However, the unit holder is as the unit is not a standalone unit. advised to approach DIPC for reconsideration of his proposal.

5 IIDF 2010-15 Scheme Claim application of M/s. Avanthi Approach road 73,02,049/- Scrutiny and verification Committee Feeds Limited, Kovvuru, West Godavari District – and extension reviewed and deferred for the following: Submission of claim proposal - for sanction of Industrial of 33 KV 1 Clarification on replacement of existing Power line. Infrastructure Development Fund (IIDF) under 2010-15. poles and lines with new one 2 for Stand alone certificate. 3 The definition of Stand alone for expansion to be decided by SLC.

6 IIPP 2010-15 Scheme – Claim application of M/s. Srini Erection of 4.1 48,69,377/- Scrutiny and verification committee Food Park Private Limited, Sy. No.11-24/2, Mogili (V), Kms of 33 KV approved and recommended to place in Bangarupalem (M), Chittoor District – Submission of line and 33/11 SLC for sanction of incentives under IID KV Sub-station claim proposal - for sanction of Industrial Infrastructure Scheme Development Fund (IIDF) under IIPP 2010 – 15. 7 IIPP – 2010-15 – IIDF – Claim application of M/s. extension of 32,83,267/- Deferred for next meeting by forming a Sub- Swarnalatha Spintex Pvt. Ltd., RS No. ¼, 33 KV Supply committee for detailed study with members :: 155 ::

Serinarasannapalem (V), Bapulapadu(M), Krishna to a CMD of of FTAPSI, TRANSCO & DISCOM and District for sanction of financial assistance for the 1510 KVA with FAPSIA. expenditure incurred of Rs. 65,66,534/- and the 50% of a contracted load of 4654 the expenditure is Rs.32,83,267/- for extension of 33 HP power KV Supply to a CMD of 1510 KVA with a contracted supply to the load of 4654 HP power supply to the door step of their door step of unit under IIDF Scheme. their unit

8 M/s. Veerabhadra Exports Private Limited, Sy. No. 116, Uninterrupted 51,05,300/- Differed for next meeting Gurajanapalli (V), Karapa Mandal, East Godavari power supply District. by laying of 33/11 KV feeder line from Jagannadhapu ram Sub- station to the unit premises.

9 M/s. Paramesu Bio Tech Private Limited, R.S. No. 972, Power Line 58,14,296/- Differed for next meeting Devarapalli Village & Mandal – Sanction of Industrial Charges and Infrastructure Development Fund. laying of approach road

to the industry

10 M/s. Coastal Aqua, RS. No. 142/3 & 143/1P, Power supply 54,22,500/- Differed for next meeting Patariagadda, Karapa Mandal, Esat Godavari District. by laying of 33/11 KV feeder line from Aryavatam Sub-station to the unit premises for continuous, production.

11 M/s. Vimla Feeds Private Limited, R.S. No. 243/1 & power 30,49,256/- Differed for next meeting connection from 33 KV HT :: 156 ::

244, Vattigudipadu (V), Agiripalli (M), Krishna District.. power line with a CMD of 700 KVA and contacted load of 1200 HP and for laying of CC Road from R& B road to unit premises

12 M/s. Ravali Spinners pvt ltd, 3rd expansion unit, Extention of 85,64,000/- Differed for next meeting. khandavalli, peravali, West Godavari District for 132 KV power sanction of financial assistance for the expenditure line charges incurred under IIDF Scheme.

(B. SURESH BABU) (Dr.J.KRISHNAIAH) (B SUBBARAO) Chairman & Addl. Director Senior Manager, APSFC ED, APIIC

(L. GIRIJAPATHI) (A. SREERAM PRASAD) (G. SARATH KUMAR) AD,FTAPCCI SE/Constn, APTANSCO GM-Comml, DISCOMS

(B. ARUNADEVI), (B. SRINIVASA RAO) EE, (R&B) Joint Director I/c &member convener