Status of Grid Connected Ground mounted Solar Power Projects Phase-IV:500MWs Solar Power Date of allotment: 22 .11.2014 Name of the Company Capacity Tariff Present project location Original Locations Commissioned Sl No Technology ESCOM PPA date (MWs) (`) Village Taluk District date Photon suryakiran Pvt Ltd varavu village, nayakanahatty hobli, challakere district under process 1 20 SPV 6.71 HESCOM 12.01.2015 Pavagada Tumkur (M/s. Today Green Power Pvt. Ltd.) M/s. Asian Fab Tec Limited Sira taluk, Tumkur dist under process 2 10 SPV 6.74 BESCOM 12.01.2015 Sira Tumkur Photon suryakiran Pvt Ltd varavu village, nayakanahatty hobli, challakere district under process 3 20 SPV 6.81 GESCOM 14.01.2015 Pavagada Tumkur (M/s. Today Green Power Pvt. Ltd.) Sun Edison Energy Holdings Nelagettanahatty village, Nayakanahatty hobli, Challakere, under process 4 30 SPV 6.83 HESCOM Challakere Chitradurga Singapore Pvt Ltd dist. Sun Edison Energy Holdings Nagalamadike village, pavagada taluk, tumkur dist. under process 5 30 SPV 6.86 BESCOM 18.12.2014 Challakere Chitradurga Singapore Pvt Ltd Azure Sunrise Power Limited Kandekere, gollahalli village, taluk, chitradurga and under process 6 (M/s. Azure Power Private 50 SPV 6.89 CESC 8.01.2015 kapparahalli, holikunte and jadekunte villages, challakere taluk, Rangenahalli Hiryur , Chitradurga Limited) chitradurga Sun Edison Energy Holdings Pallavalli, Pavagada, Tumkur dist under process 7 30 SPV 6.89 BESCOM 18.12.2014 Challakere Chitradurga Singapore Pvt Ltd Sun Edison Energy Holdings Nelagettanahatty village, Nayakanahatty hobli, Challakere, Chitradurga under process 8 30 SPV 6.92 BESCOM 18.12.2014 Challakere Chitradurga Singapore Pvt Ltd dist. Azure Power (Raj) Private golahalli, kandekere villages, hiriyur taluk, chitradurga dist and under process 9 LimitedM/s. Azure Power India 40 SPV 6.93 HESCOM 14.01.2015 kapparahalli village, challakere taluk, . Sanekeri Hiryur Chitradurga Private Limited M/s. Asian Fab Tec Limited Sira taluk, Tumkur district under process 10 5 SPV 6.94 CESC 12.01.2015 Sira Tumkur Photon suryakiran Pvt Ltd varavu village, nayakanahatty hobli, challakere district under process 11 10 SPV 6.95 HESCOM 12.01.2015 Pavagada Tumkur (M/s. Today Green Power Pvt. Ltd.) M/s. Azure Power India Private Kandekere village, hiriyur taluk, chitradurga and kapparahalli, under process 12 Limited 40 SPV 6.96 GESCOM 24.01.2015 jadekunte villages, challakere taluk, chitradurga PD Kote Dharampur Chitradurga

Sun Edison Energy Holdings Nagalamadike village, pavagada taluk, tumkur dist. under process 13 30 SPV 6.97 BESCOM 18.12.2014 Challakere Chitradurga Singapore Pte Ltd M/s. Welspun Renewables Energy SPV Kodihalli village, Darmpura hobli, Hiriyur taluk,Chitradurga Kodihalli village, Darmpura under process Chitradurga Pvt. Ltd. 34 hobli, Hiriyur taluk 14 50 7.01 BESCOM 14.01.2015 Rajapura village, molakalmuru taluk, Chitradurga Rajapura village, under process 16 Chitradurga molakalmuru taluk M/s. Bhoruka Power Corporation Kanajanahalli village, Hiriyur taluk, Chitradurga district under process 15 20 SPV 7.02 MESCOM 26.02.2015 Hiryur Chitradurga Limited Photon suryakiran Pvt Ltd varavu village, nayakanahatty hobli, challakere district under process 16 10 SPV 7.05 BESCOM 13.01.2015 Pavagada Tumkur (M/s. Today Green Power Pvt. Ltd.) M/s. Welspun Renewables Energy Bedareddyhalli, Thalak (Hobli) Challkere, Chitradurga District under process 17 50 SPV 7.09 BESCOM 14.01.2015 Kusthagi Koppal Pvt. Ltd. M/s. Kavit Industries Limited Hanumasagar village, Koppal district under process Mallapura, 18 5 SPV 7.1 GESCOM Challakere Chitradurga Nayakanahatti M/s. Surana Telecom and Power Kudrikotagi village, Yelaburga taluk, Koppal district under process 19 10 SPV 7.12 MESCOM 12.02.2015 Tingloor Madhugir Tumkur Limited Photon suryakiran Pvt Ltd varavu village, nayakanahatty hobli, challakere district under process 20 10 SPV 7.12 MESCOM 5.02.2015 Pavagada Tumkur (M/s. Today Green Power Pvt. Ltd.) Total 500