Doncaster Metropolitan Borough Council Air Quality Action Plan.

Progress Report April 2013.

Contents

Introduction 3

Summary of Action Plan Progress 3

Table 1 Local Transport Plan Actions 6

Table 2 Stand Alone Actions from MBC 14 Air Quality Action Plan 2003

Table 3 Overview of Previously Removed and 20 Completed Actions

Conclusions 25

2

Introduction

The Air Quality Action Plan was published in 2003 following consultation with a range of stakeholders and approval from the Department for Environment, Food and Rural Affairs (DEFRA).

The plan contained 51 actions from departments across the council and with partner organisations that have the potential to impact beneficially on the air quality levels within the AQMAs specifically but also on the wider area.

The trends in air quality in Doncaster show that declining levels of pollution have stabilised and there still exists significant exceedences in the AQMAs. This trend is one of national significance and has been replicated across the South area. The difficulty comes in balancing the regeneration of the area, which continues to be one of ’s most deprived areas, with the need to protect air quality. The situation requires focus towards ensuring continued development does not hamper the achievement of the objectives. The actions referring to development control and transport will be instrumental in ensuring this.

Summary of Action Plan Progress

The action plan measures are summarised in the tables below. Table 1 contains measures that are included in the third Local Transport Plan (LTP3). Actions have been removed from the plan since the original because the initial measure has been completed, however updates have been included. This will enable the tabulated document to be used as a working document containing only those measures that need progressing.

A number of actions relating to planning have been updated with the relevant corresponding policy numbers in the Local Development Framework (LDF) Core Strategy, which has now been published. Several of these measures are now in effect complete, and all that remains is for the application of these policies through the development control system.

3 In order to focus on those measures of highest priority it is necessary to quantify the impacts of those actions. However it will not be possible to quantify strategic level actions due to their nature. It has been decided that when case studies are available these would be used to produce proxy indicators of the measures. No specific case studies have been identified, when suitable data is available this will be included within the table.

The actions in Table 2 are not directly linked to LTP priorities and therefore have been left as a series of stand-alone measures. In terms of progression the measures will be dealt with as described above.

In table 3 actions that have been removed and completed in previous reporting periods have been collated as a summary of progress.

In integrating the action plan into the LTP funding for a number of projects has been obtained. The monthly meeting of the LTP Air Quality Steering Group has provided the foundations of closer working across the authorities air quality and transport departments, of which the success of these projects demonstrates.

As we move through the third Local Transport Plan (LTP3) the projects funded here will become new actions in the action plan. Many of these projects are still in the earlier stages of implementation therefore have not yet been included in the report as specific measures but are referred to where they may contribute to current measures.

Such measures include projects looking at the implementation of electric and biogas vehicles in addition to enhanced modelling and monitoring. A scheme looking at energy generation from transport infrastructure is also included in the LTP.

The projects discussed below have been project managed by partners under the LTP scheme but not added to the action plan.

 The Care4air campaign

4 The campaign has been used across to promote air quality. A website has been produced as a resource for the public, annual conferences are held for air quality professionals to share best practice and the care4air awards are run annually. The campaign has been recognised for its good practice and the website has won numerous awards.

 South Yorkshire wide Emissions Database (EDB) on Airviro A South Yorkshire wide database has been commissioned to assess the wider impacts of transport schemes in the region on air quality. MBC and CC now have completed EDBs. Phase 2 will roll out to the other authorities.

Several transport related measures are ongoing such as cycle lanes and park and ride and although it is difficult to individually measure such actions they will work to provide choice and alternatives to the car.

5

Table 1 Action Plan Progress No. Measure Lead Sub-actions Target Progress to date Progress in last 12 Estimated Comments authority and timescales annual months completion relating to emission date emission reduction reductions Vehicle Emission Reduction 1 Undertake feasibility Doncaster 1. Collate and Attempt once Originally LTP3 projects April 2014. In Too little study into the Council read guidance actions feasibility of LEZ to include pilots for line with information introduction of Low and best defined. be considered. No electric and biogas LTP3 project available Emission Strategies practice. progress or vehicles. The timescales. regarding (LES) within the December 2009. resources success of such the effect of AQMAs and in other 2. Produce currently available projects will feed LES areas of the Borough actions and for project. Bids into consideration of generally. where vehicle timescales to were unsuccessful LES within the Once emissions have a take forward. however further region and individual major impact on air April 2010. avenues for Borough. measures quality. investment are are brought being considered. forward will try to quantify in terms of emissions reductions. 2 The council will Doncaster 1. Check Start 2010 to Original initiatives Sub-action 1: April 2013 Although continue to ensure that Council progress and start of 2011 met including Complete. (update) this is a its own vehicle fleet is assessment tonnes per introduction of bio Sub-action 2: general progressively greened results of eco- year = NOx – diesel, purchase of Progressive fleet emissions by carrying out stars scheme. 0.7 at least Euro 4 renewal to newer saving a initiatives as detailed in December 2009. PM 10 – 0.06 vehicles. Euro engine large original action plan. 2. Produce CO2 – 25. ECOstars sign up vehicles. percentage action plan and (Taken from in 2009, with a Sub-action 3: of the timescales table 4.2, 3star rating. Outstanding. vehicles will

6 No. Measure Lead Sub-actions Target Progress to date Progress in last 12 Estimated Comments authority and timescales annual months completion relating to emission date emission reduction reductions based on ECOstars Vehicle tracking travel assessment. evaluation introduced. through December 2010. report, ttr, Assessment made AQMA 1 3. Ascertain if 2010) Based by Energy Savings frequently funding on vehicle Trust 2008/2009. due to the available. replacement depot December 2010. targets. proximity. Copy of report available if required. Traffic Reduction and Management 3 Implement specific Doncaster Relocation to Attempt once Reviewed and re- Relocation to new December Policy policies within the Council new offices and actions launched in 2006. offices, new building 2012. actions Council’s Commuter associated defined. Update to staff has a planning needed prior Plan. policies in place. travel plan rolled condition for new to assessing December 2012. up into proposed travel plan to be likely relocation to CCQ produced prior to reductions to enable policies occupation. to be implemented Secured extra on new site. Bike cycling storage to work scheme in facilities and car place with 450 parking being employees signed considered. up. Pool car trial in place since February 2012. 4 Expand the existing Doncaster Feasibility study Awaiting Directly linked with Integr8 major April 2013 Details of

7 No. Measure Lead Sub-actions Target Progress to date Progress in last 12 Estimated Comments authority and timescales annual months completion relating to emission date emission reduction reductions network of bus only Council for A630. information to LTP priorities. Bus scheme has been (update) bus lanes, targeting the April 2011. implement lanes in place in withdrawn. A630 improvemen AQMAs as a first Phase 1 now proxy AQMA 1and 4. bus lane under ts to be priority. complete. Phase indicator. Feasibility for construction. South provided 2 to start May A630 complete. Yorkshire has £5 once A630 2012. million from the operational. better bus fund, Links to some for actions5 & infrastructure but 6. mostly for new buses. Included Woodfield Way bus priority measures. 5 Implement 2 park and Doncaster A638 north and South West park Completed Voluntary ride sites by 2005 and Council south opened Sept and ride to be original agreement complete a feasibility 2008. delivered as part of measure. on bus study into other sites, DRI site at larger development Further sites standards targeting as a priority racecourse by private sector at long term for routes those routes that opened August Woodfield Way. April 2013 from park traverse AQMAs. 2009. East park and ride (updates). and ride. All feasibility being at least Euro considered by 3 but most private developer. are now Patronage is Euro 4. growing steadily. Public Transport 6 Implement the A638 Doncaster Monitoring to be Repeat A638 Road The monitoring has April 2013 Repeat Quality Bus Corridor Council completed once monitoring to and A638 York not yet been (updated monitoring and investigate the works finished. be carried out Road completed repeated but there monitoring) to be carried feasibility of expanding December 2010. to compare March 2009. are several diffusion out to

8 No. Measure Lead Sub-actions Target Progress to date Progress in last 12 Estimated Comments authority and timescales annual months completion relating to emission date emission reduction reductions the Quality Bus A630 to be against before tubes along the compare Corridor scheme to implemented by results. A638 Bawtry Road against other major routes that March 2011. corridor. Tube before traverse the AQMAs, numbers 5,6, 19 results. Also beginning with the and 20. All tubes in improvemen A630 Balby Road the vicinity show a ts seen in Corridor. stable to downward park and trend since the QBC ride will be was operational. relevant. 7 Improve the Doncaster N/a N/a Ongoing Approximately 12 April 2013 Fleet attractiveness of public Council programme of bus per annum being upgrade transport use by a boarders and replaced. should result process of continual shelter in upgrading of replacement. Bus improvemen passenger pick up operators ts. See points and vehicles. upgrading fleet to Action 5. Euro III/IV engines to complement QBC/bus priority measures. 8 The council will Doncaster Feasibility of Not able to No progress Funding obtained to April 2013 Not able to investigate the Council using ECOstars quantify. made, little support look at taxi fleets in quantify. feasibility of carrying scheme to take of project. one ECOstars pilot Case out vehicle emission forward. ECOstars national area. studies may testing on the April 2010. pilot may attempt be used Boroughs fleet of signing up taxi where private hire vehicles as fleets. Will use this appropriate. part of the licensing as a case study to procedure. assess whether action should go forward.

9 No. Measure Lead Sub-actions Target Progress to date Progress in last 12 Estimated Comments authority and timescales annual months completion relating to emission date emission reduction reductions Promotion and Publicity 9 The council will, Doncaster Progress ‘Going N/a Approaches made None. April 2013. Not able to together with the Council Green Scheme’. however costs realistically operators of the new April 2011 involved quantify. transport interchange, prohibitive. Interest ensure that air quality shown in joining information, in ‘Going Green particular the current Scheme’ which level of air pollution may provide within the Borough is opportunity to made available to all progress. users of the interchange and other stakeholders. 10 The council will Doncaster N/a N/a Completed 2005. Sustrans bike-it April 2012 Not readily continue to develop the Council Ongoing officer now in place quantifiable. Safe Routes to School programme of to work full-time Will add Programme, the object minor works to with schools. 14 appropriate of which is to assess improve access to schools now have case studies and where applicable individual schools the Bronze when improve the safety of including Sustrans Mark. available. the routes taken by Campsmount and School in Doncaster children to and from Hall Cross during came top in school in order to 2009/10. Yorkshire for the encourage more ‘Big Pedal’. walking and cycling Proposals for Kirk and reduce the number Sandall and of journeys made by Hungerhill now in car. place. 11 The council will Doncaster Target of 15 N/a Completed 2005. Most of Doncaster April 2013 Not readily

10 No. Measure Lead Sub-actions Target Progress to date Progress in last 12 Estimated Comments authority and timescales annual months completion relating to emission date emission reduction reductions continue its ongoing Council further schools School travel plan Schools now signed (update) quantifiable. commitment to by March 2008 co-ordinator in up Will add producing School place 2004 and appropriate Travel Plans by funding until 2012. case studies engaging schools in Bike-it scheme in when the process of place. By March available. researching all aspects 2010 120 plans of travel to and from implemented school, linking directly which is 90% of all into the Safer Routes schools. to School Programme. One aspect of this commitment is the implementation of a Walking Bus network. 13 Ensure that all Doncaster 1.Consultation N/a LDF in place with Action 1: Complete. April 2013 Impacts at strategies in the LDF Council on LDF. policies to Action 2: Complete (update) strategic and LTP complement Summer 2010. complement action levels each other and that 2. Working on 13. difficult to development plan LTP3. April assess. allocations and local 2011. Case transport and studies of investment are closely individual linked. actions will be used were available to demonstrate emissions reductions. 14 Promote the use of Doncaster Once policy N/a None. Parking Issues relating to April 2013 Case

11 No. Measure Lead Sub-actions Target Progress to date Progress in last 12 Estimated Comments authority and timescales annual months completion relating to emission date emission reduction reductions parking polices, Council adopted assess policy adopted. charging for (update) studies of alongside other actions that workplace parking individual planning and transport have a positive for the Council are actions will measures, to promote impact on air under discussion. be used sustainable transport quality. were choices and reduce the available to reliance on the car. demonstrate emissions reductions. 15 Implement the findings LTP Awaiting N/a Regional Freight South Yorkshire April 2015 Impacts at of the countywide partnership. strategy. Strategy Group Freight Partnership strategic study into the feasibility established. in place. Business levels of producing a HGV plan produced and difficult to strategy. now a sub-group of assess. the LTP. Case studies of individual actions will be used were available to demonstrate emissions reductions. 17 Ensure that new Doncaster Consultation on N/a As part of current LDF Core Strategy April 2011. Impacts at development shall, Council LDF. Summer planning process. published. Policy strategic where appropriate, 2010. Policy to be number 9 levels contribute to the embedded in LDF, implements this difficult to provision of transport consultations action. assess. infrastructure for taken place. Case walking, cycling, public studies of

12 No. Measure Lead Sub-actions Target Progress to date Progress in last 12 Estimated Comments authority and timescales annual months completion relating to emission date emission reduction reductions transport and highway individual improvements, actions will secured through be used Section 106 were agreements. available to demonstrate emissions reductions. 18 Expand the existing Doncaster Programme to N/a Cycle lanes have Completed the April 2013 Adds to network of cycle lanes Council include further been implemented to (update) attractivenes within the Borough, phases of around Borough. route. s of cycling with particular Conisbrough to Cycling maps Roman Ridge cycle but the emphasis on the Woodfield, produced. lane due in 2012. direct AQMAs. Thorne Road impacts and Southern cannot be Greenway. realistically quantified. 19 (New The ECOstars scheme ECOstars Pilot study to Varies with Started in 2009. Successful April 2013 Case measure) was devised under the steering broaden current case. Report Successful sign up European bid to (update) studies will LTP. It is a free to sign group. scheme. produced by including several broaden scheme. be made up to scheme for April 2011 ttr on nationally National pilot available. operators of large emissions, operational scheme rolled out. See also vehicle fleets. The reductions companies. Report Awaiting information action 2. scheme awards a expected in 2 on scheme on current scheme rating for the cases. available with membership. environmental further details. standards of the fleet and provides a roadmap for improvements.

13

Table 2 Doncaster Council Stand Alone Action Plan

No. Measure Lead Sub-actions and Target Progress to date Progress in last Estimated Comments authority timescales annual 12 months completion relating to emission date emission reduction reductions Planning In Doncaster’s forthcoming Local Development Framework (LDF) Core Strategy there will be a policy regarding air quality issues specifically within Actions Doncaster. These policies act towards strengthening the potential to consider air quality in future planning applications. The following actions are expected to be within this strategy. 1 Ensure that new Doncaster N/a Consulted on core LDF core strategy Completed. Impacts at strategic developments are Council strategy, RSS and published. Policy levels difficult to located, designed relevant supplementary 2. assess. Case and managed so documents. Ongoing with studies of individual that the number of national and regional actions will be used additional vehicle guidance and consultation were available to journeys they are in development demonstrate likely to generate management process with emissions are minimised. Highways development reductions. control. Comments made on approximately 350 housing allocations. In addition to commercial/industrial and minerals allocation plans. 2 Ensure that new Doncaster N/a Green travel plans LDF Core Completed. Impacts at strategic development Council required on specific Strategy levels difficult to provides a real developments. Strategic published. Policy assess. Case choice of transportation unit 9. studies of individual transport, assesses these plans. actions will be used including walking, were available to cycling and public demonstrate transport and that emissions such development reductions. contributes to

14 No. Measure Lead Sub-actions and Target Progress to date Progress in last Estimated Comments authority timescales annual 12 months completion relating to emission date emission reduction reductions meeting the demand for the transport provision that it generates. 3 Active Doncaster N/a To include in LDF. LDF Core Completed Impacts at strategic management of Council Transport model also in Strategy levels difficult to the pattern of operation to assess published. Policy assess. Case urban growth to impacts. 2. studies of individual make the fullest actions will be used use of public were available to transport and demonstrate focus major emissions transport reductions. generators of travel demand in town and district centres and near to major public transport interchanges. 4 Ensure that day- Doncaster Pollution to N/a LDF to implement. LDF Core April 2013. Impacts at strategic to-day facilities, Council continue providing RSS allocations are in Strategy levels difficult to which need to be comments for place and local published. assess. Case near their clients allocations plan. development management Allocations plan to studies of individual in local centres, procedures refer back to follow. actions will be used are located so that this strategy. RSS no were available to they are longer in place. demonstrate accessible by emissions walking and reductions. cycling. 5 Place new Doncaster Pollution to contine N/a LDF to implement. LDF Core April 2013. Impacts at strategic

15 No. Measure Lead Sub-actions and Target Progress to date Progress in last Estimated Comments authority timescales annual 12 months completion relating to emission date emission reduction reductions housing principally Council providing Brownfield housing Strategy levels difficult to within existing comments for development now at 98% published. assess. Case urban areas, with allocations plan. RSS allocations Allocations plan to studies of individual emphasis on considered in follow. Policy 2. actions will be used locations which development management were available to are highly processes. demonstrate accessible by emissions public transport, reductions. walking and cycling. 6 Ensure that Doncaster N/a Implemented with green LDF Core Completed. Impacts at strategic development Council travel plans and LDF to Strategy levels difficult to comprising implement. published. Policy assess. Case employment 9. studies of individual shopping, leisure actions will be used and services were available to offers a realistic demonstrate choice of access emissions by public reductions. transport, walking and cycling., 7 The council will Doncaster New: Read NPPF N/a Weekly planning lists PPS 23 has now Update Not readily have regard to the Council and implement screened. In house leaflet been withdrawn. action and quantifiable. guidelines necessary produced. Monitoring NPPF adopted. implement Appropriate case contained in the changes to requirements for possible EPUK Adequacy sub-actions studies may be forth-coming consultation. Dec new exposure. checklist used to April 2013. available to revision of 2012. Standardised comments assess all air demonstrate Planning Policy based on Guidance. quality emissions Statement PPS23, New: Consider assessments reductions. Planning and implementing any received. Pollution Control, new guidance Policy 18 provides

16 No. Measure Lead Sub-actions and Target Progress to date Progress in last Estimated Comments authority timescales annual 12 months completion relating to emission date emission reduction reductions when determining available for specifically for planning assessment of air consideration of applications. quality impacts. air quality impacts April 2013. of developments. Monitoring, modelling and information dissemination. 10 The council will Doncaster Production of EDB N/a Upgraded modelling Final community April 2013 N/a continue to Council for airviro. May capabilities now in place monitoring ceased expand its air 2009. Complete. and used in Detailed January 2012. An quality monitoring Wider monitoring Assessment. area of concern is and modelling using diffusion Used community scheme now being capabilities in tubes. to widen monitoring to investigated. order to identify April 2010. local area and involve and predict areas Complete. schools. of current or Monitoring carried out with potential elevated 5 schools and 4 air pollution. communities. Community monitoring now ceased. Miscellaneous 12 The council will Doncaster Produce an No annual 22.35% since 1996. NI’s no longer June 2012 Very few Local continue to work Council Affordable Warmth target. applicable. In the Authorities have towards achieving Strategy for the Average Corporate plan achieved the 30% a 30% energy authority. The final saving is Doncaster target. In saving by 2010 by draft is awaiting 2.5% which Borough are Doncaster’s case, reducing CO2 approval by the is the signed up to a the 22.35% emissions and fuel Director of equivalent target 2% carbon reduction is a poverty, Neighbourhoods. to 13,000 reduction of local considerable increasing the t/c (tonnes authority housing achievement as no energy efficiency NI 186 – Reduce of carbon). and private stock. capital funding has

17 No. Measure Lead Sub-actions and Target Progress to date Progress in last Estimated Comments authority timescales annual 12 months completion relating to emission date emission reduction reductions and affordable carbon emissions The results will be been allocated for warmth indices of per capita. available in June private sector properties within Reported annually. 2012 but it is improvements and the Borough by expected that this this is the largest such methods as:- NI 187 – Reduce will be met. opportunity for Provision of no. of properties savings. The energy advice to with SAP <35 and Council have been householders. increase no. of one of few to make Freephone advice. properties with energy efficiency a Tailored home SAP >65 – priority in its energy reports. Reported annually. housing stock which One to one home has enabled it to energy advice make an impact on visits. this target. Over Insulation grants £15m of external and bulk discount funding has been insulation and secured to spend heating schemes. on measures over the duration of the target. 13 The council will Doncaster 1. Present to RWG N/a Attendance at Respiratory Sub action 1: April 2013. N/a liase closely with Council on areas of poor Working Group meetings. Complete. the Primary Care air quality in Sub-actions completed by Sub-action 2: Trusts responsible Borough. questionnaire to group Complete for the Borough in December 2009. members. Highlighted Sub-action 3: respect of 2. Distribute areas where more Discussed identifying any relevant information is required. information linkage between presentations on Some interest in dissemination and areas of the health and air conducting short term continuing Borough where quality to group. monitoring exercises. attendance at residents suffer December 2009. meetings. PCTs

18 No. Measure Lead Sub-actions and Target Progress to date Progress in last Estimated Comments authority timescales annual 12 months completion relating to emission date emission reduction reductions increased levels of 3. Develop are due to be respiratory ideas/search for replaced and problems and air best practice to therefore the pollution, develop measure. continuation of particularly from April 2010. this action will traffic emissions. depend on working with newly formed departments.

19

Table 3 Overview of Previously Removed and Completed Actions Action Original Progress up to & including Complete Priority action & timescale Timescale 2008 Y/N Investigate the feasibility of Feasibility No progress. Resistance to action N Action removed 2007. Unlikely to be taken forward. introducing High Occupancy Vehicle study by and no funding. Nature of road Lanes on the major arterial routes into December network an issue. town 2004. The council, together with the SYPTA Feasibility No progress made, other bus N Action removed 2007. No progress/funding. will carry out a feasibility study into 2003. projects going ahead such as the use of guided bus lanes QBC. The council will approach the December No progress was made. Not N Action removed 2007. Highways Authority in order to 2003. feasible given limited space on investigate the possibility of using the message boards. new electronic message signs located on the motorways traversing the Borough to provide air quality information and pollution episode warnings. The council will support and promote December Interchange completed 2006 Y Action removed 2008. the new transport interchange in order 2005 to ensure a fully integrated road/rail public transportation system is provided for the residents of and visitors to the Borough. The council will expand the Borough’s December Completed 2005. No further Y Action removed 2008. successful “Quality Streets” initiative 2005 pedestrianisation planned. to extend the amount of pedestrianised streets, both within the town centre and the retail centres of the satellite towns. The council will continue to minimise No Reactive work now outside of Y Action removed 2009. domestic emissions to the deadline Pollution Control team remit.

20 atmosphere by rigorous enforcement Procedure continues. of the Clean Air Act. The council will continue to use all its No Transfer to PPC, risk based Y Action removed 2009. powers to control industrial & deadline – inspections completed. commercial emissions to the ongoing. Enforcement carried out to non- atmosphere by liaison with the compliance in 2007. Environment Agency in respect of Inspections completed on time. Part A processes and the institution of risk based process inspection in respect of Part B Processes. The council will expand its existing air No Information updates 3 times a day Y Action removed 2009. quality information provision service deadline. – web, radio and answer phone. Twitter account set-up. to include more use of strategically Public display units and screens. Information on plasma screens in main Council public buildings. located electronic information Website has won awards. message units. The council will produce an air quality December Done in collaboration with wider N Action removed 2009. promotion and project pack for use in 2003 departmental themes. schools to encourage children to All primary years presentations in become aware of the importance of place. good air quality and the role that Monitoring project first round now private car use and public transport complete. can play in decreasing and improving air quality respectively Acquire, produce if necessary and December Motorists guide, developers guide Y Action removed 2009. distribute relevant leaflets and 2003 and air matters leaflets produced promotional material relating to and distributed. improving air quality and reducing (in Walk the first mile booklets for particular vehicle) emissions. This council officers collaboration. material to be distributed in all council Care4Air materials including eco- offices where the public may visit, driving. major retails outlets, libraries, GP’s surgeries and hospitals and all public events. When considering a planning No Pollution should be consulted on N Action removed 2009. application the council shall: - deadline. all major applications, sometimes

21 A. Ensure that air quality Procedure failing. Attempting to screen impacts are fully considered set up to weekly lists to close loophole in all Environmental Impact deal with however this doesn’t allow us to Assessments application catch pre-application discussions B. Ensure that air quality s. or EIA scoping reports. impacts are fully considered in all Traffic Impact Assessments C. Fully consider air quality impacts where traffic volumes are anticipated to increase on roads within or near to AQMAs. D. Ensure that new developments do not lead to the declaration of further AQMAs if they are planned to be located near to busy roads etc

The council will actively participate in October Completed. Y Action removed 2009. ‘Walk to School Week’ in order to use 2002 then Continued support. First event this as a starting point for sustainable annual 2002 then annually. walking to school. participatio n. Ensure that all travel information December Included on materials where Y Action removed 2009. leaflets, maps and information for the 2005 appropriate. Borough contain information on the public transport, cycling and walking amenities. The council will actively support and No ‘In town without my car day’ Y Action removed 2009. take part in all national and local deadline supported in conjunction with events targeted towards reducing EMW. private car use, increasing public Staff initiatives. ‘Walk the first transport and cycling use and mile’ along with production of

22 reducing traffic pollution. Examples maps. include “Walk to Work Day”, “Don’t Care4Air events. Choke Britain Campaign” and “DMBC Funding committed via LTP. Car Sharing Promotion”. Introduce a council car sharing April 2003 Scheme set-up 2002. Widened to Y Action removed 2009. scheme Bassetlaw and Doncaster NHS Trusts. 160 staff registered at 2007. The council will review its car December Policy is set nationally and little N Action removed 2009. allowance and car loan schemes in 2003 impact can be made within one Mileage rates reduced and standardised across engine size. order to identify and implement council alone. Consultation is only Pool cars being trialled. reforms which encourage the use of option. the cleanest and most fuel efficient vehicles and minimise business mileage inline with Inland Revenue payment guidelines. Liase with the Vehicle Inspectorate to December Procedure in place to forward all Y Action removed 2009.. ensure all vehicles producing 2005 complaints. excessive and visible exhaust emissions “smoky vehicles” are inspected, tested and their emission reduced to acceptable levels. Carry out the Authority’s duties under December Initial testing carried out in 2004. Y .Action removed 2009. Road Traffic (Vehicle 2003 Successful as an awareness Emissions)(Fixed Penalty)(England) campaign. Regulations 2002 in respect of Second round in 2007 data used carrying out roadside vehicle to inform fleet composition emission testing and issuing fixed throughout South Yorkshire penalty notice in partnership with the AQMAs. other South Yorkshire Local Authorities and the Police. Carry out the Authorities duties under December Initially completed 2003. Y Action removed 2009. Road Traffic (Vehicle 2003 Informal surveys undertaken on Emissions)(Fixed Penalty)(England) an ad-hoc basis, some warnings Regulations 2002 in respect of issued.

23 stopping engines when vehicles are stationary and together with the SYPTE encourage bus drivers to switch off their engines when stationary. Ensure that all transport termini and December Compliant by 2003. Y Action removed 2009. bus stops are provided with prominent 2003 New interchange replaced signs requiring drivers to switch off original bus stations in 2006 and their engine when stationary. is now compliant.

24 Conclusion

The action plan measures continue to be progressed. No further measures are expected to be removed from the plan in the forthcoming year however it is expected that the next action plan will included measures from the LTP.

Proxy indicators are still required for many measures and any data made available will be used to formulate these when possible.

A further action plan will need to be produced, in 2013, for Doncaster’s fifth Air Quality Management Area, it may be possible to either integrate or update the wider action plan at this time. A progress report will be required in April 2013.

25 References

Air Quality Action Plan, 2003, Doncaster MBC

Air Quality Action Plan Progress Reports, 2004/2005/2006/2007/2008/2010/2011, Doncaster MBC.

Doncaster MBCs Planning and Development Control Department.

Local Development Framework, Planning Policy, Doncaster Council

Updating and Screening Assessment, 2009, Doncaster MBC

Strategic Transportation Unit, 2012