API RP 575 Inspection of Tanks
May 8, 2017 10:30am to 11:00am, Las Vegas
John Scott, LyondellBasell Industries, Study group Chair
Study Group Agenda:
Discuss Study Group approach
Reaffirm?
Minor changes?
Need Master Editor?
Meeting Notes:
Discussed the know issues with the current document to determine the pathforward. There are currently no score card issues other than a note to recheck the new material added related in the last edition related to LPG tanks. The following items were discussed as areas needing improvement:
Tank floor chime sealing issue
Normative references
Definition consistency/Acronyms
Refrigerated tank score card item
Should/shall review
Sync with 653 minor changes
This list preliminary list was deemed sufficient to require a Task Group and Mater Editor to update the document.
It was required that we have an SCAST Vice Chair – Nelson Acosta volunteered.
An SR3 form has been submitted for Master Editor (post meeting)
Pathforward for next meeting in Dallas:
1. Hope to have a Master Editor assigned by then
2. Will request input for more specific score card items from SCI and SCAST
3. Will Schedule a Task group meeting at the fall meeting in Dallas to begin pulling together issues for the Master Editor to work on