FORM 1 M

APPLICATION FOR MINING OF MINOR MINERALS UNDER CATEGORY ‘B2’ FOR LESS THAN AND EQUAL TO FIVE HECTARE

II Basic Information The granite building stone quarry of M/s Devadaru Agro –Land Ventures Pvt. Ltd at Village Kidoor, (i) Name of the Mining Lease Taluka , District Kasargod, State

Sr. No. Latitude (N) Longitude BP-1 12°37'59.00"N 74°58'47.80"E BP-2 12°38'2.61"N 74°58'48.61"E BP-3 12°38'3.64"N 74°58'46.58"E Location / site (GPS Co- BP-4 12°38'1.78"N 74°58'44.83"E (ii) BP-5 12°38'0.01"N 74°58'43.93"E ordinates): BP-6 12°37'59.42"N 74°58'44.70"E BP-7 12°37'57.88"N 74°58'45.16"E BP-8 12°37'57.25"N 74°58'45.02"E BP-9 12°37'57.49"N 74°58'44.49"E BP-10 12°37'56.90"N 74°58'46.70"E

Size of the Mining Lease (iii) 1.7765 Ha (Hectare): Capacity of Mining Lease (iv) 1,00,000 TPA (TPA) (v) Period of Mining Lease 12 Years (vi) Expected cost of the Project 75 Lac Mathew Jose Managing Director, Devadaru Agro-Land Ventures Pvt. Ltd. Door No: PGP IX -301 , Industrial Development (vii) Contact information Plot, Anathapuram, Kannur P.O., Dist - 671321 Email : [email protected] Phone : 9740311448

Environmental Sensitivity Sr. No. content Areas Distance in Km /details

Distance of project site from nearest 1. Rail bridge 5.41Km west rail or road bridge Road bridge over river 3.17 Km west over the concerned River, Rivulet, Nallah Shiriya river is 400m in the west river, rivulet, Nallah etc Distance from infrastructural facilities

Railway station Railway Station 06.18Km SW

National Highway NH-66 Edapally Panvel highway - 5.82KM W

State highway SH -31 - 13.89 Km E

Air Port International Airport - 37.64 Km N

2 Electric transmission line, The quarry lease area is not facilitated with power line. Nearest pole or tower electric poles is 150 meters away.

In-take for drinking water 2.0KLD requirement will met by well and tube well pump house

Intake or Irrigation canal pumps NIL

Areas protected under international conventions, national or local 3 legislation for their Bheemanadi Reserve Forest - 44.91Km – SE (Aerial) ecological, landscape, cultural or other related value Areas which are important or sensitive of ecological reasons Anekallu River – 5.83 Km N – wetlands, water 4 Madhuvahini River – 6.79 Km S courses or other water bodies, Shiriya River – 400 m W coastal zone, biospheres, mountains, forests Areas used by protected, important or sensitive species of flora or fauna 5 Bheemanadi Reserve Forest - 44.91Km – SE (Aerial) for breeding, nesting, foraging, resting, over wintering, migration Inland, coastal, Anekallu River – 5.83 Km N marine or Madhuvahini River – 6.79 Km S 6 underground Shiriya River – 400 m W waters Arabian Sea coast – 6.52 Km W

7 State, national Karnataka Border – 7.89 Km NE boundaries Routes or facilities Sri Mahadeva Temple 0.50 Km used by the public for access to Masjid e Rehman 2.52 Km recreation or other Zakariya Masjid 3.64 Km tourist, pilgrim areas Muhiyaddeen Juma Masjid 4.10 Km

8 Chilangad Juma Masjid 3.05 Km Quliriya Masjid adka 4.53 Km

Subhaniya Masjid 4.66 Km

Bilal Masjid 5.22 Km

Kunil Masjid 5.18 Km Shiriya Temple 5.62 Km

Shiriya Masjid 5.53 Km

Poomani Kinnimani Daivastan 2.05 Km

Shree Cherumba Bhagvati temple 4.80 Km

Anantpura lake temple 5.37 Km

Muchilot Bhagvati temple 4.84 Km

Routes used NH-66 Edapally Panvel highway - 5.82KM W SH -31 - 13.89 Km E Kalathur – Arthila road – 1.13Km E Arikkady – Puthige road – 1.03Km S Defence 9 NIL Installations Places Kidoor 550m E Kalathur 1.32Km SE Ujarulvar 2.11 km W Thada compound 1.25km NW Heroor 2.50Km NW Kayyar 2.70Km N Densely populated Puthige 3.70Km SE 10 or built-up area Ichilampady 2.71Km S Arikady 3.99km SW Edanad 3.90km SE Mugu 4.48km SE Ichilangod 3.10km NW Koipady 4.24km SW Mulyadukkam 3.53km SW Angadimogar 3.74km NE

Sl. Places Dist. from No. Project Site Areas occupied by (Km) sensitive man- Tourist & Pilgrim areas made land uses 1 Sri Mahadeva Temple 0.50Km 11 (hospitals, schools, 2 Masjid e Rehman 2.52 Km place of worship, 3 Zakariya Masjid 3.64 km community 4 Muhiyaddeen Juma Masjid 4.10 km facilities) 5 Chilangad Juma Masjid 3.05 Km 6 Quliriya Masjid adka 4.53 Km 7 Subhaniya Masjid 4.66km 8 Bilal Masjid 5.22 Km 9 Kunil Masjid 5.18km 10 Shiriya Temple 5.62 Km 11 Shiriya Masjid 5.53Km 12 Poomani Kinnimani 2.05Km Daivastan 13 Shree Cherumba Bhagvati 4.80Km temple 14 Anantpura lake temple 5.37km 15 Muchilot Bhagvati temple 4.84km Schools & Colleges 1 Govt. LP School Kidoor 0.50Km 2 Pachambala Arabic school 2.72Km 3 Meepry govt. hr.sec school 2.35Km 4 Govt. basic primary school 1.04km 5 Chilangad LP school 3.06 Km 6 Chilangad Huda Madrassa 3.04Km 7 Lateefiyan English medium 5.46Km school 8 GB LP school 3.63km 9 Zaman hr. sec. school 2.31km 10 Govt. LP & UP school 2.76Km 11 ASB school 1.54 km Hospitals 1 Ayurvedic Dispensary 2.64 Km 2 Nisha Hospital 5.75 Km 3 Mogral Puthur PHC 8.63km

Areas containing important high quality or scarce resources (ground There are rivers (Shiriya River – 400 m W), wildlife reserve water resources, 12 forest (Bheemanadi Reserve Forest - 44.91Km – SE (Aerial). surface resources, Kasargod district is rich in mineral resources. forestry There are agricultural lands. agriculture, fisheries, tourism minerals) Areas already subjected to pollution or 13 None environmental damage.(those where existing legal environmental standards are exceeded) Areas susceptible to natural hazard which could cause 1. Project area falls in earthquake zone III. Thus there the project to will be least chances of earthquake. present 2. This is the case if open cast mining. There will not be any case of subsidence. environmental 3. There will be benches formed in it with safe bench problems and pit parameters. There will be least chances of 14 landslide. (earthquakes, 4. The nearest river is more than 200ms away. The subsidence, mine site is much above the HFL of the river. There will landslides, not be any chances of flooding. erosion, flooding As per the past records there are least chances of extreme or or extreme or adverse climatic conditions. adverse climatic conditions) Is proposed site located over or 15 near fissure / NIL fracture for ground water recharge Whether the proposal involves

Approval / clearance under: if yes, details of the same and their status to be given. 16 NIL (a) The Forest (Conservati on) Act, 1980?

(b) The Wildlife (Protection) Act 1972? The C.R.Z. Notification, t99l? Forest land L7 involved NIL @ectares) Whether there is any litigation pending against the products and/or land in which the project is propose to set up?

(a) Name of the NO l8 Coutr

@) Case.No.

(c) Orders/Directions of the court,

Ifany and its relevance with the proposed project-

Mr. MathewJose Managing Director Devadaru Agro-Land Yentures hrt. Ltd

(Signature of Project Proponent)