Public Involvement Plan
Total Page:16
File Type:pdf, Size:1020Kb
Public Involvement Plan
Bridge Replacement Project PIN: 1247.08 BIN: 1-00705-0 Route 9P over Saratoga Lake Outlet Saratoga County Town of Saratoga City of Saratoga Springs
Name of Preparer: Erica Rousseau, Project Manager Date Prepared: 10/12/2005 Preparer’s Functional Area: Consultant Management
Current Phase (check one): Scoping Phase I-IV Phase V-VI Construction Other
Project Schedule as of Date Prepared
IPP Approved ------December 3, 2003 Scoping Approval ------June 15, 2006 Design Approval ------March 15, 2007 PS&E ------September 25, 2008 Construction Begins ------March 2009 Construction Completion ------November 2010
1. IPP update - The traffic volume and bridge ratings have been updated based on current data. The construction estimate will be updated as the project progresses through the design process. (Please see Appendix L for the approved IPP)
List changes that have occurred since IPP: The Bridge was determined to be eligible for the National Register of Historic Places. Both rehabilitation and replacement alternatives were investigated as feasible alternatives to address bridge deficiencies.
2. Project Data
Funding...... ____Fed-Aid NHS __X__Fed-Aid Non-NHS ____100% State
Check Project Type (s). ____NEPA Class I __X__NEPA Class II ____NEPA Class III X SEQR Non-Type II SEQR Type II
Brief Description of Project Work Eliminate the structure deficiencies using a cost effective treatment to ensure an un-posted structural condition for at least 50 years.
NYSDOT person designated as community contact Erica Rousseau Public Involvement prior to IPP (y/n) No If yes, describe Attach relevant correspondence and/or meeting minutes. 3. Project Scoping
PI Objectives in Scoping: 1. Identify Stakeholders 2. Inform stakeholders of project and proposed project scope/needs. 3. Gather information on the project context.
3.1 Identify Stakeholders
List Internal Stakeholders: Regional Planning; Regional Design Group; Regional Structures Group; Regional Landscape/Environmental Group; Regional Traffic and Safety Group; Regional Construction Group; Regional Maintenance Group.
List External Stakeholders: City of Saratoga Springs, Town of Saratoga, County of Saratoga, USACOE, FHWA, NYSDEC, NYSOPRHP, Saratoga Lake Protection and Improvement District, Saratoga Rowing Association, Power Squadron, Mohawk Hudson Bicycling, NYS Bicycling Coalition, Saratoga Lake Association, Saratoga Lake Sailing Club, Saratoga County Historical Society, Saratoga Lake Marinas, Saratoga Lake Businesses, Emergency Services, local/seasonal residents, traveling public
3.2 Potential community concerns: Increased vertical clearance under the bridge, wider travel lanes/shoulders for bicyclists, impacts to local businesses, State boat launch, and emergency services during construction, Sidewalks for pedestrians,
3.3 Communication Methods to be used to inform Stakeholders:
Meetings with public officials: Meetings will be held to introduce the project to the municipalities involved and receive feedback from them. In addition, we will be discussing the opportunity for additional work to be included in the project as a betterment.
Public information meetings: Open house meetings with presentations will be held during all phases of design.
Is a citizen’s advisory committee necessary? No If yes, attach description of how it will be organized, list committee make-up and affiliation, and committee objectives.
Other public involvement techniques: Direct mailings News releases Website E-mail 3.4 Schedule for Public Involvement Activities: The first public information meeting will be held during scoping. In addition, a website will be created for public access with an email account. Direct mailings and news releases will be used to notify the public of the meetings. 4. Design
PI Objectives during Design: Preliminary Design: Summarize information gained from Scoping. Seek consensus on preferred alternative. Detailed Design: Update stakeholders on progress, discuss any changes.
4.1 Information
List Internal Stakeholders: Regional Planning; Regional Design Group; Regional Structures Group; Regional Landscape/Environmental Group; Regional Traffic and Safety Group; Regional Construction Group; Regional Maintenance Group
List External Stakeholders: City of Saratoga Springs, Town of Saratoga, County of Saratoga, USACOE, FHWA, NYSDEC, NYSOPRHP, Saratoga Lake Protection and Improvement District, Saratoga Rowing Association, Power Squadron, Mohawk Hudson Bicycling, NYS Bicycling Coalition, Saratoga Lake Association, Saratoga Lake Sailing Club, Saratoga County Historical Society, Saratoga Lake Marinas, Saratoga Lake Businesses, Emergency Services, local/seasonal residents, traveling public
4.2 Communication Methods to be Used:
Meetings with public officials: Meetings will be held as needed to keep the municipalities involved. In addition, we will be actively working with them to coordinate any additional work to be included to the project as a betterment.
Public information meetings: Meeting formats: Open house forum with a slide show presentation and an opportunity for questions. Brochure: A brochure will be provided with project information. Visualizations: Displays will be available for public viewing and comments.
Other public involvement techniques: Direct mailings News releases Website E-mail
4.3 Schedule for Public Involvement Activities: Two Public Information Meetings will be held during Phases I-IV to solicit feedback from the feasible alternatives and to present the preferred alternative selected. An additional Public Meeting may be held during Phase V if needed. The public meetings will be advertised by direct mailings and news releases. In addition, the project website will continue to provide updated project information. The public has the ability to submit comments via email. 5. Construction Phase
PI Objective During Construction: Inform and maintain contact with affected residents/businesses/other stakeholders concerning construction activity schedule and impacts.
5.1 Issues requiring continued public outreach: Maintenance and protection of traffic (MPT): To be determined Public education for operational features (e. g., roundabout):To be determined Minimizing community economic impacts during construction: Work closely with local businesses. Post-construction community feedback Other issues
5.2 Communication Methods to be Used: Pre-construction public meeting Media advertising Highway message signs Website
5.3 Schedule for Public Involvement Activities: Pre-construction public meeting to notify the public of the proposed construction schedule and impacts. Keep the public informed through the media, use of highway message signs, and project website.