KAYSON Oil, Gas & Industry Building a Better World for Future Generations Mission To Provide World- Class Construction Services through People and Organizational Development to Improve the Quality of Life

Values ■ Respecting People, Their Values & Rights ■ Observing Professional Ethics and Adhering to all Obligations ■ Insisting on Health, Safety and Environment ■ Esteeming Desired Quality ■ Cherishing Creativity, Initiative and Innovation Culture ■ Promoting Continual Technical & Managerial Improvements ■ Evolving Win-Win-Win Relationship

Services ■ Project Development ■ Project Management ■ Engineering ■ Procurement ■ Construction ■ Financing ■ Investment in Design and Construction and Sale of Economic Plans ■ Utilities Operation and Maintenance

Divisions

Oil, Gas and Industry ■ Refineries & Petrochemical Plants ■ Pumping & Compressor Stations ■ Power Generation Plants, Power Transmission & Substations ■ Industrial Manufacturing Plants ■ Pipelines & Tank Farms ■ Gas Injection Projects

Housing and Urban Development ■ Mass Housing ■ Residential Complexes ■ Townships ■ Infrastructure Facilities & Landscaping

Railway Transportation Systems ■ Railways ■ Urban Railways ■ Monorails

Water and Wastewater ■ Dams ■ Water Transfer and Diversion Tunnels ■ Irrigation and Drainage Networks ■ Water and Wastewater Treatment Plants ■ Water Transmission Lines ■ Sewerage Collection and Transmission Lines (by Pipejacking Method)

Civil and Building ■ Commercial & Office Complexes ■ Sports, Recreational, Cultural & Medical Facilities ■ Ports & Harbors ■ Airports ■ Roads, Elevated Highways & Tunnels ■ Bridges National Commitment

■ Poldasht Irrigation & Drainage Network ■ Ray – Ideloo 346 Km, 16” Oil Pipeline ■ Sattarkhan (Ahar) Clay Core Earth Dam & Related Facilities ■ East Anzali Wastewater Treatment Plant ■ Foomanat (D1) Irrigation and Drainage Network ■ Siah Bishe Pumped Storage Project Upper & Lower Dams ■ Neka-Ray Crude-Oil Pipeline Pumping Stations and Related Installations

Poldasht ■ Aliabad Katoul-Shahrood 70 km, 16” Gas Pipeline Ahar ■ Al-Teymour (Mashhad) Wastewater Treatment Plant Tabriz Anzali Lahijan Neka Mashhad ■ Petroleum Tanks of Siah Bishe Shahrood Torbateh Hydarieh City ■ Hamedan Sewerage Project Torbateh Hydarieh by Pipe-Jacking Method Qom ■ 7200 Tonne/Day Saveh Grey ■ Kermanshah 4,920–unit Cement Plant, Production Lines Housing Project Kermanshah ■ National Qom Monorail System Hamedan Line 1, Phase 1&2 ■ 400-Unit Cement Factory Workers Doroud Residential Complex of Doroud City Esfahan ■ Esfahan – Foolad Shahr Highway Ahwaz (Section II) Shahin Shahr Highway Marvdasht ■ East Ahwaz Wastewater Treatment Plant Aghajari ■ Ahwaz Urban Railway Project Rafsanjan ■ Goyom – Marvdasht Farashband ■ 1505-Unit Ahwaz Teachers’ Residential Complex 27 Km,16” Gas Pipeline ■ Hamidieh-Qods Plain Irrigation and Drainage Network Tonbak Sirjan ■ Rafsanjan Sports & Cultural ■ Shirin Shahr Township Civil Works & Infrastructural Complex Installations Assaluyeh ■ Esfahan – Rafsanjan 232 Km, 16” Oil Pipeline Bandar Abbas ■ Aghajari Gas Injection Project ■ Bandar Abbas – Rafsanjan 104 Km, 26” Oil Pipeline ■ EPC2 South Pars Gas Field Development, Phase 12 ■ Golgohar Pelletizing Plant

■ Almahdi Aluminum ■ Civil & Underground Works in Olefin Plant-Bushehr Petrochemical Co. ■ Mall Commercial Complex Complex ■ 4th Aromatics Plant, Process Area ■ Ayandeh Bank Headquarter’s Building ■ South Pars, Phases 4 & 5 Site Preparation ■ Farashband Gas Refinery ■ Tehran Sewerage Pipeline Project via ■ South Pars Field Development Project, Phases 2 & 3, Processing Unit Pipejacking Method Site Preparation Development Plan ■ Parand New City 16,080–unit Housing Project ■ Civil Work (A,B,C,D South Pars Gas Field ■ Tehran Book Garden Development Phase-1 Plant ■ Sattarkhan Great Mall ■ Planning System & Project Control of , Lines 1 & 2 ■ Amir Kabir Commercial Complex ■ Amir Kabir Underground Motorway ■ Imam Khomeini International Airport ■ Navab Residential Complex ■ Yadegar Imam Flyover ■ Central Fruit & Vegetable Market of Tehran (Phase 2) ■ Afsarieh Interchange ■ Parand 552-Unit Residential Complex ■ Drilling and Grouting Operations of Tehran Metro Tunnel, Lines 1&2 ■ Transfer Canals of Tehran's Subsurface Waters to and Rey Plain ■ Sorkhe-Hessar & Valfajr Water Canals World-Class Construction

Minsk New City Center ƒ ƒ Rehabilitation and Widening of Bishkek-Osh Road

Prilesie Logistic Center ƒ

ƒ 1,920-Unit Housing Project, Baghdad

Construction of Akuetom- Mocomo- ƒ Djibloo- Bizam road in D’Anisok district Belarus ƒ Al Kifil Water Treatment Plant and Irrigation Network Project Kyrgyzstan Iraq India Oman Cameroon Venezuela Equatorial ƒ Al Nasseriya Water Treatment Plant Guinea and Irrigation Network Project Construction of Sangmelima to Bikoula ƒ Road

ƒ Iraqi Airways’ Cargo Village in Baghdad ƒ Iraqi Airways’ Aircraft Training Center in Baghdad Bridge Across the Wadi Bani Souq in ƒ Wilayat Rustaq Khasab to Al-Khalidyeh Road ƒ

ƒ Widening & Strengthening of Andhra 10,000-Unit Housing Project ƒ Pradesh State Highway (APSH9)

10,008-Unit Housing Project ƒ South Pars Gas Field Development – Phase 12 Onshore Facilities, Gas Condensates Processing and Utilities (EPC2)

Project Outline gas condensate as well as 750 tonnes of The South Pars is a natural gas and granulated sulfur per day. Client: Petropars Limited condensate field located in the Persian Gulf. Partners: South Korea’s Daelim, Sazeh and It is the largest gas field shared between Iran The onshore gas treatment facilities of South IIND of Iran (DSKI joint venture) and Qatar. The field encompasses an area Pars gas field development project (Phase Type of Contract: EPCC (Engineering, of nearly 9,700 square kilometers, of which 12) have been broken down into three Procurement, Construction and 3,700 square kilometers belongs to Iran. separate EPC projects, the most important Commissioning) According to the latest estimates, the Iranian of which, EPC2, is carried out by DSKI Contract Period: 40 months part of the field holds 14 trillion cubic meters joint venture, including Daelim of South Location: Tombak Area, Bushehr Province, of in-place gas, equivalent to 50 percent Korea; Sazeh Consultants, Engineering & Iran of Iran’s and 8 percent of the world’s total Construction; Kayson and Iran Industrial Status: Under Construction associated gas reserves. The Iranian side Networks Development Company (IIND). also holds 18 billion barrels of condensates. The onshore facilities of Phase 12 are comprised of the following units: Phase 12 is situated in the southeastern block of the South Pars gas filed on the ■ Receiver and separator of border with Qatar and covers an area equal gas and condensates to 130 square kilometers. The onshore ■ Gas condensate stabilization unit facilities of EPC2 portion is being built by ■ Six identical trains for gas the DSKI joint venture in Tombak area some processing each consisting of 55 Km west of Assaluyeh. Sweetening unit, Dehydration unit, Dry gas Dew-pointing The purpose of developing Phase 12 is to unit, De-mercaptanization produce 78 MMSCMD natural gas to inject unit. (The daily output of each into IGAT-6 pipeline and alternatively to train is 500 MMSCFD) deliver two third of the capacity, as sour ■ Export gas compression unit wet gas, to liquefying natural gas units of ■ Sulfur recovery and granulation unit IRAN L.N.G Project. Another executive ■ Mono-Ethylene Glycol (MEG) objective of this great national project regeneration unit is to produce 120,000 barrels of heavy ■ Utility services such as emergency Scope of Work Key statistics power, steam, desalination, The project’s scope of work includes ■ Cut and fill: 1,334,000 m3 water treatment, Nitrogen engineering, procurement, and installation of: ■ Piping: 975,500 inch-dia plant, instrument & utility air ■ Marine pipeline, pig receiver, ■ Equipment weight: 17,447 t ■ Other services such as Slug catcher, HP separators ■ Steel structure: 23,000 t flare system, Fuel gas unit, ■ Gas condensate ■ Concrete: 152,000 m3 Water fire fighting system, stabilization-backup unit ■ Industrial buildings: 18,200 m2 wastewater treatment unit ■ Mono Ethylene Glycol ■ Camp area: 61,200 m2 ■ Control rooms, Power substations, (MEG) regeneration unit/ ■ Electrical cabling:1,508,000 m Laboratory, Workshop, Offices sour water stripper ■ Instrument cabling: 993,000 m ■ Four storage & exportation ■ Flares, Blow down, Burn reservoirs for gas condensates Pit system, Utilities and offsite drain system The contract of phase 12 onshore includes ■ Technical buildings, Central site preparation for an area of about control building, Laboratory, 220 hectares for the refinery and 78 hectares Telecommunication building for housing camps, as well as costal and Access roads protection and some other works which are ■ Emergency power system, Steam considered as project services. generator, Fuel gas system ■ Instrument and utility air, Nitrogen generation plant ■ Sea water intake & outfall, Waste effluent disposal ■ Sea water desalination, Water polishing through ion exchangers, Wastewater treatment unit, Potable water purification unit, Cooling water 4th Aromatics Plant, Process Area

Project Outline light hydrocarbons, heavy aromatics and The 4th Aromatics Plant is the world’s raffinate are considered as byproducts of Client: Borzouyeh Petrochemical Company largest petrochemical aromatics producing this plant and 3.19 million tonnes of them are Partners: Jahan Pars & Tehran Jonoob complex. The Oil Ministry and the National yearly produced. The annual feedstocks of Companies Petrochemical Company (NPC) of Iran the plant are supplied by the liquefied gases Consulting Engineers: SAZEH, LG, TEC awarded this project to a joint venture of first, second and third phases of South Supervision Body: SAZEH between Jahan Pars, Kayson and Tehran Pas Gas Field which are 4.5 million tonnes as Type of Contract: Construction Jonoob companies. well as 270,000 tonnes of benzene pyrolysis Contract Period: 26 months which are provided by Jam Petrochemical Location: Assaluyeh, Bushehr province, Iran The project employed over 2,500 workers Company, the implementer of the 10th Olefin Status: Completed and nearly 250 site staff, mostly engineers project. and technicians, making it one of the largest petrochemical projects carried out by a private sector company in Iran.

With a total annual capacity of 1.28 million tonnes, the plant produces 750,000 tonnes of paraxylene, 430,000 tonnes of benzene and 100,000 tonnes of orthoxylene per year as its main products. Pentane cut, liquefied gas, Scope of Work Key Statistics The project involved civil and structural ■ Earthwork: 394,000 m3 works, installation of mechanical and ■ Total Concrete: 77,000 m3 electrical equipment, instrumentation, above ■ Industrial Building: 12,000 m2 and underground cabling and piping. An ■ Steel Structure: 6,750 t important feature of the project was the ■ Total Piping: 1,110,000 (inch-dia) contractor’s commitment to operate a quality ■ Super heavy Equipment: 6,800 t management system based on ISO 9001 ■ Fixed, Rotary, Fire Heaters: standards, using advanced techniques of 23,000 t project control and putting in place effective ■ Insulation Work: 160,000 m2 occupational health, safety & environmental ■ Electrical Cabling: 636 km management systems. ■ Instrument Cabling: 513 km* ■ Painting: 346,000 m2

* 11,000 I/O Aghajari Gas Injection Project

Project Outline Natural gas from South Pars Gas Field largely Client: Petroleum Engineering & is slated to be shipped north for home and Development Co. (PEDEC) industrial consumption via a planned 56 inch, Partners: Hirbodan EPC & Chegalesh 512 kilometer, IGAT-3 pipeline. The gas, Consulting Engineers Companies (Mehras) mainly from phases 6, 7 & 8 of South Pars Type of Contract: EPC (Engineering, Gas Field (Assaluyeh), will also be reinjected Procurement & Construction) to boost output at the huge Aghajari field. Contract Period: 36 months The pressure of the gas entering Aghajari Location: Aghajari, Khuzistan Province, Iran Gas Injection station is increased 240 bars Status: Completed by seven turbo-compressor units in two stages, transported out of the station by means of two 24-inch North-South pipelines and injected into 22 oil wells. Main equipment of Aghajari Gas Injection station

Turbo compressor: Each set of turbo compressors includes a 32,587 KW turbine (in ISO Rating condition), one gearbox for accelerating rotation speed, helical gear with 1:2/5 transmission coefficient and a 2-stage, 6-blade, back-to- back compressor. The gas which flows into the station, reaches the pressure of 130 and 240 bars at the first and second stages, respectively. A decrease in temperature is the result of the flow of gas into the air coolers after each stage.

Air Cooler: As mentioned before, each set of turbo compressors is equipped with two air coolers known as stage 1 and stage 2 air coolers. The first and second stage air coolers, which operate with 37 KW, 400 volt motors respectively, cool the compressed fluid by increasing its pressure initially 140 bars and then 258 bars to achieve the desired temperature. Each cooler has four impellers and four motors.

Pressure Vessel: There are 22 pressure vessels at the gas injection station, including: ■ KO drum of the first stage: 7 units ■ KO drum of the second stage: 7 units ■ Fuel HP KO Drum: 1 unit ■ Fuel LP KO Drum: 1 unit ■ Flare KO Drum: 1 unit ■ Air Receiver: 1 unit ■ Feed-line Scrubber: 1 unit ■ Instrument Air: 1 unit ■ Nitrogen Storage Vessel: 2 units

Storage Tank: There are five storage tanks at the gas injection station, including: ■ A 4,750 m3 fire-fighting water tank ■ A 100 m3 diesel fuel tank ■ A 72 m3 fresh turbine oil tank ■ A 72 m3 meter used turbine oil tank ■ A 71 m3 drinking water tank 7200 Tonne/Day Saveh Grey Cement Plant, Production Lines

Project Outline Limestone, the main raw material used in The Saveh grey cement factory is located Saveh grey cement factory, is acquired from Client: Saveh White Cement Company 50 km from Saveh, a city in Markazi province the huge Doshakh quarry located only 4 km Consulting Engineers: Archen Consulting in central Iran. Encompassing an area of away from the project site. Also, 400 hectares Engineers 120 hectares, the plant is set to produce of uncultivated land surrounding the factory Type of Contract: Construction 7200 tonnes of cement per day, which can is devoted to planting trees, shrubs, and Location: Saveh, Markazi Province, Iran be increased to 8000 tonnes. Saveh grey other greeneries, thus providing a pleasant Status: Completed cement factory is one of the most advanced scenery and minimizing the factory’s cement producing plants in Iran, as well as negative impacts on the environment. the Middle East. Given the fact that over the past 20 years construction time for cement factories built in Iran has averaged 8 years or more, the Saveh factory is completed in 36 months (including civil & installation works), is destined to usher in a new era in Iran’s cement industry as far the speed of construction is concerned. The plant will also exceed national quality standards. Scope of Work Key Statistics Kayson’s scope of work involved the civil ■ Concrete: 145,000 m3 works of Saveh grey cement factory’s ■ Reinforcement: 18,000 t production lines, including cut and fill ■ Formwork: 250,000 m2 operations, concrete pour of above and ■ Heavy steelwork: 4000 t under-ground structures, limestone crushing ■ Earthwork: 220,000 m3 plant, raw mill feed bunkers, raw mills, two nine-stage 110-meter high preheaters, coolers, ESP (electrostatic precipitator) dedusting units, cement silos, clinker silos, packing and loading plant, blending silos, masonry work, building construction, structural steelwork, etc. South Pars Gas Field Development – Phase 12 Onshore Facilities, Gas Condensates Processing and Utilities (EPC2)

Almahdi Aluminum Complex (8 Separate Contracts)

Project Outline Construction Time and Kick-off Date of Each Almahdi is one of the largest and most Contract: Client: Almahdi Aluminum Complex modern aluminum smelting plants in the ■ Civil engineering work of Consulting Engineers: M & F Wimpey, Novin, Middle East. phase 1: 24 months, 1992 Kahanroba, Pars Adak, Noha, Enerji Farda, ■ Manufacture and sale of steel Parsican Iran structures of the potroom: Location: Bandar Abbas, Hormozgan 7.5 months, 1993 Province, Iran ■ Transportation and installation Status: Completed of potroom’s steel structures: 9 months,1993 ■ Zinc factory: 6 months, 1994 (Client: Iran Mineral Processing Co.) ■ Civil engineering works of P.F.T.P. units 1 & 2: 10 months, 1994 ■ Wastewater network and landscaping: 8 months, 1995 ■ Anode-rodding and pallet storage: 30 months, 1995 ■ Electrical substation and rectifier: 20 months, 1997 Main Features ■ Design, manufacture and installation of machinery and equipment ■ Civil engineering work relating to pot repair shop, warehouse, workshop, with a total area of 64,000 m2 ■ Installation of a substation, rectifier & auxiliary facilities ■ Anode rodding plant: 17,000 m2 ■ Zinc smelting plant: 10,000 m2 ■ Surface water network: 5200 m ■ Earthwork: 408,500 m3 ■ Concrete: 120,000 m3 ■ Reinforcement: 9,980 t ■ Steel structure: 2,290 t ■ Formwork: 134,000 m2 Neka-Ray Crude-Oil Pipeline Pumping Stations & Related Installations

Project Outline This swap project which was implemented Client: National Iranian Oil Engineering & by our client, the National Iranian Oil Construction Co. Engineering and Construction Company, is Supervision Body: Pars Consulting designed to facilitate the transfer of crude Engineering Group oil from littoral states of Caspian sea to Type of Contract: EPC (Engineering, petroleum refining facilities in Tehran. The Procurement & Construction) project called for the installation of 16-inch Contract Period: 18 Months and 32-inch crude-oil pipelines, with a daily Location: Neka-Ray, Iran capacity of 115,000 barrels of crude oil in Status: Completed its first phase. The project’s capacity will increase to 370,000 and 500,000 barrels per day respectively when the second and third phases of the project come online.

The 340 km crude oil pipeline links the Caspian Sea to Iran’s 250,000 bpd Tehran refinery and the 100,000 bpd Tabriz refinery. Five international companies, including Russia’s Lukoil, Dublin-based Dragon Oil, Kazakhstan’s Munai-Impex, BP-controlled Sidanco and European trader Vitol, are already involved in shipping crude to Neka. The oil delivered is exchanged for an equal amount of Iranian crude loaded for export at Iran’s Kharg Island terminal in the Persian Gulf.

Scope of Work The Project’s basic engineering was performed by the design & engineering division of National Iranian Oil Company (NIOC) and the installation of 4 pumping stations, a pressure breaker, and a terminal was awarded to Kayson within the framework of an EPC (Engineering, Procurement, Construction) contract. It was the first time in the history of the Iranian construction industry that the NIOC entrusted an EPC project to a private sector company.

Kayson’s scope of work involved local and foreign procurement, process, mechanical, electrical, and civil engineering, piping and architectural works, as well as start-up and delivery. Kayson was also responsible for putting in place safety, quality assurance and quality control procedures in accordance with contract requirements.

South Pars Field Development Project, Phases 2 & 3, Site Preparation

Project Outline The South Pars Field is being developed Client: TOTAL South Pars in multi phases, each of which is based on Partner: Bec Freres of France an output level of at least one billion cubic Type of Contract: DB (Design and Build) feet per day of natural gas and 40,000 Contract Period: 8 Months barrels per day of associated condensate. Location: Assaluyeh, Bushehr Province, Iran The sphere of the work performed by the Status: Completed joint venture covered phases two and three and included the actual site of the gas treatment facility, the construction area where the prefabrication workshop for the gas treatment plant will be located, and the camp area comprising office space, sleeping quarters, a clinic, as well as storage and other facilities.

Main Features The TOTAL South Pars Gas Field Development Project (Phases 2 & 3) which encompassed an area of over 2.8 million square meters called for nearly 7 million cubic meters of earthwork, 24 km of earth and concrete-lined culverts and channels. 12 km of fencing, 14.5 km of roads, 91,000 square meters of slope protection, over 5000 square meters of office, living, storage and other facilities- all to be completed within merely 8 months. To get the work done on time, Kayson mobilized as many as 1300 workers laboring 10-hour days and 350 pieces of light and heavy construction equipment operating virtually around the clock.

South Pars, Phases 4 & 5, Site Preparation

Project Outline provide reliable communication links and The South Pars Gas Field Site Preparation information flow throughout the project Client: AGIP Iran Project (Phases 4 & 5) was the second management organization, and deploy Partners: Jahan Pars & Tehran Jonoob project in which Kayson experienced working schedule & cost control procedures to make Companies, Iran with a foreign client in the Iranian port of certain that the project was completed on Type of Contract: DB (Design and Build) Assaluyeh. The only difference was that this time and within budget. Contract Period: 5 Months time the project had to be completed in half Location: Assaluyeh, Bushehr Province, Iran the time- although it involved virtually the In a matter of a few weeks, site mobilization Status: Completed same scope of work, including the same was completed, an HSE unit composed of 22 volume of earthwork as phases 2 & 3. employees assumed responsibility for health & safety and environmental management, the Apart from the time pressure, the most Finance and Administration Department took challenging issue facing the project charge of 1800 workers and employees and management team was to bring the project’s a considerable cash flow per month, the IT implementation process into line with quality & Computer Services Department set up a standards and construction procedures network to handle the storage, retrieval and employed in developed countries. Thus, distribution of information, the documentation Kayson had to put in place an effective section drew up a master plan for total and quality management system, set up an ongoing documentation of construction efficient and well-equipped HSE unit, work activities, the logistics and procurement units out detailed plans for daily, weekly & monthly saw to it that the project’s requirements were progress reporting, make sure the necessary met in a timely and efficient manner. hardware and software were available to

After implementation (after 5 months)

Before implementation General Information Scope of Work Key Statistics The South Pars Gas Field Development ■ Detailed engineering ■ Cutting: 4,086,477 m3 Project (Phases 4 & 5) is designed to ■ Grading of natural soil to form ■ Filling: 1,953,446 m3 produce 50 million cubic meters of natural five horizontal plane levels ■ Roads: 8,249 m gas per year, 8 thousand barrels of ranging from +90m to +38m ■ Fencing: 4,616 m associated condensates per day, 1.05 million ■ Construction of the main roads ■ Drainage network: 14,947 m tonnes of liquefied natural gas per day, and 1 to provide access during million tonnes of ethane per year to be used construction of the refinery Achievements at Peak as feed stock by petrochemical plants. ■ Preliminary drainage system to ■ Cutting: provide surface draining during 56,023 m3/day construction of the refinery ■ Filling & grading: ■ Temporary fencing of the site 44,726 m3/day ■ Total number of equipment at site: 845 Set ■ Total workforce: 1800 people Golgohar Pelletizing Plant

plant, following the construction of an iron ore Scope of Work concentration plant. ■ Geotechnical studies Client: Gol-e-Gohar Industrial & Mining Co. This plant is capable of producing high ■ Site preparation (GEG) quality pellets which are usable in Direct ■ Performing detailed engineering Partner: Farat Tahghigh Sepahan Co. (SBR) Reduction (DR) furnaces. It will also design based on Outotec’s Type of Contract: EPCC (Engineering, manufacture pellets with suitable and desired basic designs (these activities Procurement, Construction, and quality which can be fed directly into blast are carried out by Sepahan Commissioning) furnaces. Beyond Research Company) Contract Period: 39 months ■ Procurement and transportation Location: Sirjan, Kerman Province, Iran Procedures of Pellet Production of equipment, steel structures, Status: Under Construction Golgohar pelletizing unit will be constructed mechanical, piping, electrical & in Sirjan by Gol-e-Gohar Iron ORE Co. with instrumentation (this part is related production capacity of 5 million tonnes per to items which are not Outotec year. Company’s responsibilities) Through a 470 meters long conveyor ■ Execution and installation belt, Golgohar’s concentrated outputs are of all equipment transported to primary storage tanks, each ■ Pre-commissioning and with the capacity of 2000 tonnes. One of the commissioning Project Outline reservoirs is dedicated to hematite ore. As a raw material, Iron ore does not have Key statistics considerable added value by itself. Thus Producing pellet consists of three main ■ Cutting: 31,240 m3 processing and producing of pellet and stages: ■ Filling: 11,200 m3 sponge iron and finally its conversion into ■ Preparing the material that ■ Site preparation: 50,000 m2 steel not only creates job opportunities but includes drying, milling, separating ■ Reinforced Concrete: 30,000 m3 also supplies the producers with a rather small and large particle, storing ■ Reinforcement: 2,517 t higher added value. in storage pits and mixing ■ Formwork: 20,790 m2 Continuous growth of steel production in the ■ Producing raw pellet by means ■ Steel structure: 8,350 t country highlights the ever increasing need of rotary drums pelletizers for establishing pelletizing units. Golgohar ■ Indurating, screening and Mining and Industrial Co. accordingly transporting for maintenance decided to construct a pellet producing or distribution Farashband Gas Refinery Processing Unit Development Plan

Project Outline finally delivered to border area Farashband gas refinery processing unit of EPC2 project in order to be Client: Iranian Central Oil Fields Co. development plan has been broken down injected into an IGAT pipeline. (ICOFC) into two separate EPC projects, comprising ■ The sour gas will also be Consultant: Enerchimi Engineering EPC1’s gas and EPC2’s gas condensates delivered to a 42 inch-dia Company stabilization. Design, procurement and transmission pipeline. Type of Contract: turnkey, lump sum establishment of gas processing facilities are ■ Gas condensates will be delivered Contract Period: 24 months awarded to Kayson Company. The project unprocessed to EPC2 project. Location: Farashband, Fars province, is located in Farashband in Fars Province, Iran 170 km southwest of Shiraz. In Farashband Scope of Work Status: Under Construction gas refinery, natural gas, which is extracted ■ Endorsing basic engineering from Aghar and Dalan fields, is processed. design packages The purpose of Farashband gas refinery ■ Performing detailed engineering development plan, however, is to transport design (these activities are carried the following amounts of natural gas to EPC1 out by Enerchimi Engineering project for processing: Company and Kayson’s ■ 5.1 MMSCMD natural gas engineering management) extracted from wells of ■ Resolving site land conflicts Dey field (through a 14 inch- dia including displacement of pipes, 40 km long pipeline) transmission tower and landscapes ■ 10.2 MMSCMD natural gas from ■ Leveling the territories Sefid-zakhur gas field (through of EPC1 and EPC2 a 20 inch-dia 90 km pipeline) ■ Fencing the whole site ■ 5 MMSCMD additional gases of EPC1 and EPC2 from Aghar and Dalan fields ■ Purchasing equipment and form Farashband gas refinery. bulk items for EPC1 ■ Executing operations such as Along with the conveyance of these gases, civil, mechanical, piping, electrical the condensates, which are recovered in & instrumentation in EPC1 Sefid-zakhur field, are transported to EPC1 ■ Pre-commissioning and project via a 6 inch-dia 90 km transmission commissioning pipeline. Key statistics After the separation of gas and condensates ■ Cutting: 300,000 m3 in EPC1 project, the output flows into four ■ Filling: 110,000 m3 units of Dehydration each with the capacity ■ Concrete: 18,000 m3 of 6.6 MMSCMD. ■ Equipment weight The final products of EPC1 project feed (70 pieces): 1,600 t EPC2 project and will be delivered to the ■ Steel structure: 700 t contractor on border area of EPC2 project: ■ Piping: 130,000 inch-dia ■ The sweet gas which flows into ■ Cabling: 65,000 m two Dew-pointing units (each with ■ Displacing 8 inch-dia the capacity of 6.6 MMSCMD) is pipelines: 1,700 m 4th Aromatics Plant, Process Area

Headquarter: No.18, 2nd St. (Abghari), Sa’adat Abad Ave., Tehran 1998618871, Iran Tel: (+9821) 24801000, 22131032 Fax: (+9821) 22134992 www.kayson-ir.com