Contra Costa Transportation Authority 2016 Express Bus Study Update Final Report
Total Page:16
File Type:pdf, Size:1020Kb
Load more
Recommended publications
-
THIS STAFF REPORT COVERS CALENDAR ITEM NO.: 8 for the MEETING OF: April 19, 2007 TRANSBAY JOINT POWERS AUTHORITY BRIEF DESCRIPT
THIS STAFF REPORT COVERS CALENDAR ITEM NO.: 8 FOR THE MEETING OF: April 19, 2007 TRANSBAY JOINT POWERS AUTHORITY BRIEF DESCRIPTION: This staff report provides the status of a planning feasibility study for a future pedestrian connection tunnel between the Transbay Transit Center and the BART/MUNI Metro stations on Market Street. SUMMARY: The TJPA is conducting a study of the feasibility and estimated construction cost for a new pedestrian connection tunnel along one of the following four alternative alignments. • Beale Street (Alternative 1) • Fremont Street (Alternative 2) • First Street (Alternative 3) • Ecker Place (Alternative 4) Estimated construction costs vary for each alignment, with the Beale Street and Ecker Place alignments expected to cost less than the Fremont Street or First Street alignments due to the shorter total length of the tunnel structures. There is currently no funding identified for inclusion of the pedestrian connection tunnel in Phase 1 of the Transbay Transit Center Program. Consequently, it remains a “design option” that would be implemented during the Caltrain Downtown Extension project in Phase 2 of the Transbay Transit Center Program, as originally envisioned in the Final Environmental Impact Statement/ Environmental Impact Report (FEIS/EIR). If adequate funding is secured, construction of the pedestrian connection tunnel appears technically feasible along any of the four alignments studied. A study report with input from City and regional stakeholders is planned for consideration by the TJPA Board at its May 2007 meeting. REPORT: FEIS/EIR Consideration of a Pedestrian Connection Tunnel The Locally Preferred Alternative (LPA) that was adopted during the preparation of the FEIS/EIR included a “design option” for a pedestrian connection tunnel below Fremont Street between the train mezzanine level of the new Transit Center and the mezzanine level of the existing BART/MUNI Metro Embarcadero Station, as part of the Caltrain Downtown Extension Project. -
Glenn Transit Service Short Range Transit Plan
Glenn Transit Service Short Range Transit Plan Final Report Prepared for Glenn Transit Service Prepared by LSC Transportation Consultants, Inc. TABLE OF CONTENTS Chapter Page 1 Introduction and Key Study Issues ............................................................................. 1 Introduction ........................................................................................................ 1 Study Issues ........................................................................................................ 1 2 Study Area Characteristics ......................................................................................... 3 Review of Previous Studies and Projects ...............................................................18 3 Review of Existing Transit Services ............................................................................21 Glenn Transit Services .........................................................................................21 Other Transit Providers .......................................................................................32 4 Public Outreach ........................................................................................................39 Introduction .......................................................................................................39 Stakeholder Interviews ........................................................................................39 Information Booths .............................................................................................41 -
West Contra Costa County High Capacity Transit
El Cerrito February 28, 2017 Hercules El Cerrito City Councilmembers El Sobrante Municipal Advisory Councilmembers Hercules City Councilmembers Pinole City Councilmembers Pinole Richmond City Councilmembers San Pablo City Councilmembers Richmond RE: West County High Capacity Transit Study Update and Presentation Dear Councimembers: Thank you for the opportunity to share with you West Contra Costa Transportation Advisory San Pablo Committee’s progress on its West County High Capacity Transit Study. The study is nearing completion and we are seeking stakeholder and public opinion on the initial draft findings from the study. Your staff have invited us to give presentations to your Councils on the West County High Capacity Transit Study’s highlights and gather community feedback. Contra Costa County BACKGROUND AND DISCUSSION In the spring of 2015, WCCTAC launched its West County High Capacity Transit Study. A team of transportation consultants working with the WCCTAC Board and its Technical Advisory Committee and staff developed study goals and objectives and evaluated existing and future AC Transit transportation networks, land uses, and travel markets. The study’s consultants analyzed this information then developed an initial set of alternatives that then underwent a technical evaluation that considered travel time improvements, access to regional transit centers, transit market potential, service to low-income areas and markets lacking major transit connections, etc. BART Throughout this study process, community outreach efforts have been on-going. A study- dedicated website (www.WestCountyTransitStudy.com) provides the public with opportunities to check on the study’s status and review presentations and technical memos. In November 2015, WCCTAC and the Contra Costa Transportation Authority (CCTA) held a joint telephone town hall, which attracted 2,045 total attendees, with 700 callers at its peak and an average of 150 WestCAT 6333 Potrero Avenue, Suite 100, El Cerrito CA 94530 Phone: 510.210.5930 ~ www.wcctac.org attendees over sixty minutes. -
The Third Crossing
The Third Crossing A Megaproject in a Megaregion www.thirdcrossing.org Final Report, February 2017 Transportation Planning Studio Department of City and Regional Planning, University of California, Berkeley Acknowledgements The authors would like to acknowledge the Department of City and Regional Planning (DCRP) at the College of Environmental Design (CED) at UC Berkeley, the University of California Transportation Center and Institute of Transportation Studies (ITS), UC Berkeley for support. A special thanks also goes to the helpful feedback from studio instructor Karen Trapenberg Frick and UC Berkeley faculty and researchers including Jesus Barajas and Jason Corburn. We also acknowledge the tremendous support and insights from colleagues at numerous public agencies and non-profit organizations throughout California. A very special thanks goes to David Ory, Michael Reilly, and Fletcher Foti of MTC for their gracious support in running regional travel and land use models, and to Professor Paul Waddell and Sam Blanchard of UrbanSim, Inc. for lending their resources and expertise in land use modeling. We also thank our classmates Joseph Poirier and Lee Reis; as well as David Eifler, Teresa Caldeira, Jennifer Wolch, Robert Cervero, Elizabeth Deakin, Malla Hadley, Leslie Huang and other colleagues at CED; and, Alexandre Bayen, Laura Melendy and Jeanne Marie Acceturo of ITS Berkeley. About Us We are a team of 15 graduate students in City Planning, Transportation Engineering, and Public Health. This project aims to facilitate a conversation about the future of transportation between the East Bay and San Francisco and in the larger Northern California megaregion. We are part of the Department of City and Regional Planning in the UC Berkeley College of Environmental Design, with support from the University of California Transportation Center and The Institute of Transportation Studies at the University of California, Berkeley. -
Vii. Report Preparation
VII. REPORT PREPARATION A. REPORT PREPARATION LSA Associates, Inc. Report Production and Management; Project Description; Land Use, Population and Housing; Agriculture; Air Quality; Noise; Global Climate Change; Public Services; Utilities and Energy; Visual and Scenic Resources; Alternatives; and Other CEQA Considerations. 2215 Fifth Street Berkeley, CA 94710 Judith H. Malamut, AICP, Principal-in-Charge and Project Manager Hannah Young, AICP, Planner Amy Fischer, Senior Planner (Air Quality and Noise) Phil Ault, Analyst (Air Quality and Noise) Jason Paukovits, Air Quality Specialist (Global Climate Change) Fred Bauermeister, Planner Lauren Haring, Assistant Planner Jennifer Morris, Word Processing and Production Patty Linder, Graphics and Production LSA Associates, Inc. Historic and Cultural Resources; and Biological Resources. 157 Park Place Point Richmond, CA 94801 Christian Gerike, Principal (Cultural Resources) Steve Foreman, Principal (Biological Resources) E. Timothy Jones, Cultural Resources Manager Tim Lacy, Biological Resources Manager Andrew Pulcheon, Associate (Cultural Resources) Greg Gallaugher, Associate (GIS Specialist) LSA Associates Inc. Air Quality and Noise 20 Executive Park, #200 Irvine, CA 92614 Tony Chung, Principal (Air Quality and Noise) Ronald Brugger, Air Quality Specialist Baseline Environmental Consulting. Hydrology and Water Quality; Geology, Soils, Seismicity, and Mineral Resources; and Hazards and Hazardous Materials. 5900 Hollis Street, Suite D Emeryville, CA 94608 Yané Nordhav, Principal Bruce Abelli-Amen, Hydrologist (Geology/Soils, Hydrology/Water Quality) Cheri Page, Senior Geologist (Hazards) Ralph Russell, Environmental Specialist (Geology/Soils, Hydrology/Water Quality) P:\CYK0701 Yolo GP EIR\PRODUCTS\DEIR\Public\7-RprtPrep.doc (4/27/2009) PUBLIC REVIEW DRAFT 819 LSA ASSOCIATES, INC. YOLO COUNTY 2030 COUNTYWIDE GENERAL PLAN EIR APRIL 2009 VII.REPORT PREPARATION Estep Environmental Consulting. -
SAMTRANS CORRESPONDENCE As of 12-11-2020
SAMTRANS CORRESPONDENCE as of 12-11-2020 December 8, 2020 The Honorable Gavin Newsom Governor, State of California State Capitol, Suite 1173 Sacramento, CA 95814 Dear Governor Newsom: Bay Area transit systems continue to struggle in the face of dramatically reduced ridership and revenues due to the COVID-19 pandemic. This challenge was already the most significant crisis in the history of public transportation, and now it has persisted far longer than any of us would have predicted. Since the beginning, our workers have been on the front lines, doing their jobs as essential workers, responsible for providing other front line workers with a way to safely travel to and from essential jobs. Now that the availability of a vaccine is on the horizon, we are proud to echo the attached call from the Amalgamated Transit Union (ATU). Specifically, we urge you to work to ensure that transit, paratransit, and school transportation workers are prioritized along with other essential workers to receive the vaccine following the critical need to vaccinate the State’s healthcare workers. Even with reduced ridership, an average of 8 million monthly riders continue to depend on Bay Area transit services. These riders are the healthcare workers, grocery clerks, caregivers, emergency services personnel and others doing the critical work that has kept California functioning during the pandemic. They cannot continue to do so without access to reliable public transportation, and are therefore dependent on the health of the transit workers that serve them every day. Our agencies have worked hard to ensure the public health of riders and transit workers during this crisis. -
Transbay Temporary Terminal : Project Fact Sheet
Transbay Temporary Terminal PROJECT FACT SHEET Temporary Terminal The Transbay Joint Powers Authority (TJPA) continues to make exciting progress toward building the Transbay Transit Center, the “Grand Central of the West.” Groundbreak- ing commenced in December 2008 for the Temporary Terminal that will serve bus pas- sengers while the new Transit Center is un der construction. ➤ SPEAR STREET ➤ ➤ ➤ ➤ HOWARD STREET MAIN STREET ➤ Temporary Temporary Terminal Rendering + Terminal Site ➤ BEALE STREET ➤ ➤ Sign-up for Notices ➤ The TJPA is committed to mitigating traffic impacts during ➤ FOLSOM STREET the course of construction. However, traffic disruptions are FREMONT STREET expected throughout the course of the project. ➤ In order to stay informed on our progress, upcoming community meetings and potential street closures, please ➤ ➤ sign up to receive email alerts and to join our project mailing list at www.temporaryterminal.org Map of Project Area + PROJECT TIMELINE December 2008 Summer 2010 Fall 2010 Late Fall 2010 2012 2017 2018 Temporary Terminal Temporary Terminal construction completed. Demolition SamTrans Construction Construction Construction Groundbreaking. of East Loop and Golden of the of the of the Caltrain Greyhound, AC Transit, MUNI and WestCAT (Phase II of Gate Transit Caltrain Transbay Downtown Lynx operations move to the Temporary Temporary move to the Downtown Transit Rail Extension Terminal. Terminal) Temporary Rail Center to be to be Begin demolition of Transbay Terminal; completed. Terminal. Extension to completed. completed. construction of new Transit Center begins. begin. Temporary Terminal to close. For more information, please visit: www.temporaryterminal.org 06.10 PROJECT FACT SHEET Frequently Asked Questions Transbay Transit Center Rendering + WHAT IS THE TEMPORARY TERMINAL? The Temporary Terminal is the temporary replacement bus facility that will serve bus passengers while the new, multi-modal Transbay Transit Center is under construction. -
West Contra Costa/Albany Transit Wayfinding Plan
FINAL WEST CONTRA COSTA TRANSIT ENHANCEMENT STRATEGIC PLAN and WEST CONTRA COSTA/ALBANY TRANSIT WAYFINDING PLAN Prepared for: West Contra Costa Transportation Advisory Committee October 2011 Acknowledgements WCCTAC BOARD City of El Cerrito Janet Abelson, Vice Chair City of Hercules Donald Kuehne City of Pinole Roy Swearingen, Chair City of Richmond Courtland “Corky” Boozé City of Richmond Thomas Butt City of Richmond Jeff Ritterman City of San Pablo Genoveva Calloway AC Transit Joe Wallace BART Joel Keller WestCAT Tom Hansen Contra Costa County John Gioia WCCTAC STAFF Christina Atienza, Executive Director Linda Young John Rudolph Joanna Pollock WCCTAC WORKING GROUP City of El Cerrito Yvetteh Ortiz City of Hercules Robert Reber City of Pinole Winston Rhodes City of Richmond Chad Smalley, Hector Rojas, Steven Tam City of San Pablo Kanwal Sandhu, Adele Ho AC Transit Nathan Landau, Puja Sarna, Aaron Priven BART Diedre Heitman WestCAT Rob Thompson Contra Costa County Jamar Stamps MTC Jay Stagi CONSULTANT TEAM Fehr & Peers Nelson/Nygaard Bob Grandy (Project Manager) Linda Rhine Brooke DuBose (Deputy PM) Joey Goldman Matthew Ridgway Meghan Mitman Studio L’Image Ellen Poling Sue Labouvie Josh Peterman Max Heim Steve Rhyne Carrie Carsell Eisen Letunic Nikki Hervol Niko Letunic Nikki Foletta table of contents I Introduction II Study Locations III Community Participation IV Travel Demand Management & Parking Strategies V Richmond BART Transit Center Enhancement Strategies VI Richmond Parkway Transit Center Enhancement Strategies VII El Cerrito Del -
AQ Conformity Amended PBA 2040 Supplemental Report Mar.2018
TRANSPORTATION-AIR QUALITY CONFORMITY ANALYSIS FINAL SUPPLEMENTAL REPORT Metropolitan Transportation Commission Association of Bay Area Governments MARCH 2018 Metropolitan Transportation Commission Jake Mackenzie, Chair Dorene M. Giacopini Julie Pierce Sonoma County and Cities U.S. Department of Transportation Association of Bay Area Governments Scott Haggerty, Vice Chair Federal D. Glover Alameda County Contra Costa County Bijan Sartipi California State Alicia C. Aguirre Anne W. Halsted Transportation Agency Cities of San Mateo County San Francisco Bay Conservation and Development Commission Libby Schaaf Tom Azumbrado Oakland Mayor’s Appointee U.S. Department of Housing Nick Josefowitz and Urban Development San Francisco Mayor’s Appointee Warren Slocum San Mateo County Jeannie Bruins Jane Kim Cities of Santa Clara County City and County of San Francisco James P. Spering Solano County and Cities Damon Connolly Sam Liccardo Marin County and Cities San Jose Mayor’s Appointee Amy R. Worth Cities of Contra Costa County Dave Cortese Alfredo Pedroza Santa Clara County Napa County and Cities Carol Dutra-Vernaci Cities of Alameda County Association of Bay Area Governments Supervisor David Rabbit Supervisor David Cortese Councilmember Pradeep Gupta ABAG President Santa Clara City of South San Francisco / County of Sonoma San Mateo Supervisor Erin Hannigan Mayor Greg Scharff Solano Mayor Liz Gibbons ABAG Vice President City of Campbell / Santa Clara City of Palo Alto Representatives From Mayor Len Augustine Cities in Each County City of Vacaville -
Transit Information El Cerrito Del Norte Station El Cerrito
Transit Stops Paradas del tránsito 公車站地圖 On Key Blvd at Cutting Blvd: Transit On Cutting Blvd: Information JL•JR•JPX 7 El Cerrito del 72•72M•72R Oakland Norte Station 76 OHLONE GREENWAY 376 El Cerrito 684 800 San Francisco Map Key You Are Here ONLYBUS 3-Minute Walk CUTTING BLVD 500ft/150m Radius Bus Transit Stop BART Parking 29 BART Police Bike Lockers Bike Parking Green Express Line Inside Station: Elevator Escalator All BART Trains Passenger Pick-up/Drop-off L San Francisco Restrooms Stairs Red Line•82 Station Agent Booth Station Entrance/Exit Taxi Stand Telephone 72 Hilltop Mall Ticket Vending: 72R Contra Costa College Clipper/BART Tickets 72M Point Richmond Addfare 800 Richmond BART Paratransit Transit Information L Drop-Off Only Transit Lines Construction AC Transit SAN PABLO AVE Local Bus Lines 7 Downtown Berkeley CDPH Shuttle 72 Hilltop Mall A r e a 72 Jack London Square 72M Point Richmond 72M Jack London Square 72R Contra Costa College 72R Jack London Square 76 Hilltop Mall 376 Pinole Nights 40 All Nighter Bus Lines (Approx. 1 am–5 am) 800 San Francisco (Market St & Van Ness Ave) 800 Richmond BART Transbay Bus Line 704 L San Francisco Early Bird Express 704 San Francisco Temporary Transbay Terminal Golden Gate Transit 40 San Rafael Transit Center ONLYBUS SolanoExpress 82 Sereno Transit Center Green Express Fair eld / Suisun City Red Line Vallejo / Fair eld / Suisun City N Vine Transit 29 Napa WestCAT W E JL Hilltop Mall / Pinole / Hercules Transit Center JR Pinole / Hercules Transit Center JPX Pinole / Hercules Transit Center Note: Service may vary with time of day or day S of week. -
AC Transit) for Easypass Program 2021 to 2025
Page 1 of 5 Office of the City Manager CONSENT CALENDAR December 15, 2020 To: Honorable Mayor and Members of the City Council From: Dee Williams-Ridley, City Manager Submitted by: Liam Garland, Director, Department of Public Works Subject: Contract: Alameda-Contra Costa County Transit District (AC Transit) for EasyPass Program 2021 to 2025 RECOMMENDATION Adopt a Resolution authorizing the City Manager to execute a contract and any amendments with Alameda-Contra Costa County Transit District (AC Transit) for the EasyPass bus transit pass program for City of Berkeley employees in an amount not to exceed $774,453 for the five-year period commencing January 1, 2021 through December 31, 2025. FISCAL IMPACTS OF RECOMMENDATION Total projected five-year cost of the EasyPass program is $774,453. Funds for calendar year 2021 are available in the Payroll Deduction Trust Fund (Fund 013), and future fiscal years funding is subject to appropriation in those annual budgets. Based upon the current estimated minimum pool of 1,402 passes (one pass per employee), the City will remit payment to AC Transit over the life of the contract as projected here: Contract Period Minimum Annual Cost Total Annual Employee Pool Per Pass Contract Costs1 1/1/2021 - 12/31/2021 1,402 $106.15 $148,826 1/1/2021 - 12/31/2022 1,402 $106.15 $148,826 1/1/2022 - 12/31/2023 1,402 $110.48 $154,891 1/1/2023 - 12/31/2024 1,402 $114.80 $160,955 1/1/2024 - 12/31/2025 1,402 $114.80 $160,955 Total $774,453 1 Calculation of total annual contract costs is based upon AC Transit’s level of service score allocated to every COB worksite (approximately 30 as of October 2020), combined into a weighted average that is then multiplied by minimum pool of participants. -
San Mateo County Paratransit Rider's Guide
HOW TO USE REDI-WHEELS AND REDICOAST San Mateo County Paratransit Rider’s Guide OCTOBER 2019 EDITION HOW TO USE REDI-WHEELS AND REDICOAST San Mateo County Paratransit Rider’s Guide To request a copy of this guide in an accessible format, please call 1-800-660-4287 This information is also available at www.samtrans.com/Accessibility ABOUT REDI-WHEELS AND REDICOAST ADA Paratransit is for persons with disabilities who cannot independently use regular bus service some of the time or all of the time. The San Mateo County Transit District (SamTrans) provides ADA paratransit service using Redi-Wheels on the Bayside of the county and RediCoast on the Coastside. Trips must be scheduled at least one day in advance. The purpose of this guide is to enable San Mateo County paratransit riders, their families, and advocates to become familiar with the paratransit services offered by Redi-Wheels and RediCoast and to help ensure that our customers enjoy the best riding experience we can provide. The information contained in this guide is divided into sections by topic, and is listed in a table of contents beginning on the following page. Please note that Redi-Wheels and RediCoast policies are subject to change without notice. Experienced customers should review this guide carefully, as some sections and policies have changed. All SamTrans buses are accessible, and many persons with disabilities are able to use the regular fixed-route bus service. However, if you are unable to use accessible fixed-route transit for some or all of your trips, you may be eligible for paratransit.