Signed:-

At,

John

For

Poultry Statement Poultry

Relating

Environ

Maghernacaldry,

Joe

087-2924047

Bsc.(Hons)Eng.,

Sheridan

John

Beggan

--<\•~

Sheridan

Units

Unit

To

A.

Eng.

-Proposed

.

mental

the

MIEI,

and

For inspection purposes only.

Cootehill, C.Build.E, Consent of copyright owner required for any other use.

Construction

Poultry

the

MCIOB

Unit

Extension

at Co.

Maghernacaldry

Impact

Cavan

of

Td.,

of

1

Cootehill,

New

2

08/11/16

Existing

Co. EPA Export 29-06-2017:03:06:18

1 John Sheridan -Proposed Poultry Unit at Maghernacaldry Td., Cootehill, Co.Cavan

Table of Contents 1.0 INTRODUCTION & PREAMBLE ...... 6

1.1 IDENTIFICATION OF LIKELY SIGNIFICANT IMPACTS ...... 6

2.0 NON-TECHNICAL SUMMARY ...... _...... _ ...... 7

3.0 ALTERNATIVE CONSIDERATIONS ...... 8

3.1 Alternatives explored during the Design Process ...... 8

3.2 Alternative location of site ...... 8

3.3 Alternative activities/ processes ...... 8

3.4 Final design choice ...... 9

3.5 Difficulties encountered in compiling the required information: ...... 9

3.6 Potential Impacts of the Proposed Scheme ...... 9

3.7 Construction Impacts ...... 10

3.7.1 Mitigation ...... 10

3.7.2 MONITORING ...... 11

3.8 Construction ...... 11

3.9 Residual Impacts ...... 11

4.0 SITE LOCATION ...... 11

5.0 SITE LAYOUT ...... For...... inspection. purposes...... only...... 12 Consent of copyright owner required for any other use.

6.0 PLANNING CONSIDERATIONS ...... 12

6.1 Planning Justification ...... 12

7.0 CONSTRUCTION DETAILS ...... 13

8.0 OPERATIONAL DETAILS ...... 14

8.1 Introduction ...... - ...... 14

8.2 Batch Cycle/House Depopulation details: ...... 14

8.3 House Details: ...... 14

8.4 Feeding and Drinking: ...... 14

8.5 Ventilation: ...... 15

8.6 Controls: ...... 15

2

EPA Export 29-06-2017:03:06:18 John Sheridan -Proposed Poultry Unit at Maghernacaldry Td., Cootehill, Co.Cavan

8.7 Records: ...... 15

9.0 Human Beings ...... 15

9.1 Introduction ...... lS

9.2 Development Impact On Human Beings ...... 16

9.3 Mitigation ...... 16

9.4 Conclusion ...... 16

10.0 EM MISSIONS TO ATMOSPHERE ...... 16

10.1 Dust: ...... 16

10.2 Odour: ...... 17

11.0 FLORA AND FAUNA ...... 17

11.1 Introduction ...... 17

11.2 Rodent Control Programme: ...... 18

12.0 ARCHAEOLOGY...... 18

13.0 NOISE EMISSIONS...... 18

13.1 Construction Noise: ...... 18

13.2 Operational Noise: ...... 19

13.3 Summary Of Potential Interaction/ Inter Relationships ...... 19

13.4 Operational Noise: ...... -...... For inspection purposes only...... 22 Consent of copyright owner required for any other use.

13.4.1 Existing Sources of Air Emissions ...... 22

13.4.2 IM PACTS...... 23

13.4.2 ...... ·-· ...... 23

13.4.3 MITIGATION MEASURES - Dusting ...... 23

13.4.4 Odour ...... 23

14.0 DISEASE CONTROL ...... 24

15.0 WASTE MANAGMENT ...... 25

15.1 Introduction ...... 25

15.2 Avoidance, Remedial or Reductive Measures ...... 25

15.3 Waste Management & Minimisation ...... 26

3

EPA Export 29-06-2017:03:06:18 22.0

23.0

20.0

21.0

19.0

18.0

17.0

16

23.2

23

18.4 18

18 18 17.3 17.1 16.4 17

16.3 16

16.2

.

15.10 15.9

15.8

15

15.6

15.5

0

TRANSBOUNDARY

TRAFFIC

Forecasting .

CLIMATE LANDSCAPE

MATERIAL

SOIL

.

. .

. WATER

.

15.9.1

.

1 3

2

2 1

1

7

Operational

Conclusion

Operation Introduction Conclusion Construction Introduction Conclusion Geological

Impacts Introduction

Decomm Spent

Pollutants

Operational Dead

Conclusion

Transport

Land

John

.

.

.

..

CONSTRUCTION

..

..

Stock

.

..

Poultry

......

...

....

Sheridan

and

ASSETS

and

.

..

....

i

...

&

ssioning

......

..

.

.

and

. setting

......

...

. . .

.

...

......

..

...... Mitigation

......

Soil

......

...

Phase

Network

phase

Remedial

...

... .

.

....

phase

.

.

......

.

. .

Litter

..

. . .

...

Waste

...

... . .

..

.

......

.....

...

.

IMPACTS

.

......

...

-Proposed

......

.

......

...

. .

......

..

......

.

......

......

...

.

. .

.

......

.. ...

.....

...

.

.

....

.

.....

.

......

.

.

.

......

..

....

. .

.

.....

..

IMPACTS

.

.

......

......

.

.

.

......

.. .

......

.

..

.

. actions .. ..

.

......

..

...

..

.. .

......

......

.

..

.

.

......

.

......

. ...

.. ..

......

......

.

. ...

For inspection purposes only. .

.

.

......

. .

.. .

.

... . .

.. .

..

......

.

.

. Consent of copyright owner required for any other use. ..

......

. .

.

......

..

......

.

.

.

..

.

. ... .

......

...... Poultry

......

.. .

....

......

.

.

.

. ....

......

....

.. ..

......

......

......

..

.

.

AND

.

. .

....

......

.

.

. .

......

.

.

..

......

..

...

.

.

......

..

.

... .

..

......

.

. .. .

..

......

.. .

.

......

......

......

......

.

......

......

..

.

MITIGATION

......

.

......

Unit

......

. ...

..

..

... ..

. ..

..

...

..

......

. .. ..

....

......

......

......

.. . .

..

.

......

.

.

.

....

......

......

.. ..

.

..

.' .

...

. .. . .

.

......

..

at

...

..

......

..

......

. . .

.... .

..

......

.

...

......

......

.

Maghernacaldry

......

...

.

...

......

....

. .

.. . .

......

.

.

..

......

.

......

......

.

......

......

.

.. . ..

. .

......

... ..

.

...

. . . . .

......

.

. ...

.

......

Impacts

......

...

.

.. ,

..

.

......

..

....

..

.. . ..

. .

.

......

......

......

......

......

. . . . .

.

..

......

.

.

. .

.

.

.

......

...

......

.

.

......

......

......

......

......

......

. .

......

. ... .

. ....

......

.. ...

.. . . .

..

......

:- ... .

. . ...

......

.

.

......

......

......

......

Td.,

......

...

..

.

......

.

......

......

.

..

......

......

..

......

.

......

Cootehill,

......

......

.

......

......

...... , . .

......

.....

......

......

.. .

......

.

.

. . . .

...

......

......

. .

......

...... ,

.

......

......

. ..

.. .

.

......

.

......

......

.

......

......

. ..

. . ,

......

.. Co.Cavan ......

..

....

......

......

......

.

......

......

...

......

......

......

......

..

.

. .

......

......

.

. ..

.. .

......

.. .

......

.

......

......

.....

......

. . .

.

...... , ......

..

......

.

......

. .. .

......

......

. EPA Export 29-06-2017:03:06:18

..

......

..

......

......

...

......

.

.

......

..

....

......

......

...

. ...

......

.

.

......

.

..

.

......

.

......

......

.

.

30 30 28 30 28 32 30 30 27 30 31 33 32 27 33 29 31 26 33 29 33 32 28 26 32 29 27 26

4 John Sheridan -Proposed Poultry Unit at Maghernacaldry Td., Cootehill, Co.Cavan

23.3 Economic Minerals ...... 33

23.4 Construction of the poultry House ...... 33

23.5 Raw material inputs for increased poultry production capacity ...... 33

23.6 RESIDUAL IMPACTS ...... 33

23.7 Difficulties Encountered While Compiling Report ...... 34

24.0 CONCLUSION OF REPORT...... 34

For inspection purposes only. Consent of copyright owner required for any other use.

5

EPA Export 29-06-2017:03:06:18 John Sheridan -Proposed Poultry Unit at Maghernacaldry Td., Cootehill, Co.Cavan

1.0 INTRODUCTION & PREAMBLE

The applicant, John Sheridan, Contacted Joe Beggan, Bsc (Hons) Eng., A. Eng., MIEI, MCIOB, CABE, SCSI to carry out an Environmental Impact Statement (EIS) in relation to construct one new poultry units at Maghernacaldry, Cootehill, Co. Cavan and extend the two existing poultry untis with the following stocking capacities • 1 New Unit With Maximum Of 37,400 Birds • House No. 1 will increase stocking capacity from 18,800 birds to 32,050 birds (13,250 Increase) • House No. 2 will increase stocking capacity from 20,900 birds to 35,250 birds (14,350 Increase) Total Stocking Capacity to be 104,700 Broilers The proposed development will be located c. 20.0 km North East of the county town of Cavan and 12.0km North West of the town of . The proposed development will be on a brown field site. John Sheridan has substantial experience in the poultry industry. Mr. John Sheridan, has been directly involved in the poultry industry for most of his adult life.

Having reviewed the terms of reference regarding the application, the consultant undertook a study of the impacts both real and perceived, which the proposal would have on the receiving environs and community. The areas, which were reviewed, include all areas, which an Environmental Impact Statement is required to cover. The applicant is obliged to have an EIS carried under the following regulations:

1) EC (Environmental Impact Assessment) Regulations 1989: Article 24, 1st Schedule, Part II 1. (d) "Poultry rearing installations where the capacity would exceed 100,000 units, where units have For inspection purposes only. the following equivalents: 1 broilerConsent = of 1copyright unit, owner1 layer, required turkey for any or other other use. fowl = 2 units".

• Planning and development Regulations 2001 (S.I. No. 600 of 2001). These regulations state that even if the development is under the relevant EIA threshold ( i.e 100k places), the planning authority is required under article 103 to request an EIS where it considers that the proposed development is likely to have significant environmental effects. • Section 17: An EIS is required for "installations for the intensive rearing of poultry or pigs with more than: (a) 85,000 places for broilers, 60,000 places for hens".

1.1 IDENTIFICATION OF LIKELYSIGNIFICANT IMPACTS

Schedule 6 of the Planning and Development Regulations requires that the EIS describes likely, direct and indirect significant impacts of a proposed scheme. The EPA (Guidelines on the information to be contained in Environmental Impact Statement 2002) defines an impact as "the degree of change in an environment resulting from a development" and goes on to elaborate on

6

EPA Export 29-06-2017:03:06:18 John Sheridan -Proposed Poultry Unit at Maghernacaldry Td., Cootehill, Co.Cavan

impacts in terms of quality (positive, neutral or negative), significance (imperceptible, slight, moderate, significant or profound), duration (temporary, permanent, short-term or long-term) and type (cumulative, indeterminable, irreversible, residual, synergistic or "worse case")

The following factors have been considered for this EIS when determining the significance of the impacts, both positive and negative, of the proposed scheme on the various aspects of the receiving environment:-

• The quality and sensitivity of the existing/baseline receiving environment.

• The relative importance of the environment in terms of national, regional, or local importance.

2.0 NON-TECHNICAL SUMMARY Cavan County Council Planning Authority requires that an Environmental Impact Statement be submitted in support any poultry development where the capacity on site will exceed 40,000 birds. The area is a predominantly rural farmland and the proposed bird density will be for 104,700 birds. The proposed poultry units are to be located approximately 53.0m South of nearest dwelling house, which belongs to the applicants sister. The development will be accessed by an existing agricultural entrance which connects to a local secondary road. The Applicants fathers family dwelling is located 37.0m west of the existing poultry units. The proposed new poultry unit will be insulated steel frame construction set on a concrete wall and foundation, and would have a stocking capacity of approximately 37,400 broilers. The units to be extended will be traditional timber frame construction. The operation, as with the existing complex, For inspection purposes only. would involve the rearing of chickensConsent from of copyright day-olds owner required over for a any period other use. of approximately 7 weeks, the exact duration depending on market requirements. Chickens will be supplied and collected at the cycle end by Carton Group. Feed will be supplied Kolbe Feeds. Dead birds will be collected by Michael Galligan, Gortnaleck, Co. Monaghan.

The floor will be litter-based, with wood shavings supplied by directly by the applicant. Spent litter, containing poultry manure, will be collected at the end of each batch cycle by Eamon Fitspatrick, Clonavilla, Clones, Co. Monaghan for tillage use. (Refer to letters in Appendix 2).

It is proposed that a Gas powered indirect heating system will be supplied to the unit, and a mechanical ventilation system installed. Two new waste water (washings) tanks will be provided on site to serve this development with a capacity of approximately 2,500 Gallons (11.36 m3) each. The nearest habitable dwelling 53.0 North of the proposed development.

7

EPA Export 29-06-2017:03:06:18

3.3 3.3

With With

transport transport

electrical electrical

infrastructure infrastructure

remedial remedial

this this

project project

3.2 3.2

and and

employed employed

3.1 3.1

3.0 3.0

The The

A A

in in • •

• •

• •

Alternative Alternative

• •

• •

• •

• •

• •

• •

Alternative Alternative

• •

• •

The The

site. site.

based based

this this

ALTERNATIVE ALTERNATIVE

review review

Alternatives Alternatives

the the

The The

supplier, supplier,

how how

The The

The The

The The

cost cost

The The

environmental environmental

designed designed

Existing Existing

An An

for for

Resources Resources

The The

developer developer

The The

should should

No No

proposed proposed

Conditions Conditions

in in

infrastructure infrastructure

Acquiring Acquiring

applicant applicant

new new

John John

route route

works. works.

in in

on on

existing existing

use use

significant significant

mind, mind,

site site

site site

nature nature

EPA's EPA's

area area

the the

prohibitive. prohibitive.

manufacturers manufacturers

house house

of of

the the

is is

knowledge knowledge

development development

Sheridan Sheridan

have have

as as

all all

drainage drainage

readily readily

is is

chosen chosen

business business

through through

Bord Bord

activities/ activities/

industry industry

the the to

has has

location location

the the

BATNEEC BATNEEC

lined lined

house house

substantially substantially

Furthermore, Furthermore,

available available

has has

other other

type type

agricultural agricultural

of of

for for

chose chose

alternative alternative

explored explored

ample ample

no no

applicant applicant

Bia Bia

the the

problems problems

disruption. disruption.

the the

no no

would would

available. available.

carcass carcass

highest highest

is is

Other Other

is is

signs signs

-Proposed -Proposed

lands lands

type. type.

CONSIDERATIONS CONSIDERATIONS

system system

and and

operates operates

provided provided

these these

at at

close close

operation operation

reason reason this this

found found

birds. birds.

of of

of of

land land

at at

for for

Guidance Guidance

present. present.

processes processes

the the

site. site.

also also

the the

of of

site. site.

during during

lands lands

in in

lands lands

entrance entrance

typical typical

level level

chose chose

the the

disposal disposal

specification specification

proximity proximity

of of lands lands

space space For inspection purposes only.

to to

over over

capable capable

construction construction

the the

Coupled Coupled

to to Department Department

Consent of copyright owner required for any other use. house

operation operation

have have

by by

as as following following

be be

Poultry Poultry

and and

is is

explored explored

employ employ

was was

The The

ownership ownership

this this

there there

poultry poultry

development development

Note Note

the the

satisfactory satisfactory

type type

in in

for for

such such

to to

sites sites

onto onto

are are

requires requires

the the

of of

the the to

ruled ruled

reasons reasons

site site

with with

be be

meal, meal,

Design Design

for for

Unit Unit facilitating facilitating

is is

of of

that that

constantly constantly

in in

have have

alternative alternative

reasons: reasons:

vicinity vicinity

farmers farmers

in in

public public

were were

extended extended

for for

required required

of of

the the

terms terms

costs costs

this, this,

housing housing

out out

the the

applicants applicants

of of

at at

Agriculture. Agriculture.

there there

the the

birds birds

minimal minimal

been been

as as

as as

Poultry Poultry

the the

Maghernacaldry Maghernacaldry

Process Process

either either

of of

event event

as as

road road

operational operational

of of

to to

of of

regards regards

following following

in in

would would

undulating undulating

the the

the the

applicant applicant

adherence adherence

working working

his his

is is

encountered encountered

and and

energy energy

why why

via via

the the

operational operational

employed employed

can can

from from

little little

of of

excavation excavation

Sector Sector

development. development.

poultry poultry

residence residence

additional additional

a a

greater greater

a a

litter litter

no no

be be

increase increase day day

bespoke bespoke

disease disease

alternative alternative

reasons reasons

a a

efficiency efficiency

to to

costs costs

alternative alternative

utilised. utilised.

was was

domestic domestic

advises advises

profile profile

to to

to to

complex complex

ensure ensure

would would

as as

area: area:

Td

procedures procedures

day day

in in

guidelines guidelines

works. works.

undertaken undertaken

costs costs

would would

outbreak. outbreak.

it it

line line

.

......

the the

, ,

as as

Cootehill, Cootehill,

running running

and and

is is

that that

and and

have have

their their

to to

or or

to to

running running

was was

to to

no no

imposed imposed

the the

increase increase

the the

would would

agricultural agricultural

serve serve

. .

minimal minimal

the the

be be

.. ..

housing housing

access access

to to

provided provided

chosen chosen

than than

most most

and and

available available

process process

prior prior

developer developer

Co

be be

of of

the the

require require

would would

.

those those

its its

when when

Cavan Cavan

the the

modern modern

provided. provided.

to to

is is

are are

development. development.

to to

by by

perspective. perspective.

in in

selection selection

as as

forming forming

the the

proposed proposed

make make

extensive extensive

the the terms terms

EPA Export 29-06-2017:03:06:18

follows follows

design design

flock flock

road road

The The

the the

of of

of of

8 8 a a John Sheridan -Proposed Poultry Unit at Maghernacaldry Td., Cootehill, Co.Cavan

3.4 Final design choice It was decided to construct the new development to the proposed design for the following reasons: • Thermal efficiency / Running costs • Appearance / profile in the landscape • Economical efficiency • Environmental efficiency • Lack of alternatives available • Requires less energy to heat [Metal v Wooden structure] • No significant problems known with this type of unit.

Furthermore, the applicant is proposing the operational procedures for the following reasons: • Existing farmland holding • Environmental efficiency • Lack of alternatives available

3.5 Difficulties encountered in compiling the required information: The process and activities associated with developments of this nature are well established and understood. Examination was undertaken of all elements of the development such as site selection & integration, building type and style, waste disposal, vehicular access and impacts. No significant difficulties were encountered in compiling the required information.

3.6 Potential Impacts of the Proposed Scheme The magnitude of the impacts outlined in the chapters which follow, take into account the guidelines given by the EPA and those scales used in other EIS documents for significant For inspection purposes only. Consent of copyright owner required for any other use. developments in this country. A broad outline of the scale of impacts is given in the table below. Where mitigation in the form of design measures have been suggested throughout the evolution of the EIS, these have been incorporated into the scheme design as far as is possible from an engineering perspective.

General Criteria used to quantify the Potential Impacts of the Proposed Scheme; Degree of Definition of Impact Impact/Significance level

Profound !Significant IAn impact, which obliterates sensitive characterisation Impact

Major An impact, which by its character, magnitude, duration or intensity alters a sensitive aspect of the environment. Moderate An impact that alters the character of the environment in a manner hat is consistent with existing and emerging trends

9

EPA Export 29-06-2017:03:06:18 John Sheridan -Proposed Poultry Unit at Maghernacaldry Td., Cootehill, Co.Cavan

Slight IAn impact, which causes noticeable changes in the character of the ienvironment without affecting its sensitivities

Not significant Neutral or IAn impact which does not change the quality of the environment is imperceptible capable of being measured but without noticeable consequences and Impact causes changes in the character of the environment which are not significant or profound

It is anticipated that following the construction of the proposed development, there will be no significant impact in an overall landscape context. The continued management of the hedgerows and the maintenance of the poultry houses will not have significant impact in terms of landscape and visual impact.

3.7 Construction Impacts Construction activities e.g. excavations, earth moving etc. may generate quantities of construction dust, particularly in drier weather conditions. The extent of any construction dust generation depends on the nature of the construction dust (soils, sands, gravels, silts etc.) and the construction activity. The potential for construction dust dispersion depends on the local meteorological facts such as rainfall, wind speed and wind direction. The issue of construction dust dispersion may be exaggerated with vehicles transporting sand/gravels/soils etc. to and from the site having the potential to cause an environmental nuisance. The effect of construction activities on air quality, in particular construction dust, will not be significant following the implementation of the proposed mitigation measures outlined below. The main environmental nuisance associated with construction activities is dust.

For inspection purposes only. Consent of copyright owner required for any other use.

3.7.1 Mitigation It is proposed to adhere to good working practices and dust mitigation measures to ensure that the levels of dust generated will be minimal and are unlikely to cause any environmental nuisance. Hard surface roads shall be swept to remove mud and aggregate materials from their surface. Any un-surfaced roads shall be restricted to essential site traffic only. Public roads outside the site shall be regularly inspected for cleanliness, and cleaned as necessary. Material handling systems and site stockpiling of materials shall be designed and laid out to minimise exposure to wind. Diesel engines of plant machinery and trucks shall be properly maintained so that they do not discharge excessive quantities of visible smoke likely to result in a local nuisance.

10

EPA Export 29-06-2017:03:06:18 this The

hedgerow, This

addition trees

benefit

residences

being

town and There

4.0

local

located

Northings

dealt

3.9

As

birds

removal 3.8

investigation

mitigation

feasible In

nuisance.

complaints

3.7.2

The

The

a

the

The

There

assessment.

Residual

Construction There

site

will

proposed

secondary

SITE

of

proposed

and

with

and

minimum,

an

will

MONITORING

from

approximately

event

site Cavan

developer

to

and

of

be

and

established

John

fencing.

breeding/roosting

-

be

in

An

is

measures

trees

this

in

is

the

are

812552. LOCATION

accessed

all

of

accordance

low following

development

a

the

close

no

development

ambient

Impacts

that

and

Sheridan

is

minor

results

road.

development

proposed

received,

the

and

the

the

density

protection

proposed

The

chose

proximity 12.0km

dust

existing

The

fencing

will

contractor

poultry

fact

loss

via

the

made

53.0

site

dust

-Proposed

with

the

be

proposed

housing

that

or

development

a

the

of

EPA

and

North

chosen

will

follow-up

monitoring

South

developed

of

bats.

habitat

and

available site farm.

deposition

odour

development

to

advice

will

development

visibility

Air

birds

not

rejuvenation.

will the For inspection purposes only.

all

of

West

be

and Consent of copyright owner required for any other use. If

Guidance

The of

for

development

adversely

the

Poultry

hedgerows from

from

development,

comply

from

badger

and

constructed

nearest

investigation

to

from

minimal

the

to

of

is

for

existing

site

survey

the

beneath

bats

the

a

the

the

eliminate

proposed

is

dust

Unit

of

brownfield

the

boundary

on

sets

with

Local

local

affect

an

town

The

dwelling

proposed

and

an

Odour

are

development

development

will

approach

at

or

will

are

established

all

existing

the

at

Authority

they

NPWS

site

Maghernacaldry

shall

mature

will

of

the

this

odour

be

poultry

legislative

be

IGR

located,

footprint

Assessment

Shercock.

is

area,

house

boundaries

be

have

nuisance.

carried

dwelling.

located

have

well

development

wildlife

roads

[Irish

agricultural

at

initiated.

and

and

units

periodically

in not

for

defined

agricultural

pre

the

regard

which

of

dense.

provisions

the out

is

c.

The

Grid

EPA

the

ranger.

been

the

or

In

minimal.

is

(AG5)

Poultry

20.0

are

Td.,

general

by

This

following during

the

the

for

proposed

belongs

to

by

Reference]

proposed

entrance

considered

is

marked

an

Cootehill,

km

inspection.

reducing

most

a

will

event

used

will

creating

holding

growing

combination relating

(See

aid

construction,

North

vicinity.

be

to

be

reasons:

favourable

for

poultry

of

quality

units.

initiated.

by

which

Appendix

the

initiated

Eastings

impacts

Odour

Co.Cavan

grazing

East located

for

an

to

a operation.

As

applicants

combination

the

hedgerow/tree

units

environmental

connects

specialist

of

of

there

nuisance

they

location.

as

purpose

the

1). on

whilst

hedgerow,

which

-

are EPA Export 29-06-2017:03:06:18

662287,

soon

nesting

are

county

will

If

sister

to

to

also

and

any

will

an

no

be

be

11

as

In

of

of

a John Sheridan -Proposed Poultry Unit at Maghernacaldry Td., Cootehill, Co.Cavan

• It has been decided to develop the existing agricultural entrance as it is best suited to the proposed revised location of the poultry units. No difficulties arose over the choice of this entrance. Sight visibility splays are in place over the applicant's lands and no third party permissions are required. • Resources available at site- water, gas, electricity etc. • Localised stops for all ancillary traffic- deliveries & collection of birds, waste etc. • Existing drainage system capable of facilitating extended development. However, the perimeter drainage system will benefit from renunciation and cleaning. • The EPA's BATNEEC Guidance Note for the Poultry Sector advises that the developer should have ample land space in the vicinity of his poultry complex to be available for use as lined carcass disposal sites in the event of a disease outbreak.

5.0 SITE LAYOUT The location for the proposed poultry units would be situated approximately 53.0 south of nearest dwelling house and will be accessed via the development of an existing agricultural entrance which connects to a local secondary road. The existing units are located over 30.0 meters from the edge of the Local Service road to the East of the site, as indicated in Appendix 1 "Site Layout Plan". The proposed development would have a capacity of approximately 104,700 broilers. The maximum height of the proposed house would be approximately 5.65m, at the highest point of the sloping roof. The proposed house will have an internal controls room at the front corner of the house. Two new waste water (washings) tanks will be provided on site to serve this development with a capacity of approximately 2,500 Gallons (11.36 m3) each. The site boundary is marked by hedgerow, trees and fencing. The existing agricultural entrance is located to the West of the proposed site and this is For inspection purposes only. capable of facilitating the proposedConsent development, of copyright owner as requiredindicated for any in other the use. Site Layout Plan.(See Appendix

1) Drainage: Yard and roof runoff are to be diverted via a new storm water drainage network which in turn will be diverted into a gravel based soil polishing bed, prior to final discharge. It is recommended that all existing drains in the vicinity will receive deepening and rejuvenation.

6.0 PLANNING CONSIDERATIONS

6.1 Planning Justification The development has legitimacy and a valid, defensible status under the Planning Acts. The site has been used in an agricultural capacity for over 100 years. The site profile lends itself to a development of this nature and will in no way constitute an intensification of use. Other developments in the area are predominantly agricultural

12

EPA Export 29-06-2017:03:06:18 John Sheridan -Proposed Poultry Unit at Maghernacaldry Td., Cootehill, Co.Cavan

The environmental impacts on the area as a result of this established use will be integrated and 'subsumed' into the existing effects. There will be no generation of any 'new' effects. Environmental impact will thus be confined to the existing geographical area. There will be no significant extension of effects geographically nor any new effects generated within the technical operational context.

7.0 CONSTRUCTIONDETAILS

Foundation: The proposed poultry houses will be constructed on an impermeable concrete foundation, to be laid by a hired subcontractor. This phase would take approximately two to four days.

Housing: The housing will be installed by a contractor and will consist of a metal portal frame structure. The structure is Insulated with preformed composite panels to the Side Walls. Rising walls are insulated concrete panels supplied by Wrights of Swans Cross, Co. Monaghan.

Roofing: The roofing will be composite cladding panel supplied by Kingspan or other equal or approved.

Washing Tanks: The proposed washings tanks (2 No.) will be situated underground adjacent to the houses and constructed of reinforced concrete. The tank construction will conform to the Department of Agriculture, Food and Forestry's Specification No. 123 "Minimum Specification Slatted Livestock Units: Reinforced Concrete Tanks" DAFF, 1994. See attached technical specification/ data sheet

For inspection purposes only. Feed Silo: On completion of constructionConsent of copyright works, owner feed required silos for any will other beuse. installed adjacent to the new houses with capacities of 28 tonnes each.

Ventilation: Mechanically controlled roof ventilation will be incorporated into the design of the house. The ventilation will be controlled by thermostatically controlled roof vents.

Heating: Gas fired water heating will be installed in the new units.

Feeding/Drinking Apparatus: An auger style feeding system and nipple-type drinkers will be Installed in the new and existing units. Construction works are expected to take approximately 8 weeks and it is hoped to commence construction following final grant of planning permission. As construction works are expected to continue for approximately 8 weeks duration, the extra traffic and noise generated will be only t(;!mporary, and complaints are not expected from those living in and travelling through the area.

13

EPA Export 29-06-2017:03:06:18 John Sheridan -Proposed Poultry Unit at Maghernacaldry Td., Cootehill, Co.Cavan

8.0 OPERATIONALDETAILS

8.1 Introduction

The proposed poultry houses would be run by the developer, Mr. John Sheridan, who has been involved in the poultry unit for all his adult life.

The proposed new unit would have a stocking capacity of approximately 37,400 broilers. The two existing houses will be expanded in order to increase capacity of house No. 1 from 18,800 birds to 32,050 birds (13,250 Increase) and House No 2 from 20,900 birds to 35,250 birds (14,350 Increase). This will raise the total stocking capacity of the site to 104,700 Broilers. The operation will be run exactly as with typical poultry units, which involves the rearing of chickens from day olds over a 7 week period. Carton Brothers hatchery will deliver day old birds to the site. There are approximately 6 batches per year, with a break between batches of approximately 2 weeks, during which cleaning of the house and yard is carried out.

8.2 Batch Cycle/House Depopulation details: • Day 34 or 35: 30-50% of the flock is taken by Carton Brothers Limited (to cater for customer requirements for smaller broilers) • Day 42 - 45: remainder of flock is depopulated, depending on market requirements Any dead birds will be stored in sealed containers and taken off site by Michael Galligan, Gortnaleck, Ballyconnell, Co. Cavan approximately once every two weeks, or once a week on request if necessary.

8.3 House Details: Flooring: The flooring will be dry litter based, with chopped straw supplied directly by the applicant. Spent litter, containing poultry manure, will be collected at the end of each batch cycle Eamon For inspection purposes only. Consent of copyright owner required for any other use. Fitzpatrick, Clonavilla, Clones, Co. Monaghan for tillage use. (Refer to letters in Appendix 2).

Cleaning: The house will be washed with water between batches, and the wash water stored in the washings tank adjacent the house. A disinfectant is used on the floor when dry, so this does not lead to any runoff. No detergents are used in the cleaning of the poultry house or yard. When the washings tank is full, the contents are siphoned out and transferred and land spread on the designated lands in the sites vicinity which are in the ownership of the applicant.

8.4 Feeding and Drinking: The proposed supplier of feed will be designated by Carton Group. Feed will be stored in the silos adjacent to the houses and fed down lines into the house in an auger style system. Feed wastage: as with the similar operations, feed wastage will be reduced through good practice, e.g., regular checking of the feeding lines to ensure adequate feed stock, no blockages, no contamination, etc. Water will be supplied from proposed deep bore well on site. Drinkers will be nipple style, which creates less wastage to the litter floor, with water being supplied from the mains. Drinkers will be

14

EPA Export 29-06-2017:03:06:18 John Sheridan -Proposed Poultry Unit at Maghernacaldry Td., Cootehill, Co.Cavan

checked regularly for leaks in the system, thus ensuring efficient and economical water consumption and minimal wastage of water.

8.5 Ventilation: The ventilation system will consist of mechanically controlled by thermostatically controlled roof vents. The developer is aware that strict controls are essential for bird welfare - too little causes bird respiratory problems, too much causes poor litter conditions and wastes energy.

8.6 Controls: A small control room will be situated at the front corner of the new house (Outside but attached to the house) where strict controls and records are maintained on relation to temperature, ventilation, lighting, and water and feed consumption, etc.

8.7 Records: The following are some examples of records that would be kept in the control room, as with the existing houses: • Manure Disposal Record (House no./ date/ destination) • Chemical Stock and Usage (disinfectants) • Dispatch dockets • Feed Delivery Record • House Preparation Checklist • Water Meter Readings

• Flock Inspection Sheets (daily and For weekly inspection checks, purposes only. corrective actions) Consent of copyright owner required for any other use. • Rodent Control Record

All records concerning waste collection, recycling and recovery shall be maintained on site and be available for inspection and submitted to the Environment Section, Cavan County Council annually.

9.0 Human Beings

9.1 Introduction

The surrounding area of the proposed development has a substantial rural pattern with agricultural activity predominant in the area. In the current context, the most significant impacts relating to human beings are further considered in the following sections Noise Emissions, Disease Control, Waste Management, Traffic, Landscape and Material Assets.

15

EPA Export 29-06-2017:03:06:18

of of

will will

be be

10.1 10.1

are are

10.0 10.0 keeping keeping

It It

procedures procedures

9.4 9.4

transport transport

temperature temperature

litter litter

annually annually

At At

green green

disperse

in. in.

Visually, Visually,

the the

application. application.

south south

of of

reduction reduction

will will

9.3 9.3

It It

dust, dust,

The The

There There

9.2 9.2

dust dust

is is

is is

negligible. negligible.

External External

land land

not not

the the

not not

Dust Dust

Conclusion Conclusion

developer developer

be be

Mitigation Mitigation

considered considered

Development Development

main main

Dust: Dust:

dust dust

proposed proposed

smell smell

in in

EMMISSIONS EMMISSIONS

western western

are are

within within

expected expected

be be

constructed constructed

with with

end end

. .

use use

colour. colour.

levels levels

and and

the the

During During

phase, phase,

John John

as as

areas areas

an an

in in

no no

along along

& &

construction construction

The The

possible. possible.

best best

from from

the the

Thorough Thorough

of of

mitigation mitigation

proposed proposed

in in

issue. issue.

the the

noise

dwellings, dwellings,

and and

generated generated

Sheridan Sheridan

that that

the the

that that

boundaries boundaries

the the

for for

there there

providing providing

this this

low low

with with

area area

practice practice

houses. houses.

grazing grazing

the the

. .

approximately approximately

An An

Impact Impact

consideration consideration

the the

poultry poultry

the the

crop crop

lying lying

phase, phase,

Air Air

any any

available available

will will

local local

cleaning cleaning

development development

adequate adequate

will will

-Proposed -Proposed

development development

increased increased

other other

materials materials

quality quality

by by

TO TO

guidelines guidelines

additional additional

Minimal Minimal

that that

landscape landscape

to to

be be

cycle cycle

economy. economy.

be be

unit

of of

the the

On On

no no

a a

poultry poultry

ATMOSPHERE ATMOSPHERE

all all

than than

provided provided

slight slight

the the for for

For inspection buildings purposes only.

of of

development, development,

. .

Human Human

is is the the

ventilation ventilation Consent of copyright owner required for any other use.

A A

mitigation mitigation

when when

53.0m 53.0m

levels levels

discussed discussed

the the will will

impact impact

cattle cattle

Poultry Poultry

certain certain

site site

and and

those those

restrictions/ restrictions/

and and

will will

nuisance nuisance

extract extract

farming farming

would would

houses houses

also also

examining examining

in in

relevant relevant

of of

Beings Beings

and and

will will

be be

some reduced reduced some

South South

grazing

on on

of of

the the

Unit Unit

contribute contribute

dust dust

amount amount

system system

measures measures

elsewhere elsewhere

screened screened

be be

family family

human human

be be

the the

fans fans

between between

both both

from from

will will

form form

at at

of of

will will

constraints constraints

. .

adversely adversely

carried carried

regulations, regulations,

However, However,

proposed proposed

Maghernacaldry Maghernacaldry

nearest nearest

only only

the the

will will

in in

employed employed

odour. odour.

of of

members, members,

of of

be be

beings beings

the the

are are

to to

by by

covered covered

effect effect

batches batches

in in

dust dust

generated, generated,

be be

impact impact

levels levels

out out

reducing reducing

this this

construction construction

existing existing

adapted adapted

dwelling dwelling

This This

affected affected

more more

placed placed

will will

the the

will will

landscaping landscaping

in in

it it

of of

document. document.

in in

on on

is is

tarpaulins tarpaulins

will will

will will

directly directly

within within

full full

be be

human human

the the

proposed proposed

be be

concluded concluded

hedgerows hedgerows

site site

visual visual

extensively extensively

and and

by by

Td

as as

house. house.

minimal. minimal.

ensure ensure

be be

by by

compliance compliance

discharged discharged

houses houses

.

the the

, ,

is is

and and

will will

occur occur

110.0m 110.0m

properly properly

dust dust

Cootehill

beings beings

on on

to to

impact impact

Planning Planning

plan plan

to to

further further

operational operational

that that

Economically, Economically,

unit unit

be be

the the

that that

will will

or or

The The

in in

contain contain

to to

expected, expected,

used used

the the

will will

of of

odours. odours.

submitted submitted

the the

will will

implemented. implemented.

developer developer

to to

ensure ensure

, ,

and and

with with

significant significant

the the

proposed proposed

Co

this this

assist assist

Department. Department.

region region

atmosphere atmosphere

be be

emission emission

serve serve

.

will will

Cavan Cavan

to to

as as

north north

best best

visual visual

development. development.

phase, phase,

no no

During During

much much

reduce reduce

be be

in in

the the

during during

to to

of of

with with nuisance nuisance

EPA Export 29-06-2017:03:06:18

due due

impacts impacts

practice practice

east east

new new

blending blending

brown/ brown/

6 6

of of

impact, impact,

benefit benefit

change change

would would

of of

times times

litter litter

dust dust

to to

and and

unit unit

the the

and and

this this

the the

the the

In In

16 16 a a John Sheridan -Proposed Poultry Unit at Maghernacaldry Td., Cootehill, Co.Cavan

construction phase. Such dust will only be evident on the site and will not impact on dwellings and other buildings in the vicinity of the site, which are situated far enough from the operation so as not to be effected by any dust generated. Regular washing of the yard areas and periodic rainfall will also mitigate any dispersal of dust generated by site traffic. Dust monitoring should be carried out on a visual basis and mitigation measures employed if deemed necessary.

10.2 Odour:

Although odour generated in the operation may be more detectable at certain times, as partly influenced by prevailing weather conditions, the and surrounding are well accustomed to occasional odour from agricultural developments. With this in mind however, odour levels generated do not cause significant nuisance in the surrounding area, as the operation is located in a predominately agricultural area and over 280m distance from any the closest dwelling other than the developer's. The poultry houses will be cleaned out between batches, approximately 6 times per year, and the cleared out litter and manure taken away by Eamon Fitzpatrick, Clonavilla, Clones, Co. Monaghan for tillage use. Wash water from the cleaning of the house will be stored in a precast underground storage tank, 2500 gallon (11.36 m3) capacity at the end of each house. The proposed washings tanks will be precast concrete factory produced and not block built on site. Additionally, as the manure is scraped out of the houses with the litter between batches, the level of manure in the wash will be negligible.

The following measures will ensure little or no impact from odour on the surrounding environment: Good practice in terms of...... • Poultry house temperature control

• Carcass storage and removal from For the inspection site purposes only. Consent of copyright owner required for any other use. • Thorough cleaning out of the poultry house between batches • Regular yard cleaning • Strict adherence to good land spreading practice

Such measures will be taken by the developer in an effort to ensure the proposed poultry houses do not cause a nuisance in the surrounding area.

11.0 FLORAAND FAUNA

11.1 Introduction Currently the site of the proposed new dwelling is a Greenfield site. It is used predominately for grazing. Medium hedges and trees surround the site and boundary of the proposed houses. The entrance to be used in the proposed development is the existing entrance to the site. Some levelling off of ground levels will be required to facilitate the new development and the developer will

17

EPA Export 29-06-2017:03:06:18

22:00 22:00

13.1 13.1

For For

Night Night

Daytime: Daytime:

sensitive sensitive

comply comply

development development

generated generated

EPA:-

archaeological archaeological

identified identified

13.0 13.0

ameliorative ameliorative

12.0 12.0

the the

number, number,

baiting baiting

maintain maintain

The The

management management

boundary, boundary,

Scientific Scientific

11.2 11.2

Stringent Stringent drainage drainage

drains drains

cooperate cooperate

• •

A A

clarification clarification

Various Various

developer. developer.

The The

It It

Construction Construction

nearest nearest

time: time:

certain certain

to to

Rodent Rodent

ARCHAEOLOGY ARCHAEOLOGY

NOISE NOISE

is is

will will

Transport Transport

stations stations

with with

08:00. 08:00.

inevitable inevitable

locations locations

comments, comments,

will will

within within

Interest), Interest), procedure procedure

a a

John John

cleaning cleaning

24.0m 24.0m

with with

require require

in in

weekly weekly

action action

maps maps

conditions conditions

amount amount

is is

ensure ensure

of of

watercourse watercourse

the the

Control Control

significance. significance.

The The

Sheridan Sheridan

proposed proposed

45dB(A) 45dB(A)

SSdB(A) SSdB(A)

any any

daytime daytime

will will

the the

the the

EMISSIONS EMISSIONS

-

at at

to to

construction construction

surrounding surrounding

procedures, procedures,

taken taken

and and

that that

so so

of of

developer developer

conditions conditions

check check

confines confines

Noise: Noise:

development. development.

be be

the the

the the

for for

actions actions

of of

be be

constructional constructional

will will

Programme: Programme:

drawn drawn

which which

noise noise

a a

the the

rejuvenated, rejuvenated,

closest closest

( (

( (

is is

surrounding surrounding

-Proposed -Proposed

which which

when/if when/if

pest pest

certain certain

LAeq(lh) LAeq(lh)

LAeq(lh) LAeq(lh)

therefore therefore

and and

normally normally

to to

No No

Development Development

or or

and and

will will

stipulate stipulate

will will

up. up.

specified specified

the the

control control

proper proper

associated associated

in in

point. point.

areas areas

operate operate the the

and and For inspection purposes only.

noise noise

necessary. necessary.

be be

date. date.

the the

The The set set

Consent of copyright owner required for any other use. A

development development

Poultry Poultry not not

site. site.

defined defined

supplies supplies

generated generated

"Baiting "Baiting

flora flora

operational operational

deepened deepened

The The

proximity proximity

or or

bait bait

storage, storage,

system system

element element

for for

that that

by by

Recorded Recorded

impact impact

above above

monuments monuments

The The

and and

proposed proposed

the the

at at

records. records.

Plan Plan

the the

Unit at at Unit

operating operating

as as

to to

Checklist" Checklist"

various various

following following

is is

fauna fauna

the the

Local Local

on on

disposal disposal

by by

and and

of of

08:00 08:00

the the

would would

proposed proposed

a a

were were

is is

phases. phases.

......

checks checks

any any

the the

Bord Bord

threshold threshold

Maghernacaldry Maghernacaldry

site site

piped piped

A A

a a

development development

Authority Authority

will will

.. ..

strategic strategic

of of

proposed proposed to to

be be

rare rare

consulted consulted

noise noise

map map

minor minor

Bia Bia

will will

and and

sound sound

not not

archaeological archaeological

22:00 22:00

a a

will will

in in

Farm Farm

development development

flora flora

bait bait

factor factor

be be

outlining outlining

transfer transfer

be be

some some

requirements requirements

levels levels

stream stream

be be

in in

locations locations

kept, kept,

pressure pressure

adversely adversely

programme programme

and and

development. development.

or or

relation relation

sites sites

carried carried in in

is is

of of

cases. cases.

fauna. fauna.

should should

Td

not not

night night

order order

such such

of of

recording recording

the the

located located

.

such such

, ,

wash wash

and and

situated situated

Cootehill

around around

to to

limits limits

is is

out out

effected. effected.

an an

locations locations

of of

time time

not not

to to

this. this.

which which

as as

a a

historical historical

the the

operation. operation.

water, water,

on on

to to

identify identify

be be

vital vital

are are

details details

this this

is is

the the

Some Some

within within

, ,

a a

EPA EPA

the the

will will

usually usually Co

exceeded exceeded

weekly weekly

set set

and and

new new

and and

element element

whereupon whereupon

.

Cavan Cavan

are are

be be

potential potential

South South

local local

of of

any any

ASSI ASSI

down down

Noise Noise

efficient efficient

enforced enforced

numbers numbers

Bait Bait

houses houses

required required

defined defined

basis basis

perimeter perimeter areas areas

EPA Export 29-06-2017:03:06:18

(Area (Area

at at

Eastern Eastern

Station Station

by by

of of

will will

noise noise

were were

and and

and and

this this

the the

the the

site site

18 18

be be

as as

by by

to to

Of Of

of of of of the fauna topics

summarised guidelines factors

issues complementary surrounding Development exists into

location

13.3

construction hours. construction

Neighbouring weeks

13.2

To

In •

Again,

• account

Considering

potential

Summary

Operational

such for

an

primarily

the

Also,

was

line

fully

Transport

The

Operational

Site

existing

John

interaction

example

on

mitigation

installation

as

also

Traffic

in with construction

as

environment

explain

poultry

work

noise

Regulations

dwellings

noise

birds

the

Sheridan

interactions

part

feature

agriculture mitigation

the

Of

taken

requirements

-

table

-

Noise:

is

during

activity

of

Potential

of

and

will

foundation relate

what between

vehicles house

provided.

of

the livestock,

of

are

into

-Proposed

below

under

material

be

of

operational

2001,

housing

is

agricultural

is

normal

far

exclusively

-

measures

and

the

doors

account

into

temporary

expected

ventilation,

moving

meant

two

enough

Interaction

the

houses

associated

the

laying

Noise of For inspection purposes only. supplies,

assets

account Consent of copyright owner required for any other use.

associated

will

or

heading

working

Poultry

EC

interactions/inter-relationship

as

by noise

around

more

have

and

can from

phase

to

to be

Directive

part

in

in

an

birds

wastes,

human

be

ecological

activity kept

the

interact

Unit

would

when

environmental

nature.

the

of

/

inter-relationship

been

hours,

of

the

will

works

Inter

minimal,

(

form

Human

on

the

site

at

closed

site

take

etc.

85/337/EC

beings.

involve

proposed in stocking

Maghernacaldry

making

with

so

EIS

avoiding

of

Relationships

Mitigation should

the

assessment

during

that

approximately

commercial Environment

when

taking

scoping

vicinity.

a

operation

However,

topics,

and

number

noise

.

their

only

construction

These

(as

early

possible.

or

into

emptying)

measures

and

also. take

should

interaction

between

the

amended) assessment

livestock

Td.,

account

of

morning

and

during

interactions

noise

assessment.

3-4

relevant

approximately

environmental

The

Cootehill,

not

most

days

will

the

can

normal

be

and

impact

the

between

and

or

specialists

various

of

and

and involve

an

impact

late

so

remoteness

are

Co.Cavan

the

Where

the

issue.

daytime

then

it

of

where

2-3

evening

aspects.

standards

discussed must

environmental

environmental

Planning

noise

on

carrying

after

have

weeks,

a

terrestrial EPA Export 29-06-2017:03:06:18

be

potential

possible

working

on

of

a

taken work.

taken

Noise

and

and

and

site

few

out

the

the

19 John Sheridan -Proposed Poultry Unit at Maghernacaldry Td., Cootehill, Co.Cavan

Summary of Potential Interactions/Inter-relationships

SUBJECT Interaction with Interaction/inter-relationships

IAir Human beings Air quality is not a concern both at the local community level and on a broader national/global scale. In terms of the proposed poultry housing, dust (both during the construction phase) and its impact on he communities and residents adjacent to the poultry housing will be he main issue.

Flora & Fauna !Vegetation can act as a purifier for air in absorbing CO2 and giving out oxygen. Dust could affect fauna during construction phase.

Water No interactions/Inter-relationships Soils Dust from exposed soils during construction could cause deterioration tof air quality in the immediate vicinity of the development

Climate Local heating of air in the poultry houses of embankments could cause microclimate change in those areas. Material Assets No interactions/Inter-relationships

Noise Human Beings Sensitive receptors located close to the proposed extension may experience some increase in noise particularly during the construction stage. Flora & Fauna Construction proposals could result in significant noise disturbance which may impact on the birdlife currently using the area.

Material Assets No Interactions/Inter-relationships

Landscape Human beings rrhe proposed development will have a minor actual and perceived landscape appearance in the area and directly impact on the local !Community and adjacent residences.

Flora & Fauna IA small loss of hedgerow will occur and these are very important as For inspection purposes only. Consentwildlife of copyrightcorridors owner for required animals. for any Improvementother use. of the remaining hedgerow will be conducted post development Water No Interaction/Inter-relationships

Soils Movement of significant quantities of soil from one area of another lean affect the appearance of the landscape. This will be necessary as part of the construction when material is removed from the tonstruction zone.

Material Assets No interactions/Inter-relationships

Flora & Fauna Human beings There will be minor impact on the fauna and flora of the area as they suffer habitat loss and dislocation due to the proposed scheme.

20

EPA Export 29-06-2017:03:06:18 John Sheridan -Proposed Poultry Unit at Maghernacaldry Td., Cootehill, Co.Cavan

Water During construction there is a minor risk of disturbance of drainage K:hannels need special precautions to avoid disturbance of sediments rv,.tithconsequent effects on fauna.

Soils Stabilisation methods for soft soil area could alter the pH balance with consequent change in flora cover and species of fauna supported.

Climate No Interactions/Inter-relationships Material Assets Land take will cause some local loss of range area for terrestrial fauna

[Water Human Beings No Interactions/Inter-relationships Soils Rainfall runoff waters could cause deterioration of water quality of streams

Material Assets No Interactions/inter-relationships

Soils Human Beings Dust from exposed soils during the construction period can cause dust nuisance if not properly mitigated.

Material Assets Extraction, movement and placing of soils will have an energy input requirement.

Climate Human Beings No interactions/Inter-relationships Material Assets No Interactions/Inter-relationships

Material Human Beings Current land-use will be permanently altered including the loss of !Assets ~cological habitat and farmland. For inspection purposes only. Consent of copyright owner required for any other use.

Part 2 (Second Schedule) of the above mentioned regulations requires that the interactions between human beings, flora and fauna, soil, water, air and climatic factors, landscape, material assets, cultural heritage, architectural & archaeological must be assessed. The aspects of the environment likely to be significantly affected by the proposed development have been considered in the proceeding chapters of this EIS. In order to further demonstrate the areas in which significant interactions occur, a matrix has been prepared and is included below (Fig. 13). Where any environmental element is on the top row of the matrix (The Receptor) is likely to be affected in any way by any element in the left most column (The Impactor), which contains the list of environmental aspects most likely to be significantly affected by the proposed development

21

EPA Export 29-06-2017:03:06:18

up up

have have

The The

oxides, oxides,

houses. houses.

domestic domestic

12.0km 12.0km

13.4 13.4

13.4.1 13.4.1

Fig. Fig.

to to

Neptlve Neptlve

NotApplcable NotApplcable

~ ~

N@utral N@utral

Posltlw Posltlw

Hmtaae Hmtaae

Malerla!Aslels Malerla!Aslels

CulbNal CulbNal

Human Human

Flara&Fauna Flara&Fauna

Noise Noise

Visual Visual

Landscape& Landscape&

Alr&almale Alr&almale

Wam Wam

Soll Soll

proposed proposed

Operational Operational

13 13

95% 95%

limited impact impact limited

sulphur sulphur

Existing Existing

LPG LPG

North North

-

fuel fuel

8elnp 8elnp

John John

Matrix Matrix

efficiency efficiency

is is

combustion. combustion.

development development

the the

West West

Sheridan Sheridan

dioxide dioxide

Sources Sources

Indicating Indicating

least least

Noise: Noise:

and and

on on

of of

N/A N/A

Neg Neg

N/A N/A

N/A N/A

Neg Neg

N/A N/A

Pos Pos

Neg Neg

N/A N/A

N/A N/A

Neg Neg

Neg Neg

Soll Soll

N N

and and

offensive offensive

the the

air air

-Proposed -Proposed

are are

of of

Emissions Emissions

will will

particulates particulates

quality quality

town town

fully fully

Air Air Inter-relationships Inter-relationships

be be For inspection purposes only.

Water Water

of of

Emissions Emissions

condensing condensing

N/A N/A

N/A N/A

N/A N/A

N/A N/A

N/A N/A

N/A N/A

N/A N/A

Neg Neg N/A N/A

of of Consent of copyright owner required for any other use.

located located as as

the the

Poultry Poultry

from from

Shercock. Shercock.

a a

fossil fossil

as as

result result

oil oil

Air Air

c. c.

well well

Unit Unit

therefore therefore

fuels. fuels.

& &

combustion combustion

20.0 20.0

N/A N/A

N/A N/A

N/A N/A

Neg Neg

N/A N/A

N/A N/A N/A N/A

N/A N/A

Neg Neg

N/A N/A

Cllmab! Cllmab!

The The

of of

as as

at at

Maghernacaldry Maghernacaldry

emissions emissions

km km

greenhouse greenhouse

New New

between between

main main

further further

North North

Landsalpe& Landsalpe&

LPG LPG

include include

Visual Visual

source source

N/A N/A

N/A N/A

N/A N/A

N/A N/A

Neg Neg

N/A N/A

N/A N/A

N/A N/A

powered powered

East East

from from

EIA EIA

reducing reducing

gases. gases.

mainly mainly

of of

of of

Factors Factors

Td., Td.,

combustion combustion

the the

air air

hot hot

This This

Noise Noise

emissions emissions

N/A N/A

N/A N/A

Neg Neg

Neg Neg

Neg Neg

N/A N/A

Neg Neg

N/A N/A

N/A N/A

Cootehill, Cootehill,

pollution pollution

carbon carbon

county county

water water

facility, facility,

of of

heating heating

monoxide, monoxide,

town town

to to

Co

would would

LPG LPG

Traffic Traffic

if if

N/A N/A

N/A N/A

Neg Neg

Neg Neg

Neg Neg

atmosphere. atmosphere.

Neg Neg

Neg Neg

N/A N/A

N/A N/A

.

Cavan Cavan

permitted, permitted,

of of

to to

systems systems

Cavan Cavan

arise arise heat heat

EPA Export 29-06-2017:03:06:18

nitrogen nitrogen

from from

and and

are are

the the

will will 22 22 13.4.3

13.4.4

13.4.2

13.4.2

Odour:-

Odour

53.0 system dispersed

and the

so up

rainfall

of

would

Dust:-

The

disinfectant site

articulated

(iii)

managed regime. (i)

(ii) required.

Monaghan

During

made

dust

as

regularly

construction

Dust

other

m

on

Odour

Odour

MITIGATION

not

IMPACTS

be

minimisation

to

from

will

will

the

John

employed

The

floors. All

All

same

ensure

negligible.

levels

around

buildings

to

from

doors

for

also

tankers,

not

operational

and

trailers

programme.

Management

the

Sheridan

be

litter

day

tillage

be

the

generated

nearest

will

effected

phase.

mitigate

no

the

closed

in

from

an

in

as

is

dusting

Thorough

proposed

not

feed

for

MEASURES

yard

the

the

to

use.

-Proposed

issue.

litter

and

Such

cause

neighbouring

in

the

be

instant

by

any

vicinity

lines,

houses

plan

areas

houses

This

by

occurs.

kept

construction

is

any

Minimal

operation

dust

dispersal

and

cleaning

any

For inspection purposes only. the

removed

is

fans is Consent of copyright owner required for any other use.

as

to

dust

of

removal

Poultry

John

-

will

until

will

a

problems

existing

development,

a

Top

the

the

Dusting

same

are

levels

result

dwelling

generated.

only

ensure

of

final

is

absolute

site

of

Sheridan's

soil

and

phase

power

Unit

the

removed

day

dust

by

site.

be

of

of

all

extraction

will

off

houses

they

at

the

dust

no

evident which

of

Eamon

activity.

of

site.

generated

be

The

hosed

Maghernacaldry

minimum

both

which

Regular

ventilation

the

nuisance

statement

begin

removed

will

from

belongs following between

poultry

of

on

in

first,

Fitzpatrick,

be

Power

are

birds

a

the

the

the

washing

even

generated,

by

strict

situated

of

followed

off-site

systems

to

site

growing

of

houses

batches

construction

site

has

hosing

is

dust

the

though

intent

the

Td.,

washing

and

taken

traffic.

of

Clonavilla, applicants

and

far

within

current

Cootehill,

by

in

and

Contractors

as

will

the

will

facility

of

the

enough

the

stored

place.

ceilings,

is

ensure

An

yard

not

how

loaded

programme

and

to

poultry

the

houses

cleaning/washing

all

adequate

sister.

be

impact

Clones,

appropriately

Co.Cavan

areas

from operational

odours

houses.

efforts

that

expected,

walls

arrive

onto

site

will

the

the

on

and

and

and

is

will be

will

the

Co.

ventilation

on

operation

Any

dwellings EPA Export 29-06-2017:03:06:18

emission

within

periodic

cleaned

phase,

be

be

during

if

dust

23 John Sheridan -Proposed Poultry Unit at Maghernacaldry Td., Cootehill, Co.Cavan

(iv) Houses are disinfected with a high solution, doors are then closed to let dry.

(v) Washings from cleaning of poultry houses are kept in underground storage tank.

(vi) Water minimisation is kept to a minimum due to the cost of pumping water to wash houses. Approximately 100 gallons are used to clean houses.

In the event that an odour nuisance is occurring from the poultry litter, the mitigation measure will be the use of a masking agent which is a chemical component in an open-air spray specifically designed to mix with the fugitive odour. These masking agents typically have pleasant odours designed to "mask" the unpleasant odour.

14.0 DISEASECONTROL Strict disease control procedures will be applied in the proposed development. Laws, Codes of Practice and Regulations regarding disease control are administered by the Department of

Agriculture, Fisheries and Food under various EU directives. Stringent in-house procedures, monitoring and adherence to guidelines obtained from Carton Group and their nominated veterinary inspector, Agrihealth. Both of the aforementioned work closely with an Bord Bia to ensure every effort is made to minimise the risk of disease outbreak. Also, the developer is familiar with the protocol in the event of a disease outbreak from his background in the agriculture industry. The Carton Group provides developers with a Code of Practice outlining various bio security guidelines, to ensure contamination is not brought to or from the operation - for example, details of vaccination, general hygiene, dead chickens, pest control, cleaning out and litter disposal. The applicant will also be required to consult guidelines in relation to the use of disinfectant foot dip and cleaning agents, visitor restrictions, use of protective clothing, bird and catcher hygiene For inspection purposes only. measures. Consent of copyright owner required for any other use.

Agrihealth Vetinary Ltd, Monaghan, works closely with the developer to minimise health risk to the flocks and provides procedures to be followed in the event of compromised health/welfare of the flock. They also provide a Health and Hygiene Programme involving guidelines on good practice in relation to Feeding, Catching, Culling, Ventilation and Temperature Control as well as guidelines on site bio security. Also provided is a "Terminal Hygiene Programme" and associated checklist to follow in the event of a disease outbreak, as part of a Bio security Programme. The development will be assigned its own Veterinary Adviser. The developer will also be required to consult "Chicken Quality Assurance Scheme - Code of Practice for Chicken Producers", Teagasc guidelines on Farm Safety and Disease Prevention and HACCP Principles for Poultry Farm Safety. Operational controls to reduce· the risk of disease outbreak include ...... • Temperature Control: The temperature inside the house is strictly controlled, as it must be varied according to the stage of the birds' life cycle • Ventilation checks and control • Regular inspection of Feedlines and Drinkers • Regular inspection of Appearance of Birds 24

EPA Export 29-06-2017:03:06:18 John Sheridan -Proposed Poultry Unit at Maghernacaldry Td., Cootehill, Co.Cavan

• Regular inspection of Litter condition • Strict visitor control- including the use of a visitor book, adequate protective clothing and footwear, disinfectant foot dip and hand wash where necessary.

• Rodent Control Programme- as described on the Flora and Fauna Section.

Strict feeding and drinking rituals are adhered to, and the condition of the birds is inspected at various intervals on a daily basis. Dead birds are stored in sealed containers and will be taken by Michael Galligan, Gortnaleck, Ballycorinell, Co Cavan. The developer reports anything suspicious to

Carton Group and Agrihealth, Clones road, Monaghan, Co. Monaghan. The Department Veterinary Office is notified immediately of any matters arising, and all incidents are logged by the developer. In the event of a Class A disease outbreak, the Department of Agriculture takes control of the site and associated surrounding lands and makes subsequent decisions regarding the future of the development, all determined by the extent of the outbreak. In conclusion, given the stringent controls, procedures and checks proposed and regulated for this type of development, the new development would be adequately prepared for any disease outbreak among the flock.

15.0 WASTEMANAGMENT

15.1 Introduction

The applicant, John Sheridan recognises the importance of good waste management practices in the operation of a modern agricultural activity and is committed to operating in an environmentally responsible manner and consequently views waste as a resource to be used and not a by-product to For inspection purposes only. be discarded. Operational practicesConsent on the of copyright proposed owner developmentrequired for any other and use. the design of the development are aimed at minimising wastes to landfill and the potential for pollution of surrounding land, water or air arising from the development in line with current legislation. The waste management issues within the proposed development will be controlled at all stages of its life cycle i.e. design, construction, operation and decommissioning.

15.2 Avoidance, Remedial or Reductive Measures

The new poultry units will be operated by the developer within the management system utilised by Carton Group, for whom the developer will rear the poultry flock. Methods utilised include ....

• Waste management & minimisation • Energy efficiency • Water conservation (efficient usage in an effort to minimise waste of the resource) • Effluent and emission minimisation • Purchasing decisions 25

EPA Export 29-06-2017:03:06:18 John Sheridan -Proposed Poultry Unit at Maghernacaldry Td., Cootehill, Co.Cavan

15.3 Waste Management & Minimisation Waste management has been examined during two distinct phases of the development.. .. • Construction phase, and • Operational phase Both phases of the development require adequate management to minimise waste generation and protect the surrounding environment from damage and ensure the success of the development.

15.4 Construction Phase It is anticipated that the principle sources of waste arising during the construction of the proposed development will be ..... • Storage and disposal of spoil • Storage and construction materials on site • Reuse and recycling of materials • Disposal of waste construction material, spare materials and containers Potential environmental impacts arising from the construction stage can include ..... • Pollution from stored material run-off • Problems arising from residual wastes • Fuel/oil leakages from construction equipment

15.5 Operational phase During the operational phase of the development anticipated sources of waste from the operation of the development are ...... • Possible contamination of the surrounding environment arising from inappropriate • waste management • Accidental spillages of fuels/chemicals For inspection purposes only. • Additional road traffic emissionsConsent ofassociated copyright owner with required additional for any other traffic use. volumes arising

• from the operation of the development • Waste feed/litter from each batch housed within the units • Liquid waste arising from the housing of each batch within the units • Flock fatalities

15.6 Dead Stock A twice-daily inspection will be carried out within the poultry house to remove the carcases of any dead birds. These will be removed from the area inhabited by flock to a storage container (wheelie bin of 240 litre capacity), there will be two bins commissioned for each of the new houses. These containers will be emptied by Michael Galligan, Gortnaleck, Ballyconnell approximately every two weeks.

15.7 Spent Poultry Litter It is proposed that dry litter will be used within the proposed poultry unit. The type of feed proposed to be utilised, which will be supplied by Carton Group, is engineered to reduce phosphate

26

EPA Export 29-06-2017:03:06:18 John Sheridan -Proposed Poultry Unit at Maghernacaldry Td., Cootehill, Co.Cavan

and nitrate levels within the excreta produced by the flocks being reared to reduce the nutrients contained within the waste to be disposed. At the end of each 8 week farming cycle when the entire stock has been removed, the combined poultry litter and manure are removed by Eamon Fitzpatrick, Clonavilla, Clones, Co. Monaghan for tillage use (See Appendix 2).

15.8 Decommissioning Upon future cessation of use, each unit will be cleaned and sterilised as is the procedure prior to the introduction of a new flock of birds. Once the structures have been sterilised, they will be taken down and the various components made available for reuse or recycling where possible.

15.9 Pollutants and Waste

To prevent chemical pollution during the operation of the poultry operation, all fuels or

chemicals kept on site will be stored in bunded containers. LPG will be the primary fuel source

on site and it is not required to bund LPG tanks. In the event of a leak, LPG will disperse to atmosphere where it is diluted. All major refuelling and maintenance events will be undertaken away from_ the site. Equipment will be regularly maintained and leaks repaired immediately away from the site if possible. Accidental spillages will be contained and cleaned up immediately. Remediation measures will be carried out in the unlikely event of pollution of adjacent watercourses in accordance with the consultant's recommendations.

15.9.1 CONSTRUCTIONIMPACTS AND MITIGATION Impacts:-

Loss or alteration of habitats and species - There will be a minor loss of improved grassland habitats and species as a consequence of the expansion of the site.

Increased suspended solids:- For inspection purposes only. Consent of copyright owner required for any other use. The construction works associated with expansion of the poultry growing operation has the potential to cause the release of sediments into watercourses notably drainage ditches on site. It is predicted ) that this will be a short-term impact as the construction phase is short.

Pollutants and waste:-

The likely sources of chemical contamination would be from site machinery and vehicles. Pollution could occur in a number of ways, such as neglected spillages, the storage handling and transfer of oil and chemicals and refuelling of vehicles. Accidental leakage or discharge of

chemicals and pollutants could cause changes in the PH of the water and could have a direct toxic impact on the fauna and flora at the location of the development and further downstream. If waters become polluted, species more tolerant to pollution can extend their distribution, thus altering the species composition of the watercourse.

27

EPA Export 29-06-2017:03:06:18 and

waters

proposed

layout

transferred aquatic the combination

low and

protection involved

and

measures quantities burned

16.1

16.0WATER 15.10

MONITORING

RESIDUAL existing ecological

of

Mitigation:-

Loss

to

which value,

License,

construction

associated

The

lying

Due

increased

disposal.

record

the

or

Introduction

plan.

Quarterly Assuming

Conclusion

through

or

alteration

environment

poultry

will

to

abundant

in

there

perimeter

topography

that

John

to

of

habitat,

buried

IMPACTS

these

of

construction

the

to

This

keeping

be

of

waste

protect

the environmental All

should

:-

local

Sheridan

local

suitably

factors

should

efficient

retained

operation

improved

monitoring

all

self-regulating

samples

on

of

wastes

the

water

generated

supplies

drainage

mitigation

habitat

:-

authority

the

the

watercourses

associated

in

has

be

impacts

be

such

permitted

this

running

and

-Proposed

on-site

no

developers

aquatic

supply

kept

to

agricultural

arising

will

suffered

and

of

residual

avoid

as

of

area

operation ditch

burden

measures

will

from

to

be

the

inspections

legislation,

surface

and

approach For inspection purposes only. species:

of

will

with

environment.

the

of

tested

will Consent of copyright ownerbe required for any other use.

will

disturbing

waste

storm

this

Poultry

the

the

against

included

impacts.

County

site.

be

is

minimum

kept

practices

be

the

be

of

expected

type

loss

and

are

adverse

provided

-

for

water

carried

the

contractors

Hence,

to tightly

To

to

has

wastes,

the

Unit

put

are

Cavan

of

COD

agricultural

groundwater neighbouring

a

in

water

minimise

potential

required.

minimum,

The

REPS

led

the

development

outflow

in

in

not

at

to

out.

effects

in

monitored

via

at

place

terms

Maghernacaldry

Annual

to be

has

together

management

significant.

intense

terms

an

programme,

a

Under

for

improvement

minimal.

the

impacts

through

in

local

and

Construction

independent

of

of

dealt

pollution.

disposal

the

habitats.

of

within

loss

Environmental

nature

land

inadequate

the

the

at

in

water

with

wastes

past

with

of

on

terms

all

the

loss

required

spreading

was

the

Ireland

catchment

the

strong

or

of

Td

presented stages

However,

scheme

appropriately

gravel

However

in

of

generated

should

habitat

laboratory;

.

of

treatment,

incorporated

agriculture

,

surrounding

habitat

the

Cootehill,

mitigation

strict

conditions

Report.

dictate

awareness

of

based

quality and

as

be

and

management

since

problems

the

monitoring,

is

in

approached

indicated

by

waste

of

the

species,

in

combined

Co.Cavan

the polishing

no

recent

development

the

it

environment,

into

measures

low

of

terms

of

is

wastes records

of

importance

many

the

development,

already

storage.

ecological

the

whereby

all

on

the

years

of

inspection

IPPC

filter

initiatives

from EPA Export 29-06-2017:03:06:18

planning

with

persons the

storage

surface

will

area

of

in

a

It

and

the

site

low

the

the the

the

the

be

28

of

is John Sheridan -Proposed Poultry Unit at Maghernacaldry Td., Cootehill, Co.Cavan

of the proposed development, and the developer already operates the existing agricultural unit on site to this principle.

16.2 Geological setting The site overlies an Rkc "Regionally Important Aquifer" as identified in the GSI National Draft Generalised Bedrock map in appendix 3. The GSI Groundwater Protection Scheme further classifies the aquifer potential of this area as being "poor", which Is Generally Unproductive Except For Local

Zones". The till soil is described as "1711derived chiefly from Paleozoic Limestones and Shales" (TLPSsS). Vulnerability in this area is Extreme (E).

Surface Water Bodies :-

All surface / roof water will be diverted through a polishing filter prior to final discharge to groundwater which in turn may feed into this drain given its position, downhill of the proposed development.

16.3 Impacts and Remedial actions It is proposed to supply the development with water from a the existing water supply taken from the Barraghy GWS. A dry litter bedding system is proposed for the new unit, in an effort to minimise the generation of liquid wastes from the operation. The water supply to the flocks will be via a nipple drinker system within each poultry house, which provides water as required and minimises losses to the floor. The principle source of liquid waste arising within the development will be wash water

generated at the end of each batch cycle For inspectionwhen the purposes house only. is being cleaned in preparation for the Consent of copyright owner required for any other use. arrival of the next stock batch. Wash water from the cleaning of the house will be stored in a precast underground storage tank, 2500 gallon (11.36 m3) capacity at the end of each house. The proposed washings tanks will be precast concrete factory produced and not block built on site. Additionally, as the manure is scraped out of the houses with the litter between batches, the level of manure in the wash will be negligible. All land spreading activities will be carried out in accordance with the relevant directives and guidelines, especially the Department of Environment's Code of Practice for Farming. The developer will thus avoid spreading activities during prolonged wet spells and frost while also paying particular attention to recommended buffer zones. Surface water run-off arising from the development will be diverted to the proposed surface water drainage network via the gravel based soil polishing filter.

16.4 Conclusion The aquifer, on which the site is located, is regionally important and is classified as being of extreme vulnerability. Taken into consideration along with the adequate soil cover, setback from the

29

EPA Export 29-06-2017:03:06:18 John Sheridan -Proposed Poultry Unit at Maghernacaldry Td., Cootehill, Co.Cavan

peat areas, sound concrete foundations, strict monitoring of the operation at all stages and the unlikelihood of point or diffuse source pollution from the development, no adverse effect to local groundwater/aquatic environment or local water amenity value is envisaged.

17.0 SOIL

17 .1 Introduction The till soil is described as "Till derived chiefly from Palaeozoic sandstones and shales" (TTLPSsS). Vulnerability in this area is Extreme (E). Specific subsoil regions are indicated on the GSI subsoil's classification map included in Appendix 3.

17.2 Operation The proposed development will be operated on an impermeable concrete base with sufficient storm water drainage system, and will use a dry litter system of bedding and provide storage facilities for wash waters. The dry litter waste arising on site is removed from the development by Eamon Fitzpatrick, Clonavilla, Clones, Co. Monaghand for tillage use (See Appendix 2) .. The wash waters

stored on site are land spread on lands in the ownership of the developer as per REPS scheme. Soil samples are collected annually and analysed by Teagasc to determine the nutrient content of the soil and determine the fertilising programme for the following year, if required.

17 .3 Conclusion It is not envisaged that the proposed development will adversely affect the soils in the area, due to the strictly controlled nature of the operation. Land spreading will be carried out in a strictly

controlled manner, adhering to the REPS programme, Codes of Practice and other guidelines.

For inspection purposes only. Consent of copyright owner required for any other use.

18.0 TRAFFIC

18.1 Introduction The proposed development will be located c. 20.0 km North East of the county town of Cavan and 12.0km North West of the town of Shercock. The proposed development will be on a green field site. John Sheridan has substantial experience in the poultry industry. A local secondary roadway

runs parallel to the proposed development and runs North East To North West. Access to the

proposed development expanding an existing Agricultrual entrance.

The area is a predominantly rural farmland. The proposed poultry units are to be located approximately 53.0 South of nearest dwelling house and will be accessed via the development of an existing agricultural entrance which connects to a local secondary road. The local area supports a well-established farming community; with most of the land in the vicinity of the site being used for agricultural purposes (grazing, land spreading). The traffic impacts associated

30

EPA Export 29-06-2017:03:06:18 John Sheridan -Proposed Poultry Unit at Maghernacaldry Td., Cootehill, Co.Cavan

with this nature of development are assessed in terms of issues surrounding both the construction and operational stages of the project.

18.2 Construction phase The construction phase of the proposed development is predicted to be completed within a 4 to 6 week frame. The first few days will contribute to heaviest traffic flows of the construction phase-with approximately forty lorry trips to and from the site (mainly the delivery of stones, concrete, and other building materials) as well as earth-moving equipment to carry out ground works. The building contractors working on site will also contribute to the daily vehicular traffic. After the foundation is laid there would be nothing happening for a few weeks and then the house would be installed. The installation of the houses would involve a single 40ft lorry to deliver the prefabricated structure, therefore generating four lorry trips at this stage.

18.3 Operational Phase There will be limited traffic directly and indirectly resulting from the operation of the proposed development. The developer and his family will staff the development, which will not result in additional traffic volumes which are directly associated with the employment of additional labour for day-to-day site operations. The main traffic sources associated with the development will be the delivery of hatchlings to the unit for rearing, the transport of reared birds to processing plants, the delivery of feed, the removal of carcasses, the delivery of litter material and the removal of spent litter material. In relation to the delivery of hatchlings / day olds, the proposed unit will result in 1 No delivery, as there will be capacity on the single 20ft lorry to deliver the required number of hatchlings. As For inspection purposes only. regards the transport of reared birds,Consent it is of copyrightexpected owner to required generate for any approximately other use. 24 lorry trips per batch

upon commissioning of 1 No units. This part of the operation leads to the highest generation of traffic and is to be expected for this type of enterprise. Feed will be delivered to the silos on site by Kolbe Feeds approximately 10 times per batch (30 tonnes per delivery). It should also be noted that these vehicles are often passing through the local road network to service other sites in the area, so the area is accustomed to such traffic. The need for removal of a larger quantity of bird carcasses upon commissioning of 1 No. additional poultry houses is expected to generate 1 No collection per week. Michael Galligan will remove these carcasses approximately every week. The requirement for delivery of shavings (litter material) will generate 1 No. forty foot lorry trip per batch. It is expected that the removal of spent litter for the proposed houses would generate 2 No. forty foot lorry trip per batch. Occasional visits by veterinarian inspectors (annually), An Bord Bia staff (annually) and Carton Group inspectors (approx. twice per batch, twelve visits per year) are made during the course of the operational year. It is important to note that all these visitors to the site, from delivery of hatchlings / day olds to visits by inspectors are already visiting various poultry operations in this region. The

31

EPA Export 29-06-2017:03:06:18

the the

backup backup

Arrangements Arrangements

supply supply

National National

further further

21.0 21.0

should should

increase increase

Therefore Therefore

20.0 20.0

blend blend

or or

surrounding surrounding

low low

visibility visibility

the the

road road

road road

19.0 19.0 local local

collections collections

developments developments

predicted predicted

regional regional

18.4 18.4

assumption assumption

poultry poultry

a a

National National

The The

The The

density density

The The

surrounding surrounding

The The

soil soil

road road

level level

in in

with with

Conclusion Conclusion

CLIMATE CLIMATE

from from

not not

MATERIAL MATERIAL

system system

LANDSCAPE LANDSCAPE

adverse adverse

houses houses

the the

power power

immediate immediate

Grid. Grid.

of of

sit~ sit~

embankment. embankment.

in in

road. road.

proposed proposed

to to

John John

the the

networks. networks.

in in

adversely adversely

the the

from from

the the

dwellings dwellings

traffic traffic

district. district.

the the

Grid Grid

environment, environment,

give give

that that

of of

and and

Additional Additional

are are

proposed proposed

existing existing

on on

requirement requirement

This This

in in

Sheridan Sheridan

on on

the the

complex complex

impact impact

other other

National National

lands lands

to to

rise rise

due due

site. site.

in in

several several

the the

the the

levels levels

development development

area area

proposed proposed

function, function,

road road

place place

Efforts Efforts

impact impact

in in

to to

ASSETS ASSETS

to to

agricultural activities activities agricultural

greater greater

region region

The The

agricultural agricultural

being being

A A

the the

on on

_

development development

significant significant

-Proposed -Proposed

supply supply

is is

this this

will will

during during

landscape landscape

Grid, Grid,

is is

sites sites

however however

if if

predominately predominately

proposed proposed

vicinity vicinity

of of

the the

will will

upon upon

relatively relatively

necessary, necessary,

be be

and and

adding adding

employed employed

resultantly resultantly

development development

the the

vicinity. vicinity.

an an

are are

can can

be be local local

For inspection purposes only. relatively

will will

the the

the the

also also proposed proposed

Consent of development copyright owner required for any other use.

additional additional

automatic automatic

the the

made made for for

Poultry Poultry

be be

visited visited

plan plan

significant significant

development development

generate generate

material material

construction construction

community community

will will

important important

a a

proposed proposed

ensuring ensuring

The The

facilitated facilitated

by by

in in

combination combination

not not

has has

by by

a a

not not

minimal minimal

agricultural agricultural

the the

and and

in in

Unit Unit

on on

farming farming

development development

site site

being being

the the

traffic traffic

the the

generator generator

been been

assets assets

severely severely

installation installation

minimal minimal

increased increased

one one

its its

on on

energy requirements requirements energy

at at

road road

development development

is is

applicant applicant

Region. Region.

is is

by by

will will

peripheries peripheries

and and

site. site.

Maghernacaldry Maghernacaldry

from from

the the

submitted submitted

volumes volumes

in in

journey journey

area. area.

envisaged, envisaged,

within within

the the

of of

used used

not not

enterprises. enterprises.

close close

impact impact

cause cause

operational operational

extra extra

trees trees

system system

the the

traffic. traffic.

existing existing

The The

will will

With With

require require of of

to to

the the

by by

on on

approaching approaching

suggests suggests

proximity proximity

further further

be be

of of

and and

road road

further further

as as

poses poses

proposed proposed

are are

on on

vehicles vehicles

local local

the the

the the

and and

will will

large large

met met

part part

grid grid

the the

a a

rural rural

hedgerow-

The The

traffic traffic

surrounding surrounding

exception exception

Td., Td.,

major major

stages stages

area. area.

minimal minimal

be be

hedgerow, hedgerow,

consequently consequently

by by

are are

obscure obscure

landscape landscape

of of

volumes volumes

in in

the the

to to

site site

and and

involved involved

development development

Cootehill, Cootehill,

employed employed

electricity electricity

this this

close close

met met

country country

in in

draw draw

an an

unlikelihood unlikelihood

of of

is is

agricultural agricultural

visible visible

the the

application. application.

existing existing

of of

during during

already already

the the

the the

located located

proximity proximity

of of

down down

National, National,

native native

the the

of of

in in

area area

greenhouse greenhouse

Co

road road

complex complex

supplied supplied

as as

the the

development, development,

the the

impact. impact.

deliveries deliveries

minor minor

.

interruptions interruptions

Cavan Cavan

is is

an an

of of

and and

due due

highly highly

slightly slightly

trees, trees,

area area

development development

therefore therefore

or or

with with

of of

power power

to to

emergency emergency

Regional Regional

Due Due

proposed­

any any

predicted predicted

to to

additional additional

from from

from from the the

EPA Export 29-06-2017:03:06:18

and and

most most

fencing fencing

utilised utilised

to to

similar similar

to to

gases gases

above above

other other

from from

site. site.

the the

and and

the the

the the

will will

not not

32 32

no no

in in

or or of of

The The

23.6 23.6

23.5 23.5

significant significant

23.4 23.4

/ /

operation operation

23.3 23.3

will will

23.2 23.2

other other

23.1 23.1

out out

be be

impact impact

point), point),

23.0 23.0

impacts impacts

application application

an an

Northern Northern

22.0 22.0

to to

have have

being being

no no

of of

There There

No No

prevent prevent

Construction Construction

be be

The The

adjoining adjoining

It It

usage usage

using using

This This

Overall Overall

impact impact

Under Under

RESIDUAL RESIDUAL

intense intense

an an a a

is is

generated. generated.

no no

residual residual

Forecasting Forecasting

transboundary transboundary

TRANSBOUNDARY TRANSBOUNDARY

on on

Raw Raw

Construction Construction

Economic Economic

Transport Transport

temporary temporary

Land Land

identified. identified.

influence influence

is is

increase increase

considered considered

the the

will will

Ireland Ireland

significant significant

John John

impact impact

will will

of of

natural natural

Section Section

a a

on on

for for

the the

wasteful wasteful

raw raw

material material

green green

following following

similar similar

not not

and and

member member

be be

the the

impacts impacts

observations observations

Sheridan Sheridan

proposed proposed

material material

IMPACTS. IMPACTS.

water water

on on

lead lead

(or (or

a a

and and

However, However,

on on

in in

existing existing

Soil Soil

nature nature

(174) (174)

Given Given

Minerals Minerals

Network Network

field field

minor minor

impact impact

mineral mineral

developments developments

that that

consumption consumption

any any

the the

the the

impacts impacts

to to

other other

of of

inputs inputs

headings. headings.

state state

are are

in in

& &

-Proposed -Proposed

of of

site site

the the

a a

when when

the the

local local

expansion expansion

other other

the the

during during

the the

use use

increase increase

road road

Mitigation Mitigation

significant significant

predicted

the the

on on

the the

resources. resources.

to to

resources resources

of of

distance distance

within within

poultry poultry

operation operation

are are

or or

for for

proposed proposed

land land

of of

needed needed

the the

2000 2000

jurisdiction jurisdiction

network. network. the the

For inspection purposes only. developer

the the national national

Consent of copyright owner required for any other use. IMPACTS

minimal minimal

raw raw

increased increased

of of

are are

on on relevant relevant

or or

Poultry Poultry

an an

of of

. .

E.U., E.U.,

construction construction

Planning Planning

increase increase

energy energy

from from

soils. soils.

House House

in in

natural natural

the the

located located

Any Any

will will

existing existing

materials materials

will will

expansion expansion

the the

climate. climate.

there there

and and

will will

poultry poultry

be be

the the

outside outside

disruption disruption

Unit Unit

atso atso

authorities authorities

vicinity vicinity

on on

poultry poultry

& &

brought brought

in in

resources resources

ensure ensure

not not

in in

border border

farm farm

Development Development

increase. increase.

at at

is is

traffic traffic

site. site.

close close

phase phase

associated associated

operation operation

considered considered

Maghernacaldry Maghernacaldry

an an

the the

of of

of of

holding holding

to to

efficient efficient

The The

with with

in in

production production

indication indication

the the

the the

proximity. proximity.

state) state)

in in

movements. movements.

of of

services services

from from

from from

respect respect

area. area.

the the

proposed proposed

Northern Northern

poultry poultry

in in

with with

in in

Act, Act,

and and

under under

nearby nearby

the the

development. development.

energy energy

this this

the the

and and

for for

As As

of of

where where

the the

the the

increase increase

region region

capacity. capacity.

Td

growing growing

ownership ownership

Therefore, Therefore,

this this

such, such,

Ireland Ireland

any any

a a

development development

existing existing

sources sources

., .,

development development

use use

increase increase

need need

Cootehill

report. report.

the the

transfrontier transfrontier

will will

it it

at at

in in

(18.0 (18.0

is is

operation operation

site's site's

Forecasting Forecasting

to to

all all

transport transport

such such

have have

use use

considered considered

of of

there there

formally formally

times, times,

, ,

in in

John John

Co

location location

Km Km

of of

as as

will will

a a

is is

poultry poultry

.

Cavan Cavan

will will

minor minor

raw raw

local local

likely likely

environmental environmental

at at

will will

and and

therefore therefore

Sheridan. Sheridan.

networks networks

was was

the the

be be

submit submit

that that

materials. materials.

is is

quarries have have

EPA Export 29-06-2017:03:06:18

will will

negative negative

to to

growing growing

minimal minimal

close close

nearest nearest

carried carried

affect affect

there there

work work

will will

the the

33 33

not not

no no

No No

to to . . John Sheridan -Proposed Poultry Unit at Maghernacaldry Td., Cootehill, Co.Cavan

23.7 Difficulties Encountered While Compiling Report

There were no significant time delays or difficulties encountered during the compilation of the EIS.

24.0 CONCLUSIONOF REPORT Following the examination of the processes and associated issues involved with the nature of the proposed development, no significant adverse impacts or areas of concern are predicted as arising during the construction or operational phases of the development. Where real impacts are identified, mitigation measures will be put in place to reduce insofar as possible. Given that the existence of agricultural activity and associated industry in the vicinity by the developers, it is proposed that the development of a poultry unit will have limited effects on the surrounding environment.

For inspection purposes only. Consent of copyright owner required for any other use.

34

EPA Export 29-06-2017:03:06:18

Maps Maps

• •

• •

• •

• •

Poultry Poultry

Site Site

Land Land

Site Site

......

John John

Sheridan Sheridan

Layout Layout

& &

Ownership Ownership

environs environs

Unit(s) Unit(s)

-Proposed -Proposed

Appendix Appendix

. . Plan Plan

For inspection purposes only.

Plan Plan Consent of copyright owner required for any other use. Map Map

Poultry Poultry

- 1 1 -

Map-1 Map-1

:500 :500

Unit Unit

-1 -1

at at

:2500 :2500

Maghernacaldry Maghernacaldry

:10,560 :10,560

No. No.

Td

.

, ,

1 1

Cootehill, Cootehill,

Co

. Cavan Cavan EPA Export 29-06-2017:03:06:18

a a

t,> t,>

n~I n~I

of of

)( )(

l'f l'f

~l ~l

t t

fd< fd<

111H 111H

11-all 11-all

1sid.: 1sid.:

m m

mtsh mtsh

rop rop

:,

:::ni :::ni

ou

~ ~

the the 1\)pN/: 1\)pN/:

::

I?)) I?))

=

0011C

)

iCCl."plcd. iCCl."plcd.

I.xii I.xii

,und1ioo ,und1ioo

infill infill

tht tht

a:atln

S S

3P1

a a

lhelbn~~ lhelbn~~

;MJ ;MJ

ro ro

tht: tht:

th;.'fl th;.'fl

lhc lhc

1 1

h h

.. ..

:

no.11in.ll no.11in.ll

~ ~

nr nr

•i •i

lli

pb=moo

:>37-292.0~1 :>37-292.0~1

225111m 225111m

llthttllh..."Tio-h llthttllh..."Tio-h

/ /

6~m. 6~m.

be be

wd! wd!

or\.."}.>.. or\.."}.>..

•ith •ith

y

1floll. 1floll.

lmuJn-1

>..i.-epu._'lCe,ind >..i.-epu._'lCe,ind

Sf\"tifcin Sf\"tifcin

.mJ .mJ

CLONES CLONES

~ ~

10 10

rqgimi rqgimi

wll wll

Beggan Beggan

infki~hl infki~hl

&,,.·eh. &,,.·eh.

pro!tt!..J pro!tt!..J

1o 1o

ull ull

j~~g;;pn~~ir

(!tt (!tt

,f~Cmg ,f~Cmg

\ol~~af

5m 5m

b: b:

Hm Hm

rlikJ rlikJ

I I

J

rlK( rlK(

Mt'IIL Mt'IIL

SZL'el SZL'el

~n;:::,re-C::>ni:.A\in;;1 ~n;:::,re-C::>ni:.A\in;;1

"lm "lm

d!O!ffl d!O!ffl

.. ..

MDNA,GH,t,,N MDNA,GH,t,,N

O.Jl-513~7 O.Jl-513~7

~ructcd ~ructcd

bi: bi:

t t

~

al•,J'.-c al•,J'.-c

~....,"Uft.-d ~....,"Uft.-d

!hill !hill

lo.'U.5d lo.'U.5d

N' N'

Ill Ill

lON

~,il.ll1 ~,il.ll1

l:c: l:c:

10.00 10.00

t:d11

wll wll

ti:, ti:,

rnm rnm

ai,J ai,J P,'1 P,'1

YOIII YOIII

C Co Co

E-1,'.AI~: E-1,'.AI~:

'h: 'h:

Joe Joe

art art

11:-1.l 11:-1.l

50

~tsfll\!J ~tsfll\!J

lh lh

u:ll:, u:ll:,

i

~

art art

,

I I

inlo inlo

~U ~U

ll

1J11IIJ 1J11IIJ 1k 1k

EPA Export 29-06-2017:03:06:18

~;,ocid ~;,ocid

.ir .ir

~~ ~~

lrtfll lrtfll

,

hlill hlill

'nn 'nn

1

at( at(

rni~in-prii:ir rni~in-prii:ir

t1-aU~ t1-aU~

hiJU!o!S hiJU!o!S

~ar..hions ~ar..hions

uscl. uscl.

Olllr-

he he

Jlu'I Jlu'I

100rM; 100rM;

Cl'l"ICT~

ill ill

'\ill '\ill

atmi atmi

t

but: but:

rrul rrul

1111! 1111!

\.

m.~lb.ll~:;l1:dk~ldbrin1n1»

Jlcm! Jlcm!

sh.Ill sh.Ill

Where Where

y

in-

rl~I rl~I

xri

lil lil

ffl,li'I ffl,li'I

mtil,li mtil,li

ipfL1i

'JP 'JP

wl.11.'t wl.11.'t

jf;;1,1lll'IC'mully~

·

]

wU wU

in in

sim:hion:i sim:hion:i

WALLS WALLS

J J

h' h'

~, ~,

Y1'1lb Y1'1lb

paotl, paotl,

1uilb 1uilb

!5 !5

u!d u!d

hmh:ore hmh:ore

oorH

~ ~

ULi:n ULi:n

·lt.'I ·lt.'I

Sw:ll•

.cturc:d .cturc:d

6fXlirJTI 6fXlirJTI

3 3

,~Jfl.11t(cN\'

cor£rdt cor£rdt

1.111 1.111

Wh.:re Wh.:re

!It !It

h1-ljl1 h1-ljl1

~ ~

be be

i!h i!h

kip!

5mma1 5mma1

B!) B!)

......

W

1111N' 1111N'

Wini! Wini!

1

IS,\mm IS,\mm

Juli Juli

\las; \las;

,...1.c. ,...1.c.

111lk.mfrt1Spn:ir1t::1tia11Sl!J. 111lk.mfrt1Spn:ir1t::1tia11Sl!J.

we-J1.itlifir~WU-\II we-J1.itlifir~WU-\II

1'1tQ'll

lhicl lhicl

t11ll t11ll

1

.\'N: .\'N:

t

>hall >hall • •

~1rombing ~1rombing

fo, fo,

M1

BL.OCKWORK BL.OCKWORK

concrdc concrdc

· ·

morw-. morw-.

I I

(!Ccmtr.lli>,lrol'l~t

tiMW1t.1(p.n;..,_, tiMW1t.1(p.n;..,_,

,54'.lllVll. ,54'.lllVll.

I I

r

\1pmlraffllrr \1pmlraffllrr

~th ~th

.in.i

kd, kd,

,tadiiem ,tadiiem

O'r< O'r<

t

trr} trr}

~

. .

"'lh "'lh

rn':!rn.: rn':!rn.:

111C1nJl-::1o-.: 111C1nJl-::1o-.:

l~Omn l~Omn

sof

i:

10 10

' '

-.;ip -.;ip

biJ biJ

mi.iml[I\ mi.iml[I\

-1!.I_.,_ -1!.I_.,_

bolks.111' bolks.111'

m

in:;u

pmas.1 pmas.1

111 111

A A

of of

.,n .,n

\\'a.Ill \\'a.Ill

1111J!Ul

.-vn.

'-'"•

DPC DPC

1

,.,

: :

1t-: 1t-:

!'I('! !'I('!

llk,J. llk,J.

t t

cewmr cewmr

~.t:,.y ~.t:,.y

CONCRETE CONCRETE

Y,ihtct Y,ihtct

:

~ll

u

(Mmimllm!111:511 (Mmimllm!111:511

t

idr"°'1unoooc

t-ln t-ln

.100\

ll,urf ll,urf

l..md-btariac l..md-btariac

I I

·

:n :n

a

Alttnt.Wvcf)

lll

(),)I~~ (),)I~~

l

~«n."OI ~«n."OI

m1mm1101 m1mm1101

M M

'l;,fW~lu 'l;,fW~lu

~ ~

r--1~,c r--1~,c

Propritlary Propritlary

.\bu .\bu

ti

a a

:'ion :'ion

MASS MASS

tU1,.lfUIL1:r.ui~ri

IU IU

Th:: Th:: rm rm

:'¢.'111ro

12~1191lffi'll'.fdt 12~1191lffi'll'.fdt

·.J.b

\\':.lh \\':.lh

Far1111,htndtdanr.lil Far1111,htndtdanr.lil

b~~blmmaybcus.'dut!ltnlfaid,:,,ct~!!,,~lhalamnulsma

1enlilanonat-;,,,c1~,rni(r;1.&,i,,c 1enlilanonat-;,,,c1~,rni(r;1.&,i,,c

lk.'llit',t!I lk.'llit',t!I

1W

Tu

~ ~

hktr.iwi. hktr.iwi.

fonmtt fonmtt

, ,

• •

µir-

l1~ l1~

im.,nlM'IHrtiol~

"'.'In "'.'In

Whm

89.4 89.4

factofMll•

cl...- ~~, ~~,

89.Z 89.Z

119J 119J ·u¥!

~ ~

Any Any rrinfom:mcnt rrinfom:mcnt

~ ~

rfrir. rfrir.

89.1 89.1

~olr: ~olr:

89 89

,,.u11 ,,.u11

WW/Shftli119 WW/Shftli119

liti;ru.; liti;ru.;

CAVAN CAVAN

Al:b Al:b

/l))J /l))J

,:.:,n.,.ct.:: ,:.:,n.,.ct.::

millffllm millffllm

I I

FLOORS FLOORS

l l

'.\~~ '.\~~

R1i11form! R1i11form!

:-.,1Grn1trlh119001D111111gb :-.,1Grn1trlh119001D111111gb

Root& Root&

"""'''"'­

UM:T UM:T

__J __J

cmi,,lr cmi,,lr

o, o,

Dl'C Dl'C

~lbc ~lbc

1 1

,.zrJ ,.zrJ

in.-:,xpcYil! in.-:,xpcYil!

__ __

1

uli uli

-

Co. Co.

J

TION TION

CONCRETE CONCRETE

m::-. m::-.

Lh: Lh:

;lull ;lull

f\oln f\oln

_. _.

(Ill (Ill

t1o:n t1o:n

·nll;:.J ·nll;:.J l1iJ l1iJ

8' 8'

Con.TC'.! Con.TC'.!

,!ullbchid.~vn,,1,."'.!1.1..,,,i1lvhrr.in~ill'ha\)'roll.:r ,!ullbchid.~vn,,1,."'.!1.1..,,,i1lvhrr.in~ill'ha\)'roll.:r

Sllid Sllid

1

IJENTILA IJENTILA

Elln:JJl Elln:JJl

.Jm .Jm

f

fric.'d fric.'d

c.:,n

minim.lffl minim.lffl

pr&-roly pr&-roly

RIDGE RIDGE

l l

1

wti.:r: wti.:r:

iiull iiull

11U111Jf1:t= 11U111Jf1:t=

-1,iti, -1,iti,

Jioald Jioald

No.:-

~ ~

,1...-. ,1...-.

1., 1.,

ii_'CII' ii_'CII'

pJ.>il!K pJ.>il!K

J:,or J:,or

fo, fo,

COOTEHILL, COOTEHILL,

i i

CT,:'i:•cl CT,:'i:•cl

~ ~

.tiJi.~ .tiJi.~ .:cri:nl .:cri:nl

i7 i7

lrJd lrJd

A A

IJ IJ

p.-r•,.>1Ht:l p.-r•,.>1Ht:l

l!Ulnii

; ;

~,k ~,k

f'i~ f'i~

li!ld. li!ld.

;i

fu,r

DRAWING DRAWING

.litinj .litinj

To.' To.'

!\: !\:

i·ed11.-.ilnWIJflmllwpmai1i~ i·ed11.-.ilnWIJflmllwpmai1i~

'A-A' 'A-A'

CT

d.»r d.»r

.lull .lull

iii.ii~ iii.ii~

or or

L-'\.'t L-'\.'t

b.-

~ey ~ey

On On

wl!i~ wl!i~

,lull ,lull

91JU,'\J 91JU,'\J

o'Jtt.ir~r.l~ o'Jtt.ir~r.l~

-!i.iin~ -!i.iin~

JR! JR!

2m 2m

~ B

p.: p.:

I I

!~

rllt rllt

J J

DJ\! DJ\!

,it: ,it:

-

1tuo 1tuo

o-.i1r.k5P(l,-iti:Ji1SIO! o-.i1r.k5P(l,-iti:Ji1SIO!

·.h: ·.h:

inpJ inpJ

!.h, !.h,

1

n

h

,Mm~ ,Mm~

fi.V fi.V

J J

.,1r .,1r

100 100

1

wid..,-

BY:

b,: b,:

:

DOORS DOORS

.,tb:

,

\h)-.,; \h)-.,;

1

Section Section

Jl,1 Jl,1

dton dton

~: ~:

Ilk.ti! Ilk.ti!

ilt..J.h..~

AR AR

Ll'l.tru.:

BIS BIS

1 .lull .lull

Extension Extension

• •

i~ i~

l'C l'C

, ,

nl nl

wll wll

~~ ~~

bokcJ bokcJ

mtn mtn

,>o,;:J ,>o,;:J

\2mml \2mml

Sill

rult; rult;

10(1(1 10(1(1

f-OOrnm f-OOrnm

;..'l.'llft!l~ ;..'l.'llft!l~

CHECKED CHECKED

bt bt

..iMI. ..iMI.

,. ,.

~.:-:1 ~.:-:1

MAGHERNACALDRY MAGHERNACALDRY

h.1h h.1h

foMdMioo foMdMioo

n.t n.t

l.:t.=p l.:t.=p

1u 1u

S S

lid lid

• •

.x .x ,

lll lll

1'1) 1'1)

111d 111d

1)-pc 1)-pc

Y11th Y11th

lhicb,::,., lhicb,::,.,

~111 ~111

!fli

Ur.rm Ur.rm

is is

1n-J 1n-J

ahcnuti\dy. ahcnuti\dy.

~ioo-wll ~ioo-wll

ttq ttq

N.S<:p!lt N.S<:p!lt

ia!h! ia!h!

Clwv-' Clwv-'

m, m,

JOO.nm JOO.nm

'Ul

l l

,

-

or or

ta ta

a a

t/lkt t/lkt

,Ji...-J.. ,Ji...-J..

~nd ~nd

1ni:n. 1ni:n.

Proposed Proposed

P~ P~

AT AT

JB JB

,~.,_"".;~ ,~.,_"".;~

1,¢ 1,¢

romply romply

sun..~ sun..~

tnddi tnddi

tl'lro'A!h tl'lro'A!h

Hmm Hmm

8.."+.Ml..-s.inflt: 8.."+.Ml..-s.inflt:

bJ.k bJ.k

fn\i.bJ fn\i.bJ

ho!...._ ho!...._

1'rl,lfif.l(e 1'rl,lfif.l(e

a1''d. a1''d.

.

r~L

·

I I

(,(Om,ii (,(Om,ii

stn'l. stn'l.

l

\lll \lll

11tlh.s« 11tlh.s«

I I

1

plain plain

~Smtla]s,;hiDCd ~Smtla]s,;hiDCd

i-

~.t ~.t

SN!I SN!I

k k

o( o(

c,tl\,,...... ,i;c c,tl\,,...... ,i;c

;!ullb,:u,,.,d ;!ullb,:u,,.,d

~ ~

2&1 2&1

r~ r~

of of

!Ki~ !Ki~

l l

wl!.i. wl!.i.

l).)tt.j l).)tt.j

l

~lid ~lid

(or (or

r.lt r.lt

thred'\l thred'\l

~ ~

a a

Extension Extension

1U11: 1U11:

lltl"IS,&1)' lltl"IS,&1)'

lrJ lrJ

.Jr.i

BY:-

dtpdr, dtpdr,

tluoo!f, tluoo!f,

1)1 1)1

ltl

~n_!~ ~n_!~

from from

k>tg_ k>tg_

tb:n tb:n

1:mpl.ll: 1:mpl.ll:

.i,·d .i,·d

a9-iri.l a9-iri.l

Cb11l Cb11l

piato piato

dn~ dn~

pt<.'l' pt<.'l'

•• ••

;p!l.1fL'1rilllliJl..-1 ;p!l.1fL'1rilllliJl..-1

~ ~

!llllCT !llllCT

:irt :irt

~ ~

of of

; ;

.\II .\II

. .

bn bn

IOml!m~n IOml!m~n

8N 8N

the the

No. No.

ll\ilf: ll\ilf:

cen'.rtof,'!acflion cen'.rtof,'!acflion

micimum micimum

.t5t'n:i .t5t'n:i

~11Vie ~11Vie

tio!B tio!B

prtknbly prtknbly

.:,:oo-~..:!F1gur! .:,:oo-~..:!F1gur!

of of

JI JI

a a

pl~ pl~

i:i.c:-illf11L,'CI.II.Toi i:i.c:-illf11L,'CI.II.Toi

carool carool

protc.1cd protc.1cd

A A

i5mrulfflln-{lipti>~1~kr111yof i5mrulfflln-{lipti>~1~kr111yof

Of Of

~ ~

ia ia

r.:,Jllll.~ r.:,Jllll.~

pl.u pl.u

i; i;

Tk Tk

;._"f ;._"f

~ ~

md md

be be

A A

~ ~

fnmenrritod, fnmenrritod,

bol~ bol~

o•w o•w

JJUm.l' JJUm.l'

~KT!' ~KT!'

of of

DRAWN DRAWN

lr"JI lr"JI

~l

Poultry Poultry

in'.O in'.O

IN! IN!

m;rrr.ib.1'.1r~f

DI DI

on,:: on,::

fr.(d fr.(d

111( 111(

bot-> bot->

Proposed Proposed

CLADDING CLADDING

WII WII

, ,

I.I I.I

.tlkr•!II .tlkr•!II

i;'\ll\:o:lc i;'\ll\:o:lc

~ ~

t!l<' t!l<'

portal portal

be be

gull) gull)

Ii\.: Ii\.:

~

inJO inJO

i.li;pos,I i.li;pos,I

:h

t-c t-c

1 1 r r

'1

approwd approwd

SIDE SIDE

ro:lKm ro:lKm

;o."!.lml. ;o."!.lml.

Dcinqe: Dcinqe:

,.

IOmmN.}· IOmmN.}·

T T

l

rilM rilM

inf.,-.1111ilti.Joi>!o..

1 1

& &

'$fall '$fall

an an

our our

saxhK saxhK

C\: C\:

sirw1.:d sirw1.:d

HOUSE HOUSE

;'1,YJf~ ;'1,YJf~

holint,~o holint,~o

29111m~.lr,1,11biJ!Li.t~~ 29111m~.lr,1,11biJ!Li.t~~

Olt'I' Olt'I'

lllk"I' lllk"I'

~cfplrc.sJd ~cfplrc.sJd

; ;

io io

m m

ilb!Ylnl ilb!Ylnl

ii ii

«(I «(I

l

(ftlffl (ftlffl

~'J'l1li~ ~'J'l1li~

1

FOUNDATIONS FOUNDATIONS

l

olT;.:1 olT;.:1

Juli Juli

bot

bt bt

,-s ,-s

Pip,1 Pip,1

LIi LIi

-

:11(,pec.( :11(,pec.(

lt\,d lt\,d

fr..xn fr..xn

Existing Existing

of,~ of,~

;xf~ ;xf~

2Cm11 2Cm11

J~c,:,r.m."Cil.t: J~c,:,r.m."Cil.t:

pi,.

elm elm

l.!Ur\lt~( l.!Ur\lt~(

C C

forl'l.ti.!pl.i:esdwia~po:IIUl!! forl'l.ti.!pl.i:esdwia~po:IIUl!!

to to

skill skill

111"-> 111"->

min min

CLADDING CLADDING

1h: 1h:

11!( 11!(

(W (W

hlit hlit

X

Thtllllfflh:T(lfh;i)~dr.n.-.JbyasU!llbrdl50mmfla

:111.:b.it :111.:b.it

Don Don

mini= mini=

.wtrrrrl .wtrrrrl

rt'Q,Uired. rt'Q,Uired.

I'm• I'm•

00 00

§f'OUOO §f'OUOO

Ill Ill

to to

lobcrnl6 lobcrnl6

!ht !ht

is is

nC nC

ier ier

nnlUIIMI nnlUIIMI

.Til .Til

in in

tc.'1Tlbin~1iMi. tc.'1Tlbin~1iMi.

at at

!

0

n·hioailU n·hioailU

dnlld dnlld

!D',111 !D',111

p

r

'.

CONCRETE CONCRETE

ud ud

kl kl

ROOFDRAfNAGE ROOFDRAfNAGE

ROOF ROOF

'J i; i;

Pl

•ith-t •ith-t

Forstudllon1Nffltd.or Forstudllon1Nffltd.or

FotWllct!lrn\111thSfl,lm~ter~l~111ml.1o~llp('Ctllfrl.'DtS.lllccoocrrt.:four.rl.ilion FotWllct!lrn\111thSfl,lm~ter~l~111ml.1o~llp('Ctllfrl.'DtS.lllccoocrrt.:four.rl.ilion

trap, trap,

E E

~tioffi ~tioffi

I I

'.11.'(llll:'li '.11.'(llll:'li

IMW'.IOII IMW'.IOII

abo,e abo,e

, ,

UNIT UNIT

~1mgtborroof~c~60m8~rn ~1mgtborroof~c~60m8~rn

Wh!rti

~llr. ~llr.

111,:..ilbl, 111,:..ilbl,

coo,:ctp,..~i-Xi coo,:ctp,..~i-Xi

Holding Holding

111 111

·i,ilid1 ·i,ilid1

i»lt:ddo-."in,.1112\",> i»lt:ddo-."in,.1112\",>

mWlll:m mWlll:m

b.:: b.::

'"ott: '"ott:

miaii11-wof miaii11-wof

1

OOv.n OOv.n

Th: Th:

·Mldal ·Mldal

ptCTW11h:9((1l9C{lmmlNli1c-.micdupfrums..,!idstnta,mib,:UlnslQC(lmrn&q! ptCTW11h:9((1l9C{lmmlNli1c-.micdupfrums..,!idstnta,mib,:UlnslQC(lmrn&q!

87

~-oo..Trlf ~-oo..Trlf

J«p J«p

Bl Bl

~lly ~lly

~ ~

spttif11:J1i~SJN:-himyard spttif11:J1i~SJN:-himyard

0811 0811

to}'gutttrt1lth~ to}'gutttrt1lth~

L

111: 111:

810 810 OOwn-jlir:' OOwn-jlir:'

ul<-lkw.~:-

Glltttn Glltttn Sl.'Clll'd)"fmtl Sl.'Clll'd)"fmtl

J J

TRY TRY

DATE:-

0 0

POUL POUL

R R

Yelbw Yelbw

&ten!ion &ten!ion

Sh,,·.n Sh,,·.n

p p

t\; t\;

OUlflf!edln OUlflf!edln

Proposed Proposed

EXISTING EXISTING

SCALE:- To To

Consent of copyright owner required for any other use. other any for required owner copyright of Consent

For inspection purposes only. purposes inspection For

EXTENSION EXTENSION

s s

rs rs

PROPOSED PROPOSED

~nly ~nly

e

rs rs

Broiler

e

-

!:levation !:levation

Broil

J J

00 00

1

Broil

00 00

.

Ora,.ing Ora,.ing

1Ft

00 00

, ,

3,250 3,250

1:125 1:125

Uriit Uriit

_R~ar _R~ar

I I

171

8,800

050 050

,

I I

10 10

32

f f

Pl3nnirtJ Pl3nnirtJ

1 1

m

-

Capacity:-

PouTfry PouTfry

SHERIDAN SHERIDAN

No. No.

945 945

Capacity:-

a a

Capacity:-

Are

Stocking Stocking

Total Total

Stocking Stocking

Exisfincj Exisfincj

Unit Unit

House House

floor floor

DRAWING:

JOHN JOHN

xisting xisting

roposed roposed

Additional Additional

E

Broiler Broiler

jP

!

Poultry Poultry

-) -)

Extension Extension

Existing Existing

1

Proposed Proposed

Elevation Elevation

Elevation Elevation

00 00

200 200

:2

:

Side Side

1

1

Side Side

Elevation Elevation

1:125 1:125

Front Front

w w

e

Vi

200 200

:

1

Plan Plan

llii:11 llii:11

1 1

0

DurfWaltl DurfWaltl

R

l l

900mm 900mm

ftle ftle

' '

Than Than

(O!Kfflr (O!Kfflr

.. ..

:-

f.rnm- '-ol

Rool&WllfSl!fflin9 Rool&WllfSl!fflin9

Rrinl«ffl Rrinl«ffl

GIWnA~ing GIWnA~ing

REF REF

REVISIONS REVISIONS

ILE ILE

f f J J n~1

I

E .! :.

..

JJJ7

­

......

:;::)ffl

L'WO

-..

.~,

..

..

-,.;

~,

,

~-~

h,

:,t ';;~

.. • •• ,o.-...

l....,.,

LO u-1

(~ .

.

..___..

,

,:

.,_.~

.,_

c....

,>,

..

......

,~ ,.,

.,.. ...

"it -: ...... _,1

..

_

,= ~

ES

.. , ......

:-

,_

......

...

~·u;..,.J

'.1.V-2n

:•.

.

r"I

....

,r;_;~=:

u.

.. ..

,,......

o

o ....,.o;o- /

.._~4

--,_•

" ,

...

~,

'-<', .. .._

,.L•'-••"-,.

~~

~ .-~,,

J.

......

..

..,

,.,.a.,t'->OI, . ,, ... u , _ 1 ,

..J"::t...:

....

.

-. ..

. CLON .

;.."';~·,L

'"'"'""'·

....

._.,.,_

,i. . .. Beggan -'"P'...-..:•,-

l

·

, ~o~;i;;pn§~i,.::m

..

..

"' 1~7

1• : ~

,

,11< :_~

4i,b.-,,i..:_

.:.11,

'"'

......

,.,.

• ..

,1 :

)c

·

,......

• -

• -

... ,.,.,, ~

A, ,_ :

-~ . ,.,

~

_ ,,:. 7-5

.

, •H,:

,~--.

...__,,.., ,...,.

~.I ..

~

..,..

.,..,u,.

.

... MON"-GHA/J

ri

.:~

_.,

·

......

~ ....

...

"l;'--

b4

..

.. -.r __

•••

..

......

,:.r.J~•l.:1<•.::l.-,.__, ....

..., - Gr-"o.,, .,,

_..,,, ......

I

c,,,.._1,

.__

,,.._,

.

·

~=J"'""'"Jo

.,

~ ,>

, .,1...... -, ,.c,r_,,-,..

PH:'.H

.. Cto Co

WIIN!'n.::,,,~.'.::'.)fW.tll"I~ EPA Export 29-06-2017:03:06:18

..... E-tl,._1

,.. Joe . .. -

, ... .

•U __ ~II

,..

. ....

~

1·, ,u '.-7-:::::-:.~.r- ~·

>.t..!

.,.,...,_

u,;.;., .

,.

1<

..., J•la.C....:.. ..

.....

l

;

..

-

__. filli-L :..:.::~~.c·~·

"

-,

. ...

.

_

...:.-- ;:11.lp.

, · J

..,

......

ir.! ...

~,

......

...... Jre o

... -;

..__,_ ~

..

..., -

, i"

~

__

-

,.:.r

-,•

.. ,;<,-o

· 11.•

,., 1.1..

...

u.o.

...._,....1-...

..

ria:

......

,...,.,._,.....,.

..... ,_ . ---- ,rJ, 4"rbfJ1-=.J...,1!..!..cci,, 11--.

,.,....

..

rm,.,;li;, ._~ il.Jd-.:- ..-..,_,,..._

,-.

...... ~ lo.dut,,-~._....,,,._.,_

····---- ,

~

..,,

:i;~~--~t

;

-1

J .. • 6i)lmm ,

.,1

...

. • ::~ ~

.

,

~<.,

... ,..._

_i .

ShHUng

Ill

f'-. ~, I<.!

, ~ ..,,_,.,~~ ._-,_,.-.-.1-,,rp_, ·-- ..., .. ._

, , .. flJ

......

~ !- ::."~:::::

· ilh

1~t&..-nu;,JJM~

"i~

150-MI

.u1

Wall

&

sm:io>:•

1riJ1~11ilh

Rool

RtinfomdlonmlrD.,,,,rf\\all, GtMtlAgrltild:Mg

~

minirnJm

h.!J

A

UI\:'

~

·

»1

·

Qln,,.~!

1 r,..-;--.~·

J

I

lt,wj~

;u.

as

:-

.,.

ill

!5mm

I I

~

*":pl';mr,i:

tw

r:cra

Cini

~

nun 1

m

~·i11l11Xlli.1!xi1rn)'rol!.r,

1111111 :1:111:i:;;1;1:

11'

·.\i:h

lffl

1

FLOORS

I :1:11 ~ J

1::d

..

'1ll!:!at,

i

re

1.Al.1.-.r

i:om;,ly

CAVAN

,mpa

·,

ia.ll1

~--

~L.J7"..t

-

\lll

O:

r:r;r,l

COHCRETE

ill!lilill

M

Floort

.

-

h1».::1,UP(

°"'"*' I

1

11

11

~

a

)J

i'

I" 1

11),:lf)

Co.

- 1

88

Cort.."r.!e 1 !JJ .ullbo:IJiL, Solid

I I

- II

,

·

= y

I

-

II '

I fir~

= i

i

cc..,form

I

111J1illl'.J111

I

¢mbl .J__J__

1u:1 7

a

·~M~

INII --

ffi.QIW:t..1~ EIIPUJI

I

1,11111 · ,·:

';E=

: .

v.ill

;a.Rlld J.

pa-

I

-

ntd

\

111d

du'5

J;

i.r,c

1<l

sb

~,~

III'

1h)f \b.'I'

for

J!

,r:'

inltl

K'r'lllyof

~

Pip..-s

' 'I n~1.."ll ha),dn

~all»n.rn

lid

. ~,:t;

No.: ccmpl)·

c..-ntrJI

,

..

bad ---

nl

Sin

.\

1-, :111:,:

p,.T5011XI

m.:r1.triil1

J

J

.

llc"Tdoorsar~J.liO~!!o.l

COOTEHILL,

I ~

L___l,__

~c ,N.11

ro

aiut,:

I 1 of

:~

i ~

fin!tl

find

C»::rs

;if¥

,

~~-

'A-A

~I

tl-.roup

.

l.(Ommfl.ilf~~is

Cla.i:!in

1\III

!mfi:o

~ O.w

l tlni!E!g'

111-ith ---

,.111. 1111

.Juli\>.:

..lidini

1:i,,:1 Ill

li:-.el

\II

10m

~

'j

~.u To

On

m DRAWING

Pfd~) ,1

II

p(tjO;;tOO

W(lpt

85 75mm~ll-Jlipc

cootple1t

i/\Jll

urunl...:,,,mi."!

!'r.u'ld

~

i)WTI.

JiJ.iag

.,.\

.

il'l1

!m

!"'I)°'

6011

I

fit~

lyp:o

CLADDING

The

i..~r,c

.hall

.ilt

h:

!WI)' ?m

1h1n 1,r··. 1111•, 111111

di'f'l"',ll

~

ii'lt

t ,1 2

1

h

I0lllDIN)·

--=~

,!ic.li11!

&siDE II II

.

llr Nttdir,:z

I

.

lit'

Aider

or ·

'll

(11n

\>.:

11iu,-

OOOffS

Section 1:100 I I

~?3

P'ipn

'

.ihu

.....

bd

doon

1:

irofoot d..-io

.

1

~U

81$ ~../ltighl Juli i11itna..1W.

mill~ i~e

11k1>1.,1ot1le~~ificdinSl02

il lilt

,,, Th(ntm.:rorhl)\driir.atb)·asurxbrd

DPn

BY:-J8

1:1

l'l.'q\iimi

pt'UOO

IO

is

111. ~~ 8.' --· o-,

1:1· ad

·

ROOFDRAINAGE

-ROOFcl.AIJlJ100

·

lnfl

-

· lkl\l-s:-

gunnwidla

eta

8812 lp-4op'.!cn,:1hof C1um itttJ!'clyli111l. by

.tsfo gul~ thr,Dmrornl!in1lioo;,lf.ifll.lltdllooteadd1h.=11ullcrrun ;p,xilica1i00S129.Fir111:,ardDr:!inagc 00\1·n-pii,= htw!'C

i'1T1i111:

1;1,111:;

:,111:1:1111:

::

CHECKED

MAGHERNACALDRY

J

a

,

br

,

U1

•J

l-f

angk

ul

t1l\'.l'!

1r,'1

!

l(f!rnl

SUJ

,

60Jmn

»11,

h'

;it~

HI}.~

~

N d

<4.7,

~~ilt

AT

kbl

fn.:111 ~.:-rp

ila:111

:ir.

li!:lili1 ,kr,

rn

·

lY 31

:io

iapbteiot-c 26).

i.>

l!

lhlf.i1"1"'

M~~

is

75mm

1 lro.-)

01uw 2

on,

d

tr.t

.1.1i005.

.

1nd

lwil~

...

stt

w,,:,,:w:rcttrcur.d&oon

,.,.

U"t,:•r

l41ft

-x

M!I , c.nth

IN

t

Hmm,

I

&ll

cirri..\l

. BY:- Unit

'

pu-,U.\i

SU1IJ

lll

ulk.

n1

....

·~11trpt f

Jn

1

tit

l11, ai:J

, .1.nr., ,1,;r

·

..

( lkq

t~

~

solid »1c..

:

h1k

!111

11

lliilij'

1111

1 No ;h;ill b>

11 ljllt:

on

ilT1 .

,

..:-.1,.,

~IW111)cno,'-1:-.a

from

~udl:

f

11t

J.1-

Hpu:!,1,

'I 1

~

r,l

l:'lff

;

H011111\I«.~

mh vp

u

.pxiru·OO

1

,,

Poultry

l111

:11:: ii

!1

DRAV/N

fux

nnitd.

11

I

·,or

min,mld

J

...

11111~ Sllndticns

1111aJ1.o1

ii' .:.'Q.,.l 11 ,1 CllOO.'.I

1h

.\ 1

11.:,

t5 1 ~~

11p1

1

.;t.Jt,41111T..i

ftJ 1n

rramn

1

1 1, ITl

=.:- til

1

T

I.NI

d

:r

ir;;,

...

ioobb..--h,rrinfx.:mm1;lu;lbc'~lint~f,noJJlb1L

L--'

1J1t"'-'ul\.h. UUll.lf.L~>

.

..,~

HOUSE

1.l

I

c:il

u

;...,

porttl

q1,

11:· ~

Llll'-'-"'

Slan

lli

llt

M'~fot!II

I

Existing

or

1115

ll('fmtJ

600mm

-

xc I

I

~~,M

for

\\i\h 1r.-,

l

l

Oill'rl'.djt,tf,A

ft

C "-bdu:

k-

er r,.,

!<111:1D

,c.11fJ'Ulil

• II :I

...-tinfo.llldJ•

II

(,{(I !nt.."T.cl

1-'!t.:

f-OUNDAnoNS Pitn mdrd, I

ob

ProposedErflnsim

Out/irtedfnYeflow

clT

IM Iii

l

oolt,mJyb:Jll'".:d

I

rf

I

:

!~ 1 ".d1rl l"1ffi

?l~l:t•

~~lll:

nmlr

I

H

1.-...... ,..Jm..~

1 l

rJ,

m

Ill Ill tJ

,b I

l,i

E lt,;t

1:1:liiil tlM

~

r1.

llli m~-.

:11\.iu

I

UNIT

itric!

~,,,ilh,~pal(ftlunl~andinallpo,ulrJallr> ,

I ililil'!il'!if dld ;t. if'o

111ncbio111

h

d

..

h

Lil

Fou~lio1

pi.er

CONCRETE

I II

JiTI\ '-'i

u

1" .ilb'

I

~M'..._lfl("l'hi..::U.,.'\

,.:.m..tiln;1rt

h 1

For

ii' Pua

fo,

:

.

"*W:

s• ....,

il

~

L1lll(

• f.lllOI.J'.t• J

I :I'

,1

111.

B7.1

pi."1Wlllxs«lx900mmtluliscarrialuprltffl!idid BT ~olt!

CC'IICl\11: ,.,i.w Th: bolleJ&i.nwilh lh-p ~ m, II rni~irnum~r~mfmm ..

d.: Y.'btor ~olt: ~<>-+illcl.

ti ,,:rnd

TRY

DATE:-

I

111

!r

:

I I

,1

I I 0

1

:

POUL

..

r1r

R

11

'l

:11::1:1;:· 11:1,,:<:t

hi·,n

Lr

i

p 5

[II

: :1 -

As

111 I

-

I 111

I

EXISTING

:::

To

SCALE:-

;1.111:::ii

--

:ilili:::

I.

r1·1·1r11111,, 1

IJ

II ii'

: -

I

Consent of copyright owner required for any other use. other any for required owner copyright of Consent

I I I

= For inspection purposes only. purposes inspection For

I

11:· Ir

EXTENSION

I 111

I

I

111

~c...=== l

~rs.

Unit

'I'l

111,11l!l'ill 1q1111,

Broil

ers

I I

:;1lll'lll!.1'

Broilers

J

00

2

I ==

Broil

0

11'

00 nly

PROPOSED

O 35

0FL

Poultry 00

1

=

:1

:

1

14,

-

1111

I I !

.S80

20,900

IO

11

:-

35.250

f

II

Ora·.,ng

2

2

11111 11111 I

Elevation

m

.

I Existin

ii' II

capacity:-

983

No

1

Capacity

111

11111

1:125 Capacity:-

Planning

Rear

11

I

I

1

.

Area

I

Stocking o

on

T

1

SHERIDAN

II

Stocking

House

Floor

,ii ] I

-

kd m

er

,I e !1

t

opo

=-=.:...:=---====

:I

•r

r Broil Additional E.-.:isling

Tl' Ex :;

unTf

DRAWING:-

d

:ii

JOHN

1:1:1 se

,,r 1111

lit

-===

l11

roQo =-

11:, ·

ii,

P

1'111 11111

1:1;1

1

:

1

-='--=

111 l!ii' :

ltll

1

ExisrintjPouitry

1'I

1

;I

111111 i"

--===-

1111

l'I::,

1:1

,.

;,

Elevation

:1:1

Elevation

I

e

:

fl' :

:200

.

1

Sid

1:200

Side

,

:I ,

-

I

1

Front

Viev,,

200

:

1:125

Elevation

1

P!an

,!:xistin

.-

iJI

f I

Jl1

S

~l

Hi&•

[

Roi

908mm

F,le

ION

..

Tb11

S

:-

_

..

Gmtrr

Rff

Rool&WallS/w,gtjng

Sot

RN""1d(Hctrit(hm1'W1

._

REVI

FILE 1

n,::

-

~

Htl

-:::.rn

!'ir:

:?;?

n;J

-

<>

7

.n .Ji;

J,;

p n;

;

/

7

~~

t

CLO"'fEi

o

3 Beggan

1

:,r::-::>

;1~GHA1J

/r-

?:•

I o

:

]-5

.t

~n:

M

:Q

lOM

o EPA Export 29-06-2017:03:06:18

C

PH C

E-l}AIL

Joe WINI

1

Sheridan

Cavan

Co.

=====

John

Mr.

For

1619

Cootehill,

1\

-

REF:- Td.,

CAVAN

Plan

L1JI

W

U

====

Co.

-

Sheet

Development

O.:

:500

N

: 1 G Lgyout

Digital

.

S

.

Site

Maghernacaldry SCALE

Proposed DRAVIIN O

COOTEHILL,

:-

To.,

Shown

rn

===~=-

-

Acres

hectares

Area

65

BY: 88

,

Site 4

1

CKED

E

CH

J8

TO

MAGHERNACALDRY

ROOF

BY:-

All

POl~HING

111

r,.r,~

AT

FOR

-SOI.

D~CHARGE

B

PRIOR

i~.h141

FOl SU

..

ERI

w

elnU:..UOf

DRAWN

11tSl~1•t1

l0m2

1 ALTER WAJ GROIJND/IAJER 1

1,-

70'ii•Al

P11tC•t~

IJlt..,U

hS..r;;rw.;l".n-~a,,1

T

'NI

15

/,Jl11!1u

Ow

..

&ml

r!td:xtl!Dnc"".,..' th

2')

:J

r'.. D

11 Whl

NW s

C

mbar

EXTENSIONS

,

lfo,

E

UNIT

J

DATE:-

0

R

POULTRY

l1J,n

e,

p

S

As

:-

[ft

,• UNIT

.

., :

I'.­

=-.,:1

.

~

..

r

:

.&, _,,n

:

:

-,~

.,,.,

;:

•·

!• •:.- SCALE

,c-

L

-4·,· :!

;

W:

~.~

..

•'<

..

un

..

;•·

•lr

r;;,• 1

,

,

•:

.. ,,::

~tM

~

~_,

-

!

'l•

'll r

,

!~"

,

•: ~

!JlUC

·•· ,

,

r,-;:

r•

:J<

,!""" ft'c'•

"'•

l•<£~

l

•''

; ,·,

,,

,rc· ii Consent of copyright owner required for any other use. other any for required owner copyright of Consent ,:c .

~,·

l~

'·'

POULTRY

I;

!'I:

''" :t

(Lf

-~ t.!,!. only. purposes inspection For

--

,TC '·Ht

;

,"' I-€

~

'.

: :

:.·:,.,r;:,o-.r;

,t,·1 .

t•~

1-.t

l:

,-,

~

;

•L

,;&;([11.'l(!"'CL,,;HLI"•?

·.>

c ... c·,.

u,r

:.t

11 l>tH

1:

C

,,

II! ,

•!

:,,,_.,

~ 1>,E;

:, ____

.. i•

~!I NEW

1~:

~

1-

~;_l,.

:;r

~

:1'

.

"

_,,,;•r

uc~;,.,

'

;f" ;::

~

f

lil

';-,.,

..

..

·

l

.:,;.<:

,, ' .. c,u

1r;

H•CL

n·f=ru..-

.

f

::

1111 1

ll ·

,.,

l"'U. ":,,

: .,•,:,: ..

"-,(

... ~

c:

,_

,

,.

------

,,_; '""~

,:: ..

c: = !,,'.!]

·,3-·.·

•:

Ho"

• e

1

r,,.

""'-l- ",

cull

....

(•

;,

·:

.,

(I&'

,:1

;;•

~

anc -

'!';

,i::

,1:,"""

1:

~u·,

,;

•:,r

::;1 l',;n

;

<>a

=•,:,..:

L,__ Entr

h'

II

••:• ~

h:

,.~ l•u"'-"'''I c be

!M

(lF>

ubic

--

PROPOSED

P

E)jsting

Of

-

Al

~Ian

i

'J Hce

-- l

o ·

locafon

N

----

l3J

,

il

S

---

SHERIDAN

-

DRAWING:-

JOHN

7

------

-

--

--

--

-

REF

ll.E

I

REVISIONS ------,

FILE REF Fil, R,1

.1.1.l ...... Jollbrha ...... T~1,e Ira...__.,_._,_.,•.._ .... ~.. .., , .. .,._...... _ ...... _pa-! BT CONCRETEFOUNDATIONS

H7.I Foi1ud11ionPia, for Sl111ChioM:S1..1och1m, ihall t..-wn,\I L'!I, ff tlUill ~w ~;·= !: :: 11Ho1..-uo.:r.'1.( pi..'f rninmlll1l (',{~, t{,01run1hll i1CUTi..'li up fr,-r:1,._,hd,:r..'.l and i; 01,a q BfO ROOFCLAODING&SIDECLAODING .. JI lt.?Slf(tfrr.m ~ for ,l~lur.-s ~•th,~ ~:1::r 1han l!m arA.Itn JII p,.'IUJ fram,:,; 111(.:C'fMl.1~ li:-un~lioop1~r 1lull b.: !.((I , 91.1C)mm!bt i, cmh:J ~p from ii.- l~ ,._~,J,-tu!.i.:uiJbeat k.ht 'H¥'mmthp BBi? ROOFORAINAGE G11ttm 111d.O.t110 Pipn ~tull I.-.:fitted wmpk1t ',\1th n,.-.:~ br)(~Cl.ianiJ ,01t: For\1'111Chlommdtd, ,r poml rn.mn ..irritd on uak "Ilk, see Cl111t "-'-"'-"I) li\ed. TI1enwitier orba)> Jr.iinnl O)·a --iand.:ml15{hnm Julf-ro~nJ gul'.~'f h ,...... , 0,Slll, "'":" a,;folkt-.1,:- -~ r~~..!lMh1m; ~II !x ir,.:r~ m10 I~ pr.:rs J mm11num dr..rlhof NMklm or .::: ____:.._'OJ1Jll!:1.!J~.. 13'.k.j1:.11,;!fc,ranyuf pl11cstm1n 1hidn,,;s, 1:mml \l.ddr..'ll~, 1h-:ro.<,( of l~ :.ur-di.."(I.;mJ holo.hr.:tJ,,.,.." ·~~ !~,,,~ 1~ uoo-.~u'lnbmJtimi. 1f ,itllilll'1 al llfk'.'.-nd oi 111,:!WL,- run:uth,:,-,1i>< t trnmm 4 .. ,- ,i...... lJhUh.UlJ• ~ts.. Com,T'Jl.lnehioo;sh.:ill N OOlto.100\\n"'ith 4 So ].C.,m ~.dtlini00'-A~ 1:\)1:s, !i)!:1 1'.!"h t,ll - u.fftll--jlip,:i, requir.:d lmll-f'i~"S )!:.a.IIbe prot.."1.1rJ~1ir<">I dirr-4"1:. Pirc-; -.lull ,4:0mmlong. lklli hdi."Sin ba._~ pl.l!~to Na mmtm1m1cf 40mmifl fu.~ ~i,bcr~ ci;.:h;i~ ~ gruuOO~cl c\Cf a gully uaper pr:krrl} tl-.migha hrl mid t:,~ d rta: BJSC~c-, fer i111i:rmcdi.1!<,ur,ch1c,ns -hall N bcltcJ ih.n llil~ 2 \~ ••• r._ ... , . _.._ • ...... , .. ,,. '·:: ..: -- gull) hJf ~ lbc dao ..,,ur d!,fC',ll ~~cm. ..\II c!ra1M,,"Yit.all cmirJ:- 11i1I 20mm Boll in lo ~ .1, rninU)lllD]C'f ~ hclain~ ib.n roll,.EOmm l'ff!- hcb pb~ ~...... ,r,.,;1i1.:J1.il'll Sll9• F.n11)W l":nin~ .K!rnmfK'rn~rfrl:.leMid.'dalctntrcC'r~lallChion~ct,1fi~!~i I • I• ••~ ,,. .. , o r , ,._ ,., .:." ..::.: ---~:.:-; : :~- •..L!...~"-1""1 ..a.# HC'~ ®n h:hs shall ~ -«urrd 1nill~ ~icr b) using -Jmrn :\ -~mm ...-.. "' - ... , ...... ~I Jng-1.:11hicb ~ dtilkd !(l auurulJOQl~ 11!( 1k L~lt~ar< 100l 1tu-~ ~ r~~!':'-~ ··.:r·,.:-~·- "-:-:-: Lhrruglland futd -.:.'CWtlyin (OWld.ilK'flpal Mrn ix1lri~ C\:TKme•.\ ;.ui~~ . · ,. --: tc~K shall N ~ lo k«r belts m crnu1pc,1ticn for ~..N rill~ alli~ !'('Wini ··· t··: ~· ~ cm.:rrtt1Figur:26i . .. ..,...~""'~ ~ (_llarh,,_.io~ .ir.p IS"(I?" -:b..vlll.!.J -- •• -. -y:·•·- __,._:..-;:_::-C"I:,'· .. .. AJ.I ...... _...... 4...... _.. -' n.,----- Section On X-x· ,- .....::~-:: ·-----":-' ~. ~ 1n11\c ...... "--ora,,.. "~I'!:,tn:hl('r,~ dr( clf,-(l m fC'tll"rO;Jl1c,,Heil; rcifilmt'°,.-(r.t>!!JII /;'( t.'!al .. ~-r- :_::!_=-:·'-,~::=--:_ ) ' .:-::_:!'_.:; ·-:_· '':_' - =~==:'_'T-/ __ ";·_-_=~ . . J~im ' ' . ,__...... 1-- ~1 1:100 .._._ ..... •• .,...... :~i· <~:;:/.: ~~;',-hJth~~~:~?!)r~7 i-~·(~;~ :\ort: P:t1ffltancb« l:(,;1511\e.) ~ .1.llc11edin rlac~ c( ~-m N'\l; mi 1c.:dtfk-:. m ~~~-~grl;\t:::~-2:.l-:;;{;l~ir_::~ .:~1?-:.\~~~; )llCU. :md LlbLllkd.in AACIxcoo1an.c 11ilti the maoofxmr

I :!!-4.1.1.-,.n._.. Solid Floon ,hall be .1, miolmtLrn125mm l'OOCJ"i:I~ 1 1;.J sn'O.'th11i1h a non-l;l1plinish ,\U tb.-ua shall I:'< to Ci;:ntra.l v.h(re ,.-,' _,--~- -. ·------"-·- ,._._.._ "'' doon wiJcr I !m shdill!-[hi~ pa,~ Ii~ -...'' --- ::i: ·~ ',-.._,, '•:· ,,, ,.._..._,. .-- "-( -, J.,;"_ ... , "1:LULUnply with B6 minimum150mm h.lse --· ,._ ...... -~ ~= Cone~ fLlllit aru\t \ lllrJ-cor: shallalso bes.liding The ~idin~ ~r WII be 1i11N3lld l'm:ted ;is pa n,;:inufa.iurm • -, - ~allbclilclcooipa,.-i(dwi1h1lbf.uingo1l1cl\)'f0!1Cfandtq:,p(d11oithfinc!,lf,J_Al1 i~;lru;ti"'llS for th.: si1~ .;rid ,wight or iloor ~;ieJ. A ~1~ ii-« SOO\h.lp

, ~113--~-

!~ l!l!!J!!.!l!.i.!JJ!!l!i!!!l.!l!ll::-'1

'tr-..-111 •

For inspection purposes only. Consent of copyright owner required for any other use.

ll

II

e):fc,llet" Floor l\r~J 1827 l.1rt,r I 19..(tli1 I IFt)I Stoc:~1n~ C.lip.,clty :- 37,400 00 Broilers

f Ol,11Area lni;-t.uding .!ito,.., L Pt,mt Jlo.:Jof11 2 1 I fJ:119.6•1 m f 19,B77-23Ft ) 7

-:- ·= ,l 7 ' :,~- --·;,r=..--~r- - •-- :,~~,- --- ,.~.i-- -•- 1,r-r.1

/.'

REVISIONS p R l'.i ~I E C T Joe Beggan

JOHN SHERIDAN - PROPOSED NEW POULTRY UNIT AT MAGHERNACALDRY TD., COOTEHILL, Co. CAVAN CLOMli?r CLO:IES Co Mm~AGHAN DRAWING:- ~lann1n•JUri·,ing Only SCALE:- As ShJ•111n DATE:- October 1116 DRAWN BY:- JB CHECKED BY:- J B DRAWING NO.:- u1nrn - 01 Pn :'J.t?-S13.tl / J37-N2.tJ.t7 E-/JAI~: j~oe;;i ~:::,n<>,e1r:'.:fll n~1 'llffll en:::.t"'!!e-::~n;·.Alin~::jfll

EPA Export 29-06-2017:03:06:18 I ILE REF F,I, Rel

..

l..2! Li-Y$"1._l ~ l\ ,:~"'~'U. :, -: HEi O.lr (., ». o ! : .. ·; 4' , . /:[; :'\ T>-• t," :f &\I,,~ HhC• {~ -.,,.,_, ,..,~1 p --:,,·,:-..{ !r<,0..) r-# 1,: l T• Y1 •Ii

Ir S fff ~=·:·,:•OL \l- !ICf Applic.antsSiste~ DDwelhn1

f>-~ --~ • !>-\ -~ \~ ! . f' Yl.ll> ;.><&•• ~ CL[IP[t T:, fl>;\C! l .!IR i' =·•:.t'-'. >-1\I-Eli 1>-&\ 2::-- .. J.i.:111' 1-11: u.:. ,~TI£'"-~"~~ (IFS 1:.£•&• ~~l':>llll 61!; :~ilN[C ~ •E>'T ;;till; Tlf."'l'f~'I lM •:u ~ .::.-.1.ni,.1·E•,..__, •"c.:- .. , .;~ 1..-r "f.'if =• r.t >c.-:·,e:, .!. >-IJ "·":•I \J :;_; (I; D.'-""' I! .0..:(fff.•= ,~ Cle>- Y _;~oU'I Sl'".lt Tee :·:~r :• o·u:,"c, ~c _,.,,Ire r.: ;; ·;; E£ ;:.hr;,-._, IJ'l'\K'-"T r•, we... S11•L c••1'-..::E o. ~-: uH _ H: "iH l I ,,ur; ><.:.IE;ccH ac.::, ru Site Layout Plan Maghernacaldry Td., Cootehill, Co. Cavan O.S. Digital Sheet REF:- 1619 SCALE: l :500 Proposed Development For Mr. John Sheridan

Locofon 01 Pubic No~ceAt Exis~ngEntrance

Site Area Shown :- 4,65 Acres For inspection purposes only. 1 88 hectares Consent of copyright owner required for any other use.

11 .!&r•d Pr 111 W,1,1) 11f'lp t 11,~ WJud:iW,Ul'ro,,l,,Jel ,i i.u~, o r llW-a ab ~,11Ptrf ·.~Jt u Jteonc.t 1HEml·,uJ or,....,,

50m2SUB-SOIL POL~HING ALTERFOR FOR ALL ROOF WATERSPRIOR '------Jo!JilAL'.ll;;:HA;.:;cTO GROUNDWATER

REVISIONS .J = E== c ~=T======0 Joe Beggan

JOHN SHERIDAN - PROPOSED NEW POULTRY UNIT 13. POULTRY UNIT EXTENSIONS AT MAGHERNACALDRY TD., COOTEHILL, Co. CAVAN CLONKl?rC, CLOOES Co Mot1AGHAN DRAWING:- Site Laput Piao SCALE:- As Sha;11 DA TE:- fi,Ji2mber 1016 DRAWN BY:- J B CHECKED BY:- J B DRAWING No.:- EtlPLHI - :J\ PH 0~7-519-17 t J37-2nno E-1/,"-IL: f=~;r;i~a.~;r:::.;n n ~I '111111 ~-='.)f~-;::')fl;Ulin:;J -:::)fll

EPA Export 29-06-2017:03:06:18 FILE REF LANDOWNERSHIP MAGHERNACALDRY,C00TEHILL, Co. CAVAN DIGITALMAP REF.:-1553 OUTLINEDIN BLUE

1835-1836 1908-1910

ITM CENTRE PT COORDS 662287,812552

DESCRIPTION

MAP SHEETS

6inch MN023 MN026 CN017

Authorised Internet Map

...... _aa...... _..o...il =-..=r.:-~=.....,.-'*'·--·--~a.._...... ,._.,.__ __....,__ OliaiaEna ...... lr&aa_ _ _,,,__,._...... ,._ For inspection purposes only. Consent of copyright owner required for any other use. Gn..cau....-.~dllllt­ ...... adllip!al.1aliilr,llda)alatai"iliD ...... blmladlpeallllmtiiMIUftli .... ,..,,.,_•dlap:lit. ..""' ..... ,...._.., .._ ffllRldlc:ed•~il-,basti,-,-..._ .. ,.._,.._..d .. ~oal!M,...... _,bea::llnillJllaatt.A••lilncai• .-lalill•dall~~a11a-.a1a n,atad:ar~IIIMl'l'illlamd ...... _.ala

·---.. ...,.__ll!lnaidlclllllillOlll:laa~ra tit.- ...... ~- ~-...... ------""'""­radD..,. ... Olaltnpal~lllanl.

0 Suirbhei"eacht On:lanttis Eireann.2016 ~ Ordiance Survey Ireland, 2016

,fl_ , 811644 N 0 200 400 600 800 1,000 Metres 8116« "' I Scale:- 1:10,560 U~L _J Plot Ref. No. 19728214_1 Scala:- 1:10,560 Plot Date 16-OCT-2016 ~ f\ 0 500 1,000 1,500 2,000 2,500 Feet

p R 0 J E C T Joe Beggan

JOHN SHERIDAN - PROPOSED NEW POUL TRY UNIT AT MAGHERNACALDRY TD., COOTEHILL, CO. CAVAN CLONKIRK. CLONES, Co Mor;AGHAN DRAWING:- LandOwnership Map SCALE:- 1:10,560 DATE:- Oct. 2016 DRAWN BY:- JB CHECKED BY:- JB DRAWING No.:- ENPL037-06 PH :047-51847 / 087-2924047 E-MAIL : joebeggan gleircom nel www encore-consulling com

EPA Export 29-06-2017:03:06:18

EPA Export 29-06-2017:03:06:18

nel nel

,

com com

com

ir

9'e

087-2124047 087-2124047

nsulling nsulling

/ /

o

CLONES, CLONES,

re-c

Beggan Beggan

joebeggan joebeggan

co

: :

en

MONAGHAN MONAGHAN

047-51847 047-51847

. .

:

PH PH

CLONKIRK. CLONKIRK.

WWH WWH

Co

E-MAIL E-MAIL

Joe Joe

2016 2016

.. ..

......

_... _...

_ _

_ _

_ _

liln::aill liln::aill

Map Map

_ _

2016 2016

_ _

,..110 ,..110

E~eann. E~eann.

......

milllnae

......

••laduila ••laduila

.. ..

......

COORDS COORDS

......

~-~En. ~-~En.

Ireland, Ireland,

~Odnil: ~Odnil:

~-

1na1. 1na1.

......

Ordanais Ordanais

.. ..

PT PT

__ __

SHEETS SHEETS

~_...., ~_....,

n.~--~cfl n.~--~cfl

______

N N

Internet Internet

Authorised Authorised

S..vey S..vey

-~-

A A

______

______

,.. ,..

......

,, ,,

llilrlCll.d..lC:.-

.. .. ct..isl

Map Map

MAP MAP

______

_.,_...., _.,_....,

DESCRIPTION DESCRIPTION

......

••tflllllldl;acall ••tflllllldl;acall

1553 1553

.. ..

CENTRE CENTRE

~ ~

...,_....,.,,""*"_ ...,_....,.,,""*"_

......

Ordnance Ordnance

Suirbheireacht Suirbheireacht

,.._,_.....r1 ,.._,_.....r1

ri::al.Rl•...-••twmad ri::al.Rl•...-••twmad __ _....., _.....,

...... Nillil:aabi:ias,bald!RO

......

__ __

......

© ©

......

-·-- ©

ITM ITM

llpadlalr:lar___..il-,bll•.,., llpadlalr:lar___..il-,bll•.,.,

.. ..

__ __ Gadl~•cr.aat.McaalilladlDClllillllll!a

......

....._.,~, ....._.,~,

_._ _._

...... , ...... , ,...,._.,,..., ,...,._.,,..., Ollilllliia.-

,.. ,.. ------

-

1553 1553

Digital Digital

662287,812552 662287,812552

812337 812337

812767 812767

. .

~ ~

g: g:

o

REF.:-

__, __,

0~ 0~

-

MAP MAP

ENPL037 ENPL037

______

-----, -----,

1 1

. .

_ _

DIGITAL DIGITAL

,

:::;:;==-

. .

1 1

NO.:-

_ _

19728214 19728214

DRAWING DRAWING

16-OCT-2016 16-OCT-2016

No. No.

SISTERS SISTERS

Date Date

Ref. Ref.

CAVAN CAVAN

NG NG

T T

Plot Plot

Plot Plot

. .

CAVAN CAVAN

EU.I

JB JB

APPLICANTS APPLICANTS

CO

DW

-

C C

:

Co. Co.

BY

D D

E E

E

Metres Metres

------"

-

CHECK

250 250

Consent of copyright owner required for any other use. other any for required owner copyright of Consent

COOTEHILL, COOTEHILL, C00TEHILL, C00TEHILL,

For inspection purposes only. purposes inspection For 0

/ /

ROAD ROAD

To., To.,

R R

Map Map

COOTEHILL COOTEHILL

l l

.

200 200

p p

TO TO

SHERCOCK SHERCOCK

JB JB

Feet Feet

BY:-

MAGHERNACALDRY, MAGHERNACALDRY,

II II

500 500

PLACE PLACE

150 150

DRAWN DRAWN

MAGHERNACALDRY MAGHERNACALDRY

400 400

3.19 3.19

2016 2016

AT AT

Rural Rural

100 100

Oct Oct

300 300

___l__ ___l__

-

:

UNIT UNIT

E

T

DA

i--

200 200

50 50

I I

I I

\ \

1:2500 1:2500

. .

POULTRY POULTRY

100 100

NEW NEW

SCALE:-

:,,k-~1--1 :,,k-~1--1

0 0

0 0

2015 2015

2000 2000

PROPOSED PROPOSED

RED RED

:2,500 :2,500

:2,500 :2,500

-

1 1

IN IN

Map Map

-

- 1

:

:

Levelled Levelled

Surveyed Surveyed

Revised Revised

LOCATION LOCATION

Scala

Scale

locat,on locat,on

Site Site

SHERIDAN SHERIDAN

OUTLINED OUTLINED

SITE SITE

~~~--~~-

i i g: g:

~ ~

:!: :!:

812337 812337

812767 812767

JOHN JOHN

.. ..

DRAWING:-

REF REF FILE FILE

Maps Maps

• •

• •

Michael Michael

Eamon Eamon

......

John John

Sheridan Sheridan

Fitzpatrick Fitzpatrick

Galligan Galligan

-Proposed -Proposed

. . Appendix Appendix

For inspection purposes only. Consent of copyright owner required for any other use.

Poultry Poultry

-

Letter Letter

-

Unit Unit

Letter Letter

at at

Maghernacaldry Maghernacaldry

Of Of

Of Of

Confirmation Confirmation

No. No.

Confirmation Confirmation

Td

.

2 2

, ,

Cootehill, Cootehill,

Co

. Cavan Cavan EPA Export 29-06-2017:03:06:18

:!: :!:

,;., ,;.,

-·., -·.,

90i 90i

Company Company

November. November.

""""' """"' ./::::i!l

:

Jl/ Jl/

,/ ,/

DAFM:-

·)t}llllS°"ections ·)t}llllS°"ections

2016 2016

''.ijr ''.ijr

· ·

,:1111:·::ri,,,, ,:1111:·::ri,,,,

Contract~r,J~~~

This This

on on

manure manure

&umm &umm

.::;;' .::;;'

Form Form

Farmers Farmers

is is

!J !J

::T>''' ::T>'''

......

,,fiHlF ,,fiHlF

RE: RE:

EFK EFK

Lo Lo

d d

3 3

will will

COl]

£i6MJWe £i6MJWe

fertili:ser fertili:ser

submitted submitted For inspection purposes only.

()47 ()47 M~::~ty;ri~rfco M~::~ty;ri~rfco

returns; returns; Consent of copyright owner required for any other use. Collection Collection

accepting accepting

~!.~

be be

are are

"

.Jrorn''t11e .Jrorn''t11e

Maghernacaldry Maghernacaldry

2()894 2()894

,,,,:> ,,,,:>

No. No.

fj,iupabticfi fj,iupabticfi

transported transported

'

,::ilHH' ,::ilHH'

that that

projected, projected,

and/or and/or

in in

To To

elotKb elotKb

to to

~~U~

For:\I\J~;~!~~eridat~li;;;:i,· For:\I\J~;~!~~eridat~li;;;:i,·

keeping keeping

Earg~

of of

'

Prem]sos Prem]sos

DAFM DAFM

and and

'4ifuilen' '4ifuilen'

whom whom

.AwMc .AwMc

holding holding

•eoilet"'s •eoilet"'s

in in

~'~ ~'~

''

in in

the the

& &

in in

in in

_

-

P

with with

it it

within within

the the

covered covered

a a

itzpatrick. itzpatrick.

production production ......

Coolehill Coolehill

~Mn ~Mn

siruan:d siruan:d

may~~: may~~:

087 087

of of

position position

manure' manure'

oroer oroer

manure' manure'

Departmoot's Departmoot's

John John

the the

829 829

of of

( (

trailers trailers

of of

at:-

~bj,.manure ~bj,.manure

Sheridan Sheridan

time time

CLpd) CLpd)

to to

(Registered (Registered

Co Co

200 200

1657 1657

,shaJI ,shaJI

Cavan Cavan

of of

collect collect

Cavan Cavan

.. ..

composL composL

allowed. allowed.

for for

> >

be be

regulations regulations

300 300

use use

and and

specified specified

tonne. tonne.

Agricultural Agricultural

as as

remove remove

an an

organic organic

and and alJ alJ EPA Export 29-06-2017:03:06:18

/ /

1,,:· 1,,:·

H' H'

rl rl

Yours Yours

Dept Dept

Should Should

sincerely. sincerely.

of of

AU AU

Agriculture Agriculture

you you Agricultural Agricultural

For inspection purposes only. records

Consent of copyright owner required for any other use. require require

contact contact

(Document (Document

in in

any any

me me

accordance accordance

Practia: Practia:

at at

further further

the the

3s 3s

above above

foc foc

information information

etc.) etc.)

witb witb

the the

telephone telephone

i= i=

i~::r i~::r 1~m: 1~m:

/ /

shall shall

protection protection

•nitrate~ •nitrate~

:~~i~::;::r :~~i~::;::r

t···· t····

.

. .

::niH!

be be

please please

submitted submitted

· ·

i(

.::·· .::··

number. number.

regulations regulations

~i

of of

i

:,:

do do

Water). Water).

r r

......

·::::·

.:

!:::::::!· !:::::::!·

.,,;Em

not not

· ·

. .

· ·

.

. .

to to

: :

.

hesitate hesitate . .

;, ;,

iH!:::: iH!::::

··:::w ··:::w

and and

the the

. .

i' i'

(Good (Good

to to :;~~!~:::/g:· :;~~!~:::/g:·

EPA Export 29-06-2017:03:06:18

. .

1::t 1::t

•• ••

:.::::::1 :.::::::1

·::

:

:: ::

. .

:; :;

.. ..

~ ~

ff ff ~-~ ~-~

.: .:

~!' ~!'

s;~H

·:

:

· ·

H: H:

~; ~;

i i

~~ii~:;: ~~ii~:;:

. .

:i~ :i~

~ ~

~I ~I

J J ., ., .,=,

.

r:

l:

i3.a1,.J,~

.Pua

~3

A

Jn

-

ND

-

Po££

------

OF

I.LJJ.J.OM

Pnoc

CPNl::lEL1..

;:J-H

.....

R&:G:U!>A:-C(QJJ

aE J

£..S.SED

t

.

!!

!

·;;

:

:.

'

I

(T

J"i

I

TRAN~PQRTiNG

f

icHae:J.

Co

MA"'J,

P.t;cDulT.S For inspection purposes only.

Consent of copyright owner required for any other use. (AV4N:,1

-

I

.

(

CoNcEnN.

G::84-bivAN.,

f"

LSNDf'CTAkE

--.....---

c.)

J

I$

N

Na. a

hJj

A

REG:1$

t-1

cc.c,u

i

'

'

Loc.n-rEQ

Alt

Dl,

Michael

7o

~

-087

gi:f 7)rn

~;m

81-

IEL!

..

Co

:

11 ~

a:,,:k::

1

:

~F

_

~

cg.:.

ED

.

_

Cavan

Sli!MPwf'

i

..

gg

:~!

cam

E

_ 76 :: e.~

'

tl

AY

_

1665_1..:.....·

W;47'4i

ai

.

~~

~

1

~1JC]

~ttnl61ft'.K

L

1

~~H~

-3:'.

f

·

.

l

1 ...

!

~

.

:

~!

+::

1':l'RI/CUf

.:_

-

......

:::;

t

;;

Bl.),.

-rHE

/$

hJJ

: H:·=u:=

j

!

P'

- !;;

,m!

~

'"Ii!

-

,,

l:

11

=

·"t,_HllHI

= EPA Export 29-06-2017:03:06:18

TTill

.,:,·

::

..

.::

i: 1:;·

:

H ,

.,=1;:,:!f![:h.

:!i~~I~l~t

w=

,iw

•.

:~irn~

··::,

.,i!)Jli!i

.::Jijj('i;:lT

·:::·

,

'

·"·

;rn'

Maps Maps

• •

• •

• •

• •

• •

Teagasc Teagasc

Teagasc Teagasc

Groundwater Groundwater

Aquifer Aquifer

Bedrock Bedrock

......

Fergal Fergal

Mc Mc

Map Map

Topsoils Topsoils

Entee Entee

Subsoils Subsoils

Map Map

~. ~.

Appendix Appendix -Proposed -Proposed

Vulnerability Vulnerability For inspection purposes only. Consent of copyright owner required for any other use.

GIS GIS

Map Map

Map Map

New New

Poultry Poultry

Maps Maps

Unit Unit

Map Map

At At

No. No.

Knockaturly Knockaturly

3 3

Td

.

, , Monaghan Monaghan EPA Export 29-06-2017:03:06:18 ,~;~'t1.· Legend /I;:""-=~ ::~. John Sheridan - Aquifer uata Map E!ll Bedrock Aquifer Faults I - Bedrock Aquirer Fault1; 660000 Bedrock Aquifer Pl - Poor Aquifer - Bedrock which is Generally Unproductive excepl for Local Zones

c:=]0s1 Bascmap

H

For inspection purposes only. Consent of copyright owner required for any other use. ~,_A_C.,E_f:·><

660000

N Scale: Map Centre Coordinates 1 :25,000 0 0.175 0.35 0.7 mi (ITM) 662,287 812,552 Snapshot Date: October Geological Survey of Ireland W©E 26, 2016 0 0 .275 0.55 1.1 km s Ordnance Survey Ireland Licence No, EN 0047216 This map and its data may not be used or reproduced for commercial purposes without the prior written permission of Copyright holders. © Ordnance Survey Ireland/Government of Ireland This map is a user generated static output from an Internet mapping site and is for general reference only, © Geological Survey Ireland/Government of Ireland n;:it;::i 1:=ivP.r~ th;::it ::mnP.:=ir nn this m;:in m:=iv nr m;::iv nnt hP. :=ir.r.1 ir.::itP. r.t 1rrP.nt nr nthP.rwisP. rP.li.::ihlP. tiA::in M!:it~ /r:'I nnc.nC::trootf.,1~n rnntrih1 ,+,..re:: EPA Export 29-06-2017:03:06:18 ·=-, Legend ,,•~,,...__~, -~·--c=,, ·-~-.-· . ~ John Sheridan - Bedrock Geology Map J Bedrock Structure ~ I -11F1-2 660000 Bedrock Outcrop Outcrop

Generalised Bedrock (Rock Unit Groups) Silurian Melasedimenls and Voh;;mics

~ OSI Basemap

For inspection purposes only. Consent of copyright owner required for any other use.

660000

N Scale: 1 :25,000 -@ o 0.175 0.35 0.7 mi Map Centre Coordinates (ITM) 662,287 812,552 Snapshot Date: October 26, 2016 Geological Survey of Ireland w : v E 0 0,275 0.55 1.1 km s Ordnance Survey Ireland licence No. EN 0047216 This map and its data may not be used or reproduced for commercial purposes without the prior written permission of Copyright holders. © Ordnance Survey Ireland/Government of Ireland This map is a user generated static output from an Internet mapping site and is for general reference only. © Geological Survey Ireland/Government of Ireland n;:itr1 li=i vP.r~ th;:it ;:mnP.::ar nn thi~ m:in m::iv nr mi=iv not hf! ;:ic:n 1r;:ifP. C"J 1rrr~nt nr nlhP.rwi~P. n=!lii=ihlP. t.A~n r4:::d!:) lr.l nnonC:.tr,:.. :. thA ~n ,...... -,trih, ,trvc: EPA Export 29-06-2017:03:06:18 John Sheridan - Groundwater Vulnerability Legend Groundwater Vulnerability X- Rock al or near surface or Karst 660000 E - Extrem e H- High AWAU M - Moderate ~ l-low

' C]_os1 Basemap

T' I(;:,..,_ ...... ~

DRUMBARKH .I -, .

For inspection purposes only. Consent of copyright owner required for any other use.

• ~

I .. N' Y ' '

660000

N Scale: 1 :25,000 0 0.175 0.35 0.7 mi Map Centre Coordinates (ITM) 662,287 812,552 Snapshot Date: October 26, 2016 Geological Survey of Ireland W E ~ O 0.275 0.55 1.1 km s Ordnance Survey Ireland Licence No EN 0047216 This map and rts data may not be used or reproduced for commercial purposes without the prior written permission of Copyright holders. © Ordnance Survey Ireland/Government of Ireland This map is a user generated static output from an Internet mapping site and is tor general reference only. © Geological Survey Ireland/Government of Ireland n;u;:a l;:avP.~ lh~I :=innP.;:ar on this m;:m m~v nr m.:1v nnl hF! ;:arn ir;:af P. r-.11rrP.nt or nthP.rwi~ n~li::ihlP. f\ft!:ln rl!:if!:I (f.'i nt'"lonC:.trootr-.11!:in rnntrih1 dnrc: EPA Export 29-06-2017:03:06:18 John Sheridan - Teagasc Subsoils Legend Teagasc Subsoils Alluvium

660000 Cutovcr raised peal Bedrock outcro p or subcrop lacustrinc r. cdimcnts Made ground Till dr:rivcd fr om Lower Palar.ozoic s.:instoncs and shales Water

t Josi Bascmap

For inspection purposes only. Consent of copyright owner required for any other use.

660000

Map Centre Coordinates Scale: 1 :25,000 "" 0 0.175 0.35 0.7 mi (ITM) 662,287 812,552 Snapshot Date: October 26, 2016 Geological Survey of Ireland W.E 0 0.275 0.55 1.1 km s Ordnance Survey Ireland Licence No. EN 0047216 This map and its data may not be used or reproduced for commercial purposes without the prior written permission of Copyright holders.

C]os1 B.iscmap

For inspection purposes only. Consent of copyright owner required for any other use.

660000

N Scale: 1:25,000 0 0.175 0.35 0.7 mi Map Centre Coordinates (ITM) 662,287 812,552 Snapshot Date: October 26, 2016 Geological Survey of Ireland W E • 0 0.275 0.55 1.1 km s Ordnance Survey Ireland Licence No EN 0047216 This map and its data may not be used or reproduced for commercial purposes without the prior written permission of Capyrighl holders. © Ordnance Survey Ireland/Government of Ireland This map is a user generated static output from an Internet mapping site and is for general reference only. © Geological Survey Ireland/Government of Ireland n;:i1;:i l;:ivP.rs th;:if ~nnP.;:ir nn this m;:in m~ nr m;:iv not hP. r1r:n1rr1IP. r-JirrP.nt or nthP.rwiSP. rP.li;:ihlP. t1.1t!ln rk1t~ fi:l f\nanC:::troatiA~n rt"\nfrih, ,trv~ EPA Export 29-06-2017:03:06:18

Maps Maps

• •

• •

• •

Washings Washings

Interceptor Interceptor

Silt Silt

......

John John

Trap Trap

Washings Washings

Sheridan Sheridan

Details Details

-Proposed -Proposed

Tank Tank

. .

Appendix Appendix Details Details

For inspection purposes only. Consent of copyright owner required for any other use.

Details Details

Poultry Poultry

Unit Unit

Tank Tank

Maghernacaldry Maghernacaldry at

No. No.

Details Details

Td., Td.,

4 4

Coote Coote

hill, hill, Co.Cavan Co.Cavan EPA Export 29-06-2017:03:06:18 Tel: + 353 (0)59 9159100 Fax: + 353 (0)59 9159831 Carlow Concrete Tanks UK M.obile: + 44 (0) 7540 564 276 6mail; sales@carlowta nks. com

2500 GALLON (11.36 cubic metre) TANK

3.050 (10 ft) ·

Lid with 9" pot Lid with Standard Lid with Slatted Cover with Safety Manhole Standard safety Manhole

Lid Plan Options

0.175 [7")

2.315 (7'-714") I

!, ~L . I l - .. _. ' ..

For inspection purposes only. SECTION Consent of copyright owner required for any other use.

1. Select lid suitable to your application. Inlet and outlet 2. Select inlet and outlets location if desired, mark location and size of COiiars available on these on the drawing. request. 3. Fill out the farm order confirmation with drawings and post it to out office. Tanks require a level, well compacted base of Cl 804, thickness of which will depend on site conditions typically 150mm thick (112ft).

Lorry must be able to reverse to the edge of the excavation.

Tank is then installed by a crane at the rear of the lorry. 3DVIEW After installation we recommend filling the tank with water to prevent flotation until backfilling is complete (only in high water table areas).

Site with a high water table may require a hoop of concrete with rebar at the base of the tank to prevent flotation.

Tank should be backfilled with material free of boulders and large stones.

Weight of base 5.5 Te Weight of Lid 2.85 Te

Solid lids can carry 5.8 Te wheel load

Slatted lids can carry 4 Te wheel load

EPA Export 29-06-2017:03:06:18

EPA Export 29-06-2017:03:06:18 Export EPA

I I 120 120

965mm 965mm 125mm 125mm BOV1 BOV1 4400 4400 Z25Dle Z25Dle e,oVs e,oVs CNIP CNIP

.. .. I I

l l

,~ ,~ I I

,

1 1

j j

1 1

./J ./J

I I l l ~ ~ J J I I

I I

.§ .§

t/ t/ Plan Plan Roof Roof !f., !f.,

Consent of copyright owner required for any other use. other any for required owner copyright of Consent For inspection purposes only. purposes inspection For

Plan Plan • Jntemal Jntemal

lm lm 2m 2m 3m 3m Om Om

l l .

L L

~ ~

~ ~ ··"' ··"' ~1 s s s s

T T .,

~ ~

1-1,372--j 1-1,372--j -' -' El•v•tlon El•v•tlon Side Side

_J_ _J_ ' I I

Lµ Lµ or

L L

l l I I

11 11 1 I I oya oya

~o ~o

1.430 1.430 11

I I 0,9Jil 0,9Jil

-f -f I I

l l I I

1,430 1,430

I I 51 11 11

I I

o o fr

«J «J :-11 :-11 7 1

I I

7_ 7_ 58 1. ~-

, , - (CP8BP) (CP8BP) 2,875 2,875 __ __ ,__ ,__ ig ig

t t

CPBBP CPBBP Interceptor Interceptor Modular Modular Bypau Bypau

ltd ltd AOJI.Aqlax'" AOJI.Aqlax'" Environmental Environmental Cmd Cmd

' ' I

EPA Export 29-06-2017:03:06:18 Export EPA

SCAl.E: SCAl.E: 1:25 1:25

~ ~

r------1ses ----- ~ ~

SCAL.E i 1:SD 1:SD

lfllBJ. lfllBJ. .!12!!!!!& .!12!!!!!&

.. .. __ _ _ ...... _ _

_ __ __

,,,,. ,,,,.

, , -

,, ,, , , ,

I , , - ~,, ~,, l l

,, ,, ------, 1 1

I I ,,,' ,,,' "" , , I I

I I __ __ ...... ------...... I I

I I I I

I I I I

l l I I

I I I I

l l

I I

SCALl!i SCALl!i 1:Z5 1:Z5

I I

PbMYJIWI PbMYJIWI I I

i--.:--

15l~m 15l~m MAX MAX

Consent of copyright owner required for any other use. other any for required owner copyright of Consent

I I f--

~ ~

j j m~m m~m MAX MAX

For inspection purposes only. purposes inspection For 1 ~ 11 11

Slit Slit Capacity Capacity 1580 1580 Ltrs. Ltrs.

ROO

COMPACTED COMPACTED Ol\JSHED Ol\JSHED

150mm 150mm LEVEL. LEVEL. WEL.L WEL.L ~ ~

• • COVl:R COVl:R SI.Alli SI.Alli tON* tON* 0 , 85 85

tonnes tonnes • • TANK: TANK: 1,9 1,9

ffAN O AAO AAO t,H ff ff W lt GHTJt GHTJt

"°" "°"

IITANOAIID IITANOAIID UZU UZU ...C ...C AVAi ~ ~ 00C 00C AI QU IIII' IIII'

- ~ ~ .. .. iOOmffl iOOmffl

-90D""'" -90D""'" ll ll l5001hm l5001hm

• •

1400mm 1400mm x x 950mm 950mm

ftMPAAP ftMPAAP KSIP KSIP Of!I IJPIG IJPIG mu1 mu1

6S 6S

2150 2150 IMlittolA.lf IMlittolA.lf VlctNO'Y VlctNO'Y Of Of THI= THI= TANK TANK

2 0 1 5 5 a,.mu c,;; a15 a15 l;IWOI l;IWOI Sl«)\,ILQ Sl«)\,ILQ lifC~\/0 1IIE 1IIE 1 - Ill Ill 2325 2325

.!!2!Jl .!!2!Jl i.MCilt i.MCilt 1 fl01 ~ ~ Vl! tf " rt,.~ rt,.~ U U )t,,,Ot )t,,,Ot tROM tROM 4) 4)

EQUI\/A&..ENT EQUI\/A&..ENT TO TO 85 85 ~) ~)

!MPOS~D !MPOS~D Sl.lfl.Cl"IAAGl ltf'Vml ltf'Vml

1 1 10 10 U0L U0L (HA (HA l~OtNG l~OtNG

I6IIIII I6IIIII

ONl:ROUS ONl:ROUS APPllCAllONS. APPllCAllONS. HOA£ HOA£

~fAVV ~fAVV DVf'V DVf'V OR OR CUSTOM CUSTOM L1DS L1DS CAN CAN ll ll MANUrACTUUD MANUrACTUUD fQA fQA

DEAD DEAD LOAD: LOAD: UP UP TO TO lrn lrn OVERIURDEN OVERIURDEN

IMPOSED IMPOSED LOACI LOACI IIIN/m 10 10 UDL. UDL. DA DA 5,8SO 5,8SO kg kg WKHL WKHL LQAD LQAD

2 2

.ldlll .ldlll

fTAND -A •O •O Pf!HY P! P! \: O•Ofl O•Ofl

2250 2250 Ltrs Ltrs silt silt trap trap

Cmd Cmd Environmental Environmental ltd ltd