Montana Department of Transportation Contact Information: AASHTOWare Project Help Desk AASHTOWare Project Construction & Materials Phone: 1-877-406-4338 Date : 09/30/2021 Active Construction Contracts Report Report Name: AASHTOCON015 District 1 - Missoula Project Manager: Benda, John Work Phone: 523-5858 Cell Phone: 396-4766 Email:
[email protected] Crew 1185 Contract No: 03917 SM Contractor Nm: SLETTEN CONSTRUCTION COMPANY Contr Time: 250 Wrk Adjusted Time: 293 Award DT: 11/07/2017 Final Accpt: 02/12/2021 Award Amt: 5,305,777.55 Cont Total: 6,563,616.15 CO Days: 43 Time Charged: 273 Work Beg: 03/26/2018 Fnl Est Rls: 03/12/2021 CO Amt: 1,257,838.60 Time Used: 93.17% Project Id NHPB 90-1(203)41 County Mineral Engineer Est $ 5,868,254.36 Est C.E. $ 477,519.98 Project Descr I-90 BRIDGE DECKS MP 40-70, D1 System/Route I / I-90 Award Amt $ 5,305,777.55 C.E. Costs $ 680,655.55 Project No 8087203000 Lat/Long 470511 / 1144657 Tot CO Amt $ 1,257,838.60 Cntr Used % 101.08 Project Engineer/Phone HARDAN-CHRIS / 406 444-9221 Beg/End Term 41.05 / 71.60 Total Amt $ 6,563,616.15 C.E. Used % 142.54 Work Descr BRIDGE CONSTRUCTION, REHAB AND REMOVAL Begin / End 1020+84.60 / 716+00.00 Cont Pymnts $ 6,634,500.67 C.E. Cost % 10.26 Claim Status None Contract No: 03C20 CM Contractor Nm: ACME CONCRETE PAVING, INC. Contr Time: 195 Wrk Adjusted Time: 195 Award DT: 02/23/2021 Final Accpt: N/A Award Amt: 6,862,709.52 Cont Total: 6,919,949.67 CO Days: 0 Time Charged: 123 Work Beg: 04/05/2021 Fnl Est Rls: N/A CO Amt: 57,240.15 Time Used: 63.08% Project Id IM 90-1(232)28 County Mineral Engineer Est $ 8,620,372.80 Est C.E.