PROJECT: LIME STONE & DOLOMITE MINING PROJECT PRE-FEAS IBILITY REPORT APPLICANT: SRI K.H.SABARAD

1

PROJECT: LIME STONE & DOLOMITE MINING PROJECT PRE-FEAS IBILITY REPORT APPLICANT: SRI K.H.SABARAD

PRE-FEASIBILITY REPORT

FOR

HEBBAL LIMESTONE & DOLOMITE MINE

(Expansion)

Hebbal Village, Taluk, District

Area - 4.86 ha Enhancement Production:-57,000 TPA to 1,20,000 TPA

Applicant:

Sri. K.H. Sabarad APMC Yard, Mallammanagar Nagar, Mudhol-587313 Mudhol Taluk, ,

Prepared by:

M/S SRI SAI MANASA NATURE TECH PVT. LTD (SSMNTECH) #906, B, WING, 9TH FLOOR, MITTAL TOWER MG ROAD, BANGALORE-56001 2

PROJECT: LIME STONE & DOLOMITE MINING PROJECT PRE-FEAS IBILITY REPORT APPLICANT: SRI K.H.SABARAD

1.1 EXECUTIVE SUMMARY

1.2 EXECUTIVE SUMMARY

The subject Mining lease area granted for Mining of Limestone and Dolomite by Sri. K.H. Sabarad of Hebbal Limestone & Dolomite Mine for ML No.2493 is situated in Sy.No. 118(P), in 4.86 Ha, in Hebbal Village, Mudhol Taluk, Bagalkot District Karnataka state in Patta Lands.

The lease area is a non- forest waste land. The mining plan was approved under MMDR Act, 1957 vide approval No.MP/MAN-562(KNT)/GOA/2004-05 DATED 27.09.2004. As per the MMDR Act, 2015 the mining lease period would be for 50 years from 01.07.2005 to mine limestone. The date of expiry of mining lease will be 30.06.2055 and the date of commencement of mining operation in this area was 06.12.2006. The modification in approved mining plan was approved under MCDR Act 1988 for enhancement of production vide approval No.MP/MAN-562(KNT)/GOA/200-2005 DATED 16.01.2008. The 1st Scheme of mining for the period from 2011-12 to 2015-16 was approved under MCDR 1988 vide approval letter No-MSH/MAN-216/KNT/GOA/2011-12 DATED 206.08.2011 The 2nd Scheme of Mining has been approved by IBM their vide letter no MSH/OTF.MECH- 101(KNT)/GOA/2015-2016 dated 10.03.2016. (Annexure-I). The present proposal is submitted for enhancement of 57,000 to 1, 20,000 TPA of Limestone and the project is proposed considering as Category B2.

1.3 SALIENT FEATURES OF THE PROJECT

Environmental setting Hebbal Limestone & Dolomite Mine Project name

Location of mine Sy.N. 118(P), Hebbal Village, Mudhol Taluk, Bagalkot District Karnataka state Latitude N160 11’39.73” to N160 11’46.55” Longitude E750 20’21.07” to E750 20’21.05” Toposheet number 47 P/8

Type of Land Patta Land

3

PROJECT: LIME STONE & DOLOMITE MINING PROJECT PRE-FEAS IBILITY REPORT APPLICANT: SRI K.H.SABARAD

Minerals of mine Limestone & Dolomite Total geological reserves 10,15,810n Tons Total mineable geological reserves 7,82,059 Tons Life of mine 7 years Proposed production of mine 1,20,000 Tons/year Method of mining Open Cast Semi mechanized mining method No of working days 300 Water demand 5.28 KLD Sources of water Near By Bore wells Man power 32 Nearest railway Station Bagalkot Railway station- 45 kms- (E) Nearest state highway/national Bagalkot to Belgum-SH 44- 4.5 Kms (E) highway Gulbarga-- Hwy- NH218- 30Kms (E) Nearest air port Hubli Airport- 96 Kms- (S) Seismic zone Seismic zone III

1.4 PROPOSED PLANNING

Mining method - Open Cast Semi mechanized mining method Project cost - Rs 50 Lakhs Production - Enhancement of 57,000 to 1, 20,000 TPA EXISTING LAND USE PATTERN

S. No. Particulars Present land use pattern (ha) 1 Area under mining 3.021

4 Roads 0.248

3 Green belt 0.375

4 Undisturbed Area 1.216

Total 4.86

4

PROJECT: LIME STONE & DOLOMITE MINING PROJECT PRE-FEAS IBILITY REPORT APPLICANT: SRI K.H.SABARAD

1.5 CONCLUSION Karnataka has the largest limestone reserve in . The districts of Gulbarga, Bagalkot, , Shimoga and other Uttara districts are endowed with extensive high grade limestone. The present and consistent production of approximately 14 million tonnes provides for the cement plants in these districts.

2. INTRODUCTION OF THE PROJECT/ BACKGROUND INFORMATION The mining lease was executed over an area of 4.86 Ha, in Hebbal Village, Mudhol Taluk, Bagalkot District Karnataka in favor of Sri. K.H. Sabarad.

2.1 BRIEF INFORMATION ABOUT THE PROJECT

The lessee wants to enhance the production from 57,000 TPA to 1, 20,000 TPA of Limestone and Dolomite by semi mechanized method. The lease area is 4.86 ha. No forest land is involved. The total mineable geological reserves available are 7, 82,059 MT of limestone. The expected life of the mine is 7 years. Total top soil generation during the life of the project will be 1695.10 Cum and OB will be 1, 21, 46.15 Cum. The black cotton soil will be removed during mining will be utilized to form bund all along the lease boundary on which green belt will developed. The intercalated waste which is an intercalated shale in the plan period may used for lying road from mine to approach road and to maintain roads within mine area and rest will be dumped in the area earmarked on mineralized area within the lease area. Water requirement for the proposed project for domestic use, dust suppression and plantation, will be 5.28 KLD, which will be met from tube well pumps at nearest village.

2.3 NEED FOR THE PROJECT AND ITS IMPORTANCE TO THE COUNTRY OR REGION

The basic objective of the project is to effective utilization of Mineral in the country and /or region. With the development and industrialization has enhanced the demand of Limestone. Limestone is greatly used in architecture as it is easily obtained, cut and carved. Limestone rocks contain flint, clay, sand and calcite in varying amounts. It is also preferred by most of the people

5

PROJECT: LIME STONE & DOLOMITE MINING PROJECT PRE-FEAS IBILITY REPORT APPLICANT: SRI K.H.SABARAD in architecture and decoration, as it is long lasting and does well in every climatic condition. Calcareous sedimentary rocks are known as limestone and they are composed of the mineral calcite. When calcite’s calcination is done, it gives lime as a product. In nature, limestone is available in various purity levels, depending upon the other minerals present with it. For example, if some limestone is present with more than 10% of dolomite, it is called as dolomite limestone and same goes for magnesium limestone too. When limestone is recrystallised and polished, it becomes a decorative and building stone called “marble.

2.4 DEMANDS-SUPPLY GAP In India Limestone has a wide application and demand. The major application of limestone in India is in cement Industry. According to the Cement Manufacturers’ Association, (2010) India ranks second in cement production in the world, with an installed capacity of about 230 million tonnes in 2008–09. The Indian cement industry has been on a high growth trajectory for more than a decade, led by buoyancy in sectors such as real estate and construction. Government expenditure on infrastructure, in the Eleventh Five Year Plan (2007–2012), is expected to be to the tune of US$ 350 billion. Moreover, the government's continued thrust on infrastructure will help the key building material to maintain an annual growth of 9-10 per cent in 2011. The mining industry has witnessed continuous modernization and adoption of new technologies in recent years for the excavation of mineral like Limestone. Limestone demand has been on an upsurge in India due to the high-rise demand in the cement Industry. Demand is being driven by mega infrastructure, residential and commercial projects.

Major producing areas/ Supply In India, limestone is available in many states such as Karnataka, Rajasthan, Himachal Pradesh, Madhya Pradesh, Tamil Nadu, Andhra Pradesh and Jharkhand. The value of production of non-metallic minerals was at Rs. 3527.62 crores during 2008- 09, and increased by 2.89% as compared to the previous year. Limestone retained its leading position by contributing 70.92% of the total value of non-metallic minerals in 2008-09. The production of Limestone at 204 million tonnes in 2008-09 increased by 5% as compared the previous year. Limestone is widely produced in India. As much as 88% of the total output in 2008-09 was contributed by seven principal States; viz. Andhra Pradesh (22%), Rajasthan

6

PROJECT: LIME STONE & DOLOMITE MINING PROJECT PRE-FEAS IBILITY REPORT APPLICANT: SRI K.H.SABARAD

(18%), Madhya Pradesh (13%), Gujarat (11%), and Tamil Nadu, Chhattisgarh and Karnataka (8% each). The remaining 12% of the total production was shared by other limestone producing States.

2.5 IMPORTS VS. INDIGENOUS PRODUCTION There will be no import of Limestone. 2.6 EXPORT POSSIBILITY Limestone production from this project will be exported. 2.7 DOMESTIC/ EXPORT MARKETS DOMESTIC MARKET Sri. K.H. Sabarad of Hebbal Limestone & Dolomite Mine is supplier of limestone to major industries. EXPORT MARKET The proposed mining activity is for indigenous consumption only for producing cement.

2.8 EMPLOYMENT GENERATION

DIRECT EMPLOYMENT

Total employment in the mining lease will be around 32 people. The local villagers will be preferred for employment.

A list of technical, supervisory staff, semi-skilled and skilled persons are given below:

1 Highly Skilled 2

2 Skilled 1

3 Semi-skilled 10

4 Un-skilled 19

Total 32

7

PROJECT: LIME STONE & DOLOMITE MINING PROJECT PRE-FEAS IBILITY REPORT APPLICANT: SRI K.H.SABARAD

3. PROJECT DESCRIPTION

3.1 TYPE OF PROJECT INCLUDING INTERLINKED AND INTERDEPENDENT PROJECTS, IF ANY. The proposed project of 4.86 ha area is operating limestone mine and falls under Category-“B2” As per the EIA notification of Ministry of Environment Forests and Climate Change, Govt of India (MoEF&CC), dated 14th September, 2006, as amended from time to time.

3.2 LOCATION

The mining lease area is located in Hebbal Village, Mudhol Taluk, Bagalkot District Karnataka. The mining lease area falls in Survey of India Toposheet No. 47 P/8. The vicinity map is given below:

8

PROJECT: LIME STONE & DOLOMITE MINING PROJECT PRE-FEAS IBILITY REPORT APPLICANT: SRI K.H.SABARAD

Fig: Vicinity Map

9

PROJECT: LIME STONE & DOLOMITE MINING PROJECT PRE-FEAS IBILITY REPORT APPLICANT: SRI K.H.SABARAD

Toposheet Details

Toposheet No. : 47 P/8

Latitude : N160 11’39.73” to N160 11’46.55”

Longitude : E750 20’21.07” to E750 20’21.05”

The Lease area is well connected. Petlur-Yadwad PWD Road is 0.45 km in South direction. -Yadwad Main Road is 1.25 km in North direction.

3.3 DETAILS OF ALTERNATE SITES No alternate site was considered as the project is mineral specific.

3.4 SIZE OR MAGNITUDE OF OPERATION 3.4.1 GEOLOGY 3.4.1.1 GENERAL GEOLOGY

Calcareous materials occur in almost all the geological formations of India, but, those of Commercial importance occur in the rocks of Pre-cambrian, Triassic, Eocene and Sub Recent to Recent formations. In Karnataka state, calcareous materials cover a large area Especially in Bhimas and Kaladgis of Pre-cambrian era.

The study area forms a part of the basin which belongs to the Upper Cuddapah system. “Kaladgi Series” was the name originally given by Bruce Foote (1876) to the rocks deposited in an interior basin named after the town of Kaladgi, where rocks of this group were first seen well developed. Kaladgi series are exposed fringing the southern border of the great expanse of flat- laying Deccan trap cover and are seen to extend in the form of an E-W trending irregular doubly plunging basin. Bulk exposures are confined to Belgaum, Bijapur and Bagalkot districts with outliers in Dharwad and Gadag districts.

The basin extends E-W for nearly 500 Km and is hidden beneath the Deccan trap to the west and to north.

The Kaladgi rocks were originally divided by Foote in to two groups, lower and upper group, on the basis of unconformity and distinct tectonic evidences. But, the recent works have necessitated a recision in stratigraphy. The Kaladgi has now been accorded a Supergroup status

1 0

PROJECT: LIME STONE & DOLOMITE MINING PROJECT PRE-FEAS IBILITY REPORT APPLICANT: SRI K.H.SABARAD consisting of a lower group for which the name Bagalkot group has been given. The upper sequence is designated as the Group. A number of formations have also been recognized.

The order of superposition as given by B. P. Radhakrishna (1997) is given as follows.

Badami Goup Shales, Limestones and Haematite Schists

(Upper) quarzites, local conglomerate, breccia

------Angular Unconformity ------

Bagalkot Goup Limestones, clays and shales, sandstones

(Lower) and shales, silicious limestone and

hornstone breccia quartizite,

conglomerates and sandstones.

The lower Bagalkot group and the upper Badami group of rocks of Kaladgi Super Group are divided by a distinct angular unconformity in-between. The upper Badami group has a thickness of 290m while the lower Bagalkot group has thickness of 3360m.

The lower Bagalkot group is further divided into lower Lokapur sub group (2211 m thick) and upper Simikere sub group (1149 m thick). The Lokapur and Simekere sub groups possess similar litho-units but, the former has a greater thickness and larger area extent. The Bagalkot groups of rocks are confined to the central parts of the Kaladgi basin and always occur as elongated doubly plunging synclines and complimentary anticlines of different dimensions with longer axes trending E-W to WNW-ESE. The Badami group of rocks overlies the two subgroups of Bagalkot group as well as the basement granitoids with an unconformity marked by a prominent conglomerate horizon.

Limestone formations of the area are by and large confined to the Lokapur sub group of the lower Bagalkot group.

RESERVES

Reserves based on availability of limestone encountered at each trial pits and trenches have been estimated.

10

PROJECT: LIME STONE & DOLOMITE MINING PROJECT PRE-FEAS IBILITY REPORT APPLICANT: SRI K.H.SABARAD

TABLE: ESTIMATION OF RESERVES AS PER UNFC GUIDELINES

UNFC Quantity in Grade Code tons

Limestone Limestone

A. Total Mineral Reserve

Proved Mineral Reserve 111 111 7,82,059 CaO 47.62 MgO 03.36

B. Total Remaining Resources ------

Prefeasibility mineral resource 221 and 222 222 2,33,751 CaO 47.62 MgO 03.36

Total Reserves + Resources 10,15,810 --

PRODUCTION PARAMETERS

The Geological Reserve is 10, 15,810 tones of Limestone and mineable Reserve is 7, 82,059 tones. The production target for the first five years, along with the target for removal of OB and waste is given below:

11

PROJECT: LIME STONE & DOLOMITE MINING PROJECT PRE-FEAS IBILITY REPORT APPLICANT: SRI K.H.SABARAD

TABLE: PRODUCTION TARGETS

Year Total Top Soil OB/SB/IB ROM (Cu m) ROM/ tentative (0.5m @5% generated @95% recovery Waste

Excavatio (Cum) Ratio

n ROM reject No. Ore Ore Miner

(Cu m) (Cum) @ 2.60 al

Pit (Cum) @2.60 t/mbd (t) reject

t/mbd (Cum) Mineral (t) 1 2 3 4 5a 5b 6a 6b 7 8 9

I. I 50278.18 1695.10 2429.23 6,316 46153.85 1,20,000 -- -- 1:0.05 2016-17

II. I 48583.08 -- 2429.23 6,316 46153.85 1,20,000 -- -- 1:0.05 2017-18

III. I 48583.08 -- 2429.23 6,316 46153.85 1,20,000 -- -- 1:0.05 2018-19

IV. I 48583.08 -- 2429.23 6,316 46153.85 1,20,000 -- -- 1:0.05 2019-20

V. 2020- I 48583.08 -- 2429.23 6,316 46153.85 1,20,000 -- -- 1:0.05 21 Total 244610.50 1695.10 12146.15 31,580 230769.25 6,00,000 -- -- 1:0.05

3.5 PROJECT DESCRIPTION WITH PROCESS DETAILS

3.5.1 METHOD FOR DEVELOPING AND WORKING THE DEPOSITS The mine will be worked by means of opencast semi-mechanized method of mining with the conventional system, which includes drilling, blasting, loading and transportation.

3.5.2 METHOD OF MINING It is proposed to work the area by opencast method of mining utilizing heavy earth moving equipments for overburden removal and manual labour for limestone extraction. a- Surface soil capacity shall be taken and stacked separately. b- The benches will be kept at 3 m height and 4m width, until suitable permission from DGMS is obtained to keep higher benches in hard strata. For this, the present bench

12

PROJECT: LIME STONE & DOLOMITE MINING PROJECT PRE-FEAS IBILITY REPORT APPLICANT: SRI K.H.SABARAD

heights which are more than 3 m height will be made to 3m gradually starting from the top most benches c- The deposit is considered upto 544.41 m level. After exploration the feasible depth to which excavations can be extended with 600 ultimate slope will be decided. d- The depth of the working will extend upto 523.66 m.

3.5.2.1 MECHANIZATION Selection of major mining equipment is an integral part of mine production planning. The details of equipments proposed to be used in mining operation are listed below:-

S. Name of Equipment No. Model Capacity No. 3 1 Excavator 2 TATA 0.9 m

2 Dumper 10 T. 3 TATA 10 ton

3 Compressor 3 VT4 Atlas 140Cum

4 Jack Hammers 1 - -

5 Water tanker 1 TATA make 3000 liters

6 Jeep 1 Mahindra 2523cc

3.5.3 BLASTING PARAMETERS The explosive required per annum at a powder factor of 7 tonnes/ kg will be 1,26,316 /7t/kg =18,045 kg(say). It is proposed to use slurry explosive. The charge per hole is 250gms ; charging will be by safety fuse ; handling – tie up with the explosive suppliers (sale, possesses and use of explosives) ; system of initiation – ordinary. In addition, we require 67,476 m of safety fuse and 44,984 number of ordinary detonators for detonation purpose. About 150 holes to be blasted/day. 75 holes will be blasted at one time, likewise 2 times blasting will be done in a day. No significant air blast or vibrations will be envisaged. However, since the area is surrounded by an agricultural land, if required, sand bags/ mud bags will be kept on holes and will be muffled.

13

PROJECT: LIME STONE & DOLOMITE MINING PROJECT PRE-FEAS IBILITY REPORT APPLICANT: SRI K.H.SABARAD

Powder factor :

The detailed calculations showing the powder factor in this area is as follows.

Spacing ………………………… 1.00 m

Burden ………………………… 0.90 m

Depth of the hole ………………… 1.50 m

Bulk Density ………………… 2.60 t/Cum

Blasting efficiency ……………… 80%

Therefore, the powder factor = 1.00m x 0.90m x 1.5m x 2.60 t/Cum

= 3.51 tonnes for 0.5 kg. Explosives

For 1 Kg Explosives = 7.02 say 7t/Kg

Therefore, each hole gives us =1.00m x 0.90m x 1.5m x 0.80 x 2.60 t/Cum

= 2.808 tonnes ROM

The ROM to be handled is 1,26,316 tpa.

No. of holes required for 1,26,316 tpa will be 1,26,316 / 2.808 = 44,984Nos

Total drilling required will be 44,984 x 1.5m = 67,476 m

One tractor mounted compressor can give 30,000 m/ annum. Thus Three tractors

Compressors are more than adequate for the proposed production.

3.5.3.1 STORAGE OF EXPLOSIVE Storage of explosive at the mine site is not required as a vendor having valid license for blasting has been assigned to do blasting in the mines.

3.6 RAW MATERIAL REQUIRED ALONG WITH ESTIMATED QUANTITY, LIKELY SOURCE, MARKETING AREA OF FINAL PRODUCT/S, MODE OF TRANSPORT OF RAW MATERIAL AND FINISHED PRODUCT No raw material will be required for production of limestone. ROM limestone will be sent to nearby industries. The mode of transportation of raw material and finished product will be through roads/ highways.

14

PROJECT: LIME STONE & DOLOMITE MINING PROJECT PRE-FEAS IBILITY REPORT APPLICANT: SRI K.H.SABARAD

3.7 RESOURCE OPTIMIZATION/ RECYCLING AND REUSE Not envisaged.

3.8 AVAILABILITY OF WATER ITS SOURCE, ENERGY/ POWER REQUIREMENT AND SOURCE 3.8.1 WATER REQUIREMENT Water for drinking and operations is required to be 5.28 KLD, which will be met from tube well at nearest village. S.No. Description Water Requirement (KLD) 1. Domestic 1.28 2. Dust suppression & Green 4.00 Belt Total 5.28

3.8.2 POWER If any, as per requirement. 3.9 QUANTITY OF WASTES TO BE GENERATED (LIQUID AND SOLID) AND SCHEME FOR THEIR MANAGEMENT/ DISPOSAL 3.9.1 SOLID WASTE GENERATION & ITS DISPOSAL The black cotton soil of 1695.10 Cum (0.5m thick) will be removed during mining will be utilized to form bund all along the lease boundary on which green belt will developed. The intercalated waste which is an intercalated shale in the plan period may used for lying road from mine to approach road and to maintain roads within mine area and rest will be dumped in the area earmarked on mineralized area within the lease area. The retaining wall of about 117m length on 3 sides of waste dump to avoid runoff of fragments and 325m of garland drain around waste dump to control wash off of silt and sediments will be made in the 1st year of plan period and plantation will be made on the dump. The height of the dumps will be maintained average 10m from the ground surface taking necessary measures to maintain the dump slope at an angle of 270 natural slope from the horizontal for proper stability.

15

PROJECT: LIME STONE & DOLOMITE MINING PROJECT PRE-FEAS IBILITY REPORT APPLICANT: SRI K.H.SABARAD

3.9.2 LIQUID EFFLUENT The domestic and service building effluents are collected by a sewerage system and biological treatments is adopted by means of septic tanks and soak pits.

4. SITE ANALYSIS 4.1 CONNECTIVITY

The Lease area is well connected. Petlur-Yadwad PWD Road is 0.45 km in South direction. Lokapur-Yadwad Main Road is 1.25 km in North direction.

4.1.1 NEAREST RAILWAY STATION

Bagalkot Railway station- 45 kms- (E) 4.1.2 NEAREST AIRPORT Hubli Airport- 96 Kms- (S) 4.1.3 NEAREST HIGHWAY Bagalkot to Belgum-SH 44- 4.5 Kms (SE) Gulbarga-Bijapur-Hubli Hwy- NH218- 30Kms (E) 4.2 LANDUSE 4.2.1 LAND USE The existing land use pattern is as below:-

S. No. Particulars Present land use pattern (ha) 1 Area under mining 3.021

4 Roads 0.248

3 Green belt 0.375

4 Undisturbed Area 1.216

Total 4.86

4.3 TOPOGRAPHY & DRAINAGE

Topography: The Lease area is a waste/agriculture land. The terrain is gently sloping towards East and South. No major roads pass through the Lease area.

16

PROJECT: LIME STONE & DOLOMITE MINING PROJECT PRE-FEAS IBILITY REPORT APPLICANT: SRI K.H.SABARAD

No human settlements within or in the vicinity of the Lease area. No nallahs or streams are seen within the Lease area.

The nearest wild life sanctuary is at Dandeli which is at a distance of 140 kms from the Lease area. Drainage: The drainage pattern of the buffer zone is dendritic to sub-dendritic in nature.

No perennial nallahs or streams are seen within the Lease area.

There are no natural springs in the area.

The water table is about 80 m (i.e. 486.85 m RL) generally below the ground level.

4.5 EXISTING INFRASTRUCTURE

At present there is a regular mine office within the lease area, a rest shelter and First-Aid station etc. as per the statutory provisions. Residence of officials and staffs are at Banjari and laborers are all local resident.

4.6 SOIL CLASSIFICATION

There is only black cotton soil in the area.

Black cotton soil is usually light black to black in colour and vary in thickness from 0.25mtrs to 0.5 mtrs and have high water holding capacity.

4.7 CLIMATIC DATA FROM SECONDARY SOURCES

The climatic conditions are Semi-arid. The maximum and minimum temperature during the year varies from 36 0C in summer to 28 0C in winter on the basis of last 8 years observations. The average rainfall in the area is 85 cm per year. Solar radiations are available for about nine months per year. Average humidity is 12 %.

The temperature variations in different three seasons are given below:

Season Minimum Temperature Maximum Temperature

th th 0 0 0 0 Summer (16 Feb to 15 15.7 C – 20.5 C 31.7 C – 36.0 C June)

17

PROJECT: LIME STONE & DOLOMITE MINING PROJECT PRE-FEAS IBILITY REPORT APPLICANT: SRI K.H.SABARAD

th th 0 0 0 0 Rainy (16 June to 15 18.8 C – 20.9 C 25.6 C – 28.2 C October)

Winter (16th Oct to 15th Feb) 14.50C – 16.80C 28.30C – 29.4 0C

4.8 SOCIAL INFRASTRUCTURE AVAILABLE  Company will adopt a program of Eye Camp & Medical Camp for the neighborhood villages two times a year. In each camp, about 50 patients are examined. Medicinal costs are met by the lessee, and spectacles are provided free of cost time to time.  First aid training has been regularly imparted to trainees from the neighboring villages.  The lessee also distributes saplings to the local villagers as a part of social forestry.

5. PLANNING BRIEF 5.1 PLANNING CONCEPT It is a mining industry in which open cast semi mechanized mining method will be plasticized. Project will Enhance the production of Limestone 57,000 TPA to 1, 20,000 TPA.

5.2 LANDUSE PLANNING The land-use of this region has approximately been estimated and is given in Table below:

S. No. Particulars Present land End of the fifth Conceptual use pattern years land use pattern (ha) (ha) (ha) 1 Area under mining 3.021 3.302 3.302

2 Waste dump site -- 0.351 0.351

3 Mineral Storage -- 0.287 0.287

4 Roads 0.248 0.130 0.130

5 Green belt 0.375 0.563 0.750

6 Undisturbed Area 1.216 0.227 0.04

Total 4.86 4.86 4.86

18

PROJECT: LIME STONE & DOLOMITE MINING PROJECT PRE-FEAS IBILITY REPORT APPLICANT: SRI K.H.SABARAD

5.3 ASSESSMENT OF INFRASTRUCTURE DEMAND (PHYSICAL & SOCIAL)

The existing road network will be sufficient to meet the proposed production capacity; however required infrastructure for transport within the leasehold area will be further strengthened and improved. No new routes or alteration are required in this regard.

5.4 AMENITIES/FACILITIES Applicant proposes to employ about 32 persons. This employment has a positive impact on the soci-economic conditions of the surrounding as most of the work force employed will be from nearby areas. Local persons will be hired for meeting the requirement of trucks loading, plantation, construction of check dams, retaining walls etc. The benefits due to quarry to the local population will be in the form of direct and indirect employment opportunities.

6. PROPOSED INFRASTRUCTURE 6.1 INDUSTRIAL AREA (PROCESSING AREA)

No infrastructure is proposed. 6.2 RESIDENTIAL AREA (NON PROCESSING AREA) As the local person will be given employment, no residential area/ housing is proposed. 6.3 GREEN BELT:

It is proposed to develop green belt all along the boundary covering length of 50 m/ year and afforestation will be done using 50 saplings per year at an interval of 2m in two rows. Same rate of afforestation will be carried out upto lease period. Thus, entire length of boundary will be covered.

Year No,s Species

Common Name Botanical Name 1 50 Bage Albezia lebbeck Krisha cadmba tree Anthocephalus cadamba 2 50 Neem tree Azadirachta indica Custard Apple Annona reticulata Sugar-apple Annona squamosa 3 50 Hibiscuc plant hibiscus tilliaceus Champak tree (sampige) Michelia champaca 4 50 Honge tree Pongamia pinnata Ashok tree Polyalthia longifolia

19

PROJECT: LIME STONE & DOLOMITE MINING PROJECT PRE-FEAS IBILITY REPORT APPLICANT: SRI K.H.SABARAD

5 50 Aakash mallige Millingtonia hortensis Arali Ficus religiosa Ala Ficus benghalensis Sacred tree (Muthuga) Butea monospema Total 250

6.4 SOCIAL INFRASTRUCTURE

 Company will adopt a program of Eye Camp & Medical Camp for the neighborhood villages two times a year. In each camp, about 50 patients are examined. Medicinal costs are met by the lessee, and spectacles are provided free of cost time to time.

 First aid training has been regularly imparted to trainees from the neighboring villages.  The lessee also distributes saplings to the local villagers as a part of social forestry.

6.5 CONNECTIVITY

Road is very close to the working site. There is no proposal to make any new kind of connectivity.

6.6 DRINKING WATER MANAGEMENT

Water for drinking and operations is required to be 5.28 KLD. It is proposed to obtain water for drinking and operations from Tube-wells. After implementation of EMP, treated waste water will be used in plantation.

6.7 SEWERAGE SYSTEM Domestic waste water will be treated into septic tank followed by soak pit.

6.8 INDUSTRIAL WASTE MANAGEMENT

Not applicable

6.9 SOLID WASTE MANAGEMENT

The black cotton soil of 1695.10 Cum (0.5m thick) will be removed during mining will be utilized to form bund all along the lease boundary on which green belt will developed.

20

PROJECT: LIME STONE & DOLOMITE MINING PROJECT PRE-FEAS IBILITY REPORT APPLICANT: SRI K.H.SABARAD

The intercalated waste which is an intercalated shale in the plan period may used for lying road from mine to approach road and to maintain roads within mine area and rest will be dumped in the area earmarked on mineralized area within the lease area. The retaining wall of about 117m length on 3 sides of waste dump to avoid runoff of fragments and 325m of garland drain around waste dump to control wash off of silt and sediments will be made in the 1st year of plan period and plantation will be made on the dump. The height of the dumps will be maintained average 10m from the ground surface taking necessary measures to maintain the dump slope at an angle of 270 natural slope from the horizontal for proper stability.

6.10 POWER REQUIREMENT & SUPPLY/ SOURCE If any, as per as requirement

7 REHABILITATION AND RESETTLEMENT (R&R) PLAN Not Applicable

8 PROJECT SCHEDULE & COST ESTIMATES 8.1 LIKELY DATE OF START OF CONSTRUCTION AND LIKELY DATE OF COMPLETION

The construction activity will be taken up in parallel along with the opening of mine.

8.2 ESTIMATED PROJECT COST ALONG WITH ANALYSIS IN TERMS OF ECONOMIC VIABILITY OF THE PROJECT

The estimated project cost will be Rs. 50 lakhs

8.2.1 COST OF MINING

The estimated total cost of the project is Rs. 50 lakhs. The land is patta lands including the cost of the machinery and additional preliminary works and working capital i.e. for the application and processing fee, etc.,

21

PROJECT: LIME STONE & DOLOMITE MINING PROJECT PRE-FEAS IBILITY REPORT 8.2.2 COST APPLICANT:OF THE MINERAL SRI K.H.SABARAD

The maximum proposed production of limestone during the first five years is around 1, 20,000 TPA.

Operating cost of limestone is projected as Rs. 173/tons

Sale value of produced limestone is projected as Rs. 300/ tons.

9.0 ANALYSIS OF PROPOSAL (FINAL RECOMMENDATIONS)

9.1 FINANCIAL AND SOCIAL BENEFITS WITH SPECIAL EMPHASIS ON THE BENEFIT TO THE LOCAL PEOPLE INCLUDING TRIBAL POPULATION, IF ANY, IN THE AREA. The project will provide necessary raw material for the Cement plant. In addition it will add to revenue generation of the District/ State.

There will be social benefits from the mining operations and the integrated cement plant in the region. The underlying benefits through the proposed project are:-

It aims to provide additional employment to the local population of the area.

The proposed project aims to fulfill its social sustainable responsibility though promoting and maintain permanent structures as follows:-

• Facility for village schools including classroom/toilet construction, ceiling fans/coolers or books for school library.

• Vocational training to be provided to the persons for improving their skills in income generation techniques like stitching, Hatchery, plumber, carpentry, blacksmithy etc.

• Formation of Self- Help Groups to develop the savings and helping each other with financial resources instead of going for heavy interest debts.

• As per the preliminary site visit, the above activities were identified on the need based requirement of the study area. Further activities will be analyzed, after the analysis of the baseline data generation and socio- economic survey; the appropriate sustainable development will be contributed and projected by the proposed project. The appropriate amount of CSR is proposed to be Rs. 2.00 Lakhs .

*****************

22