Distribution and Transmission Annual Planning Report

December 2019

Disclaimer is registered as both a Distribution Network Service Provider and a Transmission Network Service Provider. This Distribution and Transmission Annual Planning Report 2019 has been prepared and published by Ausgrid under clause 5.13.2 and 5.12.2 of the National Electricity Rules to notify Registered Participants and Interested Parties of the results of the distribution and transmission network annual planning review and should only be used for those purposes. This document does not purport to contain all of the information that a prospective investor or participant or potential participant in the National Electricity Market, or any other person or interested parties may require. In preparing this document it is not possible nor is it intended for Ausgrid to have regard to the investment objectives, financial situation and particular needs of each person who reads or uses this document. In all cases, anyone proposing to rely on or use the information in this document should independently verify and check the accuracy, completeness, reliability and suitability of that information for their own purposes. Accordingly, Ausgrid makes no representations or warranty as to the accuracy, reliability, completeness or suitability for particular purposes of the information in this document. Persons reading or utilising this document acknowledge that Ausgrid and their employees, agents and consultants shall have no liability (including liability to any person by reason of negligence or negligent misstatement) for any statements, opinions, information or matter (expressed or implied) arising out of, contained in or derived from, or for any omissions from, the information in this document, except insofar as liability under any and Commonwealth statute cannot be excluded.

DOCUMENT AND AMENDMENT HISTORY

Issue Date Approved by Summary of Changes No.

1 December 2019 General Initial Issue Manager of Asset Management

Contact For all enquiries regarding the Distribution and Transmission Annual Planning Report 2019 and for making written submissions contact: Ausgrid Head of Asset Investment GPO Box 4009 NSW 2001 Email: [email protected]

i

Contents 1 EXECUTIVE SUMMARY ...... 1 2 INTRODUCTION ...... 2 2.1 About Ausgrid ...... 2 2.1.1 Our purpose and vision ...... 2 2.1.2 Our operating environment ...... 3 2.2 Ausgrid’s network ...... 4 2.2.1 Number and types of network assets ...... 4 2.3 Annual planning review ...... 6 2.3.1 Distribution ...... 6 2.3.2 Transmission ...... 6 2.3.3 Distribution and Transmission Annual Planning Review and Reporting ...... 6 2.4 Ausgrid’s planning approach ...... 6 2.4.1 Investment objectives and decision criteria ...... 7 2.4.2 Network planning process ...... 8 2.4.3 Network area plans ...... 9 2.5 Significant changes from previous DTAPR ...... 9 2.6 Distribution System Limitations Template – Online Data ...... 9 3 FORECASTS FOR THE FORWARD PLANNING PERIOD ...... 11 3.1 Data tables online ...... 11 3.2 Zone and Subtransmission substation load forecasting methodology ...... 12 3.2.1 Spatial trend component of forecast ...... 12 3.2.2 System level econometric model component of forecast ...... 13 3.2.3 Assumptions applied to substation load forecasts ...... 14 3.2.4 Explanation of substation forecast outcomes ...... 16 3.3 Transmission - distribution connection point load forecasts ...... 17 3.4 Subtransmission feeder load forecasts ...... 17 3.5 Primary distribution feeder load forecasts ...... 17 3.5.1 Load transfer capacities of zone substations ...... 17 3.6 Other factors having a material impact on the network ...... 18 3.6.1 Fault levels ...... 18 3.6.2 Voltage levels ...... 18 3.6.3 Other power system security requirements ...... 19 3.6.4 Quality of supply ...... 19 3.6.5 Embedded generation ...... 19 3.7 National Transmission Network Development Plan ...... 19 3.7.1 Transgrid is responsible for transmission outcomes in NSW ...... 20 4 NETWORK ASSET RETIREMENTS AND DERATINGS ...... 21 5 DISTRIBUTION LOAD AREAS ...... 22 5.1 Camperdown and Blackwattle Bay load area...... 23 5.1.1 Description of Camperdown and Blackwattle Bay load area ...... 23 5.1.2 Identified system limitations...... 24 5.1.3 Identified Substation and Feeder limitations changes from last year’s DAPR - deferred or committed projects 24 5.2 Canterbury Bankstown load area ...... 25 5.2.1 Description of Canterbury Bankstown load area ...... 25 5.2.2 Identified system limitations...... 26 5.2.3 Identified Substation and Feeder limitations changes from last year’s DAPR - deferred or committed projects 26 5.3 Carlingford load area ...... 27 5.3.1 Description of Carlingford load area ...... 27 5.3.2 Identified system limitations...... 28 5.3.3 Identified Substation and Feeder limitations changes from last year’s DAPR - deferred or committed projects 28 5.4 Eastern Suburbs load area ...... 29 5.4.1 Description of Eastern Suburbs load area ...... 29 5.4.2 Identified system limitations...... 30 5.4.3 Identified Substation and Feeder limitations changes from last year’s DAPR - deferred or committed projects 31 5.5 Greater Cessnock load area ...... 32 5.5.1 Description of Greater Cessnock load area ...... 32 5.5.2 Identified system limitations...... 33

ii

5.5.3 Identified Substation and Feeder limitations changes from last year’s DAPR - deferred or committed projects 33 5.6 Inner West load area ...... 34 5.6.1 Description of Inner West load area ...... 34 5.6.2 Identified system limitations...... 35 5.6.3 Identified Substation and Feeder limitations changes from last year’s DAPR - deferred or committed projects 35 5.7 Lower Central Coast load area ...... 36 5.7.1 Description of Lower Central Coast load area ...... 36 5.7.2 Identified system limitations...... 37 5.7.3 Identified Substation and Feeder limitations changes from last year’s DAPR - deferred or committed projects 37 5.8 Lower North Shore load area ...... 38 5.8.1 Description of Lower North Shore load area ...... 38 5.8.2 Identified system limitations...... 39 5.8.3 Identified Substation and Feeder limitations changes from last year’s DAPR - deferred or committed projects 39 5.9 Maitland load area ...... 40 5.9.1 Description of Maitland load area ...... 40 5.9.2 Identified system limitations...... 41 5.9.3 Identified Substation and Feeder limitations changes from last year’s DAPR - deferred or committed projects 41 5.10 Manly Warringah load area ...... 42 5.10.1 Manly Warringah load area ...... 42 5.10.2 Identified system limitations...... 43 5.10.3 Identified Substation and Feeder limitations changes from last year’s DAPR - deferred or committed projects 43 5.11 Newcastle Inner City load area ...... 44 5.11.1 Newcastle Inner City load area ...... 44 5.11.2 Identified system limitations...... 44 5.11.3 Identified Substation and Feeder limitations changes from last year’s DAPR - deferred or committed projects 45 5.12 Newcastle Ports load area ...... 46 5.12.1 Description of Newcastle Ports load area ...... 46 5.12.2 Identified system limitations...... 47 5.12.3 Identified Substation and Feeder limitations changes from last year’s DAPR - deferred or committed projects 47 5.13 Newcastle Western Corridor load area ...... 48 5.13.1 Description of Newcastle Western Corridor load area ...... 48 5.13.2 Identified system limitations...... 49 5.13.3 Identified Substation and Feeder limitations changes from last year’s DAPR - deferred or committed projects 49 5.14 North East Lake Macquarie load area ...... 50 5.14.1 Description of North East Lake Macquarie load area ...... 50 5.14.2 Identified system limitations...... 51 5.14.3 Identified Substation and Feeder limitations changes from last year’s DAPR - deferred or committed projects 51 5.15 North West Sydney load area ...... 52 5.15.1 Description of North West Sydney load area ...... 52 5.15.2 Identified system limitations...... 52 5.15.3 Identified Substation and Feeder limitations changes from last year’s DAPR - deferred or committed projects 53 5.16 Pittwater and Terrey Hills load area ...... 54 5.16.1 Description of Pittwater and Terrey Hills load area ...... 54 5.16.2 Identified system limitations...... 55 5.16.3 Identified Substation and Feeder limitations changes from last year’s DAPR - deferred or committed projects 55 5.17 Port Stephens load area ...... 56 5.17.1 Description of Port Stephens load area ...... 56 5.17.2 Identified system limitations...... 57 5.17.3 Identified Substation and Feeder limitations changes from last year’s DAPR - deferred or committed projects 57 5.18 Singleton Load area ...... 58 5.18.1 Description of Singleton load area ...... 58 5.18.2 Identified system limitations...... 59 5.18.3 Identified Substation and Feeder limitations changes from last year’s DAPR - deferred or committed projects 59

iii

5.19 St George load area ...... 60 5.19.1 Description of St George load area ...... 60 5.19.2 Identified system limitations...... 61 5.19.3 Identified Substation and Feeder limitations changes from last year’s DAPR - deferred or committed projects 61 5.20 Sutherland load area ...... 62 5.20.1 Description of Sutherland load area ...... 62 5.20.2 Identified system limitations...... 63 5.20.3 Identified Substation and Feeder limitations changes from last year’s DAPR - deferred or committed projects 63 5.21 Sydney CBD Load Area ...... 64 5.21.1 Description of Sydney CBD load area ...... 64 5.21.2 Identified system limitations...... 65 5.21.3 Identified Substation and Feeder limitations changes from last year’s DAPR - deferred or committed projects 65 5.22 Upper Central Coast load area ...... 66 5.22.1 Description of Upper Central Coast load area ...... 66 5.22.2 Identified system limitations...... 67 5.22.3 Identified Substation and Feeder limitations changes from last year’s DAPR - deferred or committed projects 67 5.23 Upper Hunter load area ...... 68 5.23.1 Description of Upper Hunter load area ...... 68 5.23.2 Identified system limitations...... 69 5.23.3 Identified Substation and Feeder limitations changes from last year’s DAPR - deferred or committed projects 69 5.24 Upper North Shore load area ...... 70 5.24.1 Description of Upper North Shore load area ...... 70 5.24.2 Identified system limitations...... 70 5.24.3 Identified Substation and Feeder limitations changes from last year’s DAPR - deferred or committed projects 71 5.25 West Lake Macquarie load area ...... 72 5.25.1 Description of West Lake Macquarie load area ...... 72 5.25.2 Identified system limitations...... 73 5.25.3 Identified Substation and Feeder limitations changes from last year’s DAPR - deferred or committed projects 73 5.26 Primary distribution feeder limitations ...... 73 6 TRANSMISSION LOAD AREAS ...... 74 6.1 Preliminary notes ...... 74 6.1.1 Changes in dual function asset status ...... 74 6.1.2 Dual function connection points...... 74 6.1.3 Inter-Network Impact ...... 74 6.2 Ausgrid System Total Maximum Demand Forecasts ...... 74 6.2.1 Dual function substation demand forecasts ...... 75 6.3 Transmission load area - Central Coast ...... 76 6.3.1 Description of Central Coast transmission load area ...... 76 6.3.2 Identified system limitations...... 77 6.3.3 Identified Feeder limitations changes from last year’s DTAPR - deferred or committed projects77 6.3.4 Changes in dual function asset status ...... 78 6.3.5 Dual function connection points...... 78 6.4 Transmission load area – Lower Hunter ...... 79 6.4.1 Description of Lower Hunter 132kV transmission load area ...... 79 6.4.2 Identified system limitations...... 80 6.4.3 Identified System limitations changes from last year’s DTAPR - deferred or committed projects80 6.4.4 Changes in dual function asset status ...... 81 6.4.5 Dual function connection points...... 81 6.5 Sydney Inner Metropolitan transmission load area ...... 82 6.5.1 Description of Sydney Inner Metropolitan transmission load area ...... 82 6.5.2 Identified system limitations...... 84 6.5.3 Identified Feeder limitations changes from last year’s DTAPR - deferred or committed projects90 6.5.4 Changes in dual function asset status ...... 90 6.5.5 Dual function connection points...... 90 6.6 Frequency control and load shedding ...... 91 6.7 Stability ...... 91 7 NETWORK INVESTMENTS ...... 92 7.1 Regulatory investment tests ...... 92

iv

7.1.1 Completed during the year ...... 92 7.1.2 In progress during the year...... 93 7.1.3 For the forward planning period - Distribution ...... 94 7.1.4 Longer term constraints and indicative developments – Distribution ...... 97 7.1.5 For the forward planning period – Dual Function...... 99 7.1.6 Longer term constraints and indicative developments – Dual Function ...... 100 7.1.7 Not proceeding – Distribution ...... 102 7.1.8 Not proceeding – Dual Function ...... 103 7.2 Completed or cancelled investments ...... 104 7.2.1 Refurbishment, replacement or augmentations – Distribution ...... 104 7.2.2 Refurbishment, replacement or augmentations – Dual Function ...... 104 7.3 Committed investments ...... 106 7.3.1 Refurbishment, replacement or augmentations – Distribution ...... 106 7.3.2 Refurbishment, replacement or augmentations – Dual function ...... 124 7.3.3 Committed dual function augmentations ...... 127 7.4 Urgent and unforseen investments ...... 127 8 JOINT PLANNING ...... 128 8.1 Joint planning with TransGrid TNSP ...... 128 8.1.1 Process and methodology ...... 128 8.1.2 Joint TransGrid - Ausgrid planning completed in 2018 ...... 129 8.1.3 Planned joint TransGrid-Ausgrid network investments ...... 131 8.2 Joint planning with other DNSPs ...... 132 8.2.1 Process and methodology ...... 132 8.2.2 Joint Ausgrid and other DNSP planning completed in preceding year ...... 132 8.2.3 Planned DNSP joint network investments ...... 132 8.2.4 Additional information ...... 132 9 NETWORK PERFORMANCE ...... 133 9.1 Reliability measures and standards ...... 133 9.1.1 Supply reliability standards ...... 133 9.1.2 Network Supply reliability performance in the preceding year ...... 134 9.1.3 Service Target Performance Incentive Scheme (STPIS) ...... 136 9.1.4 Forecast of network reliability performance ...... 137 9.1.5 Compliance with network reliability standards ...... 137 9.2 Quality of supply standards ...... 138 9.2.1 Voltage range for supplied electricity ...... 138 9.2.2 Harmonics and total harmonic distortion ...... 138 9.2.3 Voltage fluctuations (Flicker) – Applicable quality of supply codes, standards and guidelines139 9.2.4 Voltage unbalance – Applicable quality of supply codes, standards and guidelines ...... 139 9.3 Quality of supply performance for preceding year ...... 139 9.3.1 Supply voltage performance ...... 139 9.3.2 Harmonic content of supply voltage waveform ...... 139 9.3.3 Voltage fluctuations (Flicker) performance ...... 140 9.3.4 Voltage unbalance performance...... 140 9.4 Corrective action planned to meet quality of supply standards ...... 140 9.4.1 Supply voltage ...... 140 9.4.2 Flicker, Harmonics and Unbalance ...... 140 9.5 Compliance with quality of supply standards ...... 140 10 ASSET MANAGEMENT...... 142 10.1 Ausgrid’s asset management approach ...... 142 10.2 Risk management strategies...... 142 10.2.1 Subtransmission underground cable strategy ...... 143 10.2.2 11kV switchgear strategy ...... 143 10.3 Distribution network losses ...... 144 10.4 Obtaining further information on asset management ...... 144 11 DEMAND MANAGEMENT ...... 145 11.1 Demand management ...... 145 11.2 Demand management considerations in 2019 ...... 146 11.3 Demand management activities in 2018-19 ...... 146 11.3.1 Demand management projects initiated in 2018-19 ...... 146 11.3.2 Demand management projects implemented in 2018-19 ...... 147 11.3.3 Demand management innovation ...... 147 11.4 Forecast demand management projects ...... 155 11.5 Demand side engagement ...... 155

v

11.6 Embedded generator enquiries and connection applications ...... 155 12 INVESTMENTS IN INFORMATION TECHNOLOGY AND COMMUNICATION SYSTEMS ...... 156 12.1 Information, Communication and Technology ...... 156 12.1.1 ICT investment actual 2018/19 and forecast ...... 157 12.2 Advanced Distribution Management System (ADMS) ...... 157 12.2.1 ADMS Benefits ...... 158 12.2.2 ADMS Program Implementation ...... 158 12.3 Network Asset Digitisation ...... 159 12.3.1 Network Asset Digitisation Benefits ...... 159 12.3.2 Network Asset Digitisation Program Implementation ...... 160 ANNEXURE A – GLOSSARY ...... A ANNEXURE B – RELIABILITY AND PERFORMANCE LICENCE CONDITIONS ...... B ANNEXURE C – COMPLIANCE CHECKLISTS...... C

vi

1 Executive Summary

Ausgrid is both a registered Distribution Network Service Provider and a Transmission Network Service Provider, and is required to produce a Distribution Annual Planning Report (DAPR) covering its distribution network and a Transmission Annual Planning Report (TAPR) covering its transmission (dual function asset) network. To align the publication of the DAPR and TAPR, the National Electricity Rules (NER) permit the publication of both documents in a combined annual planning report. This Distribution and Transmission Annual Planning Report (DTAPR) presents the results of Ausgrid’s annual planning review of both its distribution and transmission (dual function asset) network conducted since the publication of the previous DTAPR in December 2018. The objective is to: • Provide transparency to Ausgrid’s decision making processes to assist non-network providers, other Network Service providers and connection applicants to make efficient investment decisions • Provide information on Ausgrid’s distribution assets planning process, including forecasting, identification of network limitations, and the development of potential credible options to address these limitations covering a minimum five year forward planning period • Report on the results of Ausgrid’s annual planning review, including subtransmission substation (STS), zone substation (ZS) and subtransmission feeder forecast loading, identified network limitations including capacity, asset condition and other limitations on the subtransmission and distribution assets; and the potential credible solutions to address these limitations • Provide third parties the opportunity to offer alternative proposals to the identified network needs, including non-network solutions such as demand management or embedded generation • Provide timely indication of the planned commencement dates for the assessment of proposed projects that will be subject the Regulatory Investment Test for Distribution • Provide information on Ausgrid’s demand management activities and actions taken to promote non-network initiatives each year, including plans for demand management and embedded generation over the forward planning period, and • Describe significant changes to identified network limitations including capacity, asset condition and other limitations on the network assets; changes to potential credible solutions, and project deferrals and cancellations. The DAPR section covers a minimum five year forward planning period and the TAPR section covers a ten year forward planning period from December 2019. Online data associated with the 2019 DTAPR, as well as the document itself, is accessible via Ausgrid’s website: www.ausgrid.com.au/DTAPR

1

2 Introduction

This Distribution and Transmission Annual Planning Report (DTAPR) has been prepared to comply with National Electricity Rules (NER) clause 5.13.2 “Distribution Annual Planning Report” (DAPR), and clause 5.12.2 “Transmission Annual Planning Report” (TAPR). Version 124 of the NER has been used. Ausgrid has prepared this DTAPR with a five year forward planning horizon. It reflects the outcomes of the annual planning review of Ausgrid’s electricity network since the publication of the December 2018 DTAPR. The purpose of this document is to inform Registered Participants, stakeholder groups and interested parties of the identified future network needs, the committed and proposed solutions to these needs and the potential opportunities for non-network solutions, particularly for large investments where the Regulatory Investment Test for Distribution (RIT-D) applies. Ausgrid’s DTAPR has been prepared to meet the requirements of the National Electricity Rules Schedule S5.8 Distribution Annual Reporting Requirements to: • Provide transparency to Ausgrid’s decision making processes and assist non-network providers, other Network Service providers and connection applicants to make efficient investment decisions • Promote efficient investment decisions in the electricity market • Include information on the planning process including forecasting, identification of network limitations, and the development of potential credible options to address these limitations • Set out the results of Ausgrid’s annual planning review, including joint planning with other Network Service Providers, covering a minimum five year forward planning period for distribution assets • Give third parties the opportunity to offer alternative proposals to the identified network needs, including non-network solutions such as demand management or embedded generation • Inform Registered Participants and interested parties on the outcomes of the annual planning review, including network capacity and load forecasts for subtransmission lines, zone substations and transmission- distribution connection points, and any 11kV primary distribution feeders which are constrained or are forecast to be constrained within the next two years • Provide information on Ausgrid’s demand management activities and actions taken to promote non-network initiatives each year, including plans for demand management and embedded generation over the forward planning period. Ausgrid also owns, develops, operates and maintains transmission dual function assets in NSW. Although these dual function assets form part of our distribution network they are operated in parallel with TransGrid’s network, and essentially perform a transmission function by supporting the main NSW transmission network. Ausgrid is therefore also registered as a TNSP and is required to publish a Transmission Annual Planning Report (TAPR) covering our dual function assets. The NER permit Ausgrid to publish its TAPR as part of the DAPR to align the publication of both reports each year. Ausgrid has combined the two reports into one Distribution and Transmission Annual Planning Report. 2.1 About Ausgrid Ausgrid’s network is a shared asset that has powered the lives of our customers and their communities for over a century. Our network is made up of large and small substations connected through high and low voltage powerlines, underground cables and power poles spread across more than 22,275 square kilometres. Our network extends from Waterfall in Sydney’s south, to Auburn in inner western Sydney, to the Central Coast and Hunter Valley. Today, we support over 20 percent of the national gross domestic product and serve over 4 million people in almost 1.8 million homes and businesses. Our core business is to provide distribution network services to our customers. We do this by building and operating assets and delivering non-network solutions to ensure safe and reliable access to electricity at an efficient and reasonable price. As technology evolves, our customers’ needs and expectations are changing. Households, communities and businesses now expect to generate, consume and store their own electricity and sell any excess back into the grid. The grid has a pivotal role in supporting customers during this transition. We are committed to working with our customers and stakeholders to realise this lower carbon future at the lowest possible cost. 2.1.1 Our purpose and vision Our Vision is to become a leading energy solutions provider, recognised both locally and globally.

2

Our Purpose is to connect communities and empower lives with a focus on affordability, reliability and sustainability Our Values guide the standard of behaviour expected of Ausgrid and our employees. These following values form the basis for everything we do: • Work Safe, Live Safe • Customer-focused • Commercially minded • Collaborative • Honest • Accountable, and • Respectful. 2.1.2 Our operating environment Ausgrid is regulated by statutory and legislative requirements, including Work Health and Safety (WH&S), environmental, competition, industrial, consumer protection and information laws, National Electricity Regulation (detailed below), and the NSW Electricity Supply Act 1995 (ESA). We must also comply with the conditions of our NSW Distribution Network Service Provider licence (under the ESA). The National Electricity Regulation is primarily represented by the National Electricity Law (NEL) and National Electricity Rules (NERs) which regulate the National Electricity Market, and the National Energy Customer Framework. Ausgrid operates in the National Electricity Market (NEM) as both a distribution and transmission network service provider (DNSP and TNSP). The National Electricity Objective (NEO), as stated in the National Electricity Law is to: “promote efficient investment in, and efficient operation and use of, electricity services for the long term interests of consumers of electricity with respect to: (a) price, quality, safety, reliability and security of supply of electricity; and (b) the reliability, safety and security of the national electricity system.” We meet these obligations with investments that address our customers’ requirements for safe, affordable, reliable and sustainable network services. We manage compliance with these laws and regulations through our internal codes and policies and a common control framework. This control framework comprises plans, policies, procedures, delegations, instruction and training, audit and risk management. On 4 June 2015, the Electricity Network Assets (Authorised Transactions) Act 2015 and the Electricity Retained Interest Corporations Act 2015 were enacted. The legislation allowed the NSW Government to deliver its policy to lease 49 percent of the state's electricity networks and to use the proceeds from those transactions to build new infrastructure. This lease agreement was completed on 1 December 2016. Since that time Ausgrid has been managed as a Network Asset & Operator Partnership with the majority share (50.4%) held by AustralianSuper & IFM Investors and 49.6% held by the NSW Government.

3

2.2 Ausgrid’s network In 2018/19, Ausgrid’s network supplied electricity to more than 1.7 million network customers. Our distribution area (Figure 2.1) covers an area of 22,275 square kilometres and includes some of the most densely populated and fastest growing areas of NSW. We supply customers as far north as the Upper Hunter Valley, as far south as Waterfall and to Auburn in Sydney’s west.

Figure 2.1: Ausgrid’s network area

2.2.1 Number and types of network assets Ausgrid’s subtransmission and distribution network includes: • A dual function subtransmission system of 132kV assets (these are transmission assets which support the main TransGrid transmission system); • A subtransmission system of 33kV, 66kV and 132kV assets; • A high voltage distribution system of predominantly 11kV, with some 5kV, 22kV and 33kV and 12.7kV Single Earth Wire Return assets; and • A low voltage distribution system of 400V assets (230V single phase).

4

Table 2.1: Ausgrid network statistics

Network Asset 2018/19 Dual function (Transmission) System – 132kV (km) 895 Subtransmission System - 33kV, 66kV and 132kV (km) 3,007 Substations - Subtransmission (STS) 48 Substations - Zone (ZS) 182 Substations - Distribution 32,301 High Voltage Overhead (km) 10,023 High Voltage Underground (km) 8,482 Low Voltage Overhead (km) 18,670 Low Voltage Underground (km) 7,708 Feeder Numbers CBD 59 Feeder Numbers Urban 1,936 Feeder Numbers Short Rural 372 Feeder Numbers Long Rural 6 Pole (number) 511,656 Streetlights (number) 250,279

NOTES: • Distances for overhead and underground lines are circuit km. • Asset counts and lengths do not include private assets. • Low voltage overhead and underground lengths include streetlighting. For the 2018/19 financial year, length of OH streetlighting mains is 5,582km, length of UG streetlighting mains is 1,229km.

Figure 2.2: Typical components of an electricity network

5

2.3 Annual planning review 2.3.1 Distribution The National Electricity Rules (Version 124) require that the annual planning review includes the planning for all assets and activities carried out by Ausgrid that would materially affect the performance of its network. This includes planning activities associated with replacement and refurbishment of assets and negotiated services. The objective of the distribution annual planning review is to identify possible future issues over a minimum five year planning horizon that could negatively affect the performance of the distribution network to enable DNSPs to plan for and adequately address such issues in a sufficient timeframe. This document provides information to Registered Participants and interested parties on the nature and location of emerging constraints on Ausgrid’s subtransmission and 11kV distribution network assets, commonly referred to as the distribution network. The timely identification and publication of emerging network constraints allows the market to identify potential non-network options and Ausgrid to develop and implement appropriate and timely solutions. 2.3.2 Transmission The NER require network service providers, who own and operate dual function assets to register as Transmission Network Service Providers by virtue of the definition of 'TNSP' in the rules. Certain parts of the rules treat dual function assets in the same way as other subtransmission assets. However, for the purposes of the transmission annual planning review and reporting, dual function assets are treated as transmission assets requiring a Transmission Annual Planning Report. For the purposes of economic evaluation and consultation with Registered Participants and Interested Parties, dual function assets are treated as distribution network assets and are subject to the same economic evaluation test. Ausgrid’s dual function network is defined as those assets with a voltage of 66kV and above that are owned by Ausgrid, and operate in parallel with and provide material support to the TransGrid transmission network. These assets may either operate in parallel with the transmission network during normal system conditions or can be configured so that they operate in parallel during specific system conditions. 1 An asset is deemed to provide material support to TransGrid’s transmission network if:

• there is otherwise limited or no system redundancy within the transmission network, or • investment in the transmission system would be required within the regulatory period if that network asset did not exist, or • the feeder provides operational support to the transmission network (e.g. to facilitate maintenance of transmission assets or improve security of supply) and the asset provides an effective parallel with the transmission network via a relatively low impedance path. Ausgrid reviews the function of its dual function assets annually to determine if they continue to provide material support to TransGrid’s transmission network. This review is used as input for preparing Ausgrid’s regulatory reporting, the regulatory submission, and pricing methodology. For the purpose of AER Revenue Determination submissions, the list of dual function assets is determined based on the forecast load and the system configuration as at the beginning of the regulatory period. 2.3.3 Distribution and Transmission Annual Planning Review and Reporting Reporting of both planning reviews have been merged into one document. The information that the NER requires Ausgrid to report for both distribution and transmission is covered throughout the various sections of the DTAPR. 2.4 Ausgrid’s planning approach The network planning and development process for both the distribution and transmission networks is carried out in accordance with the NER Chapter 5, Part D, Network Planning and Expansion. Planning for distribution and subtransmission assets is carried out in accordance with NER 5.13.1 - Distribution annual planning review and NER 5.12.1 - Transmission annual planning review for dual function assets.

1 Network Planning Standard NIS433: Classification of Dual-Function Assets

6

2.4.1 Investment objectives and decision criteria Ausgrid’s investment objectives respond to one or more of three key policy directives: • Comply with its obligations under Chapter 5 of the NER; the Licence conditions for the operator of a transacted distribution system, as part of the Distributor’s Licence granted to Ausgrid Operator Partnership2, and other applicable regulatory instruments; • Manage business risks with particular regard to ensuring the safety of its employees, customers and the broader community; maintaining the reliability of supply to its customers; and protecting the environment; and • Improve the efficiency of the business or produce an affordable and sustainable supply of energy to the community. The following table, taken from Ausgrid’s Network Development and Planning Strategy, provides a summary of these objectives:

Reliability Ensuring network development and the integration of customer connections allows for reliability standards to be maintained in accordance with Ausgrid’s asset management objectives. This means: - Meeting corporate objectives for STPIS outcomes; - Complying with licence conditions for reliability performance at feeder category and individual feeder level; and - Deliver network performance that customers are prepared to pay for. Safety Planning the network to support the elimination of safety incidents so far as reasonably practicable or reduce risks to be as low as reasonably practicable consistent with Ausgrid’s Electricity Network Safety Management Plan (ENSMS). This includes: - Undergrounding where appropriate; - Minimising bushfire risk and exposure by selecting appropriate line routes and

construction; and - Configuration of assets to minimise worker exposure (e.g. through redundancy or interconnectivity) to risk (e.g. isolators and interconnectivity to allow electrical isolation of assets for work.). Affordable & Sustainable - Utilising cost benefit analysis to assess feasible options including demand management to deliver network performance objectives at least cost. - Use long term planning to manage long life cycle assets by considering changes in operating requirements over the lifespan of the assets.

To provide a sound and consistent approach, decisions to invest are made based on (as appropriate): • Clearly defined requirements in terms of legislative obligations and identified risks; • Compliance with Ausgrid’s policies and standards; • Sound risk assessment (safety, unserved energy, environmental, financial, community impact); • Consideration of whole-of-life costs and benefits and the time-value of money; • Consideration of the range of feasible solutions without bias for technology; and • A level of analysis which is commensurate with the costs and risks. In compliance with the requirements of the National Electricity Objective and various elements of the NER, investments in the network are made on the basis of best economic value to all producers and consumers of electricity in the NEM. Network investment options are selected where they deliver the highest Net Present Value (NPV), taking into account the costs, risks and anticipated benefits. Ausgrid’s investment processes are designed to promote:

2 Refer to Annexure B - Licence conditions for the operator of a transacted distribution system, part of the Distributor’s Licence granted to Ausgrid Operator Partnership (with Ministerial variation, dated 5 February 2019).

7

• Efficient and prudent investments consistent with its stated investment objectives; • Timely identification of the business’s capital and resource requirements; • Investment decisions that are informed by a full understanding of the costs, benefits and regulatory requirements and are authorised in accordance with the business’s internal delegations policy; • Compliance with statutory and regulatory obligations to the Board, stakeholders, shareholders, broader community, regulators and appointed auditors; • Co-ordination with related organisations, including other network service providers and utilities; • Investment opportunities being prioritised to best meet the objectives of the corporation and reviewed at Board level; and • A sustainable investment profile over the long term, to minimise peaks and troughs that can lead to instability in electricity prices. 2.4.2 Network planning process Ausgrid follows a structured planning process that can be summarised by the following diagram from our Network Investment Policy. The planning phase involves identifying the investment needs and risks; developing one or more options to address these needs; assessing costs and benefits associated with those options to select the preferred option and initiating the preferred option.

Planning Phase

Forecast Plans

Identify Existing Develop Investment Design & Needs & Initiate Manage Retire Network Options Appraisal Build Risks

Investment Objectives

Figure 2.3: Ausgrid planning process

The timeframe and complexity of this process varies according to network level, risk profile, and the project scale and intent. Accordingly, Ausgrid organises its planning activities by distinct investment categories. This approach allows Ausgrid to adopt a level of analysis and justification that is commensurate with the costs, risks and obligations associated with each investment category discussed below: Major projects These are generally major subtransmission investments designed to meet the various needs of the network, in particular demand growth, voltage, supply quality, fault duty, stability and asset renewal requirements. Investment options are identified by a cost-benefit analysis within an Area Planning framework to meet the requirements of large geographic areas over a 20 year planning period. Given that these projects are generally of significant value, this process involves detailed analysis of a number of alternatives. In cases where the need is specific to a particular facility or asset, these requirements can be met by a specific planning study to update the area plan. Asset replacement and network risk These investments are designed to manage risks associated with asset conditions and the safe and reliable operation of the network. Investment is either to meet specific obligations and standards; or justified based on an assessment of cost and benefits, in terms of risk mitigated (e.g. determined from condition assessments and historical performance). Investments usually involve programmes of work that generally comprise larger volume of smaller projects designed to address the risks associated with assets of a similar type. Distribution (generally 11kV) These investments address the needs of the distribution network, in particular demand growth, voltage, supply quality and fault duty requirements. These investments are planned to meet the requirements of the distribution

8

network over a five year planning horizon. The level of analysis depends on the scale and complexity of individual projects. Customer connections These investments are for the reinforcement of the up-stream portion of the shared network associated with connections that are not customer funded. Investments are initiated by customer connection applications. Investment requirements are forecast on the basis of historical expenditure trends adjusted for changes in Ausgrid’s connection policy. Reliability These investments address gaps in reliability performance that will not be met by the other investment categories. Proactive investments are planned to respond to forecasts of reliability performance considering investments planned under other investment categories; and reactive investments are determined through an assessment of reliability outcomes based on actual performance. 2.4.3 Network area plans To ensure Ausgrid’s investment is prudent and efficient, our planning of major investments in the network: • is based on meeting the requirements of geographic areas, defined on the basis that they represent discrete electrical areas and with relative independence from network interconnections; • considers Ausgrid’s obligations under the NER and other applicable regulatory instruments in a holistic manner; and • considers identified needs over a twenty year planning horizon to allow for the development of a long term strategy that addresses various drivers and minimises long term cost. Ausgrid’s plans are documented in ‘Area Plans’, covering the identified network needs, potential credible options and the preferred solution for each geographic area. For the purposes of planning investments to meet the needs of the subtransmission network, Ausgrid has divided its network into geographic ‘Areas’ and generates an ‘Area Plan’ for each geographic ‘Area’. The requirements of the Ausgrid 132kV network that links TransGrid’s bulk supply points to Ausgrid’s subtransmission network are considered based on the broader Sydney Inner Metropolitan, Central Coast and Lower Hunter regions to create three ‘Transmission Area Plans’. Each of these regions encompasses multiple ‘Areas’. Projects that comprise the preferred strategy for each Area Plan are determined by cost-benefit analysis and entered in the Major Project List (Project List) with each project initiated based on this list and on expected project lead times, and in accordance with Ausgrid’s Investment Initiation Standard. The Project List records the identified system limitation and need date, the required completion date and the estimated cost for each project. The Area Plans are reviewed on approximately a five year basis. In order to optimise project implementations, the identified need date of projects within the Major Project List is reviewed annually as new information and forecasts become available. Any changes to the projects within the Project List are recorded and supported by planning reports which include the reason for the change. This Project List also forms the basis of the economic assessment, consultation and reporting requirement under the RIT-D. 2.5 Significant changes from previous DTAPR Significant changes from the previous DTAPR report are covered in the various sections of the DTAPR and explain the reasons for project cancellations or deferment beyond the 5 year planning horizon for distribution and 10 years for transmission. The structure of the 2019 DTAPR and associated data files are similar to those of the 2018 DTAPR and associated data files. 2.6 Distribution System Limitations Template – Online Data A requirement introduced in 2017 is clause 5.13.3 of the NER, whereby Ausgrid is required to publish online data in the format prescribed by the Australian Energy Regulator (AER) in a Distribution System Limitation Template. In keeping with the principle expressed by the AER that data should be provided in a more analysis friendly format than lengthy PDF documents, other key data tables have also been provided online so that they can be downloaded by interested parties.3 Following the release of the TAPR guidelines in December 2018, we have populated a Transmission System Limitation Template for the first time in 2019.

3 Reference AER Final Decision – Distribution Annual Planning Report Template V1.0, June 2017, pages 1-3 and 1-4.

9

Online data associated with the 2019 DTAPR, as well as the document itself, is accessible via Ausgrid’s website at www.ausgrid.com.au/DTAPR

10

3 Forecasts for the forward planning period

3.1 Data tables online In keeping advice from the AER, that data should be made accessible in a format that can been readily interrogated, forecast and related data tables are published online and can be accessed via Ausgrid’s website at www.ausgrid.com.au/DTAPR Table definitions for the ‘Substation capacity and demand forecast’ table and the ‘Dual Function asset 10 year demand forecast’ table located on Ausgrid’s website are as follows:

Substation capacity and demand forecast table definitions Heading Label Description Area Plan An area as defined by Ausgrid used to describe a collection of substations of similar geographical region Substation Name of the substation. Details on the primary and secondary voltages of the substation included in the name to differentiate some locations of similar naming convention Substation Type Denotes either Zone Substation (ZS) or Subtransmission Substation (STS) Total Capacity Maximum load able to be carried by the substation with all elements in service. A summer (MVA) and winter Total Capacity value is provided Firm Capacity Load able to be carried by the substation with the largest rated element out of service. A (MVA) summer and winter Firm Capacity is provided Load Transfer Amount of load that can be restored in the event of a whole zone outage by switching the Capacity (MVA) distribution network. The transfer capacity assumes that a single zone is rendered out of service and the rest of the network is in system normal configuration. A summer and winter Transfer Capacity is provided 95% Peak Load The number of 15 minute occurrences that exceeded the 95th percentile value of Exceeded maximum demand was summed and divided by four to determine the "hours within 95% (hrs/yr) of peak" value. A summer and winter 95% Peak Load exceeded value is provided Embedded The Solar PV capacity by zone substation is consistent with the information used in the Generation - forecast and is current as at March 2018 and includes all known systems under 100kW. Solar PV (MW) Solar generation systems over 100kW are included with the “Other” embedded generation. The solar generation capacity is based on information gathered and recorded from the application for connection forms completed at the time of applying for a solar installation. Embedded Embedded generation “Other” includes all known diesel, landfill biogas, coal seam Generation - methane, natural gas including tri-generation and co-generation, hydro and mini hydro, Other (MW) coal washery, waste heat recovery generating units and Solar PV systems larger than 100kW known to Ausgrid. Not all of these units export to the grid as they are not capable of operating in parallel with the Ausgrid network and are intended for standby operation in island mode. Actual Load Recorded peak demand for the substation. A summer and winter actual is provided (MVA) Actual Load Recorded power factor for the substation at time of peak load. The value is compensated (PF) and takes into account the actual switching of capacitors at the substation at time of peak load. A summer and winter actual is provided Forecast Load POE50 medium scenario planning forecast peak demand in MVA for each respective (MVA) forecast year for the substation. A summer and winter actual is provided Forecast Load Forecasted power factor as calculated from POE50 medium scenario planning forecast (PF) for each respective forecast year for the substation. The value is compensated and takes into account the forecasted switching of capacitors at the substation for any given forecast year. A summer and winter actual is provided

11

Dual Function asset 10 year demand forecast table definitions Heading Label Description Substation Name of the substation. Details on the primary and secondary voltages of the substation included in the name to differentiate some locations of similar naming convention Substation Type Denotes either Zone Substation (ZS) or Subtransmission Substation (STS) Substation Recorded peak demand in MW for the substation. A summer and winter actual is provided Actual MW Substation Recorded peak reactive load for the substation. The value is compensated and takes into Actual MVAr account the actual switching of capacitors at the substation at time of peak load. A summer and winter actual is provided Substation POE50 medium scenario planning forecast peak demand in MW for each respective Forecast MW forecast year for the substation. A summer and winter actual is provided Substation POE50 medium scenario planning forecast peak reactive load in MVAr for each respective Forecast MVAr forecast year for the substation. The value is compensated and takes into account the forecasted switching of capacitors at the substation for any given forecast year. A summer and winter actual is provided

3.2 Zone and Subtransmission substation load forecasting methodology This section describes the maximum demand planning forecasting methodology (the forecast) used by Ausgrid for zone substations and subtransmission substations. The forecasts of peak demand are prepared at the zone substation level and at the subtransmission substation level. These spatial forecasts form a key input into the planning of Ausgrid’s capital expenditure program. The underlying forecast is constructed from two primary components; a near term forecast that is based on the statistically derived trend line of the weather corrected historical customer electricity demand, and a medium to long term forecast that is based on a system level econometric model. This recognises the need for the forecast model to consider the short term trend and long term macro econometric factors. Both components are adjusted for out of trend impacts from embedded generation, energy storage, electric vehicles and energy efficiency. The forecast is prepared seasonally for summer and winter. Adjustments to the forecast are also made at a spatial level to account for planned new large customer connections and planned changes to the network architecture such as load transfers. 3.2.1 Spatial trend component of forecast The near term component of the forecast is based upon the local historical trend in total customer demand from both grid supplied electricity and customer embedded generation. The process for deriving the local substation forecast is as follows: a) Raw metered electricity demand data is obtained for zone substations and subtransmission substations for 7 years at 15min intervals. b) 10 years of weather data is obtained from the Bureau of Meteorology for weather stations across Ausgrid’s network area. Each zone and subtransmission substation is assigned a representative Bureau of Meteorology weather station. c) Network configuration data is obtained from Ausgrid’s planning and customer connections groups. d) The metered grid supplied electricity demand data is cleansed to remove abnormal loads (generally resulting from temporary network switching and abnormal configurations). This prevents abnormally switched loads from distorting historical trends. e) The total customer electricity demand is then weather corrected based on the variable of “average ambient temperature” and subjected to Monte Carlo simulation analysis. This enables calculation of probability of exceedance (POE) levels. f) Embedded generation demand for all 30 min intervals is modelled from a representative sample of customer interval meter data (gross metered systems) for customer solar power systems. The historical non- dispatchable embedded generation (30 min intervals) at each zone substation is derived from the embedded generation demand model and historical customer connection information. The embedded generation is then added to the weather corrected grid supplied electricity demand data to derive the customer electricity demand. g) Maximum demand impacts from historical block loads are then identified from planning information and actual network system meter data for the historical time series. These block loads comprise all customer

12

connections which result in a step change in demand at the zone substation. The basis for including or excluding block loads is described in section 3.2.3.8 below. These step changes to maximum demand are then reversed from the customer electricity demand data to derive the underlying customer electricity demand data series. h) By excluding step changes due to larger, lumpy customer loads and including the electricity supplied by customer generation, a more stable underlying trend of customer demand is revealed. i) Regression of the resultant data series calculates the underlying rate of growth using a line of best fit at each zone and subtransmission substation. Any step changes in demand (solar, historical block loads and load transfers) are then reinserted to arrive at the starting point. j) This local substation trend forms the basis for the first 2 years and is a component of years 3 and 4 of the forecast. 3.2.2 System level econometric model component of forecast The medium to long term component of the forecast is based upon a system level econometric model. The econometric model is derived from key drivers at the local and system total level for both residential and non- residential elements. The process for deriving the econometric component of the forecast is as follows: a) The residential and non-residential components of the econometric model includes both price and income response elements. The residential component includes drivers for the change in real retail residential electricity prices and the change in real average household disposable income. The non-residential component includes drivers for the change in real retail non-residential electricity prices and the change in NSW Gross Value Added Services. The residential component also includes impacts from any forecast changes in population growth. b) Forecast variation in real retail residential electricity prices, real average household disposable income, real retail non-residential electricity prices and NSW Gross Value Added Services are obtained. For the 2019 forecast, this data was obtained from the Australian Energy Market Operator (AEMO) and is the data used for AEMO’s 2019 Electricity Statement of Opportunities (ESOO). Due to an improved regression fit, NSW Gross Value Added Services replaced NSW Gross State Product as the income explanatory variable in the 2019 non-residential demand regression model c) Due to the collinearity of the historical customer price response with historical impacts from energy efficiency improvement, the model is based upon the total ‘electricity services‘ to customers. The ‘electricity services’ includes the total metered demand (grid supply), the historical demand impacts from embedded generation and the historical demand impacts from Commonwealth and New South Wales government energy efficiency programs. d) The total metered electricity demand (grid supply) is obtained for all 30 min intervals from the bulk supply point meter data for Ausgrid’s network. e) From the interval metered data for over 500,000 customers and the total system metered electricity demand data from the bulk supply point meters, a regression model is used to calculate the separate metered electricity demand for residential customers and non-residential customers. f) The historical demand impacts from non-dispatchable embedded generation are obtained as per item f in the description of the spatial trend forecast above. These are allocated separately for residential and non- residential customers. g) The historical and forecast demand impacts from Commonwealth and New South Wales government energy efficiency programs are obtained for three key programs: i. the Minimum Energy Performance Standards (MEPS) program which sets national minimum energy performance standards for electrical appliances such as air conditioners, motors, televisions and refrigerators; ii. the Building Code of (BCA) which sets minimum energy performance standards for buildings; and iii. the NSW Energy Savings Scheme (ESS) which encourages customers to invest in energy efficiency improvements in their homes and businesses. Ausgrid obtains the historical and forecast demand impacts for these energy efficiency programs from external expert advice. The demand impacts are allocated separately for residential and non-residential customers. The peak demand contribution is derived from the seasonal daily load factor on day of system peak. h) The historical ‘electricity services’ for residential customers and the ‘electricity services’ for non-residential customers are then regressed against the separate independent variables of price and income. The econometric model determines the elasticities for both income and price for each of the residential and non- residential customer sectors. i) Following derivation of the econometric elasticities, historical embedded generation and energy efficiency impacts are reversed out to return to the starting point. This process excludes effects likely to pollute the relationship between grid supplied electricity demand and the price and income variables.

13

j) Impacts due to new block loads, embedded generation, battery storage systems, energy efficiency, electric vehicles and air conditioner take-up by customers are included as post model adjustments to the econometric model. k) The impacts from household energy (battery) storage and rooftop solar, or distributed energy resources (DER), in the 2019 maximum demand forecast are based upon model outputs from external consultancy advice. The model calculates annual electricity bill savings for representative customer types to derive likely uptake rates for DER across the Ausgrid network. In conjunction with modelled price paths for rooftop solar and batteries, an ROI is calculated for each representative customer type over time, which in turn drives the uptake of DER. Spatial allocation of the DER is based on the current allocation of the representative customer types across the Ausgrid network area and their respective DER projections from the model, aggregated to the zone substation level. l) The impact from electric vehicles (EV) has been guided by information obtained from AEMO in mid-2019. The AEMO projections of the GWh volume impact of EVs in NSW & ACT is allocated to the Ausgrid network area and converted to a count of EVs using mileage and fuel economy assumptions aligned with AEMO. Peak demand impacts of EVs are informed by results from the Smart Grid Smart City (SGSC) project (a smaller trial of 20 EVs) and similar US based trials (a much larger trial involving thousands of EVs). From these trials, the maximum demand impact of EVs is estimated to be +0.4kW per vehicle in the near term forecast years declining to +0.2kW in the later forecast years. This declining peak demand impact is based on the diversified maximum demand impact of +0.2kW to +0.4kW per vehicle observed in the SGSC and US trials as well as external expert advice. Impacts are spatially allocated using a combination of NSW vehicle registration data for electric vehicles obtained from NSW Roads and Maritime Services, the 2018 ABS vehicle census by postcode data, and ABS 2016 census LGA income statistics. m) The residential component includes impacts from forecast changes in population growth based upon data from the NSW Department of Planning and ABS population projections. The population projections data from the NSW Department of Planning extracted from 2016 is revised using the 2018 ABS population projections. n) Each component is allocated at a zone substation level. Allocation of embedded generation and energy storage is based upon the current penetration of rooftop solar. Allocation of energy efficiency impacts is based upon each substation’s share of annual metered electricity volume. Allocation of impacts due to population changes is based upon the 2016 NSW Department of Planning data at the Local Government area level, adjusted for the substation service boundaries. o) This econometric model forms the basis for years five and beyond of the forecast for each substation and a component of years 3 and 4 of the forecast. 3.2.3 Assumptions applied to substation load forecasts 3.2.3.1 Endeavour supplied substations There are three Ausgrid zone substations not supplied from within Ausgrid’s network, but supplied from at 66kV and 33kV. These zone substations are Epping 66/11kV, Leightonfield 33/11kV and Hunters Hill 66/11kV. Demand from these zone substations is included in the aggregate data. Note, in 2018 a project was committed which will see 2 more zone substations be supplied from Endeavour Energy at 33kV. From 2019/20 both Auburn 33/11kV and Lidcombe 33/11kV zone substations will be supplied from Camelia STS in the Endeavour network area. Demand from these zone substations will remain as being included in the aggregate data. 3.2.3.2 Customer negotiated capacity Where a customer has negotiated a higher standard of service than the default planning standard and the agreed financial terms have been met, the substation load forecast is adjusted accordingly so that this capacity is reserved for that customer. If a customer has negotiated a lower standard of service (e.g. to reduce their costs), this is generally not incorporated into the forecast. Generally these requests are considered during network planning, or inherent in the connection of the customer. 3.2.3.3 Embedded generation The historical load data includes the impact of downstream embedded generation that was generating at the time of peak, consequently, the forecast includes the impact of non-dispatchable small scale generation such as rooftop solar installations. Where a generator has a material impact on peak load that is not accurately reflected in the historical data and information is available about generator output and reliability, the forecast is adjusted to reflect the expected impact of the generator, taking into account:

• the historical reliability of the generator and expectations about its future reliability, including weather dependency where relevant;

14

• when the generator was installed and whether it is a temporary or permanent installation; • contractual obligations for Ausgrid to provide backup or standby supply to a site; and • network support agreements with the generator. Larger generators that are relied on for network support are generally included as a negative block load. In determining whether a generator is ‘large’, Ausgrid uses the same approach as is used for block loads and transfers. 3.2.3.4 Capacitors for power factor correction Reactive compensation for locations with known capacitor installations is modelled according to the following guidelines: • Growth rates are applied to the uncompensated MVAr component of load prior to switching in Ausgrid capacitors. In other words, growth rates are not applied to capacitors. • The amount of reactive compensation for forecast years is applied according to the nameplate step size and maximum available MVAr capacity and the application of 2 adjustment factors, the voltage adjustment factor and the operational adjustment factor. • The voltage adjustment factor calculated at 0.84 accounts for the difference between the nameplate rated voltage and the operational voltage at the corresponding substation. The voltage adjustment is the square of the ratio of nominal operational secondary voltage at the substation over the nameplate rated voltage of the capacity ie (11/12kV)² or (33/36kV)². • The operational factor accounts for the fact that capacitors are not necessarily switched in to maximise power factor. In determining the operational factor, historical patterns of capacitor switching are used. 3.2.3.5 Weather correction Historical loads are weather corrected, to enable statistical trend line calculation of growth rates and the determination of probabilistic forecast loads. The weather correction factor is the percentage difference between the weather corrected and actual load in the most recent historical year. This correction factor can be negative, positive or zero. Weather correction is applied according to the following rules: Maximum demands are weather corrected with a probability of exceedance of 50% (POE50) which forms the basis for planning decision-making.

• Each substation uses 10 years of Bureau of Meteorology (BOM) data from the geographically closest BOM weather station; • Ambient temperature is used; and • Weather correction is applied using a Monte-Carlo simulation method to determine the POE50 maximum demand. The simulation incorporates non-working days to model the effect of substations that can peak on a non-workday. 3.2.3.6 Exceptions for weather correction Weather correction is not applied to zone substations or subtransmission substations where the load does not exhibit weather dependency for that season, or where the load exhibits weather dependency that does not follow the general trend expected for that season based on an examination of the seasonal load versus temperature relationship. Weather correction is not applied to dedicated large customer loads (connected at the subtransmission level). 3.2.3.7 Rate of growth The rate of growth, which may be negative, is calculated according to the following process: • the historical block loads, load transfers, and small scale solar generation are adjusted out of the historical weather corrected loads to reveal the underlying trend; • the weather corrected and adjusted trends are reviewed by an expert panel to consider factors that could influence the growth rates, such as Local Government Plans; and • a growth rate of zero is applied to dedicated customer loads (connected at the subtransmission level). 3.2.3.8 Block loads and transfers Block loads for customer connections greater than a predefined threshold (as described below) are included after the application of underlying growth rates which specifically exclude these often large and lumpy changes in customer demand. A block load or transfer can result in either an increase or decrease in the forecast load (e.g. load can be transferred to or from a zone substation). This approach to block loads has been adopted as there is a need to distinguish between natural load growth and growth arising from these larger customer connections. Large individual customer connections at a spatial

15

level is often sporadic in nature and including such loads in the trend can lead to an over or under forecast of demand for the network asset. Removing these changes in demand for the calculation of the trend ensure that we capture the underlying trend. Depending on the nature of block loads activity, some block loads may be individually small or there may be numerous block spot loads occurring around the same time at a given substation. To account for these possibilities, the sum of block loads for each year for each zone substation is compared to a threshold of 50A (approximately 1MVA @ 11kV). Where the sum is less than the threshold, the growth is considered to be organic and not included as a block load adjustment in the forecast. Block loads are differentiated to account for the differing nature of these customer connections. The block load categories are late stage 11kV block loads, early stage 11kV block loads and major customer connection block loads. Scaling factors are derived from a detailed analysis of actual historical customer demand and connection data which are then applied to the requested capacity.

A summary of the block load categories is as follows: Category Description Scaling Factor Early-stage General 11kV connections which have applied for 0.36 11kV connection Late-stage General 11kV connections which have received 0.58 11kV connection design approval Major 33kV+ connections or unique industry 11kV connections based on Customers (e.g. rail) industry

The higher resultant scaling factor for late stage 11kV block loads has been determined from detailed analysis of historical block load data and reflects the higher probability for a connection proceeding when a connection has progressed to this stage. As the 11kV scaling factors are derived from actual customer connection data and the actual resultant demand at the local 11kV panel and at the time of 11kV panel peak for real customer connections, they incorporate coincidence with peak, probability of proceeding and any industry-specific scaling factors in the case of major customer connections. Major customer connections have a representative scaling factor applied that varies depending on the industry type and expected customer future demand profile. Where available, actual demand data from existing customers by industry type is used to derive coincidence factors. A further probabilistic factor is applied to reflect the probability of occurrence and oversizing to derive an overall scaling factor for each individual major customer connection. 3.2.4 Explanation of substation forecast outcomes The resultant 2019 spatial maximum demand forecast at a system level is broadly similar to the 2018 forecast with significant block load activity continuing to drive higher growth rates at selected locations in the Sydney region. The 2019 forecast update includes continued improvements to forecast components including revision to the latest available relevant data sources, particularly in the econometric model. Due to an improved regression fit, NSW Gross Value Added Services has replaced NSW Gross State Product as the income explanatory variable in the 2019 non-residential econometric regression model. This change allowed for the use of the latest available historical demand information as previous forecast iterations had seen the non-residential econometric regression model using NSW GSP becoming less stable Further forecast improvements were also evident upon updating inputs for the take-up of rooftop solar, batteries and electric vehicles. The impact of these updated forecast components is modest with similar outcomes to the 2018 forecast. Moderation in demand in the long term is principally due to rooftop solar and battery storage, and energy efficiency forecasted impacts. Electric vehicles are expected to provide a modest lift to demand beyond 2030 though pockets of network stress due to peak demand impact of electric vehicle uptake may exist spatially prior to 2030. The near term forecast continues to show rising demand, due largely to sustained levels of connection activity from large customers. The overall volume of large customer connection (block load) activity continues to be at the high levels seen in the 2018 forecast and this has a significant impact on the forecast at a local spatial level. In combination with a very high level of high density residential developments, significant investment in road, rail and air transport infrastructure and rapid growth in data centre developments, large customer and generator connection activity remains at a rate not seen in over a decade. For the 2019 forecast, at the spatial level, around 60% of zones in summer and 40% of zones in winter are expected to experience growth in maximum demand over the next 5 years to 2024 (based on compound annual

16

growth). This is up from 54% of zones in summer and down 43% of zones in winter expected to experience growth to 2024 in the 2018 forecast. 3.3 Transmission - distribution connection point load forecasts Ausgrid prepares an annual transmission distribution connection point forecast which is provided to TransGrid in May each year as part of the annual planning review and load forecast information provisions of the NER. A forecast of future loads over a ten year forward planning period is prepared for each dual function subtransmission substation connected to the TransGrid transmission network. These load forecasts are presented in Section 6.2.1 Dual function substation demand forecasts. As part of the annual load forecast development Ausgrid provides TransGrid with the “132kV TransGrid Report” which provides an input for their power system load flow modelling of the Ausgrid network. It contains MW, MVAr and uncompensated power factor data per year for the most recent actual year and 10 forecast years for each: • 132kV connection point (subtransmission substations, 132/11kV zone substations and 132kV customers); and • Zone substation supplied from other Distribution Network Service Providers (DNSPs), such as Epping, Leightonfield, and Hunters Hill, irrespective of supply voltage. 3.4 Subtransmission feeder load forecasts Ausgrid undertakes an annual review of subtransmission feeder capacity constraints (“the feeder load forecast”) using load-flow analysis to simulate credible network contingencies. Initial analysis is conducted using network load-flow models for a forward looking 20 year period, based on: • A 50% POE Planning Spatial Demand Forecast, including committed spot loads and uncommitted spot loads by applying a probability; • Committed network developments and load transfers, and • Line and cable cyclic normal and long-term emergency ratings. The results of this analysis form an input into the Area Planning process and the Annual Capital Review process. During these processes, a cost benefit analysis based on a probabilistic criteria is undertaken in order to maximimise the economic benefit of investment to relieve identified constraints. 3.5 Primary distribution feeder load forecasts Ausgrid’s primary distribution feeder forecast contains peak load values that are selected seasonally and adjusted to account for temperature variation and abnormal switching on the distribution network. The summer and winter peak loads are identified by comparing the 15 minute interval load data for the primary distribution feeders to the associated zone substation historic peak load data. Any inconsistencies between the primary distribution feeder and zone substation interval data, as well as any abnormal load switching are identified. If there is no evidence of abnormal switching the primary distribution feeder peak load value can be assessed as normal and no further analysis of the historic load is required. If there is any evidence of abnormal switching, it is investigated and the load value is adjusted accordingly to compensate. The weather correction applied to the associated zone substation load is also applied to the primary distribution feeder if appropriate. The associated zone substation forecast load rate of growth (ROG) and known network changes (spot loads and transfers) are applied to the previously adjusted load value for a forward planning period covering the next 6 years if appropriate. There are no primary distribution feeders that exceeded their rating in the past year or are forecast to exceed it in the next two years during normal conditions. 3.5.1 Load transfer capacities of zone substations Load transfer capacity is the amount of load that can be restored in the event of a whole zone outage by switching the distribution network. The transfer capacities presented in the distribution demand forecast table as described in Section 3.1 assume that a single zone is rendered out of service and the rest of the network is in system normal configuration. Load transfers are generally considered to be a temporary solution as transferring load to neighbouring zone substations will increase the utilisation of the destination zone and feeders. This has an adverse impact on the operability of the network as the remaining distribution network is more highly utilised than planned and further restoration of subsequent contingencies may not be possible.

17

Transfer capacities presented in this document are based on the configuration of the HV network in Summer 2017/18. Installation of additional HV interconnection and transfer capacity is typically a further consideration where it might provide a cost effective alternative to other capital investment associated with zone substations or the subtransmission network. Load transfer impacts are assessed on a case by case basis (typically in a load flow program) to ensure that the overall impact of load transfers does not overload assets in the distribution network. Additionally, a load transfer alters the configuration of the distribution network which may impact the capacity of subsequence load transfers. Therefore, the presented transfer capacities assume that no other load transfers have occurred. 3.6 Other factors having a material impact on the network 3.6.1 Fault levels Ausgrid plans its network to provide that fault currents are within the rated limits of network and customer equipment for considered operating scenarios a range, which allows this equipment to operate correctly and safely. The particular scenarios that are considered vary by network type and location commensurate with the associated risks under those conditions. In general, investment cost and reliability consequences increase with voltage and higher voltage networks are held to more rigorous performance measures than lower voltage networks. Particular areas where fault levels are currently affecting the operation and investment decisions on the network follow: Fault levels at TransGrid’s Beaconsfield BSP exceed 40kA under some operating arrangements. TransGrid has installed new 50kA rated switchgear at Beaconsfield BSP (condition-driven replacement) and Ausgrid is now using equipment rated at this level for potential future Ausgrid developments in the area. Nearby existing substations with 40kA rated switchgear, under certain operating scenarios, operate very close to their limits and this restricts some network configurations. There are numerous open points on the 132kV meshed transmission system due to these fault level limitations. These open points create more complicated switching arrangements and limit network flexibility. 132kV series reactors have been installed by TransGrid at the new Rookwood Rd BSP in part to limit fault level contribution (along with power flow control). In addition to these reactors new open points have been created on the 132kV network to restrict fault levels to below equipment ratings following the energisation of this BSP. For a number of 132/33kV subtransmission substations (STS) refurbishments changes have been made in the standard arrangement for neutral earthing due to the limitations uncovered in past Ausgrid network standards. This results in individual transformer neutral earthing reactors being installed in place of a common neutral earthing resistor. The HV Network Reinforcement program is designed to overcome fault level issues in the HV network. These issues can be for both high and low fault levels. Feeders that have high fault levels can result in damage to equipment. Feeders with low fault levels may have protection that cannot see or discriminate between fault locations which leads to increased clearing times or excessive customers being interrupted. Typical solutions to these issues are to upgrade the feeder, modify the protection settings or alter the network configuration. 3.6.2 Voltage levels The meshed inner-metropolitan network is supplied by two large radial 330kV cables with very high charging capacitance. The inner-metropolitan network is also comprised of a number of long 132kV cables with significant cable charging capacitance. This means capacitor banks are required during cable outages to replace this lost reactive support, however during low load conditions shunt reactors are required to reduce voltages. These cables also have series reactors for power flow and fault level control, which exacerbate voltage issues at some times. Capacitor banks are located at Beaconsfield BSP, Peakhurst STS and Bunnerong STS and shunt reactors at Rookwood Rd BSP to help manage the voltage on the 132kV meshed network. Since the commissioning of Rookwood Rd BSP, in order to manage voltage levels in the northern Sydney area, one of the two 132kV shunt reactors at Mason Park is almost always in service with the other one switched in during times of low load. Both reactors at Mason Park are presently in defective state resulting in managing the voltage has become significantly more difficult. Due to its specialised nature, the 132kV shunt reactor will take some time to be replaced. Until it is replaced, the operating difficulties will continue. The radial network connected to Muswellbrook BSP is supplied from three 132kV overhead feeders and spans a significant distance to Singleton 132kV STS. Under system abnormal conditions of the 132kV subsystem and high network loading, network voltages can drop below 0.9pu at Singleton 132kV STS. Closing of the normally open 132kV interconnector to Newcastle BSP will assist in maintaining system voltages during these conditions. Voltage control to manage 11kV network voltages is done at zone substations using tap changing transformers and where necessary capacitor banks.

18

3.6.3 Other power system security requirements Ausgrid’s under frequency load shedding capabilities are assessed on a bi-annual basis to ensure compliance with NER requirements. Projects are created where compliance is no longer met due to network topology rearrangements or at the request of AEMO. 3.6.4 Quality of supply Ausgrid endeavours to provide quality of supply to customers that is necessary to operate their equipment. In general, this is achieved by operating Ausgrid’s network, and requiring customers to operate their electrical installations, consistent with power quality requirements set out in the National Electricity Rules (NER), NSW Service and Installation Rules (SIR) and Ausgrid’s Network Standard NS238. Ausgrid investigates supply quality issues as they arise, including supply voltage, harmonics, and flicker. At Ausgrid, supply quality is monitored through permanent monitors at a selection of sites across the network at different voltage levels. Temporary supply quality monitors are installed at customer premises to investigate specific supply quality issues and complaints. 3.6.5 Embedded generation Ausgrid has published on its website, guidance for proponents seeking to connect an embedded generating system under Chapter 5A or Chapter 5 of the NER. The information includes guidelines, Network Standards, Electrical Standards and proforma contracts, and Connection Application forms. A register of completed generator connections is also maintained in accordance with the NER requirements. Ausgrid provides basic connection offers services and offers for inverter coupled micro embedded generator units up to 30kW where augmentation of the network is not required. All other embedded generating units are offered a negotiated template connection offer consistent with Chapter 5A for units that are not registered with AEMO and Chapter 5 in the case of Registered Generators of the Rules. During 2018, Ausgrid completed a review of our Network Standard NS194 which sets out technical requirements for connection of generators. A new version of NS194 was published in October 2018, and provides the following improvements for customers connecting inverter coupled systems between 30kVA and 200kVA: • Aligns requirements for these systems to AS/NZS4777.1 Grid connection of energy systems via inverters, with options for alternative protection configurations within the bounds of the standard; and • Refers design approval and verification of these protection systems to the external market, removing a common source of project delays. These systems represent the majority of applications for connection of larger embedded generators (over 30kVA). Ausgrid continues to work with industry partners including the Clean Energy Council, ENA and other DNSP's to better understand the current and future network impacts of embedded generation and the emerging battery storage market and its implications within Chapter 5A of the Rules. This includes working with the ENA and other DNSP to establish national guidelines for connection of embedded generation to facilitate the fair and efficient integration of distributed energy resources into the grid. National guidelines for basic micro, low voltage embedded generation connections were published during 2019 and are available from the ENA website here: https://www.energynetworks.com.au/projects/national-grid-connection-guidelines/ Work is underway to produce the next set of guidelines to address medium voltage (MV) and high voltage (HV) connections within the distribution system. Ausgrid has experienced a substantial increase in the number of customers applying to connect embedded generation, and particularly the level of activity in relation to Registered Participants and the interaction between the Ausgrid network and their respective generator proposals. This includes modification to existing embedded generators, new generator proposals and interactions with market aggregators. 3.7 National Transmission Network Development Plan The National Transmission Network Development Plan (NTNDP)4 is the outcome of the Australian Energy Market Operator (AEMO) annual national transmission review. It provides an integrated overview of the current state and potential future development of the National Electricity Market (NEM) transmission grid. The NTNDP includes a review of the: • National transmission flow paths

4 NTNDP is now covered in the Integrated System Plan (ISP) published by AEMO.

19

• Identification of forecast constraints on the national transmission flow paths, and • Options that are technically capable of relieving forecast constraints on national transmission flow paths. A copy of the annual NTNDP is available on AEMO’s website at https://www.aemo.com.au 3.7.1 Transgrid is responsible for transmission outcomes in NSW In the NTNDP, network augmentation proposals by TNSPs that affect national transmission flow paths are taken into account by AEMO in the development of conceptual augmentation options and market development scenarios. TransGrid is the Jurisdictional Planning Body (JPB) for NSW in the NEM. In this role TransGrid: • represents the NSW jurisdiction on the Inter-Regional Planning Committee (IRPC); and • provides jurisdictional information to the IRPC to enable it to assist AEMO in producing its annual Statement of Opportunities (SOO) and the NTNDP.

Accordingly, TransGrid is responsible for providing information concerning transmission developments in NSW which may affect the power transfer capacity of national transmission flow paths. Further details are available on TransGrid’s website at https://www.transgrid.com.au

20

4 Network Asset Retirements and Deratings

To maintain reliable, safe, sustainable and efficient network services to consumers Ausgrid manages the replacement of aged assets through a combination of individual projects and programs of work. These works manage the risks associated with asset failure, obsolescence (economic or technological), environmental as well as employee & Public Safety concerns. A major project is a discrete, non-recurring scope of work that has specific objectives, budget and resourcing. Due to their complexity and scale, major projects are planned at an area level to identify opportunities to efficiently address other replacement, augmentation or connection issues. Replacement programs consist of proactive and reactive programs. Proactive programs involve the planned replacement of assets where it has been determined that the supply or other risks of failure exceed the cost of replacement. Reactive programs are developed to replace assets where it is feasible to replace them at end of life or after failure. Due to the uncertain nature of reactive programs, no details of these replacements are provided in this report. The assets that Ausgrid is planning to replace as major projects and proactive replacement programs in the next five planning years are detailed in data tables published online, with the online data as described in Section 3.1. Assets with individual replacement values of less than $200,000 are grouped by asset category. In keeping with advice from the AER, that data is made accessible in a format that can been readily interrogated, forecast and related data tables are published online and can be accessed via the following web address: www.ausgrid.com.au/DTAPR

21

5 Distribution Load Areas

This section should be read in conjunction with the rating and demand forecast data files which are available for download from Ausgrid’s website at www.ausgrid.com.au/DTAPR, and as outlined in Section 3.1. DNSPs are required to provide information on anticipated system limitations in this Annual Planning Report (refer NER Schedule 5.8, clause (c)). Under the former licence conditions and planning standards, system limitations could be readily identified as constraints, due to the nature of the deterministic approach. However, with the removal of those standards, Ausgrid has adopted a probabilistic planning methodology, based on the AER suggested approach of assessing risk of expected unserved energy (EUE) against the value of customer reliability (VCR). In relation to the timing of anticipated system limitations, for the purpose of this Annual Planning Report, the proposed investment date is reported as determined by the cost / benefit analysis as part of the probabilistic planning methodology. Consideration of remedial action is required when network elements exceed secure capacity. Identified limitations and indicative solutions are listed in Area Plan regional groupings, with the following information: • Substation – the name of the location, usually a zone or subtransmission substation; • Feeder – the name of the feeder, indicating the location of the feeder; • Timing – the identified need date by which a solution is planned to be implemented; and • System limitation – an identified network need. “Capacity” indicates there is a projected network capacity shortfall on the basis of expected unserved energy, and cost benefit analysis has been applied to identify an optimum solution and its timing. “Asset condition” refers to an asset being identified as having condition issues or approaching the end of service life, and cost benefit analysis has been applied to identify an optimum solution and its timing.

22

5.1 Camperdown and Blackwattle Bay load area 5.1.1 Description of Camperdown and Blackwattle Bay load area The Camperdown and Blackwattle Bay network area is a predominantly urban area on the fringe of the Sydney CBD. It includes high-density residential developments and commercial areas such as Darling Harbour, Broadway, Pyrmont and Camperdown. A small geographical area is supplied by Darling Harbour 132/11kV Zone Substation, Camperdown 33/11kV and Blackwattle Bay 33/5kV zone substations. There is one remaining Zone Substation in Ausgrid’s network that supplies electricity at 5kV, and conversion to 11kV is in progress. Camperdown ZS, Blackwattle Bay ZS and Darling Harbour ZS supply the suburbs of Pyrmont, Ultimo, Glebe, Camperdown, Forest Lodge and Annandale. Camperdown ZS also partly supplies the University of Sydney. Pyrmont STS is also included in the Camperdown and Blackwattle Bay network area. Supply at 33kV is provided from Pyrmont STS to three major customers: Barangaroo South, Sydney Trains and Global Switch (a data centre). The network in the Camperdown and Blackwattle Bay area has the following characteristics: • Darling Harbour ZS and Pyrmont STS are located in the same building and are both supplied at 132kV from Haymarket Bulk Supply Point (BSP); and • Camperdown 33/11kV ZS and Blackwattle Bay 33/5kV ZS are supplied from Pyrmont STS. Blackwattle Bay is the only zone with a 5KV distribution network in Ausgrid and hence, has very limited load transfer capability with adjacent zones. The 5kV distribution system in the Blackwattle Bay area is among the oldest assets in Ausgrid’s system. Ausgrid’s policy is to progressively replace the 5kV system with 11kV assets to increase operational flexibility by allowing load transfers between adjacent zone substations if required. There is a committed project to decommission Blackwattle Bay ZS by converting the 5kV to an 11kV system and transferring the load to Camperdown and Darling Harbour ZS. Details of this project are provided in Chapter 7.

Figure 5.1: Camperdown load area

23

5.1.2 Identified system limitations

Substation/ System limitation Load Impact on Discussion of Potential Credible Solutions Feeder name reduction Transmission - for 1 year Distribution Timing Driver deferral Connection (MVA) Points Nil

5.1.3 Identified Substation and Feeder limitations changes from last year’s DAPR - deferred or committed projects Substation/Feeder Name System Limitation Reason for Change Timing Driver Nil

24

5.2 Canterbury Bankstown load area 5.2.1 Description of Canterbury Bankstown load area The Canterbury Bankstown network area extends from Leightonfield in the north-west, Revesby in the south, and east as far as Dulwich Hill. The area encompasses a broad spectrum of load types from low density residential through to large commercial and industrial customers. The area contains substantial industrial precincts at Chullora, Leightonfield, Milperra and Padstow. Due to the anticipated – City & Southwest project, both commercial and residential developments are forecasted in the Canterbury and Bankstown surrounding areas extending from Dulwich Hill to Bankstown. The network in the Canterbury Bankstown area: • is supplied from Ausgrid’s Inner Metropolitan transmission system, except for Revesby and Milperra zone substations, which are supplied from TransGrid’s Sydney South Bulk Supply Point; • includes 132/33kV subtransmission substations at Bankstown and Canterbury which supply five 33/11kV zone substations and provide 33kV supply to Sydney Trains and the M5 motorway; • includes six zone 132/11kV substations at Greenacre Park, Bankstown, Potts Hill, Sefton, Revesby and Milperra; • includes Leightonfield, a “stand-alone” 33kV zone substation, which is supplied from Endeavour Energy’s network at Guildford subtransmission substation; • includes substantial lengths of 33kV gas-pressure cables, which are an obsolete technology; and • is traversed by transmission feeders 92C, 92X, 91X2, 91Y2, 910, and 911.

Figure 5.2: Canterbury Bankstown load area

25

5.2.2 Identified system limitations

Substation/ System limitation Load Impact on Discussion of Potential Credible Solutions Feeder name reduction Transmission Timing Driver for 1 year -Distribution deferral Connection (MVA) Points 1.Leightonfield Sep-23 Asset condition 11.4 MVA None Credible solutions include: ZS (11kV 1. Refurbish Leightonfield ZS; switchgear) 2. Retire Leightonfield via new zone substation; 3. Retire Leightonfield ZS via load transfer; or 4. Defer retirement of Leightonfield ZS via demand management. An assessment of non-network options concluded that it is not considered probable that sufficient demand management measures could be feasibly implemented to achieve the required demand reduction to make the project deferral technically and economically viable. Note that the assessment was based upon preliminary assumptions for project costs, unserved energy and other benefits with a more detailed assessment to be conducted as part of the Regulatory Investment Test.

5.2.3 Identified Substation and Feeder limitations changes from last year’s DAPR - deferred or committed projects Substation/Feeder Name System Limitation Reason for Change Timing Driver Nil

26

5.3 Carlingford load area 5.3.1 Description of Carlingford load area The Carlingford network area extends east from Endeavour Energy's Carlingford subtransmission substation to Epping and Macquarie Park, and as far south as Hunters Hill and Meadowbank. The area is bounded by the supply boundary with Endeavour Energy to the north-west, by the Lane Cove River Valley to the north, and the Parramatta River and Sydney Harbour to the south and east. The Macquarie Park area, running along the northern boundary of the Carlingford network area contains significant commercial load arising from but not limited to: • Macquarie University; • Macquarie Park commercial area; • Data Centres; and • North Ryde Station precinct. Significant commercial developments are expected to continue in this area as a result of the proposed North West rail line. Between the commercial areas there is significant residential load with high density development in the Epping, Macquarie Park, Meadowbank and Ryde areas. The distribution network in the Carlingford load area is supplied by two electrically separate subtransmission systems - a 66kV network supplied from Endeavour Energy’s Carlingford subtransmission substation, and Ausgrid’s 132kV network interconnected to TransGrid’s Sydney North Bulk Supply Point, Lane Cove Switching Station and Mason Park Switching Station. The area adjoins Endeavour Energy so the new developments can be supplied via Endeavour Energy.

Figure 5.3: Carlingford load area

27

5.3.2 Identified system limitations

Substation/ System limitation Load Impact on Discussion of Potential Credible Solutions Feeder name reduction Transmission for 1 year -Distribution Timing Driver deferral Connection (MVA) Points Nil

5.3.3 Identified Substation and Feeder limitations changes from last year’s DAPR - deferred or committed projects Substation/Feeder Name System Limitation Reason for Change Timing Driver 1. Macquarie STS Jan-22 Customer connection The Regulatory Investment Test for Distribution (RIT-D) was completed for this project in October 2018 and is a committed project.

The project assessment report considered two credible network options and non-network alternatives; determining that the option with the highest net market benefits was for the construction of a new 132/33kV subtransmission substation co-located with the Macquarie Park zone substation site. The draft and final project assessment reports and notice of non-network options can be found on Ausgrid’s website at www.ausgrid.com.au/ritd under ‘Address increased customer demand requirements in the Macquarie Park area’.

28

5.4 Eastern Suburbs load area 5.4.1 Description of Eastern Suburbs load area The Eastern Suburbs load area includes Sydney’s eastern seaboard from South Head to La Perouse, and extends inland to Surry Hills in the north-west, and west as far as Marrickville. The area encompasses a broad spectrum of load types from medium-density residential through to large commercial and industrial customers. The area contains substantial industrial precincts at Botany, Mascot and Alexandria, as well as major customers such as Sydney’s major domestic and international airports, the Garden Island Naval base, the University of New South Wales and the Sydney Cricket Ground/Football Stadium. The NSW Department of Planning views Alexandria as a corridor for major commercial and industrial growth in the medium-term future. The network in the Eastern Suburbs area: • is supplied from the Inner Metropolitan transmission network, including Bunnerong North subtransmission substation, Alexandria subtransmission substation and TransGrid’s Beaconsfield West and Haymarket Bulk Supply Points; • includes 132/11kV and 33/11kV zone substations, as well as 132kV and 33kV gas, oil and HSL feeders; • supplies high voltage customers including Sydney Trains (Surry Hills), Sydney Airport, AMCOR, and a chemical plant directly at 33kV; • supply Equinix data centre and WestConnex from Alexandria STS; • includes assets which are in poor condition, particularly 132kV and 33kV cables and many zone substation 11kV busbars, and • much of the existing 33kV standby feeder network involves extremely long feeders, complex connections and is operationally difficult. In addition to existing loads in the area, Sydney Airport Corporation Limited (SACL) has indicated plans to increase their demand in both the medium-term and long-term future. Several other large load applications in particular data centres and Transport for NSW projects in the Alexandria area have been submitted to Ausgrid and are under development. Information from town planning cites Alexandria as an area for major future development. These developments provide an opportunity to efficiently replace existing assets at the same time as providing additional capacity.

Figure 5.4: Eastern Suburbs load area

29

5.4.2 Identified system limitations

Substation/ System limitation Load Impact on Discussion of Potential Credible Solutions Feeder name reduction Transmission for 1 year -Distribution Timing Driver deferral Connection (MVA) Points 1. Sydney Dec-21 Asset Condition NA None Credible solutions include: Airport ZS (33kV (dedicated 1. Reconfigure Sydney Airport ZS 33kV switchgear) customer arrangement; site) 2. Retire Sydney Airport via a new 132/11kV zone; 3. Retire Sydney Airport ZS via load transfer; 4. Reconfigure Sydney Airport zone and replace 33kV feeders from Bunnerong North STS; or 5. Defer the retirement of feeders via demand management.

A review of customer requirements and the potential impact of large infrastructure projects was completed. Upon completion, and the confirmation of any changes to the credible network solutions, a demand management assessment will be completed. 2. Mascot ZS Dec-22 Asset Condition 3.0 MVA None Credible solutions include: (11kV 1. Refurbish existing Mascot ZS; switchgear) 2. Retire Mascot via new 33/11kV ZS; 3. Retire Mascot via new Mascot East 132/11kV ZS. The possible solution is 3. Feeders 327, Dec-22 Asset Condition As per None transfer some load to adjacent zones initially 328, 332, 337, Mascot and for the 132kV supply loop into existing 341 & 360 – ZS. See feeder 9FF (ex 91M/3)); Bunnerong item 2 4. Retire Mascot ZS via load transfer; or North STS to above. 5. Defer retirement of Mascot ZS via demand Mascot ZS management.

An assessment of non-network options concluded that it is probable that sufficient demand management measures could be feasibly implemented to make the project deferral technically and economically viable.

Note that the assessment was based upon preliminary assumptions for project costs, unserved energy and other benefits with a more detailed assessment to be conducted as part of the Regulatory Investment Test.

30

Substation/ System limitation Load Impact on Discussion of Potential Credible Solutions Feeder name reduction Transmission for 1 year -Distribution Timing Driver deferral Connection (MVA) Points 4. Paddington Mar-22 Asset condition Fdr 380: None Credible solutions include: 33kV feeders 12.0 MVA 1. Like-for-like replacement of feeders at 380, 381 and Paddington ZS together; 2. Replacement of Paddington feeders in two 382 Fdr 381: 21.5 MVA stages; 3. Decommissioning of Paddington ZS along with 33kV feeders; or Fdr 382: 4.Defer replacement of Paddington 33kV 17.8 MVA feeder via demand management.

An assessment of non-network options concluded that it is not considered probable that sufficient demand management measures could be feasibly implemented to achieve the required demand reduction to make the project deferral technically and economically viable. Note that the assessment was based upon preliminary assumptions for project costs, unserved energy and other benefits with a more detailed assessment to be conducted as part of the Regulatory Investment Test. 5. Surry Hills ZS Jun-24 Asset condition Fdr 376: None Credible solutions include: 33kV feeders 14.7 MVA 1. Like-for-like replacement of feeders at 376, 383, 384 Surry Hills ZS; 2. Decommissioning of Surry Hills ZS along and 385 Fdr 383 14.7 MVA with 33kV feeders; or 3.Defer replacement of Surry Hills 33kV feeders via demand management. Fdr 384

14.7 MVA An assessment of non-network options concluded that it is not considered probable Fdr 385 that sufficient demand management 14.7 MVA measures could be feasibly implemented to achieve the required demand reduction to make the project deferral technically and economically viable. Note that the assessment was based upon preliminary assumptions for project costs, unserved energy and other benefits with a more detailed assessment to be conducted as part of the Regulatory Investment Test.

5.4.3 Identified Substation and Feeder limitations changes from last year’s DAPR - deferred or committed projects Substation/Feeder Name System Limitation Reason for Change Timing Driver 1. Feeder 265 Bunnerong STSS Jan-22 Asset condition This is a dual function asset and hence, included – Maroubra ZS in Chapter 6.0 as part of transmission Load areas.

31

5.5 Greater Cessnock load area 5.5.1 Description of Greater Cessnock load area The Greater Cessnock network area extends in the north to Rothbury and Allandale and south to Laguna and Quorrobolong. The area also extends from Kurri in the east, to Mt View and Pokolbin State Forest in the west. The area is geographically bounded by the Sugarloaf Mountain range in the east as well as the Watagan Mountains and Wollemi National Park to the south. Predominantly rural, the main urban development lies between and around Kurri township and the City of Cessnock. Development activity is focussed around the Pokolbin and Rothbury vineyard district, with ongoing winemaking and tourism development, as well as residential developments such as the Vineyards Resort at Rothbury becoming more prevalent. The new Huntlee township near Rothbury to the north of the area has commenced and will continue to grow over the next 20 years. The network in the Greater Cessnock area: • predominantly comprises a 33kV network supply from the Kurri subtransmission substation (STS), which is itself supplied via 132kV feeders from TransGrid Newcastle BSP at Killingworth; • includes two 132/11kV zone substations, one located at Rothbury and the other at Kurri ; • includes four 33/11kV zone substations; • includes one 33kV connected mining customer near Ellalong; • consists of approximately 100km of predominantly overhead 33kV feeder network; • is partially traversed by a number of 132kV overhead feeders between Killingworth and Kurri STS; and • is traversed by 132kV and 66kV feeders between Kurri subtransmission substation and Singleton STS.

Figure 5.5: Greater Cessnock load area

32

5.5.2 Identified system limitations

Substation/ System limitation Load Impact on Discussion of Potential Credible Solutions Feeder name reduction Transmission- for 1 year Distribution Timing Driver deferral Connection (MVA) Points

Nil

5.5.3 Identified Substation and Feeder limitations changes from last year’s DAPR - deferred or committed projects Substation/Feeder Name System Limitation Reason for Change Timing Driver Nil

33

5.6 Inner West load area 5.6.1 Description of Inner West load area The Inner West load area extends from Homebush Bay in the north, south-west to Rozelle and Leichhardt and west as far as Auburn. The area is divided by parts of the harbour and the Lane Cove River. Parramatta Road runs through the southern part of the area. The network in the Inner West area: • is supplied from TransGrid’s transmission system at Sydney North, and via Chullora subtransmission switching station from Beaconsfield and Sydney South Bulk Supply Points; • includes 132/33kV subtransmission substations at Homebush, Strathfield and Rozelle; • includes four 132/11kV zone substations at Burwood, Croydon, Drummoyne, Flemington, Homebush Bay and Leichhardt, supplied via Mason Park subtransmission switching station; • includes three 33/11kV zone substations at Auburn, Concord and Lidcombe, supplied via Homebush subtransmission substation; and • includes planned new Transport of NSW infrastructure projects that may add to load in the area.

Figure 5.6: Inner West load area

34

5.6.2 Identified system limitations

Substation/ System limitation Load Impact on Discussion of Potential Credible Solutions Feeder name reduction Transmission for 1 year -Distribution Timing Driver deferral Connection (MVA) Points 1. Concord Dec-22 Asset Condition 40.0 MVA None Credible solutions include: (11kV 1. Refurbish Concord ZS; Switchgear) 2. Retire Concord via new zone substation; 3. Retire Concord ZS via load transfer; or 4. Defer refurbishment of Concord ZS via demand management.

An assessment of non-network options concluded that it is not considered probable that sufficient demand management measures could be feasibly implemented to achieve the required demand reduction to make the project deferral technically and economically viable. Note that the assessment was based upon preliminary assumptions for project costs, unserved energy and other benefits with a more detailed assessment to be conducted as part of the Regulatory Investment Test.

5.6.3 Identified Substation and Feeder limitations changes from last year’s DAPR - deferred or committed projects Substation/Feeder Name System Limitation Reason for Change Timing Driver 1. Rozelle STS Oct-22 Customer connection The Regulatory Investment Test for Distribution (RIT-D) was completed for this project in December 2018 and is a committed project underway. The project assessment report considered one credible network option to upgrade the existing Rozelle STS to cater for the increased customer load. The upgrade includes the installation of new 33kV switchgear in a new switchroom building to be located at the western end of the Rozelle STS site, and the replacement of existing 132/33kV 30MVA transformer No.2 with a new 60MVA unit. The project assessment reports and notice of non-network options can be found on Ausgrid’s website at www.ausgrid.com.au/ritd under ‘Addressing increased customer demand requirements in the Rozelle area’.

35

5.7 Lower Central Coast load area 5.7.1 Description of Lower Central Coast load area The Lower Central Coast area includes all of the Gosford local government area and a portion of Wyong Shire. The area extends south from Tuggerah Bulk Supply Point (BSP) to Broken Bay/Brisbane Water. There is bushland to the west of the region, and water to the east and south. The coastal area of the Lower Central Coast is a popular holiday destination and is a dormitory suburb for Sydney. The area is currently a mix of rural, residential, commercial and industrial land use. The network in the Lower Central Coast area: • is normally supplied from TransGrid’s transmission system at Tuggerah and Vales Point Bulk Supply Points to the north via Ausgrid’s Central Coast 132kV transmission system. There is also a “normally closed” connection with Sydney East Bulk Supply Point to the south; • includes a mix of 132kV, 66kV and 33kV feeders and 132/11kV, 66/11kV and 33/11kV zone substations. 132kV supply to zone substations is a relatively recent supply development in the area. Historically, areas of high load density were supplied at 66kV; • supplies Sydney Trains at 66kV via the Ourimbah subtransmission substation; and • provides a 33kV supply at Mangrove Creek for water pumping.

Figure 5.7: Lower Central Coast load area

36

5.7.2 Identified system limitations

Substation/ System limitation Load Impact on Discussion of Potential Credible Solutions Feeder name reduction Transmission for 1 year -Distribution deferral Connection (MVA) Points

Nil

5.7.3 Identified Substation and Feeder limitations changes from last year’s DAPR - deferred or committed projects Substation/Feeder Name System Limitation Reason for Change Timing Driver Nil

37

5.8 Lower North Shore load area 5.8.1 Description of Lower North Shore load area The Lower North Shore load area extends from Chatswood and Castle Cove in the north to North Sydney in the south, and east to Mosman. The network in the Lower North Shore area: • is supplied from TransGrid’s transmission system at Sydney East via four 132kV feeders to Lindfield switching station; • includes Castle Cove, Crows Nest, Mosman, North Sydney and RNSH 132/11kV zone substations and Willoughby subtransmission substation, which are supplied at 132kV from Lindfield switching station; • includes 33/11kV zone substations at Chatswood and Gore Hill, which are supplied radially at 33kV from Willoughby subtransmission substation; • includes 132kV oil filled cables, which are an obsolete technology, the replacement or retirement is in progress; • supplies high rise commercial load in Chatswood and North Sydney; • predominantly serves residential and commercial load; • includes the 33kV supplies to three major customers, the Lane Cove Tunnel, Sydney Trains and Gore Hill Technology Park; and • includes planned new Transport of NSW infrastructure projects and data centres that may add to load in the area.

Figure 5.8: Lower North Shore load area

38

5.8.2 Identified system limitations

Substation/ System limitation Load Impact on Discussion of Potential Credible Solutions Feeder name reduction Transmission for 1 year -Distribution Timing Driver deferral Connection (MVA) Points 1.Willoughby Sep-24 Asset condition 229 MVA None Credible solutions include: STS (33kV 1. Refurbish Willoughby STS in the existing switchgear) switchroom; 2. Refurbish Willoughby STS in a new switchroom; 3. Retire Willoughby STS; or 4. Defer refurbishment of Willoughby STS via demand management.

An assessment of non-network options concluded that it is not considered probable that sufficient demand management measures could be feasibly implemented to achieve the required demand reduction to make the project deferral technically and economically viable. Note that the assessment was based upon preliminary assumptions for project costs, unserved energy and other benefits with a more detailed assessment to be conducted as part of the Regulatory Investment Test. 5.8.3 Identified Substation and Feeder limitations changes from last year’s DAPR - deferred or committed projects Substation/Feeder Name System Limitation Reason for Change Timing Driver Nil

39

5.9 Maitland load area 5.9.1 Description of Maitland load area The Maitland network area extends in the north from Luskintyre and Woodville and south to Heddon Greta and Black Hill. The area is traversed from west to east by the Hunter River. The associated flood plains create the northern and eastern boundary along with Hexham Wetlands to the south. The majority of existing urban development lies along the and railway transport corridor which passes from east to west through the middle portion of the area. Major residential development is continuing to the east of Maitland and around Thornton, and also to the west, north of Aberglassyn. The surrounding suburbs and villages contain a mixture of urban and rural development, with increasing amounts of light to medium industry along the main transport corridor. Intensive agricultural activities are also prevalent along the Hunter River flood plain. The network in the Maitland area includes: • Kurri and Beresfield subtransmission substations (STS) which are supplied via 132kV feeders from TransGrid’s transmission system at Killingworth (Newcastle); • one 132/11kV zone substation located at Brandy Hill; • six 33/11kV zone substations, three supplied from the 33kV network from Kurri STS, and three supplied from the 33kV network from Beresfield STS; • two 33kV connected mining customers and a 33kV connection for Hunter Water supply at Tarro; • 33kV feeder interconnections to the Tomago and Waratah 33kV networks via Tarro zone substation; and • provides the backup 33kV supply to the network supplying Martin’s Creek and Gresford.

Figure 5.9: Maitland load area

40

5.9.2 Identified system limitations

Substation/ System limitation Load Impact on Discussion of Potential Credible Solutions Feeder name reduction Transmission for 1 year -Distribution Timing Driver deferral Connection (MVA) Points 1. Tarro 33/11kV Sep-2023 Asset Condition, 15.5 MVA none Credible solutions include: Zone 11kV switchgear 1. Install new 11kV switchgear; Substation 2. Retire Tarro via new zone substation at Beresfield; Probabilistic Planning Assessments have shown the best net economic benefit of all credible solutions is the replacement of the 11kV Switchgear at Tarro 33/11kV Zone Substation. The assessment is based on the probability of equipment failure and resulting load at risk if any. It is expected that the replacement of the 11kV switchboard at Tarro 33/11kV Zone Substation will be completed in 2023. An assessment of non-network options concluded that it is not considered probable that sufficient demand management measures could be feasibly implemented to achieve the required demand reduction to make the project deferral technically and economically viable. Note that the assessment was based upon preliminary assumptions for project costs, unserved energy and other benefits with a more detailed assessment to be conducted as part of the Regulatory Investment Test.

5.9.3 Identified Substation and Feeder limitations changes from last year’s DAPR - deferred or committed projects Substation/Feeder Name System Limitation Reason for Change Timing Driver Nil

41

5.10 Manly Warringah load area 5.10.1 Manly Warringah load area The Manly Warringah area is bordered on three sides by Middle Harbour and the Tasman Sea. It is separated from the adjoining Terrey Hills and Pittwater area by Narrabeen Lakes and bushland. The network serves both urban residential and commercial areas, with major industrial demand in Brookvale and Dee Why West, and retail demand at Warringah Mall. The area is principally residential. There is substantial high density development along the beachfront forming the eastern boundary of the area whereas the rest of the area is characterised by detached dwellings. The Manly Warringah network supplies Manly and most of Warringah Shire, and: • is supplied at 33kV from Warringah subtransmission substation (STS), which is in turn supplied from TransGrid’s Sydney East Bulk Supply Point by four 132kV circuits; • includes eight 33/11kV zone substations and one 132/33/11kV zone substation; and • is supplied by a complex network of 33kV feeders, comprising both overhead lines, which generally cover inland areas, and underground cables, which generally cover coastal areas.

Figure 5.10: Manly Warringah load area

42

5.10.2 Identified system limitations

Substation/ System limitation Load Impact on Discussion of Potential Credible Solutions Feeder name reduction Transmission for 1 year -Distribution Timing Driver deferral Connection (MVA) Points Nil

5.10.3 Identified Substation and Feeder limitations changes from last year’s DAPR - deferred or committed projects Substation/Feeder Name System Limitation Reason for Change Timing Driver 1. Belrose ZS Sep-32 Asset condition (11kV Deferred due to updated status of the 11kV switchgear) switchgear condition.

43

5.11 Newcastle Inner City load area 5.11.1 Newcastle Inner City load area The Newcastle Inner City network area lies on the eastern seaboard of Newcastle. It is bounded by the Hunter River to the north and Glenrock State recreation area to the south and extends west to New Lambton. The area includes the principal CBD precinct for Newcastle, comprising a mixture of commercial and high density residential load. The surrounding suburbs contain a mixture of residential, commercial and industrial areas. Newcastle Harbour and the Hunter River, which form the northern boundary of the Newcastle Inner City area include the Honeysuckle development precinct along the foreshore and also contain several larger industrial 11kV customers including Port Waratah coal loading facility and State Dockyards at Carrington. The network in the Newcastle Inner City area: • is predominantly supplied at 33kV from Merewether subtransmission substation (STS); • is traversed by two 132kV feeders (960 & 961) which supply Merewether STS from TransGrid’s transmission system at Killingworth and a 132kV oil-filled cable, (9N9) which provides an alternative 132kV supply to Merewether STS from Waratah STS; • comprises six zone substations of which four are currently supplied from the 33kV network originating from Merewether STS and two are supplied from the 132kV network; • consists of around 36km of 33kV underground cables and 15km of overhead 33kV feeders; and • includes an underground 11kV triplex network supplying the Newcastle CBD area.

Figure 5.11: Newcastle Inner City load area 5.11.2 Identified system limitations

Substation/ System limitation Load Impact on Discussion of Potential Credible Solutions Feeder name reduction Transmission for 1 year -Distribution Timing Driver deferral Connection (MVA) Points Nil

44

5.11.3 Identified Substation and Feeder limitations changes from last year’s DAPR - deferred or committed projects Substation/Feeder Name System Limitation Reason for Change Timing Driver Nil

45

5.12 Newcastle Ports load area 5.12.1 Description of Newcastle Ports load area The Newcastle Ports network area extends from Hexham and Island in the north to Mayfield and Waratah in the south. It is bordered on the east by Newcastle Harbour and extends west to Jesmond, Shortland and Sandgate. The area contains significant heavy industrial development including coal transport and ship- loading facilities, steel manufacturing and processing and other port related activities. General urban residential and commercial development is also present around the Mayfield and Shortland areas. The University of Newcastle is located at Callaghan, which is adjacent to the now retired Shortland zone substation. The principal heavy industrial development is located on either side of the south-arm of the Hunter River at Mayfield North and on Kooragang Island. The former BHP-Billiton steel-works site is now largely unused and has been targeted for future development for port-based commercial and industrial activities. With the retirements of Carrington 33kV Zone Substation, Mayfield 33kV Zone Substation and Kooragang 33kV Switching Station the 33kV Subtransmission network in the Newcastle Ports area have been disconnected from the network. Only customer owned 33kV feeders to various heavy industrial customers remains as well as the Kooragang Island 33kV distribution network. The network in the Newcastle Ports area: • receives supply from TransGrid’s Bulk Supply Points at Newcastle BSP and Waratah West BSP. The 132kV network emanating from these substations supply both subtransmission (STS) and zone substations (ZS) within the area; • there are a number of 132kV feeders that interconnect with adjacent areas – Newcastle Western Corridor and Newcastle Inner City; and • there is also one major customer (Onesteel) that is supplied from the 132kV network. • there is also one major customer (Molycop, previously Comsteel) that is supplied from the 33kV network.

Figure 5.12: Newcastle Ports load area

46

5.12.2 Identified system limitations

Substation/ System limitation Load Impact on Discussion of Potential Credible Solutions Feeder name reduction Transmission- for 1 year Distribution Timing Driver deferral Connection (MVA) Points Nil

5.12.3 Identified Substation and Feeder limitations changes from last year’s DAPR - deferred or committed projects Substation/Feeder Name System Limitation Reason for Change Timing Driver Nil

47

5.13 Newcastle Western Corridor load area 5.13.1 Description of Newcastle Western Corridor load area The Newcastle Western Corridor network area is bounded by Hexham Wetlands to the north, and extends south to Boolaroo and Holmesville. It includes the suburbs of Wallsend and Cardiff to the east and extends west to the M1 Pacific Motorway and Mount Sugarloaf. The area includes a mixture of residential, light industrial and commercial development as well as several coal mining operations. It contains the principal urban expansion areas for Newcastle and Lake Macquarie. There is ongoing residential development, particularly around Maryland and Fletcher, as well as between Edgeworth and Cameron Park. The Glendale area is becoming an increasingly important commercial and transport hub as urban development in the area continues. The network in the Newcastle Western Corridor area: • is currently supplied from Argenton subtransmission substation; • consists of two older 33/11kV zone substations at Cardiff and Edgeworth; • includes two new 132/11kV zone substations at Maryland and Argenton; • contains two 33kV connected mining customers; • consists of approximately 40km of predominantly overhead 33kV feeder network; • contains TransGrid’s 330/132kV Newcastle Bulk Supply Point at Killingworth; and • is traversed by several 132kV overhead feeders between Killingworth Bulk Supply Point and a number of Ausgrid substations.

Figure 5.13: Newcastle Western Corridor load area

48

5.13.2 Identified system limitations

Substation/ System limitation Load Impact on Discussion of Potential Credible Solutions Feeder name reduction Transmission for 1 year -Distribution Timing Driver deferral Connection (MVA) Points

Nil

5.13.3 Identified Substation and Feeder limitations changes from last year’s DAPR - deferred or committed projects Substation/Feeder Name System Limitation Reason for Change Timing Driver Nil

49

5.14 North East Lake Macquarie load area 5.14.1 Description of North East Lake Macquarie load area The North East Lake Macquarie load area is bounded by Lake Macquarie to the west and the Pacific Ocean to the east. The load area extends from Charlestown in the north to Catherine Hill Bay in the south. The North East Lake Macquarie area includes the Charlestown CBD precinct, which comprises typical inner city commercial load. The surrounding suburbs contain a mixture of residential and commercial areas. The opportunity exists for significant future beachside and lakeside developments, particularly to the south of Swansea Channel. Increasing densities within both residential and commercial areas are anticipated for much of the area, particularly around Charlestown, which is becoming the principal commercial centre for Lake Macquarie. The network in the North East Lake Macquarie area: • is currently supplied from both Merewether subtransmission substation (STS) and Argenton STS which are both supplied via 132kV feeders from TransGrid’s transmission system at Killingworth; • consists of six 33/11kV zone substations, of which four are supplied from the 33kV network originating from Merewether STS, and two (Mt Hutton and Croudace Bay) are supplied from the 33kV network from Argenton STS; • consists of one 132/11kV zone substation at Charlestown; • is a predominantly overhead 33kV feeder network with a combined total length of more than 110 km; and • is traversed on its northern boundary by a double circuit 132kV tower line from Newcastle 330kV substation to Merewether STS.

Figure 5.14: North East Lake Macquarie load area

50

5.14.2 Identified system limitations

Substation/ System limitation Load Impact on Discussion of Potential Credible Solutions Feeder name reduction Transmission for 1 year -Distribution Timing Driver deferral Connection (MVA) Points Nil

5.14.3 Identified Substation and Feeder limitations changes from last year’s DAPR - deferred or committed projects Substation/Feeder Name System Limitation Reason for Change Timing Driver Nil

51

5.15 North West Sydney load area 5.15.1 Description of North West Sydney load area The North West network area includes the area from Sydney North Bulk Supply Point in the north, north-east to Berowra and south to Pennant Hills. The area is relatively geographically isolated, bordering Ku-ring-gai Chase National Park and other bush land. The main Sydney to Newcastle freeway and railway run through the eastern edge of this area. Most loads in this area arise from urban residential development in the south-eastern half of the area. Development is mixed and ranges from high-value residential properties in the Cherrybrook area to large scale apartment development at Hornsby. The network in the North West area: • is supplied from TransGrid’s transmission system at Sydney North Bulk Supply Point; • consists of three 132/11kV zone substations at Berowra, Hornsby, Pennant Hills supplied on a 132kV ring from Sydney North BSP, and Galston zone substation supplied from Sydney North BSP; and • includes a 66kV supply to Sydney Trains from Berowra zone substation.

Figure 5.15: North West Sydney load area

5.15.2 Identified system limitations

Substation/ System limitation Load Impact on Discussion of Potential Credible Solutions Feeder name reduction Transmission for 1 year -Distribution Timing Driver deferral Connection (MVA) Points Nil

52

5.15.3 Identified Substation and Feeder limitations changes from last year’s DAPR - deferred or committed projects Substation/Feeder Name System Limitation Reason for Change Timing Driver Nil

53

5.16 Pittwater and Terrey Hills load area 5.16.1 Description of Pittwater and Terrey Hills load area The Pittwater & Terrey Hills network area forms a long, narrow corridor beginning at Sydney East subtransmission substation (west of Belrose), and extending from Terrey Hills to Palm Beach in the north, and down the coast to Narrabeen. The area is bounded to the west by bushland and Broken Bay, and to the north and east by the Tasman Sea. The area is primarily low density residential, although there is continuing development of medium density housing in the Warriewood area. The network in the Pittwater & Terrey Hills area: • is supplied from TransGrid’s transmission system at the TransGrid/Ausgrid Sydney East subtransmission substation via two 120MVA transformers and three overhead 33kV feeders to Terrey Hills and Narrabeen zone substations, and Warriewood subtransmission switching station; • has two connection points with the Manly-Warringah distribution network to the south, which provides limited emergency back-up in the event of multiple 132/33kV transformer outages; and • has a 5MW landfill gas generator at Belrose which feeds in at Sydney East subtransmission substation 33kV busbar supplying the network.

Figure 5.16: Pittwater and Terrey Hills load area

54

5.16.2 Identified system limitations

Substation/ System limitation Load Impact on Discussion of Potential Credible Solutions Feeder name reduction Transmission for 1 year -Distribution Timing Driver deferral Connection (MVA) Points Nil

5.16.3 Identified Substation and Feeder limitations changes from last year’s DAPR - deferred or committed projects Substation/Feeder Name System Limitation Reason for Change Timing Driver Nil

55

5.17 Port Stephens load area 5.17.1 Description of Port Stephens load area The Port Stephens network area approximately coincides with Port Stephens local shire area. It extends from Nelson Bay and the coastline in the east, to Raymond Terrace in the west, and from Karuah in the north, to Stockton and Tomago in the south. The area is very diverse and includes tourism-based commercial development, heavy industrial development, the RAAF Fighter Base, and Newcastle Airport at Williamtown. The Port Stephens area has been targeted for future development and continues to grow steadily. Medium density tourist-related and residential urban development is prevalent around Nelson Bay. Two precincts have been identified at Medowie and Raymond Terrace for major subdivision developments. Tanilba Bay and Anna Bay have been earmarked for other large residential developments. The industrial developments at Heatherbrae and Tomago both have large portions of land subdivided for industrial development. The network in the Port Stephens area: • is supplied from Tomago subtransmission substation (STS); • includes eight zone substations all of which are supplied from the 33kV network from Tomago; • includes 33kV customer connections for the RAAF Fighter Base at Williamtown, Hunter Water Corporation at Tomago and AGL; • provides a back-up 33kV supply to Tea Gardens for Essential Energy; and • consists of approximately 195km of predominantly overhead 33kV feeder network.

Figure 5.17: Port Stephens load area

56

5.17.2 Identified system limitations

Substation/ System limitation Load Impact on Discussion of Potential Credible Solutions Feeder name reduction Transmission for 1 year -Distribution Timing Driver deferral Connection (MVA) Points 1. Stockton Sep-2021 Asset Condition 6.2 MVA None Credible solutions include: 33/11kV Zone (11kV Substation switchgear) 1. Replace 11kV switchgear

2. Build replacement ZS

Probabilistic Planning Assessments have shown the best net economic benefit of all credible solutions is the replacement of the 11kV Switchgear at Stockton 33/11kV Zone Substation. The assessment is based on the probability of equipment failure and resulting load at risk if any.

It is expected that the replacement of the 11kV switchboard at Stockton 33/11kV Zone Substation will be completed in 2021.

An assessment of non-network options concluded that it is not considered probable that sufficient demand management measures could be feasibly implemented to achieve the required demand reduction to make the project deferral technically and economically viable. 5.17.3 Identified Substation and Feeder limitations changes from last year’s DAPR - deferred or committed projects Substation/Feeder Name System Limitation Reason for Change Timing Driver Nil

57

5.18 Singleton Load area 5.18.1 Description of Singleton load area The Singleton network area extends from Liddell in the west and Westbrook to the north, through to Branxton in the east and south to the Putty Valley. The area is very diverse and includes residential customers, light to heavy industry, coal mining, agriculture, a number of vineyards and wineries, as well as dairy and beef farms and several horse studs. There are a number of residential developments to the north of Singleton and there is also likely to be increasing industrial activity in the Whittingham area south-east of Singleton. The principal developed areas are clustered around the New England Highway and rail network, with the main township of Singleton centrally located. There are many smaller rural communities around Singleton, including Bulga, Branxton, Greta, Broke, Jerry’s Plains, Putty Valley, Belford, Elderslie, Mitchell’s Flat and Glendon Brook. The network in the Singleton area: • is supplied from the Singleton 132/66kV STS and the Liddell 33kV Switching Station at ; • has an expansive 66kV subtransmission system comprising two closed ring networks; • includes a 66kV interconnection to Kurri STS via Branxton zone substation; • includes a smaller 33kV network supplied from AGL auxiliary 33kV supply at Liddell, which supplies a number of mining operations and conveyors; • includes seven 66/11kV zone substations and a number of Ausgrid-owned switching station sites on the Liddell 33kV network; and • has over twenty 66kV and 33kV connected mining customers.

The Singleton network area also contains AGL owned coal fired Power Stations, Bayswater and Liddell, forming part of NSW base load generation. AGL has formally indicated its intention to decommission Liddell Power Station in 2023. The expected closure of Liddell Power Station may require Ausgrid to seek alternate supply options for the 33kV network connected to the auxiliary supply from Liddell Power Station. Ausgrid is currently developing these supply options in consultation with AGL and TransGrid.

Figure 5.18: Singleton load area

58

5.18.2 Identified system limitations

Substation/ System limitation Load Impact on Discussion of Potential Credible Solutions Feeder name reduction Transmission for 1 year -Distribution Timing Driver deferral Connection (MVA) Points Nil

5.18.3 Identified Substation and Feeder limitations changes from last year’s DAPR - deferred or committed projects Substation/Feeder Name System Limitation Reason for Change Timing Driver Nil

59

5.19 St George load area 5.19.1 Description of St George load area The St George network area extends west from Arncliffe and Sans Souci on Botany Bay, and inland to Peakhurst. This is a predominantly urban area that includes high density residential developments and commercial areas such as the Hurstville retail district. Population growth continues to drive load growth along the rail corridor. The East Hills and railway lines and pass through the area. There are limited opportunities for connection with other areas of the network because of various geographic, network and physical features of the area, including water, transport infrastructure and customer load control frequencies. The construction of two new zone substations in the area allows for 11kV load transfers to facilitate retirement of three zone substations to address asset condition issues. The network in the St George area: • is supplied from Peakhurst subtransmission substation via two 132kV feeders from TransGrid’s transmission system at Sydney South Bulk Supply Point; • Includes five 33/11kV zone substations Arncliffe, Blakehurst, Mortdale, Riverwood and Sans Souci; • three 132/11kV zone substations Hurstville North, Kogarah and Rockdale; and • is traversed by 132kV XLPE cables from Peakhurst to Canterbury and Beaconsfield BSP.

Figure 5.19: St George load area

60

5.19.2 Identified system limitations

Substation/ System limitation Load Impact on Discussion of Potential Credible Solutions Feeder name reduction Transmission for 1 year -Distribution Timing Driver deferral Connection (MVA) Points 1.Riverwood ZS Sep-23 Asset condition 9.8 MVA None Credible solutions include: (11kV 1. Refurbish Riverwood ZS; switchgear) 2. Retire Riverwood via new zone substation; 3. Retire Riverwood ZS via load transfer; or 4. Defer refurbishment of Riverwood ZS via demand management.

An assessment of non-network options concluded that it is not considered probable that sufficient demand management measures could be feasibly implemented to achieve the required demand reduction to make the project deferral technically and economically viable. Note that the assessment was based upon preliminary assumptions for project costs, unserved energy and other benefits with a more detailed assessment to be conducted as part of the Regulatory Investment Test. 5.19.3 Identified Substation and Feeder limitations changes from last year’s DAPR - deferred or committed projects Substation/Feeder Name System Limitation Reason for Change Timing Driver 1.Peakhurst STS Mar-22 Asset condition (33kV The Regulatory Investment Test for switchgear) Distribution (RIT-D) was completed for this project in December 2018 and is a committed project. The project assessment report considered two credible network options and non-network alternatives; determining that the option with the highest net market benefits was for the construction of a new 33kV switchroom, installation of new 33kV switchgear and the retirement of the existing 33kV switchgear buildings at Peakhurst STS. The draft and final project assessment reports and notice of non-network options can be found on Ausgrid’s website at www.ausgrid.com.au/ritd under ‘Managing asset risks in the St George network area”’

61

5.20 Sutherland load area 5.20.1 Description of Sutherland load area The Sutherland network area extends from the Kurnell Peninsula in the north-east, along the southern side of Botany Bay and the Georges River, south as far as Waterfall and east towards the coast. It serves a mixture of residential, commercial and industrial areas. The network in the Sutherland area: • is supplied from TransGrid’s bulk supply point at Sydney South, via two double circuit 132kV tower lines • includes six 33/11kV zone substations supplied from 132/33kV subtransmission substations (STS) at Port Hacking and Kurnell, together with three 132/11kV and one 132/33/11kV zone substations • consists mainly of overhead lines, operating at 132kV and 33kV; • is exposed to a marine atmosphere in some places due to its proximity to the ocean (especially feeders 916 and 917); • has connections at 33kV to two landfill gas generators at Lucas Heights; • supplies Sydney Trains at Heathcote and Port Hacking, ANSTO at Lucas Heights, Caltex oil refinery, Sydney Water Desalination Plant at Kurnell, and Sydney Water at Woronora Dam; and • includes the ability to provide a 132kV back up supply to Endeavour Energy at Bellambi in the south.

Figure 5.20: Sutherland load area

62

5.20.2 Identified system limitations

Substation/ System limitation Load Impact on Discussion of Potential Credible Solutions Feeder name reduction Transmission for 1 year -Distribution Timing Driver deferral Connection (MVA) Points Nil

5.20.3 Identified Substation and Feeder limitations changes from last year’s DAPR - deferred or committed projects Substation/Feeder Name System Limitation Reason for Change Timing Driver 1. Miranda ZS Sep-30 Asset Condition, Deferred due to updated status of the 11kV 11kV switchgear switchgear condition.

63

5.21 Sydney CBD Load Area 5.21.1 Description of Sydney CBD load area The Sydney CBD network area extends from Circular Quay in the north, west to Darling Harbour, east to Woolloomooloo, and south to Haymarket. Bounded by Darling Harbour, Central Railway Station and the Domain, it comprises an area of less than 3 square kilometres. This is the commercial heart of Sydney, which contains approximately 45% of Sydney’s office space and is home to some 49,000 residents. A reduction in forecast CBD load has allowed for the deferral of Bligh St zone substation, with asset condition issues now able to be addressed by 11kV load transfers in the shorter term. The network in the Sydney CBD area: • includes 132/11kV zone substations at City Central, City North, City South and Dalley St. and a 33/11kV zone substation at City East; • is supplied at 132kV from TransGrid’s Haymarket Bulk Supply Point and from Ausgrid’s Inner Metropolitan Transmission network which includes supply from Rozelle and Lane Cove STSS; • includes 33kV supply to City East 33/11kV zone sourced from Surry Hills STS; • is an underground network, and • at the 11kV level, is predominantly of an underground triplex5 construction and provides an N-1 distribution supply.

Figure 5.21: Sydney CBD load area

5 The triplex design used on much of the distribution network in the CBD means distribution substations generally comprise three distribution transformers supplied radially by three 11kV feeders.

64

5.21.2 Identified system limitations

Substation/ System limitation Load Impact on Discussion of Potential Credible Solutions Feeder name reduction Transmission for 1 year -Distribution Timin Driver deferral Connection g (MVA) Points

1. Dalley St ZS Dec- Asset Condition 37.4 MVA None The Regulatory Investment Test for 2023 (11kV Distribution (RIT-D) was completed for this Switchgear) project in November 2018 along with City East decommissioning project and is part of 2. Feeders Dec-23 Asset Condition the preferred staged strategy for the Sydney CBD area. 92M/2, 928/1, (oil filled) 92L/1 and The project assessment report considered 929/2 two credible network options and non-network alternatives; determining that the option with the highest net market benefits was for the transfer of the substation loads of City East and Dalley Street zone substations to the Belmore Park zone substation in one 2×10 way duct bank and decommissioning City East and Dalley Street zone substations and its associated feeders. The draft and final project assessment reports and notice of non-network options can be found on Ausgrid’s website at www.ausgrid.com.au/ritd under ‘Addressing reliability requirements in the Sydney CBD’. 5.21.3 Identified Substation and Feeder limitations changes from last year’s DAPR - deferred or committed projects Substation/Feeder Name System Limitation Reason for Change Timing Driver Nil

65

5.22 Upper Central Coast load area 5.22.1 Description of Upper Central Coast load area The Upper Central Coast area covers the Wyong Shire and includes the area north of Tuggerah Bulk Supply Point , extending to Vales Point in the north, east to the coast, and to the western boundary of Wyong shire. The area includes Tuggerah Lakes and Lake Munmorah, which largely separate the inland areas from major industries include coal mining and power generation. The network in the Upper Central Coast area is comprised of a southern 132kV system and a northern 33kV system. The 132kV southern system: • comprises of a 132kV line linking TransGrid’s 330/132kV Munmorah and Tuggerah bulk supply points; • consists of three 132/11kV zone substations at Wyong, Charmhaven and Lake Munmorah; • provides support to TransGrid’s Tuggerah 330/132kV substation which is currently supplied by two 330kV feeders and transformers; and • includes a 132kV line running from Vales Point to Morisset zone substation (West Lake Macquarie area) and Ourimbah subtransmission substation. Although this line traverses the area, it does not supply the load within the area. The 33kV northern system: • comprises two radial feeders which are supplied from Munmorah STS, supplying zone substations at Noraville and Vales Point.

Figure 5.22: Upper Central Coast load area

66

5.22.2 Identified system limitations

Substation/ System limitation Load Impact on Discussion of Potential Credible Solutions Feeder name reduction Transmission for 1 year -Distribution Timing Driver deferral Connection (MVA) Points

Nil

5.22.3 Identified Substation and Feeder limitations changes from last year’s DAPR - deferred or committed projects Substation/Feeder Name System Limitation Reason for Change Timing Driver Nil

67

5.23 Upper Hunter load area 5.23.1 Description of Upper Hunter load area The Upper Hunter area is a large area extending to Wingen in the north, Liddell to the south-east and Kars Springs to the north-west. The main townships in the area are Muswellbrook, Aberdeen, Scone, Denman and Merriwa. Around these towns are many smaller rural communities including Moonan, Rouchel, Ellerston, Wingen, Parkville, Glenbawn, Dartbrook, Baerami and Sandy Hollow. Most of the area is either rural or sparsely developed, and includes many isolated and remote dwellings. Other than some residential developments occurring around Muswellbrook and on the eastern side of Scone, there is limited urban expansion taking place in the area. The area includes urban residential, light to heavy industrial development - particularly coal mining, as well as extensive vineyards, wineries, dairy and beef industries and horse studs. Predominant economic activities are power generation and coal mining. Future connection of generation in this area is considered to be possible, but has significant uncertainty. The network in the Upper Hunter area: • is supplied from both Mitchell Line 132/66kV subtransmission substation (STS) and Muswellbrook 132/33kV STS which are supplied via 132kV feeders from TransGrid’s transmission system at Sandy Creek near Muswellbrook; • includes nine Ausgrid zone substations, with four supplied at 66kV and the rest at 33kV; • includes six mining customers; with one supplied at 33kV and the others at 66kV; • includes a 33kV connection point for the Glenbawn Hydro-generator near Rouchel; • includes more than 200km of overhead 33kV & 66kV feeder network; and • consists of a predominantly radial subtransmission system with either limited or non-existent 11kV interconnections.

Figure 5.23: Upper Hunter load area

68

5.23.2 Identified system limitations

Substation/ System limitation Load Impact on Discussion of Potential Credible Solutions Feeder name reduction Transmission for 1 year -Distribution Timing Driver deferral Connection (MVA) Points 1. Muswellbrook Sep-2022 Asset Condition 20.2 MVA None Credible solutions include: 132/33kV (33kV Subtransmission switchgear) 1. Refurbish substation and consolidate Substation assets

2. Build replacement substation

An assessment of non-network options concluded that it is not considered probable that sufficient demand management measures could be feasibly implemented to achieve the required demand reduction to make the project deferral technically and economically viable. 2. Muswellbrook Sep-2022 Asset Condition 12.2 MVA None Credible solutions include: 33/11kV Zone (33kV Substation switchgear) 1. Refurbish substation (and replace assets like for like)

2. Build replacement substation

An assessment of non-network options concluded that it is not considered probable that sufficient demand management measures could be feasibly implemented to achieve the required demand reduction to make the project deferral technically and economically viable.

5.23.3 Identified Substation and Feeder limitations changes from last year’s DAPR - deferred or committed projects Substation/Feeder Name System Limitation Reason for Change Timing Driver Nil.

69

5.24 Upper North Shore load area 5.24.1 Description of Upper North Shore load area The Upper North Shore network area extends from St Ives in the north, west to Turramurra, through Pymble and south to Lindfield. The Pacific Highway and the North Shore and Western railway lines run through the area. The Upper North Shore is a predominantly urban area that includes residential and commercial load. The network in the Upper North Shore area: • is supplied via Kuring-gai subtransmission substation via a radial 33kV underground network. Kuring-gai STS is supplied from TransGrid’s transmission system at Sydney East Bulk Supply Point via two 132kV feeders, 9E1 and 9E2, which predominantly comprise a single double circuit tower line • consists of Pymble, Lindfield, St Ives and Turramurra zone substations supplied from Kuring-gai STS • provides standby supplies to Sydney Trains at 33kV from a busbar at Gordon, teed off a feeder from Kuring- gai STS to Lindfield zone substation, and • supplies both residential and commercial load.

Figure 5.24: Upper North Shore load area 5.24.2 Identified system limitations

Substation/ System limitation Load Impact on Discussion of Potential Credible Solutions Feeder name reduction Transmission for 1 year -Distribution Timing Driver deferral Connection (MVA) Points Nil

70

5.24.3 Identified Substation and Feeder limitations changes from last year’s DAPR - deferred or committed projects Substation/Feeder Name System Limitation Reason for Change Timing Driver Nil

71

5.25 West Lake Macquarie load area 5.25.1 Description of West Lake Macquarie load area The West Lake Macquarie network area lies along the western edge of Lake Macquarie, located south-west of Newcastle. The area extends from Teralba in the north to Wyee in the south, and west to Wakefield, Cooranbong and Mandalong. The area includes Toronto town centre and emerging Morisset regional centre, as well as a mix of urban residential and light industrial areas. Most of the existing urban development is concentrated in the vicinity of the Lake Macquarie shore-line. The surrounding areas contain a mix of industrial, power generation, coal-mining and semi-rural areas. The M1 Pacific Motorway and the main northern rail-line pass through the area. There is opportunity for continued urban development in the area as there are large tracts of vacant land. Cooranbong has been identified in the Department of Planning’s Lower Hunter regional strategy as a priority land release area, with 3,000 new lots expected to be released. The network in the West Lake Macquarie area: • is supplied from both Awaba STS and Eraring STS via 132kV feeders from TransGrid’s transmission system at Killingworth and Vales Point; • includes six zone substations. Three of the six zone substations are supplied from the 33kV network originating at Eraring STS (of which two are dedicated to mining customers). The remaining three zone substations are supplied from the 132kV network; • provides dedicated 11kV supply to underground coal-mining operations at Myuna and Cooranbong via two of the zone substations; • includes three 33kV-connected mining customers (Mandalong, Awaba and Newstan) and a 33kV connection for railway supplies at Awaba; • consists of approximately 105km of predominantly overhead 33kV feeder network; and • serves most of the area’s 11kV supply needs from Avondale ZS, Toronto West ZS, Rathmines ZS and Morisset ZS.

Figure 5.25: West Lake Macquarie load area

72

5.25.2 Identified system limitations

Substation/ System limitation Load Impact on Discussion of Potential Credible Solutions Feeder name reduction Transmission for 1 year -Distribution Timing Driver deferral Connection (MVA) Points

Nil

5.25.3 Identified Substation and Feeder limitations changes from last year’s DAPR - deferred or committed projects Substation/Feeder Name System Limitation Reason for Change Timing Driver Nil

5.26 Primary distribution feeder limitations There were no distribution feeder trunk section ratings exceeded in the preceding year, or expected to be exceeded over the next two years during normal conditions. Distribution feeders are proactively planned to not exceed their ratings by performing regular assessment of the existing feeder network and the proposed network within a 6-year horizon. Additionally, distribution feeders are assessed for new HV connections to ensure there is enough capacity and the new connection does not cause an overload. An augmentation project is initiated if a future overload is forecast to occur. A final assessment of every distribution feeder is performed prior to onset of summer to identify if any feeders will exceed their trunk section rating in its normal configuration. Any feeder expected to exceed its rating will, where possible, have action taken to address the constraint before the summer peak. This occurs because the resultant configuration of the distribution network has a reduced ability to restore supply in the event of a subsequent contingency compared to the planned ability.

73

6 Transmission Load Areas

6.1 Preliminary notes 6.1.1 Changes in dual function asset status The list of Ausgrid’s dual function assets is reviewed periodically and is used as input for preparing Ausgrid’s regulatory reporting, regulatory submission and pricing methodology. For the purpose of the regulatory submission, the list of dual function assets is determined based on the forecast load and the system configuration as at the beginning of the regulatory period. Ausgrid’s dual function network is defined as those assets with a voltage 66kV and above that are owned by Ausgrid and operate in parallel with and provide material support to the TransGrid transmission network. These assets may either operate in parallel with the transmission network during normal system conditions, or can be configured so that they operate in parallel during specific system conditions. An asset is deemed to provide material support to the TransGrid transmission network if: • there is otherwise limited or no system redundancy within TransGrid’s network, or • investment in the transmission system would be required within the regulatory period if that network asset did not exist, or • the feeder provides operational support to the transmission network (e.g. to facilitate maintenance of transmission assets or improve security of supply) and the asset provides an effective parallel with the transmission network via a relatively low impedance path. 6.1.2 Dual function connection points The NER requires a TNSP to set out planning proposals for dual function connection points. Ausgrid’s joint planning with customers, TransGrid and other NSPs may involve the establishment of new connection points. These augmentations are driven by constraints on the distribution network. However, when the augmentation options are considered in the future, the preferred solution may comprise a mix of dual function and distribution network augmentations. Planning of new or augmented connections involves consultation between Ausgrid and the connecting party, the determination of technical requirements, and the completion of connection agreements. New connections can result from joint planning with TransGrid, other DNSPs, or be initiated by generators or customers through the application to connect process. 6.1.3 Inter-Network Impact The Augmentation proposals described in this report are reliability projects and do not have a detrimental material inter-network impact. 6.2 Ausgrid System Total Maximum Demand Forecasts The forecast system total summer maximum demand and the system total winter maximum demand is shown below. Each chart displays the actual and weather corrected actual maximum demand to 2018/19 and the 50% Probability of Exceedance (PoE) forecast maximum demand from 2019/20 in megawatts (MW).

74

Figure 6.1: Summer Global Peak Forecast

Figure 6.2: Winter Global Peak Forecast

6.2.1 Dual function substation demand forecasts Actual and forecast demand data tables (summer and winter) for individual dual function substations are published online and can be accessed on Ausgrid’s website at www.ausgrid.com.au/DTAPR

75

6.3 Transmission load area - Central Coast 6.3.1 Description of Central Coast transmission load area Ausgrid prepares a Central Coast Transmission Load Area plan that covers all Ausgrid 132kV subtransmission assets and dual function assets which operate in parallel and support the main TransGrid transmission network in the Lower Central Coast and Upper Central Coast subtransmission load areas. It forms the basis for TransGrid – Ausgrid joint planning and the sharing of network models and data in the Central Coast area. The Central Coast transmission load area includes all of the Gosford and Wyong local government areas. The area extends south from Lake Macquarie to Broken Bay/Brisbane Water. Most of the development in the area has occurred in a coastal strip to the east of the M1 Pacific Motorway. Development is bound by bushland to the West of the region, and water to the north, south and east. The coastal area of the Lower Central Coast is a popular holiday destination and is a dormitory suburb for Sydney. The area is currently a mix of rural, residential, commercial and industrial land use. The major industries in the area are coal mining and power generation, both of which are in the northern part of the area. The Department of Planning’s Regional Strategy for the Central Coast predicts continued population growth in the area over the next 15 years. 41,500 additional dwellings are expected in the area in the period to 2036, mostly as a result of in-fill development. As the population grows, industries in the region are likely to generate an increase in the number of jobs in wholesaling, retailing, property and business services, tourism, health services, cultural and recreational services and personal services. Although manufacturing jobs will increase in total numbers, the proportion of manufacturing jobs will decline. Development in the area is currently constrained by water supply issues, which prevent development of extensive areas of land west of the Sydney to Newcastle motorway. Greater population growth may be possible if the water supply issues are resolved. Ausgrid’s Central Coast transmission system comprises a network of 132kV lines running from north to south along the length of the Central Coast. The system interconnects TransGrid’s 330/132kV supply points at Vales Point and Munmorah in the north of the area with TransGrid’s centrally located Tuggerah 330/132kV supply point in the south. The network extends south from Tuggerah Bulk Supply Point (BSP) through the lower Central Coast, and connects to the inner metropolitan network at Mt Colah STSS. The Central Coast 132kV network: • provides 132kV supply to four zone substations and three STSs in the area; • supports the TransGrid owned 330/132kV substations at Tuggerah and Munmorah, with Munmorah BSP currently provide only non-firm supply; • operates in parallel with TransGrid’s 330kV system, linking major power stations on the upper Central Coast area with the Sydney metropolitan area. This means that power flows in the 132kV system are influenced by the configuration of the 330kV system; • has no 132kV busbar at Vales Point bulk supply point although there are two 330/132kV transformers • has no 132kV busbar at Munmorah 330/132kV BSP; and • requires substantial work to establish a 132kV busbar if any additional 132kV feeders were to be connected to either Munmorah or Vales Point BSP.

76

Figure 6.3: Identified system limitations in Central Coast 132kV load area

6.3.2 Identified system limitations Substation/ System limitation Load Impact on Discussion of Potential Credible Feeder reduction Transmission- Solutions name for 1 year Distribution Timing Driver deferral Connection (MVA) Points Nil

6.3.3 Identified Feeder limitations changes from last year’s DTAPR - deferred or committed projects Substation/F System Limitation Reason for Change eeder Name Timing Driver

Nil

77

6.3.4 Changes in dual function asset status No changes since the publication of the December 2018 DTAPR 6.3.5 Dual function connection points 6.3.5.1 Augmentation of existing dual function connection points Ausgrid has not identified any constraints to the capacity of existing dual function connection points in the next 10 years. 6.3.5.2 Committed new dual function connection points No committed projects since the publication of the December 2018 DTAPR.

78

6.4 Transmission load area – Lower Hunter 6.4.1 Description of Lower Hunter 132kV transmission load area Ausgrid prepares a Lower Hunter transmission load area plan that covers all Ausgrid 132kV subtransmission assets and dual function assets supplying the Lower Hunter subtransmission load areas. It forms the basis for TransGrid – Ausgrid joint planning and the sharing of network models and data in the Lower Hunter transmission area. The Lower supplied by Ausgrid’s 132kV network extends from the Tomaree Peninsula and Karuah in the north, to Wyee and Swansea in the south. It is bordered on the east by the coastline and extends north- west to Pokolbin and south-west to Mandalong. The Lower Hunter 132kV network provides supply to the Ausgrid network serving Cessnock, Lake Macquarie, Maitland, Newcastle and Port Stephens local government areas; and connection between TransGrid’s 330/132kV bulk supply points in the Lower Hunter and TransGrid feeders supplying Essential Energy’s Lower North network. The Lower Hunter 132kV transmission network provides 132kV supply to the following Ausgrid network areas: • Newcastle Inner City • Newcastle Ports • Newcastle Western Corridor • North-East Lake Macquarie • West Lake Macquarie • Port Stephens • Maitland • Greater Cessnock. Ausgrid has prepared separate area strategy documents for each of these network areas; these documents set out the supply strategies for each area. The Lower Hunter 132kV Transmission network: • comprises around 300km of predominantly overhead 132kV feeders; • is supplied from the TransGrid transmission network Bulk Supply Points (BSP) at Killingworth (named Newcastle BSP), Waratah West and Tomago; • provides 132kV transmission connections from Tomago BSP to TransGrid feeders supplying the Essential Energy network at Taree and Stroud; • includes 132kV network interconnections to the Upper Hunter 132kV network at Rothbury and the Central Coast 132kV network via Morisset and Eraring substations; • provides 132kV supply connections for the OneSteel manufacturing facilities at Mayfield North and the Hydro Aluminium Smelter near Kurri Kurri (which ceased operations in 2013); and • includes nine 132/33kV subtransmission substations and thirteen 132/11kV zone substations.

79

Figure 6.4: Identified system limitations in Lower Hunter transmission area

6.4.2 Identified system limitations Substation/ System limitation Load Impact on Discussion of Potential Credible Feeder reduction Transmission- Solutions name for 1 year Distribution Timing Driver deferral Connection (MVA) Points Nil

6.4.3 Identified System limitations changes from last year’s DTAPR - deferred or committed projects Substation/F System Limitation Reason for Change eeder Name Timing Driver

1. Awaba January 33kV asset Cost Benefit analysis has deferred the need date by over 5 132/33kV STS 2026 condition years.

80

6.4.4 Changes in dual function asset status No changes since the publication of the December 2018 DTAPR 6.4.5 Dual function connection points 6.4.5.1 Augmentation of existing dual function connection points Ausgrid has not identified any constraints to the capacity of existing dual function connection points in the next 10 years. 6.4.5.2 Committed new dual function connection points No committed projects since the publication of the December 2018 DTAPR

81

6.5 Sydney Inner Metropolitan transmission load area 6.5.1 Description of Sydney Inner Metropolitan transmission load area Ausgrid prepares a Sydney Inner Metropolitan Transmission Load Area plan that covers all Ausgrid 132kV subtransmission assets and dual function assets which operate in parallel and support the main TransGrid transmission network in the Sydney Metropolitan subtransmission load areas. It forms the basis for TransGrid – Ausgrid joint planning and the sharing of network models and data for the Sydney Metropolitan transmission area. Joint planning activities with Transgrid are discussed in greater detail in Section 8.1 of this report. The Sydney Inner Metropolitan 132kV transmission network provides 132kV supply to the following Ausgrid network load areas: • Camperdown and Blackwattle Bay load area • Canterbury Bankstown load area • Carlingford load area • Eastern Suburbs load area • Inner West load area • Lower North Shore load area • Manly Warringah load area • North West Sydney load area • Pittwater and Terrey Hills load area • St George load area • Sutherland load area • Sydney CBD load area • Upper North Shore load area.

The Sydney Inner Metropolitan transmission network supplies most of the eastern part of the Sydney metropolitan area. The load area extends from the Pacific Ocean, west to Ryde and Auburn, and is bounded to the south by the Royal National Park and to the north by the Hawkesbury River, but excludes the area east of the Lane Cove River valley. The Inner Metropolitan transmission system is defined as TransGrid’s 330kV cables 41 and 42, and the 330/132kV substations at Beaconsfield, Haymarket, Rookwood Road, Sydney North and Sydney South, together with Ausgrid’s 132kV dual function network that links those supply points. Total demand within the area amounts to more than 4,000MW. Sydney North and Sydney South Bulk Supply Point substations are strongly connected to the main NSW 330kV transmission network, and TransGrid makes firm 132kV capacity available at both locations. Beaconsfield and Haymarket substations are supplied by a single 330kV cable each, and Ausgrid’s interconnected 132kV dual function network provides the necessary connections to provide supply redundancy from these substations. This integrated supply arrangement has been in place since the mid-1970s and has been progressively developed through joint planning between TransGrid and Ausgrid. It represents the least cost solution to meet existing capacity requirements while providing the greatest potential to maximise the utilisation of all network assets. Following the commissioning of Rookwood Road BSP, the Sydney North 132kV network has completely been separated via open points from the remaining 132kV system due to fault level limitations. However, to support the remaining meshed 330kV and 132kV network, there remains the opportunity to transfer some load between the northern and southern 132kV networks via these open points.

82

Figure 6.5: Identified limitations in Sydney Inner Metropolitan transmission load area

83

6.5.2 Identified system limitations

Substation/ System limitation Load Impact on Discussion of Potential Credible Feeder name reduction Transmissio Solutions for 1 year n- Timing Driver deferral Distribution (MVA) Connection Points 1. Feeder 265 – Jan-22 Asset Condition NA None Credible solutions include: Bunnerong STSS to 1. Like-for-like replacement by Maroubra ZS replacing oil-filled cables with XLPE;

2. Like-for-like replacement by replacing oil-filled cables with XLPE, with inclusion of a spare duct to reduce the cost of installing a future feeder between Bunnerong STSS and Kingsford ZS or to another ZS beyond there;

3. Defer replacement or retirement of 132kV feeder via demand management of Maroubra loads.

An assessment of non-network options concluded that it is not considered probable that sufficient demand management measures could be feasibly implemented to achieve the required demand reduction to make the project deferral technically and economically viable.

Note that the assessment was based upon preliminary assumptions for project costs, unserved energy and other benefits with a more detailed assessment to be conducted as part of the Regulatory Investment Test.

2. Feeder 9FF Post Asset Condition NA None Credible solutions include: (ex 91M/3) – 2024 Beaconsfield to 1. Like-for-like replacement by Bunnerong replacing oil-filled portions with XLPE;

2. Retirement of 132kV 9FF;

3. Defer replacement or retirement of 132kV feeder via demand management.

An assessment of non-network options concluded that it is not considered probable that sufficient demand management measures could be feasibly implemented to achieve the required demand reduction to make the project deferral technically and economically viable.

Note that the assessment was based upon preliminary assumptions for project costs, unserved energy and other benefits with a

84

Substation/ System limitation Load Impact on Discussion of Potential Credible Feeder name reduction Transmissio Solutions for 1 year n- Timing Driver deferral Distribution (MVA) Connection Points more detailed assessment to be conducted as part of the Regulatory Investment Test.

3. Feeder 928/3 Sep-23 Asset Condition NA None Credible solutions include: and 929/1 – Lane Cove STS 1. Like-for-like replacement by to Dalley St ZS replacing oil-filled cables with XLPE;

2. Retirement of 928/3 and 929/1 feeder – part of Powering Sydney’s Future (PSF) Strategy, please refer to PSF for more detail;

3. Defer retirement or replacement of feeder 928/3 & 929/1 via demand management.

Assessment for non-network solutions was completed as part of the joint planning process with TransGrid for the Inner Metro Transmission network as part of Powering Sydney Future Strategy.

This process concluded that non-network solutions could form part of the least cost solution. Refer to TransGrid’s website at www..com.au for details on the assessment and next steps.

4. Feeder 260/1 Dec-2024 Asset Condition NA None Credible solutions include: and 261/1 – Beaconsfield 1. Like-for-like replacement; BSP to Zetland 2. Retirement of 260/1 and 261/1 feeder along with retirement of Zetland ZS by transferring 11kV load to neighbouring zone substations;

3. Retirement of 260/1 and 261/1 feeder along with retirement of Zetland ZS by installing a new zone substation looped into a 132kV feeder between Beaconsfield and Campbell Street;

4. Defer retirement or replacement of 260/1 and 261/1 via demand management.

An assessment of non-network options concluded that it is not considered probable that sufficient demand management measures could be feasibly implemented to

85

Substation/ System limitation Load Impact on Discussion of Potential Credible Feeder name reduction Transmissio Solutions for 1 year n- Timing Driver deferral Distribution (MVA) Connection Points achieve the required demand reduction to make the project deferral technically and economically viable.

Note that the assessment was based upon preliminary assumptions for project costs, unserved energy and other benefits with a more detailed assessment to be conducted as part of the Regulatory Investment Test.

5. Feeders 9SA Post Asset Condition NA None Credible solutions include: & 92P – 2024 Beaconsfield 1. Like-for-like replacement by replacing oil-filled portions with BSP to XLPE; Campbell St ZS and Belmore 2. Remediation of the cable section Park ZS Wellington St, Redfern initially and replacement of remaining oil-filled portions at a later date;

3. Defer replacement or retirement of 132kV feeder via demand management.

An assessment of non-network options concluded that it is not considered probable that sufficient demand management measures could be feasibly implemented to achieve the required demand reduction to make the project deferral technically and economically viable.

Note that the assessment was based upon preliminary assumptions for project costs, unserved energy and other benefits with a more detailed assessment to be conducted as part of the Regulatory Investment Test.

6. Feeder 264 – Post Asset Condition NA None Credible solutions include: Beaconsfield 2024 BSP to 1. Like-for-like replacement by Kingsford ZS replacing oil-filled cables with XLPE;

2. Retirement of feeder 264 by transferring Maroubra and Kingsford ZS loads to surrounding zones;

3. Defer replacement or retirement of feeder 264 via demand management of Maroubra and Kingsford zone loads.

An assessment of non-network options concluded that it is not considered probable that sufficient demand management

86

Substation/ System limitation Load Impact on Discussion of Potential Credible Feeder name reduction Transmissio Solutions for 1 year n- Timing Driver deferral Distribution (MVA) Connection Points measures could be feasibly implemented to achieve the required demand reduction to make the project deferral technically and economically viable.

Note that the assessment was based upon preliminary assumptions for project costs, unserved energy and other benefits with a more detailed assessment to be conducted as part of the Regulatory Investment Test.

7. Feeder 202 – Post Asset Condition NA None Credible solutions include: Drummoyne ZS 2024 to Rozelle STS, 1. Like-for-like replacement of feeder and Drummoyne 202 followed by like-for-like ZS 132kV replacement of feeders 203 and switchgear 204;

2. Like-for-like replacement of feeder 202 followed by replacement of feeders 203 and 204 with a single feeder;

3. Like-for-like replacement of feeders 202 and 203 followed by replacement of feeder 204 via Burwood ZS and a new feeder between Burwood and Croydon ZSs;

4. Defer replacement or retirement of 132kV feeder via demand management of Drummoyne loads.

Credible solutions all include replacement of 132kV switchgear at Drummoyne ZS at the same time as 132kV cable connections at this site.

An assessment of non-network options concluded that it is not considered probable that sufficient demand management measures could be feasibly implemented to achieve the required demand reduction to make the project deferral technically and economically viable.

Note that the assessment was based upon preliminary assumptions for project costs, unserved energy and other benefits with a more detailed assessment to be conducted as part of the Regulatory Investment Test.

8. Feeder 203 & Post Asset Condition NA None Credible solutions are investigated in 204 – Mason 2024 combination with the feeder 202 (item 8).

87

Substation/ System limitation Load Impact on Discussion of Potential Credible Feeder name reduction Transmissio Solutions for 1 year n- Timing Driver deferral Distribution (MVA) Connection Points Park STSS to Drummoyne ZS

9. Feeder 91X Post Asset Condition NA Yes Credible solutions include: and 91Y – 2024 Beaconsfield 1. Like-for-like replacement by BSP to Chullora replacing oil-filled cables with STSS via XLPE; Marrickville ZS 2. Retirement of 91X and 91Y feeder – part of Powering Sydney’s Future Strategy (PSF), please refer to PSF for more detail;

3. Defer retirement and replacement of feeder 91X and 91Y via demand management.

Assessment for non-network solutions was completed as part of the joint planning process with TransGrid for the Inner Metro Transmission network and as part of Powering Sydney Future Strategy.

This process concluded that non-network solutions could form part of the least cost solution. Refer to TransGrid’s website at www.transgrid.com.au for details on the assessment and next steps.

10. Feeder 92C Post Asset Condition NA None Credible solutions include: (Formerly 2024 known as: 1. Like-for-like replacement by 91A/2) and 92X replacing oil-filled cables with (Formerly XLPE; 91B/2) – St Peters to 2. Retirement of 92C and 92X feeder Chullora STSS – part of Powering Sydney’s Future Strategy (PSF), please refer to PSF for more detail;

3. Defer retirement or replacement of feeder 92C and 92X via demand management.

Assessment for non-network solutions was completed as part of the joint planning process with TransGrid for the Inner Metro Transmission network and as part of Powering Sydney Future Strategy.

This process concluded that non-network solutions could form part of the least cost solution. Refer to TransGrid’s website at

88

Substation/ System limitation Load Impact on Discussion of Potential Credible Feeder name reduction Transmissio Solutions for 1 year n- Timing Driver deferral Distribution (MVA) Connection Points www.transgrid.com.au for details on the assessment and next steps.

11. Feeder 9S2 Post Asset Condition NA None Credible solutions include: – Beaconsfield 2024 BSP to 1. Like-for-like replacement by Haymarket BSP replacing oil-filled cables with XLPE;

2. Retirement of 9S2 feeder – part of Powering Sydney’s Future Strategy (PSF), please refer to PSF for more detail;

3. Defer retirement and replacement of feeder 9S2 via demand management.

Assessment for non-network solutions was completed as part of the joint planning process with TransGrid for the Inner Metro Transmission network and as part of Powering Sydney Future Strategy.

This process concluded that non-network solutions could form part of the least cost solution. Refer to TransGrid’s website at www.transgrid.com.au for details on the assessment and next steps.

12. Feeder Post Asset Condition NA None Credible solutions include: 90T/1 – 2024 Haymarket BSP 1. Like-for-like replacement by to Green Square replacing oil-filled cables with ZS XLPE;

2. Retirement of 90T/1 feeder – part of Powering Sydney’s Future Strategy (PSF), please refer to PSF for more detail;

3. Defer retirement and replacement of feeder 90T/1 via demand management.

Assessment for non-network solutions was completed as part of the joint planning process with TransGrid for the Inner Metro Transmission network and as part of Powering Sydney Future Strategy.

This process concluded that non-network solutions could form part of the least cost

89

Substation/ System limitation Load Impact on Discussion of Potential Credible Feeder name reduction Transmissio Solutions for 1 year n- Timing Driver deferral Distribution (MVA) Connection Points solution. Refer to TransGrid’s website at www.transgrid.com.au for details on the assessment and next steps.

13. Feeder 270 Post Asset condition NA None Credible solutions include: – Kingsford ZS 2024 to Maroubra ZS 1. Like-for-like replacement by replacing oil-filled cables with XLPE;

2. Replacement using spare duct installed as part of the replacement of 265;

3. Defer replacement or retirement of 132kV feeder via demand management.

An assessment of non-network options concluded that it is not considered probable that sufficient demand management measures could be feasibly implemented to achieve the required demand reduction to make the project deferral technically and economically viable.

Note that the assessment was based upon preliminary assumptions for project costs, unserved energy and other benefits with a more detailed assessment to be conducted as part of the Regulatory Investment Test.

6.5.3 Identified Feeder limitations changes from last year’s DTAPR - deferred or committed projects Substation/Feeder Name System Limitation Reason for Change Timing Driver Feeders 929/2, 92L/1, 928/1 & Sep-23 Asset Condition Now reported in Chapter 5 as they are 92M/2 – Surry Hills STS to distribution assets Dalley St ZS

6.5.4 Changes in dual function asset status No changes since publication of the 2018 DTAPR. 6.5.5 Dual function connection points The following section details dual function projects that are driven by network constraints. 6.5.5.1 Completed new dual function connection points This section describes augmentations that have been completed since the publication of 2018 DTAPR. Alexandria 132/33kV subtransmission substation:

90

The energisation of the high voltage busbar, switchgear, feeder connections and power transformers was completed in October 2017. Commissioning of the first 33kV feeders occurred in November 2018. Subsequent 33kV feeders will be commissioned as separate customer driven projects. Rockdale 132/11kV zone substation: The energisation of the high voltage busbar, switchgear, feeder connections and power transformers was completed in March 2018. Decommissioning of the aging 33kV and 11kV equipment was completed in March 2019. 6.5.5.2 Proposed augmentation of existing dual function connection points Ausgrid has not identified any constraints to the capacity of existing dual function connection points in the next 10 years. 6.5.5.3 Committed new dual function connection points Ausgrid has identified committed new dual function network connection points as tabulated below.

Region Proposal Purpose Timing

Sydney Strathfield South Replace existing 33/11kV Enfield Jun-20 132/11kV Zone ZS (distribution) infrastructure Substation

Sydney Macquarie 132/33kV Supply new customers in Macquarie Jan-22 Subtransmission Park area Substation

6.6 Frequency control and load shedding Emergency control schemes exist to make decisions in different situations so as to prevent the system from experiencing undesired conditions, and in particular to avoid large catastrophic disturbances. As a transmission network service provider, Ausgrid has implemented various control schemes for maintaining system security. Some of emergency control schemes that have been implemented or proposed to be implemented are described as below. • Network switching and splitting to prevent circuits tripping due to thermal overloading as a preventive measure to ensure frequency control within limits; • Under frequency load shedding schemes have been implemented at most zone and subtransmission substations. They will be implemented on existing substations when an opportunity arises during augmentation or replacement works; and • Joint planning between Ausgrid and TransGrid to identify and implement load shedding schemes as per the connection agreement. 6.7 Stability As per NER S5.1.8, the network service provider must ensure and endeavour for stable operation of the national grid in following three stability aspects. • The power system will remain in synchronism. No generators or major augmentations were commissioned during this period that will affect the power system synchronism. Ausgrid cooperates with TransGrid to ensure that the power system remains in synchronism by sharing necessary network data as part of the joint planning process. • Damping of power system oscillations will be adequate. No generators or major augmentations were commissioned during this period that will affect the damping of power system oscillations. Ausgrid cooperates with TransGrid to ensure that the damping of power system oscillations will be adequate by sharing necessary network data as part of the joint planning process. • Voltage stability criteria will be satisfied. It is important to maintain voltage stability by keeping voltage within acceptable levels during normal operating conditions as well as following the loss of a single network element in the power system. The single element includes a transmission line, a cable, a transformer, a reactive support plant or a generator. Ausgrid performs QV analysis regularly to ensure that there is adequate reactive margin at each 132kV bus in Ausgrid’s network. As necessary, Ausgrid considers providing reactive support by way of installing shunt reactors and capacitors in suitable locations in the Ausgrid network. The current QV analysis has indicated that reactive margin is sufficient for all the buses in Ausgrid network. .

91

7 Network investments

7.1 Regulatory investment tests 7.1.1 Completed during the year The following Regulatory Investment Tests for Distribution (RIT-D) have been completed in 2019. Cost estimates are in real dollars, as reported in the documents available in Ausgrid’s website at the following link: https://www.ausgrid.com.au/Industry/Regulation/Network-planning/Regulatory-investment-test-projects.

Expected Date of Estimated Region Constraint Project Name Project RIT-D Cost ($m) Completion completion Addressing increased customer Load Sydney demand requirements in the Rozelle 2021/22 23.2 14/01/2019 Growth area

This project relates to capital works for network expansion. A summary is provided to describe the identified need Ausgrid is seeking to address, outline the credible network options considered and explain why other network options were disregarded, identify the proposed preferred option and explain the reasons for its selection. In addition, the summary includes the corresponding dates in which the different steps of the RIT-D process were completed. 7.1.1.1 Addressing increased customer demand requirements in the Rozelle area The 33kV supply at Rozelle STS is currently dedicated to providing electricity to the Sydney Trains network and there is no 33kV busbar. Electricity distribution to Rozelle and adjacent suburbs is provided at 11kV and there is no other accessible 33kV source in this area. The future combined load is forecast to increase from several major customers in the Rozelle supply area and is anticipated to place significant constraints on the existing Rozelle subtransmission substation (STS) and the associated network. The Rozelle area, along the eastern boundary of Sydney Inner West, will contain significant commercial load arising from major transport infrastructure services and Urban Growth NSW development plans, which includes renewal activities at White Bay, Rozelle Bay and the former Rozelle Rail Yards in the long term. Major customer loads included in the load forecast for this area are the connection requests submitted by Roads and Maritime Services (RMS) for permanent firm electricity supply (N-1 supply) of 33MVA associated with the approved WestConnex Rozelle Interchange (Stage 3B of the WestConnex motorway project) and 32MVA for the proposed Western Harbour Tunnel project. In addition, there are significant load requirements currently foreshadowed at the vicinity of the Rozelle area, such as the redevelopment of the White Bay area, which is part of a broader initiative that is likely to integrate a future metro station (under the proposed project) and harbour activities into urban renewal plans. Given the scale of expected load, augmentation of the existing network is required and Ausgrid investigated options for expanding the subtransmission network supplying the Rozelle area to meet the forecast requirements. Ausgrid’s existing Rozelle STS site was identified as being well-located to service these anticipated loads and has space available to enable its expansion. Redevelopment of this site was shown to be the most efficient solution based on the outcome of a RIT-D, and is the only option available that can be delivered to meet the preferred timing for major customers in the area. The scope of this project includes upgrade of Rozelle STS, which consists of the installation of new indoor 33kV switchgear in an arrangement capable to enable expansion in the future in a new switchroom building, the replacement of the existing 132/33kV 30MVA transformer No.2 with a new 60MVA unit, the construction of new transformer bays to contain the existing and the replacement transformer, trencning work to install 33kV ductlines and cables to enable connection of existing and new customers, and the transfer of the existing 33kV supply of Sydney Trains to the new switchgear and facilitate new 33kV connection. The estimated capital cost of this option is $23.2 million. Other options were considered but found to be not credible. One option involved installation of an additional 132/33kV transformer and additional 33kV bus sections at Alexandria STS. Such an expansion would significantly increase customers’ costs because long distance feeders would be required and, given the cable egress issues at Alexandria STS, could also have significant costs for Ausgrid to facilitate the connection. Furthermore, this option will not avoid the need to augment the network at Rozelle STS to accommodate future 33kV load requirements in the area. Another option considered construction of a new STS in the Rozelle area. This was disregarded because the cost estimate was almost twice the credible option (i.e. Rozelle STS

92

upgrade), without providing additional benefits, and it would not be able to meet the connection date requested by the customers. A Draft Project Assessment Report (DPAR) was published on 26 October 2018. A separate non-network screening notice was also released outlining that for this RIT-D, non-network solutions were unable to form a standalone credible option, or form a significant part of a potential credible option. The DPAR called for submissions from parties by 7 December 2018 and no submissions were received on either the DPAR or the separate non-network screening notice. A Final Project Assessment Report (FPAR) was then published on 14 December 2018, re-presenting the assessment undertaken in the DPAR. The 30- day dispute period ended on 14 January 2019 and no enquiries/disputes were received. Construction work commenced in 2018/19 following completion of the RIT-D assessment and subsequent project approvals. The expected commissioning in 2021/22 will enable electricity supply for tests and trials of the WestConnex Stage 3B, prior to being opened to traffic in 2023.

7.1.2 In progress during the year This section describes the RIT-D assessments commenced in 2019 that remain open for consultation/disputes from market participants. Estimated costs are provided in real dollars, as reported in the documents available in Ausgrid’s website.

Expected Estimated Region Constraint Project Name Project Cost ($m) Completion

New Mascot East 132/11kV ZS and retirement Sydney Asset Condition Dec-2025 38 of Mascot 33/11kV ZS

This project relates to capital works for network replacement or refurbishment. A summary is provided to describe the identified need Ausgrid is seeking to address, outline the credible network options considered and explain why other network options were disregarded, identify the proposed preferred option and explain the reasons for its selection. The summary also includes the corresponding dates in which the initial steps of the RIT-D process have been so far completed.

7.1.2.1 New Mascot East 132/11kV ZS and retirement of Mascot 33/11kV ZS The existing Mascot 33/11kV ZS has asset condition issues associated with its 11kV switchgear and the 33kV feeders supplying the substation. Of the five groups of 11kV switchgear at Mascot ZS, three of them are compound insulated and the remaining two groups are air insulated. A risk analysis has recommended implementing the replacement of the 11kV switchboard at Mascot zone substation from 2020 onwards, as it offers economic benefits that exceed the annualised costs of replacing the asset. Potential credible options to address the issues above are: • Establishment of a new Mascot 132/11kV ZS and associated 132kV connections to replace the existing Mascot ZS and associated 33kV feeders; • Retirement of the existing Mascot ZS and associated 33kV feeders by transferring the 11kV load to neighbouring substations (i.e. Green Square ZS); • Refurbishment of the existing Mascot ZS and replacement of the existing 33kV feeders with new XLPE cables from Bunnerong North STS; and • Refurbishment of the existing Mascot ZS and replacement of the existing 33kV feeders with new XLPE cables from Alexandria STS (currently in construction). All replacement options are currently under review. Given that three high capacity 132kV feeders crossing the Mascot network area have been shorlisted for replacement/retirement in the 2020s, the most cost effective solution is likely to be the new Mascot 132/11kV ZS, provided it is located at a site that best realise the network developments associated with the 132kV feeder replacement projects in the area. The expected completion date for this project is December 2025, noting that a risk mitigation action is currently in progress to address issues with the deteriorating 11kV switchgear at Mascot ZS. A transfer of 11kV load (25MVA) from Mascot to Green Square ZS in 2018 is being delivered to mitigate the identified risk. This 11kV load transfer project was committed in December 2017. A Non-network Options Report was published on 23 September 2019.to engage with non-network proponents and explore demand management options to address the identified network need in relation to Mascot ZS. Submissions responding to the Non-network Options Report are able to be lodged until 23 December 2019. Following this date, a DPAR will be prepared incorporating the latest available information on demand

93

forecasts, VCR estimates, project cost estimates of the network and information about the proposals provided by non-network propoents in reponse to the Non-network Options Report Ausgrid is intending to publish the DPAR in early 2020. Further consultation will then proceed in accordance with the RIT-D process set out in the Rules.

7.1.3 For the forward planning period - Distribution This section describes the network investments for which a RIT-D assessment is expected to be initiated in 2020. Estimated costs are provided in real 18/19 dollars.

Expected Estimated Region Constraint Project Name Project Cost ($m) Completion

Sydney Asset Condition Sydney Airport 33kV switchgear replacement Dec-2021 6.5

Sydney Asset Condition Concord ZS 11kV switchgear replacement Dec-2022 17.5

33kV Feeders 380, 381 & 382 Surry Hills STS- Sydney Asset Condition Mar-2022 6.0 Paddington ZS replacement

Load Growth & Hunter Tarro 11kV switchgear replacement Sep-2023 10.0 Asset Condition

Willoughby STS 33kV switchgear Sydney Asset Condition Sep-2024 34.5 refurbishment

7.1.3.1 Sydney Airport 33kV switchgear replacement Electricity supply to Sydney Airport is provided via five 33kV cables from Bunnerong North STS to Sydney Domestic Airport and International Terminal 33/11kV zone substations. Whilst these cables are aged and there are condition issues associated with pilot cables, the feeders provide sufficient supply redundancy and therefore failures do not lead to loss of supply. However; there are condition issues with the 33kV switchgear assets at the two substations. It has been determined that it would be cost effective to address the 33kV switchgear condition issues. Two credible network options have been identified to address identified issues: • Option 1 – Replace the existing 33kV switchgear with new equipment in situ, which requires a staged approach and therefore involves a longer delivery timeframe; and • Option 2 – Replace the existing 33kV switchgear with new equipment in a new switchroom. Other options considered but not progressed were the retirement of Sydney Airport ZS via 11kV load transfers to surrounding zones, the rearrangement of the 33kV supply to tail-end transformers and retire the 33kV switchgear, or the establishment of a new 132/11kV zone substation. The retirement option is not feasible because there is no spare capacity at the nearby Mascot and Botany zone substations to absorb current and future airport load. The option to rearrange supply and retire the 33kV busbar by connecting the 33kV cables directly to Sydney Airport’s owned 33/11kV transformers was rejected by the customer on the basis that it would reduce reliability of supply and operational flexibility, as well as limiting future growth. In addition, this option has significant construction risks. Finally, the construction of a new Sydney Airport 132/11kV ZS would cost several times more than the combined replacement of both the 33kV and 11kV switchgear, without providing a commensurate increase in benefits and also bring forward replacement investments in subtransmission feeders. The ability of non-network options to assist in addressing the risks has been considered. In this case, it is not appropriate to consider deferral of the network option with traditional demand management initiatives since this network provides a dedicated supply to Sydney Airport. A partial reduction in the load does not help to reduce the risk, only the removal of the entire load offers a viable demand management solution, but this is not feasible. Subject to discussions to align the required work within Sydney Airport redevelopment works, the replacement of the 33kV switchgear is expected to be replaced by December 2021. 7.1.3.2 Concord ZS 11kV switchgear replacement Concord ZS is a 33/11kV zone substation located in the Sydney Inner West area of Ausgrid’s network. It was commissioned in 1955 and is supplied via four 33kV cables from Homebush STS predominantly with XLPE type

94

with small sections of paper insulated cables near the substation site. The paper insulated cables are 62 years of age, but at present there are no known condition issues with these cables. Concord ZS comprises of three groups of double busbar compound insulated switchgear. The 11kV bulk oil circuit breakers (OCB) were replaced with vacuum units. However, the 11kV compound insulated switchboard is beyond its design life and considered obsolete, with an increasing reliability risk that could expose customers in the area to a level that exceeds applicable reliability standards. A failure of the switchboard may cause a fire, which could lead to both loss of supply and severe damage to equipment and buildings, and ultimately result in safety hazards and extended outages. In addition, there are secondary systems such as the 11kV control and protection equipment and the voltage regulation scheme that are about to reach the end of their service life, and the oil containment system at this substation is not adequate to ensure compliance with modern day standards. Two credible network options have been identified to address identified issues: • Option 1 – Concord ZS refurbishment, which could involve temporary load transfers to adjacent zone substations while undertaking staged replacement of 11kV switchgear; and • Option 2 – Construction of a new switchroom building on the existing site and transfer the load from the old to the new switchgear to enable retirement of the aged 11kV switchgear. Other options considered but not progressed were the construction of a new zone substation (either 33/11kV or 132/11kV) on a greenfield site to replace the existing Concord 33/11kV ZS. These options were disregarded because the costs are considerably higher (in excess of $25 million each) than Options 1 and 2, without providing commensurate market benefits. Pending consideration of non-network options, Option 2 is the preferred solution, as it has the highest net market benefits. It involves the construction of a new switchroom building on the existing site to replace the existing 11kV switchgear and associated control and protection, noting that upgrades of the voltage regulation scheme and the oil containment system will be undertaken under corresponding replacement programs. The expected completion date for this project is December 2022.

7.1.3.3 33kV Feeders 380, 381 & 382 Surry Hills STS-Paddington ZS replacement The gas-insulated 33kV feeders 380, 381 and 382 from Surry Hills STS to Paddington ZS are approximately 1.5km. These feeders are aged and in poor condition. Three options were considered to address the condition issues, including retiring Paddington ZS: • Option 1 – Replace the existing 33kV feeders with three new XLPE cables in a new route to allow retirement of the existing aged feeders; • Option 2 – Retire Paddington ZS via 11kV load transfers to surrounding zone substations; and • Option 3 – Retire Paddington ZS via construction of a new zone substation, transfer of load from the existing Paddington ZS to the new zone substation and construction of new 33kV feeders from Surry Hills STS to the new zone substation route to allow retirement of the existing aged feeders. Consideration will be given to assess the feasibility of a staged replacement of the feeders, as it may be possible to install three conduits, replace two cables and maintain one of the existing feeders in service until failure, by which time a third cable can be installed. Pending consideration of non-network options and further assessment of the staged replacement of the feeders, the most practical and economic option is to replace the existing feeders from Surry Hills STS to Paddington ZS via a new route to allow the existing feeders to retire. This project is expected to complete in March 2022. 7.1.3.4 Tarro ZS 11kV switchgear replacement Tarro ZS is a 33/11kV zone substation located in the Maitland area of Ausgrid’s network. It was commissioned in 1960 and is supplied via two 33kV feeders from Beresfield STS. The compound-insulated 11kV switchgear has a deteriorating condition and is considered to be beyond its design life. Furthermore, new industrial developments in the area may lead to forecast demand exceeding the capacity to supply such requirements. Two options were considered to address the identified issues at Tarro ZS: • Option 1 – Tarro ZS refurbishment involving construction of a new switchroom building to house new 11kV switchgear; • Option 2 – Retirement of Tarro ZS via construction of a new zone substation. Other options considered but not progressed were the transfer of 11kV load to nearby existing zone substations followed by either Option 1 or Option 2. The retirement of Tarro ZS by transferring all 11kV load to existing nearby zone susbtations was disregarded because of required extensive 11kV augmentation to maintain

95

adequate voltage levels and higher costs and longer delivery timeframes, without providing commensurate market benefits. Pending confirmation of new load requirements and consideration of non-network options, the preferred option at this stage is the replacement of 11kV switchgear by installing a new switchroom building within the existing site and transfer the 11kV loads from the existing to the new switchgear. The expected completion date for this project is September 2023. 7.1.3.5 Willoughby STS 33kV switchgear refurbishment Willoughby STS is a 132/33kV subtransmission substation located in the Lower North Shore area of Ausgrid’s network. It was commissioned in 1968 and is supplied by four 132kV cables from TransGrid’s Sydney East 330/132kV Bulk Supply Point (BSP) via Ausgrid’s Lindfield 132kV Subtransmission Switching Station (STSS). Most of the 33kV switchgear is considered to be at the end of its service life. In particular, there have been failures in the 33kV wall bushings due to their poor condition, with explosive failure modes attributed to degraded insulation quality. The 33kV isolators and earth switches are also in poor condition, with an operating system that requires manual operation through a series of drive rods and linkages. In addition, the 33kV switchroom building and control room roof is in poor condition. In the event of fire, the building’s physical structure does not allow contemporary levels of segregation within the switch room building. Furthermore, new industrial developments in the area may lead to augment the network in the area to be able to supply such requirements. The substation supplies Chatswood and Gore Hill Zone substations as well as a number of major subtransmission customers including the North West Metro, a number of data centres and the Gore Hill Technology Park. One credible option has been identified to address the identified issues at Willoughby STS. It involves replacement of the 33kV circuit breakers and associated secondary equipment in a new building on a vacant portion of the existing site, and demolition of the existing building. The other option which was considered but not progressed was the like-for-like replacement of all existing 33kV switchgear within the existing building and refurbishment of existing structures at Willoughby STS. This option is not considered feasible due to unavailability of some of the assets such as the dead tank transformer and bus section circuit breakers at the required ratings for procurement from any manufacturer. Pending confirmation of new load requirements and consideration of non-network options, the preferred option at this stage is the replacement of 33kV switchgear by installing a new switchroom building within the existing site and transfer the 33kV feeders from the existing to the new switchgear. The expected completion date for this project is September 2024.

96

7.1.4 Longer term constraints and indicative developments – Distribution The following section provides an overview of network investments in the distribution network that are expected to initiate a RIT-D assessment during 2021 and beyond. The list includes indicative developments that may be initiated within the 2020-25 period. Estimated costs of the proposed network investments are provided in real 18/19 dollars.

Expected Estimated Region Constraint Indicative Development Project Cost ($m) Completion

Sydney Asset Condition Leightonfield ZS 11kV switchgear replacement Sep-2023 7.3

Sydney Asset Condition Riverwood ZS 11kV switchgear replacement Sep-2023 9.9

33kV Feeders 383, 384 & 385 Surry Hills STS- Sydney Asset Condition Jun-2024 5.8 Surry Hills ZS replacement

33kV Feeders 313, 318, 324 & 340 Bunnerong Sydney Asset Condition Dec-2025 8.1 STS-Matraville ZS replacement

Clovelly ZS 11kV switchgear (Group 2) Sydney Asset Condition Sep-2025 13.5 replacement

Sydney Asset Condition Pymble ZS 11kV switchgear replacement Sep-2026 11.9

Darlinghurst ZS 11kV load transfers and Sydney Asset Condition Sep-2026 12.4 substation retirement

Sydney Asset Condition Blakehurst 33kV ZS decommissioning Sep-2026 19.4

Managing asset risks in the West Lake Hunter Asset Condition Sep-2026 7.0 Macquarie network area

Sydney Asset Condition Milperra ZS 11kV switchgear replacement Sep-2027 9.0

Lidcombe ZS 11kV switchgear (Group 1) and Sydney Asset Condition Sep-2028 14.8 associated 33kV feeder replacement

Botany ZS 11kV switchgear (Group 1) Sydney Asset Condition Sep-2028 5.9 replacement

132kV Feeder 202 Rozelle STS – Drummoyne Sydney Asset Condition Sep-2028 15.7 ZS replacement

132kV Feeders 203 & 204 Mason Park STSS Sydney Asset Condition Sep-2028 31.8 – Drummoyne ZS replacement

Drummoyne ZS 132kV switchgear Sydney Asset Condition Sep-2028 25.4 replacement

132kV Feeders 923/2 & 924/2 Mason Park Sydney Asset Condition Sep-2028 9.4 STSS – Burwood ZS replacement

7.1.4.1 Leightonfield ZS 11kV switchgear replacement The 11kV compound switchgear at Leightonfield ZS was approaching the end of its service life and was prioritised for replacement. The 11kV circuit breakers panel 1-4 are already decommissioned and loads have been distributed to the remaining panels in the same zone. The probability based cost benefit analysis indicates the optimal timing to replace the remaining panels on a new site adjacent to existing Leightonfield ZS is September 2023. 7.1.4.2 Riverwood ZS 11kV switchgear replacement The 11kV switchgear at this zone substation is compound insulated and is in poor condition. The probability based cost benefit analysis indicates the optimal timing to replace the switchgear is September 2023.

97

7.1.4.3 33kV Feeders 383, 384 & 385 Surry Hills STS-Surry Hills ZS replacement The 33kV feeders 383, 384 and 385 from Surry Hills STS to Surry Hills ZS are gas insulated cables and are approximately 1km long. These feeders are expected to be replaced by June 2024 with modern equivalent technology (XLPE cables), due to the deteriorating condition of the cables. 7.1.4.4 33kV feeders 313, 318, 324 & 340 Bunnerong North STS-Matraville ZS replacement The 33kV feeders from Bunnerong North STS to Matraville ZS are a combination of paper insulated and gas pressure cable technologies, and have reached the end of their service lives. Each feeder has a total length of approximately 1.4 km, from which approximately 0.95km and gas pressure cables and the remaining 0.45km are paper insulated.These feeders are aged and in poor condition. Pending consideration of non-network options, the most practical and economic option is to replace the existing feeders from Surry Hills STS to Paddington ZS via a new route to allow the existing feeders to retire. This project is expected to complete in December 2025. 7.1.4.5 Clovelly ZS 11kV switchgear (Group 2) replacement Group 2 of the 11kV switchgear at Clovelly ZS consists of an air-insulated switchboard with vacuum cricuit breakers. It was commissioned in 1970 and due to its deteriorating condition and age of the technology, Group 2 of the 11kV switchgear at Clovelly zone substation is recommended to be replaced by September 2025. Pending consideration of non-network options, the preferred option is to replace the switchgear in space available on the existing switchroom building. 7.1.4.6 Pymble ZS 11kV switchgear replacement The 11kV air insulated switchgear at Pymble ZS has reached the end of its service life and is in poor condition. The probability based cost benefit analysis indicates the optimal timing to replace the air insulated switchgear is September 2026. 7.1.4.7 Darlinghurst ZS 11kV load transfers and substation retirement Darlinghurst ZS is a 33/11kV zone substation located in the Eastern Suburbs area of Ausgrid’s network, outside the eastern boundary of the Sydney CBD. It was commissioned in 1966 and is supplied by four 33kV cables from Surry Hills STS. Several asset condition issues have been identified at Darlinghurst ZS, namely the deteriorating condition of the 11kV switchgear, which comprises one group of compound insulated busbars (switchboard) with oil circuit breakers, and a second group of air insulated busbars with oil circuit breakers; and the deteriorating condition of the 33kV gas pressure cables supplying the substation (feeders 386, 387, 388 and 389), which have experienced failures and increased gas leakage rates. Replacement of the 11kV switchgear and 33kV feeders was dismissed from a technical perspective due to the congested nature of the Darlinghurst area and the limited size of the existing site. Similarly, the construction of a new Darlinghurst 33/11kV ZS on a new site to replace the existing Darlinghurst ZS was dismissed since retirement options were significantly lower cost and achieved similar benefits. As non-network options cannot cost-effectively address the risk of unserved energy, the preferred solution is to transfer half of 11kV loads to Campbell St and Surry Hills to enable retirement of the 11kV compound insulated switchgear, 33kV gas pressure feeders 388 and 389 and associated transformers. The probability based cost benefit analysis indicates the optimal timing for completion of works is by September 2026. 7.1.4.8 Blakehurst 33kV ZS decommissioning The 11kV switchgear at this zone substation is compound insulated and is in poor condition. In addition, the 33kV bulk oil circuit breakers and 33kV Essantee isolator switches are estimated to have reached the end of their serviceable life and some parts of the 33kV busbar do not comply with current clearance requirements. Furthermore, the 33kV feeders between Peakhurst Subtransmission Substation (STS) and Blakehurst ZS are gas pressure cables and approaching the end of their service life. Therefore, it is proposed to decomission Blakehurst ZS by transferring load from Blakehurst ZS load to surrounding zone substations. The cost benefit analysis indicates the optimal timing for these works is by September 2026. 7.1.4.9 Managing asset risks in the West Lake Macquarie network area Awaba 132/33kV STS is located in the West Lake Macquarie area of Ausgrid’s netowrk. It was commissioned in 1960 and much of the equipment is still original. Awaba STS is an entirely outdoor substation which, after the commissioning of Toronto West 132/11kV ZS, supplies industrial load. The supplied load consists of several major customers (mine developments) and a railway supply. The deteriorating condition of multiple assets (132kV transformers & switchgear, 33kV switchgear, control & protection, instrument transformers and the building) indicates that retirement or replacement is required. All original 33kV circuit breakers (14x33kV outdoor bulk-oil circuit breakers) and associated isolators and earth switches (28 in total) have surpassed their service life and are considered to be in poor condition. In addition, the 33kV busbar is below minimum height requirements, which is a safety hazard. The switch room and

98

control building are serviceable but may have asbestos containing materials in fire doors, compressed tar switchboards, amenity walls and ceiling and are being managed accordingly. Pending consideration of non-network options, the conversion of Awaba STS into a 33kV switching station is a preferred option. The expection completion date of this project is September 2026. The project involves the retirement of the 33kV switchyard and redundant feeders at Awaba STS and converting the site to a 33kV subtransmission switching station, which will maintain dedicated 33kV connections to the major customers in the area (i.e. two mine developments and the State Rail Authority). 7.1.4.10 Milperra ZS 11kV switchgear replacement The 11kV switchgear at this zone substation is compound insulated and is in poor condition. The probability based cost benefit analysis indicates the optimal timing to replace the air insulated switchgear is September 2027. 7.1.4.11 Lidcombe ZS 11kV switchgear (Group 1) and associated 33kV feeder replacement There are two groups of compound insulated 11kV switchgear at Lidcombe ZS. Works to replace switchgear Group 2 are currently committed, while oil circuit breakers originally installed in switchgear Group 1 were replaced with vacuum trucks in recent years. The probability based cost benefit analysis indicates the optimal timing to replace the switchgear Group 1 is September 2028. 7.1.4.12 Botany ZS 11kV switchgear (Group 1) replacement The compound-filled 11kV switchgear at Botany ZS present a high fire risk, because the bituminous compound can act as a fuel source in the event of simple outages. Considering its deteriorating condition and age, the 11kV switchgear replacement at Botany ZS was staged into two stages. The first stage of replacing Group 2 and Group 3 11kV switchgear is committed and is expected to complete in 2019. As the second stage of the replacement, Group 1 switchgear are planned to be replaced by September 2028. 7.1.4.13 132kV feeder 202 Rozelle STS – Drummoyne ZS replacement The 132kV cable 202 between Rozelle STS and Drummoyne ZS is approximately 3.8km long and is fluid- filled, with a submarine crosing of Iron Cove. Commissioned in 1977, the feeder 202 poses a risk of deteriorating reliability, and crosses Parramatta River, which is an environmentally sensitive area. It is recommended to replace feeder 202 with modern equivalent technology (i.e. a single XLPE cable) by September 2028. 7.1.4.14 132kV feeders 203 & 204 Mason Park STSS – Drummoyne ZS replacement The existing 132kV feeders 203 and 204 from Mason Park STSS to Drummoyne ZS are single core 1000mm2 oil-filled cables. Commissioned in 1980, these feeders have experienced moderate iol leaks over the past 15 years. Testing indicates that there may be problems with the outer serving of the cables which could lead to oil leaks in the future. A number of options were considered to address this issue and the most likely option is to replace feeders 203 and 204 by September 2028. 7.1.4.15 Drummoyne ZS 132kV switchgear replacement The gas-insulated 132kV switchgear at Drummoyne ZS was commissioned in 1979 and is in deteriorating condition. The most economic option is to construct a new 132kV switchroom on the site adjacent to the existing Drummoyne ZS and install new 132kV switchgear. Then the transformers and feeders can be transferred to the new 132kV switchgear to allow retirement of the existing gas insulated switchgear. To enable construction efficiences, the replacement of the switchgear is recommended to be aligned with the replacement of feeders 202, 203 and 204. It is recommended to complete these works by September 2028, however proposed developments in the area may make other options viable. 7.1.4.16 132kV feeders 923/2 & 924/2 Mason Park STSS – Burwood ZS replacement The 132kV feeders 923/2 and 924/2 supply Burwood ZS from Mason Park STSS. Commissioned in 1976, these feeders are oil filled cables with approximately 1.6km in length. 923/2 has experienced oil leaks over the past 15 years. With their age and deteriorating condition, it is recommended to replace them like for like with a modern XLPE cable on a similar route. This replacement project is expected to be completed by September 2028.

7.1.5 For the forward planning period – Dual Function This section describes the augmentation and replacement driven projects for which a RIT-T assessment is expected to be initiated in 2020. Estimated costs are provided in real 18/19 dollars.

99

Expected Estimated Region Constraint Project Name Project Cost ($m) Completion 132kV Feeder 265 Bunnerong STSS – Sydney Asset Condition Jan-2022 14.5 Maroubra ZS replacement

Load Growth & New Waterloo 132/11kV ZS and retirement of Sydney Asset Condition Zetland 132/11kV ZS Dec-2024 39.6 132kV Feeders 260/1 and 261/1 Sydney Asset Condition decommissioning

7.1.5.1 Replacement of 132kV Feeder 265 between Bunnerong STSS and Maroubra ZS Feeder 265 is an oil-filled underground cable, approximately 3.8km long, installed in 1979. An updated risk assesment recommends the replacement of this feeder in the period 2019-24, due to a deteriorating condition that increases the risk that a substantial portion of Maroubra could experience an extended blackout. Replacement options are still under consideration, however the most likely option is to replace the oil-filled cable sections with XLPE cable. The expected completion date for this project is January 2022. 7.1.5.2 New Waterloo 132/11kV ZS and retirement of Zetland 132/11kV ZS The project is to establish a new Zone Substation in the vicinity of Alexandria North in the Eastern Suburbs area of Ausgrid’s network. The need is expected to arise because of growth concentrated in the “Central to Eveleigh Precinct” area that is being managed by Urban Growth NSW Government agency. Area growth is also driven by the development of a Metro Station at Waterloo as part of a new rail corridor, and the establishment of new Information Technology based facilities. The new zone substation, which could be named Waterloo or Alexandria North, would also assist in achieving the retirement of the ageing Zetland ZS and its oil-filled cables originated from Beaconsfield BSP (132kV feeders 260/1 and 261/1). Allowing for new loads being connected to Green Square in the short term, the need for this substation is expected to arise by December 2024. The proposed location will be close to the route of a 132kV cable that will replace the oil-filled cable 9SA. Thus there will be minimal cable cost if the new substation is connected to this cable. Other potential credible options could include 11kV connections to neighbouring zone substations such as Green Square ZS. Consideration will be given to the possibility of installing 33kV connections or implementation of non-network options to defer investment in a new substation to align with the retirement of Zetland ZS.

7.1.6 Longer term constraints and indicative developments – Dual Function The following section provides an overview of dual function network assets that are expected to initiate a RIT-T assessment during 2021 and beyond. The list includes indicative developments that may be initiated within the next 10 years. Estimated costs are provided in real 18/19 dollars.

Expected Estimated Region Constraint Indicative Development Project Cost ($m) Completion

132kV Feeder 264 Beaconsfield BSP – Sydney Asset Condition Mar-2026 25.7 Kingsford ZS replacement

132kV Feeder 91M/3 Beaconsfield BSP – Sydney Asset Condition Sep-2027 16.1 Bunnerong STSS oil section replacement

132kV Feeders 91A/1 & 91B/1 Beaconsfield Sydney Asset Condition Sep-2027 12.9 BSP – St Peters ZS replacement

132kV Feeders 9SA & 92P Beaconsfield BSP Sydney Asset Condition Sep-2028 18.8 to Campbell St ZS/Belmore Park ZS

Sydney Asset Condition St Peters ZS 11kV switchgear replacement Dec-2028 26.5

100

7.1.6.1 Replacement of 132kV Feeder 264 between Beaconsfield BSP and Kingsford ZS Feeder 264 is an oil-filled underground cable, approximately 5.5km long, which was installed in 1977. The oil- filled cable have been identified as approaching the end of its service life. A risk assessment has determined the need to replace this cable by March 2026. Replacement options are still under consideration, however the most likely option is to replace the oil-filled cable sections with XLPE cable. 7.1.6.2 132kV Feeder 91M/3 Beaconsfield BSP – Bunnerong STSS (oil section) replacement Feeder 91M/3 is approximately 9.3km long and was installed in 1973. A section of this feeder is currently being replaced, between Bunnerong STSS and Mill Pond Rd, Botany. The remaining section, from Mill Pond Rd to Beaconsfield BSP, when considered in isolation, is recommended for replacement in the period 2024-29. Taking into account, synergies between this feeder replacement and other projects suggest that it is cost effective to bring forward the replacement of feeder 91M/3 remaining section to coordinate with the project to replace the existing Mascot ZS. Replacement options are still under consideration, however the most likely option is to replace the oil-filled cable section by September 2027. 7.1.6.3 Replacement of 132kV Feeders 91A/1 & 91B/1 between Beaconsfield BSP and St Peters ZS Feeders 91A/1 and 91B/1 consists of oil-filled underground cables commissioned in 1968, with an approximate length of 1.5km. An updated risk assesment recommends the replacement of this feeder in the period 2024-29, due to age and condition issues. Replacement options are still under consideration, however the most likely option is to replace the oil-filled cable sections with XLPE cable. The expected completion date for this project is September 2027. 7.1.6.4 132kV Feeders 9SA & 92P Beaconsfield BSP – Belmore Park/Campbell St ZS replacement 132kV feeder 9SA from Beaconsfield BSP to Campbell St ZS, and 132kV feeder 92P from Beaconsfield BSP to Belmore Park ZS are oil-filled underground cables commissioned in the 1970s. These cables are approximately 5.7km and 5.5km long respectively. The risk assesment recommends the replacement of these feeders in the period 2024-29, taking into account the history of oil leaks, failures and increased rates of corrective works. As part of the State Government’s WestConnex motorway project, Roads and Maritime Services (RMS) is widening Euston Road between Campbell Road and Maddox Street, Alexandria. WestConnex is also replacing a 1.6km section of feeders 9SA and 92P. As a result, the cost of replacing the SCFF feeders has been significantly reduced, and the resulting cost benefit analysis update has recommended advancing the replacement of remaining sections to the 2020-24 regulatory period. Ausgrid initiated a partial replacement of an additional 1.0km section as a result of the relocation triggered by the WestConnex project. This decision was taken to achieve construction efficiencies and avoid significant additional costs of replacing the cables in roads with increased traffic flows. These early works were committed for completion in 2018/19. Replacement of the remaining 3.0km sections are still under consideration, however the most likely option is to replace the remaining oil-filled cable sections with XLPE cables. The expected completion date for this project is September 2028. 7.1.6.5 Replacement of 11kV Switchgear St Peters ZS The existing St Peters 132/11kV ZS has asset condition issues associated with its 11kV switchgear. An updated risk assesment recommends the replacement of the air insulated 11kV switchgear by December 2028, due to age and condition issues. Potential credible options to address the issues above are the replacement of the existing 11kV switchgear at St Peters ZS with new switchgear in a new switchroon on a block of land adjacent to the existing substation, the retirement of St Peters ZS via 11kV load transfers to surrounding substations (i.e. Marrickville ZS and Zetland ZS) provided there is sufficient capacity to accommodate this load, and the establishment of a new St Peters 132/11kV ZS and associated 132kV connections in a nearby site to replace the existing St Peters ZS. All these options are still under consideration, however the most likely network option is to replace the 11kV switchgear at St Peters ZS in a new switchroom building on an adjoining site. 7.1.6.6 Replacement of 132kV Feeder 9SE between Beaconsfield BSP and Green Square ZS Feeder 9SE is an oil-filled underground cable, approximately 1.0km long, installed in 1988. An updated risk assesment recommends the replacement of this feeder in the period 2024-29, due to age and condition issues. Replacement options are still under consideration, however the most likely option is to replace the oil- filled cable sections with XLPE cable. The expected completion date for this project is 2029.

101

7.1.7 Not proceeding – Distribution The table below shows the projects associated with distribution assets identified in the preceding DTAPR which are now not expected to proceed to the RIT-D assessment process in the next five years.

Region Project Previous Reason for cancellation/deferral or RIT-D Need Date not proceeding

Addressing reliability RIT-D not required, as the cost of the only Hunter requirements in the 2020/21 credible option to address identified need is Stockton load area less than $6 million. Managing asset risks in the RIT-D not required, as the cost of the only Hunter Muswellbrook network 2020/21 credible option to address identified need is area less than $6 million. An updated risk-based cost-benefit analysis New 132kV feeder Clovelly indicates that the benefits of reduced unserved ZS – Maroubra ZS and Sydney Sep-2027 energy do not exceed the annualised cost of retire Feeder 262 Double replacing the 132kV cable within the planning Bay – Clovelly horizon. An updated risk-based cost-benefit analysis indicates that the benefits of reduced unserved Miranda ZS 11kV Sydney Sep-2022 energy do not exceed the annualised cost of switchgear replacement replacing the 11kV switchgear within the planning horizon. An updated risk-based cost-benefit analysis indicates that the benefits of reduced unserved Belrose ZS 11kV Sydney Sep-2022 energy do not exceed the annualised cost of switchgear replacement replacing the 11kV switchgear within the planning horizon.

Two of the network investments listed in the table above are exempted from the obligation to publish a RIT-D because the cost of credible network options is less than $6 million. Further details of these two cases are provided below. 7.1.7.1 Stockton ZS 11kV switchgear replacement Stockton ZS is a 33/11kV zone substation located in the Port Stephens area of Ausgrid’s network. It was commissioned in 1968 and is supplied by two 33kV overhead lines from Williamstown ZS, with tail-ended transformers. The substation is located on the periphery of the Port Stephens area and supplies the Stockton peninsula. Stockton ZS comprises of compound insulated 11kV switchboard with oil circuit breakers. The compound insulated switchgear in other sites has exhibited failures ranging from single equipment failures to multiple equipment failures impacting the operation of the entire substation. The 11kV switchgear is considered to be beyond its design life. These assets are likely to become less reliable, which could expose customers in the Stockton peninsula to a supply risk that exceeds allowable levels under the applicable reliability standards One credible network options has been identified to address asset condition issues. It involves the replacement of the 11kV switchgear at Stockton ZS, by installing a new switchroom. Other options were considered in the assessment but not progressed. The replacement of the 11kV switchgear in situ involved increased construction risks and longer delivery timeframes relative to the new switchroom. The retirement of Stockton ZS via 11kV load transfers is considered not feasible as the only adjacent substation is Williamstown ZS which is over 10km away. Retiring the substation would therefore require extensive 11kV augmentation. Another option considered was the construction of a new 33/11kV Zone Substation on a greenfield site to replace the existing Stockton 33/11kV ZS, but it was disregarded because it cost almost three time more than the replacement of the 11kV switchgear in situ and would not provide any additional benefits. The replacement of the 11kV switchgear with a new switchroom is therefore the preferred option. It involves the installation of a new Mobile Equipment Room to accommodate the new 11kV switchboard comprising two sections of single bus switchgear and 11kV circuit breakers. The estimated capital cost of this option is $5.4 million.

102

It is expected that construction work will commence in 2019/20 pending completion of the project approvals, with expected commissioning in 2021/22. The decommissioning and removal of redundant equipment is also expected to be completed in 2021/22. 7.1.7.2 Managing asset risks in the Upper Hunter network area Muswellbrook 132/33kV STS is located in the Upper Hunter area and provides 33kV supply to Muswellbrook ZS and a mine customer, as well as a normally open back-up supply to Rouchel ZS. It was commissioned in 1964, utilising the switchyard of the old Muswellbrook Power Station that operated adjacent to the site. Condition issues have been identified in the 33kV outdoor switchgear of both Muswellbrook STS and Muswellbrook ZS, and secondary systems at Muswellbrook STS. In particular, the 33kV Essantee isolators have additional safety risks to personnel involved in switching operations. Furthermore, the 33kV oil filled circuit breakers of this age and type have a history of failures derived from degraded insulation quality. There are extensive condition issues with the existing control and protection, earthing and oil containment systems. There is also an opportunity to retire/reconfigure parts of the 33kV network after recent projects in the area have resulted in disused 33kV feeders and equipment. One credible network option has been identified to address asset condition issues at Muswellbrook STS. It involves refurbishing Muswellbrook STS, to retire the 33kV switchgear that is redundant to the network and replace the minimum equipment to maintain 33kV supply in the area, and rearrangement of the Muswellbrook STS 33kV network. Other options were considered but not progressed because they were not feasible. These included the retirement of Muswellbrook STS and reconfiguration of the 33kV network in the area; the retirement of both Muswellbrook STS and Muswellbrook ZS and transferral of 11kV load to Mitchell Line ZS and Aberdeen ZS, including rearrangement of the 33kV network to provide supply to mine operations and maintain back up supply to Moonan ZS and Rouchel ZS; and the establishment of a new Muswellbrook 132/33kV STS. These options were disregarded because the costs were considerably higher than Options 1 and 2, noting that if both Muswellbrook STS and Muswellbrook ZS are retired, the supply capacity will be considerable reduced in the area. The connection of possible future renewable generation will pose increased technical and economic issues without Muswellbrook STS. Furthermore, the reconfiguration of the 132kV network post retirement of Muswellbrook STS will require extensive protection upgrades to achieve compliance with the National Electricity Rules. Refurbishment of Muswellbrook STS and rearrangement of the Muswellbrook STS 33kV network is the preferred option. The expected completion date for this project is September 2022. The works will involve the retirement of a transformer and decommissioning existing 33kV switchgear and all redundant 33kV equipment at Muswellbrook STS, as well as the rearrangement of the 33kV network by dismantling redundant connections and installing new links required. The estimated capital cost of this option is $5.8 million. 7.1.8 Not proceeding – Dual Function The following dual function asset augmentation or replacement projects described in the preceding DTAPR have either been deferred beyond the ten year forward planning period or cancelled.

Region Project Previous Reason for cancellation/deferral Need Date

An updated risk-based cost-benefit analysis 132kV Feeder 9SE indicates that the benefits of reduced unserved Sydney Beaconsfield BSP – Green Sep-2029 energy do not exceed the annualised cost of Square ZS replacement replacing the 132kV cable within the planning horizon. An updated risk-based cost-benefit analysis 132kV Feeder 270 indicates that the benefits of reduced unserved Sydney Kingsford ZS – Maroubra Sep-2027 energy do not exceed the annualised cost of ZS replacement replacing the 132kV cable within the planning horizon.

103

7.2 Completed or cancelled investments For the purposes of this document, a project is considered to be complete when it is commissioned and in service (practically complete). 7.2.1 Refurbishment, replacement or augmentations – Distribution The following distribution refurbishment or replacement projects described in DTAPR 2018 have either been completed or cancelled during the preceding year.

Completed or Cancelled Refurbishment or Load Area Reason / comments Replacement Investment - Distribution

Canterbury – Punchbowl ZS11kV switchgear replacement Completed Bankstown Canterbury – Bass Hill ZS 11kV switchgear replacement Completed Bankstown

Eastern Suburbs Botany ZS 11kV switchgear Group 2 & 3 replacement Completed

Inner West New Croydon 132/11kV ZS Completed

Greater Cessnock New Cessnock 33/11kV ZS & retire Cessnock ZS Completed

New Tighes Hill 33/11kV ZS and decommissioning Newcastle Inner City Completed Carrington ZS Merewether to Kotara 33kV Feeders 773 & 775 Newcastle Inner City Completed Replacement

Newcastle Inner City Ex-City Main ZS retaining wall refurbishment Completed

Pittwater & Terrey Mona Vale ZS 11kV switchgear replacement Completed Hills

Singleton Newdell ZS 11kV switchgear replacement Completed

Singleton Branxton ZS 11kV switchgear replacement Completed

Decommission 33/11kV Arncliffe ZS and 11kV load St George Completed transfers

Sutherland Refurbish 132/33kV Port Hacking STS Completed

7.2.2 Refurbishment, replacement or augmentations – Dual Function The following dual function refurbishment or replacement projects described in DTAPR 2018 have either been completed or cancelled during the preceding year.

Completed or Cancelled Refurbishment or Load Area Reason / comments Replacement Investment - Distribution

St George New Rockdale 132/11kV ZS Completed

Kurnell STS 33kV network rearrangement and 33kV Sutherland Completed Busbar Retirement Lane Cove STS to Top Ryde 132kV feeder 92G, and Sydney Inner Metro Lane Cove STS to Meadowbank ZS 132kV feeder 92J Completed replacement.

Sydney Inner Metro New 132kV Feeder 90Y Beaconsfield BSP-Belmore Park Completed ZS and decommissioning 132kV Feeders 92L/3 & 92M/1

104

Completed or Cancelled Refurbishment or Load Area Reason / comments Replacement Investment - Distribution

Sydney Inner Metro Installation of New Wholesale Metering Points Completed

Sydney Inner Metro Peakhurst STS to Bunnerong STS and Beaconsfield Completed BSP 132kV Feeders 91L & 91M Replacement

105

7.3 Committed investments Ausgrid has identified all committed refurbishment or replacement investments with an estimated capital cost of $2 million or more. Capital cost estimates are shown in nominal dollars and excludes contingency costs. 7.3.1 Refurbishment, replacement or augmentations – Distribution

Expected Estimated Committed Refurbishment or Replacement Load Area Project Cost Investment – Distribution Completion (nominal $m)

Camperdown and Convert Blackwattle Bay load from 5kV to 11kV and Nov-20 16.5 Blackwattle Bay load transfer and retire 33/5kV Blackwattle Bay ZS Canterbury - Bankstown STS 33kV switchgear replacement Oct-19 17.6 Bankstown 11kV Load Transfer to enable retirement of Inner West Aug-20 7.5 Flemington ZS 11kV switchgear Group 1 Canterbury - New 132/11kV Greenacre ZS & decommission Dec-19 29.7 Bankstown Greenacre Park ZS Canterbury - Sydney South to Revesby 132kV feeders Jun-20 17.1 Bankstown replacement New 132kV Feeder Kingsford to Clovelly and Eastern Suburbs Mar-21 16.6 decommissioning of Zetland-Clovelly 132kV feeders Matraville ZS 11kV switchgear Groups 1, 2 and 4 Eastern Suburbs Jun-20 14.2 replacement

Eastern Suburbs Surry Hills ZS 11kV switchgear replacement Sep-20 18.1

Eastern Suburbs Decommission Darlinghurst 33/11kV ZS – Stage 1 Oct-21

Inner West Leichhardt ZS 132kV conversion. Jun-20 25.1

Lidcombe 33/11kV ZS 11kV switchgear Group 2 Inner West Jul-20 6.7 replacement

Inner West Decommission 132/33kV Strathfield STS Feb-20 9.3

New Summer Hill 33/11kV ZS and associated 33kV Inner West Jun-20 40.9 feeders and decommission Dulwich Hill 33/11kV ZS

Inner West Rozelle STS new 33kV switchgear Oct-22

Replace 33kV feeders – Homebush STS to Inner West Sep-20 Lidcombe ZS and Auburn ZS

Lower North Shore Willoughby to Mosman 132kV Feeders Replacement Nov-20 35.4

Newcastle Ports Waratah 132/33kV STS refurbishment Jun-20 17.0

St George Peakhurst STS 33kV switchgear replacement Mar-22

11kV Load Transfers from Dalley St ZS to City North Sydney CBD Jan-21 18.9 ZS

Upper North Shore Kuringai STS 33kV switchgear replacement Nov-19 32.2

106

7.3.1.1 Convert Blackwattle Bay load from 5kV to 11kV and load transfers and retire Blackwattle Bay ZS Key project milestones: • Project initiated in November 2015. • Project expenditure authorised by Ausgrid Board in June 2017. • Project completion is expected by November 2020. Options Analysis Three network options were considered to resolve the above issues: Option 1 - Commission the 4th transformer at Camperdown zone substation and transfer Blackwattle Bay load to Camperdown zone substation This option involves: • 2016/17 – Surry Hills to Camperdown zone substation 11kV load transfer to facilitate 11kV switchgear replacement at Surry Hills zone substation; • 2017 – Commission the 4th transformer and associated 33kV feeder and install 11kV switchgear at Camperdown zone substation; • 2018 – Convert Blackwattle Bay zone substation load from 5kV to 11kV and transfer load to Camperdown zone substation; and • Three minor 11kV load transfer projects post 2028. The total Net Present Cost (NPC) of this option is $19.0 million. Option 2 - Transfer Blackwattle Bay load to Camperdown and Darling Harbour zone substations This option involves: • 2016/17 – Surry Hills to Campbell St zone substation 11kV load transfer to facilitate 11kV switchgear replacement at Surry Hills zone substation; • 2018 – Convert Blackwattle Bay zone substation load from 5kV to 11kV and transfer to Camperdown and Darling Harbour zone substations; • 2022 - Commission the 4th transformer and associated 33kV feeder and install 11kV switchgear at Camperdown zone substation; • 2022 – 10MVA 11kV load transfer Darling Harbour to Camperdown zone substation; and • Three minor 11kV load transfer projects post 2027. The total NPC of this option is $20.2 million. Option 3 – Transfer Camperdown load to Leichhardt zone substation and transfer Blackwattle Bay load to Camperdown and Darling Harbour zone substations This option involves: • 2016/17 – Surry Hills to Camperdown zone substation 11kV load transfer to facilitate 11kV switchgear replacement at Surry Hills zone substation; • 2018 – 8MVA load transfer from Camperdown to Leichhardt zone substation via switching; • 2018 – Convert Blackwattle Bay zone substation load from 5kV to 11kV and transfer load to Camperdown and Darling Harbour zone substations; • 2020 – 4MVA 11kV load transfer from Darling Harbour to Camperdown zone substation; • 2023 - Commission the 4th transformer and associated 33kV feeder and install 11kV switchgear at Camperdown zone substation; • 2023 – 8MVA 11kV load transfer Darling Harbour to Camperdown zone substation; and • Three minor 11kV load transfer projects post 2027. The total NPC of this option is $19.8 million. Given the low deferral value available for reducing demand and the scale of load reduction required it was determined that non-network options could not form part of a credible option for this replacement investment. The NPC results of the network options are considered equivalent given the accuracy of planning estimates. Option 3 is the recommended solution because it provides greater flexibility to address future growth in the Blackwattle Bay area, as several commercial and residential developments are likely to occur. In addition, it defers the need for the additional transformer at Camperdown zone substation until 2023.

107

The project was approved by Ausgrid Board on 20/06/2017, at a total cost of $18.1 million ($16.5 million excluding contingency). The original completion date of the 11kV load transfers was September 2018, with decommissioning of Blackwattle Bay 33/5kV zone substation targeted for March 2019. Project complexities associated with staging/planning customer outages, night works and increased cable testing requirements have led to extend the project construction timeframe. Geographical view of works required in Blackwattle Bay project

7.3.1.2 Bankstown STS 33kV switchgear replacement Key project milestones: • Project initiated in November 2009. • Project expenditure authorised by Ausgrid Board in September 2010 • Project completion is expected by October 2019. Options Analysis The 33kV circuit breakers at Bankstown STS are of the bulk oil type and are at the end of their service lives. Replacement requirements are addressed in conjunction with work to address the non-compliant busbar height. The Bankstown STS 33kV switchgear replacement project is common across all strategies considered in the Bankstown Area Plan. Since this project is driven by asset condition and Duty of Care requirements, there are no viable non-network alternatives for this project. The Canterbury Bankstown Area Plan considered the issues at Bankstown subtransmission substation in conjunction with other issues in the area. Four strategies were developed and analysed to resolve network issues in the Canterbury Bankstown area. The replacement of the 33kV switchgear at Bankstown subtransmission substation is common to all four strategies considered in the Canterbury Bankstown Area Plan. Since this project is driven by asset condition and Duty of Care requirements, there are no viable non-network alternatives for this project.

108

The preferred solution involves replacing the existing outdoor 33kV busbars and associated structures and 33kV switchgear with new indoor 33kV GIS in a new switchroom, to be constructed on the Bankstown subtransmission substation site. Accordingly, all existing transformer and feeder connections are to be re-connected to the new GIS equipment. In addition, 132kV overhead feeders 914 and 915 are to be relocated to maintain suitable clearances within the Bankstown subtransmission substation site. Given the low deferral value available for reducing demand and the scale of load reduction required it was determined that non-network options could not form part of a credible option for this replacement investment. The project was approved by Ausgrid Board on 22/09/2010, at a total cost of $19.4 million ($17.6 million excluding contingency).

7.3.1.3 11kV Load Transfers to enable retirement of Flemington ZS 11kV switchgear Group 1 Key project milestones: • Project initiated in June 2017. • Project expenditure authorised by Ausgrid Chief Executive Officer in August 2018. • Project completion is expected by August 2020. Options Analysis The 11kV switchgear at Flemington zone substation consists of both compound and air insulated types. Group 1 of 11kV switchgear at Flemington ZS uses bituminous compound insulation busbars (switchboard) and oil- filled circuit breakers. The presence of both oil and insulating compound creates a heightened fire risk in the event of failure and therefore this is regarded as obsolete technology. Three options have been considered to address issues with Flemington zone substation: Option 1 – Refurbishment of Flemington Zone Substation This option involves refurbishing Flemington zone substation, utilising the existing switchroom building. The 11kV loads would need to be transferred to other zone substations to allow the refurbishment work to take place. The Net Present Cost of this option is $23.6 million. Option 2 – Retirement of compound-filled 11kV switchgear at Flemington zone substation and replacement of Transformer 4 This option proposes the transfer of all Group 1 load at Flemington zone substation (approximately 42MVA) to adjacent Olympic Park zone substation and Auburn zone substation. Flemington zone substation 11kV switchgear Group 2 is to remain in operation and Tx3 will continue to be used in service but be physically moved to Flemington Tx2 bay, while Tx4 is to be replaced by a transformer made surplus by the reconfiguration of Clovelly zone substation. The Net Present Cost of this option is $7.7 million. Option 3 – Replacement of Flemington compound-filled 11kV switchgear and Transformers 2 and 4 This option involves replacement of compound filled 11kV switchgear and transformers 2 and 4, using a new switchroom. 11kV loads will need to be transferred to other zone substations to enable these replacements. The Net Present Cost of this option is $17.5 million. The preferred option is Option 1 as it is the least cost option. Options 2 and 3 were considered but not progressed, because their costs are significantly higher than Option 1 and do not provide a corresponding increase in benefits. A RIT-D assessment was completed for this project in 2018. The project was approved by the Chief Executive Officer on 21/08/2018, at a total cost of $9.4 million ($7.5 million excluding contingency).

7.3.1.4 New 132/11kV Greenacre Park ZS and decommission zone substation Key project milestones: • Project initiated in November 2013. • Project expenditure authorised by Ausgrid Board in June 2017. • Project completion is expected by December 2019. Options Analysis Nine options were investigated in detail. These options were costed using high level estimates following completion of concept drawings, development of staging and identification of risks.

109

Option Description Cost 1 New Greenacre Zone (2x50MVA and 3x132kV bus sections) $33.6M 2 Brownfield 11kV Switchgear + Greenfield Indoor 132kV GIS and new transformers $59.9M 3 Brownfield 11kV Switchgear + Greenfield Outdoor 132kV GIS and new transformers $56.1M 4 Brownfield using out 132kV Hybrid GIS and new transformers $50.8M 5 Brownfield using out 132kV Hybrid GIS using existing transformers $43.6M 6 Brownfield with tail ended 132kV using existing transformers $34.6M 7 Brownfield with DCB's using existing transformers $35.2M 8 Greenfield Substation 2x132kV bus sections and new transformers $32.7M 9 Greenfield 132kV Hybrid GIS, Brownfield 11kV switchgear using existing transformers $48.2M

Option 8 was discounted due to the additional network risk associated with having two rather than three bus sections and Option 6 was not considered an acceptable solution due to the reduced flexibility and network security of the tail ended arrangement. Consideration was also given to the possibility of decommissioning the existing Greenacre Park zone substation by transferring all 11kV loads to Bankstown zone substation. This option was not progressed because it requires extensive 11kV connections, as well as an additional 132/11kV 50MVA transformer; associated 132kV feeder and 11kV switchgear to be installed at Bankstown zone substation. The estimated cost of this option exceeded $44 million. The two remaining lowest cost alternatives (Options 1 and 7) have been analysed and compared in greater detail, with consideration given to construction time, staging, technical issues/constraints and costs including property resale. Option 1 – New Greenacre 132/11kV zone substation (2x50MVA) • New Greenacre zone substation adjacent to existing Greenacre Park zone substation. The existing substation would be decommissioned and the land would be available for sale. • Current forecasts indicate a load constraint in 2032 however the design can incorporate potential future expansion to meet this load. Option 7 - Greenacre Park Brownfield with DCBs (4x37.5MVA) • Staged Brownfield 11kV switchgear replacement within existing 11kV switchroom. Use of 11kV mobile switchroom to facilitate staging. • Replacement of existing control room and staged outdoor 132kV Isolators & Earthing Switches replacement with hybrid disconnector-circuit breakers. • Remediation of existing 11kV switch room building required to address condition issues. • Structural modification to the existing switchroom floor structural beam to accommodate replacement of 11kV switchgear and complete 11kV equipping. • Multiple 11kV load transfers required as part of the electrical staging. • Enables property sale of 222-230 Hume Highway, Greenacre.

Option 1 delivers a completely new 2x50MVA zone substation. The capacity of Option 1 would be less than Option 7 however expansion to meet potential future demands can be catered for. The purchase price of $3.9 million for the new site and an allowance of $1.5 million for the potential sale of the existing site have been included in the cost estimate of $33.6 million. Option 7 retains the existing 4 x 37.5MVA transformers arrangement and involves a staged 11kV switchgear replacement in the existing building plus a new control room. Implementation of this option is expected to take at least two years longer than Option 1. This option provides less network flexibility as no 132kV feeder circuit breakers would be installed and a mobile switchroom would need to be deployed at this location for several years. Pricing assumes internal delivery. The cost for this option is $35.2million and includes $3.9 million for the sale of the purchased site. Decommissioning of the 132kV feeders 291/1 and 292 has not been included, as this work is common to both options. Given the low deferral value available for reducing demand and the scale of load reduction required it was determined that non-network options could not form part of a credible option for this replacement investment.

110

Option 1 is preferred because it has the lowest cost and can be delivered in a shorter timeframe than the refurbishment option. In addition, the new zone substation can achieve higher network reliability by providing increased switching flexibility than a brownfield development of the site. The project was approved by Ausgrid Board on 20/06/2017, at a total cost of $31.8 million ($29.7 million excluding contingency). This project was initiated in 2013 with a view to complete the works by December 2017. The project was delayed because a staged brownfield construction was identified during project development activities as a feasible alternative. A more detailed options analysis was then conducted and investigations were completed in early 2016, confirming the new zone substation as the preferred option.

Plan view of the proposed Greenacre zone substation adjacent to the existing Greenacre Park ZS

7.3.1.5 Sydney South to Revesby 132kV Feeders Replacement Key project milestones: • Project initiated in October 2017. • Project expenditure authorised by Ausgrid Board in October 2018. • Project completion is expected by June 2020. Options Analysis The 132kV self-contained, fluid-filled underground feeders 282/1 and 283/1 supplying Revesby ZS and Milperra ZS from Sydney South BSP utilise an obsolete technology. These feeders are prone to the risk of leakage and require specialist skills to repair and maintain. Outage times can be lengthy, and spares are not readily available. Three options have been considered to address issues with feeders 282/1 and 283/1: Option 1 – Replacement of feeders 282/1 and 283/1 with new XLPE cable to Revesby ZS This option involves installing two new 132kV feeders from Sydney South BSP to Revesby ZS in a combined trench. These feeders will replace existing 132kV feeders 282/1 and 283/1 between Sydney South bulk supply point and Revesby zone substation. The proposed route of the replacement feeders is presented in the figure below. The Net Present Cost of this option is $12.3 million. Option 2 – Replacement of feeders 282/1 and 283/1 with new overhead feeders This option proposes replacing the existing 132kV feeders 282/1 and 283/1 with overhead feeders from Sydney South BSP to Revesby ZS. This option is not considered a viable option due to the major community impact on existing heavily developed urban areas.

111

Option 3 – Replacement of feeders 282/1 and 283/1 with new underground feeders from Bankstown STS This option involves replacing 132kV feeders 282/1 and 283/1 with two new underground XLPE feeders from Bankstown STS. This option will require a longer project span for design and construction as well as the acquisition of easements. The Net Present Cost of this option is $17.7 million. Given the low deferral value available for reducing demand and the scale of load reduction required it was determined that non-network options could not form part of a credible option for this replacement investment. The preferred option is Option 1 as it has the highest net market benefit, less likely to cause community objection, and with minimum requirements for easements. A RIT-D was completed for this project in 2018. The project was approved by Ausgrid Board on 29/10/2018, at a total cost of $19.2 million ($17.1 million excluding contingency). Existing and proposed route plans

7.3.1.6 Kingsford to Clovelly New 132kV Feeder Key project milestones: • Project initiated in October 2017. • Project expenditure authorised by Ausgrid Board in October 2018. • Project completion is expected by March 2021 Options Analysis The 132kV self-contained fluid filled underground feeders 260/2 and 261/2 supplying Clovelly ZS from Zetland ZS utilise an obsolete technology. These feeders are prone to the risk of leakage and require specialist skills to repair and maintain. Outage times can be lengthy, and spares are not readily available. Three options have been considered to address issues with feeders 260/2 and 261/2: Option 1 – Replacement of feeders 260/2 and 261/2 like-for-like This option involves the like-for-like replacement of 132kV feeders 260/2 and 261/2 by installing two new 132kV feeders from Zetland ZS to Clovelly ZS. The Net Present Cost of this option is $25.1 million. Option 2 – Decommission feeders 260/2 and 261/2 by offloading Clovelly to adjacent zone substations This option proposes transferring all load from Clovelly ZS to nearby substations in order to decommission 132kV feeder 260/2 and 261/2. This option will require an additional transformer at Waverley ZS to be able supply the load transferred from Clovelly zone substation.

112

The Net Present Cost of this option is $37.6 million. This option has been disregarded because it would result in a decrease of capacity in the area and lower reliability. In addition, it involves a significantly higher capital costs than the other options. Option 3 – Decommission feeders 260/2 and 261/2 by installing new feeder Kingsford - Clovelly with spare duct This option involves the installation of a new 132kV feeder and spare conduit (for a second future feeder) from Kingsford ZS to Clovelly ZS. This feeder will replace existing 132kV feeders 260/2 and 261/2 between Clovelly and ZS’s. The proposed route for the new feeder is presented in the figure below. The Net Present Cost of this option is $14.0 million. Given the low deferral value available for reducing demand and the scale of load reduction required it was determined that non-network options could not form part of a credible option for this replacement investment. The preferred option is Option 3 as it has the highest net market benefits. In addition, this option considers the installation of a spare duct that will facilitate the future replacement of feeder 262 and network reconfigurations in the Eastern Suburbs area. A RIT-D assessment was completed in 2018 for this network investment. The project was approved by Ausgrid Board on 29/10/2018, at a total cost of $17.8 million ($16.6 million excluding contingency). Proposed route plan for the new Kingsford to Clovelly 132kV feeder

7.3.1.7 Matraville 11kV switchgear Groups 1, 2 and 4 replacement Key project milestones: • Project initiated in May 2010. • Project expenditure authorised by Ausgrid Board in March 2017.

113

• Project completion is expected by June 2020. Options Analysis Three options have been considered to address issues at Matraville zone substation: Option 1 – Retire Matraville via a new zone substation This option involves purchasing a site and greenfield construction of a new Matraville 33/11kV zone substation. Load would be transferred from the existing Matraville to the new zone substation. New 33kV feeders would need to be run from Bunnerong STS to allow retirement of the existing aged 33kV feeders. The estimated cost of this option is $39 million. The Net Present Cost (NPC) is $37 million. Option 2 – Retire Matraville via 11kV load transfer to surrounding zone substations This option involves transferring all loads to Port Botany and Maroubra zone substations to enable the retirement of Matraville ZS. The estimated cost of this option is $26 million and the NPC is $25 million. Option 3 – Replace Matraville 11kV switchgear and 33kV feeders This option involves staged replacement of the aged 11kV switchgear with fixed-pattern single bus switchgear. Transformer 3 will be permanently decommissioned due to their poor condition. In this option, the replacement of the 33kV feeders supplying Matraville zone substation as well as Group 3 11kV switchgear can be deferred to be completed by mid 2020s. The estimated cost of this option is $32 million. The NPC is $27 million. Although Option 2 has the lowest NPC, Option 3 is still preferred because: • It provides greater network flexibility than Option 2, as the load transfers required under the latter would leave no spare 11kV panels at Maroubra zone substation; and • There is greater risk due to the magnitude of 11kV cable works required and confidence in the supporting cost estimates. Given the low deferral value available for reducing demand and the scale of load reduction required it was determined that non-network options could not form part of a credible option for this replacement investment. The project was approved by Ausgrid Board on 28/03/2017, at a total cost of $15.4 million ($14.2 million excluding contingency). This project is a complex brownfield substation refurbishment, which led to experienced significant delays at development stage.

7.3.1.8 Surry Hills 11kV switchgear replacement Key project milestones: • Project initiated in June 2011. • Project expenditure authorised by Ausgrid Board in February 2015. • Project completion is expected by September 2020. Options Analysis Three network options were considered to address identified issues at Surry Hills ZS: Option 1 – Retire Surry Hills zone substation via 11kV load transfers to surrounding zone substations Campbell St is the only zone substation near Surry Hills with significant spare capacity and potential for expansion; however, even if augmented to its potential three-transformer arrangement it will not have enough spare capacity to absorb the load required to allow full retirement of Surry Hills ZS. Campbell St ZS is forecast to have around 30MVA of spare capacity at the end of the planning period in its augmented arrangement, while Surry Hills ZS load is forecast to be over 55MVA. This option is therefore not considered technically feasible. Option 2 – New Surry Hills zone substation Surry Hills ZS is located in a dense urban area with narrow, busy streets and sensitive residents and businesses. As such, an appropriate site for a replacement zone for Surry Hills would likely be prohibitively expensive. Egress of transmission and distribution cables would likely be difficult, and the cost of transferring load from the old zone to the new zone would likely be more than replacing the switchgear in the existing Surry Hills switch-room.

114

This option would not only resolve issues with the 11kV switchgear, but also resolve condition issues with the 33kV gas pressure cables supplying Surry Hills ZS. The estimated cost of this option is $43 million. The Net Present Cost of this option is $39 million. Option 3 – Replace Surry Hills 11kV switchgear and 33kV feeders In this option, 11kV load is to be transferred from Surry Hills ZS to Campbell St and Camperdown zone substations, allowing staged replacement of the aged 11kV switchgear with fixed-pattern single bus switchgear. The 33kV feeders from Surry Hills STS to Surry Hills ZS would be replaced with modern equivalent technology by 2024. The Net Present Cost of this option is $25 million. Given the low deferral value available for reducing demand and the scale of load reduction required it was determined that non-network options could not form part of a credible option for this replacement investment. Option 2 is significantly more expensive than Option 3, and Option 1 is not technically feasible. As a result, the proposal to replace Surry Hills ZS 11kV switchgear and 33kV feeders (Option 3) is shortlisted as the preferred solution. The project was approved by Ausgrid Board on 25/02/2015, at a total cost of $19.1 million ($18.1 million excluding contingency).

7.3.1.9 Decommission Darlinghurst 33/11kV ZS – Stage 1 Key project milestones: • Project initiated in February 2018 • Project expenditure authorised by the Ausgrid Chief Operating Officer in June 2019 (Stage 1) • Project completion is expected by October 2021 Options Analysis Two network options were considered to address identified asset condition issues at Darlinghurst ZS: Option 1 – Staged retirement by staged transfer of load This strategy involves transferring the existing load on Darlinghurst ZS to adjacent zone substations in two stages. The first stage allows for the retirement of the highest risk switchgear with compound insulated busbars, and deferral of the remaining switchgear with air insulated busbars until a later time. The Net Present Cost of this option was $2.8 million (Stage 1 only). Option 2 – Single-staged retirement by transfer of all load This strategy involves transferring all of the existing load on Darlinghurst ZS to adjacent zone substations in one project and allows for the earlier decommissioning of Darlinghurst ZS. There is no cost deferral benefit with this approach. Option 2 was ultimately disregarded because it costs three times more than Option 1 and the fact that replacement of the 11kV air insulated switchgear is not required in the short term. In addition, Option 2 does not provide a corresponding increase in benefits. Given the low deferral value available for reducing demand and the scale of load reduction required it was determined that non-network options could not form part of a credible option for this replacement investment. The project was approved by Ausgrid Chief Operating Officer on 27/06/2019, at a total cost of $4.2 million ($3.9 million excluding contingency).

7.3.1.10 Leichhardt ZS 132kV Conversion Key project milestones: • Project initiated in March 2009. • Project expenditure authorised by Ausgrid Board in February 2010. • Project completion is expected by June 2020. Options Analysis The issues identified at Leichhardt 33/11kV ZS are addressed as part of the network strategies proposed for the Eastern Inner West network area. Each strategy integrates a suite of projects to resolve asset condition issues

115

with the 132kV fluid-filled feeder 900 (Mason Park STSS to Rozelle STS), the 33kV gas pressure cables supplying Leichhardt ZS, as well as the condition of the 11kV switchgear and 33/11kV transformers at Five Dock ZS. Two strategies were considered in this case: Strategy 1 – Retain 33kV in the Eastern Inner West network area This strategy involves a like-for-like replacement of feeder 900 from Mason Park STSS to Rozelle STS via a new route which avoids the harbour. At the same time Rozelle STS would be uprated and new 33kV feeders would be installed from Rozelle STS to Leichhardt ZS to retire the existing 33kV feeders supplying Leichhardt. A new Croydon 33/11kV ZS would be constructed with new 33kV feeders supplied from Homebush STS to replace the existing Five Dock 33/11kV ZS. The Net Present Cost (NPC) of this strategy was $102.6 million. Strategy 2 – Conversion of the Eastern Inner West network area to 132kV supply This strategy involves the conversion of Leichhardt ZS to 132kV operation and the replacement of Five Dock ZS with a new 132/11kV facility nearby. 132kV supply to these new zone substations will be provided via the replacement of 132kV feeder 900. The NPC of this strategy is $90.1 million. Ausgrid’s preferred strategy for the Eastern Inner West network area is the 132kV development strategy. It is more cost effective than retaining 33kV supply to Leichhardt and Five Dock ZS’s as the distance of these substations from available 33kV capacity is significant. Under the proposed 132kV strategy, supply to both zone substations can be provided at a small incremental cost by re-routing the cables that will replace feeder 900. Given the low deferral value available for reducing demand and the scale of load reduction required it was determined that non-network options could not form part of a credible option for this network replacement investment. The project was approved by Ausgrid Board on 17/02/2010, at an original cost of $19.7 million ($18.2 million excluding contingency). Since then, two project variations have been required in 2012 and 2015, increasing the total to $26.7 million ($25.1 million excluding contingency). Work on Leichhardt 132kV conversion was severely impacted by the financial collapse in 2012 of the company engaged to undertake the civil & building contract, as well as variations of scope in replacement of feeder 900, of which the last variation was authorised by the Board in 2014.

7.3.1.11 Lidcombe 33/11kV Zone Substation Group 2 11kV Switchgear Replacement Key project milestones: • Project initiated in September 2014. • Project expenditure authorised by Ausgrid Board in December 2017. • Project completion is expected by July 2020. Options Analysis The options analysis was initiated in 2013 and further reviewed in 2014 and 2015. The network options considered solutions to address condition issues with 11kV compound insulated switchgear at Lidcombe ZS and 33kV supply to both Auburn and Lidcombe zone substations. The options explored reconfiguration of the existing zone substations as well as the transition towards a 132kV supply. These options and their corresponding net present costs (NPC) in $ million are listed below:

Option Description NPC

1 Uprate Auburn and retire Lidcombe $68.5M

2 Auburn 132kV conversion and retire Lidcombe (not feasible) N/A

3 Replace both Auburn and Lidcombe with a new 132/11kV zone substation $57.8M

4 Replace 33kV feeders like-for-like and refurbish Lidcombe $72.5M

5 Replace 33kV feeders from Homebush STS to Auburn and reconfigure Lidcombe $58.2M

6 Replace 33kV feeders from Camellia Substation and reconfigure Lidcombe $48.5M

116

7 Replace Lidcombe with new 132/11kV substation and reconfigure Auburn 33kV feeders $51.9M

8 Replace 33kV feeders from Camellia Substation and reconfigure both substations $42.0M

Given the low deferral value available for reducing demand and the scale of load reduction required it was determined that non-network options could not form part of a credible option for this replacement investment. Option 8 has the lowest NPC and the least risk. It is therefore the preferred option. Further development of this option identified opportunities to defer the replacement of Group 1 switchgear at Lidcombe zone substation, which have been replaced with vacuum trucks. As a result, the scope and cost of the preferred option has been reduced as it considers replacing the 11kV switchgear (Group 2 only) at Lidcombe zone substation now and the remaining switchgroup at a later date. The NPC of the enhanced Option 8 was further reduced to $40.2 million, of which $9.1 million is the contribution of replacing the 11kV compound insulated switchgear (Group 2). This project experienced significant delays because it is developed in combination with the replacement of 33kV feeders supplying Auburn and Lidcombe zone substations. Extensive community consultation on the feeders and coordination issues with the project that involves the widening of the M4 Motorway (part of the WestConnex development) have caused such delays. The project was approved by Ausgrid Board on 14/12/2017, at a total cost of $9.1 million ($6.7 million excluding contingency).

7.3.1.12 Decommission Strathfield STS Key project milestones: • Project initiated in August 2015. • Project expenditure authorised by Ausgrid Chief Executive Officer in June 2017. • Project completion is expected by February 2020. Options Analysis Two network options to address the asset condition issues at Strathfield STS were considered: Option 1 – Decommissioning of Strathfield STS This option involves transferring the Sydney Trains Strathfield Substation load from Strathfield STS to Homebush STS by installing two new 33kV feeders. Modifications will need to be made to protection elements and 132kV connections as part of the decommissioning works at Strathfield STS. The transfer of Sydney Trains load will enable the decommissioning of Strathfield STS. 132kV feeders 923 and 924 would need to be modified at the Strathfield STS point along the feeder to become a transition point so that load continues to pass from Mason Park STSS to Burwood zone substation. The cost of this option is approximately $11 million. Option 2 – Refurbishment of Strathfield STS This option involves the like for like replacement of six 33kV circuit breakers and four 132kV isolators at Strathfield STS. In the initial analysis, it was assumed that other secondary issues could be addressed by various replacement sub-programmes at minimal costs. However; additional condition issues have been identified at Strathfield STS and it was discovered that such issues could not be easily addressed via like for like replacement. A refurbishment of the STS would be a complex task that will require extensive staging, since there is limited space available at the Strathfield STS site. This option is estimated to cost in excess of $20 million. Given the low deferral value available for reducing demand and the scale of load reduction required it was determined that non-network options could not form part of a credible option for this replacement investment. Option 1 is preferred because it has the lowest cost and can be delivered in a shorter timeframe than the refurbishment option. The project was approved by the Chief Executive Officer on 21/06/2017, at a total cost of $10.5 million ($9.3 million excluding contingency).

7.3.1.13 New Summer Hill 33/11kV ZS and decommission Dulwich Hill 33/11kV ZS Key project milestones:

117

• Project initiated in March 2012. • Project expenditure authorised by Ausgrid Board in May 2017. • Project completion is expected by June 2020. Options Analysis Three strategies were considered to address issues in the Canterbury Bankstown network area. Each strategy integrates solutions to issues at Enfield, Campsie and Dulwich Hill zone substations. Strategy 1 – Enfield 132/11kV zone substation and Dulwich Hill 33/11kV replacement This strategy involves replacement of the existing 33/11kV Enfield with a new Strathfield South 132/11kV ZS, establishment of a new 33/11kV Dulwich Hill ZS adjacent to the existing zone site and load transfers from Campsie to Enfield to facilitate the switchgear replacement at Campsie ZS. The Net Present Cost (NPC) of this strategy is $62.2 million. Strategy 2 – Replace Enfield and Dulwich Hill zone with new Ashbury 132/11kV zone This strategy involves construction of a new Ashbury 132/11kV ZS and decommissioning of 33/11kV Enfield ZS and Dulwich Hill ZS by transferring all existing load to the new Ashbury ZS. This would be followed by the installation of an additional 132/11kV transformer at Ashbury ZS and load transfers from Campsie ZS to Ashbury to facilitate the switchgear replacement at Campsie ZS. The NPC of this strategy is $61.0 million. Strategy 3 – Dulwich Hill and Enfield zone substation replacement This strategy involves 11kV switchgear and 33kV feeder replacement at Dulwich Hill and Enfield ZS’s, with the installation of an additional transformer at Canterbury STS. Another transformer would then be installed at Enfield ZS and load transferred from Campsie to Enfield to facilitate the switchgear replacement at Campsie ZS. The NPC of this Strategy is $80.1 million. Given the low deferral value available for reducing demand and the scale of load reduction required it was determined that non-network options could not form part of a credible option for this replacement investment. Ausgrid’s preferred strategy for Canterbury Bankstown area is Strategy 1, which involves replacing Dulwich Hill Zone substation with a new 33/11kV zone substation. This strategy is preferred because: • Strategies 1 and 2 have NPC estimates that are considered equivalent (within the level of accuracy of the estimate) and materially lower costs than Strategy 3. • Considering the location and characteristics of loads in the area, extensive 11kV work would be required to connect all 11kV feeders to the single point of supply proposed under Strategy 2. 11kV development costs often vary greatly as a result of issues encountered during the construction phase compared to pre-project estimates. Hence, there is less uncertainty in cost estimates for Strategy 1. • Strategy 1 provides greater system flexibility and better coverage of the surrounding 11kV networks than Strategy 2, especially for some load areas (e.g. Belfield, Strathfield and Strathfield South). Additional investigations were carried out to determine the viability of a conversion to 132kV operation, as well as the most ideal location of the new Dulwich Hill ZS. The conversion of Dulwich Hill to 132kV operation was rejected due to the high costs associated with achieving 132kV feeder connections. Although 132kV supply in the area is currently available via feeders 92C, 92X, 91X or 91Y, all these fluid filled cables are targeted for retirement within the next 10 years. Any other 132kV supply to connect a new 132/11kV zone substation at this location would need to originate from Chullora STS (approximately 7km long), looping into the existing 132kV overhead feeders 910/911 via an underground connection (approximately 3km long), or an underground connection from Marrickville zone substation (approximately 4km long). In all these cases, the installation of 132kV switchgear at the Dulwich Hill end will be required. The area to the south of the existing site is the preferred location as it provides one street frontage for 33kV cable replacement and two street frontages for 11kV feeder cutover. In addition, it reduces community impact as works will not be adjacent to residential properties. An aerial view of Dulwich Hill ZS and its proposed replacement is included in the figure below.

118

Existing and proposed substation sites for Dulwich Hill and Summer Hill ZS’s

The project was approved by Ausgrid Board on 01/05/2017, at a total cost of $43.9 million ($40.9 million excluding contingency). A prolonged development time was experienced as the scope of the project was refined to reduce project costs.

7.3.1.14 Rozelle STS new 33kV busbar Key project milestones: • Project initiated in September 2017 • Project expenditure authorised by Ausgrid Board at a meeting in March 2019 • Project completion is expected by October 2022 Options Analysis Sydney Motorway Corporation has submitted a connection request for a supply of 38MVA for the Main Tunnel (Stage 3A) and 33MVA for the Rozelle Interchange (Stage 3B) of the proposed WestConnex motorway. WestConnex Stages 3A and 3B are both currently under construction. Westconnex Stage 3A is to be supplied from Alexandria 132/33kV STS. Two network options were considered to supply Westconnex Stage 3B: Option 1 – Upgrade Rozelle STS This option includes the installation of a 33kV busbar and upgrade of one Rozelle transformer from 30MVA to 60MVA. This approach provides a diversity of supply to the Westconnex Stage 3 tunnel and will facilitate other future connections at Rozelle anticipated due to development in the Rozelle and White Bay areas. This option provides network assets close to the required connection point. The Net Present Cost of this option is $25.7 million. Option 2 – Expand Alexandria STS Alexandria STS has been recently completed, and would require expansion to facilitate the additional connections. This approach would have all Westconnex Stage 3 tunnel supplies from a common source, does not address other anticipated connection requirements at Rozelle 132/33kV STS. The length of new 33kV cables would be greater with this option. Option 2 was ultimately disregarded because the connection of additional 33kV cables may require complex civil works (i.e. underbore) due to cable access/egress issues in the underground routes at Alexandria STS. In addition, this option will not avoid the need to augment the network to accommodate future load requirements in the Rozelle area. Ausgrid has also considered the ability of non-network solutions to assist in meeting the identified need. A demand management assessment has determined that non-network options cannot cost-effectively address the need to connect the customer loads.

The project was approved by Ausgrid Board on 15/03/2019, at a total cost of $24.2 million ($22.7 million excluding contingency).

119

7.3.1.15 Replace 33kV feeders – Homebush to Lidcombe ZS and Auburn ZS Key project milestones: • Project initiated in August 2014 • Project expenditure authorised by Ausgrid Board at a meeting in February 2018 • Project completion is expected by September 2020 Options Analysis Auburn and Lidcombe ZS’s are 33/11kV zone substations located in the Inner West area of Ausgrid’s network. These substations are supplied by three 33kV underground feeders respectively, all of which originate at Homebush STS. The oldest sections supplying Auburn ZS date back to 1942, while most feeder sections on the other feeders were commissioned in the 1940s and 1950s. These underground subtransmission feeders are a combination of paper insulated and gas pressure cable technologies, and have reached the end of their service lives. They have a combined length of approximately 37km, from which 22km are paper insulated and the remaining 15km are gas pressure cables. In particular, the gas pressure cables are prone to gas leakages that results in high levels of unavailability due the long time required to locate and repair leaks. While paper insulated cables do not have the same requirements of pressured gas (nitrogen) to maintain insulation integrity and therefore do not present same risks as gas pressure cables, the paper insulated cable sections have experienced a number of outages in recent years. If these issues are left unaddressed, the risk of failure and poor availability of these assets will expose customers in the Inner West network area to a network risk that exceeds allowable levels under the applicable reliability standards. Refer to section 7.3.1.11 for details of the options considered to address identified issues. Ausgrid, working with Endeavour Energy, identified a preferred solution that makes use of spare capacity on the Endeavour network following closure of a Shell Australia oil refinery at Clyde in Western Sydney. Ausgrid considers that these joint planning efforts identified the most efficient solution across the respective networks as a whole. In particular, this solution was found to come at a significantly lower cost than rebuilding the existing feeders on a ‘like-for-like’ basis. In fact, the proposed solution defers upstream investments that would otherwise be required if supply of Auburn and Lidcombe ZS’s were to continue to come from Homebush STS. The proposed route from Camellia STS to Auburn ZS is mainly through industrial areas, crossing Duck Creek and the existing M4 Western Motorway by following the Duck River Cycleway. Ausgrid plans to use underground cables in certain areas in response to community feedback and to minimise risks along the M4 motorway. The overhead route between Auburn ZS and Lidcombe ZS will pass primarily through industrial areas and cross under the main western rail line at Percy Street. Ausgrid plans to locate the cables on the western side of Percy Street, on existing low voltage powerline structures to minimise construction impacts. The project was approved by Ausgrid Board on 03/02/2018, at a total cost of $37.2 million ($31.3 million excluding contingency).

7.3.1.16 Willoughby to Mosman 132kV Feeders Replacement Key project milestones: • Project initiated in July 2017. • Project expenditure authorised by Ausgrid Board in October 2018. • Project completion is expected by November 2020.

Options Analysis The 132kV self-contained fluid filled underground feeders supplying Mosman zone substation 9Y7/2, 9Y9/2 from Castle Cove zone substation to Mosman zone substation and 9P7 from Willoughby subtransmission substation to Mosman zone substation are an obsolete technology. These feeders require specialist skills to repair and maintain, outage times can be lengthy, and spares are not readily available. Two options have been considered to address issues with 132kV feeders 9Y7/2, 9Y9/2 and 9P7: Option 1 – Replacement of feeders 9Y7/2 and 9Y9/2 from Willoughby subtransmission substation to Mosman zone substation via future Cremorne Junction zone substation and decommissioning of feeder 9P7 This option involves the installation of two new 132kV feeders from Willoughby subtransmission substation to Mosman zone substation via Ausgrid’s proposed future Cremorne Junction zone substation site. The Net Present Cost of this option is $29.0 million.

120

Option 2 – Replacement of feeders 9Y7/2 and 9Y9/2 from Castle Cove zone substation to Mosman zone substation (like-for-like) and decommissioning of feeder 9P7 This option involves the like-for-like replacement of 132kV feeders 9Y7/2 and 9Y9/2 by installing two new 132kV feeders from Castle Cove zone substation to Mosman zone substation. Feeder 9P7 is to be decommissioned. This option consists of a longer feeder route than Option 1, as well as require new 132kV feeder to connect the proposed Cremorne Junction zone substation. In addition, this option does not provide any reliability improvements, as a loss of Willoughby to Castle Cove feeders 9Y7/1 and 9Y9/1 would result in an outage of both Castle Cove and Mosman zone substations. The Net Present Cost of this option is $37.6 million. The preferred option is Option 1 as it is the highest net market benefit. In addition, this option allows for future expansion through Cremorne Junction zone substation, while requiring a shorter route in comparison to Option 2. A RIT-D was completed for this project in 2018. The project was approved by Ausgrid Board on 29/10/2018, at a total cost of $37.7 million ($35.4 million excluding contingency). The figure bellow provides a geographical view of the Lower North Shore area and highlights the connections between Castle Cove and Mosman and the connection between Willoughby STS and Mosman ZS. Lower North Shore network area

7.3.1.17 Waratah 132/33kV STS refurbishment Key project milestones: • Project initiated in April 2010. • Project expenditure authorised by Ausgrid Board in March 2016. • Project completion is expected by June 2020. Options Analysis The 33kV industrial busbar at Waratah STS is significantly aged and needs to be retired from service. The 33kV domestic busbar was refurbished in the 1980s but the oil circuit breakers now require replacement. Four out of seven of the 132/33kV transformers are at the end of their service lives. Two options have been considered to address issues with Waratah STS: Option 1 – Waratah STS supply rearrangement and refurbishment This option involves removing all loads, except major customers, from the Waratah domestic busbar. All unused equipment at Waratah STS is to be decommissioned, including four transformers and three sections of 33kV busbars.

121

In addition, neighbouring zone substations Mayfield, Shortland and Wallsend and Kooragang West switching station are to be decommissioned with all loads to be transferred to new substations recently commissioned or about to be commissioned. The estimated cost for this option is $19.8 million. Option 2 – Waratah STS replacement This option proposes constructing a new 132/33kV substation on a nearby site and decommissioning the existing Waratah subtransmission substation. In addition, neighbouring zone substations Mayfield, Shortland and Wallsend and Kooragang West switching station are to be decommissioned with all load is to be transferred to new substations recently commissioned or about to be commissioned. The estimated cost for this option is $44.3 million. Given the low deferral value available for reducing demand and the scale of load reduction required it was determined that non-network options could not form part of a credible option for this replacement investment. The preferred option is Option 1 as it is the least cost option. The project was approved by Ausgrid Board on 30/03/2016, at a total cost of $18.1 million ($ 17.0 million excluding contingency).

7.3.1.18 Peakhurst STS 33kV switchgear replacement Key project milestones: • Project initiated in November 2016 • Project expenditure authorised by Ausgrid Board at a meeting in December 2018 • Project completion is expected by March 2022 Options Analysis Two network options were considered to address the asset condition issues with the 33kV switchgear and switch building at Peakhurst STS: Swap options as per DPAR RIT-D paper Option 1 – Replacement of 33kV switchgear in new building This option involves construction and equipping of a new 33kV switch building within the existing STS site. The Net Present Cost of this option is $26.5 million (with 10% risk). Option 2 – Replacement of 33kV switchgear in existing building This option involves a staged replacement of the 33kV switchgear in the existing switch building, in conjunction with the refurbishment of the building which has structural and roofing problems. The Net Present Cost of this option is $26.6 million (with 40% risk). Option 1 is the preferred option. The estimated costs of each option are similar, however, the cost estimate for Option 2 has much more uncertainty due to the risks and unknowns associated with working in a “brownfield” situation, working around existing live equipment. Option 2 also has increased complexity in staging and longer outage requirements with increase risk of interruptions to customers. A demand management assessment into reducing the risk of unserved energy from the 33kV feeders showed that non-network alternatives cannot cost-effectively address the risk, compared to the two network options outlined above. The project was approved by Ausgrid Board on 17/12/2018, at a total cost of $26.8 million ($25.0 million excluding contingency).

7.3.1.19 11kV Load Transfers from Dalley St ZS to City North ZS Key project milestones: • Project initiated in January 2016. • Project expenditure authorised by Ausgrid Chief Executive Officer in April 2017 (Stage 1) and January 2018 (Stage 2).

122

• Project completion is expected by January 2021. Options Analysis Ausgrid’s strategic decisions for ensuring reliable supply in the Sydney CBD area arise from the need to address ageing infrastructure at City East and Dalley St ZS’s. Three strategies were considered, which will address the identified risks to an appropriate degree: Strategy 1 – New 132/11kV zone substation and decommission Dalley St and City East substations This strategy involves establishing a new 132/11kV substation on the northern section of Sydney CBD, transferring all load at Dalley St and City East to the new zone substation and after that decommission both Dalley St and City East ZS’s. The net present cost of this strategy is $165 million. Strategy 2 – Decommission Dalley St and City East by transferring load to City North and Belmore Park substations This strategy involves transferring approximately two thirds of the existing Dalley St ZS load to City North ZS, and all load at City East as well as the remaining load at Dalley St to Belmore Park ZS. Once completed, both Dalley St and City East substations will be decommissioned. The net present cost of this strategy is $58 million. Strategy 3 – Refurbish existing City East ZS and decommission Dalley St ZS This strategy involves transferring City East load to Belmore Park ZS, refurbish City East ZS at 33kV, transferring Dalley St load to the newly refurbished City East and decommission Dalley St ZS. The net present cost of this strategy is $115 million. Strategy 2 has the lowest net present cost and is the preferred option. To capture any differences in the value of the assets remaining at the end of the planning period residual benefits were calculated for each strategy. The present value of residual benefits for Strategies 1 and 3 were $20 million compared to $10 million for Strategy 2. This difference is not material compared to the cost difference of the strategies. As the risk of equipment failure is significant at Dalley St ZS and could result in a prolonged outage, the partial offloading of Dalley St to City North zone substation should be completed as soon as practical. Up to 65% of the load at Dalley St ZS can be transferred to City North ZS, which will substantially reduce network risks at Dalley St and enable relatively low cost recovery actions in the event of a switchgear failure. Non-network options were considered based upon a one-year deferral value of $25/KVA and a total reduction of 50MVA required to be removed from Dalley St zone substation (65% of the load). Given the low deferral value available for reducing demand and the scale of load reduction required it was determined that non-network options could not form part of a credible option for this replacement investment. The 11kV load transfers from Dalley St to City North ZS were initiated as a single project in January 2016. In order to reduce the impacts derived from the construction of the CBD & South East Light Rail Project, the 11kV load transfers were segmented in two stages. The two stages were presented as one project to Ausgrid Board for preliminary project approval (Gate 2 approval) because both are required to address the identified network need. The Board provided Gate 2 approval for the project in April 2016. Stage 1 was authorised by the Chief Executive Officer on 07/04/2017 at a cost of $9.9 million ($9.0 million excluding contingency). The latest schedule review has adjusted the completion date of the project to March 2019. Stage 2 was authorised by the Chief Executive Officer on 03/01/2018, at a total cost of $12 million ($9.9 million excluding contingency). Stage 2 was originally scheduled for completion in September 2018. This second set of load transfers have significant dependencies on the completion of the Light Rail Project, which is experiencing construction delays.

7.3.1.20 Kuringai STS 33kV switchgear replacement Key project milestones: • Project initiated in June 2010. • Project expenditure authorised by Ausgrid Board at a meeting dated August 2011. • Project completion is expected by November 2019. Options Analysis The 33kV switchgear replacement at Kuringai STS is driven by non-compliance of the 33kV busbar with current clearance requirements, as well as the poor condition of the bulk-oil circuit breakers which have reached the end of their service lives and are scheduled for replacement in 2014/2015.

123

The Upper North Shore Area Plan considered the issues at Kuringai STS in conjunction with other issues in the area. Four strategies were developed and analysed to resolve network issues in the Upper North Shore area. The replacement of the 33kV switchgear at Kuringai STS is common to all four strategies considered in the Upper North Shore Area Plan. Therefore, there are no viable strategic alternatives to resolve the issues at Kuringai STS. The estimated cost for this strategy over the 20 year planning horizon is $113.0 million. The net present cost of this strategy is $66.5 million. The preferred solution involves the replacing the outdoor 33kV switchgear and busbar at Kuringai STS with new 33kV indoor gas-insulated switchgear. A new 33kV switchroom within the Kuringai STS to accommodate new switchgear will also be built as part of this project. The project was approved by Ausgrid Board on 16/08/2011, at a total cost of $25.9 million ($ 23.1 million excluding contingency). The project has undergone contractual difficulties causing delays and further expenses. A further $9.1 million and revised project authority to $35.0 million ($32.2 million excluding contingency) was approved by Ausgrid Board on 27/11/2015.

7.3.2 Refurbishment, replacement or augmentations – Dual function Region Committed Refurbishment or Replacement Expected Estimated Investment – Transmission Project Cost ($m) Completion Canterbury- Canterbury STS 132kV Busbar Replacement and 33kV Bankstown Switchgear Replacement Jan-20 43.3

Carlingford New Macquarie 132/33kV STS Jan-22 34.3

Singleton Singleton ZS 11kV switchgear replacement Nov-19 9.1

7.3.2.1 Canterbury STS 132kV Busbar Replacement and 33kV Switchgear Replacement Key project milestones: • Project initiated in August 2009. • Project expenditure authorised by Ausgrid Board in May 2010. • Project completion is expected by January 2020. Options Analysis Canterbury STS was established in 1961 and is currently a four transformer 132/33kV substation. In TAPR 2013 it was mentioned that the 132kV busbar has been identified as being inadequate to meet increased fault levels on the subtransmission system following the completion of proposed new connections to Beaconsfield BSP and Peakhurst STS. The 33kV switchgear has been identified as approaching the end of its service life, while the 33kV busbar height does not meet current standards. Replacement of the 132kV outdoor busbar with indoor GIS to meet increased fault levels and the replacement of the outdoor 33kV switchgear with an indoor busbar and switchgear are now under a single project. Two options have been considered to address issues with Canterbury STS: Option 1 – Outdoor 132kV busbar refurbishment and indoor 33kV rebuild This option involves rebuilding sections of the outdoor 132kV busbar that do not meet the required future fault rating and construction of a new 33kV switchroom, as well as rearranging the 33kV underground feeders into the new switchroom. In addition, this option also requires the construction of a new feeder bay to accommodate future feeder 907 and the refurbishment of ex-908/909 feeder bay to accommodate future 906. This option is not viable from a system security perspective as it requires two transformers are required to be out of service for periods of up to three months. The estimated cost for this option is $32.4 million.

124

Option 2 – Full 132kV and 33kV rebuild as indoor GIS This option proposes constructing a new building to house the 132kV and 33kV GIS switchgear and new control room, as well as rearranging the 132kV and 33kV underground feeders to the new GIS building. The estimated cost for this option is $35.9 million. The preferred option is Option 2 as it does not require outages of two transformers. This option also has a quicker construction time and utilise significantly less land area due to the compactness of indoor GIS plant. The project was approved by Ausgrid Board on 19/05/2010, at a total cost of $45.4 million ($43.3 million excluding contingency).

7.3.2.2 New Macquarie 132/33kV STS Key project milestones: • Project initiated in May 2018 • Project expenditure authorised by Ausgrid Board at a meeting in July 2019 • Project completion is expected by January 2022 Options Analysis Three options, including some further variations, have been considered to make provision for the connection of a number of large customers in the Macquarie Park area. Option 1A – New 132/33kV STS on the existing Macquarie Park ZS site, with expansion capability This option was investigated and found not to be viable due to space constraints on the Macquarie ZS site. Option 1B – New 132/33kV STS on a new site, with expansion capability This option was investigated and found not to be viable within the required timeframe (completion 2021). Ausgrid does not own a suitable site and additional land would have to be acquired. Option 1C – New 132/33kV STS on the existing Macquarie Park ZS site, without expansion capability This option was investigated. A number of risks were identified, but it is considered to be viable. This approach is expected to meet the required timeframe of 2021 completion and allows for utilisation of land that is already owned by Ausgrid. The Net Present Cost of this option is $33.7 million. Option 2 – New 132/33kV STS and 132/11kV ZS at Macquarie University, without expansion capability This option was investigated but ultimately not progressed because it is subject to the provision of a suitable site by Macquarie University, and is considered unlikely to meet the required project timeframe. This option was also found to be higher in costs than Option 1C, and involve the construction of new assets remote from the load centre. Option 3 – Third Transformer at Top Ryde ZS, deferring the need for new STS by two years This option would assist in enabling Ausgrid to meet the required customer connection timing, however, it is not efficient as the new 11kV capacity would not be utilized in the longer term. Following a two-year deferral, it is anticipated that one of the other options would still be required. Therefore, this option was disregarded. This would act as an interim measure only and would require a further major network augmentation within a short period of time. The preferred option is Option 1C as it is the only credible option capable to meet the required customer connection timing. The project was approved by Ausgrid Board on 01/07/2019, at a total cost of $40.1 million ($34.3 million excluding contingency).

125

Location of proposed new Macquarie STS on existing Macquarie Park ZS site

7.3.2.3 Singleton ZS 11kV switchgear replacement Key project milestones: • Project initiated in April 2010. • Project expenditure authorised by the Chief Executive Officer in May 2016. • Project completion is expected by November 2019. Options Analysis The 11kV switchgear at Singleton ZS has asset condition and is nearing the end of its service life. The Singleton Area Plan considered the issues at Singleton ZS in conjunction with other issues in the area. Four strategies were developed and analysed to resolve network issues in the Singleton area: Strategy 1 – Upgrade Singleton STS and refurbish Singleton ZS The estimated cost for this strategy is $32.0 million. The Net Present Cost of this option is $20.7 million. Strategy 2 – Construct Newdell STS and refurbish Singleton ZS The estimated cost for this strategy is $56.0 million. The Net Present Cost of this option is $42.7 million. Strategy 3 – Upgrade Singleton STS and replace Singleton ZS The estimated cost for this strategy is $41.0 million. The Net Present Cost of this option is $26.5 million. Strategy 4 – Construct Newdell STS and replace Singleton ZS The estimated cost for this strategy is $65.0 million. The Net Present Cost of this option is $48.5 million. The preferred strategy is Strategy 1 as it is the least cost option. Although the works associated with Singleton 11kV switchgear are not common to all strategies, a load transfer from Singleton to Singleton North was underway at the time of development. This indicates that the works under this project are purely driven by asset condition and removing the need to replace Singleton ZS due to capacity constraints. Therefore there are no viable strategic alternatives. The preferred solution involves the construction and installation of a new modular 11kV switchroom at Singleton 66/11kV zone substation; installation of two new 11kV switchgear and transferral of 11kV feeders to the new groups; decommissioning and removal of two groups of 11kV switchgear. Given the low deferral value available for reducing demand and the scale of load reduction required it was determined that non-network options could not form part of a credible option for this replacement investment. The project was approved by the Chief Executive Officer on 17/05/2016, at a total cost of $9.8 million ($9.0 million excluding contingency).

126

7.3.3 Committed dual function augmentations There are no identified network constraints requiring dual function asset augmentations at this stage. As no projects have appeared in previous TAPR publications as proposed network augmentations, there cannot be committed projects. For the purposes of the TAPR, an augmentation is considered to be committed if it satisfies all the criteria that are defined in AEMO’s Electricity Statement of Opportunities (SOO), as follows: • Board commitment has been achieved (this requires the appropriate planning approvals and licences to be in place) • Funding has been approved • The project has satisfied the Regulatory Test, and • Construction has either commenced, or a firm date has been set for it to commence

7.4 Urgent and unforseen investments There were no distribution network Regulatory Test projects required to address an urgent or unforeseen network investment in the preceding year. There were no dual function asset RIT-T projects or Regulatory Test projects required to address an urgent or unforeseen network investment in the preceding year.

127

8 Joint planning

Joint Planning is carried out with other Network Service providers, in particular TransGrid, Endeavour Energy, Essential Energy and Sydney Trains. 8.1 Joint planning with TransGrid TNSP Ausgrid plans its transmission network jointly with TransGrid as the Ausgrid 132kV dual function network provides support to TransGrid’s 330kV network. In carrying out joint planning TransGrid and Ausgrid: • meet regularly, at least 4 times per year; • record minutes and decisions; • prepare work plans and monitor progress; • assess augmentation options on the basis of least cost to the community; • initiate projects within each organisation following the normal approval processes; and • jointly consider demand management as an option. Ausgrid and TransGrid have established a Joint Planning Committee structure which comprises a steering committee and a joint planning sub-committee to coordinate the planning activities of Ausgrid and TransGrid in accordance with the joint planning requirements of the National Electricity Rules. Under the agreed terms of reference, there are quarterly meetings of the sub-committee and bi-annual steering committee meetings. Members include relevant planning, operations, design and project development staff. The key considerations of the joint planning committees are: • load forecasting; • connection agreement issues, including major new connections; • reliability criteria; • major plant refurbishment; • plant retirement issues; • demand management and embedded generation opportunities; • network augmentation options; • reactive plant requirements; • system fault levels; • earthing coordination; • major network control coordination; • overview of protection, metering and communication issues; and • network business communication requirements. Committee activities and deliverables are managed through an agreed work plan, with decisions documented in approved Joint Planning Reports for major milestones. Joint Planning Report sign-offs range from Planning Manager level (Ausgrid L5) for more routine agreements up to Executive level. The more routine operational decisions and actions required are agreed on and recorded via the joint planning meeting minutes. 8.1.1 Process and methodology Ausgrid plans the Inner Sydney Metropolitan, Central Coast and Lower Hunter Transmission Load Areas jointly with TransGrid. From 1 July 2018, TransGrid and Ausgrid are required to comply with the “NSW Electricity Transmission Reliability and Performance Standard 2017”. This standard requires the NSW electricity transmission network to be designed and planned to a certain level of redundancy and level of expected unserved energy. This is a significant change from the former deterministic assessment of the network. Each bulk supply point is allocated one of three categories. The level of redundancy required for each category is as follows: • Category 1 – a supply interruption may occur following the outage of a single system element;

128

• Category 2 – a non-zero amount of load must be supplied following the outage of a single system element; or • Category 3 – a non-zero amount of load must be supplied following the outage of a single system element. In addition, for Inner Sydney, a non-zero amount of load must be supplied following the simultaneous outage of a single 330kV cable and any 132kV feeder or 330/132kV transformer. There is provision in the standard for flexibility in planning for the level of expected unserved energy. Compliance with the expected unserved energy allowance is not required provided that: • A plan regarding measures for altering the reliability of the supply capacity of the bulk supply point has been developed and submitted to IPART; • That the plan provides a greater net-benefit, using the cost-benefit methodology defined in the RIT-T, than the net-benefit of compliance with the standard; and • That IPART has advised in writing that it is satisfied that the plan submitted, if implemented would: • Be likely to provide a greater net-benefit than would be provided with compliance; and • Not result in a material reduction in the level of expected unserved energy at any bulk supply point. The NER sets out the planning process and consultation requirements and includes requirements on forecasting, annual reviews, regulatory tests and consultations. The main inputs to the joint planning process are: • Ausgrid supply point load forecasts; • Review of network capacity and utilisation; • Planning criteria and indicators; • Condition, operational and risk assessments; • TransGrid transmission network and Ausgrid supporting dual function network load flow analysis; and • TransGrid – Ausgrid network planning reviews. 8.1.2 Joint TransGrid - Ausgrid planning completed in 2018 8.1.2.1 Sydney Inner Metropolitan transmission load area Existing and future constraints on the Sydney Inner Metropolitan transmission network are centred on two critical areas: • Transmission supply into Beaconsfield BSP from Bulk Supply Points at the edge of the city, Sydney South, Sydney North, and Rookwood Rd BSP. This is known as Transmission Corridor 1 (‘TC1’). • Transmission supply into Haymarket BSP and surrounding Ausgrid 132kV zone substations from Sydney South BSP (Cable 42) and Ausgrid 132kV connections from Beaconsfield BSP and the meshed 132kV network. This is known as Transmission Corridor 2 (‘TC2’). Both transmission corridors operate as meshed systems of 330kV and 132kV circuits, with significant interdependencies between both corridors. Both have limitations due to the age and condition of existing circuits, including significant reduction in capacity of cables where in-situ conditions are not adequate to support design ratings. The Inner Metropolitan Area Joint Planning strategy must resolve issues on both corridors. During 2014, TransGrid and Ausgrid consulted widely on the Powering Sydney’s Future project, which was jointly formulated to address network needs for assets within transmission corridors TC1 and TC2. At the time, there were five key drivers behind the Powering Sydney’s Future project – namely: • the ‘modified N-2’ NSW transmission reliability standard in place at the time; • the age and reliability of TransGrid’s Cable 41; • the rating of Cable 41, which had been derated from 663 MVA to 575 MVA in 2011; • the rating and retirement of Ausgrid oil-filled cables; and • peak demand was forecast to increase. The Powering Sydney’s Future project has commenced the formal RIT-T process. Since 2014, a number changes to the key drivers has occurred, in particular: • all oil-filled cables in Inner Sydney are now two years older and consequently less reliable; • a further derating of Cable 41 from 575 MVA to 426 MVA in August 2016 as a result of testing the thermal resistivity of backfill and bedding materials; and

129

• an increase in summer peak demand in Inner Sydney in 2016 and a forecast increase in demand from heightened economic activity expected within Inner Sydney TransGrid and Ausgrid have considered a range of options and their ability to address the risk of supply disruption for consumers. Both network and non-network solutions have been considered as potential credible options for the RIT-T analysis – in particular: • a range of network options has been included in the RIT-T assessment • non-network option components have been incorporated into the assessment of all network options to potentially defer the timing of network investment. The preferred strategy for Powering Sydney’s Future to address the network needs was identified as the following: • A combination of non-network solutions to manage the risk of unserved energy before the network option can be commissioned • installing two 330 kV cables in two stages, with commissioning of the first cable in time for the 2022/23 summer • operating 330kV Cable 41 at 132 kV from 2022/23 • decommissioning Ausgrid’s cables in two stages. In April 2018, the Australian Energy Regulator (AER) made it’s final determination of Transgrid’s 2018-2023 regulatory submission, which included the Powering Sydney’s Future project. The final determination included full provision for the first stage of Powering Sydney’s Future as proposed in TransGrid’s revised regulatory submission. With completion of the RIT-T and funding approval, TransGrid and Ausgrid are now jointly developing the first stage of the Powering Sydney’s Future project. 8.1.2.2 Sydney Inner Metropolitan transmission load area (greater network) TransGrid have installed new GIS switchgear at Beaconsfield Bulk Supply Point and all of Ausgrid’s 132kV feeders except 9RT were transferred by the end of 2016. Following the further derating of Cable 41 in 2016, cable 9RT (Beaconsfield BSP to Peakhurst STS,) has been retained in service to provide contingency support pending completion of Stage 1 of Powering Sydney’s Future. It was cut over to the new Beaconsfield North GIS busbar in September 2017. In preparation for the 2014-2019 Regulatory Submission, Ausgrid reviewed the classification of Dual Function assets in line with the definitions in the National Electricity Rules. This resulted in changes to the classification of a number of Ausgrid assets, both from Distribution to Dual Function and from Dual Function to Distribution. Changes in classification may result in the need for upgraded wholesale metering at the new boundary points between the Dual Function and Distribution assets. A project for the installation of new wholesale metering points was created for both Sydney and Hunter sites where the wholesale metering boundary points have changed. This project is underway and expected to be completed in early 2019. TransGrid’s Sydney North 330/132kV Bulk Supply Point substation was commissioned in 1963. The substation is a major interconnection point in the TransGrid 330kV network and provides supplies to a number of Ausgrid substations including Mason Park and Lane Cove STSS. A condition assessment of the Sydney North Substation identified that the Secondary Systems require replacement. On TransGrid’s request, Ausgrid initiated a project to carry out the required protection and communication modification works on all affected Ausgrid feeders. Communication modifications and protection upgrades were coordinated with TransGrid’s program of works at Sydney North BSP. These works were completed in April 2018. TransGrid’s Sydney East 330/132kV Bulk Supply Point substation was commissioned in 1965. The substation is a major interconnection point in the TransGrid 330kV network and is the sole source of supply to Ausgrid’s substations in Sydney’s Northern Beaches and North Shore areas. One of the 330/132kV transformers at Sydney East Substation was recently replaced but the remaining three transformers are now approaching the end of their serviceable life. Joint planning in 2018 determined that two of the three older Sydney East transformers should be replaced and the third should be retired without replacement. TransGrid commenced the RIT-T process to replace these two transformers in late 2018. TransGrid and Ausgrid will review the need for a fourth transformer at Sydney East as part of the normal annual planning process. TransGrid’s Beaconsfield 330/132kV substation originally had three transformers. Transformer number 3 was installed in 2012. Transformers 1 and 2 were installed in 1979 and are now approaching the end of their useful life. Joint planning in 2015 determined that one of the two older Beaconsfield transformers should be replaced and the second should be retired without replacement. Since this joint planning there has been an increase in the demand forecast and a reduction in capacity of the 330kV cable supplying Beaconsfield. In 2018, a new standard was introduced for Electricity Transmission Reliability and Performance. TransGrid and Ausgrid are currently reviewing the need for a third transformer at Beaconsfield in light of the new transmission reliability standard and the expected implementation of the first stage of Powering Sydney’s Future.

130

8.1.2.3 Transmission load area – Central Coast No significant issues were identified on the Central Coast network. One generator connection enquiry in Vales Point for a 60MW solar farm connected to the 33kV network has progressed to a formal connection application. Network augmentation and detailed analysis of the generator connection will commence in 2019. The connection of this generator is expected to have some upstream flows to the Central Coast 132kV network. 8.1.2.4 Transmission load area – Lower Hunter The increase in rooftop photovoltaic (PV) solar installations in the Hunter area over the past 10 years has resulted in an increase to the voltage level on the LV network. The continued increase in voltage levels can no longer be managed by transformer taps on the 11kV distribution network and zone substation transformers. An investigation found that upstream voltage levels on the subtransmission network also remained quite high as transformers at subtransmission substations did not have an adequate tapping range to achieve the required voltage levels on the 33kV network. After implementing easily available options (with minimal expenditure) within the Ausgrid network, the investigation also concluded a reduction to the voltage level at a number of Hunter transmission connection points was also required. TransGrid is currently reviewing the scope of works required to change voltage levels at three BSPs (Newcastle, Tomago and Waratah West) and a project will be initiated in 2019. No other significant issues were identified in the Lower Hunter transmission network. Ausgrid has received numerous enquiries for large generator connections (generally more than 30MW) in the Lower Hunter area. Only three enquiries have progressed to a formal application and they are in various stages of detailed analysis. The connection of these generators may result in upstream flows to the 132kV network in the Lower Hunter area. Ausgrid has received enquiries from the new owner of the Redbank generator to reconnect to the 132kV network (it was disconnected in 2014). The most recent enquiry was in December 2018 and has not proceeded into a formal connection application but customer negotiations remain ongoing.

8.1.3 Planned joint TransGrid-Ausgrid network investments Planned future network investments, excluding committed projects, discussed at TransGrid - Ausgrid joint planning meetings in the preceding year include: • Planning discussions including identified needs reviews and on-going feasibility studies to review and refine a range of supply options for the Inner Sydney Metropolitan transmission load area. This will include approaches to meet any supply shortfall before the commissioning of the first stage of the Powering Sydney’s Future Project. 8.1.4 Additional information Further information on TransGrid and Ausgrid’s completed joint planning and joint network investment can be found in TransGrid’s Transmission Annual Planning Report. It is published on their website as well as AEMO’s website.

131

8.2 Joint planning with other DNSPs Ausgrid follows the same principles when joint planning with Endeavour Energy, Essential Energy and Sydney Trains. However due to the limited number of network dependencies between the organisations, joint planning meetings may only take place once per year, or less, unless a particular issue has been identified and needs to be progressed and monitored. 8.2.1 Process and methodology Joint planning meetings with Endeavour Energy and Essential Energy are arranged on a needs basis, and generally there are not more than two meetings in any year. The joint planning process and methodology is similar to the joint planning process between Ausgrid and TransGrid. A formalised joint planning arrangement is also in place with Sydney Trains. Joint planning meetings may be initiated by any party to discuss planning issues, identified network needs and proposed solutions near adjoining network boundaries that are likely to affect either party. The joint planning meetings are also the forum used to discuss proposed changes on the network that may have a material impact on either DNSPs network. 8.2.2 Joint Ausgrid and other DNSP planning completed in preceding year A joint planning meeting with Essential Energy was held this year in October. The meeting confirmed that no changes are required to the connection points between the two networks. Essential Energy will continue to review the demand growth at Clarencetown and Seaham areas, which may result in a requirement to increase the capacity of one 11kV connection supplied by Ausgrid. Ausgrid had no need to carry out joint planning with Endeavour Energy this year. However, there were regular project meetings with Endeavour Energy in relation to the planned supply of Auburn and Lidcombe zone substations from Endeavour Energy’s Camellia Transmission Substation. There are no other identified network issues that affect either Endeavour Energy or Ausgrid. Quarterly planning meetings were held with Sydney Trains, with ongoing regular meetings planned to ensure that the electrical network can cater for increased power requirements of new trains and timetables. 8.2.3 Planned DNSP joint network investments There is currently a project to supply Auburn and Lidcombe zone substations from Endeavour Energy’s Camellia Transmission Substation. There were no jointly planned network investments with Essential Energy or Sydney Trains in the preceding year. 8.2.4 Additional information Information on completed Ausgrid and other DNSP joint planning and joint network investments may be found in Ausgrid Distribution and Transmission Annual Planning Reports published on our website. Where a proposed future DNSP joint planning project satisfies the requirements for a RIT-D project, the identification of non- network options, the consultation on potential credible options and their economic assessment will be published in accordance with the NER.

132

9 Network performance

9.1 Reliability measures and standards Ausgrid’s objective is to maintain reliability performance at current levels and comply with regulatory requirements at minimum cost, given the condition and utilisation of existing network assets and the funding available to maintain and augment the electricity network.

Under the NSW Reliability and Performance (R&P) Licence Conditions for Electricity Distributors6 Ausgrid is required to comply with specific targets for reliability standards and individual feeder standards. The purpose of the licence conditions is to facilitate the delivery of a safe and reliable supply of electricity. Ausgrid is required to report to the Minister to ensure compliance with the R&P licence conditions. Under the National Electricity Rules (NER), and the Service Target Performance Incentive Scheme (STPIS), Ausgrid is given financial incentives to improve the customer’s reliability performance compared to historic outcomes over time (as well as penalties if the performance level deteriorates). Reliability measures used are SAIDI (System Average Interruption Duration Index), or minutes off supply for the average customer, and SAIFI (System Average Interruption Frequency Index), or number of interruptions experienced by the average customer. The reliability performance is monitored at distribution feeder level for unplanned interruptions (excluding major event days, planned interruptions and circumstances beyond the reasonable control of the electricity distributor). The distribution feeders are categorised as CBD (Sydney city), Urban, Short Rural and Long Rural based on feeder length and load density. Ausgrid distribution network consists of 59 CBD feeders, 1936 Urban feeders, 372 Short Rural feeders and 6 Long Rural feeders. Over 84% of Ausgrid’s customers are connected to Urban feeders. Our customers must plan around the possibility that the electricity supply may not always be available and that interruptions could occur without notice, or with notice in accordance with their supply contract. 9.1.1 Supply reliability standards 9.1.1.1 Average feeder category reliability standards The purpose of the R&P licence condition Schedule 2 – “Network Overall Reliability Standards” is to: • define minimum average reliability performance, by feeder type, for a distribution network service provider across its distribution network, and • provide a basis against which a distribution network service provider’s reliability performance can be assessed.

Average Reliability duration standards

CBD Urban Short Rural Long Rural SAIDI 45 80 300 700 SAIFI 0.30 1.20 3.20 6.00

9.1.1.2 Individual feeder standards The purpose of the R&P licence condition Schedule 3 – “Individual Feeder Standards” is to: • specify minimum standards of reliability performance for individual feeders; • require a distribution network service provider to focus continually on improving the reliability of its feeders, and • enable the reliability performance of feeders to be monitored over time.

6 The Minister for Energy established licence conditions for distribution network service providers on 1 August 2005 (revised December 2007, July 2014,for the Ausgrid Operator Partnership (“Ausgrid”) on 1 December 2016, and for the operator of a transacted business on 4 December 2017). See: Annexure B and https://www.ipart.nsw.gov.au/Home/Industries/Energy/Energy-Networks-Safety-Reliability-and-Compliance/Electricity- networks/Licence-Conditions-and-Regulatory-Instruments

133

Individual feeder standards

CBD Urban Short Rural Long Rural SAIDI 100 350 1000 1400 SAIFI 1.4 4 8 10

9.1.2 Network Supply reliability performance in the preceding year 9.1.2.1 SAIDI and SAIFI Performance The following graphs depict the normalised (i.e. Major Event Days data excluded) SAIDI and SAIFI trends over the 9-year period 2010/11 to 2018/19: AER normalised SAIDI 120

100 98

80 82 77 76 79 72 75 68 69 60

40 OrganisationalSAIDI 20

0 2010/11 2011/12 2012/13 2013/14 2014/15 2015/16 2016/17 2017/18 2018/19

Figure 9.1: Global unplanned SAIDI AER normalised SAIFI 1.2 1.09 1.0 0.91 0.8 0.83 0.73 0.70 0.71 0.68 0.68 0.66 0.6

0.4 OrganisationalSAIFI 0.2

0.0 2010/11 2011/12 2012/13 2013/14 2014/15 2015/16 2016/17 2017/18 2018/19

Figure 9.2: Global unplanned SAIFI

134

9.1.2.2 Major Event Days Ausgrid uses the methodology described in IEEE 1366 standard for defining Major Event Days, as outlined in the R&P licence conditions and AER STPIS Definitions. There were nine Major Event Days for 2018/19:

Date Excluded SAIDI Cause of Major Event Day 20 October 2018 3.89 Major storm

15 December 2018 28.45 Major storm

16 December 2018 3.07 Major storm

20 December 2018 5.83 Major storm

5 January 2019 3.25 Major storm

31 January 2019 3.52 Major storm and Sub Transmission fault

13 February 2019 13.02 Asset Fire

14 March 2019 6.36 Major storm

19 March 2019 3.22 STS TX Fail

9.1.2.3 Individual Feeder Reliability Performance As required under the R&P Licence Conditions for Ausgrid, each feeder currently exceeding the Individual Feeder Standard is analysed and an investigation report identifying the causes and, as appropriate, any action required to improve the poor performance is reported in the next quarterly performance report. The majority of feeder exceedances were determined to be random events and action was limited to monitoring ongoing reliability performance. A small number of feeders required remedial actions such as vegetation management and repairs to network assets or minor capital works. All actions required were completed in the timeframes required. Ausgrid has an ongoing reliability management program that targets those feeders that have exceeded the Individual Feeder Standards as outlined in Schedule 3 of the R&P Licence Conditions. The individual feeder performance against the standard is given in the table below.

Individual feeder performance against the standard during 2018/19

CBD Urban Short Rural Long Rural

Feeders (Total Number) 59 1,936 372 6

Feeders that Exceeded the Standard 5 63 9 0 during the Year

Feeders Not Immediately Investigated 0 0 0 0

Feeders Not Subject to a Completed 0 0 0 0 investigation report by the Due Date Feeder Not having Identified Operational Actions Completed by 0 0 0 0 Due Date Feeders Not having a Project Plan 0 0 0 0 Completed by Due Date

135

9.1.2.4 Feeder Categories Reliability Performance All feeder category performances were compliant against the NSW R&P Reliability Standards for 2018/19. Whole Organisation and Feeder Category reliability performance

12-month period to end of June 2019

ORG* CBD Urban Rural short Rural long

Actual 74.69 24.86 65.84 131.71 465.90 SAIDI Licence Conditions 45 80 300 700 standard Actual 0.66 0.11 0.60 1.04 2.22 SAIFI Licence Conditions 0.30 1.20 3.20 6.00 standard Note: * Refers to the average performance of the organisation overall. This measure does not form part of the licence conditions but is needed to calculate the overall NSW result.

9.1.3 Service Target Performance Incentive Scheme (STPIS) The Australian Energy Regulator's (AER) distribution Service Target Performance Incentive Scheme (STPIS) provides a financial incentive for Ausgrid to maintain or improve its reliability and customer service performance over time. As part of the AER final determination for Ausgrid, the AER set elements of the STPIS for the 2015/16 – 2018/19 period including at-risk revenue caps, reliability targets, and customer service targets. The revenue at risk for each regulatory year is capped at 2.5 per cent with a 2.25 per cent cap for the reliability of supply component and 0.25 per cent cap for the customer service component. The SAIDI and SAIFI targets set by the AER in their final determination for each feeder category for the reliability component of the STPIS are set out in the tables below7.

STPIS results – Unplanned SAIDI Targets vs Actuals 2017/18 2018/19 Target Actual Target Actual CBD 16.58 12.68 16.58 24.68 Urban 62.41 64.24 62.41 65.84 Short Rural 157.28 114.03 157.28 131.71 Long Rural 436.53 353.56 436.53 465.90

STPIS results – Unplanned SAIFI Targets vs Actuals 2017/18 2018/19 Target Actual Target Actual CBD 0.054 0.064 0.054 0.11 Urban 0.674 0.647 0.674 0.60 Short Rural 1.426 0.982 1.426 1.04 Long Rural 3.099 1.597 3.099 2.22

7 Table extracted from the AER’s Final Decision Ausgrid Determination 2014-15 to 2018-19 Attachment 11 – Service Target Performance Incentive Scheme.

136

9.1.4 Forecast of network reliability performance Ausgrid’s Reliability Forecasting System (RFS) forecasts the reliability performance of each feeder category based on 5 years of historical performance and looking forward considers the impact of the following: • The aggregate performance change due to past and proposed investments • The aggregate performance reduction due to the general ageing of network assets and changes in demand.

SAIDI 2019/20

System 74 CBD 14 Urban 65 Short Rural 130 Long Rural 519 (Average minutes of supply interruption per customer per year)

SAIFI 2019/20

System 0.69 CBD 0.06 Urban 0.62 Short Rural 1.15 Long Rural 2.61 (Average number of network interruptions per customer per year)

Where a shortfall in reliability is identified for feeder category performance, improvement methods may include: • improvements of individual feeder performance - affecting a sufficient number of individual feeders to influence the category average, or • Improvements at a subtransmission level, or • Improvements with wide spread impacts such as operating policy and its implementation, SCADA systems, and the development of intelligent network options. Project proposals within these three categories are short-listed and the anticipated cost benefit of each option is estimated. The cost estimates are based on standard unit costs and adjusted to reflect, to the extent practicable, the realities of implementing the solution. 9.1.5 Compliance with network reliability standards Ausgrid monitors feeder outages and records the duration of outage events into the Outage Management System (OMS). For reliability reporting purposes, the network performance is measured at the 11kV distribution level. Excluding any excluded events, including planned interruptions and Major Event Days, the recorded outage information provides Ausgrid with the frequency and duration of feeder outages that are used to determine the SAIDI and SAIFI of individual feeders. In turn these individual feeders are grouped into categories, to enable an average SAIDI and SAIFI to be determined for each feeder category (CBD, Urban, Short Rural and Long Rural). Every quarter Ausgrid submits a report stating the business performance against the overall Reliability, Individual Feeder and Customer Service Standards to IPART and the Minister administering the Electricity Supply Act 1995 within one month of the end of each quarter. The report lists performance against the pro-rata SAIDI and SAIFI average standards, along with any reasons for non-compliance and Ausgrid’s plans to improve the feeder performance. Similarly, the Individual Feeder document details the date at which a feeder first exceeded the relevant Individual feeder standard and the SAIDI and SAIFI performance for that 12 month period, including details of the remedial action to be taken to improve performance, and the planned date of completion for the action plan. Typical remedial action plans include either operational and/or capital expenditure, or alternatively there is the option of a non-network solution.

137

Operational work may include works like vegetation maintenance or retro-fitting of animal proofing on electrical mains and apparatus. Any identified and reported operational work is due to be completed by the end of the third quarter following the feeder first exceeding the individual feeder standards. Capital expenditure to improve feeder reliability can be in the form of a network augmentation project involving feeder reclosers or covered overhead mains to prevent or correct some known outage triggers. Any required capital work is to be developed, planned and commenced by the end of the second quarter following the feeder first exceeding the individual feeder standards. Some investigations find that a feeder outage occurred due to a one-off event that is not likely to occur again. Non-network solutions may include energy storage systems to provide ride-through capability during outages. 9.2 Quality of supply standards Ausgrid’s objective is to achieve the best possible overall supply quality of our electricity network, given the condition and utilisation of existing network assets, within the funding available to maintain and augment the electricity network. The NSW Code of Practice - Electricity Service Standards8 provides a framework for supplying electricity to customers on the Distribution Network. Ausgrid’s network standard NS 238 Supply Quality9 sets out Ausgrid’s standards for Quality of Supply which customers can expect from Ausgrid’s network. Ausgrid does not control the frequency on the electricity supplied through its electricity network, as this standard is set during the process. The Australian Energy Market Operator (AEMO) establishes standards and regulates the frequency of supply on the national grid. 9.2.1 Voltage range for supplied electricity Supply voltage is the voltage, from phase to neutral or phase to phase, for electricity that is supplied at a customer’s point of supply. Maintaining this steady state supply voltage is important to ensure appropriately designed equipment does not malfunction and is not damaged. When Ausgrid identifies or is notified that the steady state supply voltage is outside the specified target range, Ausgrid will take reasonable steps to modify the network to ensure that the voltage will be maintained at the required level and achieve Ausgrid’s steady state voltage supply objective. 9.2.1.1 Low voltage network Ausgrid’s objective for the operation of its network is to maintain a target steady state phase to neutral supply voltage (measured as a ten-minute average) within the range of 216V to 253V at customers’ points of supply under normal operating conditions. This range is the nominal voltage range of 230V as defined in the relevant Australian Standard AS 61000.3.100, with a tolerance of +10%/- 6% to allow for voltage regulation on the mains th between distribution substations and customers’ points of supply. The 99 percentile (V99%) of the 10 minute st average voltage readings for a 1 week survey should be less than 253V and the 1 percentile (V1%) should be greater than 216V. 9.2.1.2 High voltage network Ausgrid’s high voltage distribution network operates at several voltage ranges. Accordingly, high voltage customers must obtain from Ausgrid the network operating objective for supply voltage applicable to their location, particularly before proceeding with any project expenditure or commitments. 9.2.1.3 Applicable quality of supply codes, standards and guidelines Ausgrid relies on the following standards and/or guidelines when setting and assessing network voltage performance: • Network Standard: NS 238 Supply Quality • Australian Standards: AS/NZS 60038 and AS 61000.3.100 • NER S5.1a.4 – Power Frequency Voltage • NSW Service and Installation Rules (SIR): Section 1.10.1 refers to AS/NZS 600038 & AS 61000.3.100. 9.2.2 Harmonics and total harmonic distortion Voltage waveform distortion including harmonic distortion results from the operation of appliances or equipment that draw non-sinusoidal currents from the network. Harmonic distortion can cause the supply voltage to depart from a sine wave in a repetitive manner. Maintaining waveform distortion within acceptable limits is important because it can otherwise cause interference and damage to sensitive customer and network equipment. This

8http://www.resourcesandenergy.nsw.gov.au/energy-supply-industry/pipelines-electricity-gas-networks/network- connections/electricity_connect_code_of_practice_electricity_service_standards.pdf

9http://www.ausgrid.com.au/Common/Our-network/Standards-and- Guidelines/~/media/Files/Network/Documents/NS%20and%20NUS/NS238.pdf

138

form of distortion can also cause light flicker, incorrect operation of ripple control devices (used for off peak electric hot water) and computers, audible noise in television, radio and audio equipment and vibration in induction motors. 9.2.2.1 Applicable quality of supply codes, standards and guidelines Ausgrid relies on the following standards and/or guidelines when limiting and assessing harmonic performance: • Network Standard: NS 238 Supply Quality • Australian Standards: TR IEC 61000.3.6:2012, AS 61000.2.2:2003, AS 61000.2.12:2003, SA/SNZ TR IEC 61000.3.14:2013 • Standards Australia handbook for power quality HB264 • NER S5.1a.6 – Voltage Waveform Distortion • NSW Service and Installation Rules (SIR): Section 1.16.2.1 (b) refers to AS/NZS 61000.3.2, 61000.3.4, 61000.3.12. 9.2.3 Voltage fluctuations (Flicker) – Applicable quality of supply codes, standards and guidelines Ausgrid relies on the following standards and/or guidelines when limiting and assessing Voltage fluctuations performance: • Network Standard: NS 238 Supply Quality • Australian Standards: TR IEC 61000.3.7:2012, AS 61000.2.2:2003, AS 61000.2.12:2003, SA/SNZ TR IEC 61000.3.14:2013 • NER S5.1a.5 – Voltage Fluctuations • NSW Service and Installation Rules (SIR): Section 1.16.2.1 (b) refers to AS/NZS 61000.3.3, 61000.3.5, 61000.3.11. 9.2.4 Voltage unbalance – Applicable quality of supply codes, standards and guidelines Ausgrid relies on the following standards and/or guidelines when limiting and assessing Voltage Unbalance performance: • Network Standard: NS 238 Supply Quality • Australian Standards: TR IEC 61000.3.13:2012, AS 61000.2.2, AS 61000.2.12, SA/SNZ TR IEC 61000.3.14:2013 • NER S5.1a.7 – Voltage Unbalance. 9.3 Quality of supply performance for preceding year At Ausgrid, monitoring for supply quality is undertaken by a number of means including review of customer complaints files, permanent monitoring at a selection of sites across the network at different voltage levels, undertaking survey of distribution substation voltages, installation of temporary meters at customer premises to investigate supply quality complaints, and participation in the Long Term National Power Quality Survey (LTNPQS) conducted by the University of . 9.3.1 Supply voltage performance Voltage is measured to AS 61000.3.100. Distribution substations with Voltage monitoring showed 98.9% of sites met the V1% limit and 92.9% of sites met the V99% limit. The high V99% figure is a consequence of the network being historically designed for a nominal 240V range. As stated in the next section 9.4 (Corrective Action) Ausgrid is currently undertaking a 230V migration program to further manage this. In recent years, the high penetration of solar generation has resulted in localised high voltage issues generally observed by customers experiencing loss of energy exports due to inverter behaviour as prescribed under AS/NZS 4777. These are investigated when reported by customers and in the majority of cases are resolved by either changing the Power Quality response modes of the customer’s inverter(s) as specified in AS/NZS 4777 or by way of ‘tap changes’ on the customer’s supplying transformer. 9.3.2 Harmonic content of supply voltage waveform There were four complaints registered for harmonic issues. Three were related to light flicker caused by Ripple Control signals on the network and one by a timber processing plant (which was investigated but all harmonics were within the limits set by the Australian standards).

139

9.3.3 Voltage fluctuations (Flicker) performance There were 37 complaints registered as being about flicker or fluctuations. None were confirmed to be flicker or fluctuations within the definition of TR IEC 61000.3.7 standard. • 6 were identified as Solar Inverter issues (resolution was generally by either changing inverter settings or by carrying out a transformer tap change). • 2 were reclassified as voltage unbalance (see section 9.3.4) • 9 were identified as no fault found or other network cause. • 17 were related to light flicker caused by Ripple Control signals on the network. • 1 was building site using cranes with high inrush current on startup. • 2 were still under investigation at time of this report. 9.3.4 Voltage unbalance performance There were 8 complaints registered as being unbalance plus 2 more originally classified as flicker. Of these 4 had phase voltages that indicated unbalance above 3%. The remainder were not confirmed as voltage unbalance. 9.4 Corrective action planned to meet quality of supply standards 9.4.1 Supply voltage Measurements on the LV network indicate that a number of sites exceed the V99% and V1% values when measured to AS 61000.3.100. Generally where a site is under the V1% limit, and the cause is determined to be a consequence of the local network conditions, Ausgrid will attempt to carry out remediation to maintain the correct voltage. With regards to the V99% limits, under the 230 Volt migration program Ausgrid is currently undertaking the following activities to lower the LV across the network and deliver network functional compliance: • Lowering of the Zone substation 11kV float voltages • Change of Distribution transformer tap settings to deliver the correct 99th percentile voltage (to AS 61000.3.100). Tap setting changes are carried out in conjunction with other maintenance works to constrain costs to the community. Tap setting changes will be carried out earlier in the case of customer complaints that are identified to be due to higher voltages at the Distribution transformers (for example where a customer has installed a PV Solar system that is limiting export due to AS/NZS 24777 settings). 9.4.2 Flicker, Harmonics and Unbalance Ausgrid monitors customer complaints and resolves any supply quality issues as they arise.

9.5 Compliance with quality of supply standards Under the Standard Form Customer Connection Contract with Ausgrid, our low voltage network customers are required to comply with the requirements of the Service and Installation Rules of NSW and any other reasonable Ausgrid requirements. Consistent with those Rules and our rights under the Contract, Ausgrid requires our customers to ensure that: • their electrical installation does not adversely affect Ausgrid’s network or other customers’ installations, and • that any audible or electronic noise generated by their electrical installation does not breach relevant laws or adversely affect others. If disturbances on the network are caused by more than one customer, Ausgrid will establish overall limits for the interference by each customer, and customers who exceed their limits are required to rectify the situation. Ausgrid’s network modelling process includes checks for voltage compliance on the high voltage network and our internal standards specify compliance requirements for low voltage. Customer quality of supply complaints are reviewed and corrective action taken as necessary. The process for managing supply quality emission limits for major customer connections is generally dictated by the National Electricity Rules (NER) requirements for connection agreements. Ausgrid is required to provide a 20 day turnaround on responses to connection enquiries under the NER. Limits for automatic and minimum access standards for supply quality are included in Ausgrid’s response to the connection enquiries. There are different rules which apply to network customers and registered generators. However, generally the allocation of emission limits for customers and generators are defined in NER clauses S5.1.5-5.1.7. Supply quality requirements for connections are based around the following access standards: • Automatic Access Standards

140

• Minimum Access Standards • Negotiated Access Standards.

For Generators allocation limits are defined according to NER Clauses S5.2.5.2. For network customers allocation limits are defined according to NER Clauses S5.3.7 and S5.3.8. For both generators and customers, harmonic and flicker allocations are based on the AS/NZS61000.3 series of documents. For voltage unbalance the proposed approach within Ausgrid is to follow (SA/SNZ) TR IEC61000.3.13:2012, which mirrors the Stages 1-3 approach of the harmonic and flicker standards. The process for achieving compliance with the prescribed supply quality allocation limits is likely to be an iterative process, with consideration given to alternative connection points, or mitigation measures, should initial investigations indicate non-compliance. Where necessary this may involve a reassessment of limits, or the acceptance of a negotiated access. Suitable clauses are included in Ausgrid’s connection agreements to ensure compliance with the supply quality allocation limit via agreed levels of monitoring of the installation, and also for appropriate notification and approval of customers’ planned major equipment changes, such as new distorting loads or power factor correction. It should be noted that the NER provides scope for Ausgrid to subsequently enforce automatic access standards where network conditions change.

141

10 Asset management

10.1 Ausgrid’s asset management approach Ausgrid’s vision is to be a leading energy solutions provider, both locally and globally. In providing services to our customers, we manage, operate and maintain a widespread electrical network that consists of a large variety of assets. We manage the assets across our network using a systematic risk based, whole of life approach to ensure that the services that we provide are safe, reliable and efficient and meet the needs of our customers and stakeholders. This approach also ensures we deliver and align with the National Electricity Objective and our regulatory and legal requirements, in particular obligations under the WHS Act 2011 and associated regulations, the Electricity Supply (Safety and Network Management) Regulation 2014 (NSW), the National Electricity Law (NEL) and the Electricity Supply Act 1995 (NSW). Our asset management system leverages the capabilities, policies and standards that have been developed over the last fifteen years, in combination with the current state of the network, the increasing availability of network information, and the changes in context of the external operating environment. It is underpinned by a framework that ensures alignment from the leadership, management and culture of the organisation through to the achievement of the asset management objectives. This is achieved through fit for purpose systems and processes, and a clear framework of governance and assurance. Sound and efficient asset management processes and methods have further enabled Ausgrid to transparently demonstrate to industry regulators the prudence and efficiency of our expenditure as it relates to specific assets. Our asset management system, including the strategies, models and processes adopted by Ausgrid, has been certified to conform with the requirements of AS ISO 55001:2014 Asset Management – Management Systems – Requirements in accordance with our Distribution Licence Conditions. 10.2 Risk management strategies Risk management techniques to manage the identified business risks are maintained in accordance with a Risk Management Board Policy and Ausgrid’s Risk Management framework, which is consistent with AS/NZS ISO 31000-2018 Risk Management – Principles and Guidelines. Risk management associated with the various asset classes is underpinned by Ausgrid's asset management system. Assets carry risk and opportunity through all stages of their lifecycle. Ausgrid’s asset management approach utilises risk management techniques that eliminate safety risks so far as is reasonably practicable (SFAIRP) and where it is not reasonably practicable to eliminate the risk, Ausgrid manages those risks on an ongoing basis to ensure the risk remains minimised SFAIRP. Ausgrid’s risk assessment techniques identify hazards and, and when it is not reasonably practicable to eliminate the hazard, then develop controls to minimise those hazards and their outcomes SFAIRP. The result is a risk-based system to safely manage the electricity network. Ausgrid undertakes Failure Mode Effects and Criticality Analysis (FMECA) which is a structured method for identify potential failure modes, their causes and effects on system performance. The identified failure modes are then assessed for their consequences and frequency to obtain a criticality which can be ranked to prioritise mitigating measures. In addition, an initial determination is proposed for an applicable mitigating action (e.g. preventive maintenance task, re-design, renewal) to manage the failure mode to minimise risk SFAIRP. In determining preventative maintenance requirements, Ausgrid undertakes Maintenance Requirements Analysis (MRA) utilising FMECA / Reliability Centred Maintenance (RCM) to determine effective maintenance tasks and optimal intervals. The outputs from the MRA process form Ausgrid’s Technical Maintenance Plans (TMP). Condition Based Maintenance (CBM) is undertaken to understand asset residual risk. Where conditional issues present an unacceptable risk based on Ausgrid’s risk appetite, corrective action such as repair or renewal may be carried out. Where the residual risk cannot be effectively and efficiently mitigated within Ausgrid’s risk appetite, the asset is considered for re-design. At all times Ausgrid manages those risks on an ongoing basis to ensure the risk remains minimised SFAIRP. Rectification of defects are prioritised and assigned a rectification timeframe depending on the risk likelihood of failure and the potential consequence. Ausgrid has developed methods to inform when to replace assets such as poles, cables and substation equipment using Cost-Benefit Analysis (CBA). Determining when to replace network assets is a complex task because replacing assets too early results in customers bearing costs earlier than necessary, whereas waiting too long to replace assets results in increased asset failures. This can result in economic costs such as loss of supply, potential safety impacts and damage to property and the environment. An overview of significant asset class replacement strategy is outlined in the below sections:

142

10.2.1 Subtransmission underground cable strategy Ausgrid’s subtransmission cables are in continuous use and are an essential part of our supply network. Ausgrid has approximately 1,150km of subtransmission cables with the majority operating at either 33kV or 132kV and a small number at 66kV.These assets cannot routinely be taken out of service except for brief periods necessitated by the need for maintenance and repair, particularly those which operate at 132kV supplying the inner metropolitan area of Sydney. There are four cable technology types used for these cables – these are listed below (from oldest to youngest type): • 254km of Paper insulated, lead covered (‘paper lead’) cables • 71km of Gas pressure cables • 285km of Self contained fluid filled (‘SCFF’) cables • 541km of Cross-linked polyethylene (‘XLPE’) cables Approximately 51% (588km) of Ausgrid subtransmission cables operate at 132kV and many of these form the critical backbone of the subtransmission network. Failure of multiple 132kV cables can have significant impacts upon our customers, particularly in the Sydney CBD and surrounding urban areas. Ausgrid has developed an asset failure probability model for SCFF cables which is used as an input into the organisation’s probabilistic area planning approach to determine the optimal timeframe for cable retirement or replacement. SCFF cables mostly operate at 132kV however there are smaller lengths which operate at 33kV. Due to the environmental risks posed by these cables, Ausgrid consults with the Environmental Protection Agency (EPA) in order to take reasonable steps and exercise due diligence with regard to management of the environmental risk. The asset failure probability model takes into consideration: • The unavailability of individual SCFF cables • Defect related performance of individual SCFF cables primarily based on their level of fluid leakage over 5 years and the condition of the cable serving • Defect repair time • The environmental risk from individual cables, in particular those crossing major waterways Gas pressure cables equate to approximately 6% of Ausgrid subtransmission cables and they all operate at 33kV. Ausgrid has identified these cables are reaching end of life due to degradation of the cable system which has resulted in increasing gas leakage rates as well as failure of mechanically fatigued joints. Ausgrid is generally now targeting retirement of all remaining gas pressure cables in the next 10-15 years, with the optimal timeframe for cable retirement determined under our probabilistic planning approach. This may result in short term deferral of the retirement of some cables. Ausgrid also has a substantial population of paper lead cables which all operate at 33kV. These cables formed the backbone of the subtransmission network at its inception and remain relatively reliable despite their age, with some sections up to 90 years old. The lifespan of these cables is generally considered to be approximately 80 years, however individual circuits may be retired prior to reaching this age based on condition (issues related to corrosion of the lead sheath or loss of resistance in the paper insulation) or circuit reconfiguration due to other work. XLPE cables are the current technology being installed for 33kV, 66kV and 132kV circuits. Ausgrid has been utilising this cable technology for approximately 20 years and is expecting a 60 year operating life from them. 10.2.2 11kV switchgear strategy Between the late 1930s and the early 1970s Ausgrid progressively installed a large number of compound insulated 11kV switchboards with bulk oil circuit breakers (OCB). As technology progressed, air insulated switchboards (non-internal arc classified technology) with bulk oil circuit breakers (OCBs) became widely available, and were installed from the late 1960s until the late 1970s, when vacuum circuit breakers (VCB) were introduced. From 2004, internal arc classified switchgear became the accepted industry standard for new installations. This progression of technology has resulted in a corresponding reduction in the risk of catastrophic failure (both likelihood and consequence). This reduction in risk was traded off against a larger construction footprint in a typical urban style Zone Substation. In rural and lower loaded areas, outdoor 11kV switchgear (cubicle or recloser style) has generally been used as this is a more economical design than indoor switchgear in those areas. However due to the increased exposure to local environmental conditions, this type of switchgear has deteriorated over time, leading to more frequent failures and higher maintenance costs.

143

Ausgrid has in place a program for the retirement for poor condition and high risk 11kV switchgear. Due to the age and condition issues associated with 11kV compound switchboards, switchboards using this technology are approaching end of life. An end of life forecasting model is used to provide failure rate forecasts as an input into network planning and capital budgeting processes. It is understood that switchboards experience age related wear out mechanisms leading to various failure modes. For the purposes of developing a population failure forecasting model only failures resulting in a replacement (i.e. end of life failure) of an individual switchboard panel have been considered. The Weibull distribution was used as it was deemed the most appropriate to provide the best fit to the population failure (i.e. life) data. To validate the outputs of the model a subject matter expert review of each switchboard was completed to give an estimated recommended remaining life. Switchgear risks are considered in conjunction with other planning needs and cost / benefit analysis to determine the optimal replacement timeframes. Oil filled circuit breakers pose an additional risk to safety, reliability and secondary asset damage due to the catastrophic nature in which they can fail. To mitigate this risk and defer retirement of older style air insulated switchboards, Ausgrid has a program to replace the remaining 11kV oil filled circuit breakers in zone substations with vacuum equivalents (VCBs) where practical. 10.3 Distribution network losses Distribution network losses refer to the difference in energy obtained from the transmission network to that supplied to customers. Ausgrid’s distribution network losses as a percentage of total energy for the 2017/18 financial year was 3.74%10. Electrical energy losses represent a cost to those who produce, consume and transport electricity and therefore it is Ausgrid’s objective to minimise these losses, while maintaining a safe and reliable electricity supply, at minimum cost to the community. When considering potential network projects under the NER’s Regulatory Investment Test for Distribution, Ausgrid must consider changes in electrical energy losses if they are material or may alter the selection of a preferred investment option. Ausgrid’s methodology for calculating losses is published on its website as part of the requirements of the NER to maintain a method for calculating Distribution Loss Factors (DLFs). This methodology is based on a report from consultants Evans & Peck entitled “Ausgrid – Evaluation of Losses in Project Evaluation” . The aim of this methodology is to enable the quantification of incremental values of network loss savings in the assessment of proposed network project options, and the quantification of network losses as required under the RIT-D. Ausgrid’s technical specifications for the assessment of losses for primary plant such as subtransmission transformers, distribution transformers, shunt reactors etc, specify the method of assessing capitalised losses when comparing tender offers from suppliers. 10.4 Obtaining further information on asset management Further information on asset management may be obtained from Ausgrid’s Asset Management Policy (available on request from the General Manger Asset Management) and Electricity Network Safety Management System (ENSMS) Annual Performance Report available on the Ausgrid website.

10 The distribution network losses are reported at the end of each calendar year, using the previous financial year’s accumulated loss data.

144

11 Demand management

11.1 Demand management When Ausgrid identifies a network limitation, non-network options are considered as an alternative to the preferred network option. The implementation of a non-network alternative is commonly referred to as demand management in that the solution has historically involved the reduction or modification of customer demand for grid supplied electricity. With rapidly developing alternatives such as advanced solar and battery inverter control, demand management solutions can now include support for voltage unbalance, power factor and harmonics management. Demand management is an important part of efficient and sustainable network operations; and can help address a network need due to rising customer demand, aging network assets, voltage unbalance or other investment driver. Effective use of demand management reduces the cost to maintain the network and results in lower electricity bills for all customers. There are a range of demand management or non-network solutions available for use by electricity networks. Examples include: • Energy efficiency (e.g. replacing lights with more efficient, lower wattage options); • Demand response (e.g. operating appliances at lower power demand for short periods such as air conditioner load control); • Operation of embedded generators (including renewable generators); • Energy storage (e.g. batteries); • Power factor correction (a form of energy efficiency); • Load shifting (shifting equipment use from peak to non-peak periods such as off-peak hot water); • Converting the appliance energy source from electricity to an alternative (e.g. switching from electric to gas heating); and • Voltage management (e.g. operation of customer inverters in voltage support modes).

When a review of a network limitation is initiated, a review of options that includes both network and non-network options is completed. The goal is to identify the solution which offers the highest net benefit and meets the required reliability standards. The solution may be: • Modifications or additions to the existing network (i.e. network solution); and/or • Support of the existing network by others (i.e. non-network or demand management solution).

Ausgrid’s planning process assesses network needs across 28 different network areas. Solution options are developed by area for all known network needs to allow for comprehensive solutions to address multiple needs. To ensure a thorough investigation, Ausgrid consults with the community on larger projects about the network requirements and the potential non-network options available. To determine the right balance, we apply the process depicted in Figure 11.1. For projects where the preferred network option cost is greater than $6 million, the Regulatory Investment Test for Distribution (RIT-D) process is followed. The orange boxes denote the reports which are published as part of the RIT-D process. For projects where the preferred network option cost is less than $6 million, Ausgrid applies a similar but simplified process appropriate to the cost of the project. The RIT-D process is a cost-benefit test that must be applied to all network investment projects where the most expensive credible option costs more than $5 million. It must be applied by network distribution businesses when assessing the economic efficiency of different investment options in order to select the best option available to meet their network’s needs. This helps to promote better consistency, transparency and predictability in our planning processes and follows the NER rules under Chapter 5.

145

Figure 11.1: Demand Management Assessment process

11.2 Demand management considerations in 2019 There were 26 projects in the forward planning period which met Ausgrid’s criteria for demand management consideration. Ausgrid assesses the viability of demand management alternatives for projects which are scheduled for the forward planning period and which meet minimum threshold costs. For one of these projects, assessment for non-network solutions has determined that it is considered likely that demand management will form part of the least cost solution to the need. The assessments for all projects were based upon preliminary assumptions for project costs, unserved energy and other benefits. A full assessment conducted as part of the RIT-D process, including a request for submissions via the Non-Network Options Report (NNOR) or equivalent will occur in future. 11.3 Demand management activities in 2018-19 11.3.1 Demand management projects initiated in 2018-19 There was one (1) demand management project initiated in FY2018-19 that was linked to a network investment need. Project 1: Based on latest demand forecasts, Ausgrid identified an emerging network constraint associated with three interconnected 11kV feeders in the Gillieston Heights area, part of the LGA in the Hunter Region of NSW. Based on cost-assessment, Ausgrid determined that demand management was likely to offer a cost-efficient alternative to augmentation of the distribution network.

A Request for Proposal (RFP) was published in April 2019 which invited demand management proponents, including those who were registered on Ausgrid’s Demand Management Engagement Register, to submit proposals for non-network solutions that could defer the proposed supply-side network upgrade in the Gillieston Heights area. One (1) proposal was received in response to the RFP. Response 1: Residential behavioural demand response Response 1 proposed a residential behavioural demand response type solution based on smart meter technology. Upon review, the proposal did not include the costs for activities such as marketing and customer acquisition, smart meter installation, customer incentive payments and project management.

With end-to-end costs included, the total cost for Response 1 was estimated to be 220% of the upper limit of the available project budget and therefore was considered not economically viable.

146

Current activities Ausgrid is currently pursuing an internally-run DM program based on air-conditioning (AC) load control demand response leveraging experience from Ausgrid’s own CoolSaver program. Cost-benefit assessment indicated it was economically feasible to reduce the load at risk on the relevant 11kV feeders for a single summer 2019/20. Further details will be provided in the Ausgrid’s 2019-20 DTAPR publication.

11.3.2 Demand management projects implemented in 2018-19 There were no demand management projects implemented in 2018-19 that were linked to a network investment need. 11.3.3 Demand management innovation As part of our efforts to explore alternative demand management solutions, Ausgrid investigates potential demand management solutions that may offer cost-effective alternatives to traditional network options. These research projects are funded through the Demand Management Innovation Allowance (DMIA) and approved by the Australian Energy Regulator. A description of the projects is provided in the following table.

Table 11.2: Demand management innovation projects

Project Project Description Name 1 Demand This project aims to test the viability of using non-network options to defer or Management manage the load at risk associated with network investments that involve retiring for or replacing aged assets. Around 80% of Ausgrid’s capital investment Replacement expenditure over the next 5-10 years is related to the retirement or replacement Needs of aged assets and this will be an important project in building demand (“Power2U – management capability for this type of network investment. Solar and Using non-network solutions to manage risk from replacement driven Lighting investments differs markedly from typical overload risk and requires an Incentives innovative approach to build a portfolio of permanent and temporary load Program”) reductions across the daily profile. The project proposes to leverage the capability of market participants, including electricity retailers, solar installers, energy efficiency providers and other key market participants. The project consists of two independent project components: Part A – An incentives program to encourage permanent demand reductions (e.g. additional solar power systems and energy efficiency activity) in a defined geographical area or areas. Part B – Feasibility studies into the use of traditional demand response solutions for a network outage scenario. The results of the activities during 2018/19 included: • Finalisation of contracts with all five market providers selected via the Request for Information (RFI) process; • Launch of the program with market providers initiating engagement with Ausgrid customers in the selected 20 suburbs of the program; • Monthly results communicated and tracked for assessing the progress of each market provider with respect to uptake of the market providers’ offers related to the program’s incentives, learnings from the activities undertaken and discussion of matters specific to each market providers’ market segments and strategies. More information on the trial can be found on Ausgrid’s website at https://www.ausgrid.com.au/power2u.

147

Project Project Description Name 2 Battery This project explores whether battery VPP’s can provide reliable and cost Demand competitive sources of demand reductions or voltage support services to defer Response network investment. The three primary objectives of the project include: (“Power2U – • Test whether customer battery systems offer a technically and Battery Virtual commercially viable demand management option. Power Plant Trial”) • Test customer take-up of a network support offer whereby customer battery systems are dispatched to align with network needs. • Investigate and trial the integration of battery management platforms or systems within the Distributed Energy Resource (DER) optimisation platform of Ausgrid’s Advanced Distribution Management System (ADMS). Secondary objectives include: • Better understanding of the types of customer battery systems being installed by early adopters of the technology • Better understanding of the impacts on maximum demand and energy volume for a customer with a battery system with and without a demand response offer. The project is divided into 3 phases to align with the objectives set for the project: • Phase 1 - Battery customer market research (completed in 2018/19); • Phase 2 - Customer trial over 2 to 3 summer seasons; • Phase 3 – Distributed Energy Resource integration with the Advanced Distributed Management System (ADMS) Phase 1 of the trial included collation and analysis of information of battery systems connected to Ausgrid’s network and an exploration of possible offers and contractual arrangements with a range of different market providers (e.g. battery suppliers, aggregators and energy service providers). Phase 1 was completed in 2018/19 and a summary report for this phase is available on Ausgrid’s website at https://www.ausgrid.com.au/Industry/Our-Research/DMIA- Research-and-trials.

Phase 2 of the project will include customer battery system dispatch and further development of aggregator partnerships. This Phase was initiated in 2018/19.

Phase 3 of the project will focus on the integration of network support dispatch and constraint management into the DER platform of Ausgrid’s Advanced Distributed Management System (ADMS).

3 DTAPR As a result of Ausgrid’s annual publication of its Distribution and Transmission Mapping Annual Planning Report (DTAPR), feedback from industry stakeholders indicated Platform that they desired a more accessible way to gain information about Ausgrid’s network investment plans and projects to identify opportunities for non-network solutions. The primary aim of the project is to produce an online mapping platform to present information contained in the DTAPR in a more accessible manner. In FY2018/19, the project undertook its first phase that included activities such as the initial investigation of various mapping platforms that were available in the market, exploring different options in scope and design development approaches of the tool and uploading information contained in the 2018 DTAPR. The link to the mapping interface used to represent Ausgrid’s 2018 DTAPR is here: https://nationalmap.gov.au/renewables/ FY2019/20 activities will be based on the selection of the design development option, engagement with the appropriate market provider and initial development.

148

Project Project Description Name 4 Peak Time Peak Time Rebate project is to assess the cost-effectiveness of a peak time Rebate rebate offer to test whether this option can be used to alleviate location specific (Retailer short-term network constraints to defer or reduce the need for longer term Demand network infrastructure upgrades. Response) The four primary objectives of the project include: • Measure demand reductions on peak event days; • Assess customer acquisition strategies and associated costs; • Identify average costs to roll out this program; and • Identify opportunities and barriers for future deployments.

Ausgrid planned to collaborate with electricity retailers to leverage their existing residential peak time rebate customer offerings for summer 2019/20 and potentially future summers

Locations proposed for this trial will be selected based on similar weather conditions, location and demographics to areas forecast to have network investment needs in the future.

Up until June 2019, the project was still being developed and no specific results can be reported. Research was conducted on past projects and discussions and workshops with electricity retailers were held to investigate and collaborate on a potential program. These discussions and further project development will continue into 2019/20 towards development of a full implementation proposal plan.

149

Project Project Description Name 5 Stand Alone This project was developed to improve the techniques by which Stand Alone Power Power Systems (SAPS) can be assessed as non-network options for Ausgrid’s Systems demand management investigations and regulatory investment test- distribution (RIT-D) projects.

The primary objective of this project is to develop the tools for performing initial screening of network investments. Secondary objectives include identifying case studies SAPS are a potentially viable alternative to traditional network options.

The project is planned to take place over two years in 2018/19 and 2019/20 in three phases:

Phase 1 - Costs Benefit Assessment tool development for SAPS Phase 1 will involve the development of a suite of tools that can be used to quantitatively assess whether a Stand-Alone Power System is a more cost- effective alternative to a traditional network solution. This phase of the project will provide: • A whole-of-life SAPS sizing and costing tool that determines the optimum SAPS configuration based on customer interval demand data and a given set of constraints; • A customer interval demand data estimation tool where metered interval data is not available; • A cost-benefit assessment (CBA) tool which will capture all the relevant costs and benefits associated with deploying a SAPS Phase 2 – Case study identification and customer engagement The case study identification phase of the project would commence in parallel with activities to help define the inputs, scope and outputs required for the tools being developed in Phase 1. The customer engagement phase would develop a customer engagement process and strategy for providing customers with a SAPS solution which would consider how the various ownership options might influence the overall process (customer-owned, third party owned or DNSP owned). Phase 3 – Stand Alone Power Systems pilots In this phase, one or more of the case studies identified earlier could be progressed to a pilot program. The budget for a pilot program has not been included in this proposal and may be funded from Ausgrid’s Network Innovation program funding for the 2019-24 regulatory period.

2018/19 activities

In 2018/19, an external provider was engaged to deliver the whole-of-life SAPS sizing and costing tool and customer interval data estimation tool of Phase 1. Further project development will continue into 2019/20 towards full implementation of all project phases.

150

Project Project Description Name 6 Electric This 2-year project will explore the potential impacts of electric vehicle (EV) Vehicle charging on the Ausgrid network by supporting an ARENA-funded project called Demand Charge Together and trial demand management options for electric vehicles. Research The primary objectives of the project are:

• Understand and research options for demand management interventions using EV chargers to shift or curtail demand during peak demand periods; and • Conduct a demand management trial based on the research outcomes.

The project will be conducted in two phases:

Phase 1 - Charge Together Project support, led by Evenergi in 2019 There are three main activity streams for this project to develop:

• A suite of fleet products which can be provided to fleet managers with all the tools necessary to migrate their fleets to electric vehicles; • A product that will provide individual EV buyers with the tools necessary to make an EV purchasing decision; • An electricity network planning tool to assist Australian electricity network providers in planning and preparing for the impacts of EV charging on their network. Phase 2 – Customer pilot/ trial to commence in 2020 This phase of the project will trial demand management options for electric vehicle charging based on the outcomes of Phase 1.

2018/19 activities

Up until June 2019, the following activities were completed as part of Phase 1 support for the EVenergi project:

• Ausgrid (with the support of AEMO) conducted an Australian DNSP survey of electric vehicle impact forecasting methodologies during April 2019. The results from this survey were presented at an AEMO Forecasting Reference Group meeting in April 2019; • In June 2019, a workshop with Ausgrid, Endeavour Energy, Essential Energy, SA Power Networks EVenergi, NSW Government and Macquarie University was conducted in Sydney to develop the framework and typology methodology to be used for the network forecasting tool; and • Participation by Ausgrid’s fleet and sustainability manager in meetings and development work for the fleet products and tools.

Further project development will continue into 2019/20 towards full implementation of all project phases.

151

Project Project Description Name 7 Digital Energy This project is a 3-year research project being led by Monash University in which Futures Ausgrid is a co-funding and in-kind contributor in partnership with Energy Consumers Australia and Ausnet Services. The project has been granted funding from the Australian Research Council (ARC) due to its innovative combination of research techniques.

The project aims to understand and forecast changing digital lifestyle trends and their impact on future household electricity demand, including at peak times. The project expects to generate new knowledge by employing digital ethnography and sociological theories to investigate how changing social practices will impact on electricity sector planning. This should provide significant benefits, such as lowering the cost of infrastructure spending, and helping secure affordable electricity provision.

The project has 5 key objectives, which are to:

• Understand how Australian household practices (e.g. heating, cooling, entertaining) are changing and likely to change in relation to emerging digital technologies and across different electricity consumer groups. • Identify emerging future scenarios and principles that will affect electricity sector planning in the near-medium (2025-30) and medium-far (2030-50) futures. • Develop a theoretical and methodological approach to anticipate changing trends in household practices and energy demand, which brings a futures perspective to theories of social practice and digital ethnography. • Develop an industry-relevant forecasting methodology for tracking and anticipating peak electricity demand, and energy consumption more broadly, that incorporates insights from this future-oriented social science research. • Develop practical demand management solutions for Australian electricity network businesses to plan for efficient, cost-effective and reliable networks.

The project will take place over 3 years, starting in late 2018/19 and continuing through 2019/20, 2020/21 with completion expected to be in 2021/22.

In 2018/19, the project was in a development phase and involved work on developing the original ARC grant proposal in conjunction with the lead and partner organisations and finalising the partner agreements for the ARC grant funding. The ARC grant was awarded in January 2019. Further project development will continue into 2019/20 towards full implementation of all project phases.

152

Project Project Description Name 8 Cost This 2-year project will aim to quantify the peak demand reduction benefits from Reflective the introduction of cost reflective network pricing to residential and small Networking business customers to better understand the effectiveness of these pricing Pricing structures as a targeted demand management tool for network investments. The Research network pricing structure under study will include both seasonal time of use and monthly demand pricing structures and be focused on the residential sector for the first phases of the project.

The primary objective of this project is to better understand and quantify the impact of cost reflective network pricing structures on reducing electricity demand at times of peak demand.

Secondary objectives include better understanding of the complementary measures that could be used to increase the effectiveness of these network pricing signals as an effective demand management tool.

The project will be conducted over a 2-year period in three phases:

Phase 1 – Customer research (surveying) and focus groups Phase 1 will involve surveying around 1,000 residential customers and obtaining more detailed information about their appliances, socio-demographics and retail pricing plans. Phase 1 will also involve following up with a sample of customers from the survey to further explore their understanding of pricing plans, energy-use behaviours and responses to these pricing signals. Phase 2 – Demand reduction study and analysis Phase 2 will involve a more detailed study of the impact of cost-reflective network pricing using historical data from interval and smart meter customers, results from the customer survey above, and further survey work or follow ups with customers from the survey.

A more detailed scope of works will be developed during FY19/20 including monitoring of customer statistics and details of customers who are defaulted onto demand pricing during FY19/20.

Phase 3 – Trial program Phase 3 would involve a trial of complementary measures identified in Phase 1 and Phase 2 that increase the effectiveness of seasonal time of use or monthly demand pricing in reducing peak demand as well as mitigating customer impacts particularly on vulnerable customers.

2018/19 activities

In 2018/19, work included development of the project and completion of the Phase 1 resident customers’ survey of 1,118 respondents. This survey was statistically designed to achieve the objectives of the study and included over sampling in areas of the network where there is a known or emerging network constraint.

Analysis of the survey results and Phase 2 activities are planned for 2019/20.

153

Project Project Description Name 9 Community This project aims to develop a feasibility study and model business case for Battery community batteries as a solution for local network constraints. The program is Feasibility designed to research and develop capability in a new and innovative approach to Study managing network constraints driven by peak load, minimum demand and associated issues with voltage, system frequencies and power quality management, and the need to manage diverse power flows and system security issues.

The project will take place over the 2018/19 and 2019/20 years in two phases:

Phase 1 – Feasibility study and model business case The first phase of the project is to develop a Feasibility Study and Model Business Case for community batteries as a solution for local network constraints.

Phase 2 – Community Battery pilot project The details and funding of this phase would be contingent upon review of Phase 1 outcomes. Where the solution is found to be potentially viable, the project will develop an implementation proposal/plan for a community battery pilot to verify model business case assumptions on battery and market performance.

2018/19 activities

A consultant was engaged for Phase 1. As part of this phase, Ausgrid conducted a detailed analysis of all 34,000 distribution transformers in the network to identify representative distribution transformers to assist in the development of the use cases for the feasibility study and model business case. In addition, customer half-hourly energy use data from around 10,000 customers from the representative distribution transformer dataset was compiled and provided to the consultants for more detailed analysis to better understand the potential customer and network benefits of a community battery.

Final reports from the Phase 1 feasibility study and model business case are expected to be completed early in 2019/20.

154

11.4 Forecast demand management projects For the forward planning period, a preliminary demand management assessment has determined that non- network alternatives are likely to offer a cost-effective option for two projects. In advance of the need date, a non-network options report will be published on Ausgrid’s website at www.ausgrid.com.au/ritd for these projects. 11.5 Demand side engagement During 2019 Ausgrid continued to inform and engage interested parties over a range of activities to improve demand management outcomes in meeting network needs. Our main channel of engagement continued to be through our quarterly e-newsletters to inform stakeholders about our demand management initiatives, research and other relevant industry information. Past e-newsletters can be viewed on our Keep Informed page at www.ausgrid.com.au/dm. In addition, we notified members on our demand management engagement register about our assessments on all RIT-D projects and invited them to submit comments and proposals during the consultation process. This included notifications for 8 RIT-D projects which can be viewed at www.ausgrid.com.au/ritd: • Lower North Shore • Clovelly • Revesby/Milperra • Macquarie Park, • St George • CONSAC cabling project • Rozelle • Upper Hunter Our engagement activities also included our corporate membership with the Clean Energy Council where we presented at a number of CEC industry events to share with peers about our project activities in demand management as well as women in renewables. For further information on our demand management programs and activities please contact Ausgrid’s Demand Management team at [email protected]. For more information on how Ausgrid investigates and implements non-network solutions, please refer to our Demand Side Engagement Document at www.ausgrid.com.au/dm. 11.6 Embedded generator enquiries and connection applications The following table summarizes embedded generation enquiries and applications that Ausgrid received under NER clause 5.3A.5 and 5.3A.9 during the financial year 2018/19.

Item Description Quantity Connection enquiries received under clause 5.3A.5 37

Applications to connect received under clause 5.3A.9 4

Average time taken to complete applications to connect N/A*

*The connection applications received have not been finalised/processed completely i.e. no offer has been made, we are currently still going through the approval process.

155

12 Investments in information technology and communication systems

12.1 Information, Communication and Technology Information, Communication and Technology (“ICT”) provides the critical business systems to enable Ausgrid to perform its network operations, which includes undertaking effective asset management planning, and fulfilling regulatory and statutory reporting obligations. ICT systems are integral to performing functions such as asset lifecycle management, asset operations, customer and market management and financial reporting, with Supervisory Control and Data Acquisition & Network control systems being integral to performing key network activities such as monitoring and managing the electrical network. Information technology also allows Ausgrid to prudently adopt and effectively implement technology that enables Ausgrid to deliver better services to network customers and reduce costs over time. Key ICT systems support the following Ausgrid core business functions:

Domain Description

Asset Lifecycle Asset management is one of Ausgrid’s most critical functions. The asset management Management business function concerns the management of all physical components of Ausgrid’s electrical system across the lifecycle of assets from investment through to retirement/replacement at the component level. It is also tightly integrated with operations and planning at the Network level. The asset management systems are therefore integral to providing services, reliability and quality of supply and protecting the safety of customers, community and employees.

Works Works management refers to the efficient management of Ausgrid’s resources in the delivery Management of services within the Network. It encompasses processes which are tightly associated with the asset management capability described above, scheduling and dispatch, warehousing and mobility.

Market Market management includes all of the processes related to the collection of revenue resulting Management and from the provision of energy distribution services. The main processes in delivering this Customer business capability are metering, revenue management, and network billing. Market Management management also incorporates network pricing, market transactions, meter data management and financial reporting. Customer management includes functions and processes related to customer interactions, connections and disconnections, as well as the provision of a customer contact centre.

Enterprise Commercial and corporate includes functions necessary for executive control and oversight of Management normal organisational functions, such as finance, reporting, strategy development and implementation, human resource management, non-system asset management and property management.

IT Management The effective management of information across Ausgrid has become crucial. The nature of the business dictates that information needs to be collected, managed and analysed in order to provide timely and effective decision support. Information management is also required to satisfy regulatory obligations and core financial and organisational reporting and analysis. Infrastructure provides the backbone to Ausgrid’s business capabilities and systems. It includes all of the hardware, communication, operating systems and devices required to support the business.

Asset Operations System IT provides the core functions regarding provision and development of the Distribution Network Management System (DNMS) and Supervisory Control And Data Acquisition (SCADA) systems, core telecommunication networks (MPLS, 4G) and distribution network monitoring and control.

156

12.1.1 ICT investment actual 2018/19 and forecast Throughout the year, key applications and infrastructure have been maintained to enable a reliable, scalable and secure computing platform. These include our SAP applications, enterprise content management platform, customer relationship management platform, supporting Ausgrid critical infrastructure licence conditions, metering systems and data centre and telecommunications technologies. In the development of the forward plan and strategy the following principles were adopted:

• Customer Centric: Knowing our customer to enable us to provide a seamless and efficient service; • User Experience: Enable a secure, capable and reliably mobile experience; • Data Driven Culture Extract value from data and enhance capabilities; enable self-service analytics capability; • Platforms: Enable business agility with flexible “pay as you go” models; continue the focus on efficiency by Consolidating, Standardising and Automating. • Cyber Security: To protect the network and customer information including compliance with laws and the distributor licence conditions, and to be recognised as the leader in cyber security within in the Power and Utilities industry.

The key objectives of the ICT Capex program are to:

• Comply – Deploying technology solutions and processes to ensure compliance for both national and state based licencing and legislative obligations; • Protect – Maintaining the safety of the distribution system through the provision of distribution network services and customer services; • Maintain – Ensure technology solutions and processes are maintained to preserve the quality, reliability of supply, the security of the distribution network or the provision of distribution network services and customer services; and • Adapt – Implementing technology systems, processes and people that enables Ausgrid to meet and manage expectations and demands from customers, legislative and regulatory requirements.

The table below contains a summary of actual ICT investment in 2018/19 and forecast investment in 2019/20 through to 2023/24.

ICT Investment actual 2018/19 and forecast 2019/20 to 2023/24 (real $) *

Actual Forecast ($m) ($m)

2018/19 2019/20 2020/21 2021/22 2022/23 2023/24

Total ICT Capital 116.9 64.0 44.5 26.4 24.3 29.4 Investment *Excludes the Advanced Distribution Management System – see below.

12.2 Advanced Distribution Management System (ADMS) Ausgrid’s distribution network is managed using a group of systems where control room staff integrate various information flows and take consequent actions to maintain the security and stability of the network. The DNMS is the core operational management tool in that group of systems. It is a single vendor and in-house developed hybrid system dating from the 1990s. Ausgrid’s current DNMS control system started development in the 1990’s and has been in use with limited change for over a decade. The DNMS has: • high costs to maintain the necessary contemporary cyber security protections; • limited functionality that cannot be easily developed or extended due to insufficient resources with the required expertise and inherent system architecture constraints;

157

• inefficient connection of new types of network equipment due to the lack a modern system providing asset and connection integration capabilities; • high development and support costs, solely funded by Ausgrid; and • difficulty integrating with new applications and technologies to support the evolving network and customer needs. The DNMS has been assessed as being unable to make the transition to deliver support for the core functions required by a modern distribution utility, i.e. Distributed Energy Resource Management (DERMS), Fault Location Isolation and Rectification (FLISR) and Advanced Metering Infrastructure (AMI). Three replacement options for DNMS were considered with the preferred option being to replace current systems with an ADMS. An ADMS platform provides an integrated set of tools to remotely monitor and control the network, manage system outages, improve planned and emergency event management, and optimise fault location and restoration processes. This will allow Ausgrid to provide the services expected by customers and stakeholders in the rapidly changing energy market 12.2.1 ADMS Benefits An ADMS would address the above challenges of our current DNMS. Improved functionality benefits would include: • management of system outages and restoration works; • planned and emergency event management; • situational awareness from power-flow analysis; • network fault location analysis, automated isolation and restoration capabilities; • provision of a platform for the integration of distributed energy resource management systems as well as other corporate systems enabling the Distribution System Operator (DSO) construct; • an ability to better integrate with Ausgrid’s enterprise systems to ensure a consistent real time situational view (that is not dependant on staff entering and updating information in multiple systems); and • the ability to use digitised switching instructions which would enable non-verbal communications between the control room and field operators. The core benefits assessed in the business case for an ADMS implementation are described in the following table.

Benefit Description

Risk Mitigation Mitigates legacy-system risk (including cyber risk) to as low as reasonably practical

Operational Drives significant operating efficiencies across the major operational groupings Efficiency

Enabling ADMS provides a platform for existing system and process capability integration and enables Platform simple integration of future capabilities

Safety Greater visibility of the operational state of the network and aligned data will improve safety by providing all personnel operating on the network with improved situational awareness

Customer Helps meet increasing customer expectations via the provision of accurate and timely outage information through the ADMS which would be in real-time between field operations and customers using our online outage information systems and the contact centre

12.2.2 ADMS Program Implementation The overall program (Program) will be managed via a Program Delivery Management Group reporting to an Executive Steering Committee (ESC). The Program will be delivered via a series of phases between January 2019 and March 2024. The high-level objectives of each phase are described in the following table:

158

Phase Description Timing

1 Replacement of DNMS - this delivers mission-critical monitoring January 2019 to July and control functionality (SCADA) 2021

2 Replacement of Outage Management System (OMS) July 2019 to January 2023

3 Advance Applications – this delivers Automated Fault Detection March 2021 to March and Isolation Restoration and advanced applications to enhance 2024 the optimisation of the network, e.g. Distribution Energy Resource Management.

The table below contains a summary of actual and forecast investment in from 2018/19 through to 2023/24.

Forecast Capex Costs including contingency & overhead to 2023/24 (nominal $):

Actual ($m) Forecast ($m)

2018/19 2019/20 2020/21 2021/22 2022/23 2023/24

Advance Distribution Management System 18.2 25.5 23.5 17.5 13.0 10 (ADMS)

12.3 Network Asset Digitisation The implementation of the Network Asset Digitisation Program will deliver a digital twin of Ausgrid’s overhead network that will enable a range of cost efficiencies within network planning, design and works delivery. It is focused on six fundamental streams to acquire accurate network asset data, integrate various information sources and model into a virtual world accessible to staff and relevant third parties to better inform business decisions and drive efficiencies. These streams are:

• Data acquisition • Data management • Establish asset digital twin • Analytics and insights • Reporting • Platform development. The data acquisition activities will rapidly increase the volume and accuracy of asset information, requiring the alignment of current asset information with the establishment of a single asset data model. This model will build upon work conducted as part of the ADMS project and enable the value of this information to be maximised for users and ongoing system implementations, such as the smart meter data acquisition and SAP S/4 Hana implementation. The use of an aligned model will also enable the rapid integration of asset information between systems, reducing effort for users to access and update information. This program includes minor enhancements to existing system integration to streamline data access and update processes. 12.3.1 Network Asset Digitisation Benefits Ausgrid manages a substantial set of asset information to enable efficient and effective business operations. Asset information is recorded and processed into asset management systems from:

• over 5 million recorded assets; • over five hundred thousand inspections/site visits annually; and • hundreds of measurements per day from nearly a million network points.

159

Information from these assets and inspections is currently collected through both automated and manual processes. However, recent advances in technology such as Light Detection and Ranging (LiDAR), panoramic imagery and processing, 3D modelling, machine learning algorithms and capture techniques are allowing utilities to develop much more comprehensive and accurate data sets at significantly reduced costs. A business case was developed assessing the economic benefit to customers as part of the FY20-24 revised regulatory proposal. This process also included an independent assessment of the modelling, assumptions and likely realisation of benefits by GHD. The independent report concluded that the technology and capability was proven in Australia and internationally, the inputs used established supplier costs and the benefits identified utilised a conservative approach suitable to offset any potential overstatement. The benefits of implementation of the Network Digitisation program include:

• Improving capital efficiency from reduced planning and design effort for overhead line investigation and replacement activities; • Improved network reliability and reducing network risk (outage, fire-starts, emergency response) from identification and prioritisation of defects and the installation of LV spreaders where advantageous in non- bushfire areas; • Reduced capital and operational expenditure associated with vegetation encroachments; • Reduced operational expenditure by optimising vegetation management cycles; and • Information partnering with RMS and local councils. 12.3.2 Network Asset Digitisation Program Implementation Ausgrid has undertaken trials of the latest LiDAR and imagery technology to capture a representative sample of Ausgrid’s overhead assets and test the accuracy of information, available analytics and digital twin platforms utilised to represent these assets. Learnings from these trials have been used to inform the development of this program. The implementation of this program will be undertaken in three sequential stages:

• Stage 1 – Initial network asset acquisition, data management and platform development; • Stage 2 – Second cycle of asset acquisition, processing and comparative analytics; and • Stage 3 – Operationalised asset acquisition and data maintenance. This approach will provide for review and validation of ongoing benefit realisation prior to the implementation of subsequent stages. Each data acquisition and analysis cycle will be delivered in a single stage as shown below. Program delivery stages

The estimated program costs are provided in the table below. Program cost estimates including contingency & overhead ($m, nominal)

FY20 FY21 FY22 FY23 FY24 Total

Network Digitisation 4.9 5.0 1.3 1.2 1.3 13.7

160

Annexure A – Glossary

ADMS Advanced Distribution Management System

AER Australian Energy Regulator

AEMC The Australian Energy Market Commission is the rule maker and developer for Australian energy markets AEMO Australian Energy Market Operator

CBM Condition Based Maintenance

DLF Distribution Loss Factor

DPAR Draft Project Assessment Report

DTAPR Distribution and Transmission Annual Planning Report prepared by a Distribution Network Service Provider under the National Electricity Rules DNSP A Distribution Network Service Provider who engages in the activity of owning, controlling, or operating a distribution system, such as Endeavour Energy, Ausgrid and Essential Energy Dual Function Asset Any part of a network owned, operated or controlled by a Distribution Network Service Provider which operates between 66kV and 220kV and which operates in parallel, and provides support, to the higher voltage transmission network and is an asset which forms part of a network that is predominantly a distribution network ENSMS Electricity Network Safety Management System

ESA NSW Electricity Supply Act 1995

EUE Expected Unserved Energy

FMECA Failure Mode Effects and Criticality Analysis

FPAR Final Project Assessment Report

GJ gigajoule One gigajoule = 1000 megajoules. A joule is the basic unit of energy used in the gas industry equal to the work done when a current of one ampere is passed through a resistance of one ohm for one second GWh gigawatt hour One GWh = 1000 megawatt hours or one million kilowatt hours

HV high voltage Consists of 11kV and 22kV distribution assets

JPB Jurisdictional Planning Body

LV low voltage Consists of 400V and 230V distribution assets

kV kilovolt One kV = 1000 volts

kW kilowatt One kW = 1000 watts

KWh kilowatt hour The standard unit of energy which represents the consumption of electrical energy at the rate of one kilowatt for one hour MRA Maintenance Requirements Analysis

MVA (unit of electrical power) Mega Volt Amp

MVAr MVA (reactive). Where quoted as part of a demand forecast, it is assumed that capacitors are in service. MW megawatt One MW = 1000 kW or one million watts

December 2019

MWh megawatt hour One MWh = 1000 kilowatt hours

N capacity The capacity of a network (or sub-section of network) with all elements in service. N-1 capacity The capacity of a network (or sub-section of network) following a failure of a single critical element. NEL National Electricity Law

NER National Electricity Rules

NTFP National Transmission Flow Path

NTNDP National Transmission Network Development Plan

OCB Oil Circuit Breaker

POE 50 In this document, refers to a demand forecast with a 50% probability of being exceeded (i.e. 1 in 2 years) Primary distribution feeder Distribution line connecting a subtransmission asset to either other distribution lines that are not subtransmission lines, or to distribution assets that are not subtransmission assets pf Power Factor

RCM Reliability Centred Maintenance

RIT-D Regulatory Investment Test for Distribution

SAIDI System Average Interruption Duration Index

SAIFI System Average Interruption Frequency Index

SCFF Cables Self-Contained Fluid Filled Cables

SFAIRP So Far As Is Reasonably Practicable

SOO Statement of Opportunities

STPIS Service Target Performance Incentive Scheme

STS Subtransmission Substation

Subtransmission Any part of the power system which operates to deliver electricity from the higher voltage transmission system to the distribution network and which may form part of the distribution network, including zone substations Subtransmission system Consists of 132kV, 66kV and 33kV assets, including dual function assets

TNSP Transmission Network Service Provider

V volt A volt is the unit of potential or electrical pressure

VCB Vacuum Circuit Breaker

VCR Value of Customer Reliability

W watt A measurement of the power present when a current of one ampere flows under a potential of one volt XLPE Cross-linked Polyethylene

ZS Zone substation

December 2019

Annexure B – Reliability and Performance Licence Conditions

The Reliability and Performance Licence Conditions for Electricity Distributors came into effect on 1 July, 2014 and repeal Schedule 1 of the former Design, Reliability and Performance Licence conditions.

December 2019

MINISTER FOR INDUSTRY, RESOURCES AND ENERGY

DISTRIBUTOR'S LICENCE UNDER THE ELECTRICITY SUPPLY ACT 1995 (NSW)

granted to

Ausgrid Operator Partnership a partnership carried on under that name by Blue Op Partner Pty Ltd (ACN 615 217 500) as trustee for the Blue Op Partner Trust, ERIC Alpha Operator Corporation 1 Pty Ltd (ACN 612 975 096) as trustee for ERIC Alpha Operator Trust 1, ERIC Alpha Operator Corporation 2 Pty Ltd (ACN 612 975 121) as trustee for ERIC Alpha Operator Trust 2, ERIC Alpha Operator Corporation 3 Pty Ltd (ACN 612 975 185) as trustee for ERIC Alpha Operator Trust 3, and ERIC Alpha Operator Corporation 4 Pty Ltd (ACN 612 975 210) as trustee for ERIC Alpha Operator Trust 4.

Dated:

Licence to operate a distribution system that is a transacted distribution system under the Electricity Network Assets (Authorised Transactions) Act 2015 effective on completion (which is as designated by the Completion Order made by the Treasurer of the State of New South Wales under the Electricity Network Assets (Authorised Transactions) Act 2015*). *Note: the date of completion was designated to be BY The Hon. Anthony Roberts, Minister for Industry, Resources and Energy ("The Minister") TO Ausgrid Operator Partnership, a partnership carried on under that name by: (a) Blue Op Partner Pty Ltd (ACN 615 217 500) as trustee for the Blue Op Partner Trust; (b) ERIC Alpha Operator Corporation 1 Pty Ltd (ACN 612 975 096) as trustee for ERIC Alpha Operator Trust 1; (c) ERIC Alpha Operator Corporation 2 Pty Ltd (ACN 612 975 121) as trustee for ERIC Alpha Operator Trust 2; (d) ERIC Alpha Operator Corporation 3 Pty Ltd (ACN 612 975 185) as trustee for ERIC Alpha Operator Trust 3; and (e) ERIC Alpha Operator Corporation 4 Pty Ltd (ACN 612 975 210) as trustee for ERIC Alpha Operator Trust 4. ("Licence Holder")

kyys A0137729916v5 120465441 25.6.2015 page 1 The Minister has determined to grant a distributor's licence under section 14 of the Electricity Supply Act 1995 (NSW) in respect of the transacted distribution system operated by the Licence Holder on the conditions set out in the schedule to this licence and any conditions imposed by the Electricity Supply Act 1995 (NSW) and any regulations under that Act.

SIGNED by:

_ THE HON. ANTHONY ROBERTS Minister for Industry, Resources and Energy

kyys A0137729916v5 120465441 25.6.2015 Page 2 SCHEDULE OF MINISTERIALLY IMPOSED LICENCE CONDITIONS FOR THE OPERATOR OF A TRANSACTED DISTRIBUTION SYSTEM

This schedule provides a list of conditions which the Minister has determined to impose pursuant to clause 6(1)(b) of Schedule 2 of the Electricity Supply Act 1995 (the Act) on the operator of a transacted distribution system under the Electricity Network Assets (Authorised Transactions) Act 2015. In addition to ministerially-imposed conditions, licensees are subject to obligations imposed by the Act, Regulations and associated regulatory instruments which include (without limitation) an obligation to comply with requirements imposed by or under regulations made pursuant to section 111A of the Environmental Planning and Assessment Act 1979.

GENERAL CONDITIONS

1 Operate within distribution district At all times this Licence is in force, the Licence Holder must ensure that it and all other network operators of its distribution system only operate a distribution system: (a) within its distribution district as set out in Schedule 3 of the Act; (b) within such other areas outside of its distribution district in which the Licence Holder operates a distribution system as at the date of this Licence, as set out or described in Schedule 1 to these conditions; and (c) within such other areas outside of its distribution district as agreed and authorised by the Tribunal and the Licence Holder for the relevant distribution district.

2 National Electricity Market registration At all times this Licence is in force, the Licence Holder must ensure that it and all other network operators of its distribution system: (a) are registered or exempt from the requirement to be registered as a Network Service Provider under the National Electricity Rules; or (b) hold any equivalent authorisation or right of participation in any national electricity market, granted by the person responsible for the granting of such an authorisation or right of participation under any legislation enacted for the purpose of introducing such a market.

3 Technical and prudential criteria The Licence Holder must, for the duration of this Licence, ensure that it and all other network operators of its distribution system satisfy the technical and prudential criteria that each entity is required to meet as a condition of its registration or exemption, or equivalent authorisation or right of participation in any national electricity market, referred to in condition 2.

kyys A0137729916v5 120465441 25.6.2015 Page 3 RELIABILITY AND PERFORMANCE CONDITIONS

4 Network overall reliability standards

4.1 A Licence Holder must not, when excluded interruptions are disregarded, exceed in a financial year the SAIDI average standards that apply to its feeder types.

4.2 A Licence Holder must not, when excluded interruptions are disregarded, exceed in a financial year the SAIFI average standards that apply to its feeder types.

5 Individual feeder performance

5.1 This condition applies where one or more of the feeders of a Licence Holder exceed the relevant individual feeder standards for any 12 month period ending at the end of March, June, September or December, when excluded interruptions are disregarded.

5.2 A Licence Holder must: (a) investigate the causes for each feeder exceeding the individual feeder standards; (b) by the end of the quarter following the quarter in which the feeder first exceeded the individual feeder standards, complete an investigation report identifying the causes and as appropriate, any action required to improve the performance of each feeder to the individual feeder standards; (c) complete any operational actions identified in the investigation report to improve the performance of each feeder against the individual feeder standards by the end of the third quarter following the quarter in which each feeder first exceeded the individual feeder standards; (d) except as permitted by condition 5.2(e), where the investigation report identifies actions, other than operational actions, required to improve the performance of each feeder to the individual feeder standards, develop a project plan, including implementation timetable, and commence its implementation by the end of the second quarter following the quarter in which the feeder first exceeded the individual feeder standards; (e) consider non-network strategies which provide reliable outcomes for customers. Where found by the investigation report to be equal or more cost-effective than the lowest cost feasible network option such strategies shall be adopted rather than network augmentation options; (f) ensure that the implementation timetable for the network project plan or alternative non- network solutions is as short as is reasonably practicable; (g) where all reasonable steps to improve supply reliability have been taken, the costs of further actions to rectify the non-compliance must be subject to a cost benefit analysis. Where such analysis does not provide a positive benefit, no further action will be taken to improve the feeder’s performance and the ongoing non-conformance with the individual feeder standards will be reported to the Minister by the Licence Holder.

kyys A0137729916v5 120465441 25.6.2015 Page 4 5.3 The investigation report is to include a documented rectification plan where action is found to be justified in order to improve the performance of a feeder to the individual feeder standards. The action that is required may involve work to other network elements, or may involve only repair or maintenance work where capital works are not warranted and take into account any one-off events and previous performance trends.

6 Customer service standards

6.1 A Licence Holder must pay the sum of $80 to a customer on each occasion when the Licence Holder exceeds the interruption duration standard at the customer’s premises and the customer has made a claim to the Licence Holder within three months of the interruption ceasing.

6.2 A Licence Holder must pay the sum of $80 to a customer where the Licence Holder exceeds the interruption frequency standard at the customer’s premises in a financial year and the customer has made a claim to the Licence Holder within three months of the end of the financial year to which the interruptions relate.

6.3 A Licence Holder must determine a claim for payment under condition 6, and notify the customer of the determination in writing, within one month of receipt of a claim. For customers eligible for payment, the notice of determination must include the amount to be paid, the manner of payment and the timing of payment. Where the claim is not paid (whether in part or in full), the notice of determination must include reasons for the decision.

6.4 A Licence Holder is required to take reasonable steps to make customers aware of the availability of payments on the terms set out in condition 6. Reasonable steps include, as a minimum, publication of information on the Licence Holder’s website and annual newspaper advertisements. On request from a customer, a Licence Holder must provide written information on the availability of payments on the terms set out in condition 6.

6.5 A Licence Holder is required to make only one payment of $80 to a customer per premises in a financial year for exceeding the interruption frequency standard.

6.6 A Licence Holder is required to pay no more than $320 under condition 6 to a customer per premises in any one financial year.

6.7 A payment under this condition does not: (a) in any way alter or diminish any rights that a customer may have against any person under any trade practices or other applicable legislation, common law or contract; (b) represent any admission of legal liability by the Licence Holder; or (c) alter, vary or exclude the operation of section 119 of the National Electricity Law or any other statutory limitations on liability or immunities applicable to a Licence Holder.

6.8 Customers who are eligible for payments under this clause are limited to those customers who are supplied electricity through a metered connection point on an electricity distributor’s system.

kyys A0137729916v5 120465441 25.6.2015 Page 5 7 Performance monitoring and reporting

Network overall reliability standards report

7.1 A Licence Holder must submit a network overall reliability standards quarterly report to the Tribunal within one month of the end of each quarter.

7.2 Each network overall reliability standards report must include the following matters for the previous 12 month period to the end of that quarter: (a) performance against the SAIDI average standards and SAIFI average standards by feeder type, disregarding excluded interruptions; (b) reasons for any non-compliance by the Licence Holder with the network overall reliability standards and plans to improve performance; and (c) any other matter notified by the Tribunal in writing.

Individual feeder standards report

7.3 A Licence Holder must submit, within one month of the end of each quarter, a quarterly individual feeder standards report to the Tribunal on feeders that exceeded the relevant individual feeder standards during the previous 12 month period to the end of that quarter, together with, for each feeder: (a) the date at which the feeder first exceeded the relevant individual feeder standard, together with the actual SAIDI and SAIFI performance of the feeder for the 12 month period; (b) details of the remedial action that the Licence Holder intends taking, or has taken, to improve the performance of those feeders; (c) either of the following: (i) the date of completion, or the date of planned completion, of the remedial action plan; or (ii) details of the investigation and action proposed or undertaken leading to the decision to advise the Tribunal that it is not economically justifiable to bring the feeder performance into compliance with the individual feeder standards; and (d) any other matter notified by the Tribunal in writing.

Customer service standards report

7.4 A Licence Holder must submit a quarterly customer service standards report to the Tribunal on the following matters within one month of the end of each quarter, for the preceding quarter and for the previous 12 month period to the end of that quarter: (a) the number of payments given under condition 6 to customers by each type of area listed in Column 1 of Table 1 of Schedule 5 and by the type of standard, as shown in Columns 2 and 3 of Table 1 of Schedule 5; (b) the number of claims not paid (whether in part or full) under condition 6 by each type of area listed in Column 1 of Table 1 of Schedule 5 and by the type of standard, as shown in Columns 2 and 3 of Table 1 of Schedule 5; and (c) any other matter notified by the Tribunal in writing.

kyys A0137729916v5 120465441 25.6.2015 Page 6 Incident reporting

7.5 A Licence Holder must prepare and submit reports on any incident in accordance with any Reporting Manuals issued by the Tribunal.

Independent audit report

7.6 An independent audit must be conducted after the end of each financial year to audit the Licence Holder’s performance against the: (a) network overall reliability standards; (b) individual feeder standards; and (c) customer service standards.

7.7 The audit must be conducted in accordance with any Audit Guidelines issued by the Tribunal.

7.8 A Licence Holder is required to nominate a person to conduct the independent audit by written notice given to the Tribunal in accordance with auditor nomination procedures published in any Audit Guidelines issued by the Tribunal.

7.9 The person nominated to conduct the independent audit is to be a person who is: (a) independent of the Licence Holder; and (b) competent to exercise the functions of an auditor in respect of the matters to be audited.

7.10 The nomination of an auditor by a Licence Holder ceases to have effect if the Tribunal advises the Licence Holder, by notice in writing, that the nomination is not acceptable or has ceased to be acceptable.

7.11 The Tribunal may nominate an auditor to carry out an audit, and the person so nominated is taken to have been nominated by the Licence Holder, if: (a) the nomination of an auditor by the Licence Holder ceases to have effect; or (b) the Licence Holder fails to nominate an auditor to carry out the audit in accordance with any requirements specified by the Tribunal by notice in writing to the Licence Holder.

7.12 A Licence Holder must provide a copy of the auditor’s report by 30 September each year to the Tribunal.

General matters concerning reports

7.13 Where the Tribunal determines the format of a report required by this condition, a Licence Holder must submit the report in that format.

7.14 The Tribunal may from time to time publish requirements to be followed by the Licence Holder in respect of reports required by this condition and the Licence Holder must comply with any such requirements.

7.15 The Tribunal may from time to time require, by notice in writing to the Licence Holder, further reports relating to these licence conditions including, without limitation, reports relating to capital expenditure works, network refurbishment and maintenance programs.

7.16 A Licence Holder must provide a report submitted to the Tribunal under this condition to the Minister, if requested to do so by the Minister by notice in writing.

kyys A0137729916v5 120465441 25.6.2015 Page 7 8 Business continuity and disruptions

8.1 The Licence Holder must have a documented system to ensure that it has adequate arrangements in place to identify, assess and manage business continuity risks and manage business disruptions relating to the operation of its distribution system (a Business Continuity Plan).

8.2 The Licence Holder must ensure that it and any other network operator of its distribution system implements and complies with the Business Continuity Plan.

CRITICAL INFRASTRUCTURE LICENCE CONDITIONS For the purposes of conditions 9, 1O and 11 of this Licence, it is acknowledged that the assets which the Licence Holder operates may constitute "critical infrastructure" being those physical facilities, supply chains, information technologies and communication networks which, if destroyed, degraded or rendered unavailable for an extended period, would significantly impact on the security, social or economic wellbeing of the State of New South Wales and other States and Territories which are from time to time electrically interconnected with New South Wales and other States and Territories. These licence conditions will be reviewed by the Minister from time to time (and where necessary) in consultation with responsible Ministers of the Commonwealth and relevant States and Territories. According to its own legislation and policy, the Commonwealth may require a Licence Holder to agree to certain arrangements. The Licence Holder should also establish procedures for national security threat sharing with the Critical Infrastructure Centre and action received information on a good-faith basis.

9 Substantial presence in Australia

9.1 Except to the extent allowed for under the Protocol agreed with the Commonwealth Representative, the Licence Holder must take all practical and reasonable steps to ensure: (a) the maintenance of its distribution system is undertaken solely from within Australia, except where maintenance requires either physical servicing of components offshore or the acquisition of replacement components from outside Australia. In such an instance, it is the responsibility of the senior officer responsible for network operations to ensure this maintenance does not impact condition 9.2; and (b) that any third party or non-Licence Holder employee, including individuals/entities from outside Australia, undertaking maintenance of the distribution system is subject to the approval of the senior officer responsible for network operations.

9.2 Except to the extent that the Licence Holder is undertaking steps in accordance with, and for the duration of, a Protocol agreed with the Commonwealth Representative, the Licence Holder. (a) must, by using best industry practice for electricity network control systems, ensure that operation and control of its distribution system, including all associated ICT infrastructure, can be accessed, operated and controlled only from within Australia, and that its distribution system is not connected to any other infrastructure or network which could enable it to be controlled or operated by persons outside Australia; (b) must notify the Commonwealth Representative in advance of any engagement with the market to procure a contract under which it outsources the operation and control of its

kyys A0137729916v5 120465441 25.6.2015 Page 8 distribution system, including any ICT infrastructure associated with the operation and control of its distribution system. Note: For the purposes of Licence condition 9.2 (a); Best industry practice includes access required by relevant Australian regulators and market and system operators to meet the Licence Holder's obligations under Australian law.

9.3 The Licence Holder must: (a) have at least two directors who are Australian citizens; and (b) have senior officers responsible for (notwithstanding their title):

(i) operational technology; (ii) network operations; and (iii) security operations in relation to its distribution system,

who are persons residing in Australia and hold an appropriate national security clearance, being a clearance of not less than Negative Vetting Level 1 (or equivalent) issued by the NSW Government on advice from the Australian Government Security Vetting Agency (AGSVA). Note: For the purposes of Licence condition 9.3 (b):

The senior officer responsible for operational technology is the officer whose responsibilities include: • Delivering the Supervisory Control and Data Acquisition (SCADA) capability required to safely and reliably operate the NSW distribution system;

• Developing and implementing strategies to manage cyber security and other threats affecting the network operational technology environment; and

• Developing systems for effectively managing assets remotely, including but not limited to network switches, condition monitoring and remote interrogation or operation of protection systems and relays; and The senior officer responsible for network operations, is the officer whose responsibilities include: • The day to day operation, monitoring and maintenance of the distribution system; and

• Directing the operational planning, management, control and security of the distribution system. The senior officer responsible for security operations, is the officer whose responsibilities include: • Approval for the Licence Holder's personnel or other nominated personnel to access the Licence Holder's information systems or physical access to the Licence Holder's premises and associated infrastructure; kyys A0137729916v5 120465441 25.6.2015 Page 9 • Personnel security; and • Managing relationships with Commonwealth and state government agencies. Note: The above responsibilities may be held by a single officer or shared between more than one officer. Where the responsibilities are shared between more than one officer, the relevant senior officer responsibility contemplated in condition 9.1(a) is the joint responsibility of the multiple officers and the approval contemplated in condition 9.1(b) must be obtained from each of those officers.

9.4 The Licence Holder is not in breach of its obligations under: a) condition 9.3(a) if, in the case of a casual vacancy on the board of directors, the vacancy is filled within two months of the casual vacancy first occurring; b) condition 9.3if: (i) following the first issue of these conditions to the Licence Holder; or (ii) any position identified in condition 9.3 being vacated or the relevant person ceasing to satisfy the qualifications set out there for any reason,

the Licence Holder

(iii) procures the appointment of a person to the relevant position that the Licence Holder bona fide believes will be able to obtain the required security clearance; and

(iv) has procured that the person applies for the required security clearance.

9.5 The exception in condition 9.4(b) ceases to apply to the Licence Holder if: a) an appointment and application for national security clearance for the person is not made within 4 months of (as relevant) the first issue of these conditions or the relevant vacancy or disqualification occurring; or b) if the application referred to in condition 9.5(a) is made and is rejected or withdrawn, the Licence Holder does not procure a replacement application being made within 4 months of that rejection or withdrawal; or c) the Licence Holder does not procure compliance with condition 9.3(b) in any event with respect to any position within 8 months (or such longer period as approved in writing by the Minister) of (as relevant) the first issue of these conditions or the relevant vacancy occurring.

10 Data security

10.1 Licence Holder must ensure that: (a) all of its information (being design specifications, operating manuals and the like) as to the operational technology (such as the SCADA system) and associated ICT infrastructure of the operational network is held solely within Australia, and that such information is accessible only by a Relevant Person who has been authorised by the Licence Holder and only from within Australia; kyys A0137729916v5 120465441 25.6.2015 Page 10 (b) all: (i) Load Data; and (ii) Bulk Personal Data Records, relating to or obtained in connection with the operation of the distribution system by a Relevant Person is held solely within Australia, and is accessible only by a Relevant Person or a person who has been authorised by the Licence Holder; and (c) it does not export, and has appropriate security controls in place to prevent the export, of Bulk Personal Data Records relating to or obtained in connection with the operation of the distribution system by a Relevant Person, outside of Australia.

10.2 The Licence Holder is not in breach of its obligations under conditions 10.1(a), 10.1(b)(i) or 10.1(c) if the Licence Holder discloses, holds, uses or accesses any information or data referred to in those conditions, or the Licence Holder allows a Relevant Person approved by the senior officer referred to in condition 9.3(b)(i) to disclose, hold, use or access any information or data referred to in those conditions for the purposes of: (a) disclosure to a recognised stock exchange so that such information is made available publicly in compliance with a binding obligation on the part of the Licence Holder or an Associate to do so; (b) complying with any law of the Commonwealth of Australia, or of any of its States and Territories; (c) disclosure to the financial, accounting, insurance, legal, regulatory and other advisers, auditors, insurers, security trustees and financiers (and each of their advisers) of the Licence Holder, any Associate, and any bona fide prospective purchaser of any interest in, or of any interest in the main undertaking of, the Licence Holder or any Associate, but in each case only to the extent necessary in order for those persons to provide the advisory or other services bona fide required of them; (d) disclosure to participants, regulators and service providers in the electricity sector, provided it is in the ordinary course of business and in accordance with good electricity industry practice, and such information is required by those persons to provide the services or to perform the functions bona fide required of them; (e) providing aggregated data which does not permit identification of any particular customer or customer’s connection points or their demand characteristics; (f) allowing a service provider or contractor to hold, use or access information where that arrangement is approved by the Tribunal, in the case of arrangements approved as of the first issue of this Licence, and otherwise where the Licence Holder has provided the Commonwealth Representative with a submission demonstrating that: (i) the service provider or contractor is reputable; and (ii) the service provider or contractor has data security systems in place to ensure information security is maintained; and has obtained the written agreement of the Commonwealth Representative for the arrangement.

kyys A0137729916v5 120465441 25.6.2015 Page 11 (g) allowing a service provider or contractor who is a provider to the Licence Holder at the date of this Licence to hold, use or access information for the period of 12 months after the date of this Licence provided, after a transition plan is approved by the Tribunal in writing during that period, the Licence Holder undertakes the steps (if any) that are required to be undertaken in that 12 month period as set out in that transition plan; and (h) such other circumstances as approved by the Tribunal in writing. Prior to seeking approval from the Tribunal, the Licence Holder must provide the Commonwealth Representative with a reasonable opportunity within a period not ending less than 60 calendar days, to confirm in writing to the Tribunal that the Commonwealth does not intend to make any further requests or submissions in relation to the matter.

10.3 The Licence Holder is not in breach of its obligations under condition 10.1(b)(ii) if a Relevant Person or a person authorised to access the information by the Licence Holder discloses, holds, uses or accesses personal information in accordance with the Privacy Act 1988 (Cth).

10.4 The Licence Holder must ensure that third party data or information (including without limitation communications within the meaning of the Telecommunications (Interception and Access) Act 1979 (Cth), personal information within the meaning of the Privacy Act 1988 (Cth), and closed- circuit television footage) which is indirectly accessed or obtained by the Licence Holder because that third party data or information is transferred by a carrier or other party using the Licence Holder's infrastructure, are held by the Licence Holder solely within Australia, and are accessible only by a Relevant Person or a person who has been authorised by the Licence Holder and, in each case, only from within Australia.

11 Compliance

11.1 By 30 September each year the Licence Holder must furnish a report to the Tribunal and the Commonwealth Representative detailing whether the Licence Holder has complied with conditions 9 and 10 over the preceding financial year to 30 June.

11.2 The report required under condition 11.1 must be audited by an Approved Critical Infrastructure Auditor by a date specified by the Tribunal. The audit required by this condition 11.2 must be a comprehensive audit and must meet any requirements specified by the Tribunal. The Licence Holder must provide the audited report to the Commonwealth Representative at the same time that the report is provided to the Tribunal.

11.3 The Tribunal may provide guidance to the Approved Critical Infrastructure Auditor as to the Licence Holder's practices that have satisfied or will satisfy conditions 9 and 10.

11.4 The report required under condition 11.1 must be accompanied by a certification in writing supported by a resolution of the Board of the Licence Holder that, with respect to the relevant period: a) the Licence Holder has complied with conditions 9 and 10; or b) the Licence Holder has not complied with conditions 9 and 10, and certifying the nature and extent of each non-compliance and the steps taken by the Licence Holder to ensure compliance (and to preclude further non-compliance) and the timeframe within which it expects to achieve compliance.

kyys A0137729916v5 120465441 25.6.2015 Page 12 CONDITIONS RELATING TO MANAGEMENT SYSTEMS

12 Maintenance of certified management systems

12.1 Within two years after the date of this Licence, the Licence Holder must have and maintain: (a) an asset management system that is consistent with the International Standard ISO 55001 Asset Management System – Requirements; and (b) an environmental management system that is consistent with International Standard ISO 14001 Environmental Management, which comply with this condition 12.

12.2 The Licence Holder must ensure that, by the time it is required to comply with condition 12.1: (a) its asset management system is certified by an appropriately qualified person to be consistent with International Standard ISO 55001 Asset Management System – Requirements; and (b) its environmental management system is certified by an appropriately qualified person to be consistent with International Standard ISO 14001 Environmental Management.

12.3 The Licence Holder must ensure that, once its asset management system and environmental management systems are each certified in accordance with condition 12.2, the certifications are maintained for the remainder of the duration of the Licence.

12.4 The Licence Holder must notify the Tribunal, in accordance with any Reporting Manuals issued by the Tribunal, of any significant changes it proposes to make to its asset management system or environmental management system.

13 Implementation of management systems The Licence Holder must ensure that its asset management system and environmental management system are fully implemented and all relevant activities undertaken by it or any other network operator of its distribution system are carried out in accordance with the relevant management system.

CONDITIONS RELATING TO COMPLIANCE, REPORTING AND FEES

14 Reporting in accordance with Reporting Manuals The Licence Holder must prepare and submit reports in accordance with any Reporting Manuals issued by the Tribunal.

15 Complying with Audit Guidelines issued by the Tribunal The Licence Holder must comply with any Audit Guidelines issued by the Tribunal.

kyys A0137729916v5 120465441 25.6.2015 Page 13 16 Compliance management systems The Licence Holder must ensure internal systems are developed and maintained that are capable of effectively managing compliance with its Licence.

17 Compliance with statistical operating obligations The Licence Holder must provide to the Tribunal such operating and statistics and performance indicators as may be required from time to time by the Tribunal. The Tribunal will provide the Licence Holder with reasons for its request when the initial request is made and after that when a request relates to operating statistics and performance indicators that are of materially different type or category to that provided under the initial or subsequent request.

18 Information about compliance with Licence Conditions The Licence Holder must furnish to the Tribunal (at such times and in respect of such periods as the Tribunal may determine and in the manner and form specified by the Tribunal) such information as the Tribunal may determine, to enable the Tribunal to ascertain whether or not the Licence Holder is complying with the conditions of its Licence, the Act or the Regulations.

19 Information about compliance with Employment Guarantees

19.1 The Licence Holder must furnish to the Tribunal (at such times and in respect of such periods as the Tribunal may determine and in the manner and form specified by the Tribunal) such information as the Tribunal may determine, to enable the Tribunal to ascertain whether or not the Licence Holder is complying with the 'Employment Guarantees' set out in Schedule 4 to the Electricity Network Assets (Authorised Transactions) Act 2015.

19.2 The Licence Holder must comply at its own expense and within a reasonable timeframe nominated by the Tribunal, with any request from the Tribunal to have information provided under condition 19.1 audited by an Approved Auditor.

20 Licence fees

20.1 It is a condition of this Licence that the Licence Holder pay such fees (annual or otherwise) in connection with the holding of the Licence as may be determined by the Minister from time to time.

20.2 The Licence Holder must pay the fees referred to in condition 20.1 in the manner and within the period specified by the Tribunal.

kyys A0137729916v5 120465441 25.6.2015 Page 14 INTERPRETATION AND DEFINITIONS Interpretation In these Licence conditions, unless the context requires otherwise: (a) the singular includes the plural and vice versa; (b) headings are used for convenience only and do not affect the interpretation of these Licence conditions; (c) a reference to a document includes the document as modified from time to time and any document replacing it; (d) the word "person" includes a natural person and any body or entity whether incorporated or not; (e) references to conditions are references to conditions in these Licence conditions.

Definitions Expressions used in these Licence conditions that are defined in the Act or the Regulations have the meanings set out in the Act or the Regulations. In these Licence conditions: Act means the Electricity Supply Act 1995. Approved Auditor means an auditor nominated in accordance with conditions 7.8 to 7.11 (inclusive). Approved Critical Infrastructure Auditor means an auditor who has been approved by the Tribunal as having the necessary independence, experience, and expertise in system security or has otherwise demonstrated to the Tribunal's satisfaction the capability to audit compliance with the critical infrastructure licence conditions (being conditions 9, 10 and 11) and who is independent of the Licence Holder. Associate has the meaning given to that term in the Corporations Act 2001 (Cth). Audit Guidelines means any document setting out audit requirements for Licence Holders which is prepared by the Tribunal and is available on its website at www.ipart.nsw.gov.au as amended from time to time. Bulk Personal Data Records means any holdings or files of personal information (within the meaning of the Privacy Act 1988 (Cth)) about multiple individuals which contain fields or categories. Business Continuity Plan has the meaning given to it condition 8.1. CBD Sydney feeder means a feeder forming part of the triplex 11kV cable system supplying predominantly commercial high-rise buildings, within the City of Sydney.

kyys A0137729916v5 120465441 25.6.2015 Page 15 Commonwealth Representative means the First Assistant Secretary, with responsibility for Critical Infrastructure Security within the Commonwealth or equivalent level in a subsequent agency with responsibility for Critical Infrastructure Security. Note: At the time of varying this licence, the Commonwealth Representative is the First Assistant Secretary responsible for the Critical Infrastructure Centre within the Commonwealth Attorney General's Department. Customer means a wholesale or retail customer who is supplied electricity through a connection point on an electricity distributor’s system. Customer service standards means the customer service standards in Schedule 5 to these conditions. Distribution system means the distribution system of which the Licence Holder is a network operator. Distribution district has the meaning given to it in Division 2 of Part 7 of the Electricity Supply Act 1995. Excluded interruptions means excluded interruptions listed in Schedule 4 to these conditions. Feeder means a high-voltage line operating at over 1kV and generally at or below 22 kV that connects between a zone substation and a distribution substation. Feeder type means a CBD Sydney feeder, long rural feeder, short rural feeder or urban feeder as the case may be. Financial year means the period commencing on 1 July and ending 30 June the following calendar year.

First issue of conditions or first refers to the date of the first issue of this Licence being issue of this Licence 1 December 2016.

Individual feeder standards means the individual feeder standards in Schedule 3 to these conditions. Interruption means any temporary unavailability of electricity supply to a customer associated with an outage of the distribution system including outages affecting a single premises, but does not include disconnection. Interruption duration standards means the interruption duration standards set out in Schedule 5 to these conditions. Interruption frequency standards means the interruption frequency standards set out in Schedule 5 to these conditions. Licence means the distributor's licence authorising the Licence Holder to operate its distribution system. Licence Holder means a person who is the holder of a Licence.

kyys A0137729916v5 120465441 25.6.2015 Page 16 Load Data means data as to the quantum of electricity delivered (both historical and current load demand from or to any one or more sites (or their connection points) which satisfies each of the following criteria: i. it is not historical load data older than 30 days; ii. it is not fault data; iii. it describes a location that allows a customer(s) or connection point(s) to be identified; iv. it describes the date and time of the data record; and v. it describes a duration - a length of time that allows for a quantum to exist.

Local government area has the meaning given in the Local Government Act 1993. Long rural feeder means a feeder with a total feeder length greater than 200 km which is not a CBD Sydney feeder or an urban feeder. Metropolitan means the areas comprising the local government areas and suburbs listed in Schedule 7, but only to the extent that the Licence Holder may operate a Distribution system in the relevant areas in accordance with condition 1. Major event day has the meaning given in Schedule 6. Minister means the Minister responsible for administering the Act. Network overall reliability standards means the requirements imposed under condition 7 of these conditions. Non-metropolitan means areas in NSW other than areas defined as metropolitan. Planned interruption means an interruption that has been planned by the Licence Holder.

Protocol means a document of the type referred to in conditions 9.1 and 9.2, that is required by the Commonwealth and which must be agreed to between the Commonwealth Representative and the Licence Holder, the document may set out (among other things) the: i. specified purposes for which maintenance of distribution system equipment may be conducted offshore and the circumstances in which it may be conducted offshore; ii. methodology and activities to be undertaken to allow for maintenance and repairs of distribution system equipment to be carried out involving remote access from offshore; iii. the exceptional circumstances in which the Protocol applies; and iv. activities and processes which achieve requisite levels of cyber-security.

Quarter means a period of three months commencing 1 January, 1 April, 1 July and 1 October and concluding on the following 31 March, 30 June, 30 September and 31 December dates respectively. Regulations means regulations made under the Act. kyys A0137729916v5 120465441 25.6.2015 Page 17 Relevant Person means the Licence Holder, any other network operator of the distribution system, and any person who is contracted or sub- contracted by the Licence Holder to work on the distribution system. Reporting Manual means any document setting out reporting requirements for Licence Holders which is prepared by the Tribunal and is available on its website at www.ipart.nsw.gov.au as amended from time to time. SAIDI means the average derived from the sum of the durations of each sustained customer interruption (measured in minutes), divided by the total number of customers (averaged over the financial year) of the Licence Holder. SAIDI average standards means the standards set out in item 1, Schedule 2. SAIFI means the average derived from the total number of sustained customer interruptions divided by the total number of customers (averaged over the financial year) of the Licence Holder. SAIFI average standards means the standards set out in item 2, Schedule 2. Short rural feeder means a feeder with a total feeder route length less than 200 km, and which is not a CBD Sydney feeder or an urban feeder. Suburb means an area defined by boundaries determined and gazetted by the Geographical Names Board of New South Wales. Transacted distribution system means a transacted distribution system under the Electricity Network Assets (Authorised Transactions) Act 2015. Tribunal means the Independent Pricing and Regulatory Tribunal of New South Wales established under the Independent Pricing and Regulatory Tribunal Act 1992. Urban feeder means a feeder with actual maximum demand over the reporting period per total feeder route length greater than 0.3 MVA/km and which is not a CBD Sydney Feeder.

kyys A0137729916v5 120465441 25.6.2015 Page 18

SCHEDULE 1 – Authorised Areas The Licence Holder is authorised to operate a distribution system within all areas outside of its distribution district in which the Licence Holder operates a distribution system as at the date of this Licence, including any such areas notified by the Licence Holder to the Tribunal for the purposes of inclusion on any register maintained by the Tribunal.

kyys A0137729916v5 120465441 25.6.2015 Page 19 SCHEDULE 2 – NETWORK OVERALL RELIABILITY STANDARDS

1. SAIDI Average Reliability Duration Standards (Minutes per customer)

SAIDI (Minutes per customer) AUSGRID Feeder type CBD Sydney 45 Urban 80 Short-rural 300 Long-rural 700

2. SAIFI Average Reliability Interruption Standards (Number per customer)

SAIFI (Number per customer) AUSGRID Feeder type CBD Sydney 0.3 Urban 1.2 Short-rural 3.2 Long-rural 6

kyys A0137729916v5 120465441 25.6.2015 Page 20 SCHEDULE 3 – INDIVIDUAL FEEDER STANDARDS

1. SAIDI Individual Feeder Average Reliability Duration Standards (Minutes per customer)

SAIDI (Minutes per customer) AUSGRID Feeder type CBD Sydney 100 Urban 350 Short-rural 1000 Long-rural 1400

2. SAIFI Individual Feeder Standards Average Reliability Interruption Standards (Number per customer)

SAIFI (Number per customer) AUSGRID Feeder type CBD Sydney 1.4 Urban 4 Short-rural 8 Long-rural 10

kyys A0137729916v5 120465441 25.6.2015 Page 21 SCHEDULE 4 – EXCLUDED INTERRUPTIONS

The following types of interruptions (and no others) are excluded interruptions:

(a) an interruption of a duration of one minute or less; (b) an interruption resulting from: (i) load shedding due to a shortfall in generation; (ii) a direction or other instrument issued under the National Electricity Law, Energy and Utilities Administration Act 1987, the Essential Services Act 1988 or the State Emergency and Rescue Management Act 1989 to interrupt the supply of electricity; (iii) automatic shedding of load under the control of under- frequency relays following the occurrence of a power system under-frequency condition described in the Power System Security and Reliability Standards made under the National Electricity Rules; (iv) a failure of the shared transmission system; (c) a planned interruption; (d) any interruption to the supply of electricity on a Licence Holder’s distribution system which commences on a major event day; and (e) an interruption caused by a customer’s electrical installation or failure of that electrical installation.

kyys A0137729916v5 120465441 25.6.2015 Page 22 SCHEDULE 5 – CUSTOMER SERVICE STANDARDS

Interruption duration standard: 1. The interruption duration standard is the maximum duration, set out in column 2 of table 1, of an interruption to a customer’s premises located in the relevant area in column 1 of table 1.

Interruption frequency standard: 2. The interruption frequency standard is the maximum number of interruptions in a financial year set out in column 3 of table 1, to a customer’s premises located in the relevant area in column 1 of table 1:

Table 1

Column 1 Column 2 Column 3

Interruption frequency Type of area in Interruption duration standard (number of which customer’s standard (hours) interruptions and hours premises is located of duration)

4 interruptions of greater metropolitan 12 than or equal to 4 hours

4 interruptions of greater non-metropolitan 18 than or equal to 5 hours

Interruptions to be disregarded 3. In calculating the interruption duration standard or the interruption frequency standard the following types of interruptions (and no others) are excluded: (a) an interruption resulting from the following external causes: (i) a shortfall in generation; (ii) a failure or instability of the shared transmission system; (iii) a request or direction from an emergency service organisation; (b) a planned interruption; (c) an interruption within a region in which a natural disaster has occurred and: (i) the responsible Minister has made a declaration of a Natural Disaster enabling the NSW Disaster Assistance Arrangements to apply in respect of that natural disaster for that region; and

(ii) the interruption occurred during the period for which a declaration of a kyys A0137729916v5 120465441 25.6.2015 Page 23 Natural Disaster and NSW Disaster Assistance Arrangements were in effect; (d) an interruption caused by the effects of a severe thunderstorm or severe weather as advised by the Bureau of Meteorology. These effects may include the necessary operation of a circuit protection device which interrupts supply to customers in areas not directly impacted by the severe thunderstorm or severe weather. (e) an interruption caused by third party actions other than animal or vegetation interference (e.g. vehicle-hit-pole, vandalism) where the interruption is not also caused by any failure of the Licence Holder to comply with relevant plans, codes, guides or standards (e.g. low conductor clearance).

kyys A0137729916v5 120465441 25.6.2015 Page 24

SCHEDULE 6 – MAJOR EVENT DAY The following material is reprinted with permission from IEEE Std. 1366-2012, IEEE Guide for Electric Power Distribution Reliability Indices, by IEEE. The IEEE disclaims any responsibility or liability resulting from the placement and use in the described manner. For the avoidance of doubt and the promotion of consistency, Items “a”, “b”, “c” and “e” listed in Schedule 4 should be removed from daily records before applying the following methodology to calculate a major event day.

Explanation and Purpose The following process (“Beta Method”) is used to identify major event days which are to be excluded from the network overall reliability standards and individual feeder standards. The method is to be used provided that the natural log transformation of the data results closely resembles a Gaussian (normal) distribution. Where this is not the case, Ausgrid may seek the Tribunal’s approval to apply a different threshold value. Its purpose is to allow major events to be studied separately from daily operation, and in the process, to better reveal trends in a daily operation that would be hidden by the large statistical effect of major events. A major event day under the Beta Method is one in which the daily total system (i.e. not on a feeder type basis) SAIDI value (“daily SAIDI value”) exceeds a threshold value, TMED. The SAIDI is used as the basis of determining whether a day is a major event day since it leads to consistent results regardless of utility size and because SAIDI is a good indicator of operational and design stress. In calculating the daily total system SAIDI, any interruption that spans multiple days is deemed to accrue on the day on which the interruption begins. That is, all minutes without supply resulting from an interruption beginning on a major event day are deemed to have occurred in the major event day, including those minutes without supply occurring on following days. Determining a major event day The major event day identification threshold value TMED is calculated at the end of each financial year for each electricity distributor for use during the next financial year as follows: (a) Collect daily SAIDI values for the last five financial years. If fewer than five years of historical data are available, use all available historical data for the lesser period. (b) Only those days that have a daily SAIDI value will be used to calculate the TMED (i.e. days that did not have any interruptions are not included). (c) Take the natural logarithm (In) of each daily SAIDI value in the data set. (d) Find α (Alpha), the average of the logarithms (also known as the log-average) of the data set. (e) Find β (Beta), the standard deviation of the logarithms (also known as the log-standard deviation) of the data set. kyys A0137729916v5 120465441 25.6.2015 Page 25

(f) Complete the major event day threshold TMED using the following

equation: TMED = e(α + 2.5β) (g) Any day with daily SAIDI value greater than the threshold value TMED which occurs during the subsequent financial year is classified as a major event day.

Treatment of a major event day To avoid doubt, a major event day, and all interruptions beginning on that day, are excluded from the calculation of an electricity distributor’s SAIDI and SAIFI in respect of all of its feeder types.

From IEEE Std. 1366-2012. Copyright 2012. All rights reserved.

kyys A0137729916v5 120465441 25.6.2015 Page 26

SCHEDULE 7 – LIST OF METROPOLITAN AREAS

1. Local Government Areas ASHFIELD HUNTERS HILL PITTWATER AUBURN HURSTVILLE RANDWICK BANKSTOWN KOGARAH ROCKDALE BAULKHAM HILLS KU-RING-GAI RYDE BLACKTOWN LAKE MACQUARIE SHELLHARBOUR BOTANY BAY LANE COVE STRATHFIELD BURWOOD LEICHHARDT SUTHERLAND CAMDEN LIVERPOOL SYDNEY CAMPBELLTOWN MANLY WARRINGAH CANTERBURY MARRICKVILLE WAVERLEY CANADA BAY MOSMAN WILLOUGHBY FAIRFIELD NEWCASTLE WOLLONGONG GOSFORD NORTH SYDNEY WOOLLAHRA HOLROYD PARRAMATTA WYONG

HORNSBY PENRITH

2. Suburbs A. Blue Mountains area BLACKHEATH LINDEN BLAXLAND MEDLOW BATH BULLABURRA MOUNT RIVERVIEW FAULCONBRIDGE MOUNT VICTORIA GLENBROOK SPRINGWOOD HAWKESBURY HEIGHTS VALLEY HEIGHTS HAZELBROOK WARRIMOO KATOOMBA WENTWORTH FALLS LAPSTONE WINMALEE LAWSON WOODFORD LEURA YELLOW ROCK

kyys A0137729916v5 120465441 25.6.2015 Page 27

B. Cessnock-Bellbird area ABERDARE CESSNOCK BELLBIRD KEARSLEY BELLBIRD HEIGHTS NULKABA

C. Kiama area BOMBO KIAMA HEIGHTS KIAMA MINNAMURRA

KIAMA DOWNS

D. Kurri Kurri-Weston area ABERMAIN PELAW MAIN HEDDON GRETA STANFORD MERTHYR KURRI KURRI WESTON

NEATH

E. Maitland area ABERGLASSLYN MOUNT DEE ASHTONFIELD OAKHAMPTON BOLWARRA OAKHAMPTON HEIGHTS BOLWARRA HEIGHTS PITNACREE EAST MAITLAND RAWORTH HORSESHOE BEND RUTHERFORD LARGS SOUTH MAITLAND LORN TELARAH LOUTH PARK TENAMBIT MAITLAND THORNTON METFORD WOODBERRY

MORPETH

kyys A0137729916v5 120465441 25.6.2015 Page 28

F. Newcastle Industrial area

FERN BAY WILLIAMTOWN

FULLERTON COVE

G. Port Stephens area CORLETTE SALAMANDER BAY FINGAL BAY SHOAL BAY NELSON BAY SOLDIERS POINT H. Raymond Terrace area HEATHERBRAE TOMAGO

RAYMOND TERRACE I. Richmond-Windsor area BLIGH PARK NORTH RICHMOND CLARENDON RICHMOND HOBARTVILLE SOUTH WINDSOR MCGRATHS HILL VINEYARD MULGRAVE WINDSOR

kyys A0137729916v5 120465441 25.6.2015 Page 29

Annexure C – Compliance Checklists

December 2019

2019 TAPR - NER v124 REQUIREMENTS CHECKSHEET

Section in NER Clause NER Requirements DTAPR Subject to paragraph 5.12.2 (b), by 30 June each year all TNSP's must publish an 5.12.2 (a) TAPR setting out the results of the annual planning review conducted in Throughout accordance with clause 5.12.1. If a Network Service Provider is a TNSP only because it owns, operates or 5.12.2 (b) controls dual function assets then it may publish its TAPR in the same document Throughout and at the same time as its DAPR. 5.12.2 (c) The TAPR must set out: see below the forecast loads submitted by a DNSP in accordance with clause 5.11.1 or as modified 5.12.2 (c)(1) 6.2 in accordance with clause 5.11.1(d), including at least: a description of the forecasting methodology, sources of input information, and the 5.12.2 (c)(1)(i) 6.2 assumptions applied in respect of the forecast loads; a description of high, most likely and low growth scenarios in respect of the forecast 5.12.2 (c)(1)(ii) 6.2 loads; an analysis and explanation of any aspects of forecast loads provided in the 5.12.2 (c)(1)(iii) Transmission Annual Planning Report that have changed significantly from forecasts 6.2 provided in the Transmission Annual Planning Report from the previous year; and an analysis and explanation of any aspects of forecast loads provided in the 5.12.2 (c)(1)(iv) Transmission Annual Planning Report from the previous year which are significantly 6.2 different from the actual outcome; for all network asset retirements, and for all network asset de-ratings that would result in a network constraint, that are planned over the minimum planning period specified in 5.12.2 (c)(1A) 4 clause 5.12.1(c), the following information in sufficient detail relative to the size or significance of the asset: 5.12.2 (c)(1A)(i) a description of the network asset, including location; 4 the reasons, including methodologies and assumptions used by the Transmission Network Service Provider for deciding that it is necessary or prudent for the network 5.12.2 (c)(1A)(ii) 4 asset to be retired or de-rated, taking into account factors such as the condition of the network asset; the date from which the Transmission Network Service Provider proposes that the 5.12.2 (c)(1A)(iii) 4 network asset will be retired or de-rated; and if the date to retire or de-rate the network asset has changed since the previous 5.12.2 (c)(1A)(iv) 4 Transmission Annual Planning Report, an explanation of why this has occurred; for the purposes of subparagraph (1A), where two or more network assets are: (i) of the same type; (ii) to be retired or de-rated across more than one location; 5.12.2 (c)(1B) (iii) to be retired or de-rated in the same calendar year; and 4 (iv) each expected to have a replacement cost less than $200,000 (as varied by a cost threshold determination), those assets can be reported together... 6.1.2, 5.12.2 (c)(2) planning proposals for future connection points; 7.1, 7.5 a forecast of constraints and inability to meet the network performance requirements set 5.12.2 (c)(3) in schedule 5.1 or relevant legislation or regulations of a participating jurisdiction over 1, 6 3, and 5 years, including at least: 5.12.2 (c)(3)(i) a description of the constraints and their causes; 6 5.12.2 (c)(3)(ii) the timing and likelihood of the constraints; 6 a brief discussion of the types of planned future projects that may address the 5.12.2 (c)(3)(iii) 6 constraints over the next 5 years, if such projects are required; and sufficient information to enable an understanding of the constraints and how such 5.12.2 (c)(3)(iv) 6 forecasts were developed; in respect of information required by subparagraph 5.12.2 (c)(3), where an estimated 5.12.2 (c)(4) reduction in forecast load would defer a forecast constraint for a period of 12 months, 6 include: 5.12.2 (c)(4)(i) the year and months in which a constraint is forecast to occur; 6 the relevant connection points at which the estimated reduction in forecast load may 5.12.2 (c)(4)(ii) 6 occur; 5.12.2 (c)(4)(iii) the estimated reduction in forecast load in MW needed; and 6 a statement of whether the TNSP plans to issue a Request For Proposals for augmentation or a non-network option identified by the annual planning review 5.12.2 (c)(4)(iv) 6 conducted under clause 5.12.1 (b) and if so, the expected date the request will be issued;

Page C1 of C6 2019 TAPR - NER v124 REQUIREMENTS CHECKSHEET

Section in NER Clause NER Requirements DTAPR for all proposed augmentations to the network the following information, in sufficient 5.12.2 (c)(5) detail relative to the size or significance of the project and the proposed operational date 6 of the project: project/asset name and the month and year in which it is proposed that the aset will 5.12.2 (c)(5)(i) 6 become operational; the reason for the actual or potential constraint, if any, or inability, if any, to meet the network performance requirements set out in schedule 5.1 or relevant legislation or 5.12.2 (c)(5)(ii) 6 regulations of a participating jurisdiction, including load forecasts and all assumptions used; the proposed solution to the constriant or inability to meet the newtork performance 5.12.2 (c)(5)(iii) 6 requirements identified in subparagraph (ii), if any: 5.12.2 (c)(5)(iv) total cost of the proposed solutions; 7 whether the proposed solution will have a material inter-network impact. In assessing whether an augmentation to the network will have a material inter-network impact a 5.12.2 (c)(5)(v) 6.1.3 TNSP must have regard to the objective set of criteria published by AMEO in accordance with clause 5.21 (if any such criteria have been published by AEMO); and other reasonable network options and non-network options considered to address the actual or potential constraint or inability to meet the network performance requirements identifield in subparagraph (ii), if any. Other reasonable network and non-network 5.12.2 (c)(5)(vi) 6.3, 6.4, 6.5 options include, but are not limited to, interconnections, generation options, demand side options, market network service options and options involving other transmission and distribution networks. the manner in which the proposed augmentations relate to the most recent NTNDP (National Transmission Network Development Plan) and the development strategies for 5.12.2 (c)(6) 3.6.1 current or potential national transmission flow paths (NTFPs) that are specified in that NTNDP. for proposed new or modified emergency frequency control schemes, the manner in 5.12.2 (c)(6A) 6.6 which the project relates to the most recent power system frequency risk review; information on the Transmission Network Service Provider’s asset management 5.12.2 (c)(7) 10 approach, including: a summary of any asset management strategy employed by the Transmission 5.12.2 (c)(7)(i) 10 Network a summary of any issues that may impact on the system constraints identified in the 5.12.2 (c)(7)(ii) Transmission Annual Planning Report that has been identified through carrying out 10 asset management; and information about where further information on the asset management strategy and 5.12.2 (c)(7)(iii) methodology adopted by the Transmission Network Service Provider may be 10 obtained. 5.12.2 (c)(8) any information requirement to be included in an TAPR under: see below clause 5.16.3(c) in relation to a network investment which is determined to be required 5.12.2 (c)(8)(i) 7.4 to address an urgent and unforeseen network issue; or clauses 5.20B.4(h) and (i) and clauses 5.20C.3(f) and (g) in relation to network 5.12.2 (c)(8)(ii) investment and other activities to provide inertia network services, inertia support N/A activities or system strength services. emergency controls in place under clause S5.1.8, including the Network Service 5.12.2 (c)(9) Provider's assessment of the need for new or altered emergency controls under that 6.7 clause; 5.12.2 (c)(10) facilities in place under clause S5.1.10; 6.6 an analysis and explanation of any other aspects of the Transmission Annual Planning 5.12.2 (c)(11) Report that have changed significantly from the preceding year's Transmission Annual 2.5 and 4 Planning Report, including the reasons why the changes have occurred; and the results of joint planning (if any) undertaken with a Transmission Network Service Provider under clause 5.14.3 in the preceding year, including a summary of the process 5.12.2 (c)(12) 8.1 and methodology used by the Transmission Network Service Providers to undertake joint planning and the outcomes of that joint planning.

Page C2 of C6 2019 DAPR - NER v124 REQUIREMENTS CHECKSHEET

Section in NER Clause NER Task Description DTAPR 5.13.2 A DNSP must publish a Distribution Annual Planning Report: See below 5.13.2(a) by 31 December each year Throughout 5.13.2(b) including results of annual planning review Throughout 5.13.2(c) with information as described in Schedule 5.8 Throughout 5.13.2(d) unless separately reported as required by legislation n/a must include contact details for a suitably qualified staff member to whom queries may 5.13.2(e) inside cover be directed 5.13.3 Distribution system limitation template 5.13.2(a)-(c) Requirements of the template that the AER must provide n/a At the same time as it publishes its Distribution Annual Planning Report each year, a Distribution Network Service Provider must publish a report which contains the 2.6, 5.13.2(d) information specified in paragraph (c) in the form required by the system limitation Ausgrid website template. Information regading the Distribution Network Servcie Provider and its network, S5.8(a) See below including: S5.8(a)(1) provide a description of Ausgrid’s network 2.1 & 2.2 S5.8(a)(2) provide a description of Ausgrid's operating environment 2.1 & 2.2 S5.8(a)(3) provide a description of the number and types of distribution assets 2.2 provide methodologies used in preparing the Distribution Annual Planning Report, S5.8(a)(4) including methodologies used to identify system limitations and any assumptions 2.3 & 2.4 applied provide analysis and explanation of any aspects of forecasts and information provided in S5.8(a)(5) the Distribution Annual Planning Report that have changed significantly from previous 2.5, 2.6, 3.1.2, 4 forecasts and information in the preceding year. S5.8(b) Forecasts for the forward planning period, including at least: See below a description of the forecasting methodology used, sources of input information, and the S5.8(b)(1) 3.2, 3.4, 3.5 assumptions applied; S5.8(b)(2) Provide load forecasts: See below S5.8(b)(2)(i) at the transmission-distribution connection points 3.3 S5.8(b)(2)(ii) for sub-transmission lines, and 3.1, 3.4 S5.8(b)(2)(iii) for zone substations 3.1, 3.2 S5.8(b)(2) Including, where applicable, for each item above: See below S5.8(b)(2)(iv) total capacity 3.1 S5.8(b)(2)(v) firm delivery capacity for summer periods and winter periods 3.1 peak load (summer or winter and an estimate of the number of hours per year that 95% S5.8(b)(2)(vi) 3.1 of peak is expected to be reached) S5.8(b)(2)(vii) power factor at time of peak load 3.1 S5.8(b)(2)(viii) load transfer capacities 3.1, 3.5.1 S5.8(b)(2)(ix) generation capacity of known embedded generating units 3.1 Provide forecasts of future transmission-distribution connection points (and any S5.8(b)(3) associated connection assets), sub-transmission lines and zone substations, including 6.1 to 6.4 for each future transmission-distribution connection point and zone substation: S5.8(b)(3)(i) its location 6.1 to 6.4 S5.8(b)(3)(ii) future loading level 6.1 to 6.4 S5.8(b)(3)(iii) proposed commissioning time (estimate of month and year) 6.1 to 6.4 forecasts of Ausgrid’s performance against any reliability targets in a service target S5.8(b)(4) 9.1.4 performance incentive scheme ; and Provide a description of any factors that may have a material impact on Ausgrid’s S5.8(b)(5) see below network , including factors affecting; S5.8(b)(5)(i) fault levels 3.6.1 S5.8(b)(5)(ii) voltage levels 3.6.2 S5.8(b)(5)(iii) other power system security requirements 3.6.3 S5.8(b)(5)(iv) the quality of supply to other Network Users (where relevant); and 3.6.4 S5.8(b)(5)(v) ageing and potentially unreliable assets 5 & 10 for all network asset retirements, and for all network asset de-ratings that would result in a system limitation, that are planned over the forward planning period, S5.8(b1) See below the following information in sufficient detail relative to the size or significance of the asset:

Page C3 of C6 2019 DAPR - NER v124 REQUIREMENTS CHECKSHEET

Section in NER Clause NER Task Description DTAPR S5.8(b1)(1) a description of the network asset, including location; 4 & 5 the reasons, including methodologies and assumptions used by the Distribution Network Service Provider, for deciding that it is necessary or prudent for the network asset to be S5.8(b1)(2) 4 & 5 retired or de-rated, taking into account factors such as the condition of the network asset; the date from which the Distribution Network Service Provider proposes that the network S5.8(b1)(3) 4 & 5 asset will be retired or de-rated; and if the date to retire or de-rate the network asset has changed since the previous S5.8(b1)(4) 4 & 5 Distribution Annual Planning Report, an explanation of why this has occurred; S5.8(b2) for the purposes of subparagraph (b1), where two or more network assets are: See below S5.8(b2)(1) of the same type; 4 S5.8(b2)(2) to be retired or de-rated across more than one location; 4 S5.8(b2)(3) to be retired or de-rated in the same calendar year; and 4 each expected to have a replacement cost less than $200,000 (as varied by a cost S5.8(b2)(4) threshold determination), those assets can be reported together by setting out in the 4 Distribution Annual Planning Report: a description of the network assets, including a summarised description of their S5.8(b2)(5) 4 locations; the reasons, including methodologies and assumptions used by the Distribution Network Service Provider, for deciding that it is necessary or prudent for the network assets to be S5.8(b2)(6) 4 retired or de-rated, taking into account factors such as the condition of the network assets; the date from which the Distribution Network Service Provider proposes that the network S5.8(b2)(7) 4 assets will be retired or de-rated; and if the calendar year to retire or de-rate the network assets has changed since the S5.8(b2)(8) 4 previous Distribution Annual Planning Report, an explanation of why this has occurred; Information on system limitations for sub-transmission lines and zone S5.8(c) See below substations, including at least: S5.8(c)(1) estimates of the location and timing (month(s) and year) of the system limitation 3 & 5 analysis of any potential for load transfer capacity between supply points that may S5.8(c)(2) 3 & 5 decrease the impact of the system limitation or defer the requirement for investment impact of the system limitation, if any, on the capacity at transmission distribution S5.8(c)(3) 3 & 5 connection points a brief discussion of the potential solutions that may address the system limitation in the S5.8(c)(4) 3 & 5 forward planning period, if a solution is required; and where an estimated reduction in forecast load would defer a forecast system limitation S5.8(c)(5) See below for a period of, at least, 12 months, include: S5.8(c)(5)(i) an estimate the month and year in which a system limitation is forecast to occur 3 & 5 the relevant connection points at which the estimated reduction in forecast load may S5.8(c)(5)(ii) 3 & 5 occur the estimated reduction in forecast load in MW or improvements in power factor needed S5.8(c)(5)(iii) 3 & 5 to defer the forecast system limitation. for any primary distribution feeders for which Ausgrid has prepared forecasts of S5.8(d) maximum demands under NER clause 5.13.1(d)(1)(iii) and which are currently 5.26 experiencing an overload, or are forecast to experience an overload in the next S5.8(d)(1) the location of the primary distribution feeder; 5.26 the extent to which load exceeds, or is forecast to exceed, 100% (or lower utilisation S5.8(d)(2) factor, as appropriate) of the normal cyclic rating under normal conditions (in summer 5.26 periods or winter periods); S5.8(d)(3) the types of potential solutions that may address the overload or forecast overload; and 5.26 where an estimated reduction in forecast load would defer a forecast overload for a S5.8(d)(4) 5.26 period of 12 months, include: S5.8(d)(4)(i) an estimate of the month and year in which the overload is forecast to occur; 5.26 a summary of the location of relevant connection points at which the estimated S5.8(d)(4)(ii) 5.26 reduction in forecast load would defer the overload;

Page C4 of C6 2019 DAPR - NER v124 REQUIREMENTS CHECKSHEET

Section in NER Clause NER Task Description DTAPR the estimated reduction in forecast load in MW needed to defer the forecast system S5.8(d)(4)(iii) 5.26 limitation. A high-level summary of each RIT-D project for which the regulatory investment S5.8(e) test for distribution has been completed in the preceding year or is in progress, 7.1 including: if the regulatory investment test for distribution is in progress, the current stage in the S5.8(e)(1) 7.1 process S5.8(e)(2) a brief description of the identified need 7.1 a list of credible options assessed or being assessed (to the extent reasonably S5.8(e)(3) 7.1 practicable) S5.8(e)(4) If the RIT-D has been completed, a brief description of the conclusion, including: 7.1 S5.8(e)(4)(i) the net economic benefit of each credible option 7.1 S5.8(e)(4)(ii) the estimated capital cost of the preferred option; and 7.1 the estimated construction timetable and commissioning date (where relevant) of the S5.8(e)(4)(iii) 7.1 preferred option Any impacts on Network Users, including any potential material impacts on connection S5.8(e)(5) 7.1 charges and distribution use of system charges that have been estimated. For each identified system limitation which Ausgrid has determined will require a S5.8(f) regulatory investment test for distribution , provide an estimate of the month and 7.1 year when the test is expected to commence a summary of all committed investments to be carried out within the forward planning period with an estimated capital cost of $2 million or more (as varied by S5.8(g) 7.3 & 7.4 a cost threshold determination) that are to address an urgent and unforeseen network issue as described in clause 5.17.3(a)(1), including: a brief description of the investment, including its purpose, its location, the estimated S5.8(g)(1) capital cost of the investment and an estimate of the date (month and year) the 7.3 & 7.4 investment is expected to become operational; a brief description of the alternative options considered by the Distribution Network Service Provider in deciding on the preferred investment, including an explanation of the S5.8(g)(2) ranking of these options to the committed project. Alternative options could include, but 7.3 & 7.4 are not limited to, generation options, demand side options, and options involving other distribution or transmission networks; Include the results of any joint planning undertaken with the Transmission S5.8(h) 8.1 Network Service Provider in the preceding year, including: a summary of the process and methodology used by Ausgrid and the relevant S5.8(h)(1) 8.1.1 Transmission Network Service Provider to undertake joint planning; a brief description of any investments that have been planned through this process, S5.8(h)(2) including the estimated capital costs of the investment and an estimate of the timing 8.1.2 & 8.1.3 (month and year) of the investment; and S5.8(h)(3) where additional information on the investments may be obtained. 8.1.4 Include the results of any joint planning undertaken with other Distribution S5.8(i) 8.2 Network Service Providers in the preceding year, including: a summary of the process and methodology used by the Distribution Network Service S5.8(i)(1) 8.2.1 Providers to undertake joint planning; a brief description of any investments that have been planned through this process, S5.8(i)(2) including the estimated capital cost of the investment and an estimate of the timing 8.2.2 & 8.2.3 (month and year) of the investment; and S5.8(i)(3) where additional information on the investments may be obtained. 8.2.4 Provide information on the performance of the Distribution Network Service S5.8(j) 9 Providers network, including: a summary description of the reliability measures and standards in applicable regulatory S5.8(j)(1) 9.1 instruments; a summary description of the quality of supply standards that apply, including the S5.8(j)(2) 9.2 relevant codes, standards and guidelines a summary description of the performance of the distribution network against the S5.8(j)(3) 9.1 & 9.3 reliability and quality measures and standards for the preceding year where the network reliability and quality measures and standards were not met in the S5.8(j)(4) 9.1, 9.4 & 9.5 preceding year, information on the corrective action taken or planned

Page C5 of C6 2019 DAPR - NER v124 REQUIREMENTS CHECKSHEET

Section in NER Clause NER Task Description DTAPR a summary description of Ausgrid’s processes to ensure compliance with the measures S5.8(j)(5) 9.1 & 9.5 and standards described under subparagraphs (1) and (2) above; and an outline of the information contained Ausgrid’s most recent submission to the AER S5.8(j)(6) 9.1.3 under the service target performance incentive scheme (RIN). S5.8(k) Include information on Ausgrid’s asset management approach, including: 10 S5.8(k)(1) a summary of any asset management strategy employed by the DNSP; 10.1 & 10.2 an explanation of how the Distribution Network Service Provider takes into account the S5.8(k)(1A) cost of distribution losses when developing and implementing its asset management 10.3 and investment strategy a summary of any issues that may impact on the system limitations identified in the S5.8(k)(2) Distribution Annual Planning Report that has been identified through carrying out asset 3.6 management information about where further information on the asset management strategy and S5.8(k)(3) 10.4 methodology adopted by Ausgrid may be obtained. S5.8(l) Include information on Ausgrid's demand management activities, including: 11 S5.8(l)(1) a qualitative summary of: See below non-network solutions that have been considered in the past year, including generation S5.8(l)(1)(i) 11.3 from embedded generating units; key issues arising from applications to connect embedded generating units received in S5.8(l)(1)(ii) 3.6.5 the past year; actions taken to promote non-network initiatives in the preceding year, including S5.8(l)(1)(iii) 11.5 generation from embedded generating units; and the DNSPs plans for demand management and generation from embedded generating S5.8(l)(iv) 11.4 units over the forward planning period (5 years for Distribution). S5.8(l)(2) a quantitative summary of: 11.6 S5.8(l)(2)(i) connection enquiries received under clause 5.3A.5; 11.6 S5.8(l)(2)(ii) applications to connect received under clause 5.3A.9; and 11.6 S5.8(l)(2)(iii) the average time taken to complete applications to connect; 11.6 Include information on Ausgrid's investments in information technology and communication systems which occurred in the preceding year, and planned S5.8(m) 12 investments in information technology and communication systems related to management of network assets in the forward planning period. Include a regional development plan consisting of a map of Ausgrid's network as S5.8(n) a whole or maps by regions in accordance with Ausgrid's planning methodology See below or as required under any regulatory obligation or requirement identifying: sub-transmission lines, zone substations and transmission-distribution connection S5.8(n)(1) 5 points; any system limitations that have been forecast to occur in the forward planning period, S5.8(n)(2) 5 including, where they have been identified overloaded primary distribution feeders.

Page C6 of C6