Suncor Energy Products Inc. P.O. Box 2844 150 - 6th Avenue SW Calgary, Alberta, T2P 3E3 Tel 403 296 8000 Fax 403 724 3699 www.suncor.com

March 1, 2016

Ministry of the Environment and Climate Change Environmental Approvals Branch 2 St. Clair Avenue West, Floor 12A , ON, M4V 1L5

Attention: Nick Colella, Senior Project Evaluator

Dear Mr. Colella:

Reference: Suncor Energy – Adelaide Wind Power Project: Renewable Energy Approval Amendment

Suncor Energy Products Inc. received a Renewable Energy Approval (REA) for the Suncor Energy Adelaide Wind Power Project (the Project) on December 11, 2013 (#8279-9AUP2B). The REA was assigned to a subsidiary, Suncor Adelaide Wind Limited Partnership (Suncor) on August 5, 2014. Since receipt of the REA, Suncor has identified the need to make a minor amendment to the Project as it was described in the REA Application documents and subsequently approved by the Ministry.

The Project started construction in spring 2014 and became fully operational on January 29, 2015. During a recent internal review of the Project’s final as-built design, it was noted that an access road and collector cable leading to Turbine WTG 22 was installed with a slight deviation from the approved location. The as-built access road and cable leading to WTG 22 was constructed on top of an existing farm lane. A portion of the as built location of the cable and access road were constructed through an unassessed area of land approximately 0.35 acres in size. Please see the attached drawing entitled T22 Access Road/Cable Amendment which shows the route approved as part of the REA and the as-built location of the access road and collector cable. The participating landowner of the subject property has approved of the as-built location.

Suncor is seeking to amend the Project’s REA to reflect the as-built location of the access road and collector cable.

The deviation in location of the as-built access road and collector cable are minor in scale and remains outside of all natural features. No new potential effects or mitigation measures not previously assessed as part of the REA application documents have been identified. In due diligence, Stantec was retained by Suncor to conduct a Stage 2 archaeological assessment for the portion of access road and collector cable which had not been previously captured by the original Stage 2 surveys. As documented in the report, no construction impacts were evident within the additional study area, no archaeological resources were identified and thus, no further archaeological assessment of the additional study area is required. A copy of the report and associated acceptance letter by the Ministry of Tourism, Culture and Sport is attached.

With the exception of a minor change to the Site Plan for this property as provided in the REA application documents, no additional changes are required. Any changes to the REA application documents and associated Site Plan are considered to have been addressed by the issuance of this letter and its attachments.

2

Thank you for your attention to this matter and please do not hesitate to contact me if you have any questions or concerns regarding the proposed amendment.

Yours sincerely,

Mark Kozak Project Manager, Renewable Energy Suncor Energy Products Inc. By its duly authorized agent, Suncor Energy Services Inc.

Telephone: (647) 467-8461 Email: [email protected] Website: www.suncor.com/adelaidewind

Attachments: 1. Figure - T22 Access Road/Cable Amendment 2. Stage 2 Archaeological Assessment Report and MTCS Acceptance Letter Ü

47.13m

59.96m

Suncor Energy Inc. 150 - 6th Ave. S.W 1:3,000 Calgary, AB Access Road/ Collector Line - REA T2P 3E3 0 0.045 0.09 As Built Access Road/ Collector Line T22 ACCESS ROAD/CABLE Kilometres AMENDMENT OPERATING AREA: DRAWN BY: MAP REVISED: REV: NAD 1983 UTM Zone 17N Adelaide DSTEFFENSEN 11/27/2015 A NOTES: REQUESTED BY: FILE: M. Kozak RN0014.mxd

THIS DRAWING IS COPYRIGHT AND IS THE PROPERTY OF SUNCOR ENERGY. IT MAY NOT BE COPIED, REPRODUCED OR USED IN WHOLE OR IN PART IN ANY WAY WITHOUT WRITTEN PERMISSION FROM SUNCOR ENERGY OPERATING INC. USE OF THIS DRAWING IS PERMITTED ONLY FOR THE SPECIFIC USE FOR WHICH IT WAS ISSUED. Page 1 of 1

Ministry of Tourism, Culture and Sport Ministère du Tourisme, de la Culture et du Sport

Archaeology Programs Unit Unité des programmes d'archéologie Programs and Services Branch Direction des programmes et des services Culture Division Division de culture 401 Bay Street, Suite 1700 401, rue Bay, bureau 1700 Toronto ON M7A 0A7 Toronto ON M7A 0A7 Archaeology@.ca [email protected]

Feb 1, 2016

Parker S. Dickson (P256) Stantec Consulting 171 Queens London ON N6A 5J7

RE: RE: Entry into the Ontario Public Register of Archaeological Reports: Archaeological Assessment Report Entitled, "Stage 2 Archaeological Assessment: Additional Lands on the Suncor Energy Adelaide Wind Power Project, Part of Lot 5, Concession 2 North of Egremont Road, Geographic Township of Adelaide, now Township of Adelaide-Metcalfe, Middlesex County, Ontario ", Dated Jan 26, 2016, Filed with MTCS Toronto Office on N/A, MTCS Project Information Form Number P256-0385-2015, MTCS File Number HD00507

Dear Mr. Dickson:

The above-mentioned report, which has been submitted to this ministry as a condition of licensing in accordance with Part VI of the Ontario Heritage Act, R.S.O. 1990, c 0.18 has been entered into the Ontario Public Register of Archaeological Reports without technical review.1

Please note that the ministry makes no representation or warranty as to the completeness, accuracy or quality of reports in the register.

Should you require further information, please do not hesitate to send your inquiry to [email protected]

cc. Archaeology Licensing Officer Chris Scott,Suncor Energy Products Inc. Sarah Paul,Ministry of Environment and Climate Change

1 In no way will the ministry be liable for any harm, damages, costs, expenses, losses, claims or actions that may result: (a) if the Report(s) or its recommendations are discovered to be inaccurate, incomplete, misleading or fraudulent; or (b) from the issuance of this letter. Further measures may need to be taken in the event that additional artifacts or archaeological sites are identified or the Report(s) is otherwise found to be inaccurate, incomplete, misleading or fraudulent.

Stage 2 Archaeological Assessment: Additional Lands on the Suncor Energy Adelaide Wind Power Project

Part of Lot 5, Concession 2 North of Egremont Road, Geographic Township of Adelaide, now Township of Adelaide-Metcalfe, Middlesex County, Ontario

Prepared for: Mr. Chris Scott, P. Eng. Suncor Energy Products Inc. 207 Douglas Street Stratford, ON N5A 5P8 Tel: (519) 328-0424 Email: [email protected]

Prepared by: Stantec Consulting Ltd. 171 Queens Avenue, 6th Floor London ON N6A 5J7

Licensee: Parker Dickson Licence Number: P256 PIF Number: P256-0385-2015 FIT Number: FIT-002187-WIN-130-601 Project Number: 160940226

ORIGINAL REPORT

January 26, 2016

STAGE 2 ARCHAEOLOGICAL ASSESSMENT: ADDITIONAL LANDS ON THE SUNCOR ENERGY ADELAIDE WIND POWER PROJECT

Table of Contents

EXECUTIVE SUMMARY ...... V

1.0 PROJECT CONTEXT ...... 1.1 1.1 DEVELOPMENT CONTEXT ...... 1.1 1.2 OBJECTIVES ...... 1.2 1.3 HISTORICAL CONTEXT ...... 1.2 1.3.1 Post-contact Aboriginal Resources ...... 1.2 1.3.2 Historic Euro-Canadian Resources ...... 1.3 1.3.3 Recent Reports ...... 1.4 1.4 ARCHAEOLOGICAL CONTEXT ...... 1.5 1.4.1 The Natural Environment ...... 1.5 1.4.2 Pre-contact Aboriginal Resources ...... 1.5 1.4.3 Previously Identified Archaeological Sites and Surveys ...... 1.6 1.4.4 Determination of Archaeological Potential ...... 1.8 1.4.5 Existing Conditions ...... 1.9

2.0 FIELD METHODS ...... 2.1

3.0 RECORD OF FINDS ...... 3.3

4.0 ANALYSIS AND CONCLUSIONS ...... 4.1

5.0 RECOMMENDATIONS ...... 5.1

6.0 ADVICE ON COMPLIANCE WITH LEGISLATION ...... 6.1

7.0 BIBLIOGRAPHY AND SOURCES ...... 7.1

8.0 IMAGES...... 8.1 8.1 PLATES ...... 8.1 8.2 PHOTOGRAPHS ...... 8.2

9.0 MAPS ...... 9.1

10.0 CLOSURE ...... 10.1

LIST OF TABLES Table 1: Historic Information as Illustrated on the 1878 Map of Adelaide Township ...... 1.4 Table 2: Recent Reports Concerning the Suncor Energy Adelaide Wind Power Project1.4 Table 3: Cultural Chronology of the County of Middlesex ...... 1.5 Table 4: Inventory of Documentary Record ...... 3.3

dp w:\160940226 - suncor adelaide st 2 and 3\work_program\report\additional stage 2 - 2015\final\p256-0385-2015_26jan2016_re.docx i STAGE 2 ARCHAEOLOGICAL ASSESSMENT: ADDITIONAL LANDS ON THE SUNCOR ENERGY ADELAIDE WIND POWER PROJECT

LIST OF FIGURES Figure 1: Location of Additional Study Area ...... 9.2 Figure 2: Additional Study Area Requiring Stage 2 Survey ...... 9.3 Figure 3: Treaties and Purchases (Adapted from Morris 1943) ...... 9.4 Figure 4: Portion of the 1878 Historic Map of Adelaide Township ...... 9.5 Figure 5: Stage 2 Methods and Results ...... 9.6

dp w:\160940226 - suncor adelaide st 2 and 3\work_program\report\additional stage 2 - 2015\final\p256-0385-2015_26jan2016_re.docx ii STAGE 2 ARCHAEOLOGICAL ASSESSMENT: ADDITIONAL LANDS ON THE SUNCOR ENERGY ADELAIDE WIND POWER PROJECT

Project Personnel

Project Manager: Tracie Carmichael, BA, B.Ed. (R140)

Licensed Archaeologist: Parker Dickson, MA (P256)

Licensed Field Director: Parker Dickson, MA (P256)

Field Technicians: Krista Lane, BA (R382)

Report Writer: Krista Lane, BA (R382)

Quality Review Colin Varley, MA, RPA (P002)

Licensee Review Parker Dickson, MA (P256)

Independent Review: Tracie Carmichael, BA, B.Ed. (R140)

Acknowledgments

Proponent Contact: Chris Scott, P. Eng. – Suncor Energy Products Inc. Mark Kozak – Suncor Energy Products Inc.

Ministry of Tourism, Culture and Sport: Robert von Bitter

dp w:\160940226 - suncor adelaide st 2 and 3\work_program\report\additional stage 2 - 2015\final\p256-0385-2015_26jan2016_re.docx iii

STAGE 2 ARCHAEOLOGICAL ASSESSMENT: ADDITIONAL LANDS ON THE SUNCOR ENERGY ADELAIDE WIND POWER PROJECT

Executive Summary

The Suncor Adelaide Wind Power Project (the Project) includes an 18 wind turbine generator facility and associated infrastructure, with a total nameplate capacity of 40 megawatts (MW), located in the Township of Adelaide-Metcalfe, Middlesex County, Ontario. A Stage 1 archaeological assessment for the Project was conducted by Golder Associates Ltd. (Golder) in 2012 (Golder 2012a) and a Stage 2 archaeological assessment was conducted for the Project by Golder (2012b) and Stantec Consulting Ltd. (Stantec) (Stantec 2012, Stantec 2013, Stantec 2014) on behalf of Suncor Energy Products Inc. (Suncor). The Stage 1 and 2 assessments for the Project were undertaken in order to meet the requirements for an application for a Renewable Energy Approval (REA), as outlined in Ontario Regulation 359/09 sections 21 and 22 of the Environmental Protection Act (Government of Ontario 1990).

A REA was issued to Suncor on December 11, 2013 (REA #8279-9AUP2B). The REA was issued for the construction, installation, operation, use and retiring of the Suncor Adelaide Wind Power Project, a Class 4 wind facility including 18 wind turbine generators with a total nameplate capacity of 40 MW, and associated ancillary equipment. The Project started construction in spring 2014 and became fully operational in winter 2014.

During an internal review of the Project by Suncor, it was noted that an access road and collector cable leading to Turbine WTG 22 had been rerouted during the construction phase. The revised route traversed through a portion of land which had not been previously assessed as part of the original Stage 2 archaeological assessment for the Project. In due diligence, Stantec was retained by Suncor to conduct a Stage 2 archaeological assessment for the portion of the revised access road which had not been previously captured by the original Stage 2 surveys.

The current Stage 2 assessment was conducted on behalf of Suncor by Stantec for an approximately 0.17 hectare additional study area located on part of Lot 5, Concession 2 North of Egremont Road, Township of Adelaide, now Township of Adelaide-Metcalfe, Middlesex County, Ontario. In addition to Suncor’s due diligence, the Stage 2 assessment of the additional study area was conducted to meet the requirements for an amendment to a REA, as outlined in Ontario Regulation 359/09 Sections 21 and 22, under Part V.0.1 of the Environmental Protection Act (Government of Ontario 1990).

The additional study area includes a former gravel farmer’s lane (Plate 1). With the addition of extra gravel, this lane was used for access during the construction of the Project and continues to be used for access to Turbine WTG 22. Thus, the construction impacts by the Project to the unassessed lands were minimal and limited to the pre-existing disturbed gravel farmer’s lane. No evidence of soil disturbance could be identified related to the rerouting of the collector cable south of the access road in the agricultural field portion of the additional study area. No further construction impacts were evident within the additional study area. Further, no archaeological

dp w:\160940226 - suncor adelaide st 2 and 3\work_program\report\additional stage 2 - 2015\final\p256-0385-2015_26jan2016_re.docx v STAGE 2 ARCHAEOLOGICAL ASSESSMENT: ADDITIONAL LANDS ON THE SUNCOR ENERGY ADELAIDE WIND POWER PROJECT

resources were identified during the pedestrian survey of the agricultural field portion of the additional study area.

The Stage 2 archaeological assessment determined that the construction impacts by the Project to the unassessed lands were minimal and limited to the pre-existing disturbed gravel farmer’s lane. No evidence of soil disturbance could be identified related to the rerouting of the collector cable south of the access road in the agricultural field portion of the additional study area. No further construction impacts were evident within the additional study area. Further, no archaeological resources were identified during the pedestrian survey of the agricultural field portion of the additional study area. Thus, in accordance with Section 2.2 and Section 7.8.4 of the MTCS’ 2011 Standards and Guidelines for Consultant Archaeologists (Government of Ontario 2011b), no further archaeological assessment of the additional study area is required.

The MTCS is asked to review the results presented and to accept this report into the Ontario Public Register of Archaeological Reports.

The Executive Summary highlights key points from the report only; for complete information and findings, the reader should examine the complete report.

dp w:\160940226 - suncor adelaide st 2 and 3\work_program\report\additional stage 2 - 2015\final\p256-0385-2015_26jan2016_re.docx vi STAGE 2 ARCHAEOLOGICAL ASSESSMENT: ADDITIONAL LANDS ON THE SUNCOR ENERGY ADELAIDE WIND POWER PROJECT

Project Context January 26, 2016

1.0 Project Context

1.1 DEVELOPMENT CONTEXT

The Suncor Adelaide Wind Power Project (the Project) includes an 18 wind turbine generator facility and associated infrastructure, with a total nameplate capacity of 40 megawatts (MW), located in the Township of Adelaide-Metcalfe, Middlesex County, Ontario (Figure 1). A Stage 1 archaeological assessment for the Project was conducted by Golder Associates Ltd. (Golder) in 2012 (Golder 2012a) and a Stage 2 archaeological assessment was conducted for the Project by Golder (2012b) and Stantec Consulting Ltd. (Stantec) (Stantec 2012, Stantec 2013, Stantec 2014) on behalf of Suncor Energy Products Inc. (Suncor). The Stage 1 and 2 assessments for the Project were undertaken in order to meet the requirements for an application for a Renewable Energy Approval (REA), as outlined in Ontario Regulation 359/09 sections 21 and 22 of the Environmental Protection Act (Government of Ontario 1990).

The Green Energy Act (Government of Ontario 2009) enabled legislation governing project assessments and approvals to be altered to allow for a more streamlined Renewable Energy Approval (REA) process. Under Section 22(1) of the REA, an archaeological assessment must be conducted if the proponent concludes that engaging in the project may have an impact on archaeological resources. Golder Associates Ltd. (Golder) previously determined that archaeological potential for the recovery of pre-contact Aboriginal and Euro-Canadian historic archaeological resources exists within the Project’s study area (Golder 2012a, 2012b). Currently, Ontario Regulation 359/09 of the Environmental Protection Act (Government of Ontario 2011a) governs the REA process for renewable energy projects such as wind, anaerobic digestions, solar, and thermal treatment facilities.

A REA was issued to Suncor on December 11, 2013 (REA #8279-9AUP2B). The REA was issued for the construction, installation, operation, use and retiring of the Suncor Adelaide Wind Power Project, a Class 4 wind facility including 18 wind turbine generators with a total nameplate capacity of 40 MW, and associated ancillary equipment. The Project started construction in spring 2014 and became fully operational in winter 2014.

During an internal review of the Project by Suncor, it was noted that an access road and collector cable leading to Turbine WTG 22 had been rerouted during the construction phase. The revised route traversed through a portion of land which had not been previously assessed as part of the original Stage 2 archaeological assessment for the Project. In due diligence, Stantec was retained by Suncor to conduct a Stage 2 archaeological assessment for the portion of the revised access road which had not been previously captured by the original Stage 2 surveys.

The current Stage 2 assessment was conducted on behalf of Suncor by Stantec for an approximately 0.17 hectare additional study area located on part of Lot 5, Concession 2 North of Egremont Road, Township of Adelaide, now Township of Adelaide-Metcalfe, Middlesex County, Ontario. Figure 2 illustrates the additional study area as well as the original intended

dp w:\160940226 - suncor adelaide st 2 and 3\work_program\report\additional stage 2 - 2015\final\p256-0385-2015_26jan2016_re.docx 1.1 STAGE 2 ARCHAEOLOGICAL ASSESSMENT: ADDITIONAL LANDS ON THE SUNCOR ENERGY ADELAIDE WIND POWER PROJECT

Project Context January 26, 2016 route of the access road and the previously assessed area by Golder (2012b). In addition to Suncor’s due diligence, the Stage 2 assessment of the additional study area was conducted to meet the requirements for an amendment to a REA, as outlined in Ontario Regulation 359/09 Sections 21 and 22, under Part V.0.1 of the Environmental Protection Act (Government of Ontario 1990).

1.2 OBJECTIVES

For the purposes of this Stage 2 assessment the Ministry of Tourism, Culture and Sport’s (MTCS) 2011 Standards and Guidelines for Consultant Archaeologists (Government of Ontario 2011b) were followed. The objectives of the Stage 2 assessment were to document archaeological resources present within the study area, to determine whether any of the resources might be artifacts or archaeological sites with cultural heritage value or interest requiring further assessment, and to provide specific Stage 3 direction for the protection, management and/or recovery of the identified archaeological resources (Government of Ontario 2011b).

Permission to enter the study area to document archaeological resources was provided by Mr. Chris Scott at Suncor.

1.3 HISTORICAL CONTEXT

1.3.1 Post-contact Aboriginal Resources

The post-contact Aboriginal occupation of was heavily influenced by the dispersal of various Iroquoian-speaking communities by the New York State Iroquois and the subsequent arrival of Algonkian speaking groups from at the end of the 17th century and the beginning of the 18th century (Konrad 1981; Schmalz 1991). By 1690, Algonkian speakers from the north appear to have begun to repopulate Bruce County (Rogers 1978:761). This is the period in which the Mississaugas are known to have moved into southern Ontario and the lower Great Lakes watersheds (Konrad 1981). In , however, members of the Three Fires Confederacy (Chippewa, and Potawatomi) were immigrating from Ohio and Michigan in the late 1700s (Feest and Feest 1978:778-779).

The additional study area first enters the Euro-Canadian historic record when the Chippewa entered into Treaty Number 21 (Figure 4). Treaty 21 was a provisional agreement…

entered into on the 9th day of March, 1819, between John Aiken, Esquire, on behalf of His Majesty, and the Principal Men of the Chippewa Nation of Indians, inhabiting a tract of land, whereas the said John Aikens for His Majesty was to pay the said Indians 600 pounds yearly for the said tract described as follows:

“Commencing at the northerly side of the River Thames at the south west angle of the Township of London; thence along the western boundary of the Township of London, in a course north 21 degrees, 30 minutes west, twelve miles to the north west angle of the

dp w:\160940226 - suncor adelaide st 2 and 3\work_program\report\additional stage 2 - 2015\final\p256-0385-2015_26jan2016_re.docx 1.2 STAGE 2 ARCHAEOLOGICAL ASSESSMENT: ADDITIONAL LANDS ON THE SUNCOR ENERGY ADELAIDE WIND POWER PROJECT

Project Context January 26, 2016

said Township; then on a course about south 62 degrees and 30 minutes west forty- eight miles more or less until it intersects a line on a course produced north two miles from the north east angle of the Shawnee [Sombra] Township; then along the eastern boundary line of the said Township, twelve miles and a half more or less to the northern boundary line of the Township of Chatham; then east twenty-four miles more or less to the River Thames; then along the water[‘]s edge of the River Thames against the stream to the place of beginning, reserving a tract of land situate[d] on the northerly side of the River Thames nearly opposite to the northerly angle of the Township of Southwold and south west angle of the Del[a]ware Township containing 15,360 acres; also reserving two miles square distant about four miles above the rapids where the Indians have their improvements and nearly parallel to the Moravian Village containing 5,120 acres.”

(Morris 1943: 24-25)

Treaty Number 21 was further modified and confirmed in Treaty Number 25 which modified the method of quantity of payment to the First Nation groups concerned and some minor variation in the description of the land surrendered (Morris 1943: 25). While it is difficult to exactly delineate treaty boundaries today, Figure 3 provides an approximate outline of Treaty Number 21 and 24 (identified by the letter “R”).

1.3.2 Historic Euro-Canadian Resources

In the 1830s the first Euro-Canadian settlement began in the general vicinity of the additional study area soon after historic Adelaide Township was surveyed by Peter Carroll (Carroll 1831a, Carroll 1831b). At this time, Lieutenant Governor of Sir John Colborne recognized that the road network was insufficient to allow European settlers into the area and did not provide a sufficient military transportation route. As a result, Colborne requested that Egremont Road be surveyed in order to increase settlement of the area as well as to provide a sufficient military transportation route should the need arise (Nielsen 1993:3). Carroll surveyed in the route of Egremont Road along with “three tiers of lots on either side” (Nielsen 1993:6). The 1878 Illustrated Historical Atlas of the County of Middlesex (Page and Co. 1878), illustrates the settlement of the Geographic Township of Adelaide in the late 19th century. The 1878 map shows the increase in settlement noted by numerous structures and landowners (Figure 4). Although locations are only approximate on these maps, they indicate potential for archaeological Euro-Canadian remains that could be impacted within the additional study area. Typically these locations no longer exhibit any visible evidence of their former structure. Table 1 summarizes the 1878 property owners for Lot 5, Concession 2 North of Egremont Road (NER) as illustrated on the 1878 map of Adelaide Township.

dp w:\160940226 - suncor adelaide st 2 and 3\work_program\report\additional stage 2 - 2015\final\p256-0385-2015_26jan2016_re.docx 1.3 STAGE 2 ARCHAEOLOGICAL ASSESSMENT: ADDITIONAL LANDS ON THE SUNCOR ENERGY ADELAIDE WIND POWER PROJECT

Project Context January 26, 2016

Table 1: Historic Information as Illustrated on the 1878 Map of Adelaide Township

Lot Concession Owner Comment 5 2 NER Shalto Galloway No structures visible 5 2 NER William Miller Three structures and one orchard 5 2 NER Miles McCabe One Structure and one orchard

As noted on Figure 4 and in Table 1, three structures and one orchard are illustrated directly north of the additional study area. A farmhouse is still standing south of the (Cuddy Drive) today.

Historical county atlases, however, were produced primarily to identify factories, offices, residences and landholdings of subscribers and were funded by subscription fees. Landowners who did not subscribe were not always listed on the maps (Caston 1997:100). As such, all structures were not necessarily depicted or placed accurately (Gentilcore and Head 1984).

The majority of the region surrounding the additional study area has been subject to European- style agricultural practices for over 100 years, having been settled by Euro-Canadian farmers by the mid-19th century. Much of the region today continues to be used for agricultural purposes.

1.3.3 Recent Reports

The rationale for fieldwork strategies for the present Stage 2 archaeological assessment was informed in part by reports previously written for the Suncor Energy Adelaide Wind Power Project. Table 2 lists these archaeological assessment reports and each discussed in Section 1.4.3 below.

Table 2: Recent Reports Concerning the Suncor Energy Adelaide Wind Power Project

Year Report Title Consultant PIF# 2012a Stage 1 Archaeological Assessment, Suncor Adelaide Wind Power Project, Municipality of Adelaide Metcalf, Middlesex County, Golder P218-217-2011 Ontario 2012b Stage 2 Archaeological Assessment, Suncor Adelaide Wind Power Project, Various Lots and Concessions Municipality of Adelaide Golder P218-100-2011 Metcalfe, Middlesex County, Ontario. 2012 Stage 2 Archaeological Assessment, Suncor Energy Adelaide Wind Power Project, Lot 25, Concession 2 N.E.R., Municipality of Adelaide Stantec P379-002-2012 Metcalfe, Middlesex County, Ontario. 2013 Stage 2 Archaeological Assessment, Suncor Energy Adelaide Wind Power Project, Lot 7, Concession 2 N.E.R., Municipality of Adelaide Stantec P001-750-2013 Metcalfe, Middlesex County, Ontario. 2014 Stage 2 Archaeological Assessment Additional Properties, Suncor P389-0023- Energy Adelaide Wind Power Project, Various Lots and Concessions, Stantec 2013 Municipality of Adelaide Metcalfe, Middlesex County, Ontario.

dp w:\160940226 - suncor adelaide st 2 and 3\work_program\report\additional stage 2 - 2015\final\p256-0385-2015_26jan2016_re.docx 1.4 STAGE 2 ARCHAEOLOGICAL ASSESSMENT: ADDITIONAL LANDS ON THE SUNCOR ENERGY ADELAIDE WIND POWER PROJECT

Project Context January 26, 2016

1.4 ARCHAEOLOGICAL CONTEXT

1.4.1 The Natural Environment

The additional study area is located within the Horseshoe Moraines physiographic region, as identified by Chapman and Putnam (1984). The Horseshoe Moraines is a moderately hilly area with gravel terraces and swampy floors (Chapman and Putnam 1984:128). The soil type in the additional study area is a Huron series silt loam that is moderately drained (Hagerty and Kingston 1992). Although not ideal, this soil is suitable for Aboriginal and Euro-Canadian agricultural practices.

The closest source of potable water is a tributary of Adelaide Creek, located approximately 135 metres west of the additional study area.

1.4.2 Pre-contact Aboriginal Resources

This portion of southwestern Ontario has been occupied by First Nations peoples since the retreat of the glaciers approximately 11,000 years ago. For the majority of this time people followed a hunter gatherer lifestyle, moving seasonally between areas of localized resource abundance. Approximately 1,300 years ago, with the arrival in Ontario of corn, beans, and squash, there was a gradual move towards farming and the reliance on domesticated foodstuffs, resulting in the eventual emergence of permanent villages by the 10th century A.D. Table 3 provides a general outline of the cultural chronology of Middlesex County, based on Ellis and Ferris (1990).

Table 3: Cultural Chronology of the County of Middlesex

Period Characteristics Time Period Comments Early Paleo-Indian Fluted Projectiles 9,000 – 8,400 B.C. spruce parkland/caribou hunters Late Paleo-Indian Hi-Lo Projectiles 8,400 – 8,000B.C. smaller but more numerous sites Early Archaic Kirk and Bifurcate Base Points 8,000 – 6,000 B.C. slow population growth Middle Archaic Brewerton-like points 6,000 – 2,500 B.C. environment similar to present Lamoka (narrow points) 2,000 – 1,800 B.C. increasing site size Late Archaic Broad Points 1,800 – 1,500 B.C. large chipped lithic tools Small Points 1,500 – 1,100 B.C. introduction of bow hunting Terminal Archaic Hind Points 1,100 - 950 B.C. emergence of true cemeteries Early Woodland Meadowood Points 950 - 400 B.C. introduction of pottery Couture Corded Pottery 400 B.C. - A.D. 500 increased sedentism Middle Woodland Riviere au Vase Phase A.D. 500 - 800 seasonal hunting and gathering Younge Phase A.D. 800 - 1200 incipient agriculture Late Woodland Springwells Phase A.D.1200 - 1400 agricultural villages

dp w:\160940226 - suncor adelaide st 2 and 3\work_program\report\additional stage 2 - 2015\final\p256-0385-2015_26jan2016_re.docx 1.5 STAGE 2 ARCHAEOLOGICAL ASSESSMENT: ADDITIONAL LANDS ON THE SUNCOR ENERGY ADELAIDE WIND POWER PROJECT

Project Context January 26, 2016

Table 3: Cultural Chronology of the County of Middlesex

Period Characteristics Time Period Comments Wolf Phase A.D. 1400 - 1550 earth worked villages, warfare Contact Various Algonkian and early written records and A.D. 1600 - 1875 Aboriginal Iroquoian Groups treaties A.D. 1749 - Historic French/Euro-Canadian European settlement present

1.4.3 Previously Identified Archaeological Sites and Surveys

In order that an inventory of archaeological resources could be compiled, the registered archaeological site records kept by the MTCS were consulted. In Ontario, information concerning archaeological sites is stored in the ASDB maintained by the MTCS. This database contains archaeological sites registered according to the Borden system. Under the Borden system, Canada is divided into grid blocks based on latitude and longitude. A Borden Block is approximately 13 kilometres east to west and approximately 18.5 kilometres north to south. Each Borden Block is referenced by a four-letter designator and sites within a block are numbered sequentially as they are found. The study area under review is within Borden Block AgHk.

Information concerning specific site locations is protected by provincial policy, and is not fully subject to the Freedom of Information and Protection of Privacy Act. The release of such information in the past has led to looting or various forms of illegally conducted site destruction. Confidentiality extends to all media capable of conveying location, including maps, drawings, or textual descriptions of a site location. The MTCS will provide information concerning site location to the party or an agent of the party holding title to a property, or to a licensed archaeologist with relevant cultural resource management interests.

An examination of the ASDB has shown that three archaeological sites have been registered within a one-kilometre radius of the additional study area (Government of Ontario n.d.). The sites are summarized below in Error! Reference source not found..

Table 4: Archaeological Sites Registered Within One Kilometre of the Study Area Site Name Borden Number Cultural Affiliation Site Type Location 5 AgHk-170 19th century Euro-Canadian Surface scatter N/A AgHk-167 19th century Euro-Canadian Surface scatter Location 36 AgHk-133 Unknown Unknown

A Stage 1 archaeological assessment was previously conducted by Golder (2012a) and resulted in the determination that the potential for pre-contact Aboriginal and Euro-Canadian sites was deemed to be moderate to high and therefore a Stage 2 assessment was recommended for the Project.

dp w:\160940226 - suncor adelaide st 2 and 3\work_program\report\additional stage 2 - 2015\final\p256-0385-2015_26jan2016_re.docx 1.6 STAGE 2 ARCHAEOLOGICAL ASSESSMENT: ADDITIONAL LANDS ON THE SUNCOR ENERGY ADELAIDE WIND POWER PROJECT

Project Context January 26, 2016

A Stage 2 archaeological assessment was conducted by Golder (2012b) and focused on the proposed wind turbine layout, including turbine sites, collector cable routes, access roads, construction roads, transmission lines, laydown areas and substations. Approximately 608.9 hectares was subject to Stage 2 archaeological assessment, the majority of which was assessed using the pedestrian survey method at an interval of five metres. Ditches and tree lines that could not be assessed using the pedestrian survey method were assessed using the test pit method at an interval of five metres (Golder 2012a). Fifty-one locations were found during the Stage 2 archaeological assessment by Golder (2012a). Nine of those locations were recommended for Stage 3 assessment: Location 4 (AgHk-125), Location 12 (AgHj-11), Location 15 (AgHj-12), Location 26 (AfHj-137), Location 27 (AfHj-138), Location 30 (AfHj-139), Location 36 (AgHj-15), Location 39 (AgHj-16), and Location 43 (AgHk-130). The remaining 42 sites were not recommended for further work (Golder 2012b).The Stage 2 assessment conducted by Stantec in 2012 (Stantec 2012) focused on one property for an additional collector cable route for the Project. Approximately 0.97 hectares were subject to Stage 2 archaeological assessment, all of which was assessed using the pedestrian survey method at five metre intervals. This assessment conducted by Stantec resulted in the identification of one pre-contact Aboriginal findspot. The recovered artifact did not fulfill the criteria for a Stage 3 archaeological investigation and was not recommended for Stage 3 assessment (Stantec 2012).

An additional Stage 2 assessment was conducted by Stantec (2013) for supplementary collector cable routes related to the Project. Approximately 5.73 hectares were subject to Stage 2 archaeological assessment, the majority of which was assessed using the pedestrian survey method at an interval of five metres. Small areas of ditches and tree lines that could not be assessed using the pedestrian survey method were assessed using the test pit method at an interval of five metres. Stantec’s (2013) Stage 2 assessment resulted in the identification of two archaeological sites: Location 2 (AgHk-166) and Location 3 (AgHk-167), both of which were recommended for Stage 3 assessment.

Another Stage 2 assessment was conducted by Stantec (2014) for additional properties on the Project. The properties, totaling 34.8 hectares, consisted primarily of agricultural fields, as well as an orchard, a pasture, manicured and landscaped lawns, and water courses. The majority of the study area was assessed using the pedestrian survey method at five metre intervals. The orchard, pasture, and lawns were subject to test pit survey at five metre intervals. A small portion of the study area consisted of a water course and was exempt from Stage 2 assessment. Stantec’s (2014) Stage 2 additional properties assessment resulted in the identification of five archaeological locations: Location 4, 5, 6, 7, and 8. Locations 4, 6, and 8 comprised isolated pre- contact Aboriginal findspots and did not meet the criteria for Stage 3 assessment (Stantec 2014) Location 7 (AgHk-171) and Location 5 (AgHk-170) were both recommended for Stage 3 archaeological assessment. To Stantec’s knowledge, the only archaeological fieldwork conducted within 50 metres of the additional study area is related to the Project. Suncor Energy Adelaide Wind Power Project and is described in the reports listed in Section 1.2.3 of this report.

dp w:\160940226 - suncor adelaide st 2 and 3\work_program\report\additional stage 2 - 2015\final\p256-0385-2015_26jan2016_re.docx 1.7 STAGE 2 ARCHAEOLOGICAL ASSESSMENT: ADDITIONAL LANDS ON THE SUNCOR ENERGY ADELAIDE WIND POWER PROJECT

Project Context January 26, 2016

1.4.4 Determination of Archaeological Potential

Archaeological potential is established by determining the likelihood that archaeological resources may be present on a subject property. Stantec applied archaeological potential criteria commonly used by the MTCS (Government of Ontario 2011b) to determine areas of archaeological potential within the region under study. These variables include proximity to previously identified archaeological sites; distance to various types of water sources; soil texture and drainage; glacial geomorphology; elevated topography; and the general topographic variability of the area.

Distance to modern or ancient water sources is generally accepted as the most important determinant of past human settlement patterns and, considered alone, may result in a determination of archaeological potential. However, any combination of two or more other criteria, such as well-drained soils or topographic variability, may also indicate archaeological potential. Finally, extensive land disturbance can eradicate archaeological potential (Wilson and Horne 1995).

Distance to water is an essential factor in archaeological potential modeling. When evaluating distance to water it is important to distinguish between water and shoreline, as well as natural and artificial water sources, as these features affect sites locations and types to varying degrees. The MTCS (Government of Ontario 2011b) categorizes water sources in the following manner:

 Primary water sources: lakes, rivers, streams, creeks;

 Secondary water sources: intermittent streams and creeks, springs, marshes, swamps;

 Past water sources: glacial lake shorelines, relic river or stream channels, cobble beaches, shorelines of drained lakes or marshes; and

 Accessible or inaccessible shorelines: high bluffs, swamp or marshy lake edges, sandbars stretching into marsh.

The current Stage 2 additional study area is located in close proximity to a tributary of Adelaide Creek. It is also important to recognize that additional ancient and/or relic tributaries of the various primary and secondary water sources may have existed but are not identifiable today and are not indicated on historic mapping.

Further examination of the additional study area’s natural environment identified soil conditions suitable for Aboriginal and Euro-Canadian agriculture, as well as areas of elevated topography. Storck (1982) notes that archaeological sites, particularly Paleo-Indian sites, tend to be in situated in areas of elevated topography as these areas would possess better drainage and would provide a broad view of the surrounding terrain for game watching. An examination of the ASDB has identified three previously registered archaeological sites within one kilometre of

dp w:\160940226 - suncor adelaide st 2 and 3\work_program\report\additional stage 2 - 2015\final\p256-0385-2015_26jan2016_re.docx 1.8 STAGE 2 ARCHAEOLOGICAL ASSESSMENT: ADDITIONAL LANDS ON THE SUNCOR ENERGY ADELAIDE WIND POWER PROJECT

Project Context January 26, 2016 the additional study area. Overall, the pre-contact and post-contact Aboriginal archaeological potential of the area is judged to be moderate to high.

For Euro-Canadian sites, archaeological potential can be extended to areas of early Euro- Canadian settlement, including places of military or pioneer settlements, early transportation routes, and properties listed on the municipal register or designated under the Ontario Heritage Act or property that local histories or informants have identified with possible historical events. The 1878 Illustrated Historical Atlas of the County of Middlesex, Ont. (Page & Co. 1878) demonstrates that the study area and its environs were densely occupied by Euro-Canadian farmers by the late 19th century. Much of the established road and rail networks and agricultural settlement from that time is still visible today. Considering the above, the historic Euro-Canadian archaeological potential of the study areas is judged to be moderate to high.

1.4.5 Existing Conditions

The additional study area comprises approximately 0.17 hectares of land and includes an existing gravel road and agricultural field. The additional study area is triangular in shape and is located on part of Lot 5, Concession 2 North of Egremont Road, Geographic Township of Adelaide, now Township of Adelaide-Metcalfe, Middlesex County, Ontario. The topography of the immediate area is generally flat, with some rolling topography noted beyond the additional study area. The Stage 2 archaeological assessment was conducted under Project Information Form (PIF) P256-0385-2015 issued to Parker Dickson, MA, of Stantec by the MTCS. Additional details regarding the existing conditions of the additional study area are provided in Section 2.0.

dp w:\160940226 - suncor adelaide st 2 and 3\work_program\report\additional stage 2 - 2015\final\p256-0385-2015_26jan2016_re.docx 1.9 STAGE 2 ARCHAEOLOGICAL ASSESSMENT: ADDITIONAL LANDS ON THE SUNCOR ENERGY ADELAIDE WIND POWER PROJECT

Field Methods January 26, 2016

2.0 Field Methods

Prior to the Stage 2 assessment of the additional study area, the archaeological reports related to the Project were reviewed. The Stage 2 archaeological assessment of the additional study area was conducted under archaeological consulting license P256 issued to Parker Dickson, MA, of Stantec by the MTCS. The Stage 2 survey was conducted on December 2, 2015. During the Stage 2 survey, the weather was cool and overcast. Field, weather, and lighting conditions were excellent and at no time were they detrimental to the recovery of archaeological material. Figure 5 provides an illustration of the Stage 2 survey methods, as well as photograph locations and directions.

As described in Section 1.1, the Stage 2 assessment of the additional study area is being conducted for a portion of land which was not previously assessed. During the construction phase of the Project and prior to Stage 2 assessment, the additional study area was impacted by the rerouting of the access road and collector cable leading to Turbine WTG 22.

Aerial imagery obtained from Google Earth Pro (Plate 1), illustrates the conditions of the additional study area in 2006. At that time, a gravel farmer’s lane was already constructed through the area. In recent consultation with Suncor, the original access road alignment to Turbine WTG 22 was designed to eliminate the need for tight turning radii during turbine blade delivery. During construction though, it became apparent that the turning radii of the existing farmer’s lane could be navigable during blade delivery. Moreover, the current landowner request the use of the existing farmer’s lane if at all possible to minimize impacts to existing agricultural land. Thus, the existing farmer’s lane was used, and continues to be used, as the access road to Turbine WTG 22. Rather than the need to construct a new access road through the previously assessed agricultural field (see Figure 2), additional gravel was added to the existing farmer’s lane to support the anticipated delivery load. The collector cable was also rerouted from its original alignment to follow the existing farmer’s lane. The new alignment is illustrated on Figure 5. During the Stage 2 survey it was determined that soil disturbance from the installation of approximately 55 metres of collector cable was minimal as there was no evidence of disturbance on the ground surface (Photos 4 and 5). It should also be noted that the green- roof barn, north of the additional study area as illustrated in Plate 1 and Figure 5, has been demolished and only the silo structures remain (see background of Photo 2).

The additional study area comprises approximately 0.17 hectares, consisting of an existing gravel lane/access (as described above) and ploughed and weathered agricultural field. Based on the available information, it was determined that the existing gravel lane (now gravel access road to Turbine WTG 22) is an area of modern disturbance. The existing gravel lane accounts for approximately 34% of the additional study area. Impacts from the construction phase of the Project associated with the access road were minimal and appear to be limited to the additional gravel along the pre-existing lane. As such, the existing gravel lane was not surveyed,

dp w:\160940226 - suncor adelaide st 2 and 3\work_program\report\additional stage 2 - 2015\final\p256-0385-2015_26jan2016_re.docx 2.1 STAGE 2 ARCHAEOLOGICAL ASSESSMENT: ADDITIONAL LANDS ON THE SUNCOR ENERGY ADELAIDE WIND POWER PROJECT

Field Methods January 26, 2016 but was photographically documented. Photos 1 to 3 in Section 8.2 depict the gravel lane, as well as the fresh gravel added during construction.

The remaining portion of the additional study area, approximately 66%, consists of ploughed and weathered agricultural field with ground visibility greater than 80%. This portion was subject to a pedestrian survey at a five metre interval in accordance with Section 2.1.1 of the MTCS’ 2011 Standards and Guidelines for Consultant Archaeologists (Government of Ontario 2011b). Photos 4 and 5 in Section 8.2 depict the pedestrian survey and ground visibility conditions. Aside from a few pieces of fresh gravel located within one metre of the existing gravel lane, no other evidence of construction impacts was noted within the portion of the agricultural field surveyed as part of the additional study area. No evidence of disturbance related to the installation of the buried collector cable was evident. No further archaeological methods were employed since no archaeological resources were recovered during the pedestrian survey.

dp w:\160940226 - suncor adelaide st 2 and 3\work_program\report\additional stage 2 - 2015\final\p256-0385-2015_26jan2016_re.docx 2.2 STAGE 2 ARCHAEOLOGICAL ASSESSMENT: ADDITIONAL LANDS ON THE SUNCOR ENERGY ADELAIDE WIND POWER PROJECT

Record of Finds January 26, 2016

3.0 Record of Finds

The Stage 2 archaeological assessment was conducted employing the methods described in Section 2.0. An inventory of the documentary record generated by fieldwork is provided in Table 4 below.

Table 4: Inventory of Documentary Record

Current Location of Document Type Additional Comments Document Type In original field book and photocopied in project 5 Pages of Field Notes Stantec office in London file 2 Maps Provided by Client Stantec office in London Hard and digital copies in project file 18 Digital Photographs Stantec office in London Stored digitally in project file

No archaeological resources were identified within the additional study area and so no material culture was collected. As a result, no artifact storage arrangements are required.

dp w:\160940226 - suncor adelaide st 2 and 3\work_program\report\additional stage 2 - 2015\final\p256-0385-2015_26jan2016_re.docx 3.3 STAGE 2 ARCHAEOLOGICAL ASSESSMENT: ADDITIONAL LANDS ON THE SUNCOR ENERGY ADELAIDE WIND POWER PROJECT

Analysis and Conclusions January 26, 2016

4.0 Analysis and Conclusions

As noted earlier, during an internal review of the Project by Suncor, it was noted that an access road leading to Turbine WTG 22 had been rerouted along an existing farmer’s lane during the construction phase. Additionally, the collector cable route was also revised to follow along the south side of the existing farmer’s lane. The revised route traversed through a portion of land which had not been previously assessed as part of the original Stage 2 archaeological assessment for the Project. In due diligence, Stantec was retained by Suncor to conduct a Stage 2 archaeological assessment for the portion of the revised access road which had not been previously captured by the original Stage 2 surveys.

The additional study area includes a former gravel farmer’s lane (Plate 1). With the addition of extra gravel, this lane was used for access during the construction of the Project and continues to be used for access to Turbine WTG 22. Thus, the construction impacts by the Project to the unassessed lands were minimal and limited to the pre-existing disturbed gravel farmer’s lane. No evidence of soil disturbance could be identified related to the rerouting of the collector cable south of the access road in the agricultural field portion of the additional study area. No further construction impacts were evident within the additional study area. Further, no archaeological resources were identified during the pedestrian survey of the agricultural field portion of the additional study area.

dp w:\160940226 - suncor adelaide st 2 and 3\work_program\report\additional stage 2 - 2015\final\p256-0385-2015_26jan2016_re.docx 4.1 STAGE 2 ARCHAEOLOGICAL ASSESSMENT: ADDITIONAL LANDS ON THE SUNCOR ENERGY ADELAIDE WIND POWER PROJECT

Recommendations January 26, 2016

5.0 Recommendations

Stantec was retained by Suncor to complete a Stage 2 archaeological assessment for an additional study area associated with the Project, consisting of approximately 0.17 hectares, located on part of Lot 5, Concession 2 North of Egremont Road, Geographic Township of Adelaide, now Township of Adelaide-Metcalfe, Middlesex County, Ontario. The Stage 2 archaeological assessment determined that the construction impacts by the Project to the unassessed lands were minimal and limited to the pre-existing disturbed gravel farmer’s lane. No evidence of soil disturbance could be identified related to the rerouting of the collector cable south of the access road in the agricultural field portion of the additional study area. No further construction impacts were evident within the additional study area. Further, no archaeological resources were identified during the pedestrian survey of the agricultural field portion of the additional study area. Thus, in accordance with Section 2.2 and Section 7.8.4 of the MTCS’ 2011 Standards and Guidelines for Consultant Archaeologists (Government of Ontario 2011b), no further archaeological assessment of the additional study area is required.

The MTCS is asked to review the results presented and to accept this report into the Ontario Public Register of Archaeological Reports.

dp w:\160940226 - suncor adelaide st 2 and 3\work_program\report\additional stage 2 - 2015\final\p256-0385-2015_26jan2016_re.docx 5.1 STAGE 2 ARCHAEOLOGICAL ASSESSMENT: ADDITIONAL LANDS ON THE SUNCOR ENERGY ADELAIDE WIND POWER PROJECT

Advice on Compliance with Legislation January 26, 2016

6.0 Advice on Compliance with Legislation

This report is submitted to the Minister of Tourism, Culture and Sport as a condition of licensing in accordance with Part VI of the Ontario Heritage Act, R.S.O. 1990, c 0.18. The report is reviewed to ensure that it complies with the standards and guidelines that are issued by the Minister, and that the archaeological fieldwork and report recommendations ensure the conservation, protection and preservation of the cultural heritage of Ontario. When all matters relating to archaeological sites within the project area of a development proposal have been addressed to the satisfaction of the Ministry of Tourism, Culture and Sport, a letter will be issued by the ministry stating that there are no further concerns with regard to alterations to archaeological sites by the proposed development.

It is an offence under Sections 48 and 69 of the Ontario Heritage Act for any party other than a licensed archaeologist to make any alteration to a known archaeological site or to remove any artifact or other physical evidence of past human use or activity from the site, until such time as a licensed archaeologist has completed fieldwork on the site, submitted a report to the Minister stating that the site has no further cultural heritage value or interest, and the report has been filed in the Ontario Public Register of Archaeological Reports referred to in Section 65.1 of the Ontario Heritage Act.

Should previously undocumented archaeological resources be discovered, they may be a new archaeological site and therefore subject to Section 48(1) of the Ontario Heritage Act. The proponent or person discovering the archaeological resources must cease alteration of the site immediately and engage a licensed consultant archaeologist to carry out archaeological fieldwork, in compliance with Section 48(1) of the Ontario Heritage Act.

The Cemeteries Act, R.S.O. 1990 c. C.4 and the Funeral, Burial and Cremation Services Act, 2002, S.O. 2002, c.33 (when proclaimed in force) require that any person discovering human remains must notify the police or coroner and the Registrar of Cemeteries at the Ministry of Government and Consumer Services.

dp w:\160940226 - suncor adelaide st 2 and 3\work_program\report\additional stage 2 - 2015\final\p256-0385-2015_26jan2016_re.docx 6.1 STAGE 2 ARCHAEOLOGICAL ASSESSMENT: ADDITIONAL LANDS ON THE SUNCOR ENERGY ADELAIDE WIND POWER PROJECT

Bibliography and Sources January 26, 2016

7.0 Bibliography and Sources

Carroll, Peter. 1831a. Field Notes Taken in the Survey of a Road from the Northeast Corner of Carradoc to with three tiers of Lots on each side thereof. By order from the Surveyor General’s Office bearing date at York the 30th day of May 1831. Field Book Number 15. Unpublished manuscript, on file with the Ministry of Natural Resources Crown Land Survey Records Office, Peterborough.

Carroll, Peter. 1831b. Plan of the Township of Adelaide. By Peter Carroll, Deputy Surveyor, 29th December 1831. Map No. 438. Map on file with the Ministry of Natural Resources Crown Land Survey Records Office, Peterborough.

Caston, Wayne A. 1997. Evolution in the Mapping of Southern Ontario and Wellington County. Wellington County History 10:91-106.

Chapman, Lyman John and Donald F. Putnam. 1984. The Physiography of Southern Ontario. 3rd ed. Ontario Geological Survey Special Volume 2. Toronto: Ontario Ministry of Natural Resources.

Ellis, Chris J. and Neal Ferris (editors). 1990. The Archaeology of Southern Ontario to A.D. 1650. Occasional Publication of the London Chapter, Ontario Archaeological Society, Number 5.

Feest, Johanna and Christian Feest. 1978. Ottawa. In Handbook of North American Indians. Volume 15, Northeast, edited by Bruce Trigger, pp. 772-786. Washington: Smithsonian Institution Press.

Gentilcore, R. Louis and C. Grant Head. 1984. Ontario’s History in Maps. Toronto: University of Toronto Press.

Golder Associates Ltd. 2012a. Stage 1 Archaeological Assessment, Suncor Energy Adelaide Wind Power Project, Municipality of Adelaide Metcalfe, Middlesex County, Ontario. Report on file with the Ministry of Tourism, Culture and Sport, Toronto.

Golder Associates Ltd. 2012b. Stage 2 Archaeological Assessment, Suncor Energy Adelaide Wind Power Project, Municipality of Adelaide Metcalfe, Middlesex County, Ontario. Report on file with the Ministry of Tourism, Culture and Sport, Toronto

Government of Ontario. 1990. Environmental Protection Act. R.S.O. 1990, CHAPTER E.19. Last amendment: 2010, c. 16, Sched. 7, s. 2. Electronic document: http://www.e- laws.gov.on.ca/html/statutes/english/elaws_statutes_90e19_e.htm. Last accessed January 8, 2014.

dp w:\160940226 - suncor adelaide st 2 and 3\work_program\report\additional stage 2 - 2015\final\p256-0385-2015_26jan2016_re.docx 7.1 STAGE 2 ARCHAEOLOGICAL ASSESSMENT: ADDITIONAL LANDS ON THE SUNCOR ENERGY ADELAIDE WIND POWER PROJECT

Bibliography and Sources January 26, 2016

Government of Ontario. 2009. The Green Energy Act, S.O. 2009, Chapter 12, Schedule A. Last amendment: 2011, c.9, Sched. 27, s.27. Electronic document: http://www.e- laws.gov.on.ca/html/statutes/english/elaws_statutes_09g12_e.htm. Last accessed January 20, 2016.

Government of Ontario. 2011a. Ontario Regulation 359/09: Renewable Energy Approval Under Part V.0.1 of the Act. Electronic document: http://www.e- laws.gov.on.ca/html/regs/english/elaws_regs_090359_e.htm. Last accessed January 20, 2016.

Government of Ontario. 2011b. Standards and Guidelines for Consultant Archaeologists. Toronto: Ministry of Tourism, Culture and Sport.

Hagerty, T.P. and M.S. Kingston. 1992. The Soils of Middlesex County. Report Number 56 of the Ontario Centre for Soil Resource Evaluation. 2 volumes. Resources Management Branch, Ontario Ministry of Agricultural and Food, Ontario.

Konrad, Victor. 1981. An Iroquois Frontier: The North Shore of Lake Ontario during the Late Seventeenth Century. Journal of Historical Geography 7(2): 129-144.

Morris, J.L. 1943. Indians of Ontario. 1964 reprint. Department of Lands and Forests, Government of Ontario.

Nielsen, Eleanor. 1993. The Egremont Road: Historic Route from Lobo to Lake Huron. Sarnia: Lambton Historical Society.

Page, H.R. and Co. 1878. Illustrated Historical Atlas of the County of Middlesex. 1972 reprint. Sarnia: Edward Phelps.

Rogers, E.S. 1978. Southeast Ojibwa. In Handbook of North American Indians. Volume 15, Northeast, edited by Bruce Trigger, pp. 760-771. Washington: Smithsonian Institution Press.

Schmalz, Peter S. 1991. The Ojibwa of Southern Ontario. Toronto: University of Toronto Press.

Stantec Consulting Ltd. 2012. Stage 2 Archaeological Assessment, Suncor Energy Adelaide Wind Power Project, Lot 25, Concession 2 N.E.R., Municipality of Adelaide Metcalfe, Middlesex County, Ontario. Report on file with the Ministry of Tourism, Culture and Sport, Toronto.

Stantec Consulting Ltd. 2013. Stage 2 Archaeological Assessment, Suncor Energy Adelaide Wind Power Project, Municipality of Adelaide MetCalfe, Middlesex County, Ontario. Report on file with the Ministry of Tourism, Culture and Sport, Toronto.

dp w:\160940226 - suncor adelaide st 2 and 3\work_program\report\additional stage 2 - 2015\final\p256-0385-2015_26jan2016_re.docx 7.2 STAGE 2 ARCHAEOLOGICAL ASSESSMENT: ADDITIONAL LANDS ON THE SUNCOR ENERGY ADELAIDE WIND POWER PROJECT

Bibliography and Sources January 26, 2016

Stantec Consulting Ltd. 2014. Stage 2 Archaeological Assessment Additional Properties, Suncor Energy Adelaide Wind Power Project, Municipality of Adelaide Metcalfe, Middlesex County, Ontario. Report on file with the Ministry of Tourism, Culture and Sport, Toronto.

Storck, P.L. 1982. Paleo-Indian Settlement Patterns Associated with the Strandline of Glacial Lake Algonquin in Southcentral Ontario. Canadian Journal of Archaeology 6:1-31.

Wilson, J.A. and M. Horne. 1995. City of London Archaeological Master Plan. London: City of London, Department of Planning and Development.

dp w:\160940226 - suncor adelaide st 2 and 3\work_program\report\additional stage 2 - 2015\final\p256-0385-2015_26jan2016_re.docx 7.3 STAGE 2 ARCHAEOLOGICAL ASSESSMENT: ADDITIONAL LANDS ON THE SUNCOR ENERGY ADELAIDE WIND POWER PROJECT

Images January 26, 2016

8.0 Images

8.1 PLATES

Plate 1: Ground Conditions of Additional Study Area in 2006

[Source: Google Earth Pro, imagery dated March 31, 2006]

dp w:\160940226 - suncor adelaide st 2 and 3\work_program\report\additional stage 2 - 2015\final\p256-0385-2015_26jan2016_re.docx 8.1 STAGE 2 ARCHAEOLOGICAL ASSESSMENT: ADDITIONAL LANDS ON THE SUNCOR ENERGY ADELAIDE WIND POWER PROJECT

Images January 26, 2016

8.2 PHOTOGRAPHS

Photo 1: Existing Gravel Lane (former farmer’s lane, now with additional gravel) – Disturbed and Not Surveyed, facing west

Photo 2: Existing Gravel Lane (former farmer’s lane, now with additional gravel) – Disturbed and Not Surveyed, facing north

dp w:\160940226 - suncor adelaide st 2 and 3\work_program\report\additional stage 2 - 2015\final\p256-0385-2015_26jan2016_re.docx 8.2 STAGE 2 ARCHAEOLOGICAL ASSESSMENT: ADDITIONAL LANDS ON THE SUNCOR ENERGY ADELAIDE WIND POWER PROJECT

Images January 26, 2016

Photo 3: Existing Gravel Lane (former farmer’s lane, now with additional gravel) – Disturbed and Not Surveyed, facing northeast

Photo 4: Stage 2 Pedestrian Survey at a Five Metre Interval, facing east

dp w:\160940226 - suncor adelaide st 2 and 3\work_program\report\additional stage 2 - 2015\final\p256-0385-2015_26jan2016_re.docx 8.3 STAGE 2 ARCHAEOLOGICAL ASSESSMENT: ADDITIONAL LANDS ON THE SUNCOR ENERGY ADELAIDE WIND POWER PROJECT

Images January 26, 2016

Photo 5: Ground Visibility during Stage 2 Pedestrian Survey at a Five Metre Interval

Photo 6: Pedestrian Survey at a Five Metre Interval, facing south

dp w:\160940226 - suncor adelaide st 2 and 3\work_program\report\additional stage 2 - 2015\final\p256-0385-2015_26jan2016_re.docx 8.4 STAGE 2 ARCHAEOLOGICAL ASSESSMENT: ADDITIONAL LANDS ON THE SUNCOR ENERGY ADELAIDE WIND POWER PROJECT

Images January 26, 2016

Photo 7: Pedestrian Survey at a Five Metre Interval, facing north

dp w:\160940226 - suncor adelaide st 2 and 3\work_program\report\additional stage 2 - 2015\final\p256-0385-2015_26jan2016_re.docx 8.5 STAGE 2 ARCHAEOLOGICAL ASSESSMENT: ADDITIONAL LANDS ON THE SUNCOR ENERGY ADELAIDE WIND POWER PROJECT

Maps January 26, 2016

9.0 Maps

All maps will follow on succeeding pages.

dp w:\160940226 - suncor adelaide st 2 and 3\work_program\report\additional stage 2 - 2015\final\p256-0385-2015_26jan2016_re.docx 9.1 435000 440000 445000 450000

2 Ross Road 3 235 5 245 Bornish Drive 230 230 245 22 5 235 245 230 245 245 240 230 225

245 220 225

0 420 245 225 Lamon Drive 240 240 235

5

3

230 2 240 Co Roddick Road ldst 240 Haskett Road

235 Legend 230 230 ream R 230 Fort Rose Road 230 200 ± River Drive 2 240 30 Project Boundary Sylvan Road 240 o 230 0 12 0 225 235 a Hodgins Road d 220 190 Nor th Middl esex Elm Tree Drive Project Components 240

205 Centre Road 5 915 220 210 Kerwood Road 22 4770000 4770000  Proposed Turbine Location Fossil Road 200 205 5 215 215 195 210 5 1 5 215 5 32 5 Watson Road 210 205 225 2 220 Access Road

215 22 210 5 325 0

225 220 220 Overhead/Underground Collector Line

210 230 220 230

Cameron Road 210 215 245 240 Substation 235 ^ 230 235 Ausable Road 230 F P let o 0 235 215 p $+ 42 c la Met Tower 205 h 215 e r Hill R r Road 235 255 35 2 215 12 0 0 52 0 230 o Existing Features 220 Spri ngbank ad 5 32 5 210 Glasgow Street 235 Townsend Line Expressway / Highway 230 210 220 225 240

225 240 Island Road 230 Road

225 215 220 220

225 230

230

Sexton Road Existing Transmission Line Mcc 320 225

255 220 ubbin Road Topographic Contour (metres ASL) 255 215 Birnam Line 220 eertS t Langan Drive Wyatt Road 240 Watercourse 240 225 e 255 225 255 ylgrA 230 Keyser Springbank Road 235 Waterbody 5 3 5 225 2 225

230 Wooded Area

220

230 240

225  24 245 5 Petty Street 240 235 Municipal Boundary 220 225 llihnreF irD ve

230 240

225 220 235

230

225

Pedden Road 250 Additional Study 225 230  245 250 Area  5 225  225 Wardell Drive 240 2 230 50 225     230  4765000  225 $+  235 4765000 230 240 Middlesex Centre e vir e 235 230

245

5 4

5 D 2

3 240 2 2 5 newceM 0 Bri ck Yard L ine Crathie 250 Cuddy Dri ve Crathie Drive $

245 235 240 240 240

Wood Roa 250 240   240  250 0 40  250 0 2 d 4   a

2 255

R 255 245 230   255

l

School Road

245  35 e o d 2

w

255 ^  e l

N  255 240 240 260 255 Warwick 32 5 250

255  0

255

Morse Road

5 Lake 240 240 250 255 2 250 260 Robotham Road  Huron

t Hansford Road

240 260

e Adelaide Metcalfe

ett  r  Toronto

S 255

245 250 245 52 5 245 n ONTARIO

Seed Road

Wilson Road 240 e Wri ghtmans

K

240 245 250 Lake Ontario Egremon Roadt Egremont Dri ve Adelaide Corners 235 255 235

240

235 255 250 255 255 245 42 5 245 250 255 245 250 245 5 4 5 245 2 245 52 5 255 24 245 5 STUDY AREA 2 42 5 45 Lake Erie 250 245 KEY MAP 235

250 240 240

245 255 250 245 245 250 240 5 250 245 0

4

Highway 402 5 250 240 240 0 50 2 2 Highway 402 240 2 245 240 Notes 250 5 42 5 245 d

a 4760000 4760000

245 240 o 245 e 1. Coordinate System: NAD 1983 UTM Zone 17N R 2 v 4

n

i 0 5 iyrDrkociH

3 h 230 2 240 p 240 l 2. Base features produced under license with the Ontario Ministry of 245 o D Natural Resources © Queen's Printer for Ontario, 2013. 0 32 250 240 23

Wright Street 230 235 250 5 Mu lli farry 230 Zion Li ne 250 23 Mullifarry Drive 240 32 5 Adair Boulevard 240 5 240 January 2016 240 245 235 16060710 0 52 0

h

t

245 r 40

Sullivan Road o 2 245 Client/Project 240 N 235 5 32 5

e 235 235 250 240 225 Suncor Energy 5 3 5 5

S 2 3

2

Brown Road Strathroy-Caradoc

d 235 0 240 245 52 a Adelaide Wind Power Project 230 e t ert irD ve H 225 230 225 e 250 240 Pinetree Lane yl M gn 235 245 22 5 Pike Road ce el vo G t Figure No. 240 s y 245 a 250 Strathroy Ro 5 42 5 t E ee ad 225 r

235 t Y 1 230 230 235 S o a 240 5 325 r P rkv 225 lfe k ie a A w Title 5 45 tc venu 2 42 5 e D r 240 M iv 235 0 e e 1,500 3,000 5 Location of Additional 0 32 0 22 m 235

230 230 230 1:60,572 230 32 0 Study Area 230 230 230 230 230 230 240 W:\active\60960710\drawing\MXD\Archaeology\Stage2_Addendum_Dec2015\160960710_Fig1_LocationOfAdditionalStudyArea_20160116.mxdRevised: 2016-01-20 By: dharvey 435000 440000 445000 450000 438100 438200 438300 438400 438500 438600 438700

± Legend Underground Collector Line Access Road Cuddy Drive Constructible Area Road

4764300 4764300 Watercourse Property Boundary Additional Study Area Previously Assessed (Golder 2012b) 4764200 4764200

Area of 4764100 4764100 28 Detail  27 20 18 16 15      14 26  11 21 19 17 12 9 8  23     6 24  13  22   7 5 402

Strathroy 4764000 4764000 Notes 1. Coordinate System: NAD 1983 UTM Zone 17N

2. Base features produced under license with the Ontario Ministry of Natural Resources © Queen's Printer for Ontario, 2013.

3. Orthoimagery © First Base Solutions, 2015 Imagery taken in Spring 2010.

January 2016 160960710 Client/Project

Suncor Energy Adelaide Wind Project

Figure No. 4763900 4763900 2

Title 0 50 100 m

1:2,000 Additional Study Area W:\active\60960710\drawing\MXD\Archaeology\Stage2_Addendum_Dec2015\160960710_Fig2_StudyAreaConstructedInfrastructureRequiringInvestigation_20160122.mxdRevised: 2016-01-26 By: dharvey 438100 438200 438300 438400 438500 438600 438700 Requiring Stage 2 Survey 84°W 82°W 80°W 78°W 76°W 74°W

AE

48°N ± Legend _^ Study Area Municipal Boundary - Upper Tier

Y 46°N Municipal Boundary - Lower or Single Tier Q u é b e c Watercourse Waterbody

Z

A Treaty No. 381, May 9th, 1781 (Mississauga and Chippewa) B Crawford's Purchase, October 9th, 1783 (Algonquin and Iroquois) B1 Crawford's Purchase, October 9th, 1783 (Mississauga) B2 Crawford's Purchases, 1784, 1787 And 1788 (Mississauga) X A2 John Collins' Purchase, 1785 (Chippewa) AF B C Treaty No. 2, May 19th, 1790 (Odawa, Chippewa, K Pottawatomi, and Huron) S D Treaty No. 3, December 2nd, 1792 (Mississauga) V E Haldimand Tract:from the Crown to the Mohawk, 1793 46°N F Tyendinaga:from the Crown to the Mohawk, 1793 G Treaty No. 3 3/4:from the Crown to Joseph Brant, n October 24th, 1795 G e o r g i a H Treaty No. 5, May 22nd, 1798 (Chippewa) B a y I Treaty No. 6, September 7th, 1796 (Chippewa)

44°N J Treaty No. 7, September 7th, 1796 (Chippewa) N B1 L Treaty No. 13, August 1st, 1805 (Mississauga) M Treaty No. 13A, August 2nd, 1805 (Mississauga) H A2 Q AB F N Treaty No.16, November 18th, 1815 (Chippewa) O Treaty No. 18, October 17th, 1818 (Chippewa) AA P Treaty No. 19, October 28th 1818 (Chippewa) N Q Treaty No. 20, November 5th, 1818 (Chippewa) L a k e n R Treaty No. 21, March 9th, 1819 (Chippewa) H u r o B2 S Treaty No. 27, May 31st, 1819 (Mississauga) AG T Treaty No. 27½, April 25th, 1825 (Ojibwa and Chippewa) O U Treaty No. 35, August 13th, 1833 (Wyandot or Huron) k e L a o V Treaty No. 45, August 9th, 1836 (Chippewa and Odawa, W t a r i O n "For All Indians To Reside Thereon") L W Treaty No. 45½, August 9th, 1836 (Saugeen) X Treaty No. 57, June 1st, 1847 (Iroquois of St. Regis) Z Treaty No. 61, September 9th, 1850 (:Ojibwa) P M AA Treaty No. 72, October 30th, 1854 (Chippewa) AB Treaty No. 82, February 9th, 1857 (Chippewa) AF Williams Treaty, October 31st and November 15th, 1923 (Chippewa and Mississauga)

44°N G T AG Williams Treaty, October 31st, 1923 (Chippewa) A E D

Study Area Notes I D 42°N ^_ 1. Coordinate System: NAD 1983 Statistics Canada Lambert 2. Base features produced under license with the Ontario Ministry R of Natural Resources © Queen's Printer for Ontario, 2012. 3. Treaty boundaries adapted from Morris 1943 (1964 reprint). J For cartographic representation only.

C e January 2016 L a k 160960710 r i e E Client/Project

U Suncor Energy Adelaide Wind Project

Figure No. 3

42°N Title 0 75 150 km Treaties and Purchases 1:3,000,000 (Adapted from Morris 1943) W:\active\60960710\drawing\MXD\Archaeology\Stage2_Addendum_Dec2015\160960710_Fig3_Treaties_ArchSt2_20160120.mxd Revised: 2016-01-20 By: dharvey 86°W 84°W 82°W 80°W 78°W 76°W d

Townsend Line

± Legend

Island Road Project Boundary Project Components

SextonRoad  Proposed Turbine Location

Access Road k nabSpring k Birnam Line Langan Drive Overhead/Underground Collector Line ^ Substation $+ Met Tower Keyser Existing Features Expressway / Highway

 Road Watercourse Waterbody Municipal Boundary

       Add itional Study $+ Area

Brick Yard Line Cuddy Drive $

 

Road l Schoo l Road



 Lake ^ Huron Toronto ONTARIO Lake Ontario

Warwick

MorseRoad

t Adelaide Metcalfe STUDY AREA e KEY MAP Lake Erie

r

S

son Road liW sonRoad Notes

n

Seed Road

e ett 1. Historic Map Source- Page, H.R. and Company. 1878. Illustrated

K Historical Atlas of the County of Middlesex.1972 reprint. Sarnia: Edward Egremont Road Egremont Drive Adelaide

January 2016 160960710 Client/Project Suncor Energy Adelaide Wind Power Project

Highway 402 Figure No. 4

Title 0 880 1,760 m

Portion of the 1878 Historic Map of Adelaide Township W:\active\60960710\drawing\MXD\Archaeology\Stage2_Addendum_Dec2015\160960710_Fig4_1878_AdelaideTwp_20160120.mxdRevised: 2016-01-20 By: dharvey 43834 0 43835 0 43836 0 43837 0 43838 0 43839 0 43840 0 43841 0 43842 0 43843 0

Legend 0 ± 0 ; Pho t o Loc a tion s

476409 476409 ! Und erground C o llec torLin e Ac c essRoa d Co nstru c ti b le Are a ; Add itiona lStudyAre a Requiring Stag e 2 7 ! Survey

0 0 Stage 2 Survey Methods Existin g Gr a velR o a d – Distur b e d a nd No t 476408 476408 Surveyed

Surveye d b yPed estrian Surveya t a Five Metre Interv a l ! ; 1 PreviouslyA s se s se d (Go lder2012b ) ! ! ; ! 0 4 0

!5 476407 476407

! ! 6 ; 0 0 ; !! 476406 3 476406 d

Area of 28 Detail  27 20 18 16  15 14 ith_AsBuilts_20160125.mx        W 26 11 21 19 17 12 9 8 0 0  23     6 24  13  22   _Results_ 476405 476405 d 7 5 402

Strathroy 0 0

476404 476404 Notes 1. Co o rdin a teSystem :NAD1983UTMZ o ne 17 N Dc21\6901_i5Sre_etod tho s_an 2015\160960710_Fig5_Survey_Me _Dec m 2. Basefea turesprod uced und erlice nsew ithth e O ntari o Ministryo f ; Na turalResource s© Quee n'sPrinterfo r O ntario,2013 . !2 3. O rtho i m a g ery© FirstBaseSolutions,2015 Im a g eryt a ke n inSprin g 2010 .

Ja nua ry2016 16096071 0 0 0 Client/Pr o je c t 476403 476403 Sun c o rEnergy

y Adelaid e W ind Projec t rve

a Figur e No . 5 Title 0 6 12 m 0 0 Survey Methods and Results 1:30 0 \ctv\0670da n\XDAcaeolg\tge_d end u e2_Add e o logy\Stag D\Archa ing\MX tive\60960710\draw :\ac 476402 476402 W :2016-01-26By:dh Revised 43834 0 43835 0 43836 0 43837 0 43838 0 43839 0 43840 0 43841 0 43842 0 43843 0 STAGE 2 ARCHAEOLOGICAL ASSESSMENT: ADDITIONAL LANDS ON THE SUNCOR ENERGY ADELAIDE WIND POWER PROJECT

Closure January 26, 2016

10.0 Closure

This report documents work that was performed in accordance with generally accepted professional standards at the time and location in which the services were provided. No other representations, warranties or guarantees are made concerning the accuracy or completeness of the data or conclusions contained within this report, including no assurance that this work has uncovered all potential archaeological resources associated with the identified property.

All information received from the client or third parties in the preparation of this report has been assumed by Stantec to be correct. Stantec assumes no responsibility for any deficiency or inaccuracy in information received from others.

Conclusions made within this report consist of Stantec’s professional opinion as of the time of the writing of this report, and are based solely on the scope of work described in the report, the limited data available and the results of the work. The conclusions are based on the conditions encountered by Stantec at the time the work was performed. Due to the nature of archaeological assessment, which consists of systematic sampling, Stantec does not warrant against undiscovered environmental liabilities nor that the sampling results are indicative of the condition of the entire property.

This report has been prepared for the exclusive use of the client identified herein and any use by any third party is prohibited. Stantec assumes no responsibility for losses, damages, liabilities or claims, howsoever arising, from third party use of this report. We trust this report meets your current requirements. Please do not hesitate to contact us should you require further information or have additional questions about any facet of this report.

Quality Review (signature)

Colin Varley, MA, RPA

Independent Review (signature)

Tracie Carmichael, BA, B.Ed.

dp w:\160940226 - suncor adelaide st 2 and 3\work_program\report\additional stage 2 - 2015\final\p256-0385-2015_26jan2016_re.docx 10.1