Green Initiatives

1. Revival of water bodies is completed at station. 2. LED lighting has been provided at all Railway stations with a cost of ` 6.5 lakhs

Passenger Train Services

Details of New Trains/ Special Trains/ Provision of Stoppages/ Extension/Increase in frequency of Trains in the jurisdiction of Nellore Parliamentary constituency

New Trains Humsafar Express stoppage at Nellore and Nellore 1. Tr.No.16793/16794 Rameshwaram–Faizabad Parliamentary Constituency Express. 7. Tr . N o . 1 6 7 9 3 / 1 6 7 9 4 R a m e s w a r a m – 2. Tr.No.22841/22842 Santragachi – Chennai Faizabad–Rameswaram Weekly Express Shri Narendra Modi Express stoppage at Gudur Hon’ble Prime Minister 3. Tr.No.19603/19604 Ajmeer – Rameshwaram 8. Tr.No.17209/17210 Express Seshadri Express stoppage at 4. Tr.No.17237/17238 Nellore – Chennai Central 9. Tr.No.12389/12390 Chennai Egmore–Gaya RAIL DEVELOPMENTAL WORKS MEMU Express Express stoppage at Nellore Nellore Parliamentary Constituency Jurisdiction Running of Special trains Extension of Trains 1. Nellore to Ajmer 1 special train 1. T r . N o . 1 7 4 0 1 / 1 7 4 0 2 / 1 7 4 0 3 / 1 7 4 0 4 2. Gudur to Yesvantpur 1 special train . Machilipatnam/Narsapur– up to (Total 2 special Trains) D h a r m a v a r a m w i t h n e w T r . N o . South Central Railway serving 17245/17246/17247/17248 the entire state of Telangana, Provision of Stoppage 2. Tr.No. 12733/12734 Tirupati – Secunderabad major portion of Andhra up to Lingampalli 1. T r . N o . 2 2 7 0 8 / 2 2 7 0 7 T i r u p a t i – Pradesh and considerable Visakhapatnam–Tirupati Double Decker Tri‐ 3. Tr.No. 17487/17488 Tirupati – Visakhapatnam portion of Karnataka, Weekly Express stoppage at Nellore up to Kadapa Maharastra states and small SOUTH CENTRAL 2. Tr.No.22801/22802 Visakhapatnam– 4. Tr.No. 20889/20890 Howrah – up parts of Tamilnadu and Chennai–Visakhapatnam Weekly Express to Tirupati. Madhya Pradesh. RAILWAY stoppage at Nellore and Gudur The Rail developmental works 3. Tr.No.16864/16863 Mannargudi–Jodhpur in the jurisdiction of Nellore Weekly Express stoppage is given at Gudur Parliamentary constituency has and Nellore geared up its movement in the 4. Tr.No.22837/22838 Hatia–Ernakulam recent past. Continuous Humsafar Weekly Express stoppage at monitoring has been done for Nellore and Gudur bringing perceptible change in 5. Tr.No.22877/22878 Howrah–Ernakulam the prime areas such as Antyodaya Weekly Express stoppage at infrastructure, safety, security Nellore and Passenger amenities/ 6. Tr.No. 22833/ 22834 Bhubaneswar– facilities. Krishnarajapuram– Bhubaneswar Weekly ASSEMBLY SEGMENTS Road Over / Under Bridges With a view to strengthen Road Over Bridge estimated cost of `42.93 Crore is safety at Level Crossing 1. Construction of ROB at Kavali Yard in under progress gates and to avoid untoward lieu of LC No.158 with sanctioned cost 5. ROB in lieu of LC No.128 between of `34.79 Crore is under progress. Gudur – Vijayawada with an estimated Kandukur incidents and also to provide 2. ROB in lieu of LC No.113 between cost of `48.74 Crore is under progress seem less journey to road Vedayapalem‐Nellore with an 6. Proposed for ROB in lieu of LC No.107 Kavali traffic, The following Road estimated cost of `46.27 Crore is at Venkatachalam Yard with an U n d e r B r i d g e s a r e under progress estimated cost of Rs.50.00 Crore Atmakur constructed / proposed for 3. ROB in lieu of LC No.112 between Road Under Bridge construction at different Vedayapalem‐Nellore with an 1. All unmanned level crossings are estimated cost of `47.01 Crore is under eliminated in Nellore Jurisdiction Kovur stations under Nellore progress t h r o u g h C o n s t r u c t i o n o f Parliamentary constituency. 4. ROB in lieu of LC No.144 between RUB/LHS/Manning Nellore City Alluru Road – Bitragunta with an

Nellore Rural Safety – The First Priority Passenger Amenities

Udayagiri Provision of Passenger Amenities and facilities, and its improvements at Railway Stations is one of the most important aspect Railway Services.

Station Amenity Amount in ` Status RAIL DEVELOPMENTAL WORKS Srivenkateswarapalem Toilets 1 Lakh Constructed Nellore Parliamentary Constituency Jurisdiction Nellore, Vedayapalem PF Extension 1.81 crore Completed Bitragunta PF Extension 1.32 crore Proposed Safety is the priority on SCR, to ensure Vedayapalem Waiting Room 45 Lakhs Constructed safety of the Rail users, Foot over Nellore 3 Escalators 3 Cr Provided Infrastructural Development Bridges (FoBs) / Road under/ over Kavali Signages 1.10 Cr Proposed Bridges are constructed / proposed for 2 Stations Wi‐Fi facility 3 Lakhs Completed New Railway Lines construction at various stations/ Kavali 24 CCTVs 55 Lakhs Proposed locations in Narsapuram Parliamentary 1. A new Railway line between Piduguralla and Savalyapuram for a distance of 45 Kms of Nadikudi – Kavali Circulating Area 63 Lakhs Developed Constituency Jurisdiction. Srikalahasthi Section is under progress with cost of ` 333 crore Kavali 1 WVMs ‐‐‐ Provided Nellore 3 WVMs ‐‐‐ Provided 2. Proposed for construction of a new railway line between Savalyapuram– for a Construction of a Foot OVer Bridge at distacne of 264 Kms of Nadikudi–Srikalahasthi section with an estimated cost of ` 1953.60 crore Nellore South Railway Station is Nellore 4 ATVMs 3. Construction of Venkatachalam–Obulavaripalli section of Obulavaripalli – for a Completed with the cost of `50 lakhs Kavali 2 ATVMs 10.5 Lakhs Installed distance of 92.73 Kms with an estimated cost of ` 956.04 crore is completed and commissioned. Vedayapalem ATVM Nellore CoTVM 4.5 Lakhs Installed 4. Proposed for construction of Gudur–Durgarajapatnam for a distance of 42 Kms with an estimated Kavali CIB & TIB 1.09 Crore In progress cost of ` 761.37 crore. Nellore Improved Illumination Provided Tripling Railway Lines Tada Toilets 11 Lakhs In Progress 1. Proposed for Tripling of Vijayawada–Gudur for the distance of 288 Kms with an estimated cost of Krishnapatnam Port PF Extension 4.04 crores Proposed `3246.26 crore. Krishnapatnam Port PF Shelter 4.02 crores Proposed Krishnapatnam Port Station Building 1.62 crores Proposed Capacity Enhancement Nellore 3 Lifts 1.5 crores Provided

1. As a part of yard remodeling , Improvements to loading facility at Kondagunta Station is completed with the cost of `30 Lakhs. 2. Provision of Additional platform between road No.4 to 7 at Gudur Junction is completed with the cost of `10.68 crore 3. Longer loop provision at Bitragunta is under progress in Vijayawada – Gudur (295 km) section with the cost of `10.00 crore