A.1 CONTACT LIST Municipality of Middlesex Centre Stormwater Management Master Plan Municipal Class Environmental Assessment

Stakeholder Contact List

Interest Agency Title First Name Last Name Department Title Address City Pr Postal Phone Email Provincial Contacts Provincial Ministry of Natural Resources and Forestry Ms. Kathryn Markham Aylmer District District Planner 615 John Street North Aylmer ON N5H 2S8 kmarkham@.ca Provincial Ministry of the Environment and Climate Change Mr. Craig Newton Southwestern Region Regional Environmental Assessment Coordinator 733 Exeter Road London ON N6E 1L3 Provincial Ministry of the Environment and Climate Change Environmental Assessment & Approvals Branch Director 135 St. Clair Avenue West, 1st Floor ON M4V 1P5 Email only completion notice Provincial Ministry of Tourism, Culture and Sport Ms. Rosi Zirger Culture Services Unit Heritage Planner 401 Bay Street, Suite 1700 Toronto ON M7A 0A7 [email protected] Local Government (EMAIL ONLY) Mayor Municipality of Middlesex Centre Mayor Aina Deviet 10227 Ilderton Road ColdstreamON N0M 2A0 Council Municipality of Middlesex Centre Dept. Mayor John Brennan 10227 Ilderton Road ColdstreamON N0M 2A0 Council Municipality of Middlesex Centre Counc. Debbie Heffernan 10227 Ilderton Road ColdstreamON N0M 2A0 Council Municipality of Middlesex Centre Counc. Wayne Shipley 10227 Ilderton Road ColdstreamON N0M 2A0 Council Municipality of Middlesex Centre Counc. Derek Silva 10227 Ilderton Road ColdstreamON N0M 2A0 Council Municipality of Middlesex Centre Counc. Brad Scott 10227 Ilderton Road ColdstreamON N0M 2A0 Council Municipality of Middlesex Centre Counc. Hugh Aerts 10227 Ilderton Road ColdstreamON N0M 2A0 Local Contacts Local City of London Mr. Scott Mathers Environmental and Engineering Services Director, Water and Wastewater 300 Dufferin Avenue, 3rd Floor London ON N6A 4L9 [email protected] Local City of London Mr. Chris McIntosh Environmental and Engineering Services Environmental Services Engineer, Manager of Industrial Land Developme 300 Dufferin Avenue, 3rd Floor London ON N6A 4L9 [email protected] CA Upper Conservation Authority Ms. Karen Winfield Land Use Regulations Officer 1424 Clarke Road London ON N5V 5B9 [email protected] CA Ausable Bayfield Conservation Authority Mr. Daniel King Water and Planning Regulations Coordinator 71108 Morrison Line RR3 Exeter ON N0M 1S5 [email protected] CA St. Claire Conservation Authority Ms. Melissa Deisley Planning and Regulations Regulations Officer 205 Mill Pond Cres Strathroy ON N7G 3P9 [email protected] Middlesex Middlesex-London Health Unit Mr. Fatih Sekercioglu Environmental Health Team Manager 50 King St. London ON N6A 5L7 519-663-5317 ext. 2 [email protected] Source Protect Thames-Syndenham Source Protection Ms. Jenna Allain Drinking Water Source Protection Source Protection Coordinator 1424 Clarke Road London On N5V 5B9 519-451-2800 [email protected] County County of Middlesex Mr. Chris Traini Roads County Engineer 399 Ridout Street North London ON N6A 2P1 [email protected] Parks Ontario - Ministry of Environment, Conservation and Parks Mr. Tim Marchand Southwest Parks Zone Senior Park Planner 659 Exeter Road London ON N6E 1L3 519-873-4618 [email protected] Parks Ontario - Ministry of Environment, Conservation and Parks Mr. Rhonda Card Park Superintendant PO Box 9, Port BurweON N0J 1T0 519-874-4601 ext. [email protected] Contacts Local Chippewas of the Thames Chief Jacqueline French Chief 320 Chippewa Road RR1 Muncey ON N0L 1Y0 519-289-5555 [email protected] Local Chippewas of the Thames Ms. Rochelle Smith Lands and Resources Consultation Coordinator 320 Chippewa Road RR1 Muncey ON N0L 1Y1 T:519.289.2662 ext [email protected] Local Chippewas of the Thames Ms. Fallon Burch Consultation Coordinator 320 Chippewa Road RR1 Muncey ON N0L 1Y1 519.289.5555 ext. [email protected] Local Oneida Nation of the Thames Chief Jessica Hill 2212 Elm Avenue Southwold ON N0L 2G0 T: 519-652-6161 [email protected] Local Oneida Nation of the Thames Ms. Catherine Cornelius Political Chief Assistant 2212 Elm Avenue Southwold ON N0L 2G0 T: 519-652-6161 [email protected] Local Munsee-Delaware Nation Chief Roger Thomas - 289 Jubilee Road Muncey ON N0L 1Y0 T:519-289-5396 Ext. [email protected] Local Munsee-Delaware Nation Mr. Glenn Forrest Band Manager 289 Jubilee Road Muncey ON N0L 1Y0 T:519-289-5396 Ext. [email protected] Local Delaware Nation Chief Denise Stonefish - 14760 School House Line RR #3 Thamesvil ON N0P 2K0 T: 519.692.3936 F: [email protected] Local Bkejwanong Territory (Walpole Island) Chief Dan Miskokomon - 117 Tahgahoning Road RR #3 Wallacebu ON N8A 4K9 T.(519) 627-1481 [email protected] Local Bkejwanong Territory (Walpole Island) Ms. Janet Macbeth Project Review Coordinator 117 Tahgahoning Road RR #3 Wallacebu ON N8A 4K9 T: 519.627.1475 Ex [email protected] Local Bkejwanong Territory (Walpole Island) Dr. Dean Jacobs Consultation Manager 117 Tahgahoning Road RR #3 Wallacebu ON N8A 4K9 T: 519.627.1475 [email protected] Local Caldwell First Nation Chief Mary Duckworth Chief P.O.Box 388 LeamingtoON N8H 3W3 T: 519.322-1766 [email protected] Local Caldwell First Nation Mr. Allen Deleary Director of Operations P.O.Box 388 LeamingtoON N8H 3W3 T: 519.322-1766 [email protected] Local Chippewas of Kettle and Stony Point First Nation Chief Tom Bressette 6247 Indian Lane Forest ON N0N 1J0 T: 519-786-2125 [email protected] Local Chippewas of Kettle and Stony Point First Nation Ms. Valerie George Consultation Coordinator 6247 Indian Lane RR#2 Forest ON N0N 1J0 T: 519.786.2125 F: [email protected] Local Aamjiwnaang First Nation Chief Chris Plain - 978 Tashmoo Avenue ON N7T 7H5 T: 519.336.8410 F: [email protected] Local Aamjiwnaang First Nation Ms. Sharilyn Johnston Environment Coordinator 978 Tashmoo Avenue Sarnia ON N7T 7H5 T: 519.336.8410 ext. [email protected] Local Aamjiwnaang First Nation Mr. Dennis Plain Species at Risk Technician 978 Tashmoo Avenue Sarnia ON N7T 7H5 T: 519-336-8140 ext [email protected] Developers/Consultants (EMAIL ONLY) Tridon Mr. Don De Jong Tridon Mr. Maneesh Podnar Sifton Mr. Matthew Robertson Stantec Mr. Chris Hendriksen c Development Engineering Mr. Ryan Hern EngPlus Mr. Vinh Pham v Southwinds Mr. Mattew Falls Litera Investments Mr. Jacob Katz Strik Baldinelli Moniz Mr. Kevin Moniz A&M Sod Mr. James Glover Mr. Emil Pattyn DeveloPro Land Services Mr. Craig Linton c AECOM Mr. Peter McAllister Sco-Terra Mr. Richard Pellerin Name Address City Prov Postal Phone Email Communications PIC 1 Notice PIC 2 Mailout Johns Drive Bryanston ON attended PIC 2

Received email March 11, 2019 (NE) with video of water coming off Weldon Park at Cherden Drive Denfield ON attended PIC 2

Email Tuesday July 31/August 19 2018. Experienced flooding during the severe storm in July. Notes that Pioneer drive was recently repaved, and believes that this may have contributed to the flooding issue. Also notes that they are at a low point within the subidivision, and have witnessed erosion of the hill from higher areas of the subdivision. B. Lima responded on August 7th, and noted that the recent construction did not raise the road profile or curb lines. Recent storm was well beyond the 100 year storm event for which the storm sewers are designed. emailed Aug 19th to inquire about the design of the stormwater management measures for the subdivision, and if measures have/can be taken to mitigate impacts of the construction of houses/impervious surfaces on Pioneer Drive Kilworth ON downstream properties. attended PIC 2 Email June 3 regarding drainage problem - drainage patterns disrupted by construction of new lots to the south. Highbury Ave North Ilderton ON Water pools in backyard. Thames Ave Komoka attended PIC 2 Email Feb 18th, 2018 to be added to mailing list email April 23 via email St. Johns Drive Bryanston ON attended PIC 2 Willow Ridge Ilderton ON attended PIC 2

Resident reached out to Stantec. Site visit April 4, 2019. Memo saved in file. Discussion surrounded surface water and basement flooding, with observations of fence post rotting, sidewalk heaving, sump pumps discharge to surface, ponding along fence and end of driveway. Willow Ridge Ilderton ON attended PIC 2

Residents reached out to Stantec. Site visit April 4, 2019. Memo saved in file. Discussion surrounded surface water and basement flooding, with observations of fence post rotting, sidewalk heaving, sump pumps discharge to surface, ponding along fence and end of driveway. Willow Ridge Ilderton ON attended PIC 2 Komoka Road Komoka ON attended PIC 2 Attended PIC 1 letter received March 22, 2019 - comment sheet from PIC 2 filled out (saved in file) Phone call Feb 13. Would like to be added to study Ilderton Road Ilderton ON mailing list and informed of upcoming PICs. Friday April 20 Post submitted comments online Mail May 1 Feb 19 via Canada Post Submitted comment via webmap Feb 20, 2019

Submitted comments online Email May 1st via email attended PIC 2 Submitted comment via webmap June 10, 2018 Email received March 8, 2019 (NE) with request of input/assistance with the pooling issue NE meeting March 27, 2019 Discussion with Muni staff Feb 20th. Catch basin not full and not draining in the northwest corner of his yard creating ponding to the west. Drainage from Queen Street washes sand into back yard of neighbour to the east ( Fieldstone Cr. Komoka ON N0L Cr.). Friday April 20 Canada Post Feb 19 via Canada Post Called March 28 to discuss drainage situation at ponds southwest of Komoka Rd/Glendon Drive. Flows from Bella Lago development drain through several ponds, and then through a DIY pipe to an area southwest - there is no overland flow route to the Thames, and flows are managed Komoka Rd. Komoka ON through groundwater. email April 23 via email attended PIC 2 Woodland Drive Kilworth ON attended PIC 2 Medway Road Arva ON attended PIC 1 - mail (unsure of email from contact list) Ilderton ON Submitted comments online email April 23 via email Received email March 12, 2019 (NE) with videos of water pooling and overland flow condos)

Email Feb 20 - drainage concerns attributed to TH, draining towards sideyard. email April 23 via email attended PIC 2 attended PIC 2 Called May 1st to discuss drainage issues in his back yard due to ongoing development Email May 8th attended PIC 2 attended PIC 2 attended PIC 2 attended PIC 2 Submitted comments online email April 23 via email attended PIC 2 Submitted comments via webmap June 8, 2018 m Submitted comment via webmap Feb 17, 2019 m Submitted comments online email April 23 via email Submitted comments online email April 23 via email attended PIC 2 attended PIC 2 attended PIC 2 attended PIC 2 attended PIC 1 attended PIC 2 Email received March 12, 2019 - questions regarding the presented alternatives at the PIC attended PIC 2 m Submitted comments via webmap May 9/2018 Emailed April 2nd to discuss drainage concerns at property. Neighnouring property owner has burried drainage pipe leading onto property. During drain events, overland flow running between properties. Added drainage rock at the low point of the property. Sump pump running constantly, even during dry periods. email April 23 via email Submitted comment via webmap August 17, 2018 Called March 13 to be added to study mailing list Friday April 20 Canada Post Feb 19 via Canada Post attended PIC 2 attended PIC 2 attended PIC 2 attended PIC 2 attended PIC 2 .com Submitted comments via webmap May 2, 2018 attended PIC 2 Attended PIC 1 Submitted comments online email April 23 via email il.com attended PIC 2 a attended PIC 2 attended PIC 2 submitted comments online email April 23 via email Submitted comment via webmap Feb 20, 2019 attended PIC 2 Emailed to be added to the list on Friday May 18th Emailed Wednesday Feb 28th 2018 to be added to the study contact list. email April 23 via email Submitted comments online email April 23 via email attended PIC 2 Feb 19 via Canada Post om attended PIC 2 Attended PIC 1 attended PIC 2 Attended PIC 1 Phone call Wednesday Feb 14, 2018. Just generally inquiring about the project and new Municipal stormwater charge. Stantec and Municipality followed up regarding Friday April 20 Canada Post - Followed up with PIC stormwater charge. Materials on Monday May 14 via email Phone call Feb 27, 2018. Noted that after re-paving and culvert replacement along Thirteen Mile Rd. and Salisbury, experiences ponding in front of his property, and his basement has flooded. Friday April 20 Canada Post Feb 19 via Canada Post Submitted comment via online webmap April 24, 2018 Submitted comment via webmap Sept 28, 2018 Feb 19 via Canada Post Submitted comment via online webmap Aug 28, 2018 Submitted comment via webmap August 29, 2018 attended PIC 2

Email - March 25 to discuss status of the master plan project, has concerns regarding drainage to oxbow creek Phone call with project team Friday April 5th, 2019 to discuss erosion and sedimentation in Oxbow creek, and the impacts of more drainage from future developments.