LOCAL AREA High Speed Rail Consultation In Your Area 12: to Hampton-in-Arden

Find out here about:

●● what is proposed between Kenilworth and Hampton-in-Arden; ●● what this means for people living between Kenilworth and Hampton-in- Arden; and ●● what would happen during construction.

What is proposed between What this means for people Kenilworth and Hampton-in- living between Kenilworth and Arden? Hampton-in-Arden

The proposed route would pass the north-east The proposed green tunnel at Burton of Kenilworth largely in cutting, passing Green underneath the to Kenilworth railway. The 300 metre long green tunnel would pass Following the alignment of a disused railway in under Cromwell Lane in . Green cutting, it would then pass through Burton tunnels differ from bored tunnels. The former Green, hidden within a 300 metre long green are built from the surface downwards, whereas tunnel. It would continue along this disused rail bored tunnels are built from below the ground. corridor towards and to the north- east of . East of Berkswell Station it would cross over the to Coventry railway and past Berkswell House.

The proposed route would then pass alongside the in a cutting, running north of Balsall and Bradnock’s Marsh. The A452 would be raised east of Hampton-in-Arden to lift the road over the high speed line.

A typical green tunnel High Speed Rail Consultation In Your Area 12: Kenilworth to Hampton-in-Arden

We would expect the green tunnel to take 1 to For most of its length, the track level of the 2 years to build. Construction would involve viaduct would be between 8m and 10m above work in the existing cutting, building a tunnel ground level. We would commission an structure within it and then landscaping back architectural design to ensure as attractive an over with earth. appearance as possible, and we would provide noise barriers to limit noise. We do not expect that there would be any noticeable vibration effects for residents in the Construction would take 1 to 2 years. We have vicinity of the tunnel. not considered detailed locations for work sites at this time. We would work closely with local The proposed viaduct at Berkswell people and relevant authorities to ensure that When it passes by Berkswell the proposed any disruption during construction would be route would be about 5 to 7 metres above minimised, including the movement of ground level on an embankment. It would pass construction traffic. over the existing railway and Truggist Lane, as well as a number of Noise water features. Much of the proposed section would run in cutting or follow the line of the disused railway The existing railway would be crossed on a line. We would incorporate noise barriers or short bridge, but Truggist Lane and the bunds (earth banks) to minimise the effects of adjacent ponds would be crossed on a viaduct noise and as a result we currently predict that due to the watercourse and flood plain. only a small number of households would be likely to experience a perceptible increase in The proposed viaduct at Berkswell would be a noise. These are located in the areas marked in two track viaduct built from concrete, with grey on the noise map in this factsheet and are spans of 20m – 50m. It would be 240m long typically those areas close to the proposed rail and about 15-17m wide. corridor.

Three areas in close proximity to the proposed route at Burton Green, Lavender Hall Lane, Berkswell and adjacent to the A452 – indicated in yellow on the noise map – may experience a noise increase that would qualify for noise insulation as described in the current Railway Noise Insulation Regulations (NIRR). One area – indicated in red on the noise map – close to the line alongside the B4102 may experience a high noise level. If the project is taken forward we would carry out more detailed noise assessments and consideration of noise Plan of viaduct and surrounding area mitigation to see whether these potential noise effects could be further reduced or avoided. Landscape and townscape habitat fragmentation and create opportunities We have identified no effects on internationally, that could improve the natural links between nationally or regionally protected landscapes in other local wildlife sites and habitats. this section of route. The green tunnel at Burton Green would help reduce visual effects in this Heritage area. Tree planting and landscaped earth bunds This section of the proposed route would could also help integrate the railway into the largely avoid direct impacts on any landscape and reduce visual effects. internationally important heritage features. However, the Grade II listed building at Dale Where viaducts are proposed, for example the House Farm could be demolished or possibly one proposed near Berkswell, we would ensure moved. The setting of the Grade II* Lavender such structures would be designed sensitively Hall Farmhouse could also be affected. We to suit the local area. would work with property owners and English Heritage to assess and minimise potential Water impacts to the structure or settings of such The proposed route would cross several rivers properties. and streams including the River Blythe, as well as a number of flood plains. Any potential Property and Land effects on these waterways and their wildlife We expect that five homes would probably would be kept to a practicable minimum and need to be demolished in this area. A small we would work with the Environment Agency number of further properties could be at risk of and Natural in order to determine the having some land taken; although once detailed best approach for doing this. All of the design is carried out it may prove that many of proposed engineering structures would be these are not affected. designed to take into account future flood risk. Where the Government needs to compulsorily Wildlife purchase and demolish individual properties we No effects on internationally important wildlife do not expect this to happen before 2015, and sites have been identified for this section but later than that in the majority of cases. Where the route would cross one nationally important homes would need to be demolished owners site – the River Blythe Site of Special Scientific would be fully compensated. Equally, where Interest (SSSI). The route would pass directly businesses would be affected they would be over this SSSI on a viaduct that would be eligible for compensation. See factsheet: engineered to avoid pillars in the river. This “Arrangements for Dealing with Property Blight” would minimise any direct effects. We would for more details. work closely with relevant agencies to ensure that any possible effects on the SSSI would be Transport networks and access managed appropriately and would also look for It may be necessary to carry out permanent opportunities where the route corridor could minor diversions of several roads, including help benefit biodiversity. Dalehouse Lane, the A429 north-east of Kenilworth, Lavender Hall Lane and the A452 The route would directly cross a locally south-east of . Several important woodland – Broadwells Wood – and temporary diversions could also be needed. would skirt the edge of Crackley Wood Local We would work with local authorities in order to Nature Reserve. There would be a good minimise any traffic disruption which might arise opportunity in these areas to help address from this. High Speed Rail Consultation In Your Area 12: Kenilworth to Hampton-in-Arden

Noise Impact Key The map gives an indication of the properties that would experience noise once the proposed HS2 services are operating, based on our noise modelling, and assuming mitigation in place.

Noticeable Noise Increase Areas which could have a perceptible change in average daytime railway noise levels where the predicted

noise level is more than 50dBLAeq,18hr and there has been a 3dB increase or more.

Noise Insulation (NIRR) Areas which could have a requirement for noise insulation (based on regulations) where façade noise levels

are more than 68dBLAeq,18hr with a 1dB increase or more.

High HS2 Noise Levels Within the areas which could qualify for noise insulation we have also identified locations which could be

exposed to “high” average noise levels i.e. greater than or equal to 73dBLAeq,18hr. This is the level taken from the Environmental Noise Regulations. High Speed Rail Consultation In Your Area 12: Kenilworth to Hampton-in-Arden

Any effect on cycle routes and footpaths and any necessary diversions would be addressed as more detailed planning is done. Wherever possible, paths would be reinstated or alternatives provided to ensure continued public access.

What would happen during construction

In consultation with local authorities and other key authorities, contractually binding conditions covering all aspects of construction would be put in place to regulate how works are conducted at each site.

The effects of construction, for example dust, noise or traffic disruption, would be minimised through a combination of careful design, working with the local community and close management of the construction process. These would be managed through a Code of Construction Practice, relevant Environmental Management Plans or Traffic and Transport Management Plans.

If you would like more detail on this topic…

Please visit our website – http://highspeedrail. dft.gov.uk/ – where you will see the “High Speed Rail: Investing in Britain’s Future – Consultation” and all the documentation published alongside it, as well as detailed maps of the proposed route between London and the West and images and visualisations. High Speed Rail Consultation In Your Area 12: Kenilworth to Hampton-in-Arden

© Crown Copyright 2011. Product code HSRFCT40. Printed in Great Britain on paper containing at least 75% recycled fibre.