Building One City for You James Oddo Annual Report Fiscal Year 2015

Bill de Blasio Dr. Feniosky Peña-Mora Mayor Commissioner Dear Borough President Oddo,

The capital projects on Staten Island help City thrive.

At DDC, we’ve made it a priority to listen to you, to understand your design and construction needs, and to deliver capital projects on Staten Island with a newfound sense of urgency. We understand that in order for to thrive, Staten Island must thrive as well.

I’m renewing our commitment to you and want to share our new values: urgency, responsiveness, service, collaboration, and mentorship. As leaders in design and construction management, it is our responsibility to provide innovative and cost-effective expertise for each one of the facilities we build for you. These values serve as the new foundation of our agency, and of all the work we do.

This is how we see our future on Staten Island with you – strong, sustainable, and transformative. It’s an exciting time to be changing our City, and we’re excited to be your partner in the transformation.

I would like to thank you for your continued commitment to New York City. We understand that great achievements are the result of great collaboration – all for the benefit of the communities we serve. My door at DDC is always open; please feel free to reach out with any ideas, questions, or concerns.

Sincerely,

Dr. Feniosky Peña-Mora Commissioner

2 New York City Department of Design and Construction Values Lenses

Our values guide the way we work. Our lenses provide perspective to what we do.

Urgency, responsiveness, service, collaboration, and mentorship—these values are at the Growth, sustainability, resiliency, equity, and healthy living—these are the lenses through core of how we approach our work at the Department of Design and Construction. As we which we look at our work. They help us bring to life the Mayor’s vision of a strong and deliver sustainable capital projects to every neighborhood in the city, our values ensure just city. From these perspectives, DDC projects and client agency programs provide that our buildings and sites are efficient, effective, and safe. From design decisions the places that accommodate a burgeoning population, the high efficiency systems and to client relations, our guiding values anchor our position as the preeminent municipal green roofs that protect our environment, the infrastructural innovation that safeguards design and construction agency in the United States. our shores, the buildings and sites that welcome all, and the spaces that improve our health and mental well-being.

Urgency Growth DDC goes above and beyond to exceed client goals and community expectations, DDC’s projects meet demographic needs by building infrastructure that enables working for the city that never sleeps. Whether it is a planned capital project or an growth. We build to meet the demands of the world’s most dynamic urban economy unexpected emergency, we act quickly, efficiently, and with unmatched urgency. with a focus on creating thriving communities.

Sustainability Responsiveness By 2050, NYC will reduce carbon emissions by 80% based on 2005 levels We respond quickly and whole-heartedly to the requests and concerns of all client and DDC is helping to make it happen. We use design elements, such as agencies and communities. Getting things done means staying ahead of the curve geothermal wells, green roofs, and solar technology to create sustainable projects and anticipating the needs of those who count on us. for future generations.

Service Resiliency At DDC, we proactively tackle problems, anticipating the changing needs of clients Superstorm Sandy demonstrated the vulnerability of New York City infrastructure and communities. We provide specialized, individual attention to every neighborhood and neighborhoods, particularly along the shorelines. DDC’s design and construction and agency, bringing empathy and caring to the capital project work we do together. projects enable communities to overcome devastation and emerge stronger than ever.

Collaboration Healthy Living DDC excellence is built on our working collaboration with our partner agencies, The stairways, step streets, and bike lanes that DDC builds help New Yorkers to be communities, elected officials, and design and construction professionals. We fit, active, and healthy. Our infrastructure and building projects use design to support healthy minds and healthy bodies. make it a priority to learn from each other, so that the expertise of one becomes the expertise of all. Equity More than just assuring the fair distribution of the many built assets that bring Mentorship communities together, we make it our priority to ensure that all our projects are At DDC, we value and promote new ideas and keep our processes open to the welcoming to the growing and diverse population of New York City. possibilities of change. We believe in the professional development of our staff and creating diverse opportunities for them to learn and grow.

3 New York City Department of Design and Construction 4 New York City Department of Design and Construction Public Buildings Infrastructure Project Locations Project Locations Project Schedule for Staten Island Project Schedule for Staten Island Projects in Design and/or Construction Projects in Design and/or Construction (Approximated by Quarter as of April 29, 2016)

Q3’14 Q4’14 Q1’15 Q2’15 Q3’15 Q4’15 Q1’16 Q2’16 Q3’16 Q3’14 Q4’14 Q1’15 Q2’15 Q3’15 Q4’15 Q1’16 Q2’16 Q3’16 HOLLIS-ROOF REPLACEMENT HOLLIS-ROOF REPLACEMENT

SUNNYSIDE LIBRARY ROOF SUNNYSIDE LIBRARY ROOF

ROOF REPLACEMENT-BAISLEY ROOF REPLACEMENT-BAISLEY

HVAC REPLACEMENT AT ROSEDALE HVAC REPLACEMENT AT ROSEDALE

ROOF REPLACEMENT AT LEFFERTS LIBRARY ROOF REPLACEMENT AT LEFFERTS LIBRARY

FOREST HILLS LIBRARY ROOF REPLACEMENT FOREST HILLS LIBRARY ROOF REPLACEMENT

ROOF REPLACEMENT-SOUTH JAMAICA ROOF REPLACEMENT-SOUTH JAMAICA

QUEENSBORO HILL ROOF QUEENSBORO HILL ROOF

RAVENSWOOD UNIVERSAL PRE-K RAVENSWOOD UNIVERSAL PRE-K

WHITESTONE-SELECTED MASONRY WHITESTONE-SELECTED MASONRY

EAST ELMHURST EXPANSION EAST ELMHURST EXPANSION

BRIARWOOD-ROOF REPLACEMENT BRIARWOOD-ROOF REPLACEMENT

WOODHAVEN-ROOF REPLACEMENT WOODHAVEN-ROOF REPLACEMENT

MCGOLDRICK-HVAC & CONTROLS MCGOLDRICK-HVAC & CONTROLS

QUEENS WEST HUNTERS POINT NEW BRANCH WEST HUNTERS POINT NEW BRANCH

ROCHDALE VILLAGE ROOF REPLACEMENT ROCHDALE VILLAGE ROOF REPLACEMENT

LONG ISLAND CITY LIBRARY-SECURITY LIGHTING LONG ISLAND CITY LIBRARY-SECURITY LIGHTING

LANGSTON HUGHES-MASONRY & WATERPROOFING LANGSTON HUGHES-MASONRY & WATERPROOFING

HVAC REPLACEMENT AT BAISLEY HVAC REPLACEMENT AT BAISLEY Jul’14 Jul’15 Jul’16 Jul’14 Jul’15 Jul’16 Oct’14 Oct’15 Oct’14 Oct’15 Apr’15 Apr’16 Apr’15 Apr’16 Jan’15 Jan’16 Jan’15 Jan’16

*On-hold projects *On-hold projects

Projected/Actual Projected/Actual

Design Design Procurement Procurement Construction Construction

7 New York City Department of Design and Construction 8 New York City Department of Design and Construction Project Schedule for Staten Island Project Schedule for Staten Island Projects in Design and/or Construction Projects in Design and/or Construction

Q3’14 Q4’14 Q1’15 Q2’15 Q3’15 Q4’15 Q1’16 Q2’16 Q3’16 Q3’14 Q4’14 Q1’15 Q2’15 Q3’15 Q4’15 Q1’16 Q2’16 Q3’16 HOLLIS-ROOF REPLACEMENT HOLLIS-ROOF REPLACEMENT

SUNNYSIDE LIBRARY ROOF SUNNYSIDE LIBRARY ROOF

ROOF REPLACEMENT-BAISLEY ROOF REPLACEMENT-BAISLEY

HVAC REPLACEMENT AT ROSEDALE HVAC REPLACEMENT AT ROSEDALE

ROOF REPLACEMENT AT LEFFERTS LIBRARY ROOF REPLACEMENT AT LEFFERTS LIBRARY

FOREST HILLS LIBRARY ROOF REPLACEMENT FOREST HILLS LIBRARY ROOF REPLACEMENT

ROOF REPLACEMENT-SOUTH JAMAICA ROOF REPLACEMENT-SOUTH JAMAICA

QUEENSBORO HILL ROOF QUEENSBORO HILL ROOF

RAVENSWOOD UNIVERSAL PRE-K RAVENSWOOD UNIVERSAL PRE-K

WHITESTONE-SELECTED MASONRY WHITESTONE-SELECTED MASONRY

EAST ELMHURST EXPANSION EAST ELMHURST EXPANSION

BRIARWOOD-ROOF REPLACEMENT BRIARWOOD-ROOF REPLACEMENT

WOODHAVEN-ROOF REPLACEMENT WOODHAVEN-ROOF REPLACEMENT

MCGOLDRICK-HVAC & CONTROLS MCGOLDRICK-HVAC & CONTROLS

QUEENS WEST HUNTERS POINT NEW BRANCH QUEENS WEST HUNTERS POINT NEW BRANCH

ROCHDALE VILLAGE ROOF REPLACEMENT ROCHDALE VILLAGE ROOF REPLACEMENT

LONG ISLAND CITY LIBRARY-SECURITY LIGHTING LONG ISLAND CITY LIBRARY-SECURITY LIGHTING

LANGSTON HUGHES-MASONRY & WATERPROOFING LANGSTON HUGHES-MASONRY & WATERPROOFING

HVAC REPLACEMENT AT BAISLEY HVAC REPLACEMENT AT BAISLEY Jul’14 Jul’15 Jul’16 Jul’14 Jul’15 Jul’16 Oct’14 Oct’15 Oct’14 Oct’15 Apr’15 Apr’16 Apr’15 Apr’16 Jan’15 Jan’16 Jan’15 Jan’16

*On-hold projects *On-hold projects

Projected/Actual Projected/Actual

Design Design Procurement Procurement Construction Construction

9 New York City Department of Design and Construction 10 New York City Department of Design and Construction Project Schedule for Staten Island Project Schedule for Staten Island Projects in Design and/or Construction Projects in Design and/or Construction

Q3’14 Q4’14 Q1’15 Q2’15 Q3’15 Q4’15 Q1’16 Q2’16 Q3’16 Q3’14 Q4’14 Q1’15 Q2’15 Q3’15 Q4’15 Q1’16 Q2’16 Q3’16 HOLLIS-ROOF REPLACEMENT HOLLIS-ROOF REPLACEMENT

SUNNYSIDE LIBRARY ROOF SUNNYSIDE LIBRARY ROOF

ROOF REPLACEMENT-BAISLEY ROOF REPLACEMENT-BAISLEY

HVAC REPLACEMENT AT ROSEDALE HVAC REPLACEMENT AT ROSEDALE

ROOF REPLACEMENT AT LEFFERTS LIBRARY ROOF REPLACEMENT AT LEFFERTS LIBRARY

FOREST HILLS LIBRARY ROOF REPLACEMENT FOREST HILLS LIBRARY ROOF REPLACEMENT

ROOF REPLACEMENT-SOUTH JAMAICA ROOF REPLACEMENT-SOUTH JAMAICA

QUEENSBORO HILL ROOF QUEENSBORO HILL ROOF

RAVENSWOOD UNIVERSAL PRE-K RAVENSWOOD UNIVERSAL PRE-K

WHITESTONE-SELECTED MASONRY WHITESTONE-SELECTED MASONRY

EAST ELMHURST EXPANSION EAST ELMHURST EXPANSION

BRIARWOOD-ROOF REPLACEMENT BRIARWOOD-ROOF REPLACEMENT

WOODHAVEN-ROOF REPLACEMENT WOODHAVEN-ROOF REPLACEMENT

MCGOLDRICK-HVAC & CONTROLS MCGOLDRICK-HVAC & CONTROLS

QUEENS WEST HUNTERS POINT NEW BRANCH QUEENS WEST HUNTERS POINT NEW BRANCH

ROCHDALE VILLAGE ROOF REPLACEMENT ROCHDALE VILLAGE ROOF REPLACEMENT

LONG ISLAND CITY LIBRARY-SECURITY LIGHTING LONG ISLAND CITY LIBRARY-SECURITY LIGHTING

LANGSTON HUGHES-MASONRY & WATERPROOFING LANGSTON HUGHES-MASONRY & WATERPROOFING

HVAC REPLACEMENT AT BAISLEY HVAC REPLACEMENT AT BAISLEY Jul’14 Jul’15 Jul’16 Jul’14 Jul’15 Jul’16 Oct’14 Oct’15 Oct’14 Oct’15 Apr’15 Apr’16 Apr’15 Apr’16 Jan’15 Jan’16 Jan’15 Jan’16

*On-hold projects *On-hold projects

Projected/Actual Projected/Actual

Design Design Procurement Procurement Construction Construction

11 New York City Department of Design and Construction 12 New York City Department of Design and Construction $100,000,000 50

Trending Data Staten Island Cost Data for Staten Island $100,000,000 Capital Dollars Spent* 40 Last 5 Projects (Competitively Bid, Substantially Completed) Numb e s

t $60,000,000 30 c $100,000,000 e ro j r

P o f f o P r ro j e c t

$40,000,000 20 s Numb e $100,000,000

$20,000,000 $18,694,878 10 $60,000,000 $13,485,798 $11,524,858 $11,039,414 $10,204,262 $8,851,355

118% 88% 88% 73% 82% 65% 49% 62% 15% 37% 12% 8% $0 0 $40,000,000 FY09 FY10 FY11 FY12 FY13 FY14

$20,000,000

$0

FY09 FY10 FY11 FY12 FY14

1 2 3 4 5 *Values include change order registrations for active projects, registered projects, and de-registered projects

1 RESURFACING - , , AND QUEENS 2 SAN & STM SEWERS IN RICHMOND VALLEY Sept Plan No. of Projs for Sept Plan Actual vs. Target No. Projs Percent 3 DISTRIBUTION WM EXTENSIONS / REPLACEMENTS, SI & BK 4 STORM SEWER EXT IN AMSTERDAM AVE Target Plan No. of Projs for Target Actual vs. Target $ Percent 5 OCEAN BREEZE ATHLETIC CENTER - STATEN ISLAND Actual No. of Projs for Actual Capital Dollars Spent

DDC Estimated Bid Amount Orig. Bid Amount vs. DDC Est. Bid Amount Original Bid Amount Orig. Awd-NMSC vs. Orig. Bid Amount Original Award-NMSC Final Award vs. Orig. Awd-NMSC Final Award

13 New York City Department of Design and Construction 14 New York City Department of Design and Construction Bid Data for Staten Island Project List (sorted by completion date) Last 5 Sealed Competitive Bid Results (winning bid may not result in awarding of contract)

NYPD OPS FIRE SUPPRESSION SYSTEM FOR NYPD LOCATIONS REMEDIATION OF PETROLEUM SITES MULTIPLE ADDRESSES MULTIPLE ADDRESSES Estimated Completion Date: Q3 2014 Estimated Completion Date: Q2 2015

$100,000,000 DOT DPR MULTI-SITE PEDESTRIAN SAFETY SANDY DAMAGE NEW PREFAB MODULAR UNITS MULTIPLE ADDRESSES MULTIPLE ADDRESSES Estimated Completion Date: Q3 2014 Estimated Completion Date: Q2 2015

$100,000,000 DCLA NYPL SHCC BLDG’S “F&G” INTERIOR RECONSTRUCTION & RENO AIR CONDITIONING UPGRADE 982 RICHMOND TERRACE, STATEN ISLAND, NY 10301 2550 VICTORY BOULEVARD, STATEN ISLAND, NY 10314 Estimated Completion Date: Q4 2014 Estimated Completion Date: Q4 2015

$60,000,000 FDNY NYPL FDNY’S FIVE COMMUNICATIONS OFFICES BOILER REPLACEMENT & ELEVATOR UPGRADE MULTIPLE ADDRESSES 10 CENTRAL AVENUE, STATEN ISLAND, NY 10301 Estimated Completion Date: Q4 2014 Estimated Completion Date: Q4 2015

$40,000,000 OPS DPR FUEL TANK REPLACEMENT OCEAN BREEZE ATHLETIC CENTER MULTIPLE ADDRESSES MASON AVENUE, STATEN ISLAND, NY 10305 Estimated Completion Date: Q4 2014 Estimated Completion Date: Q4 2015

DCLA DPR $20,000,000 SHCC: ENERGY CONSERVATION UPGRADES INDOOR HORSE RIDING ARENA 982 RICHMOND TERRACE, STATEN ISLAND, NY 10301 777 SEAVIEW AVENUE, STATEN ISLAND, NY 10305 Estimated Completion Date: Q1 2015 Estimated Completion Date: Q4 2015

NYPL DCAS $0 WEST NEW BRIGHTON EXTERIOR ENVELOPE & ENTRANCE S. I. FAMILY JUSTICE CENTER 976 CASTLETON AVENUE, STATEN ISLAND, NY 10310 126 STUYVESANT PLACE, STATEN ISLAND, NY 10301 FY09 FY10 FY11 FY12 FY14 Estimated Completion Date: Q1 2015 Estimated Completion Date: Q1 2016

DCLA DOT 1 2 3 4 5 SIIAS INTERIOR RECONS OF BLDG’S A&B AT SHCC CITYWIDE WHEN & WHERE - FEMA 982 RICHMOND TERRACE, STATEN ISLAND, NY 10301 MULTIPLE ADDRESSES Estimated Completion Date: Q2 2015 Estimated Completion Date: Q1 2016

1 CONSTRUCTION OF STORM AND SANITARY SEWERS AND APPURTENANCES IN MASON STREET, ETC. - STATEN ISLAND 2 RECONSTRUCTION OF SOUTH BEACH AREA STREETS (PHASE II)-BOROUGH OF STATEN ISLAND DCLA DEP Index3 (FEMAContract FUNDED) Description CONTRACT RESURFACING WITH 2’ ASPHALTICCntract CONCRTE Type WEARING COUSEProject AND Description INSTALLATION ST. GEORGE THEATER CAPITAL IMPROVEMENTS PHASE 1 REON AVENUE 1 OFCONSTRUCTION MISSING PEDESTRIAN OF STORM AND RAMPS, SANITARY ETC. SEWERS -PHASE AND 2B -CITYWIDEConstruction/Regular/Sewer/N/A STORM SEWER IN MASON STREET, SI 25 HYATT STREET, STATEN ISLAND, NY 10301 MULTIPLE ADDRESSES APPURTENANCES IN MASON STREET, ETC. - STATEN ISLAND 4 CONSTRUCTION OF SANITARY AND STORM SEWERS AND APPURTENANCES IN RAMBLE ROAD, Estimated Completion Date: Q2 2015 Estimated Completion Date: Q2 2016 2 ETC-BOROUGHRECONSTRUCTION OF OF STATEN SOUTH BEACHISLAND AREA STREETS (PHASE II)- Construction/Regular/Highways/ RECONSTRUCTION OF SOUTH BEACH 5 CONSTRUCTIONBOROUGH OF STATEN OF STORMISLAND AND SANITARY SEWERS AND WATERN/A MAINS AND APPURTENANCESAREA (SE-793) IN 3 MARKHAM(FEMA FUNDED) PLACE CONTRACT BET. JEWETT RESURFACING AVE & WARDWELL WITH 2' ASPHALTIC AVE, ETC.-BOROUGH Construction/Regular/Highways/ OF STATEN ISLANDRESURFACING PHASE 2B FEMA DCAS DEP CONCRTE WEARING COUSE AND INSTALLATION OF MISSING N/A FUNDED ELECTRICAL UPGRADE STORM & SANITARY SEWERS IN BERTRAM AVE PEDESTRIAN RAMPS, ETC. -PHASE 2B -CITYWIDE 10 RICHMOND TERRACE, STATEN ISLAND, NY 10301 MULTIPLE ADDRESSES 4 CONSTRUCTION OF SANITARY AND STORM SEWERS AND Construction/Regular/Sewer/N/A SANITARY & STRM SEWER IN RAMBLE APPURTENANCES IN RAMBLE ROAD, ETC-BOROUGH OF STATEN ROAD Estimated Completion Date: Q2 2015 Estimated Completion Date: Q2 2016 ISLAND 5 CONSTRUCTION OF STORM AND SANITARY SEWERS AND WATER Construction/Regular/Sewer/N/A STORM AND SANITARY SEWERS IN MAINS AND APPURTENANCES IN MARKHAM PLACE BET. JEWETT WARDWELL AVENUE, SI AVE & WARDWELL AVE, ETC.-BOROUGH OF STATEN ISLAND

DDC Estimated Bid Amount Orig. Bid Amount vs. DDC Est. Bid Amount Original Bid Amount Orig. Awd-NMSC vs. Orig. Bid Amount Original Award-NMSC Final Award vs. Orig. Awd-NMSC Final Award

15 New York City Department of Design and Construction 16 New York City Department of Design and Construction Project List Project List

DEP DPR DEP DOT WOODROW ROAD WILLOWBROOK POND MODIFICATIONS TWOMBLY AVE MILLING - BROOKLYN & STATEN ISLAND MULTIPLE ADDRESSES ETON PL, STATEN ISLAND, NY 10314 MULTIPLE ADDRESSES MULTIPLE ADDRESSES Estimated Completion Date: Q2 2016 Estimated Completion Date: Q3 2016 Estimated Completion Date: Q1 2017 Estimated Completion Date: Q2 2017

DEP DEP DEP DOT AMSTERDAM AVENUE DISTRIBUTION WATER MAINS XENIA STREET ETC AMBOY RD - HUGUENOT AVE AMSTERDAM AV, STATEN ISLAND, NY 10314 MULTIPLE ADDRESSES MULTIPLE ADDRESSES MULTIPLE ADDRESSES Estimated Completion Date: Q2 2016 Estimated Completion Date: Q4 2016 Estimated Completion Date: Q1 2017 Estimated Completion Date: Q2 2017

DEP DEP NYPL DOT SPRAGUE AVENUE JEWETT AVENUE STORM SEWER EXTENSION HUGUENOT PARK FIRE ALARM UPGRADE SOUTH AVE & FOREST AVE MULTIPLE ADDRESSES MULTIPLE ADDRESSES 830 HUGUENOT AVENUE, STATEN ISLAND, NY 10312 MULTIPLE ADDRESSES Estimated Completion Date: Q2 2016 Estimated Completion Date: Q4 2016 Estimated Completion Date: Q1 2017 Estimated Completion Date: Q2 2017

DEP DEP DCLA DOT TV INSPECTION AND CLEANING - CITYWIDE HARVEST AVE & CARY AVE SIIAS - BUILDING H CLIMATE CONTROL SANDY PHASE 2 RESURFACING (FEMA) MULTIPLE ADDRESSES MULTIPLE ADDRESSES 912 RICHMOND TERRACE, STATEN ISLAND, NY 10310 MULTIPLE ADDRESSES Estimated Completion Date: Q2 2016 Estimated Completion Date: Q4 2016 Estimated Completion Date: Q2 2017 Estimated Completion Date: Q2 2017

OPS NYPL DCLA DCAS CM DESIGN/BUILD DSNY STATEN ISLAND 1 GARAGE RICHMONDTOWN ELEVATOR UPGRADE HRT-CENTER ST. MUSEUM BLDGS UTILITY UPGRADES SOUTH SHORE BABE RUTH LEAGUE 539 JERSEY STREET, STATEN ISLAND, NY 10301 200 CLARKE AVENUE, STATEN ISLAND, NY 10306 395 CENTER STREET, STATEN ISLAND, NY 10306 PAGE AVENUE, STATEN ISLAND, NY 10307 Estimated Completion Date: Q2 2016 Estimated Completion Date: Q4 2016 Estimated Completion Date: Q2 2017 Estimated Completion Date: Q3 2017

NYPD NYPL DEP DCAS DESK REPLACEMENT CITYWIDE WEST NEW BRIGHTON FIRE ALARM UPGRADE NEW CREEK - BMPS AND 3 CULVERTS SOUTH SHORE LITTLE LEAGUE UPGRADE MULTIPLE ADDRESSES 976 CASTLETON AVE, STATEN ISLAND, NY 10310 MULTIPLE ADDRESSES 245 BEDELL AVENUE, STATEN ISLAND, NY 10307 Estimated Completion Date: Q2 2016 Estimated Completion Date: Q4 2016 Estimated Completion Date: Q2 2017 Estimated Completion Date: Q3 2017

DCLA OPS DEP DOT CARRIAGE BARN FACILITY IN RICHMONDTOWN CM DESIGN/BUILD PETROLEUM STORAGE TANKS STORM & SANITARY SEWERS IN SHELDON AVENUE BLOOMINGDALE PARK SIDEWALKS 145 ARTHUR KILL ROAD, STATEN ISLAND, NY 10306 MULTIPLE ADDRESSES MULTIPLE ADDRESSES DRUMGOOLE RD W, STATEN ISLAND, NY 10309 Estimated Completion Date: Q3 2016 Estimated Completion Date: Q4 2016 Estimated Completion Date: Q2 2017 Estimated Completion Date: Q3 2017

DEP DOT DEP DCLA STORM AND SANITARY SEWERS IN RICHARD AVE MILLING & RESURFACING - FEDERAL EARMARK GRANTWOOD AVE SIIAS - ROOF AND DORMERS RECONSTRUCTION MULTIPLE ADDRESSES MULTIPLE ADDRESSES MULTIPLE ADDRESSES 75 STUYVESANT PLACE, STATEN ISLAND, NY 10301 Estimated Completion Date: Q3 2016 Estimated Completion Date: Q4 2016 Estimated Completion Date: Q2 2017 Estimated Completion Date: Q4 2017

DEP DOT NYPL DCAS STORM & SANITARY SEWERS IN WARDS POINT AVE SCHOOL SAFETY PROGRAM 3 TODT HILL WESTERLEIGH ADA/RESTROOM UPGRADE DSNY - LIGHTING DEBUNDLING PROJECTS MULTIPLE ADDRESSES MULTIPLE ADDRESSES 2550 VICTORY BOULEVARD, STATEN ISLAND, NY 10314 MULTIPLE ADDRESSES Estimated Completion Date: Q3 2016 Estimated Completion Date: Q4 2016 Estimated Completion Date: Q2 2017 Estimated Completion Date: Q4 2017

NYPL DEP NYPL DCAS STAPLETON BRANCH LIBRARY - ROOF REPAIR OF INTERCEPTING SEWERS - BK & SI TOTTENVILLE BRANCH FIRE ALARMS BX CONC PLZA: BERGEN, HSG CT MARC JUDIC CTR 140 CANAL STREET, STATEN ISLAND, NY 10304 MULTIPLE ADDRESSES 7448 BRIGHTON STREET NY, STATEN ISLAND, NY 10307 MULTIPLE ADDRESSES Estimated Completion Date: Q3 2016 Estimated Completion Date: Q1 2017 Estimated Completion Date: Q2 2017 Estimated Completion Date: Q4 2017

17 New York City Department of Design and Construction 18 New York City Department of Design and Construction Project List

DCAS DOT QUEENS WEST CENT REPAIR SHOP: FR.KILLS, BK VICTORY BLVD & MANOR ROAD MULTIPLE ADDRESSES MULTIPLE ADDRESSES Estimated Completion Date: Q4 2017 Estimated Completion Date: Q4 2017

DCAS DCLA REMEDIATION OF PETROLEUM SITES BRITTON COTTAGE RESTORATION MULTIPLE ADDRESSES 395 CENTER STREET, STATEN ISLAND, NY 10306 Estimated Completion Date: Q4 2017 Estimated Completion Date: Q1 2018

DEP DCAS WARDWELL AVE ENERGY CONSERVATION AT SI BOROUGH HALL MULTIPLE ADDRESSES 10 RICHMOND TERR, STATEN ISLAND, NY 10301 Estimated Completion Date: Q4 2017 Estimated Completion Date: Q1 2018

DEP DEP BLOOMINGDALE ROAD - SEWERS INSTALLATION RICHMOND AVE MULTIPLE ADDRESSES MULTIPLE ADDRESSES Estimated Completion Date: Q4 2017 Estimated Completion Date: Q1 2018

DEP DCLA MASON STREET SI ZOO- AQUARIUM RECONSTRUCTION MULTIPLE ADDRESSES 650 BROADWAY, STATEN ISLAND, NY 10310 Estimated Completion Date: Q4 2017 Estimated Completion Date: Q2 2018

DEP DEP ST. JOSEPH AVE & DIXON AVE WATER MAINS IN CLOVE ROAD MULTIPLE ADDRESSES MULTIPLE ADDRESSES Estimated Completion Date: Q4 2017 Estimated Completion Date: Q2 2018

DEP DEP FORRESTAL CT ETC WILLOW AVENUE MULTIPLE ADDRESSES WILLOW AV, STATEN ISLAND, NY 10305 Estimated Completion Date: Q4 2017 Estimated Completion Date: Q2 2018

DOHMH DEP S. I. ANIMAL SHELTER - EXPANSION & RENOVATION PARK HILL COURT 3139 VETERANS ROAD WEST, STATEN ISLAND, NY 10309 MULTIPLE ADDRESSES “Urgency is a gut reaction–it is Estimated Completion Date: Q4 2017 Estimated Completion Date: Q2 2018 NYPD NYPL 120 PCT EXTERIOR FACADE RESTORATION NEW DORP FIRE ALARM UPGRADE 78 RICHMOND TERRACE, STATEN ISLAND, NY 10301 309 NEW DORP LANE, STATEN ISLAND, NY 10306 knowing my job, knowing the Estimated Completion Date: Q4 2017 Estimated Completion Date: Q2 2018

DOT DOT VICTORY BLVD & CLOVE RD MULTI SITE PEDESTRIAN SAFETY needs of the people I work with, VICTORY BOULEVARD, STATEN ISLAND, NY 10301 MULTIPLE ADDRESSES Estimated Completion Date: Q4 2017 Estimated Completion Date: Q2 2018 and going the extra mile now.”

Winnie Corton DDC Recruitment Coordinator, Human Resources

20 New York City Department of Design and Construction Project List Project List

DOT DOT NYPL DOT WOODROW ROAD BUS PAD CONTRACT - CITYWIDE EDENWALD LANDSCAPING AND EXTERIOR LIGHTING CIRCLE ROAD OFF TODT HILL RD WOODROW RD, STATEN ISLAND, NY 10309 MULTIPLE ADDRESSES MULTIPLE ADDRESSES MULTIPLE ADDRESSES Estimated Completion Date: Q2 2018 Estimated Completion Date: Q3 2018 Estimated Completion Date: Q1 2019 Estimated Completion Date: Q3 2019

DOT DOT NYPL DOT HYLAN BLVD SBS - BUS PADS AMBOY RD - ELTINGVILLE NEW DORP ROOF REPLACEMENT SOUTH BEACH AREA MULTIPLE ADDRESSES AMBOY RD, STATEN ISLAND, NY 10312 309 NEW DORP LANE, STATEN ISLAND, NY 10306 MULTIPLE ADDRESSES Estimated Completion Date: Q2 2018 Estimated Completion Date: Q3 2018 Estimated Completion Date: Q1 2019 Estimated Completion Date: Q3 2019

DEP DOT DOT DCLA NEW STORM & SANITARY SEWERS IN HUSSON ST TRAVIS AVENUE WIDENING SOUTH BEACH - FHWA GROUP 14 SNUG HARBOR CULT. CTR. SITE - WIDE ELECTRIC MULTIPLE ADDRESSES MULTIPLE ADDRESSES MULTIPLE ADDRESSES 1000 RICHMOND TERR, STATEN ISLAND, NY 10301 Estimated Completion Date: Q3 2018 Estimated Completion Date: Q3 2018 Estimated Completion Date: Q1 2019 Estimated Completion Date: Q4 2019

DEP DOT DOT NYPL RAMBLE ROAD B/T ADRIENNE PL AND DENT RD ARTHUR KILL ROAD AMBOY ROAD & PAGE AVENUE ST. GEORGE EXTERIOR & INTERIOR RENOVATION MULTIPLE ADDRESSES MULTIPLE ADDRESSES MULTIPLE ADDRESSES 10 CENTRAL AVENUE, STATEN ISLAND, NY 10301 Estimated Completion Date: Q3 2018 Estimated Completion Date: Q3 2018 Estimated Completion Date: Q1 2019 Estimated Completion Date: Q4 2019

DEP DOT DEP DEP NAUGHTON AVENUE HYLAN BLVD @ NEW DORP LANE TRAVIS AREA ROCKLAND AVENUE MULTIPLE ADDRESSES HYLAN BLVD, STATEN ISLAND, NY 10306 MULTIPLE ADDRESSES MULTIPLE ADDRESSES Estimated Completion Date: Q3 2018 Estimated Completion Date: Q3 2018 Estimated Completion Date: Q2 2019 Estimated Completion Date: Q1 2020

DEP DOT DEP DOT EAGAN AVE MIDLAND BEACH - FHWA GROUP 15 ACACIA AVE ROMA & HETT AVENUE MULTIPLE ADDRESSES MULTIPLE ADDRESSES MULTIPLE ADDRESSES MULTIPLE ADDRESSES Estimated Completion Date: Q3 2018 Estimated Completion Date: Q3 2018 Estimated Completion Date: Q2 2019 Estimated Completion Date: Q1 2020

DEP DOT DEP DOT WEST CASTOR PLACE STATEN ISLAND NON-WHEN & WHERE - FEMA HALPIN AVENUE WOODROW RD - ALEXANDER AVE TO AK RD MULTIPLE ADDRESSES MULTIPLE ADDRESSES MULTIPLE ADDRESSES MULTIPLE ADDRESSES Estimated Completion Date: Q3 2018 Estimated Completion Date: Q3 2018 Estimated Completion Date: Q3 2019 Estimated Completion Date: Q1 2020

DEP DEP DEP NYPL KATAN AVENUE CHESTER AVENUE NEW STORM SEWER EXTENSION IN TODT HILL ROAD CHARLESTON NEW LIBRARY MULTIPLE ADDRESSES MULTIPLE ADDRESSES MULTIPLE ADDRESSES MULTIPLE ADDRESSES Estimated Completion Date: Q3 2018 Estimated Completion Date: Q4 2018 Estimated Completion Date: Q3 2019 Estimated Completion Date: Q2 2020

NYPL DEP DOT DEP TOTTENVILLE ROOF REPLACEMENT ROBINSON AVE SCHOOL SAFETY - TIGER GRANT SNUG HARBOR AREA 7448 BRIGHTON STREET, STATEN ISLAND, NY 10307 MULTIPLE ADDRESSES MULTIPLE ADDRESSES MULTIPLE ADDRESSES Estimated Completion Date: Q3 2018 Estimated Completion Date: Q4 2018 Estimated Completion Date: Q3 2019 Estimated Completion Date: Q3 2020

NYPL NYPD DOT DEP RICHMONDTOWN ROOF REPLACEMENT ELECTRICAL SYSTEM AT 60TH PRECINCT TODT HILL ROAD BMP NC-16 + STORM AND SANITARY SEWERS 200 CLARKE AVENUE, STATEN ISLAND, NY 10306 MULTIPLE ADDRESSES MULTIPLE ADDRESSES MULTIPLE ADDRESSES Estimated Completion Date: Q3 2018 Estimated Completion Date: Q4 2018 Estimated Completion Date: Q3 2019 Estimated Completion Date: Q4 2020

21 New York City Department of Design and Construction 22 New York City Department of Design and Construction Project List

DCLA SHC CENTER MUSIC HALL, DRESSING AND ADA COMPLIANCE 1000 SNUG HARBOR ROAD, STATEN ISLAND, NY 10310 Estimated Completion Date: Q1 2021

DOT BLOOMINGDALE ROAD MULTIPLE ADDRESSES Estimated Completion Date: Q3 2022

“We are renewing the lives of the people we serve—helping our neighbors build back their communities, house by house, after devastation.”

Miguel Cedeno DDC Assistant Commissioner, Build it Back Program

23 New York City Department of Design and Construction Ocean Breeze Athletic Center New York City Department of Design and Construction 30-30 Thomson Avenue Long Island City, NY 11101 nyc.gov/ddc