Building D Is a 4 Story Office Building Located at 55 Corporate Drive in Bridgewater NJ

Total Page:16

File Type:pdf, Size:1020Kb

Building D Is a 4 Story Office Building Located at 55 Corporate Drive in Bridgewater NJ

Building A, 2 nd Floor Renovation Project

Building A is a 5 story office building located at 55 Corporate Drive in Bridgewater, NJ. The following briefly describes the necessary alterations required as part of the A-2 renovation.

Please reference the following drawings for complete scope of work: AZ Corporation drawings – Sanofi 2nd Floor Office Improvements Progress Set Dated January 3rd, 2014 inclusive of: A-001, A-002, A-100D, A-110, A-112, A-113, A-114, A- 600, E-110.

The project focuses on the vast majority of the second floor of Building A. The innovation hub is excluded from the project scope.

Scope of Work:  Demo carpet, furnish and install new carpet tile in the open area, offices A-2507 – A2511, A-2513 – A-2517, A2303 – A2306, new Huddle Rooms A-201 – A-205, three conference rooms (A-2292, A-2552, A-2553).  Demo ten offices: A-2530 – A-2534, A-2536 – A-2540.  Furnish and install 5 new Huddle Rooms: A201 – A205 inclusive of light relocation.  Paint offices A-2507 – A2511, A-2513 – A-2517, A2303 – A2306, new Huddle Rooms A-201 – A-205, three conference rooms (A-2292, A-2552, A-2553), perimeter of work area, hallways, common areas, and new partition walls.  Provide a HVAC allowance of $25,000.  Provide a Fire Protection allowance of $10,000.  Electric (454 data/ voice lines, 73 120v circuits, 24 new poke thrus, 27 wall mount power/ data, data/ phone/ power for six copiers, two new 150 amp subpanels, four new 48 patch panels. Labeling to be performed per Sanofi standards.  Provide temporary plastic barriers with walk off mats at all access points into the construction area.  Construction signage to be installed at all access points into the construction area.

Exclusions:  All knockdown and reinstallation of workstations, lockers, and furniture by Sanofi.

This project shall be bid as a Single Phase, Lump Sum project. All permit fees shall be included in your bid. Note, all work to be completed off hours. Earliest start is 6p weekdays. A work plan must be submitted with your proposal including a project schedule. Assume work to commence in June. This work plan must be approved by Sanofi prior to project start. All contractors must abide by the attached US Sanofi Contractor Safety Program.

Alternates:  Please provide an alternate deduction to perform all work during normal working hours. Note, demolition of offices and poke thrus with associated power and network cabling to occur after 6p.  Please provide an alternate deduction to complete this project with power poles in lieu of poke thrus. Contractor is responsible to furnish and install approved power pole.  Please provide an alternate to complete project in Three Phases as indicated on the drawings. Please consider and describe proposed egress means during each phase.

Unit Pricing – please provide unit pricing for the following:  Additional poke thru  Additional power poles  Additional infrastructure to support one copier  Additional data drop  Additional duplex receptacle  Carpeting per square foot  Ceiling tiles  Light fixtures