Jayadeva Flyover Demolition
Total Page:16
File Type:pdf, Size:1020Kb
May 2020 Issue 121 Jayadeva Flyover Demolition Jayadeva Flyover demolition work was done in Two Phases. Phase-1-Banneraghatta Loop-from 15.08.2019 to 31.10.2019 and Phase-2-Main Flyover–from 20.01.2020 to 05.06.2020. A total of 1,03,272 Man hours have been spent along with heavy machines. In This Issue Shri Durga Shanker Mishra, IAS ——————————————–— Secretary to GoI, Ministry of Housing & Urban Affairs, & Chairman, Bangalore Metro Rail Corporation Limited Land Acquisition Status & Critical Issues Phase-2 Civil Progress at a Glance Shri Ajay Seth, IAS Launching of Tunnel Boring Machine Managing Director Track Progress Bangalore Metro Rail Corporation Limited E-News Letter for BMRC Website only https://english.bmrc.co.in/News/NewsSection Address: Bangalore Metro Rail Corporation Limited U Can Contact us 3rd Floor, BMTC Complex, K H Road, Shanthinagar, Email: [email protected]; [email protected] Bengaluru - 560 027. Web: www.bmrc.co.in Toll-free Helpline: 1800-425-12345 1 Critical issues faced regarding Land Acquisition for Phase-2 of the Project Reach-6 Underground Section Langford Town Station:- Local Military Authorities (LMA) have sent the proposal for transfer of 2137.334. sqm of land on permanent basis and 5866.569 sqm on temporary basis to Army Head Quarters. Matter is being pursued with Defence Authorities. Lakkasandra Village Sy. No. 14 and 15:- The re-location of 101 encroachers at Lakkasandra land is under consideration of Deputy Commissioner, Bangalore Urban and Karnataka Slum Development Board. Phase-2 Progress up to 31st May, 2020 PHASE-2 CIVIL WORKS PROGRESS IN PERCENTAGE REACH-1A (BAIYAPPANAHALLI TO VISVESVARAYA INDUSTRIAL 65 AREA) REACH-1B (VISVESVARAYA INDUSTRIAL AREA TO WHITEFIELD) 78 REACH-2A (MYSURU ROAD TO PATTANAGERE) 96 REACH-2B (PATTANAGERE TO CHELLAGHATTA DEPOT) 84 REACH-3C (HESSARAGHATTA CROSS TO BANGALORE 60 INTERNATIONAL EXHIBITION CENTER) REACH-4B (PUTTENAHALLI CROSS TO ANJANAPURA TOWNSHIP) 90 REACH-5-P1 (BOMMASANDRA TO HOSA ROAD) 76 REACH-5-P-2 (HOSA ROAD TO BOMMANAHALLI) 80 REACH-5-P-3 (BOMMANAHALLI TO R V ROAD) 45 REACH-6-ELEV (GOTTIGERE TO SWAGATH CROSS ROAD) 27 0 20 40 60 80 100 120 2 Land Acquisition Status for the month of May, 2020 of Phase-2, ORR -2A & Airport -2B Line No. of properties Handed over to Eng. No. of properties Balance to be Handed Sl. Acquired Section up to Reaches Required over to Engg. Section No [As per 28(4) & 3(1)] May - 2020 Govt. Priv. Total Govt. Priv. Total Govt. Priv. Total Govt. Priv. Total Reach-1 Extn 38 487 525 38 479 517 38 479 517 0 8 8 1 Forest Land 21 0 21 0 0 0 21 0 21 0 0 0 Reach-2 Extn 25 99 124 25 97 122 25 97 122 0 2 2 Station & Viaduct 2 Challaghatta Depot 10 24 34 10 24 34 10 24 34 0 0 0 3 Reach-3C Extn 3 105 108 3 105 108 3 105 108 0 0 0 Reach-4B Extn. 12 294 306 12 294 306 12 294 306 0 0 0 4 Anjanapura Depot 1 20 21 1 20 21 1 1 2 0 19 19 Reach-5 New Line 46 798 844 46 798 844 46 790 836 0 8 8 5 Hebbagodi Depot 1 57 58 1 57 58 1 57 58 0 0 0 Reach-6 (Elevated) 34 222 256 34 222 256 34 222 256 0 0 0 6 Reach - 6 (UG) 52 289 341 52 276 328 49 279 328 3 10 13 Kothnur Depot 4 64 68 4 64 68 4 64 68 0 0 0 Total 247 2459 2706 226 2436 2662 244 2412 2656 3 47 50 7 ORR Line 31 56 87 30 55 85 29 51 80 2 5 7 8 Airport line 59 179 238 59 179 238 13 12 25 46 167 213 Total 90 235 325 89 234 323 42 63 105 48 172 220 Grand Total 337 2694 3031 315 2670 2985 286 2475 2761 51 219 270 3 Phase– 2 Progress Photos at a glance R-1A: Garudacharpalya Station Roof Truss erection work in progress R-1B : Whitefield Station I-Girder Erection work in progress R-2A: Viaduct view from Jnanabharathi Station towards R-2B: Track laying work in progress along Viaduct Pattanagere Station R-4B: Hand Rail work in Ground Floor Entrance at R-3C: Parapet Gantry-2 Launching works in progress Anjanapura Road Cross 4 Phase– 2 Progress Photos at a glance: R-5-P1: Electronic City-I Station works in progress R-5-P2: Oxford Station- Grid C to E Platform Level slab concreting completed. R-5-P3: Sump Raft concrete completed at Ragigudda station R - 6 - Ele: Swagath Station – 04 Pier location P2, P3, P9 & P10 Pier Arm Erection done at Concourse Level R-6-UG-RT1: Aerial view of works at Dairy Circle UG Station R-6-UG-RT1: Barricading works in progress at Lakkasandra Station 5 Launching of Tunnel Boring Machine-R6-UG-RT-2 Lowering of 1st TBM cutter head at Shivajinagar UG Station Contractor - M/s Larson & Toubro Ltd—RT-02 Sl No RT-02 Details of TBM 1 Name of the two TBM’s Avni Lavi 2 TBM Procured from China Railway Construction Heavy Industry, China 3 Launched / Lowered into the Tunnels 28th May 2020 Shivajinagar & Rashtriya Military School 4 Will Tunnel Between Underground Stations 5 Length of the two Twin Tunnels 2141 Meters 6 Diameter of the Cutter Head 6.74 Meters 7 Finished inside diameter of Tunnels 5.80 Meters 6 Launching of Tunnel Boring Machine-R-6-UG-RT-3 Lowering of 2nd TBM cutter head at Cantonment UG Station Contractor - M/s Larson & Toubro Ltd—RT-03 Sl No RT-03 Details of TBM 1 Name of the two TBM’s Urja Vindya 2 TBM Procured from China Railway Construction Heavy Industry, China 3 Launched / Lowered into the Tunnels 28th April 2020 3rd June 2020 4 Will Tunnel Between Cantonment & Shivajinagar Underground Stations 5 Length of the two Twin Tunnels 860 Meters 6 Diameter of the Cutter Head 6.74 Meters 7 Finished inside diameter of Tunnels 5.80 Meters 7 Track Progress at a glance View of Track work completed at Reach-4Extn up to Anjanapura Station Contractor - M/s Texmaco Rail & Engineering Limited Sl No Item Description Unit Track Plinth Casting Reach 4 Reach 2 Sections Track Meters (May 2020) (May 2020) 1 Scope of Work Trm 12580 17628 2 Progress for the month Trm Nil 70 3 Cumulative progress Trm 11700 5193 4 Access Handed over Trm 11700 14000 8 .