Pre-Bid Queries for NIT for Installation of 13179 Nos. of 300Wp Solar Home Power Packs and 4184 Nos. of 40Wp Solar Street Lights including 5 years’ Comprehensive Maintenance for Electrification of 895 Nos. of Off-Grid Villages in under Deen Dayal Upadhyaya Gram Jyoti Yojana (DDUGJY) including Supply of LED Bulbs, BLDC Fans, Poles, Sign Boards & other material etc. NIT No: RECPDCL/ANP/DDG/16-17/3740 Dated: 23.02.2017

Page No. / S. No. Parameter Technical Specifications as per RFP Queries / Modifications / Changes Suggested Amendments / Clarifications / Remarks Clause No.

Comprehensive warranty - For NIT 2 Bidders whoever supply the material will be responsible for guarantee / warranty for (installation work) - Here the entire project period. comprehensive warranty will include what The Execution Agency will maintain critical spares at site/Service Centers and - As per NIT 2 the major work is coordinate with Supply Agencies for other spares. Execution Agency will be responsible 1- - - installation and supply of pole and few for comprehensive maintenance. small items. How can installer take warranty of the material supplied by the other party. Authorized person of the JV/consortium Lead Member’ shall be authorized shall be authorized on behalf of on behalf of Consortium/Joint Consortium/Joint Venture Firm to deal Venture Firm to deal with the with the tender/RECPDCL, sign the General tender/RECPDCL, sign the agreement or enter into contract in condition for agreement or enter into contract in respect of the said tender, JV has to consortium respect of the said tender, to open a JV account to receive payment 2 /joint venture - receive payment and such activities and such activities in respect of the said No change firms point 6 in respect of the said tender/ tender/ contract. All notices/ (page no-23) contract. All notices/ correspondences with respect to the correspondences with respect to contract would be sent only to address of the contract would be sent only to the Consortium/Joint Venture Firm. this ‘Lead Member’ of Consortium/Joint Venture Firm.

All formalities in respect of All formalities in respect of submission of submission of tender shall be done General tender shall be done in the name of only in the name of ‘Lead Member’ condition for Consortium/Joint Venture. and not in the name of consortium Authorized person having legal power of Consortium/Joint Venture Firm. 3 /joint venture - attorney from the JV has to make all No change However, name & other details of firms point 2 formalities. However, name & other both the members of Consortium/ (page no-23) details of both themembers of Joint Venture Firm should be Consortium/ Joint Venture Firm should be clearly mentioned in the clearly mentioned in the Bid/Response. Bid/Response.

General Required EMD shall be submitted condition for either by the ‘Lead Member’ or by consortium Required EMD shall be submitted either the ‘Joint Venture/Consortium 4 /joint venture - by the ‘Lead Member’ or “Consortium No change Firm’ itself. EMD submitted by firms point 7 ( Partner”. Consortium Partner shall not be page no-23) considered. Notice Inviting Tender (Bid Invited through e-Tendering mode only) for Installation of 13179 Nos. of 300Wp Solar Home Power Packs and 4184 Nos. of 40Wp Solar Notice Inviting Tender (Bid Invited through e-Tendering mode only) for Installation & Street Lights including 5 years’ Commissioning of 13179 Nos. of 300Wp Solar Home Power Packs and 4184 Nos. of Title of Comprehensive Maintenance for 40Wp Solar Street Lights including 5 years’ Comprehensive Maintenance and supply of 5 (Page no: 1) NIT/Tende N/A Electrification of 895 Nos. of Off- LED Bulbs, Poles, Sign Boards & other material etc. for Electrification of 895 Nos. of Off- r Grid Villages in Arunachal Pradesh Grid Villages in Arunachal Pradesh under Deen Dayal Upadhyaya Gram Jyoti Yojana under Deen Dayal Upadhyaya (DDUGJY). Gram Jyoti Yojana (DDUGJY) including Supply of LED Bulbs, BLDC Fans, Poles, Sign Boards & other material etc.

Financial Eligibility Criteria (Annual Trunover as per Sl. No. 2): This Financial Eligibility Criteria (Avg. Annual turnover) (100%) should be met by all Section IV, Eligibility 6 criteria (100%) should be jointly met consortium members collectively and Lead Bidder should meet atleast 50% of the (Page no: 7) Criteria by Lead bidder and consortium criteria. partner.

Amendment: Cable 2C, 4 sq. mm max. 20 mtr per household DETAILED Cable 2C, 1.5 sq. mm max. 20 mtr per household SCOPE Fresh Addition: OF WORK Cable 2C, 4 mm approx. 20 mtr Section V, All Cable required quantity mentioned in this tender is tentative only, may vary as per & each lot 7 Clause A, f N/A site prevailing requirements. Bidder will consider actual cable length to be required at CONDITIO Cable 2C, 1.5 mm approx. 20 mtr (Page no: 10) site without any extra cost. NS OF each lot CONTRA Streelighting - CT Cable 2C, 4 sq. mm min. 5 mtr per Streetlight.

DETAILED SCOPE 1 No. three pin socket + 6 Nos. 7 Nos. On/Off switches (5 for LED lamps, 1 for DC Fan, 1 for TV socket). 5 lamp Section V, OF WORK On/Off switches on switchboard holders, 2 DC sockets (each for TV and Fan), 1nos. USB port 24V/1Amp, 1nos. DC Claue A, f & 8 N/A MCB 5 amp. (Page no: 9 CONDITIO All required Thimbles, ferrule, lugs, and 10) NS OF PVC Conduit pipe, Cable Ties etc. CONTRA CT

Bidder should have successfully Bidder should have successfully executed similar solar power projects (Grid Connected/ executed similar solar power Off-grid/ Mini-grid) or power sector projects (Generation/ Transmission/ Distribution) in projects (Grid Connected/ Off-grid/ last 7 Financial Years of value as below: Mini-grid) or power sector projects For Single Bidder: (Generation/ Transmission/ One Work Order of 12.0 Crores Distribution) of value a below: OR For Single Bidder: Two Work Orders of 7.0 Crores One Work Order of 12.0 Crores OR OR Three Work Orders of 6.0 Crores Two Work Orders of 7.0 Crores For Consortium/JV: OR Two Work Orders of 7.0 Crores Three Work Orders of 6.0 Crores OR For Consortium/JV: Three Work Orders of 6.0 Crores Two Work Orders of 7.0 Crores OR OR Three Work Orders of 6.0 Crores

The bidder must have successfully erected, tested and commissioned power generation or power sub-transmission or distribution projects/system in a single turnkey contract in last 7 years as on the date of bid opening, having installation of at least 40% of the KW capacity* considered in proposed bid and the system so created must be in satisfactory operation for at least one (1) year as on date of opening of techno-commercial bid. OR The bidder must have successfully erected, tested and commissioned power generation we are interested to participate in the or power sub-transmission or distribution projects/system in a Two contracts in last 7 Section IV, tender. So, we hereby request you to Eligibility years as on the date of bid opening, having installation of at least 25% of the KW 9 Sl. No. 3 kindly reduce the Financial Eligibility Criteria capacity* considered in proposed bid and the system so created must be in satisfactory (Page no: 7) Criteria if possible so that we can operation for at least one (1) year as on date of opening of techno-commercial bid. contentedly participate.

OR The bidder must have successfully erected, tested and commissioned power generation or power sub-transmission or distribution projects/system in a Three contracts in last 7 years as on the date of bid opening, having installation of at least 20% of the KW capacity* considered in proposed bid and the system so created must be in satisfactory operation for at least one (1) year as on date of opening of techno-commercial bid. OR Technical experience of erection, testing and commissioning of renewable energy solar offgrid/ grid project in single contract whose generation capacity shall be at-least 5% of total KW capacity* proposed in the bid and the system so created must be in satisfactory operation for at least one (1) year as on date of opening of techno- commercial bid. #Proposed bid capacity (in KW) means [(Total Nos. of Households covered * 0.3 KW/HH for standalone system) + (Total Nos. of street lights covered * 0.04 KW/street light fitting)].

Total sanctioned period for DETAILED complete design, engineering, SCOPE manufacture, testing, supply OF WORK including transportation up to Section V, Total sanctioned period for execution as per scope of work defined at the tender is 4 & Central Locations, insurance, 10 Claue B,1,1 N/A (Four) Months from the date of Allocation Letter/Work Order which can be extended CONDITIO unloading of material is 2 (Two) (Page no: 12) subject to approval of RECPDCL. NS OF Month from the date of Allocation CONTRA Letter/Work Order which can be CT extended subject to approval of RECPDCL. a. If the Successful Bidder is not COMMER able to supply of materials to the CIAL satisfaction of RECPDCL within a. If the Successful Bidder is not able to excute the work to the satisfaction of TERMS, Section VII, sanctioned period, PBG amount RECPDCL within sanctioned period, PBG amount submitted shall be forfeited. CONDITIO 11 Clause no: 3 submitted shall be forfeited. N/A NS & (Page no: 17) b. If the supplier does not fulfill its b. If the supplier does not fulfill its obligations as mentioned Section-V, Clause No. B, OTHER obligations as mentioned Section- (4), PBG amount shall be forfeited. PROVISIO V, Clause No. A (5) & A (6), PBG NS amount shall be forfeited.

All Households and Solar Street Lighting systems are to be provided with a sign board on flex laminated sheet with colour printing by Screen printing method (with proper permanent painting withstanding site conditions) for unique identification of the SECTION-VI, TECHNIC Supply and Installation of 1 Ft X 1 household / structure. The details of pre-painting preparations, painting and writing clause 3(a), AL FT sign Board for Identification shall be as per scope of work. The sign board (1ft x 1ft) should indicate the name of 12 N/A sign board, SPECIFIC each Solar Home Lighting and the scheme, name of implementation agency, capacity of household system / street page 14, ATIONS Street Lighting System separately. lighting system. The sign board should be put up immediately after commissioning. The sign board should contain the name of scheme, Details of village with census code & district name, number of households covered, number solar street lights installed under the scheme etc.

10.1: Supporting Documents: On completion of district wise work, contractor shall provide beneficiary wise details of COMMER standalone system installed in the village depicting unique serial no of set, name of CIAL beneficiary, contact number of beneficiary, name & census code of village, date of Section VII, TERMS, commissioning, details of Aadhar Card/election card and digital photograph. Clause no CONDITIO The contractor must obtain a copy of photo id proof like Aadhar card, voting id card 13 10, Payment New Clause N/A NS & etc for each household wherein standalone system has been provided. The contractor Terms (page OTHER shall also take digital photographs of all equipment including house wiring, panel, no: 18) PROVISIO battery etc and submit the photographs in soft copy of each households to the Project NS Manager. The Project Manager shall ensure strict compliance before release of payment to the contractor. Any other such document if required by RECPDCL, shall also be provided by the bidder.

14 h. ISI marked system wiring as per following: i. Panel to charge controller: 2 core 4 sqmm flexible multi strand copper conductor cable as per IS 694. Cable between panel to Solar DC charge controller shall be fixed properly with cable ties and shall be laid underground as per CPWD specifications between installation support and household. ii. Charge controller to battery: 2 core 4 sqmm flexible multi strand copper conductor cable as per IS 694 iii. Cable for House wiring: 2C 1.5 sq mm flexible multi strand copper conductor cable as per IS 694. All cables shall be terminated using copper lugs (ring type) duly crimped by a crimping machine. The cable shall be free of joints. All required Round Thimbles, connectors, ferrule, lugs, PVC Conduit pipe, Cable Ties SECTION-VI, TECHNIC New Clause N/A etc. clause 2 AL Wiring fixtures: Rigid non-metallic 12mm dia conduits for electrical installations as per IS (Page 14) SPECIFIC 2509 (latest amendment) having ISI stamping to be used for all system and internal ATIONS wiring works. The wires must be properly dressed and fixed on supporting structure at 1 feet intervals. Suitable tying materials like nylon cable ties or 16/18 SWG insulated GI wire shall be used to tie / dress the wire at interval of 1 ft. Depending on size of wall structure available at beneficiary house, decision shall be taken to provide length of cable ties. In case brick wall or solid structure of house is available for wiring, clips may be provided at 1 feet distance to hold the rigid non- metallic 12mm dia conduits pipes. 25 w power plug, USB port shall be installed on 40 mm dia round switch board properly installed on wall structure. At all corners wiring should be dressed properly using round corners etc. In addition to the description of Wiring mentioned as above, the detailed technical specification of cable ties shall be included as mentioned below: - Non-releasable Nylon Cable Ties shall be used suitable for continuos use on -40 degree to +85 degree centigrade temperature. It should be MIL 23190 E Tensile Strength complied cable ties having flame resistance capacity in accordance with UL 94V2. Following sizes of cable ties shall be used depending upon requirement at site (a) 120mm Long - 4.8mm Wide (b) 200mm Long - 4.8mm Wide (c) 430mm Long - 4.8mm Wide.

COMMER CIAL TERMS, SECTION- CONDITIO All the Components must comply with Applicable BIS Standards and MNRE guidelines 15 New Clause N/A VII, Page 16 NS & if any. OTHER PROVISIO NS Supply of BLDC Fan is excluded from the scope of Execution tender No: RECPDCL/ANP/DDG/16-17/3740. 16 - - General - Supply of BLDC Fan is included in the scope of Supply tender No: RECPDCL/ANP/DDG/16-17/3739 with total 13179 nos. of BLDC fans (1 No. per Solar Power Pack).

New RECPDCL has right to allocate supply work to different agencies within a district of 17 Section IX General conditions of Bid - Clause Aruncal Pradesh

1) In case completion of commissioning of material by Executing Agency is delayed beyond Six (6) months from delivery of first lot of supply/material by Solar Power pack/Solar Street lighting supplier, then the Store will be further maintained by the Solar Power pack/Solar Street lighting supplier on payment of such additional cost i.e. monthly rent etc. by Executing Agency mutually agreed between Bidder and Executing Agency. 18 2) In case execution is delayed due to unforseen circumstances / force majeure conditions within 6 months, then Solar Power pack/Solar Street lighting supplier will maintain the store upto 9 months from delivery of first lot of supply/material at his own expenses.

Any new tax introduced or revision in respective applicable tax rates after the date of New 19 - techno – commercial bid opening, shall be paid/reimbursed by the purchaser subject to Clause submission of requisite documentary evidence by the bidder. Section V, Addition: Other 20 -- - Bidder has to provide necessary support and services for collection of data from conditions, monitoring system, if required. Caluse no: b

New Proposed Village List attached. However this list is tentative and bidder has to survey 21 Annexure (Village List) - Clause and verify the same.

Page no: 44, Annexure-XIII FINANCIA Annexure - XIII, i.e., FINANCIAL BID of Execution Tender was revised and uploaded at 22 FINANCIAL BID - FINANCIAL L BID tenderwizard portal for online submission. BID The Date and Time for submission of bids is further extended, as detailed here under:

Details Scheduled Date and Time Extended/Revised Date and Time Last date of submission of Tender 24.03.2017 at 16:00 hrs. 03.04.2017 at 16:00 hrs. Date of opening of Technical Bid 24.03.2017 at 16:30 hrs. 03.04.2017 at 16:30 hrs.

Please contact for further queries:

Phone: 0120-4383759, 767 Email: [email protected]  RURAL ELECTRIFICATION OF 895 NOS. OF OFF-GRID VILLAGES IN ARUNACHAL PRADESH BY INSTALLING 300Wp SOLAR POWER PACKS UNDER DEENDAYAL UPADHYAYA GRAM JYOTI YOJANA (DDUGJY) Proposed Proposed Total Qty. of Proposed Proposed Qty. of Proposed Unit Total Proposed Powerpac Qty. of Sr. No. Name of District Qty. of Powerpack Qty. of Rating Rating Qty. of Street k for Street Powerpack for Powerpa (Wp) (Wp) Lights Public Lights Households ck Places 1 Anjaw 192 170 22 192 57600 68 68 2 Changlang 1043 748 37 785 235500 303 226 3 Dibang Valley 156 131 7 138 41400 52 46 4 East Kameng 2379 2072 151 2223 666900 735 682 5 East Siang 43 40 3 43 12900 13 13 6 Kurung Kumey 5505 4970 439 5409 1622700 1760 1725 7 Lohit 33 31 2 33 9900 10 10 8 Lower Dibang Valley 393 344 21 365300 109500 121 112 9 Lower Subansiri 1936 1177 88 1265 379500 662 429 10 Papum Pare 342 299 6 305 91500 97 85 11 170 72 7 79 23700 58 27 12 Upper Siang 137 126 11 137 41100 44 44 13 Upper Subansiri 1959 1369 135 1504 451200 652 492 14 West Kameng 327 130 6 136 40800 95 40 15 West Siang 786 514 51 565 169500 253 185 GRAND TOTAL 15401 12193 986 13179 3953700 4923 4184 Annexure (Village List) Decentralized Distribution Generation (DDG) Projects under Deendayal Upadhyaya Gram Jyoti Yojana List of villages Village No. of Census No. of No. of Street Sl. No. District Village name Block Name Code House Public Light as per Hold Places s 2011

12347910 1 Changlang 11 K.M. PWD Camp (Maithingro Kaan - II) Manmao 264166 26 29 2 East Kameng Gidi Sullung Bameng 262114 16 2 6 3 East Kameng Taffo Bameng 262123 17 2 6 4 East Kameng Lengdi/Liang Bameng 262116 18 2 7 5 East Kameng Nabalang Bameng 262085 19 2 7 6 East Kameng Emboriang Bameng 262112 19 3 8 7 East Kameng Sallang Bameng 262083 20 2 7 8 East Kameng Kojo Bameng 262089 20 2 7 9 East Kameng Bisai Bameng 262069 21 2 7 10 East Kameng Sachung Bameng 262072 21 3 8 11 East Kameng Upper Liyak Doncha Bameng 262125 22 2 8 12 East Kameng Drakshi Bameng 262088 30 2 10 13 East Kameng Upper Liyak Donia Bameng 262124 30 3 11 14 East Kameng Poube Sullung Bameng 262127 33 3 11 15 East Kameng Effa Bameng 262113 34 3 12 16 East Kameng Rapung Bameng 262093 39 2 12 17 East Kameng Lada H.Q. Bameng 262082 48 3 15 18 East Kameng Tawe Bameng 262073 60 2 17 19 East Kameng Lower Liyak Bameng 262094 63 3 19 20 East Kameng Afaksung Bana 261997 19 2 7 21 East Kameng New Longte Poube Bana 262014 20 2 7 22 East Kameng Byale Sullung Chayangtajo 262248 19 2 7 23 East Kameng Nampe Bagang Chayangtajo 262273 22 2 8 24 East Kameng Loto Yangfo Chayangtajo 262255 26 2 9 25 East Kameng Yakli Sullung Chayangtajo 262277 26 2 9 26 East Kameng Saliwa Yangfo Chayangtajo 262217 31 2 10 27 East Kameng Nampe Chayangtajo 262265 31 2 10 28 East Kameng Saria Takhang Chayangtajo 262271 36 2 11 29 East Kameng Veo Chayangtajo 262275 40 2 12 30 East Kameng Lamnio Chayangtajo 262257 69 3 20 31 East Kameng Langri I.A.Y.Village Khenewa 262196 16 2 6 32 East Kameng Latum I.A.Y.Village (Sangbia) Khenewa 262189 52 2 15 33 East Kameng Pajewa Pakke Kessang 261968 16 2 6 34 East Kameng Laluwapa Pakke Kessang 261967 20 2 7 35 East Kameng Balipota Pakke Kessang 261970 35 2 11 36 East Kameng Talomlati Pipu 262180 20 2 7 37 East Kameng Lasak Cheda Pipu 262158 23 3 9 38 East Kameng Miri Sollung Pipu 262175 24 2 8 39 East Kameng Lochung Pipu 262143 25 2 8 40 East Kameng Gyawe Purang Hq. Pipu 262181 27 2 9 41 East Kameng Dokre Gyadi Pipu 262174 31 2 10 42 East Kameng Tabri Pipu 262144 40 2 12 43 East Kameng Flago Pipu 262139 52 2 15 44 East Kameng Richi Lamgu Pipu 262182 56 2 16 45 East Kameng Tagang Warang Pipu 262179 61 3 18 46 East Kameng Doka Pipu 262137 73 2 20 47 East Kameng Bokar Pipu 262142 78 2 22 48 East Kameng Hamba – Pinda SEPPA 262039 64 3 19 49 East Siang Messing Pangin 263786 16 2 6 50 Kurung Kumey Techipu Koto Chambang 265570 16 3 7 51 Kurung Kumey Pha Chambang 265584 16 2 6 52 Kurung Kumey Mugli Chambang 265604 16 2 6 53 Kurung Kumey Tayo Chambang 265642 16 2 6 54 Kurung Kumey Korapu Chambang 265669 16 2 6 55 Kurung Kumey Kembing Chambang 265630 17 2 6 56 Kurung Kumey Paha Chambang 265520 18 2 7 57 Kurung Kumey Gad Chambang 265576 18 2 7 58 Kurung Kumey Pitak Chambang 265614 19 2 7 59 Kurung Kumey Boje Chambang 265655 19 2 7 60 Kurung Kumey Kote Chambang 265553 20 2 7 61 Kurung Kumey Bungkung Chambang 265615 21 2 7 62 Kurung Kumey Puch-Pute Chambang 265653 21 2 7 63 Kurung Kumey Rembing Chambang 265627 22 2 8 64 Kurung Kumey Cvuth Chambang 265644 23 2 8 65 Kurung Kumey Paka Chambang 265657 25 1 8 66 Kurung Kumey Tokriang Damin 265778 20 2 7 67 Kurung Kumey Galan Damin 265817 22 2 8 68 Kurung Kumey Putong Damin 265779 23 2 8 69 Kurung Kumey Omla Damin 265789 24 2 8 70 Kurung Kumey Dania Damin 265827 24 2 8 71 Kurung Kumey Peni Damin 265791 28 2 9 72 Kurung Kumey Dogwa Damin 265819 31 2 10 73 Kurung Kumey Sejik Damin 265799 36 2 11 74 Kurung Kumey Furek Koloriang 265495 16 2 6 75 Kurung Kumey Longlefoth Nyapin 265372 17 1 6 76 Kurung Kumey Jugriang Nyapin 265410 19 2 7 77 Kurung Kumey Raris Nyapin 265413 20 3 8 78 Kurung Kumey Gufa Nyapin 265416 20 2 7 79 Kurung Kumey Hill Top Nyapin 265354 21 2 7 80 Kurung Kumey Mingpa Nyapin 265357 21 2 7 81 Kurung Kumey Dilanggang Nyapin 265373 21 2 7 82 Kurung Kumey Pate Nyapin 265421 21 2 7 83 Kurung Kumey Diba Koyar Nyapin 265423 21 2 7 84 Kurung Kumey Tabing Nyapin 265364 23 1 8 85 Kurung Kumey Kudung Palin 265176 16 2 6 86 Kurung Kumey Jiirilangney Palin 265189 16 2 6 87 Kurung Kumey Kusuk Palin 265203 16 2 6 88 Kurung Kumey Papey Palin 265178 17 2 6 89 Kurung Kumey Tapey Palin 265192 17 2 6 90 Kurung Kumey Kikum Palin 265249 17 2 6 91 Kurung Kumey Yapap Bogu Palin 265238 19 2 7 92 Kurung Kumey Khawong Palin 265200 20 2 7 93 Kurung Kumey Tabu Palin 265240 20 2 7 94 Kurung Kumey Hujuriang Palin 265244 22 2 8 95 Kurung Kumey Langtey Palin 265231 23 2 8 96 Kurung Kumey Pijo Palin 265241 23 2 8 97 Kurung Kumey Robo Palin 265194 26 2 9 98 Kurung Kumey Dokio Pep Palin 265250 29 2 9 99 Kurung Kumey Riope-Riome Palin 265197 31 2 10 100 Kurung Kumey Cheba Parsi Parlo 265748 16 2 6 101 Kurung Kumey Rashik I Parsi Parlo 265742 17 2 6 102 Kurung Kumey Kelin Parsi Parlo 265757 19 2 7 103 Kurung Kumey Bampung Hema Parsi Parlo 265722 20 2 7 104 Kurung Kumey Mangdo-I Parsi Parlo 265715 22 2 8 105 Kurung Kumey Tasum Parsi Parlo 265713 23 2 8 106 Kurung Kumey Lumdang Parsi Parlo 265734 23 2 8 107 Kurung Kumey Made Parsi Parlo 265749 23 2 8 108 Kurung Kumey Joku Parsi Parlo 265759 23 2 8 109 Kurung Kumey Pachik Parsi Parlo 265772 23 2 8 110 Kurung Kumey Renchiporiang -I Parsi Parlo 265720 24 2 8 111 Kurung Kumey Yarba-I Parsi Parlo 265731 24 2 8 112 Kurung Kumey Pado I Parsi Parlo 265733 24 2 8 113 Kurung Kumey Pilop Parsi Parlo 265751 24 2 8 114 Kurung Kumey Pape Parsi Parlo 265765 24 2 8 115 Kurung Kumey Topuriang Parsi Parlo 265767 24 2 8 116 Kurung Kumey Yerba Parsi Parlo 265730 29 2 9 117 Kurung Kumey Pachang Parsi Parlo 265762 31 2 10 118 Kurung Kumey Geyang Parsi Parlo 265774 31 2 10 119 Kurung Kumey Mala Parsi Parlo 265771 33 2 10 120 Kurung Kumey Libia Parsi Parlo 265717 48 2 14 121 Kurung Kumey Molo Parsi Parlo 265724 48 2 14 122 Kurung Kumey Dangu Sangram 265287 16 2 6 123 Kurung Kumey Palin Sangram 265288 18 1 7 124 Kurung Kumey Regba Sangram 265333 18 2 7 125 Kurung Kumey Niayahutung Sangram 265310 19 2 7 126 Kurung Kumey Haggar Sangram 265285 20 2 7 127 Kurung Kumey Sangmey Sangram 265297 25 2 8 128 Kurung Kumey Kerium Hapa Sangram 265320 29 2 9 129 Kurung Kumey Reyup Sangram 265282 32 2 10 130 Kurung Kumey Biyar Tali 265885 16 2 6 131 Kurung Kumey Cholo Tali 265886 19 2 7 132 Kurung Kumey Jhapuk Tali 265892 19 2 7 133 Kurung Kumey Hokpuk Tali 265883 51 2 15 134 Lohit Chiblaliang Tezu 266408 23 2 8 135 Papum Pare Poteh Sagalee 262638 21 2 7 136 Upper Siang Palling H.Q. 263957 30 4 12 137 Upper Subansiri Lomigaling Giba 263011 16 2 6 138 Upper Subansiri Hara Giba 263072 16 2 6 139 Upper Subansiri Raha village Giba 263083 17 2 6 140 Upper Subansiri Hengnedoku Giba 263084 17 2 6 141 Upper Subansiri Lomi Giba 263091 19 2 7 142 Upper Subansiri Dargung Giba 263034 22 2 8 143 Upper Subansiri Goha Giba 263090 25 2 8 144 Upper Subansiri Marging Giba 263022 27 2 9 145 Upper Subansiri Rikung Giba 263087 30 2 10 146 Upper Subansiri Nilling Giba 263086 39 3 13 147 Upper Subansiri Markia Giba 263021 42 2 13 148 Upper Subansiri Ketha Siyum 262885 17 2 6 149 Upper Subansiri Ekke Siyum 262884 67 3 20 150 Upper Subansiri Neignu Taliha 262991 30 2 10 151 Upper Subansiri Nimpu Taliha 262940 46 3 15 152 West Kameng West Sachung Nafra 261716 22 2 8 153 West Siang Liduk Gensi 263700 18 3 8 154 West Siang Meying Kaying -Payum 263422 31 2 10 155 West Siang Yorkodom Monigaon 263363 16 2 6 156 West Siang Paning Monigaon 263380 19 2 7 157 West Siang Simuging Monigaon 263366 20 2 7 158 West Siang Nema Sibo Monigaon 263360 21 2 7 159 West Siang Pape Krong Monigaon 263361 21 2 7 160 West Siang Soyorgong Monigaon 263364 12 2 5 161 West Siang Sukudom Monigaon 263369 12 2 5 162 West Siang Chingo Monigaon 263359 15 3 7 163 West Siang Yogong Rumgong 263502 38 2 12 164 Anjaw Kanguliang 266812 12 1 4 165 Changlang Relangkan CHANGLANG 264146 33 2 10 166 Changlang Gandhigram Bl.I & II KHAGAM-MIAO 264244 342 5 91 167 Dibang Valley Aoli ANELIH-ARJU 266024 13 1 4 168 Dibang Valley Tyee Model Village ANELIH-ARJU 266013 8 0 2 169 Dibang Valley Awoka ANELIH-ARJU 266014 4 0 1 170 Dibang Valley Cheppe ANELIH-ARJU 266017 6 0 2 171 Dibang Valley Akhuli ETALIN-MALINEY 265968 2 0 1 172 Dibang Valley Ambolin ETALIN-MALINEY 265969 4 0 1 173 East Siang Lissing Pangin 263785 13 1 4 174 East Siang Sipo(Hipo) RAMLE BANGO 263827 4 0 1 175 Kurung Kumey Baggam (Baojam) Pipsorang 265842 31 2 10 176 Kurung Kumey Biya Pipsorang 265856 28 2 9 177 Kurung Kumey Chome Pipsorang 265861 10 2 5 178 Kurung Kumey Gatam Pipsorang 265857 5 1 2 179 Kurung Kumey Gyapin Pipsorang 265840 80 2 22 180 Kurung Kumey Ha Pipsorang 265846 58 3 18 181 Kurung Kumey Habak Pipsorang 265858 7 1 3 182 Kurung Kumey Haimachi Pipsorang 265839 17 2 6 183 Kurung Kumey Haina Pipsorang 265847 30 3 11 184 Kurung Kumey Hapuk (L) Pipsorang 265855 11 2 5 185 Kurung Kumey Kaba Pipsorang 265849 38 2 12 186 Kurung Kumey Keyang Pipsorang 265863 28 2 9 187 Kurung Kumey Kokso Pipsorang 265862 7 1 3 188 Kurung Kumey Nabiya Pipsorang 265843 71 2 20 189 Kurung Kumey Nayeng Pipsorang 265845 42 2 13 190 Kurung Kumey Neorum Pipsorang 265836 11 2 5 191 Kurung Kumey New Zara Pipsorang 265864 34 2 11 192 Kurung Kumey Nikbia Pipsorang 265859 20 2 7 193 Kurung Kumey Nyache Pipsorang 265853 48 2 14 194 Kurung Kumey Pija Pipsorang 265854 16 2 6 195 Kurung Kumey Pilua Pipsorang 265850 37 2 11 196 Kurung Kumey Raha Pipsorang 265860 34 2 11 197 Kurung Kumey Richik Pipsorang 265851 6 1 3 198 Kurung Kumey Samba Karsang Pipsorang 265832 38 2 12 199 Kurung Kumey Sangia Pipsorang 265852 45 2 13 200 Kurung Kumey Tami Pipsorang 265848 34 2 11 201 Kurung Kumey Zara Pipsorang 265844 40 3 13 202 Kurung Kumey Giba TALI 265903 35 2 11 203 Kurung Kumey Guchi TALI 265880 63 4 20 204 Kurung Kumey Hokpu TALI 265879 24 2 8 205 Kurung Kumey Panio TALI 265875 32 2 10 206 Kurung Kumey Sojam TALI 265881 19 2 7 207 Lower Dibang Valley Karo -Kronli 266117 5 0 1 208 Lower Dibang Valley Rango Hunli-Kronli 266055 2 0 1 209 Lower Dibang Valley Gimbo (28 K.M. Point) Roing 266142 20 2 7 210 Lower Subansiri Biku Tamen-Raga 265118 16 1 5 211 Lower Subansiri Bini Tamen-Raga 265119 24 2 8 212 Lower Subansiri Bokbarijop (Kina) Tamen-Raga 265117 11 1 4 213 Lower Subansiri Chirdi Tamen-Raga 265116 20 2 7 214 Lower Subansiri Dokne Puri Tamen-Raga 265145 7 0 2 215 Lower Subansiri Gote Tamen-Raga 265122 5 0 1 216 Lower Subansiri Jal Tamen-Raga 265155 15 1 5 217 Lower Subansiri Lelin Tamen-Raga 265121 12 1 4 218 Lower Subansiri Moinpu Tamen-Raga 265165 13 1 4 219 Lower Subansiri Pega Tamen-Raga 265157 9 1 3 220 Lower Subansiri Rilki Tamen-Raga 265123 4 0 1 221 Lower Subansiri Rottom Tamen-Raga 265120 50 2 15 222 Lower Subansiri Tass Tamen-Raga 265166 8 0 2 223 Lower Subansiri Tepko Tamen-Raga 265156 11 1 4 224 Lower Subansiri Teririjo Tamen-Raga 265115 41 2 12 225 Lower Subansiri Yemin Deru Tamen-Raga 265142 11 1 4 226 Lower Subansiri Digen ZIRO - I 264651 2 0 1 227 Lower Subansiri Kiidi ZIRO - I 264705 5 0 1 228 Lower Subansiri Layo ZIRO - I 264622 4 0 1 229 Lower Subansiri Pakhang Toku ZIRO - I 264735 1 0 1 230 Lower Subansiri Pobii ZIRO - I 264704 2 0 1 231 Lower Subansiri Pusa Yoda ZIRO - I 264657 1 0 1 232 Lower Subansiri Talle Valley ZIRO - I 264642 2 0 1 233 Lower Subansiri Taro More ZIRO - I 264643 1 0 1 234 Lower Subansiri Zamra ZIRO - I 264645 1 0 1 235 Papum Pare Dwr Rabg Balijan 262420 3 0 1 236 Papum Pare Sichir Doimukh 262462 36 2 11 237 Papum Pare Bomch-Bomte Kimin 262745 1 0 1 238 Tawang Luguthang Jang-Thingbu 261611 11 1 4 239 Tawang Thangphe Gonpa TAWANG 261496 5 0 1 240 Upper Siang Pongging Geku 264034 50 3 16 241 Upper Siang Peki-Modi MARIYANG 264023 13 2 5 242 West Siang Dibe GENSI 263703 5 0 1 243 West Siang Gate KAYING-PAYUM 263410 47 3 15 244 West Siang Richi - Rite LIKHABALI 263748 5 0 1 245 West Siang Lipo 263435 8 1 3 246 West Siang Upper Heyo MECHUKA 263428 7 0 2 247 West Siang Hemi Monigaon 263381 25 3 9 248 West Siang Labukar Monigaon 263367 16 1 5 249 West Siang Talamying Monigaon 263382 22 2 8 250 West Siang Yasing RUMGONG 263504 34 3 12 251 Tawang Bemathang Gonpa Tawang 261474 3 01 252 Tawang Chala Gonpa Tawang 261475 3 01 253 Tawang Yuesa Gonpa Tawang 261491 2 01 254 Tawang Sarong Jang-Thingbu 261606 2 01 255 Tawang Tebo Zemithang-Dudunagar 261389 4 01 256 East Kameng Welling Tawe Bameng 262074 3 01 257 East Kameng Prait Bameng 262081 5 01 258 East Kameng Mara Tassar Sullung Chyang-Tajo 262242 3 01 259 East Kameng Kowa Sullung Chyang-Tajo 262254 3 01 260 East Kameng Diya Sullung Chyang-Tajo 262266 4 01 261 East Kameng Mebuwa - I Seppa 262046 2 01 262 East Kameng Ladu Sullung Pipu 262138 4 01 263 East Kameng Dabiwa Cheda Pipu 262153 3 01 264 East Kameng Longik Sullung Pipu 262156 4 01 265 East Kameng Moku Sullong Pipu 262157 2 01 266 East Kameng Sangripu (Tara Sullung) Pipu 262159 3 01 267 East Kameng Debiwa Sollung Pipu 262162 3 01 268 East Kameng Sagya Sullung Pipu 262166 2 01 269 East Kameng Anuk Sollung Pipu 262176 1 01 270 East Kameng A - 1 Block Seijosa 261901 5 01 271 East Kameng Dirring Seijosa 261911 1 01 272 East Kameng Japu Khenewa 262197 5 01 273 West Kameng Phomdong Dirang 261665 4 01 274 Papum Pare Taram Doimukh 262317 2 01 275 Papum Pare Rumi Sagalee 262525 5 01 276 Papum Pare Habia Sagalee 262529 3 01 277 Papum Pare Pachin Sagalee 262583 4 01 278 Papum Pare Taipu Sagalee 262640 3 01 279 Papum Pare Langke Sagalee 262655 5 01 280 Papum Pare Upper Rupung Sagalee 262656 3 01 281 Papum Pare Talikso Sagalee 262672 4 01 282 Papum Pare Lengke Balijan 262406 5 01 283 Papum Pare Lengso Balijan 262430 5 01 284 Papum Pare Boginadi Forest Beat Kimin 262759 2 01 285 Lower Subansiri Amperi Tamen-Raga 265033 4 01 286 Lower Subansiri Subnar Tamen-Raga 265035 2 01 287 Lower Subansiri Bomri Hapa Tamen-Raga 265040 5 01 288 Lower Subansiri Katri Tamen-Raga 265044 3 01 289 Lower Subansiri Dirgo Tamen-Raga 265046 4 01 290 Lower Subansiri Ayi Poot Rejo Tamen-Raga 265048 2 01 291 Lower Subansiri Dabi Hapa Tamen-Raga 265053 3 01 292 Lower Subansiri Langding Tamen-Raga 265072 3 01 293 Lower Subansiri Hatak Putu Tamen-Raga 265074 4 01 294 Lower Subansiri Dansok Tamen-Raga 265086 2 01 295 Lower Subansiri Ajo Phab Tamen-Raga 265102 3 01 296 Lower Subansiri Laa II Tamen-Raga 265106 1 01 297 Lower Subansiri Kemyir Tamen-Raga 265139 4 01 298 Lower Subansiri Tiiba Ziro-I 264594 5 12 299 Lower Subansiri Taring (Hong) Ziro-I 264599 1 01 300 Lower Subansiri Haley Ziro-I 264602 2 01 301 Lower Subansiri Lodderkonti Ziro-I 264603 1 01 302 Lower Subansiri Lower Dilo Ziro-I 264607 5 01 303 Lower Subansiri Sichobo Ziro-I 264609 2 01 304 Lower Subansiri Belongbo Ziro-I 264612 1 01 305 Lower Subansiri Cholo Agya Ziro-I 264613 2 01 306 Lower Subansiri Bhu Ziro-I 264621 1 01 307 Lower Subansiri Rabii Ziro-I 264626 1 01 308 Lower Subansiri Saliyoga Ziro-I 264628 3 01 309 Lower Subansiri Dilo Yao Ziro-I 264630 2 01 310 Lower Subansiri Boi Ziro-I 264632 1 01 311 Lower Subansiri Lodder Ziro-I 264634 1 01 312 Lower Subansiri Lodder I Ziro-I 264636 2 01 313 Lower Subansiri Yo Daboi Ziro-I 264637 1 01 314 Lower Subansiri Sugyu Pabu Ziro-I 264641 2 01 315 Lower Subansiri Dolu Poba Ziro-I 264647 2 01 316 Lower Subansiri Lentha Pabu Ziro-I 264648 3 01 317 Lower Subansiri Tayuko Ziro-I 264652 3 01 318 Lower Subansiri Hakap Ziro-I 264653 5 01 319 Lower Subansiri Sangepo Ziro-I 264656 4 01 320 Lower Subansiri Namiligo Ziro-I 264659 2 01 321 Lower Subansiri Ukobije Ziro-I 264660 1 01 322 Lower Subansiri Rantii Ziro-I 264661 2 01 323 Lower Subansiri Pokheakamg Ziro-I 264666 3 01 324 Lower Subansiri Yolyo Ziro-I 264667 1 01 325 Lower Subansiri Tero Ago Ziro-I 264669 2 12 326 Lower Subansiri Siri Dipii Ziro-I 264670 1 01 327 Lower Subansiri Taru Kelyang Ziro-I 264671 1 01 328 Lower Subansiri Rubu Ziro-I 264672 5 01 329 Lower Subansiri Poralya Ziro-I 264673 3 01 330 Lower Subansiri Pepungko Ziro-I 264678 1 01 331 Lower Subansiri Nanu Ziro-I 264681 3 01 332 Lower Subansiri Pai Achang Ziro-I 264685 3 12 333 Lower Subansiri Miding Passu Ziro-I 264691 2 01 334 Lower Subansiri Bokan II Ziro-I 264692 1 01 335 Lower Subansiri Tiibeko Ziro-I 264701 3 01 336 Lower Subansiri Tariko Ziro-I 264703 1 01 337 Lower Subansiri Siringpakho Ziro-I 264722 1 01 338 Lower Subansiri Amung Ziro-I 264725 4 01 339 Lower Subansiri Myoliku Ziro-I 264729 3 01 340 Lower Subansiri Kalo Ziro-I 264730 1 01 341 Lower Subansiri Nyibo Ziro-I 264731 2 01 342 Lower Subansiri To Myobia Ziro-I 264732 1 01 343 Lower Subansiri Byore Ziro-I 264733 1 01 344 Lower Subansiri Gyabu Ziro-I 264734 5 01 345 Lower Subansiri Lenting Layu Ziro-I 264737 1 01 346 Lower Subansiri Shi Ziro-I 264741 1 01 347 Lower Subansiri Kululemp Ziro-I 264742 4 01 348 Lower Subansiri Yashibo Ziro-I 264751 3 12 349 Lower Subansiri Bubu Ziro-I 264758 5 01 350 Lower Subansiri Saro Ziro-I 264759 2 01 351 Lower Subansiri Kato Ziro-I 264760 4 12 352 Lower Subansiri Riku Lanche Ziro-I 264761 3 01 353 Lower Subansiri Kiile Pakho Ziro-I 264787 1 01 354 Lower Subansiri Saro Ziro-I 264803 5 01 355 Lower Subansiri Myochi Ziro-I 264804 5 01 356 Lower Subansiri Lengo Ziro-I 264813 5 01 357 Lower Subansiri Tanyo Ziro-I 264817 5 01 358 Lower Subansiri Polu Happa Ziro-II 264883 1 01 359 Lower Subansiri Kotu Nampam Ziro-II 264889 3 01 360 Lower Subansiri Howu Happa Ziro-II 264905 1 01 361 Lower Subansiri Paa Yorda Ziro-II 264907 3 01 362 Lower Subansiri Moob Happa Ziro-II 264923 2 01 363 Kurung kumey Nyoya Chambang 265525 3 01 364 Kurung kumey Hatey Chambang 265526 4 01 365 Kurung kumey Korayer-I Chambang 265528 1 01 366 Kurung kumey Korayer-II Chambang 265529 1 01 367 Kurung kumey Bongkung Chambang 265547 5 01 368 Kurung kumey Pitak Chambang 265548 5 01 369 Kurung kumey Sonia Chambang 265558 2 01 370 Kurung kumey Boring Chambang 265572 5 01 371 Kurung kumey Lomak Hapa Chambang 265575 5 01 372 Kurung kumey Dayam Hapa Chambang 265585 5 01 373 Kurung kumey Banga Kotho Chambang 265589 3 01 374 Kurung kumey Genchi Chambang 265598 2 01 375 Kurung kumey Hepu-Hapa Chambang 265641 4 01 376 Kurung kumey Kott-Ratt Chambang 265672 3 01 377 Kurung kumey Namniar Damin 265813 5 01 378 Kurung kumey Manghe II Koloriag 265436 4 01 379 Kurung kumey Deyang Koloriag 265466 5 01 380 Kurung kumey Buhan Koloriag 265467 3 01 381 Kurung kumey Chimpu Koloriag 265478 4 01 382 Kurung kumey Torme Yarda Nyapin 265356 4 01 383 Kurung kumey Lower Guha Nyapin 265367 1 01 384 Kurung kumey Lower Lorio Nyapin 265369 2 01 385 Kurung kumey Humga Jariang Nyapin 265380 1 01 386 Kurung kumey Suriu Nyapin 265386 4 01 387 Kurung kumey Guha Nyapin 265394 3 01 388 Kurung kumey Pinchung Nyapin 265399 3 01 389 Kurung kumey Youndo Nyapin 265406 3 01 390 Kurung kumey Saleriang(Sulung) Nyapin 265411 5 01 391 Kurung kumey Sikey Nyapin 265419 4 01 392 Kurung kumey Bumpey Palin 265188 5 01 393 Kurung kumey Serak Palin 265224 4 01 394 Kurung kumey Jejer Palin 265263 5 01 395 Kurung kumey Demepup Sangram 265294 5 01 396 Kurung kumey Miba Sangram 265347 5 01 397 Upper Subansiri Bhur Daporijo 263100 5 01 398 Upper Subansiri Cheha-Rijo Daporijo 263109 3 01 399 Upper Subansiri Nirpelibe Dumporijo 263197 5 01 400 Upper Subansiri Dogi Rosarijo Dumporijo 263269 5 01 401 Upper Subansiri Dape Nacho 262804 5 01 402 Upper Subansiri Kojup Nacho 262847 4 01 403 Upper Subansiri Gich Putu Puchi-Geko 263149 2 01 404 Upper Subansiri Dadu Limeking 262764 5 01 405 Upper Subansiri Bodok Limeking 262784 4 01 406 Upper Subansiri Nyare Limeking 262786 1 01 407 Upper Subansiri Mepu Limeking 262788 2 01 408 Upper Subansiri Orak Camp Limeking 262793 1 01 409 Upper Subansiri Makodo Limeking 262797 1 01 410 Upper Siang Amging Tuting 263953 5 01 411 West Siang Gai Mechuka 263437 2 01 412 West Siang Tasum Monigong 263365 2 01 413 West Siang Sijak Monigong 263387 3 01 414 West Siang Gekar Monigong 263391 4 01 415 West Siang Panglum Monigong 263394 4 01 416 Dibang Valley Akaya Anelih-Arju 266021 3 01 417 Dibang Valley Ethore Anelih-Arju 266033 3 01 418 Dibang Valley Idipo Anelih-Arju 266037 2 01 419 Dibang Valley Ithun Camp Anelih-Arju 266038 1 01 420 Dibang Valley Adali -Mipi 265908 4 01 421 Dibang Valley Jingupu Anini-Mipi 265911 5 01 422 Dibang Valley Ediya Anini-Mipi 265915 3 01 423 Dibang Valley Kamuyi Anini-Mipi 265918 4 01 424 Dibang Valley New Achuli Anini-Mipi 265927 4 01 425 Dibang Valley Achengo Anini-Mipi 265937 2 01 426 Dibang Valley Maley Anini-Mipi 265938 1 01 427 Dibang Valley Apunli Etalin-Maliney 265978 2 01 428 Dibang Valley Aningo Etalin-Maliney 265980 1 01 429 Dibang Valley Chanli Etalin-Maliney 265985 4 01 430 Lower Dibang Valley Asongo Hunli-Kronli 266057 3 01 431 Lower Dibang Valley Aphungu Hunli-Kronli 266066 3 01 432 Lower Dibang Valley Akuli Hunli-Kronli 266070 5 01 433 Lower Dibang Valley Chelaka (82 K.M.) Hunli-Kronli 266072 4 01 434 Lower Dibang Valley Akanda Hunli-Kronli 266092 4 01 435 Lower Dibang Valley Bititi Hunli-Kronli 266104 5 01 436 Lower Dibang Valley Chumduku Hunli-Kronli 266105 3 01 437 Lower Dibang Valley Chruango Hunli-Kronli 266110 3 01 438 Lower Dibang Valley Pi-Kha Hunli-Kronli 266116 2 01 439 Lower Dibang Valley Necha Hunli-Kronli 266120 3 01 440 Lower Dibang Valley Arini Hunli-Kronli 266121 5 01 441 Lower Dibang Valley Theyapra Hunli-Kronli 266128 2 01 442 Lower Dibang Valley Pika Hunli-Kronli 266129 2 01 443 Lower Dibang Valley Mariso Hunli-Kronli 266132 5 01 444 Lower Dibang Valley Mariso Hunli-Kronli 266133 5 01 445 Lower Dibang Valley Lupong Roing 266168 4 01 446 Lower Dibang Valley Natipi Roing 266270 5 01 447 Lower Dibang Valley Chela Roing 266271 5 01 448 Lower Dibang Valley Akela Roing 266272 3 01 449 Lower Dibang Valley Ithini Roing 266348 1 01 450 Anjaw Dong 266880 4 01 451 Anjaw Maha Hayuliang 266702 3 01 452 Anjaw Khowegko 266843 5 01 453 Anjaw Payaparap Chaglagam 266847 4 01 454 Anjaw Long Jam Manchal 266744 3 01 455 Anjaw Eliang Manchal 266746 3 01 456 Anjaw Pirah Manchal 266747 4 01 457 Anjaw Chutong Manchal 266758 4 01 458 Changlang 9 K.M. PWD Camp (Jongkey) Changlang 264110 3 01 459 Anjaw Doringko Chaglagam 266848 9 0 2 460 Anjaw Chipuiliang Chaglagam 266841 10 2 5 461 Anjaw Tabretong Chaglagam 266845 10 2 5 462 Anjaw Payagam Chaglagam 266854 11 2 5 463 Anjaw Pailiang Chaglagam 266844 13 2 5 464 Anjaw Gomin Chaglagam 266850 14 2 6 465 Anjaw Chirang HAYULIANG 266789 10 2 5 466 Anjaw Glotong HAYULIANG 266788 11 2 5 467 Anjaw Qunboo Manchal 266757 10 2 5 468 Anjaw Ekailiang Manchal 266760 11 2 5 469 Anjaw Chowailing Manchal 266745 12 3 6 470 Anjaw Chowagong Walong 266915 7 0 2 471 Changlang Industrial Estate CHANGLANG 264086 13 2 5 472 Changlang 3 K.M. Forest Camp (Namdang-II) CHANGLANG 264143 13 2 5 473 Changlang 17 Mile M.V. Road (Sher) (17 Mile Village) KHAGAM-MIAO 264287 12 2 5 474 Changlang Daragaon KHAGAM-MIAO 264238 47 2 14 475 Changlang Dawodi KHAGAM-MIAO 264239 37 2 11 476 Changlang Phaparbari KHAGAM-MIAO 264240 47 3 15 477 Changlang Gaherigaon KHAGAM-MIAO 264241 11 2 5 478 Changlang Hazolo KHAGAM-MIAO 264242 32 3 11 479 Changlang Ramnagar KHAGAM-MIAO 264243 21 3 8 480 Changlang Chidudi KHAGAM-MIAO 264245 30 2 10 481 Changlang Mazgaon KHAGAM-MIAO 264246 42 3 14 482 Changlang Sidikuh KHAGAM-MIAO 264250 39 2 12 483 Dibang Valley Wanli ANELIH-ARJU 266019 11 2 5 484 Dibang Valley Ahungo ANINI-MIPI 265913 7 0 2 485 Dibang Valley Eyongo ANINI-MIPI 265953 8 0 2 486 Dibang Valley Ebamee ANINI-MIPI 265939 10 2 5 487 Dibang Valley Agagu ANINI-MIPI 265925 15 2 6 488 Dibang Valley Alney (Aloney ) ETALIN-MALINEY 265981 4 0 1 489 East Kameng Babey Camp BAMENG 262126 6 0 2 490 East Kameng Pipiang BAMENG 262070 7 0 2 491 East Kameng Laja Sullung BAMENG 262115 7 0 2 492 East Kameng Dongkha BAMENG 262075 8 0 2 493 East Kameng Nissangjang BAMENG 262071 9 0 2 494 East Kameng Kampa - N.V. BAMENG 262077 9 0 2 495 East Kameng Gikung BAMENG 262079 9 0 2 496 East Kameng Wabalang BAMENG 262084 9 0 2 497 East Kameng Pia BAMENG 262078 13 2 5 498 East Kameng Wakke BAMENG 262087 13 2 5 499 East Kameng Granjang BAMENG 262086 10 2 5 500 East Kameng Satuk (Ramda) BAMENG 262080 11 2 5 501 East Kameng Rojo BAMENG 262090 15 2 6 502 East Kameng Lelung Bana 262013 13 2 5 503 East Kameng Warriam Sullung CHAYANGTAJO 262270 7 0 2 504 East Kameng Parte CHAYANGTAJO 262267 8 0 2 505 East Kameng Mechi CHAYANGTAJO 262260 10 2 5 506 East Kameng Weigung Sullung CHAYANGTAJO 262249 11 2 5 507 East Kameng Dao CHAYANGTAJO 262251 12 2 5 508 East Kameng Dara Yangfo CHAYANGTAJO 262258 12 2 5 509 East Kameng Mechar CHAYANGTAJO 262259 13 2 5 510 East Kameng Tassar Sullung CHAYANGTAJO 262241 14 2 6 511 East Kameng Sario CHAYANGTAJO 262269 15 2 6 512 East Kameng Venia CHAYANGTAJO 262276 15 2 6 513 East Kameng Wagyung Khenewa 262187 6 0 2 514 East Kameng Sefew Khenewa 262201 9 0 2 515 East Kameng Yacho Khenewa 262186 10 2 5 516 East Kameng Kapa Khenewa 262206 10 2 5 517 East Kameng Chaling Khenewa 262205 11 2 5 518 East Kameng Kawarang Khenewa 262208 12 2 5 519 East Kameng Kampu Seba PAKKE KESSANG 261981 13 2 5 520 East Kameng Pania Sullung Pipu 262140 6 0 2 521 East Kameng Meomey Sollung Pipu 262177 8 0 2 522 East Kameng Longo Gollo Pipu 262178 8 0 2 523 East Kameng Hisa Plangta Pipu 262183 8 0 2 524 East Kameng Papiwa Sullung Pipu 262184 9 0 2 525 East Kameng Lanka Seijosa 261896 7 0 2 526 East Kameng New Dissing Seijosa 261919 11 2 5 527 East Kameng Sangdu Seijosa 261925 12 2 5 528 East Kameng Lasum Pathe Seijosa 261926 12 2 5 529 East Kameng New Lasum Pathe Seijosa 261927 12 2 5 530 East Kameng Mebuwa - II SEPPA 262047 8 0 2 531 East Kameng Dari SEPPA 262029 9 0 2 532 East Siang Jate RAMLE BANGO 263828 7 0 2 533 Kurung Kumey Bodepu CHAMBANG 265514 6 0 2 534 Kurung Kumey Sangha CHAMBANG 265519 6 0 2 535 Kurung Kumey Lungchi CHAMBANG 265546 10 2 5 536 Kurung Kumey Tapaha CHAMBANG 265556 6 0 2 537 Kurung Kumey Yangte II CHAMBANG 265624 6 0 2 538 Kurung Kumey Mebia CHAMBANG 265625 6 0 2 539 Kurung Kumey Mipum-Namching CHAMBANG 265629 6 0 2 540 Kurung Kumey Tapa-Poring CHAMBANG 265633 6 0 2 541 Kurung Kumey Gangte (Gente) CHAMBANG 265648 6 1 3 542 Kurung Kumey Charbia CHAMBANG 265649 6 0 2 543 Kurung Kumey Takeng CHAMBANG 265531 7 0 2 544 Kurung Kumey Piriayer CHAMBANG 265552 7 0 2 545 Kurung Kumey Nama CHAMBANG 265640 7 0 2 546 Kurung Kumey Tatung-Koter CHAMBANG 265561 8 0 2 547 Kurung Kumey Tarha CHAMBANG 265563 8 0 2 548 Kurung Kumey Hidung Songo CHAMBANG 265564 8 0 2 549 Kurung Kumey Tabum CHAMBANG 265567 8 0 2 550 Kurung Kumey Pakung CHAMBANG 265593 8 0 2 551 Kurung Kumey Tabyer CHAMBANG 265621 8 0 2 552 Kurung Kumey Chimpigi CHAMBANG 265628 8 0 2 553 Kurung Kumey Tapaha CHAMBANG 265542 9 0 2 554 Kurung Kumey Tamak poring CHAMBANG 265591 9 0 2 555 Kurung Kumey Tumhaming CHAMBANG 265594 9 0 2 556 Kurung Kumey Raiga II CHAMBANG 265597 9 0 2 557 Kurung Kumey Mencha CHAMBANG 265600 9 0 2 558 Kurung Kumey Gongbing CHAMBANG 265601 9 0 2 559 Kurung Kumey Gai IV CHAMBANG 265617 9 0 2 560 Kurung Kumey Taliyer CHAMBANG 265618 9 0 2 561 Kurung Kumey Phoi CHAMBANG 265622 9 0 2 562 Kurung Kumey Harak CHAMBANG 265632 9 0 2 563 Kurung Kumey Lolcee CHAMBANG 265646 9 0 2 564 Kurung Kumey Raseng Hapa CHAMBANG 265503 10 2 5 565 Kurung Kumey Sanglo Putung CHAMBANG 265511 10 2 5 566 Kurung Kumey Payer CHAMBANG 265533 10 2 5 567 Kurung Kumey Kamrung-III CHAMBANG 265574 10 3 6 568 Kurung Kumey Lungchi CHAMBANG 265595 10 2 5 569 Kurung Kumey Taya Rimpa CHAMBANG 265599 10 2 5 570 Kurung Kumey Sango II CHAMBANG 265607 10 2 5 571 Kurung Kumey Bump-Hapa CHAMBANG 265631 10 3 6 572 Kurung Kumey Sangching Nyoriang CHAMBANG 265532 11 2 5 573 Kurung Kumey Kamrung II CHAMBANG 265538 11 3 6 574 Kurung Kumey Yeripu CHAMBANG 265540 11 2 5 575 Kurung Kumey Poksa CHAMBANG 265557 11 2 5 576 Kurung Kumey Haming CHAMBANG 265559 11 2 5 577 Kurung Kumey Pikte CHAMBANG 265634 11 2 5 578 Kurung Kumey Delinge CHAMBANG 265638 11 2 5 579 Kurung Kumey Delling CHAMBANG 265517 12 2 5 580 Kurung Kumey Harak II CHAMBANG 265545 12 2 5 581 Kurung Kumey Higio II CHAMBANG 265569 12 2 5 582 Kurung Kumey Rai II CHAMBANG 265603 12 2 5 583 Kurung Kumey Tagiaraha CHAMBANG 265612 12 2 5 584 Kurung Kumey Lengdi I CHAMBANG 265619 12 2 5 585 Kurung Kumey Tudh-Bath III CHAMBANG 265509 13 2 5 586 Kurung Kumey Tangtanpuring CHAMBANG 265516 13 2 5 587 Kurung Kumey Pukpe CHAMBANG 265583 13 2 5 588 Kurung Kumey Boa II CHAMBANG 265609 13 2 5 589 Kurung Kumey Bindo CHAMBANG 265620 13 2 5 590 Kurung Kumey Nyomi CHAMBANG 265523 14 2 6 591 Kurung Kumey Amprakpak CHAMBANG 265605 14 2 6 592 Kurung Kumey Phacha CHAMBANG 265610 14 2 6 593 Kurung Kumey Taniyatab CHAMBANG 265635 14 2 6 594 Kurung Kumey Dorduk (T-Tab ) CHAMBANG 265636 15 2 6 595 Kurung Kumey Restaring CHAMBANG 265650 15 2 6 596 Kurung Kumey Gachi CHAMBANG 265652 15 2 6 597 Kurung Kumey Kish NYAPIN 265368 6 0 2 598 Kurung Kumey Taya NYAPIN 265393 6 0 2 599 Kurung Kumey Langria NYAPIN 265400 6 0 2 600 Kurung Kumey Rayer Solung NYAPIN 265424 6 0 2 601 Kurung Kumey Rluguha NYAPIN 265407 7 0 2 602 Kurung Kumey Pinchi Solung NYAPIN 265422 7 0 2 603 Kurung Kumey Langdo NYAPIN 265359 8 0 2 604 Kurung Kumey Yorung NYAPIN 265415 8 0 2 605 Kurung Kumey Pach NYAPIN 265361 9 0 2 606 Kurung Kumey Sangripo NYAPIN 265398 9 0 2 607 Kurung Kumey Ralung NYAPIN 265425 11 2 5 608 Kurung Kumey Kaberiang NYAPIN 265358 14 2 6 609 Kurung Kumey Taris NYAPIN 265417 14 2 6 610 Kurung Kumey Tapone KOLORIANG 265455 6 0 2 611 Kurung Kumey Puriok KOLORIANG 265497 6 0 2 612 Kurung Kumey Kiodhriang KOLORIANG 265473 7 0 2 613 Kurung Kumey Nyobia KOLORIANG 265465 8 1 3 614 Kurung Kumey Degging II KOLORIANG 265483 8 0 2 615 Kurung Kumey Chinkongne Village KOLORIANG 265454 9 0 2 616 Kurung Kumey Ratell KOLORIANG 265487 9 0 2 617 Kurung Kumey Sulungyar KOLORIANG 265456 11 2 5 618 Kurung Kumey Pinging KOLORIANG 265461 11 2 5 619 Kurung Kumey Johat KOLORIANG 265468 11 2 5 620 Kurung Kumey Radang KOLORIANG 265460 12 3 6 621 Kurung Kumey Kokpu Nyoyer KOLORIANG 265471 13 2 5 622 Kurung Kumey Naji Bibok KOLORIANG 265472 14 2 6 623 Kurung Kumey Barta Camp PALIN 265270 6 0 2 624 Kurung Kumey Tagia PALIN 265279 6 0 2 625 Kurung Kumey Pajja PALIN 265204 7 0 2 626 Kurung Kumey Hinggo Happa PALIN 265221 8 0 2 627 Kurung Kumey Nidey Happa PALIN 265273 8 0 2 628 Kurung Kumey Rukso PALIN 265186 9 0 2 629 Kurung Kumey Kayekh PALIN 265173 10 2 5 630 Kurung Kumey Karko PALIN 265179 10 2 5 631 Kurung Kumey Koyer- Kamcho PALIN 265213 10 2 5 632 Kurung Kumey Geyo PALIN 265214 10 2 5 633 Kurung Kumey Hina PALIN 265253 10 2 5 634 Kurung Kumey Gyate PALIN 265196 11 2 5 635 Kurung Kumey Tamak PALIN 265209 11 2 5 636 Kurung Kumey Gopo PALIN 265215 11 2 5 637 Kurung Kumey Pungmi PALIN 265226 12 2 5 638 Kurung Kumey Bugdu PALIN 265193 13 3 6 639 Kurung Kumey Yerlo PALIN 265219 13 2 5 640 Kurung Kumey Tegdo PALIN 265222 13 2 5 641 Kurung Kumey Dumbu PALIN 265187 14 2 6 642 Kurung Kumey Gyachi PALIN 265260 15 3 7 643 Kurung Kumey Nisuk DAMIN 265820 6 0 2 644 Kurung Kumey Nayopuk DAMIN 265810 7 0 2 645 Kurung Kumey Yaso DAMIN 265784 8 0 2 646 Kurung Kumey Katuk DAMIN 265805 8 0 2 647 Kurung Kumey Chera DAMIN 265812 9 0 2 648 Kurung Kumey Sibia DAMIN 265795 10 2 5 649 Kurung Kumey Tikla DAMIN 265797 10 2 5 650 Kurung Kumey Pipa DAMIN 265801 10 2 5 651 Kurung Kumey Boruk DAMIN 265781 12 2 5 652 Kurung Kumey Chedam DAMIN 265829 13 2 5 653 Kurung Kumey Hirik DAMIN 265821 12 2 5 654 Kurung Kumey Hume DAMIN 265828 10 2 5 655 Kurung Kumey Kelong DAMIN 265824 23 2 8 656 Kurung Kumey Ruba DAMIN 265807 45 2 13 657 Kurung Kumey Terik DAMIN 265803 12 2 5 658 Kurung Kumey Subuk DAMIN 265822 12 2 5 659 Kurung Kumey Sara Sangram 265295 8 0 2 660 Kurung Kumey Kampong Sangram 265332 8 0 2 661 Kurung Kumey Tagum Sangram 265308 9 0 2 662 Kurung Kumey Kamha Hapa Sangram 265322 10 2 5 663 Kurung Kumey Rallang Sangram 265317 13 2 5 664 Kurung Kumey Kaglang Sangram 265283 14 2 6 665 Kurung Kumey Pirsepa Sangram 265309 14 2 6 666 Kurung Kumey Ningpopu Sangram 265325 15 2 6 667 Kurung Kumey Paching Sangram 265326 15 2 6 668 Kurung Kumey Nyori Sangram 265327 15 2 6 669 Kurung Kumey Tahuk Parsi Parlo 265775 9 0 2 670 Kurung Kumey Bigo Parsi Parlo 265725 13 2 5 671 Kurung Kumey Barbia Parsi Parlo 265744 13 2 5 672 Kurung Kumey Passik Parsi Parlo 265753 14 2 6 673 Kurung Kumey Solung Parsi Parlo 265729 15 2 6 674 Kurung Kumey Lamia Parsi Parlo 265770 13 4 7 675 Kurung Kumey Marmia Parsi Parlo 265736 13 4 7 676 Kurung Kumey Nyokuriang Parsi Parlo 265743 32 4 12 677 Kurung Kumey Raba Karsang Pipsorang 265833 19 2 7 678 Kurung Kumey Tedung Pipsorang 265831 39 4 14 679 Kurung Kumey Sepaha Pipsorang 265834 56 4 18 680 Kurung Kumey Korapu Pipsorang 265837 62 4 20 681 Kurung Kumey Koleng Pipsorang 265835 65 4 20 682 Kurung Kumey Longding Koling HQ Pipsorang 265830 157 4 43 683 Kurung Kumey New Sarli SARLI 265681 7 0 2 684 Kurung Kumey Kaney SARLI 265694 10 4 7 685 Kurung Kumey Lentso SARLI 265692 4 2 3 686 Kurung Kumey Bala SARLI 265704 3 2 3 687 Lohit Labeliang TEZU 266406 8 0 2 688 Lower Dibang Valley Cheyada Hunli-Kronli 266097 6 0 2 689 Lower Dibang Valley Ashini Hunli-Kronli 266108 7 0 2 690 Lower Dibang Valley Maruni Hunli-Kronli 266109 7 0 2 691 Lower Dibang Valley Enjani Hunli-Kronli 266111 7 0 2 692 Lower Dibang Valley Arondo Hunli-Kronli 266058 8 0 2 693 Lower Dibang Valley Anoro Hunli-Kronli 266064 8 0 2 694 Lower Dibang Valley Amonggo Hunli-Kronli 266102 8 0 2 695 Lower Dibang Valley Gango Hunli-Kronli 266107 8 0 2 696 Lower Dibang Valley Mihundo Hunli-Kronli 266130 8 1 3 697 Lower Dibang Valley New Pika Hunli-Kronli 266139 8 0 2 698 Lower Dibang Valley Androni (73 K.M.) Hunli-Kronli 266073 9 0 2 699 Lower Dibang Valley Michido Hunli-Kronli 266119 9 0 2 700 Lower Dibang Valley Pengo Hunli-Kronli 266124 9 0 2 701 Lower Dibang Valley Yanli Hunli-Kronli 266089 11 2 5 702 Lower Dibang Valley Chuyuni Model village Hunli-Kronli 266115 12 25 703 Lower Dibang Valley Boongo (65 KM) Hunli-Kronli 266074 27 2 9 704 Lower Dibang Valley Kapali Roing 266346 8 0 2 705 Lower Dibang Valley Thuango Roing 266347 12 2 5 706 Lower Dibang Valley Lemo Roing 266282 14 2 6 707 Lower Dibang Valley Ithun Roing 266286 14 2 6 708 Lower Dibang Valley Alambro Roing 266172 15 2 6 709 Lower Dibang Valley Elopa Roing 266267 15 2 6 710 Lower Dibang Valley Miuliati Roing 266279 15 2 6 711 Lower Subansiri Nill Poto Tamen-Raga 265019 6 0 2 712 Lower Subansiri Tokuso Rijo Tamen-Raga 265020 6 0 2 713 Lower Subansiri Kunde Tamen-Raga 265068 6 0 2 714 Lower Subansiri Byan Byap Tamen-Raga 265078 6 0 2 715 Lower Subansiri Pet-Milli Tamen-Raga 265128 6 0 2 716 Lower Subansiri Jop Hapa Tamen-Raga 265075 7 0 2 717 Lower Subansiri Mengi Kabak II Tamen-Raga 265077 7 0 2 718 Lower Subansiri Mid Putu Tamen-Raga 265081 7 0 2 719 Lower Subansiri Letkamt Tamen-Raga 265168 7 0 2 720 Lower Subansiri Leya Tamen-Raga 265028 8 1 3 721 Lower Subansiri Putu Tamen-Raga 265052 8 0 2 722 Lower Subansiri Boa Model Tamen-Raga 265103 8 0 2 723 Lower Subansiri Pakh Rijo Tamen-Raga 265021 9 0 2 724 Lower Subansiri Rugya Hapa Tamen-Raga 265087 9 0 2 725 Lower Subansiri Setha Pury Tamen-Raga 265064 12 2 5 726 Lower Subansiri Posa Tamen-Raga 265029 13 2 5 727 Lower Subansiri Onga Tamen-Raga 265107 14 2 6 728 Lower Subansiri Pelmilli Tamen-Raga 265129 15 2 6 729 Lower Subansiri Sihing ZIRO - I 264658 6 0 2 730 Lower Subansiri Tabung Byarang ZIRO - I 264702 6 0 2 731 Lower Subansiri Sisang ZIRO - I 264727 6 0 2 732 Lower Subansiri Tiba ZIRO - I 264624 7 0 2 733 Lower Subansiri Tayuga ZIRO - I 264627 7 0 2 734 Lower Subansiri Makung ZIRO - I 264654 7 0 2 735 Lower Subansiri Khahu ZIRO - I 264663 7 0 2 736 Lower Subansiri Khogyo ZIRO - I 264693 7 0 2 737 Lower Subansiri Puduwan ZIRO - I 264743 7 0 2 738 Lower Subansiri Gandi Ali ZIRO - I 264752 7 0 2 739 Lower Subansiri Diley ZIRO - I 264805 7 0 2 740 Lower Subansiri Dusa ZIRO - I 264606 8 0 2 741 Lower Subansiri Kontii ZIRO - I 264610 8 0 2 742 Lower Subansiri Myolyang ZIRO - I 264747 8 0 2 743 Lower Subansiri Myobya Hagya ZIRO - I 264768 8 0 2 744 Lower Subansiri Siro Ago ZIRO - I 264617 9 1 3 745 Lower Subansiri Moko ZIRO - I 264728 9 0 2 746 Lower Subansiri Gyachi ZIRO - I 264766 9 0 2 747 Lower Subansiri Tarutahe ZIRO - I 264615 10 2 5 748 Lower Subansiri Taho ZIRO - I 264668 10 2 5 749 Lower Subansiri Paro Lyapo ZIRO - I 264697 10 2 5 750 Lower Subansiri Shibu ZIRO - I 264800 10 2 5 751 Lower Subansiri Lyako ZIRO - I 264811 10 2 5 752 Lower Subansiri Myoli ZIRO - I 264816 10 2 5 753 Lower Subansiri Khachi ZIRO - I 264683 11 2 5 754 Lower Subansiri Katunyatu ZIRO - I 264694 11 2 5 755 Lower Subansiri Yashibo ZIRO - I 264767 11 2 5 756 Lower Subansiri Myodipu ZIRO - I 264815 12 2 5 757 Lower Subansiri Byabia ZIRO - I 264778 13 2 5 758 Lower Subansiri Pokhe Ayo ZIRO - I 264680 14 2 6 759 Lower Subansiri Takhu Sidhi ZIRO - I 264773 14 2 6 760 Lower Subansiri Kardo ZIRO - I 264802 14 2 6 761 Lower Subansiri Bakhani ZIRO - I 264662 15 2 6 762 Lower Subansiri Siikhebu ZIRO - I 264664 15 2 6 763 Lower Subansiri Dilang ZIRO - I 264794 15 2 6 764 Lower Subansiri Pyuchi ZIRO - I 264822 15 2 6 765 Lower Subansiri Kasing-Puttung ZIRO - II 264866 6 0 2 766 Lower Subansiri Thowu ZIRO - II 264913 7 0 2 767 Lower Subansiri Mompotu ZIRO - II 264868 8 0 2 768 Lower Subansiri Khompu ZIRO - II 264949 8 0 2 769 Lower Subansiri Mego ZIRO - II 264950 8 0 2 770 Lower Subansiri Taki Ko Happa ZIRO - II 264874 9 0 2 771 Lower Subansiri Jabli (Verma Point) ZIRO - II 264880 9 0 2 772 Lower Subansiri Tepin Happa ZIRO - II 264884 9 1 3 773 Lower Subansiri Peji Tabi ZIRO - II 264946 9 0 2 774 Lower Subansiri Nyllo ZIRO - II 264893 10 2 5 775 Lower Subansiri Komru ZIRO - II 264895 11 2 5 776 Lower Subansiri Trattabi ZIRO - II 264945 11 2 5 777 Lower Subansiri Proibrin Happa ZIRO - II 264876 12 2 5 778 Lower Subansiri Machin ZIRO - II 264894 12 2 5 779 Lower Subansiri Rewa Deli ZIRO - II 264947 12 2 5 780 Lower Subansiri Polin ZIRO - II 264845 13 2 5 781 Lower Subansiri Pekir Passa ZIRO - II 264892 13 2 5 782 Lower Subansiri Chun ZIRO - II 264839 15 2 6 783 Lower Subansiri Pogi Happa ZIRO - II 264906 15 2 6 784 Papum Pare Duda Namchang Doimukh 262347 7 0 2 785 Papum Pare Gungi SAGALEE 262573 6 0 2 786 Papum Pare Ngudang - I SAGALEE 262602 6 0 2 787 Papum Pare 47 K.M. Camp SAGALEE 262551 7 0 2 788 Papum Pare Hoj -II SAGALEE 262559 7 0 2 789 Papum Pare Muglang SAGALEE 262585 7 0 2 790 Papum Pare Sharik SAGALEE 262681 7 0 2 791 Papum Pare Bodak SAGALEE 262584 8 0 2 792 Papum Pare Rach - II SAGALEE 262591 8 0 2 793 Papum Pare Pare-Hapa SAGALEE 262682 8 0 2 794 Papum Pare Alw Tuda SAGALEE 262683 8 0 2 795 Papum Pare Cherso SAGALEE 262569 9 0 2 796 Papum Pare Nyoriso SAGALEE 262625 9 0 2 797 Papum Pare Tar SAGALEE 262626 9 0 2 798 Papum Pare Ligamtung Balijan 262395 6 0 2 799 Papum Pare Sindhu Patta Balijan 262305 7 0 2 800 Papum Pare New Bam Balijan 262391 7 0 2 801 Papum Pare Nyoing Balijan 262400 7 0 2 802 Papum Pare Kampung Reng Balijan 262422 7 0 2 803 Papum Pare Yadang - II Balijan 262383 8 0 2 804 Papum Pare Palap Balijan 262397 8 1 3 805 Papum Pare Ragia Balijan 262403 8 0 2 806 Papum Pare Diderso Balijan 262417 8 0 2 807 Papum Pare Bukka - II Kimin 262729 8 0 2 808 Papum Pare Borsetum Kimin 262756 8 1 3 809 Papum Pare Pacho Mengio 262710 9 0 2 810 Tawang Thespa Gonpa TAWANG 261508 15 2 6 811 Tawang Gyamo Zemithang-Dudunagar 261431 12 2 5 812 Tawang Rishorekharchen Mukto-Bongkhar 261594 15 2 6 813 Upper Siang Monge TUTING 263930 7 0 2 814 Upper Siang Monge TUTING 263954 7 0 2 815 Upper Siang Gome TUTING 263941 14 2 6 816 Upper Subansiri Cheging GIBA 263066 7 0 2 817 Upper Subansiri Jumbu Rage GIBA 263076 7 0 2 818 Upper Subansiri Roji GIBA 263008 8 0 2 819 Upper Subansiri Hamriga GIBA 263080 8 0 2 820 Upper Subansiri Machi- Rijo GIBA 263051 14 2 6 821 Upper Subansiri Makba GIBA 263018 10 2 5 822 Upper Subansiri Piya GIBA 263023 10 2 5 823 Upper Subansiri Hina GIBA 263037 18 2 7 824 Upper Subansiri Lokarijo GIBA 263082 10 2 5 825 Upper Subansiri Lingcha GIBA 263069 12 2 5 826 Upper Subansiri Dayam GIBA 263079 12 2 5 827 Upper Subansiri Dadi GIBA 263081 12 2 5 828 Upper Subansiri Puda GIBA 263010 13 2 5 829 Upper Subansiri Rapi GIBA 263070 13 2 5 830 Upper Subansiri Lokar Rijo GIBA 263085 13 2 5 831 Upper Subansiri Rago GIBA 263019 14 2 6 832 Upper Subansiri Rava GIBA 263020 14 2 6 833 Upper Subansiri Moya GIBA 263043 14 2 6 834 Upper Subansiri Lingking GIBA 263067 14 2 6 835 Upper Subansiri Thungba(Tungba) Limeking 262769 6 0 2 836 Upper Subansiri Yaja Limeking 262767 7 0 2 837 Upper Subansiri Taying Limeking 262771 7 0 2 838 Upper Subansiri Redding Camp Limeking 262792 7 0 2 839 Upper Subansiri Redding Limeking 262766 12 2 5 840 Upper Subansiri Orak III Limeking 262795 12 2 5 841 Upper Subansiri Reddy Limeking 262765 13 2 5 842 Upper Subansiri Orak II Limeking 262794 13 2 5 843 Upper Subansiri Ishneya (Isnia) II Limeking 262774 17 2 6 844 Upper Subansiri Kache Limeking 262768 20 2 7 845 Upper Subansiri Ishneya (Isnia) I Limeking 262773 20 4 9 846 Upper Subansiri Gumsing Limeking 262772 21 2 7 847 Upper Subansiri Ojugu Limeking 262775 21 2 7 848 Upper Subansiri Dojubung Limeking 262763 2 5 18 849 Upper Subansiri Dolering Limeking 262782 15 0 1 850 Upper Subansiri Lingbing Limeking 262770 19 2 6 851 Upper Subansiri Gelinceniak Camp Limeking 262790 1 2 7 852 Upper Subansiri Gelomo Camp (Golomoring) Limeking 262791 11 0 1 853 Upper Subansiri Taksing H.Q. Limeking 262776 52 2 5 854 Upper Subansiri Tidiegi PUCHI GEKO 263158 7 0 2 855 Upper Subansiri Gisa Putu PUCHI GEKO 263151 9 0 2 856 Upper Subansiri Pitak PUCHI GEKO 263162 9 0 2 857 Upper Subansiri Tompu Rijo DAPORIJO 263107 8 0 2 858 Upper Subansiri Shikrijo DAPORIJO 263116 8 0 2 859 Upper Subansiri Top-Rijo DAPORIJO 263111 7 0 2 860 Upper Subansiri Rite DAPORIJO 263132 13 2 5 861 Upper Subansiri Lebar DAPORIJO 263141 13 2 5 862 Upper Subansiri Pakdam DAPORIJO 263143 14 2 6 863 Upper Subansiri Paba Nacho 262818 15 2 6 864 Upper Subansiri Chokar Nacho 262817 15 2 6 865 Upper Subansiri Litenirin DUMPORIJO 263256 6 0 2 866 Upper Subansiri Yaipu DUMPORIJO 263251 11 2 5 867 Upper Subansiri Lebi DUMPORIJO 263224 12 2 5 868 Upper Subansiri Lenyi Annu DUMPORIJO 263244 14 2 6 869 Upper Subansiri Paja DUMPORIJO 263265 21 3 8 870 Upper Subansiri Bedarba TALIHA 262976 6 0 2 871 Upper Subansiri Bokjingboktemara TALIHA 262911 8 0 2 872 Upper Subansiri Lingri TALIHA 262939 9 0 2 873 Upper Subansiri Tainampomara TALIHA 262922 10 2 5 874 Upper Subansiri Abiajobe TALIHA 263000 12 2 5 875 Upper Subansiri Kagar TALIHA 262986 15 2 6 876 Upper Subansiri Bajor Repe BARIRIJO 263277 12 2 5 877 Upper Subansiri Laigi BARIRIJO 263285 30 2 10 878 Upper Subansiri Lebri BARIRIJO 263286 30 3 11 879 Upper Subansiri Riko BARIRIJO 263284 25 3 9 880 Upper Subansiri Dapo Siyum 262866 10 2 5 881 Upper Subansiri Pirong Siyum 262872 12 2 5 882 Upper Subansiri Kicherai Siyum 262881 36 2 11 883 West Kameng Sabang Nafra 261715 6 0 2 884 West Kameng Zomoje KALAKTANG 261796 88 2 24 885 West Kameng Kharumali KALAKTANG 261888 10 2 5 886 West Siang Komte Monigaon 263386 11 2 5 887 West Siang Changrang Monigaon 263362 8 0 2 888 West Siang Lusing Yingbe Monigaon 263354 9 0 2 889 West Siang Pongte Monigaon 263392 9 0 2 890 West Siang Saline Monigaon 263395 11 2 5 891 West Siang Damsong Monigaon 263368 14 2 6 892 West Siang Pangri Monigaon 263385 14 3 7 893 West Siang Singbu Monigaon 263390 14 2 6 894 West Siang Kamte LIKHABALI 263760 7 0 2 895 West Siang New Ngopi LIKHABALI 263755 10 3 6 Total Proposed Quantity 12193 986 4184

Note: However this list is tentative and bidder has to survey and verify the same.