Social Safeguard Monitoring Report

Project No. 45148-005 Period Covering January to December 2017 June 2018

Sri Lanka: Greater Water and Wastewater Management Improvement Investment Program - Tranche 1 and Tranche 2

Prepared by the National Water Supply and Drainage Board for the Asian Development Bank.

This social monitoring report is a document of the borrower. The views expressed herein do not necessarily represent those of ADB's Board of Directors, Management, or staff, and may be preliminary in nature. Your attention is directed to the “terms of use” section on ADB’s website. In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area

Greater Colombo Water & Wastewater Management Improvement Investment Programme National Water Supply & Drainage Board

ANNUAL SOCIAL SAFEGUARD MONITORING REPORT- 2017

Project Management Unit Greater Colombo Water & Wastewater Management Improvement Investment Programme National Water Supply & Drainage Board No.65, St. Lawrence Road Colombo 06 Tel: 011-2589235, 011-2503170

Social Safeguard Annual Monitoring Report - 2017

NOTE The annual safeguard monitoring report for year 2017 is mainly based on the status of the sub projects, progress of pipe laying work, land acquisition and location changes in proposed constructions under the Project 01 and Project 02 in Greater Colombo Water and Wastewater Management Improvement Investment Program during the year 2017.

Contents List of Tables ...... iv List of Figurers ...... iv Abbreviations ...... v 01 Introduction ...... 1 01.1 Project implementing area ...... 1 02 Purpose of the Report ...... 1 03 Legal Frame Work for Resettlement Plan ...... 2 04 Scope of the Project ...... 4 04.1 System Rehabilitation- Colombo North Area (Package 01) ...... 4 04.1.1 Scope of Work ...... 4 04.1.2 Project Location Map ...... 5 04.1.3 Project Goal and Scope of Work ...... 6 04.1.4 Present Progress ...... 6 04.1.5 Grievance Redress Mechanism for Package I ...... 7 04.1.6 Occupational & Public safety at site ...... 8 04.1.7 Mitigation Measures ...... 9 04.2 System Rehabilitation- Colombo East Area (Package 02) ...... 12 04.2.1 Pipe laying and other work ...... 12 04.2.2 Grievance Redress Mechanism for Package II ...... 13 04.2.3 House to house Awareness programme for Meter shifting at Housing scheme...... 14 04.2.4 Awareness programme at Maning town Housing scheme ...... 14 04.2.5 Public awareness on Meter Relocation through street drama ...... 15 04.2.6 Public information notice for water interruption or Project activity ...... 16 04.2.7 Action taken to minimize the impact ...... 17 04.3 Construction of NRW office in Maligakanda ...... 20 04.4 Construction of Ellie house Area Engineer’s office ...... 21 Current status ...... 22 05 Scope of the Project (Project 2 -ADB Components) ...... 24 05.1 Current status of the Project ...... 24 05.1.1 System Rehabilitation- Colombo West Area (Package 03) ...... 24 05.1.2 Scope of work and Project Goals...... 24 05.1.3 Project Goal and Scope of Work ...... 25 05.1.4 Pipe laying work ...... 26 05.1.5 House to House Survey...... 26

ii

Social Safeguard Annual Monitoring Report - 2017

05.1.6 Occupational and Public safety ...... 26 05.1.7 Action taken to minimize the Public disturbances ...... 27 05.1.8 Grievance redress mechanism for Package III ...... 28 05.2 System Rehabilitation- Colombo South Area (Package 04) ...... 30 05.2.1 Scope of work ...... 30 05.2.2 Project Goal and Scope of Work ...... 31 05.2.3 Pipe laying work ...... 31 05.2.4 House to House Survey...... 32 05.2.5 Mitigation measures ...... 33 05.2.6 Grievance redress mechanism for Package IV ...... 34 05.3 Construction of New Training Center with Hostel facility.-Thelawala ...... 36 05.4 Construction of office buildings for Area Engineer- ...... 36 05.5 Construction of office buildings for Area Engineer- ...... 37 05.6 Booster pump house at Eli house reservoir site ...... 37 06. Public awareness activities done by the project Media Consultant ...... 38 06.1 Leaflet ...... 38 6.2 Mini Press Conference ...... 40 06.3 Project Web Site ...... 41 06.4 Bak Maha Ulela ...... 41 06.5 Paper Notice ...... 43 06.7 Awareness Program for Community Leaders ...... 44 06.8 School Art Exhibition ...... 44 06.9 Rupavahini News & Rupavahini Programme ...... 45 06.10 Hoarding ...... 46 07. Conclusion and further actions ...... 47 07. Annexes ...... 48

List of Tables

Table 04.1 Basic Details of Colombo North Package

Table 04.2 Basic Details of Colombo East package

Table 04.3 Action taken to minimize the impact

Table 04.4 Basic Details of construction of Eli house Area Engineer office

Table 04.5 Basic Details of Colombo West Package

Table 04.6 Basic Details of Colombo South Package

Table 04.7 Basic Details of Construction of Area Engineer office for Maharagama

Table 04.8 Basic Details of Construction of Booster pump house at Elihouse

Table 04.9 Conducted Rupavahini Programme

List of Figurers

Figure 04.1 Project location map (Package I)

iv

Social Safeguard Annual Monitoring Report - 2017

Abbreviations

ADB Asian Development Bank AGMC Awareness Generation Media Consultant CMC Colombo Municipal Council GCWWMIIP Grater Colombo Water & Wastewater Management Improvement Investment Programme GRC Grievance Redress Committee GRM Grievance Redress Mechanism LAA Land Acquisition Act MFF Multi-Tranche Financing Facility NGO Non-Government Organization NIRP National Involuntary Resettlement policy NRW Non-Revenue Water NWSDB National Water Supply & Drainage Board PCP Public Communications Policy PMU Project Management Unit RP Resettlement Plan SPS Safeguard Policy Statement UDA Urban Development Authority

Social Safeguard Annual Monitoring Report - 2017

01 Introduction

The Greater Colombo Water and Wastewater Management Improvement Investment Program (GCWWMIIP) aims at delivering better urban water supply and sewerage services in an effective and efficient manner in Greater Colombo area. The Investment Program comprises: (i) establishing Colombo-wide NRW reduction mechanism; (ii) rehabilitating the water distribution network; (iii) strengthening institutional, operational and implementation capacity of National Water Supply and Drainage Board (NWSDB) and Colombo Municipal Council (CMC);(iv) increasing public awareness on NRW; and (v) improving wastewater management in the Greater Colombo Area beyond Colombo city. The investment program is to be implemented from 2015 to 2019.The program uses a Multi-Tranche Financing Facility (MFF) investment approach for Project 1 & 2. MFF will concentrate on improving water supply in North & East part of Colombo city under the project 1 and West & South part of the Colombo city under the project 02. The initial target for project 01 and Project 02 is to reduce the overall NRW in Colombo city from the current 49% to less than 18% by the end of 2020. 01.1 Project implementing area

a. Area covered under the Project 01

1) Package 1 : , ,, ,Bloemendal 2) Package 2 : ,Boralla, , Maligawatta(part)

b. Area covered under the Project 02

1) Package 3 : , , Part of , 2) Package 4 : Nrahenpitiya, Part of Cinnamon Gardern, Thimprigassya ,, , Wellawatta, Kirulapone,

02 Purpose of the Report

This Annual Safeguard Monitoring Report has been prepared for aforementioned investment programme which involves: (i) increase water supply availability and efficiency in Colombo; (ii) enhance the distribution system and reduce NRW; (iii) establish a mechanism to reduce NRW; (iv) enhance the institutional, operational and project management capacity of NWSDB.

The ADB Public Communications Policy (PCP 2011) refers the Safeguard Policy Statement (SPS 2009) with respect to information disclosure related to project safeguard documentation states that ADB shall post on its website the safeguard documents submitted by the borrower and/or client. These safeguard documents include Resettlement (RP), and the social safeguard and environmental monitoring reports. It requires that monitoring report shall be submitted periodically over the total

implementation period of the project, covering Environment, Resettlement and social safeguard issues.

The above requirements are spelled out in this Social Safeguard Monitoring Report of the Project for the year of 2017.

03 Legal Frame Work for Resettlement Plan

The Resettlement Plan for GCWWMIIP has been prepared according to the National Involuntary Resettlement Policy (2001) and ADB Safeguard Policy Statement 2009. The land owners who lose land due to the project will be compensated at replacement value or land for-land where feasible. The policy framework and entitlements for the Project are based on national laws: The Land Acquisition Act, 1950 (LAA, amended in 1979) the National Involuntary Resettlement Policy, 2001 (NIRP); and ADB’s Safeguard Policy Statement 2009.

The survey and assessment undertaken during preparation of the project indicated that the project will entail some degree of resettlement impact. Therefore GCWWMIIP is designed to minimize land acquisition and resettlement impacts. The Project will:

1. Utilize existing lands for rehabilitation of existing water supply facilities. 2. Utilize vacant Government land to the extent possible for new facilities. 3. Where Government land is unavailable due to constraints (proximity and elevation requirements) in locating facilities, land selected will minimize any dislocation.

The above aspects are addressed as relevant in this report.

2

Social Safeguard Annual Monitoring Report - 2017

Greater Colombo Water and Wastewater Management Improvement Investment Program (Project 01) (ADB Components)

04 Scope of the Project

Under project 01, Following packages are proposed

1. System Rehabilitation- Colombo North Area (Package 01) 2. System Rehabilitation- Colombo East Area (Package 02) 3. NRW office for Maligakanda 4. Area Engineer’s office at Eli house reservoir site.

04.1 System Rehabilitation- Colombo North Area (Package 01)

Table 04.1 Basic Details of Colombo North package

a. Name of the System Rehabilitation for NRW Reduction in North of Colombo City Contract b. Contract No. CWSSIP/ADB/CIVIL/ICB/01 c. Name of the M/s.TODA Corporation and Sierra Construction (Pvt) Ltd Joint Venture Contractor d. Date of 13th Nov 2014 e. Scheduled date of 13th July 2018 award of completion - Contract: Original f. Contract 5th Jan 2015 g. Scheduled date of Commencem Completion as per ent Date: EOT

04.1.1 Scope of Work

Under the title of ‘System Rehabilitation for NRW Reduction in North of the Colombo city’ is an integral part and the project 1 of the Colombo Water and Waste Water Management Improvement Programme funded by the Asian Development Bank (ADB) and the Government of and it is expected to rehabilitate the pipe line network for water supply with particular emphasis on reducing the present high level of None Revenue Water (NRW) and establishing District Metered Areas (DMA) so that the National Water Supply & Drainage Board (NWSDB) is able to monitor NRW on a continuous basis and take remedial measures to minimize physical water losses. This Contract is for the water supply distribution network improvement in the group of subzones 1, 2,3,4,5,6,9,10,11 & 26 which constitute sixteen DMAs. The Name of the ten DMAs of the Colombo City North Area within the Colombo Municipal Council limits respectively are;

 Ellie house Mattakkuliya Riverside DMA (DMA 1)  Ellie house North East DMA (DMA 2A , 2B)  Ellie house Mattakkuliya Seaside DMA (DMA 3)  Ellie house East DMA (DMA 4A , 4B)  Ellie house South DMA (DMA 5A ,5B ,5C)

4

Social Safeguard Annual Monitoring Report - 2017

 Ellie house South Central DMA (DMA 6)  Ellie house Adjacent North DMA (DMA 9A , 9B)  Ellie house Adjacent West DMA (DMA 10)  Ellie house West DMA (DMA 11A , 11B)  Gothatuwa CMC North End DMA (DMA 26)

04.1.2 Project Location Map

Figure 04.1 Project location map (Package I)

04.1.3 Project Goal and Scope of Work

Goal: 1) Rehabilitation of North of Colombo city water supply scheme, update GIS database and DMA design 2) Establishment of hydraulically isolated DMAs for easy monitoring and reduction of water losses 3) Carryout NRW management within each DMA and reduce NRW to below 18% Scope: 1) Approximately 104km of pipe lines to be laid 2) Transfer nearly 23,200 service connections 3) Nearly 9km is considered to be rehabilitated with trenchless technology (Descaling, re-lining and pipe bursting).

04.1.4 Present Progress

 Pipe laying progress in DMAs - 2A, 2B, 03, 9A, 9B, 5A & 5B, 11B,  Pipe laying completed length - 87Km  Pressure testing completed length- 56Km  Connection transfer completed Nos- 5,876  NRW management - DMA 03 & 01 - NRW% reduce to below 18%  DMA 4A- NRW management work is in progress

As per to the traffic condition of the area, more than 70% of pipe laying work schedule at the night time.

6

Social Safeguard Annual Monitoring Report - 2017

04.1.5 Grievance Redress Mechanism for Package I

Complaints are handled through the Grievance Redress Mechanism as prescribed in the Resettlement Planning Document. Grievance redress/ suggestion forms, complaints / suggestion boxes and complain register were placed at the following four locations:

1. Divisional Secretary office -Colombo 2. Project Management Unit -Wellawatta 3. NWSDB, Area Engineer’s Office -Mattakkuliya 4. Contractor office –Mattakkuliya Display boards with contact details are kept at sites for any affected people to make a complaint. Complaint registers are also maintained by the project.

During the year 2017, 47 complaints received to the project and reported complaints were solved at the site level. There are not any outstanding issue for the period of 2017.Recived complaints related to Water leakage, No water complaints, House connection damages, Dust controlling issue and Road reinstatement issue. These type of issues can be solved at the site level. Received details of complaints attached as annexure 05

04.1.6 Occupational & Public safety at site

To ensure the safety of the public and workers is one of the most important responsibilities of the contractor. All the safety equipment especially footwear, safety jackets, helmets, etc. should be supplied to the workers according to the job assigned to them.

8

Social Safeguard Annual Monitoring Report - 2017

Safety meeting at the site-Regarding the workers safety

04.1.7 Mitigation Measures

 Distribution of water interruption notices and loud speaker announcement for water interruption - by the contractor  Due to the damage of existing water lines, water bowser has been engaged to supply the water to affected consumers until repair works competed.  Minimize the dust generation - sprinkling water bowser have been used  Providing temporary access to pedestrian, motorists and householders  Properly cleaning the site after completion of work  Regular site visit to oversee the resettlement plan implementation

Following photographs further describes the way of minimize the disturbance to public

Dust Control

Site cleaning work Traffic controlling work

Loud speaker announcement for water cut

10

Social Safeguard Annual Monitoring Report - 2017

Road permanent reinstatement works done after the completion of the pipe laying work.

Providing temporary access to the house

04.2 System Rehabilitation- Colombo East Area (Package 02)

Table 04.2 Basic Details of Colombo East package a. Name of the System Rehabilitation for NRW Reduction in East of Contract Colombo City b. Contract No. CWSSIP/ADB/CIVIL/ICB/02 c. Name of the Kolon Global Corporation. Contractor d. Date of award of e. Scheduled date of 4th Jul Contract: completion - 2018. Original f. Contract 13th July g. Scheduled date of Commencement 2015 Completion as per Date: EOT

Goal: 4) Rehabilitation of East of Colombo city water supply scheme, update GIS database and DMA design 5) Establishment of hydraulically isolated DMAs for easy monitoring and reduction of water losses 6) Carryout NRW management within each DMA and reduce NRW to below 18% Scope: 4) Approximately 145km of pipe lines to be laid 5) Transfer nearly 22,000 service connections

04.2.1 Pipe laying and other work

 Pipe laying work in progress- DMA 25, 30A, 30B, 30C, 30D, 27A, 27B, 18, 28A & 28B.  Pipe laying completed length - 55 Km  Pressure testing completed length - 23 km  House Connection transfer completed Nos- 1500

More than 70% of pipe laying work scheduled at night time to minimize the disturbance the public. Although some selected by roads and by lane pipe laying work are doing in the day time by considering the congestion of the area.

12

Social Safeguard Annual Monitoring Report - 2017

04.2.2 Grievance Redress Mechanism for Package II

Complaints are handled through the Grievance Redress Mechanism as prescribed in the Resettlement Planning Document. Grievance redress/ suggestion forms, complaints / suggestion boxes and complain register were placed at the following four locations: 1. Divisional Secretary Office –Colombo and Thimbirigasyaya 2. Project Management Unit -Wellawatta 3. NWSDB, Area Engineer’s Office -Maligawatta 4. Contractor office Display boards with contact details are kept at sites for any affected people to make a complaint. Complaint registers are also maintained by the project.

During the reporting period of 2017, Received 155 complaints and all the issues were solved at the site level with the support of the NWSDB project staff, Water board O & M staff, Electricity board and Drainage division of Colombo Municipal Council. When consider about the received complaints, more than 95% of complaints made by the NWSDB project staff regarding Water line damages, Water Leakages, Electricity cable damages, sewer line damages, road damages, dust controlling issue and road reinstatement issues. Received details of complaints attached as annexure 06

04.2.3 House to house Awareness programme for Meter shifting at Maligawatta Housing scheme.

As per to the requirement of the project, A comprehensive House to House awareness programme was conducted for the purpose of water meter relocation in Maligawatta Flat (DMA 27 B), by the project NGO team. This programme carried out under the supervision of project manager of package 02.While doing awareness programme, project awareness leaflet also distributed to the households.

04.2.4 Awareness programme at Maning town Housing scheme

A community awareness and discussion had with the community representative in Manning Town (DMA30D) on 2017/11/19 (Sunday) at the Tower Premises of Manning Town. Necessary invitation has been distributed to all community leaders in Manning Town and discussed on going activities of the project and requested to get the support for the construction activity done by the project.

14

Social Safeguard Annual Monitoring Report - 2017

04.2.5 Public awareness on Meter Relocation through street drama

In order to make aware of the community at maligawatta housing scheme, a special street drama was performed on 17.12.2017.It was organized by the project Media Consultant (A &D Advertising (Pvt) Ltd) under the supervision of the NWSDB. During the street drama, explained the benefits of ongoing project and water meter relocation.

04.2.6 Public information notice for water interruption or Project activity

Before construction work start in any area, prior notice distribute to resident and motorist usually use the roads. As well as prior water interruption notice distribute to residents where water cut schedule to be planned. It is help full to affected people to collect water before water cut staring.

Sample of the prior information Notice for water cut

16

Social Safeguard Annual Monitoring Report - 2017

04.2.7 Action taken to minimize the impact

During the period of reporting, following action have been taken to minimize the impact by the contractor.

Table 04.3 Action taken to minimize the impact S/N Particulars Action taken 01  Water Spreading during the trench excavation Controlling of dust emission  Properly cleaning the site after completion of work using the water. 02 Controlling the noise  Use Brand New Machines & Equipment 03  Provide personal protective equipment for all workers & Staff Occupational Safety  Awareness program was carried out  Arrange proper lightning for reduce the accidents during the night work  Utilize HSE Engineer & Safety Officer to ensure the Occupational safety 04  Provide adequate sign boards to provide Public Safety information to the public  Provide traffic controllers to manage the traffic  Displaying safety and awareness boards to aware the public  Installing hazard warning flash lights to aware the public  Using Illumination (Duel Colour) traffic controlling battens to proper traffic management 05  Distribute of prior notice to the public Social Impacts  Only Half road closure to minimize the disturbances

06  Remove quarry dust and pothole patching by Minimize the Disturbances to asphalt Road Users  Remove material and site cleaning Continuous road maintenance up to permanent reinstatement

Wearing personal protective equipment

04.3 Construction of NRW office in Maligakanda

General Description: Construction of NRW Building (Maligakanda)

Package No: GCWWMIIP/ADB/ BUILD/NRW/NCB/03

Procurement Method: NCB

Name of the contractor: Link Engineering Commencement Date: 24th April 2017 Scheduled Completion Date: 23rd October 2018.

Current Status: 5th Floor slab was concreted. Ground floor backfilling & Rubble work are in progress. Note: The land belongs to NWSDB (Water Board) and there is not any resettlement impact to public.

20

Social Safeguard Annual Monitoring Report - 2017

 Safety and warning signboards have been displayed at site.  The Contractor has fenced off safety mesh over the building.

04.4 Construction of Ellie house Area Engineer’s office

Table 04.4 Basic Details of construction of Eli house Area Engineer office a. Name of the Contract Construction of Elliehouse Area Engineering Office, Sri Lanka b. Contract No. GCWWMIIP/ADB/BUILD/ELLIE/NCB/02R c. Name of the M/S Darinton Construction (Pvt) Ltd Contractor d. Date of award of 11.06.2016 e. Scheduled date of 19.01.2018 Contract: completion - ( As per site handing Original over date, But Advance payment to be made) f. Contract 20.07.2016 g. Scheduled date of Commencement ( Site handing Completion as per Date: over date) EOT

Current status  Finishing works & electrical works is in progress. Note: The lands belongs to NWSDB (Water Board) and there isn’t any Involuntary Resettlement impact.

22

Social Safeguard Annual Monitoring Report - 2017

Greater Colombo Water and Wastewater Management Improvement Investment Program (Project 2) (ADB Components)

05 Scope of the Project (Project 2 -ADB Components)

Under project 02, Following packages are proposed. 1. System Rehabilitation- Colombo West Area (Package 03) 2. System Rehabilitation- Colombo South Area (Package 04) 3. Construction of New Training Center with Hostel facility.-Thelawala and LS Yard at Polwatte 4. Construction of office buildings for Area Engineer- Maharagama 5. Construction of office buildings for Area Engineer- Pamankada 6. Booster pump house at Eli house reservoir site

05.1 Current status of the Project

05.1.1 System Rehabilitation- Colombo West Area (Package 03)

Table 04.5 Basic Details of Colombo West Package h. Name of the System Rehabilitation for NRW Reduction in West of Contract Colombo City i. Contract No. CWSSIP/ADB/CIVIL/ICB/03 j. Name of the China Geo & China Harbour Contractor k. Date of award of 20th l. Scheduled date of Contract: Oct completion - 2nd 2016 Original February 2021. m. Contract 1st n. Scheduled date of Commencement March Completion as per Date: 2017 EOT

05.1.2 Scope of work and Project Goals.

This contract is for the water supply distribution network improvement in the group of subzones 7A,7B,7C,8A,8B,12A,12B,12C,13,14,15A,15B,15C,16A,16B,19A,19B,21 and 22 which constitute Nineteen DMAs. The Name of the Nineteen DMAs of the Colombo City Western Area within the Colombo Municipal Council limits respectively are;

24

Social Safeguard Annual Monitoring Report - 2017

7A Ellie House south west (A) DMA 7B Ellie House South West (B) DMA 7C Ellie House South West (C) DMA 8A Ellie House Harbour DMA

8B Ellie House Harbour DMA

12A Ellie House Maharoof (A) DMA

12B Ellie House Maharoof (B) DMA

12C Ellie House Maharoof (C) DMA 13 Port City DMA 14 Maligakanda Railway DMA 15A Maligakanda West DMA 15B Maligakanda West DMA 15C Maligakanda West DMA 16A Maligakanda West Coastal DMA 16B Maligakanda West Coastal DMA 19A Maligakanda South West Coastal DMA 19B Maligakanda South West Coastal DMA 21 Maligakanda South Coastal DMA 22 Maligakanda North DMA

05.1.3 Project Goal and Scope of Work

Scope: -  Approximately 99 km of pipe lines to be laid  Transfer nearly 9,305 service connections  Nearly 19.9 km is considered to be rehabilitated with trenchless technology (de- Scaling, Re-lining, and pipe bursting)

Goal: -

 Rehabilitation of West of Colombo city water supply scheme, update GIS database and DMA design

 Establishment of hydraulically isolated DMAs for easy monitoring and reduction of water losses  Carryout NRW management within each DMA and reduce NRW to below 18%

05.1.4 Pipe laying work

Pipe laying will be commenced after completion of detail design and approved by the engineer. As a priority, some area’s pipe laying work were started due to request made by the Colombo Municipal Council.

05.1.5 House to House Survey

A total data base of consumers on DMA basis, in GPS format is an essential tool for NRW management. In order to do this, a house to house survey is being carried out collecting information. In consultation with the NWSDB, a hand out in all three languages was drafted is been distributed to the consumers in all DMAs. This handout gives an outline of the objectives and scope of the project as well as the benefits the consumers will derive from it.

05.1.6 Occupational and Public safety

The contractor is equipped with all the safety gear for workmen, equipment necessary for road safety during the night work including lighting, excavation and road reinstatement, GPS

26

Social Safeguard Annual Monitoring Report - 2017

equipment for recording locations of pipe and other utilities as well as for house to house survey.

05.1.7 Action taken to minimize the Public disturbances

1. Properly barricade the site to minimize the accident

2. Experienced workers has been deployed to control the traffic.

3. More than 70% of pipe laying work scheduled at night time. 4. Permanent reinstatement done after the completion of the pipe laying work

05.1.8 Grievance redress mechanism for Package III

Followings are the main objectives of establishing a Project Grievance Redress Mechanism.

 Ensure better safeguards mechanisms for implementation of subprojects.  Resolve social and environmental grievances in the Project areas.  Build up a relationship of trust amongst the project staff and the affected parties.  Ensure transparency in dealings amongst stakeholders including affected parties through a proper communication system.

Package III Grievance Redress Mechanism was established in 13th December 2017 with the participation of Divisional Secretary of Colombo, Head of the Gramaniladhari, Grama Niladharies, Project Manager of Package III, Chief Engineer (Planning) (PMU), PMU Social Safeguards Officer, Health ,Safety & Environmental specialist of consultant’s, Contractor’s representatives and representatives of relevant Community Based Organizations. The Social Safeguards Officer of the PMU initially briefed about the Grievance Redress Mechanism of the Project, importance of establishing GRM, Process of solving issues, Members of the GRC and explained the procedures and formats to be used including the reporting procedures.

28

Social Safeguard Annual Monitoring Report - 2017

Composition of Grievance Redress Committee (GRC) is as follows.    Fort), NWSDB,   Health ,Safety & Environmental specialist (Consultant)   ased Organizations (CBOs),

The local representative of CEA and representatives of Road Development Authority (RDA), Provincial Road Development Authority (PRDA), Colombo Municipal Council (CMC) and concerned GN Officers may be invited to GRC meetings as and when required

As per the decision taken at the above meeting, grievance redress/ suggestion forms, complaints / suggestion boxes and complain register were placed at the following four locations:

1. Divisional Secretary Office -Colombo 2. Project Management Unit -Wellawatta 3. NWSDB, Area Engineer’s Office -Fort 4. Contractor office –Kolpitty GRM establishment Meeting minutes and Attendance sheets were attached as annexure 02 & 03

GRM Establishment Meeting- Package III

05.2 System Rehabilitation- Colombo South Area (Package 04)

Table 04.6 Basic Details of Colombo South Package

o. Name of the System rehabilitation for NRW Reduction in South Part of Contract The Colombo City p. Contract No. GCWWMIIP/ADB/CIVIL/ICB/04 q. Name of the Sinohydro Contractor r. Date of award of 20th Oct s. Scheduled date of 4th June Contract: 2016 completion - 2021 Original t. Contract 5th u. Scheduled date of Commencement June Completion as per Date: 2017 EOT

05.2.1 Scope of work

This contract constitutes improvement of the water supply distribution network in the group of 14 DMA or subzones namely 20, 31A, 31B, 32, 33A, 33B, 34, 35A, 35B, 36A, 36B, 37A, 37B, & 38. There are Approximately 170 km of pipe lines, transfer nearly 35,000 service connections, nearly 15 km is considered to be rehabilitated with trenchless technology (Relining), Laying of approximately 155 km. of pipes of diameters laying from 1000 mm. to 63mm. The identification details of the above DMAs in south part of the Colombo City Area identified within the Colombo Municipal Council limits as follows;

DMA 20 - Maligakanda South DMA

DMA 31 A – Jubilee CMC North (A) DMA

DMA 31 B - Jubilee CMC North (B) DMA

DMA 32 – Jubilee CMC East DMA

DMA 33 A – Jubilee CMC Central South (A) DMA

DMA 33 A – Jubilee CMC Central South (B) DMA

DMA 34 – Jubilee CMC South DMA

30

Social Safeguard Annual Monitoring Report - 2017

DMA 35 A – Jubilee CMC North Coastal (A) DMA

DMA 35 B – Jubilee CMC North Coastal (B) DMA

DMA 36 A – Jubilee CMC Central Coastal (A) DMA

DMA 36 B – Jubilee CMC Central Coastal (B) DMA

DMA 37 A – Jubilee CMC West Coastal (A) DMA

DMA 37 B – Jubilee CMC West Coastal (B) DMA

DMA 38 – Jubilee CMC South Coastal DMA

05.2.2 Project Goal and Scope of Work

Goal:  Rehabilitation of South of Colombo city water supply scheme, update GIS database and DMA design  Establishment of hydraulically isolated DMAs for easy monitoring and reduction of water losses  Carryout NRW management within each DMA to reduce NRW to below 18%

05.2.3 Pipe laying work

Currently engaged in pipe laying and other related works in priority area of south of the Colombo city. There are several other locations where the pipe laying work is to be started.

05.2.4 House to House Survey

In accordance with the requirement of project, House to house survey is being carried out to collect data from the households in Colombo south area covering 35000 HHs. An information sheet with a questionnaire was compiled with assistance of the NWSDB and expatriate specialist. Accordingly, along with the general information of the consumer, GPS coordinates of each connection, status of present service, physical state of each service connection and prevailing pressure at the consumer end are now being recorded. While doing the survey, a project awareness leaflet distribute to get an idea of the project and its benefits to consumers. Project awareness leaflet consisting with all three language (Sinhala, Tamil and English).

32

Social Safeguard Annual Monitoring Report - 2017

05.2.5 Mitigation measures

1. To minimize the disturbance to public, More than 70% of the pipe laying work scheduled at night time.

2. Prior information leaflet distribute to households, regarding on going activities in the area.

3. Temporary reinstatement or Permanent reinstatement work done just after the completion of the pipe laying activities.

4. Personal protective equipment was provided to all workers to minimize the accident in the site.

05.2.6 Grievance redress mechanism for Package IV

Followings are the main objectives of establishing a Project Grievance Redress Mechanism.

 Ensure better safeguards mechanisms for implementation of subprojects.  Resolve social and environmental grievances in the Project areas.  Build up a relationship of trust amongst the project staff and the affected parties.  Ensure transparency in dealings amongst stakeholders including affected parties through a proper communication system.

Package III Grievance Redress Mechanism was established in 27th December 2017 with the participation of Divisional Secretary of Thimbirigasyaya, Head of the Gramaniladhari, Grama Niladharies, Project Manager and Deputy project Manager of Package IV, PMU Social Safeguards Officer, Health ,Safety & Environmental specialist of consultant’s, Contractor’s representatives and representatives of relevant Community Based Organizations. Deputy Project Manager of the Package IV initially did the introduction about the project and after that PMU Social Safe Guard Officer briefed about the Grievance Redress Mechanism of the Project, importance of establishing GRM, Process of solving issues, Members of the GRC and explained the procedures and formats to be used including the reporting procedures.

34

Social Safeguard Annual Monitoring Report - 2017

Composition of Grievance Redress Committee (GRC) is as follows.

 Divisional Secretary (Thimbirigasyaya) as Chairperson,  Project Director  Area Engineer (Pamankada), NWSDB,  NWSDB PMU Social Development/Safeguards Officer  Health, Safety & Environmental specialist (Consultant)  Director of the project NGO,  Community Based Organizations (CBOs),

The local representative of CEA and representatives of Road Development Authority (RDA), Provincial Road Development Authority (PRDA), Colombo Municipal Council (CMC) and concerned GN Officers may be invited to GRC meetings as and when required

As per the decision taken at the above meeting, grievance redress/ suggestion forms, complaints / suggestion boxes and complain register were placed at the following four locations:

1. Divisional Secretary Office -Thimbirigasayaya

2. Project Management Unit -Wellawatta

3. NWSDB, Area Engineer’s Office -Pamankada

4. Contractor office –Poorvarama mw ()

GRM establishment Meeting minutes and Attendance sheets were attached -annexure 04 and 05.

GRM Establishment meeting-P IV

05.3 Construction of New Training Center with Hostel facility.-Thelawala

The selected land belongs to NWSDB. Hence there is no any land acquisition or IR impacts anticipated.

Current Status:

 Contract to be commenced. 05.4 Construction of office buildings for Area Engineer- Maharagama

Table 04.7 Basic Details of Construction of Area Engineer office for Maharagama h. Name of the Contract Construction of Upper two floors of the existing Area Engineer’s office building at Maharagama – Project 2, Sri Lanka i. Contract No. GCWWMIIP/ADB/BUILD/MAHA/NCB/01 j. Name of the M/S Luminex (Private) Limited Contractor k. Date of award of 08.12.2014 l. Scheduled date of 15.12.2015 Contract: completion - ( As per site handing Original over date, But Advance payment made on 11.05.2015) m. Contract 15.02.2015 n. Scheduled date of Commencement ( Site handing Completion as per 12.04.2016 Date: over date) EOT

Status:  Construction works completed and building was handed over to NWSDB.

36

Social Safeguard Annual Monitoring Report - 2017

05.5 Construction of office buildings for Area Engineer- Pamankada

General Description: Construction of buildings for Area Engineers-Pamankada

Package No: GCWWMIIP/ADB/BUILD/PAMAN/NCB/08

Procurement Method: NCB 1S-1E

Current Status:

Architect consultant contract (Archie Triad) was held up due to the land issue. (CMC took the originally proposed land to construct the pump house).

05.6 Booster pump house at Eli house reservoir site

Table 04.8 Basic Details of Construction of Booster pump house at Elihouse o. Name of the Contract Construction of Ellie House Pump , Sri Lanka p. Contract No. GCWWMIIP/ADB/PH/NCB/05 q. Name of the M/S Darinton Construction (Pvt) Ltd Contractor r. Date of award of 03.08.2016 s. Scheduled date of 19.01.2018 Contract: completion - ( As per site handing Original over date, But Advance payment to be made) t. Contract 1.12.2016 u. Scheduled date of Commencement Completion as per 31.05.2018 Date: EOT

Current Status:

 Pump house slab concreted. Note: Due to the land belonging to NWSDB, There is not any involuntary resettlement impact.

06. Public awareness activities done by the project Media Consultant.

The objective of the communication strategy is to: (i) promote awareness of the Investment Program and water supply and wastewater projects during implementation; (ii) secure the participation of the community in all stages of project planning and implementation; (iii) establish two-way flow of information and dialogue with directly involved stakeholders, to integrate their concerns and increase support and involvement in the projects; and (iv) secure the participation of high-quality professionals, including contractors, in project implementation. The communication strategy includes a media based awareness campaign, web disclosure, and direct communication through meetings and consultations.

06.1 Leaflet As a public awareness tool, a leaflet on Colombo Water Supply Service Improvement project was designed and handed over to the all packages to distribute to the households. Leaflet printed in all three language (Sinhala, Tamil& English). The designed leaflet is given below.

38

Social Safeguard Annual Monitoring Report - 2017

Leaflets distribution

6.2 Mini Press Conference

A mini press conference was held on 23rd May 2017 with the representatives of Lakehouse, Dinamina, Daily mirror, Thinakaran, Daily Mirror, Mawbima newspapers at the Conference Hall of Project Management Unit. The objective of the mini press conference was to increase the awareness among public on CWSSIP, which is being implemented currently in the city of Colombo by the NWSDB.

Published Paper articles about the Project

40

Social Safeguard Annual Monitoring Report - 2017

06.3 Project Web Site

The project web site was designed and launched on 27 March 2017 during the project launching ceremony. The website contains the latest project updates such as news and information, and will include the portent articles, statistics, photos, graphics and videos under the below given sections:

 Home – Brief on project, News and events  About us project at a glance ,objectives, Benefits ,Approach ,Packages, Project Financing - Procurements Tender Notice ,Ongoing procurements ,Contract awarded  Implementation  Publication – ADB reports, progress report  Gallery – Videos, photos, and Audio  FAQs  Contact Us

06.4 Bak Maha Ulela

Media consultant proposed to organize the bak maha ulela on the 29th April 2017. The objective of the Bak Maha Ulela is to increase awareness among the public on the CWSSIP, which is being implemented currently in the city of Colombo by the NWSDB.Bak Maha Ulela/ Sinhala and Tamil New Year festival was sponsored by the Colombo Water Supply Service Improvement Project (CWSSIP) with the collaboration of all partners of the project, was held on 29 April, 2017 at the Ratnam Grounds, Colombo 13.

The event consisted of many fun-filled folk games including Kanna Muttiya Bidima,Baniskema, Kaba adima, Hodama Hinawa, Hodama adima, Aliyata Asa Thebima, Piti Thula Kasiya Sevima, Pol Gema, Andayata Kiri Kewema, Idikatuwata Nula Demima, Sauna Amuththa Sevima, Piththra Ellima, Goni Race, Balloons Pipirima, Musical Chairs, Dehi Gediya Handa Matha Divima, Banis Kema, Vikata Adum, Sigithi Avurudu Kumara, Kumariya, Avururdu Kumariya and competitions including a 65-kilometer bicycle race which was held under the supervision of the Sri Lanka Cycling Federation. The public living in and around the North (Package I) and East (Package II) of Colombo participated in the event enthusiastically. Photos of the Bak Maha Ulela are given below.

42

Social Safeguard Annual Monitoring Report - 2017

06.5 Paper Notice Paper notices on pipe lying schedule publish on 1st week of the every month in Daily News, Lankadepa and Verrakesari. Media consultant designed a paper notice to aware the public on pipe laying schedule based on the information received from package 01, package 02, package 03 and package 04.

06.7 Awareness Program for Community Leaders An awareness program on Colombo Water Supply Service Improvement project was conducted on 24th October 2017 at Mahaweli Center, Colombo 07. Twenty nine community leaders from Colombo Municipal council area and 30 staff members including project staff members and NWS&DB officers participated. The objective of the awareness program was to make the Community Leaders aware of the CWSSIP, Introduction of Randiya Program and the component of the improvement of the water system of government owned condominium.

06.8 School Art Exhibition

The art competition was organized in order to increase public awareness of the on-going Colombo Water Supply Service Improvement Project (CWSSIP) and 50 selected schools in Colombo East (Package II) and North (Package I) participated for the competition. The exhibition and prize giving of the school art competition titled ‘The renewing water supply for the developing Colombo’ and it was held at the J. D. A. Perera Art Gallery, Colombo 07, on 31st October 2017.Arts were judged on 16th October by Senior Lecturers Dr . R.M.Dharmasena and Mr. Sarath Perera who lectures at Faculty of fine arts.

44

Social Safeguard Annual Monitoring Report - 2017

06.9 Rupavahini News & Rupavahini Programme

In order to make aware of the public, there were some Rupavahini programmes & news on CWSSIP telecasted in different Rupavahini channels during the Year of 2017.Following three Rupavahini programs were conducted during the year.

Table 04.9 Conducted Rupavahini Programme

Date Channel Name of the Duration Participants program 19/10/2017 National Sanhinda (Live) 15 Project Director and Rupavahini Minutes Deputy Project Director 23/10/2017 ITN wasantham Makkal Service 1 Hr Project Director and Project live program Manager (Pacakege 02) Tamil 24/10/2017 National Udaya Darsanam ½ Hr Project Director and Project Rupavahini live program Manager (Pacakege 01 Eye Channel Tamil

06.10 Hoarding

A Hoarding was placed in front of the Kelani Thissa power plant and on top of the Senok Building. It’s useful to know about the ongoing project done by the NWSDB.

Photo 01: Erected Hoarding in front of Kelani Thissa Power Plant

46

Social Safeguard Annual Monitoring Report - 2017

07. Conclusion and further actions

The report confirms that the water supply service improvement in Greater Colombo area under the all tranches not have adverse social impacts associated with land acquisition and resettlement .There are no any land acquisitions under this project due to all the Pipe laying work along the public road and Building construction at existing lands belongs to the NWSDB. It is expected that the project will benefit entire population of the city of Colombo after the completion of the Project.

As per ADB’s safeguard policy statement, the project authority established Grievances Redress Mechanism for all 4 packages to receive and facilitate resolution of affected persons’ concerns, complaints and grievances about the project’s Social and Environmental performance. It will be addressed affected peoples’ concerns and complaints promptly, using an understandable and transparent process that is gender responsive, culturally appropriate, and readily accessible to all the affected people.

During the period of 2017, Overall safeguards implementation is stand at satisfactory level. Always paid special attention to minimize the impact to Colombo city resident and also the motorists, pedestrian and businessmen. Further to that monitoring of safeguard activities regularly overseen by the PMU and PIU staff.

07. Annexes

48

Social Safeguard Annual Monitoring Report - 2017

Annexure 01 GRM establishment Meeting Minute-Package III

50

Social Safeguard Annual Monitoring Report - 2017

Annexure 02 GRM establishment Meeting Attendance-Package III

52

Social Safeguard Annual Monitoring Report - 2017

54

Social Safeguard Annual Monitoring Report - 2017

Annexure 03 GRM establishment meeting Minute for Package IV

56

Social Safeguard Annual Monitoring Report - 2017

58

Social Safeguard Annual Monitoring Report - 2017

60

Social Safeguard Annual Monitoring Report - 2017 Annexure 05 Received complaints for 2017(Package I)

Complain by(Name), Date of Resolve S/N Address, Description / Location Action Taken Remarks Complain Date ID Number, Mobile 1 2017.02.13 Mr. Eric: - 48/2, Malwahtha open trench for a long time A team deployed to back 2017.02.13 Action taken by the Ishara (EA- lane, mattakkuliya. period in front of the house fill the trench PIU)(complain received via 0777557121 (since last week) mobile phone call)

2 2017.05.15 Mr. M.Rajendran, 63 4/B, Water Leakage Leak repaired on 2017.05.15 The rectified issue confirmed by Modara Street, Colombo 15. 15.05.2017 night, by Mr. Mr. Suthakaran (PM-CN) via 0714081813 Leo (contractor Eng.) phone call.

3 2017.05.16 Mr.Eraj wanninayake. Water Leakage from leak repaired on16.05,2017 2017.05.16 confirmed by Mr. 143/17, sri wikrama MW contractor's water meter day time by Sasanka manju(sociologist -CN) colombo 15, (water Meter installed for (contractor supervisor) 0773865359 sensory the minimum night flow)

4 2017.05.30 Mrs.darshani rupika water leakage in front of the leak repair on 31.05.2017 a 2017.05.31 confirmed by Mr. amarasekara. 64/38,Modara house team deployed to repair the manju(sociologist -CN) street colombo 15 0712340594 leak (Mr .dilrukshang (Eng.)-(contractor)

5 2017.05.30 Mr.Nalla thambi, no water supply Temporary water 2017.0501 Confirmed by Mr. Manju 331, modara street Colombo 15. connection given from the (sociologist -CN) via telephone 0112527391- owner complained exiting line, until house call. by Mr.Rojendran (0785158727) connection transferring to the newly laid line.

6 2017.06.02 Mr.I.N Ananda, paramananda no water supply a team deployed to rectify 2017.06.02 confirm by Mr. Asanka (EA- viharaya MW,kotahena.colombo the issue NWSDB) 13, (119/5) 0788611112

7 2017.05.17 J.M.ferdinand 40/10, St Mary’s Objection for providing Due to the objection, 2017.06.5 Visited several time to solve the lane, mattakkuliya, Colombo 15. water supply to number connection not transferred issue and met both parties, but 40/7 from newly laid line. to new line unable to solve the issue .Therefore decided to water supply provide through the existing line. 8 2017.06.19 Navin Fernando, 15, Wasala Rd, reinstatement work not A team deployed to rectify 2017.06.21 confirmed by Mr.Asanka Kotahena. 0777 315 656 done properly, the issue (Mr.shanaka- (EA-NWSDB) contractor engineer)

9 2017.06.20 M.S. perera, 311/5, ferguson Rd, Waste water line damaged repaired damage waste 2017.06.21 confirmed by Mr.Kadafi (EA- mattakkuliya colombo 15. due to pipe laying works. water line by the contractor NWSDB) 0114933572

10 2017.06.27 Mrs.Ravindran, 30/2, mayfield Private road pipe laying Road cleaning and 2017.06.28 confirmed by avenue. Kotahena, colombo 14, compaction not done compaction done by the Mr.manju(sociologist) 2017.06.29 0112335786 properly, site cleaning not contractor. done after the completion of work.

ii

Social Safeguard Annual Monitoring Report - 2017 11 2017.06.27 Mr.Eshwaranathan, 765/3, Farm Compacted soil washed Temporary reinstatement 2017.06.30 Rd. Mattakkuliya. 0714230829 away due to the heavy rain. has been done by the contractor again.

12 2017.06.28 Mr.N.Sivakumar. water supply is not A team deployed to rectify 2017.06.30 8/275(233/301) henemulla available (no water the issue Camp, colombo .15, complain) 0758522023

13 2017.06.28 Mr.M.S perera . 311/05, access road damage in A team deployed to rectify 2017.06.28 Confirmed by the Mr. sanjaya ferguson Rd, mattakkuliya, several location due to the the issue by Mr. Teron (Eng.) visited to Ferguson Rd to colombo 15, 01114933572 house connection (Eng.)- contractor re leak the water contractor rectify transferring activities the issue in a proper way or not on 29th June 2017 with Eng. Mr. sanjaya.

14 2017.06.29 Mr.shane fernando. water supply not available rectified issue on 30th June 2017.06.30 Repaired on 29 th June 2017 at No.524,Aluth MW, colombo 15, since 28th June 2017 2017(Mr.dilrukshan- the night time but still Water 0771566855 contractor engineer) supply not Available re informed to Contractor to rectify the issue immediately 30th June rectified issue again. Confirmed by Mr. Manju (P1)

15 2017.06.30 Mr.Hashim Rasheed . No 132, Inconvenient to Access to temporary Reinstatement 2017.06.30 Informed Mr. Prasad (DPM- ST Joseph Steet , Colombo 14. House Due to the temporary done by the sierra on 30th sierra)to rectify the issue on 30th 0777304111 Reinstatement wasted away June 2017 June 2017. (confirmed by Mr. (by rain) manju)

16 2017.07.03 Mr.waduguyiya pillei, no Public drain blocked due A team deployed to rectify 2017.07.04 Relevant engineer of the area and 21,wasala Rd, kotahena. to the construction activity. the issue. sociologist visited the location Colombo 14. 0112445341 and promised to solve the issue immediately. Confirmed by mr.Shanaka

17 2017.07.03 Mr.L.nallathambi,125/8,16th Water leak at the side of the water leak repaired by 2017.07.03 Confirmed by Mr.manju. lane Colombo 13.07777 16th lane kotahena. (in front labors of contractor under of the house) the super vision of operation and maintenance division of water board

18 2017.07.03 Mr.E.m.Priyantha collin. No Water meter lost at the time a new meter installed by 2017.07.05 Acc:No,10/11/245/306/15 meter 298,modara street Colombo 15. of pipe laying and requested the contractor no:0803052313 visited to 0778340058 install a new water meter. complain location met Mr. priyantha on 03/07/2017 requested a letter for install a new water meter due to water meter lost on 05/07/2017

19 2017.07.04 Mr.samantha. No 26/1,fransa Requesting a newly laid PE Discussed the matter with visited to location and met waththa ,mattakkuliya,colombo line transfer to other side of the resident and agreed to relevant people on 04/07/2017 15,0729302500 the road because of the transfers the line other side construction of new drain of the road. line.

iv

Social Safeguard Annual Monitoring Report - 2017 20 2017.07.10 Mr.gavakumaran.no 30/2, due to the pipe laying for informed to the contractor 2017.07.10 Concrete Rd, temporary mayfield avenuve, kotahena, RKS garage entrance to do permanent reinstatement done. confirmed by colombo 14. 0777770990 damaged, and stormier line reinstatement, permanent Mr. Shanaka (Sierra Engineer) block reinstatement done by the contractor

21 2017.07.24 Mr.K.B.M. Ramzan . Water leakage in front of Water leak repaired by the 2017.07.24 Confirmed by Mr. Lea (Sierra 356,Modara Street, Colombo. the house contractor Engineer) 0112527853

22 2017.07.27 Mr.Sugunawanathan . 62/22B, Private road, Back filling Water leakage repaired 2017.08.08 Confirmed by contractor Eng. Mr. Sri Kalyangaram Road, not done properly, water Backfilling was done Sathisa (Eng.) Colombo 15. 0724414192 leakage has started at the properly by the Contractor side of the road.

23 2017.07.28 Mr.K.B.M. Ramzan . Dust Generation due to the visited to location and 2017.07.29 356,Modara Street, Colombo. constriction activates informed to sierra to clean 0777946644 the site and engorge water sprinkling baser to minimize the dust

24 2017.08.09 A.M.M. Uvaise .844/6, Water leakage started after A team engaged to rectify 2017.08.13 Confirmed by sociologist through Aluthmawatha Rd, Colombo 15 laying of new line (house the issue (Mr.Dilrukshan the phone call . 0772242732 0774804869 connection damage) (Eng. Sierra)

25 2017.08.14 Mr. Mervine soyza. 228/3, drainage line blocked due to rectified the issue with the 2017.08.14 After recited issue ,visited to Modara Street, Colombo 15 pipe laying activities support of the CMC location and met the residents of 0774874742 sewerage division the area contractor Labors also attended to the work

26 2017.08.15 Mr.Navin Fernando. No 15, Dust generation due to pipe Water bowser has been 2017.08.15 Mr.Navingave a call to thank for Wasala Road, Kotahena, laying activities engaged for sprinkling the immediate action taken by the Colombo 13. 0777315656 grater project team. On 16th Aug 2017.

27 2017.08.15 Mr.Shiraj. No. 358, Modara Drainage line blocked due A team deployed to rectify 2017.08.18 Got the support form CMC Steet, Colombo 15. 0766117716 to the activity the issue by contractor sewerage Section to clear the gully chamber.

28 2017.08.15 Mr.S.balasubramaniyam , water supply is not Rectified the issue on 15th 2017.08.15 visited to location to verified 23/24A,wals lane, colombo 15. available since 3 days Aug. 2017 at night. By the weather issue rectified or not by 0752727459 O&M selection of sociologist NWSDB

29 2017.08.16 Mr.Sugunawanthan, 62/22B, excavated soil not removed Informed the issue to 2017.8.18 Sociologist visited to location kalyani gangarama MW sierra and agreed to and informed to responsible colombo 15 0724414192 remove all the excavated officer of contractor side to solve soil. the issue.

30 2017.08.17 Mrs.irangani, 42/4 walls lane, Water leakage at walls lane. water leak repaired with 19.08.2017 water leak repair supervision was modara, colombo 15. the support of the O&M done by the PIU EA Mr.Rohana staff of NWSDB contractor labors also attended to work,

31 2017.08.18 Mr.udaya kumara, 162/370 A, Water leakage at the side of Issue rectified by the 2017.08.19 kibula ela colombo15. the house connection. contractor's labors.

32 2017.08.18 Mr.C.P.daniel, requesting of pipe laying Informed to contractor stop 2017.08.18 Temporary reinstatement work, No,11,sumithrarama work stop on 19th Aug work at sumithraram MW site cleaning works machinery MW.Colombo 13, 011 2394309 2017 at night time 19th Aug 2017 at night transport work done by the sierra sumithraram MW time. on19th Aug 2017 sociologist personally attended to supervise the work.

vi

Social Safeguard Annual Monitoring Report - 2017 33 2017.08.29 Mr.sundareswaram, no 40, dust generated due to pipe Visited to location with 2017.08.29 Temporary reinstatement done by kotahena street, laying activities contractor's Eng., and the contractor on 28th Aug kotahena.colombo 13. advice to clean the road at 2015.but advice to saeap the road 0773850841 night time. again.

34 2017.08.29 mr. selvaraj, 162/375, Back filling work not done Advice to rectify the issue 2017.08.29 site visit done with contractor Rd,colombo 15, properly. immediately sub- Eng.’s , sub-contractor(relevant) 072 6800678 contractor stored the work gave contract number to informed just after the site weather issue rectified or not inspection.

35 2017.08.30 mr. Alhaj jaufer no.25/2/B, Water leakage in front of Visited to location out wet 2017.09.08 kalyanigangarama the house. the resident informed to MW.(Aliwatta) colombo 15. contractor (relevant 0777937681 Engineer) to rectify the issue.

36 2017.08.30 Mrs.K.V. chithra ramani , no Objection of replacing PVC PM (CN), sociologist, EA, 2017.09.17 Due to the requirement of the 88/2, mattakkuliya church road, house connection line due visited to site and met both project more than 30 years 3/4 colombo 15, to the pending land case in parties, complainer agreed inch line replaced. the district court Colombo. to allow the trail trench. To trace the live after tracing the existing line, near PE line laid along the same rout.

37 2017.09.15 Mr.T.H.Karunarathna, New PE line and water Site visit was done by the Took time to get the consent 88/6,Wsala Rd. transferring work not done project team and wrote a from the CMC kotahena.colombo13, by the project due to the letter to CMC to excavate 0773279670 road asphalted by the CMC the ready laid asphalt area requested lay new pipe line to lay the PE line and by our a lifter. water transferring work.

38 2017.09.18 Mr.fazeel, No 47,Bluemandal storm water line blocked had a site visit with the 2017.09.18 Attended to rectify the issue Rd, colombo 13, 0777487677 due to the project activity project manager 2017.09.27 several time by contractor but therefore storm water (NWSDB),DPM (sierra) 2017.09.29 unable to rectify the issue collect in front of the his and instructed to sierra permanently several complain shop (timber) DPM to rectify the issue made by Mr.fazeel on this water. immediately (3 lines However contractor could able to attended to rectify the issue give the permanent reinstatement permanently) on this area.

39 2017.09.28 Mrs.A.H.S. gunawardane, 32/5, Tapping T was not fixed Informed to responsible 2017.10.01 St, mary's school lane, colombo due to the she was not at the officer of house connection 15, 0775727299 home when the water transferring and also the transferring period. massage passed to sierra house connection transferring team.

40 2017.10.11 Mr.Ramzan, 356, Modara Surface Water fall in to the a team deployed to back 2017.10.11 Street, Colombo 15. nearly created hole in the fill the hole site visit had 0777946644 waddle of the nearly laid with the Mr. lea (Sierra) pipe line regarding this matter

viii

Social Safeguard Annual Monitoring Report - 2017 41 2017.10.17 Mr.Berti.76 Garden, st. james Requesting of expedite the site visit had with relevant 2017.10.23 project manager of Colombo street, Colombo 15 071060681 pipe laying work due to the DMA responsible North also visited the site 0752265376 interlocking project has Engineers of NWSDB and passed for the by roads Contractor and advice to expedite the work

42 2017.10.30 Mr.Latis Moosa, No. 264, Drainage line relocked due visited to location on 30th 2017.10.27 Complain received from CMC on Modara street. Colombo 15 to the pipe laying activates Oct 2017 but at the time of by CMC 30th Oct 2017 (Drainage 0775599464 visiting the location issue Division) was rectified by the CMC on 27 th Oct 2017

43 2017.11.04 218, Vystwike Road , Colombo Saner line damage a team deployed to rectify 2017.11.05 Supervised by the contractor side 15 077346110 0112525911 the issue engineer Mr. Teran

44 2017.11.05 Mr.Janfer, 25/2 B, Aliawatta, Water leakage has stored in A team engage to rectify 2017.11.05 Colombo 15 0777936781 front of the house the issue

45 2017.11.09 Mr. Amitha , Maintenance Water line damage and no repair was done by the 2017.11.08 confirmed by giving a phone call Manager, Upali News Paper . Water supply form 3 days NWSDB O&M team either to Mr. Amitha 0777396281 ago support of the Contractors workers

46 2017.11.16 Mr.sundereshaamam, No 14, No Temporary Reinstatement visited to location and 2017.11.16 14. Kotahena Street, not done properly and dust agreed to do the COLOMBO 13 generation reinstatement on the 16 th 077773850841 November 2017 night

47 2017.11.27 Mr.Rohana Mendis, 27, Drainage line damage due a team deployed to repair 2017.11.28 Confirmed by sierra Engineer Mr. Bluemandhal Road, Colombo to the pipe laying activates the damaged line Praneeth 13 0779792968

Annexure 06

Received complaints for 2017 –Package II

Complainer Location Incident Execution S/ Entered Date Remarks N By Address/Pho Supervised Attend Date Name ne Road Location Utilities / Type Details by ed by Time Sri Jayawardena Damage during REPAIR 1 25/02/2017 25/02/2017 Jawahir Dinal pura 50mm water line excavation Sumith Isuru CORRECTED Damage during 2 25/02/2017 25/02/2017 Jawahir Wasantha Kalaimagal Street Police station CEB cable excavation Wasantha CEB 17.3 10,Rodney Damage during REPAIR 3 27/02/2017 23/02/2017 Dinal Dinal Place Rodney Place #10 house 20 mm water line excavation Dinal Finite 1.00 PM CORRECTED Madushan Damage during soil Recomplaint/alredy 4 27/02/2017 23/02/2017 ka Mr.Rohan 763600487 Bauddaloka mw 410 waththa SLT transport Nabrees SLT 13.3 attended Damage during REPAIR 5 28/02/2017 27/02/2017 Dinal Dinal House 25 mm water line excavation Sumith Kolon 0.73 CORRECTED 01/013/201 6 01/03/2017 Madushan Mr. Tickel road sudden apper of no identification of ka Samitha AE Cotta road junction water damage Sumith ONM 7 11.00 am type of damage 100 ci was damage rectified the leak by 7 01/03/2017 03/01/2017 ilyas ilyas rosmead place 0+095.55 water during exc. ilyas O & M 2.00 a.m o&m Damage during REPAIR 8 02/03/2017 01.03.2017 wasantha wasantha parisara mawatha 0+082 water 50mm PVC excavation Rajitha O & M 16.00 pm CORRECTED Madushan 9 03/03/2017 ka Raj 773403267 410 waththa No: 20 Bad reinstatement no vehicle access Damage during 10 06/03/2017 tiral tiral kirula rd CEB cable excavation tiral CEB Completed the requested roads 11 06/03/2017 06/03/2017 Mr Lesly Ranagala Wanathamull Reinstatement to close to the ground Jawahir Kuruppu 777761963 Mw, Kuruppu rd a ground Road rectify Madusanka Kolon 10.00am by 11th march Removed blance Qurreydust and 12 08/03/2017 08/03/2017 Mr Roy dumbing material & ABC after Dust Jawahir Antony 772245427 Rosmead Avenue No:02 dust Sumith Kolon 2.00 pm contralling Temporary connected 13 09/03/2017 09/03/2017 (10/03/2017 Ruhunukala Cotta road Damage during permanently Dinal Dinal mawatha junction 110 mm upvc excavations Dinal Finite 4.15 am repaired the line) Near Bawa Damage during REPAIR 14 09/03/2017 Dinal Dinal Cotta road Place CEB line excavations Dinal Finite CORRECTED

15 09/03/2017 Area By Lane Leak after connecting 09/03/2017 12:15 Jawahir Samitha Engineer Lake Drive Juncion 90mm PVC line with new Line Sumith Kolon noon Leak Rectified

16 09/03/2017 ilyas ilyas barnes road 0+188.6 Rhs ceb line Damage during ilyas ceb 09/03/2017 12.3 Temporary x

Social Safeguard Annual Monitoring Report - 2017 excavations connected

Damage during 17 09/03/2017 09/03/2017 ilyas ilyas rosmead place 0+112 lhs 100 c.i excavations ilyas kolan rectified by kolan Damage during REPAIR 18 10/03/2017 11.3.2017 wasantha wasantha Barnes road 0+166 RHS 63mm PVC excavations wasantha Kolon 11 CORRECTED Damage during REPAIR 19 10/03/2017 12.3.2017 wasantha wasantha Barnes road 0+313 RHS 4" CI excavations wasantha O & M 2.03am CORRECTED

Mr Jayantha 20 11/03/2017 12/03/2017 Kuruppu, Weerasekara mw Reinstatement to Reinstatement Jawahir CMC 777761963 Road rectify Aqeel Kolon 0.21 rectified Damage during REPAIR 21 14/03/2017 14/03/2017 wasantha wasantha parisara mw 63mm pvc water excavation wasantha kolon 16.3 CORRECTED Damag e Damage during REPAIR 22 15/03/2017 wasantha wasantha Jothipala by rd 32mmpvc warer wasantha during 15.3.2017 20 excavation CORRECTED excavat ion Bowser water supplied, service 23 16/03/2017 18/03/2017 connection ferrule Area 100/1, Rosmead Rosan Block after damage Aqeel, Kolon, point shifted, meter Jawahir Samitha Engineer place Mahanama hs service line repair Sumith O&M 13:30 pm replaced

24 16/03/2017 Damage during Aqeel, 17.6.2017 REPAIR wasantha wsantha barnc,place 1/2, pvc excavation Sumith kolon 9.30Am CORRECTED

25 16/03/2017 tiral mangala parth 32mm compacting t-trench tiral o&m No water to customer 26 18/03/2017 Area Engineers after activation of new 18/03/2017 New line connected Jawahir Samitha Engineer Lake Drive house line Sumith Kolon 7.00 pm to existing line Closed valve at new 27 18/03/2017 Area No water from 18/03/2017 connection poit Jawahir Samitha Engineer Lake Drive Royal Park 160mm PVC yesterday Sumith Kolon 14:00 pm openend back damaged during 28 18/03/2017 Jawahir Rajitha Ramya Place CEB cable excavation Rajitha CEB damaged during REPAIR 29 18/03/2017 18/03/2017 Jawahir Sumith Branded place CEB cable excavation Sumith CEB 6.00pm CORRECTED Repaired, But the incident went upto 30 19/03/2017 19/03/2017 AGM level by Isuru Jayawardenapura 63mm PVC water damaged during (Charitha Jawahir Kapuruge AGM(O&M) road By road? line excavation Tiral Kolon 0.08 0774597663) Parisara Mw by damaged during REPAIR 31 20/03/2017 20/03/2017 wasantha Wasantha Rd CeB cable excavation Wasantha CEB 16.10Pm CORRECTED damaged during REPAIR 32 21/03/2017 22/03/2017 wasantha Wasantha Ramya Place RHS 0+025.2 SLT excavation Wasantha SLT 17 CORRECTED

Mr. erlier dmaged/ 33 21/03/2017 Madushan amarasingh Maning town incomplete ka e 714909060 MangLA PATH f;lats Swerage rectification Nabrees Kolon pending repair Reapair done by 34 24/03/2017 Madushan Madushank clarge cavity under the 24/03/2014 Kolon for the sake ka a Madushanka Kuruppu road Kuruppu road CMC road Malaka CMC 10.40 am of CMC MangLA damaged during REPAIR 35 24/03/2017 24/03/2014 Sumith Sumith MangLA PATH PATH 40 mm dia water excavation Sumith O&M 16.3 CORRECTED damaged during 36 24/03/2017 24/03/2017 wawantha wasantha Barnce place Rhs 0+70 2" pvc pipe excavation wasantha kolon 24 reparied damaged during REPAIR 37 24/03/2017 wasantha wasantha barnce place RHS 0+75 ceb cable excavation wasantha ceb CORRECTED Reapair done by 38 25/03/2017 Sumith / Kolon for the sake Jawahir Kuruppu CMC Kuruppu road Road damage Cavity in trench Madusanka Kolon of CMC damaged during REPAIR 39 26/03/2017 Dinal Dinal HR Jothipala mw B19 Flat SLT Cable excavation Dinal SLT CORRECTED damaged during REPAIR 40 27/03/2017 29.3.2017 Dinal Dinal Ramya Place SLT excavation Dinal SLT 17 CORRECTED damaged during 41 27/03/2017 tiral SLT ja milton petera excavation

Kynsey to Kolon 42 27/03/2017 27/03/2017 Mr.Swamin No.125, Rosmed Place Eng.Pa Nabrees adan Rosmed Place Rosmed Place Entrace Water Leakes Water Leaks Nabrees dmasiri Repair Corrected damaged during REPAIR 43 28.3.2017 29.03.2017 wasantha wasantha HR Jothipala mw SLT Cable excavation Chaminda SLT 16.3 CORRECTED

44 04/04/2017 Mr Reinstatement to Madushank 07/04/2017 Jawahir Kuruppu CMC Kuruppu road Kuruppu road road reinstatement rectify a Kolon 16.3 completed damaged during REPAIR 45 05/04/2017 5.4.2017 wsantha wasantha Rana mw by rd water 63mm,pvc excavation wasantha kolon 12 CORRECTED In front Of 46 04/06/2017 Survey damaged during Rajitha Rajitha CMC Kirula Rd Department excavation Rajitha Kolon O&M, Dumping debris to 47 05/05/2017 Jawahir Mr Samitha NWSDB Fairfield garden No: 47 clean Ajith The complaint belongs to CMC 48 05/05/2017 05/04/2017 drainage division & 14, 16 Danyal informed Jawahir Kirula road avenue opened trench can't access home Tiral 0.85 accordingly Nearby 49 05/05/2017 Kuwait During Yesterday pipe 06/04/2017 REPAIR Sumith Sumith Rosmead place Embassy Water line laying Sumith kolon 1.00am CORRECTED

50 06/04/2017 JA Milton Perera Near HR damaged during 06/04/2017 temporary line Dinal Dinal Mw Jothipala mw CEB Cable excavation Dinal CEB 0.02 given

xii

Social Safeguard Annual Monitoring Report - 2017 near 51 06/04/2017 srijayawardane modelfarm damaged during 06/04/2017 ilyas ilyas road junc. wmain excavation ilyas o&M 4

52 17/04/2017 Madushan Rathwathth srijayawardane opposite of ka a 113056931 road tickel road Settlement Access matter Aqeel

53 22/04/2017 darmasiri gamage damaged during 22.4.2017 REPAIR wasantha wasantha by rd B 36 Flat 32mm pvc pipe excavation wasantha kolon 13 CORRECTED damaged during NWSD REPAIR 54 25/04/2017 25.4.2018 wasantha wasantha Rana mw by rd N Flat 110 Pvc excavation wasantha B 13 CORRECTED damaged during 55 25/04/2017 26.4.2017 wasantha wasantha HR Jothipala mw 63mm Pvc excavation wasantha kolon 16 darmasiri gamage damaged during 56 26/04/2017 26.4.2017 wasantha wasantha by rd 32mm pvc excavation wasantha Kolon 17 In front of the 57 26/04/2017 meuceas damaged during 26/04/2017 REPAIR Chaminda Chaminda NWSDB Rosmed plase college 40 mm ci excavation Chaminda CMC 10.3 CORRECTED

58 28/04/2017 In front of the damaged during Sumith Sumith Rosmed plase No 94 Hose CEB excavation Sumith CEB In front of the 59 28/04/2017 No 103A damaged during Sumith Sumith Rosmed plase Hose CEB excavation Sumith CEB

60 29/04/2017 In front of the damaged during 06/05/2017 REPAIR Sumith Sumith Rosmed plase No 59 Hose CEB excavation Sumith Ceb CORRECTED infront of no damaged during 61 04/05/2017 ilyas ilyas ceb barnes pla 31 ceb excavation sumith CEB infront of damaged during 62 07/05/2017 ilyas ilyas slt ramya by road B22/G1 slt excavation ilyas JA Milton Perera infront of damaged during 63 08/05/2017 8.5.2017 wSnth ilyas Mw 225A Water line excavation Ajith Kolon

64 08/05/2017 In front of no Sumith Sumith Water Mangala path house Water line During backfilling Kolon

65 15/06/2017 Madushan Weerasingh Kolon, 15/06/2017 ka e 773937247 mangalapath BS/G/12 no water no water Sumith ONM 16 damaged during 66 17/05/2017 Chaminda Chaminda Banse plase 0+327 Lhs CEB Cable excavation Chaminda CEB cable Damage when 67 27/05/2017 Chaminda Chaminda Milton perere mw damage excavation Chaminda

68 2.3

69 30/05/2017 Madushan Mr. 155/8 castle pressure testing pit ka Kuruppu 772753974 Castle str street entrance blocked pressure testing pit Illiyas backfilled and ok Near Asiri damaged during 70 31/05/2017 Dinal Dinal Kirula Road hospital CEB cable excavation Dinal CEB repair work done

Damaged from the 71 31/05/2017 Near Asiri Dinal Dinal Kirula Road hospital 32mm water line ferrule during exc. Dinal O & M repair work done

72 06/06/2017 JA Milton Perera in front of damaged during chaminda chaminda Mw Ramya plase CEB cable excavation Chaminda CEB

73 07/06/2017 In front of damaged during 09/06/2016 Sumith Sumith Kirula Road Asiri Hospital Dialog cable excavation Dialog

74 11/06/2017 In front of damaged during Sumith Sumith Kirula Road Asiri Hospital CEB cable excavation CEB Srijayawardane 30B-TT- damaged during 75 13/06/2017 ilyas ilyas wmain road D2(P) Water excavation ilyas Informed to O &M Near 410/6 damaged during 76 14/06/2017 14/06/2027 Sumith Sumith 410 watta house CEB cable excavation Sumith CEB 16 repair done by CEB Near damaged during 77 15/06/2017 housings excavation Sumith Sumith Boosewana road schame CEB cable Arunachelam damaged during 78 15/06/2017 16/06/2017 Sumith Sumith avanue Near 6 house CEB cable excavation Sumith CEB 11 repair done by CEB F/main 225- damaged during repair done by 79 21/06/2017 20/06/2017 ilyas ilyas wmain J.A.Milton 160 Water excavation ilyas water waterboard H.R jotipala by damaged during repair done by 80 21/06/2017 20/06/2017 ilyas ilyas wmain road 27A-57-67 Water excavation ilyas water waterboard damaged during 81 22/06/2017 27AD-66- 23/06/2017 wasantha wasantha B-9 Flat Ramay Place LHS 27AD-67 CEB cable excavation wasantha CEB 12 repair done by CEB damaged during 82 24/06/2017 24.6.2017 wasantha wasantha Rana mw By rd L-Flat 60mm Pvc Pipe excavation wasantha Water 15.3

Former Airwise Kolon / 83 02/07/2017 Jawahir Cotta road Cotta road drainage Drainage block Sathheek marshal CMC Fernando

damaged during 84 01/07/2017 Hortan place by 01/07/2017 ilyas ilyas road 07A-07B 63mm pvc excavation ilyas water 715 kolan repaired removed material Unloaded abc on the 85 02/07/2017 Sewer Chamber 02/07/2017 apart of chamber chamber ilyas Cotta road 129/7 blocked ilyas Kolan 9.3 balance to be done damaged during water 86 06/07/2017 6.7.2017 wasantha wasantha kirula rd 63mm pvc excavation wasantha board 1 11.00 am Sampath RDA, close to Madushank Backfilling and 87 10/07/2017 Jawahir Cotta road road pot holes Kolon 07/10/2017 up to (EA) Gothami road a repair night Mallika Mr 88 10/07/2017 Jawahir Hemachandra Horton place 73?? plants pipe stacked over Aqeel Kuruppu Jewelleries

xiv

Social Safeguard Annual Monitoring Report - 2017 Metland 89 10/07/2017 Madushan Thilaka 15/3 chandrawankya 15/3 colombo ka Padmini Colombo7 mw 7 water pipe HH connection Aqeel 18D22-25 damaged during 90 07/12/2017 chaminda chaminda Banes Place (LHS) CEB cable excavation damaged during 91 13/07/2017 13.7.2017 wasantha wasantha Rana mw By rd 63mm Water excavation wasantha Kolon 10.45

92 14/07/2017 Pradeepa mw damaged during 7-14-2017 ilyas ilyas 400 crossing Preadeepa mw TT 68-R2 90mm water excavation ilyas Kolon 11 complete by kolon 12/76 ABC Filling and 93 17/07/2017 Madushan 12/76 Manning Manning Road damage 17/07/2017 Compaction by ka Nelka 770349099 town town Road damage Sumith Kolon 15 Kolon Material removed 94 17/07/2017 Mrs 71&72, no reinstateent, 18/07/2017 Jawahir Fernando 112699016 Horton place Hortonplace Road damage material stocked Aqeel Kolon 9.30 Am and road cleaning Madushank 19/20-07- 95 17/07/2017 Jawahir raod damage no reinstateent a KGC 17 night done damaged during water 96 18/07/2017 19.07.2017 Wasantha Wasantha J A Miltan Perera 50mm pvc pipe excavation board damaged during 97 22/07/2017 RG Senanayake 23/07/2017 Sumith Sumith mv by road 52/4 house House connection excavation Sumith Kolon 10.00 Am complete by kolon

Mrs. KGC.T To be 98 24/07/2017 Madushan dharmarath 714334661/0 Madushank hamel/ rectified pending reply from ka na 112686213 Castle street No: 91 Wall damage During pipe laying a Aashik KGC Madushank 99 24/07/207 Jawahir PD 772442044 Matha Road Matha Road Road Reinstatement a KGC is not attendig Madushan CEB cable 100 24/07/2017 ka Mr. Ahmed Horton terras horton teras Horton teras damage while excavation Aqeel Rosmead CEB cable 101 03/08/2017 Wasantha Wasantha Place Rosmead place damage while excavation wasantha O&M 102 24/07/2017 Mr.Madush Divisio 06/08/2017 Dinal anka Gothami Road No 11 1" upvc water line while excavation Dinal n 9 Done

103 24/07/2017 RG Senanayake 06/08/2017 Dinal Dinal By road CEB Cable while excavation Dinal CEB 0.48 Done

104 24/07/2017 106/4 Horton 106/4 Horton 08/08/2017 sumith Sumith place Horton place place CEB Cable while excavation Sumith CEB 16.3 Done pradeepa mw (infront of 400pe 105 24/07/2017 ilyas ilyas pradeepa mw ceb cable while excavation ilyas crossing maligawatte place

106 11/08/2017 Wasantha Wasantha J A Miltan Perera 160mm water damaged during wasantha water 11.8.2017 13.30pm Done by water

excavation Board board

damaged during 107 14/08/2017 14.8.2017 Wasantha Wasantha Melwata rd 63mm water excavation wasantha 18.3 Done by kolon Temporaly 108 15/08/2017 R G Senanayake 15.8.2017 Connection given sumith sumith 71/3 mv by road No 71 ceb cable while excavation Sumith CEB 16.3 by CEB

109 18/08/2017 Wasantha Wasantha 6 watta 40mm waer while excavation wasantha kolon 18.8.2017 13.30pm Done by kolon Close to Agreed to 110 22/08/2017 Madushan Priyadarsha CMC District Jayarathna Reinstatement to Kolon complete/Mr. ka na 4 office Bauddaloka Mw Florist be done Cold mix Aasshik Kolon Aashik

111 25/08/2017 71 Roamed Near 71 25/08/2017 sumith sumith place Rosmead place house 1" pvc Water wile backfilling Kolon Kolon 16 Done by kolon damaged during 112 25/08/2018 Kynsey road Kynsey road by 25/08/2017 sumith sumith by road road CEB cable backfilling Kolon CEB 24 damaged during 113 25/08/2018 Parisara mw Wasantha Wasantha 280mm Line CEB cable excavation Kolon CEB

114 28/08/2017 Heapup of Stone & Madus Jawahir 112323710 Ohlums Place quarrydust Kolon hanka Madus 115 28/08/2017 155/8, Castle anka/ Jawahir Kuruppu 772753974 Street, Co-8 No: 155/8, Open pit Kolon Aqeel damaged during wasant 116 02/09/2017 02/09/2017 Wasantha Bance place 32mm woter backfilling Kolon ha 23.30pm Done by NWSDB 97/3, rosmead 117 07/09/2017 07/09/2017 jawahir rosmead place place 97/3 road reinstatement kolon sumith 14.1 Done by kolon CEB slab removed, conduits filled with 118 07/09/2017 water due to water line Indika, EE Bauddaloka repair. pipe laid over Mdusa jawahir CEB mw Bauddaloka mw CEB cable CEB trench nka

119 11/09/2017 Area Horton place by Damage/Blockge 11/09/2017 Sumith Engineer Horton place road 106/4 Drain drainage Systems Kolon Sumith 13.3 Done by kolon Mr 120 11/09/2017 Rothitha Austing place by Reinstatement to 11/9/0201 Sumith Freanando Austing Place road 16/A be done Cold mix kolon Sumith 21 Done by kolon

121 12/09/2017 House Horton place by Hose Gate Gate Damage during 12/09/2027 106/4 Horton place road 106/4 Damage excavation kolon Sumith 13.3 Done by kolon Debrit not Ms Kumari removed after Debrit not removed 122 15/09/2017 Hatharasing Completion of after Completion of Rajitha he RIT Alas RIT Alas work work kolon cover plate moved 123 15/09/2017 Jawahir Mr Perera 723079178 Rosmead Place 35/2 Open Trench away Aqeel xvi

Social Safeguard Annual Monitoring Report - 2017 R.G. R.G. Senanayake damaged during 124 23/09/2017 Sumith Sumith Senanayake CEB cable Sumith CEB 23/09/2017 11.3 Done by CEB mv by road excavation mv by road sri damaged during 125 04/10/2017 darmaram sridarma rama mw 04/10/2017 excavation ilyas mw 0+315 wmain 110mm ilyas dinal 6.3 done by nwsdb damaged during 126 04/10/2017 r.g ilyas senenayake r.g.senenayake CEB cable excavation ilyas Near No 1 damaged during 127 10/10/2017 Kaundhi Castle avanue house 2" GI pipe water excavation sri damaged during 128 13/10/2017 ilyas darmarama 110pvc ilyas ilyas 13/10/2017 8.3 done by nwsdb excavation road damaged during 129 18/10/2017 wasantha wasantha Ward Place CEB cable excavation wasantha damaged during 130 18/10/2017 RG Senanayake Near #69 & Kamal(TO- Dinal Dinal Road #71 CEB cable excavation KGC) Done by CEB

no 67B, Mr. Gihan no 67B, Madushan Gregories 131 23/10/2017 alagiyawan Gregories road Gregories No Water No water Aqeel kolon 14/10/2017 2.30Am Done by contractor ka road, Col 7/ na road, Col 7 0777440436

Near food damaged during 132 23/10/2017 Sumith Word place 100 CI line Sumith O&m 14/10/2017 4.30Am Done by O&M city excavation Kolon Inform to No 114/6 Road damage Inter House Holder 133 25/10/2017 Sumith PD Horton Place 114/6 House Road Sumith kolon 26/10/2017 9.30 Am Horton place lock Immediatly rectify the Interlocking. RIT alles Lohan Damage with Pot 134 02/11/2017 Jawahir Mw, RIT Alles Mw Road Damage Madusanka Kolon 0911-2017 8.3 Asphal the Road Rajapaksha holes 0711932226 Mr Lalith Barnes place Barnes Place By 108/1, Damage in Kolon Eng say not 135 07/11/2017 Jawahir Hettiarachc Road damage Aqeel Kolon 10/11/2017 10 No: 108/1.. road 108/2...... reinstatement they fault hi Chamber cover to Saloon Saloon, Settlement of road, 136 07/11/2017 Jawahir Barnes Place Park end CMC culvert Aqeel Kolon 08/11/2017 22 be romove informe Owner 0766216622 MS plated to CMC Kamal Senior Project Cotta Jn, improper maintenance 137 07/11/2017 Jawahir Dajhanayak Gothami Road Road damage Jawahir Kolon 14/11/2017 Report sent to ADB Officer, ADB Gothami rd of road a damaged during 138 10/11/2017 wasantha wasantha Maligawatta place 90Pvc water Dulan Kolon 10.11.2017 5.00Am Repaied by Kolon excavation 139 10/11/2017 wasantha wasantha Maligawatta place CEB Dulan CEB 10.11.2017

Eng. Mr priyantha One Lady Bauddaloka From Cotta Repeating pot holes & 140 13/11/2014 Jawahir Buuddaloka Mw Road damage Madusanka W/B agreed to do the Dr Mw Railway dust reinstatement. DS RG Senanayaka 141 14/11/2014 wasantha senanayaka 4 CI Pipe wasantha W/B 14.11.2017 mw College Rohitha Austin Place, Damage in 142 14/11/2014 Jawahir 717265899 16/A, 16/1 Road damage Aqeel kolon 16/11/2017 13 Repaied by Kolon Fernando reinstatement

no.80 Ward Agreed rectify it. 143 15/11/2017 Aqeel Gunsekara place/077768 Ward Place no.80 Property Damage Fence Aqeel Koln 15.11.17 15.3 agreed by both 5385 parties Sri darmarama damaged during 144 27/11/2017 wasantha 110pvc water wasantha kolon 28.11.2017 8.30am Repaied by Kolon mw excavation No water due to valve Valve replaced by 145 30/11/2017 Jawahir DGM(WC) RSC(WC) Manning Town D/7/3/1/ Valve closure Nabrees Kolon 30.11.2017 4.00pm closure Kolon Open pit with cover Pressure test poit pit 146 01/12/2017 Jawahir Police Kurunduwatta Thurstan Road 5th Lane Jn Pit Madusanka Kolon 02.12.2017 11.00am plate (setteled) backfilled

AE(Maliga Leak repaired by 147 02/12/2017 Jawahir Maligakanda Manning Town Leak Customer meter leak sumith O&M 02.12.2017 12.00noon watte) O&M, NWSDB Bridge Lake Graden 148 04/12/2017 Sumith Miss Perera Lake Drive embankment sumith Informe to O&M 0012693515 Damage damaged during 149 04/13/2017 kaundhi Mangalapath Mangalapath 69/12 90 pvc water excavation for house kaundhi Kolon 05/12/2017 2.45 pm Repaied by Kolon connection CEB T.LIN Sri darmarama 150 05/12/2017 ILYAS 0+080.8 CEB DAMAGE ILYAS E 05/12/2017 temp. rectify by ceb mw GIVE N sewer Sri darmarama while exca. wall 151 05/12/2017 ILYAS 0+080.8 sewer chamber DAMAGE ILYAS chamb 05/12/2017 mw damage er damaged during 1/42, horton 152 08/12/2017 kaundhi Horton place 18D 5- 115 Ferrule excavation for house kaundhi Kolon 08/12/2017 place connection damaged during 153 13/12/2017 kaundhi Mangalapath Mangalapath Dec-82 1/2" pvc Kolon 13/12/2017 backfilling RG Senanayaka damaged during 154 21/12/2017 wasantha CEB cable wasantha mw excavation sri damma road in frout Sri darmarama damaged during 155 26/12/2018 sarath 4'' pvc sarath kolon 26/12/2017 of garment mw excavation factory

xviii