1

Annexure I DETAILS OF PENDING PROJECTS (Power Sector)

Rs. Lakh

Sl. No Name of Scheme Installed Capacity (in MW) Estimated CostFunds required for Grant provision completion of project. for 2007-08

Total A PROJECTS COMPLETED UPTO 90%

TAWANG DISTRICT

1 Nuranang MHP 6.00 3458.08 49.86

WEST KAMENG DISTRICT 2 Sessa Nallah MHS 1.50 532.00 22.60

UPPER SUBANSIRI DISTRICT 3 Sippi SHP 4.00 3832.92 1557.17

WEST 4 Kambang SHP 6.00 4160.55 1476.44

UPPER SIANG DISTRICT 5 Sirnyuk MHS 2.00 2464.32

6 Singa MHS at Singa 0.05 94.16 21.86 7 Silingri MHP at Geling 0.03 84.18 8.84 A+B+C+D= Rs. 6911.00 Lakh 8 Kopu MHP near 0.25 214.00 58.51

LOWER DIBANG VALLEY DIST. 9 Deopani MHS PH-II ( 2 X 250 0.50 721.84 15.54 KW)

DIBANG VALLEY DISTRICT 10 Mini hydel over Echi Ahfra 0.40 484.79 30.01 11 Aug. of Awapani MHS 0.50 613.57 89.72

ANJAW DISTRICT 12 Yapak Nallah MHS at 0.20 535.21 108.16 13 Mati Nallah MHS at Chingwinti 0.50 598.56 in ( 2 x 250 KW)

Total of 90% 21.93 17794.18 3438.71 2

Sl. No Name of Scheme Installed Capacity (in MW) Estimated CostFunds required for Grant provision completion of project. for 2007-08

Total

B PROJECTS COMPLETED UPTO 80% DISTRICT 1 Kitpi Ph-II 3.00 2959.04 915.98 2 Bramdhongchung MHS 0.10 105.30 65.30 3 Shakti Nallah MHS 0.10 109.32 74.35 4 Bongleng MHS 0.10 114.27 79.27 5 Thimbu MHS 0.10 126.91 86.91

WEST KAMENG DISTRICT 6 Domkhrong MHP 2.00 2845.77 285.40

WEST SIANG DISTRICT 7 Liromoba MHS 2.00 2792.18 180.00

UPPER SIANG DISTRICT 8 Sipit MHS 2.00 2147.84 60.00

EAST SIANG DISTRICT

ANJAW DISTRICT 9 Teepani MHS 0.50 575.30 434.20

TIRAP DISTRICT

Total upto 80% 9.90 11775.93 2181.41

C PROJECTS COMPLETED UPTO 70% 1 Shaikangchu MHP 6.00 4060.00 3578.71 2 Mago MHS 0.10 140.44 140.44

3 Khet MHS 0.10 144.27 144.27 3

Sl. No Name of Scheme Installed Capacity (in MW) Estimated CostFunds required for Grant provision completion of project. for 2007-08

Total

WEST KAMENG DISTRICT 4 Ankaling MHP 0.03 66.35 66.35

KURUNG KUMEY DISTRICT

5 MHP over Koye river 0.05 90.00 90.00

WEST SIANG DISTRICT

6 MHS over river Yingko Sikong at 0.05 40.14 40.14 Rapum village under Tato Circle

UPPER SIANG DISTRICT

7 Sidip MHS 3.00 3405.52 1325.55

8 Angong Nallah MHS at Janbo 4.50 3470.00 2751.12

9 Gosang MHS 0.50 826.00 788.78

ANJAW DISTRICT

10 Langpani MHS at Gamliyang 0.40 543.91 530.86

11 Tah Nallah MHP 0.10 122.99 122.99 12 Krawti Nallah MHP 0.10 119.07 119.07 13 Ashapani MHP 0.06 99.98 99.98

14 Hathipani MHP 0.10 120.44 120.44 15 Maipani MHP 0.06 98.14 98.14 16 Kachopani MHP 0.20 393.33 393.33

CHANGLANG DISTRICT 17 MHS over Ngonalo at Vijay 0.10 408.45 344.47 Nagar Total upto 70% 15.45 14149.03 10754.64

Grand Total : 57.85 54669.39 16374.76 D. DETAILS OF RENOVATION & MODERNISATION PROJECTS

PROJECTS COMPLETED UPTO 80%

TAWANG DISTRICT 1 Kitpi MHS Ph - I 1.50 374.72 237.89

LOWER DIBANG VALLEY DIST. 2 Deopani MHS Ph - I 0.75 237.90 234.52

DIBANG VALLEY DISTRICT 3 Awapani MHS Ph - I 0.15 93.10 63.83

Total upto 80 % 2.40 705.72 536.24 4

Sl. No Name of Scheme Installed Capacity (in MW) Estimated CostFunds required for Grant provision completion of project. for 2007-08

Total Grand total (Generation) 60.25 55375.11 16911.00 6911.00 Annexure-I B DETAILS OF RENOVATION & MODERNISATION PROJECTS

Sl. Name of Scheme Installed Capacity Estimated Grant provision for No (in MW) Cost completion for completion of project Total

PROJECTS COMPLETED UPTO 80%

TAWANG DISTRICT 1 Kitpi MHS Ph - I 1.50 374.72 237.89

LOWER DIBANG VALLEY DIST. 2 Deopani MHS Ph - I 0.75 237.90 234.52

DIBANG VALLEY DISTRICT 3 Awapani MHS Ph - I 0.15 93.10 63.83

Total upto 80 % 2.40 705.72 536.24