Optimizing Prefabrication Jessica Kelley with Lean Who is Southland?
Southland Industries is one of the US's largest MEP building systems experts. Taking a holistic approach to building performance, we specialize in the design, construction, and operation of mechanical, electrical, plumbing, fire protection, process piping, automation and controls systems, as well as comprehensive energy services.
Southland Industries ©2019 All rights reserved.
Capabilities
DESIGN-BUILD SERVICES TRADES • HVAC • Pipefitting • Process piping • Sheet metal • Plumbing • Plumbing • Fire protection • Sprinkler-fitting • Controls and automation • Energy • Electrical Markets Served
Healthcare Mission Critical Biotechnologies Sports/Entertainment
Industrial/Manufacturing Commercial Education Government
Southland Industries ©2019 All rights reserved. Why Prefabrication?
Safety Quality Productivity Labor Shifting
Laydown space Schedule Cost
Southland Industries ©2019 All rights reserved. Culture Shift
Southland Industries ©2019 All rights reserved. Project Type and Environment Matter
• New vs Renovation • Tight Timelines • Lack of Repetition • Wrong Team • Wrong Owner • Distance from Shop • Site Access Project Delivery Method Matters
Southland Industries ©2019 All rights reserved.
Southland Workflow Ideas Come From Anywhere
Fab Shop Crew Engineer
Detailer Field Crew
Group Planning Meetings Project Manager
Leveraging BIM
1 9 BIM… not a guarantee: Understand your Tolerances
20” gap between segments RECEIVING LOGISTICS FABRICATION SHEETMETAL PLUMBING ASSEMBLY PIPING PIPING ASSEMBLY ASSEMBLY SM DESIGN TEAM STAGING TOOLS
SHIPPING Offsite Prefab Facilities Too Many Carts Universal Cart
Universal Cart Closed Cage Conversion Material Handling Options
Transport Safety Stackable for Shipping/Storage Planning: Last Planner® informs Project Schedule
• Who develops the Design Schedule? • Who develops the Construction Schedule? • Are they aligned?
Planning: Pull Schedule (Internal)
Hanger Fabrication and Delivery
OLD NEW
Eliminate the Risk
Southland Industries ©2019 All rights reserved. Recordable Incident Rate .63
Ex Mod Rate .46
Southland Industries ©2019 All rights reserved. What does Integrated Project Delivery enable? Healthcare
Van Ness & Geary Hospital
San Francisco, CA
Engineering and Construction
Southland Industries ©2019 All rights reserved. Sheetmetal 15% Detailing Increase
25% Labor Reduction
Southland Industries ©2019 All rights reserved. Plumbing
• 15 Jigs for Lavatory and Shower Assemblies • 75% increase in detailing labor • 14% overall labor savings Manufacturing
Procter & Gamble
West Virginia
Engineering, Construction
Southland Industries ©2019 All rights reserved. Highly Restricted
Innovation Preassembled Ductwork (AHU-204) Description The supply and return ductwork for AHU-204 was designed to be installed between roof joists and steel grid. The ductwork was fabricated and preassembled in (3) large sections and installed with the structural contractor’s crane. Rather than installing the duct run in 5’ pieces, this allowed 110’ run to be installed ahead of the construction schedule saving time and production costs. Safety/Risk The duct runs were installed in larger sections, thus limiting the amount overhead work. impact Quality impact: The larger sections allowed for the QC team to inspect the ductwork fully on the ground rather than inspecting only visible sections in the air. Schedule impact: Allowed this work to be installed in advance of the building construction.
Cost impact: Allowed Southland to install 60% of the ductwork utilizing only 40% of the labor for a savings of 20% of labor costs. Piping Racks Improved Piping Racks
Multi-Disciplinary Savings: Struct: $200K of $400K saved Mech: $250K of $1.8M saved Safety: 7,800 hours moved to shop Schedule: 3 of 40 weeks saved Healthcare
Penn Medicine
Philadelphia, PA
Engineering, Construction
Southland Industries ©2019 All rights reserved. Site Logistics
• Curb-to-curb construction • Active medical campus • Limited laydown area • Heavy traffic and limited parking Prefabrication Maps
Conceptualize prefabricated elements before design is completed.
Mechanical layout supports prefabrication on day 1
Effective communication tool to show architectural team construction constraints
Visual guide to % of off site manufacturing (OSM)
Southland Industries ©2019 All rights reserved. 46 Multi-Trade Pipe Racks Wall Assemblies Bathroom Pods
Coordination of Pod Types
Project Award ~2015 Struct/Arch Coordination Clinical Mockup
Prototypes A3’ G 2016 Functionality Mockup Constructability Mockup Fabrication
Southland Industries ©2019 All rights reserved. 49 From Shop to Field
• 1 Finish Schemes • 504 Pods • 2 Layouts • 10% reduced onsite labor, projected • 7 Plumbing Variations • 10 less deliveries, weekly Penn Medicine Metrics - Piping
Total Pipe Length [Miles]
35 Miles of Piping Patient Floors (L7-L14)
10 %
10,5; 30 % Prefab Pipe 20 % Bathroom Pod Piping Onsite 70 % 25; 70 %
Excludes 3 pipe Med Gas racks
Prefab Pipe Onsite Interventional/OR (L4-L6) Penn Medicine Metrics - Sheetmetal
Total Project Sheetmetal [Tons] OSM 46 % 1100 tons (2.2 Million lbs) of Sheetmetal Onsite 54 %
220; 20 %
50; 5 % Patient Floors (L7-L14) 830; 75 %
OSM 49 % Onsite 51 %
Fitout Duct C&S Headers Onsite Labor Shift Peak Manpower (Traditional): 1,200 Peak Manpower (w/ Prefabrication): 1000
Southland Industries ©2019 All rights reserved. Sharing Strategies REVIT UNIFI Prefab Playbook Prefab Strategy Meeting Prefab Playbook
5 8 Metrics
• Month over Month Trend • By Division • By Market • Project Specific
Southland Industries ©2019 All rights reserved. We know the best value is delivered for our customers when we connect all of our services in an integrated design- build-operate process.
I ’ h lifecycle and our connections to our ’ h y differentiate us. Questions Jessica Kelley, PE [email protected] www.southlandind.com