The World Bank Report No: ISR9457

Implementation Status & Results Urban Development Project (P083322)

Operation Name: Sichuan Urban Development Project (P083322) Project Stage: Implementation Seq.No: 9 Status: ARCHIVED Archive Date: 22-Jun-2013 Country: China Approval FY: 2007

Public Disclosure Authorized Product Line:IBRD/IDA Region: EAST ASIA AND PACIFIC Lending Instrument: Specific Investment Loan Implementing Agency(ies): Key Dates Board Approval Date 07-Sep-2006 Original Closing Date 31-Dec-2013 Planned Mid Term Review Date 01-Sep-2010 Last Archived ISR Date 23-Dec-2012 Public Disclosure Copy Effectiveness Date 05-Jan-2007 Revised Closing Date 31-Dec-2013 Actual Mid Term Review Date 10-Jan-2011

Project Development Objectives Project Development Objective (from Project Appraisal Document) To improve core urban functions in an equitable and resource efficient manner by removing identified infrastructure bottlenecks hampering land development, transport, and environmental conditions in four second-tier cities in Sichuan Province. Has the Project Development Objective been changed since Board Approval of the Project?

Yes No Public Disclosure Authorized Component(s)

Component Name Component Cost Pioneer Park 49.96 Mianyang Southern Economic Development Zone (SEDZ) 48.73 Suining Area 58.23 Suining Xining Road 6.75 Route A 40.44 Yibin Route B 35.91 Bing-Ren Road 80.22 Panzhihua Bing-Jiang Road 9.32

Public Disclosure Authorized Panzhihua: Sewerage 10.41 Panzhihua: River embarkment and landscape improvement 25.60

Overall Ratings Previous Rating Current Rating Public Disclosure Copy Progress towards achievement of PDO Satisfactory Satisfactory Overall Implementation Progress (IP) Satisfactory Satisfactory

Page 1 of 6 Public Disclosure Authorized The World Bank Report No: ISR9457

Previous Rating Current Rating Overall Risk Rating Moderate Moderate

Implementation Status Overview The project is making good progress towards removing identified infrastructure bottlenecks and improving environmental conditions in four medium-sized cities, Mianyang, Suining, Yibin, Panzhihua, in Sichuan Province.

In Suining, all project related investments have been completed and provide improved access to the new development and urban expansion zone in Xining District.

In Yibin, both roads (Route A and B) and two bridges have been opened to traffic. Route A greatly improved connectivity between the old city, the Tianyuan District and the proposed new Lingang Economic Development Zone. River embankments along Route B have been improved and include a widely used walkway, the road has also been westward from the

Public Disclosure Copy Cultural Square in the center of Nan An District and eventually connect to a new development zone planned towards the west of the city.

In Panzhihua, all roads were completed and opened to traffic, including bridges and tunnels, which have greatly reduced travel times and improved accessibility to new areas of the city, thereby reducing congestion in the downtown area. The sewerage works have been completed and wastewater treatment collection and treatment volumes have increased.

All road investments in the Southern Economic Development Zone in Mianyang have been substantially completed and opened to traffic. The improved access and overall infrastructure conditions have helped increase land sales and revenues. In Pioneer Park, most roads have been opened to traffic and have improved access, benefiting land sales. The only ongoing construction is in the Xinglong Area, which were included as part of the restructuring of the project. These works are moving forward reasonably well, but experienced some delays due to slow resettlement and land acquisition progress.

Locations Country First Administrative Division Location Planned Actual China Sichuan Sheng Yibin

China Sichuan Sheng Xining

China Sichuan Sheng Mianyang

China Sichuan Sheng Panzhihua

Results

Project Development Objective Indicators Public Disclosure Copy

Page 2 of 6 The World Bank Report No: ISR9457

Indicator Name Core Unit of Measure Baseline Current End Target Evidence that identified bottlenecks have been Text Value Not applicable Time savings on the roads Evidence identified via reports removed, as expected by the strategic are apparent adn overal from technical and social investments of the project, including a high satisfaction of PAPs is high, audits level of satisfaction among users of but need a more detailed investments and PAP assessment. Date 07-Sep-2006 30-Apr-2013 28-Jun-2013 Comments Critical bottlenecks have been addressed and roads are operational.

Public Disclosure Copy Intermediate Results Indicators Indicator Name Core Unit of Measure Baseline Current End Target Mianyang: Area of land sold (ha) Text Value 0 Pioneer Park: 208ha Pioneer Park: 238; SEDZ: 312 SEDZ: 192.4ha Date 01-Dec-2005 30-Apr-2013 28-Jun-2013 Comments The previous number in the Difficult to quantify in how far report for SEDZ was wrong this (infrastructure) project and has been corrected. contributes to land sales and values. Mianyang: Number of new residents on site Text Value 0 Pioneer Park: 65,020 30,440 (Pioneer Park), 18,202 SEDZ: 3,850 (SEDZ) Date 01-Dec-2005 30-Apr-2013 28-Jun-2013 Comments The numbers reflect changes in policies after the Earthquake, with more residents moving to PP. Mianyang: Satisfaction of PAPs with Text Value Not applicable 75% of PAPs satisfied with resettlement process and outcome in both resettlement process and Pioneer Park and SEDZ. outcome both in Pioneer Park and SEDZ Date 01-Dec-2005 30-Apr-2013 28-Jun-2013 Comments Final survey is being prepared as the reported number of 100% is not believable and need to be substantiated. Suining: Area of land sold (ha) Text Value 0 70.6ha 141 ha Date 01-Dec-2005 30-Apr-2013 28-Jun-2013 Public Disclosure Copy Comments Difficult to quantify in how far this (infrastructure) project

Page 3 of 6 The World Bank Report No: ISR9457

contributes to this indicator (land area sold). Suining: Number of new residents on site Text Value 0 17,500 19,820 Date 01-Dec-2005 30-Apr-2013 28-Jun-2013 Comments Suining: Satisfaction of PAPs with resettlement Text Value Not applicable 75% of PAPs satisfied with process and outcome resettlement process and outcome Date 01-Dec-2005 30-Apr-2013 28-Jun-2013 Comments Site visits find the majority of PAP satisfied, but more Public Disclosure Copy detailed information needs to be collected after completion of activities. Yibin: Reduced travel time from Mianjiang Text Value 10 min 6 min 7.5 min Bridge to Chang Jiang Bridge: Travel time in Date 01-Dec-2005 30-Apr-2013 28-Jun-2013 minutes at peak Comments Yibin: Satisfaction level of landscape Text Value Not applicable 75% of sampled people improvements satisfied with landscape improvements Date 01-Dec-2005 30-Apr-2013 28-Jun-2013 Comments A proper survey needs to be conducted. Yibin: Satisfaction of PAPs with resettlement Text Value Not applicable 75% of PAPs satisfied with process and outcome resettlement process and outcome Date 01-Dec-2005 30-Apr-2013 28-Jun-2013 Comments A proper survey needs to be conducted. Panzhihua: Wastewater service coverage Text Value 40 88 85 (average wastewater volume collected and Date 01-Dec-2005 30-Apr-2013 28-Jun-2013 treated, 1000 m3/d) Comments Revised since the previous number was wrong (referred to length of sewer constructed). Panzhihua: Reduced travel time at peak in Text Value 56.4 min. 20 49.9 min. minutes -- East Duren Road at KM 49 to Date 01-Dec-2005 30-Apr-2013 28-Jun-2013

Public Disclosure Copy railway station Comments Greatly reduced as a result of a tunnel built.

Page 4 of 6 The World Bank Report No: ISR9457

Panzhihua: Satisfaction level of scenic Text Value Not applicable 75% of sampled people improvements satisfied with landscape improvements Date 01-Dec-2005 30-Apr-2013 28-Jun-2013 Comments Results will be provided as part of the final survey. Panzhihua: Satisfaction of PAPs with Text Value Not applicable 75% of PAPs satisfied with resettlement process and outcome resettlement process and outcome Date 01-Dec-2005 30-Apr-2013 28-Jun-2013 Comments A survey will be conducted at Public Disclosure Copy the end of project when resettlement activities have been fully completed. Suining: Travel time in minutes at peak from Text Value 25 min 16 min Railway station to Xining District Date 01-Dec-2005 30-Apr-2013 28-Jun-2013 Comments No data has been reported recently. Roads constructed, non-rural Kilometers Value 0.00 80.70 87.10 Date 01-Dec-2005 30-Apr-2013 28-Jun-2013 Comments This include all roads and Core indicators being Cumulative for all 4 cities. sewage and drainage measured first time at an pipelines (including service aggregate level for all cities. roads as described in the restructuring paper). People provided with access to ‘improved Number Value 21300.00 24375.00 sanitation facilities” under the proj. Date 30-Apr-2013 30-Jun-2013 Comments Based on number of households connected (7,100) x 3 people/household. People provided with access to “improved Number Value 21300.00 24375.00 sanitation facilities” - urban Sub Type Date 30-Apr-2013 30-Jun-2013 Breakdown Comments Based on number of Based on number of households connected households connected (7,100) x 3 people/household. (8,125) x 3 people/household.

Data on Financial Performance (as of 27-Dec-2012) Public Disclosure Copy Financial Agreement(s) Key Dates

Page 5 of 6 The World Bank Report No: ISR9457

Project Ln/Cr/Tf Status Approval Date Signing Date Effectiveness Date Original Closing Date Revised Closing Date P083322 IBRD-48380 Effective 07-Sep-2006 27-Oct-2006 05-Jan-2007 31-Dec-2013 31-Dec-2013

Disbursements (in Millions) Project Ln/Cr/Tf Status Currency Original Revised Cancelled Disbursed Undisbursed % Disbursed P083322 IBRD-48380 Effective USD 180.00 180.00 0.00 177.52 2.48 99.00

Disbursement Graph Public Disclosure Copy

Key Decisions Regarding Implementation The are a few punctual resettlement issues that need to be resolved, so the roads can be fully utilized and benefit the local population.

Restructuring History Level two Approved on 18-Aug-2011

Related Projects There are no related projects. Public Disclosure Copy