Prepared by IPC 21/09/17 A glimpses of Port of Cirebon Operation Area of Pelindo I,II,III and IV

We are ‘HERE’

3 | Energizing Trade. Energizing Port of Cirebon – Facility and Equipment

Dermaga Samadikun : 67 M / -4 MLWs LAPANGAN 2 Lp. Muarajati : 4.480 M Dermaga Perniagaan I - IV : 44 M / -3 MLWs 2 Lp. Pelita : 9.780 M 2 Dermaga S. Sumantri I - V : 68 M / -3,5 MLWs Lp. Suryat Sumantri : 8.048 M 2 Dermaga Muara Jati I - III : 603 M / -5,5 sd -6 MLWs Lp. Linggarjati : 5.600 M GUDANG Dermaga Linggar Jati I -II : 171 M / -4,5 MLWs 2 Gudang Muarajati : 4.000 M Dermaga Pelita I - III : 98 M / -5,5 MLWs 2 Gudang 101 : 1.806 M Kade Khusus Pelra : 150 M / -2 MLWs 2 Gudang 102 : 1.500 M 2 Total Panjang Dermaga : 1,201 M Gudang 103 : 306 M 2 Gudang 104 : 1.050 M 2 Gudang Terbuka Pelra : 1.200 M

Wheel Loader Kap.5,1 M3 HL 780- Mobil Crane IHI 25 Ton 1 1 7A Merk Hyundai

Jembatan Timbang 1 Wheel Loader Kap.5 Ton 1

Excavator Komatsu 2 Wheel Loader kap 3 Ton 1

Excavator Hyundai 2 Rampdoor 3

Excavator Caterpilar 2 Forklift Kap.5 Ton 1

Dump Truck 4 4 Mobil PMK Kapasitas 5.000 m3 1 4 | Energizing Trade. Energizing Indonesia Port of Cirebon - Ships Traffic

Dominate by Tug and Barge

Gross Tonnage Unit 2.500.000 1.800

1.600

2.000.000 1.400

1.200 1.500.000 1.000

800 1.000.000 600

500.000 400 200

- - s/d Juli s/d Juli 2013 2014 2015 2016 2013 2014 2015 2016 2017 2017 GT 1.974.9 2.139.0 1.987.1 1.048.8 1.296.7 UNIT 1.407 1.536 1.329 788 934

5 | Energizing Trade. Energizing Indonesia Port of Cirebon – Cargo Throughput

Dominate by Dry Bulk Commodity (Tonnage) 5.000.000 4,513,941 4.500.000 4,028,447 4,200,471 4.000.000 3.500.000

3.000.000 2,359,869 2,271,442 2.500.000 2.000.000 1.500.000 1.000.000 500.000 - 2013 2014 2015 2016 s/d Juli 2017 General Cargo - - 46.606 28.884 893 Curah Cair 331.169 322.516 313.100 288.568 200.059 Bag Cargo 264.029 144.709 115.021 108.955 61.775 Curah Kering 3.433.249 4.046.716 3.725.744 1.933.462 2.008.715

6 | Energizing Trade. Energizing Indonesia Potential Market Opportunities Due to limited draft, the cargo is currently transit in some neighbouring ports. Strategic Market Opportunities

3 Biggest Animal Feed Factory in Cirebon have average production 1.000.000 tonnes 1 annually, currently it is unloaded at Ciwandan dan Cigadeng Port in Banten 2 Fertilizer company around Cirebon have average production up to 50.000 tonnes annually More than 20 textile company and other industries moved from Bandung, Jakata, and 3 Tangerang to Cirebon-Indramayu-Majalengka-Kuningan (CIAYUMAJAKUNING) 4 Potential volume form salt, sugar, and cattle industry

5 Cargo handling of PLTU 2 & 3 project

6 Liquid bulk facility improvement potential

7 Passenger Vessel & Roro services

8 Domestik and international container services

8 | Energizing Trade. Energizing Indonesia WEST SPATIAL PLAN

West Jawa Saptial Structure Plan

PKN METROPOLITAN BODEBEK Kawasan Industri PKN METRO PKN CIREBON PKW METRO PELABUHAN BANDUNG RATU

PKWp RANCA BUAYA PKNp PANGANDA RAN

Sumber : BAPPEDA JABAR PKN, PKW : National/Regional Center of Activity Pengembangan Kawasan Strategis Cirebon Spatial Plan Kabupaten Cirebon Economic Growth Strategic Region (KSK) - (Agro Region Arjawinangun) Java Social and Sea Culture Strategic Region Economic (Gunung Growth Jati Region) Strategic Region (KSK) - (Plumbon Region)

Economic Growth Strategic Region (agro Ciledug KABUPATEN KUNINGAN Cirebon District Strategic Region) 10 Region Plan

(KSK Cirebon) Sumber : BAPPEDA Kabupaten Cirebon Port of Cirebon

DLKR/DLKP Pelabuhan Cirebon

According to “Keputusan Bersama Menteri Dalam Negeri dan Menteri Perhubungan No. 58 tahun 1988 dan Nomor : KP 25/AL 108/PHB-88 tentang Batas- batas DLKR/DLKP Pelabuhan Cirebon”, it has been stated that Cirebon Port have 51 ha DLKR dan 25 ha DLKP, also 8.410,91 ha of Port Basin Area.

Port of Cirebon is currently can handle only for the vessel up to -6.5m. For the vessel that have more than -6.5mlws has to be discharge at the outer area that safe and recommended by Harbour Master. The future plan, Port of Cirebon expected big vessels that have draft up to -10mlws to come and discharge in the port.

11 Port of Cirebon Development Plan Fairway Developmen Plan before -5.5mlws to be -12mlws

DATA SURVEI ARUS DAN GELOMBANG

Arah Arus Laut

Pelabuhan Cirebon

Gugusan karang

CIREBON Palung

Alur Rencana – 12 MLws , jarak ± 36 KM / 18 Mil

Alur Eksisting BREBES

13 | Energizing Trade. Energizing Indonesia Project Detail

PengembanganPort of Cirebon PelabuhanDevelopmentCirebon :

The development of Deep Sea Port that is integrated with Industrial estate to accommodate the cargo throughput growth, industrial estate development, and potential hinterland of Cirebon Port.

InformasiProject InformationProyek : IRR : 11,2 % Capital Expenditure: Rp 8,9 Triliun; Phase One: Rp 3,8 Triliun

14 | Energizing Trade. Energizing Indonesia Master Plan of Port of Cirebon

15 | Energizing Trade. Energizing Indonesia Port Development Plan Phase I: 50 Ha

16 | Energizing Trade. Energizing Indonesia Port Development Plan

Phase I (2018 – 2021) Reclamation Area : 50 Ha Berth Area : 19.200 M2

Phase II (2022 – 2032) Reclamation Area : 153 Ha Berth Area : 31.200 M2

17 | Energizing Trade. Energizing Indonesia Thank you