Quick viewing(Text Mode)

Longyan Railway Project

Longyan Railway Project

Environmental Monitoring Report

Project Number: 33442 (Loan 1850) December 2006

People’s Republic of : - Railway Project

Prepared by the OASIS Environment Protection Technology Co., Ltd.

{Firm name}

{City, country}

For {Executing agency} {Implementing agency}

This report has been submitted to ADB by the Ministry of Railway and is made publicly available in accordance with ADB’s public communications policy (2005). It does not necessarily reflect the views of ADB.

Asian Development Bank Loan Project

Ganzhou-Longyan Railway

Environment Monitoring Summary Report

Beijing OASIS Environment Protection Technology Co., Ltd.

December 2006

Table of Contents

1 PREFACE ...... 1

1.1 PROJECT INTRODUCTION...... 1

1.2 OBJECTIVES ...... 2 2 INTRODUCTION OF THE PROJECT ...... 3

2.1 INTRODUCTION OF ENGINEERING ...... 3

2.2 GENERAL ENVIRONMENTAL SITUATION ALONG THE LINE...... 5 3 REVIEW OF ENVIRONMENTAL PROTECTION IN CONSTRUCTION PERIOD .8

3.1 ENVIRONMENTAL MANAGEMENT OF PRE- CONSTRUCTION PERIOD ...... 8

3.2 ENVIRONMENTAL MONITORING DURING CONSTRUCTION PERIOD ...... 13 4 SURVEY OF ENVIRONMENTAL PROTECTION MEASURES IN OPERATIONAL PERIOD ...... 17

4.1 ECOLOGICAL ENVIRONMENT ...... 17

4.2 ACOUSTIC ENVIRONMENT ...... 22

4.3 WATER ENVIRONMENT ...... 26

4.4 AIR ENVIRONMENT...... 28

4.5 SOLID WASTE ...... 28

4.6 IMPLEMENTATION OF ENVIRONMENTAL MANAGEMENT AND MONITORING SYSTEM DURING

OPERATIONAL PERIOD ...... 29 5 SURVEY OF IMPACTS ON LOCAL ECONOMY BY THE RAILWAY...... 29

5.1 RAILWAY SECTION IN ...... 29

5.2 RAILWAY SECTION IN PROVINCE ...... 30 6 SUMMARY...... 32 List of Pictures 1. Environment protection dissemination brand. 2. Sedimentation tank at Xiashan Tunnel. 3. Grass planted on the embankment slope. 4. Grass planted in the framework on embankment slope. 5. Protection of cut slope. 6. DK26+600 borrow pit. 7. DK77+200 borrow pit. 8. DK87+600 borrow pit. 9. DK101+400 borrow pit. 10. DK177+340 Nanshan village borrow pit. 11. Borrow pit at the right side of Xinquan station. 12. Cut excavations used into Xiaochi Station. 13. Spoil disposal site at DK73+000 for Damadu Tunnel exit. 14. Spoil disposal site for No.2 Shenkeng tunnel exit. 15. Spoil disposal site at DK118+800 for Mingan Tunel. 16. Spoil disposal site at DK213+500. 17. Spoil disposal site at DK246+100. 18. Spoil disposal site for the inclined shaft of Jiaoyang tunnel. 19. River bank protection of Diaozhongyan Super Major Bridge. 20. Quadrant revetments of Nanshan Major Bridge. 21. Cofferdams of Liangfu 2# Major Bridge had been cleared. 22. Spaces between piers of Jiangxia Super Major Bridge had been recovered. 23. The camp of Diaozhongyan super major bridge had been changed into a timber mill. 24. Rail laying base at Maodian Station had been recovered. 25. Remained access roads at DK101+400. 26. Square in the fron of Changding station. 27. Huanglong Elementary School (originally known as Liulidian Elementary School). 28. New site of Dongxi Elementary School. 29. New site of Yudu Work Technique School. 30. Shanfeng Elementary School. Environment Monitoring Summary Report of Ganzhou-Longyan Railway

31. New school building of Shantang Elementary School.

Beijing OASIS Enviroment Protection Technology Co.,Ltd. 4

32. New site of Niushui Elementary School. 33. New school building of Meigang Middle School. 34. New site of Shangxishanxia Village. 35. New site of Nanduan Elementary School. 36. Waste water treatment equipment in Yudu station. 37. Waste water treatment equipment Xijiang station. 38. Waste water treatment equipment locomotive returning station. 39. Waste water treatment equipment Ruijin station. 40. Waste water treatment equipment Changding station. 41. Waste water treatment equipment Guanzhishan station. 42. Waste water treatment equipment Shanghang station. 43. Solar water heater in Yudu station. 44. Solar water heater in Ruijin locomotive returning station.

Environment Monitoring Summary Report of Ganzhou-Longyan Railway

1 Preface

1.1 Project Introduction Ganzhou-Longyan Railway is a project to be executed by using loan from Asian Development bank. It starts from Ganzhou City of Jiangxi, runs eastwards along Gongshui River, a branch of Ganjiang River, enters Changting, Liancheng and Shanghang in Fujian Province after running through Gan County, Yudu, Huichang and Ruijin, and then ends at Longyan City of Fujian. It wholly is 290.1km long (132.3km in Jiangxi and 157.8km in Fujian). Construction of the railway has opened a new way for transportation in Jiangxi and Fujian province, and will make great significance in improvement of rail web distribution as well as local railway transportation. Construction of Ganzhou-Longyan Railway was from December 2001 to 30th December 2004. Freight train began running on 1st April 2005 and passenger train began on 11th October 2005. According to the Environmental Protection Law of PRC and environmental management regulations for construction projects, construction of the line had been implemented EIA rule and “three contemporary” rule, which means environmental facilities and major engineering to be designed, constructed and put into use contemporarily. During the construction period, Construction Commander of the project had strictly obeyed the environmental laws and rules of our country, and ensured the environmental measurements and funds to be implemented. Ganzhou-Longyan Railway between the Ministry of Railway and Asian Development Bank, both the Ministry and the Bank have agreed that the environment-monitoring task for Ganzhou-Longyan Railway shall be borne by Beijing OASIS Environment Protection Technology Co., Ltd.. According to relevant laws and regulations of the state as well as the environmental monitor plan of this line and the signed monitor agreement, Oasis Company sent environmental protection experts from Jun. 2002 to present to provide pre-post training on site, survey and supervise the site. It has submitted 13 quarterly and annual monitor reports regularly to Ganzhou~Longyan Railway Construction Headquarters, Ministry of Railways, and Asian Development Bank. This report is the environment monitoring summary report.

Beijing OASIS Enviroment Protection Technology Co.,Ltd. 1 Environment Monitoring Summary Report of Ganzhou-Longyan Railway

1.2 Objectives The objective of this monitoring report is, based on project design and environment assessment, to check how the environment protection measures are performed during the construction period and what problems exist and to give some suggestions to solve such problems. It is supplementary to the environment impact evaluation of the project and also is to supervise the performance of environment protection measures. This report is to report how the onsite environment protection measures are executed in the construction activities and to ensure that these activities are in compliance with related environmental protection regulations and the requirements from MOR (Ministry of Railway) and Asian Development Bank. More exactly, the report is to:

• Verify whether actual environmental impacts at construction phase were similar to those predicted by the EIA; • Inspect implementation situation of the environmental protective measures designed in the EIA; • Identify any unexpected problems and put forward recommended solutions; and • Report to MOR, Asian Development Bank and concerning departments about the environmental protection activities for this project.

According to the environment impact assessment report (EIA), the environment monitoring report includes the following contents: ecological impact caused by railway construction such as restoration of borrow pit, spoil disposal site, and construction camp, protection of roadbed slope, reforestation of station site, etc.; implementation of related treatment of waste water and noise mitigation measures in operational period; and environmental problems affecting local economy development due to construction of Ganzhou-Longyan Railway.

The persons in charge of preparing this environment monitoring report are as follows:

Sun Jian Engineer

Beijing OASIS Enviroment Protection Technology Co.,Ltd. 2 Environment Monitoring Summary Report of Ganzhou-Longyan Railway

Lu Dongmei Engineer Wang Zhiqiang Engineer

2 Introduction of the project

2.1 Introduction of engineering The newly built Ganzhou-Longyan Railway is from the Ganzhou east station on Beijing-Jiulong Line to Longyan Station on -Longyan line, passes Ganxian County, , Ruijin City in Jiangxi Province and Changding County, Liancheng County, , of Longyan City in Fujian Province. Total length of the line is 290.1km, including 132.3km in Jiangxi Province and 157.8km in Fujian Province. The line extended from west to east, detailed line direction see the line Plan.

2.1.1 Main Technical Criteria Main technical criteria of the Ganzhou-Longyan Railway construction design see table 2-1.

Table 2-1: Main Technical Criteria of the Ganzhou-Longyan Railway Project Technical Criteria Line Classification Ⅰ Number of Main Track Single line Ganxian-Ruijin 6‰ Ruling Gradient Ruijin-Longyan double headed train 12.5‰ 1,200m in ordinary areas; 550m in several Minimum Radius of Curve difficult areas Kind of Traction Diesel Locomotive Type of Locomotive DF4D Tonnage Rating 3500 t Effect Length of Track 650 m

2.1.2 Amount of Traffic 2007 is the original future design year, 2009 is the near future design year, 2014 is the specified future design year of Ganzhou-Longyan railway. On 1st April 2005, the railway started operating. Designed and Actual Pairs of Trains see table 2-2.

Beijing OASIS Enviroment Protection Technology Co.,Ltd. 3 Environment Monitoring Summary Report of Ganzhou-Longyan Railway

Table2-2: Designed and Actual Pairs of Trains Unit:(Pairs/day) Pairs of Trains Design in near future Design in specified future Actual (2009) Section (2014) Passenge Passenge Passenger r coach wagon r coach wagon coach wagon Ganzhou-Longyan 8 12 12 14 3 7

2.1.3 Dimension of the main stations Dimension of the main stations see table 2-3. Table2-3: Dimension of the main stations Station Character Engineering contents Passing Newly-built 2 receiving-departure lines; little amount of Sanmei Station Station domestic sewage discharged after treated by septic tank. Newly build 2 receiving-departure lines and a shunting neck of 350m long; 2100 m2 passenger building; a main platform Intermediate Yudu Station and an intermediate platform of 400 6m and 400 9m Station × × respectively. Newly-built waste water treatment plant adopting integrated treatment equipment. Passing Huanglin Station Newly-built 3 receiving-departure lines. Station Newly build 2 receiving-departure lines and a shunting neck of 350m long; 2100 m2 passenger building; a main platform Intermediate Xijiang Station and an intermediate platform of 400 6m and 400 9m Station × × respectively. Newly-built waste water treatment plant adopting integrated treatment equipment. Shimenyu Intermediate Newly-built 3 receiving-departure lines. Station Station Newly-built 4 receiving-departure lines and a shunting neck of 350m long; 4100 m2 passenger building; a main platform Intermediate Ruijin Station and an intermediate platform of 500 9m and 500 9m Station × × respectively. Newly-built waste water treatment plant adopting SBR technique. Passing Gucheng Station Newly-built 2 receiving-departure lines. Station Intermediate Newly-built 2 receiving-departure lines and a shunting neck of 350m long; 2200 m2 passenger building; a main platform Changding Station and an intermediate platform of 400×6m and 400×9m Station respectively. Newly-built waste water treatment plant adopting integrated treatment equipment. Intermediate Newly-built 2 receiving-departure lines and 3200 m2 Hetian Station Station passenger building. Passing Zhongfu Station Newly-built 2 receiving-departure lines. Station Newly-built 2 receiving-departure lines and a shunting neck of 250m long; 2200 m2 passenger building; a main platform Guanzhishan Intermediate and an intermediate platform of 400×6m and 400×9m Station Station respectively. Newly-built waste water treatment plant adopting integrated treatment equipment.

Beijing OASIS Enviroment Protection Technology Co.,Ltd. 4 Environment Monitoring Summary Report of Ganzhou-Longyan Railway

Intermediate Newly-built 2 receiving-departure lines and 3200 m2 Xinquan Station Station passenger building. Passing Zhuyuan Station Newly-built 2 receiving-departure lines. Station Newly build 2 receiving-departure lines and 2100 m2 Shanghang Intermediate passenger building and a main platform of 400 × 6m. Station Station Newly-built waste water treatment plant adopting integrated treatment equipment. Intermediate Newly-built 2 receiving-departure lines and 3200 m2 Xiaochi Station Station passenger building.

2.1.4 Locomotive and vehicle equipment A locomotive reversing station will be set at Ruijing.

2.1.5 Amount of the main engineering Amount of the main engineering of this project see table 2-4. Total estimated budget of the project is 6.3297billion , including 164.6million yuan of environmental investment, equaling to 2.6% of the total investment.

Table 2-4: Actually finished main engineering amount Unit of Name of the item Amount measure Length of main line Newly-built km 290.1 Roadbed 4397 Roadbed engineering ×104m3 Stations 187.76 10 super large bridges 87 big bridges 44 medium Number 156/35766 Bridges and culverts bridges /meter 15 minor bridges Number Culverts 1200/35571 /meter Number Tunel Newly-built 120/68481 /meter Total length of bridges and tunels km 104.247 Percent of bridges and tunels % 35.9 Buildings Newly-built m2 91635 Land occupy 14336

2.2 General environmental situation along the line

2.2.1 General situation of natural environmental Ganzhou-Longyan Railway is from Ganzhou to Longyan, along 319 and 323

Beijing OASIS Enviroment Protection Technology Co.,Ltd. 5 Environment Monitoring Summary Report of Ganzhou-Longyan Railway national road, passes through south Jiangxi Province and west Fujian Province. Topography along the line is mainly medium and low hill areas, valleys, most of which is densely covered with vegetation. The line passed the Wuyi Mountain where Jiangxi Province and Fujian Province meet and water is divided into two different systems. West side of the Wuyi Mountain in Jiangxi Province is belonged to Gongshui water system, which is a branch of Ganjiang River. Boping Mountain and Daiyun Mountain are the watersheds in Fujian Province, from west food of the mountains to Wuyi Mountain belongs to water system of Dingjiang River and east side belongs to water system of River. Impacted by the climate, topography, biology, parent rock and soil forming age, etc., soil types along the line are different, mainly as laterite, including loess, purple soil, soil, meadow soil, chao soil and paddy soil, etc. Climate along the line belongs to wet subtropic monsoon area, warm in winter and hot in summer. Average temperature is between 15℃ and 19.9℃. Annual rainfall is between 1400 and 1800mm. Impacted by monsoon climate, monthly rainfall is not even, which is most during April and June equaling to 45~48% of a year. Vegetation resources along the line are rich, mainly as ever-green broad leave forest and monsoon broad leave forest, which are the highest communities among the vegetations in middle and south subtopic zone and have the highest stability and biggest ecological effectiveness. But because of over exploitation for a long time, most natural forests have disappeared, only can be found in rural mountain areas such as in Buyun and Plum blossom mountain Natural Protection Area, and boundary between Yanshi and Wan’an, etc. Vegetation coverage percent in Jiangxi Province is 49.1%~70.8% and mainly as young forests. In some hilly places with serious soil , vegetation coverage percent is below 10%. Forest coverage percent in Fujian Province is 76.4~81.9%, mainly as timber and firewood forest, but vegetation coverage around Hetian in Changding County is not good. There are few rare wild animals in Jiangxi Province but many wild animals in Fujian Province because of comparatively good ecological environment in large scale of mountain area in Fujian Province. But because of longtime irregular deforestation, forest resources were destroyed seriously. Together with irregular

Beijing OASIS Enviroment Protection Technology Co.,Ltd. 6 Environment Monitoring Summary Report of Ganzhou-Longyan Railway killing and capture, amount of many wild animals has decreased greatly, some of which are tending to disappear, especially big carnivore. At the beginning after liberation, there were still South Chinese Tigers and Clouded Leopard, etc., which had threatened local living stocks. In the beginning of 1990s’, tigers occationally appeared at Huangzong and Heci area in Laiyuan County. Now we can only judge through the foot print and claw trace found in Plum blossom Mountain 20km away from the line that South Chinese Tiger still exists. According to surveys, there are 380 species, 229 genus and 79 families of land-inhabiting backbone animal, including 70 species, 42 genus and 20 families of beasts, 211 species, 135 genus and 41 families of birds, 70 species,40 genus and 10 families of reptiles and 30 species, 8 genuses and 8 families of amphibians.

2.2.2 Social Environment Situation Direct absorb areas of Ganzhou-Longyan Line are Ganzhou city in Jiangxi province and Longyan city in Fujian province, about 58367km2, with 1.073million porpulation, the density of which is 184persons per km2. Peasant porpulation is about 8.92million, account for 83.2% of the total. Agricultur has some dominance in the area and is the traditional domain. But because located in mountain areas, field is short compared with big porpulation, self food supply is not enough. Located in mountain areas, areas along the line own rich forestry resources and special forestry products. Thanks for good weather condition, the area also produces lots of economical crops like , tobacco leave and orange, and Ganzhou city is famous for her oranges across China. Mineral resources in the area is very large, mainly as coal, iron, manganese, copper, lead, zinc, tungsten, troilite and salt ore, etc. At present, most of the ores have been exploited. The area owns some industrial background, but distribution of which is unbalanced. Industries and ores mainly distribute in Longyan and Ganzhou city area. Main industrial products include raw coal, pig iron, electricity, cement, synthetic ammonia and drinks, etc. Coal, metallurgy, electricity and building material industry are comparatively developed in Longyan city, which is an important energy and raw materials producing base. At present, there are 4 types of transportation through railway, highway, waterway and air. Railway and highway transport carry most of the freight, air transport only takes on a very small quantity of freigh.

Beijing OASIS Enviroment Protection Technology Co.,Ltd. 7 Environment Monitoring Summary Report of Ganzhou-Longyan Railway

There are many traveling resources in the area, natural and culture sights are both famous. At a distance of 45km from the railway, Yongding Siol building in Longyan is a world famous building. Guanzhishan Mountain, a nation-level scenery, is about 20km from the line. Longkong Cavity in Longyan, a province-level scenery, is about 30km from the line. Plum blossom Mountain, a nation-level natural protection area, is about 20km from the line. Lishi Ancestral Hall is about 30km from the line. All of the above forms a travel zone famous as “one building, one cavity, one area and one hall”. The Plum blossom Mountain natural protection area owns many sources of animals and plants, including 8 kinds of 1st class protective animal and 33 kinds of 2nd class of that. It is proved that the special kind of tiger, South Chinese Tiger, is also exit in the area. So it is called “a on the desert zone on the Tropic of Cancer” and “gene bank of animals and plants”. There are many revolution sites in west Fujian and south Jiangxi province. Ruijin Central Revolution Base Memorial is about 15km from the line, and Shanghang Gutian Meeting Memorial is about 10km away from the line. Both of them are listed in the 100 national demonstration bases for patriotism education. At present, because the travel resources have not been developed very well, together with inconvenient traffic, tourism in most of the area is need to be exploited.

3 Review of environmental protection in construction period

3.1 Environmental management of pre- construction period

3.1.1 Environmental protection before construction Ganzhou~Longyan Railway Construction Headquarters puts environmental impact report and contents involved in the environmental monitor plan into the tender document of the project, and the environmental protection measures as formal articles into the civil engineering contract during engineering bidding to be strictly implemented by the bidding sectors. In the early stage, pre-post training on environmental protection is provided for leaders in charge of environmental protection from the construction and supervision units of all tender sections as well as professional and part-time engineers. The experts from Oasis give lectures on laws and regulations of the

Beijing OASIS Enviroment Protection Technology Co.,Ltd. 8 Environment Monitoring Summary Report of Ganzhou-Longyan Railway state and locality concerning environmental protection and soil preservation involved in the construction project; environmental protection problems advanced in design as well as measures and requirements for environmental protection during the construction period; major contents and requirements of the environmental impact appraisal report and environmental action plan; contents of environmental protection for the railway project during construction period and relevant regulations; contents concerning environmental monitor for Ganzhou~Longyan Railway Project.

3.1.2 Environmental protection in construction period Railway Bureau Ganzhou~Longyan Railway Construction Headquarters and Railway Bureau Ganzhou~Longyan Railway Construction Headquarters establish the environmental protection working systems respectively led by Executive Deputy Commander Yungen, Fu Siliang and with participants from the executives of all tender sections to take charge of environmental protection for Ganzhou~Longyan Railway during the construction period. See Figure 3-1 and 3-2. The construction tender sections formulate respective measures for environmental protection and soil preservation according to environmental monitor requirements, put environmental management into details, carry out the environmental protection personnel responsibility system, clarify their responsible areas, analyze the environmental pollution possibly met during construction, and formulate regulations on daily environmental monitor. In the process of construction, Ganzhou~Longyan Railway Construction Headquarters strictly carries out the laws and regulations of the state on environmental protection, ensures fulfillment of environmental protection measures and capital, check environmental protection and construction of the whole line regularly and irregularly, and conducts immediately correction and settlement of the environmental impact occurred during construction and requests advanced by Oasis Company through daily monitor. It also develops environmental protection activities on “Protect Ecological Environment and Construct Green Passage” over the whole line to enhance the consciousness of all the personnel on environmental protection and . It asks all tender sections to set up slogans and boards concerning environmental protection (picture 1) and soil erosion on which the executives and telephone numbers of

Beijing OASIS Enviroment Protection Technology Co.,Ltd. 9 Environment Monitoring Summary Report of Ganzhou-Longyan Railway contact or complaint are marked. The works of environmental protection and soil erosion are put into the quarterly labor competition appraisal of the headquarters.

Beijing OASIS Enviroment Protection Technology Co.,Ltd. 10

Gan-Long Railway Construction Commanding

Office of Nanchang Railway Bureau Environment Monitoring Summary Report ofGanzhou-Longyan Railway

Environmental Protection Principal: Li Yungen Beijing OASIS Enviroment Protection Technology Co.,Ltd Environmental Protection Contact Person: Fan Chunyu

No.3 No.1 No.2 No.4 No.5 No.6 No.7 Tender Tender Tender Tender Tender Tender Section Tender

Fan Shuiqi Liu Heling Xing Baozhen Li Chuan Wang Faming Rong Denglu Li Xianhui Xue Jin Dongchun Wang Zhenghai Zhang Hongtao Cheng Ruirong Wencai Chen liangping

Note: The boldface words are the names of environmental protection principals; and the non-boldface ones are the names of environmental protection contact persons.

Figure 3-1 Diagram of Environment Protection Management System of Gan-Long Railway (Jiangxi Section)

11 11

. Environment Monitoring Summary Report of Ganzhou-Longyan Railway

No.19 Tender Hongtu Rongwei No.18 Tender Bao Xiaodong Bao Mingqing Lan No.17 Tender Liu Xueqin Kefeng Cheng Mingzhong No.16 Tender Wei Zhao Xiaoyang Gan-Long Railway (Fujian Section) g Guanren No.15 Tender Tender Section Huan Caibo Liu

Bureau y uang No.14 Tender Tender iu Zengg iu Hengquan Bai

L ontact Person: Guo Huaping hai Railwa g No.13 Tender Zhang Zhiming Li Gang Office of Shan Office No.12 Tender Qinyan Hui Wang t Protection Management System of System t Protection Management Gan-Long Railway Construction Commanding environmental protection principals; protection principals; environmental . Environmental Protection Principal: Fu Siliang Principal: Protection Environmental Protection C Environmental e names of environmental protection contact persons. persons. protection contact of environmental e names No.11 No.11 Tender Shen Guanlin Guanlin Shen Shen Zhenxing No.10 Tender Tender Xu Weiquan Weiquan Xu Haiquan Zhou No.9 Tender Tender Xu Weinong Weinong Xu Li Zhiqing

No.8 and the non-boldface ones are th and the non-boldface ones Tender Tender Figure 3-2 Diagram of Environmen Li Zhongliang Zhongliang Li Fuxiang Liu Note: The boldface words are the names of names The boldface words are the Note:

Beijing OASIS Enviroment Protection Technology Co.,Ltd 12 Environment Monitoring Summary Report of Ganzhou-Longyan Railway

3.2 Environmental monitoring during construction period

3.2.1 Contents and system of environmental monitoring Our company is responsible for seasonal environmental monitoring survey to construction sites. Construction units and supervision unit conduct daily monitoring in construction period. Data in different aspects was collected during the monitoring and monitoring report was addressed according to the field visit. Block diagram of environment monitoring system see figure 3-3. Their main monitoring contents include: retaining and protection of slag spoiling ground for tunnels and recovery of vegetation, disposal of spoiled slag during construction of bridge foundations, treatment measures of muddy water due to excavation of pier foundations, leveling, tillage restoring or grass planting situations of large borrow pits along the line, protection state of spoil ground, protection and vegetation recovery for roadbed slopes along the line, dust control of construction roads, garbage treatment, living sewage treatment and sanitation conditions in construction campsite, relics protection along the line, implementation state of protection measures for schools severely affected by noise along the line, etc.. Following aspects were the requirements to each construction unit by us as environmental monitoring unit: Require various concerning organizations to employ full-time environment protection persons. All full-time environment protection persons must have accepted special training on environment protection and they should be responsible to supervise and manage various environmental problems arising during production of their own organizations and assist environment management departments to well manage environment protection work. z Require various construction units to perform various environment protection statements in the construction contract. The construction units are required to work out appropriate environment protection measures according to environment protection requirements set forth in design documents, so as to protect the environment of construction sites and avoid and reduce environment pollution and damage due to inappropriate construction measures. Once any event to damage the environment happens, they should

Beijing OASIS Enviroment Protection Technology Co.,Ltd. 13 Environment Monitoring Summary Report of Ganzhou-Longyan Railway

actively take remedies. If they cannot solve such events by themselves, they should immediately invite appropriate experts and organizations to assist them to solve the problems. z Requires to perform daily environment supervision work upon environment protection requirements set forth in the construction contract. once any environmental problems occur during construction, it should urge the construction unit to solve them in time and it should incorporate environment protection into the engineering quality supervision system.

Beijing OASIS Enviroment Protection Technology Co.,Ltd. 14 Environment Monitoring Summary Report of Ganzhou-Longyan Railway

Consultation Services

Entrust and Assist

Gan-Long Railway Gan-Long Railway

Construction Commanding Construction Commanding

Office of Nanchang Bureau Office of Shanghai Bureau

Contract award

Environment Contracting Training Monitoring Unit Implementation & Supervision

Construction Unit Supervision Company

Implementation Supervision

Construction of Gan-Long Railway Project Implementation Supervision

Figure 3-3 Block Diagram of Environment Monitoring System

Notes of the block diagram: Gan-Long Railway Engineering Commanding Office of Nanchang Railway Bureau and Gan-Long Railway Engineering Commanding Office of Shanghai Railway Bureau: As the project implementation units, entrust and assist the supervision companies to complete supervision, and when awarding the contract, sign up the contract containing environment protection requirements with construction and supervision companies.

Construction company: According to contractual requirements, execute the construction of the project and complete the environment protection work

Supervision company: According to contractual requirements, supervise the project quality and environment protection procedures.

Monitoring unit: As external monitoring unit, train various construction and supervision persons, supervise the execution of environment protection work, and submit the monitoring report to the Ministry of Railway and Asian Development Bank.

Beijing OASIS Enviroment Protection Technology Co.,Ltd. 15 Environment Monitoring Summary Report of Ganzhou-Longyan Railway

3.2.2 Effects of environmental monitoring During the construction, all construction units earnestly carry out contract articles concerning environmental protection, organize construction in strict accordance with the design scheme, and basically synchronize roadbed consolidation and protection, tunnel slope and intercepting ditch protection, tunnel dump area protection, bridge cone protection, etc. with construction of the bulk project. The earth and rocks from tunnel and roadbed excavation shall try to be used for filling roadbeds and stations, processing slice stones or for construction of local villages, towns, and roads. Surplus tunnel slag is generally dumped on waste lands or slopes to reduce occupation of arable land. After dumping, level the surface for forestation or hand the land to local townships for house construction. There has been no slag (earth) area that collapses or coasts due to improper baffling. For construction of bridge piers in water, coffers are set up to prevent mud flowing into the river, the slag and earth are removed promptly after construction; the mud from borehole foundation is generally treated by temporary settling tank for cyclic use; after foundation construction, the mud in the settling tank is dried naturally and filled and compacted between the bridge piers to avoid secondary pollution. For turbid sewage from tunnel construction, different volumes of settling tanks are set up according to the water yield of the tunnel to guarantee certain period of detention and settle the suspended matter down. The construction unit at the outlet of Xiashan Tunnel builds a simple settling tank and the tunnel water becomes quite clear after going through three-level sedimentation, the drainage may satisfy requirements of grade 1 in the GB-8978-1996 Sewage comprehensive discharge standard, does not produce pollution over downstream river channels. To alleviate and prevent soil erosion from railway construction, protection of roadbeds, trenches, borrow-pits, and dump areas is strengthened during construction; seeds and turfs are grown on the slopes for forestation. Plants have a low survival rate in the region near Ganzhou~Longyan Line where it is dry, and the headquarters organizes the construction units to grow plants anew where the grass has dried up to prevent new soil erosion. Sewage treatment facilities have been built for the stations and they can take

Beijing OASIS Enviroment Protection Technology Co.,Ltd. 16 Environment Monitoring Summary Report of Ganzhou-Longyan Railway sewage from station operation. Compensative measures for noise sensitive points had been implemented according to the EIA report. Large temporary projects, such as construction camps on the whole line, are mostly cleared according to requirements when the construction teams withdraw. Some have been handed over to the localities according to local governmental requests. Through environmental monitoring in construction period, construction units were supervised to control their constructive activity according to the requirement of environmental protection and strictly implement “three contemporary” system, which had effectively improved environmental protection work in construction period and implemented the mitigation measures in EIA report.

4 Survey of environmental protection measures in operational period

4.1 Ecological environment Ecological environmental impact survey of Ganzhou-Longyan railway include: side slope protection measures of subgrade; protection and recovery measures for borrow pit and waste disposal site; flooding and shore protection measures of bridges and culverts; station area afforestation measures and recovery measures of large-scale temporary projects.

4.1.1 side slope protection measures of subgrade Newly built subgrade of the railway is 185.5km, including embankment and cut. Embankment is the main engineering and totally 328 cuts with a total length of 38.5km. Generally, side slope of embankment is protected by grass, eg grass planting or grass planting with bush planting (picture 3 and 4); side slope of high embankment is protected by guard wall and arch-shaped framework with grass or tree planting; embankment near a river is protected by building gravity retaining wall on the pile foundation to maintain the shore, and slope is protected by dry laid stone fragments or grass; immerseable embankment is

Beijing OASIS Enviroment Protection Technology Co.,Ltd. 17 Environment Monitoring Summary Report of Ganzhou-Longyan Railway protected by dealing with the foundation firstly through stone squeezing, and slope is protected by dry laid stone fragments or dry laid stone fragments plus grass. Side slope of cut is protected by retaining wall with foundation, gravity retaining wall or wet shotcreting (picture 5). Field visit showed side slopes of subgrades had been generally well protected by engineering or plant measures. Surface of slope is stable and soil erosion is not happened.

4.1.2 borrow pit and waste disposal site Ganzhou-Longyan railway passes mountain areas and hilly lands of west Fujian province and east Jiangxi province. Tunnel, embankment, bridge and culvert, cut, station are main engineering of the project. Total earth and rock work is about 4397×104m3, including 2622×104m3 of fill, 1775×104m3 of cut excavation and

377×104m3 of tunnel excavation. Earth from borrow pit is totally 994×104m3.

Spoiled earth disposed in waste disposal site is 288×104m3. Wastes from tunnels are 228×104m3.

(1) borrow pit

There are 77 borrow pits, earth from which is totally 994×104m3. Field visit mainly investigated distribution, borrowed quantity, occupied area, restoration and protection situation of typical borrow pits. Results of the survey were listed in table 4-1. Table 4-1: Survey results of typical borrow pits Borrowed Area Original Restoration No. Name /Mileage quantity Remarks (mu) situation (104m3)

Hills with valleys, DK26+600 Plant grass 1 18 4 mainly farms, no Pic.6 borrow pit after flattened residents

DK77+200 A hilltop facing Plant grass 2 Niushui village 45 23 south with little Pic.7 after flattened borrow pit plants Forest area on Change into easy-gradient DK87+600 fishpond after 3 85.6 40 hillside; the Pic.8 borrow pit borrowing nearest distance to finished. a stream is 50m;

Beijing OASIS Enviroment Protection Technology Co.,Ltd. 18 Environment Monitoring Summary Report of Ganzhou-Longyan Railway

only one household nearby. Mountain area, a DK101+400 village at about Plant grass 4 11.3 4.5 Pic.9 borrow pit 300 m form the after flattened borrow pit. DK177+340 Small-sloped hill Plant grass 5 Nanshan village 37.1 22.9 side with terraced Pic.10 after flattened borrow pit field at left side. Hill side with Borrow pit at the dense plants at Plant grass 6 right side of 15.9 7.4 right side of the Pic.11 after flattened Xinquan station railway, no residents.

According to the field visit, excavations from some cuts were used as fills of embankments and cut-fill transition is balanced. Totally there were about 1479× 104m3 of excavations used as fills on the whole line. Typical excavations relocated as fills see picture12. cuts excavations were used to fill the Xiaochi Station. Locations of some borrow pits were combined with local plans. Flatted areas after borrowing were distributed to nearby villagers as household or development areas, eg. borrow pit against Shanghang Station, and borrow pit at front of Ruijin Station. Borrow pits along the line were generally adopted slope cutting, top flattening or refarming, etc. when earthwork finished, such as borrow pit at the right side of Xinquan Station, DK77+200 borrow pit, DK26+200 borrow pit, DK101+400 borrow pit, etc. Some of the borrow pits were rebuilt as fishpond, such as the DK87+600 borrow pit. (2) Waste disposal site There are 93 disposal site all together, including 42 earth discarding sites for 298 ×104m3 of cut spoils and 51 disposal sites for 228×104m3 of tunnel wastes. Survey results of the typical waste disposal sites see table 4-2.

Table 4-2 Survey results of typical waste disposal sites Disposed Area Original Restoration No. Name /Mileage quantity Remarks (mu) geomorphology situation (104m3) Spoil disposal site at Ravine with little Plant grass 1 DK73+000 for 25 11 plants, with no after retain wall Pic.13 Damadu Tunnel residence. built. exit Spoil disposal Ravine with some Plant grass 2 7 2.6 Pic.14 site for No.2 plants coverage, after retain wall

Beijing OASIS Enviroment Protection Technology Co.,Ltd. 19 Environment Monitoring Summary Report of Ganzhou-Longyan Railway

Shenkeng tunnel with no residence. built. exit Spoil disposal site Plant fruit trees at 3 15 5 Ravine after retain wall Pic.15 DK118+800 built. for Mingan Tunel Built into a Spoil disposal Ravine with some baboo matting 4 site at 4.2 1.3 plants coverage, Pic.16 factory after DK213+500 with no residence. flattened Spoil disposal Plant grass Ravine with good 5 site at 35.9 28.9 after retain wall Pic.17 plants coverage. DK246+100 built. Built into a Spoil disposal wood site for the Ravine with good 6 33.5 15.6 processing Pic.18 inclined shaft of plants coverage. plant after Jiaoyang tunnel flattened.

It was found during the monitoring that tunnel wastes were effectively utilized, waste quantity and land occupy were decreased. For example, wastes from DK191+200 Jinhua tunnel were used in the building of Longchang Highway. Spoils from the Gutian tunnel entrance were used by local people as building material. According to the field visit, waste disposal site was allocated mainly at hilly farm, undeveloped land, river beach, and occupied as little farm as possible. Waste disposing is generally according to the principle of “protect first, then dispose”. The sites were chosen in hilly area, waste valley or a small amount of low-productive fields, which are depressions and difficult to be eroded by surface flow. These sites were protected by retained wall and tops of the wastes were flattened and planted with grass or recultivated. For example, grass was planted on the top of the wastes from exit side of Shenkeng 2# tunnel; fruit trees were planted on the waste site of DK118+800. Because lack of land, some of the waste disposal sites were utilized after built. For example, DK213+500 waste disposal site had been built into a bamboo mat factory; waste disposal site of Jiaoyang tunnel had built into a timber mill. 4.1.3 Protection situation of bridges There are 156 newly built bridges along the line, include 10 super major bridges, 131 major and medium bridges and 15 minor bridges, with a total length of 35766 meters. There are 1200 culverts with a total transverse length of 35571

Beijing OASIS Enviroment Protection Technology Co.,Ltd. 20 Environment Monitoring Summary Report of Ganzhou-Longyan Railway meters. Because designing of the bridges and culverts is according to the principle of “no occupy of river channel” and “set culverts when meet with canals”, bridge/culvert ration of the line is relatively large, and its impact on surface water system is not obvious. A system of protection measure was adopted during the construction of bridges. For example, cofferdam was built when under-water pier constructed; mud from pile foundation was precipitated; excavation waste was temporarily protect; waste was cleared after work finished, etc. Field survey showed that construction of bridges has not made obvious impact on the environment of rivers and neighborhood. Survey showed quadrant revetments of abutments of the bridges were intact, and protection of riverbank was completed. For example, quadrant revetments of Diaozhongyan Super Major Bridge see picture 19 and that of Nanshan Major Bridge see picture 20. Cofferdams and wastes in the river had been cleared, and river channel had not been narrowed, see picture 21 of Liangfu 2# Major Bridge, cofferdam of which had been cleared. Spaces between piers had been recovered, see picture 22 of Jiangxia Super Major Bridge. 4.1.4 restoration of temporary projects Railway project has the character of lots of constructive sites, long line, large scale, long period, with many machinery as well as big work group in lining distribution. Temporary projects as lodging of workers, access roads, beam making sites, rail laying bases and sites for materials, etc. would occupy some land. Usually, these lands were rented, and compensated year by year according to the local policy, and restored after work finished. According to the survey, constructive camps of Ganzhou-Longyan Railway were mainly rented from local people. A small number of the camps located at rural mountain areas for tunnel and bridge construction were newly built. Most of the camps had been pulled off and the sites were recovered. Some relatively large and good camps were handed over to local government used as workshop. For example, the camp of Diaozhongyan super major bridge had been changed into a timber mill (picture 23). Beam making sites, rail laying bases and other constructive sites such as concrete mixing plants had been cleared. For example, rail laying base at Maodian Station had been recovered into constructive area of the station (picture 24). Most of the access roads had been handed over to local

Beijing OASIS Enviroment Protection Technology Co.,Ltd. 21 Environment Monitoring Summary Report of Ganzhou-Longyan Railway

villages used as country roads and are convenient for the local people (picture 25). 4.1.5 Survey of stations

There are many natural and cultural landscape along the line, which was fully considered during designing of the new stations, and made the stations into a new scenery of local area. The survey showed that stations had fine and distinctive styles, station areas were planted with arbors, brushes and grasses, which not only beautified environment, but also improved environmental quality of station area. Especially the designing of Changding Station (picture 26), which is like a park and has become into a place of entertainment for the people of Changding County. 4.1.6 summary

Constructive units of Ganzhou-Longyan Railway paid attention to ecological protection, and had conducted according to EIA requirements. Fund used in ecological restoration and protection is relatively big and had obtained good effect by adopting the ecological measures as biological measures, engineering measures or both. 4.2 Acoustic environment 4.2.1 EIA report and implementation of its official reply comments The survey showed that constructive units of Ganzhou-Longyan Railway had adopted related noise mitigation measures to the sensitive places according to the EIA report and its official reply comments by the State Environmental Protection Administration. Implementation of the measures see table 4-3.

Table 4-3: Implementation of the noise mitigation measures Name of Original Noise Actual the distance Noise No. Mileage mitigation implementati Remarks sensitive from the sources measure on site line(m) At the Liulidian right side Railway Moved to 1 Elementary 41 Move away Picture 27 of K1834 and road 500m away School +510 Dongxi DK34+7 Railway Moved to 2 Elementary 38 Move away Picture 28 70 and road 1000maway School Yudu Work Compensativ Compensative DK36+4 Railway 3 Technique 19 ely build ly build Picture 29 00 and road School dormitories dormitories far

Beijing OASIS Enviroment Protection Technology Co.,Ltd. 22 Environment Monitoring Summary Report of Ganzhou-Longyan Railway

far from 120m from 120m Shanfeng DK45+7 Moved to 4 Elementary 14 Railway Move away Picture 30 00 200m away School Shantang Separate with DK50+5 Moved to 5 Elementary 32 Railway trees, use Picture 31 00 300m away School long rail Yangwu DK55+8 Moved to 6 Elementary 68 Railway 00 500m away School Niushui DK77+9 Moved to 7 Elementary 19 Railway Move away Picture 32 00 500m away School Compensatio Change n fee has function, been paid, Meigang compensative DK92+6 new school 8 Middle 35 Railway ly build some Picture 33 00 building at School classrooms 500m away and has been domitories built. Shangxish Whole village DK142+ 9 anxia 30 Railway moved to Picture 34 600 Village 200m away Nanduan DK157+ Moved to4 10 Elementary 18 Railway Move away Picture 35 900 500m away School Chenguan DK167+ Moved to 11 Elementary 57 Railway 900 200m away School Compensatio Huangjiazh n fee has uang DK184+ been paid, 12 65 Railway Noise barrier Elementary 600 new school School site is selecting. Railway Liangfu change to DK207+ 13 Elementary 32 Railway Move away another way, 650 School the school is 500m away. East Had been side of dismissed and Titshany Yangmei joined into 14 Elementary 113 Railway Waiyang Locomot School Elementary ive School, 300m Returnin away. g Depot Because constructive units of Ganzhou-Longyan Railway had paid much attention to the noise problem, not only did they implemented all the mitigation measures in EIA report, but also adopted relocation and compensative measures to the new sensitive sites, which are seriously impacted by railway noise, such as Yangwu Elementary School, Shangxishanxia village and Chenguang

Beijing OASIS Enviroment Protection Technology Co.,Ltd. 23 Environment Monitoring Summary Report of Ganzhou-Longyan Railway

Elementary School, etc. 4.2.2 Impact analyze of railway noise during operational period

(1) Measurement of the noise Through field investigation, Jiangkou sanitarium, Guangming Elementary School, Xiashanxi Village 3 sensitive sites and typical embankments, bridges were chosen as the noise measurement sites (see figure 4-1~4-4). Noise at the railway border ( 30 meters away from the center of the outside track) was analyzed to determine if the noise met with the limit requirement of GB12525-90 Noise Limit at Railway Border and Its Measurement Method, and if the noise at hospitals and schools met with the requirement of 60dBA in daytime and .50dBA in nighttime, and judge the noise attenuation at typical sections along the line. z Measurement method GB12525-90 Noise Limit at Railway Border and Its Measurement Method TB/T3050-2002 Measurement techniqueNorm of Environmental Noise along railway

At present, because the train flow of this line is low and unbalanced, one hour measurement of noise is not suitable. So equal noise level of the trains was measured, and noise value was calculated respectively according to the train flow frequency of day and night. Train speed, measuring time, vehicle type and train formation were recorded simultaneously. z Calculation formula n ⎧ 1 ⎡ 1.0 Lpi ⎤⎫ TLeq = lg10)( ⎨ ⎢∑ti ×10 ⎥⎬ ⎩T ⎣ i=1 ⎦⎭ Meanings of the letters: Leq(T): equal noise level during T time (dBA);

th ti: noise functional time at the prediction point by the i noise source; th Lpi: A noise level created at the prediction point by the i noise source; T: time used to calculate equal noise level; n: noise source amount in T time. Day and night time was divided according to:

Beijing OASIS Enviroment Protection Technology Co.,Ltd. 24 Environment Monitoring Summary Report of Ganzhou-Longyan Railway

Day time: 6:00~22:00; Night time: 22:00~6:00. (3) Result analysis of the measurement See table 4-4. Table4-4: Noise measurement results Unit: dBA Name Mileage Distan Height Location Limit value Measured Conformance ce (m) differen value to the limit ce Day Night Day Night Day Night (m) Jiangkou Left of 1m outside sanitarium K1833 + 58 -5 bedroom 60 50 49.4 47.5 - - window 600 Guangmin DK137 + 1m outside Elementary 64 6 classroom 60 52.6 700 - School window Xiashanxi DK143 + 1m outside Village of the house 300 30 -4 70 70 55.0 51.8 30m away - - from the line Embankment At 30m away DK86 + 30 -3 60.4 57.8 sectional from the line 400 area At 60m away 60 -3 56.6 54.2 from the line At 120m 120 -3 away from 54.2 51.7 the line Bridge At 30m away DK105 + 30 -18 58.7 56.9 sectional from the line 200 area At 60m away 60 -18 56.9 55.2 from the line At 120m 120 -18 away from 53.9 52.1 the line Notice: Height difference means the height difference between rail surface and building ground assuming rail surface as benchmark.

Data in the table 4-4 shows Equal noise levels at the school and sanitarium along the line can generally meet with the requirement of “60dBA at daytime and 50dBA at nighttime”. Along the line, Equal noise levels at the railway border (30 meters away from the center of the outside track) and within the border can meet with the limit requirement of GB12525-90 Noise Limit at Railway Border and Its Measurement Method, namely “both 70dBA at daytime and nighttime”. Equal noise level at the sensitive points outside 60 meters away from the track is between 56.6 and 56.9dBA in daytime, between 54.2 and 55.2dBA in nighttime. Equal noise levels at the sensitive points outside 120 meters away from the track is 53.9 between 54.2dBA in daytime, between 51.7 and 52.1dBA in nighttime. Railway operation has little impact on the daily life of local people.

Beijing OASIS Enviroment Protection Technology Co.,Ltd. 25 Environment Monitoring Summary Report of Ganzhou-Longyan Railway

4.2.3 Summary

The survey showed constructive units of Ganzhou-Longyan Railway had implemented all the mitigation measures in EIA report and related official reply. Noise measuring at typical sensitive sites showed noise level of the both side along the line could generally meet with the requirement of related standard. 4.3 Water environment 4.3.1 Implementation of sewage treatment equipment at stations

Water pollution sources of the line during operational period are mainly from domestic sewage of the 6 newly built station and production sewage of Ruijin Locomotive Turnaround Depot. At present, constructive units of Ganzhou-Longyan Railway had implemented the mitigation measures in EIA report and related official reply. Because the later change of the design, track joint site was not located at Ganxian County Station, and Ganxian County Station was not included in the project. So the sewage treatment equipment of Ganxian County Station required in EIA report was canceled. Implementation of the measures was listed in table 4-5.

Table 4-5: Implementation of the sewage treatment measures Character Quantity Actual Treatment Direction of Organize of waste (m3/d) treatment Remarks technique in EIA discharge water measure Funds obligated, sewage Ganzhou Funds had discharge into City sewage passenge domestic 1500 been city sewage system r station prepared. system and treat together Integrated waste Yudu Gongjiang Domestic 13 water treatment Put into use Picture 36 station River equipment Integrated waste Xijiang Domestic 13 water treatment Put into use Xijiang River Picture 37 station equipment Ruijin Oil separation Discharge locomotiv Productive and into station e and 15 Put into use Picture 38 sedimentation treatment returning domestic tank plant station Integrated waste SBR Ruijin Jinjiang Domestic 21 water treatment techniue,put Picture 39 station River equipment into use Integrated waste Changdin Dingjiang Domestic 16 water treatment Put into use Picture 40 g station River equipment Guanzhis Domestic 35 Integrated waste SBR Pengkou Picture 41

Beijing OASIS Enviroment Protection Technology Co.,Ltd. 26 Environment Monitoring Summary Report of Ganzhou-Longyan Railway

Character Quantity Actual Treatment Direction of Organize of waste (m3/d) treatment Remarks technique in EIA discharge water measure han water treatment techniue,put River station equipment into use Integrated waste Shanghan Pingpu Domestic 15 water treatment Put into use Picture 42 g station stream equipment Other minor stations Domestic 4~5 Septic tank Put into use along the line Notice: technique of integrated waste water treatment equipment is as follows: Sewage Barrier Modulation pump well Reaction tank Sedimentation tank Discharge

According to the survey, sewage treatment equipments imposed in EIA and designing report had all been constructed, and fund used to joint sewage transportation tube with city sewage system had been in budget. Besides that, at the end of the designing period, large number of travelers for the famous traveling sites around Ruijin and Guanzhi station had been taken into consideration, and the original designed sewage treatment equipments in Ruijin and Guanzhi station had been changed into SBR treatment technique to improve the quality reliability of discharged water. 4.3.2 Quality measurement of station sewage In order to find out the quality of station sewage, sewage of Guanzhi and Shanghang station was measured in this survey. (1) Spot distribution for the measurement Sewage entrance and exit of sewage treatment plant at Guanzhi station; Exit of sewage treatment plant at Shanghang station. (2) Measuring indicators PH, BOD5, CODcr, SS, vegetable and animal oils for domestic sewage. (3) Sampling Frequency At the condition of normal operational situation, without rain or only small rain with no surface flow formed, continuously sampling for 3 days, respectively once at forenoon and t afternoon per day. (4) Analyzing method According to the analyzing method specified in GB8978-1996 Comprehensive Standard of Sewage Discharge.

Beijing OASIS Enviroment Protection Technology Co.,Ltd. 27 Environment Monitoring Summary Report of Ganzhou-Longyan Railway

(5) Results of the measurement

See table 4-6.

Table 4-6 Water quality measurement data at the entrance and exit of waste water treatment plant Unit: mg/l except for pH Items Vegetable pH CODcr BOD5 SS Location oil and fat Entrance 7.47 32.7 13.5 30 0.8 Guanzhishan Exit 7.47 26.4 10.4 10.2 <0.05 station Treatment 19.2 22.9 66.0 efficiency % Shanghang Exit 7.62 43 5.6 11 station Limits 6~9 100 30 70 20

The results showed quality of treated sewage met with the 1st class requirement of GB8978-1996 Comprehensive Standard of Sewage Discharge. 4.3.3 Summary Sewage treatment facilities of Ganzhou-Longyan Line had been constructed and put into use. According to the monitoring, quality of treated sewage met with the requirement of standard. It is suggested that the facilities should be maintained and managed in daily operation and quality of the sewage should be measured to ensure its discharge follow the standard requirement. 4.4 Air environment

According to the survey, all the boilers burning coals had changed into cleaning energy, such as solar energy or electric water heater, which is good for the improvement of air quality. Thermal used solar energy at Yudu station and Ruijin locomotive turnaround depot see photo 43 and 44. 4.5 Solid waste

Solid waste is mainly from passenger trains, domestic waste at station areas and mud created by sewage treatment equipments. According to field visit, regular waste delivery sites for passenger trains had been built up at Ganzhou and Longyan station. Wastes from passenger trains were collected to the waste transferring station, then transferred by local environmental unit to dispose together. Waste disposal Fee was paid by the

Beijing OASIS Enviroment Protection Technology Co.,Ltd. 28 Environment Monitoring Summary Report of Ganzhou-Longyan Railway station to local environmental unit. Waste storage site of Longyan station had been put into use and that of Ganzhou station had been exist. Other small stations along the line has relative small number of stuffs and waiting passengers, domestic waste quality is small, and are generally equipped with domestic waste box and special stuff for waste cleaning. Wastes are transported by local environmental unit and disposed collectively. Quality of mud from sewage treatment equipments is rather small, and mud are dried up and transported to local waste site and will not has obvious impact on environment. 4.6 Implementation of environmental management and monitoring system during operational period

According to the survey, Ganzhou-Longyan railway will be managed by Nanchang Railway Administration after being constructed. Nanchang Railway Administration has a special department responsible for environmental management work, and its subordinate stations and depots also have environmental units and related staffs. Environmental monitoring station of Nanchang Railway Administration is responsible for internal environmental monitoring works of the Administration. Manage department of the Administration can know the environment changes along the line through environmental monitoring datas. 5 Survey of impacts on local economy by the railway

5.1 Railway section in Jiangxi province Construction of Ganzhou-Longyan railway has greatly improved local economy. According to the GDP statistics of the 4 counties (cities) along the line in Jiangxi province, total GDP the 4 counties (cities) was 6.845 billion yuan in year 2001 vs 10.83 billion yuan in 2005, improvement of which is 58.3%; the improvement of local financial income is as high as 92.8%, the income reach 1.07 billion yuan in 2005. Relied on Ganzhou-Longyan railway, industrial structures of local areas along the line had been greatly adjusted; industrial and commercial business has been developed; construction of small cities was actively imposed; development of land resources and economy was improved. Construction of the railway had created much opportunity to local poor people and surplus labors in rural places to get rich and have a job. During the construction period, local people had actively joined in the construction and gotten a relatively good income. Some

Beijing OASIS Enviroment Protection Technology Co.,Ltd. 29 Environment Monitoring Summary Report of Ganzhou-Longyan Railway people would be accepted as a railway worker after the railway was operated, and get a stable income. Besides farming, local people can also engage in industry and commerce, and improve their income from many aspects. Construction of the railway has improved convenience of local transportation and improved environment of investment and resource superiority has changed into economic superiority. Main enterprises invested in the 4 counties (cities) along the line were Ganxian Shirui Mine Product Co. Limited, Ganzhou Xinye Art and Craft Co. Limited and Shenshi Costume (Ganzhou) Co. Limited, investment of which is 170 million yuan, and had solved employment problem for more than 5,000 persons. The counties along the line have grasped opportunity of the railway construction in resent years, have developed and built up industrial areas, a group of enterprises with good future have been built up, investments have been increased in machinery and electron, knitwear, mineral product processing, food processing and construction material industry. For example, limestone resources in Huichang and Ruijin are very rich. A major enterprise named Ruijin Brand Factory of Jiangxi Wannianqing Cement had been firstly invested 480 million yuan, productivity of which is 40 million ton of cement per year. A second investment will be 160 million yuan. This project can solve employment for 600 persons and the factory adopted spin-drier technique, which is conformed to the requirement of national industrial policy. According to the survey, this project has passed the procedure of EIA review. 5.2 Railway section in Fujian province Natural resources along the line is rich, operation of the railway will make the transportation along the line more convenient and absorb external commercial investment. At present, new enterprises enter the area have been more than 300, the biggest investment of which is more than 3 billion yuan and the biggest productivity of which is about 10 billion yuan per year. After the infrastructure of railway is gradually completed and industrial chain is formed, there will be more than 50 million tons commodities to be transported outside, include 20 million tons of cement, 10 million tons of coal and 9 million tons of new-typed construction material, 6 million tons of iron ore, 3 million tons of agriculture product, and large amount of machineries, etc. These products are mainly transported by Ganzhou-Longyan railway. Construction of the railway had improved the economy along the line. Mainly

Beijing OASIS Enviroment Protection Technology Co.,Ltd. 30 Environment Monitoring Summary Report of Ganzhou-Longyan Railway devoted in construction material of cement, projects like machinery and food processing, etc. will increase year by year with the operation of the railway. It is predicted that freight traffic volume will increase 9.1 million tons during the 11th five year. Natural and traveling resources in Yongding county is rich. National enterprise of cement Co. limited and Jinye Corporation located in the county can produce cement 3millon and 1.5million tons per yea respectively, and Haifeng Stone Material Processing Project Center can produce high quality Yongdinghong brand stone material 1.2million tons. Total freight increased by the above 3 enterprises is 5.7 million tons. If products as vegetables, livestock and fertilizers were added, freight increase will be 6.81 million tons per year for the county. Shanghang county is a famous place for its gold mine, identified mineral resources in the county have been more than 30 types such as gold, copper, silver, etc., identified deposits have been more than 100, which will increase freight 8.06million tons per year. All these products will be transported by Ganzhou-Longyan line. After the line has been operated, 6 enterprises have entered Shanghang county, total investment of which is more than 3.8billion yuan. If their productivity was full, productive value of them would be more than 10billion yuan per year. owns rich mineral resources such as coal, lime stone, swelling earth, manganese iron ore and CaCO3, etc. With the increasing of product and food processing projects setting up, it is predicted that freight will increase 7.85million tons per year during the 11th five year. Freight in Changding county is mainly from products of textile, machinery processing and agriculture. Besides that, rare earth ore there is the richest in Fujian province, which can provide 9million tons per year. After Ganzhou-Longyan line has been operated, industrial enterprises in Changding county have been developed fastly, and only in the 2 more resent years since 2003, number of industrial enterprises has increased to more than 280. Original scattered freights have been planned to transported by major or middle sized container because of freight increasing. According to prediction, there will be 1,747 standard containers enter railway-sea transportation system in Changding. Main products in Changdin include 0.6milliom tons of costume per year, 0.5million tons of textile per year, 1.5million tons of products per year from container producing enterprises, all of which will increase 2.66million tons of freight per year. Added with products of car accessories, agricultural vehicle and livestock farming, etc., freight of the

Beijing OASIS Enviroment Protection Technology Co.,Ltd. 31 Environment Monitoring Summary Report of Ganzhou-Longyan Railway whole county will increase 4.86million tons per year during the 11th five year. Traveling is the leading industry of Liancheng county, which owns rich traveling resources. Guanzhishan mountain, a 4A-leveled national major scenery, will absorb 2million person times in year 2010. Liancheng county also owns rich mineral resources, which will form a 3.964million tons of freight increase per year during the 11th five year as predicted. Operation of the railway will have a positive effect on the traveling resources along the line. Longyan owns the most scenery brands of Fujian province. Kejia travel represented by Yongding soil building, ecological travel represented by Guanzhishan mountain and Plum blossom mountain, etc. are some special traveling industry and are developing quickly. Present travelers is 5million person times per year, the number is getting higher year by year and will be reach 10million person times per year in 5years.

6 Summary

According to the survey, “three contemporary” requirement has been strictly implemented in Ganzhou-Longyan railway construction. Environmental protection measures proposed in EIA report and its official reply of SEPA have been implemented. Operation of the railway has improved local transportation condition, and has created a good chance for local economy development, and will exert a very important effect on local appeal to external investment and on traveling economy development as well.

Beijing OASIS Enviroment Protection Technology Co.,Ltd. 32