Orange Water and Sewer Authority

Total Page:16

File Type:pdf, Size:1020Kb

Orange Water and Sewer Authority

Orange Water and Sewer Authority 3rd Party Project Asset Valuation

Project Date Location Developer Engineer Gen. Contractor Utility Contractor

Water Mains Owned by OWASA (does not include Private Fire Suppression Lines) Pipe Size 2” 4” 6” 8” 12” 16” Other Pipe Material Copper DIP DIP DIP DIP DIP DIP Linear Feet

Fire Hydrants Privately Owned Fire Suppression Lines No. of Hydrants Private Fire Suppression 2.5” 4” 6” 8” Installed Number of each

Water Services Owned by OWASA (up to and including the meter) Water Meter Size 5/8”x3/4” 1” 1-1/2” 2” 3” 4” 6” 8” No. of each

Total Cost Water Assets (not including private fire suppression lines) $

Sewer Mains Owned by OWASA (does not include sewer laterals) Pump Sta. Force Main Pipe Size 8” 12” 16” Other Pipe Size Pipe Material Pipe Material Linear Feet Linear Feet

Privately Owned Sanitary Sewer Laterals Pipe Size No. of 4” No. of 6” No. of 8” Other No. Sewer Laterals

Sewer Manholes (owned by OWASA) Manhole Diameter 4’ Diameter 5’ Diameter 6’ Diameter Other Number of each

Total Cost of Sewer Assets (not including pump station) $ Total Cost of Pump Station and Force Main $

Reuse Water Mains (owned and maintained by OWASA) Pipe Size 6” 8” 12” 16” 24” Other ____ Pipe material DIP DIP DIP DIP DIP DIP Linear Feet

Reuse Services Owned by OWASA (up to and including the meter) Water Meter Size 5/8” 1” 1-1/2” 2” 3” 4” 6” 8” No. of each

Total Cost of Reuse Assets $

Additional Information:

(Engineer’s Seal & Signature)