DAS weekly Progress achieved upto 29.12.2015
Sl No. Particular Package Description Status
• DAS system design Implementation and customization is in progress. • Configuration and Development System setup in BICC-1, HSR Layout, DAS & SG BESCOM office for training of BESCOM personnel. 1 DAS System Design • DAS PreFAT activities has commenced. • Substation model building of GIS data is completed. • The details required for the integration of CCCS with DAS has been provided by DAS section to GM (CR) section.
Control Centre-1:
All civil engineering works have been completed, except the following works which are in progress; Fire dampers Gas suppression system to server room, CH room and VPS 2 Control Centers enclosure. Control Centre-2: LoI issued for control centre-2 construction work. Architectural DBR and drawings are cleared from consultant M/s STUP. Foundation works completed.
Package-I UHF:
DL (Decision to grant license) for UHF frequency is issued by WPC (Wireless Planning & Coordination wing). Frequency WPC has issued Import License to import MARS Equipment of 3 Allocation Communication system. 1. Microwave :
2. WPC has issued DL (Decision to grant license) for microwave frequency vide letter dated 28.07.2014.
SACFA has issued clearance for construction of communication towers at 8 tower sites. Tower Construction Status: HSR Layout Tower : construction completed Communication Tannery Road Tower: construction completed Towers 4 Byatraynapura tower: construction completed J P Nagar Tower: Foundation completed. Shelter and DG foundation work completed Anandrao Circle Tower: Foundation completed
Radio Frequency survey work has been commenced. Remote radio’s installed at 55 locations.
Page 1 of 3 RTUs RTUs Field Name of the Ordered Allotted Installed Performance Sl No. Package Package Description Contractor Quantity RMUs upto Test(FPT) upto 29.12.2015 29.12.2015 1. Package-II(A) Remote Terminal M/s ABB 700 699 683 653 2. Package-II(B) Units for Existing M/s CGL 495 492 490 468 and New Ring Main 3. Package-II(C) Units M/s Efacec 395 372 359 333
Site Supplied Erected as Acceptance Package Name of the Ordered Sl No. Package Description upto upto Test (SAT) Number Contractor Quantity 29.12.2015 29.12.2015 upto 29.12.2015 Line Reclosers (LRC) 500 Completed Completed 495 Package- 1. Load Break Switches M/s P&C Co. III(A) 450 Completed Completed 447 (LBS) Line Reclosers (LRC) 295 Completed Completed 287 Package- 2. Load Break Switches M/s Entec III(B) 295 Completed Completed 291 (LBS)
Supplied Erected as Commissioned Package Package Name of the Ordered Sl No. upto upto upto Number Description Contractor Quantity 29.12.2015 29.12.2015 29.12.2015 M/s New Ring Main 3. Package-IV(A) Schneider 345 Completed Completed Completed Units(3 WAY) Electricals New Ring Main 4. Package-IV(B) M/s CGL 250 Completed Completed 249 Units(5 WAY) New Ring Main 5. Package-IV(C) M/s Siemens 195 Completed Completed Completed Units(5 WAY) Replacement of existing RMU with M/s Eshwari 6. Package-V(A) 200 Completed Completed Completed DAS compatible Electricals RMU Replacement of M/s existing RMU with 7. Package-V(B) Schnieder 600 Completed 580 580 DAS compatible Electricals RMU Construction of 695 694.6 694.6 Overhead Completed Kms Km Km Lines(Coyote) Construction of M/s L&T 500 255 249 8. ** Package-VI Overhead 254.6 Kms Limited Kms Kms Kms Lines(ABC) DP 270 Completed Completed Completed Spun Pole 1125 Completed Completed Completed Page 2 of 3 Construction of M/s L&T 230.5 229.629 229.444 9. Package-VII Underground Completed Limited Kms Kms Kms Cables
** M/s L&T Limited has supplied only 255Kms out of 500Kms AB Cable.