1.0 GENERAL INFORMATION

1.1 Introduction

M/s. BSCPL infrastructure limited proposes to construct a residential building in Perumbakkam and Arasankalani Village, Taluk, , spread over a plot area of approximately 109110 Sqm. The total built-up area of the proposal is 321137.9 Sqm. The proposed project falls under 8(b) category as per MoEF, EIA Notification, and 14th September 2006. Hence it is required to submit Terms of Reference (ToR) as per State Level Environmental Impact Assessment Authority (SEIAA), . In order to obtain the Environmental Clearance for the proposed residential building from the SEIAA, Chennai, BSCPL has engaged the services of us to conduct Rapid Environmental Impact Assessment (REIA) study and to prepare the Environmental Management Plan (EMP) for the proposed project.

1.2 Contact details of the Project Proponent

Name & Contact Address: Mr. J. Karthygayan M/s. BSCPL Infrastructure limited Bollineni Hillside, Arasankalani – Perumbakkam Road, Sithlapakkam post Chennai – 600126. E – Mail: [email protected]

1.3 Land Description

The area of the plot is 109110 sqm. It is a vacant land and is converted for residential development. As per CMDA Master Plan, the proposed site is classified under primary residential and urbanisable Use. Site is having flat terrain and soil quality of the land is fertile in nature. It has the capacity to absorb rainfall. The project site is located at 12°52'42.32"N latitude and 80°12'12.84"E longitude. The site is well connected by SH 49A (East) and main road (West). The site is situated in Perumbakkam and Arasankalani Village, in Kanchipuram district. The environmental settings of the site are given below: Table 1: Details of Environmental Setting

S. No. Particulars Details 1. Latitude 12°52'42.32"N 2. Longitude 80°12'12.84"E 3. Total Plot Area 109110 sqm SH 49A – Rajiv Gandhi IT express way/OMR 4. Nearest Highway (East – 2.5 km) 5. Nearest Railway Station Station ( 10 Km, North ) 6. Nearest Airport Chennai International airport (13 km, NW) 7. Nearest Harbor (25 km, NE)

1.4 Project Survey nos.

S. No. 443/2, 444/1, 444/2 of Perumbakkam village & 92 to 98, 100 to 102, 103/1A2, 116/1B, 117/2A1, 117/2A2, 117/2B, 118/2B12, 118/2B13, 131/23, 131/4 of Arasankalani village, St. Thomas mount Panchayat union, Sholinganallur taluk, Kanchipuram dt.

Land use map and Land ownership documents are enclosed in Annexure – IV.

1.5 Local Regulation applicable for township and Area development

We are following the regulations of Chennai Metropolitan Development Authority (CMDA) as per Second Master Plan of Chennai Metropolitan Area 2026 -Volume II Development Regulations.

1.6 Litigation(s) pending against the proposed project and /or any directions or orders passed by any court of law/any statutory authority against the project is to be detailed out

No litigations against the project.

2.0 PROJECT DESCRIPTION

M/s. BSCPL infrastructure limited proposes to construct residential apartments in Perumbakkam and Arasankalani Village, Sholinganallur taluk in Kanchipuram district in the state of . Total Plot area is 109110 sqm. The total built-up area of the proposal is 321137.9Sqm.

Salient Features of the project:

Particulars Details Project Name Bollineni Zion Location Perumbakkam and Arasankalani Village, Sholinganallur taluk in Kanchipuram district Type of project Construction of residential Apartment Total Plot Area 109110 Sqm Total Built up area 321137.9 Sqm OSR 10175.12 Sqm Ground coverage 21004.29 Sqm Road & pavements 29441.84 Sqm Green Belt 44540.99 Sqm Surface parking area 700 Sqm STP, Solid Waste Disposal and Other 3247.76 Sqm Utilities Area Number of Two basement + 17 blocks with a club House Blocks/floors and a school Building Height 54 m Road Approach road – Bollineni Hill side Road (18.3 m / 60 feet wide) Nearest Railway Station Velachery Station ( 10 Km, North ) Nearest Airport Chennai International airport (13 km, NW) Nearest Harbor Chennai Port (25 km, NE) Nearest Town Perumbakkam (2.5km, N) Parking facilities Cars – 22 60 Two wheelers - 2640 Power requirement 10410 kva Source of power TNEB Power backup 500 kva x 4 nos , 250 kva x 5 nos, 1x 160 kva Water requirement Total water requirement : 2037 Fresh water: 1207 Water Source Ground water Estimated 15956 persons population Project cost 500 crores

2.2 Man power requirement :

Local labors from nearby areas will be deployed for the project work and there is no labor camp proposed. Nearly 400 - 500 skilled and unskilled laborers will be employed during peak construction period.

2.3 Land Use Area Break up:

Table 2: Land use Break up S. Area in Land Use Type No. Sqm 1. Total Plot Area 109110 Tota l Ground Coverage Area of Buildings 2. 21004.29 (19.25%) 3. Roads and Pavements Area (26.98%) 29441.84 4. Surface or open Parking Area (6.4%) 700 Transformer yard, STP, Solid Waste Disposal & 5. 3247.76 Other Utilities Area (2.97%) 6. Greenbelt development Area (40.82%) 44540.99 7. OSR Area (10%) 10175.12

Built-up Area Breakup:

TOWER A:

Total Built FSI Non FSI Parking Floor up area (Sqm) (Sqm) (Sqm) (Sqm) Ground Floor 687.63 111.6 - 799.23

1st to 9 th Floor 6709.35 556.8 - 7266.15 10 th Floor 638. 93 56.36 - 695.29 11 th Floor 405.54 44.95 - 450.49

12 th Floor 274.46 38.98 - 313.44

13 th & 14 th Floor 316.4 66.18 - 382.58

Total 9032.31 874.87 9907.18

Tower B

Total Built FSI Non FSI Parking Floor up area (Sqm) (Sqm) (Sqm) (Sqm) Ground Floor 776.26 102.82 - 879.08 1st to 18 th Floor 14749.92 1160.64 - 15910.56

Total 15526.18 1263.46 16789.64

Tower C

Total Built FSI Non FSI Parking Floor up area (Sqm) (Sqm) (Sqm) (Sqm) Ground Floor 776.26 102.82 - 879.08

1st to 18 th Floor 14749.92 1160.64 - 15910.56

Total 15526.18 1263.46 16789.64

Tower D

Total Built FSI Non FSI Parking Floor up area (Sqm) (Sqm) (Sqm) (Sqm) Ground Floor 687.63 111.6 - 799.23

1st to 9 th Floor 6709.35 556.8 - 7266.15

10 th Floor 638.93 56.36 - 695.29

11 th Floor 405.54 44.95 - 450.49

12 th Floor 274.46 38.98 - 313.44 13 th & 14 th Floor 316.4 66.18 - 382.58

Total 9032.31 874.87 9907.18

Tower E

Total Built FSI Non FSI Parking Floor up area (Sqm) (Sqm) (Sqm) (Sqm) Ground Floor 687.63 111.6 - 799.23

1st to 9 th Floor 6709.35 556.8 - 7266.15

10 th Floor 638.93 56.36 - 695.29

11 th Floor 405.54 44.95 - 450.49

12 th Floor 274.46 38.98 - 313.44 13 th & 14 th Floor 316.4 66.18 - 382.58

Total 9032.31 874.87 9907.18

Tower F

Total Built FSI Non FSI Parking Floor up area (Sqm) (Sqm) (Sqm) (Sqm) Ground Floor 776.26 102.82 - 879.08

1st to 18 th Floor 14749.92 1160.64 - 15910.56

Total 15526.18 1263.46 16789.64

Tower G Total Built FSI Non FSI Parking Floor up area (Sqm) (Sqm) (Sqm) (Sqm) Ground Floor 776.26 102.82 - 879.08

1st to 18 th Floor 14749.92 1160.64 - 15910.56

Total 15526.18 1263.46 16789.64

Tower H Total Built FSI Non FSI Parking Floor up area (Sqm) (Sqm) (Sqm) (Sqm) Ground Floor 687.63 111.6 - 799.23

1st to 18 th Floor 13418.71 1113.6 - 14532.31

Total 14106.34 1225.2 15331.54

Tower J Total Built FSI Non FSI Parking Floor up area (Sqm) (Sqm) (Sqm) (Sqm) Ground Floor 776.26 102.82 - 879.08

1st to 18 th Floor 14749.92 1160.64 - 15910.56

Total 15526.18 1263.46 16789.64

Tower K

Total Built FSI Non FSI Parking Floor up area (Sqm) (Sqm) (Sqm) (Sqm) Ground Floor 776.26 102.82 - 879.08

1st to 18 th Floor 14749.92 1160.64 - 15910.56

Total 15526.18 1263.46 16789.64

Tower L Total Built FSI Non FSI Parking Floor up area (Sqm) (Sqm) (Sqm) (Sqm) Ground Floor 687.63 111.6 - 799.23

1st to 18 th Floor 13418.71 1113.6 - 14532.31

Total 14106.34 1225.2 15331.54

Tower M

Total Built FSI Non FSI Parking Floor up area (Sqm) (Sqm) (Sqm) (Sqm) Ground Floor 776.26 102.82 - 879.08

1st to 18 th Floor 14749.92 1160.64 - 15910.56

Total 15526.18 1263.46 16789.64

Tower N

Total Built FSI Non FSI Parking Floor up area (Sqm) (Sqm) (Sqm) (Sqm) Ground Floor 776.26 102.82 - 879.08

1st to 18 th Floor 14749.92 1160.64 - 15910.56

Total 15526.18 1263.46 16789.64

Tower P Total Built FSI Non FSI Parking Floor up area (Sqm) (Sqm) (Sqm) (Sqm) Ground Floor 776.26 102.82 - 879.08

1st to 18 th Floor 14749.92 1160.64 - 15910.56

Total 15526.18 1263.46 16789.64

Tower R Total Built FSI Non FSI Parking Floor up area (Sqm) (Sqm) (Sqm) (Sqm) Ground Floor 687.63 111.6 - 799.23

1st to 9 th Floor 6709.35 556.8 - 7266.15

10 th Floor 638.93 56.36 - 695.29

11 th Floor 405.54 44.95 - 450.49

12 th Floor 274.46 38.98 - 313.44

13 th & 14 th Floor 316.4 66.18 - 382.58

Total 9032.31 874.87 9907.18

Tower S Total Built FSI Non FSI Parking Floor up area (Sqm) (Sqm) (Sqm) (Sqm) Ground Floor 1264.03 91.7 - 1355.73

1st to 18 th Floor 22752.5 1650.64 - 24403.14

Total 24016.53 1742.34 25758.87

Tower T Total Built FSI Non FSI Parking Floor up area (Sqm) (Sqm) (Sqm) (Sqm) Stilt Floor 0 143.15 1473 1616.15

1st to 18 th Floor 28314.72 1101.92 - 31840.74

Total 28314.72 1245.07 1473 31032.79

Clubhouse Total Built FSI Non FSI Parking Floor up area (Sqm) (Sqm) (Sqm) (Sqm) Ground Floor 3072.53 163 - 3235.53

Total 3072.53 163 3235.53

School Total Built FSI Non FSI Parking Floor up area (Sqm) (Sqm) (Sqm) (Sqm) Ground Floor 2097.3 48.63 - 2145.93

1st Floor 2097.3 48.63 - 2145.93

2nd Floor 1993 48.63 - 2041.63

3rd Floor 1993 48.63 2041.63

Total 8180.6 194.52 0 8375.12 Total built-up area Total built -up FSI Area Non FSI Area Parking Area Description area (Sqm) (Sqm) (Sqm) (Sqm)

Upper Basement 15580.5 15580.50

Lower Basement 16001.50 16001.50

Tower : A 9032.31 874.87 - 9907.18

Tower : B 15526.18 1263.46 - 16789.64

Tower : C 15526.18 1263.46 - 16789.64

Tower : D 9032.31 874.87 - 9907.18

Tower : E 9032.31 874.87 - 9907.18

Tower : F 15526.18 1263.46 - 16789.64

Tower : G 15526.18 1263.46 - 16789.64

Tower : H 14106.34 1225.2 - 15331.54

Tower : J 15526.18 1263.46 - 16789.64

Tower : K 15526.18 1263.46 - 16789.64

Tower : L 14106.34 1225.2 - 15331.54

Tower : M 15526.18 1263.46 - 16789.64

Tower : N 15526.18 1263.46 - 16789.64

Tower : P 15526.18 1263.46 - 16789.64

Tower : R 9032.31 874.87 - 9907.18

Tower : S 24016.53 1742.34 - 25758.87

Tower : T 28314.72 1245.07 1473 31032.79

Clubhouse 3072.53 163 - 3235.53 School 7947.58 182.56 - 8130.14

Total 267428.9 20653.99 33055 321137.9

2.4 Occupancy Details The occupancy details are given below .

Area Details/ Occupancy S.No Project Components Apartments load 1. Residential Units 2552 5 persons per unit 12760 Visitors, Workers & 10% of the residential 2. - 1276 Maintenance staff population 3. School - 1920

Total Occupancy 15956

2.5 Source of Water and Consumption

During Construction Phase: Total water requirement estimated during the construction phase will be 80 - 100 KLD, which will be sourced through tanker supply.

During Operation Phase: Total water requirement estimated during the operation phase will be 2031KLD of which daily fresh water requirement for domestic use will be 1207 KLD. Source of fresh water supply is

Flushing water requirement = 641 KLD (STP treated water) Gardening water requirement = 156 KLD (STP treated water) Local body = 742 KLD (STP treated water)

Water Requirement

The total water requirement during operation is 2031 KLD. The wastewater generation from the project is estimated to be about 1621 KLD. During operational phase the sewage generated will be treated in the proposed STP of 1650 KLD. The treated water will be recycled for flushing, gardening and local body for avenue plantation and public parks. The estimation of water requirement and the water balance chart is shown in table below:

Water Requirement Calculation

Recycled Total Water Domestic water Project Occupancy water Requirement Requirement Components load Requirement (lpd) (lpd) (lpd) 1722600 1148400 574200 Residential units 12760 (135 lpcd) (90 lpcd) (45 lpcd) Visitors Workers & 57420 19140 38280 1276 Maintenance staff (45 lpcd) (15 lpcd) (30 lpcd) 86400 57600 28800 School 1920 (45 lpcd) (30 lpcd) (15 lpcd) Total 1866420 1225140 641280 Water requirement for Gardening purposes based on the 155893.46 155893.46 Gardening area (44540.99Sqm (@ 3.5 litres/Sqm) Swimming pool Top up 9000 9000 Total 2031313 1234140 797173.5

Summary of water Requirement:

Total Water Requirement = 2031 KLD Fresh water requirement for domestic purposes = 1225 KLD Treated water requirement for Flushing purposes = 641 KLD Treated water requirement for Gardening purposes = 156 KLD Swimming pool Top up = 9 KLD

WATER BALANCE

Daily Fresh Water Requirement

(1234 KLD)

Domestic 980 KLD 1621 KLD STP 1225 KLD (80%) 1660 KLD

1539KLD Swimming Pool Top Up 641 KLD 9 KLD Flushing 641 KLD (641 KLD )

Gardening 156KLD 156 KLD

Local body 742 KLD 742 KLD

2.6 Power Requirement

The estimated power requirement during operation phase is about 10410 KVA and it will be sourced from the nearby TNEB grid which will be distributed through the transformers within project premises. For emergency purposes, it is proposed to use DG sets of following capacities:

 4 x 500 KVA, 5 X 250 KVA, 1X 160 KVA Capacities.

2.7 Solid Waste Generation

Solid waste would be generated both during the construction as well as during the operation phase. The solid waste expected to be generated during the construction phase will comprise of excavated materials, used bags, bricks, concrete, MS rods, tiles, wood etc. The following steps are proposed to be followed for the management of solid waste:

• Construction yards are proposed for storage of construction materials. • The excavated material such as topsoil and stones will be stacked for reuse during later stages of construction • Excavated top soil will be stored in temporary constructed soil bank and will be reused for landscaping of the proposed Residential plotted colony project. • Remaining soil shall be utilized for refilling / road work / rising of site level at locations.

Construction Waste

Construction Empty cement Waste, Broken bags, containers Excavated Soil bricks, waste etc., plaster

Topsoil conserved

Used in re- filing, Sold to agency for for landscaping,

raising site level recycling balance used in re- filling

Table 10: Typical Solid Waste Sources and Quantity of Generation during Construction

S. No. Sources of waste Type of waste Quantity Sand, concrete, gravel, stone, Generat ion at the rate 1 Non-Biodegradable bricks, plastic, metal and glass 40-50 kg/Sqm of 2 Paper and wood Biodegradable construction area

Operation Phase:

Municipal Solid waste:

As the proposed project is Residential building, the solid waste envisaged during its operation phase includes waste papers, kitchen waste, plastic wastes etc.,. As per the manual on municipal solid waste prescribed by Central Public Health and Environmental Organization (CPHEEO), the quantity of solid waste generated varies between 0.2 to 0.6 kg/ capita/day. Quantity of solid waste generated from the proposed residential building is given below:

Table 11.1: Solid waste calculation Total solid Waste Occupancy Per Capita S. No. Project Components generation load generation Kg/day

1. Residential units 12760 0.5 6380 Visitors & 2. 1276 0.15 191.4 Maintenance staff

3. School 1920 0.2 384

4. STP Sludge 80 Total Waste Generation in - 7035 Kg/day

Source: Central Public Health and Environmental Engineering Organization (CPHEEO)

Table 11.2: Composition of waste

S. Quantity Description Mode of treatment / disposal No. (Tons/day) Biodegradable (@60% of Will be treated in Organic Waste Converter 1 4.17 waste generated) and used as manure for gardening. Non - Biodegradable (@ Sent to authorized recyclers or local bodies 2 2.78 30% of waste generated) for recycling will be used as manure for greenbelt 3 STP sludge 80 development

2.7 Parking requirement

No. of two wheeler Total area allotted Description No. of car parks parks for parking in Sqm

Basement Parking -UB 1101 1010 15580.5

Lower Basement (LB) 1139 980 16001.5

Stilt parking 400 720

Surface parking (outside 20 250 700 the building foot print)

Total parking provided 2260 2640 33002

Total parking required 2259 2608 32931.9 as per CMDA norms

Traffic Management Plan at the Entry & Exit to the Project Site: The project will have access through Mount Poonamalle Road (100 ft) wide road. Internal roads of 9.0 m wide will be provided within the site for smooth movement of vehicles. The parking plan & traffic circulation plan showing the entry and exit and the internal circulation is given in Site plan.

2.9 Type of building material to be used

Following building material will be used at site:

S. No. Building Material 1. Coarse sand 2. Fine sand 3. Stone aggregate 4. Stone for masonry work 5. Cement 6. Reinforcement steel 7. Pipe scaffolding (cup lock system) 8. CLC fly ash blocks 9. PPR (ISI marked) 10. P.V.C. conduit 12. MDS, MCBs 13. PVC rain water down take 14. Joinery hardware- ISI marked 15. PVC waste water lines 16. S.W. sewer line up to main sewer

2.10 Environmental Liability of the site

Project site is a vacant land. Hence the land is not polluted and it is suitable for residential development.

2.11 Existing Structure/Type of Material Demolition Debris etc

There are no existing structures in the project site, it is a vacant land. Hence there is no demolition/debris management involved.

2.12 Essential Topo sheets/Maps to be provided with ToR application

Google maps covering 1 km, 5 km and 10 km radius are enclosed in Annexure –

2.13 Digital Elevation Model/ Contour Map

Contour Map is enclosed in Annexure - IV. Details of environmentally sensitive places, wind pattern will be included in the EIA Report.

Detailed layout plan of proposed project development, approach roads, landscape, sewage disposal facilities and waste disposal etc., will be given. Lay out plan of built up areas with covered construction such as DG set rooms, transformer will be provided in EIA report. Requirement of natural resources such as water, sand, and wood will be used during construction stage. The required natural resources are planned to procure from the nearby local market. Master Plan enclosed as Annexure – III.

2.14 Site Selection and Planning

The project site is owned by M/s. BSCPL Infrastructure limited. The project site is a vacant land which is categorized as Primary residential / Urbanisable Zone. Site selection was done based on proximity to local communities, ecologically sensitive areas, Geo technical report will be covered in the EIA study.

3.0 DESCRIPTION OF THE ENVIRONMENT

Baseline studies are carried out to provide the detailed description of the existing ecosystem, landscape, infrastructure, cultural heritage and urban environment. A baseline study describes the initial state of the environment within the selected boundaries of the study area. Water quality, soil quality, vegetation pattern, ecology, socio-economic profile, land use, places of archaeological importance etc. will be included in the EIA report.

Study Area

The details about the existing environmental values are projected at each section in the form of the maximum and minimum values at each location and the measurement duration will be provided in the Map. The area of the study covers 10 km radius around the proposed site. To make the process easier, the entire zone is divided into two, namely the core zone comprising of the proposed construction project area and the buffer zone covering the remaining areas covered under the 10 km radius. Monitoring will be done within the study area and as per CPCB guidelines. Primary data collection will be in one season.

3.1 Land Environment

a) Topography

From the topographical point of view, contour levels, slope of the site, landform and terrain characteristics etc, is vital for the planning and implementation of environmental protection measures. Investigation Report on the topography will be enclosed in the EIA Report.

Methodology

The methodology and the study will envisage different Land Use and Land Cover (LULC) around the proposed project area. b) Soil

From the environmental point of view of soil type and characteristics, permeability, Sub-soil permeability and the soil fertility etc, is vital for the planning and implementation of green belt development, as part of maintaining the ecological balance of the region. The physical, strength and type of the soil characteristics Geotechnical investigation Report will be enclosed in the EIA Report. To identify soil quality Ph, Electrical conductivity, Moisture content, Total Kjeldahl nitrogen as N, Phosphorous as P will be analyzed as per Indian Standards test Method.

3.2 Air Environment

For the Climatology data the nearest authoritative meteorological recording station is maintained by the Regional Meteorological Center at , Chennai. The basic meteorological parameters such as wind speed, wind direction, Temperature, Humidity and Rain fall are pertinent to the air pollution studies are those governing the transport and diffusion of the pollutants in the atmosphere and it will be covered in EIA report. Base line data of air pollutant parameters extending an area of 10 km from the project site will be

monitored at 7 locations. Ambient air quality parameters namely PM 2.5 , PM 10 , Nitrogen dioxide, Sulphur dioxide and Carbon monoxide, Ozone, Pb, NH3, Benzene, Benzo alpha pyrene, Arsenic, Nickel will be analyzed as per Indian Standards 5182 method.

3.3 Noise Environment

Noise Level Study

The main objective of noise monitoring in the study area is to establish the baseline noise levels and assess the impact of the total noise generated by the operation of the activities around it. The environmental impact of noise can have several effects varying from Noise Induced Hearing Loss (NIHL) to annoyance depending on loudness of noise. The environmental impact assessment of noise from construction activity, vehicular traffic can be undertaken by taking into consideration various factors like potential damage to hearing, physiological responses, and annoyance and general community responses. Noise survey should be conducted in the study area while covering 10 km distance from the project site. Noise monitoring will be undertaken for 24 hours at each location. Using hand held instruments sound Pressure Level (SPL) measurements and the levels were measured at all locations, recording for 5 minutes at each hour was taken for 24 hours continuously. The day noise levels have been monitored during 6 am to 10 pm and night levels during 10 pm to 6 am at all the sampling locations covered in the study area. The results will be produced as per the Noise Pollution (Regulation and Control) Rules 2000 – Ambient Air Quality Standards in respect of Noise.

3.4 Water Environment

Water quality

Water is a vital commodity for the survival of human beings, animals, and vegetation and also for the proper balance of the eco-system. As such any adverse impact on water quality due to the proposed construction will have serious consequences on the environment. Hence it is essential to study the water quality, water table, Rain water harvesting of the regime likely to b influenced by the project and allied activities as per TOR and MoEF, EIA Manual. The water quality of the study will be covered in EIA report. Sampling and Analysis

Water sampling is to determine the existing quality of ground water around the project area and also to assess the impact from the proposed project. Sampling will be done by following standard guidelines for physical, chemical and bacteriological parameters. Analysis will be carried out by following methods prescribed in “Standard Methods for the Examination of Water and Wastewater (21st Edition)”. Samples will be collected from surface water body and bore wells in the study area. The site selection was done taking into account the drainage pattern and locations prone to water contamination. seven water sampling locations will be selected around 10 km distance from the project site.

3.5 Rain Water Harvesting

Keeping in mind the importance of water and it scarcity it is proposed to conserve water by rainwater harvesting by which the subsoil water condition / moisture content is maintained / improved to a great extent. Also it is proposed to harvest rainwater from the terrace area by collecting the same in a rainwater collection sump of suitable capacity and re-used for domestic purposes with the provision of a filtration unit. And the rainwater collected from open paved and landscape area will be collected in the storm water drain which is connected to Rainwater recharging pit; will be included in EIA report in detail.

Table 9: Run – off Calculations

Rainfall Area in coefficient Total Rainwater Description intensity in Sqm runoff Runoff Cum/day m/day Road area 29441.84 0.75 0.06 1324.88

Green area 54716.11 0.1 0.06 328.29

Roof area 21004.29 0.9 0.06 1134.23

Total Run-off 2787.84

The run-off will be routed through recharge wells. 15 nos. of recharge wells are being proposed for rain water harvesting.

Details of Recharge Trenches: Trench maintained all along the boundary, the depth of the trenches will be around 1.00 m. It is planned to remove the entire impervious layer to facilitate rain water recharge. The width of the proposed trenches is 1.5 m. Pebbles of different size will be provided in an ascending order in the tank and a layer of sand will be provided on top of the filter media. The rain water flowing through the open land, paved area and green belt area will be used for recharging to ground water through the above said trenches.

3.6 Biological Environment

Ecological survey will be done with the following objectives. 1. To carry out a systematic baseline survey of Flora and Fauna around 10 km radius of the study area. 2. To list the plants and animals present in the study area as per the classifications of MOEF, 3. To identify the impacts of the proposed expansion activities on the plants and animals, 4. To evaluate the impacts of the proposed action, and to propose Environmental Management Plan.

Scope of the work involved 1. The study is required to be carried out as part of EIA study as per the guidelines of the Ministry of Environment and Forests (MOEF) and State Pollution Control Board (SPCB). 2. The study should be based on the systematic field survey and secondary data (One season). 3. The study will cover the following: Flora a) Area will be divided as core zone and buffer zone b) Listing of all species (scientific and local names) found in the study area - 10 km. Radius. c) Listing of species as per the following classifications:  Agricultural crops  Commercial crops  Plantation  Natural vegetation  Grass lands  Endangered species  Endemic species  Others d) Based on the above findings Impacts of the proposed expansion. e) Environmental Management plans to improve existing status of flora in the area.

Fauna a) Core and Buffer zone divisions b) Listing of all species in the study area of 10 km radius around the study area c) Schedule for each species as per the Wild Life (Protection) Act, 1972 and as amended subsequently should also be furnished. d) Zoological and local name of the species should be furnished e) Listing of species should be classified as:  Endangered species  Endemic species  Migratory species  Details of aquatic fauna a) Presence of endangered and endemic species should be supplemented by density.

3.7 Socio Economic

The methodology adopted for the present study is the review of secondary data (2011 Census and District Statistical Handbook) with respect to population, occupational structure and infrastructure facilities available in the region in 10 km radius area. The information on socio-economic aspects of the study area will be compiled from various other secondary sources, which include public offices, semi-government and government agencies and focused in the EIA report.

3.8 Solid Waste

Construction Phase: Solid wastes generated are characterized and quantified according to different activities due to proposed project during construction and operation phase. Major components construction waste includes Cement Concrete, Bricks, Cement Plaster Steel (from RCC, door/window frames, roofing support, railing of Staircase) Rubble, Stone (marble, granite, sand stone) ,Timber / wood and the Minor components are Conduits (iron, plastic), Pipes (GI, iron plastic), Electrical Fixtures (copper / aluminum wiring, wooden baton, bakelite / plastic switches, wire insulations), Panels (wooden , laminated), Others (glazed tiles, glass panes). Construction wastes generated is estimated to be about 40-60 kg/m2.

Usage of Excavated soil, prevention of soil contamination, raw material handling and storage and disposal will be covered in the EIA report.

4.0 ANTICIPATED ENVIRONMENTAL IMPACTS AND MITIGATION MEASURES

. S. No. Environmental Potential Potential S ource of Impact Controls Through EMP Impact Evaluation Remedial Measures components Impacts & Design 1. Ground Water Ground Water Construction Phase No surface accumulation No significa nt impact as Quality Contamination Waste water generated will be allowed. majority of labors would from temporary labor be locally deployed tents. Operation Phase Waste water will be sent No n egative impact on Discharge from the to STP. After treatment, it ground water quality project will be used for Flushing, envisaged. Gardening and local body for avenue plantation and public parks. 2 Ground Water Ground Water Construction Phase: No significant impact on Quantity Depletion Source of water during ground water quantity construction is tanker envisaged. water supply Operation Phas e: No significant impact on The source of water Surface/ground water during operation phase is quantity envisaged. CMWSSB 3 Surface Water Surface water Construction Phase Silt traps and other Quality contamination Surface runoff from site measures such as during construction additional on site activity. diversion ditches will be constructed to control surface run-off during site development Operation Phase: Domestic waste water Treated waste Discharge of domestic will be STP for further water will be used wastewater to STP. treatment flushing, gardening and local body for avenue plantation and public parks. Excess water if generated will be sent to CMWSSB sewer lines. 4 Air Quality Dust Emissions Construction Phase: Suitable control measures Not significant because During All heavy construction will be adopted as per dust generation will be construction phase activities air pollution control plan. temporary and will the contractors are settle fast due to dust advised to suppression techniques facilitate masks for the labours. Water sprinklers will be used for suppression of dust during construction phase. Emissions of Construction Phase Rapid on -site Not significant. Regular PM 2.5 & PM 10 ,  Operation of construction monitoring of SO 2, NO x and construction and improved emissions and CO equipment and maintenance control vehicles during site of equipment measures will be development. taken to  Running D.G. set (back reduce the up) emission levels. Operation Phase: Use of low sulphur diesel Not significant. Use of Personal DG set would be used as Protective Power generation by DG Landscape development power back-up Equipment Set during power failure with tree plantation will (PPE) like be developed earmuffs Emission from vehicular and earplugs traffic in use Use of equipment fitted during with silencers construction activities. Proper maintenance of Stack height of DG equipment set as per CPCB standards 5 Noise Construction Phase Provision of noise shields No significant impact Environment near the heavy due to prominent Noise from vehicular construction operations landscape movement and acoustic enclosures for DG set Operation Phase Construction activity Noise from DG sets will be limited to day time operation hours only

Landscape development

DG set will be equipped with acoustic enclosures 6 Land Soil Construction Phase Construction debris will No significant impact. Environment contamination Disposal of construction be collected and suitably Impact will be local, as debris used on site as per the waste generated will be solid waste management reused for filling of low plan for construction lying areas etc. phase Operation Phase Generated Biodegradable Not significant. Generation of municipal solid waste will be treated solid waste in Organic waste converter. Used oil generated from D.G. set Used oil generated will be sold to authorized recyclers 7 Biological Displacement Construction Phase Important species of Environment of Flora and Site Development trees, if any, will be (Flora and Fauna on site during construction identified and marked Fauna) and will be merged with landscape plan Operation Phase Suitable landscape Beneficial impact Increase in green development with tree covered area plantation will be developed as per landscaping plan in and around the site using local flora 8 Socio- Population Construction Phase Local labourers from No negative impact Economic displacement Construction activities nearby will be used. Environment leading to relocation Oper ation Phase Project will provide Beneficial impact Site operation employment opportunities to the local people in terms of labor during construction and service personnel (guards, securities, gardeners etc) during operations Providing quality- Integrated infrastructure 9 Traffic Increase of Construction Phase Heavy Vehicular No negative impact Pattern vehicular Heavy Vehicular movement will be traffic movement during restricted to night time construction only and adequate parking facility will be provided with sufficient road width Operation Phase Vehicular movement Traffic due to residents will be regulated inside once the project is the project with sufficient operational road width

5.0 SPECIFIC STUDIES

The energy consumption analysis and data sheets are as per the Energy conservation Building codes 2007/Bureau of Energy Efficiency. The total power requirement for the project and the number of required DG sets will be provided in EIA report in detail.

5.1 Transport

Please refer site plan which will include the connectivity existing and proposed road. Traffic survey data will be discussed in the EIA report.

5.2 Energy Conservation

Energy conservation will be one of the main focuses during the complex planning and operation stages. The conservation efforts would consist of the following:

Architectural design

 Maximum utilization of solar light will be done.  Maximize the use of natural lighting through design.  The orientation of the buildings will be done in such a way that maximum daylight is available.  The green areas will be spaced, so that a significant reduction in the temperature can take place.

Energy Saving Practices

 Energy efficient lamps will be provided within the complex.  Constant monitoring of energy consumption and defining targets for energy conservation.  Adjusting the settings and illumination levels to ensure minimum energy used for desired comfort levels.

Behavioral Change on Consumption

 Promoting resident awareness on energy conservation  Training staff on methods of energy conservation and to be vigilant to such opportunities

Green Belt Development

It is proposed to have tree plantation along the periphery of the site and also to develop lawn and greenery inside the project area. The vegetation for the green belt will be selected from the native species adapted to the local environment. About 44540.99 Sqm of green area will be provided.

Landscaping has been taken care of in view of the environment and aesthetics of the surrounding areas. Stress has been laid on providing ample green areas in close conjugation to the hard areas in a manner, that the overall harmony and ambience is maintained. Landscaping takes into account the various aspects of the architectural design. Trees are proposed to be planted to form an integral part of the landscape plantation and their selection is based on their ability to provide shade, flowers and fragrance apart from their high-yielding growth pattern. The addition of shrubs, hedges and ground cover will add to the aesthetics and softness to the hard building surfaces.

6.0 ENVIRONMENTAL MONITORING PROGRAM

Table 12.1: During Construction Stage

Sl. No Item Parameters Frequency Location

Ambient Air At major construction 1 SPM,RSPM,SO ,NO Quarterly Quality 2 X area (total 5 stations) Equivalent Noise Level At major construction 2 Noise Level Daily Db (A) Area Water Physical, chemical & Ground water/Tanker 3 Quarterly Analysis Biological parameters Water

Table 12.2: During Operation Stage

Sl. No Item Parameters Frequency Location

1 Ambient Air SPM,RSPM,SO 2,NO X Quarterly At major construction area Quality (total 5 stations) around periphery of the site 2 Noise Level Equivalent Noise Quarterly Near DG sets, Near STP, Level Db (A) Near Parking Area.

3 Exhaust from SPM, SO 2 Quarterly Stacks of DG sets DG Set 4 Water Physical, chemical Quarterly • Ground water Analysis and Biological • Harvested water stored parameters in Tank (after treatment) 5 Waste water PH, BOD, COD,TSS, Quarterly • Before and after Analysis TDS, Oil and ga s treatment from STP

All parameters shall be monitored; compilation and reporting will be done by NABL Accredited Laboratory.

7.0 ADDITIONAL STUDIES

7.1 Risk Assessment and Disaster Management Plan

Risks in the complex will be due to natural calamities like earthquake, flooding and others such as fire and accidental hazards. All precautions will be taken to control these risks and a well-planned Disaster Management Plan will be covered in the EIA report.

7.2 Natural Resource conservation

Realizing the need for an eco-friendly environment has proposed to do the following natural resource conservation techniques. To minimize water demand the project proposal will have Water balance chart, sewage treatment plant, plan for treated water usage, dual pipe line rain water harvesting, regular air; water quality monitoring will be explained in EIA report of the project.

8.0 PROJECT BENEFITS

During construction phase local people will get benefited by the construction type of employment. The project site is located in the development zone. It will act as a pioneer for other development.

9.0 ENVIRONMENT MANAGEMENT PLAN

Environmental Management plan is a vital process of any management plan of the development project. This helps in signaling the potential problems that resulting from the proposed project and will allow for prompt implementation of effective corrective measures. The environmental monitoring will be carried out for the construction and operational phases.

Table 13: Environmental Monitoring Plan

Frequency of Sl. No Description Sampling & Analysis Construction Phase 1 Ambient Air Quality Once in three month 2 Stack Emission from DG set Once in three month 3 Ambient Noise Level Once in three month 4 Soil Qualit y Once in three month 5 Ground Water Once in three month Operation Phase 1 Ambient Air Quality Once in three month s 2 Stack Emission from DG set Once in three month s 3 Ambient Noise Level Once in three month s 4 Treated Sewage Once in a week 5 Ground Water Once in three month s

Budget Allocation for Environmental Monitoring Plan

Table 14.1: Construction Phase Total Cost (Rs. In Lakhs) S. No Parameter Operational expenses Capital cost (per Annum) Drinking water & sani tation 1 25 3 (Temporary toilets facilities) 2 Storm Water management 9 4 3 Solid waste /debris management 15 8 4 Environmental Monitoring - 5 Dust suppression Measure 19 9 Total Cost 68 24

Table 14.2: Operation Phase Cost In Lakhs Operational / S. No Item Setup Maintenance Cost per annum 1 STP Cost 240 12 Rain water Harvesting 2 45 10 (Recharge pits & collection sump) Environmental Monitoring 3 40 15 (NABL approved agency) 4 Energy conservation 75 12 5 Gardening 90 15 6 Solid Waste Managemen t 40 10 Total Cost 530 74

The budget allocation for proposed expansion will be provided subsequently in EIA report.

10.0 CSR ACTIVITIES Detailed CSR initiatives mentioning specific financial commitment with time bound programme will be included in the EIA Report.

11.0 SUMMARY & CONCLUSION

The proposed project is a development of Residential apartment.

 There will be minimum negative impact on Air, Noise and Water Environment.  Treated Waste Water will be reused for gardening and flushing.  Rain Water harvesting system is proposed.  Organic waste converter for solid waste management is proposed.  There will be positive Impact on Social conditions in and around the site.  The Project will not result in any adverse impact to the Environment.  The marginal impact of setting up the Development in the proposed location will be fully mitigated by the Environment Management Plans. (EMP)  The proposed project will improve the quality of living being offered through better environmental aspects like large landscaped areas & better amenities.

All the above mentioned details of practices as provided in this ToR will be studied in detail during the EIA report.