Work Instruction Functional Area: Project Systems Run Plan Comparison Report

Purpose Project Systems Overview and Reporting - Project Creation and Management

Use this procedure to run a report that displays the actual cost, commitments, and planned amounts for specified WBS elements.

Trigger

Perform this procedure when you need to compare the actual costs and commitments to a specific plan version.

Prerequisites

The WBS element must exist in the system for which a report is generated.

Menu Path

Use the following menu path to begin this transaction:

 Select Information Systems Project System Financials Costs Plan-Based By Cost Element Actual/Commitment/Total/Plan in CO Area Currency to go to the Actual/Comm/Total/Plan in COAr Crcy: Selection screen.

Transaction Code

S_ALR_87013542

Helpful Hints

 This report can be exported to a local file or printed and then sent to a Project Manager if there are requests for this information.  The report displays a breakdown of commitments by purchase requisitions, purchase orders, and funds reservation.  The R/O/C column in the field description tables below defines whether the field is required (R), optional (O), or conditional (C).  On certain screens you may have to scroll to view some data entry fields. Work Instruction Functional Area: Project Systems Run Plan Comparison Report

Procedure

1. Start the transaction using the menu path or transaction code.

2. Perform one of the following: If the Enter profile window Go To Appears Step 3 Does not appear Step 5

Enter profile

3. As required, complete/review the following fields:

Field R/O/C Description

Database prof. Required Key identifying a profile for selecting data from the database; This is the Project information system profile. Example: 000000000001

4. Click .

06_PS_S_ALR_87013542_Run Plan 11/17/2017 CompariReport_0_ProjectSystems_02.udc 2/12 Ver: © University of Cincinnati Work Instruction Functional Area: Project Systems Run Plan Comparison Report

Actual/Comm/Total/Plan in COAr Crcy: Selection

5. As required, complete/review the following fields:

Field R/O/C Description

WBS Element Required Work Breakdown Structure Element Example: 98052A10

Enter the WBS element or range of WBS elements that you wish to group or choose them from the dropdown box. The wildcard character * can be used as well to select all WBS elements.

06_PS_S_ALR_87013542_Run Plan 11/17/2017 CompariReport_0_ProjectSystems_02.udc 3/12 Ver: © University of Cincinnati Work Instruction Functional Area: Project Systems Run Plan Comparison Report

Field R/O/C Description

Unlabeled field (to the Optional This is the WBS Element to field right of the WBS Element field) Example: 98052A40

Use this field to enter a range of WBS elements. Click to select multiple WBS elements. If wildcard was used, this field can be left blank.

Controlling Area Required Self-contained organizational unit for cost accounting Example: UC

Plan Version Required Contains a one or two alphanumeric key that differentiates between scenarios in an organizational plan Example: 0

Enter the plan version for this project. This field defaults with 0.

From Fiscal Year Required Beginning value to be entered when specifying a range of fiscal years Example: 2002

Enter the beginning fiscal year for the range of years you wish to display.

To Fiscal Year Required Ending value to be entered when specifying a range of fiscal years Example: 2005

Enter the ending fiscal year for the range of years you wish to display.

From Period Required Beginning value to be entered when specifying a range Example: 1

Enter the beginning period for the range of periods you wish to display.

06_PS_S_ALR_87013542_Run Plan 11/17/2017 CompariReport_0_ProjectSystems_02.udc 4/12 Ver: © University of Cincinnati Work Instruction Functional Area: Project Systems Run Plan Comparison Report

Field R/O/C Description

To Period Required Ending value to be entered when specifying range Example: 12

Enter the ending period for the range of periods you wish to display.

6. Click .

Act/Com/Total/Plan

7. Review the displayed information.

You must use the scroll bars to view all fields.

06_PS_S_ALR_87013542_Run Plan 11/17/2017 CompariReport_0_ProjectSystems_02.udc 5/12 Ver: © University of Cincinnati Work Instruction Functional Area: Project Systems Run Plan Comparison Report

8. Perform one of the following: If You Want To Then Go To Click on the project or WBS element in the View project details Variation: Object section for which you Step 9 want to view details.

Exit this transaction Click . Step 18

Act/Com/Total/Plan (2)

9. Review the displayed information.

The screen and fields displayed will vary according to your selection in Step 8.

10. Perform one of the following:

06_PS_S_ALR_87013542_Run Plan 11/17/2017 CompariReport_0_ProjectSystems_02.udc 6/12 Ver: © University of Cincinnati Work Instruction Functional Area: Project Systems Run Plan Comparison Report

If You Want To Then Go To Double-click the displayed value for which View additional details Step 11 you want to view details.

Exit this transaction Click . Step 18

Display Actual Cost Line Items for Projects

11. Review the displayed information.

The screen and fields displayed will vary according to your selection in Step 10.

12. Perform one of the following: If You Want To Then Go To Double-click the displayed value for which View additional details Step 13 you want to view details.

Exit this transaction Click . Step 18

06_PS_S_ALR_87013542_Run Plan 11/17/2017 CompariReport_0_ProjectSystems_02.udc 7/12 Ver: © University of Cincinnati Work Instruction Functional Area: Project Systems Run Plan Comparison Report

Document Overview - Display

13. Review the displayed information.

The screen and fields displayed will vary according to your selection in Step 12.

14. Click .

06_PS_S_ALR_87013542_Run Plan 11/17/2017 CompariReport_0_ProjectSystems_02.udc 8/12 Ver: © University of Cincinnati Work Instruction Functional Area: Project Systems Run Plan Comparison Report

Display Actual Cost Line Items for Projects (2)

15. Click .

Display Actual Cost Line Items for Projects (3)

16. Click .

06_PS_S_ALR_87013542_Run Plan 11/17/2017 CompariReport_0_ProjectSystems_02.udc 9/12 Ver: © University of Cincinnati Work Instruction Functional Area: Project Systems Run Plan Comparison Report

Act/Com/Total/Plan (3)

17. Click .

Exit Report

06_PS_S_ALR_87013542_Run Plan 11/17/2017 CompariReport_0_ProjectSystems_02.udc 10/12 Ver: © University of Cincinnati Work Instruction Functional Area: Project Systems Run Plan Comparison Report

18. Click .

Actual/Comm/Total/Plan in COAr Crcy: Selection (2)

19. Click until you return to the SAP Easy Access screen.

20. You have completed this transaction.

06_PS_S_ALR_87013542_Run Plan 11/17/2017 CompariReport_0_ProjectSystems_02.udc 11/12 Ver: © University of Cincinnati Work Instruction Functional Area: Project Systems Run Plan Comparison Report

Result

You have created a report that displays the actual cost, commitments, and planned amounts for specified WBS elements.