National Highway Authority of India (Maharashtra Division) PIU SOLAPUR
Sub: Brief on Design, Engineering, Construction, Development, Finance, Operation and Maintenance of 4 laning of Pune-Solapur section of NH-9 from Km. 144.400 to Km. 249.000 in the state of Maharashtra under NHDP Phase III on DBFOT basis (Concessionnaire: M/s Pune Solapur Development Company Ltd..)
The Government of India has mandated the National Highways Authority of India (NHAI) to implement the National Highway Development Project (NHDP). The National Highway – 9 (NH-9) connects the state of Maharashtra with Karnataka and Andhra Pradesh. This is one of the major corridors from North and West to South and vice versa. This is one of the major high-density traffic corridors in India connecting Northern and Western India with Southern India and is a major and integral part of NHDP. The Section from Mumbai to Pune is already four laned and the section from Pune to Solapur is in the advance stage of 4 laning.
The project that 4 lane of Pune Solapur Section of NH 9 in Km. 144/400 to Km. 249/000 in the State of Maharashtra under NHDP Phase-III on DBFOT basis Pkg.II.
(A)Project Details :-
Sr. Description Details No. Design, Engineering, Construction, Development, Finance, Operation and Maintenance of 4 laning of Pune-Solapur section of NH-9 from Km. 1 Name of Project 144.400 to Km. 249.000 in the state of Maharashtra under NHDP Phase III on DBFOT basis 2 Name of Concessionaire M/s. Pune Solapur Road Development Company Ltd.,
3 Name of Independent Consultant M/s. ICT.
4 Name of EPC Contractor M/s. IECCL. 5 Date of Signing of Agreement 30h September 2009. 6 Appointed Date (Date of Start) 28.09.2011. 7 Construction Period 910 days Actual / Schedule Date of Completion of 8 14.01.2014 Construction work 9 Concession Period 20 years (including construction period). 10 Length of Project (Km) 101 Km in Maharashtra. 11 Project Cost 835 Crores (B) Scope of Work / Silent Features of the Project :-
Sr. No. Description Details 1 The total length of project 101 Km. in Maharashtra 2 Major Bridges 7 nos. 3 Minor Bridges 21 nos. 4 Culverts 197 nos. 5 Inter changes/Flyovers Nil 6 Road Over Bridge (ROB) 2 nos. 7 Vehicular Underpasses 10+2 nos. 8 Pedestrian Underpasses 7 nos. + 4 nos. In the approaches of PUP. 9 Bypasses 1 nos. i) Tembhurni Bypass - Existing Ch. 153/300 to Existing Ch. 158/900 = 6.8 Kms. 10 Service Roads 83.05 Km 11 Major Road Junctions & Minor Road 28 nos. Junction 12 Bus bays with passenger shelter 2 x 31 nos = 62 places in Both directions.
13 Truck Lay byes 3 nos.
14 Toll Plaza 2 Nos. at Ist Toll Plaza at Km. 172/972 (Design Ch. 178/572) & IInd Toll Plaza Km. 223/750 (Design Ch. 229/350) 15 Base Traffic/ (PCU)-2010 19166
16 Rest Area 2 Nos.
(C)Progress of the Project :- 80%
Sr. Description Details No.
1 Physical Progress up to July-2013. 80%