Wrexham County Borough Council
Total Page:16
File Type:pdf, Size:1020Kb
Wrexham County Borough Council Annual Progress Report 2002/3
Wrexham County Borough Council
LOCAL TRANSPORT PLAN
ANNUAL PROGRESS REPORT
April 2002 – March 2003
CONTENTS Page
Summary 2 Section 1 Introduction 7 Section 2 Improvements/Additions to the Local Transport Plan 19 Section 3 Progress 22 Section 4 Programme and Targets 39 Section 5 Progress of Regional Transport Partnerships 44 Section 6 Financial Tables 48
APPENDICES
1 Feedback from WAG on APR for 2001-2002 53 2 Local Transport Plan – Progress on Policies 55
If you wish to make any comments, or would like a copy of this document please contact;
Julie Barnes Transportation and Engineering Department Wrexham County Borough Council PO Box 1293 Wrexham LL11 1WQ Tel. 01978 297167
Email [email protected]
The APR will also be available on the Councils Website: www.wrexham.gov.uk Large print, Welsh, or electronic versions of this document are available on request
Mae’r ddogfen hon ar gael yn Gymraeg. Ffoniwch 01978 297167 am eich copi
1 Wrexham County Borough Council Annual Progress Report 2002/3
Summary
1. The Local Transport Plan (LTP) for Wrexham County Borough was submitted to the Welsh Assembly Government (WAG) in July 2000. The LTP sets out the programme for transport in the County Borough and outlines a twenty year vision to illustrate how the Council is committed to finding sustainable solutions to its transport problems. The LTP meets WAG’s requirements to reduce traffic congestion and pollution and offer a greater choice of transport with less dependency on the car.
2. The overall objective on the LTP is to;
Overall Objective of the LTP
“Provide for present and future transport needs in the County Borough and to ensure that transportation investment is related to land use planning, environmental, social and accident reduction objectives”.
3. The Council has placed great importance on the LTP and has declared it to be one of its key Corporate Polices. During 2002/3 the Council has made excellent progress towards meeting the aims and objectives of the LTP which in turn is bringing positive benefits to the people and the environment of the County Borough.
4. In the implementation of the LTP, the Council has worked closely with WAG, the Welsh Development Agency (WDA), Community Councils, private developers, schools, voluntary organisations as well as with its neighbouring authorities in both England and Wales. This partnership approach will improve the County Borough both in the short term and for future generations.
5. During 2002/3 there has been many notable achievements in order to meet the Councils objectives and targets. These include the following;
Achievements
. Construction of Wrexham’s new Bus Station (Phase 1 completed in June 2003) . Completion of the first stage of the Wrexham Industrial Estate Access Road . Several safe routes to schools schemes . Arrive Alive Campaign – speed enforcement partnership . Free Concessionary Travel scheme . Fully accessible town centre for wheelchair users . “Education Quality Partnerships” for 20 school contracts . Continued improvement of Cycling and Walking facilities
2 Wrexham County Borough Council Annual Progress Report 2002/3
6. Progress towards meeting the targets contained in the LTP includes;
Progress
. 98% of pedestrian crossings now have facilities for the disabled . 83% reduction in the number of children killed or seriously injured (94- 98 average compared to 2002) . 27% reduction in the number killed or seriously injured . 55% increase in the number of children who received cycle training between 2000 and 2002 . 21% of Wrexham’s buses are now low floor . 150 bus stops have been improved with bus boarding features . The number of concessionary travel pass holders has increased from 7000 in 2001, to 17000 in 2002.
7. The Council is looking forward to continuing the current progress in meeting the aims and objectives of the LTP. The Council is currently implementing schemes using the following funding secured from WAG through the Transport Grant, Local Road Safety Grant, Slower Speeds Safer Streets and the Safe Routes to Schools programmes as well as using WCBC monies.
Future Funding (2003/4)
. £757k has been secured from Transport Grant for Package Bid A . £0.5million of funding has been secured to progress the Urban Villages Initiative Package . £322k of Local Road Safety Grant Funding . £300k has been allocated by WCBC for traffic calming works . £300k has been allocated by WCBC for accident reduction works . £76k has been obtained from WAG under the Slower Speeds Safer Streets programme . £36k has been secured to implement Safe Routes at Several schools
8. As the LTP is now half way through its plan period the Council is planning to undertake a comprehensive public consultation exercise in the Autumn of 2003. The exercise will invite stakeholders to comment on the progress of the plan and on the work the Council has been undertaking. The Council will obtain more detailed comments from a variety of stakeholders on the LTP strategy, the schemes implemented and how people consider the Council is progressing towards meetings its overall objectives and targets.
3 Wrexham County Borough Council Annual Progress Report 2002/3
Consultation
. Comprehensive public consultation exercise planned for Autumn 2003 . Results will assist the Council in shaping its transport strategy for the remainder of the current LTP and beyond the end of the current plan period in 2006
9. The Council acknowledge that the LTP must be flexible and capable of responding to changing prioritise and aspirations. Information obtained from the consultation exercise will assist the Council in developing its transport strategy beyond the end of the current plan period in 2006.
4 Wrexham County Borough Council Annual Progress Report 2002/3
Figure 1 – Wrexham County Borough
5 Wrexham County Borough Council Annual Progress Report 2002/3
Figure 2 - Wrexham within regional context
6 Wrexham County Borough Council Annual Progress Report 2002/3
1. INTRODUCTION
1.1. This report is the second Annual Progress Report (APR) of the Local Transport Plan (LTP) and covers the period April 2002 to March 2003.
1.2. The LTP was produced in July 2000 and covers the period 2001-2006. The LTP sets out the Councils transport programme and contains specific objectives and policies to be achieved within the five year period.
1.3. The LTP meets WAG’s requirements to reduce traffic congestion and pollution and offer a greater choice of transport with less dependency on the car and illustrates how the Council is committed to finding sustainable solutions to its transport problems.
1.4. The overall objective on the LTP is to;
Overall Objective of the LTP
“Provide for present and future transport needs in the County Borough and to ensure that transportation investment is related to land use planning, environmental, social and accident reduction objectives”.
1.5. The LTP 2001-2006 is contained within 2 volumes, Volume 1 contains the broad overview and Volume 2 contains the individual detailed daughter strategies; . Parking . Road Safety Plan . Walking . Public Rights of Way . Public Transport . Roads . Bridges . Cycling
1.6. The LTP is a robust document and it has received widespread public support. Since its adoption it has formed the basis of Council decision makings on transport issues, however it has to adapt to national, regional and local changes.
1.7. The aim of this report is to provide information on progress made during 2002/3, set out the updated financial information and highlight any relevant changes to the original Local Transport Plan.
1.8. The first APR was submitted to WAG in June 2002. The Council received feedback on the APR in early June 2003. The general conclusion regarding the submission was that the report was;
7 Wrexham County Borough Council Annual Progress Report 2002/3
Feedback from WAG on first APR
“Well presented and clear progress report. The main deficiency is the lack of quantitative measures of progress”.
A copy of the feedback is contained as Appendix 1. Some issues raised by the feedback have been addressed in this report and the remainder with be addressed during the next 12 months and subsequently reported in next years APR.
1.9. WAG have requested that this report is an updated version of the Annual Progress Report that was submitted for 2001/2. To aid understanding the progress tables contained within the report have been shaded where appropriate to indicate where the updated information has been included.
1.10. This progress report focuses specifically on the progress and achievements of the Council from April 2002 to March 2003. During this period the Council has made significant progress towards delivering the objectives and programme of the plan including;
Achievements
Construction of Wrexham’s new Bus Station (Phase 1 completed in June 2003) Completion of the first stage of the Wrexham Industrial Estate Access Road Several safe routes to schools schemes Arrive Alive Campaign – speed enforcement partnership Free Concessionary Travel scheme Fully accessible town centre for wheelchair users “Education Quality Partnerships” for 20 school contracts Continued improvement of Cycling and Walking facilities
Changes within the National Context 1.11. Since the production of the LTP, WAG have produced several important policy documents. This section provides a brief summary of those documents and reflects on the relevance of them to the evolving LTP.
The Transport Framework for Wales 1.12. The ‘Transport Framework for Wales’ document was published by the WAG in November 2001. It explains the role of local authorities in meeting the sub- regional and local transport needs of Wales.
1.13. WCBC welcomes the fact that the LTP’s play an important role in the structure of the Framework. The Framework appraisal mechanism is based 8 Wrexham County Borough Council Annual Progress Report 2002/3
on 5 criteria, accessibility, economy, environment, safety and integration all which are important objectives of the Wrexham LTP. The National Economic Development Strategy – A Winning Wales 1.14. In 2001 the WAG launched its ‘National Economic Development Strategy’ (NEDS). It considered the extent to which the Welsh economy is under- performing, laid out a vision for the future and it established policy priorities with some key targets. Many of these have direct relevance to local transport, and equally LTPs can play a key part in advancing economic prosperity.
1.15. Policy priorities focus on the twin issues of getting more people into jobs and getting more of the better jobs by;
. Closing the regional productivity gap. (The physical infrastructure has a key role to play in this respect), . Tackling the activity gap, including community regeneration and dealing with social exclusion. (Public transport has a significant role to play in this respect), . Ensuring a spatial balance, for example between rural and urban communities.
1.16. Improved, integrated and sustainable transport is important in the attraction of inward investment, in supporting the growth of indigenous businesses, in attracting tourists and for providing access to employment opportunities for the people in excluded communities and in the rural areas. The NEDS recognises the importance of increased bus usage, innovative rural transport schemes, the need to shift goods from road to rail and the need to link public transport directly with economic development in order to maximise access and minimise environmental impact. It further identifies the need to reduce congestion, remove bottlenecks and upgrade sub- standard routes.
Wales Spatial Plan 1.17. WAG has put forward a commitment to preparing a ‘Wales Spatial Plan’. The Spatial Plan is essentially an all Wales map to highlight and distinguish the policies of the WAG. It is defined as a tool which will address issues of development and restraint on a broad scale, and provide a framework for major decisions and allocations of resources, involving both local authorities and others.
1.18. The Spatial Plan will be prepared with the WAG’s Sustainable Development Scheme and support other Assembly actions such as the National Economic Development Strategy, the Transport Framework and the Rural Development Plan.
1.19. This year WAG has been working with consultants on finalising the work of the Spatial Scenarios Wales Research Project, which fed into the preparation of the plan. This work will be developed and a consultation version of the Spatial Plan is to be published late summer.
9 Wrexham County Borough Council Annual Progress Report 2002/3
Planning Guidance Wales : Planning Policy 1.20. WAG revised ‘Planning Guidance Wales: Planning Policy’ in March 2002. The document recognises that transport issues affect all aspects of peoples lives. It has a increased emphasis on the promotion of walking, cycling and supporting public transport and discusses in particular Park and Ride, together with other means of managing traffic and parking.
1.21. The document makes specific reference to LTPs and stresses the importance of the Unitary Development Plan and the LTP working together.
Public Transport Policy Review 1.22. The WAG ‘Policy Review of Public Transport’ was published in July 2001. The review covers WAG’s public transport policies and the organisational framework under which the Assembly assists in the delivery of public transport. In particular, it includes 14 wide-ranging recommendations for improvements.
1.23. The Council share WAG’s views on quality, integrated, accessible and affordable public transport and welcomes the review as a valuable contribution to the debate on how improvements may be made, especially the review's stated aim of addressing historic under-investment in public transport. The Council has already introduced or is working towards a number of improvements set out in the recommendations and in particular, as part of the Taith Consortium, is working with others on a regional basis. The Council sees working with others in Taith as increasingly important and the most sensible way forward in securing public transport improvements as this regional structure best serves the needs of the region while not ignoring significant local needs in Wrexham.
Communities First Guidance 1.24. The ‘Communities First Guidance’ was published by the WAG in September 2001. The programme is aimed at reducing poverty and helping to improve the lives of people who live in the poorest areas. It involves an integrated approach to addressing poverty and is about bringing funding and support from a number of different sources.
1.25. The Communities First Guidance recognises that LTPs are strongly linked to Communities First Plans, with the LTP being a “thematic, strategic plan” and the Communities First Plan being an “operation/delivery plan”. The Council fully support the partnership process which is being developed with the Communities First Programme and will ensure that all departments work together to maximise the benefits to be obtained from the programme. This in turn may have implications for schemes in the LTP to be developed in the appropriate wards in the County Borough.
1.26. The electoral wards eligible for Communities First Funding in Wrexham County Borough are Plas Madoc, Queens Park and Caia Park, and Gwenfro. (Note: these are old ward boundaries). As requested by WAG in their feedback of the first APR a location plan is now included at Figure 3.
10 Wrexham County Borough Council Annual Progress Report 2002/3
1.27. The LTP fully accords with all the following documents;
. The Transport Framework for Wales . The National Economic Development Strategy – A Winning Wales . Wales Spatial Plan . Planning Guidance (Wales) : Planning Policy . Public Transport Policy Review . Communities First Guidance
URBAN II and the Local Transport Plan 1.28. Wrexham Urban II is a community initiative which has been awarded £6.4 million from WAG up to 2006. It covers the communities of Brymbo, Bryn Cefn, Coedpoeth, Gwenfro, Gwersyllt, Llay and New Broughton. ). As requested by WAG in their feedback of the first APR a location plan is now included at Figure 3.
1.29. The aim of the programme is to encourage the continued economic growth of West Wrexham by supporting the residents and business communities. The vision is ‘the creation of a strong, participating, entrepreneurial community where people work together to create desirable places to live, and where residents are empowered to participate in the local economy and everyday life’.
1.30. To move towards achieving the vision, four strategic themes have been identified;
. the development of stronger and more inclusive communities; . business and enterprise development; . education, skills and training; . the development of an attractive, functional, accessible and productive environment.
1.31. To implement these themes are two priorities, each with two measures, which will contribute directly to the overall West Wrexham URBAN II strategy. Priority 1: 1.1 Entrepreneurship and business development 1.2 Development of competitive and sustainable businesses Priority 2: 2.1 Overcoming barriers to participation 2.2. Developing active communities
1.32. Priority 2 demonstrates support for community transport to encourage access for individuals and groups to participate in community activities and to improve community integration. The West Wrexham Action Plan, under key objectives, indicates the need for Community transport. Finally the five local community councils also show a need for community transport within their Action Plans.
11 Wrexham County Borough Council Annual Progress Report 2002/3
Figure 3 - Wrexham Communities First and Urban II strategy area
12 Wrexham County Borough Council Annual Progress Report 2002/3
Policy Agreements 1.33. In February 2001, WCBC confirmed to WAG of its willingness to enter into a Policy Agreement. The objectives and performance measures were submitted to the Assembly in March 2001.
1.34. The key objectives were; better opportunities for learning better health and well-being better stronger economy better quality of life
1.35. The objective for a “better stronger economy” has a target of monitoring modal shift. WCBC is currently working with its Taith partners to develop an appropriate transport model in order for data for monitoring modal shift to be collected.
Changes within the Regional Context 1.36. The Taith consortium is the sub group of the North Wales Economic Forum that deals with all transport matters for the region. Wrexham County Borough Council is an active member of Taith and during 02/03 the following have been achieved; . the appointment of a Regional Travel Plan Co-ordinator . the development of the Regional Bus Strategy
1.37. More information on the Taith consortium is contained within Section 5. In recognition of the increased importance of a regional approach on all .
1.38. WCBC are active members of the Taith group and in implementing the Wrexham LTP have full regard to how it can contribute to achieving the overall vision and key aims of Taith.
1.39. Further details of partnerships are included in Section 5.
Changes within Local Context Wrexham Bus Station 1.40. Phase 1 of the Wrexham Bus Station opened to the public in June 2003. Many of its features are now accessible to passengers, however the full Bus Station will be open in November when the site will be fully accessible and passengers will benefit from modern, purpose built and fully covered waiting accommodation with enhanced electronic information on overhead displays.
1.41. The design of the new bus station and the complementary traffic management scheme mean that the conflict between buses and pedestrians is minimised and the area is fully accessible to wheelchair users. The Shopmobility scheme will in future operate from the bus station with limited parking for disabled blue badge holders. Additionally a new taxi rank facility has been incorporated so that the new hackney carriages can deploy their ramps for wheelchair users.
13 Wrexham County Borough Council Annual Progress Report 2002/3
Development of Eagles Meadow for a large Waitrose/John Lewis Store 1.42. This major redevelopment will involve a new town centre store with a two storey car park. The current road system will be amended significantly with a major flyover removed and a new gyratory built. Measures will be implemented to prevent rat running into adjacent residential areas. Cycle routes, improved pedestrian routes, (including a new footbridge) will be implemented into the design. The scheme will enhance the town centre which is well served by public transport, particularly by the new bus station.
Regeneration of the Bridge Street area of the town centre for retail, leisure and housing 1.43. This development on the periphery of the town centre involves redevelopment of a brownfield site, demolition of low quality properties and replacement with high density, high quality apartments. This is a good use of land in sustainable transport terms due to the proximity of the town centre facilities and public transport.
Development of the Wrexham Lager Brewery Site 1.44. This retail development on the periphery of the town centre involves the construction of a gyratory road scheme with contraflow bus lanes and cycle lanes. The current road network which is used by the majority of the buses to the towns new bus station currently suffer congestion at peak periods. Removal of the congestion will result in more reliable bus journey times and generally enhance public transport.
Development of the Brymbo Steelworks for employment and housing 1.45. This development will include a new spine road which will enhance access to the village of Brymbo and reduce traffic through the Southsea/New Broughton area.
Development of the area allocated for Phase 3 of the Wrexham Technology Park for employment and housing 1.46. Detailed planning is underway for this large scale development to the West of Wrexham town centre. The design will incorporate public transport provision, possibly in connection with the Maelor Hospital and will incorporate a cycle route/footpath connecting the town centre to Gatewen (new housing development), Brymbo and Southsea.
Key Developments Study 1.47. In recognition of the potential within the town for developments, in July 2001 the Council commissioned Symonds Consultants to prepare a comprehensive transport assessment of key development sites within Wrexham. The study was funded by the WDA.
1.48. The Council commissioned the study to concern regarding the cumulative effect of traffic generation from proposed development opportunities within the Western gateway area (main access from the A483 into Wrexham(, and the subsequent capability of the existing highway networks ability to cope with this increase in traffic.
14 Wrexham County Borough Council Annual Progress Report 2002/3
1.49. The report considers various sites and identifies a number of improvements to the existing network that are considered necessary to accommodate traffic flows associated with the overall development of the Western Gateway and to provide good access by other modes.
1.50. The study has helped to form the basis for the design of all the planned developments listed previously.
Wrexham Unitary Development Plan 1.51. The Public Inquiry into the objections made to the Deposit Edition of the Plan was held between April and July 2002 and the Inspector’s Report was received in January 2003. His recommendations, together with the proposed responses to them, have now been considered by the Planning Policy Panel, the Planning Committee, the Executive Board and the full Council. In most cases the Council has agreed to accept the Inspector’s recommendations.
1.52. Proposed modifications to the Plan will now be published for a minimum six week period during July and August. The modifications will comprise :-
changes recommended by the Inspector and to which the Council agrees; changes proposed by the Council but not recommended by the Inspector; changes proposed prior to the Public Inquiry but which have not yet been the subject of formal consultation and publicity.
1.53. Representations must be related to the proposed modifications only and not to issues which have previously been examined. Between September and December, the Council will need to respond to all the representations made on the proposed modifications and, in particular, decide whether any are of sufficient weight to merit a second public inquiry. If no second inquiry is needed, it is intended that the Council should agree the final version of the Plan early in 2004. Arrangements will then be made to take the Plan forward to formal adoption, probably in April.
1.54. From a transportation point of view, the key modifications will involve the following changes to the main highway improvement policies:-
Policy T4 - A5156 Acton Roundabout/Llanypwll/Cross Lanes Proposed improvement retained but no line to be shown on Proposals Map
Policy T5 - A541 Gwersyllt : Stansty Road to Park Wall Improvement deleted and replaced by traffic management scheme to be included in Policy
Policy T7 - A541 Sydallt to Rackery Lane, Llay Improvement deleted
15 Wrexham County Borough Council Annual Progress Report 2002/3
A525 Coedpoeth and Bwlchgwyn By-pass Improvement deleted
A525 Raggs Hill, east of Bangor is y Coed Improvement deleted
1.55. An additional reference will be made in the Plan to the effect that the Local Transport Plan will form the basis for defining the Council’s future road improvement strategy.
Rail Franchise 1.56. The two rail lines, which serve the County Borough will form part of the new all Wales rail franchise which will start operation on October 12th 2003. Currently 4 bids have been shortlisted with the new franchise holder due to be announced late June 2003. The final bidders are; . Wales & Borders Trains (Nx Group) . Serco and Netherlands Railway (Joint Bid) . Arriva . GB Railways and Connex (Joint Bid)
1.57. The two lines are currently run by two different train operating companies. The Wrexham Bidston Line is run by First North Western who will relinquish the operation of the line in September 2003 ready for transfer to the successful bidder. The line currently has an hourly service. Line speeds are low but are governed by the many frequent station stops at towns and villages that it serves.
1.58. The Chester to Shrewsbury Line transferred from Central Trains operating in October 2001 to Wales & Borders Trains in preparation for the new franchise. In the last twelve months the frequency of the trains on this line has risen above the PSR (public service requirement) and trains are now running hourly until early afternoon and then again in the early evening, outside these times the service returns to its former two hourly pattern. The re-routing of direct Holyhead to Cardiff trains via this line and stopping at all stations here has proved popular. This combined with increased services and promotion of the service has resulted in average passenger increase of 17% with all stations showing increases. Wrexham General figures report an increase of 48%.
1.59. Wales & Borders Trains have also implemented an RPP (Rail Passenger Partnership Bid) to improve communications across their network. Project Inform Cymru will deliver train announcements to all the stations on this line with help points also at the rural stations. Wrexham General will also have screens and a PA system installed.
1.60. Work by the Rail Officer for this line to promote the service continues with bespoke timetables being produced for the local residents. A line guide and web site to promote visitors from outside the area has also been established.
16 Wrexham County Borough Council Annual Progress Report 2002/3
1.61. Engineering work to replace long sections of track along this line has been undertaken during 2002/2003. Linespeeds remain at 70mph
Decriminalised Parking Enforcement 1.62. Decriminalisation of parking enforcement (DPE) involves the transfer of on street parking powers for non-endorsable offences from the Police to the Local Authority. Currently in Wrexham off street parking in the town centre is enforced by the Councils car park attendants and the on street parking throughout the County Borough is enforced by a traffic warden employed by North Wales Police.
1.63. In October 2002, the Council employed specialist consultants to undertake a feasibility study to investigate the financial and organisational implications of DPE in Wrexham County Borough. The consultants have worked closely with the Council regarding the study and the final report was published in April 2003.
1.64. The Consultants used a computer model to evaluate the financial change as a result of implementing DPE. The report indicated that £234k is required to cover the set up costs in order for the Council to take on the powers required.
1.65. The Council is currently considering the financial implications of the report in order to make a decision as to whether to progress DPE.
Funding 1.66. During the second year of the LTP The Council has secured funding from various sources including Transport Grant, Safe Routes to School, Local Road Safety Grant, developers, Welsh Development Agency and Community Councils. More information on funding is detailed in Section 6.
Funding Sources (2002/3)
. Transport Grant (WAG) . Safe Routes to School (WAG) . Welsh Development Agency . Local Road Safety Grant . Community Councils . Developers
Public Consultation 1.67. The Council recognises that consultation and partnership are essential in delivering solutions to the transport problems of the County Borough. The LTP states that the Council is ‘committed to listening and working with others to develop solutions that have local support and meet local needs’ and the Council is committed to public consultation which is undertaken on all schemes.
17 Wrexham County Borough Council Annual Progress Report 2002/3
1.68. This APR is available to the public via the WCBC web site and free copies are also available on request. The Council will publicise the production of the document to all stakeholders and electronic and large print and welsh version of the document are available on request.
1.69. The feedback on the APR 2001/2 from WAG asked the Council to consider whether the APR should be the basis for some dialogue with stakeholders. The Council acknowledges the importance of stakeholder involvement and to date have achieved this through consultation for individual schemes rather than an overall general consultation.
1.70. As the LTP is now half way through its plan period the Council is intending to undertake a comprehensive public consultation exercise in the Autumn of 2003. The exercise will invite stakeholders to comment on the progress of the plan and on the work the Council has been undertaking. The Council will obtain more detailed comments from a variety of stakeholders on the LTP strategy, the schemes implemented and how people consider the Council is progressing towards meetings its overall objectives and targets.
Consultation
. Comprehensive public consultation exercise planned for Autumn 2003 . Results will assist the Council in shaping its transport strategy for the remainder of the current LTP and beyond the end of the current plan period in 2006
1.71. The Council acknowledge that the LTP must be flexible and capable of responding to changing prioritise and aspirations. Information obtained from the consultation exercise will assist the Council in developing its transport strategy beyond the end of the current plan period in 2006.
18 Wrexham County Borough Council Annual Progress Report 2002/3
2. IMPROVEMENTS TO LOCAL TRANSPORT PLAN
General 2.1. The Local Transport Plan (LTP) has proved to be an extremely robust document that has allowed the Council to make significant progress on improving transport. However, it is acknowledged that the document could be improved. In the first Annual Progress Report some omissions were highlighted and new sections of the LTP were added as a result regarding the following; Congestion, Workplace Parking Charges and Parking Standards Decriminalised Parking Disability Provision Taxis/Private Hire Vehicles Local Transport Services Grant (previously Rural Bus Subsidy Grant)
Please refer to WCBC’s APR 2001/2 for further details.
Amendment to the LTP 2.2. Since the submission of the first annual progress report the following area has been identified as requiring changes/improvements;
Amendment
Page 46 – paragraph 4.159 regarding the A541 Hope/Caergwrle Bypass reads;
“ With current transportation policies it is unlikely that such as scheme could be supported”
This sentence has been misinterpreted and therefore to avoid confusion this should be changed to;
“With current transportation policies it is unlikely that such a scheme could be financed in the short to medium term”.
Improvements to the APR 2.3. The feedback from WAG agreed that the areas identified for improvement in last years APR will be dealt with in the next LTP. The feedback however did also raise issue that the following areas need to be addressed in the APR in order for the Assembly to ensure that the LTP implementation is achieving what is required. . Trend information on traffic movements including cross-boundary movements and commuter trips. . Assessment and discussion of trends in traffic growth . Identification of likely problem areas for air quality and noise.
19 Wrexham County Borough Council Annual Progress Report 2002/3
Trend Information on traffic movements 2.4. The following table illustrates the change in traffic flows on 9 sections of the trunk road between 1998 and 2002. Traffic on all the trunk roads in the County Borough has increased and on average there has been a 2.75% increase in traffic per year over the 4 year period.
average % LINK 1998 2002 change per year A483 Rossett BP 31858 34464 2.05 A483 Gresford BP 31920 33875 1.53 A483 Wrexham North 39033 43947 3.15 A483 Wrexham Mid 39946 42325 1.49 A483 Wrexham South 34106 40150 4.43 A483 Ruabon BP 30198 33491 2.73 A483 Newbridge BP 19915 22742 3.55 A483 Chirk BP 19839 22313 3.12 Average 2.75
2.5. The following table illustrates the change in traffic flows on 12 sections of County Roads. The largest increase in traffic is on the section of the A534 near Hugmore Lane. Several sections of County Roads have experienced a slight decrease in traffic flows.
average % Location 1998 1999 2000 2001 2002 change per year A528 Cockbank - 2571 - - 2782 2.73 A525 Kingsmill 10379 - - - 11661 3.08 A525 Porthwgan - 5720 - - 5716 -0.33 A541 Gwersyllt - 16103 - - 17686 3.27 A5152 Ruabon Rd 12373 - - - 13875 3.03 A5152 Chester Rd 11689 - - - 13836 4.58 B5101 Berse Road 16816 - - - 15230 -2.25 A525 Ruthin Road 10957 - - - 10178 -2.30 A534 Hugmore Lane) - 12229 - - 14407 5.93 A534 (Plas Goulbourne) 10805 - - - 10461 -0.80 A5156 Link Road 14266 - - - 14780 0.90 A539 Eglwys Cross 1640 - - 1528 -2.30 Average 1.29
Air quality and noise 2.6. The Council is currently completing the second round of review and assessments of air quality in the Borough. Traffic related pollution, nitrogen dioxide and particles (N02 and PM10) are predicted to have a limited impact on air quality over the next three years. The situation will continue to be reviewed as part of the air quality strategy. New planning applications for 20 Wrexham County Borough Council Annual Progress Report 2002/3
road development will be expected to provide information to address any issues relating to the potential for noise or poor air quality. In addition the Council will focus over the next 18 months on providing data to map noise and air quality in some areas of the County Borough in order to identify potential problem areas for the future.
Local Authority Bus Strategy 2.7. The Draft Local Bus Strategy was submitted to WAG in June 2002. Since the submission of the draft document WAG have issued further guidance on the preparation of Local Authority Bus Strategies (LABS) and as such changes have been made to the first draft. The draft LABS for Wrexham is now included in Volume 2 of the LTP.
2.8. The LABS for Wrexham has been submitted to WAG as a separate document.
Regional Public Transport Strategies 2.9. The Regional Public Transport Strategy for the Taith region will be completed at the end of June 2003.
21 Wrexham County Borough Council Annual Progress Report 2002/3
3. PROGRESS General Overview 3.1. The Council has made great progress during 2002/3 and there have been many notable achievements to meet the objectives and targets of the LTP. These include the following;
Achievements
. Construction of Wrexham’s new Bus Station (Phase 1 completed in June 2003) . Completion of the first stage of the Wrexham Industrial Estate Access Road . Several safe routes to schools schemes . Arrive Alive Campaign – speed enforcement partnership . Free Concessionary Travel scheme . Fully accessible town centre for wheelchair users . “Education Quality Partnerships” for 20 school contracts . Continued improvement of Cycling and Walking facilities
3.2. Progress towards meeting the targets contained in the LTP includes;
Progress
. 98% of pedestrian crossings now have facilities for the disabled . 83% reduction in the number of children killed or seriously injured (94-98 average compared to 2002) . 27% reduction in the number killed or seriously injured . 55% increase in the number of children who received cycle training between 2000 and 2002 . 21% of Wrexham’s buses are now low floor . 150 bus stops have been improved with bus boarding features . The number of concessionary travel pass holders has increased from 7000 in 2001 to 17000 in 2002
3.3. Despite taking these considerable steps forward, the Council has also had set backs regarding the remaining sections of the Wrexham Industrial Estates Access road and the dualling of the A483 from Ruabon to Shrewsbury. These set backs will result in delays to the original programme.
Improved Access to Wrexham Industrial Estate 3.4. The first section of the Improved Access to Wrexham Industrial Estate – Gresford Interchange to Borras Road Roundabout, was complete on the 18 September 2002. The remainder of the scheme from the Borras Road Roundabout to the A525 was due to begin on site in September 2003. However following a Public Inquiry into the remaining section WAG declined to confirm the orders due to concerns relating to a number of environmental 22 Wrexham County Borough Council Annual Progress Report 2002/3
issues. To address these issues the Council is now reviewing the scheme and is carrying out an Environmental Impact Assessment. The latest programme for the scheme has the start of construction being 2007.
A483 – Dualling Ruabon to Shrewsbury 3.5. During 2002/3 the Council received the disappointing news from the Government Office for the West Midlands stating that the Secretary of State has carefully considered the study report and the views of local stakeholders. He had noted that the study only recommended dualling of the complete route between Shrewsbury and Ruabon in the long term. The conclusion therefore is that in the context of other transport priorities and the resources available within the 10 year investment plan, complete dualling is not an affordable option.
3.6. It was subsequently reported to members that the complete dualling of the A5/A483 from Shrewsbury to Wrexham will be long term. Members' instructions were invited. Due to the significance of this scheme to the County Borough, and indeed as part of the Trans European Road Network, the Council has resolved to continue to lobby support for commitment to the dualling of the section of the Trunk Road from Shrewsbury to Wrexham, through WAG and neighbouring authorities.
Meeting the Objectives, Policies & Targets and Programme 3.7. This section sets out the progress made between April 2002 and March 2003 and describes progress made towards meeting the, Objectives Policies and Targets Programme
Objectives 3.8. The main objectives of the LTP are listed below including examples of how The Council is working towards achieving them.
Objective 1 – Integrated Transport
The Council aims to encourage and develop the existing transport system in order to achieve a high quality public transport network, cycling and walking network, whilst recognising that there may still have to be selective road improvements.
Examples: Improvements to bus routes including new shelters, timetable provision and the introduction of low floor buses, “Education Quality Partnerships” for free school transport – a partnership for 20 school contracts Commencement of works on the new Wrexham bus station to be completed late 2003 Significant improvements to walking and cycling routes including new crossing facilities and traffic calming,
23 Wrexham County Borough Council Annual Progress Report 2002/3
Completion of the first section of the A5156 Improved Access to Wrexham Industrial Estate from Gresford Interchange to Borras Park Roundabout.
Objective 2 – Safety/Accident Reduction
The Council aims to substantially reduce the number of road traffic accidents in the County Borough through the implementation of its Road Safety Plan.
Examples: Development and introduction of several safe routes to school schemes, Child road safety project entitled “Stay Safe” Development of “999 react” programme in conjunction with the emergency services Speed reduction traffic calming schemes, Arrive Alive project - Speed enforcement cameras in partnership with North Wales Police and others Targeted road safety messages on car park tickets, Road safety dramas productions at most primary and secondary schools Local safety schemes.
Objective 3 – Environment
The Council is committed to the principles of Local Agenda 21 and to safeguarding the environment.
Examples: Annual Green Fair to promote LA21 and highlight the impact of transport on the environment, Sustainability Group set up within the Council to incorporate Sustainability into all aspects of the Council Monitoring of air quality, Regular LA21 Forum meetings with local businesses and environmental groups.
Objective 4 – Economic Growth And Tourism
The Council aims to provide a transport infrastructure which will support the County Boroughs economy and local employment and support sustainable economic growth in the urban and rural areas.
Examples: URBAN II initiative, Completion of Phase 1 of the Wrexham Industrial Estate Access Road scheme.
24 Wrexham County Borough Council Annual Progress Report 2002/3
Objective 5 – Crime and Disorder
The Councils aims to improve personal security for transport passengers and pedestrians.
Examples: CCTV coverage of town centre and car parks, Consideration of personal safety in the design of all cycle, pedestrian, public transport and car park improvement schemes, Regular liaison with North Wales Police through monthly Crime and Disorder meetings.
Objective 6 - Anti-poverty and Social Exclusion
The Council aims to tackle poverty and social exclusion and promote accessibility to everyday facilities for all, especially the most vulnerable members of society and those without a car.
Examples: Safe routes to school schemes identified using multiple deprivation index, Local safety schemes targeted at socially deprived areas with above average accidents rates, URBAN II initiative. Free Concessionary travel (Wrexham was the first authority to ensure that all applicants were issued with a pass on day one of the scheme) Community transport study completed – study recommendations being implemented from 2003/2004. Council granted aid to Chariotts dial a ride for the purchase of an additional vehicle which was fully accessible for wheel chair users. Taxi Bus System has seen a further scheme added and a growth in usage.
Objective 7 - Health
The Council aims to improve the health of its residents by reducing pollution and encouraging healthier forms of transport such as walking and cycling.
Examples: Green promotion fair, Provision of facilities to assist with walking and cycling, ‘Walk Your Way to Health’ promotion in conjunction with Groundwork, G.P. referral scheme for local leisure centres.
25 Wrexham County Borough Council Annual Progress Report 2002/3
Objective 8 - Accessibility
The Council aims to make transport accessible to all with every member of the population having the opportunity for independent mobility.
Examples: Promotion of Shopmobility scheme in Wrexham, Free unlimited duration disabled car parking in Council car parks, Inclusion of facilities to assist those with mobility impairments in cycling, walking and public transport schemes. Whole of Wrexham town centre is now fully accessible to wheelchair users following a Council funded mobility scheme. (This also enabled improvements in the centre of many towns and villages throughout the County Borough).
Progress towards meeting Policies and Targets 3.9. There are 193 policies and targets contained within the LTP and its associated daughter strategies. These are included at Appendix 2 with a summary of the progress made towards implementing the policy.
Progress towards meeting the Programme 3.10. The following tables outline the progress made to date on each scheme and sets out the status of each scheme in terms of funding, planning, construction (where applicable), accessibility and integration.
3.11. The shaded boxes denote where text changes have occurred since the production of last years APR.
26 Wrexham County Borough Council Annual Progress Report 2002/3
A WALKING AND CYCLING Brief Description Development of Wrexham County Borough Cycle Network, including of Scheme crossing facilities, on and off road cycle lanes and traffic calming features. New and improved pedestrian facilities including new crossing facilities, refuges and signposting. Includes the creation of specific routes; Chester - Trawsfynydd via Wrexham and Wrexham town centre to Gatewen and Brymbo. Benefits Provides a realistic alternative to the car for shorter journeys Integrates with facilities provided by private developers both within and outside the developments Walking schemes include provisions for the mobility impaired and therefore improve accessibility Improves health of population Progress . Upgraded pelican to puffin on A539 (examples) . 9 pedestrian refuges constructed at various locations. . 800m on road and 500m of off road cycle lanes including corduroy tactiles, red surfacing, footway widening and segregated footway and cycling on Holt Road . New Pelican crossing on A541 . New toucan crossings on Holt Road . 2 new zebra crossings to replace one pelican . Several safe routes to school schemes Funding 2002/3 - £162k (Transport Grant) £100k (Developers) Comments Package Bid A is continuing however funding has been given for Phase One of the Urban Villages Initiative Package in 2003/4 therefore improvements to walking and cycling will be on-going.
Previously there were 3 three different categories under “A Walking and Cycling” however as these categories were all interrelated these have been combined for clarity. The previous categories were “A1 General”, “A2 National Cycle Route:Chester-Wrexham-Llangollen-Trawsfynydd” and” A3 Wrexham Town centre to Gatewen and Brymbo.”
27 Wrexham County Borough Council Annual Progress Report 2002/3
B SAFE ROUTES TO SCHOOL Brief Description The aim of these schemes is to provide a safe environment for children of Scheme and parents to walk or cycle to school. Benefits Improved safety and health of pupils travelling to school Reduction in road accidents and vehicle flows Reduced congestion around schools Increased traffic awareness skills for the children Improved environmental conditions around the schools Progress The three schools which were developed during 02/03 were Ruabon High School, Ysgol y Wern in Rhos and Ysgol Penrhyn in New Broughton. Groundwork have continued to work with WCBC to provide the interface and schemes have included “planning for real exercises”. Groundwork have assisted in the questionnaires, posters and workshops and have engaged the whole school in the consultation process. Re-visits to the schools to follow up the schemes are to be arranged in the Autumn Term. Funding 2002/3- £107k Comments Further Transport Grant bid was submitted in August 2002 for additional Safe Routes Schemes and through this the Council has secured an £36k for 2003-04.
C MOBILITY IMPAIRED Brief Description To reduce physical barriers that inhibit those with mobility impairments of Scheme through the provision of dropped kerbs, tactile paving. Benefits Increased accessibility for those with mobility impairments Progress . WCBC spent 200k to provide tactile paving covering virtually all of Wrexham town centre and many town and village centres. . 98% of pedestrian crossings have facilities for disabled people (as performance indicators). . Radial bus routes now have bus boarders and low floor buses are in use on many routes. . Dropped crossings and tactile paving installed throughout the town centre. Funding 2002/3 - £200k Comments Future new build and reconstruction will include dropped crossings and tactiles. A capital bid has been made for WCBC funding for additional dropped crossings and tactiles from 2004 onwards.
28
Dropped kerbs and central refuge provided at Croesfoel Wrexham County Borough Council Annual Progress Report 2002/3
D PUBLIC TRANSPORT D1 Wrexham Bus Station Brief Description Renewal and rebuilding of Bus Station of Scheme Benefits Major improvements in facilities and accessibility Progress Phase 1 opened in June 2003. Funding 2002/3- £688k (Transport Grant) £105k (WDA) Comments The full Bus Station will be open in November when the site will be fully accessible and passengers will benefit from modern, purpose built and fully covered waiting accommodation with enhanced electronic information on overhead displays
D2 Quality Bus Measures Brief Description Improvements to selected corridors and routes of Scheme Benefits Modal shift and better accessibility Progress Services 1, 3, 4, 35, 39 and 146 complete Funding 2002/3- £20k Comments Implemented as a voluntary partnership with the bus operators. Significant expansion of quality measures has taken place – operators have provided 11 low floor buses, 150 bus stops have been improved and 21% of Wrexham’s buses are now low floor.
D3 Bus/Rail Interchange Measures Brief Description Measures to improve accessibility and interchange between bus and rail of Scheme Benefits Improve station access and encourage modal shift Progress The Council is developing a major project for the enhancement of interchange facilities at Ruabon station providing a dedicated parking area and a bus/rail interchange point. Funding 2002/3 – nil
D4 Network Ticketing/Smart ticketing/CCTV/Real Time Information Brief Description The introduction of network ticketing and smart cards on bus routes along of Scheme with the provision of real time information systems and CCTV. Benefits Improve and streamline use of public transport. Improve safety Progress Ticket machines were introduced on all Arriva buses which are compatible with the smart card technology. Smartcards issued for free travel. Funding 2002/3 - £800k Comments Funded By Taith
29 Wrexham County Borough Council Annual Progress Report 2002/3
D PUBLIC TRANSPORT continued D5 Mold Road/Grosvenor Road Gyratory Brief Description This junction is a key junction in Wrexham being the main access to the of Scheme town centre and one which the majority of buses pass through en route to the bus station. The existing junction is congested and a major improvement scheme is required at this junction in order to continue the high quality environmental corridor from the A483 into Wrexham town centre which has been funded by the WDA. Benefits Reduce congestion for buses and other vehicles Reduce travelling times for emergency vehicles from the Fire Station and the Maelor Hospital which are both situated nearby Improve the image of the main approach in to Wrexham from the A483 Improve walking and cycling facilities Progress The Brewery has now closed and planning permission has been granted subject to approval from WAG Funding 2002/3 – nil Comments The quantity of funding from the ‘public purse’ will depend on the future use and design of the redevelopment. Provisional funding of £900k is sought from Transport Grant however the developer will now meet the majority of the funding with circa £200k required from the public purse. The introduction of a gyratory scheme at the junction was included as a key element with in the Key Developments Study.
D6 New Rail Station at Johnstown Brief Description A need for a new station at Johnstown has been identified of Scheme Benefits Encourages modal shift Progress Awaiting new Train Operating Company Funding 2002/3 – Nil Comments Unlikely to progress within current plan period
30 Wrexham County Borough Council Annual Progress Report 2002/3
E CAR REDUCTION E1 Park and Ride Brief Description To provide a Park and Ride scheme on the outskirts of Wrexham to serve of Scheme the town centre. Benefits Reduce congestion in the town centre Control parking demand in the town centre Provide cost effective long stay parking for the town centre Progress The Key Developments Study has confirmed a location for the Park and Ride Site to the north of the A483 adjacent to the A541 Mold Road. Funding 2002/3 – nil Comments The Park and Ride scheme is unlikely to progress within the current plan period.
E2 Car Park Management/Residents Parking Brief Description To provide a residents parking scheme on the outskirts of Wrexham town of Scheme centre. The introduction of car park management systems to prevent motorists driving from one car park to another. Benefits Reduces congestion and pollution from cars driving around for spaces in car parks Improve traffic flow around the town centre Reduces problems in residential areas Progress A study was undertaken in November 2001 to ascertain the nature of parking problems in Wrexham town centre. Funding 2002/3 – nil Comments A survey is being undertaken in June 2003 to update the study that was conducted in 2001 and the issue will then be reviewed. A decriminalised parking review is currently in hand. If adopted set up costs of £234 will be required to be funded from WCBC.
31 Wrexham County Borough Council Annual Progress Report 2002/3
F Accident Reduction Brief Description General studies of accident statistics are used to identify areas where of Scheme accidents reoccur. These areas are then treated using engineering measures. Benefits Cost effective – First Year Rate of Returns of over 550% have been achieved Financial saving – hospital care, time off work, car repair Pain, grief and suffering savings Progress Accident reduction schemes implemented at the following locations; . B5102 Llay Road, Croeshowell Rd jnct. Station Rd . B5101 Berse Road/Gatewen Road . Bersham Road/Brymbo Link Road . A539 Wrexham Road/Argoes Lane, Overton . A525 Ruthin Road/Croesnewydd Road . Afoneitha Estate, Penycae . B5425 Llay to Wrexham Route Study . Sontley Road/Fairy Road . A525 Ruthin Road/B5430 old Road, Bwlchgwyn Non –engineering measures have included road safety plays, Child pedestrian co-ordinator, radio adverts, children’s traffic club, teacher training days, flourescent waistcoats and reins. Funding 2002/3 - £257k (includes £42k for non engineering measures) Comments Engineering schemes included a variety of measures such as advanced warning signs, skid resistance treatments, junction improvements. traffic calming and coloured surfacing. Progress is reported more fully in the Local Road Safety Grant report which is submitted to WAG June 2003.
G Travel Awareness Brief Description To promote travel awareness throughout the County Borough, promote of Scheme green transport and raising awareness of alternatives to the private car. (Including achieving this through the promotion of staff and school travel plans). Benefits Reduced reliance on the private car Reduced emissions Raises awareness and raise profile of green transport Improves health and fitness of population Progress . Green fair held in Queens Square on June 8th 2002 to promote green transport. . Green message promoted to Council staff via newsletters and payslips. Use of “Give your car a holiday” logo. . Adverts on rear of car parking pay and display tickets promote alternatives to the car. . Requirement for developers to submit green travel plans, . Creation of Sustainability Working Group incorporating travel awareness. . Regional Travel Plan Co-ordinator appointed and employed by Taith Funding 2002/3 – nil H Traffic Calming 32 Wrexham County Borough Council Annual Progress Report 2002/3
Brief Description Reducing speeds on roads to reduce accidents and traffic flows and to of Scheme encourage sustainable transport modes including walking to school. Additional environmental benefits are achieved in respect of noise, pollution and social interaction. Benefits Reduction in speed and accidents Discourages the use of cars Can discourage rat running where alternative and more suitable routes are available Encourages cycling and walking as fear of traffic is reduced Environmental benefits in respect of noise, pollution and social interaction Progress Schemes have been implemented only as part of Walking and Cycling General (see section A) and Safe Routes to School (see section B). Funding 2001/2 – Nil (However several schemes have been implemented from alternative budgets e.g. SRTS and Local Safety Schemes.) To prioritise schemes, a scoring system has been agreed by the Council. Comments Significant public support is received for traffic calming schemes and the Council regularly receive numerous requests for additional roads to be traffic calmed. These requests far outnumber the available resources. £250k allocated by WCBC for 2003/4.
I Roads I1 Wrexham Industrial Estate Access Road Brief Description To provide improved access to Wrexham Industrial Estate from both the of Scheme north and south and provide a new link bypassing Wrexham to the north- east between the A525 and the A483. Benefits Reduce congestion, including traffic rat running through the town centre Improved marketability of undeveloped sites on the Industrial Estate Increase accessibility Reduce negative environmental effects on other parts of the network in semi-rural areas Progress The first section of this scheme, Gresford Interchange to Borras Road Roundabout, was completed ahead of schedule and was open to traffic on the 18 September 2002. Funding 2002/3 - £2112 Comments The remaining section of the scheme was subject to a Public Inquiry held in February 2002. The outcome of the Inquiry was the non-confirmation of the orders due to concerns relating to a number of environmental issues. The authority is now reviewing the scheme and is currently carrying out an Environmental Impact Assessment. As a result the programme for this scheme now has a contract start date of March 2007 subject to the successful completion of the statutory procedures and finances being made available.
33 Wrexham County Borough Council Annual Progress Report 2002/3
I Roads continued I2 A55/A483 Junction South of Chester Brief Description This junction is in Cheshire but the problems have a significant impact on of Scheme Wrexham County Borough. This is a grade separated interchange between two major dual carriageway trunk roads. The upper level is controlled by traffic signals. Long queues, often exceeding 1 mile, occur in the mornings from Wrexham causing significant delays and rat running in the Counties of Cheshire, Flintshire and Cheshire. Major road works are required to relieve current congestion. Benefits Reduced journey times (including reducing journey times for the major bus route between Wrexham and Chester) Reduction in pollution from stationary vehicles Improved accessibility for local areas Increased attractiveness of Wrexham County Borough as a place to live, work and for businesses to locate. Progress Limited improvements on the Chester side of the junction to provide a free flow slip to the A55 have been completed and further measures funded by a developer are planned for the near future. Further improvements are being considered by the Highways Agency. Funding 2002/3 – nil
I3 A483 – Dualling Ruabon to Shrewsbury Brief Description The section of road is the only single carriageway section of road on this of Scheme important Transport European Highway network which more locally is the main road linking the County Borough to the West Midlands, Mid/South Wales, North West England and North Wales. Large volumes of traffic travel on this road and the nature of the single carriageway with at grade roundabouts means that there is little opportunity to overtake and there is concern regarding the number of serious and fatal accidents. In order to bring the road up to standard with the rest of the route it requires dualling. Benefits Reduction in accidents, delays and congestion A483/A5 route is of critical importance to the whole of North Wales – not just Wrexham Progress The Local Government Office for the West Midlands appointed consultants to look at the A483 from Shrewsbury to Chester. The final report of the A5/A483 Shrewsbury to Chester Road Based Study made several recommendations however the Secretary of State concluded that “complete dualling is not an affordable option”. (within the 10 year investment plan) Funding 2002/3 - nil Comments The Council is very disappointed that the complete dualling of the A5/A483 from Shrewsbury to Wrexham will be very long term and have resolved to continue to lobby support for the scheme.
34 Wrexham County Borough Council Annual Progress Report 2002/3
I Roads continued I4 Watery Road/Bradley Road Junction, Wrexham Brief Description To improve Watery Road/Croesnewydd Road west of Bradley Road of Scheme Benefits Improved accessibility Reduced congestion Reduced journey times especially for emergency vehicles Progress No progress to date. Funding 2002/3 – nil Comments Limited improvement works will be undertaken by Developers as part of the Wrexham Lager Brewery Redevelopment. Planning permission has been approved by WCBC and is subject to WAG approval.
I5 A541 Gwersyllt Improvement Brief Description Proposal which was granted planning permission in 1995 was to dual the of Scheme A541 from Stansty Road to the Park Wall, provide a roundabout at the Wheatsheaf Junction and a separate access roads to the Holy Trinity church and the retail and commercial premises at the former Westminster Colliery Site. Benefits Increased safety Increased accessibility to local amenities Improvement of area Progress No progress to date – awaiting the outcome of the A541/A550 Corridor Study. However it is felt that a review of the original proposal is necessary with an emphasis more on the severance of the Gwersyllt community by the A541, better provision of pedestrian and cycling facilities and to accommodate future developments along this section of the A541. Funding 2002/3 – nil Comments Outcome of Study is expected in July 2003.
I6 A525 Ragg’s Hill, East of Bangor on Dee Brief Description Improve a sub standard length of road which is on the main route from the of Scheme Wrexham Industrial Estate to the A41 at Whitchurch, in particular the bend at Ragg’s Hill. Benefits Reduced accidents Consistency of route Improvement of sub standard section of carriageway Progress No progress made Funding 2002/3 – nil
35 Wrexham County Borough Council Annual Progress Report 2002/3
I Roads continued I7 Plas Bennions Road, Ruabon Brief Description On line improvement to Plas Bennions Road over a length of of Scheme approximately 230m providing a carriageway width of a constant 6m and the provision of a footway enabling safe pedestrian passage for the public residing along the road. Benefits Improved safety for pedestrians and vehicles Reduced accidents Improved environmental conditions for residents Progress No progress made Funding 2002/3 – nil Comments Programmed for 04/05
I8 Stryt Las, Rhos Brief Description The improvement at the bottom of Stryt Las from its junction with the of Scheme B5605 to a point 300m east comprising of widening the road to a constant width and the provision of a footway. Benefits Would result in the removal of a pinch point which has been the site of a number of traffic accidents Provision of footway General area improvement Progress No progress made Funding 2002/3 – nil
I9 Pentre Bychan Road near Crematorium Brief Description Widening the road to a constant width of 5.5m and the provision of a 1.8m of Scheme footway, At the same time it will enable the strengthening of Pentrebychan bridge. Benefits Improved safety for pedestrians and vehicles Main access to crematorium therefore relatively high traffic and pedestrian flows Scheme allows for bridge strengthening works to be carried out Progress No progress made Funding 2002/3 - nil
36 Wrexham County Borough Council Annual Progress Report 2002/3
Roads continued I10 Structural renewal/repair of carriageway Brief Description On going general maintenance works on County Borough roads. of Scheme Benefits Essential to maintain the County Boroughs assets Reduced accidents Progress £1962k was spent on resurfacing, £255k was spent on major patching and £139k was spent on surface dressing. Funding £886k – WAG Grant £1470 – WCBC Comments About 10% less in real terms was spent on potholes in 02/03 than in 2001/2002 reversing the trend over previous years and indicating that the increased capital investment over the past 2 years is having a marked effect.
J BRIDGES Scheme Name Description Progress Funding J1 B5430 Southsea Strengthening works Bridge 2002/3 - £2k Bridge strengthened 2002 J2 A5152 Pont Felin Strengthening works Scheme 2002/3 – nil Puleston programmed for 03/04 J3 B5102 Cooks New Strengthening works Scheme 2002/3 – nil Bridge programmed for 03/04 J4 B5097 Afon Eitha Strengthening works Scheme 2002/3 – nil programmed for 05/06 J5 B5400 Chirk Highway New Bridge Works Scheme 2002/3 – nil support programmed for 2003/4 J6 B5400 Bryn Derw New Bridge Works Scheme 2002/3 – £108k retaining wall completed 2003 J7 B5434 Pont Cysyllte General Completed in 2002/3 – nil refurbishment works 01/02
J8 A5152 Eagles Scheme deleted in the 2001/2 APR Meadow Viaduct J9 A534 Brickyard General Culvert 2002/3 – £46k Cottage Culvert replacement/refurbis strengthened 2003 hment works J10 Middle Sontley Bridge General Bridge replaced 2002/3 – £68k refurbishment works 2003 J11 A525 Sands Cottage General Scheme 2002/3 – nil Culvert, Horsemans replacement/refurbis programmed Green hment works for 2003/4
37 Wrexham County Borough Council Annual Progress Report 2002/3
Bridges continued J12 Clapping Gate Canal General Due for 2002/3 – £1k Bridge replacement/refurbis replacement 2003 hment works J13 Pont Bryn Alyn General Scheme 2002/3 – nil replacement/refurbis programmed for hment works 2003/4 J14 Penley Bank Cottage General Scheme 2002/3 – nil Culvert replacement/refurbis programmed for hment works 2005/6
38 Wrexham County Borough Council Annual Progress Report 2002/3
4. PROGRAMME AND TARGETS
Amendments/Additions to the Programme 4.1. The following items have been amended/added/deleted as appropriate from the programme;
Walking and Cycling (ref A) 4.2. Previously there were 3 three different categories under “A Walking and Cycling” however as these categories were all interrelated these have been combined for clarity. The previous categories were “A1 General”, “A2 National Cycle Route:Chester-Wrexham-Llangollen-Trawsfynydd” and” A3 Wrexham Town centre to Gatewen and Brymbo.”
4.3. As part of these works overlapped the total amount for this category combined has been reduced from £3691k to £3200k.
Safe Routes to School (ref B) 4.4. Original figure included for 2001-2006 was £900k – due to previous years not receiving estimated amounts of funding, this amount has been decreased to £803k.
Mobility Impaired (ref C) 4.5. Original figure included for 2001-2006 was £200k. This amount was funded by the Council in 2002/3. Following a review this amount is to be increased to a total of £500k for 2001-2006 resulting in £100k per year for the remaining 3 years of the original LTP.
Wrexham Bus Station (ref D1) 4.6. Original figure included for 2001-2006 was £3000k. Since works have commenced this figure has been calculated as £3294.
Bus/Rail Interchange Measures (ref D3) 4.7. Due to considerable funding from Taiths Transport Grant Bid this amount has been increased from £300k to £655k.
Mold Road/Grosvenor Road Gyratory (ref D5) 4.8. Retail developers are now likely to meet a considerable amount of the scheme costs therefore the amount included is reduced from £900k to £200k.
New Rail Station at Johnstown 4.9. As it is unlikely that this will proceed before 2006 the £1000k included for this has been moved forward into the next plan period.
Park and Ride 4.10. As it is unlikely that this will proceed before 2006 the £1000k included for this has been moved forward into the next plan period.
39 Wrexham County Borough Council Annual Progress Report 2002/3
Car Park Management/Residents Parking. 4.11. This amount has been increased from £100k to £334k to take into account the £234k required if decriminalised parking enforcement is progressed.
Accident Reduction 4.12. Due to the importance of this type of work and the support from the Local Road Safety Grant and WCBC budget, this amount has been increased from £1500k in original LTP to £2246k.
Travel Awareness (ref G) 4.13. Due to lack of funding being obtained in the first 2 years of the plan period this amount has been reduced from £240k to £100k.
Traffic Calming (ref H) 4.14. Due to lack of funding being obtained in the first 2 years of the plan period this amount has been reduced from £950k to £750k.
Wrexham Industrial Estate Access Road (ref I1) 4.15. Scheme costs will be assessed following the outcome of the review into Section 2 of the scheme. This scheme is now unlikely to progress within the current plan period.
Plas Bennions Road (ref I7) 4.16. Due to more accurate scheme costs being available this amount has been reduced from £200k to £179k.
Structural Renewal/repair of carriageway 4.17. As the Special Highways Maintenance Grant has not been continued estimates have been reduced from £6160k to £5466k.
Bridges Schemes 4.18. Due to more accurate schemes costs now being available the following changes have been made to the programme.
Pont Felin Puleston - increased from £400k to £500k Chirk Highway Support – decreased from £140k to £50k Middle Sontley Bridge – increased from £50k to £68k Sands Cottage Culvert – increased from £75k to £120k Clapping Gate Canal Bridge – increased from £200k to £250k
Programme 2003/4 to 2007/8 4.19. The following tables indicate the revised programme of schemes. The programme supersedes that contained in the LTP.
40 Wrexham County Borough Council Annual Progress Report 2002/3
REVISED COSTED PROGRAMME TO 2007/08 (page 1 of 3)
41 Wrexham County Borough Council Annual Progress Report 2002/3
REVISED COSTED PROGRAMME TO 2007/08 (page 2 of 3)
42 Wrexham County Borough Council Annual Progress Report 2002/3
REVISED PROGRAMME TO 2007/08 (page 3 of 3)
43 Wrexham County Borough Council Annual Progress Report 2002/3
5. REGIONAL TRANSPORT PARTNERSHIPS
Background 5.1. Due to the geographical location of Wrexham County Borough the Council are active members in 2 regional transport partnerships; Taith Cheshire, Chester, Flintshire, Wrexham Joint Working Group (CCFWJWG) The involvement of the Council in these partnerships, the aims of the partnerships and the proposals for future working relations within these groups is described in more detail in the following sections.
Taith Background 5.2. Taith is the regional transport partnership covering North Wales comprising the six North Wales authorities.
5.3. Taith’s overall vision is to support the development of a transport system in North Wales that will:
Taiths vision
“ Provide for the present and future transport needs of North Wales by promoting transport investment related to land-use planning, economic, environmental, social, and accident-reduction objectives.”
5.4. Supporting this vision are the following key aims:
To extend the multi-modal infrastructure of the region To support sustainable improvements to the level of commercial and economic activity of the region To enhance the safety and quality of transport services within the region To support a transport system that meets the needs of all of the regions residents
5.5. Taith has already developed and promoted a partnership approach to strategic transport issues and projects across North Wales and is recognised in WAG’s Transport Framework for Wales as the regional partnership that will play a leading role in the delivery of the Assembly’s transport agenda. Taith is confident of its ability to deliver WAG’s vision for transport at a regional level as well as servicing the local needs of its partners, provided it has access to the necessary resources.
5.6. Taith has produced a Regional Transport Strategy which received widespread support in a consultation exercise and in Summer 2003 will consult on a draft Regional Bus Strategy.
44 Wrexham County Borough Council Annual Progress Report 2002/3
5.7. Taith have appointed a Regional Travel Plan Co-ordinator who is based with Flintshire County Council. At present he is working on Demand Responsive Transport System for Deeside Industrial Estate within Flintshire, however if successful it is likely that the system will roll out to Wrexham Industrial Estate. Other projects include assistance to Bangor University, Glan Clwyd Hospital, Broughton retail park and British Aerospace.
5.8. Ticket machines which have been funded by Taith were introduced during 02/03 and are now fitted on all Arriva buses in Wrexham. These machines are compatible with smart card technology.
5.9. An appointment will be made shortly of an officer with specific responsibilities on the delivery aspects of current funds allocated under the Transport Grant scheme.
5.10. Taith has proved to be a vital mechanism for the dissemination of best practice around the region as well as a mechanism for working in partnership with the bus and rail industries.
The Way Forward 5.11. Taith is reviewing its constitution and operational arrangements in order to strengthen and to put on a more formal footing the successful partnership arrangement that currently deals with regional transport issues. This process ties in with the recommendations of WAGs Environment, Planning and Transport Committee regarding a regional approach to the provision of public transport.
5.12. The review of the constitutional framework is now well in hand and remaining obstacles will be removed by Autumn 2003 by which time Taith will assume responsibility for other regional transport matters including the North East Wales Trunk Road Agency (NEWTRA).
5.13. As far as membership of Taith is concerned, care has to be taken to ensure that any executive authority is vested in those who are properly accountable for the spending of public funds with appropriate direct linkages to the decision making processes of individual partners. This almost inevitably means that the executive of Taith is constituted from the local authority partners.
5.14. It is important however, to embrace a wider membership in some form of associate status so that development of policy and strategy and the delivery of projects or initiatives where other parties are directly involved can be achieved on a truly inclusive basis. Such members of Taith could be sought from; WAG Adjoining Local Transport Authorities Strategic Rail Authority Public Transport Operators Industry and Commerce
45 Wrexham County Borough Council Annual Progress Report 2002/3
Cheshire, Chester, Flintshire, Wrexham Joint Liaison Group Background 5.15. The Group was formed in 1998 to achieve joint working between the four neighbouring authorities. The members of the group recognised that by working together to develop and implement policies that not only the needs of the individual authority areas are met but that this will also maximise the potential of the sub-region.
5.16. To achieve these objectives, the group seek to identify common goals, share information, consult on local policies which may impact the sub-region, share good practice, promote the profile of the sub-region and where appropriate develop policies that over-arch the region.
Progress 5.17. The group currently are in discussions over the congestion problems at the A483/A55 Holiday Inn (formerly Posthouse) roundabout. The roundabout is a severe bottleneck in peak periods and the congestion at the roundabout is of great concern to both Wrexham County Borough Council and Cheshire County Council. Signal improvements in recent years have improved the situation slightly, however it is recognised that major work is needed at this junction to increase its capacity. Work has recently been completed to provide a free flow slip lane form the A483 to the A55.
5.18. The Council is also in negotiations with Cheshire County Council and Flintshire County Council with regard to the Chester-Trawsfynydd Cycle route as the route passes through Wrexham County Borough. The Llangollen to Trawsfynydd section of this route would be primarily leisure, however the Wrexham to Chester section of the route would have significant transportation benefits as many of County Borough residents work in Chester and the route would be popular with commuters. As part of this group, Cheshire County Council support the scheme which would link into the Chester Business Park. Companies based on the Business Park, such as MBNA International Bank are also supportive of the scheme.
5.19. Discussions have taken place at the group in relation to the development of a sub-regional strategy for West Cheshire and North East Wales. Participants included local authority officers from Wrexham, Flintshire, Chester, Ellesmere Port and Neston, Chester and the NWRA. A paper detailing the discussions was also submitted to WAG.
5.20. It was felt that the strategy should be wide ranging and should address the inter-related issues of infrastructure, transport, housing, environment and employment with a particular focus on access to jobs.
5.21. The end product will be a concise document which has proposals and recommendations to inform, but not pre-determine future decision making across the area. The study will be managed by a steering group at the present time options for co-ordinating and carrying out the work are being discussed.
46 Wrexham County Borough Council Annual Progress Report 2002/3
The Way Forward 5.16. The Group will continue to hold regular meetings to discuss items of mutual interest. In order to increase the potential of the group The Council has highlighted to WAG the issue of joint funding for schemes funded through Transport Grant.
Wrexham’s LTP and Regional Partnership Working 5.17. WCBC are active members of both Taith and the Cheshire, Chester, Flintshire, Wrexham Joint Working Group, and in implementing the Wrexham LTP have full regard to the overall vision and key aims of both regional groups.
Other Cross Border Issues 5.18. In addition to the A55/A483 Junction and the Chester-Trawsfynydd Cycle route, the following schemes are also highlighted as being/to be developed with the aid of cross border partnerships.
A483 – Dualling Ruabon to Shrewsbury It is considered by WCBC, that the Trunk Road Forward Programme 2002, which was recently published by WAG failed to recognise the crucial importance to Wrexham and the whole of North Wales of the A483/A5 route. At present the section between Ruabon and Shrewsbury is single carriageway with at-grade junctions with the exception of the recently completed Nesscliffe Bypass. The route is heavily trafficked and the single carriageway means that there is little opportunity to overtake slow moving vehicles which in turn leads to congestion. Frustration regarding to the lack of overtaking opportunities also leads to increased number of accidents.
A541 Hope/Caergwrle Bypass This scheme is dependent upon the results of the A541/A550 Corridor Study which was carried out by consultants WS Atkins on behalf of Flintshire County Council and WCBC. The result of this study are anticipated July 2003.
47 Wrexham County Borough Council Annual Progress Report 2002/3
6. FINANCIAL TABLES
FINANCIAL TABLE : APR 1
48 Wrexham County Borough Council Annual Progress Report 2002/3
FINANCIAL TABLE : APR 2 (page 1 of 3)
49 Wrexham County Borough Council Annual Progress Report 2002/3
FINANCIAL TABLE : APR 2 (page 2 of 3)
50 Wrexham County Borough Council Annual Progress Report 2002/3
FINANCIAL TABLE : APR 2 (page 3 of 3)
51 Wrexham County Borough Council Annual Progress Report 2002/3
FINANCIAL TABLE : APR 3
52 Wrexham County Borough Council Annual Progress Report 2002/3
APPENDIX 1 Feedback from WAG on APR 2001-2002
53 Wrexham County Borough Council Annual Progress Report 2002/3
54 Wrexham County Borough Council Annual Progress Report 2002/3
APPENDIX 2 Local Transport Plan – Progress on Policies
Key to Tables ● No progress ● ● Limited Progress ● ● ● Significant Progress Completed Shaded cells denotes text changes since last years APR
Key to Policy Reference Numbers Ref Title Document policy contained within ES Environment Policy LTP UDP Unitary Development Plan Policy LTP W Walking Policy Walking Strategy and LTP C Cycling Policy Cycling Strategy and LTP PT Public Transport Policy Public Transport Strategy and LTP BS Public Transport Policy (Buses) LTP P Parking Policy Parking and Park and Ride Strategy and LTP FT Freight Transport Policy LTP GC Green Commuting Policy LTP S Road Safety Policy Road Safety Strategy and LTP TC Traffic Calming Policy LTP TX Taxis and Private Hire Policy LTP PTW Powered Two Wheelers Policy LTP RM Road and Bridge Maintenance LTP Policy
55 Wrexham County Borough Council Annual Progress Report 2002/3
ENVIRONMENT Ref Target Policy Ref Policy Progress Notes or Examples No Date No/s 1 Monitor and minimise the amount 2006 ● ● ● This is a primary role of the Public ES1 of land, air, water and noise Protection Department with specific pollution strategies/targets contained within the Air Quality Review and Contaminated Land Strategy. 2 Promote a more environmentally 2006 ● ● ● e.g. Green Transport Week, Walk to ES2 sensitive transport system School Weeks and Cycling Promotions 3 Ensure that NO2 and PM10 2006 ● ● ● Monitoring at one locality has TARGET pollutants are below standards indicated exceedances of the air (LTP) quality standards. This is related to the use of solid fuels in the area and is not linked to road traffic.
LAND USE PLANNING/UNITARY DEVELOPMENT PLAN Ref Policy Target Progress Notes or Examples Policy No Date Ref No/s 4 Implement transport schemes in 2006 ● ● ● All implemented schemes comply UDP1 accordance with the policies set out with both the current UDP and the in the Wrexham UDP future UDP which is currently subject to a public inquiry 5 Consider transport implications for 2006 ● ● ● Numerous on and off site cycleways, UDP2 all new developments. traffic calming, pedestrian crossings and public transport facilities 6 To implement highway 2006 ● ● The first stage WIE Access Road was UDP3 infrastructure works e.g. Wrexham open to traffic on the 18 Sept 2002. Industrial Estate (WIE) Access Construction of the second stage was Road programmed to start in 2003 but has now been delayed until 2007 7 To safeguard old railway lines for 2006 ● ● ● Several routes are safeguarded in the UDP4 the provision of a network of UDP walking and cycling routes 8 To support and promote the 2006 ● ● ● Phase 1 completed June 2003 and UDP5 redevelopment of Wrexham Bus Phase 2 will be completed by Station November 2003.
WALKING/ACCESSIBILITY/MOBILITY Ref Policy Target Progress Notes or Examples Policy No Date Ref No/s 9 Provide convenient, safe and 2006 ● ● ● Pedestrian refuges installed e.g W1/W3 pleasant pedestrian routes and Holt Road, Watery Road/Bradley facilities throughout the County Road, Fairy Road. Numerous Borough traffic calming schemes to keep traffic speeds low both on site and surrounding roads leading to schools and shops e.g. Rhosnesni Lane 10 Consider pedestrians at every 2006 ● ● ● Replacement of one pelican by two W2 stage of the planning/development zebras at Garden Road/Rhosddu W2.1 process Road 11 Extend traffic calming and 2006 ● ● ● Safe Routes provided at 3 new W4 pedestrianisation in Wrexham town sites including contribution from centre, villages and in the vicinity of Rhos regeneration schools
56 Wrexham County Borough Council Annual Progress Report 2002/3
WALKING/ACCESSIBILITY/MOBILITY continued Ref Policy Target Progress Notes or Examples Policy No Date Ref No/s 12 Encourage walking to improve the 2006 ● ● ● Safe Routes to School schemes. W5 health and safety of school children Working with Tanyfron Community and reduce traffic around schools Council for traffic calming outside school. 13 Increase the number of pedestrians 2006 n/a Target not yet measured. TARGET Performance Indicator (PI) - Pedestrian Surveys to be number of pedestrians conducted Summer 2003. 14 Improve accessibility for the 2006 ● ● ● 98% compliant by 31/3/03. All new TARGET mobility impaired installations are compliant. Town PI - % of pedestrian crossings with centre fully accessible by facilities wheelchairs. 15 Identify pedestrian routes and 2006 ● ● ● Wrexham Town Centre W1.1. crossings and prioritise improvements. 16 Implement improved road and route 2011 ● ● as ref 15 W1.2/ crossings identified in ref 15 W1.3 17 Provide a comprehensive 2006 ● ● Destinations agreed – to be signed W1.4 pedestrian signing scheme in during 2003/4 Wrexham town centre 18 Prepare supplementary guidance 2006 ● Standard details being produced for W2.2 on standards for pedestrian use in Development Control Design provision on all new developments Guide. 19 In conjunction with schools develop On- ● ● Five schools for safe routes to W3.1 package of physical works, going school funding. Expanding schools education, training, publicity etc liason to other schools with non – safer routes funding. Using Groundwork Wrexham and Flintshire as schools contact. Questionnaire sent to out to 2003 to assess demand. Using school plays and Child pedestrian co- ordinator in Kerbcraft scheme. 20 Identify routes and crossings used 2006 ● ● Update of July 2001 questionnaire W3.2 by school children and prioritise to schools to be completed in improvements. Summer 2003 (see ref 19) 21 Implement improved routes and 2006 ● ● SRTS programme continues. W3.3/ road crossings identified in ref 20 W3.4 22 Increase consultation with local 2011 ● ● ● Regular meeting with Disabled W4.1 access and disability groups for all Access Forum and Disabled Task significant schemes. Force 23 Carry out pedestrian audits on all 2011 ● ● Undertaken for major schemes W4.2 significant highway and traffic management schemes. 24 Identify the necessary funding On- ● ● ● Capital project funding (WCBC) & W6.1 sources and establish priorities and going Safe Routes to School (WAG) , and budgets Transport Grant (WAG) applied for 25 Encourage private sector initiatives On- ● ● ● The Carlsberg Brewery W6.2/ in implementing the strategy going Development will part finance the C8.2 objectives Regent Street/Bradley Road Gyratory and Watery Road Roundabout Improvements as well as improved pedestrian, cycle and public transport facilities.
57 Wrexham County Borough Council Annual Progress Report 2002/3
CYCLING Ref Policy Target Progress Notes or Examples Policy Ref No Date No/s 26 Introduce a cycle network of road 2006 ● ● ● Numerous routes developed C1/C1.1/ cycle lanes, quiet streets, disused including through Erddig Park NT. C1.2 railway lines, parks and new routes 27 Increase the amount of cycle 2006 ● ● ● Extensive provision including C2/C2.1/ parking in key public areas Railway stations C2.3 28 Provide cycle hire facilities as part 2006 ● Not included due to space C3 of the Bus Station redevelopment constraints. 29 Extend traffic calming in town 2006 ● ● ● Traffic calming and 1 reduced speed C4 centre, villages and vicinity of limit installed as safe routes to schools for the benefit of cyclists school 30 Provide adequate lighting on 2006 ● ● ● Most new/improved cycle/pedestrian C5 cycle/pedestrian routes routes are lit 31 Consider the needs of cyclists and 2006 ● ● ● On-going C6/C2.4/ require cycle parking as part of the C5.1 development process 32 Increase the number of cyclists 2006 ● ● There is an increase in cycling but TARGET +100% (96-2002) +100% (2003-12) currently insufficient to meet target 33 Sign leisure and mountain bike 2011 ● ● Alyn Waters Country Park cycle C1.3 routes in the County Borough routes on west and east side of parks. Erddig signed and Ceiriog Valley routes arranged with Tourism department 34 Provide cycle stands at schools in 2011 ● ● To be provided where school has a C2.2 conjunction with safe routes/cycle commitment to cycle training routes 35 Highlight the importance of cycle 2016 ● ● ● Close co-operation between C3.1 issues to other Councils Environmental Services, Planning departments for inclusion in new and Transportation e.g. Agenda developments 21/Green Transport weeks 36 Prepare supplementary planning 2006 Now WCBC policy C3.2 guidance on cycle standard for new developments 37 Publicise cycle routes and cycle 2011 ● ● ● Existing cycle map being updated. C4.1 parking facilities including Second edition of On Yer Bike encouragement to use cars less magazine produced with Flintshire and Denbighshire. 38 Consider the establishment of a 2011 Cycle forum met twice in 2002/3 C7.1/ Cycling Forum, arrange first C7.2 meeting and identify issues 39 Identify the necessary funding 2016 ● ● ● Substantial WAG Transport Grant C8.1 sources for cycling and establish obtained priorities and budgets
PUBLIC TRANSPORT Ref Policy Target Progress Notes or Examples Policy No Date Ref No/s 40 Develop the bus service and 2001 ● ● ● Study complete. Officer appointment PT1 community transport with the imminent voluntary sector in rural areas 41 Assist the elderly and disabled to 2001 ● ● Bus Station design, use of new PT2 use existing services vehicles/quality measures. 42 Support and expand the Charriotts 2001 ● ● ● Assistance for new vehicles purchase PT3 Dial a Ride operation
58 Wrexham County Borough Council Annual Progress Report 2002/3
PUBLIC TRANSPORT continued Ref Policy Target Progress Notes or Examples Policy No Date Ref No/s 43 Promote all public transport 2001 ● ● ● On-going PT4 services in the County Borough to achieve maximum usage. 44 Provide socially necessary bus 2001 / ● ● ● On-going BS1 & services subject to best value for 6 POLICY money and available funding. 1 45 Charge fares on socially 2001 / ● ● ● _ BS2 & necessary services in line with 6 POLICY commercial bus services in the 2 areas. 46 Introduce experimental bus 2001 / ● ● _ BS3 & services to enhance the current 6 POLICY network 3 47 Review the levels of service 2001 / ● ● ● New services introduced BS4 & support on Sundays and Bank 6 POLICY Holidays 4 48 Maintain the existing network of 2001 / ● ● ● _ BS5 & school services for children who 6 POLICY do not qualify for free transport 5 49 Introduce Quality Partnerships to 2001 / ● ● Negotiations for 2003/4 BS6 & improve passenger facilities and 6 developments. POLICY usage 6 50 Consider traffic management 2001 / ● New Signs Regulations makes Bus BS7 & priority measures for bus 6 Boxes as compulsory bus clearways POLICY services from 2007 7 51 Improve roadside infrastructure 2001 / ● ● Some infrastructure now in place BS8 & to maximise the use and 6 POLICY accessibility of bus services 8 52 Redevelop Wrexham bus station 2001 / ● ● ● Phase 1 completed June 2003 and BS9 & to provide modern interchange 6 Phase 2 will be completed by POLICY facilities November 2003. 9 53 Promote the rail services 2001 / ● ● ● New community led initiative of BS10 & according to the proposals put 6 through fares POLICY forward by the NWEF 10 54 Facilitate or contribute towards 2001 / ● _ BS11 & infrastructure improvements 6 POLICY along lines 11 55 With Flintshire secure evening 2001 / ● ● ● On-going BS12 & and Sunday Services on the 6 POLICY Wrexham to Bidston line 12 56 Increase public transport usage 2001 ● Initial surveys but awaiting completion TARGET (target to be set after first survey) of bus station redevelopment PI - number of passengers 57 Have regard to the transport 2001 ● ● ● _ POLICY requirements of elderly and 14 disabled passengers 58 Review concessionary travel 2001 ● ● ● Concessionary travel scheme in POLICY scheme for elderly and disabled place. Pass holders increased from 15 people to ensure that needs are 7000 in 2001/02 to 17000 on 2002/03. met 59 Promote all public transport 2001 ● ● ● On going publicity plus involvement in POLICY services thereby ensuring Green transport fair 16 maximum usage 60 Quality Standards for contract 2001 ● ● ● _ POLICY services will continue to be 17 monitored 59 Wrexham County Borough Council Annual Progress Report 2002/3
PARKING Ref Policy Target Progress Notes or Examples Policy No Date Ref No/s 61 No new Council short stay car 2006 ● ● Temporary WCBC car park on old P1 parks will be provided in Asda car park. Plans for 12 space Wrexham town centre. limited waiting car park to be constructed. 62 No new Council long stay car 2006 ● ● ● New long stay car park constructed at P2 parks in Wrexham town centre Crescent Road in advance of closure of Eagles Meadow. 63 Monitor the use and pricing of 2006 ● ● ● 6 monthly surveys undertaken P3/ town centre car parks TARGET
64 Safeguard site(s) for Park and 2006 ● ● ● Site safeguarded in UDP P4 Ride and implement in accordance with Policy P3 65 Review the need for a P&R facility 2006- ● ● See below P23 for shoppers, commuters and 2011 – P25 visitors visiting the town centre 66 Prepare a feasibility study for the 2006 ● ● ● Consultants have undertaken a Study P26 development of a park and ride on Key Developments sites in site within Wrexham Technology Wrexham including P&R. Park Recommended site Mold Road, Wrexham 67 The provision of a second park 2016 N/A Only one site now proposed P28 and ride site will be considered in the longer term . 68 Introduce specific bus priority 2006 N/A Not appropriate at this time P5/P27 measures for park and ride bus services 69 Convene a Parking Forum to 2006 ● ● Meeting to be convened in September P3 discuss parking issues 2003
70 Financial contributions by 2006 ● ● Some commuted sums paid by town P4 developers will be used to support centre developers green travel, p&r services etc. 71 Increase long stay charges in 2006 ● ● Charges were raised from £2.00 to P6 town centre car parks to £2.50 in 2000. encourage commuters to use Eagles Meadow 72 Apply reduced staff parking 2006 ● ● ● Revised parking standards adopted P7/P12 standards to new town centre development to limit growth of commuting 73 Long stay parking in residential 2011 ● ● First study in 2001 showed no demand P8 streets adjoining the Town Centre for residents parking – second survey will be discouraged to be conducted in June 2003 74 On street parking in Wrexham 2006 ● ● ● All spaces restricted except St P9 Town Centre will be restricted to Georges Crescent short stay parking only 75 On street spaces may be 2006 Complete _ P10 provided in Town Hill, Mount St and by extending Chester St limited waiting areas. 76 An on street parking places order 2006 ● _ P11 will be imposed on the south side of St George's Crescent.
60 Wrexham County Borough Council Annual Progress Report 2002/3
PARKING continued Ref Policy Target Progress Notes or Examples Policy No Date Ref No/s 77 The required level of car parking 2006 ● ● _ P12 provision at new developments may be reduced subject to the availability of alternative means for staff travel 78 Public parking provision in district 2006 ● ● Usage of district centre public car P13 centres will be assessed taking parks is monitored every three months into account local circumstances 79 New parking for the mobility 2006 ● ● ● _ P14 impaired to be designed current Government guidance 80 Undertake a review of on and off 2006 ● ● _ P15 street parking requirements of people with impaired mobility. 81 Parking for orange badge holders 2006 ● ● ● Parking remains free and no time limit P16 in the Council car parks will imposed. remain free of charge 82 All fee paying car parks will be 2006 ● ● ● 3 car parks in the town centre have P17 brought up to full Secured Car Secured Status. Parks standards 83 Security at non fee paying car 2011- N/A _ P18 parks will be improved as 2016 resources permit 84 Free motorcycle parking will be 2006 ● ● Free parking but few spaces marked P22 provided car parks in Wrexham and no security fixings. Security fixing town centre. to be investigated summer 2003.
FREIGHT Ref Policy Target Progress Notes or Examples Policy No Date Ref No/s 85 Construct a new high standard 2006 ● ● The first stage WIE Access Road is FT1 access road to Wrexham completed, subject to the outcome of Industrial Estate the environmental assessment the remaining section is due to be started in 2007. 86 Consider the recommendations of 2006 ● ● Seminar organised for North Wales FT2 the freight study of transporting authorities, businesses and the rail goods by rail industry 87 Develop freight quality 2006 Freight Quality Partnership meetings FT3 partnerships for the town centre on hold as no problem areas were and Wrexham Industrial Estate identified. 88 Support sustainable distribution of 2006 ● _ TARGET freight PI – amount of freight carried on rail network
61 Wrexham County Borough Council Annual Progress Report 2002/3
GREEN TRANSPORT Ref Policy Target Progress Notes or Examples Policy No Date Ref No/s 89 Produce a Green Transport Plan 2006 ● Staff and member travel surveys GC1/W5 for the Council undertaken .1/P19 90 Encourage large employers within 2006 ● ● Maelor hospital and Inland Revenue GC2/W5 the area to produce a Green have Green Travel Plans. .2/C6.1/ Transport Plan and monitor modal P20 shift 91 Require developers of major new 2006 ● Required as a planning condition for GC3/P2 employment sites to submit Green expansion of Pendine Park Nursing 1 Transport Plans Home in Gwersyllt and also for a proposed call centre in Rhostyllen. 92 Encourage and assist schools to 2006 ● ● Work developed with 3 schools GC4 implement Green Transport Plans/School Travel Plans 93 Reduce the use of private 2006 ● _ TARGET transport for journeys to work Performance Indicator – produce of GTP and monitor modal shift 94 Assess existing and future levels 2006 ● ● Established monitoring of schemes TARGET of traffic on County Borough and counts philosophy. Maintained roads Performance Indicator – effectiveness of automatic counters traffic flows and congestion through upgrades and new stock. Established contract for traffic counts and monitoring.
ROAD IMPROVEMENT Ref Policy Target Progress Notes or Examples Policy No Date Ref No/s 95 Implement the policies contained 2006 ● ● On-going R1 within the Road Strategy 96 A5156 - Improved access to Start in ● ● ● Section 1 complete. Section 2 R1 Wrexham Industrial Estate 2002 subject to an Environmental Impact Assessment. 97 A541 - Caergwrle Bypass Start after ● Subject to outcome of Atkins study R1 2005 98 A525 - Coedpoeth and Start after ● _ R1 Bwlchgwyn Bypass 2005 99 A5152 - Watery Road / Bradley Start ● _ R1 Rd Junction, before 2005 100 A541 Regent Street / Bradley Start ● Site adjacent to redevelopment site. R1 Road Junction before Planning application with new road 2005 proposals expected 101 A541 - Gwersyllt Improvement Between ● _ R1 2002-2005 102 A525 - Raggs Hill east of Bangor Between ● _ R1 on Dee 2002-2005 103 C - Plas Bennions Road, Ruabon Between ● _ R1 2002-2005 104 C - Stryt Las, Rhos Between ● _ R1 2002-2005 105 U/C - Pentrebychan Road - Between ● _ R1 Smithy Lane to Crematorium 2002-2005
62 Wrexham County Borough Council Annual Progress Report 2002/3
ROAD SAFETY Ref Policy Target Progress Notes or Examples Policy No Date Ref No/s 106 Progress and promote the 2006 ● ● ● Publicity campaigns supported. S1 actions of the RS Plan Numbers cycle trained has increased. Large quantity of information has been distributed. 107 Produce an annual report and 2006 ● _ S2 / statistics on Road Safety Action 1 +2 108 Identify accident cluster sites 2006 ● ● Annual assessment done. Design S3/Actio and design remedial measures being prepared. n 13 109 Progress accident remedial 2006 ● ● Ongoing S4 measures according to /Action programme of priorities 14 110 40% reduction in the number of 2006 ● ● 27% reduction by 2002 TARGET Killed and Seriously Injured (KSI) by 2010 (4% per year) 111 50% reduction in the number of 2003 83% reduction by 2003 – achieved children killed or seriously target. injured by 2010 (5% per year) 112 10% reduction in the slight injury 2006 ● ● Awaiting information from WAG in order TARGET casualty rate to calculate required statistics 113 Increase the number of children 2006 ● ● ● 7 instructors. Part time senior instructor TARGET who have received cycle training appointed to co-ordinate work. By 2002 by 3% each year numbers up 55% on 2000 and 98% of all training requests met. 114 Support, arrange or promote 2002 ● ● ● DfT, WAG and North Wales Group ACTION publicity campaigns campaigns supported. Local campaign 3 “Stop for Patrols”. 115 Display road safety publicity 2002 ● ● ● Posters have been seen up in libraries, ACTION campaign posters and leaflets schools, doctors surgeries and clinics. 4 Extra copies requested by the hospital. 116 Include road safety publicity in 2002 ● ● Internal newsletter contained road safety ACTION publications, letters, signs etc information. Road safety car park pay 5 and display stickers and stickers for children. 117 Meet all requests for information 2002 ● ● ● All requests met and queries answered ACTION and materials (or referred to a satisfactorily. 6 specialist) 118 Road safety materials to be 2002 ● ● ● Specific resources for 192 cubs and 530 ACTION given (or loaned) to parents, brownies were issued to the leaders. 7 childminders, and other groups Parents received literature via the schools. 119 A specimen road safety policy 2002 ● ● Draft Policy sent out to all schools. ACTION for schools to be prepared and 8 sent to all schools 120 Schools to adopt a road safety 2002 ● Schools were not required to report ACTION policy whether adopted. 1 secondary known to 9 have policy and 2 primaries intending to adopt. 121 Child cycle training will be 2002 ● ● 2002 numbers were up 55% on 2000 ACTION increased figures – more schools catered for. 10 122 Continue to hold MegaDrive 2002 N/A National large scale funding from ACTION training course, subject to Vauxhall ceased. Programme replaced 11 continued funding successfully with Young Driver Programme for secondary schools.
63 Wrexham County Borough Council Annual Progress Report 2002/3
ROAD SAFETY continued Ref Policy Target Progress Notes or Examples Policy No Date Ref No/s 124 Vehicle driver training to be 2002 ● Fleet drivers participate in “How’s my ACTION considered for Employees who driving?” scheme to encourage safe 12 drive for work driving 125 Seek North Wales Police views 2002 ● ● ● On-going as part of scheme ACTION before changes are undertaken consultation. 15 to the existing road network 126 Consider likely accident 2002 ● ● ● Works are signed and guarded ACTION implications for highway according to Chapter 8 16 maintenance works 127 Safety audits to be undertaken 2002 ● ● ● _ ACTION for all major highways schemes 17 128 Enforce traffic legislation in 2002 ● ● Enforcement reduced due to reduction in ACTION accordance with the North number of traffic wardens in North 18 Wales Police Traffic operations Wales Support Plan 129 Enforce legislation to ensure 2002 ● ● ● Highway Supervisors issue notices ACTION that the roads are not obstructed under the Highway Act 19 or dangerous 130 Enforce legislation on 2002 ● ● ● Caravan weight check sessions and ACTION overloading of vehicles and the advice on safe loading produced. Local 20 sale of unroadworthy vehicles Hauliers advisory sessions and 12 and equipment. routine road side checks undertake resulting in 319 vehicles s being examined and 158 being weighed. 131 Use the roads in a safe manner 2002 _ Staff encouraged to so via payslips ACTION at all times and encourage Radio adverts/other publicity encourage 21 others to do likewise safe behaviour. “Arrive Alive” cameras help speed compliance. In 2002 practical pedestrian training given to year 1 pupils in 10 schools. Role play sessions taught road safety to 30 sets of playgroups/early years. 132 The Council will instruct 2002 ● ● Formal Guidance to be issued shortly ACTION employees not to use mobile 22 phones or radios whilst driving 133 Consideration will be given to 2002 ● ● Traffic calming and accident budgets ACTION providing funding for the road from WCBC proposed 2003/2006. 23 safety and accident budgets. Traffic calming criteria agreed
TRAFFIC CALMING Ref Policy Target Progress Notes or Examples Policy No Date Ref No/s 134 Introduce traffic calming 2006 ● ● ● Funding for SRTS schemes continues TC1 measures and 20mph zones in connection with school travel initiatives 135 Introduce traffic calming in areas 2006 ● ● Several schemes installed outside TC2 seriously affected by traffic taking schools and as part of cycle routes short cuts which has reduced traffic taking short cuts.
64 Wrexham County Borough Council Annual Progress Report 2002/3
TRAFFIC CALMING continued Ref Policy Target Progress Notes or Examples Policy No Date Ref No/s 136 Discourage non essential traffic 2006 ● As ref 135 from using unsuitable routes Performance Indicator - feedback TARGET and accident statistics (annual review) 137 20mph zones to be introduced in 2006 ● ● Considering extending 20mph zone in TC3 residential areas where Queensway into Spring Lodge as part applicable of WCBC accident programme
TAXIS AND PRIVATE HIRE Ref Policy Target Progress Notes or Examples Policy No Date Ref No/s 138 Recognise the role that taxis and 2006 ● ● Consideration has been given in all TX1 private hire vehicles can play in schemes. Note: balance to be struck the transport system between variety of users e.g. deliveries, disabled and pedestrians 139 Consider the needs of taxis and 2006 ● ● Taxi bay being built at Bus Station with TX2 private hire vehicles in any town ramp for wheel chair users. centre traffic management scheme
POWERED TWO WHEELERS Ref Policy Target Progress Notes or Examples Policy Ref No Date No/s 140 Consider powered two wheelers 2006 ● ● Considered as part of the safety PTW1 (PTW) users in the design and audit process improvement of the highway 141 Provide secure parking facilities 2006 ● ● Provision of security hoops at car PTW2 for PTW users in the town centre parks investigated – to be actioned and at interchange facilities during 2003/4
ROAD AND BRIDGE MAINTENANCE Ref Policy Target Progress Notes or Examples Policy Ref No Date No/s 142 To recognise that road 2006 ● ● ● Additional funding provided RM1 maintenance is essential in order to support the existing network 143 To carry out inspections and 2006 ● ● ● Regular inspections are carried out RM2 surveys on roads and footways by Highway Inspectors on a regular basis 144 Implement the policies contained 2006 ● ● Ongoing RM3 within the Bridges Strategy 145 To provide a safe, cost effective 2006 ● ● Ongoing TARGET highway network
65 Wrexham County Borough Council Annual Progress Report 2002/3
PUBLIC RIGHTS OF WAY Ref Policy Target Progress Notes or Examples Policy Ref No Date No/s 146 Clear backlog of outstanding On- ● ● _ Action 1 Definitive Map Modification going Orders 147 Resolve known anomalies on the 2011 ● _ Action 2 Definitive Map 148 Work towards a computerised On- ● ● New layer has been added showing Action 3 version of the Definitive Map and going effect of orders statement 149 Upgrade surfacing On- ● ● Mobility impaired project and others Action 4 commensurate with use going via TG monies. 150 Continue with and assess the On- ● ● ● _ Action 5 strimming schedule going 151 Provide stile kits On- ● ● _ Action 6 going 152 Review the stile kit programme 2004 ● _ Action 7
153 Complete the bridge/ditch 2011 ● ● _ Action 8 crossing programme
154 Ensure routes are opened and 2011 ● ● _ Action 9 signed
155 Prepare a GIS linked database 2004 ● Action 10
156 Protect rights of way across On- ● _ Action 11 arable land going 157 Continue the annual survey On- ● ● 16% of routes surveyed by CCW Action 12 going 158 Protect rights of way through On- ● ● ● _ Action 13 development sites going 159 Undertake composite Definitive 2011 ● _ Action 14 Map Modification Orders 160 Progress Public Path diversion On- ● ● ● Continue to reduce backlog Action 15 orders going 161 Continue mobility impaired paths 2004 ● ● ● Groundwork continue to manage Action 16 project project well
162 Continue joint projects with On- ● ● ● Partnership with Groundwork is Action 17 Groundwork going going well 163 Instigate an adopt a path scheme 2007 ● _ Action 18 or similar
164 Co-ordinate voluntary work On- ● Action 19 going 165 Facilitate consultation exercises On- ● ● ● Local Access Forum established Action 20 going November 2002
66 Wrexham County Borough Council Annual Progress Report 2002/3
BRIDGES Ref Policy Target Progress Notes or Examples Policy Ref No Date No/s 166 B5430 Southsea Bridge Start by Bridge strengthened in 2002 RM3 2002 167 A5152 Pont Felin Puleston Start by _ RM3 ● 2002 168 B5103 Cooks New Bridge 2002-5 ● _ RM3 169 B5097 Afon Eitha 2002-5 ● _ RM3 170 B4500 Herber Fechan Start by RM3 ● _ 2005 171 Queensway subway Start by RM3 ● _ 2005 172 B5434 Pont Cysylltau Start by Bridge refurbished in 2002 RM3 2002 173 A5152 Eagles Meadow viaduct Start by ● Refurbishment postponed due to RM3 2002 redevelopment proposals for Eagles Meadow 174 A5434 Brickyard cottage culvert Start by Culvert strengthened 2002 RM3 2002 175 C234 Middle Sontley Bridge Start by Bridge replaced 2003 RM3 2002 176 A525 Sands Cottage Culvert, Start by ● _ RM3 Horsemans Green 2002 177 C145 Clapping Gate Canal 2002-5 ● ● ● Due for replacement 2003/2004 RM3 Bridge, Bettisfield 178 Pont Bryn Alyn 2002-5 ● ● _ RM3 179 C160 Penley Bank Cottage 2002-5 ● _ RM3 Culvert, Penley 180 Pont Melin-y-Castell, Chirk 2002-5 ● _ RM3 181 Brook Lane Bridge. Worthenbury By 2005 ● _ RM3 182 Whitewell Culvert, Redbrook By 2005 ● _ RM3 183 B5400 Pont Dolywern By 2005 ● _ RM3 184 B5130 Pickhill Brdige. Talwrn By 2005 ● _ RM3 185 B5400 Chirk Highway By 2002 ● _ RM3 186 B5400 Bryn Derw Retaining Wall 2002 - completed 2003 RM3 2005 187 B5099 New footbridge alongside 2002 - ● _ RM3 Bersham Bridge 2005 188 Maintain a register of all 2006 N/A _ RM3 structures affecting the County Borough Highway Network 189 Inspect the condition of these 2006 N/A _ RM3 structures and identify maintenance works necessary. 190 Carry out strength assessments 2003 ● ● _ RM3 of all road carrying bridges for 40 tonne vehicles 191 Strengthen bridges which fail the 2006 ● ● _ RM3 40 tonne assessment or impose weight restrictions 192 Survey of all roads to establish 2006 ● _ RM3 the location of walls retaining a height of 1.5m or more 193 Demolish all bridges that no 2006 ● ● _ RM3 longer serve any useful purpose
67