KNNL ______Veerbhadeshwara LIS.

Karnataka Neeravari Nigam Limited

VEERABHADRESHWARA LIFT IRRIGATION SCHEME SALIENT FEATURES 1) 1 Name of the Project : Veerabhadreshwar Lift Irrigation Scheme. 2 Name of the River : River 3 Purpose : Irrigation Lifting Point Chikkur Tanda, Mudhol Tq. 4 a) Latitude : 15° 12’ 29” N b) Longitude 75° 23’ 35” E 5 Climate : Semi Dry 6 Irrigation System : Lift cum Flow Irrigation System Lifting of water from Ghataprabha River 1 Lift point Location : Near Chikkur Tanda Village, Mudhol(Tq), 2 Quantity of water to be lifted : 2.50 TMC 3 LIFT DETAILS a) Length of Intake Channel : 100 m b) RL from which, water is to be lifted 516.00m From To Static Head JW RL.516.00 M DC RL.670.00M 154.00 M 2) Lift arrangement details JACK WELL a) Ground Level @ JW : 532.00 m b) MDDL : 516.00 m c) Sump Floor level : 510.00 m d) MDDL : 516.00 m e) Valve Floor level : 525.00 m f) Pump/Motor Floor level : 528.00 m g) Delivery Level : 670.00 m h) Static Head : 154.00 m i) Delivery to : Delivery Chamber

Raising Type of No. of Capacity of main Diameter Length No. of Rows Material Pumps Pumps Details MS Raising 8021.00 HP / RM 2.690 M 17.20 km 1 4+1(MV) Main 6 MV

3) INTAKE CANAL a) Length : 100 mtr. b) Discharge (required) : 11.94 cumecs c) Discharge (designed) : 11.94 cumecs d) MDDL of reservoir : 516.00 M e) CBL (River bed) Assumed : 510.00 M f) Bed width : 3.00 M g) Side slope : 1:1 h) Bed fall : 1 in 1000 i) η (lined canal) : 0.018 j) Velocity : 1.69 m/sec. k) FSD : 1.95 m l) Free board : 0.60 m

______GRBC-Dn-No-5, Koujalagi. GRBC-SDn-11,Koujalagi. KNNL ______Veerbhadeshwara LIS.

Irrigation System and Distribution Network Details I. Flow Irrigation System for 17377 Ha (Khariff) Irrigable Length of the Discharge required Sl.No. Name of the canal command Remarks canal in Km. in cumecs area in Ha 1 Salhalli Main canal 20.0 11477.0 7.94 Irrigation 2 Main Canal 13.0 5900.0 4.00 by canal Total 33.00 17377.00 11.94

II. IRRIGATION:~ 1. Gross Command Area : 2. Culturable Command Area : 17377 ha 3. Irrigable Command Area : 17377 Ha 4. Intensity of Irrigation : 100.00% Khariff 5. Villages Benefited : 24 Nos

Bagalkot District 4 Nos - Mudhol Taluk :- 1)KillaHoskoti, 2) Dadahatti, 3) Gudaganal, 4) District : 30 Nos - Ramdurga Taluk :- 1),2) , 3), 4)Hoskoti, 5)Budni, 6), 7)Bichguppi, 8)Kullar, 9)Timmapura, 10), 11)Bhidaki, 12)Rokkadakatti, 13), 14)BannurTanda, 15)RampuraTanda, 16)DadibhaviTanda, 17)Chandargi M, 18)Godchi, 19), 20), 21)Chadaragi, 22), 23)Gudikoppa, 24)Chikkoppa, 25)Hirekoppa, 26)Murkatnal, 27), 28)Salhalli, 29)AribinchiTanda, 30)ObalapurTanda,

Total = 34 Nos.

6. Allocation / Utilization 2.50 TMC For irrigation purpose + M.I. Tank filling (2.40+0.10)= 2.50 TMC

III. ESTIMATED COST 1 Total cost of the project : 544.00 Crores

2 Cost per Hectare of land irrigated : Rs. 3.13 Lakhs/Ha

3 Benefit cost ratio i) At 10% : 1.32

______GRBC-Dn-No-5, Koujalagi. GRBC-SDn-11,Koujalagi.