PRE FEASIBILITY REPORT OF RED EARTH QUARRY THIRU. M.PALANISAMY UNDER EIA NOTIFICATION 2006

PRE FEASIBILITY REPORT OF VANAVASI RED EARTH QUARRY FOR OVER AN EXTENT OF 0.96.0HA IN VANAVASI VILLAGE, TALUK, AND TAMILNADU OF THIRU. M.PALANISAMY, (Under the Guidelines of Ministry of Environment and Forests in terms of the provisions of EIA notification 2006 and specifically in circular No J-11013/41/2006-IA.II (I) dated 30th December, 2010) 1.0 EXECUTIVE SUMMARY OF THE PROJECT Total extent of the Area is 0.96.0Ha in Patta land at Vanavasi Village, , Salem District. It is a new Red Earth Quarry Project. The lease applied area is Exhibits almost plain topography. The Eco friendly quarry operation is proposed to carry out with open cast semi mechanized quarrying by deploying Excavator without drilling and blasting. The quarry operation is proposed up to a depth of 3m below ground level. The Total Geological reserve is about 28,800m3 of Red Earth. The Total Mineable reserve is about 12,798m3 of Red Earth for a period of Two years only. The proposed quantity of reserve is about 12,798m3 of Red Earth for a period of Two years only. Mining license applied for period of Two years. Life of the quarry is Two years. The project area does not fall in ‘HACA’ region. There is no Interstate boundary within the radius of 10kms. There is no Western Ghats within the radius of 10km. The project area does not fall in CRZ. There are no Bird Sanctuaries, wild life sanctuaries as per Wild Life Production Act 1972, within the radius of 10km. There is no habitation situated within the radius of 500km. There is no quarry within the radius of 500m. 0.3KLD of water for labor drinking and domestic purpose will be available from nearby village through package drinking water vendors. 0.3KLD and 0.4KLD for dust suppression in haul roads and Green belt during the quarrying operation, the water is available in existing borehole on near the quarry area and also available from

PRE FEASIBILITY REPORT OF VANAVASI RED EARTH QUARRY THIRU. M.PALANISAMY UNDER EIA NOTIFICATION 2006 authorized water vendors. The cost of the project: A. Fixed asset cost = 2,32,000/- B. Operational cost = 2,88,000/- C. EMP Cost = 1,90,000/-

 Total Cost(A+B+C) = 7,10,000/-  The Total EMP cost is about Rs. 1,90,000/- (one Lakh and Ninety thousand rupees only)  The total cost of the project is about 7,10,000/- (Seven lakhs and Ten thousand only)

2.0 INTRODUCTION OF THE PROJECT OR BACKGROUND INFORMATION The applicant proposes to quarry Red Earth by opencast semi mechanized quarrying over an Extent 0.96.0Ha, this project is located in Vanavasi Village, Mettur Taluk, Salem District, Tamilnadu. The Category of project-‘B2’. (i) Identification of project and project proponent: In case of mining project, a copy of mining lease/letter of intent should be given I. The quarry lease was applied at the date of 28.12.2015. II. Precise area communication was issued by the District Collector, Salem vide Rc. No. 708/2015/Mines/A dated 24.11.2017. III. The mining plan was approved by the Deputy Director, Department of Geology and Mining, Salem vide Rc. 708/2015/Mines/A dated 19.03.2018 Owner name and address (address for correspondence) Name of owner :Thiru.M.Palanisamy, Address : S/o. Muniyagounder Periya Soragai Village, Mettur Taluk, Salem District. Pincode : 636 502. Cell No : 9442588277 Email Address :[email protected]

PRE FEASIBILITY REPORT OF VANAVASI RED EARTH QUARRY THIRU. M.PALANISAMY UNDER EIA NOTIFICATION 2006

Location of Project site: Name of the quarry :Vanavasi Red Earth Quarry S.F.Nos : 258/2A and 259/1B3 Extent :0.96.0Ha Village :Vanavasi Taluk :Mettur District :Salem State : Ownership : It’s a Patta land registered in the name of Thiru.Velumani and Thiru.Yuvaraj, Vide Patta Nos-183 and 1300, The applicant has obtained consent from pattadhars, Please refer the Annexure No – IV & VII. (ii) Brief description of nature of the project The Red Earth quarrying is proposed to carry out by opencast Semi mechanized method. The Red Earth is composed of unconsolidated rock fragments. The Red Earth is an important commercial product, transportation to the needy destination manufacturing of Bricks and construction industries for Government and Public sector projects besides catering domestic housing and infrastructure projects in and around the district. To execute the above said project permission is requested to remove the Red Earth in Vanavasi Village, Mettur Taluk, Salem District. Machineries like excavator are proposed for quarrying for a Two years period of this up to 3m below ground level. No drilling and blasting is proposed. No benches are proposed the quarrying is a restricted to a 3m below ground level in the entire quarry lease applied area. There is no wastage is not anticipated during the quarry operation, the entire Red Earth is excavated and utilized. It is proposed to exploit Red Earth of about 12,798m3 of Red Earth for the period of Two Years only.

PRE FEASIBILITY REPORT OF VANAVASI RED EARTH QUARRY THIRU. M.PALANISAMY UNDER EIA NOTIFICATION 2006 (iii) Need for the project and its importance to the country and or region The Red Earth quarrying project falls in the area of Salem District, Tamilnadu where scanty The excavated Red Earth is used for excavated Red Earth is used for the Wall Whitening and Bleaching Purpose in and around the district. This project will give employment opportunities to 7members directly. Mineral Industries of the state of Tamilnadu provides employment opportunities for the people of the state as well as in the specific project area. Mining and Quarrying is two among the major core sector industries which plays a vital process of country’s economic development. (iv) Demand and supply gap There is a huge demand of Red Earth in Salem District, The excavated Red Earth is used for excavated Red Earth is used for manufacturing of Bricks and construction industries for Government and Public sector projects besides catering domestic housing and infrastructure projects in and around the district. (v) Imports vs. indigenous production There is no import of Red Earth at present in . India especially the peninsular India (southern India) has good resource of Red Earth. (vi)Export Possibility There is no possibility for export of this Red Earth. (vii) Domestic/Export Markets The excavated Red Earth is used for excavated Red Earth is used for the manufacturing of Bricks and construction industries for Government and Public sector projects besides catering domestic housing and infrastructure projects in and around the district. (viii) Employment Generation (Direct and Indirect) due to the project About 7employees including labors directly and engaged in this proposed quarry project and the tentative man power required for the proposed Red Earth quarry shall be as follows.

PRE FEASIBILITY REPORT OF VANAVASI RED EARTH QUARRY THIRU. M.PALANISAMY UNDER EIA NOTIFICATION 2006 Skilled: Mines foreman : 1 Supervisors : 1 Semi-skilled: Excavators Operators : 1 Co-operator : 1 Un -Skilled: Watchman : 1 Unskilled – helpers : 2 Total : 7 Nos.

The above man power is adequate to meet out the production schedule and the machinery strength envisaged in the mining plan and also to comply with the statutory provisions of mine safety regulations. It is been ensured that the labors will not be deployed less than 18 years, No Child labor will engaged or entertained for any kind of quarrying operations. All the labors engaged for quarrying operations will be insured till the end of life of quarry.

3.0 PROJECT DESCRIPTION (i) Type of project including interlinked and interdependent projects, if any This is a quarrying project for exploitation of Red Earth for the proposed production of 12,798m3 of Red Earth for the period of Two Years. No other allied actions like processing and beneficiation is proposed in this project. (ii) Location (map showing general location, specific location, and project boundary & project site layout) with coordinates

 The project Red Earth is about 0.96.0Ha  The project area falls in Vanavasi Village  The area is falls in GSI Topo sheet no. 58 E/14.  The Latitudes between of 11°45'06"N to 11°45'14"N  Longitudes between of 77°51'33"E to 77°51'38"E E on WGS 1984 datum.

PRE FEASIBILITY REPORT OF VANAVASI RED EARTH QUARRY THIRU. M.PALANISAMY UNDER EIA NOTIFICATION 2006 (iii) Details of alternate sites considered and the basis of selecting the proposed site, particularly the environmental considerations two into should be highlighted The opencast quarrying is proposed in the area for excavation of Red Earth upto 3m below ground level. The quarrying operation is proposed in Patta land and there is no any alternative site for this project is not considered, the project is site specific. (iv) Size or magnitude of operation The total area of the project is about 0.96.0Ha. It is proposed to exploit Red Earth about 12,798m3 of Red Earth by open cast semi mechanized quarry by deploying excavates directly for a period of Two years only. (v) Project description with process details (a schematic diagram/flow chart showing the project layout, components of the project etc. should be given) No process is involved in this project. The Red Earth is excavated from the ground directly by excavators and loaded into tippers to the customer’s site.

Excavating the Earth by excavators

Loading the Earth into tippers by excavators to the needy customers site

Mineable reserves Total Recoverable Resource up to 3m= 12,798m3 of Red Earth The applicant proposed to excavate= 12,798m3 of Red Earth for the period of Two Years. General Geology The lease applied area is exhibits Slightly undulated topography covered with Red Earth which does not sustain any type of vegetation due to the topography of the land. The altitude of the area is 368m (Maximum) from MSL, the slope of the area is

PRE FEASIBILITY REPORT OF VANAVASI RED EARTH QUARRY THIRU. M.PALANISAMY UNDER EIA NOTIFICATION 2006 gentle towards Southeastern side. Please refer the Topography, Geological plan and sections (Plate No –III). Details of Exploration No exploration is carried out. The Red Earth is found right from the surface and proposed to excavate up to a depth of 3m below ground level only. Proposed Study to be carried out As the quarrying operation is proposed to be carried out for a period of Two years to a depth of 3m Below Ground Level further exploration or proposed study is redundant. Method of Estimation of Reserves The Geological plans demarcating the commercially viable Red Earth have been prepared in 1:1000 scales (Plate No. III).

Totally Six sections have been drawn, Three sections drawn Length wise as (X-Y), (X1-Y1), (X2-Y2) another Three sections drawn width wise as (A-B), (C-D) and (E-F) to choose the maximum area cover under the lease in the Horizontal 1:1000 and Vertical 1:100 (please refer Plate No- III).

The cross sectional area for the proved depth persistence of 3m has been worked out for the section. The cross sectional area multiplied by its length of influence on the longer axis gives the volume (insitu) in the cross sectional area. The sum total of the insitu reserves available within the individual cross sectional area gives the geological reserves of the lease applied area. As the mineable of Red Earth in the terms of cubic meter. The Geological Resource, Mineable Reserves are given only in terms of Cubic meter. OPEN CAST WORKING Opencast method of shallow mining is proposed, heavy Red Earth moving machineries like excavator are proposed for quarrying this Red Earth upto 12,798m3 of Red Earth. No drilling and blasting is proposed for this type of Red Earth quarrying, it is an eco-friendly quarry operation. The Red Earth will be loaded directly to the trucks/Lorries for transportation to the needy customers. The depth of quarry is proposed to be restricted upto 3m below ground level.

PRE FEASIBILITY REPORT OF VANAVASI RED EARTH QUARRY THIRU. M.PALANISAMY UNDER EIA NOTIFICATION 2006 Overburden: There is no overburden the Red Earth is exploit right from the surface to a depth of 3m below ground level for a period of Two years only. (vi) Raw material required along with estimated quantity, likely source, marketing area of final products, Mode of transport of raw Material and Finished Products This is a quarrying project for excavating Red Earth hence there is no requirement for raw material. The excavated Red Earth is used for excavated Red Earth is used for the Wall Whitening and Bleaching Purpose in and around the district. (vii) Resource optimization/recycling and reuse envisaged in the project, if any, should be briefly outlined No optimization/ Recycling and Reuse envisaged in the proposed Red Earth quarry projects. (viii) Availability of water its source, Energy/power requirement and source should be given This Red Earth quarry project does not require huge water for the project. The total water requirement in the quarry will be around 1KLD for drinking, domestic usage and dust suppression sprinkling. The water will be brought from local suppliers.

WATER BALANCE CHART

WATER (1 KLD)

0.3KLD of Drinking water & 0.3 KLD for Dust Domestic purpose suppression

&04KLD Green belt development

Used only for drinking purpose Dust Suppression in the Haul for operational workers Roads to prevent Dust emission, domestic purposes.

PRE FEASIBILITY REPORT OF VANAVASI RED EARTH QUARRY THIRU. M.PALANISAMY UNDER EIA NOTIFICATION 2006 Table -1

Purpose Quantity Sources Drinking 0.06 KLD Water purchase from Water approved water vendors Domestic available in Vanavasi usage Other 0.240 KLD which is about 2.0Km on the Domestic Eastern side . Purpose Dust From existing borehole on nearby quarry area or 0.3 KLD suppression approved water vendors From existing borehole on nearby quarry area or Green Belt 0.4 KLD approved water vendors

Energy No Electricity is required for quarry operation; the quarry working is restricted on day time only between 7Am to 6Pm). Diesel (HSD) will be used for quarrying machineries around 2,130liters of HSD will be used for the entire project life. Diesel will be brought from nearby diesel pumps. No power is required for the project; lightings on the Night will be taken from nearby electric poles after obtaining permission from concerned authorities. Per hour Excavator will consume = 10liters / hour Per hour Excavator will excavate = 60m3 Per 12,798cbm = 12,798m3/60 = 213hours Diesel consume 213working hours = 213X10 = 2,130liters of HSD for entire project life. (ix) Quantity of wastes to be generated (liquid and solid) and scheme for their management/disposal There is no wastage is encountered during the quarrying operation the entire Red Earth is utilized. There is no toxic effluent expected to generate in the form of solid or liquid and gases and the no requirement of treatment of waste. There is no top soil available in the lease applied area.

PRE FEASIBILITY REPORT OF VANAVASI RED EARTH QUARRY THIRU. M.PALANISAMY UNDER EIA NOTIFICATION 2006 (x) Schematic representations of the feasibility drawing which give information of EIA purpose

FORM-I ALONG WITH PRE-FEASIBILITY REPORT & APPROVED MINING PLAN

To Submit DEIAA

Final Presentation

4.0 SITE ANALYSIS (i) Connectivity  There is an existing road from the area leads Vanavasi – Veerakkal Village road on Northern side of the area.  The Nearest Railway line is Mettur –Salem line which is about 6.0km on Northern side of the area.  The National Highway (NH-7) Salem – Kanniyakumari is about 21.0Km on Eastern side of the area.  The State Highway (SH-20) Mettur - Thoppur is about 7.5Km on Northern side of the area.

(ii) Land Form, Land use and Land ownership It’s a Patta land registered in the name of Thiru.Velumani and Thiru.Yuvaraj, Vide Patta Nos-183 and 1300, The applicant has obtained consent from pattadhars, Please refer the Annexure No – IV & VII. (iii) Topography (along with map) The lease applied area is exhibits Slightly undulated topography covered with Red Earth which does not sustain any type of vegetation due to the topography of the land. The altitude of the area is 368m (Maximum) from MSL, the slope of the area is gentle towards Southeastern side. Please refer the Topography, Geological plan and sections (Plate No –III).

PRE FEASIBILITY REPORT OF VANAVASI RED EARTH QUARRY THIRU. M.PALANISAMY UNDER EIA NOTIFICATION 2006 (iv)Existing land use pattern (agriculture, non-agriculture, forest, water bodies (including area under CRZ)), shortest distances from the periphery of the project to periphery of the forests, national park, wild life sanctuary, eco sensitive areas, water bodies (distance from the HFL of the river), CRZ. In case of notified industrial area, a copy of the Gazette notification should be given. The lease applied area is exhibits almost plain topography; it is a dry barren land covered with Red Earth formation, does not sustain any type of vegetation due to this Red Earth formation and does not sustain any type of vegetation due to this Red Earth formation. Ground water is about 43m depth from ground level. The quarrying is restricted up to 12,798m3 of Red Earth; hence the quarry operation will not be affected by the ground water. Govt. Agriculture Grazing Forest land Government Total (Ha) waste land land land land - - - - - 0.96.0Ha

 No CRZ within the radius 10km  No Forest within the radius of 10km  No National park, wild life sanctuary, eco sensitive area within the radius10km  No Western Ghats within the radius10km  No quarries within the radius of 500m (v) Existing Infrastructure There is no existing infrastructure in the proposed quarry lease applied area. (vi) Soil Classification Coarse to medium grained Red Earth formation, this land does not sustain any type of vegetation or Agriculture. (vii) Climatic data form secondary sources Both the North East and South West monsoon occurs here and the summer are hot and winters are cool. During April and May the temperature may shoot up to 40°C and during winter the temperature does not fall below 25°C. The annual rainfall is around 900mm.

PRE FEASIBILITY REPORT OF VANAVASI RED EARTH QUARRY THIRU. M.PALANISAMY UNDER EIA NOTIFICATION 2006 (viii) Social infrastructure available There is no social infrastructures like Government Buildings, worship in the 1Km vicinity of the quarry lease applied area. 6.0 PLANNING BRIEF (i) Planning Concept (type of industries, facilities, transportation etc.) Town and

Country Planning/Development authority Classification. This quarrying project is to excavate Red Earth by open cast semi mechanized method. Hydraulic excavator will be deploying for production. Transportation of Red Earth shall be done by tippers on roads. The project land is devoid of vegetation and lies in the backward town of Salem District. There are no specific industries or factories in and around the project area. Transportation

Hired Tippers of 10/20Ts capacity will be utilized for Transportation of excavated Red Earth is used for excavated Red Earth is used for the Wall Whitening and Bleaching Purpose in and around the district, by Tarpaulin cover to prevent spillage. During the transportation of material through the village and populated area the vehicles are strictly prohibited not exceed the 40km speed limit. Population projection There are few village located in 5km radius from the lease applied area the details of the areas are given below. Table-3 Approximate Name of the distance & Direction Approximate S.No Village from lease applied population area 1. 3.5km – NE 2000

2. Norachivalavu 3.5km – SE 200

PRE FEASIBILITY REPORT OF VANAVASI RED EARTH QUARRY THIRU. M.PALANISAMY UNDER EIA NOTIFICATION 2006 (iii) Land use planning (breakup along with green belt etc.,) The Red Earth quarrying operation is proposed for a period of Two years up to depth of 3m below ground level. The project area extent is 0.96.0Ha. The entire area is proposed to be quarried. (iv) Assessment of Infrastructure Demand (Physical & Social) The existing road facilities are already available which shall be used and maintained. Medical facilities is available for the project sites, Government and private and other basic infrastructure facilities like communication center, school, supermarket, bus stand are also available in Vanavasi which is about 2.0Km on the Eastern side. This quarry project will provide employment for about 7persons directly. (v) Amenities/Facilities The simple methods adopted and the limited scale of activities involved in quarrying does not require High Tension Electric Power supply or huge workshop facilities. The quarrying work is restricted to two general shift during day time only. Major Machinery repair works are attended at Vanavasi which is about 2.0Km on the Eastern side of the area Packaged drinking water will be brought from approved water vendors. All the facilities are available in Mettur which is about 5.5Km on the Northwestern side. 6.PROPOSED INFRASTRUCTURE (i) Industrial Area (Processing area) There is no processing area proposed within the lease applied area. (ii) Residential area (Non processing area) There is no residential area within 500m of the lease applied area. (iii) Green Belt After the completion of the quarrying operation, the land will be leveled and only used for Agriculture purpose. Afforestation is not proposed inside the area. The applicant ensures to carry out Afforestation by planting native species on the nearby villages and village road after the consultation with Panchayat authorities. The budget for Afforestation will be around Rs.25,000/-.

PRE FEASIBILITY REPORT OF VANAVASI RED EARTH QUARRY THIRU. M.PALANISAMY UNDER EIA NOTIFICATION 2006 (iv) Social infrastructure This proposed Red Earth quarry will fetch employment for about 7 people directly and 6persons indirectly. (v) Connectivity (traffic and transportation road/ Rail/ Metro/ Water ways etc.,)  There is an existing road from the area leads Vanavasi – Veerakkal Village road on Northern side of the area.  The Nearest Railway line is Mettur –Salem line which is about 6.0km on Northern side of the area.  The National Highway (NH-7) Salem – Kanniyakumari is about 21.0Km on Eastern side of the area.  The State Highway (SH-20) Mettur - Thoppur is about 7.5Km on Northern side of the area.

(vi) Drinking Water management (Source & Supply of water) This proposed Red Earth quarry project does not require huge water either for beneficiation or processing. Water required for Drinking and domestic purpose for labor is around 0.3KLD the packaged Drinking water for this will be brought from approved water vendors available at Vanavasi which is about 2.0Km on the Eastern side of the area. 1. Domestic usage Drinking Water–0.06 KLD Other Domestic –0.240 KLD Purpose 0.3KLD(Source: through approved packaged water vendors) 2. Dust Suppression –0.3 KLD(Source: From existing borehole on near the quarry area or From approved water vendors) 3. Green belt – 0.4 KLD(Source: From existing borehole on near the quarry area From approved water vendors)

Total – 1 KLD

PRE FEASIBILITY REPORT OF VANAVASI RED EARTH QUARRY THIRU. M.PALANISAMY UNDER EIA NOTIFICATION 2006 (vii) Sewerage System Toilets will be constructed as semi-permanent structure and sewage will be discharged Once in a months. The sewage waste will be collected in soak pit and discharged as manure. (viii) Industrial Waste Management No industrial waste will be generated from the project. (ix) Solid Waste Management The Red Earth quarrying does not produce any waste. The entire Red Earth is excavated and utilized. This Red Earth may not produce any toxic effluent in the form of solid liquid or gas. (x) Power Requirement & Supply / source The proposed Red Earth quarrying does not required any power supply the quarrying operation which is proposed to operate in day time only for 7 Am to 6Pm with 1 Hour lunch interval between 1Pm to 2Pm. 7.0REHABILITATION AND RESETTLEMENT (R & R PLAN) (i) Policy to be adopted (Central/State) in respect of the project affected persons including home ousters, langoustes and landless laborers (a brief outline to be given) It’s a Patta land registered in the name of Thiru.Velumani and Thiru.Yuvaraj, Vide Patta Nos-183 and 1300, The applicant has obtained consent from pattadhars, Please refer the Annexure No – IV & VII. 8.0 PROJECT SCHEDULE & COST ESTIMATES (i) Likely date of start of construction and likely date of completion (Time schedule for the project to be given) Red Earth Quarrying project which is likely to get commenced after the execution of quarrying lease. The proposed quantity reserves 12,798m3 of Red Earth for the period of Two Years.

PRE FEASIBILITY REPORT OF VANAVASI RED EARTH QUARRY THIRU. M.PALANISAMY UNDER EIA NOTIFICATION 2006 (ii)Estimated project cost along with analysis in terms of economic viability of the project Fixed assert cost:- Land cost = Rs. 1,92,000/-

Rest shelter = Rs. 20,000/-

Sanitary facility = Rs. 20,000/-

Total fixed assert cost= Rs. 2,32,000/-

Operational cost :- For excavation = Rs. 2,13,000/-

Leveling = Rs. 25,000/-

Fencing cost = Rs. 50,000/-

Total operational cost= Rs. 2,88,000/-

EMP cost

i. Drinking water =Rs. 36,000/-

ii. Sanitary Arrangements =Rs. 36,000/-

iii. Safety kits =Rs 20,000/-

iv. Water Sprinkling =Rs. 48,000/-

v. Afforestation cost =Rs. 25,000/-

vi. Cost towards charity =Rs. 25,000/-

(schools, worship places etc.,)

Total = Rs. 1,90,000/-

Total = Rs. 1,90,000/-

Fixed asset cost = 2,32,000/- Operational cost = 2,88,000/- EMP Cost = 1,90,000/- Total Cost(A+B+C) = 7,10,000/- (The Project cost including EMP Cost is about Rupees Seven lakhs and ten thousand only)

PRE FEASIBILITY REPORT OF VANAVASI RED EARTH QUARRY THIRU. M.PALANISAMY UNDER EIA NOTIFICATION 2006 Population Benefit The applicant ensures to take social responsibilities like providing School Note books, Uniforms to the Students below poverty level beside if the villages require any borehole for public use the applicant ensure to do so. The applicant will also take part and contribute the native cultural activities in the nearby villages. During summer seasons packaged drinking water will be kept in the village for public and for trespassers. The applicant will involve and contribute all the socio cultural allocation in and around the area. Government Revenue The state Government will get revenue as Royalty, sale tax, surface rent, dead rent/ VAT/ income tax etc. 7.0ANALYSIS OF PROPOSAL (FINAL RECOMMENDATIONS) (i) Financial and social benefits with special emphasis on the benefit to the local people including tribal population, if any, in the area The end use of the excavated Red Earth is used for excavated Red Earth is used for the Wall Whitening and Bleaching Purpose in and around the district. Due to this project many of the infrastructure development will be carried out in and around the district on time, nearly 7 employees directly get employment opportunity through this project. By considering the merit of the project the permission may be granted. Signature of the applicant

M.Palanisamy

Signature of Qualified Person

C.Natarajan, M.Sc., M.Phil.,

RQP/MAS/004/87/A

Place : Salem

Date :