a
m
38
ser
par
pre
con
the
17
com
is
the
not
in
resting
box
operat
BNE
This
of
Thai
line
five
major in
is
joints
Pontchar
in
monolithi
months,
details
of
largest
still
a
caps
of
years
design-
JOURNAL
the
intercon
precast
long
12
solution
is
The
cast
discusses 44
Lake
dry
prestressed
pile
Louisiana, consists
in
the
the
the
The
Expressway
PCI
all
role
the
and
prestressed
on
miles).
form
after
With
composed
1956,
using
slah,
time.
the
transportation
with
Causeway
design
in
Orleans,
Thailand,
(34 will
Site
gives
Authority
all-precast
the
expressways
bridge, Today,
deck
by
major
area.
constructed
supported
on
sections
at
a
An
superstructure
the New
of
a
The
km
extended
and
presents
piles.
the
was
BNE
place
were
represents
The
in
near
long.
it
completed
an
construction.
Transit
55 Pontchartrain
of concrete
all-precast,
in
fabricated
play
supporting
of
Bangkok,
girders
Bangkok cylinder
system
of
also miles)
Note:
Lake
link method.
to
Conceived
were
article
(ETA),
in
precast
The
accomplishment
The
project,
Rapid structure,
the
girders
Thailand.
ft)
(23.8
satisfactorily.
hollow
but
features
ing
vice,
(56
cally.
allel on
the
ponents stressing
major
crete
km
train
greater Editor’s
This
land nected
and
element
Bun.
length
out. in
span-by-span
expected
World’s
world,
in
important
on
$1
total
en
the
the
the
design also
post-tensioned
is (see
long
Southeast
BNE
Expressway
Chon
used
a
Book
in
its
an is
carried
under
the
eastern
tendons.
size
new
of
of
built
the
the
Na
(BNE)
and
and
Largest
for
in
has
the
States
earned
the
and
miles)
ever
bridge
ever
city
project
Pontchartrain,
segmental,
Guinness
RECORD
(34
Bang
job
has
record,
from
the
2000,
provides
length
operation.
bridge
techniques
the
This highway
United
to
the
km
describes
Bangkok longest
in
Lake
expressway
Expressway
1).
longitudinal
match-cast
55
the
into
development
the
billion
precast
Na
operation
and
stretches
in
January
as
precasting
Fig.
Thailand,
superstructure
longest
project
$1
at-grade
breaking
of
entry
use
Bangkok
were
around
crossing
surpasses
elevated
Bang
billion,
an
precasting
contract,
In
(see
WORLD
of
the
to
external for
new
length,
construction
of
largest
the
Records
The
top edge
tire
footnote).
Louisiana,
taken. bridge
project
As
world
of the
right
the
of Bangkok,
was
build
and
The
commercial
concrete
system girders
only
precasting gigantic
Operation
NEW
Thailand
Expressway,
Ing. Bridge
-
Dr.
Sciences
Na
Bauaktiengesellschaft
Ing. Manager
-
Division
Applied
Brockmann,
Germany
Berger
of
Project
Thailand
+
Dip!.
Germany Rogenhofer,
-
BBCD
International
Bilfinger
Horst
Wiesbaden,
26
Bangkok,
Formerly,
Bremen,
University
Prof.
Christian iv
Precasting
Longest Bangkok, Bang V.. a
V , •. —— a V VV ‘V • — a 1L—zz—z:
,—
Fig. 1. Overview of the BNE project in Bangkok, Thailand, completed in January 2000. project, ETA intends to facilitate the and intersections for a total deck area In essence, this was a lump-sum de industrial development of Southeast of 1,900,000 2m (20,400,000 sq ft). sign-build contract for the turnkey Bangkok and to connect the planned The agreement stipulated the project completion of the project. Thus, the Second International Airport as well would be completed within 3’/2 years. start of construction had to overlap the as to connect the deep-water harbor The BNE contract was broken down ongoing design. In addition, Joint with the city. Another reason for the into eight phases with each phase hav Venture BBCD, under the contract, expressway is to alleviate traffic con ing a specific completion date. The had to finance the project until com gestion in and around Bangkok. reason for this requirement is that the pletion. The total cost of planning, de The purpose of this article is to pre expressway is a toll facility and, there signing, constructing.and financing the sent the design-build contract, de fore, there was a financial incentive in project was approximately $1 billion. scribe the design features of the meeting the schedule so that each bridge, discuss the construction tech completed section could be opened to DESIGN FEATURES niques used in the project, and give traffic and start collecting toll fees. the details of the precasting operation. The entire project was stipulated to be OF PROJECT completed by January 2000. The BNE was constructed through Because of the extremely short con out its DESIGN-BUILD CONTRACT entire length on top of the cen struction period, the design phase had ter and outside medians of the exist In June 1995, a contract was signed to be completed quickly. This included ing at-grade Highway 34 (see Fig. 2), between ETA and Joint Venture soil investigations and foundation de where by contract the traffic must BBCD under the sponsorship of Bilfin sign, bridge alignment and geometry, flow without interruption at a speed ger + Berger with Ch. Kamchang PLC structural design of the columns and of 80 km/h (50 miles per hour). The as the important local partner. The superstructure, preparation of shop Department of Highways is currently contract covered 55 km (34 miles) of drawings, lighting, traffic control, and upgrading Highway 34 and the two elevated expressway together with an toll facilities. Also, a very large pre projects had to be carried out simulta additional 40 km (25 miles) of ramps casting yard had to be established. neously over the same route. IV
January-February 2000 27
at
is
of
in
85
26 el
all
the
ft)
the
H-
the
tips
ex
and box
(43
suc
box
cell
box
pre
box
box each
aes
large
struc
over
estab
as
portal
above
ramps
below
of
the
which
facili
m
which
traffic at
(89
six
accom
the
The road
lanes
the
surveil
tips
average
the
external
when
the
JOURNAL
below.
The
wing
to
the
diagonal
booths
m
to
is
13 Widening
structures
wide Each
segmental
but
accommo
of
symmetri
ramps,
allows
one
to
wide
single
unique
on
for
span
from
longitudinal toll
PCI
by
27
three
to
the
construction
and multiple U-turn
a
Up
a
wing
toll was
36
were approximately
ramps,
enhance
a
single-column ft)
two
with
to
approach
at
unusually
clearance
columns
width
plaza
lead
segmental
webs.
of
frontage
of
bridge.
is 12
long
to below.
The
10 the
approximately
space
a
roadway
cast
with
has
precast
has
located
project,
Adding
have
highway
using
at (262
to
conceived is
the
and
the
toll
ramps.
the
This
and
spanning project
the
centerline
interchanges.
on
structure
webs)
elevated
ingredient
tendons
the
m
are
This
by
similar
to up
between
joints.
precast
the
supported
addition
was
weighs
match exceptionally
of
a
in
the
there
elevated pairs structure
80
highway
structure bents
highway
line
connected
BNE
H-shaped
ft)
two
superstructure.
ft).
span-by-span
Section.
tons).
on
in
dry for
girder including
major
comprised
in
existing
by
in
roadways
support
between
viaduct.
the
are
elevated
that
ramps
the
connected
This
the
were spanning
are
bridge
is
The
expressway
(94
expressway
frames.
(46
each, facilities.
essential
main
which
main
box support
to
(138 about
only
had
the
box
These
of
accelerationldeceleration
supported
into
segment exits
construction
slab
included
existing
new
existing
m
wide
m
aesthetics.
the
An
Two
build
the
Note
The
The
The
14 and cess
widening portal
modated
lance increase girders
are the
end.
over
tures
the
construction
supported
girders the
accomplished frames
of
date
cally the
lead evated
elevated, pressway
typical
cast
(i.e., struts tonnes
girder top
girder.
ft) lanes
shape
all
wide tate
bents.
support 42
girders to thetics
post-tensioning
segmental place
to
so
any
box
spe
pric
influ
maxi
to
precast
the
a
The
and
attractive
girder
of
use
has
ft).
highly
the
aesthetically
to
box
is
superior
an
(146
design
the
was
which
Also,
all
line
m
for
3),
construction,
time,
then,
44.4
slender
of
main
were
Fig.
of
the
the
same
structure.
units
provides
speed
(see
by
of
span
method.
the
solution,
of
At
shape cific
girder mum
enced
ing other pleasing
ments, lution
ft).
seg seg
Pro
deck
com
more
(146
of
a
m
bidding
that
segmental
economical
BBCD
and
coordination
44.40
alternate.
hauling
JV
of
provided
more
precast
apparent
the
a
cast-in-place
first
and
projects.
span
and
planning
the
project,
with
line
two
became
the
I-beam
the
faster
It
than
handling
the
facilitated
construction
of
Main
an
alternate
3.
During
Fig.
28
solution
slab solution.
mental efficient, duction,
between pared
BBCD phases lishment of an efficient precasting Typically, 16 piles are necessary to The difficulties in driving the piles yard, which became the largest plant transfer the loads from the main line were due to the very soft consistency ever assembled in the world. A total columns into the sand layer. In order of the upper clay layer [12 to 20 m (39 of 40,000 segments, of varying pro to produce the spun piles, a special to 66 ft) in thickness] which does not portions, were fabricated. The quan plant had to be built with sufficient ca provide any horizontal support for the tity and rate of production for box pacity to manufacture the 900,000 m piles. The heaving pressure of the co girders was one of the highest ever (2,953,000 ft) of piles required for the hesive soil during pile driving can achieved. Approximately 60 percent project. cause a displacement of more than 1 m of the overall concrete requirements for the project were used in the yard for the segments which were cast in carefully planned and always repeti tive sequences in order to increase the speed of fabrication and quality of I product. More details on the precast ing operation will be given later on in driven piles this article. 0800mm The technology of precast segmen soft clay prestressed tal construction, and particularly span- concrete by-span construction, was pioneered by Jean Muller and the firm he heads, Jean Muller International. Segmental welded joint construction with external post-ten sioning and dry joints has been imple hard ólaS, /. 30rn mented especially by Bilfinger + Berger, Germany, on many bridge projects in Southeast Asia, Africa and Australia. The principles used on the
BNE project have been achieved be I I fore but never on such a gigantic scale. For more information on seg sand, bearing stratum mental construction and on this pro ject, see Refs. 1 to 7.
CONSTRUCTION Fig. 4. Pile foundation. TECHNIQUES This section describes the various structural elements and techniques used in constructing the substructure and superstructure of the elevated bridge.
Foundation of Main Line The city of Bangkok is situated in the delta of the Menam Chao Phraya River. The underlying soil can be sim ply classified as a three-layer model, namely, soft clay, stiff clay, and sand. It was, therefore, necessary to transfer all loads to the sand layer. For the BNE project, 800 mm (31.5 in.) diameter precast spun piles, with a wall thickness of 120 mm (4.72 in.), were used. The piles are in general 30 m (98 ft) long. They are composed of two sections which are welded to gether to ensure the transfer of tension and compression forces (see Fig. 4). Fig. 5. Mainlinecolumn with superstructure.
January-February 2000 29 __H’
(3.3 ft). Thus, the speed of construc tion was often impeded by soil pro H—var. —. 27,20 files comprising five to seven intermit tent layers of clay and sand. The loads transmitted by the columns are transferred to the piles through a pile cap of 2.5 m (8.2 ft) thickness. The top of these pile caps is always below the flow line of the drainage in the center and outer medi ans of Highway 34.
Main Columns The main line columns are H- shaped and display a slender light ap pearance. The H widens from its base 27,00 m at the pile cap to the top so that the outside corners are gracefully curved Fig.6. Configuration of portals. (see Fig. 5). The architectural design also serves a structural function. The columns are located in the open drainage area of the center me dian of Highway 34 and reduce the section of this free flow channel by a minimum amount. In the erection of the superstructure, an underslung girder is used which moves through the upper arms of the column. Since there is no cross-beam, the launching is simplified. The superstructure is placed on in clined elastomeric bearings in order to avoid moments from load transfer be tween the box girder and columns under symmetrical loads. This re quires very tight construction toler ances because the planes of the bear ings must be exactly parallel to the precast segments. The average height of the main columns is 16 m (52.5 ft). The columns are cast in three parts, i.e., legs, struts, and arms. First, a kicker is cast to ad just for the differences in height be tween the varying top levels of the pile caps and the variable height of the su perstructure. This allows the use of standardized formwork to fabricate the columns. Because the tangent at the foot of the column is vertical, the joint is easily handled. The sequence of fabrication is to first erect the inner dome of the col umn formwork and then to place the prefabricated reinforcing bar cages for the legs. After the outside forms have been erected, the legs can be cast. The casting of the strut and upper arms fol lows the same procedure. Fig.7. Erectionsequence for portal segments.
30 PCI JOURNAL Portal Beams picked up by a winch and taken to D6 Segments their final location. Erection is, In areas where the main line is there The D6 segments are the main part fore, completely separated widened, i.e., at the toll plazas and the from traffic of the structure. They span in the flow. Fig. 7 shows the erection proce merging areas of the ramps, it is nec transverse direction with a width of dure for portal segments. essary to place the superstructure on 27.20 m (89 ft) over six lanes of traf portal beams because the same cross- fic. For typical segments, their height section of Highway 34 must be main D2/D3 Segments and length are 2.60 and 2.55 m (8.53 tained. A total of 180 portals were D2 and D3 segments for two- or and 8.37 ft), respectively; for pier seg erected. three-lane decks are used for the ments, their width is 1.775 m (5.82 The portal beams are rigidly fixed at ramps, interchanges, and toll plazas. ft). The weights of typical girder and the main line portal column and at These types of segments have been pier segments are 85 and 100 tonnes each end connected to the outside previously used successfully on other (94 and 110 tons), respectively. The columns by a hinge. The maximum expressway projects by Bilfinger + unusually slender cross-section has span is typically 27 m (89 ft) long. Berger in Bangkok. Both are box gird inclined webs and two struts in the The beams are formed by match-cast ers with a deck having a maximum middle of the segment (see Fig. 9). box girders with vertical webs, which variable width of 15.60 m (51.2 ft) The inclination of the webs accentu are externally post-tensioned. (see Fig. 8). ates the curvature of the outside of the The portal columns have the same Note that these segments are erected columns and carries this line to the form as the H-columns but have, in with an overhead truss girder, which is horizontal plane of the deck. addition, corbels with the same cross- launched from column to column. The spans are longitudinally pre section as the portal beams. A cast-in- First, the segments are hung from the stressed by 22 tendons. Twenty of place joint is necessary to provide for truss and properly aligned. They are these tendons are placed externally in the adjustment between these corbels then post-tensioned longitudinally by the box and two are placed internally and the first match-cast segment. The external tendons in the box, and fi in the edge beam. The transverse post- rigid connection and the resulting ten nally placed on the bearings. tensioning is accomplished not only sile forces in this area are not only pre-compressed by the external ten dons in the beam but also by internal fl lflflf) - 1Rfl tendons in the upper part of the col D2: 7,00-11,9Cm umn (see Fig. 6). The portal beams span three traffic 0,20 m lanes in each direction and it was not permitted to interrupt the traffic for construction operations. The conven 2,40 m tional method of using beams cast-in- place on lower formwork was in addi tion too slow considering the tight D 3: 5,50 m time constraints. To fulfill both de — I mands, it was decided to use precast D2: 3,7Cm components that could be erected with metric dimensions an overhead truss. This portal truss has two compo Fig. 8. Configuration of D2/D3 segments. nents, namely, a launching girder with a length of approximately two main line spans and an erection girder, two portal spans long. Both components 27,20 are connected by a turntable, which is placed on one column. The complete truss is first launched one span between the arms of the H- column, and then vertically and hori precast strut zontally supported on three columns. Then, the turntable is fixed on the por tal frame. Finally, the erection girder is turned by 90 degrees and is then supported at the ends by the outside portal columns. metric dimensions The portal segments are delivered to the center median where they are Fig. 9. Configuration of D6 segments.
January-February 2000 31 ____
deviator segment A
deviator segment B
tendons
E pier segment anchorages
Fig. 10. Longitudinal post-tensioning. by the tendons in the top slab, but also The upper flanges of the launching place of erection. The chassis are by placing them in the webs and bot girder form the planes on which the equipped with hydraulic jacks, which tom slab (see Figs. 10 and 11). chassis move. The swivel crane places allow for three-dimensional adjust The H-column, the underslung truss, each segment on one of these chassis, ments, i.e., vertical, horizontal, and ro and the D6 segments of the superstruc which is then pulled by a winch to the tational movements. After adjusting ture were designed by Jean Muller In ternational as an integrated approach to the construction of the elevated main bridge line structure. The cross-beam of the deck H-column forms the support for the launching girder and the arms provide the horizontal support. The cross-sec ‘N live/ end dead end tion of the girder is V-shaped and it is equipped with a swivel crane for lifting and placing the segments. The segments are placed on chassis (frame supports), which are equipped with hydraulic jacks for adjusting and dead end leveling the span. The length of the girder is slightly longer than the maximum of two spans. It comprises a load carrying plate girder in the front and a truss to cantilevers and box girder support the launching in the rear. The swivel crane can be placed either at the nose of the plate girder or on the last erected span. It is, therefore, pos Z sible to deliver the segment to a 1 sta tion below the swivel crane at grade as tendon well as to the already erected deck (see Fig. 12). Fig. 11. Transverse post-tensioning.
32 PCI JOURNAL ,Jill Fig. 12. Underslung erection girder.
all the segments of a span, the external Table 1. Comparison of material quantities in superstructure segments. tendons are placed in the box and Quantities per square meter Segment Segment stressed. Then, the girder is lowered to of bridge deck 2xD3 D6 transfer the load to the bearings. The girder is supported by three slid Concrete, 3m 0.51 0.49 ing chairs and two temporary chairs Reinforcing bars, kg that are required for launching. It is 70.6 59.2 launched by the front chassis that is Post-tensioning tendons, kg 24.4 24.0 motorized. This chassis needed for Conversionfactors: 12m = 10.76sq ft; 1 3m = 35.3cu ft; 1kg = 2.2 lbs. launching is fixed to the erected super structure and pushes the girder forward using a gear. For longer spans, the cen ter of gravity during launching is in Table 2. Quantities of components/materials in total structure. front of the last support. A reaction Components/Materials Quantity force is transferred through the truss and into the erected deck. Deck area. 2m 1,900,000 D6 deck area, 2m 1,400,000 D2/D3 deck area, 2m 500,000 Comparison of D2/D3 with D6 Segments D6 segments, pieces 21,320 D2/D3 segments, pieces 18,250 The contract terms of the project al lowed the bidders considerable free Mainline piers, pieces 1,255 dom in bidding for the design. Bilfinger + Berger elected to use D2/D3 seg Piles, pieces 28,882 ments for the ramps with a width vary ing from 6.0 to 10.75 m (20 to 35 ft). Concrete, 3m 1,800,000 For the 55 km (34 miles) mainline, they selected the D6 segments. Almost Reinforcing bars, tonnes 167,000 80 percent of the total deck area of 1,900,000 2m (20,400,000 sq ft) is Post-tensioning tendons, tonnes 52,240 formed by D6 segments. A comparison Conversionfactors: I 2m = 10.76sq ft; 1 3m = 35.3cu ft; I tonne = 1.10tons.
January-February2000 33 of the main material quantities of D3 At the same time, all the logistics, i.e., the cost of land, equipment, and trans and D6 segments is shown in Table 1. production, handling, hauling, and portation facilities was about $26 mil Evaluated by local prices in Bangkok, other operations are simplified. The lion. The Bang Bo precasting yard the quantity differences alone reflect a total quantities of components/materi (see Fig. 13) is the largest plant in the savings of 7 percent in the superstruc als of the project are listed in Table 2. world and boasts the highest installed ture. Of course, these savings are not production capacity of precast compo only limited to the superstructure, but nents ever achieved. THE BANG BO extend to the substructures as well. Construction of the plant began in PRECASTING YARD the summer of 1995. Within 9 months In order to construct the BNE pro after starting the yard fill, production Construction Speed and ject, a giant precasting yard had to be of the segments commenced. A total Overall Material Quantities set up to fabricate the thousands of of 40,000 bridge segments and 30,000 The biggest advantage of segmen segments required for the bridge. The other precast reinforced concrete ele tal construction with external post- Bang Bo precasting plant was con ments such as road barriers and I- tensioning and dry joints is the speed structed at Kilometer 29, about 4.5 km beams for the ramps were produced. with which the superstructure can be (2.8 miles) north of the expressway. The facility also contained workers’ erected. In bridge construction, the Comprising an area of about 650,000 camps, canteens, offices and laborato critical path (after a given starting 2m (7,000,000 sq ft), the plant was lo ries, carpentry, mechanical and weld period) always shifts to the super gistically planned down to the mm ing workshops, a central store, a rein structure. Any increase in the rate of utest detail. forcing bar cutting and bending shop, erection directly accelerates the con The marshy terrain in the delta of the plus an area for the production and as struction period. Menam Chao Phraya River, together sembly of post-tensioning ducts. For the BNE project, six overhead with access roads, had to be completely Approximately 1800 superstruc trusses (D21D3) and five underslung developed in order to efficiently pro ture segments (D2/D3, D6, and por girders (D6) were used. When all the duce and transport the heavy precast tals) were produced per month in a girders are in operation, 2500 m (8200 concrete components. The entire pro quality controlled environment. The ft) of ramps and 2100 m (6890 ft) of duction area was founded on driven re storage area for segments and other mainline deck were erected per month. inforced concrete piles and overlaid precast sections (see Fig. 14) was In square meters of deck area, the with a cast-in-place concrete slab. about 260,000 2m (2,800,000 sq ft), erection speed for D6 girders was The amount invested in constructing corresponding to a production period twice as high as for the D2/D3 trusses. the complete plant, without counting of 7 weeks.
Fig. 13. Layout of precasting yard.
34 PCI JOURNAL to
by
op
pre 200 was
each rn3fb area. were con
enor
could
at
output
reduce reduce of of
line. the used
concrete
100 segrega sections equipped vibratorS
1,100,000 and to placed to the
there
for
of
plants the
ft) Twenty-five
concrete were
Segments were was slump
form involving volume
workable about cu rate
it
concrete. prevent
a
production increase devices
ft),
volume anufacturiflg
fresh The mixing
at to hour). was
Both to (106 reinforced
mixers
CU initial 2000
produCtiOfl tasks. Precast fresh
the
where proportioned
vibratorS and transported
m3 The per
and of
an
of the
3 segment
shaft
ft belts. extremely
concrete was
concrete concrete.
in.).
D6 time cohesive heavily cu
molds, ends concrete was with
mixers logistical
highmiXiflg
(8 and internal components total batching
15.
(38,830,000
fresh the
Vertical For The
Production posite mous of (3530 and cast m3 with mixing produce truck to conveyor consolidate required mm two The mixer crete highly tion Fig. JanuaryFebrUarY
to
to
in
to
the
the the
the
the
the
ge
and
Fig.
sur
seg
pro
into
seg
situ
con
rails, were
espe
trans
of
of to
cages
to
differ
of super
molds
and caused
patch
forms.
carried
the
survey.
the
the taken
on
the
(see
JOURNAL
segment
new
the (concrete
concrete
were
following be
drawings.
area,
bar
be
the
picked
production
match-cast
of
a be
The
arms
have
cranes them
in
accuracy
given PC!
the
soffit
of
the
can
define
developed
survey
the
again
can
the
lifts
sequence,
segments
Before
for
ends
must
layout finishing
strength,
to
was
coordinates
work.
storage
tower
inspection
segment
segments
casting
was
three
z
adjacent
brought
stressed
deformations
the
segments
both
deflections
travel
When cantilever
span.
casting,
Care
the
reinforcing
rails D6
for
portal
post-tensioning
drawings
and
layout,
has segments
at
two
day’s
and
segments
post-tensioning).
geometric
checked
the
on
fully
by
y,
with
required
the
transported,
the
here,
attention
each
deformations
the
up
after-cast line.
the
x, After
the
necessary,
full
typical
is
the
software
its
mold
match-cast
areas
placed
of
layout
a
of
and
intermediate different
were
were
If
post-tensioning,
since
the
the on
curing,
direction.
spanning
lifted
is
between
Such
and
shifted
From
the
stiffnesses.
transverse
molds.
the
Special Unlike
Each
Span
16).
structure,
mix,
avoid
ent timing
storage verse wide cially
time-dependent by
out. duction pier
segments ments
reached
segment to work
accordance check position. ated lines.
monitor After was
Special
ometry
ment,
were crete
veyed
quired and the
joints
to
of
12
ar
re
15.
D6
bar
the
ten
ten
this bars
pre
lift
with
pre
seg
seg
day. skill
only
have
19
more
cast,
are
casting
two
ends
Fig.
of
the
one
pier
variable
addition,
longitudi
segments,
curvature
formwork
travel
in areas.
the
a
were
pulled)
they
the
special
between
In
were
achieve
ratio
the
segment.
D6
whereas deviators
from
direction,
the
technical
transverse
be
segments
at
for pattern:
reinforcing
fabrication transverse
match-casting
with
within
reinforcing
of
a
To
cages
shown
the
impart pier
pier
storage
operation,
and
the
superstructure
rails
molds. and the
a
cage
which
later
to
line,
to
segment,
to
struts,
therefore,
direction, for
are
to
bar
needed.
D21D3
typical
of
on
26 two
needed
this
storage
for
difference
days.
bar
the
position
following
one will
surveyed
production,
segments,
of
a
segments
for
and,
struts
2
are
typical
transported
area
lines
also
forms
were
of
moved
a
production
were
longitudinal
the
towers
fixing
those
cranes (through
and
segment
with
the
pier
total
also
knowledge
form
in
are
there
However,
took
a
for
transverse
the
and
Molds
were
illustrate
is
particular
the
rate
and
The
reinforcing
tendons
the
a required.
molds
molds
the
In First,
i.e., Survey Match-cast Intermediate
Reinforcing Molds
Tower
To
Typical
For
typical
1.
nal
diabolos
dons fabrication dons,
together
5. molds
3. 6. which
4.
10 are
stripped, and production In 2.
cycle ranged
a complicated casting
ment. high
38 For jigs.
ment 7,
there position,
molds
on molds
fixed.
/
to
of
in
in
to
of
to to
on
are
the
the
psi)
con
con
con
limit
were
sheet
thick
dura
using
could
33
maxi
where
as
before
hydra
appro
speci
appro
mixing
to
shifting
reduces
for
a
psi).
the
of
expedite transportation.
concrete. required.
in.)
placed
For
percent
be
high-early
molds
(2900
slab
fresh
segment
cracking.
suitable
applied
the
take of
The
a
precast
plastic and
is
for
(1
beneficial that
properties
This
To
50
the
of
molds,
serves
a
of was
not
match-casting
to superstructure
cement
(8000
temperature
required
MPa
deck
was
the
cm these
practical
to
ready
satisfactory.
strength
zero. of
a
the
the
sheet
cool
more
3
and
thermal
time,
with components
mix
20
on
found
quality
situation.
was
MPa
is
match-casting
not
surfaces
a
following
might
is
to
a to
to of
of
due
stripping
method.
is
force
temperature
this
confined.
it
55
operations,
segment
and
by
temperature
the
stationary
high
it
been
job
that
is
general,
a
plastic
temperature
At
95°F)
segment
evaporation
covered
in
another
influence
was
water
for
concrete,
hours,
concrete
strength allow
to In
air
has
minimizes
D6
way
segment
The
unformed
measures
10
segments
to
it
for
since
placing
the
of
reasons,
a
(91
concrete
were
compressive
dissipation
general,
16.
and
specific prestress
short-bed previous
produced
started.
placing
cast.
the
prevent
producing
Superstructure
All
The
In
Fig.
36
the
bulkhead
the position.
strength order of produced be
After concrete
are post-tensioning get
such tion match-casting
35°C to water. heat the
crete layer
In
mum
hardened crete,
segments one know fresh priate
the crete,
priate
bility
bleeding fied produced using the long bed method. This is because their dimensions are smaller, the spans are shorter, the ge ometry is simple, and the number of pieces is relatively limited. Here, the soffit form was laid out for a full span. The outside and inner formwork trav eled to the next position after harden ing of the last cast segment. To achieve —I a high degree of accuracy between seg i-I I ments, match-casting was also used in I — ! I-. this operation. At the end of the casting — operation, all segments of one portal - - — ! span were aligned in a row. — I Figs. 17, 18 and 19 show progressive :‘.r1 views of the project under construction.
CONCLUDING REMARKS Precast segmental, span-by-span construction using dry joints is partic ularly advantageous in serial produc tion when a limited number of struc Fig. 17. Positioning of Segment D6 on mainline column. tural elements are reproduced many times. The rate of construction is much faster than any other comparable construction method. In addition, a very high quality product is ensured. The planning of an industrialized se rial production project must encom pass all steps of the process, namely, planning of the production output, de livery of materials, production itself, storage, transportation, and erection of the segments. The required means of production form a fixed ratio. The pro duction is equivalent to increasing all parts of the operation at the same rate. Therefore, the complete planning pro cess and its adaptation to a changing environment requires special attention. The above factors fit very well within the context of Thai society and culture, as well as the country’s geo graphical configuration. This makes the BNE project, undoubtedly, one of the most interesting and challenging bridges of modem times. It is expected Fig. 18. Overview of progress in erection of bridge superstructure. that the successful completion of the BNE project will not only improve the transportation system in the Bangkok CREDITS area, but will also foster commercial growth in Southeast Thailand. Owner: Expressway and Rapid Tran - Jean Muller International, San sit Authority, Bangkok, Thailand Diego, California (Columns, Super Owner’s Engineer: Louis Berger structure) ACKNOWLEDGMENT Group, East Orange, New Jersey Contractor: Joint Venture, Bilfinger + The authors would like to thank Engineering Consultants: Berger Bauaktiengesellschaft, Wies Jack Egan of JV BBCD for reviewing - Asian Engineering Consultants, baden, Germany (Sponsor) and Ch. this paper and ensuring the accuracy Bangkok, Thailand (Alignment, Kamchang Public Company, Lim of the English language. Foundations) ited, Bangkok, Thailand
January-February 2000 37 I — .4 %_,_•_
Fig. 19. The new Bang Na Expressway was completed in January 2000. This picture was taken in December 1999. Figs. 17, 18 and 19 are published through the courtesy of Jean Muller International.
REFERENCES
1. Podolny, W., and Muller, 3., Construction and Design of Pre 5. Sofia, M., and Homsi, E., “Fabrication and Erection of Pre stressed Segmental Bridges, John Wiley, New York, NY, cast Concrete Segmental Boxes for Baldwin Bridge,” PCI 1982. JOURNAL, V. 39, No. 6, November-December 1994, pp. 36- 2. Pate, D., “The Chesapeake and Delaware Canal Bridge — De 52. sign-Construction Highlights,” PCI JOURNAL, V. 40, No. 5, 6. Roberts-Wollmann, C. L., Breen, J. E., and Kreger, M. E., September-October 1995, pp. 20-30. “Temperature Induced Deformations in Match Cast Seg 3. Shafer, G., and Brockmann, C., “Design and Construction of ments,” PCI JOURNAL, V. 40, No. 4, July-August 1995, pp. the Bang Na — Bang Ph — Bang Pakong Expressway,” Pro 62-71. ceedings, Volume 1, Fédération Internationale de la Précon 7. Borkenstein, D., Brockmann, C., and Fischer, 0., “The Bang
trainte (FTP), XIII Congress, Challenges for Concrete in the Na — Bang Ph — Bang Pakong Expressway: Design and Test Next Millennium, Amsterdam, Netherlands, May 23-29, 1998, Loading of a Precast Segmental Bridge Structure,” Taiwan pp. 275-280. Construction Research Institute (Publisher): 1999 Bridge 4. Shafer, G., “Bangkok Blockbuster,” Civil Engineering, V. 69, Construction Automation Seminar, Taipei, Taiwan, 1999, pp. No. 1, January 1999, pp. 32-35. 37-59.
38 PCI JOURNAL