PROJECT : Masonry Stone Mine (Quarry project) PRE - FEASIBILTY REPORT

APPLICANT : M/s CHENDAYAD GRANITES PVT. LTD. 1

QUARRY PROJECT OF

M/s CHENDAYAD GRANITES PVT. LTD.

PROJECT FEASIBILITY REPORT ( PFR )

QUARRY SITE AT TRIPANGOTTOOR VILLAGE, TALUK, DISTRICT,

ENVIRONMENTAL ENGINEERS & CONSULTANTS PVT. LTD. Jt. Managing Director

MAY , 2017 Mr. C. G. GEORGE

PROJECT : Masonry Stone Mine (Quarry project) PRE - FEASIBILTY REPORT

APPLICANT : M/s CHENDAYAD GRANITES PVT. LTD. 2

INDEX S. No. Contents Page No. 1.0 EXECUTIVE SUMMARY 4 2.0 INTRODUCTION OF THE PROJECT / BACKGROUND INFORMATION 6 2.(i) Identification of project and project proponent 6 2.(ii) Brief description of the Nature of the project 6 2.(iii) Need for the project and its importance to the Country and or Region 7 2.(iv) Demand – Supply Gap 7 2.(v) Imports Vs. Indigenous Production 7 2.(vi) Export Possibility 7 2.(vii) Domestic / Export Markets 8 2.(viii) Employment generation (Direct & Indirect) due to the project 8 3.0 PROJECT DESCRIPTION 8 3.(i) Type of project including interlinked and interdependent projects 8 3.(ii) Location (map showing General Location, Specific Location & Project boundary & 8 Project site layout) with coordinates 3.(iii) Details of Alternate sites considered and the basis of selecting the proposed site, 9 particularly the environmental considerations 3.(iv) Size or magnitude of operation 9 3.(v) Project description with process details (a schematic diagram / flow chart showing 9 the project layout, components of the project etc should be given) 3.(vi) Raw material required along with estimated quantity, likely source, marketing area 12 of final products, mode of transport of raw materials and financial provisions 3.(vii) Resource optimization / recycling and reuse envisaged in the project 14 3.(viii) Availability of water its source, energy / power requirement & source 14 3.(ix) Quantity of wastes to be generated (liquid and solid) and scheme for their 15 management / disposal 4.0 SITE ANALYSIS 15 4.(i) Connectivity 15 4.(ii) Land form, land use and land ownership 16 4.(iii) Topography (along with map) 16 4.(iv) Existing land use pattern (agriculture, non-agriculture, forest, water bodies 16 (including area under CRZ)), shortest distances from the periphery of project. 4.(v) Existing Infrastructure 17 4.(vi) Soil Classification 17 4.(vii) Climatic Data 17 4.(viii) Social Infrastructure Available 18 5.0 PLANNING BRIEF 18 5.(i) Planning Concept (Type of industries, facilities, transportation etc.) Town & 18 Country Planning / Development Authority Classification 5.(ii) Population Projection 19 5.(iii) Land Use Planning (Break-up along with green belt etc.) 19 5.(iv) Assessment of Infrastructure Demand (Physical & Social) 19 5.(v) Amenities / Facilities 19

ENVIRONMENTAL ENGINEERS & CONSULTANTS PVT. LTD. Jt. Managing Director

MAY , 2017 Mr. C. G. GEORGE

PROJECT : Masonry Stone Mine (Quarry project) PRE - FEASIBILTY REPORT

APPLICANT : M/s CHENDAYAD GRANITES PVT. LTD. 3

6.0 PROPOSED INFRASTRUCTURE 20 6.(i) Industrial Area (Processing Area) 20 6.(ii) Residential Area (Non-processing area) 20 6.(iii) Green belt 20 6.(iv) Social Infrastructure 20 6.(v) Connectivity (Traffic & Transportation Road / Rail etc.) 20 6.(vi) Drinking Water Management (Source & Supply of water) 20 6.(vii) Sewerage system 20 6.(viii) Industrial Waste Management 20 6.(ix) Solid Waste Management 20 6.(x) Power Requirement & Supply / Source 21 7.0 Rehabilitation and Resettlement (R & R Plan) 21 7.(i) Policy to be adopted (Central / State) in respect of the project affected persons 21 including home oustees, land oustees and landless 8.0 PROJECT SCHEDULE AND COST ESTIMATES 21 8.(i) Likely date of start of production and likely date of completion (time schedule for 21 the project will be given) 8.(ii) Estimated project cost along with analysis of economic viability of project 21 9.0 ANALYSIS OF PROPOSAL 22 9.(i) Financial and Social Benefits with special emphasis on the benefits to the local 22 people including tribal population

LIST OF ANNEXURES Annexure No. Particulars 1. Copy of Letter of Intent ( LOI ) / Mine Lease 2. Photographs of the Site 3. Route Map showing location of the project site 4. Google map showing location of the project site 5. Key map of the project site 6. Topographical Contour Map 7. Production & Development Plan 8. Surface cum Geological Plan 9. Cluster Certificate 10. NABET Accreditation Certificate

LIST OF TABLES Table No. Particulars 1. List of employees 2. Size or magnitude of operation 3. List of equipments used 4. Year wise production details 5. Land use of lease area 6. Social infrastructure around the project site 7. Expected time schedule for the project 8. Estimated project cost and economic viability

ENVIRONMENTAL ENGINEERS & CONSULTANTS PVT. LTD. Jt. Managing Director

MAY , 2017 Mr. C. G. GEORGE

PROJECT : Masonry Stone Mine (Quarry project) PRE - FEASIBILTY REPORT

APPLICANT : M/s CHENDAYAD GRANITES PVT. LTD. 4

1.0 EXECUTIVE SUMMARY The building Stone Quarry (Minor Mineral) project of M/s Chendayad Granites Pvt. Ltd. is situated at Re-Survey No. 275/1A, Tripangottoor Village, Thalassery Taluk, , Kerala in an area of 1.5176 hectares. The project proponent possess Letter of Intent (LOI) for the quarry project issued by Mining & Geology Department, Govt. of Kerala and copy of the same is attached as Annexure No. 1 . Mining projects of minor minerals with area less than 50 ha. of mining lease are categorized as category 'B'. As per O.M. dated 24/12/2013 by Ministry of Environment & Forests, Govt. of , all projects with mining area less than 25 hectares is classified as Category B2. The Eco-friendly Mining Plan prepared by an Indian Bureau of Mine (IBM) approved Recognized Qualified Person (RQP) has been approved by Mining & Geology Department, Govt. of Kerala . This Mining plan is based on the requirements under the Kerala Minor Mineral Concession Rules, 2015. The land for the quarry project is private owned land and the land is possessed in name of M/s Chendayad Granites Pvt. Ltd. The targeted production of mine is 26,000 MTA. The estimated project cost is about Rs. 1.20 Crores. The expected life of mine estimated will be about 6 years. The mining operation will be carried out by opencast semi- mechanized method as per the approved Mining Plan.

1.1 SALIENT FEATURES & ENVIRONMENTAL SETTING OF THE PROJECT Particulars Details Geographical Location Latitude (N) 11 °47 '19 .26 "N to 11 °47 '24 .07 "N Longitude (E) 75 °39 '42.71 "E to 75 °39 '47 .77 "E

Total Mine Lease area 1.5176 hectare Total area owned by the proponent 2.0238 hectare Current status of the quarry Existing Abandoned Quarry Project Local name of the project area Poyiloor Project Site Toposheet No. 58 A/1 Production 26,000 MTA Geological Reserves 9,16,280 MT Mineable Reserves 1,53,703 MT Life of Mine 6 years Estimated project cost Rs. 1.20 Crores Man Power 9 Persons Highest and lowest elevation 200m (Highest) and 125m MSL (Lowest) Land use Private owned land with rocky area Nearest habitation About 241m towards West

ENVIRONMENTAL ENGINEERS & CONSULTANTS PVT. LTD. Jt. Managing Director

MAY , 2017 Mr. C. G. GEORGE

PROJECT : Masonry Stone Mine (Quarry project) PRE - FEASIBILTY REPORT

APPLICANT : M/s CHENDAYAD GRANITES PVT. LTD. 5

Nearest Town Kolavalloor, 6 km, SW Stone Crusher / M sand Available near the complex Width of access road to the site 7m wide road Nearest Airport Kannur Airport, 30 km, NW Nearest Highway / Major Roads NH-17, 22 km, SW SH-38, 12 km, West Cheruvancherry- Rd., 5 km, West Nearest Railway Station Thalassery station, 22 km, SW Power supply The total power requirement will be 75 kW for compressors which will be operated by Diesel Engine. Water and its Source The total water requirement is about 5 KLD in which 1 KLD is for domestic purpose which would be sourced from open well, 2 KLD for dust suppression in mine and 2 KLD for plantation will be sourced from storm water pond Nearest Hospital / dispensary PHC, Kunnothparamba, 8 km, SW Education facility Narikode UP School, 2 km, NE Police Station Kolavallor, 6 km, SW Fire Station Koothuparam, 15 km, NW Ambulance Kunnothparamba, 8 km, SW Church / temple / mosque Church – Aroonda, 4 km, S Temple – Poyiloor, 1 km, SW Mosque – Poyiloor, 3 km, SW Electrical installation like transformer HT / LT Line – Available at Thrippangottur, 1 km, SW /HT or LT line Mobile Towers Thrippangottur, 1 km, SW

Ecological sensitive zone (National None within the study area Park, Sanctuary, Habitat for Migratory Birds, Tiger Reserve) Interstate Boundary None within the study area Critically Polluted Area as identified None within the study area by CPCB Defense installations None within the study area Archeological Features None within the study area Nearest Forests Kannur Forest 2 km, West Nearest streams/ rivers/ water bodies Annapallam Thodu, 5 km, West (from mine boundary) Mundathode River, 7 km, South Mahe River, 10 km, SE HLWG Report status Not falling in ESA

ENVIRONMENTAL ENGINEERS & CONSULTANTS PVT. LTD. Jt. Managing Director

MAY , 2017 Mr. C. G. GEORGE

PROJECT : Masonry Stone Mine (Quarry project) PRE - FEASIBILTY REPORT

APPLICANT : M/s CHENDAYAD GRANITES PVT. LTD. 6

1.2 PRODUCTION & RESERVE The estimated annual mining production will be 26,000 MTA and the mineable reserve for the project is 1,53,703 MT. It is expected to employ about 9 Persons in the mining operation. The mined material will be transported to crusher located near the complex.

1.3 TOP SOIL & OVER BURDEN A total quantity of 2,918 cu. m. of topsoil is proposed to be removed during the mining operations. The topsoil excavated from the quarry will be dumped / stacked separately at pre-determined place and subsequently will be utilized in spreading over reclaimed areas for plantation as part of eco-restoration. About 1,459 cu. m. of overburden (OB) will be generated throughout the mine life. This waste will be utilized within the pit for lying of haul roads. At the end use, OB can be reutilized as soil base for plantation.

2.0 INTRODUCTION OF THE PROJECT / BACKGROUND INFORMATION 2.(i) IDENTIFICATION OF PROJECT AND PROJECT PROPONENT The project is for obtaining Environment clearance for building stone mining project (Minor Mineral Quarry). The quarry project is proposed by Mr. C. G. George as Jt. Managing Director of M/s Chendayad Granites Pvt. Ltd. The lease area is private own land at Re-Survey No. 275/1A, Tripangottoor Village, Thalassery Taluk, Kannur District, Kerala in area 1.5176 hectares. The project proponent possess Letter of Intent (LOI) for the quarry issued by Mining & Geology Department, Govt. of Kerala and copy of the same is attached as Annexure No. 1 . Name and : M/S CHENDAYA D GRANITES PVT. LTD. address of the (Mr. C.G. George, Joint Managing Director), CP3/C40, KSIDC Industrial Centre, Valiyavalicham, Applicant Koothuparamba, Kannur-670643. Mobile No. 09544400106 / 09447485245 E-mail :- [email protected]

2.(ii) BRIEF DESCRIPTION OF NATURE OF THE PROJECT M/s Chendayad Granites Pvt. Ltd. proposes a building stone mine for dealing in mining and trading of mineral. The main objective of the project is to carry the business of prospecting, exploring, operating and working on quarries. The main market for mineral is in Kannur District and other nearby districts in Kerala which are utilized it in construction works of buildings and roads.

ENVIRONMENTAL ENGINEERS & CONSULTANTS PVT. LTD. Jt. Managing Director

MAY , 2017 Mr. C. G. GEORGE

PROJECT : Masonry Stone Mine (Quarry project) PRE - FEASIBILTY REPORT

APPLICANT : M/s CHENDAYAD GRANITES PVT. LTD. 7

2.(iii) NEED FOR THE PROJECT AND ITS IMPORTANCE TO THE COUNTRY AND OR REGION The major need of building stone is due to its high compressive strength and durability (among the hardest, dimensional & structural stones), it can effectively withstand the vagaries of nature. The mineral-rich colors and the hardness & density, makes it useful for many applications. The proposed mining project will fulfill its end uses in buildings and construction of roads, paving and many other exterior projects. It is also known as the maintenance-free stone. The main market for mineral is in Kannur & other nearby districts which are utilized in construction works of buildings and roads. The mining and associated activities in the mineral bearing areas bring about gains in gross domestic product, i.e. there is though a minor contribution by the proposed project but will add to gains in G.D.P. (Gross Domestic Product). A total of 9 Persons will be employed in the mine. It will create employment (though marginally) for local population. Applicant will pay royalty to Govt. of Kerala for the mineral produced from the mine, direct and indirect taxes will be paid thereby contributing to the regional revenue. The public revenue will further be put for infrastructural development and other sectors like health, education and social welfare.

2.(iv) DEMAND – SUPPLY GAP Masonry / Building Stone are an important component for the construction / developmental work for all infrastructure development and building construction and road construction activities. Demand of building stone shall be fulfilled by various end users. During last few years, due to sudden increase in real estate activities and in other infrastructural development activities, the demand of the building stone has further enhanced the demand of building stone in the area. Therefore, there is a large requirement of building stone in the project vicinity to meet the demand supply chain.

2.(v) IMPORTS VS. INDIGENOUS PRODUCTION Building stone product is an indigenous production. Therefore, this product is neither exported nor imported.

2.(vi) EXPORT POSSIBILITY The building stone is an indigenous product and hence there are no possibilities of export.

ENVIRONMENTAL ENGINEERS & CONSULTANTS PVT. LTD. Jt. Managing Director

MAY , 2017 Mr. C. G. GEORGE

PROJECT : Masonry Stone Mine (Quarry project) PRE - FEASIBILTY REPORT

APPLICANT : M/s CHENDAYAD GRANITES PVT. LTD. 8

2.(vii) DOMESTIC / EXPORT MARKETS The rock produced from the quarry will be sent to the Crusher unit available near the complex. The aggregate produced will be sold to the contractors and to the consumers which are finally consumed locally for road (PWD & Panchayat roads, State Highway & National Highway) & building construction works. Fine Material will be sold to the hollow block / solid block manufactures.

2.(viii) EMPLOYMENT GENERATION (DIRECT AND INDIRECT) DUE TO THE PROJECT The total numbers of employees including skilled, semi skilled and un-skilled workers for the quarry project is expected to be about 9 Persons in which includes workers for mine. The details of the employees / workers including their position in the organization are also given below:- Table 1: List of Employees and their Designations Sr. No. NAME OF THE POST NOS. 1 Mines Manager / Asst. Mines Manager 1 2 Mines foreman 1 3 Other workers 7 TOTAL 9

3.0 PROJECT DESCRIPTION 3.(i) TYPE OF PROJECT INCLUDING INTERLINKED AND INTERDEPENDENT PROJECTS. This is a semi mechanized open cast stone mining project. Mineral will be used in the construction works. Building construction and other infrastructural facilities are the areas, where the material will be consumed. The quarry will be linked with a crusher unit available near the complex. The fine mineral is sold to the vendors who manufacture hollow block / solid block and hence they are interdependent projects attached to the mining project.

3.(ii) LOCATION (MAP SHOWING GENERAL LOCATION, SPECIFIC LOCATION, PROJECT BOUNDARY AND PROJECT SITE LAYOUT) WITH COORDINATES The proposed quarry site is in private owned land at Re-Survey No. 275/1A, Tripangottoor Village, Thalassery Taluk, Kannur District, Kerala for area 1.5176 hectares. The geographical location of the mine with respect to the boundary pillars of the lease area (extreme most points) is given below:- Latitude (N) 11 °47 '19 .26 "N to 11 °47 '24 .07 "N Longitude (E) 75 °39 '42.71 "E to 75 °39 '47 .77 "E

ENVIRONMENTAL ENGINEERS & CONSULTANTS PVT. LTD. Jt. Managing Director

MAY , 2017 Mr. C. G. GEORGE

PROJECT : Masonry Stone Mine (Quarry project) PRE - FEASIBILTY REPORT

APPLICANT : M/s CHENDAYAD GRANITES PVT. LTD. 9

The photographs of the site will be taken from different locations and directions are provided at Annexure No. 2. The route map showing location of the lease area is provided at Annexure No. 3. The google map superimposed with project boundary showing location of the lease area is provided at Annexure No. 4. The Key map of the project site showing the location of quarry site is attached at Annexure No. 5. The project site with boundary pillars and GPS Coordinates of the boundary pillars are provided in Contour drawing attached at Annexure No. 6. The cluster certificate showing the working status of other quarries within 500m radius is attached as Annexure No. 9.

3.(iii) DETAILS OF ALTERNATE SITES CONSIDERED AND THE BASIS OF SELECTING THE PROPOSED SITE, PARTICULARLY THE ENVIRONMENTAL CONSIDERATIONS. Quarrying activities are carried out based on local geology and availability of granite building stone. The proposed site is a building stone quarry and mineral specific hence no alternate site was examined. Moreover, the land is a private owned land and hence no alternate site considered.

3.(iv) SIZE OR MAGNITUDE OF OPERATION The size and magnitude of the lease area is as given below:- Table 2 : Size or Magnitude of operation Sr. No. Particulars Details 1. Lease Area 1.5176 hectares 2. Mineable Reserve 1,53,703 MT 3. Annual Production 26,000 MTA 4. Mine Waste Top Soil (2,918 cu. m. ) ; OB (1,459 cu. m.) 5. Life of Mine About 6 years 6. Total Man Power (Nos.) About 9 Persons

3.(v) PROJECT DESCRIPTION WITH PROCESS DETAILS (A SCHEMATIC DIAGRAM/ FLOW CHART SHOWING THE PROJECT LAYOUT, COMPONENTS OF THE PROJECT ETC.).

The proposed mining operations will be carried out by open cast semi-mechanized method. The process flow diagram given below depicts the mining process:-

ENVIRONMENTAL ENGINEERS & CONSULTANTS PVT. LTD. Jt. Managing Director

MAY , 2017 Mr. C. G. GEORGE

PROJECT : Masonry Stone Mine (Quarry project) PRE - FEASIBILTY REPORT

APPLICANT : M/s CHENDAYAD GRANITES PVT. LTD. 10

Cutting & Clearing of Shrubs / Trees

Removal & Stacking of Top soil & Overburden

Excavation by Drilling & Blasting

Rock Breaking & Transportation to Crusher

Crushing in Crusher

Segregation & Stacking

Dispatch to the end user

DESCRIPTION OF MINING OPERATIONS ( MANUFACTURING PROCESS) PROPOSED METHOD OF MINING It is proposed to undertake Open Cast Semi-Mechanized Mining which includes blasting, loading, transportation of rubble and dispatch to the crusher. The surface cum geological plan showing the mining steps is attached.

OPEN CAST MINING In the open cast mining, the bench height and width will be maintained at 5 to 6 m respectively. Excavated material is transported to the crusher unit located near the complex for further processing.

SALIENT FEATURES OF MINING METHOD The salient features of proposed mining method are given below. • The height and width of the bench will be maintained at 5 m and 6 m respectively. • The mining will be done from top to bottom by slicing of 2.5 m thick. • The exploitation of mineral is being done from 200 m to 140m MSL in conceptual phase. • Considering the stability of rocks the final slope or say ultimate pit slope is proposed 45° from vertical. • Haul road will be developed up to point of loading.

ENVIRONMENTAL ENGINEERS & CONSULTANTS PVT. LTD. Jt. Managing Director

MAY , 2017 Mr. C. G. GEORGE

PROJECT : Masonry Stone Mine (Quarry project) PRE - FEASIBILTY REPORT

APPLICANT : M/s CHENDAYAD GRANITES PVT. LTD. 11

• Transportation of the mineral from pit-mouth to crusher and then to the destination / market will be by tippers / trucks (15T capacity).

EXTENT OF MECHANIZATION The details of equipments proposed to be used in mining operation are listed below:- Table 3 : List of equipments used

S. No. Machine Type Required No. of M/c

1. Back Hoe 2

2. Rock Breaker 1

3. Compressor (Chicago) 2

4. Tippers/Trucks 6 5. Jack hammer 2 6. DG set (125 KVA) 1

DRILLING The excavation of mineral is proposed by excavators. The mineral is fractured and easily exploitable by rock breakers and excavators. The hard strata are proposed to excavate after drilling and blasting.

BLASTING The controlled blasting is proposed by adopting all the safety measures as per Minor Mineral Regulation Act, 1961 (MMR) and with the permission of Director General of Mines & Safety (DGMS). In this area for fragmentation of granite the blasting will be conducted. Multiple blast holes of 1.0 to 2.5 m depth will be drilled with the help of 32 mm drill rod, Jack Hammer and Air Compressor of 100 cfm capacity. It is estimated about 250g of explosives per hole is required. About 6-7 holes per blast are proposed. Therefore, the requirement of explosives will be about 1.75 kg/ blast/day.

EXPLOSIVE USED Only class 2 and class 6 explosive is proposed for use as given below:- Description Class Qty. Nitrate mixture 2, 0 100 kg Safety fuse 6, 1 2,000 mtrs. Electric/ Ordinary Detonators 6, 3 1,000 nos.

STORAGE OF EXPLOSIVE The magazine (explosive storage area) exists within the complex.

ENVIRONMENTAL ENGINEERS & CONSULTANTS PVT. LTD. Jt. Managing Director

MAY , 2017 Mr. C. G. GEORGE

PROJECT : Masonry Stone Mine (Quarry project) PRE - FEASIBILTY REPORT

APPLICANT : M/s CHENDAYAD GRANITES PVT. LTD. 12

3.(vi) RAW MATERIAL REQUIRED ALONG WITH ESTIMATED QUANTITY, LIKELY SOURCE, MARKETING AREA OF FINAL PRODUCT/S, MODE OF TRANSPORT OF RAW MATERIAL AND FINISHED PRODUCT No raw material will be required for mining of Masonry / building stone. The final product will be sent to consumer based on their demand. The mode of transportation of raw material and finished product will be by road only. Tippers/ trucks will be used for transportation to the end users.

MINERAL RESERVES The mineable reserves are arrived after deducting the reserves locked in mines safety (blocked reserve) slope along with boundary in compliance with mineral concession rules. The quantity of such kind of reserves is arrived as follows. SECTION A-A' BLOCKED RESERVES MINEABLE RESERVES BENCH M2 M DENSITY TON BENCH M2 M DENSITY TON 190 40 61 2.5 6100 190 23 52 2.5 2990 185 66 61 2.5 10065 185 59 47 2.5 6932.5 180 92 61 2.5 14030 180 96 42 2.5 10080 175 119 61 2.5 18147.5 175 120 37 2.5 11100 170 146 61 2.5 22265 170 142 32 2.5 11360 165 184 61 2.5 28060 165 132 27 2.5 8910 160 473 61 2.5 72132.5 160 122 22 2.5 6710 Sub-total 170800 Sub-total 58082.5 SECTION B-B' BLOCKED RESERVES MINEABLE RESERVES BENCH M2 M DENSITY TON BENCH M2 M DENSITY TON 190 40 29 2.5 2900 190 32 29 2.5 2320 185 67 29 2.5 4857.5 185 64 29 2.5 4640 180 93 29 2.5 6742.5 180 85 29 2.5 6162.5 175 119 29 2.5 8627.5 175 94 29 2.5 6815 170 148 29 2.5 10730 170 102 29 2.5 7395 165 185 29 2.5 13412.5 165 92 29 2.5 6670 160 222 29 2.5 16095 160 79 29 2.5 5727.5 155 259 29 2.5 18777.5 155 86 29 2.5 6235 150 297 29 2.5 21532.5 150 107 29 2.5 7757.5 145 336 29 2.5 24360 145 116 29 2.5 8410 140 414 29 2.5 30015 140 94 18 2.5 4230 Sub-total 158050 Sub-total 66362.5

ENVIRONMENTAL ENGINEERS & CONSULTANTS PVT. LTD. Jt. Managing Director

MAY , 2017 Mr. C. G. GEORGE

PROJECT : Masonry Stone Mine (Quarry project) PRE - FEASIBILTY REPORT

APPLICANT : M/s CHENDAYAD GRANITES PVT. LTD. 13

SECTION C-C' BLOCKED RESERVES MINEABLE RESERVES BENCH M2 M DENSITY TON BENCH M2 M DENSITY TON 185 56 50 2.5 7000 185 28 24 2.5 1680 180 84 50 2.5 10500 180 47 29 2.5 3407.5 175 118 50 2.5 14750 175 41 34 2.5 3485 170 151 50 2.5 18875 170 26 39 2.5 2535 165 184 50 2.5 23000 165 7 44 2.5 770 160 210 50 2.5 26250 160 13 44 2.5 1430 155 252 50 2.5 31500 155 39 44 2.5 4290 150 283 50 2.5 35375 150 49 44 2.5 5390 145 314 50 2.5 39250 145 37 44 2.5 4070 140 344 50 2.5 43000 140 20 44 2.5 2200 Sub-total 249500 Sub-total 29257.5 GRAND TOTAL 578350 GRAND TOTAL 153702.5

Summarized Reserves (in MT) Geological reserve (A) 916279.5 Mineral reserve blocked in 7.5 m Buffer zone (B) 130700 Mineral reserve blocked in Benches (C) 447650 Mined out quantity (D) 124772 Extra mineral blocked (E) 59455 Mineable Mineral reserve = A- B + C + D + E 153702.5

YEAR WISE PRODUCTION DETAILS The applicant is proposed to produce building stone working for period of about 6 years with a production of 26,000 MTA. The details of year wise production of the project is given in Table below.:- Table 4 : Year wise production of building stone Year Bench Production (MT) I 190-180 26000 II 180-175 26000 III 175-170 26000 IV 170-160 26000 V 160-150 26000 VI 150-140 23702.5 TOTAL 153702.5

ENVIRONMENTAL ENGINEERS & CONSULTANTS PVT. LTD. Jt. Managing Director

MAY , 2017 Mr. C. G. GEORGE

PROJECT : Masonry Stone Mine (Quarry project) PRE - FEASIBILTY REPORT

APPLICANT : M/s CHENDAYAD GRANITES PVT. LTD. 14

MINERAL TRANSPORTATION Loading of mineral from the quarry will be done by excavator and will be sent to the crushing unit near the complex. Trucks / Tippers of 15 MT will be used for transportation of mineral from mine site to the crusher. It is expected that 6 trips will be required on daily basis. For this, movement of truck per hour will be 1 only. Thus, the impact due to movement of trucks from mine will be marginal and well within the carrying capacity of the roads.

3.(vii) RESOURCE OPTIMIZATION / RECYCLING AND REUSE ENVISAGED IN THE PROJECT Mineral will be utilized and sent for use to different end users for road and building construction works. A total quantity of 2,918 cu. m. of topsoil is proposed to be removed during the mining operations. The topsoil excavated from the quarry will be dumped / stacked separately at pre-determined place and subsequently will be utilized in spreading over reclaimed areas for plantation as part of eco-restoration. About 1,459 cu. m. of overburden (OB) will be generated throughout the mine life. This waste will be utilized within the pit for lying of haul roads. At the end use, OB can be reutilized as soil base for plantation.

3.(viii) AVAILABILITY OF WATER ITS SOURCE, ENERGY / POWER REQUIREMENT AND SOURCE WATER The total water requirement for the proposed mining activity is 5 KLD. The detailed breakup of the same is given below:- S. No. Parti culars Quantity (KLD) Source 1. Domestic purpose (mine and ancillary) 1 Open well 2. Dust Suppression req. 2 Storm water pond 3. Green belt / Plantation 2 Total 5

The water required will be sourced from the storm water reservoir. However, the drinking water will be sourced from the open well and which will be treated / disinfected before consumption. It is proposed to collect the storm water into the Holding/ Siltation Tank by constructing appropriate channels all around the foot of hill (garland drains). The channels will be constructed with intermediate check dams/silt traps to prevent soil erosion. The sizing of the channels will be 1m x 1m. The daily water balance diagram of the unit is given below:-

ENVIRONMENTAL ENGINEERS & CONSULTANTS PVT. LTD. Jt. Managing Director

MAY , 2017 Mr. C. G. GEORGE

PROJECT : Masonry Stone Mine (Quarry project) PRE - FEASIBILTY REPORT

APPLICANT : M/s CHENDAYAD GRANITES PVT. LTD. 15

POWER The total power requirement will be 75 kW for compressors which will be operated by Diesel Engine. The source of electricity for domestic consumption within the quarry site is from the supply of Kerala State Electricity Board (KSEB).

3.(ix) QUANTITY OF WASTES TO BE GENERATED (LIQUID AND SOLID) AND SCHEME FOR THEIR MANAGEMENT / DISPOSAL. SOLID WASTE: It is estimated that around 2,918 cu. m. of top soil and 1,459 cu. m. of over burden (OB) will be generated from the proposed mining operation and which will be properly stacked. LIQUID WASTE: Domestic Sewage : The sewage to a tune of 0.80 KLD generated from the mine office.

3.(x) SCHEMATIC REPRESENTATION OF THE FEASIBILITY DRAWING WHICH GIVE INFORMATION OF EIA PURPOSE. Not Applicable

4.0 SITE ANALYSIS 4.(i) CONNECTIVITY S. No. Part iculars Distance & Direction 1. Nearest town Kolavalloor, 6 km, SW 2. Connecting Road 7m wide road 3. Nearest Airport Kannur Airport, 30 km, NW 4. Nearest Highway / Major NH-17, 22 km, SW Roads SH-38, 12 km, West Cheruvancherry-Panoor Rd., 5 km, West 5. Nearest Railway Station Thalassery station, 22 km, SW

ENVIRONMENTAL ENGINEERS & CONSULTANTS PVT. LTD. Jt. Managing Director

MAY , 2017 Mr. C. G. GEORGE

PROJECT : Masonry Stone Mine (Quarry project) PRE - FEASIBILTY REPORT

APPLICANT : M/s CHENDAYAD GRANITES PVT. LTD. 16

4.(ii) LAND FORM, LAND USE AND LAND OWNERSHIP LANDFORM The proposed building stone mine is covering an area of 1.5176 ha. The lease area is private own land. The lease area is devoid of any transmission lines, streams / nallahs, forests, habitation, etc. LAND USE The land use pattern of the existing and proposed mining project is given below: Table 5 : Land Use Details of project area Sr. Land Use Category Pre -Operational Operational for next Post Operational for No. (Ha.) five years (Ha.) life of mine (Ha.) 1 Top Soil Dump Nil 0.0444 Nil 2 Over burden Nil (outside mining area, within own land) 3 Excavation (Voids 0.4360 1.0726 1.1655 Only) (Reclaimed by plantation) 4 Road Nil 0.05 Nil 5 Built Up Area Nil Nil Nil 6 Drainage Nil 0.0612 0.0612 7 Green belt Nil 0.2909 0.2909 8 Undisturbed Area 1.0816 0.0429 Nil Total 1.5176 1.5176 1.5176

LAND OWNERSHIP The land as per revenue records is a private own land and the site is rocky land with rubber tree plantation and other native species.

4.(iii) TOPOGRAPHY (ALONG WITH MAP) Part of the proposed land is rocky area and there is no vegetation in that area. The remaining land in the proposed land is mostly covered with native trees, shrubs, herbs, grass, climbers, bushes etc. The topography of the lease area is hilly terrain. The highest elevation of the lease area is 200 m MSL and lowest is 125 m MSL. As the proposed area is hill rock, the drainage of lease area is towards South-West. No habitants are located in the lease area. The topographical contour map of the project site is attached at Annexure No. 6.

4.(iv) EXISTING LAND USE PATTERN (AGRICULTURE, NON-AGRICULTURE, FOREST, WATER BODIES (INCLUDING AREA UNDER CRZ)), SHORTEST

ENVIRONMENTAL ENGINEERS & CONSULTANTS PVT. LTD. Jt. Managing Director

MAY , 2017 Mr. C. G. GEORGE

PROJECT : Masonry Stone Mine (Quarry project) PRE - FEASIBILTY REPORT

APPLICANT : M/s CHENDAYAD GRANITES PVT. LTD. 17

DISTANCES FROM THE PERIPHERY OF THE PROJECT TO THE PERIPHERY OF THE FORESTS, NATIONAL PARK, WILD LIFE SANCTUARY, ECO SENSITIVE AREAS, WATER BODIES (DISTANCE FROM THE HFL OF THE RIVER), CRZ IN CASE OF NOTIFIED INDUSTRIAL AREA.

Land Use Pattern: The lease area is situated at Re-Survey No. 275/1A, Tripangottoor Village, Thalassery Taluk, Kannur District, Kerala in area of 1.5176 hectares. The land use pattern of site is provided at Table No. 5 above.

DISTANCES FROM THE PERIPHERY OF THE PROJECT TO THE PERIPHERY OF THE FORESTS, NATIONAL PARK, WILD LIFE SANCTUARY, ECO SENSITIVE AREAS, WATER BODIES, NOTIFIED INDUSTRIAL AREAS, CRZ AREA ETC. Particulars Name & Distance to quarry site Ecological sensitive zone (National Park, Sanctuary, None within the study area Habitat for Migratory Birds, Tiger Reserve) Critically Polluted Area as identified by CPCB None within the study area Defense installations None within the study area Archeological Features None within the study area Nearest Forests Kannur Forest 2 km, West Nearest streams/ rivers/ water bodies Annapallam Thodu, 5 km, West Mundathode River, 7 km, South Mahe River, 10 km, SE Notified Industrial Area None within the study area CRZ Area Not in CRZ Area

4.(v) EXISTING INFRASTRUCTURE The existing infrastructure around the project site includes tarred roads, electricity supply from Kerala Electricity Board, water supply from Kerala Water Authority / Panchayat supply, storm water drains along the roads. 4.(vi) SOIL CLASSIFICATION Main rock type in the study area is charnockite granite. At places where they are exposed, the charnockite granite is medium to coarse grained with dark grey quartz.

4.(vii) CLIMATIC DATA Kannur district receives a total annual rainfall of around 3438 mm. District experiences heavy rainfall during the South West monsoon season followed by North East monsoon. South West monsoon during June to September contributes 70 % of the total rainfall of the year. The northeast monsoon contributes only about 30%. The year to year

ENVIRONMENTAL ENGINEERS & CONSULTANTS PVT. LTD. Jt. Managing Director

MAY , 2017 Mr. C. G. GEORGE

PROJECT : Masonry Stone Mine (Quarry project) PRE - FEASIBILTY REPORT

APPLICANT : M/s CHENDAYAD GRANITES PVT. LTD. 18

variability of annual rainfall is around 28.2%. In general, the rainfall increases from the coast to the eastern hilly regions. Kannur district falls under wet type of climate based on Thornthwaite’s climatic classification. The temperature is more during the months of April to May and is less during December and January. The average mean monthly maximum temperature ranges from 28.4 to 36.90C and minimum temperature ranges from 19.7 to 23.90C. Relative humidity is more during south west monsoon season (ie June to September). It is more during morning hours and is less during evening hours. Humidity ranges from 77 to 88 % in the district. (Source: District Survey Report, Department of Mining & Geology, Kerala )

4.(viii) SOCIAL INFRASTRUCTURE AVAILABLE Table 6 : Social Infrastructure Details S. No. Particulars Name, Distance & Direction from the quarry site 1. Land use Private own Land with rocky land 2. Nearest habitation About 241 m towards West 3. Nearest Town Kolavalloor, 6 km, SW 4. Width of access road to site 7m wide road 5. Nearest Airport Kannur Airport, 30 km, NW 6. Nearest Highway / Major NH-17, 22 km, SW Roads SH-38, 12 km, West Cheruvancherry-Panoor Rd., 5 km, West 7. Nearest Railway Station Thalassery station, 22 km, SW 8. Power supply The total power requirement will be 75 kW for compressors which will be operated by Diesel Engine. 9. Nearest Hospital / dispensary PHC, Kunnothparamba, 8 km, SW 10. Education facility Narikode UP School, 2 km, NE 11. Police Station Kolavallor, 6 km, SW 12. Fire Station Koothuparamb, 15 km, NW 13. Ambulance Kunnothparamba, 8 km, SW 14. Church / temple / mosque Church – Aroonda, 4 km, S Temple – Poyiloor, 1 km, SW Mosque – Poyiloor, 3 km, SW

5.0 PLANNING BRIEF 5.(i) PLANNING CONCEPT (TYPE OF INDUSTRIES, FACILITIES, TRANSPORTATION ETC.) TOWN AND COUNTRY PLANNING / DEVELOPMENT AUTHORITY CLASSIFICATION. The mining will be done by open cast semi-mechanized method of mining. The bench height and width will be maintained 5 to 6 mtr. Excavated material is transported to the

ENVIRONMENTAL ENGINEERS & CONSULTANTS PVT. LTD. Jt. Managing Director

MAY , 2017 Mr. C. G. GEORGE

PROJECT : Masonry Stone Mine (Quarry project) PRE - FEASIBILTY REPORT

APPLICANT : M/s CHENDAYAD GRANITES PVT. LTD. 19

crusher unit available near the complex for further processing. The proposed mine will have capacity to produce 26,000 MTA of building stone. It will be used for construction of buildings & roads. Mineral will be transported by trucks / tippers to the end users. The production and development plan of the project is attached as Annexure No. 7.

5.(ii) POPULATION PROJECTION About 9 Persons of employees proposed for the quarrying operation. Most of the person will be sourced from neighboring villages. Thus there will be no increase in population due to the project.

5.(iii) LAND USE PLANNING (BREAKUP ALONG WITH GREEN BELT ETC.) The land use plan including the breakup along with green belt development area is provided at land use Table above.

5.(iv) ASSESSMENT OF INFRASTRUCTURE DEMAND (PHYSICAL AND SOCIAL) The mine site has its own approach road and well connected to the nearest public road / highway, which will help in commutation of workers and transportation of minerals. As such there is no major infrastructure facilities planned in this project and does not call for importance. The main mining site and secondary access road will be kept in a sufficient condition to allow access. On the basis of the site visit, the infrastructure demand in the nearby villages will be assessed on the basis of need and priority. Job opportunities are limited and newer avenues of skill development for income generation are required.

5.(v) AMENITIES/ FACILITIES Following facilities are provided for the smooth working of the mine:-  Mine office / Site office  Magazine area for storage of explosive  Parking area for vehicles  Storm water collection pond  Canteen / Mess for workers  Accommodation for workers  First aid room  Store facility  Toilet facility  Drinking water facilities  Rest shelters: Rest shelter room is provided to take lunch and rest for the mine workers.

ENVIRONMENTAL ENGINEERS & CONSULTANTS PVT. LTD. Jt. Managing Director

MAY , 2017 Mr. C. G. GEORGE

PROJECT : Masonry Stone Mine (Quarry project) PRE - FEASIBILTY REPORT

APPLICANT : M/s CHENDAYAD GRANITES PVT. LTD. 20

6.0 PROPOSED INFRASTRUCTURE 6.(i) INDUSTRIAL AREA (PROCESSING AREA) The project site area is not located in an industrial area. The project is a mining project and is site specific.

6.(ii) RESIDENTIAL AREA (NON PROCESSING AREA) As the local person will be given priority in employment, no permanent residential area / housing is proposed only labour sheds are provided within the complex.

6.(iii) GREEN BELT The year wise programme of eco-restoration for the life of mine, about 1,450 trees will be planted in an area of 1.4564 ha.

6.(iv) SOCIAL INFRASTRUCTURE The Social Infrastructure facility available around the site is provided at Table No. 6.

6.(v) CONNECTIVITY (TRAFFIC AND TRANSPORTATION ROAD / RAIL / METRO / WATER WAYS ETC.) The site is very well connected by road network to the mine, district headquarter and to the nearest towns. The area is self sufficient to cater the needs of the project.

6.(vi) DRINKING WATER MANAGEMENT (SOURCE AND SUPPLY OF WATER) The water required for the project will be sourced from the storm water reservoir and from well. The drinking water to a tune of 1 KLD will be sourced from the open well which will be treated / disinfected before consumption.

6.(vii) SEWERAGE SYSTEM The sewage to a tune of 0.80 KL will be generated daily from the mine office will be diverted to the septic tank followed by soak pit.

6.(viii) INDUSTRIAL WASTE MANAGEMENT There will be no industrial waste generation due to proposed project.

6.(ix) SOLID WASTE MANAGEMENT

(i) Topsoil Management A total quantity of 2,918 cu. m. of topsoil is proposed to be removed during the mining operations. The topsoil excavated from the quarry will be dumped / stacked separately at pre-determined place and subsequently will be utilized in spreading over reclaimed

ENVIRONMENTAL ENGINEERS & CONSULTANTS PVT. LTD. Jt. Managing Director

MAY , 2017 Mr. C. G. GEORGE

PROJECT : Masonry Stone Mine (Quarry project) PRE - FEASIBILTY REPORT

APPLICANT : M/s CHENDAYAD GRANITES PVT. LTD. 21

areas for plantation as part of eco-restoration. Precautions will be taken to limit the height of the topsoil dump / stacked to 5 to 6 meters in order to preserve its fertility and shelf life. It will be suitably protected from soil erosion and infertility by planting fodder grass and leguminous plants during temporary storage.

(ii) Overburden Management About 1,459 cu. m of overburden (OB) will be generated throughout the mine life. This waste will be utilized within the pit for lying of haul roads. At the end use, OB can be reutilized as soil base for plantation..

6.(x) POWER REQUIREMENT AND SUPPLY / SOURCE The total power requirement will be 75 kW for compressors which will be operated by Diesel Engine. The domestic supply will be met from the supply of Kerala State Electricity Board (KSEB).

7.0 REHABILITATION AND RESETTLEMENT (R & R PLAN) 7.(i) POLICY TO BE ADOPTED (CENTRAL/ STATE) IN RESPECT OF THE PROJECT AFFECTED PERSONS INCLUDING HOME OUSTEES, LAND OUSTEES AND LANDLESS LABOUR (A BRIEF OUTLINE TO BE GIVEN) The proposed site is private own land and hence there is no rehabilitation and resettlement. It is a small quarry project and there is no habitation in the lease area, therefore rehabilitation & resettlement plan is not required / applicable for this project.

8.0 PROJECT SCHEDULE AND COST ESTIMATES 8.(i) LIKELY DATE OF START OF PRODUCTION AND LIKELY DATE OF COMPLETION (TIME SCHEDULE FOR THE PROJECT WILL BE GIVEN). Table 7 : Expected Time Schedule for the Project S. No. Particulars Time Schedule (in month)* Remark If any 1st 2nd 3rd 4th 5th 1. Environmental Clearance 2. Consent To Establish Project Establishment Period 3. Consent To Operate Production Start Period *Time line may vary; subjected to rules & regulation / & other unforeseen circumstances

8.(ii) ESTIMATED PROJECT COST ALONG WITH ANALYSIS IN TERMS OF ECONOMIC VIABILITY OF THE PROJECT The proposed project cost will be about Rs. 1.20 Crores .

ENVIRONMENTAL ENGINEERS & CONSULTANTS PVT. LTD. Jt. Managing Director

MAY , 2017 Mr. C. G. GEORGE

PROJECT : Masonry Stone Mine (Quarry project) PRE - FEASIBILTY REPORT

APPLICANT : M/s CHENDAYAD GRANITES PVT. LTD. 22

Table 8 : Estimated Project Cost and Economic Viability S. No. Particulars Details 1. Quarrying Cost Rs. 200 /- Per Ton 2. Transportation with Crushing cost Rs. 250/- Per Ton 3. Royalty & Other Expenses Rs. 100/- Per Ton 4. Total Cost of Production Rs. 550/- Per Ton 5. Selling Price Rs. 650/- Per Ton 6. Gross Profit Rs. 100/- Per Ton 7. Gross Profit / Annum ( 26,000 Tons x Rs. 100/- ) Rs. 26,00,000/- Per Annum

9.0 ANALYSIS OF PROPOSAL 9.(i) FINANCIAL AND SOCIAL BENEFITS WITH SPECIAL EMPHASIS ON THE BENEFITS TO THE LOCAL PEOPLE INCLUDING TRIBAL POPULATION, IF ANY, IN THE AREA. No tribal population is residing in the study area. There will be social benefits from the mining operations. The core benefit of the proposed quarry project is the availability of Masonry building stone for construction industries.

ENVIRONMENTAL ENGINEERS & CONSULTANTS PVT. LTD. Jt. Managing Director

MAY , 2017 Mr. C. G. GEORGE

Annexure No. 2

SITE PHOTOGRAPHS – SHOWING THE SITE OF M/s CHENDAYAD GRANITES PVT. LTD. SITE PHOTOGRAPHS – SHOWING THE SITE OF M/s CHENDAYAD GRANITES PVT. LTD. Annexure No. 3 ROUTE MAP – SHOWING THE SITE OF M/s CHENDAYAD GRANITES PVT. LTD. Annexure No. 4 GOOLGE MAP – SHOWING THE SITE OF M/s CHENDAYAD GRANITES PVT. LTD. KEY MAP – SHOWING THE SITE OF M/s CHENDAYAD GRANITES PVT. LTD. Annexure No. 5

5

Year Bench Production (MT) I 190 -180 26000 II 180 -175 26000 III 175 -170 26000 IV 170 -160 26000 V 160 -150 26000