Form – I for Residential Building Complex Real Estates Private Limited

FORM – I

(I) Basic Information S.No. Item Details Residential Development Project by M/s. 1. Name of the project Perungudi Real Estates Private Limited 2. S.No. in the schedule 8 (a) Construction Area Details: Total Plot Area – 21,388 Sq.m (As per Proposed capacity/area/length/tonnage to document) & 21,400 Sq.m (As per patta) 3. be handled command area/lease Total Built up area–86,000 Sq.m area/number of wells to be drilled Please refer to the Master Plan Layout (Site Plan) attached herewith as Annexure-I. 4. New/Expansion/Modernization New 5. Existing Capacity/Area etc. Not Applicable 6. Category of Project i.e., ‘A’ or ‘B’ “B” Category Does it attract the general condition? If 7. No yes, please specify Does it attract the specific condition? If 8. No yes, please specify Plot/Survey/Khasra No. S. No. 134/4A1, & 134/5A Village 9. Tehsil District Kanchipuram State Tamilnadu Taramani Suburban Railway Station–2.0 Km aerial distance in Northern direction. Nearest railway station/airport along with Central Railway Station – 14.2 Km 10. distance in kms. aerial distance in NE direction. Chennai Airport – 8.7 Km aerial distance in NW direction. Nearest Town, city, District Headquarters Palavakkam Village, , 11. along with distance in kms. Village Panchayats, Zilla Parishad, Municipal Corporation, Local body 12. Greater Chennai Corporation (complete postal addresses with telephone nos. to be given) 13. Name of the applicant Perungudi Real Estates Private Limited. Perungudi Real Estates Private Limited, No. 110, (Old SRP Tools), 14. Registered Address , OMR Road, , Chennai-600041

Eco Services India Pvt. Ltd. Page_ 9

Form – I for Residential Building Complex Perungudi Real Estates Private Limited

Address for correspondence: Name Mr. K. S. Gnanaseelan Designation (Owner/Partner/CEO) Authorized Signatory Perungudi Real Estates Private Limited, 15. No. 110, (Old SRP Tools), Address Rajiv Gandhi Salai, OMR Road, Thiruvanmiyur, Chennai-600041 Pin Code 600 0 41 Details of Alternative Sites examined, if 16. any. Location of these sites should be No shown on a topo sheet. 17. Interlinked Projects No Interlinked Projects Whether separate application of 18. No interlinked project has been submitted? 19. If yes, date of submission - 20. If no, reason - Whether the proposal involves approval/clearance under: if yes, details of the same and their status to be given. 21. No (a) The forest (conservation) Act, 1980? (b) The wild life (Protection) Act, 1972? (c) The CRZ Notification 1991 Whether there is any Government 22. No Order/Policy relevant/relating to the site? 23. Forest land involved (hectares) No Whether there is any litigation pending against the project and/or land in which the project is propose to be set up? 24. Name of the Court No Case No. Orders/directions of the Court, if any and its relevance with the proposed project.

(II) Activity Construction, operation or decommissioning of the Project involving actions, which will cause physical changes in the locality (topography, land use, changes in water bodies, etc.) Details thereof (with approximate Information/Checklist S.No. Yes/No quantities /rates, wherever possible) with confirmation source of information data Permanent or temporary change The project site consists of temporary steel 1.1 in land use, land cover or Yes structures and commercial building which topography including increase in has been already demolished and the

Eco Services India Pvt. Ltd. Page_ 10

Form – I for Residential Building Complex Perungudi Real Estates Private Limited

intensity of land use (with respect proposed project is Residential to local land use plan) Development. The proposed development complies with the land use classification of the Chennai Metropolitan Development Authority (CMDA). Copy of the land use certificate obtained from CMDA is enclosed as Annexure-II The existing land is devoid of trees. Clearance of existing land, 1.2 No Clearance of ground shrubs will be carried vegetation and buildings? out. The project site consists of temporary steel structures and commercial building which 1.3 Creation of new land uses? Yes has been demolished and the proposed project is residential development. Geo -Technical Investigation has been Pre-construction investigations 1.4 Yes carried out and the copy of report is e.g. bore holes, soil testing? enclosed as Annexure – III. The proposed residential building complex project consist of  Tower A1 (2B + Stilt (Ground) Floor + Twenty Eight Floors + Terrace Floor),  Tower A2 (2B + Stilt (Ground) Floor + Twenty Eight Floors + Terrace Floor),  Tower A3 – LIG Block (2B + Stilt 1.5 Construction works? Yes (Ground) Floor + Thirteen Floors + Terrace Floor) comprising of 424 dwelling units and  Club House with swimming pool (2B + Stilt (Ground) Floor + Two Floors +Service Floor + Terrace Floor) with a total built up area of 86,000 Sq.m in a land area of 21,400 Sq.m. The steel structures were carefully 1.6 Demolition works? Yes dismantled, which was handed over to authorized scrap dealers. No labour camps are proposed, since local Temporary sites used for laborers from nearby areas would be hired 1.7 construction works or housing of No for the work. Adequate drinking water and construction workers? sanitation facilities will be provided for them at the project site. Above ground buildings, The proposed residential building complex 1.8 structures or earthworks including Yes project consist of linear structures, cut and fill or  Tower A1 (2B + Stilt (Ground) Floor +

Eco Services India Pvt. Ltd. Page_ 11

Form – I for Residential Building Complex Perungudi Real Estates Private Limited

excavations Twenty Eight Floors + Terrace Floor),  Tower A2 (2B + Stilt (Ground) Floor + Twenty Eight Floors + Terrace Floor),  Tower A3 – LIG Block (2B + Stilt (Ground) Floor + Thirteen Floors + Terrace Floor) comprising of 424 dwelling units and  Club House with swimming pool (2B + Stilt (Ground) Floor + Two Floors +Service Floor + Terrace Floor) with a total built up area of 86,000 Sq.m in a land area of 21,400 Sq.m. The proposed residential building complex Underground works including 1.9 Yes involves two levels of basement mining or tunneling? construction. 1.10 Reclamation works? No - 1.11 Dredging? No - - 1.12 Offshore structures? No

Production and manufacturing 1.13 No - processes? Construction material storage/handling yard will be located within the project site and separated by enclosures/barricades. Cement Facilities for storage of goods or 1.14 Yes will be stored under cover in bales. Sand materials? will be stacked under tarpaulin cover. Bricks/blocks and steel will be laid in the open. Solid Waste: Wastes generated in the project site during construction (debris) would be used for backfilling and leveling within the site. Solid waste during operation phase would be collected and segregated. The biodegradable wastes will be collected and composted in-situ through Organic Waste Facilities for treatment or disposal 1.15 Yes Converter (OWC). Non-biodegradable of solid Waste or liquid effluents? waste shall be segregated according to its characteristics & handed over to respective authorized recyclers for disposal . Liquid Effluent: During the construction phase, sewage from temporary toilets would be disposed through septic tanks with soak pits. During the operation phase, the sewage

Eco Services India Pvt. Ltd. Page_ 12

Form – I for Residential Building Complex Perungudi Real Estates Private Limited

generated will be treated in scientifically designed Sewage Treatment Plants and reused within the premises. Please refer to Sections 4.0 & 5.0 of the Conceptual Plan / Environmental Management Plan enclosed herewith for details. Facilities for long term housing of No facilities for long-term housing of 1.16 No operational workers? operational workers are proposed. New road, rail or sea traffic during 1.17 No Existing road infrastructure will be used. construction or operation? New road, rail, air waterborne or other transport infrastructure 1.18 No Not Applicable including new or altered routes and stations, ports, airports etc? Closure or diversion of existing transport routes or infrastructure 1.19 No Not Applicable leading to changes in traffic movements? Power Supply from TANGEDCO & Water New or diverted transmission 1.20 No Supply connection from CMWSSB piped lines or pipelines? supply shall be obtained prior to occupancy Impoundment, damming, culverting, realignment or other 1.21 No Not Applicable changes to the hydrology of watercourses or aquifers? 1.22 Stream crossings? No Not Applicable It is proposed to utilize the piped water Abstraction or transfers of water supply available in the project area which is 1.23 No from ground or surface waters? provided by the Water Supply and Sewerage Board (CMWSSB). Changes in water bodies or the 1.24 land surface affecting drainage or No Not Applicable run-off? Transport of personnel or There would be a movement of men and 1.25 materials for construction, Yes materials during construction & operational operation or decommissioning? phases. Long-term dismantling or 1.26 decommissioning or restoration No - works? Ongoing activity during 1.27 decommissioning which could No - have an impact on the

Eco Services India Pvt. Ltd. Page_ 13

Form – I for Residential Building Complex Perungudi Real Estates Private Limited

environment? 1.28 Influx of people to an area in There will be a daily movement of people either temporarily or Yes during the operation phase as the proposed permanently? development is a residential building. 1.29 Introduction of alien species? No - The existing land is devoid of trees. Only Loss of native species or genetic 1.30 No ground shrubs exists which will be cleared diversity? during construction. 1.31 Any other actions? No -

2. Use of Natural resources for construction or operation of the Project (such as land, water, materials or energy, especially any resources which are non-renewable or in short supply): Details thereof (with approximate quantities Information/Checklist S.No. Yes/No /rates, wherever possible) with source of confirmation information data Land especially undeveloped or The proposed site does not have any 2.1 No agricultural land (ha) agricultural or undeveloped land. It is estimated that about 30-50 KLD of water is required during peak construction period. The daily fresh water requirement Water (expected source & during operation phase is 193 KLD and this 2.2 Yes competing users) unit: KLD would be sourced from CMWSSB’s piped water supply system prevailing in the area. Please refer to Section 4.0 of the EIA report enclosed herewith for details. 2.3 Minerals (MT) No - Construction materials will be sourced from Construction material – stone, the local market. Materials with good post- 2.4 aggregates, sand / soil (expected Yes industrial recycle content like aerocon source – MT) blocks (Fly ash), steel etc. are proposed to be used in the project. It is also planned to use plywoods with good 2.5 Forests and timber (source – MT) Yes recycled content. Power requirement during construction phase will be sourced from TNEB through a Energy including electricity and temporary connection and backed by 2-3 2.6 fuels (source, competing users) Yes nos. of DG sets by the civil works Unit: fuel (MT), energy (MW) contractor. The power requirement during the operational phase of the building is about 4,000 KVA and will be sourced from the

Eco Services India Pvt. Ltd. Page_ 14

Form – I for Residential Building Complex Perungudi Real Estates Private Limited

nearby TNEB grid. For power back-up during the failure of supply from TNEB grid, it is proposed to install 3 nos. of 500 kVA capacity DG sets. Low sulphur content HSD will be used as fuel for DG sets. Any other natural resources (use 2.7 No - appropriate standard units)

3. Use, storage, transport, handling or production of substances or materials, which could be harmful to human health or the environment or raise concerns about actual or perceived risks to human health. Details thereof (with approximate quantities Information/Checklist S.No. Yes/No /rates, wherever possible) with source of confirmation information data No storage and handling of hazardous Use of substances or materials, chemicals (as per MSIHC) will be done which are hazardous (as per apart from use of diesel in DG sets. Fuel 3.1 MSIHC rules) to human health No used for the DG Sets will be of Low Sulphur or the environment (flora, fauna, High Speed Diesel (Sulphur content< and water supplies) 0.005%). Suitable drainage and waste management Changes in occurrence of disease measures will be adopted to prevent 3.2 or affect disease vectors (e.g. No stagnation of water and restrict accumulation insect or water borne diseases) of waste. This will effectively restrict the reproduction and growth of disease vectors. The standard of living of the nearby locals will improve due to the employment opportunities created by the proposed Residential Development. On completion of the project, it will improve not only the infrastructure facility but will also improve Affect the welfare of people e.g. 3.3 Yes the aesthetic looks of the surroundings. by changing living conditions? Socio economic conditions of nearby areas will improve due to local employment (direct and in direct) Moreover, this project will provide employment to local laborers during the construction and operational phases. Vulnerable groups of people who could be affected by the 3.4 No Not Applicable project e.g. hospital patients, children, the elderly etc.,

Eco Services India Pvt. Ltd. Page_ 15

Form – I for Residential Building Complex Perungudi Real Estates Private Limited

3.5 Any other causes No Not Applicable

4. Production of solid wastes during construction or operation or decommissioning (MT/month) Details thereof (with approximate quantities Information/Checklist S.No. Yes/No /rates, wherever possible) with source of confirmation information data The excavated earth and construction debris Spoil, overburden or mine 4.1 Yes will be used for backfilling and level rising wastes within the project site. Please refer 5.0 of the Conceptual Plan / Municipal waste (domestic and Yes Environmental Management Plan enclosed 4.2 or commercial wastes) herewith for details. The spent oil (approx. 300 Kg/annum) will be stored in HDPE drums in isolated covered Hazardous wastes (as per facility with impervious flooring. This will be 4.3 Hazardous Waste Yes sold to TNPCB authorized recyclers for safe Management Rules). disposal in compliance with Hazardous and Other Wastes (Management and Trans- boundary Movement) Rules, 2016. 4.4 Other industrial process wastes. No -

4.5 Surplus product No -

Sewage sludge or other sludge STP sludge will be dried and used as the 4.6 Yes from effluent treatment manure for the gardening. The excavated earth and construction debris Construction or demolition 4.7 Yes will be used for backfilling and level rising wastes within the project site. All machinery / equipment will be installed as Redundant machinery or per the requirement during construction and 4.8 No equipment would be removed by the contractors once the construction work has been completed. Contaminated soils or other No 4.9 Not Applicable materials 4.10 Agricultural wastes No Not Applicable

4.11 Other solid wastes No Not Applicable

Eco Services India Pvt. Ltd. Page_ 16

Form – I for Residential Building Complex Perungudi Real Estates Private Limited

5. Release of pollutants or any hazardous, toxic or noxious substances to air (Kg/hr) Details thereof (with approximate quantities Information/Checklist S.No. Yes/No /rates, wherever possible) with source of confirmation information data

Pollutants like particulate matters CO, SO 2 and NOx will be released into the atmosphere due to the operation of DG sets and other machineries of construction which use fossil Emissions from combustion of fuels. However the DG sets is operated only 5.1 fossil fuels from stationary or Yes during power cuts. Also the use of Low mobile sources Sulphur HSD (Sulphur content< 0.05%) and dispersion of the DG flue gases through stacks having heights as per CPCB norms will minimize the impacts. Emissions from production 5.2 No - processes There will not be major emission from material Emissions from materials handling, storage and transport. Necessary 5.3 handling including storage or Yes steps will be taken to control vehicular transport emissions. Emissions from construction activities will be reduced by using low sulphur content HSD for Emissions from construction the machineries operated with fossil fuels and 5.4 activities including plant and Yes the accumulation of particulate matter in the equipment. atmosphere will be suppressed by sprinkling of water in the dust prone areas at regular intervals. Dust or odours from handling of Dust at construction site will be suppressed by 5.5 materials including construction Yes sprinkling water at site. On-site sanitation materials, sewage and waste facilities will be provided. Emissions from incineration of 5.6 No - waste Emissions from burning of 5.7 waste in open air (e.g. slash No - materials, construction debris) Emissions from any other 5.8 No - sources

Eco Services India Pvt. Ltd. Page_ 17

Form – I for Residential Building Complex Perungudi Real Estates Private Limited

6. Generation of Noise and Vibration, and Emissions of Light and Heat: Details thereof (with approximate quantities Information/Checklist S.No. Yes/No /rates, wherever possible) with source of confirmation information data Noise control systems such as equipment From operation of equipment 6.1 foundation pads, dampers, silencers and e.g.engines, ventilation plant, Yes acoustic enclosures will be used for individual crushers units to minimize the noise & vibration. From industrial or similar 6.2 No - processes There will be no construction activity during night hours. Noise during the construction 6.3 From construction or demolition Yes activities will be kept minimum by proper and regular maintenance of construction machineries. No blasting is involved. Driven piles are 6.4 From blasting or piling No proposed and hence will not have significant impact of noise and vibration. During construction activities, care will be taken as explained above to reduce the impacts From construction or operational 6.5 Yes due to movement of heavy vehicles, while traffic operational traffic will not contribute much towards noise. Necessary care would be taken at the time of From lighting or cooling selection of equipment to minimize the noise or 6.6 Yes systems heat. Proper preventive maintenance will be adopted during the operation stage. 6.7 From any other sources No -

7. Risks of contamination of land or water from releases of pollutants into the ground or into sewers, surface waters, groundwater, coastal waters or the sea: Details thereof (with approximate quantities Information/Checklist S.No. Yes/No /rates, wherever possible) with source of confirmation information data No hazardous materials are used during the construction phase. During the operation From handling, storage, use or 7.1 No phase, the used oil generated from DG sets spillage of hazardous materials will be stored in drums and will be disposed to CPCB/ TNPCB authorized waste oil recyclers. From discharge of sewage or Please refer Section 4.0 of the Conceptual Plan 7.2 other effluents to water or the Yes / Environmental Management Plan enclosed land (expected mode and place herewith for details.

Eco Services India Pvt. Ltd. Page_ 18

Form – I for Residential Building Complex Perungudi Real Estates Private Limited

of discharge) By deposition of pollutants 7.3 emitted to air into the land or No Nil into water 7.4 From any other sources No - Is there a risk of long term build 7.5 up of pollutants in the No - environment from these sources?

8. Risk of accidents during construction or operation of the project, which could affect human health or the environment

Details thereof (with approximate quantities Information/Checklist S.No. Yes/No /rates, wherever possible) with source of confirmation information data

The proposed project activity does not impose any significant threat of explosions, spillages, From explosions, spillages, fires fires etc. During construction, all the labors etc from storage, handling, use will be provided with personal protective 8.1 No or production of hazardous equipment (PPE). Training and awareness substances about the safety norms will be provided to all supervisors and labors involved in construction activity. 8.2 From any other causes No - Could the project be affected by The project area falls in Zone - III of Seismic natural disasters causing Zoning map of India. The seismic factors have 8.3 environmental damage (e.g. No been appropriately incorporated in the civil floods, earthquakes, landslides, designs for the proposed project. cloudburst etc)?

9. Factors which should be considered (such as consequential development) which could lead to environmental effects or the potential for cumulative impacts with other existing or planned activities in the locality Details thereof (with approximate quantities Information/Checklist S.No. Yes/No /rates, wherever possible) with source of confirmation information data Lead to development of supporting facilities, ancillary The project is located in a well-developed area development or development and may not trigger the development of 9.1 No stimulated by the project which supporting and ancillary facilities and other could have impact on the developments. environment e.g.:

Eco Services India Pvt. Ltd. Page_ 19

Form – I for Residential Building Complex Perungudi Real Estates Private Limited

• Supporting infrastructure (roads, power supply, waste or waste water treatment, etc.) • Housing development • Extractive industries • Supply industries • Other Lead to after-use of the site, 9.2 which could have an impact on No Not Applicable the environment Set a precedent for later 9.3 No Not Applicable developments Have cumulative effects due to proximity to other existing or 9.4 No Not Applicable planned projects with similar effects

(III) Environmental Sensitivity

Name/ S.No. Areas Aerial distance (within 15 km) of Proposed Identity project location boundary Areas protected under international conventions, 1 national or local legislation for No Not Applicable their ecological, landscape, cultural or other related value Areas which are important or sensitive for ecological reasons - Wetland lies at an aerial distance 2 Wetlands, watercourses or other Yes of 1.9 Km in the SW direction. water bodies, coastal zone, biospheres, mountains, forests Areas used by protected, important or sensitive species 3 of flora or fauna for breeding, No - nesting, foraging, resting, over wintering, migration Inland, coastal, marine or lies at an aerial distance 4 Yes underground waters of 1.9 Km in the SW direction. 5 State, National boundaries No -

Eco Services India Pvt. Ltd. Page_ 20

Form – I for Residential Building Complex Perungudi Real Estates Private Limited

Rajiv Gandhi Salai also known as Old Mahabalipuram Road (OMR) is a major road beginning at Adyar and continuing till Routes or facilities used by the Mahabalipuram in Kancheepuram District, 6 public for access to recreation or Yes which finally merges with other tourist, pilgrim areas (ECR). Mahabalipuram is famous for its beaches , sculptures, the famous Shore Temple, Varaha Cave temple, light house among other visual treats . 7 Defence installations No - Densely populated or built-up The project site is located within the densely 8 Yes area populated area of Sholinganallur Village. The project site is surrounded by sensitive man-made land uses like hospitals, schools, places of worship and community facilities etc. Areas occupied by sensitive Temples include Vinayakar Temple, Angala man-made land uses Parameshwari Temple, Schools include 9 Yes (hospitals, schools, places of Government High School, Abacus Montessori worship, community facilities) School & Hospitals include Government Primary Health Center, Apollo Specialty Hospital etc., among other residential and commercial establishments. Areas containing important, high quality or scarce resources (Ground water resources, Pallikaranai Wetland lies at an aerial distance 10 Yes surface resources, forestry, of 1.9 Km in the SW direction. agriculture, fisheries, tourism, minerals) Areas already subjected to pollution or environmental Ambient Air and Ground Water quality in 11 damage. (Those where existing Yes some areas of Chennai City exceeds the legal environmental standards existing legal environmental standards. are exceeded) Areas susceptible to natural hazard which could cause the project to present environmental problems 12 No - (Earthquakes, subsidence, landslides, erosion, floodingor extreme or adverse climatic conditions )

Eco Services India Pvt. Ltd. Page_ 21

Form – I for Residential Building Complex Perungudi Real Estates Private Limited

“I hereby given undertaking that the data and the information given in the application and enclosures are true to the best of my knowledge and belief and I am aware that if any part of the data and information submitted is found to be false or misleading at any stage, the project will be rejected and clearance given, if any, to the project will be revoked at our risk and cost.”

Date: Place: Chennai K. S. Gnanaseelan Authorized Signatory

Eco Services India Pvt. Ltd. Page_ 22